HomeMy WebLinkAbout0895.06 DFR 103-107.pdfTo
ifutio
lac
Earth Solutions NW, LLC
LETTER OF TRANSMITTAL
RJ Development Date: January 14, 2020
401 Central Street SE ESNW No.: ES- 895.06
_Olympia, WA 98501 _ Project: _ Weatherly Inn _
Attn: Mr. Duane Meyer
Email: duane[a,)accrete.build
No. of
uo ies uate uescri tion
1 1 1/6-1/10/20 Dailv Field Report(s) # 103-107
Comments:
CC.
1:
John Wilson
ATTN:
johnw@rinocon.com
2:
Mark Richardson
ATTN:
mark(d)accrete-build
3:
Jeff Brain
ATTN:
jeff@accrete. build
4:
Jennifer Vogele
ATTN
Jennifer@accrete. build
5:
Jonathan Chavez
ATTN:
jchavez@rentonwa.gov
6:
Joe W
ATTN
joew a@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
1805 — 136t" PI NE, Suite 201 Bellevue, WA 98005
(425) 284-3300 FAX (425) 449-4711 Toll Free (866) 336-8710
.. Earth Solutions NW«C
t ; 15365 NE 901h Street, Suite 100
Redmond. WA 98052
Main (425) 449-4704 1 Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
ESNW Rep. Project No. Page
AK 0895.06
Time On Site Time Off Site Date
1:45 PM 1 2:15 PM 1 1 /6/20
Travel Time
1.25 Hr. RT
Job Location
4500 Talbot Rd. S., Renton, WA
Contact
Mike
Contact
Project No
1
Report No.
103
Day of Week
Monday
Weather
40s0F, Rain
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed LAC %/13
Project Manager Reviewed
Ray
Permit No
At the client's request, ESNW rep was onsite to observe or test pH of stormwater, footing excavations and
earthwork activities.
Test pH of Stormwater
While onsite, rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the
quarry spall entrance and observed a pH level of 6.5/7 pH. At the west of the quarry spall entrance stormwater
(temporary) collection pit and observed a pH level of 9 pH. On the street, north and south of the west entrance,
rep took a pH tests and observed stormwater to be a 6.5/7 pH. Rep tested banker tanks with stormwater and
observed that contractor had added dry ice as recommended by ESNW. Rep tested a 6.5/7 pH in tested baker
tank which is compliant with required pH levels for sewer discharge. Rep observed that pH level was contained
onsite and that stormwater pH level in street was in compliance of required pH level at 6.5/7 pH.
Footing Excavations
Rep observed contractor forming boards for the footings. Rep observed south slopes of the excavation to be
near vertical. Rep observed that the east slopes of the excavation were near a 0 75:1 (H:V) slope. Although over -
steepened, slopes are stable in current configuration and stable to work within. The contractor is responsible for
providing all safety measures in accordance with state and federal regulation. Rep observed that contractor had
sloped the southeast corner of the footing excavation to a 1:1 (H:V)
Rep observed that contractor had placed plastic sheeting over the exposed slopes for the footing excavation, the
exposed slopes between the lock and load wall and the rockery as recommended.
ESNW rep will return to observe earthwork activities when requested by client.
4-1-11 �—
Andrew Kimn, Senior Technician, 206-430-9183
y Earth Solutions NWLLc
15365 NE 90' Street, Suite 100
Redmond, WA 98052
wo Main (425) 449-4704 1 Fax (425) 449-4711
www esnw.com
DAILY FIELD REPORT
Project Name Job Location
Weatherly Inn 14500 Talbot Rd. S., Renton, WA
Contractor #1
Rino Construction
Contractor #2
contact
Mike
Contact
Are approved plans/permits on site? Project No
Supplementary Report:
ESNW Rep. Project No. Page Report No.
AK 0895.06 1/2 104
Time On Site Time Off Site Date Day of Week
10:30 AM; 11:30 AM; Tuesday
2:15 PM 3:00 PM 1/7/20
Travel Time Weather
1.25 Hr. RT 40sOF, Overcast
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC W'113
Project Manager Reviewed
Ray
Permit No
At the client's request, ESNW rep was onsite to observe or test water line backfill, test pH of stormwater, sewer
discharge, footing excavations and earthwork activities.
Water Line Backfill
While onsite, rep observed contractor use a medium sized excavator to excavate and install the water line Rep
observed contractor install a 10" ductile iron pipe at the toe of the excavation (W4'xD4') embedded in a 12" lift pea
gravel. Rep observed contractor place brown silty sand with gravel material in loose 12"-18" lifts and compacting
with a hoe pack. Rep took compaction tests on backfill and observed material to be adequate of at least 95% of
its maximum dry density (130.7 lbs./cu. ft.).
Test pH of Stormwater
Rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the quarry spall
entrance and observed a pH level of 6.5/7 pH. At the west of the quarry spall entrance stormwater (temporary)
collection pit and observed a pH level of 6.5/7 pH. On the street, north and south of the west entrance, rep took a
pH tests and observed stormwater to be a 6.5/7 pH. Rep tested banker tanks with stormwater and observed that
contractor had added dry ice as recommended by ESNW. Rep tested a 6.5/7 pH in tested baker tank which is
compliant with required pH levels for sewer discharge. Rep observed that pH level was contained onsite and that
stormwater pH level in street was in compliance of required pH level at 6.5/7 pH.
Rep observed contractor excavate the temporary retention pond with a medium sized excavator and install two
more stormwater channels below the quarry spall entrance. Rep observed contractor excavate 6%8", place plastic
sheeting, and a half pipe of 12" corrugated pipe outside facing down. Contractor expressed plans to backfill the
pipe with 4%6" quarry spalls.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of
6.5.
Footing Excavations
Rep observed contractor forming boards for the footings. Rep observed south slopes of the excavation to be near
vertical and covered in plastic sheeting. Rep observed that the east slopes of the excavation were near a 0.75:1
(H:V) slope. Although over -steepened, slopes are stable in current configuration and stable to work within. The
contractor is responsible for providing all safety measures in accordance with state and federal regulation. Rep
observed that contractor had sloped the southeast corner of the footing excavation to a 1:1 (H:V)
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWuc ESNW Rep
AK
15365 NE 901' Street, Suite 100
Redmond, WA 98052 Time On Site
Main (425) 449-4704 i Fax (425) 449-4711 10:30 AM;
www.esnw.com 2:15 PM
DAILY FIELD REPORT
Travel Time
1.25 Hr. RT
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Project No.
Page
2�2
Report No.
0895.06
104
Time Off Site
Date
Day of Week
11:30 AM:
Tuesday
3:00 PM
1/7/20
Job Location
4500 Talbot Rd. S., Renton, WA
Contact
Mike
Contact
Project No -
Weather
40s°F, Overcast
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC
Project Manager Reviewed
Ray
Permit No
Test
Test Location
Reference
Maximum
Fill
Test
% of
Number
(See Map)
Elevation
Compaction
Dry Density
Moisture
Dry Density
Maximum
wa r)
Curve
(pcf)
N
(pcf)
Dry Density
106
See map for approximate location
SG
1
130.7
11.8
124.5
95
Supplementary Report
106
4
I
` Earth
W,uc.
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
Earth Solutions NW«C
ESNW Rep.
AK
15365 NE 901 Street, Suite 100
Time On Site
Redmond, WA 98052
Main (425) 449-4704 1 Fax (425) 449-4711
10:15 AM;
www esnw corn
2:00 PM
DAILY FIELD REPORT
Travel Time
1.25 Hr. RT
Project No. Page Report No.
0895.06 1 1/1 105
Time Off Site Date Day of Week
11:15 AM; Wed
3:00 PM 1 /8/20
............
Weather
40sOF, Overcast
Job Location
4500 Talbot Rd. S., Renton, WA
Contact
Mike
Contact
Are approved plans/permits on site? Project No
Supplementary Report:
Client/Owner
RJ Development, LLC
Field Supervisor
LAC
Project Manager
Ray
Permit No.
Reviewed
��11,
Reviewed
At the client's request, ESNW rep was onsite to observe or test storm line backfill, test pH of stormwater, sewer
discharge, footing excavations and earthwork activities.
Storm Line Backfill
While onsite, rep observed contractor use a medium sized excavator to excavate and install the storm line. Rep
observed contractor install a 12" corrugated pipe at the toe of the excavation (W2'xD3.5') embedded in a 12" lift
pea gravel. Rep will test compaction of backfill as needed tomorrow, Thursday, December 9, 2020.
Test pH of Stormwater
Rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the quarry spall
entrance and observed a pH level of 6.5/7 pH. At the west of the quarry spall entrance stormwater (temporary)
collection pit and observed a pH level of 6.5/7 pH. On the street, north and south of the west entrance, rep took a
pH tests and observed stormwater to be a 6.5/7 pH. Rep tested banker tanks with stormwater and observed that
contractor had added dry ice as recommended by ESNW. Rep tested a 6.5/7 pH in tested baker tanks which were
compliant with required pH levels for sewer discharge. Rep observed that pH level was contained onsite and that
stormwater pH level in street was in compliance of required pH level at 6.5/7 pH.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 mI) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of
6.5.
Footing Excavations
Rep observed contractor forming boards for the footings. Rep observed south slopes of the excavation to be near
vertical and covered in plastic sheeting. Rep observed that the east slopes of the excavation were near a 0.75:1
(H:V) slope. Although over -steepened, slopes are stable in current configuration and stable to work within. The
contractor is responsible for providing all safety measures in accordance with state and federal regulation. Rep
observed that contractor had sloped the southeast corner of the footing excavation to a 1:1 (H:V).
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
Eari.h
�fllfll�Uf1S
Ivwl.tt;
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
Earth SollutiionS NWLLC
ESNW Rep.
AK
15365 NE 9011 Street, Suite 100
Time On Site
Redmond, WA 98052
Main (425) 449-4704 1 Fax (425) 449-4711
www.esnw.com
1:00 PM
DAILY FIELD REPORT
Travel Time
1.25 Hr. RT
Are approved plans/permits on site?
Supplementary Report:
Project No. Page Report No.
0895.06 1/2 106
Time Off Site Date Day of Week
2:45 PM 1/9/20 Thursday
Weather
40s0F, Overcast
Job Location
4500 Talbot Rd. S , Renton, WA
Contact
Mike
Contact
Project No
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC A- III-,
Project Manager Reviewed
Ray
Permit No
At the client's request, ESNW rep was onsite to observe or test storm line backfill, pH of stormwater, sewer
discharge, footing excavations and earthwork activities.
Storm Line Backfill
While onsite, rep observed contractor use a medium sized excavator to excavate and install the storm line. Rep
observed contractor install a 12" corrugated pipe at the toe of the excavation (W2'xD3.5') embedded in a 12" lift
pea gravel. Rep observed contractor place brown silty sand with gravel material in loose 12"-18" lifts and
compacting with a hoe pack. Rep took compaction tests on backfill and observed material to be adequate of at
least 95% of its maximum dry density (130.7 lbs./cu. ft.).
Test pH of Stormwater
Rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the quarry spall
entrance and observed a pH level of 9 pH. At the west of the quarry spall entrance stormwater (temporary)
collection pit and observed a pH level of 9 pH. On the street, north and south of the west entrance, rep took a pH
tests and observed stormwater to be a 6.5/7 pH. Rep observed that pH level was contained onsite and that
stormwater pH level in street was in compliance of required pH level at 6.5/7 pH.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 mI) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of
6.5.
Footing Excavations
Rep observed contractor forming boards for the footings. Rep observed south slopes of the excavation to be near
vertical and covered in plastic sheeting. Rep observed that the east slopes of the excavation were near a 0.75:1
(H:V) slope. Although over -steepened, slopes are stable in current configuration and stable to work within. The
contractor is responsible for providing all safety measures in accordance with state and federal regulation. Rep
observed that contractor had sloped the southeast corner of the footing excavation to a 1:1 (H:V).
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
s
"
t t
Earth Solutions NWLLC
15365 NE 90" Street, Suite 100
Redmond, WA 98052
ESNW Rep.
AK
Project No.
0895.06
Page
2�Z
Date
Report No
106
Day of Week
Time On Site
Time Off Site
Main (425) 449-4704 i Fax (425) 449-4711
Thursday
wwwesnw.com
1:00 PM
2:45 PM
1/9/20
DAILY FIELD REPORT
Travel Time
Weather
1.25 Hr. RT
40sOF, Overcast
Project Name
Job Location
Client/Owner
Weatherly Inn
4500 Talbot Rd.
S., Renton, WA RJ Development, LLC
Contractor #1
Contact
Field Supervisor Reviewed
Rino Construction
Mike
LAC
Contractor #2
Contact
Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No
Permit No.
Test
Test Location
Reference
Maximum
Fill
Test
% of
Number
(See Map) /
Elevation
Compaction
Curve
Dry Density
Moisture
Dry Density
Maximum
Dry Density
(pcf)
(%)
(pcf)
107
See map for approximate location SG
1
130.7
11.0
124.8
96
Supplementary Report
Earth Solutions NW«C ESNW Rep Project No. Page Report No.
" AK 0895.06 1/1 107
Redmond,n WA 98052 Y
t t 15365 NE Street, Suite 100 Time On Site Time Off Site Date Da of Week
Main (425) 449-4704 1 Fax (425) 449-4711 10:15 AM; 12:00 PM; Friday
www.esnw.com 2:15 PM 3:00 PM 1/10/20
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT x2 40s°F, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S , Renton, WA 1 RJ Development, LLC
Contractor #1 Contact
Rino Construction
Field Supervisor Reviewed
Mike
LAC
Contractor #2 Contact
Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No
Permit No
Supplementary Report:
At the client's request, ESNW rep was onsite to observe or test pH of stormwater, sewer vault, sewer discharge,
footing excavations and earthwork activities.
Test pH of Stormwater
While onsite, rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the
quarry spall entrance and observed a pH level of 7 pH. At the west of the quarry spall entrance stormwater
(temporary) collection pit and observed a pH level of 9 pH. On the street, north and south of the west entrance,
rep took a pH tests and observed stormwater to be a 6 5/7 pH. In tested baker tank, rep observed a pH level of
8.5 pH. Rep observed that pH level was contained onsite and that stormwater pH level in street was in compliance
of required pH level at 6.5/7 pH.
Sewer Vault
Rep observed contractor use a medium sized excavator to install a sewer vault located mid -east of the site.
Contractor expressed plans to continue working on sewer vault next week.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of
6.5.
Footing Excavations
Rep observed contractor forming boards for the footings. Rep observed south slopes of the excavation to be near
vertical and covered in plastic sheeting. Rep observed that the east slopes of the excavation were near a 0.75:1
(H:V) slope. Although over -steepened, slopes are stable in current configuration and stable to work within. The
contractor is responsible for providing all safety measures in accordance with state and federal regulation. Rep
observed that contractor had sloped the southeast corner of the footing excavation to a 1:1 (H:V).
ESNW rep will return to observe earthwork activities when requested by client
4—" �_
Andrew Kimn, Senior Technician, 206-430-9183