HomeMy WebLinkAboutCM_Jones Short Plat Construction_Mitigation_Sequencing_2020_08_28_v1.pdfJones Short Plat
3102 Park Ave N
Renton, WA 98056
Construction Mitigation Sequencing
Proposed Construction Dates
Grading and road construction will start upon approval of construction plans spring of 2021.
Hours of Operation for Single Family Construction Site
Per City of Renton:
Monday – Friday: 7am – 8pm
Saturday: 9am – 8pm
Sunday: None
Proposed Hauling/Transportation Routes
All equipment materials and laborers will enter the site off Park Avenue North. A detailed haul route
will be provided by the contractor selected to construct the improvements. It is anticipated that the
haul route would be via I 405. From here vehicles will head south or north to an approved location.
Measures to be implemented to minimize dust, traffic and transportation impacts, mud, noise, and
other noxious characteristics
Dust: Best management practices will be used to minimize dust on the construction site. Water trucks or
metered fire hoses will be used as needed to wet down the areas used by construction equipment.
Disturbed slopes will be hydroseeded per the Erosion/Sedimentation Control Plan to control dust.
Traffic: During road and building construction, the traffic entering and leaving the site will consist of
subcontractors and deliveries. When arriving for work, the subcontractors will be travelling opposite the
majority of traffic entering the residential areas as most commuters are leaving, and materials are
primarily delivered at off peak hours during the day. None of these operations are anticipated to have
a significant impact on the peak or non-peak hour traffic in the area. The anticipated hauling and
transportation route avoid going through neighborhoods and gets almost directly onto an interstate.
Any special hours proposed for construction or hauling
There are no special hours proposed for construction or hauling without prior approval from the City of
Renton.
Preliminary Traffic Control Plan
General access to the property will be from Park Avenue North. It is anticipated that the existing
roadway will remain open during construction and access to the properties along Park Avenue North
will be maintained. Traffic Control is anticipated to consist of occasional single lane closures along
Park Avenue North. A standard one-lane, two-way traffic control with flaggers may be used similar to
WSDOT Plan TC1.
Short Plat Application Page 1 of 1