Loading...
HomeMy WebLinkAboutCM_Const_Mitigation_201216_v1.pdfSolera - Construction Mitigation Description December 16, 2020 Solera 2842 NE Sunset Blvd. Renton, WA 98056 The Solera project is planning on starting in July, of 2021, and hoping to have the first building open by September, of 2023, and will be completed by March of 2024. Construction Hours will be from 7:00 a.m. to 7:00 p.m. Monday -Saturday. Hauling will be coordinated through the Site Earthwork and Utility Contractor, but expected to be to the closest possible dump sites and material pits available. A Storm Water Pollution Prevention Plan (SWPPP) and Best Management Practices will be observed and implemented to minimize impacts and disturbances to the surrounding community. All work is planned to be implemented during the normal construction hours. If special circumstances exist that require work outside of these time periods we will look to get permission as required. As with the hauling routes the traffic control plan will be implemented, and submitted to the City of Renton, and WSDOT, as required, by the Earthwork and Utility Contractor once the contract is awarded.