HomeMy WebLinkAboutCM_Construction_Mitigation_Joos_200520_v1Joos Construction Mitigation Description 5-20-20
Proposed Construction Dates
Start: September 2020
Completion: September 2021
Hours/Days Operation
Weekdays: 7:30 am – 5:00 pm
Transportation Routes
Mountain View Ave N to Lake Washington Blvd. to I-405 South and/or North to disposal sites
Mitigation
Water spray for dust during excavation and demolition
Silt fences and/or hay bales for erosion control
Pressure spray truck tires for excessive mud build-up
Temporary construction vehicle parking on site and adjacent to abandoned railroad line
No special traffic control contemplated