Project Name:
Puget Sound Energy Energize Eastside
Land Use File Number:
LUA18-000055, CU-H, SME
Date of Hearing
January 8, 2020
Staff Contact
Jill Ding
Senior Planner
Project Contact/Applicant
Marissa Gifford
HDR
929 108th Ave NE, Suite 1300,
Bellevue, WA 98004-4361
Project Location
From PSE's Talbot Hill
Substation (2400 S Puget
Dr. continuing north along
the existing PSE
transmission line corridor
to the northern City limits
The following exhibits are included with the Staff Report to the Hearing Examiner:
Exhibits 1-2: As shown in the Environmental Review Committee (ERC) Memo
Exhibit 3: Staff Report to the Hearing Examiner
Exhibit 4: Property Owner List
Exhibit 5: Public Meeting Summary
Exhibit 6: Public Comments available at the following link:
https://edocs.rentonwa.gov/Documents/Browse.aspx?id=1182056&dbid=0&repo=CityofRen
ton
Exhibit 7: Staff Response to Public Comments available at the following link:
https://edocs.rentonwa.gov/Documents/Browse.aspx?id=1182056&dbid=0&repo=CityofRen
ton
Exhibit 8: Vegetation Replacement Letter, dated July 24, 2019
Exhibit 9: Critical Areas Report, prepared by The Watershed Company, dated January 2019
Exhibit 10: Mitigation Plans
Exhibit 11: Photo Simulations
Exhibit 12: Construction Plans
Exhibit 13: Tree Retention Worksheets
Exhibit 14: Conditional Use Justification
Exhibit 15: Advisory Notes to Applicant
Exhibit 16: Neighborhood Detail Map
Exhibit 17: Draft Environmental Impact Statement
Exhibit 18: Final Environmental Impact Statement