HomeMy WebLinkAbout0895.06 DFR 118-122.pdfFarth
l utian
NWLtz
Earth Solutions NW, LLC
LETTER OF TRANSMITTAL
To: R1 Development Date: February 4, 2020
401 Central Street SE ESNW No.: ES- 895.06
Olympia, WA 98501 Project: Weatherly Inn
Attn: Mr. Duane Meyer
Email: duane(a,accrete.build
No. of
Copies Date Descri tioti
1 1/27-1/31/20 Daily Field Report(s) # 118-122
Comments:
CC:
1:
John Wilson
ATTN:
johnw@rinocon.com
2:
Mark Richardson
ATTN:
markpaccrefe build
3:
Jeff Brain
ATTN:
Leffpaccrete.build
4:
Jennifer Vogele
ATTN:
'ennifer accrete. build
5:
Jonathan Chavez
ATTN:
ica havez@rentonwa.gov
6:
Joe W
ATTN:
joew@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riejzel, L.G., L.E.G.
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
" Earth Solutions NWLLC
15365 NE 901h Street, Suite 100
1 Redmond, WA 98052
ESNW Rep.
AK
Project No.
0895.06
Page
1/1
Report No.
118
Time On Site
Time Off Site
Date Day of Week
Main (425) 449-4704 1 Fax (425) 449-4711
Monday
www.esnw.com
12:00 PM
1:30 PM
1/27/20
DAILY FIELD REPORT
Weather
Trave€ Time
1.25 Hr. RT
40sOF, Overcast
Project Name
Job Location
Client/Owner
Weatherly Inn
4500 Talbot Rd. S., Renton, WA
RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC WZf�
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No Permit No.
Supplementary Report:
At the client's request, ESNW rep was onsite to observe or test cut slopes, storm line backfill, sewer discharge,
test pH of stormwater and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over -steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Storm Line Backfill
Rep observed contractor use a medium sized excavator to excavate and install the storm line. Rep observed
contractor install a 12" corrugated pipe at the toe of the excavation (W2'xD4') embedded in a 12" lift pea gravel.
Rep will return to test compaction of backfill as needed tomorrow, January 28, 2020.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a pH level of
6.5.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In three south end baker tanks rep observed a pH of 6.5,
rep observed that contractor added dry ice to lower the pH level. Rep observed that pH level was contained onsite
and that stormwater pH level in street was in compliance of required pH level at 6.5/7 pH. Rep recommended that
contractor add stormwater filtration system to increase volume of discharge. Rep recommended Clear Water,
Washington Stormwater LLC., and Water Tectonics.
ESNW rep will return to observe earthwork activities when requested by client
4J,S
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLC ESNW Rep. Project No. Page Report No.
AK 0895.06 1/1 119
15365 NE mold Street, Suite 100 Time On Site Time Off Site Date Da of Week
ir Redmond, WA 98052 Y
Main (425) 449-4704 1 Fax (425) 449-4711 9:45 AM; 11:45 AM; Tuesday
www.esnw.com 1:00 PM 2:00 PM 1/28/20
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT 40s0F, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact
Rino Construction Mike
Contractor #2 Contact
Are approved plans/permits on site? Project No.
Supplementary Report:
Field Supervisor Reviewed Z/3
LAC
Project Manager Reviewed
Ray
Permit No
At the client's request, ESNW rep was onsite to observe or test cut slopes, storm line backfill, sewer discharge,
test pH of stormwater and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over -steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V)
Storm Line Backfill
Rep observed contractor use a medium sized excavator to excavate and install the storm line. Rep observed
contractor install a 12" corrugated pipe at the toe of the excavation (W2'xD4') embedded in a 12" lift pea gravel.
Rep will return to test compaction of backfill as needed tomorrow, January 29, 2020. Rep recommended using
native course sand material or using imported pit -run for backfill.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a pH level of
6.5.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In two north end baker tanks rep observed a pH of 6.5, rep
observed that contractor added dry ice to lower the pH level. Rep observed that pH level was contained onsite
and that stormwater pH level in street was in compliance of required pH level at 6.5/7 pH. Rep recommended that
contractor add stormwater filtration system to increase volume of discharge. Rep met with ESNW stormwater
manager to discuss solutions to the current discharge system.
ESNW rep will
return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
M Earth Solutions NWT«
15365 NE 90" Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 1 Fax (425) 449-4711
Vii
1
www esnw corn
DAILY FIELD REPORT
Project Name Job Location
Weatherly Inn 4500 Talbot Rd. S., Renton, WA
Contractor #1 Contact
Rino Construction Mike
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
ESNW Rep.
AK
Project No.
0895.06
Page
1/1
Report No.
120
Time On Site
Time Off Site
Date
Day of Week
Wed
7:45 AM;
10:30 AM;
1/29/20
2:30 PM
4:00 PM
Travel Time
Weather
1.25 Hr. RT (x2)
40s0F, Overcast
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC W1 3
Project Manager I
Reviewed
Ray
Project No Permit No.
At the client's request, ESNW rep was onsite to observe or test cut slopes, storm line backfill, sewer discharge,
test pH of stormwater and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over -steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V)
Storm Line Backfill
Rep observed contractor use a medium sized excavator to excavate and install the storm line. Rep observed
contractor install a 12" corrugated pipe at the toe of the excavation (W2'xD4') embedded in a 12" lift pea gravel.
Rep will return to test compaction of backfill when conditions have improved.
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a pH level of
6.5.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater In the three south end baker tanks rep observed a pH of
6.5, rep observed that contractor added dry ice to lower the pH level Rep observed that pH level was contained
onsite and that stormwater pH level in street was in compliance of required pH level at 6.5/7 pH. Rep
recommended that contractor add stormwater filtration system to increase volume of discharge Rep met with
Accrete reps to discuss the plan of stormwater discharge moving forward.
ESNW rep will return to observe earthwork activities when requested by client
-T-
Andrew Kimn, Senior Technician, 206-430-9183
M Earth Solutions NWILL
15365 NE 90" Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 1 Fax (425) 449-4711
www esnw com
DAILY FIELD REPORT
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
[Areapproved plans/permits on site?
Supplementary Report:
ESNW Rep.
Project No
Page Report No.
AK
0895.06
1/1 121
Time On Site
Time Off Site
Date Day of Week
Thursday
9:30 AM
10:45 AM
1 /30/20
Travel Time Weather
1.25 Hr. RT 40s0F, Overcast
Job Location
4500 Talbot Rd. S., Renton, WA
Mike
Contact
Project No
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC
Project Manager I Reviewed
Ray
Permit No.
At the client's request, ESNW rep was onsite to observe or test cut slopes, sewer discharge, water line backfill,
test pH of stormwater and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over -steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 mI) after testing water for one hour. Rep took PH test and found water suitable for discharge at a pH level of
6.5.
Water Line Backfill
Rep observed contractor prepping water line for thrust block pours throughout the site
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In two south end baker tanks rep observed a pH of 6.5, rep
observed that contractor added dry ice to lower the pH level. Rep observed that pH level was contained onsite
and that stormwater pH level in street was in compliance of required pH level at 6 5/7 pH. Rep recommended that
contractor add stormwater filtration system to increase volume of discharge Rep met with Accrete reps to discuss
the plan of stormwater discharge moving forward.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
t t
Earth Solutions NWLLc
15365 NE 90"' Street, Suite 100
Redmond, WA 98052
ESNW Rep.
AK
Project No.
0895.06
Page
1/1
Report No.
122
Time On Site
Time Off Site
Date
Da Y of Week
Main (425) 449-4704 1 Fax (425) 449-4711
Friday
www esnw com
10:30 AM
11:30 AM
1 /31 /20
DAILY FIELD REPORT
Weather
Travel Time
1.25 Hr. RT
40sOF, Overcast
Project Name
Job Location
Client/Owner
Weatherly Inn
4500 Talbot Rd.
Contact
Mike
S., Renton, WA
J
RJ Development,
Field Supervisor
LAC
LLC
Reviewed
Contractor #1
Rino Construction
Contractor #2
Contact
Project Manager
Reviewed
Ray
Are approved plans/permits on site?
Project No
Permit No.
Supplementary Report:
At the client's request, ESNW rep was onsite to observe or test cut slopes, sewer discharge and earthwork
activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over -steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a pH level of
6.5.
ESNW rep will return to observe earthwork activities when requested by cliel
Andrew Kimn, Senior Technician, 206-430-9183