HomeMy WebLinkAboutRS_Biologist assessment Memo
1
Technical Memorandum
To: City of Renton Planning Division
From: Ian Welch (HDR), Tobin Story, PWS (HDR)
Date: December 8, 2020
Subject: Hoquiam Avenue NE Luminaires Project Wetland and Wetland Buffer Assessment
Biologists Statement
1.0 Introduction
This memo serves to summarize the methods and results of a critical areas reconnaissance
conducted in the Hoquiam Avenue NE Luminaires Project corridor. Four new utility poles would be
installed along the project corridor within the right-of-way. In addition, new luminaires and arms
would be installed at existing and new pole locations.
Puget Sound Energy (PSE) has requested that biologists certified to conduct wetland surveys,
conduct a reconnaissance in the project corridor to document the presence of critical area, in
particular the extent of wetlands and wetland buffer conditions in relation to the project work. This
memo documents the results of the recon-level field visit.
2.0 Methods
Existing documents reviewed for this critical areas reconnaissance included the following:
City of Renton GIS data online: Critical Areas map (2020)
U.S. Fish and Wildlife (USFWS) National Wetland Inventory maps (2020)
Washington Department of Fish and Wildlife (WDFW) Priority Habitats and Species (PHS) on the
web (2020)
These documents provide background information on the hydrology, land use, and documented
wetlands and streams in the project area.
Based on a review of existing information, two wetlands are mapped by the City of Renton (2020) in
the vicinity of the project. A small stream, Honey Creek, is mapped as crossing under Hoquiam Ave
NE near the north end of the project corridor (Figure 1).
2.1 Field Investigation
Following this review, HDR biologists completed a field reconnaissance of the project corridor. The
entire corridor was walked in the field within the road right-of-way. As part of the survey, a wetland
scientist was present to confirm the extent of wetlands and wetland buffer vegetation in the project
corridor.
Existing vegetation and ground conditions throughout the project corridor were observed. Wetland
boundaries in the immediate vicinity of the project were estimated based on ground saturation,
vegetation, and topography, and wetland buffer conditions were observed and documented.
3.0 Results
The field reconnaissance survey was conducted on November 24, 2020. Site photographs from the
survey are attached in this memo. The project would add four additional poles within the project
corridor and add lighting to the remaining existing poles (Figure 1). Honey Creek, which crosses
through a culvert under Hoquiam Ave NE near the north end of the project, is not within the area
affected by any of the new pole installations and would not be impacted by any project activities. Per
Renton code (RMC 4-3-050G.2) a 115-foot stream buffer applies to Honey Creek. The project
corridor is within the road prism through which the creek is conveyed within a culvert. The stream
buffer extends perpendicular from the end of the culvert and therefore is outside the edge of the area
where project activities would occur (RMC 4-3-050G.7.c.ii).
There are two wetlands mapped and observed adjacent to the project corridor, one on each side of
Hoquiam Ave NE (Figure 1). The wetland on the east side of the road (Wetland 1) is located
adjacent to the project corridor. The wetland is a depressional PSS/PFO (palustrine scrub/shrub and
palustrine forested) wetland. Dominant species include Pacific willow (Salix lasiandra), black
cottonwood (Populus balsamifera), hardhack (Spiraea douglasii), red osier dogwood (Cornus
sericea). The wetland is associated with Honey Creek. The dominant hydrologic regime is
seasonally flooded. Based on the field visit this wetland was rated as a Category II wetland with a
moderate habitat score (6 points). Per City of Renton code (RMC 4-3-050G.2), this results in a buffer
width of 100 feet for low impact land uses. Utility corridors without a maintenance road constitute a
low impact land use (RMC 4-3-050G.2 Footnote 7).
The required buffer for Wetland 1 would extend to the edge of the existing road. Per the Renton
code (RMC 4-3-050G.2 Footnote 6), areas that are functionally and effectively disconnected from
the wetland by a permanent road or other substantially developed surface of sufficient width and with
use characteristics such that buffer functions are not provided shall not be counted toward the
minimum buffer.
Replacement of the luminaires on existing poles, and installation of the new poles would occur in the
wetland buffer (Figure 1); however, the buffer where the existing and proposed new poles are
located currently consists of road prism, and is vegetated by grasses and herbaceous species
common to disturbed areas.
Replacement of the lights and installation of the new poles would not require clearing of any trees.
Holes for the new poles would be dug within the road right-of-way and would not result in impacts to
the wetland. Any minor impacts from pole installation would be temporary, confined to the road
prism, and would be restored to existing conditions immediately following construction. No trees
would be removed as part of this project, so there would be no impacts to the existing forested
condition of the adjacent wetland buffer.
On the west side of the road, the mapped wetland (Wetland 2) is located approximately 100 feet
west of the road at the closest point. This wetland was not observed from the project area, and its
extent not verified. However, all project activities would occur on the east side of the road and would
have no impacts to the buffer of Wetland 2.
4.0 Summary
The nature of the project impacts would not adversely affect the functions of Wetland 1 or its buffer.
Excavation of holes and installation of new poles would be localized, temporary, and occur
completely within the road right-of-way. The road prism where the new poles would be installed does
not provide any ecological function for the wetland buffer, and therefore the project would not result
in any impacts to the wetland itself or the wetland buffer function. There will be no net loss of
ecological functions and processes as a result of construction or operation of this project.
5.0 References
U.S. Fish and Wildlife Service (USFWS). 2020. National Wetland Inventory (NWI) Mapper. Available
online at https://www.fws.gov/wetlands/data/mapper.html. Accessed January 2020.
Washington Department of Fish and Wildlife (WDFW). 2020. Priority Habitats and Species Mapper.
Available online at https://wdfw.wa.gov/mapping/phs/. Accessed January 2020.
Path: \\bel-srv03\gisdata\Projects\Washington\Puget_Sound_Energy_007022\HoquiamAveCAE_10261754\Map_Docs\WetlandReport\WetlandFieldRecon.mxd--kj
kj
kj
kj
kj
kj
kj
kjkj kjkj
!(
!(
!(
!(
&-
&-
!(
&-
&-
!(!We t l a n d 2 !We t l a n d 1
H
o
n
e
y
C
r
e
e
k
SR900
Hoquiam Ave NEHoquia
m
PlN
E
NE 13th Pl
PrivateRdIlwacoAveNE
NE 12th St
Oliver Hayden HS AcRd
!(Existing Pole
&-Proposed Pole
kj
Verifie d Wetlan dBoundary --Culvert
Renton Strea ms
Renton We tlands
WetlandBuffer
FIGURE 1
Date: 12/7/2020
WETLANDS FIELD R EC O NN A ISSA N C E
HOQUIAM AVENU E NELUMINAIRES PROJ ECT
SO URCES: W etlands, streams, and roads - City of Bainbridge Island (2019), Aerial - City of Renton (2020) Online.
I 0 75 150Feet1 inch = 150 feetLakeWashingtonLakeSammamish§¨405§¨ 5
ST169
§¨90
ST520
ST167
ST99
ST509
Sea ttle Bellevue
Newcast le
Renton
Tukwila
SeaTac
Kent
Des Moines
I
MAPEXTENT
Attachment A
Site Photos
Photo 1: South end of the project corridor looking north along project alignment on east side of road.
There are not critical areas at the south end of the project.
Photo 2: North end of project corridor within Wetland 1 buffer. Poles are located in the road prism that
does not provide ecological function for the buffer. Tobin is standing on the culvert inlet for the creek.