HomeMy WebLinkAboutES0895.06 SWFR172a.pdf Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
1 of 2
Report No.
172a
Time On Site
10:00 AM
Time Off Site
10:30 AM
Date
5/8/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas
• Silt Fence
G N Silt fence working as intended
2. Establish Construction Access
• Fabric; Quarry Spalls
• Wheel Wash
• Sweeper Truck
G N Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
3. Control Flow Rates
• Stormwater Vault or Facility
• Straw Wattles
• Check Dams
G N Add check dams and straw wattles as needed to
slow stormwater onsite
4. Install Sediment Controls
• Silt Fence
• Straw Bale Barriers
• Vegetation
• Straw
• Sediment Ponds, Traps & Filters
• Treatment
• Sediment Pond (Temp. or Perm.)
• Water Truck
G N Add straw as needed throughout the site, 2”
minimum
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass
• Plastic Sheeting
• Straw Stockpiles
• Stockpiles
• PAM
G N
6. Protect Slopes
• Benching; Track-Walking
• Pipe Slope Drains
• Plastic Sheeting; Anchors
G N
7. Protect Drain Inlets
• Catch Basin Inserts
• Gutter; Road
G
N
CB inserts working as intended
8. Stabilize Channels and Outlets
• Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
N/A N/A N/A
9. Control Pollutants
• Chemical Storage Area Covered
• Concrete Handling
N/A N/A N/A
10. Control Dewatering N/A N/A N/A
11. Maintain BMPs G N See recommended notes
12. Maintain SWPPP & Site Logbook G N Available upon request
13. Protect Low-Impact Development (LID BMPs)
• Bioretention Rain Garden Facilities
• Permeable Pavement
N/A
N/A
N/A
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
2 of 2
Report No.
172a
Time On Site
10:00 AM
Time Off Site
10:30 AM
Date
5/8/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Monitoring, Records & Recommendations
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? Yes No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Ongoing)
Date
(If Completed)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2” straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: _60sO F, Clear____________________
Precipitation since last inspection (approximate): 0.28______ inches
Precipitation in the last 24 hours (approximate): _0.00______ inches
Was water quality sampling part of this inspection? Yes No
If “Yes”:
• Record results in the table below.
• Characterize the stormwater discharge, e.g., the presence of suspended sediment, “cloudiness”, discoloration, or oil sheen, if
present: ____N/A________________________________________________________________________________________
• Hanna Turbidity Meter # ____________________
Monitoring Location Turbidity
(NTU) pH Notes
22 7.0
Is the site in compliance with the SWPPP and the permit requirements? Yes No
If “No”:
• Indicate the tasks necessary to bring the site into compliance in the table above.
• Has the non-compliance been reported to the Department of Ecology? Yes No
• Should the SWPPP be modified? Yes No
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Inspector Name: Jackson Lundgren CESCL Number: CESCL-EF8183892 Inspection Date: 5/8/20