LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development
401 Central Street SE
Olympia, WA 98501
Date: August 6, 2020
ESNW No.: ES- 895.06
Project: Weatherly Inn
Attn: Mr. Duane Meyer
Email: duane@accrete.build
No. of
Copies Date Description
1 6/15-7/13/20 Daily Field Report(s) # 191-198 & 200-204
Comments:
CC:
1: John Wilson ATTN: johnw@rinocon.com
2: Mark Richardson ATTN: mark@accrete.build
3: Jeff Bennett ATTN: jeffb@accrete.build
4: Jennifer Vogele ATTN: jennifer@accrete.build
5: Jonathan Chavez ATTN: jchavez@rentonwa.gov
6: Joe W ATTN: joew@accrete.build
7: Roxanne Caballero ATTN: roxanne@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 191
Time On Site Time Off Site Date Day of Week
11:30 AM 12:00 PM 6/15/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
1/1
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cast in place wall footing backfill and slope stability.
Footing Excavation
ESNW Rep observed contractor placing form boards for cast in place walls footings. While onsite, rep used a ½”
steel t-probe and observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed wall.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig. 1 Cast in place wall footing form boards.
Jackson Lundgren Field Technician 206-468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 192
Time On Site Time Off Site Date Day of Week
11:30 AM 12:30 PM 6/16/20 Tuesday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
1/1
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cast in place wall footing backfill and slope stability.
Footing Excavation
ESNW Rep observed contractor placing crushed rock basecourse in 3’ deep trenches for cast in place wall
footings. While onsite, rep used a ½” steel t-probe and observed the footing subgrade to be very dense, firm,
unyielding, and suitable for support of the proposed wall.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig. 1 Crushed rock basecourse in cast in place wall footing trench
Jackson Lundgren Field Technician 206-468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 193
Time On Site Time Off Site Date Day of Week
11:45 AM 12:45 PM 6/17/20 Wednesday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
1/1
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cast in place wall footing backfill and slope stability.
Footing Excavation
ESNW Rep observed contractor placing form boards for cast in place walls footings. While onsite, rep used a ½”
steel t-probe and observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed wall.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 194
Time On Site Time Off Site Date Day of Week
9:30 AM 1:30 PM 6/18/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water main backfill and observe slope stability.
Water Main Backfill
ESNW Rep observed contractor excavating to 9’ for water main connection. Rep observed contractor backfill with
crushed recycled concrete 1 ¼’’ minus material . While onsite, rep used a ½” steel t-probe and observed the
subgrade to be very dense, firm, unyielding, and suitable for support of the proposed water main connection. Rep
observed 1’ lifts of native material compacted with a jumping jack to grade. ESNW rep observed that the
contractor had achieved minimum compaction standards of 95% or greater in areas tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Water main tie in backfilled with 1 ¼’’ minus crushed concrete
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 194
Time On Site Time Off Site Date Day of Week
9:30 AM 1:30 PM 6/18/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Water Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
192 See map -8’ SG 7 120.2 15.28 116.5 97
193 See map -6’ SG 7 120.2 16.84 117.8 98
194 See map -4’ SG 7 120.2 16.14 115.9 96
195 See map -2’SG 7 120.2 15.26 116.2 96
196 See map -1’ SG 7 120.2 14.22 114.8 95
197 See map SG 7 120.2 13.98 117.1 97
Fig. 2 Approximate location of compaction tests 192-197 on water main backfill
192-197
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 195
Time On Site Time Off Site Date Day of Week
11:30 AM 12:15 PM 6/22/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
1/1
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cast in place wall footing backfill and slope stability.
Footing Excavation
ESNW Rep observed contractor placing form boards for cast in place walls footings. While onsite, rep used a ½”
steel t-probe and observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed wall.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 196
Time On Site Time Off Site Date Day of Week
11:15 AM 12:15 PM 6/23/20 Tuesday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
1/1
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cast in place wall footing excavation and slope stability.
Footing Excavation
ESNW Rep observed contractor placing form boards for cast in place walls footings. While onsite, rep used a ½”
steel t-probe and observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed wall.
Water Main Tie-In
ESNW Rep observed contractor excavating a trench for a shallow water main connection. Rep observed subgrade
to be very dense, firm, unyielding, and suitable for support of the proposed water main junction.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 197
Time On Site Time Off Site Date Day of Week
1:15 PM 2:00 PM 6/25/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
1/1
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cast in place wall footing excavation and slope stability.
Footing Excavation
ESNW Rep observed contractor placing form boards for cast in place walls footings. While onsite, rep used a ½”
steel t-probe and observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed wall.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 198
Time On Site Time Off Site Date Day of Week
2: 0 PM 3:30 PM 6/29/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test footing backfill and observe slope stability.
Footing Backfill
ESNW Rep observed contractor backfill trenches for cast in place walls footings. Rep observed contractor backfill
with native brown silty sand with gravel material. While onsite, rep used a ½” steel t-probe and observed the
footing subgrade to be very dense, firm, unyielding, and suitable for support of the proposed footing. Rep observed
1’ lifts of native material compacted with a hoe pack and jumping jack to grade. ESNW rep observed that the
contractor had achieved minimum compaction standards of 95% or greater in areas tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06
Time On Site Time Off Site Date Day of Week
2: 0 PM 3:30 PM 6/29/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Footing Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
202 See map -1’ SG 5 133.1 11.15 128.1 96
203 See map -1’ SG 5 133.1 10.56 126.2 95
204 See map -1’ SG 5 133.1 11.11 128.6 96
205 See map SG 5 133.1 9.59 127.7 95
Fig. 1 Approximate location of compaction tests 202-205 on footing backfill
202-205
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 200
Time On Site Time Off Site Date Day of Week
4:45 PM 5:00 PM 7/6/20 Monday
Travel Time Weather
1.25 Hr. RT 70soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe slab backfill, water line backfill and earthwork activities.
Slab Backfill
While onsite, rep observed contractor use a medium sized excavator to place material for slab backfill. Rep
observed contractor place native gray silty sand with gravel material for the slab. Rep will return tomorrow, July
7, 2020, to observe and test the compaction of the slab backfill.
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8’xL8’xD5’) at the southwest corner of the site. Rep observed that excavation was intended for the
water line tie in. Contractor expressed plans to continue water line backfill tomorrow.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 201
Time On Site Time Off Site Date Day of Week
2:45 PM 3:45 PM 7/7/20 Tuesday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe slab backfill, water line backfill and earthwork activities.
Slab Backfill
While onsite, rep observed contractor use a small sized excavator to place material for slab backfill. Rep observed
contractor place native gray silty sand with gravel material for the slab in 6” lifts and compaction with a jumping
jack. Rep took compaction tests and observed material to be adequate of at least 95% of its maximum dry density
(130.7 lbs./cu. ft.).
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water line at the
southwest corner of the site. Contractor expressed plans to continue water line backfill tomorrow, July 8, 2020.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 21
Time On Site Time Off Site Date Day of Week
2:45 PM 3:45 PM 7/7/20 Tuesday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Slab Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
210 See map for approximate location SG 1 130.7 10.3 124.2 95
211 See map for approximate location SG 1 130.7 11.1 123.8 95
210
2/2
211
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 202
Time On Site Time Off Site Date Day of Week
9:15 AM;
10:30 AM
9:45 AM;
1:00 PM 7/9/20 Thursday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
/2
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water line backfill and earthwork activities.
Water Line Backfill
While onsite, rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water
line at the southwest and northwest corner of the site. Rep observed trench lines to be W4’xD7’. Rep observed
contractor use a medium sized excavator to place native material in loose 12”-18” lifts and compact with a hoe
pack. Rep took compaction tests and observed material to be adequate of at least 95% of its maximum dry density
(130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
ϭͬϮ
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 202
Time On Site Time Off Site Date Day of Week
9:15 AM;
10:30 AM
9:45 AM;
1:00 PM 7/9/20 Thursday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
2/2
Test
Number
Test Location
(Water Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
212 See map for approximate location -4’1 130.7 12.1 124.3 95
213 See map for approximate location -2’1 130.7 10.3 124.6 95
214 See map for approximate location SG 1 130.7 9.6 124.0 95
215 See map for approximate location -4’1 130.7 11.0 123.6 95
216 See map for approximate location -2’1 130.7 11.5 123.8 95
217 See map for approximate location SG 1 130.7 11.3 124.2 95
212-214
214-217
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 203
Time On Site Time Off Site Date Day of Week
3:00 PM 3:15 PM 7/10/20 Friday
Travel Time Weather
1.25 Hr. RT 70soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water line backfill and earthwork activities.
Water Line Backfill
While onsite, rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water
line at the southwest corner of the site. Rep observed trench lines to be W4’xD7’. Rep observed contractor and
city inspector test the water line onsite. Contractor expressed plans to continue working on water line tie-in and
backfill on Monday, July 13, 2020. Rep will return on Monday to observe and test compaction of the water line as
needed.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 204
Time On Site Time Off Site Date Day of Week
9:45 AM 10:15 AM 7/13/20 Monday
Travel Time Weather
1.25 Hr. RT 60soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water line backfill and earthwork activities.
Water Line Backfill
While onsite, rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water
line at the southwest corner of the site. Rep observed trench lines to be W4’xD7’. Rep observed contractor and
city inspector test the water line onsite. Contractor expressed plans to continue working on water line tie-in and
backfill tomorrow, July 14, 2020. Rep will return to observe and test compaction of the water line as needed.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183