HomeMy WebLinkAboutInspector's Daily Reports - 10/27/2016 ri .
RENTON
AHEAD ti r i't i.is CURVE x'03853 708-Inspector's Daily Reports 10/27!2016` ,
IDR Sheet 1 of 3 Sheets
Prosect No. Prosect Name Day Date
CM-1193(003) CITY OF RENTON- 116TH AVENUE SE Thurs October 27,2016
SIDEWALK
Prime Contractor Representative/Title
A. KAMINS CONSTRUCTION,INC. Chad Kamins
Subcontractor or Agent Appr'd D/M/WBE Representative/Title
B. AGS x x Marla Dawson/TCS
C.
D.
E.
A.M. P.M.
Weather: Overcast Site Conditions:
Temperature: Low: 59 ±°F High: ±°F
Contractor's Work Activity
Description and Location
Preparing subgrade for curb and gutter All proj.Placing CB at Sta. 16+04R
Required Backup Samples Taken
Item, Description, and Location of Work Mat'Is Documentation Approved
(NOTE:Any"NO"is to be explained in Diary) Mat'I Source Approved
Pay Note Made
Item No. Contract Item Description Location Y/N Y/N Y/N Y/N
22 Catch Basin Tl Curb Inlet Sta. 16+04R y
Traffic Control
Was Traffic Control Required Today? Yes F_1 No Was WZTC according to approved TCP? Yes —]No
Was TCS on Project Site Today? Fx Yes =No Do all Flaggers have current flagging card? DYes =No
DIARY
7:30am:I have measured the southbound taper and found it to be only 75',1 have painted the C/G at 180'and have directed the contractor
to correct the length.I have spoken with AGS about relocating the Class A sign at the south end of the project to a location across
Petrovitsky and have stated that the project info signs need to be palced at each end of the project not in one location.I have also directed
the contractor to relocate the mailboxes to provide access for delivery,this will be paid as a F/A item under property protection and
restoration. 8:30am:Kamins continues to exc.for C/G at Sta 18+50R+/-and are removing spoils and asphalt at Sta. 16+50R+/-. Soos
Creek was on-site to restore one of their valve cans that had bee displaced by the contractor.9:30am: Shope has delivered the curb inlet
basins and the Type 1 basins are being removed. (5TI-ICI ).Kamins is relocating the mail boxes(IM).Kamins continues to exc.at Sta.
17+75R+/-and relocate mail boxes. 11:00am:Kamins is installing CB#2 at Sta. 16+04R
Photos taken Today?[7x Yes =No
(Signed) NAME: Construction Inspector
Reviewed By
Inspector's Daily Report
rap �sboraze, L-.--.
CONSuLnNG ENGINEERS (CONTRACTOR'S EQUIPMENT&WORKFORCE)
IDR Sheet 2 of 3 Sheets
Project No. Project Name Day Date
CM-1193(003) CITY OF RENTON- 116TH AVENUE SE Thurs October 27,2016
SIDEWALK
Prime Contractor Subcontractor
KAMINS CONSTRUCTION,INC.
CONTRACTOR' S EQUIPMENT
Operating Contractor's ID(A-E,see page 1)
No. of Equi
Units p Equipment Description Oper Stdby Down Idle REMARKS
No.
A 2 E-01 Cat 307E Exc. 10
A 1 E-02 Cat 303.5 Exc. 5
A 1 E-03 Cat 924 Loader 7
A 1 E-04 Lay Mor Sweeper 1 7
A 1 E-05 F450 U/T 8
A 1 E-06 F650 D/T 8
A 1 E-07
E-08
E-09
E-10
E-11
E-12
E-13
E-14
E-15
E-16
E-17
E-18
E-19
E-20
E-21
CONTRACTOR'S WORKFORCE
Operating Contractor's ID(A-E,see page 1)
NUMBER/HOURS NUMBER
Laborers Pipe Layr Oper Drivers Fiaggers Electrician Other Male Female Apprentice Trainee
A 2/16 / 2/ 16 / / / FOREMAN 5
B / / / / 4/ 32 / / / 4
of
(Signed) NAME: Construction Inspector
m--
Inspector's Daily Report
�3ray �®s�oa-rim, Inc:.
CONSULTING ENGINEERS (DIARY-continued)
IDR Sheet 3 of 3 Sheets
Project No. Project Name Day Date
CM-1193(003) CITY OF RENTON- 116TH AVENUE SE Thurs October 27,2016
SIDEWALK
Prime Contractor
KAMINS CONSTRUCTION,INC.
DIARY -continued
Exc.continues at Sta. 18+75R+/-. 12:30pm:Work continues. 1:30pm:Crews are placing mortar around pipe and preparing to backfill.
Asphalt removal continues at Sta. 15+OOR+/-.I have directed the contractor to widen the driveway at 17322 to provide greater access to
rhe residents.2:30pm:Kamins has finished installing the CB and are completing the compaction around the structure and pipe.3:OOpm:
AGS is removing T/C and opening all lanes.3:30pm:Work has finished for the day.
(Signed) NAME: Construction Inspector