HomeMy WebLinkAboutSummary of Bidder Inquiries No. 3Page 1 of 2 Summary of Bidders Inquiries No. 3 Lake Washington Loop Trail Project Federal Aid Number: TAP-HLP-1070-008 Date: January 14, 2021 The responses to bidder inquiries, unless incorporated into a formal addendum to the contract, are not part of the contract and are provided for the bidders’ convenience only. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The use of information provided in the responses to bidder inquiries is not to be construed in any way as a waiver of the provisions nor excuse the contractor from full compliance with the contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given and any such subsequent response or addenda should be taken into consideration when submitting a bid for the project. Bidder Inquiry No. 1 When you anticipate this project to begin? Is this a fast track project? City of Renton Response to Bidder Inquiry No. 1 Project will begin first quarter of 2021. Project duration is estimated at 60 working days. Schedule compression techniques were not used to estimate duration. Bidder Inquiry No. 2 Are there any hard deadlines the City is hoping to meet? City of Renton Response to Bidder Inquiry No. 2 No. Bidder Inquiry No. 3 Can you clarify the correct luminaire pole number and construction note for the location shown below on plan sheet IL8.04 please. Luminaire pole #8 is shown on previous plan sheet IL8.03 and there is no construction note #14. Page 2 of 2 Specification section 9-29-24 calls for the service cabinets to be made from galvanized steel and painted but the referenced City Standard plan 122.1 & 122.2 in the same specification section notes the services cabinets are aluminum with a mill finish. Can you confirm which service cabinet material is to be provided. City of Renton Response to Bidder Inquiry No. 3 Intent is for service cabinets to be aluminum with a mill finish. Plan sheet 59 and Special Provision 9- 29-24 will be revised in Addendum 1. Please refer to Addendum No. 1 for clarification. End of Summary of Bidder Inquiries No. 3