www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AES 0895.06 1 of 1 256
Time On Site Time Off Site Date Day of Week
8:00, 2:55 8:20, 3:15 12/16/20 Wednesday
Travel Time Weather
1 hr. 47°F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
General Contractor Contact Field Supervisor Reviewed
Accrete Construction, LLC Joe LAC
Contractor #2 Contact Project Manager Reviewed
Are approved plans/permits on site? Project No. Permit No.
As requested by the client, ESNW representative was onsite for testing of turbidity and pH of baker tank for
discharge into stormwater system.
While onsite, ESNW rep. observed the following:
Baker Tank
1. Morning Sample
a. Turbidity: 28.28 NTU
b. pH: 10.4
2. Afternoon Sample
a. Turbidity: 17.26 NTU
b. pH: 9.4
The baker tank did not meet the requirements of a pH between 6.5 and 8.5 for discharge into the storm system.
ESNW rep. will return as requested.
Alexandra Shaner
Field Technician
(206) 355-877