HomeMy WebLinkAboutNOA_Project Acceptance_201208DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION AND PROPOSED DETERMINATION OF
NON-SIGNIFICANCE (DNS)
A Master Application has been filed and accepted with the Department of Community & Economic Development
(CED) – Planning Division of the City of Renton. The following briefly describes the application and the necessary
Public Approvals.
DATE OF NOTICE OF APPLICATION: December 9, 2020
PROJECT NAME/NUMBER: PR20-000322 Chevron Fuel System Replacement /
LUA20-000286, ECF
PROJECT LOCATION: 1419 NE 30th St (APN 3342103271)
APPLICANT/PROJECT CONTACT
PERSON: Sean Anderson, Barghausen Consulting Engineers, Inc. / 18215 72nd Ave S, Kent,
WA 98032/ sanderson@barghausen.com
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton Document
Center website. See also https://cutt.ly/KhEGHDF
PROJECT DESCRIPTION: The applicant is requesting Environmental (SEPA) Review for the removal and
replacement of Underground Storage Tanks (UST) at the Chevron Gas Station. The project site totals 1.73-acre (75,172
square feet) and is located within the Commercial Neighborhood (CN) zone and Urban Design District D. The existing
development includes a 1,800-square-foot convenience store, a 2,000-square-foot fuel dispenser canopy, four (4) fuel
dispensers, and three (3) 15,000-gallon gasoline Underground Storage Tanks (USTs). The project will include the removal
of the three (3) USTs and installation of one (1) 20,000-gallon Regular Gasoline UST, one (1) 15,000-gallon Supreme
Gasoline UST, and one (1) 12,000-gallon Diesel UST, along with four (4) new dispensers and associated product and vapor
piping. The purpose of the project is to modernize the existing fuel system, including replacing USTs that are beyond
their warranty period and to ensure the compliance with the latest environmental standards for retail gas stations. No
changes in access to the project site are proposed. The project site is mapped with a Wellhead Protection Area, Zone 2.
DATE OF APPLICATION: November 30, 2020
NOTICE OF COMPLETE APPLICATION: December 9, 2020
OPTIONAL DETERMINATION OF NON-SIGNIFICANCE (DNS): As the Lead Agency, the City of Renton has determined that
significant environmental impacts are unlikely to result from the proposed project. Therefore, as permitted under the
RCW 43.21C.110, the City of Renton is using the Optional DNS process to give notice that a DNS is likely to be issued.
Comment periods for the project and the proposed DNS are integrated into a single comment period. There will be no
comment period following the issuance of the Threshold Determination of Non-Significance (DNS). This may be the only
opportunity to comment on the environmental impacts of the proposal. When the DNS becomes appealable, the appeal
period will be 14 days.
PERMITS/REVIEW REQUESTED: Environmental (SEPA) Review
OTHER PERMITS WHICH MAY BE
REQUIRED:
Buildng Permit
REQUESTED STUDIES: Drainage Report
CONSISTENCY OVERVIEW:
Zoning/Land Use: The subject site is designated Residential High Density (RHD) on the City of
Renton Comprehensive Land Use Map and Commercial Neighborhood (CN) on
the City’s Zoning Map.
Environmental Documents that
Evaluate the Proposed Project:
Environmental (SEPA) Checklist
NOTICE
If you would like to be made a party of record to receive further information on this proposed project, complete this form
and return to: City of Renton, CED – Planning Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR20-000322 Chevron Fuel System Replacement/ LUA20-000286, ECF
NAME:
MAILING ADDRESS: City/State/Zip:
EMAIL: ______ TELEPHONE NO.:
I prefer to receive project information and documents in hard copy via US mail
Development Regulations Used
For Project Mitigation:
The project will be subject to the City’s SEPA ordinance, RMC 4-2-120 and other
applicable codes and regulations as appropriate.
Proposed Mitigation Measures: No mitigation measures are proposed at the time of this posting.
Comments on the above application must be submitted in writing to Jill Ding, Senior Planner CED – Planning Division,
1055 South Grady Way, Renton, WA 98057, by 5:00 PM on December 23, 2020. If you have questions about this
proposal, or wish to be made a party of record and receive additional notification by mail, contact the Project Manager.
Anyone who submits written comments will automatically become a party of record and will be notified of any decision
on this project. A copy of the subsequent threshold determination is available upon request.
CONTACT PERSON: Jill Ding, Senior Planner; Tel: (425) 430-6598; Email: jding@rentonwa.gov