HomeMy WebLinkAbout0895.06 DFR 172-174.pdfEarth Solutions NW, LLC
LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development Date: May 29, 2020
401 Central Street SE ESNW No.: ES- 895.06
Olympia, WA 98501 Project: Weatherly Inn
Attn: Mr. Duane Meyer
Email: duane@accrete.build
No. of
Copies Date Description
1 5/11-5/13/20 Daily Field Report(s) # 172-174
Comments:
CC:
1: John Wilson ATTN: johnw@rinocon.com
2: Mark Richardson ATTN: mark@accrete.build
3: Jeff Bennett ATTN: jeffb@accrete.build
4: Jennifer Vogele ATTN: jennifer@accrete.build
5: Jonathan Chavez ATTN: jchavez@rentonwa.gov
6: Joe W ATTN: joew@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 172
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 5/11/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the north slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation.
Footing Backfill
Rep observed contractor use a medium sized excavator to backfill with native brown silty sand with gravel material.
Rep observed contractor place 12” lifts of native soil and compact with a jumping jack (or a hoe pack when able).
Pea gravel was placed on top of the compacted footing backfill and a vapor barrier was installed over the pea
gravel in preparation for slab pouring. Rep took compaction tests on backfill and observed material to be suitably
dense for slab support (at least 95% of its maximum dry density of 133.1 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Fig. 1 Excavator placing pea gravel on top of compacted footing backfill
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 172
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 5/11/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Footing Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
182 See map for approximate location -1 SG 5 133.1 9.89 127.2 95
183 See map for approximate location -1 SG 5 133.1 10.11 128.2 96
184 See map for approximate location -1 SG 5 133.1 11.10 125.9 95
185 See map for approximate location -1 SG 5 133.1 10.25 126.1 95
Fig. 2 Approximate location of compaction tests on footing backfill
2/2
183 182 184 185
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 173
Time On Site Time Off Site Date Day of Week
12:30 PM 1:30 PM 5/12/20 Tuesday
Travel Time Weather
1.00Hr. RT 40s, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the north slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Fig. 1 Pea gravel course in footing trench
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 174
Time On Site Time Off Site Date Day of Week
12:30 PM 1:00 PM 5/13/20 Wednesday
Travel Time Weather
1.00Hr. RT 50s, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991