Applicant Information
Project Address 2727 Mountain View Ave N. Renton, WA 98056
Parcel Number: 334210-4050
Applicant: Seaborn Pile Driving Company, 1080 W Ewing St Building B, Seattle, WA 98119 206-236-
1700
Property Owner: Sunday Heily – 2727 Mountain View Ave N. Renton, WA 98056
Legal Description: HILLMANS LK WN GARDEN OF EDEN #1 LOT 88 TGW SELY 1/2
LOT 87 MEAS MIDWAY BTWN NWLY & SELY LNS SD LOT 87 & SH LDS ADJ
Description of Work: Normal maintenance including repair of 7 support piles, removal of 3 existing wood
mooring piles, driving 3 new steel mooring piles and installing new grated surface.
Job specific comments
Purpose
The proposed dock is to provide for safe boat moorage and safe water recreational activities for a single
family residence.
Habitat Enhancement
The proposed planting plan has been designed to mitigate for the existing and proposed pier.
Water Quality
In order to prevent debris from entering the lake during the demolition stage of the project, a containment
boom will surround the crane barge and work area.
Mitigation
Shoreline Plantings: The shoreline plantings have been designed to provide the spread of tree and shrub
nutrients into the adjacent waters of Lake Washington.
Fully grated deck: The proposed dock will have a fully grated deck to provide light penetration below
the dock where there is no light penetration with the existing structure.
Contractor: Seaborn Pile Driving Company License #: SEABOPD942CG
Address: 1080 W Ewing St, Bldg B. Seattle, WA. 98119
Phone: 206.236.1700 Mobile: 253-569-0300 Fax: 206.236.2700
Contact: Kelsey Meyer Email: permits@seabornpiledriving.com
2
Construction Narrative
Mobilization
Mobilize crew, crane barge, supply and debris barges, and materials on site
Pile Repair Standard Pile Stub Method
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and
debris that may be generated during construction.
2. Cut the pile below the waterline.
3. Using a steel can pile attach it to the exiting stub with galvanized steel thru-bolts
and nuts.
4. Confirm the pilings are straight and solid.
5. Cut the pilings to elevation.
6. Attach the new pile repair to the existing pile cap.
7. Clean the work area and remove the silt fence/boom.
Mooring Pile Removal
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and
debris that may be generated during construction.
2. Attach a chain to the base of the existing pile.
3. Using the crane, pull the pile from the lakebed and place on the debris barge for
disposal in an approved upland disposal site.
4. Clean the work area and remove the silt fence/boom.
Pile Driving
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and
debris that may be generated during construction.
2. Locate the new piles to be driven per the building permit drawings.
3. Using the crane and a vibro-hammer, drive the piles to required refusal.
4. Cut the piles to elevation.
5. Clean the work area and remove the silt fence/boom.
Existing pier removal
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and
debris that may be generated during construction.
2. Mobilize crew, crane barge, supply and debris barges, and materials to the site.
3. Remove the cleats and fenders and set aside for re-installation after the deck is
installed.
4. Demo current dock and load all debris onto the debris barge.
5. Tow the debris barge to the yard and dispose in an approved upland disposal
site.
6. Clean the work area and remove the silt fence/boom.
Dock construction (Rebuild Dock)
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and debris
that may be generated during construction.
2. Install new Doug-Fir pile caps and attach to the piles with a steel plate and thru-bolts.
3
3. Install new Doug-Fir stringers on to the pile caps to support the ThruFlow grating.
4. Install new trim along edges of deck, flush with ThruFlow decking.
5. Install electrical conduit and water lines under the deck along the dock. Wiring and
re-connection to be completed by others.
6. Install the ThruFlow grating with stainless steel screws making sure the screws are
aligned and flush with the surface.
7. Install cedar fascia along side of dock to bottom of cap.
8. Install any boat or PWC lifts.
9. Clean the work area and remove the silt fence/boom.
Structural Notes
General
● All materials, workmanship, design and construction shall conform to the submitted
drawings and the International Building Code.
● The contractor will be responsible for all safety precautions and methods and processes to
perform the designated work.
Design Criteria
● The existing design and construction meets the live load specification of a minimum of
40 PSF.
Materials
All materials used in the construction of the dock will be for use on the water and of the highest quality
available on the market. All materials will conform to the International Building Code.
For example:
● Wood piles and pile stubs. The proposed wood pile stub will be Class B (12” @ 3’ from Butt) –
40’ Douglas Fir pilings per ASTM D-25.
● Steel pile collars – ASTM A53 GrB with Devran 261QC low temperate cure epoxy (16 mils)
finish coated full length.
● Structural Lumber – All lumber will be graded and marked in conformance with WCLIB standard
grading rules.
● Fasteners – All fasteners, bolts, nuts and nails will be hot-dip galvanized.
● Decking – The decking will consist of ThruFlow fiberglass grating which is pet and children
friendly and will provide years of safe and comfortable use.
Preservatives
● All wood preservatives to be state approved and will be applied and fully cured prior to
installation over the water.
● All hardware and fasteners to be hot dipped galvanized.
4
Best Management Practices
1. Above the Water Line Work
1. Seaborn Pile Driving Company will employ one each crane barge, one supply and
one debris barge to complete the scope of work. A tug will tow the barges on and
off the job site.
2. Seaborn Pile Driving Company personnel working in, near or over the water will
at all time wear either USCG approved life vests or work vest as well as hard hats
and safety glasses.
2. Material Handling
1. While at the job site, a floating containment boom will completely surround the
work area.
2. All removed piles and the existing dock structure will be placed on the debris
barge where they will be contained and kept out of the lake.
3. Hazardous Materials
● No hazardous materials will be mixed or stored in or near the water. No cleaning
of materials will be performed in or near the water.
4. Polluting Materials in Water
● Seaborn Pile Driving Company will take extra precautions to ensure materials
don’t fall into or pollute the water. Any material that enters the water will be
removed immediately. Any hazardous material such as oily rags will not be
handled near or over the water.
● A spill kit will be employed on the barges at the job site.
● If any pollutants enter the water, Seaborn Pile Driving Company will contact the
appropriate agencies and report the spill immediately.
5. Materials Disposal
● Seaborn Pile Driving Company will dispose of the rotten wood and pile sections
in an approved legal disposal site in accordance with all applicable laws and
permit requirements.