HomeMy WebLinkAboutAdmin Report
EXECUTIVE DEPARTMENT
M E M O R A N D U M
DATE: January 25, 2021
TO: Randy Corman, Council President
Members of Renton City Council
FROM: Armondo Pavone, Mayor
Ed VanValey, Chief Administrative Officer
SUBJECT: Administrative Report
• Construction for the Coulon Playground replacement is complete and the
playground opened to the public on Wednesday, January 20. The new play
equipment was chosen based on a community survey conducted in the summer of
2020. The new playground includes many all-abilities components: an all-abilities
see-saw, group swing and individual swings, and two unique climbing structures. The
project is funded by the taxpayers of Washington state through a state direct
legislative appropriation.
• The Sunset Neighborhood Park construction is complete and the park will have a
“virtual grand opening” on Wednesday, January 27, with the park officially opening
to the public on Thursday, January 28. This new 3.2-acre park celebrates a long-
range vision coming to fruition, accomplished through ongoing partnerships,
community involvement, collaboration, and investments. The park will be a
gathering place at the heart of the Sunset area, providing quality-of-life amenities
including: looped pedestrian walkways with pergolas and seating; age appropriate
children’s play areas and fitness equipment with rubberized safety surfacing; plaza
with seating and mist water feature; picnic gazebo and restrooms; art; and a large
lawn for gathering and playing. $5.3 million in outside funding has been invested to
leverage city funding to support this great project!
• Information about preventative street maintenance, traffic impact projects, and
road closures happening this week can be found at http://rentonwa.gov/traffic. All
projects are weather permitting and unless otherwise noted, streets will always
remain open. Preventative street maintenance, traffic impact projects, and road
closures will be at the following locations:
Monday, January 25 through Friday, January 29, 7:00 a.m. to 3:30 p.m.
Intermittent lane closures along Park Avenue North between North 30th Street
and North 32nd Street for the City of Renton Kennydale 320 Reservoir Capital
Improvement Project. Questions may be directed to Joel McCann at 425-757-
9595.
Randy Corman, Council President
Members of Renton City Council
Page 2 of 2
January 25, 2021
Monday, January 25 through Friday, January 29, 7:00 a.m. to 3:30 p.m. Single
lane closure along Wells Avenue South between South 2nd Street and South 3rd
Street for the City of Renton Downtown Streetscape Capital Improvement
Project. Questions may be directed to Kip Braaten at 425-757-9809.
Monday, January 25 through Friday, January 29, nighttime. Possible lane
closures at the intersection of Talbot Road South and South 48th Street due to
utility construction. Questions may be directed to Tom Main at 206-999-1833.
Tuesday, January 26, 8:00 p.m. to 5:00 a.m. South 3rd Street will be closed
between Williams Avenue South and Wells Avenue South to complete a water
line extension.
Ongoing Trail Closure through Winter of 2020. Ripley Lane North Trail closure
just north of the VMAC and the trailhead going north in support the WSDOT I-
405 Renton to Bellevue Widening and Express Toll Lanes Project. Questions may
be directed to Justin Johnson at 425-902-7172, or Kip Braaten at 425-757-9809.