HomeMy WebLinkAbout0895.06 DFR 199&210-220.pdfEarth Solutions NW, LLC
LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development
401 Central Street SE
Olympia, WA 98501
Date: September 2, 2020
ESNW No.: ES- 895.06
Project: Weatherly Inn
Attn: Mr. Duane Meyer
Email: duane@accrete.build
No. of
Copies Date Description
1 7/2-8/27/20 Daily Field Report(s) # 199 & 211-221
Comments:
CC:
1: John Wilson ATTN: johnw@rinocon.com
2: Mark Richardson ATTN: mark@accrete.build
3: Jeff Bennett ATTN: jeffb@accrete.build
4: Jennifer Vogele ATTN: jennifer@accrete.build
5: Jonathan Chavez ATTN: jchavez@rentonwa.gov
6: Joe W ATTN: joew@accrete.build
7: Roxanne Caballero ATTN: roxanne@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 199
Time On Site Time Off Site Date Day of Week
12:00 PM 2:30 PM
7/2/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test footing backfill and observe slope stability.
Footing Backfill
ESNW Rep observed contractor backfill trenches for cast in place walls footings. Rep observed contractor backfill
with native brown silty sand with gravel material. While onsite, rep used a ½” steel t-probe and observed the
footing subgrade to be very dense, firm, unyielding, and suitable for support of the proposed footing. Rep observed
1’ lifts of native material compacted with a hoe pack and jumping jack to grade. ESNW rep observed that the
contractor had achieved minimum compaction standards of 95% or greater in areas tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Water main 45o section connecting to water main junction in Talbot Road.
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 199
Time On Site Time Off Site Date Day of Week
12:00 PM 2:30 PM
7/2/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Footing Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
206 See map -1’ SG 5 133.1 9.96 128.4 96
207 See map -1’ SG 5 133.1 10.34 127.1 95
208 See map SG 5 133.1 11.48 128.2 96
209 See map SG 5 133.1 13.12 126.9 95
Fig. 2 Approximate location of compaction tests 206-209 on footing backfill
206-209
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 210
Time On Site Time Off Site Date Day of Week
11:30 AM 1:00 PM 7/27/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test roof drain backfill and slope stability.
Roof Drain Trench
ESNW rep observed contractor using a medium sized excavator to excavate a 2’ deep 250’ long trench along the
eastern margin to the building. ESNW rep observed contractor placing an 8’’ drain pipe in the trench. Rep used a
½” steel t-probe and observed the subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed roof drains. Rep observed contractor backfill with 18’’ of pea gravel then native material to grade. ESNW
rep observed that the contractor had achieved minimum compaction standards of 95% or greater in areas
tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 210
Time On Site Time Off Site Date Day of Week
11:30 AM 1:00 PM 7/27/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Roof drain
Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
221 See map SG 6 133.0 6.78 126.2 95
222 See map SG 6 133.0 7.21 128.8 97
223 See map SG 6 133.0 7.16 126.9 95
224 See map SG 6 133.0 7.44 127.6 96
Fig. 1 Approximate location of compaction tests 221-224 on water main backfill
221-224
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 211
Time On Site Time Off Site Date Day of Week
11:00 AM 12:45 PM 7/29/20 Wednesday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe roof drain trench excavation and cut slopes.
Roof Drain Trench
ESNW rep observed contractor using a medium sized excavator to excavate 100’ of a 2’ deep roof drain trench
along the Eastern perimeter of the upper building. ESNW rep observed contractor placing an 8’’ drain pipe. Rep
used a ½” steel t-probe and observed the subgrade to be very dense, firm, unyielding, and suitable for support of
the proposed roof drains.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 212
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 7/30/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water main backfill and slope stability.
Water Main Backfill
ESNW Rep observed contractor excavating to 5’ for water main connection. Rep observed contractor backfill with
crushed recycled concrete 1 ¼’’ minus material . While onsite, rep used a ½” steel t-probe and observed the
subgrade to be very dense, firm, unyielding, and suitable for support of the proposed water main connection. Rep
observed 1’ lifts of crushed recycled concrete 1 ¼’’ minus material compacted with a jumping jack to grade. ESNW
rep observed that the contractor had achieved minimum compaction standards of 95% or greater in areas
tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Water main tie in backfilled with 1 ¼’’ minus crushed concrete
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 212
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 7/30/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Water Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
225 See map -3’ SG 7 120.2 13.86 117.8 98
226 See map -2’ SG 7 120.2 13.40 118.9 99
227 See map -1’ SG 7 120.2 14.10 117.6 98
228 See map SG 7 120.2 13.68 118.2 98
Fig. 2 Approximate location of compaction tests 225-228 on water main backfill
225-228
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 213
Time On Site Time Off Site Date Day of Week
11:00 AM 12:00 PM 7/31/20 Friday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe water main connection and cut slopes.
Water Main Backfill
ESNW Rep observed contractor working on water main connection to the site in Talbot road. Contractor relayed
that after pressure testing is completed the trench will be backfilled with 1 ¼’’ minus recycled crushed concrete
material. Rep used a ½” steel t-probe and observed the subgrade to be very dense, firm, unyielding, and suitable
for support of the proposed water main connection.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 214
Time On Site Time Off Site Date Day of Week
11:15 AM 12:45 PM 8/4/20 Tuesday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe roof drain trench excavation and cut slopes.
Roof Drain Trench
ESNW rep observed contractor using a medium sized excavator to excavate 200’ of a 2’ deep roof drain trench
along the perimeter of the courtyard in the upper building. ESNW rep observed contractor placing an 8’’ drain pipe
and backfilling with a jumping jack to grade. Rep used a ½” steel t-probe and observed the subgrade to be very
dense, firm, unyielding, and suitable for support of the proposed roof drains.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Courtyard with compacted backfill in roof drain trenches
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
1 of 3
Report No.
215
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/7/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
•Buffer Zones around Sensitive Areas
•Silt Fence
G N Silt fence working as intended
2. Establish Construction Access
•Fabric; Quarry Spalls
•Wheel Wash
•Sweeper Truck
G N Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
3. Control Flow Rates
•Stormwater Vault or Facility
•Straw Wattles
•Check Dams
G N Add check dams and straw wattles as needed to
slow stormwater onsite
4. Install Sediment Controls
•Silt Fence
•Straw Bale Barriers
•Vegetation
•Straw
•Sediment Ponds, Traps & Filters
•Treatment
•Sediment Pond (Temp. or Perm.)
•Water Truck
G N Add straw as needed throughout the site, 2”
minimum
5. Stabilize Soils
•Nets & Blankets
•Mulch, Bark & Rock
•Hydroseeding; Grass
•Plastic Sheeting
•Straw Stockpiles
•Stockpiles
•PAM
G N
6. Protect Slopes
•Benching; Track-Walking
•Pipe Slope Drains
•Plastic Sheeting; Anchors
G N
7. Protect Drain Inlets
•Catch Basin Inserts
•Gutter; Road
G N CB inserts working as intended
8. Stabilize Channels and Outlets
•Channel Lining
•Check Dam
•Outlet Protection
•Nets and Blankets
N/A N/A N/A
9. Control Pollutants
•Chemical Storage Area Covered
•Concrete Handling
N/A N/A N/A
10. Control Dewatering N/A N/A N/A
11. Maintain BMPs G N See recommended notes
12.Maintain SWPPP & Site Logbook G N Available upon request
13. Protect Low-Impact Development (LID BMPs)
•Bioretention Rain Garden Facilities
•Permeable Pavement N/A N/A N/A
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
2 of 3
Report No.
215
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/7/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Monitoring, Records & Recommendations
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? Yes No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Ongoing)
Date
(If Completed)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2” straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: _70sO F, Clear____________________
Precipitation since last inspection (approximate): 0.12______ inches
Precipitation in the last 24 hours (approximate): _0.12______ inches
Was water quality sampling part of this inspection? Yes No
If “Yes”:
•Record results in the table below.
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, “cloudiness”, discoloration, or oil sheen, if
present: ____N/A________________________________________________________________________________________
•Hanna Turbidity Meter # ____________________
Monitoring Location Turbidity
(NTU) pH Notes
Is the site in compliance with the SWPPP and the permit requirements? Yes No
If “No”:
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology?Yes No
•Should the SWPPP be modified?Yes No
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Inspector Name: Jackson Lundgren CESCL Number: CESCL-EF8183892 Inspection Date: 8/7/20
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
3 of 3
Report No.
215
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/7/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Discharge Monitoring Location
Parking area
Silt fence around site perimeter
Wheel wash and quarry spalls
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 216
Time On Site Time Off Site Date Day of Week
12:00 PM 1:30 PM 8/13/20 Thursday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test cast in place wall backfill and observe slope
stability.
Wall Backfill
ESNW Rep observed contractor backfill around cast in place wall. Rep observed contractor backfill with native
brown silty sand with gravel material. While onsite, rep used a ½” steel t-probe and observed the subgrade to be
very dense, firm, unyielding, and suitable for support of the wall. Rep observed 1’ lifts of native material compacted
with a jumping jack to grade. ESNW rep observed that the contractor had achieved minimum compaction
standards of 95% or greater in areas tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Backfill around cast in place wall
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 216
Time On Site Time Off Site Date Day of Week
12:00 PM 1:30 PM 8/13/20 Thursday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Wall Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
229 See map -5 SG 5 133.1 10.98 127.6 96
230 See map -5’ SG 5 133.1 11.16 126.9 95
231 See map -3’ SG 5 133.1 9.87 128.1 96
232 See map -3’ SG 5 133.1 10.44 127.7 96
Fig. 2 Approximate location of compaction tests 229-232 on wall backfill
229-232
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
1 of 3
Report No.
216A
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/13/20
Day of Week
Thursday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
•Buffer Zones around Sensitive Areas
•Silt Fence
G N Silt fence working as intended
2. Establish Construction Access
•Fabric; Quarry Spalls
•Wheel Wash
•Sweeper Truck
G N Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
3. Control Flow Rates
•Stormwater Vault or Facility
•Straw Wattles
•Check Dams
G N Add check dams and straw wattles as needed to
slow stormwater onsite
4. Install Sediment Controls
•Silt Fence
•Straw Bale Barriers
•Vegetation
•Straw
•Sediment Ponds, Traps & Filters
•Treatment
•Sediment Pond (Temp. or Perm.)
•Water Truck
G N Add straw as needed throughout the site, 2”
minimum
5. Stabilize Soils
•Nets & Blankets
•Mulch, Bark & Rock
•Hydroseeding; Grass
•Plastic Sheeting
•Straw Stockpiles
•Stockpiles
•PAM
G N
6. Protect Slopes
•Benching; Track-Walking
•Pipe Slope Drains
•Plastic Sheeting; Anchors
G N
7. Protect Drain Inlets
•Catch Basin Inserts
•Gutter; Road
G N CB inserts working as intended
8. Stabilize Channels and Outlets
•Channel Lining
•Check Dam
•Outlet Protection
•Nets and Blankets
N/A N/A N/A
9. Control Pollutants
•Chemical Storage Area Covered
•Concrete Handling
N/A N/A N/A
10. Control Dewatering N/A N/A N/A
11. Maintain BMPs G N See recommended notes
12.Maintain SWPPP & Site Logbook G N Available upon request
13. Protect Low-Impact Development (LID BMPs)
•Bioretention Rain Garden Facilities
•Permeable Pavement N/A N/A N/A
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
2 of 3
Report No.
216A
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/13/20
Day of Week
Thursday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Monitoring, Records & Recommendations
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? Yes No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Ongoing)
Date
(If Completed)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2” straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: _70sO F, Clear____________________
Precipitation since last inspection (approximate): 0.00______ inches
Precipitation in the last 24 hours (approximate): _0.00______ inches
Was water quality sampling part of this inspection? Yes No
If “Yes”:
•Record results in the table below.
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, “cloudiness”, discoloration, or oil sheen, if
present: ____N/A________________________________________________________________________________________
•Hanna Turbidity Meter # ____________________
Monitoring Location Turbidity
(NTU) pH Notes
Is the site in compliance with the SWPPP and the permit requirements? Yes No
If “No”:
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology?Yes No
•Should the SWPPP be modified?Yes No
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Inspector Name: Jackson Lundgren CESCL Number: CESCL-EF8183892 Inspection Date: 8/13/20
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
3 of 3
Report No.
216A
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/13/20
Day of Week
Thursday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Discharge Monitoring Location
Parking area
Silt fence around site perimeter
Wheel wash and quarry spalls
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 217
Time On Site Time Off Site Date Day of Week
12:00 PM 1:30 PM 8/14/20 Friday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test cast in place wall backfill and observe slope
stability.
Wall Backfill
ESNW Rep observed contractor backfill around cast in place wall. Rep observed contractor backfill with native
brown silty sand with gravel material. While onsite, rep used a ½” steel t-probe and observed the subgrade to be
very dense, firm, unyielding, and suitable for support of the wall. Rep observed 1’ lifts of native material compacted
with a jumping jack to grade. ESNW rep observed that the contractor had achieved minimum compaction
standards of 95% or greater in areas tested.
Water Main Backfill
ESNW Rep observed contractor working on water main connection to the site in the SE corner. Contractor relayed
that after pressure testing is completed the trench will be backfilled with 1 ¼’’ minus recycled crushed concrete
material. Rep used a ½” steel t-probe and observed the subgrade to be very dense, firm, unyielding, and suitable
for support of the proposed water main connection.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Poured thrust block for water main connection
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 217
Time On Site Time Off Site Date Day of Week
12:00 PM 1:30 PM 8/14/20 Friday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Wall Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
233 See map -3 SG 5 133.1 11.08 126.2 95
234 See map -3’ SG 5 133.1 10.96 126.9 95
235 See map -3’ SG 5 133.1 11.18 127.1 95
Fig. 2 Approximate location of compaction tests 233-235 on wall backfill
233-235
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 218
Time On Site Time Off Site Date Day of Week
10:30 AM 11:30 AM 8/17/20 Monday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test cast in place wall backfill and observe slope
stability.
Wall Backfill
ESNW Rep observed contractor backfill around cast in place wall. Rep observed contractor backfill with native
brown silty sand with gravel material. While onsite, rep used a ½” steel t-probe and observed the subgrade to be
very dense, firm, unyielding, and suitable for support of the wall. Rep observed 1’ lifts of native material compacted
with a jumping jack to grade. ESNW rep observed that the contractor had achieved minimum compaction
standards of 95% or greater in areas tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Backfill around cast in place wall
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 218
Time On Site Time Off Site Date Day of Week
10:30 AM 11:30 AM 8/17/20 Monday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Wall Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
236 See map -1 SG 5 133.1 11.10 126.2 95
237 See map -1’ SG 5 133.1 10.68 127.2 95
238 See map SG 5 133.1 10.44 128.4 96
239 See map SG 5 133.1 10.78 126.7 95
Fig. 2 Approximate location of compaction tests 236-239 on wall backfill
236-239
2/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 219
Time On Site Time Off Site Date Day of Week
9:00 AM 11:30 AM 8/18/20 Tuesday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe water main connection to site and observe slope stability.
Water Main Backfill
ESNW Rep observed contractor working on water main connection to the site in the SE corner. Contractor relayed
that after pressure testing is completed the trench will be backfilled with 1 ¼’’ minus recycled crushed concrete
material. Rep used a ½” steel t-probe and observed the subgrade to be very dense, firm, unyielding, and suitable
for support of the proposed water main connection.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Fig 1. Water main connection
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 220
Time On Site Time Off Site Date Day of Week
11:30 AM 1:00 PM 8/19/20 Wednesday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test roof drain and wall backfill and slope stability.
Roof Drain Trench
ESNW rep observed contractor using a medium sized excavator to excavate a 2’ deep 250’ long trench along the
eastern margin to the building. ESNW rep observed contractor placing an 8’’ drain pipe in the trench. Rep used a
½” steel t-probe and observed the subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed roof drains. Rep observed contractor backfill with 18’’ of pea gravel then native material to grade. ESNW
rep observed that the contractor had achieved minimum compaction standards of 95% or greater in areas
tested.
Wall Backfill
ESNW Rep observed contractor backfill around cast in place wall. Rep observed contractor backfill with native
brown silty sand with gravel material. While onsite, rep used a ½” steel t-probe and observed the subgrade to be
very dense, firm, unyielding, and suitable for support of the wall. Rep observed 1’ lifts of native material compacted
with a jumping jack to grade. ESNW rep observed that the contractor had achieved minimum compaction
standards of 95% or greater in areas tested.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 220
Time On Site Time Off Site Date Day of Week
11:30 AM 1:00 PM 8/19/20 Wednesday
Travel Time Weather
1.00Hr. RT 70s, Sun
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Roof drain/ Wall
Backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
240 Wall SG 6 133.0 6.78 126.2 95
241 Wall SG 6 133.0 7.21 128.8 97
242 Roof Drain SG 6 133.0 7.16 126.9 95
243 Roof Drain SG 6 133.0 7.44 127.6 96
Fig. 1 Approximate location of compaction tests 242-243 on water main backfill
240-241
2/2
242-243
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
1 of 3
Report No.
220A
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/19/20
Day of Week
Wednesday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1. Preserve Vegetation; Mark Clearing Limits
•Buffer Zones around Sensitive Areas
•Silt Fence
G N Silt fence working as intended
2. Establish Construction Access
•Fabric; Quarry Spalls
•Wheel Wash
•Sweeper Truck
G N Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
3. Control Flow Rates
•Stormwater Vault or Facility
•Straw Wattles
•Check Dams
G N Add check dams and straw wattles as needed to
slow stormwater onsite
4. Install Sediment Controls
•Silt Fence
•Straw Bale Barriers
•Vegetation
•Straw
•Sediment Ponds, Traps & Filters
•Treatment
•Sediment Pond (Temp. or Perm.)
•Water Truck
G N Add straw as needed throughout the site, 2”
minimum
5. Stabilize Soils
•Nets & Blankets
•Mulch, Bark & Rock
•Hydroseeding; Grass
•Plastic Sheeting
•Straw Stockpiles
•Stockpiles
•PAM
G N
6. Protect Slopes
•Benching; Track-Walking
•Pipe Slope Drains
•Plastic Sheeting; Anchors
G N
7. Protect Drain Inlets
•Catch Basin Inserts
•Gutter; Road
G N CB inserts working as intended
8. Stabilize Channels and Outlets
•Channel Lining
•Check Dam
•Outlet Protection
•Nets and Blankets
N/A N/A N/A
9. Control Pollutants
•Chemical Storage Area Covered
•Concrete Handling
N/A N/A N/A
10. Control Dewatering N/A N/A N/A
11. Maintain BMPs G N See recommended notes
12.Maintain SWPPP & Site Logbook G N Available upon request
13. Protect Low-Impact Development (LID BMPs)
•Bioretention Rain Garden Facilities
•Permeable Pavement N/A N/A N/A
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
2 of 3
Report No.
220A
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/19/20
Day of Week
Wednesday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Monitoring, Records & Recommendations
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? Yes No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Ongoing)
Date
(If Completed)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2” straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: _70sO F, Clear____________________
Precipitation since last inspection (approximate): 0.02______ inches
Precipitation in the last 24 hours (approximate): _0.00______ inches
Was water quality sampling part of this inspection? Yes No
If “Yes”:
•Record results in the table below.
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, “cloudiness”, discoloration, or oil sheen, if
present: ____N/A________________________________________________________________________________________
•Hanna Turbidity Meter # ____________________
Monitoring Location Turbidity
(NTU) pH Notes
Is the site in compliance with the SWPPP and the permit requirements? Yes No
If “No”:
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology?Yes No
•Should the SWPPP be modified?Yes No
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Inspector Name: Jackson Lundgren CESCL Number: CESCL-EF8183892 Inspection Date: 8/19/20
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
3 of 3
Report No.
220A
Time On Site
10:30 AM
Time Off Site
11:30 AM
Date
8/19/20
Day of Week
Wednesday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Discharge Monitoring Location
Parking area
Silt fence around site perimeter
Wheel wash and quarry spalls