HomeMy WebLinkAboutPRE_Pre-Application_Meeting_Summary_201125_v1PREAPPLICATION MEETING FOR
Chevron Fuel System Replacement
PRE 20-000236
CITY OF RENTON
Department of Community & Economic Development
Planning Division
October 22, 2020
Contact Information:
Planner: Jill Ding, 425.430.6598, jding@rentonwa.gov
Public Works Plan Reviewer: Scott Warlick, 425-430-7216, swarlick@rentonwa.gov
Fire Prevention Reviewer: Corey Thomas, 425.276.9582, cthomas@RentonRFA.org
Building Department Reviewer: Rob Shuey, 425.430.7235
Please retain this packet throughout the course of your project as a reference. Consider
giving copies of it to any engineers, architects, and contractors who work on the
project. You will need to submit a copy of this packet when you apply for land use
and/or environmental permits.
Pre-screening: When you have the project application ready for submittal, call and
schedule an appointment with the project manager to have it pre-screened before
formal submittal.
The pre-application meeting is informal and non-binding. The comments provided on
the proposal are based on the codes and policies in effect at the time of review. The
applicant is cautioned that the development regulations are regularly amended and the
proposal will be formally reviewed under the regulations in effect at the time of project
submittal. The information contained in this summary is subject to modification and/or
concurrence by official decision-makers (e.g., Hearing Examiner, Planning Director,
Development Services Director, Department of Community & Economic Development
Administrator, Public Works Administrator and City Council).
M E M O R A N D U M
DATE: October 19, 2020
TO: Jill Ding, Senior Planner
FROM: Corey Thomas, Lead Plans Review Inspector
SUBJECT: Chevron UST replacements
1. Separate plans and permits are required to be submitted to and obtained from the Renton
Regional Fire Authority for all new tanks and tank monitoring systems. Plan on three to four
weeks for review and permitting.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: October 19, 2020
TO: Jill Ding, Planner
FROM: Scott Warlick, Engineering Specialist III, Plan Review
SUBJECT: Chevron Fuel System Replacement
1419 N 30th St
PRE20-000236
NOTE: The applicant is cautioned that information contained in this summary is preliminary and non-
binding and may be subject to modification and/or concurrence by official City decision-makers. Review
comments may also need to be revised based on site planning and other design changes required by
City staff or made by the applicant.
I have completed a preliminary review for the above-referenced proposal located at parcel(s)
3342103271. The following comments are based on the pre-application submittal made to the City of
Renton by the applicant.
WATER COMMENTS
1. The proposed project is within the City of Renton’s water service area and in the Highlands 435
pressure zone.
2. The project is inside of the Wellhead Protection Area Zone 2.
3. There are existing water main(s) in the vicinity of the site:
12-inch water main in N 30th St that can deliver a maximum capacity of 2,800 gallons per
minute (gpm) – refer to City water project plan no. W-04560E
The static water pressure is approximately 93 psi at ground elevation of 218 feet.
4. There is existing water service to property that is served by a 1” lateral domestic water meter.
5. There are 3 existing fire hydrants in the vicinity of the project:
Northwest corner of the property – Hydrant ID No. HYD-N-00177
Across the street in front of Fire Station 15 - Hydrant ID No. HYD-N-00551
West of the property on the south side of N 30th St - Hydrant ID No. HYD-N-00001
6. Based on the review of project information submitted for the pre-application meeting, the
applicant is not planning on adding any additional water service to the property.
Chevron Fuel System Replacement – PRE20-000236
Page 2 of 4
October 19, 2020
SEWER COMMENTS
1. Sewer service is provided by the City of Renton.
2. There is an existing 6” side sewer that serves the existing facility (Record Dwg: S-01790D)
STORM DRAINAGE COMMENTS
1. A drainage report complying with the current version of the City adopted Surface Water Design
Manual (SWDM) will be required. Based on the City’s flow control map, the site falls within the
Peak Rate Flow Control Duration Standard area matching Existing Peak Conditions and is within
the East Lake Washington drainage basin. Refer to Figure 1.1.2.A – Flow chart to determine the
type of drainage review required in the RSWM.
2. The site is located in Zone 2 of the City’s Aquifer Protection Area (APA). Within this zone, open
facilities such as flow control and water quality ponds, stormwater wetlands and infiltration
facilities may require a liner in accordance with the design criteria in section 6.2.4. Open
conveyance systems such as ditches and channels may require a liner in accordance with section
1.2.4.3.
3. There is an 12-inch stormwater main in N 30th St north of the subject property (Record DWG: R-
222506)
4. There are 2 private stormwater mains on the subject property (Record DWG: R-222506).
5. Detailed plans for any proposed cut and fill operations shall be submitted. These plans shall
include the angle of slope, contours, compaction and retaining walls.
6. Storm drainage improvements along all public street frontages are required to conform to the
City’s street and stormwater conveyance standards. Any new storm drain installed on or off-site
shall be designed and sized in accordance with standards found in Chapter 4 of the 2017 RSWDM
and shall account for the total upstream tributary area, assuming developed conditions for onsite
tributary areas and existing conditions for any offsite tributary areas.
7. If the new plus replaced pollution generating impervious surface exceeds 5,000 SF, the applicant
will be required to provide enhanced basic water quality treatment. Any proposed detention
and/or water quality vault shall be designed in accordance with the RSWDM that is current at the
time of civil construction permit application. Separate structural plans will be required to be
submitted for review and approval under a separate building permit for the detention and/or
water quality vault.
8. Appropriate on-site BMPs satisfying Core Requirement #9 will be required to help mitigate the
new runoff created by this development to the maximum extent feasible. On-site BMPs shall be
evaluated in order of preference by feasibility as described in Section C.1.3 of the 2017 RSWDM.
A preliminary drainage plan, including the application of on-site BMPs, shall be included with the
land use application, as applicable to the project. The final drainage plan and drainage report must
be submitted with the utility construction permit application.
9. A geotechnical soils report for the site is required per the 2017 Renton Surface Water Design
Manual Section C.1.3. Information on the water table and soil permeability (measured infiltration
rates), with recommendations of appropriate on-site BMPs per Core Requirement #9 and
Appendix C shall be included in the report. The report should also include information concerning
the soils, geology, drainage patterns and vegetation present shall be presented in order to
evaluate the drainage, erosion control and slope stability for site development of the proposed
plat. The applicant must demonstrate the development will not result in soil erosion and
sedimentation, landslide, slippage, or excess surface water runoff.
10. Erosion control measures to meet the City requirements shall be provided.
Chevron Fuel System Replacement – PRE20-000236
Page 3 of 4
October 19, 2020
11. The current City of Renton Surface Water Standard Plans that shall be used in all drainage
submittals are available online at the City of Renton website.
12. The 2020 Surface water system development fee is $0.76 per square foot of new impervious
surface, but no less than $1,900.00 for each dwelling unit. This is payable prior to issuance of the
construction permit. This fee is subject to change based on the calendar year the construction
permit is issued.
TRANSPORTATION/STREET COMMENTS
1. The project currently does not propose to construct more than $150,000 worth of improvements
based on the RMC 4-6-060, therefore frontage improvements are not required along N 30th St. If,
however, the proposal was to change, frontage improvements may be required.
2. Paving and trench restoration within the City of Renton right of way shall comply with the City’s
Trench Restoration and Street Overlay Requirements.
GENERAL COMMENTS
1. Adequate separation between utilities as well as other features shall be provided in accordance
with code requirements.
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other utilities is
required with the exception of water lines which require 10-ft horizontal and 1.5-ft
vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.
2. All construction permits for utility and street improvements will require separate plan submittals.
All plans shall confirm to the Renton Drafting Standards. A licensed Civil Engineer shall prepare
the civil plans. Please visit the Development Engineering Forms page for the most up-to-date plan
submittal requirements:
http://rentonwa.gov/business/default.aspx?id=42473
3. A landscaping plan shall be included with the civil plan submittal. Each plan shall be on separate
sheets.
4. All utility lines (i.e. electrical, phone, and cable services, etc.) serving the proposed development
must be underground. The construction of these franchise utilities must be inspected and
approved by a City of Renton inspector.
5. Fees quoted in this document reflect the fees applicable in the year 2020 only and will be assessed
based on the fee that is current at the time of the permit application or issuance, as applicable to
the permit type. Please visit www.rentonwa.gov for the current development fee schedule.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: October 22, 2020
TO: Pre-Application File No. PRE20-000236
FROM: Jill Ding, Senior Planner
SUBJECT: Chevron Fuel System Replacement
1419 N 30th St
General: We have completed a preliminary review of the pre-application for the above-
referenced development proposal. The following comments on development and permitting
issues are based on the pre-application submittals made to the City of Renton by the applicant
and the codes in effect on the date of review. The applicant is cautioned that information
contained in this summary may be subject to modification and/or concurrence by official
decision-makers (e.g., Hearing Examiner, Community & Economic Development Administrator,
Public Works Administrator, Planning Director, Development Services Director, and City
Council). Review comments may also need to be revised based on site planning and other
design changes required by City staff or made by the applicant. The applicant is encouraged to
review all applicable sections of the Renton Municipal Code. The Development Regulations are
available online at www.rentonwa.gov
Project Proposal: The project site is located to the west of I-405 and south of N 30th Street and is
addressed as 1419 N 30th St (parcel no. 3342103271). The site’s area is approximately 75,172
square feet (1.73 acres) and is zoned Commercial Neighborhood (CN). The property is currently
occupied by a Chevron gas station. The project would include the removal of three (3) 15,000-
gallon gasoline Underground Storage Tanks (USTs), the installation of one (1) 20,000-gallon
Regular Gasoline UST, one (1) 15,000-gallon Supreme Gasoline UST, and one (1) 12,000-gallon
Diesel UST, along with four (4) new dispensers and associated product and vapor piping. The
purpose of the project is to modernize the existing fuel system, including replacing USTs that are
beyond their warranty period, and to ensure the compliance with the latest environmental
standards for retail gas stations. Site grading will require disturbance of approximately 1,950
square feet, resulting in a minimum of 1,000 cubic yards of earthwork. Site grading includes, but
is not limited to, the installation of new USTs, pipe trenching, and replacement of under-
dispenser containment sumps. No changes are proposed to the existing onsite structures or use.
No change in existing access is proposed. The project site is located within a Wellhead
Protection Area, zone 2.
Current Use: Currently the site is occupied with a Chevron gas station.
Development Standards: The project would be subject to RMC 4-2-120A, “Development
Standards for Commercial Zoning Designations” effective at the time of complete application
(noted as “CN standards” herein).
Chevron Fuel System Replacement
Preapplication Meeting
October 22, 2020
Zoning: The property is located within the Residential High Density (RHD) land use designation,
the Commercial Neighborhood (CN) zoning designation, and Urban Design District D. Vehicle
fueling stations, existing legal are permitted with an Administrative Conditional Use Permit in
the CN zone.
Minimum Lot Size, Width and Depth – The minimum lot size required in the CN zone is 5,000
square feet. There are no minimum width or depth requirements. No changes are proposed to
the existing lot size, width, or depth as a result of this proposal.
Lot Coverage – The maximum building coverage permitted in the CN zone is 65% of the lot area
of 75% if parking is provided within the building. No changes are proposed to the building
footprint or impervious surface coverage as a result in this proposal.
Setbacks – Setbacks are the distance between the building and the property line or any private
access easement. Setback requirements in the CN zone are as follows: 15-foot minimum
front/side yard along a street setback, which may be reduced to 0 feet through the site plan
review process; a 20-foot maximum front/secondary front yard setback; and no rear or side yard
setbacks, except 15 feet when the site abuts a residential zone. If any expansions to the
existing building or new buildings are proposed, the applicant would be required to
demonstrate compliance with the required setback areas. Compliance with this requirement
would be verified during the formal building permit review.
Maximum Gross Floor Area of Any Single Commercial Use on a Site - 5,000 gross sq. ft. The
maximum size shall not be exceeded, except by conditional use permit. These restrictions do not apply
to residential uses subject to net density limitations. If any expansions to the existing building or
new buildings are proposed, the applicant would be required to demonstrate compliance with
the required commercial square footage. Compliance with this requirement would be verified
during the formal building permit review.
Building Orientation - All commercial uses shall have their primary entrance and shop display window
oriented toward the street frontage.
Building Height – The maximum building height permitted in the CN zone is 35 feet. The
applicant has indicated that no changes in existing building height are proposed. Compliance
with this requirement would be verified during the formal land use review process.
Landscaping –The development standards require that all pervious areas within the property
boundaries be landscaped. Therefore, all areas of the site not covered by structures, required
parking, access, circulation or patios, must be landscaped with native, drought-resistant
vegetative cover. Ten feet (10') of on-site landscaping is required along all public street
frontages, with the exception of areas for required walkways and driveways. Projects that
include the remodel of a structure that requires improvements equal to or greater than fifty
percent (50%) of the assessed property valuation are subject to compliance with the
landscaping regulations.
Surface parking lots with fewer than 15 parking spaces are exempt from the parking lot
landscaping requirements.
Tree Preservation – A tree inventory and a tree retention plan along with a tree retention
worksheet shall be provided with the formal land use application. According to the proposed
regulations, the tree retention plan must show preservation of at least 10 percent (10%) of
significant trees, and indicate how proposed building footprints would be sited to accommodate
preservation of significant trees that would be retained. The Administrator may authorize the
Chevron Fuel System Replacement
Preapplication Meeting
October 22, 2020
planting of replacement trees on the site if it can be demonstrated to the Administrator’s
satisfaction that an insufficient number of trees can be retained.
Significant trees shall be retained in the following priority order:
Priority One: Landmark trees; significant trees that form a continuous canopy; significant trees
on slopes greater than twenty percent (20%); Significant trees adjacent to critical areas and their
associated buffers; and Significant trees over sixty feet (60') in height or greater than eighteen
inches ( 18") caliper.
Priority Two: Healthy tree groupings whose associated undergrowth can be preserved; other
significant native evergreen or deciduous trees; and other significant non-native trees.
Priority Three: Alders and cottonwoods shall be retained when all other trees have been
evaluated for retention and are not able to be retained, unless the alders and/ or cottonwoods
are used as part of an approved enhancement project within a critical area or its buffer.
The Administrator may require independent review of any land use application that involves
tree removal and land clearing at the City’s discretion. A tree retention plan is required at the
time of formal building permit review, if the proposal includes the removal of trees.
Screening - All operating equipment located on the roof of any building shall be enclosed so as
to be screened from public view in accordance with the requirements outline under RMC 4-4-
095.
Fences/Retaining Walls – If the applicant intends to install any fences as part of this project, the
location must be designated on the landscape plan. A fence taller than six feet (6') requires a
building permit. New or existing fencing would need to comply with RMC 4-4-040.
Retaining walls shall be composed of brick, rock, textured or patterned concrete, or other
masonry product that complements the proposed building and site development. There shall be
a minimum three-foot (3') landscaped setback at the base of retaining walls abutting public
rights-of-way. Please refer to retaining wall standards (RMC 4-4-040) for additional information.
Parking – Retail uses are required to provide a min/max of 2.5 parking spaces per 1,000 square
feet of net floor area. If any changes to the existing building footprint are proposed, compliance
with this requirement would be required. The applicant will be required at the time of formal
land use application to provide detailed parking information (i.e. stall and drive aisle
dimensions) and calculations of the subject site. It should be noted that the parking regulations
specify standard stall dimensions. Surface parking stalls must be a minimum of 9 feet x 20 feet,
compact dimensions of 8½ feet x 16 feet, and parallel stall dimensions of 9 feet x 23 feet;
compact surface parking spaces shall not account for more than 30 percent of the spaces in the
surface parking lots. No changes or additions to the existing building are proposed.
ADA accessible stalls must be a minimum of 8 feet in width by 20 feet in length, with an adjacent
access aisle of 8 feet in width for van accessible spaces. The appropriate amount of ADA
accessible stalls based on the total number of spaces must be provided.
Bicycle parking is not required as the proposal would include less than 4,000 square feet of
commercial retail space.
Refuse and Recycling Areas – Refuse and recycling areas need to meet the requirements of RMC
4-4-090, “Refuse and Recyclables Standards”. There are general requirements for all uses for
location, signage, screening, and setbacks for collection areas and specific requirements.
Chevron Fuel System Replacement
Preapplication Meeting
October 22, 2020
In retail developments, a minimum of five (5) square feet per every one thousand (1,000) square
feet of building gross floor area shall be provided for recyclables deposit areas and a minimum
of ten (10) square feet per one thousand (1,000) square feet of building gross floor area shall be
provided for refuse deposit areas. A total minimum area of one hundred (100) square feet shall
be provided for recycling and refuse deposit areas.
If any changes in building area are proposed, compliance with this requirement would be
required.
Access – Driveway widths are limited by the driveway standards, in RMC 4-4080I. No change in
access is proposed.
Building Design Standards – Compliance with Urban Design Regulations, District ‘D’, is
required. Modifications from the standards can be applied. See Renton Municipal Code section
4-3-100. The following bullets are a few of the standards outlined in the regulations.
A primary entrance of each building shall be located on the facade facing a street, shall
be prominent, visible from the street, connected by a walkway to the public sidewalk,
and include human-scale elements.
Parking shall be located so that no surface parking is located between a building and the
front property line, or the building and side property line, on the street side of a corner
lot.
The number of driveways and curb cuts shall be minimized, so that pedestrian
circulation along the sidewalk is minimally impeded.
Amenities such as outdoor group seating, benches, transit shelters, fountains, and
public art shall be provided.
All building facades shall include modulation or articulation at intervals of no more than
forty feet (40').
Modulations shall be a minimum of two feet (2') deep, sixteen feet (16') in height, and
eight feet (8') in width.
On any facade visible to the public, transparent windows and/or doors are required to
comprise at least fifty percent (50%) of the portion of the ground floor facade that is
between four feet (4') and eight feet (8') above ground (as measured on the true
elevation). Where windows or storefronts occur, they must principally contain clear
glazing.
Buildings shall employ material variations such as colors, brick or metal banding, patterns, or
textural changes.
Critical Areas: A wellhead protection area, zone 2 is mapped on the project site. A fill source
statement is required for any fill brought onto the site.
Environmental Review: The proposal would trigger Environmental (SEPA) Review as the USTs
exceed 10,000 gallons.
Permit Requirements: The proposed project would require Environmental (SEPA) Review.
Environmental (SEPA) Review would be processed within an estimated time frame of 6-8 weeks.
The current 2020 application fees would total $1,659 ($1,580 SEPA Review + $79 technology fee
= $1,659), all fees are subject to change and are expected to increase in 2021. Detailed
information regarding the land use application submittal is available online at
www.rentonwa.gov. In addition to the required land use permits, separate construction and
building permits would be required.
Chevron Fuel System Replacement
Preapplication Meeting
October 22, 2020
Note: When the formal application materials are complete, the applicant is strongly
encouraged to have one copy of the application materials pre-screened prior to submitting
the complete application package. Please contact Jill Ding, Senior Planner at 425 -430-6598 or
jding@rentonwa.gov for an appointment.