Loading...
HomeMy WebLinkAboutExtension Request 3-27-2020 Western Washington Division Eastern Washington Division 165 NE Juniper St., Ste 201, Issaquah, WA 98027 407 Swiftwater Blvd., Cle Elum, WA 98922 Phone: (425) 392-0250 Phone: (509) 674-7433 www.EncompassES.net March 27, 2020 Angelea Weihs Renton City Hall 6th Floor AWeihs@rentonwa.gov RE: 30-Day Extension Request VEK on Aberdeen Townhomes Plat, LUA19-000280, ECF, MOD, PP,SA-H Dear Angelea, We are coming up on our April 8, 2020 additional information submittal date per “On Hold” Notice letter dated January 10, 2020 for VEK on Aberdeen and would like to request a 30-day extension. We are working hard on the storm re-design and are getting close to completion. However, once the storm re-design is completed, we still need to send it to the Geotechnical Engineer to finish updating their report and then back to Encompass to complete the response letter. Not knowing the Riley Group, Inc.’s schedule and the amount of time needed for them to complete their report we are concerned at meeting the deadline. Thank you for your consideration is this request. If you have any questions or need additional information, please call or email me at 425-961-2074 or email me at bbabcock@encompasses.net. Sincerely, Encompass Engineering and Surveying Bonnie Babcock Project Coordinator cc: Mariah Gill Nicole Mecum Chad Allen