HomeMy WebLinkAboutC_Short Plat Compliance Letter 092220.pdf
September 22, 2020
MICHAEL S. SIPPO, Civil Engineer III
Community & Economic Development Department | Planning Division
City of Renton
1055 S. Grady Way
Renton WA 98057
RE: Family First Community Center Site Plan, Conditional Use Permit, Height Variance, Street Waiver,
Driveway Design Modification (LUA19‐000212) and Preliminary Short Plat (LUA20‐000024) Conditions of
Approval Compliance Document
Michael,
The City of Renton, as the developer for the Family First Community Center, is in compliance with all of the
following conditions. Please note a Deferral of Construction Improvements was issued by the City of Renton
Department of Economic Development on September 17, 2020.
SEPA Determination: Determination of Non‐Significance – Mitigated dated October 14, 2019:
1. The project construction shall comply with the recommendations found in the submitted Geotechnical
Engineering Report, prepared by The Riley Group, Inc. (RGI), dated June 8, 2018, and future addenda.
The Geotechnical Recommendations have been incorporated into the approved permit plans
Findings of Fact, Conclusions of Law and Final Decision LUA19‐000212 dated December 6, 2019:
1. The Applicant shall comply with the mitigation measures issued as part of the Determination of Non‐
Significance Mitigated, dated October 14, 2019.
The Geotechnical Recommendations have been incorporated into the approved permit plans
2. The Applicant shall maintain a minimum concrete sidewalk width of six feet (6') throughout the
development. A final landscape plan shall be submitted and approved by the Current Planning Project
Manager prior to issuance of the construction permits.
Minimum concrete sidewalk width of six feet (6’) has been incorporated into the approved
permit plans.
3. The Applicant shall provide a secured extended use bicycle parking area for a minimum of nine (9) off‐
street bicycle parking stalls to be reviewed and approved by the Current Planning Project Manager prior
to building permit issuance.
A secured extended use bicycle parking area with a minimum of nine (9) off‐street bicycle
parking stalls has been incorporated into the approved permit plans
Recipient
Page 2 of 2
September 22, 2020
4. A lighting plan with fixture details shall be provided at the time of building permit review for review and
approval by the Current Planning Project Manager prior to building permit issuance.
An approved lighting plan with fixture details has been incorporated into the approved permit
plans
5. The Applicant shall install a minimum of two (2) seating benches to enhance the usability of the open
spaces. A final detailed landscape plan shall be submitted to and approved by the Current Planning
Project Manager prior to issuance of the construction permits.
The minimum of two (2) seating benches has been incorporated into the approved permit plans
6. The Applicant shall dedicate five and one‐half feet (5 ½') of right‐of‐way along 116th Ave SE so that
when the City does secure the funding for the frontage improvements, the right‐of‐way is available to
install improvements. Right‐of‐way dedication would be completed with short plat recording.
The ROW dedication will be recorded concurrently with the short plat recording
7. The Applicant shall bring the existing ramps along the project frontage up to current ADA standards. The
ADA ramp improvements shall be included in the construction permit application for the proposed
project and shall be completed prior to building final occupancy.
Upgrade of the existing ramps to current ADA standards has been incorporated into the
approved permit plans and the ADA ramps will be completed prior to building final occupancy.
Administrative Approval of Family First Community Center Preliminary Plat LUA20‐000024 dated March 6,
2020:
1. The applicant shall comply with the conditions of the land‐use permit (LUA19‐000212), dated December
6, 2019.
The responses above indicate that compliance is being met.
Please let me know if additional information is required.
Thank you,
Russ Woodruff, Capital Project Coordinator
Department of Community Services, Facilities