HomeMy WebLinkAbout0895.06 DFR 175-179.pdfEarth Solutions NW, LLC
LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development Date: June 2, 2020
401 Central Street SE ESNW No.: ES- 895.06
Olympia, WA 98501 Project: Weatherly Inn
Attn: Mr. Duane Meyer
Email: duane@accrete.build
No. of
Copies Date Description
1 5/14-5/21/20 Daily Field Report(s) # 175-179
Comments:
CC:
1: John Wilson ATTN: johnw@rinocon.com
2: Mark Richardson ATTN: mark@accrete.build
3: Jeff Bennett ATTN: jeffb@accrete.build
4: Jennifer Vogele ATTN: jennifer@accrete.build
5: Jonathan Chavez ATTN: jchavez@rentonwa.gov
6: Joe W ATTN: joew@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 175
Time On Site Time Off Site Date Day of Week
12:30 PM 1:30 PM 5/14/20 Thursday
Travel Time Weather
1.00Hr. RT 50s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall.
Water Main Tie-In
Rep observed City of Renton officials and Rino Construction representatives excavating the area around the water
main to tie-in site utilities. Water main to be backfilled with 5/8’’ minus crushed rock and covered with a steel plate
until backfill.
ESNW rep will return to observe earthwork activities when requested by client
Fig. 1 Footing trenches for cast-in-place walls
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 176
Time On Site Time Off Site Date Day of Week
12:30 PM 1:30 PM 5/18/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall. Rep observed footings had been poured in part of the footing trenches.
Temporary Stormwater Pond
Rep observed temporary stormwater pond immediately South of the site entrance had been filled in with native
material from the main stockpile for export in order to clear space for footing excavation along the East margin of
the site. Contractor relayed that Temporary stormwater pond will be excavated and filled in with 1’ lifts of
compacted native material at a later date after the bulk of the stockpiled material has been exported.
ESNW rep will return to observe earthwork activities when requested by client
Fig. 1 Footing trenches for cast-in-place walls with concrete poured
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 177
Time On Site Time Off Site Date Day of Week
11:45 AM 12:15 PM 5/19/20 Tuesday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe slope stability and test stormwater pH
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. The baker tank was not filled and did not require sewer
discharge. Rep observed that pH level was contained onsite.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 178
Time On Site Time Off Site Date Day of Week
12:00 PM 12:30 PM 5/20/20 Wednesday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade and slope stability.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall. Rep observed footings had been poured in part of the footing trenches.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 179
Time On Site Time Off Site Date Day of Week
1:00 PM 1:30 PM 5/21/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade and slope stability.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall. Rep observed footings had been poured in part of the footing trenches. Contractor
relayed that backfill of the 8’x8’x12’ footing with 3’ of crushed rock and native material to occur 5/22/20.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1