HomeMy WebLinkAboutF_Civil_Construction_Plans_210329_v2DEVELOPMENT ENGINEERINGNathan Janders 04/12/2021Markup LegendREDRequired RevisionsBLUERecommended RevisionsPURPLEAdvisory OnlyGREENItems to be Deleted
5plex
3plex
bathroom
water line running on
the surface, under the
trailers and
underground past the
trailer footprint
sewer line running on
the surface, under the
trailers and
underground past the
trailer footprint.
To be connected to
existing stub and
extended to reach
underside of trailer by
following COR STD
Plan 406.1
Will be removed upon
completion of the
project. Permit
SS20005996
New 1" service line
according to COR
STD Plan 320.1 +
DCVA Valve
downstream.
DEVELOPMENT ENGINEERING
Nathan Janders 04/12/2021
a separate water
permit is required for
water service.
a separate side sewer
permit is required.
a separate plumbing
permit is required for
DCVA and pipe
downstream of meter.