HomeMy WebLinkAboutCM_Construction Mitigation_200824
CONSTRUCTION MITIGATION DESCRIPTION
August 20, 2020
Planning Division
City of Renton
1055 South Grady Way
Renton, WA 98057
Project Name:
701 Monster Road SW Building - Interior Improvement
Proposed Construction Dates:
Tenant Improvements, starting in September 2020, completion by November 2020 unless
SEPA approval pushes the dates out.
Hours and Days of Operation:
Construction hours would traditionally be weekdays from 6am to 6pm. It may be possible
some work may be performed on weekends (Saturdays) to expedite the schedule.
Measures to be Implemented to Minimize Dust, Traffic impacts, Erosion, Mud, Noise:
TESC measures and watering of the site will be implemented to maintain a clean working
site, as required during Civil Work. Any work requiring impacts to traffic will utilize
flaggers and approved traffic control means. The proposed measures to reduce or control
the noise impacts will be to limit the hours of operation during the construction phase of
the project. The site is located in an Industrial area and in no proximity to a residential
neighborhood. Existing adjacent freeway traffic and facility operations create
significantly more noise than this site will produce.
Any Special Hours proposed for Construction or hauling:
It may be possible some work may be performed on weekends to take advantage of
favorable weather conditions.
Preliminary Traffic Plan:
For Civil work, this effort will be defined by the general contractor (TSL) and
coordinated with the City of Renton. No anticipated impact to traffic is expected due to
the limited size of this scope and that it will happen on the property on the far South side
out of any Traffic areas.