City Response - Willowcrest Storm & sewer line conflict at Edmonds Ave
Max, We’ve reviewed the drawings and they are Approved with Comments. Attached are the plans and the only comment is on page 3 where the storm pipe needs to be DI given that there is only ~1.7 ft of cover where it is exposed. I won’t be charging a minor revision fee for this. Regards, Nathan Janders | Civil Engineer II Community & Economic Development Department | Planning Division City of Renton | 1055 S. Grady Way | Renton WA 98057 NJanders@Rentonwa.gov<mailto:NJanders@Rentonwa.gov> COVID-19 UPDATE City Hall is currently closed to the public but we are still available to assist you. * Pay Invoice and Apply for Over-the-Counter Permit: Permitting Portal<https://permitting.rentonwa.gov/#/home> * Schedule an Inspection: Permitting Portal<https://permitting.rentonwa.gov/#/home> -OR- Building: 425-430-7202; Civil/Site: 425-430-7203 * Contact Staff: * Staff Hours: Monday through Friday 8 a.m. to 4 p.m. * Building or General Permitting: permittech@rentonwa.gov<mailto:permittech@rentonwa.gov?subject=Inquiry%20from%20Website> or 425-430-7200 * Planning: planningcustomerservice@rentonwa.gov<mailto:planningcustomerservice@rentonwa.gov?subject=Inquiry%20from%20City%20Website> or 425-430-7294 * Public Works Permitting: pwpermitting@rentonwa.gov<mailto:pwpermitting@rentonwa.gov?subject=Inquiry%20from%20City%20Website> or 206-402-8626 * Code Compliance: Renton Responds<https://rentonwa.gov/cms/one.aspx?portalId=7922741&pageId=15833143> or 425-430-7373 From: Max Berde <Max@coterraengineering.com> Sent: Wednesday, October 07, 2020 11:19 AM To: Nathan Janders <NJanders@Rentonwa.gov> Cc: Kira Connery <kira@thirdplacedesigncoop.com>; Suzanne Davis <suzanne@thirdplacedesigncoop.com>; Peter Apostol <peter@coterraengineering.com>; Eric Pravitz <eric@homesteadclt.org> Subject: RE: Willowcrest Storm & sewer line conflict at Edmonds Ave CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe. Hi Nathan, From the email chain below I believe you have been briefed on the fiber duct bank conflict with the proposed sewer and storm lines into Edmonds Ave on the Willowcrest project. Coterra has worked to revise the design for both the 8” public sanitary sewer and 8” private storm drainage lines to avoid conflicting with the 30”x30” concrete-encased duct bank. Adjusting the inverts in the two downstream structures for both sanitary sewer (SSMH #1 and SSMH #2) and storm drain (CB #2 and CB #3) and running both lines at 2.0% between these structures, we are able to clear the sewer under the duct bank and the storm drain over the duct bank, both including the 14” DI casing pipes, per the original approved design. Attached for your review and approval are the updated Composite Utility Plan, Storm Drainage Plan, and a new sheet C4.4 – Utility Profiles at Duct Bank – showing the proposed design revisions. I have called out the clearances proposed between the utilities on the profiles, as well as the proposed cover. Please get in touch directly with any questions/comments on these revisions as the general contractor is eager to keep their utility connection work moving forward. Please also let our team know if any additional fees are required to for review and approval of this design change due to the unforeseen duct bank discovered in the field. Thank you Nate! Max Berde, P.E. max@coterraengineering.com<mailto:max@coterraengineering.com> coterra ENGINEERING PLLC 321 3rd Avenue South, Suite 406 Seattle, Washington 98104 206.596.7115 coterraengineering.com By using any embedded electronic file(s) contained herewith, the recipient assumes all risks associated with their use and, to the fullest extent permitted by law, to hold harmless and indemnify Coterra Engineering PLLC and Coterra Engineering PLLC’s professional associates and consultants from and against all claims, liabilities, losses, and expenses including attorney fees, arising out of or resulting therefrom. From: Kira Connery <kira@thirdplacedesigncoop.com<mailto:kira@thirdplacedesigncoop.com>> Sent: Friday, September 18, 2020 11:53 AM To: Evan Chan <EvanC@edgedevelopers.net<mailto:EvanC@edgedevelopers.net>>; Max Berde <Max@coterraengineering.com<mailto:Max@coterraengineering.com>>; Peter Apostol <peter@coterraengineering.com<mailt o:peter@coterraengineering.com>> Cc: Suzanne Davis <suzanne@thirdplacedesigncoop.com<mailto:suzanne@thirdplacedesigncoop.com>>; Eric Pravitz <eric@homesteadclt.org<mailto:eric@homesteadclt.org>>; Roger Farrens <rogerf@marpac.net<mai lto:rogerf@marpac.net>>; Conner Chan <connerc@edgedevelopers.net<mailto:connerc@edgedevelopers.net>> Subject: Re: FW: Willowcrest Storm & sewer line conflict at Edmonds Ave Hi Max and Peter, An issue has come up with the storm and sewer line installation in Edmonds Ave (please see email from Evan below). Are you able to make a site visit to troubleshoot? Thanks, Kira On Fri, Sep 18, 2020 at 11:31 AM Evan Chan <EvanC@edgedevelopers.net<mailto:EvanC@edgedevelopers.net>> wrote: Suzanne/Kira, Can you see if Coterra can come out to the site and come up with a solution for the Storm and Sewer lines that connect from our site to the new manholes we set in Edmonds Ave. There is an unmarked concrete encased Fiber Duct bank that is in the way. City of Renton wants Coterra to come up with a fix asap and to submit it to them for approval. The COR will work with us to get a quick approval if we can get it to them quickly. Please let us know what we can do to assist. Thanks, Evan Chan Edge Community Builders, LLC P: (206) 900-8635 evanc@edgedevelopers.net<mailto:evanc@edgedevelopers.net> ________________________________ NOTICE: This communication including any attachments may contain privileged or confidential information. If you are not the intended recipient, or believe that you received this communication in error, please advise the sender immediately and delete or destroy the communication you received without copying or disclosing the contents. From: Roger Farrens <rogerf@marpac.net<mailto:rogerf@marpac.net>> Sent: Friday, September 18, 2020 10:59 AM To: Evan Chan <EvanC@edgedevelopers.net<mailto:EvanC@edgedevelopers.net>> Subject: Storm & sewer line conflict a city sidewalk Evan, See email below from Joel. Brad Stocco with COR was also on site. There is “federal” fiber duct bank encased in concrete (30”x30”) where the top of this concrete encasement is 46” down from top of sidewalk there. They want the civil engineer of record to find solution and submit to Nate with the COR. IF Coterra can get out here this afternoon then revised design can be reviewed and approved by COR on Monday so as to not delay the work any further. Roger Farrens Marpac Construction LLC | Superintendent | 1225 South Weller Street | suite 500 | Seattle, WA 98144 | Office 206.329.4992 | Direct | Mobile 206-794-3797 | rogerf@marpac.net<mailto:rogerf@marpac.net> [cid:image001.jpg@01D69D61.14EF8B80] Disclaimer “Due to recent increase in email phishing attacks. All emails originating from Marpac will have this message.” Marpac Construction Administrator. 2020 © From: Joel Mccann <JMccann@Rentonwa.gov<mailto:JMccann@Rentonwa.gov>> Sent: Friday, September 18, 2020 10:45 AM To: Nathan Janders <NJanders@Rentonwa.gov<mailto:NJanders@Rentonwa.gov>> Cc: Roger Farrens <rogerf@marpac.net<mailto:rogerf@marpac.net>> Subject: Willowcrest Townhomes Morning Nate, Contractor has installed CB#2 down in Edmonds and we have run into a problem with the fiber duct bank being directly in the way of storm line heading up the hill to the East, they could possibly go over the top of duct bank but maintaining clearance from bank and with pipe casing there will be min coverage over top of pipe. Contractor just potholed their sewer coming SSMH#1 to the East and line is running directly into the bottom of duct bank also. I let contractor know that they will need to get ahold of their engineer so he can come take a look and have something sent over to you Nate. [Renton SEAL_Color] Joel McCann Construction Inspector | CED JMcCann@Rentonwa.gov|<mailto:JMcCann@Rentonwa.gov%7C> Cell: (425) 757-9595 P Please consider the environment before printing this email Inspection Hours 7:00 a.m. to 3:30 p.m. [811 CBYD Logo] -- Kira Connery | Assoc. AIA | LEED Green Associate Associate third place design co-operative 304 Alaskan Way S., Suite 301 | Seattle, WA 98104 [o] 206-331-3795x07 | [c] 206-660-6447 | [w] thirdplacedesigncoop.com<http://thirdplacedesigncoop.com/> 率拾說旵騏粯㕏穩Ḵ롈췓埜伲穭峒坭⓷완�൪稅�ꂧꞖ聑ঘ♂坜롕換翏幻劏㣈䒪ꬊ 篾磾䄐짳戇頏㾵⣻쿌鷤﨟㾎뇴䷽鴿ﻏ⾩ﶙﭬ㏲⟳鿋㪗鲧ÿﰷ챟ử⟌쟥깈엮꧞ﹺ�햅胂涼퍨넫虯΄綘ꊫ꧉㒌᳐褸釵ꉂ䐹㌏䇥䖻躨Ⱃ㞲粃叏횦㞕湺殯ÿᾑ皔튕嫟睨珋쨝ⲳ劣᳤뗊垮쀮褒쾁쒘꺊唡辳顩裋蕣퇷槽�迤縬鱿䯾辴퍖〿睴鬿鞿㤦틭豒곃䝙鄴좪랒晵輜䫅⭓暇쭦㪣Ꙭ▌맻泬硇䟤㥳ㅫ㣃蟄㺪ÿ纨㮖掠聾鼙ﱏ㛤ꆓ卨ꪷὴ椸뛷떚ㆂ턧浣퀜뫜ﬨけ䞗疴잘崎㈹臯✆竏瓖➸㊼㮀ඤ횏뿳뷌쭷绚ꊇ巾ꟹ飯銡籩ⴉ 䞿ᒬ浇来ᬲ傂䲂삎쨞桦檲쫲쵒ࠑÿ漌床䛲ꏁ0♣ꥇ㻤騃䴻ÿ狖鿳泾ⲏÿ⏝졞ﳏ맰ÿ芺﹣⼭쟫鋮ォ㤀w관螺ᄉ洀㿙�絥ﺁ謡곺侻曼맏炷詝ᖻ衜㫲᫇瞗儡吔皒Ā鳔ꕉ㍽ﰷ韢滦聯ꕽᛍ六佞欴智Ⱏ۟趫剎▉᫂好Ѐ翼傠ᢝ墜៏䰌䞤⌠���첞牢죚甀シⴿ�홐來䦟킹�匦ꄆ嶦躡�⩮倏苀⪬ဘ⁁鮃㥼髡砂㇈蠼牰陣ᠹ凈☉셚ꯘ垱깢巅뮊瘕㟝ÿ쭙翎당댼ÿ赴㕻モἀﲇ缮ꃮ䟦嫼흟�휤狾ᆵ娀﹫닛쥿쪴ϻ䏼癙鿯湳믠稕ÿߦ ủ몼鄇⤴㥵⩣ᵵ䩊旅᭥稚㞗ᔄ푁뮁༵挕悶ﯫه敹썝윏鎛튦푤虋︂~鰀C鰀ﱻ톿讼ﺢ琺恾웳禥잩ꥥ꿝ඩ概藺諅鐵ꍎ㢃龃䞨訿ꢀ캨��㳏폒쎃귃ⶁ糾㶹挷燨ᣇ䗊�观㴛ﹳ�凾쩿ﱯﻚt錀�R숀⬇㺵羈⥞ﲯ忤鐯㼿佴煒蔞뷧ᘲ⽟뛹율ꨭ�ǰ壊ᨋꮓ圫�鞹Ꭓ㣏釾络뻾흒瓶儵郮翤ൾ找屾뿹돲㟍僾껳⚓ꮓ鋘땒�壂岪쥛⑀Ⲟ䘾ႄ挽굇ꯅ㋆㙢�篤얋퍧ӏ⛌뀨쩼癩�놫扗얮�ᆭ礹ᅬ㘀陇꾑뉦蔀﷏᳔謀碑ﯱ骤ÿ嗎ÿ䓫浾�佶㛹徙 罠抈팮ÿ鼙Ӱ㮩㌀ꪾ習ዧタÿ寥绝祥ᮽ圷攺閇뼼ॳ佽륒濕늠预ℋㆆﻸଶ傲춆伆灨恾읠㓪轌쓰ቄ깶㟯ṧ짋磡�ຕ춦ὼ骹锧ꏼ䧹毤⾍韛꼥⸏쿘陴←谡霱♩�妍隘㤾駥曖짢⤣腈鷽族瀌軁⢠烈⯅뀧ÿ皜꣼了䗑昈嬿䮚풊㹶䞥嶷㟳꿅翊徥䴡頝䴫猏6鰀ᄋ鐀ロ㘀閿맼덿�・蔀崍暑緱驛昇쿼ÿ隟ꧨ鈷ⴿ쑼弢体⻗龞⼕봭땠侧拴彩쮉뉙빃ﰠ纍麗蛶묟버追羍៧甕累ᯈﶻ卫迕벗ꆃ굜ꦮݿ봗뢺삨톪ᘘ솑ꈂﮊ眻샙⍆↋ܖ 㭀鷻晏懶鋕ꡉ龏贈憑ÿꔸÿ넸诤欛伝韛鉄䗏{ 쥟씥諃೮⫓ꠚ컶紒�艚晌텽༛ﮐ軞餽쒤쐨䭼㿍W缁簫ꏛ彞埾糀趵펥䧡鿥뭊㕾嚎ꊑ뀍ᄏ稁泰毯㡵٦屿Ṓ○輀쟍盕Ⱖ벑饾齽玏꿲돲郈ﻞ梁쿣㱺貞殾킷헼쪡䋲ÿ켍熣㰋踮ꂦꮊ뵳瓌쵓ネĀ侔쇂�兯猜씟㽄㽩䣨7�嫫ÿﲲ㿳凴㿚뿪揬ÿ죟俺緦ﺻ螄燾ソⴀﶏ뗎ﮯ윯ᓽ轶꿺ÿ꿄㻲煉榟濽뿎컹쥿쭿쥏埍쯣㗈䷫嵊㹙禹벵嬳쐫紻嚚榯㗪좱䭳袊肭緧㫀�拒飓扸类�吏䷣ÿ 狖鿳泾ⲏÿ⏝쵞ᅩ윀£ﮟ㢨1ᘀ㕉ÿꮜÿ裖�ÿ㉭삾ÿ씐国ꝝ㏾笿@鰀ﲷ㟤�폗맼븴푠뱪ං㌺묥툑妟റ狼榟㸵茆ᰡﭳ댭炲髸︍뙟낟鼿摒챛ÿ迳䥞趎묮诹걩ᗏ�鞯渭ᤵᅇ珔쥈㳗닧ه䘽籤䑦孿毕厽�僺큋㮿⾵錀驟飺ཾ樍ൈ﵈뇨䚘묪떊猅눏쟡얫爛嗀烉駠觾電䙾跘슒᪈짛᪺觗霐婡�螓枵ꯅ翌⾧꺼㲎‸ꈿメ츀{쨀勞m鬀쩟屾篘ﴽ忦哸톧桮鬝錶䯺燾篮ϊϺ嫌鬦W需遽쏉꾮䓧뢏蟾�붱﨑䮿 ⏲翲믳뿏晴ꏞ玲倛ណ곕늤瓔듫娳᥌ꍏ씫㦐跦痛䘵㹥�霽徃ᰁ醣䞰㼿듥첚榚䀙ῳ鎏ﳏは썹빙㖚붛孻擔帲坪뒲릲ᓝ啴l餙ڇြ옐蠀搲䦖䡱Ꞿ緦產뤧瓓㇟奞凹᧮隙暷㊎鶤த녃믤㌀緌蚰ᱽ䇌뺗�蔝鴩ꬿ⚐�靾ﻇﵽ?䔀뀕큓ÿ礚핯ﻴ훏Ꜿꞏ�톹㣩邿ᝏ⟳돲损쾪쩟뽂ᾝ㺸鰀图勵跇啁㍋�啐ꐂ⎓Ő쾜㾲ꗺ盛뽝�몎뿭廓娯ᨷ빼잳鋙远腙訛뙱鷭鼐쬁黾⹏ᨴẃ̮��佚괵ዜ�㭛煇㉭銔匷噆Vຂ᳄ ଉ鰜ࡂ뷘䶟ÿ狖鿳泾ⲏÿ⏝쵞ャ윀£ﮟ㦨アᘀ㕉ÿꮜÿ裖�ÿ㉭삾ÿ씐国ꝝ㏾笿俭鎏魉㏳桸ⴑ봼�꽓渢ᛯ�콭鳓뛇鷺憱爞瀿ÿ鸽鍾Ὼ翲羈ⷧÿ琯䪎绑繝戾圠鿠뭙䶇䡐ꛚ頸简�㭧碄靽徒짏8ꔀ弆�ퟏ袬泾雷䞚ÿ巎罪羢ᯧÿ긵颹巽⬮䄾ハ봀炷퉚잣ꗕ篈퀾㳄ﴉ灉ꛩ빼俳臅볒ⷭ⮃멩ꕥ⮫Ⲏ「傢잎핬齧䤞뱋뢹쏣㬐勵쯋�佮뼫뿍씪܍߭䶞ÿꇘ�ꊳ曲쏲퀿믫푔ア帀괯鼳轶뾛ꌴᆲ츀縷奫⺅퍡븡꾠ୋ⻈�퇃溮鶽쇉ᣚ鶏 셼ꔟ碬뎴弞띱럳욞濰セ鰀ﱺ鳯䑗빩퉛俸쿦㈳蹲�膚긣㓏⊔老鱔毇峬�皮䎃吭注㌇곽주�羐ᓧ⚿蚭榟딍螦㑨⏏惹벽斡ꌇ堐⚙ﶓΘ㫦☭흾鯕錻靲ﱰͬ挳ꛛ矀잟龏蟣�纙핼掙ÿ嬗뻫홪㝚躐䉷襫㡽颕劁꩸뚝㴃嵇붤ὢ揀糚ꣵ䦎纲�ÿ쿌쯹樂翇礯䵗ࣳ瓗ÿ鯌碓孞賒㜷�ꑂ쒥亱�좳圃۬팠츾づ㣡滅腍�謏医ࡍ堉炗<挀ﰟホ鰀鰗簭禍ꯥ◟뫫邰⽨煱�풵ꞑळንᰣ䎅ԕ驸靓ꨢ敏梳Ჱ䊢ᱱꋶ屮쏬�쐠 侞;鼀纉῝鏳녆쾊덜设쉛ց뗝럂鶖⥞䜔꧋W⊚쯦�鿒璈㟒⸒䐾έ缞㜏뜓醴᧡�뿨㐾⽧Y﷏㗒︧༿峸ÿ䇝䟑嫼흟�휤狾ᆵ娀﹫닛쥿쪴ϻ䏼癙�勵뿂ἦF츀碌䴤ꌏ㾑꾘ꝶ縡뛵꙯⋙㣏鯶ꍜ陋ﭳ⏻蜏辦゙㼀䫙閟簮ᅢ㤀?㤀䱲骖礂쩳䭚ꟗ뤤劽舴㖘싣槐Თ쓏ꘓ쭲蚻政ޔ黌充ꄉ氞⻳ꒃ찘龞眾쿑滇�ÿ�昿欅X鬀Ἑ뾲ṋ�༇緭鱯듳睼ÿ鐹髊뭓唅쇲♦ƀ㥉萀긺𥳐ア쌀﨣扟㡧廭掠꒿箍鿲㟳⡅喞ⷖѣ 䜃쪖䉕ࠪ抨㴈暎癶ཏ評퍝ﮉ轃辪ᤖ릟Ὸÿ露ÿ露뿦︵튊榹奾�驗交婑필熤膊툤砀紥ᓍ鸓�넝뎋熱祋ꘟ]대벼蝎㵃ݬ퇒딼쟹쩿㓩⟯培푕뾴䀯ﵦꈓ䯙檩ꗺ胛䚦瑋떲戁⠂䣾叔쯧嫚Ⲟ곋ಏ㹢耼鿹읰☍萪͉妸ꟸ㿣緧ﲗ溝�俦쿉娽䓚뼍벗ᚿꪁ븵榟衚뛒鏣妷耞皻ᔊ퉗⺻鵝㡆읦佽气龟瓈할Ꝫⳅ瘔Ώ줸俤섺详祝坋솰ꭻ괩�聋䌌뢢ࣦꌢﶦ爳砵㍎䲔༘Ӣ뜑肛챰聏噷痯훼ÿ䒜꣼듓庍ÿ罂쵱�桨请岧결ᠫ㠬돛ꭦﶳ 튢⑫╢䇂诛Ⅾ㿞㝗匷姙ð녈뷥퍻紐ῄ㴀덹꯳嫉뛽箁⛏灪뷮ͳ淅�冟ม۠嚒䈁亭裥ꓢ廥监䤺죀䠙ᝐﶾ셽斟物콤儙鮨逸O㼀鼖ﺤ嵀흨꠲땖�끩�굏ﳈ╷慕㶡愁⯢蘡흓ฉ襑�邹佇䥝괟ㇹᆭ礹ᅬ㘀陇꾑ꁧﳏ맰ÿ莺䟌嫼흟�ÿ魏㉿ÿ밳⾻椿攚馟ᛵ蚽篆蝛▖啥엢ш�ᚳ侗䜌☙긢뷃盕鑥胄ﶲ턩魴̽퉆㴹㼭뉅슂㿆蛥㗚ㆊ⫴☹鉤⽾ࡃ䒈牄鰏됕抝ⴏ敾ꍹᫌꮏﭹ៳㫌雬ጼυ郌虂ᔹ呝輈䌞꾡晊럫䂲쟤Ҏ赱岎ﶬ뿮掳 ᤡ䋊ꚌὋÿ몜庐羅꿇簊療飅Ḑ䒰坥枬⣭ꤲⴿ컞ᾎ俌룹逸匿퐎싟纏빈컁�⚾ÿÿᮔ诲ÿ똶チ倀輪ﯓﴫ濶哸纺ﻙ΅ῗ統鲳룃鹒금骠痚ק淄줔⩒⢮ꋂ咄�⁁䇘烙﹫孱燾壯ÿ箜㳐ꏙṫ덢ᓳ憞懔芼㡻袤녆捄싢睂瘽㯄灊抔쉣眫�ᦚ⍩䴠緙驕昇嗬埰쟦魗㹿좿餿缺떓煋�陈槞褦淭�ﱀݾᑉ눲䚑⩖ӕ姧ꞿꋃ껼晬筃痜䴺晗쥥ァ�㹵턘垬蟍罎畡됙喟ﭱ⑱瓵휍暉砳杼뻃霞ᡷ룸ᕇ靟昪ﳼÿ亜ﻼ峳樂퉈ퟲ涖尨厳雔 ⍎竔퀊Ȁ膪둏业엎ು⑲㛳ﴷꂃ㩴쳮ᒟ¦蘜・彻샹㠏﹛䆾頿㬚橞槞痒洁窤陵檣ᗱ禭봱དྷ⥊만嵻魣闃䨈挵賸ﭏ釖珘谘蘸߲ࣤ鳔��놫ॖ迋狼哧曲椋뿦骬雗蛥衧瑇ꆔ卵퓅泐㋃�髜칸㬰灌玟嵎㈼馘襳캰ᇳﱗ៦㲔☟孾拏䅗옅曆ꊍ뫪떥䶌逴䇙㥋ꭅ嘕䆑ྜྷ骳碌搳ยĹ甶ꭽ禊ม甑縰븛캵�ᔻὼ觹菹�❏秙嗇ﳑꞯ⊩늰㳕ꚷ齂楟늾ꛒִ죅ᡡ淸憉鷉轞聇ۨC硤⋷㽬툅쿧Ȧང塏美�ჼ伺ퟦ૦ÿ䏎鞿줼臹鸤흒禫쩿翚鮗푂 エ䘀┈醷㩼鶕⻌ꖁ쎑㞫Â졃❏蟼ㄜ쨈屆酅ዼ웦갚馟铡⚽⏡翜Ẉ秶䟹令䶯쏼㹟現髪閷ÿ甬츚氭癩鎖鉾芳鉔棦ꂭ䄢섬⬐䊁扎葶䬱ἆࠋ젒Ᏹ⟩뎐ඵ颲鏉␢ᬽ狾奟웼粚療걫桘ꘚ殅ꄶ檫釗枙욎᧖甥貲욣睦䩔㣈險둯〗Ꮋ鼞ꨮ츰脌4⟯媯痷ᎆ搬㜂秸빹ﱟﳥﳧ☬巇㪸佘㜩벓悯㒚�檚酎兪觪︳妑鍥솒磵쫎恛蘙돷㍻ꡉ縑⦾⬞ྏ쏓詞⻢垻쾫⚋濇്뺷ﱷ鰟鮟忾ÿ辜㶭鷦嶺�훋倾᪶�헝䦲蟵䨱⡵拯⸎騟ৱﱊꨬ轣璳㒹 䘔⌳씣웅⸏ᱜ픕ꅹᆩ挧괪螫헽䟵凾槾ÿ꿲粞翛妭꽹齝㔬ɍ任ᶊ㖒뚹趱₯ᐩ噴嶒��鈟ㇱ̀쀘釈⼱牕ﮝ⺇튩狪捾犆찦貪�垱깢巅뮊瘕�쮫쮼ÿ圪䧼ﳃ︓ﴯ헇ÿ﹌ﶍ휥᳷녾抿䚟ﮇ㺾懶灱�擣㣰粽帼湵ᄇ销K⬀矴⟸图ិᅰ䘀ÿ碈㣵ꕿ鵒�縙쁳윗翡솝ÿꌒ繱ힴt销㑟駾ÿﴋ齶濣ﶮ퉋�븨盛푃緸幎ꞟ㱞敻ク뫢㔼라ι眮汞꽔쾇슗䛙覆ꕆ⓾迺즫忺韴ꬿ뾞ﮭᒾ쯫ᱯឣ뻠㚕蟏畕 䲾嗾䓟⏽ÿ辕旵ÿ紎ꮿꟺᒎ㢭饭ﰱ菗Ḯ฿练㹽❭엥�嗾ﰟᮬꪟ葿頻轾㿔Ễ·卟摒๗ㆵƼ繼윗ツ�䵼碸굟쭇ÿꟲ옿埸᯼ÿጫ ̄ጀ觾´毺糭屿㿴㻒志빓�썿썷뷰䮾솏㳣㰼橝芙㿤�