HomeMy WebLinkAboutExhibit_17_On_Hold_Letter April 22, 2020 Mark Clement The Boeing Company P.O. Box 3707 MC 96-01 Seattle, WA 98124 SUBJECT: "On Hold" Notice #2 Boeing Apron E, LUA19-000145 Dear Mr. Clement: The Planning Division of the City of Renton accepted the above master application for review on July 16, 2019. During our review, staff has determined that additional information is necessary in order to proceed further. The City of Renton’s Community Economic Development Department has reviewed the project and would like an independent qualified parking and transportation professional to conduct an Independent Secondary Review of the submitted Boeing Renton Apron E Traffic Impact Analysis prepared by Transpo Group (dated June 10, 2019) for the effectiveness of any proposed mitigating measures or programs. The contract would be executed with a qualified professional from the City of Renton’s small works roster in order to provide a professional opinion regarding the proposed transportation and parking changes. No additional data would collected by the third party beyond what has been provided in the submittedstudy. Upon the conclusion of third party study review, the findings would be provided to the City in a written letter. The Independent Secondary Review would be paid at the applicant’s expense, and the Administrator shall select the third-party review professional. The applicant shall also be responsible for following: 1. Evaluating the potential to provide a greater building setback from the eastern property line along Logan Ave N in order to reduce to visual impact of the proposed structure. 2. Evaluating the potential to modulate the sound wall in order to reduce the visual impact of a 25- foot tall steel wall along a public right-of-way. 3. Submitting an updated noise study that 1) Provides justification for the stated goal of limiting ambient noise increases to 10 dBa or less, 2) Evaluates potential noise impacts to the Cedar River Trail to the west of the project site using ambient noise levels as a base, 3) Identifies the locations of the measuring equipment used to measure ambient noise levels at the adjacent sites, 4) Makes a specific finding with regards to the expected noise levels (measured in dBa) at the adjacent uses, 5) Identifies additional noise mitigation Exhibit 17 DocuSign Envelope ID: 63538EA2-9DDC-4F7A-9A88-640B330A9A04 Mark Clement Page 2 of 2 April 22, 2020 measures that the applicant could feasibly incorporate at the site after project completion should actual noise levels occur that are higher than anticipated , 6) Discusses whether or not extending the sound wall further west would reduce noise impacts to any of the adjacent sites. At this time, your project has been placed “on hold” pending receipt of the requested information. Please contact me at (425) 430-7219 if you have any questions. Sincerely, Alex Morganroth Senior Planner cc: Mr. and Mrs. Oatis /Parties of Record DocuSign Envelope ID: 63538EA2-9DDC-4F7A-9A88-640B330A9A04