HomeMy WebLinkAboutTIR
FINAL
TECHNICAL INFORMATION REPORT
FOR
KIDDIE RESEARCH DAYCARE CENTER
CITY OF RENTON, WASHINGTON
Prepared by: Gina R. Brooks, P.E.
Date: December 23, 2019
Revised: February 26, 2020
Core No.: 18227
2/26/2019
DEVELOPMENT ENGINEERING
jchavez 04/08/2020
SURFACE WATER UTILITY
JFarah 04/08/2020
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER i
KIDDIE RESEARCH DAYCARE CENTER Table of Contents
1. PROJECT OVERVIEW .......................................................................................................................... 1-1
2. CONDITIONS AND REQUIREMENTS SUMMARY ................................................................................ 2-1
2.1 Core Requirements .......................................................................................................................... 2-2
2.1.1 Core Requirement #1: Discharge at the Natural Location ...................................................... 2-2
2.1.2 Core Requirement #2: Offsite Analysis .................................................................................... 2-2
2.1.3 Core Requirement #3: Flow Control......................................................................................... 2-2
2.1.4 Core Requirement #4: Conveyance System ............................................................................. 2-2
2.1.5 Core Requirements #5: Erosion and Sediment Control ........................................................... 2-2
2.1.6 Core Requirement #6: Maintenance and Operations .............................................................. 2-2
2.1.7 Core Requirement #7: Financial Guarantees and Liability ....................................................... 2-2
2.1.8 Core Requirement #8: Water Quality ...................................................................................... 2-4
2.1.9 Core Requirement #9: On-Site BMPs ....................................................................................... 2-5
2.2 Special Requirements ...................................................................................................................... 2-5
2.2.1 Special Requirement #1: Other Adopted Area Specific Requirements .................................... 2-5
2.2.2 Special Requirement #2: Flood Hazard Area Delineation ........................................................ 2-5
2.2.3 Special Requirement #3: Flood Protection Facilities ................................................................ 2-5
2.2.4 Special Requirement #4: Source Control ................................................................................. 2-5
2.2.5 Special Requirement #5: Oil Control ........................................................................................ 2-5
2.2.6 Special Requirement #6: Aquifer Protection Area ................................................................... 2-5
3. OFFSITE ANALYSIS ............................................................................................................................. 3-1
3.1 Resource Review .............................................................................................................................. 3-1
3.1.1 Sensitive Areas ......................................................................................................................... 3-1
3.2 Field Investigation ............................................................................................................................ 3-1
4. FLOW CONTROL AND WATER QUALITY DESIGN ............................................................................... 4-1
4.1 Hydraulic Analysis ............................................................................................................................ 4-1
4.1.1 Existing Conditions ................................................................................................................... 4-4
4.1.2 Developed Conditions .............................................................................................................. 4-7
4.2 Water Quality Treatment Analysis and Design .............................................................................. 4-12
5. CONVEYANCE SYSTEM ANALYSIS AND DESIGN ................................................................................. 5-1
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER ii
6. SPECIAL REPORTS AND STUDIES ....................................................................................................... 6-4
7. OTHER PERMITS ................................................................................................................................ 7-1
8. ESC ANALYSIS AND DESIGN ............................................................................................................... 8-1
9. BOND QUANTITIES, FACILITY SUMMARIES, AND DECLARATION OF COVENANT ............................. 9-1
10. OPERATIONS AND MAINTENANCE .................................................................................................. 10-1
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 1-1
1. PROJECT OVERVIEW
The proposed Kiddie Research Daycare Center project is located at 3123 NE Sunset Blvd. Renton,
Washington within Section 4, Township 23 North, Range 5 East, W.M. See Vicinity Map below.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 1-2
The site is composed of one parcel (#0423059155) with an area of approximately 0.39 acre. The site is
bordered by NE Sunset Blvd. (which is a major arterial) to the west, NE 12th Street (collector) to the
south and commercial developed parcels to the east and north.
The site was previously developed as a car wash facility. According to City of Renton Soil Map and NRSC
Soils Resource Report, site soil type is AmC. Slopes on the site vary from about 3% up to approximately
15%.
Topography is generally downhill from east to west.
Proposed development of the property will include the construction of a building and parking which will
accommodate and house a daycare center. Utilities to support the development will be installed. All
existing structures and hard surfaces have been previously demolished and removed based on the field
investigation that took place on March 18, 2019.
The subject project’s drainage facilities were designed using the guidelines and requirements
established in the 2017 City of Renton Surface Water Design Manual (RSWDM). Peak Rate Flow Control
Standard (Existing Site Conditions) and Basic Water Quality Treatment are required for this project. No
flow control or water quality treatment facilities are proposed as the project is exempt from both flow
control and water quality treatment.
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
Part 1 PROJECT OWNER AND
PROJECT ENGINEER Part 2 PROJECT LOCATION AND
DESCRIPTION
Project Owner ___________________________
Phone _________________________________
Address _______________________________
_______________________________________
Project Engineer _________________________
Company ______________________________
Phone _________________________________
Project Name _________________________
DPER Permit # ________________________
Location Township ______________
Range ________________
Section ________________
Site Address __________________________
_____________________________________
Part 3 TYPE OF PERMIT APPLICATION Part 4 OTHER REVIEWS AND PERMITS
Landuse (e.g.,Subdivision / Short Subd. / UPD)
Building (e.g.,M/F / Commercial / SFR)
Clearing and Grading
Right-of-Way Use
Other _______________________
DFW HPA
COE 404
DOE Dam Safety
FEMA Floodplain
COE Wetlands
Other ________
Shoreline Management
Structural Rockery/Vault/_____
ESA Section 7
Part 5 PLAN AND REPORT INFORMATION
Technical Information Report Site Improvement Plan (Engr. Plans)
Type of Drainage Review (check one):
Date (include revision dates):
Date of Final:
Full
Targeted
Simplified
Large Project
Directed
____________________________________
__________________
Plan Type (check one):
Date (include revision dates):
Date of Final:
Full
Modified
Simplified
____________________________________
__________________
Part 6 SWDM ADJUSTMENT APPROVALS
Type (circle one): Standard / Experimental / Blanket
Description: (include conditions in TIR Section 2)
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
Approved Adjustment No. ______________________ Date of Approval: ______________________
2016 Surface Water Design Manual 4/24/2016 1
Kiddie Research LLC
206-430-9827
1025 N 36th St, Renton, WA 98056
Gina R. Brooks
Core Design, Inc.
425-885-7877
Kiddie Research Daycare Center
23N
5E
4
3123 NE Sunset Blvd., Renton
N/A
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
Part 7 MONITORING REQUIREMENTS
Monitoring Required: Yes / No
Start Date: _______________________
Completion Date: _______________________
Describe: _________________________________
_________________________________________
_________________________________________
Re: KCSWDM Adjustment No. ________________
Part 8 SITE COMMUNITY AND DRAINAGE BASIN
Community Plan : ____________________________________________________________________
Special District Overlays: ______________________________________________________________
Drainage Basin: _____________________________________________________________________
Stormwater Requirements: ____________________________________________________________
Part 9 ONSITE AND ADJACENT SENSITIVE AREAS
River/Stream ________________________
Lake ______________________________
Wetlands ____________________________
Closed Depression ____________________
Floodplain ___________________________
Other _______________________________
_______________________________
Steep Slope __________________________
Erosion Hazard _______________________
Landslide Hazard ______________________
Coal Mine Hazard ______________________
Seismic Hazard _______________________
Habitat Protection ______________________
_____________________________________
Part 10 SOILS
Soil Type
_________________
_________________
_________________
_________________
Slopes
_________________
_________________
_________________
_________________
Erosion Potential
_________________
_________________
_________________
_________________
High Groundwater Table (within 5 feet)
Other ________________________________
Sole Source Aquifer
Seeps/Springs
Additional Sheets Attached
2016 Surface Water Design Manual 4/24/2016 2
Newcastle
East Lake Washington
Alderwood (AmC)
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
Part 11 DRAINAGE DESIGN LIMITATIONS
REFERENCE
Core 2 – Offsite Analysis_________________
Sensitive/Critical Areas__________________
SEPA________________________________
LID Infeasibility________________________
Other________________________________
_____________________________________
LIMITATION / SITE CONSTRAINT
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
_______________________________________
Additional Sheets Attached
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet per Threshold Discharge Area)
Threshold Discharge Area:
(name or description)
Core Requirements (all 8 apply):
Discharge at Natural Location Number of Natural Discharge Locations:
Offsite Analysis Level: 1 / 2 / 3 dated:__________________
Flow Control (include facility summary sheet) Level: 1 / 2 / 3 or Exemption Number ____________
Flow Control BMPs _______________________________
Conveyance System Spill containment located at: _________________________
Erosion and Sediment Control /
Construction Stormwater Pollution Prevention
CSWPP/CESCL/ESC Site Supervisor: _____________________
Contact Phone: _________________________
After Hours Phone: _________________________
Maintenance and Operation Responsibility (circle one): Private / Public
If Private, Maintenance Log Required: Yes / No
Financial Guarantees and
Liability
Provided: Yes / No
Water Quality (include facility summary sheet) Type (circle one): Basic / Sens. Lake / Enhanced Basic / Bog
or Exemption No. ______________________
Landscape Management Plan: Yes / No
Special Requirements (as applicable):
Area Specific Drainage Requirements Type: CDA / SDO / MDP / BP / LMP / Shared Fac. / None
Name: ________________________
Floodplain/Floodway Delineation Type (circle one): Major / Minor / Exemption / None
100-year Base Flood Elevation (or range): ______________
Datum:
Flood Protection Facilities Describe:
2016 Surface Water Design Manual 4/24/2016 3
1
RSWDM 1.2.3.1.A
Limited Infiltration Drywell
RSWDM 1.2.8 Surface Area Exemption
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
Part 12 TIR SUMMARY SHEET (provide one TIR Summary Sheet per Threshold Discharge Area)
Source Control
(commercial / industrial land use)
Describe land use:
Describe any structural controls:
Oil Control
High-use Site: Yes / No
Treatment BMP: ________________________________
Maintenance Agreement: Yes / No
with whom? ____________________________________
Other Drainage Structures
Describe:
Part 13 EROSION AND SEDIMENT CONTROL REQUIREMENTS
MINIMUM ESC REQUIREMENTS DURING CONSTRUCTION
Clearing Limits
Cover Measures
Perimeter Protection
Traffic Area Stabilization
Sediment Retention
Surface Water Collection
Dewatering Control
Dust Control
Flow Control
Protection of Flow Control BMP Facilities
(existing and proposed)
Maintain BMPs / Manage Project
MINIMUM ESC REQUIREMENTS AFTER CONSTRUCTION
Stabilize exposed surfaces
Remove and restore Temporary ESC Facilities
Clean and remove all silt and debris, ensure operation of Permanent Facilities, restore
operation of Flow Control BMP Facilities as necessary
Flag limits of SAO and open space preservation areas
Other ______________________
Part 14 STORMWATER FACILITY DESCRIPTIONS (Note: Include Facility Summary and Sketch)
Flow Control Type/Description Water Quality Type/Description
Detention
Infiltration
Regional Facility
Shared Facility
Flow Control BMPs
Other
________________
________________
________________
________________
________________
________________
Vegetated Flowpath
Wetpool
Filtration
Oil Control
Spill Control
Flow Control BMPs
Other
________________
________________
________________
________________
________________
________________
________________
2016 Surface Water Design Manual 4/24/2016 4
Drywell
KING COUNTY, WASHINGTON, SURFACE WATER DESIGN MANUAL
TECHNICAL INFORMATION REPORT (TIR) WORKSHEET
Part 15 EASEMENTS/TRACTS Part 16 STRUCTURAL ANALYSIS
Drainage Easement
Covenant
Native Growth Protection Covenant
Tract
Other ___________________________
Cast in Place Vault
Retaining Wall
Rockery > 4’ High
Structural on Steep Slope
Other ______________________________
Part 17 SIGNATURE OF PROFESSIONAL ENGINEER
I, or a civil engineer under my supervision, have visited the site. Actual site conditions as observed were incorporated into this worksheet and the attached Technical Information Report. To the best of my knowledge the information provided here is accurate.
Signed/Date
2016 Surface Water Design Manual 4/24/2016 5
12-23-2019
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 2-1
2. CONDITIONS AND REQUIREMENTS SUMMARY
The proposed project is classified as requiring “Full Drainage Review” per the 2017 RSWDM. Therefore,
all nine core requirements and six special requirements will be addressed per Section 1.2 and 1.3 of the
2017 RSWDM.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 2-2
2.1 Core Requirements
2.1.1 Core Requirement #1: Discharge at the Natural Location
The project discharges its drainage at the natural location which is to the City’s conveyance system
located within the intersection of NE Sunset Blvd. and NE 12th Street.
2.1.2 Core Requirement #2: Offsite Analysis
See Section 3 of this Report for the downstream analysis.
2.1.3 Core Requirement #3: Flow Control
The site falls within the City’s Peak Rate Flow Control Standard (Existing Site Conditions). See City’s Flow
Control Application Map on the following pages. This flow control standard requires matching existing
conditions for the 2, 10, and 100-year peak rate runoffs. Existing conditions is defined as those that
existed prior to May 1979 as determined from aerial photographs and, if necessary, knowledge of
individuals familiar with the area, unless a drainage plan for land cover changes has been approved by
the City of Renton since May 1979 as part of a City permit or approval (or County-approved permit if in
an area that has been annexed by the City). If so, existing site conditions are those created by the site
improvements and drainage facilities constructed per the approved drainage plan. Per the
preapplication notes for the subject project, there is no existing detention facility on the project site that
would provide prior mitigation of currently developed flows. The existing conditions are therefore,
those flows generated from the site as it sits today.
As demonstrated within Section 4 of this Report, the subject project is exempt from flow control as the
developed condition 100-year, 15-minute peak flow does not generate an increase of 0.15 cfs above the
existing condition 100-year, 15-minute peak flow.
2.1.4 Core Requirement #4: Conveyance System
See Section 5 of this Report for the conveyance calculations.
2.1.5 Core Requirements #5: Erosion and Sediment Control
See Section 8 of this Report for the ESC design.
2.1.6 Core Requirement #6: Maintenance and Operations
See Section 10 of this report for the Operations and Maintenance Manual
2.1.7 Core Requirement #7: Financial Guarantees and Liability
This core requirement will be addressed at the time the permit is issued.
Lake
Desire
Shady
Lake (Mud
Lake)
Panther
Lake LakeYoungs
Lake
Washington
B l a ck Ri ve r
Gr ee n Riv
e
r
Ce
darRi v erUV900
UV167
UV515
UV169
UV900
UV169
UV167BN IncBN IncBBNNIInnccSSEERReennttoonnIIssssaaqquuaahh RR dd
RReennttoonnMMaapplleeVVaalllleeyyRRdd
MMaapplleeVVaalllleeyyHHwwyy
110088tthhAAvveeSSEESSWW SSuunnsseettBBllvvdd RRaaii
nnii
eerr
AAvveeNNNE 3rd St
NE 3rd S
t
SW 43rd StSW 43rd St SSEE CCaarrrrRR dd
NE 4th StNE 4th St
SSEERReennttoonn MMaappllee VVaalllleeyy RRddLLooggaannAAvveeNN
SR 515SR 515PPaarrkkAAvveeNNOOaakkeessddaalleeAAvveeSSWWSSuunnsseettBBllvvddNNEE
DDuuvvaallllAAvveeNNEEI-405 FWYI-405 FWY II--440055FFWWYYSR 167SR 167114400tthh
WWaayySS
EE
NNEE2277tthhSStt
115566tthhAAvveeSSEEUUnniioonnAAvveeNNEE111166tthhAAvveeSSEESW 7th StSW 7th St
N 8th StN 8th St
PP uuggeettDDrrSSEE
RR
ee
nnttoonnAAvvee SS
SSWW 2277tthh SStt BBeennssoonnRRddSSWWiilllliiaammssAAvveeSSMMoonnrrooeeAAvveeNNEESE 128th StSE 128th St
II
nntt
eerr
uurr
bbaannAAvveeSS HHooqquuiiaammAAvveeNNEE8844tthhAAvveeSSSSEEPPeett
rr
oovviitt
sskkyyRRddEEVVaalllleeyyHHwwyySE 192nd StSE 192nd St
SE 60th StSE 60th St
TTaallbboottRRddSSRR
ee
nntt
oo
nn
AAvveeSS116644tthhAAvveeSSEESE 208th StSE 208th St
SE 72nd StSE 72nd St
RRaaiinniieerrAAvvee
SS 111166tthhAAvveeSSEES 128th StS 128th St
NNeewwccaassttllee WWaayy
SS 221122tthh SStt
SS118800tthh SStt CCooaall
CCrreeeekkPPkkwwyySSEESW 41st StSW 41st St
114400tthhAAvveeSSEE112288tthhAAvveeSSEE6688tthhAAvveeSSSSEE 116688tthh SStt
NE 12th StNE 12th St
BBee
aa
ccoonn
AA
vv
ee
SS
FFoorreesstt DDrr SSEE
SSEE 116644tthh SStt 114488tthhAAvveeSSEESSEE MMaayy VVaalllleeyyRRdd
SS EE JJoonneess RRdd
SS EE 22 00 44 tthh WW aayySW 34th StSW 34th St
SE 144th StSE 144th St
114488tthhAAvveeSSEE115544tthhPPllSSEELL
aa
kk
ee
WWaa
sshhii
nnggtt
oonnBBll
vvddNNEEddmmoonnddssAAvveeNNEEAAbbeerrddeeeennAAvveeNNEEEEMM eerrcceerrWWaayyWWeessttVVaalllleeyyHHwwyyEast Valley RdEast Valley Rd,§-405
,§-405
,§-405
μ 012Miles
Flow Control Application Map
Reference 1-A
Date: 01/09/2014
Flow Control Standards
Peak Rate Flow Control Standard (Existing Site Conditions)
Flow Control Duration Standard (Existing Site Conditions)
Flow Control Duration Standard (Forested Conditions)
Flood Problem Flow
Unincorporated King County Flow Control Standards
Renton City Limits
Potential Annexation Area
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 2-4
2.1.8 Core Requirement #8: Water Quality
As the City of Renton does not have Sensitive Lake or Sphagnum Bog Water Quality Treatment Areas,
Basic Water Quality Treatment is the only other option available. As the proposed project is a
commercial development, Enhanced Basic Water Quality Treatment is typically required. However, per
RSWDM Section 1.2.8.1.A.Exceptions.3., the required treatment can be reduced to Basic as the
downstream conveyance is all tight-lined conveyance with discharge to Lake Washington.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 2-5
As demonstrated within Section 4 of this Report, the subject project is exempt from water quality
treatment as site conditions don’t exceed the “Surface Area Exemption” thresholds.
2.1.9 Core Requirement #9: On-Site BMPs
See Section 4.1.2 of this Report for discussion on how this Core Requirement is addressed.
2.2 Special Requirements
2.2.1 Special Requirement #1: Other Adopted Area Specific Requirements
There are no known additional requirements for the subject project.
2.2.2 Special Requirement #2: Flood Hazard Area Delineation
Not applicable since the project does not contain nor is adjacent to a flood hazard area.
2.2.3 Special Requirement #3: Flood Protection Facilities
Not applicable since the project does not rely on an existing flood protection facility or plans to modify
or construct a new flood protection facility.
2.2.4 Special Requirement #4: Source Control
Though the subject project is a commercial development, it will house a daycare and will not be storing
any type of chemicals requiring source control. A refuse area will be located on the site but, will be
sheltered from rainfall with a roof. Typical stormwater mitigation is addressed within this Report.
2.2.5 Special Requirement #5: Oil Control
Not applicable since the project is not a high use site. The expected average daily traffic is less than 100
vehicles per 1,000 square feet of gross building area.
2.2.6 Special Requirement #6: Aquifer Protection Area
Not applicable since the project is not in an Aquifer Protection Area.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 3-1
3. OFFSITE ANALYSIS
3.1 Resource Review
The proposed project is located within the Lake Washington Cedar River Watershed.
3.1.1 Sensitive Areas
Renton GIS was reviewed for sensitive areas. The proposed project site does not fall within the
following sensitive area; coal mines, erosion hazard, flood hazard, floodway, channel migration zone,
landslide, seismic hazard, regulated stream, wetland, or wellhead protection.
According to the Renton GIS Map, there is a small portion on northeast corner of the site which falls
within 15%-25% regulated slope. See picture below.
Regulated Slope: 15% to 25% slope area (Per Renton GIS Data)
3.2 Field Investigation
A field investigation was completed on March 18, 2019.
Upstream Tributary Analysis
Based on the field walk and the taken photos, both properties uphill of the proposed project site (one to
the north and one to the east) have their own storm drainage facilities. Within their parking lots, active
catch basins were found. Therefore, no upstream runoff is considered to enter the project site. See
pictures below.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 3-2
Drainage system for the property east of the subject site
Drainage system for the property north of the subject site
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 3-3
Downstream Drainage Complaints
Drainage complaints were researched within a quarter mile of the project site. City of Renton does not
list any current complaints along the project’s downstream route.
Onsite Drainage System Description
Upon the site visit, all existing catch basins on the site, noted per the topographic boundary survey,
were removed except one catch basin which is located on the southwest corner of the project site.
Based on field observation, the downstream route for this onsite catch basin could not be determined.
Same was true for the catch basin located along the flowline of the curb return of NE Sunset Blvd. and
NE 12th Street beyond the southwest corner. As this property previously housed a car wash facility, the
onsite catch basins likely discharged to the sanitary sewer though this could not be verified. It was
determined though, all of the site’s drainage would ultimately discharge to the City’s conveyance system
located within NE Sunset Blvd.
Downstream Drainage System Description
This downstream route description begins at the catch basin located at the northeast corner of NE Sunset
Blvd. and NE 12th Street. This catch basin is located between two islands within the existing crosswalk. As
catch basins within the roads were not accessible due to heavy traffic, City resources were utilized to trace
the downstream route. Based on City utility maps, the runoff flows through a series of 12”, 24”, and 36”
pipes connecting a series of Type I and Type II catch basins until drainage discharges to Lake Washington
via the outfall next to the Gene Coulon Memorial Beach Park about 1.1 miles away from the site. See
picture below.
Downstream Reach Description to a quarter mile
Pipe Material Pipe Diameter
(in)
Overall Pipe Length
(ft)
Cumulative Length
(ft)
Concrete 12 104 104
Unknown 12 255 359
Corrugate Metal 24 14 373
Corrugate Metal 36 257 630
Concrete 36 145 775
Corrugated Metal 36 541 1316
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 3-4
Outfall location next to the Gene Coulon Memorial Beach Park
4,652
388
WGS_1984_Web_Mercator_Auxiliary_Sphere
City of Renton Print map Template
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATION
Notes
None
Legend
264 0 132 264 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
03/19/2019
City and County Boundary
Parcels
Network Structures
Inlet
Manhole
Utility Vault
Unknown Structure
Control Structures
Pump Stations
Discharge Points
Water Quality
Detention Facilities
Pond
Tank
Vault
Wetland
Stormwater Mains
Culverts
Open Drains
Facility Outlines
Fences
Streets
Points of Interest
Parks
Waterbodies
Map
Extent2010
1/4 mile SITE
104ft359ft373ft630ft775ft
DOWNSTREAM ROUTE EXHIBIT
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-1
4. FLOW CONTROL AND WATER QUALITY DESIGN
A flow control facility is not proposed as the project is exempt from flow control as delineated below. A
water quality treatment facility is not proposed as the project is exempt from water quality treatment as
delineated in Section 4.2 of this Report.
PEAK RATE FLOW CONTROL EXEMPTION
Per the RSWDM Section 1.2.3.1.A. Exceptions, The facility requirement in Peak Rate Flow Control
Standard Areas is waived for any threshold discharge area in which the target surfaces subject to this
requirement will generate no more than a 0.15-cfs increase (when modeled using 15 minute time steps)
in the existing site conditions 100-year peak flow (modeled using same time step unit (e.g., 15-minute)
used to calculate the developed flow). Note: for the purposes of this calculation, target surfaces served
by on-site BMPs per Appendix C may be modeled in accordance with the on-site BMP sizing credits in
Core Requirement #9, Table 1.2.9.A.
As shown below, the existing site will produce a 100-year, 15-minute peak flow of 0.353 cfs. The
developed site will produce a 100-year, 15-minute peak flow of 0.383 cfs. The difference is these two
peak flows is 0.030 cfs which does not exceed the 0.15 cfs requiring flow control. The project therefore,
is exempt from flow control. See calculations below.
4.1 Hydraulic Analysis
The drainage analysis was modeled using MGSFlood software. Per the City of Renton Soil Survey, the
site soil is Alderwood (AmC), hydrologic soil group “C”, Till for modeling.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-2
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-3
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-4
4.1.1 Existing Conditions
See Existing Conditions exhibit on the following page.
The existing basin boundary area, 0.38 acre, is defined as that area that will be improved through
development of the subject project. The existing basin boundary area will include the property area,
0.39 acre, less the right-of-way dedications, 0.09 acre, plus frontage improvements/existing impervious
removal extending from the dedicated right-of-way to back of existing curb, 0.08 acre. Existing
impervious covers approximately 0.30 acre.
The following information was used for generating flow frequencies. See MGS Flood printout below.
EXISTING CONDITIONS Total Area = 0.38 acres
GROUND COVER AREA (acres)
Till-Grass 0.07
Impervious 0.30
————————————————————————————————— MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.50 Program License Number: 200210008 Project Simulation Performed on: 12/13/2019 9:11 AM Report Generation Date: 02/07/2020 9:40 AM
—————————————————————————————————
Input File Name: 18227MGSF.fld Project Name: Kiddie Research Daycare Center Analysis Title: Comments: ————————————————————————————————— ———————————————— PRECIPITATION INPUT ———————————————— Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected Climatic Region Number: 15
Full Period of Record Available used for Routing Precipitation Station : 96004005 Puget East 40 in_5min 10/01/1939-10/01/2097 Evaporation Station : 961040 Puget East 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1 HSPF Parameter Region Name : USGS Default
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-5
----------------------SCENARIO: PREDEVELOPED Number of Subbasins: 1 ---------- Subbasin : Existing Site ---------- -------Area (Acres) --------
Till Grass 0.070 Impervious 0.300 ---------------------------------------------- Subbasin Total 0.370
Predevelopment Runoff Tr (Years) Discharge (cfs) ------------------------------------------- 2-Year 0.121 5-Year 0.155 10-Year 0.184
25-Year 0.243 50-Year 0.288 100-Year 0.353 200-Year 0.361 500-Year 0.370
NE SUNSET BLVDNE 12TH STREETDESIGNE N G I N E E R I N G P L A N N I N G S U R V E Y I N G14711 NE 29th Place, #101Bellevue, Washington 98007425.885.7877 Fax 425.885.7963KIDDIE RESEARCH DAYCARE CENTER18227EXISTING CONDITIONS
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-7
4.1.2 Developed Conditions
See Developed Conditions exhibit on the following pages.
The developed basin boundary area is equal to the existing basin boundary area, 0.38 acre. For
simplicity to demonstrate exemption from flow control, the developed condition was conservatively
assumed to be 100% impervious.
The following information was used for generating flow frequencies. See MGS Flood printout below.
DEVELOPED CONDITIONS Total Area = 0.38 acre
GROUND COVER AREA(acres)
Till-Grass 0.00
Impervious 0.38
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 1 ---------- Subbasin : Developed Site ---------- -------Area (Acres) -------- Impervious 0.380 ---------------------------------------------- Subbasin Total 0.380
Postdevelopment Runoff Tr (Years) Discharge (cfs) ----------------------------------------- 2-Year 0.142 5-Year 0.184 10-Year 0.207 25-Year 0.260 50-Year 0.332 100-Year 0.383 200-Year 0.397 500-Year 0.416
NE SUNSET BLVDNE 12TH STREETDESIGNE N G I N E E R I N G P L A N N I N G S U R V E Y I N G14711 NE 29th Place, #101Bellevue, Washington 98007425.885.7877 Fax 425.885.7963KIDDIE RESEARCH DAYCARE CENTER18227DEVELOPED CONDITIONS
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-9
ON-SITE BMPs
Per Section 1.2.9.1 in the RSWDM, projects subject to Core Requirement #9 must apply flow control
BMPs to either supplement the flow mitigation provided by required flow control facilities or provide
flow mitigation where flow control facilities are not required. Flow control BMPs must be implemented
per the requirements and approach detailed in Sections 1.2.9.2 and 1.2.9.3 for individual lots and
subdivisions or road improvement projects, respectively. The Section applicable to this project is Section
1.2.9.2.
Per Section 1.2.9.2, projects on individual sites/lots, flow control BMPs must be selected and applied
according to the individual lot BMP requirements. The category of requirements applicable to the
subject project is the Small Lot BMP Requirements (for sites/lots <22,000 square feet).
1. The feasibility and applicability of full dispersion as detailed in Appendix C, Section C.2.1 must be
evaluated for all target impervious surfaces. If feasible and applicable, full dispersion must be
implemented as part of the proposed project. Typically, small lot full dispersion will be applicable
only in subdivisions where enough forest was preserved by tract, easement, or covenant to meet
the minimum requirements for full dispersion in Appendix C, Section C.2.1.1
Full dispersion is not feasible due to non-existent native forested area.
2. Where full dispersion of target impervious roof areas is not feasible or applicable, or will cause
flooding or erosion impacts, the feasibility and applicability of full infiltration as detailed in Appendix
C, Section C.2.2 must be evaluated (note, this will require a soils report for the site/lot). If feasible
and applicable, full infiltration of roof runoff must be implemented as part of the proposed project.
Full infiltration is not feasible due to existing onsite non-infiltrating till soils.
3. All target impervious surfaces not mitigated by Requirements 1 and 2 above, must be mitigated to
the maximum extent feasible using one or more BMPs from the following list. Use of a given BMP is
subject to evaluation of its feasibility and applicability as detailed in Appendix C. Feasible BMPs are
required to be implemented. The BMPs listed below may be located anywhere on the site/lot
subject to the limitations and design specifications for each BMP. These BMPs must be
implemented as part of the proposed project.
• Full Infiltration per Appendix C, Section C.2.2, or per Section 5.2, whichever is applicable
Full infiltration is not feasible due to existing onsite non-infiltrating till soils
• Limited Infiltration per Appendix C, Section C.2.3,
Limited infiltration will be installed to mitigate for the building and refuse roof areas along with the
exposed parking area located east of the building roof. The dry well will contain 360 cubic feet of
gravel per 1,000 square feet of impervious surface served since the soils are sandy loam (RSWDM
Section C.2.3.4). See copyclip of email below from the project’s geotechnical engineer. indicating the
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-10
soils are “sandy loam”. The dry well will be a maximum depth of 5 feet with a surface area as sized
below.
Dry Well Sizing
Roof Area = 7,739 square feet
Parking Area = 856 square feet
Volume of Gravel Required = 8,595 SF/1,000 SF * 360 CF = 3,094 cubic feet
Surface Area Required = 3,094 CF/5 FT = 619 square feet
Surface Area Provided = 14 FT * 47 FT = 658 square feet ˃ 619 square feet
• Rain Gardens per Appendix C, Section C.2.12, sized as follows:
o Rain gardens have a maximum contributing area of 5,000 square feet.
o Rain gardens must have a minimum horizontal projected surface area below the overflow that is
at least 5% of the area draining to it.
The remaining impervious surfaces on the site discharge to the catch basin located within the covered
parking area. Due to the parking being located under cover, all drainage is required to be directed to
the sanitary sewer system. Therefore, no additional impervious area requires treatment via BMPs.
• Bioretention per Appendix C, Section C.2.6, sized as follows:
o SeaTac regional scale factor equals 1.0: In till soils, provide bioretention volume based on 0.6
inches of equivalent storage depth; in outwash soils provide bioretention volume based on 0.1
inches of equivalent storage depth,
o SeaTac regional scale factor greater than 1.0: In till soils, provide bioretention volume based on 0.8
inches of equivalent storage depth; in outwash soils, provide bioretention volume based on 0.4
inches of equivalent storage depth,
See response to Rain Gardens above.
• Permeable Pavement per Appendix C, Section C.2.7
See response to Rain Gardens above.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-11
4. All target impervious surfaces not mitigated by Requirements 1, 2 and 3 above, must be mitigated to
the maximum extent feasible using the Basic Dispersion BMP described below. Use of Basic
Dispersion is subject to evaluation of its feasibility and applicability as detailed in Appendix C.
Feasible BMPs are required to be implemented. Basic Dispersion BMPs may be located anywhere on
the site/lot subject to the limitations and design specifications cited in Appendix C. The BMP must
be implemented as part of the proposed project.
• Basic Dispersion per Appendix C, Section C.2.4,
See response to Rain Gardens above.
5. BMPs must be implemented, at minimum, for an impervious area equal to at least 10% of the
site/lot for site/lot sizes up to 11,000 square feet and at least 20% of the site/lot for site/lot sizes
between 11,000 and 22,000 square feet. For projects located in Zone 1 of the Aquifer Protection
Area, these impervious area amounts must be doubled. Doubling of the minimum impervious area
required for BMP implementation in Zone 1 of the Aquifer Protection Area is not required for
projects located within 200 feet of a steep slope hazard area, landslide hazard, or erosion hazard
area. If these minimum areas are not mitigated using feasible BMPs from Requirements 1, 2, 3, and
4 above, one or more BMPs from the following list are required to be implemented to achieve
compliance. These BMPs must be implemented as part of the proposed project.
• Reduced Impervious Surface Credit per Appendix C, Section C.2.9,
• Native Growth Retention Credit per Appendix C, Section C.2.10.
• Tree Retention Credit per Appendix C, Section C.2.14
See response to Rain Gardens above.
6. The soil moisture holding capacity of new pervious surfaces (target pervious surfaces) must be
protected in accordance with the soil amendment BMP as detailed in Appendix C, Section C.2.13.
Soil amendment will be incorporated for disturbed areas not covered with hard surfaces.
7. Any proposed connection of roof downspouts to the local drainage system must be via a perforated
pipe connection as detailed in Appendix C, Section C.2.11.
As the drainage from the roof is passing through a BMP, this requirement is no longer applicable.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 4-12
4.2 Water Quality Treatment Analysis and Design
The subject project is exempt from water quality treatment per the “Surface Area Exemption”;
a) Less than 5,000 square feet of new plus replaced PGIS that is not fully dispersed will be created,
New PGIS is approximately 1,507 square feet which is well below the 5,000 square foot threshold.
b) Less than ¾ acre of new PGPS that is not fully dispersed will be added.
The area of development is 0.39 acre which is well below the ¾ acre threshold.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 5-1
5. CONVEYANCE SYSTEM ANALYSIS AND DESIGN
CONVEYANCE SYSTEM SIZING
The site is small and is not tributary to a detention facility creating backwater effects. A rational method
for the entire site assuming 100% impervious coverage is calculated below demonstrating the proposed
12” tight-lined conveyance system is adequately sized for the project. 𝑄𝑄𝑅𝑅=𝐶𝐶𝐼𝐼𝑅𝑅𝐴𝐴
where QR = peak flow (cfs) for a storm of return frequency R
C = estimated runoff coefficient (ratio of rainfall that becomes runoff)
IR = peak rainfall intensity (inches/hour) for a storm of return frequency R
A = drainage subbasin area (acres)
C can be found using Table 3.2.1.A Runoff Coefficients – “C” of the 2016 KCSWDM. Assuming the site is
100% impervious, C is equal to “0.90”.
The subbasin area is 0.39 acres. 𝐼𝐼𝑅𝑅=𝑃𝑃𝑅𝑅𝑖𝑖𝑅𝑅
where PR = total precipitation at the site, use 100 year isopluvial map found below
iR = unit peak rainfall intensity factor
The 24-hour 100 year precipitation is 3.9 inches. See Isolpluvuials map on the following pages. 𝑖𝑖𝑅𝑅=(𝑎𝑎𝑅𝑅)(𝑇𝑇𝑐𝑐)−𝑏𝑏𝑅𝑅
where Tc = time of concentration (minutes), use min 6.3 minutes
aR, bR = coefficients from table 3.2.1.B
Using Table 3.2.1.B and assuming a design storm return frequency of 100 years, ar = 2.61 and bR = 0.63. 𝑖𝑖𝑅𝑅=(2.61)(6.3)−0.63 =0.82 𝐼𝐼𝑅𝑅=(3.9)(0.82)=3.19 𝑖𝑖𝑖𝑖/ℎ𝑟𝑟 𝑄𝑄𝑅𝑅=(0.9)�3.19𝑖𝑖𝑖𝑖ℎ𝑟𝑟�(0.39𝑎𝑎𝑎𝑎)=1.12 𝑎𝑎𝑐𝑐𝑐𝑐
The conveyance system is a 12” pipe at the shallowest slope of 0.5%. A 12” pipe at 0.5% slope can
convey 2.74 cfs as calculated below, which is more than the 1.12 cfs the site will generate. The
proposed 12” conveyance system is therefore, adequately sized. 𝑄𝑄𝑚𝑚𝑚𝑚𝑚𝑚=(1.49𝑖𝑖)(𝐴𝐴)(𝑅𝑅23)(𝑆𝑆12)
where n = manning’s coefficient
A = area of pipe cross section
R = hydraulic radius
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 5-2
S = slope of pipe
𝑄𝑄𝑚𝑚𝑚𝑚𝑚𝑚=�1.490.012��𝜋𝜋4��14�23 (0.005)12 =2.74 𝑎𝑎𝑐𝑐𝑐𝑐
3.2.1 RATIONAL METHOD
FIGURE 3.2.1.D 100-YEAR 24-HOUR ISOPLUVIALS
2016 Surface Water Design Manual 6/15/2016 3-19
SITE
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 6-4
6. SPECIAL REPORTS AND STUDIES
The following reports and assessments are provided for reference and informational purposes only.
Core Design takes no responsibility or liability for these reports, assessments or designs as they were
not completed under the direct supervision of Core Design.
• Geotechnical Engineering Design Report by Mud Bay Geotechnical Services, LLC, dated
3/18/2019
GEOTECHNICAL ENGINEERING
DESIGN REPORT
3123 Sunset Blvd NE
Renton, WA 98056
Prepared for: Carson AuYeung
Livia Chen
Job No: 1054-KIN
Chris J. Heathman, P.E.
Principle Geotechnical Engineer
Mud Bay Geotechnical Services, LLC
J o b N o : 1 0 54-K I N
Table of Contents
1. Introduction ....................................................................................................................... 1
1.1. General ........................................................................................................................ 1
1.2. Location and Description.............................................................................................. 1
2. Site Conditions .................................................................................................................. 1
2.1. Site Soils and Geology ................................................................................................. 1
2.2. Subsurface and Groundwater Conditions ..................................................................... 1
2.2.1. On-Site Soils ......................................................................................................... 1
2.2.2. Surface Water and Groundwater........................................................................... 2
3. Geologic Hazards .............................................................................................................. 2
3.1. Liquefaction Potential ................................................................................................... 2
3.2. Fault Rupture Hazard ................................................................................................... 2
4. Geotechnical Recommendations ..................................................................................... 3
4.1. Seismic Design ............................................................................................................ 3
4.2. Shallow Foundation Design and Construction .............................................................. 3
4.2.1. Shallow Foundation Support ................................................................................. 3
4.2.2 Lateral Earth Pressures ............................................................................................ 4
4.2.3. Slab-On-Grade Support ............................................................................................ 4
4.2.4. Foundation Drainage Considerations ........................................................................ 5
4.3. Utilities ......................................................................................................................... 5
4.4. Earthwork Considerations ............................................................................................ 5
4.4.1. Structural Fill ......................................................................................................... 5
4.4.2. Site Grading .......................................................................................................... 6
4.5. Temporary Slopes and Structural Shoring ................................................................... 6
5. Recommended Additional Services ................................................................................ 6
6. Intended Use and Limitations .......................................................................................... 6
7. References ........................................................................................................................ 7
LIST OF APPENDICES
Appendix A – Field Exploration Program
LIST OF FIGURES
Figure 1 – Site Map
Figure 2 – Site Plan
Figure 3 – USDA Soil Map
Figure 4 – Geologic Map
Figure 5 – Site Exploration Map
J o b N o : 1 0 5 4 -K I N
LIST OF TABLES
Table 1: Seismic Design Parameters ......................................................................................... 3
Table 2: Lateral Earth Pressure Parameters ............................................................... ………….4
J o b N o : 1 0 54-K I N P a g e | 1
1. Introduction
1.1. General
This report presents the results of our geotechnical investigation and contains geotechnical
recommendations for the project taking place at 3123 Sunset Blvd NE, Renton WA 98056.
The analyses, conclusions, and recommendations in this report are based on one boring
(designated as BH-1-19) completed specifically for this project, published geologic information for
the site and vicinity and our experience with similar geologic materials. The conditions observed
in the bore hole are assumed to be representative of the subsurface conditions throughout the
project area. If during construction, subsurface conditions differ from those described in the
explorations, we should be advised immediately so we may reevaluate the recommendations.
1.2. Location and Description
The parcel is located at 3123 Sunset Blvd NE in Renton, WA. The site location and vicinity
for the property are presented in Figure 1. The site has a history of previous development,
which included a commercial building structure and pavement surface surrounding the building.
The building was recently demolished, and the entire building and pavement was removed
and cleared down to bare earth. The perimeter of the site facing Sunset Blvd NE and NE 12th
St are landscaped with small bushes and shrubs interrupted by driveway access points.
The scope of the project is to develop the site with an 8,000 to 10,000 SF, 2 to 3-story structure
with ground floor to be used for commercial use as a daycare facility. It’s anticipated the structure
will be supported on shallow strip footing foundations. The lowermost story may be a below
ground basement level for additional parking. The existing property is graded at a relatively flat
slope angle. An on-site treatment may be necessary, if infiltration testing and recommendations
are required then it will be addressed in a separate report and is not within the scope of this report.
2. Site Conditions
2.1. Site Soils and Geology
As part of this project, we reviewed available geologic data from the USDA Soil Conservation
Survey and the Washington State Department of Natural Resources and prepared site-specific
geology and soils maps, which are attached as Figures 3 and 4, respectively. The USDA Soil
Conservation Survey map indicates the surface soils at the site consist of Arents, Alderwood
Material, 6 to 15 percent slope. It should be noted the percent slope in these descriptions is an
approximation. The project vicinity geologic map indicates the project site is underlain by
Pleistocene Continental Glacial Till. The conditions in the explorations are generally consistent
with the mapped soils and geology at the site.
2.2. Subsurface and Groundwater Conditions
2.2.1. On-Site Soils
A single hand auger boring, designated BH-1-19, was performed to explore the subsurface
conditions at the site location. The approximate location of the boring is shown on Figure 5. Based
on the conditions observed in the boring, the soils at the site generally consist of moist, brownish
J o b N o : 1 0 5 4 -K I N
gray, gravelly sand. The upper 18 inches of soil is relatively loose due to the recent disturbance
from demolition activities. The material below 18 inches deep is very dense based on the difficulty
of advancing the hole. More detailed information regarding site soil conditions and a description
of our field exploration and procedures is included in Appendix A.
2.2.2. Surface Water and Groundwater
Groundwater was not encountered in boring BH-1-19. It’s not anticipated significant groundwater
is present within the limits of the excavation to be performed as part of the construction of the
project. However, based on the heterogeneous nature of the native glacial till, it is possible small
pockets of perched groundwater will be encountered. Localized seepage is common within lenses
of coarser grained sand and gravel contained in Pleistocene continental glacial till deposits
mapped at the site. Localized seepage typically occurs in areas where coarser soils such as
sands and gravels are trapped within finer grained silts and clays. The groundwater seepage
within these trapped zones generally will not result in surface water seepage until exposed either
through excavation cuts during construction or through natural erosion processes.
There are no notable natural surface water bodies within the site vicinity. The site is in an urban
environment with a significant amount of impervious surface. Surface water runoff from storm
events directly falling onto the ground in this type of environment is generally collected and
directed to detention or infiltration facilities such as swales and ponds, or to catch basins and
conveyed through underground stormwater sewer facilities to an appropriate discharge location.
A small amount of surface water will infiltrate into the ground within landscaped areas and green
space.
3. Geologic Hazards
3.1. Liquefaction Potential
Soil liquefaction is a phenomenon whereby saturated soil deposits temporarily lose strength and
behave as a viscous fluid in response to cyclic loading. Soil types considered at the highest risk
of liquefaction during a seismic event are loose sandy soils. Gravel material can be susceptible
to liquefaction if it contains a significant fraction of sand-sized particles and is capped by less
permeable material. Groundwater was not encountered in boring BH-1-19 to a depth of 7 feet.
Furthermore, the site soils are not considered susceptible to liquefaction based on their high
relative density and limited potential for groundwater at shallow depths, and therefore liquefaction
is not a design consideration for this project.
3.2. Fault Rupture Hazard
The potential impacts of fault rupture include abrupt, large, differential ground movement and
associated damage to structures that might straddle the fault. The nearest active crustal fault is
the Seattle Fault system. The closest mapped fault splay associated with the Seattle Fault system
is located approximately 1.5 to 2.0 miles away from the project site. In our opinion, the risk of fault
rupture at the site is low.
J o b N o : 1 0 5 4 -K I N
4. Geotechnical Recommendations
4.1. Seismic Design
Seismic design should be performed based on the design criteria and hazard maps in the 2015
International Building Code (IBC, 2015) for peak ground acceleration (PGA) at the site location
based on the United States Geological Survey hazard maps for the 2,475 year recurrence interval
at the site location (Peterson et. al, 2014). Adjustment factors should be applied to account for
amplification as ground motions transmit from the bedrock surface up through the soil column to
the ground surface. For design purposes, we recommend assuming Site Class D soils. Seismic
design parameters for the site location are provided in Table 1.
Table 1: Seismic Design Parameters
Site Class based on soil conditions Site Class = D
Peak Horizontal ground acceleration coefficient on Class B rock PGA = 0.61
Site coefficient for the peak ground acceleration coefficient FPGA = 1.1
Effective peak ground acceleration coefficient (g) As=FPGA(PGA)= 0.67
4.2. Shallow Foundation Design and Construction
4.2.1. Shallow Foundation Support
The site development of the parcel includes an 8,000 to 10,000 SF, 2 to 3-story structure with
ground floor to be used for commercial use as a daycare facility. We anticipate that the structure
will be supported on shallow strip footing foundations. In addition, the lowermost story may be a
below ground basement level for parking. Shallow strip footings will be used to support the
structure loads. We anticipate the footings will be supported on native glacial till soils. Prior to
construction of the footings, the subgrade should be cleared and grubbed and the exposed native
subgrade soils should be compacted in place. The subgrade should be inspected for any pockets
of loose material. Loose material should be removed and replaced with a minimum of 6-inches of
Crushed Surfacing Base Course (CSBC) meeting the requirements of Section 9-03.9(3) of the
WSDOT Standard Specifications (WSDOT, 2018) or an equivalent material.
The CSBC should be placed in layers no greater than 6-inches and compacted to at least 95
percent of the maximum dry density. Footings bearing on a subgrade prepared as described
above can be designed using a maximum allowable bearing pressure of 3,500 psf. The maximum
allowable bearing pressure may be increased by up to one-third for short-term transient loading
conditions such as wind and seismic loading. We anticipate the total settlement will not exceed
one inch, and differential settlement along a 50-foot length will not exceed half of the total
settlement. The settlement is expected to be elastic and will occur as the footings are loaded.
We recommend footing subgrade preparation be evaluated by Mud Bay Geotechnical Services,
LLC prior to placement of concrete. Foundation subgrade preparation should not be performed
during periods of wet weather. We recommend staging the foundation subgrade excavation,
compaction of native subgrade soils, and placement of CSBC to limit the time the foundation
subgrade is exposed to weather.
J o b N o : 1 0 5 4 -K I N
4.2.2 Lateral Earth Pressures
Retaining walls or stem walls should be designed to resist lateral earth pressures of the backfill
placed behind the walls. For lateral load analysis, we recommend the geotechnical parameters in
Table 2 be used for lateral design and analysis.
Backfill behind the walls should be placed in horizontal layers no more than 6 inches thick with
each layer compacted to 95 percent of the maximum density. The backfill material should be
comprised of Gravel Backfill for Walls material meeting the requirements of Section 9-03.12(2) of
the WSDOT Standard Specifications (WSDOT, 2018), or an equivalent free-draining material.
Table 2: Lateral Earth Pressure Parameters
Parameter Design Value
Backfill Unit Weight (γ) 135 pcf
Wall Backfill Soil Friction Angle (φf) 37°
Coefficient of Sliding (tan φf) 0.55
Active Earth Pressure (Ka) 0.23 (EFP 31.1 psf)
At Rest Earth Pressure (K0) 0.40 (EFP 54.0 psf)
Passive Earth Pressure (Kp) 8.78 (EFP 1,185 psf)
The passive earth pressure coefficient and coefficient of sliding presented in Table 2 are ultimate
values and should be reduced by a factor of safety equal to 1.5 for final design. The lateral earth
pressure coefficients provided in Table 2 are based on the use of Gravel Backfill for Walls. Active
earth pressures can be assumed for design, provided that the walls can yield laterally at least
0.001H (where H is the exposed wall height in feet). If the wall is not capable of yielding that
amount, then at-rest earth pressures should be used.
Seismic loading represented as a rectangular shaped dynamic uniform lateral surcharge equal to
8H psf should be applied, with the resultant acting at a height of 0.5H, where H is the height of
the wall. This value, which was calculated using the Mononobe-Okabe method, is appropriate for
yielding walls designed in accordance with the 2015 IBC (IBC, 2015).
4.2.3. Slab-On-Grade Support
All interior slabs-on-grade should be underlain by a capillary break at least 6 inches thick
consisting of free-draining, clean, course sand and fine gravel with a maximum particle size of ¾-
inch, no more than 50 percent passing the U.S. No. 4 sieve, and less than 5 percent passing the
U.S. No. 200 sieve.
Prior to placement of the capillary break layer, topsoil, mud, debris, and rootmass should be
cleared and grubbed and the native subgrade soils should be compacted in-place to a dense and
relatively unyielding condition. The six-inch capillary break layer should be compacted to at least
95 percent of the maximum dry density of the material. We recommend considering placement of
a suitable vapor barrier to further retard moisture at the slab-on-grade.
Similar to footing construction, it will be helpful to stage the excavation and subgrade preparation
of slab-on-grade areas to limit the exposure to wet weather placement of the capillary break layer.
J o b N o : 1 0 5 4 -K I N
Once in place and compacted, the low-fines-content capillary break layer will reduce the likelihood
that the subgrade is disturbed.
We recommend using a vertical modulus (Kv1) of 85 pounds per cubic inch (pci) for slab-on- grade
bearing on a subgrade prepared as described above. Note that Kv1 is appropriate for a 1-foot by
1-foot surface and the initial subgrade modulus used for design (Ks) will need to be adjusted based
on the width of the footing or slab considered using the following equation:
Ks = Kv1(B+1)2/(4B2)
where B = foundation or slab width in feet.
4.2.4. Foundation Drainage Considerations
It’s recommended including a perimeter footing drain system, consisting of a 4-inch diameter,
perforated or slotted, rigid plastic pipe placed at the base of the wall footings. The drain should
be embedded in a clean, free-draining sand and gravel meeting the requirements of Section 9-
03.12(4) of the WSDOT Standard Specifications for Gravel Backfill for Drains. The drains should
be sloped slightly to drain to an appropriate discharge area. Appropriate water and weather
proofing measures should be used in order to reduce the potential for leaks through the basement
walls.
4.3. Utilities
We anticipate that buried utilities will need to be constructed as part of the project. The utility
subgrade (base of trench excavation) should be relatively firm prior to placing bedding materials.
Subgrade observed to be soft, pumping, or containing abundant organics or refuse should be
sub-excavated to firm subgrade soil or a maximum depth of 2 feet. Sub-excavated areas should
be backfilled with structural fill.
Material placed directly below, around, and above utility pipes should consist of Gravel Backfill
for Pipe Zone Bedding as described in Section 9-03.12(3) of the WSDOT Standard Specifications
(WSDOT, 2018). The pipe bedding materials should be placed and compacted to a relatively firm
condition in accordance with the manufacturer’s specifications. Bedding and cover should be a
minimum of 6-inches thick.
4.4. Earthwork Considerations
4.4.1. Structural Fill
Soils placed as fill beyond the limits of foundation subgrade, wall backfill, and pipe zone areas
described previously should be considered structural fill. Structural fill should consist of material
meeting the requirements of Common Borrow as described in Section 9-03.14(3) of the WSDOT
Standard Specifications (WSDOT, 2018). Based on the conditions observed in boring BH-1-19,
the onsite material to be removed for construction meets the requirements for Common Borrow.
Structural fill should be placed and compacted in lifts no greater than 8 inches when using
relatively large compaction equipment, such as a vibrating compaction equipment attached to an
excavator or a drum roller. If small, hand-operated compaction equipment is used to compact the
J o b N o : 1 0 5 4 -K I N
structural fill, fill lifts should not exceed 6 inches. Based on the small size of the project and difficult
access, most likely relatively large compaction equipment will be used.
Structural fill should be placed and compacted to between 90 and 92 percent of the maximum dry
density. All other fill material should be placed and compacted as described previously. Fill placed
in softscape, landscape, or common areas that can accommodate some settlement should be
compacted to a relatively firm and unyielding condition.
4.4.2. Site Grading
We recommend grading all permanent cuts and fills to a maximum slope angle of 2H:1V. Until a
layer of vegetation is established, the upper 1 to 2 feet below the surface of the slope may be only
marginally stable. To reduce the potential for short term erosion, coir, jute, or turf reinforcement
mat should be placed on the surface of the slope until vegetation is established.
4.5. Temporary Slopes and Structural Shoring
Stability for all other temporary excavation slopes, structural shoring, and temporary works
necessary to complete the project not shown in the plans for the project remain the responsibility
of the Contractor. The Contractor will determine the appropriate measures to ensure all
excavation is in compliance with local, state and federal safety codes. Washington Administrative
Code 296-155 (WAC, 2009) contains specific requirements for trenches and temporary slopes.
For planning and cost estimating purposes, we recommend assuming 1H:1V temporary slopes
are feasible.
5. Recommended Additional Services
Before construction begins, we recommend a copy of the draft plans and specifications prepared
for the project be made available for review so we can ensure the geotechnical recommendations
in this report are included in the Contract.
Mud Bay Geotechnical Services, LLC is also available to provide geotechnical engineering and
construction monitoring services throughout the remainder of the design and construction of the
project. The integrity of the geotechnical elements of a project depend on proper site preparation
and construction procedures. In addition, engineering decisions may need to be made in the field
if conditions are encountered differ from those described in this report.
During the construction phase of the project, we recommend Mud Bay Geotechnical Services,
LLC be retained to review construction submittals, observe and evaluate subgrade for all slabs-
on-grade and footings, and provide recommendations for any other geotechnical considerations
that may arise during construction.
6. Intended Use and Limitations
This report has been prepared to assist the client and their consultants in the engineering design
and construction of the subject project. It should not be used, in part or in whole for other purposes
without contacting Mud Bay Geotechnical Services, LLC for a review of the applicability of such
reuse. This report should be made available to prospective contractors for their information only
and not as a warranty of ground conditions.
J o b N o : 1 0 5 4 -K I N
The conclusions and recommendations contained in this report are based on Mud Bay
Geotechnical Services, LLC understanding of the project at the time the report was written and
on-site conditions existing at time of the field exploration. If significant changes to the nature,
configuration, or scope of the project occur during the design process, we should be consulted to
determine the impact of such changes on the recommendations and conclusions presented in
this report.
Site exploration and testing describes subsurface conditions only at the sites of subsurface
exploration and at the intervals where samples are collected. These data are interpreted by Mud
Bay Geotechnical Services, LLC rendering an opinion regarding the general subsurface
conditions. Actual subsurface conditions can be discovered only during earthwork and
construction operations. The distribution, continuity, thickness, and characteristics of identified
(and unidentified) subsurface materials may vary considerably from that indicated by the
subsurface data. While nothing can be done to prevent such variability, Mud Bay Geotechnical
Services, LLC is prepared to work with the project team to reduce the impacts of variability on
project design, construction, and performance.
We appreciate the opportunity to serve your geotechnical needs on this project, and look forward
to working with you in the future. Please contact us at your earliest convenience if you have any
questions or would like to discuss the contents of this report.
7. References
International Building Code (IBC), 2015, International Building Code, prepared by International
Code Council.
Petersen, M.D., et al., 2014, Documentation for the 2014 update of the United States national
seismic hazard maps: U.S. Geological Survey Open-File Report 2014–1091, 243 p.,
https://dx.doi.org/10.3133/ofr20141091.
Washington Administrative Code (WAC), 2009, April 1, 2009.
Washington Department of Natural Resources Division of Geology and Earth Resources (DNR),
2016, https://geologyportal.dnr.wa.gov, accessed 8/26/2018 06:05 PM.
Washington State Department of Transportation (WSDOT), 2015, Geotechnical Design Manual,
Washington State Department of Transportation, Olympia WA. (www.wsdot.wa.gov/
Publications/Manuals/M46-03.htm)
Washington State Department of Transportation (WSDOT), 2018, Standard Specifications for
Road, Bridge, and Municipal Construction, Washington State Department of Transportation,
Olympia WA. (www.wsdot.wa.gov/Publications/Manuals/M41-10.htm)
Site Location
Figure 1: Site Map
3123 NE Sunset Blvd,
Renton, WA 98056
Site Development Geotechnical Report
JOB #: 1054-KIN Date: March, 2019
Figure 2: Site Plan
3123 NE Sunset Blvd,
Renton, WA 98056
Site Development Geotechnical Report
JOB #: 1054-KIN Date: March, 2019
LEGEND
Site Location
Figure 2: Geology Map
216 9th Ave SE
Olympia, WA 98501
Seismic Retrofit Geotechnical Report
JOB #: 1040-THU Date: February, 2018
Figure 3: Geologic Map
3123 NE Sunset Blvd,
Renton, WA 98056
Site Development Geotechnical Report
JOB #: 1054-KIN Date: March, 2019
Sources: City of Olympia, Bureau of Land Management, Esri,
HERE, Garmin, INCREMENT P, NGA, USGS | Washington
Division of Geology and Earth Resources
Sources: City of Renton, County of King, Bureau of Land Management, Esri,
HERE, Garmin, INCREMENT P, NGA, USGS | Washington Division of Geology
and Earth Resources
N
Legend
Site location
AmC Arents, Alderwood material, 6 to 15
percent slopes
Ur Urban land
Figure 4: USDA Soil Map
3123 NE Sunset Blvd,
Renton, WA 98056
Site Development Geotechnical Report
JOB #: 1054-KIN Date: March, 2019
Sample Collection Location
BH-1-19
N
JOB #: 1054-KIN Date: March, 2019
Figure 5: Site Exploration Map
3123 NE Sunset Blvd,
Renton, WA 98056
Site Development Geotechnical Report
APPENDIX A – FIELD EXPLORATION PROGRAM
FIELD EXPLORATION PROGRAM
To characterize the surface and subsurface conditions for the project, Mud Bay Geotechnical
Services, LLC performed a single boring, designated BH-1-19. The boring was completed from the existing ground surface at the approximate location shown on Figure 5.
The boring was completed using a Humboldt Manufacturing model H-4206.6A hand auger with
a 3 ¼ inch diameter bucket tube sampler. A prybar was used at selected locations to break up some of the gravel particles in order to facilitate advancing the hole.
The soil samples were classified visually in the field in general accordance with ASTM D2488, the Standard Practice for Description and Identification of Soils (Visual-Manual Procedure). Once transported back to the office, the samples were re-examined and the field classifications were modified accordingly. A summary log of the boring is included in Appendix A. Note the soil descriptions and interfaces shown on the log are interpretive, and actual changes may be gradual. Upon completion, the hole was backfilled to the original ground surface using excavated material from the spoil pile.
Completed:Hammer Type:
Backfilled:Hammer Weight:Hammer Drop:
Groundwater Depth:Total Depth of Boring:
Lithology
Note: the upper 18" was made up of construction overburden
Moist, brownish gray, gravelly sand, with med grain gravels, (SW)
Moist, brownish gray, gravelly sand, with med grain gravels, (SW)
Standard Penetration Slit Spoon Sampler (SPT)
Blows/3/4"Density
0-4 Very Loose
5-10 Loose
11-24 Medium Dense
25-50 Dense
>50 Vey Dense
REF Refusal Moisture Content (%)Additional TestSoil Group Name: modifier, color, moisture, density/consistency, grain size, other descriptors
Rock Description: modifierm color, hardness/degree of concentration, bedding and
joint characteristics, solutions, void conditions.Graphic LogDateSite Development
3/1/2019
Address:Started:
Logan Krehbiel
3123 Sunset Blvd, Renton
WA 98056
Project Number:1054-KIN
Gravel, Sand, Non-Plastic Silt Elastic Silts and Clays
Bailly & Bailly LLC BH-1-19
3/1/2019
3/1/2019
n/a Hand Auger
n/a
Dry Density (pcf)Client:Boring No. 1 of 2:
Drilling Contractor:Drill Rig Type:
3.25 inches
Steel n/a
Soil Density Modifiers
Bit Type:Diameter:
Fluid:
none Elevation:Existing Surface 84"
n/a n/a
Bore Log Symbols
Logged By:Samantha Denham
Drill Crew:
Project:Depth (feet)Sample TypeSample NumberBlow Counts (blows/3/4")California Sampler
Shelby Tube
CPP Sampler
StabIlized Ground water
Groundwater At time of Drilling
Bulk/ Bag Sample
Blows/3/4"
0-1
2-4
5-8
9-15
16-30
31-61
Very Stiff
31-60
Consistency
Very Soft
Soft
Medium Stiff
Stiff
Hard
Very Hard
3
6
S-1
S-2
n/a
n/a
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 7-1
7. OTHER PERMITS
No other permits relevant to this Final TIR are known to be required at this time.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 8-1
8. ESC ANALYSIS AND DESIGN
Per Section 1.2.5.1, Construction Stormwater Pollution Prevention (CSWPP) measures include Erosion
and Sediment Control (ESC) measures and Stormwater Pollution Prevention and Spill (SWPPS) measures.
ESC PLAN ANALYSIS AND DESIGN (PART A)
Design of the ESC plan was completed in conformance with Core Requirement #5 and Appendix D of the
2017 City of Renton Surface Water Design Manual. Compliance with the 13 ESC measures is
summarized below.
1. Clearing Limits: Clearing limits have been delineated on sheet C2.01 of the construction plans.
The clearing limits extend only to those areas that will be disturbed during construction of the
subject project.
2. Cover Measures: Temporary Cover and Permanent Cover measures are specified as notes on
sheet C2.31 of the construction plans.
3. Perimeter Protection: Silt fence will be used for perimeter protection. Silt fence will be installed
along the perimeters of those areas that will be receiving silt-laden runoff. See sheets C2.01 and
C2.32 of the construction plans for locations and detail.
4. Traffic Area Stabilization: A temporary construction access will be installed at the entrance to
the project site. See sheets C2.01 and C2.32 of the construction plans for location and detail.
5. Sediment Retention: Silt fence is utilized for sediment retention for the entire site. As the
portions of the site tributary to the silt fence have average slopes less than 10%, per the 2016
KCSWDM Section D.2.1.3, silt fence can be utilized as primary treatment for a sheet flow
distance of 250 feet. There is a portion of the site along the northeast boundary where slopes
are between 15-20%. This area still meets the requirement of primary treatment at 25% or less
slope with a sheet flow distance of 150 feet.
6. Surface Water Collection: Surface water collection is not necessary due to the site being small
enough to be solely treated with perimeter protection.
7. Dewatering Control: A note on sheet C2.31 of the construction plans addresses dewatering
control.
8. Dust Control: A note on sheet C2.31 of the construction plans addresses the procedure for dust
control should soils become too dry.
9. Flow Control: This measure is not applicable as the site is exempt from any permanent flow
control facilities. The discharged drainage during construction is not expected to be higher than
existing site conditions 2-year and 10-year runoff peaks.
10. Control Pollutants: See SWPPS Plan Design (Part B) below.
11. Protect Existing and Proposed Flow Control BMPs: The proposed drywell is the only BMP that
requires protection. Once the drywell has been installed, the inlet pipe will be plugged to
prevent any drainage from entering the facility. Per the construction sequence, no drainage will
be allowed to discharge into the drywell until the site is stabilized.
12. Maintain BMPs: Notes have been added to sheet C2.31 of the construction plans addressing
maintenance requirements.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 8-2
13. Manage the Project: The project will be managed based on seasonal work limitations and
continual inspection and monitoring throughout the project.
SWPPS PLAN DESIGN (PART B)
Design of the SWPPS plan was completed in conformance with Section 2.3.1.4 of the 2016 KCSWDM.
The CSWPPS plan contains notes establishing what materials and activities will not be allowed on the
site along with notes describing BMPs for treatment of materials and activities that will be allowed on
the site. The contractor shall designate a person as the responsible representative in charge of erosion
control and maintenance of all erosion control and stormwater pollution prevention facilities, see
CSWPPS plan. Pollution-generating activities associated with construction and mitigation are tabulated
below.
1. Storage and Handling of Liquids: Stormwater Pollution Prevention Notes have been added to
sheet C2.31 of the construction plan set addressing storage and handling of liquids.
2. Storage and Stockpiling of Construction Materials and Wastes: Storage of construction
materials and wastes will be stored within a designated stockpile area. Stockpile areas shall be
covered with plastic when not in use. Stockpile height shall not exceed 8 feet.
3. Fueling: Stormwater Pollution Prevention Notes have been added to sheet C2.31 of the
construction plan set addressing fueling.
4. Maintenance, Repairs, and Storage of Vehicles and Equipment: Stormwater Pollution
Prevention Notes have been added to sheet C2.31 of the construction plan set addressing
maintenance, repairs, and storage of vehicles and equipment.
5. Concrete Saw Cutting, Slurry, and Washwater Disposal: Stormwater Pollution Prevention Notes
have been added to sheet C2.31 of the construction plan set addressing concrete saw cutting,
slurry, and washwater disposal.
6. Handling of pH Elevated Water: Stormwater Pollution Prevention Notes have been added to
sheet C2.31 of the construction plan set addressing pH elevated water.
7. Application of Chemicals including Pesticides and Fertilizers: Stormwater Pollution Prevention
Notes have been added to sheet C2.31 of the construction plan set addressing application of
chemicals.
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 9-1
9. BOND QUANTITIES, FACILITY SUMMARIES, AND DECLARATION OF
COVENANT
See bond quantities on the following pages. The facility summary and declaration of covenant will be
addressed upon project approval.
Planning Division |1055 South Grady Way – 6 th Floor | Renton, WA 98057 (425) 430-7200
Date Prepared:
Name:
PE Registration No:
Firm Name:
Firm Address:
Phone No.
Email Address:
Project Name: Project Owner:
CED Plan # (LUA):Phone:
CED Permit # (U):Address:
Site Address:
Street Intersection:Addt'l Project Owner:
Parcel #(s):Phone:
Address:
Clearing and grading greater than or equal to 5,000 board feet of timber?
Yes/No:NO Water Service Provided by:
If Yes, Provide Forest Practice Permit #:Sewer Service Provided by:
Abbreviated Legal
Description:
SE 1/4 SW 1/4 SECTION 4 TOWNSHIP 23N RANGE 5E
3123 NE Sunset BLVD.
1025 N 36th St.
Sunset BLVD. & NE 12th
C19006760
206-430-9827
12/23/2019
Prepared by:
FOR CONSTRUCTIONProject Phase 1
Gina Brooks
36478
Core Design
12100 NE 195th Street, Suite 300
425-885-7877
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
PROJECT INFORMATION
CITY OF RENTON
CITY OF RENTON
1 Select the current project status/phase from the following options:
For Approval - Preliminary Data Enclosed, pending approval from the City;
For Construction - Estimated Data Enclosed, Plans have been approved for contruction by the City;
Project Closeout - Final Costs and Quantities Enclosed for Project Close-out Submittal
Engineer Stamp Required
(all cost estimates must have original wet stamp and signature)
Clearing and Grading Utility Providers
N/A
Project Location and Description Project Owner Information
KIDDIE RESEARCH DAYCARE CENTER
Renton, WA 98056
042305-9155
Kiddie Research, LLC
LUA 19-000129
Page 1 of 1
Ref 8-H Bond Quantity Worksheet SECTION I PROJECT INFORMATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
UnitReference #Price Unit Quantity CostBackfill & compaction-embankment ESC-1 6.50$ CY Check dams, 4" minus rock ESC-2 SWDM 5.4.6.3 80.00$ EachCatch Basin Protection ESC-3 35.50$ Each 7 248.50Crushed surfacing 1 1/4" minus ESC-4 WSDOT 9-03.9(3)95.00$ CY Ditching ESC-5 9.00$ CY Excavation-bulk ESC-6 2.00$ CY Fence, silt ESC-7 SWDM 5.4.3.1 1.50$ LF 249 373.50Fence, Temporary (NGPE)ESC-8 1.50$ LF Geotextile Fabric ESC-9 2.50$ SY Hay Bale Silt Trap ESC-10 0.50$ Each Hydroseeding ESC-11 SWDM 5.4.2.4 0.80$ SY Interceptor Swale / Dike ESC-12 1.00$ LF Jute Mesh ESC-13 SWDM 5.4.2.2 3.50$ SY Level Spreader ESC-14 1.75$ LF Mulch, by hand, straw, 3" deep ESC-15 SWDM 5.4.2.1 2.50$ SY Mulch, by machine, straw, 2" deep ESC-16 SWDM 5.4.2.1 2.00$ SY Piping, temporary, CPP, 6"ESC-17 12.00$ LF Piping, temporary, CPP, 8"ESC-18 14.00$ LF Piping, temporary, CPP, 12"ESC-19 18.00$ LF Plastic covering, 6mm thick, sandbagged ESC-20 SWDM 5.4.2.3 4.00$ SY Rip Rap, machine placed; slopes ESC-21 WSDOT 9-13.1(2)45.00$ CY Rock Construction Entrance, 50'x15'x1'ESC-22 SWDM 5.4.4.1 1,800.00$ Each Rock Construction Entrance, 100'x15'x1'ESC-23 SWDM 5.4.4.1 3,200.00$ Each 1 3,200.00Sediment pond riser assembly ESC-24 SWDM 5.4.5.2 2,200.00$ Each Sediment trap, 5' high berm ESC-25 SWDM 5.4.5.1 19.00$ LF Sed. trap, 5' high, riprapped spillway berm section ESC-26 SWDM 5.4.5.1 70.00$ LF Seeding, by hand ESC-27 SWDM 5.4.2.4 1.00$ SY Sodding, 1" deep, level ground ESC-28 SWDM 5.4.2.5 8.00$ SY Sodding, 1" deep, sloped ground ESC-29 SWDM 5.4.2.5 10.00$ SY TESC Supervisor ESC-30 110.00$ HR Water truck, dust control ESC-31 SWDM 5.4.7 140.00$ HR UnitReference #Price Unit Quantity Cost
EROSION/SEDIMENT SUBTOTAL:3,822.00SALES TAX @ 10%382.20EROSION/SEDIMENT TOTAL:4,204.20
(A)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR EROSION & SEDIMENT CONTROL
Description No.(A)
WRITE-IN-ITEMS
Page 1 of 1
Ref 8-H Bond Quantity Worksheet SECTION II.a EROSION_CONTROL
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public Private
Right-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.CostGENERAL ITEMS Backfill & Compaction- embankment GI-1 6.00$ CY
Backfill & Compaction- trench GI-2 9.00$ CY
Clear/Remove Brush, by hand (SY)GI-3 1.00$ SY
Bollards - fixed GI-4 240.74$ Each 5 1,203.70
Bollards - removable GI-5 452.34$ Each
Clearing/Grubbing/Tree Removal GI-6 10,000.00$ Acre
Excavation - bulk GI-7 2.00$ CY 31 62.00Excavation - Trench GI-8 5.00$ CYFencing, cedar, 6' high GI-9 20.00$ LFFencing, chain link, 4'GI-10 38.31$ LFFencing, chain link, vinyl coated, 6' high GI-11 20.00$ LF
Fencing, chain link, gate, vinyl coated, 20' GI-12 1,400.00$ Each
Fill & compact - common barrow GI-13 25.00$ CY 540 13,500.00
Fill & compact - gravel base GI-14 27.00$ CY
Fill & compact - screened topsoil GI-15 39.00$ CY
Gabion, 12" deep, stone filled mesh GI-16 65.00$ SY
Gabion, 18" deep, stone filled mesh GI-17 90.00$ SY
Gabion, 36" deep, stone filled mesh GI-18 150.00$ SY
Grading, fine, by hand GI-19 2.50$ SY
Grading, fine, with grader GI-20 2.00$ SYMonuments, 3' Long GI-21 250.00$ EachSensitive Areas Sign GI-22 7.00$ EachSodding, 1" deep, sloped ground GI-23 8.00$ SY
Surveying, line & grade GI-24 850.00$ Day
Surveying, lot location/lines GI-25 1,800.00$ Acre
Topsoil Type A (imported)GI-26 28.50$ CY
Traffic control crew ( 2 flaggers )GI-27 120.00$ HR
Trail, 4" chipped wood GI-28 8.00$ SY
Trail, 4" crushed cinder GI-29 9.00$ SY
Trail, 4" top course GI-30 12.00$ SY
Conduit, 2"GI-31 5.00$ LF
Wall, retaining, concrete GI-32 55.00$ SFWall, rockery GI-33 15.00$ SF
SUBTOTAL THIS PAGE:14,765.70
(B)(C)(D)(E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR STREET AND SITE IMPROVEMENTS
Quantity Remaining
(Bond Reduction)
(B)(C)
Page 1 of 3
Ref 8-H Bond Quantity Worksheet SECTION II.b TRANSPORTATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public Private
Right-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR STREET AND SITE IMPROVEMENTS
Quantity Remaining
(Bond Reduction)
(B)(C)
ROAD IMPROVEMENT/PAVEMENT/SURFACINGAC Grinding, 4' wide machine < 1000sy RI-1 30.00$ SY
AC Grinding, 4' wide machine 1000-2000sy RI-2 16.00$ SY
AC Grinding, 4' wide machine > 2000sy RI-3 10.00$ SY
AC Removal/Disposal RI-4 35.00$ SY
Barricade, Type III ( Permanent )RI-5 56.00$ LF
Guard Rail RI-6 30.00$ LF
Curb & Gutter, rolled RI-7 17.00$ LFCurb & Gutter, vertical RI-8 12.50$ LF 160 2,000.00Curb and Gutter, demolition and disposal RI-9 18.00$ LF 160 2,880.00Curb, extruded asphalt RI-10 5.50$ LFCurb, extruded concrete RI-11 7.00$ LF
Sawcut, asphalt, 3" depth RI-12 1.85$ LF
Sawcut, concrete, per 1" depth RI-13 3.00$ LF
Sealant, asphalt RI-14 2.00$ LF
Shoulder, gravel, 4" thick RI-15 15.00$ SY
Sidewalk, 4" thick RI-16 38.00$ SY 93 3,534.00 105 3,990.00
Sidewalk, 4" thick, demolition and disposal RI-17 32.00$ SY 128 4,096.00
Sidewalk, 5" thick RI-18 41.00$ SY 24 984.00 18 738.00
Sidewalk, 5" thick, demolition and disposal RI-19 40.00$ SY
Sign, Handicap RI-20 85.00$ Each 2 170.00Striping, per stall RI-21 7.00$ Each 14 98.00Striping, thermoplastic, ( for crosswalk )RI-22 3.00$ SFStriping, 4" reflectorized line RI-23 0.50$ LF
Additional 2.5" Crushed Surfacing RI-24 3.60$ SY
HMA 1/2" Overlay 1.5" RI-25 14.00$ SY
HMA 1/2" Overlay 2"RI-26 18.00$ SY 491 8,838.00
HMA Road, 2", 4" rock, First 2500 SY RI-27 28.00$ SY
HMA Road, 2", 4" rock, Qty. over 2500SY RI-28 21.00$ SY
HMA Road, 4", 6" rock, First 2500 SY RI-29 45.00$ SY 491 22,095.00
HMA Road, 4", 6" rock, Qty. over 2500 SY RI-30 37.00$ SY
HMA Road, 4", 4.5" ATB RI-31 38.00$ SY
Gravel Road, 4" rock, First 2500 SY RI-32 15.00$ SY 33 495.00Gravel Road, 4" rock, Qty. over 2500 SY RI-33 10.00$ SYThickened Edge RI-34 8.60$ LF
SUBTOTAL THIS PAGE:9,960.00 4,272.00 35,686.00
(B)(C)(D)(E)
Page 2 of 3
Ref 8-H Bond Quantity Worksheet SECTION II.b TRANSPORTATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public Private
Right-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR STREET AND SITE IMPROVEMENTS
Quantity Remaining
(Bond Reduction)
(B)(C)
PARKING LOT SURFACING No.2" AC, 2" top course rock & 4" borrow PL-1 21.00$ SY
2" AC, 1.5" top course & 2.5" base course PL-2 28.00$ SY
4" select borrow PL-3 5.00$ SY
1.5" top course rock & 2.5" base course PL-4 14.00$ SY
SUBTOTAL PARKING LOT SURFACING:
(B)(C)(D)(E)
LANDSCAPING & VEGETATION No.Street Trees LA-1 250.00$ EA
Median Landscaping LA-2
Right-of-Way Landscaping LA-3Wetland Landscaping LA-4
SUBTOTAL LANDSCAPING & VEGETATION:
(B)(C)(D)(E)
TRAFFIC & LIGHTING No.Signs TR-1Street Light System ( # of Poles)TR-2 10,000.00$ EA 3 30,000.00Traffic Signal TR-3
Traffic Signal Modification TR-4
SUBTOTAL TRAFFIC & LIGHTING:30,000.00
(B)(C)(D)(E)
WRITE-IN-ITEMS
SUBTOTAL WRITE-IN ITEMS:
STREET AND SITE IMPROVEMENTS SUBTOTAL:39,960.00 4,272.00 50,451.70
SALES TAX @ 10%3,996.00 427.20 5,045.17
STREET AND SITE IMPROVEMENTS TOTAL:43,956.00 4,699.20 55,496.87
(B)(C)(D)(E)
Page 3 of 3
Ref 8-H Bond Quantity Worksheet SECTION II.b TRANSPORTATION
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.CostDRAINAGE (CPE = Corrugated Polyethylene Pipe, N12 or Equivalent) For Culvert prices, Average of 4' cover was assumed. Assume perforated PVC is same price as solid pipe.) Access Road, R/D D-1 26.00$ SY
* (CBs include frame and lid)
Beehive D-2 90.00$ EachThrough-curb Inlet Framework D-3 400.00$ EachCB Type I D-4 1,500.00$ Each 1 1,500.00 2 3,000.00CB Type IL D-5 1,750.00$ Each 1 1,750.00
CB Type II, 48" diameter D-6 2,300.00$ Each 1 2,300.00 1 2,300.00
for additional depth over 4' D-7 480.00$ FTCB Type II, 54" diameter D-8 2,500.00$ Each for additional depth over 4'D-9 495.00$ FTCB Type II, 60" diameter D-10 2,800.00$ Each
for additional depth over 4'D-11 600.00$ FT
CB Type II, 72" diameter D-12 6,000.00$ Each for additional depth over 4'D-13 850.00$ FTCB Type II, 96" diameter D-14 14,000.00$ Each for additional depth over 4'D-15 925.00$ FT
Trash Rack, 12"D-16 350.00$ Each
Trash Rack, 15"D-17 410.00$ EachTrash Rack, 18"D-18 480.00$ EachTrash Rack, 21"D-19 550.00$ EachCleanout, PVC, 4"D-20 150.00$ Each
Cleanout, PVC, 6"D-21 170.00$ Each 1 170.00
Cleanout, PVC, 8"D-22 200.00$ Each 1 200.00Culvert, PVC, 4" D-23 10.00$ LFCulvert, PVC, 6" D-24 13.00$ LFCulvert, PVC, 8" D-25 15.00$ LF
Culvert, PVC, 12" D-26 23.00$ LF
Culvert, PVC, 15" D-27 35.00$ LFCulvert, PVC, 18" D-28 41.00$ LFCulvert, PVC, 24"D-29 56.00$ LFCulvert, PVC, 30" D-30 78.00$ LF
Culvert, PVC, 36" D-31 130.00$ LF
Culvert, CMP, 8"D-32 19.00$ LFCulvert, CMP, 12"D-33 29.00$ LF
SUBTOTAL THIS PAGE:5,550.00 5,670.00
(B)(C)(D)(E)
Quantity Remaining
(Bond Reduction) (B)(C)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Page 1 of 5
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Quantity Remaining
(Bond Reduction) (B)(C)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
DRAINAGE (Continued)Culvert, CMP, 15"D-34 35.00$ LF
Culvert, CMP, 18"D-35 41.00$ LF
Culvert, CMP, 24"D-36 56.00$ LFCulvert, CMP, 30"D-37 78.00$ LFCulvert, CMP, 36"D-38 130.00$ LF
Culvert, CMP, 48"D-39 190.00$ LFCulvert, CMP, 60"D-40 270.00$ LFCulvert, CMP, 72"D-41 350.00$ LFCulvert, Concrete, 8"D-42 42.00$ LF
Culvert, Concrete, 12"D-43 48.00$ LF
Culvert, Concrete, 15"D-44 78.00$ LFCulvert, Concrete, 18"D-45 48.00$ LFCulvert, Concrete, 24"D-46 78.00$ LFCulvert, Concrete, 30"D-47 125.00$ LF
Culvert, Concrete, 36"D-48 150.00$ LF
Culvert, Concrete, 42"D-49 175.00$ LFCulvert, Concrete, 48"D-50 205.00$ LFCulvert, CPE Triple Wall, 6" D-51 14.00$ LFCulvert, CPE Triple Wall, 8" D-52 16.00$ LF
Culvert, CPE Triple Wall, 12" D-53 24.00$ LF
Culvert, CPE Triple Wall, 15" D-54 35.00$ LFCulvert, CPE Triple Wall, 18" D-55 41.00$ LFCulvert, CPE Triple Wall, 24" D-56 56.00$ LFCulvert, CPE Triple Wall, 30" D-57 78.00$ LF
Culvert, CPE Triple Wall, 36" D-58 130.00$ LF
Culvert, LCPE, 6"D-59 60.00$ LFCulvert, LCPE, 8"D-60 72.00$ LFCulvert, LCPE, 12"D-61 84.00$ LFCulvert, LCPE, 15"D-62 96.00$ LF
Culvert, LCPE, 18"D-63 108.00$ LF
Culvert, LCPE, 24"D-64 120.00$ LFCulvert, LCPE, 30"D-65 132.00$ LFCulvert, LCPE, 36"D-66 144.00$ LFCulvert, LCPE, 48"D-67 156.00$ LF
Culvert, LCPE, 54"D-68 168.00$ LF
SUBTOTAL THIS PAGE:
(B)(C)(D)(E)
Page 2 of 5
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Quantity Remaining
(Bond Reduction) (B)(C)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
DRAINAGE (Continued)Culvert, LCPE, 60"D-69 180.00$ LF
Culvert, LCPE, 72"D-70 192.00$ LF
Culvert, HDPE, 6"D-71 42.00$ LFCulvert, HDPE, 8"D-72 42.00$ LFCulvert, HDPE, 12"D-73 74.00$ LFCulvert, HDPE, 15"D-74 106.00$ LF
Culvert, HDPE, 18"D-75 138.00$ LF
Culvert, HDPE, 24"D-76 221.00$ LFCulvert, HDPE, 30"D-77 276.00$ LFCulvert, HDPE, 36"D-78 331.00$ LFCulvert, HDPE, 48"D-79 386.00$ LF
Culvert, HDPE, 54"D-80 441.00$ LF
Culvert, HDPE, 60"D-81 496.00$ LFCulvert, HDPE, 72"D-82 551.00$ LFPipe, Polypropylene, 6"D-83 84.00$ LF 10 840.00 10 840.00 13 1,092.00Pipe, Polypropylene, 8"D-84 89.00$ LF 5 445.00
Pipe, Polypropylene, 12"D-85 95.00$ LF 170 16,150.00 10 950.00 35 3,325.00
Pipe, Polypropylene, 15"D-86 100.00$ LFPipe, Polypropylene, 18"D-87 106.00$ LFPipe, Polypropylene, 24"D-88 111.00$ LFPipe, Polypropylene, 30"D-89 119.00$ LF
Pipe, Polypropylene, 36"D-90 154.00$ LF
Pipe, Polypropylene, 48"D-91 226.00$ LFPipe, Polypropylene, 54"D-92 332.00$ LFPipe, Polypropylene, 60"D-93 439.00$ LFPipe, Polypropylene, 72"D-94 545.00$ LF
Culvert, DI, 6"D-95 61.00$ LF
Culvert, DI, 8"D-96 84.00$ LFCulvert, DI, 12"D-97 106.00$ LFCulvert, DI, 15"D-98 129.00$ LFCulvert, DI, 18"D-99 152.00$ LF
Culvert, DI, 24"D-100 175.00$ LF
Culvert, DI, 30"D-101 198.00$ LFCulvert, DI, 36"D-102 220.00$ LFCulvert, DI, 48"D-103 243.00$ LFCulvert, DI, 54"D-104 266.00$ LF
Culvert, DI, 60"D-105 289.00$ LF
Culvert, DI, 72"D-106 311.00$ LF
SUBTOTAL THIS PAGE:16,990.00 1,790.00 4,862.00
(B)(C)(D)(E)
Page 3 of 5
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Quantity Remaining
(Bond Reduction) (B)(C)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
Specialty Drainage ItemsDitching SD-1 9.50$ CY
Flow Dispersal Trench (1,436 base+)SD-3 28.00$ LF
French Drain (3' depth)SD-4 26.00$ LFGeotextile, laid in trench, polypropylene SD-5 3.00$ SYMid-tank Access Riser, 48" dia, 6' deep SD-6 2,000.00$ EachPond Overflow Spillway SD-7 16.00$ SY
Restrictor/Oil Separator, 12"SD-8 1,150.00$ Each 1 1,150.00
Restrictor/Oil Separator, 15"SD-9 1,350.00$ EachRestrictor/Oil Separator, 18"SD-10 1,700.00$ EachRiprap, placed SD-11 42.00$ CYTank End Reducer (36" diameter)SD-12 1,200.00$ Each
Infiltration pond testing SD-13 125.00$ HR
Permeable Pavement SD-14Permeable Concrete Sidewalk SD-15Culvert, Box __ ft x __ ft SD-16
SUBTOTAL SPECIALTY DRAINAGE ITEMS:1,150.00
(B)(C)(D)(E)STORMWATER FACILITIES (Include Flow Control and Water Quality Facility Summary Sheet and Sketch)Detention Pond SF-1 Each
Detention Tank SF-2 Each Detention Vault SF-3 Each
Infiltration Pond SF-4 Each
Infiltration Tank SF-5 Each Infiltration Vault SF-6 Each
Infiltration Trenches SF-7 Each
Basic Biofiltration Swale SF-8 Each Wet Biofiltration Swale SF-9 Each
Wetpond SF-10 Each
Wetvault SF-11 Each Sand Filter SF-12 Each Sand Filter Vault SF-13 Each
Linear Sand Filter SF-14 Each Proprietary Facility SF-15 Each Bioretention Facility SF-16 Each
SUBTOTAL STORMWATER FACILITIES:
(B)(C)(D)(E)
Page 4 of 5
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Quantity Remaining
(Bond Reduction) (B)(C)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR DRAINAGE AND STORMWATER FACILITIES
WRITE-IN-ITEMS (INCLUDE ON-SITE BMPs)WI-1
WI-2WI-3WI-4
WI-5WI-6WI-7
WI-8
WI-9WI-10
WI-11
WI-12WI-13
WI-14
WI-15
SUBTOTAL WRITE-IN ITEMS:
DRAINAGE AND STORMWATER FACILITIES SUBTOTAL:16,990.00 7,340.00 11,682.00
SALES TAX @ 10%1,699.00 734.00 1,168.20
DRAINAGE AND STORMWATER FACILITIES TOTAL:18,689.00 8,074.00 12,850.20
(B)(C)(D)(E)
Page 5 of 5
Ref 8-H Bond Quantity Worksheet SECTION II.c DRAINAGE
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public Private
Right-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Connection to Existing Watermain W-1 2,000.00$ Each 1 2,000.00
Ductile Iron Watermain, CL 52, 4 Inch Diameter W-2 50.00$ LFDuctile Iron Watermain, CL 52, 6 Inch Diameter W-3 56.00$ LFDuctile Iron Watermain, CL 52, 8 Inch Diameter W-4 60.00$ LF
Ductile Iron Watermain, CL 52, 10 Inch Diameter W-5 70.00$ LFDuctile Iron Watermain, CL 52, 12 Inch Diameter W-6 80.00$ LFGate Valve, 4 inch Diameter W-7 500.00$ Each
Gate Valve, 6 inch Diameter W-8 700.00$ Each 1 700.00Gate Valve, 8 Inch Diameter W-9 800.00$ EachGate Valve, 10 Inch Diameter W-10 1,000.00$ Each
Gate Valve, 12 Inch Diameter W-11 1,200.00$ Each
Fire Hydrant Assembly W-12 4,000.00$ Each 1 4,000.00Permanent Blow-Off Assembly W-13 1,800.00$ Each
Air-Vac Assembly, 2-Inch Diameter W-14 2,000.00$ Each
Air-Vac Assembly, 1-Inch Diameter W-15 1,500.00$ EachCompound Meter Assembly 3-inch Diameter W-16 8,000.00$ Each
Compound Meter Assembly 4-inch Diameter W-17 9,000.00$ Each
Compound Meter Assembly 6-inch Diameter W-18 10,000.00$ EachPressure Reducing Valve Station 8-inch to 10-inch W-19 20,000.00$ Each
WATER SUBTOTAL:6,700.00
SALES TAX @ 10%670.00
WATER TOTAL:7,370.00
(B)(C)(D)(E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR WATER
Quantity Remaining
(Bond Reduction) (B)(C)
Page 1 of 1
Ref 8-H Bond Quantity Worksheet SECTION II.d WATER
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
CED Permit #:C19006760
Existing Future Public PrivateRight-of-Way Improvements Improvements
(D) (E)Description No. Unit Price Unit Quant.Cost Quant.Cost Quant.Cost Quant.Cost
Clean Outs SS-1 1,000.00$ Each 2 2,000.00Grease Interceptor, 500 gallon SS-2 8,000.00$ EachGrease Interceptor, 1000 gallon SS-3 10,000.00$ Each
Grease Interceptor, 1500 gallon SS-4 15,000.00$ EachSide Sewer Pipe, PVC. 4 Inch Diameter SS-5 80.00$ LFSide Sewer Pipe, PVC. 6 Inch Diameter SS-6 95.00$ LF 142 13,490.00
Sewer Pipe, PVC, 8 inch Diameter SS-7 105.00$ LF
Sewer Pipe, PVC, 12 Inch Diameter SS-8 120.00$ LFSewer Pipe, DI, 8 inch Diameter SS-9 115.00$ LF
Sewer Pipe, DI, 12 Inch Diameter SS-10 130.00$ LF
Manhole, 48 Inch Diameter SS-11 6,000.00$ EachManhole, 54 Inch Diameter SS-13 6,500.00$ Each
Manhole, 60 Inch Diameter SS-15 7,500.00$ Each
Manhole, 72 Inch Diameter SS-17 8,500.00$ EachManhole, 96 Inch Diameter SS-19 14,000.00$ EachPipe, C-900, 12 Inch Diameter SS-21 180.00$ LF
Outside Drop SS-24 1,500.00$ LSInside Drop SS-25 1,000.00$ LSSewer Pipe, PVC, ____ Inch Diameter SS-26Lift Station (Entire System)SS-27 LS
SANITARY SEWER SUBTOTAL:15,490.00
SALES TAX @ 10%1,549.00
SANITARY SEWER TOTAL:17,039.00
(B)(C)(D)(E)
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
FOR SANITARY SEWER
Quantity Remaining
(Bond Reduction) (B)(C)
Page 1 of 1
Ref 8-H Bond Quantity Worksheet SECTION II.e SANITARY SEWER
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
Planning Division |1055 South Grady Way – 6th Floor | Renton, WA 98057 (425) 430-7200
Date:
Name:Project Name:
PE Registration No:CED Plan # (LUA):
Firm Name:CED Permit # (U):
Firm Address:Site Address:
Phone No.Parcel #(s):
Email Address:Project Phase:
Site Restoration/Erosion Sediment Control Subtotal (a)
Existing Right-of-Way Improvements Subtotal (b)(b)51,326.00$
Future Public Improvements Subtotal (c)4,699.20$
Stormwater & Drainage Facilities (Public & Private) Subtotal (d)(d)39,613.20$
(e)
(f)
Site Restoration
Civil Construction Permit
Maintenance Bond 19,127.68$
Bond Reduction 2
Construction Permit Bond Amount 3
Minimum Bond Amount is $10,000.00
1 Estimate Only - May involve multiple and variable components, which will be established on an individual basis by Development Engineering.
2 The City of Renton allows one request only for bond reduction prior to the maintenance period. Reduction of not more than 70% of the original bond amount, provided that the remaining 30% will
cover all remaining items to be constructed.
3 Required Bond Amounts are subject to review and modification by Development Engineering.
* Note: The word BOND as used in this document means any financial guarantee acceptable to the City of Renton.
** Note: All prices include labor, equipment, materials, overhead and profit.
EST1
((b) + (c) + (d)) x 20%
-$
MAINTENANCE BOND */**
(after final acceptance of construction)
4,204.20$
51,326.00$
116,602.20$
4,204.20$
-$
39,613.20$
-$
120,806.40$
P
(a) x 100%
SITE IMPROVEMENT BOND QUANTITY WORKSHEET
BOND CALCULATIONS
12/23/2019
Gina Brooks
36478
Core Design
R
((b x 150%) + (d x 100%))
S
(e) x 150% + (f) x 100%
Bond Reduction: Existing Right-of-Way Improvements (Quantity
Remaining)2
Bond Reduction: Stormwater & Drainage Facilities (Quantity
Remaining)2
T
(P +R - S)
Prepared by:Project Information
CONSTRUCTION BOND AMOUNT */**
(prior to permit issuance)
425-885-7877
KIDDIE RESEARCH DAYCARE CENTER
LUA 19-000129
3123 NE Sunset BLVD.
042305-9155
FOR CONSTRUCTION
C19006760
12100 NE 195th Street, Suite 300
Page 1 of 1
Ref 8-H Bond Quantity Worksheet SECTION III. BOND WORKSHEET
Unit Prices Updated: 06/14/2016
Version: 04/26/2017
Printed 2/21/2020
Core Design, Inc. KIDDIE RESEARCH DAYCARE CENTER Page 10-1
10. OPERATIONS AND MAINTENANCE
See Operations and Maintenance Manual on the following pages.
CITY OF RENTON SURFACE WATER DESIGN MANUAL
2017 City of Renton Surface Water Design Manual 12/12/2016 A-1
APPENDIX A
MAINTENANCE REQUIREMENTS FOR
STORMWATER FACILITIES AND ON-SITE
BMPS
This appendix contains the maintenance requirements for the following typical stormwater flow control
and water quality facilities and on-site BMPs (ctrl/click the title to follow the link):
No. 1 – Detention Ponds
No. 2 – Infiltration Facilities
No. 3 – Detention Tanks and Vaults
No. 4 – Control Structure/Flow Restrictor
No. 5 – Catch Basins and Manholes
No. 6 – Conveyance Pipes and Ditches
No. 7 – Debris Barriers (e.g., trash racks)
No. 8 – Energy Dissipaters
No. 9 – Fencing
No. 10 – Gates/Bollards/Access Barriers
No. 11 – Grounds (landscaping)
No. 12 – Access Roads
No. 13 – Basic Bioswale (grass)
No. 14 – Wet Bioswale
No. 15 – Filter Strip
No. 16 – Wetpond
No. 17 – Wetvault
No. 18 – Stormwater Wetland
No. 19 – Sand Filter Pond
No. 20 – Sand Filter Vault
No. 21 – Proprietary Facility Cartridge Filter Systems
No. 22 – Baffle Oil/Water Separator
No. 23 – Coalescing Plate Oil/Water Separator
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-2
No. 24 – Catch Basin Insert (not allowed in the city for oil control)
No. 25 – Drywell BMP
No. 26 – Gravel Filled Infiltration Trench BMP
No. 27 – Gravel Filled Dispersion Trench BMP
No. 28 – Native Vegetated Surface/Native Vegetated Landscape BMP
No. 29 – Perforated Pipe Connections BMP
No. 30 – Permeable Pavement BMP
No. 31 – Bioretention BMP
No. 32 – RainWater Harvesting BMP
No. 33 – Rock Pad BMP
No. 34 – Sheet Flow BMP
No. 35 – Splash Block BMP
No. 36 – Vegetated Roof BMP
No. 37 – Rain Garden BMP
No. 38 – Soil Amendment BMP
No. 39 – Retained Trees
No. 40 – Filterra System
No. 41 – Compost Amended Vegetated Filter Strip (CAVFS)
No. 42 – Media Filter Drain (MFD)
No. 43 – Compost-Amended Biofiltration Swale
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-10
NO. 5 – CATCH BASINS AND MANHOLES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Structure Sediment accumulation Sediment exceeds 60% of the depth from the bottom of the catch basin to the invert of the lowest pipe into or out of the catch basin or is within 6 inches of the invert of the lowest pipe into or out of the catch basin.
Sump of catch basin contains no sediment.
Trash and debris Trash or debris of more than ½ cubic foot which is located immediately in front of the catch basin opening or is blocking capacity of the catch basin by more than 10%.
No Trash or debris blocking or potentially blocking entrance to catch basin.
Trash or debris in the catch basin that exceeds 1/3 the depth from the bottom of basin to invert the lowest pipe into or out of the basin.
No trash or debris in the catch basin.
Dead animals or vegetation that could generate odors that could cause complaints or dangerous gases (e.g., methane).
No dead animals or vegetation present within catch basin.
Deposits of garbage exceeding 1 cubic foot in volume. No condition present which would attract or support the breeding of insects or rodents.
Damage to frame and/or top slab Corner of frame extends more than ¾ inch past curb face into the street (If applicable).
Frame is even with curb.
Top slab has holes larger than 2 square inches or cracks wider than ¼ inch. Top slab is free of holes and cracks.
Frame not sitting flush on top slab, i.e., separation of more than ¾ inch of the frame from the top slab.
Frame is sitting flush on top slab.
Cracks in walls or bottom Cracks wider than ½ inch and longer than 3 feet, any evidence of soil particles entering catch basin through cracks, or maintenance person judges that catch
basin is unsound.
Catch basin is sealed and is structurally sound.
Cracks wider than ½ inch and longer than 1 foot at the joint of any inlet/outlet pipe or any evidence of soil particles entering catch basin through cracks.
No cracks more than 1/4 inch wide at the joint of inlet/outlet pipe.
Settlement/ misalignment Catch basin has settled more than 1 inch or has rotated more than 2 inches out of alignment.
Basin replaced or repaired to design standards.
Damaged pipe joints Cracks wider than ½-inch at the joint of the inlet/outlet pipes or any evidence of soil entering the catch basin at the joint of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the joint of inlet/outlet pipes.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate. No contaminants present other than a surface oil film.
Inlet/Outlet Pipe Sediment accumulation Sediment filling 20% or more of the pipe. Inlet/outlet pipes clear of sediment.
Trash and debris Trash and debris accumulated in
inlet/outlet pipes (includes floatables and non-floatables).
No trash or debris in pipes.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016 A-11
NO. 5 – CATCH BASINS AND MANHOLES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Inlet/Outlet Pipe (cont.) Damaged inlet/outlet pipe Cracks wider than ½-inch at the joint of the inlet/outlet pipes or any evidence of soil entering at the joints of the inlet/outlet pipes.
No cracks more than ¼-inch wide at the joint of the inlet/outlet pipe.
Metal Grates (Catch Basins) Unsafe grate opening Grate with opening wider than 7/8 inch. Grate opening meets design standards.
Trash and debris Trash and debris that is blocking more than 20% of grate surface. Grate free of trash and debris. footnote to guidelines for disposal
Damaged or missing grate Grate missing or broken member(s) of the grate. Any open structure requires urgent maintenance.
Grate is in place and meets design standards.
Manhole Cover/Lid Cover/lid not in place Cover/lid is missing or only partially in place. Any open structure requires urgent maintenance.
Cover/lid protects opening to structure.
Locking mechanism not working Mechanism cannot be opened by one maintenance person with proper tools. Bolts cannot be seated. Self-locking cover/lid does not work.
Mechanism opens with proper tools.
Cover/lid difficult to remove One maintenance person cannot remove cover/lid after applying 80 lbs. of lift. Cover/lid can be removed and reinstalled by one maintenance person.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-12
NO. 6 – CONVEYANCE PIPES AND DITCHES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Pipes Sediment & debris accumulation Accumulated sediment or debris that exceeds 20% of the diameter of the pipe. Water flows freely through pipes.
Vegetation/root growth in pipe Vegetation/roots that reduce free movement of water through pipes. Water flows freely through pipes.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate.
No contaminants present other than a surface oil film.
Damage to protective coating or corrosion Protective coating is damaged; rust or corrosion is weakening the structural integrity of any part of pipe.
Pipe repaired or replaced.
Damaged pipes Any dent that decreases the cross section area of pipe by more than 20% or is determined to have weakened structural integrity of the pipe.
Pipe repaired or replaced.
Ditches Trash and debris Trash and debris exceeds 1 cubic foot per 1,000 square feet of ditch and slopes. Trash and debris cleared from ditches.
Sediment accumulation Accumulated sediment that exceeds 20% of the design depth. Ditch cleaned/flushed of all sediment and debris so that it matches design.
Noxious weeds Any noxious or nuisance vegetation which may constitute a hazard to City personnel or the public.
Noxious and nuisance vegetation removed according to applicable regulations. No danger of noxious vegetation where City personnel or the public might normally be.
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries or paint.
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate. No contaminants present other than a surface oil film.
Excessive vegetation growth Vegetation that reduces free movement of water through ditches. Water flows freely through ditches.
Erosion damage to
slopes
Any erosion observed on a ditch slope. Slopes are not eroding.
Rock lining out of place or missing (If applicable)
One layer or less of rock exists above native soil area 5 square feet or more, any exposed native soil.
Replace rocks to design standards.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-38
NO. 25 – DRYWELL BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Preventive Plugging, obstructions Any cause limiting flow into drywell. Drywell able to receive full flow prior to and during wet season.
Site Trash and debris Trash or debris that could end up in the drywell is evident. No trash or debris that could get into the drywell can be found.
Pipes Plugged inlet The entrance to the pipe is restricted due to sediment, trash, or debris. The entrance to the pipe is not restricted.
Vegetation/root growth in pipes Vegetation/roots that reduce free movement of water through pipes. Water flows freely through pipes.
Plugged pipe Sediment or other material prevents free flow of water through the pipe. Water flows freely through pipes.
Broken pipe or joint leaks Damage to the pipe or pipe joints allowing water to seep out. Pipe does not allow water to exit other than at the outlet.
Structure Basin leaks Holes or breaks in the basin allow water to leave the basin at locations other than per design.
Basin is sealed and allows water to exit only where designed.
Filter Media Plugged filter media Filter media plugged. Flow through filter media is normal.
NO. 26 – GRAVEL FILLED INFILTRATION TRENCH BMP
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN
MAINTENANCE IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Preventive Blocking, obstructions Debris or trash limiting flow to infiltration trench. Infiltration trench able to receive full flow prior to and during wet season.
Site Trash and debris Trash or debris that could end up in the infiltration trench is evident. No trash or debris that could get into the infiltration trench can be found.
Pipes Plugged inlet The entrance to the pipe is restricted due to sediment, trash, or debris. The entrance to the pipe is not restricted.
Vegetation/root growth in pipes Vegetation/roots that reduce free movement of water through pipes. Water flows freely through pipes.
Plugged pipes Sediment or other material prevents free flow of water through the pipe. Water flows freely through pipes.
Broken pipe or joint leaks Damage to the pipe or pipe joints allowing water to seep out. Pipe does not allow water to exit other than at the outlet to the trench.
Structure Flow not reaching trench Flows are not getting into the trench as designed. Water enters and exits trench as designed.
Cleanout/inspection
access does not allow cleaning or inspection of trench
The cleanout/inspection access is not
available.
Cleanout/inspection access is available.
Filter Media Plugged filter media Filter media plugged. Flow through filter media is normal.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
2017 City of Renton Surface Water Design Manual 12/12/2016 A-47
NO. 38 – SOIL AMENDMENT BMP
MAINTENANCE COMPONENT DEFECT OR PROBLEM CONDITIONS WHEN MAINTENANCE IS NEEDED RESULTS EXPECTED WHEN MAINTENANCE IS PERFORMED
Soil Media Unhealthy vegetation Vegetation not fully covering ground surface or vegetation health is poor.
Yellowing: possible Nitrogen (N) deficiency. Poor growth: possible
Phosphorous (P) deficiency. Poor flowering, spotting or curled leaves, or weak roots or stems: possible Potassium
(K) deficiency.
Plants are healthy and appropriate for site conditions
Inadequate soil nutrients and
structure
In the fall, return leaf fall and shredded woody materials from the landscape to the
site when possible
Soil providing plant nutrients and structure
Excessive vegetation growth Grass becomes excessively tall (greater than 10 inches); nuisance weeds and other
vegetation start to take over.
Healthy turf- “grasscycle” (mulch-mow or leave the clippings) to build turf health
Weeds Preventive maintenance Avoid use of pesticides (bug and weed killers), like “weed & feed,” which damage
the soil
Fertilizer needed Where fertilization is needed (mainly turf and annual flower beds), a moderate
fertilization program should be used which relies on compost, natural fertilizers or slow-release synthetic balanced fertilizers
Integrated Pest Management (IPM) protocols for fertilization followed
Bare spots Bare spots on soil No bare spots, area covered with
vegetation or mulch mixed into the underlying soil.
Compaction Poor infiltration due to soil compaction
• To remediate compaction, aerate
soil, till to at least 8-inch depth, or further amend soil with compost and
re-till
• If areas are turf, aerate compacted areas and top dress them with 1/4 to
1/2 inch of compost to renovate them
• If drainage is still slow, consider investigating alternative causes (e.g.,
high wet season groundwater levels, low permeability soils)
• Also consider site use and protection
from compacting activities
No soil compaction
Poor infiltration Soils become waterlogged, do not appear to be infiltrating. Facility infiltrating properly
Erosion/Scouring Erosion Areas of potential erosion are visible Causes of erosion (e.g., concentrate flow entering area, channelization of runoff) identified and damaged area stabilized (regrade, rock, vegetation, erosion control
matting).For deep channels or cuts (over 3 inches in ponding depth), temporary
erosion control measures in place until
permanent repairs can be made
Grass/Vegetation Unhealthy vegetation Less than 75% of planted vegetation is
healthy with a generally good appearance.
Healthy vegetation. Unhealthy plants
removed/replaced. Appropriate vegetation planted in terms of exposure, soil and soil
moisture.
Noxious Weeds Noxious weeds Listed noxious vegetation is present (refer to current County noxious weed list). No noxious weeds present.
APPENDIX A MAINTENANCE REQUIREMENTS FOR STORMWATER FACILITIES AND ON-SITE BMPS
12/12/2016 2017 City of Renton Surface Water Design Manual A-48
NO. 39 – RETAINED TREES
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITIONS WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
Tree Dead or declining Dead, damaged, or declining Tree replaced per planting plan or acceptable substitute
NO. 40 – FILTERRA SYSTEM
MAINTENANCE
COMPONENT
DEFECT OR
PROBLEM
CONDITION WHEN MAINTENANCE
IS NEEDED
RESULTS EXPECTED WHEN
MAINTENANCE IS PERFORMED
In addition to the specific maintenance criteria provided below, all manufacturer’s requirements shall be followed.
Facility – General Requirements Life cycle Once per year, except mulch and trash removal twice per year Facility is re-inspected and any needed maintenance performed
Contaminants and pollution Any evidence of contaminants or pollution such as oil, gasoline, concrete slurries, or paint
Materials removed and disposed of according to applicable regulations. Source control BMPs implemented if appropriate.
No contaminants present other than a surface oil film.
Inlet Excessive sediment or trash accumulation Accumulated sediments or trash impair free flow of water into system Inlet should be free of obstructions allowing free distributed flow of water into system
Mulch Cover Trash and floatable debris accumulation Excessive trash and/or debris accumulation Minimal trash or other debris on mulch cover. Mulch cover raked level.
“Ponding” of water on mulch cover “Ponding” in unit could be indicative of clogging due to excessive fine sediment accumulation or spill of petroleum oils
Stormwater should drain freely and evenly through mulch cover
Proprietary Filter Media/ Vegetation Substrate
“Ponding” of water on mulch cover after mulch cover has been maintained
Excessive fine sediment passes the mulch cover and clogs the filter media/vegetative substrate
Stormwater should drain freely and evenly through mulch cover. Replace substrate and vegetation when needed
Vegetation Plants not growing or in poor condition Soil/mulch too wet, evidence of spill, incorrect plant selection, pest infestation,
and/or vandalism to plants
Plants should be healthy and pest free
Media/mulch too dry Irrigation is required
Plants absent Plants absent Appropriate plants are present
Excessive plant growth Excessive plant growth inhibits facility function or becomes a hazard for pedestrian and vehicular circulation and safety
Pruning and/or thinning vegetation maintains proper plant density. Appropriate plants are present.
Structure Structure has visible cracks Cracks wider than ½ inch
Evidence of soil particles entering the structure through the cracks
Structure is sealed and structurally sound