AMENDMENTNO.1TOAGREEMENTFORDESIGN,PERMITTING
ANDCONSTRUCTIONSUPPORTFORCEDARRIVERTRAIL
RELOCATIONANDCEDARRIVERBANKSTABILIZATIONPROJECT
THISAMENDMENT,datedMay17,2021,isbyandbetweentheCityofRenton(the“City”),a
Washingtonmunicipalcorporation,andGeoEngineers,Inc.(“Consultant”),aWashingtonState
corporation.TheCityandtheConsultantarereferredtocollectivelyinthisAmendmentasthe
“Parties.”OncefullyexecutedbytheParties,thisAmendmentiseffectiveasofthelastdate
signedbybothparties.
Whereas,theCityengagedtheservicesoftheConsultantunderAgreementCAGͲ21Ͳ006,dated
December14,2020,toprovidenecessaryservicesforthedesign,permittingandconstruction
supportforCedarRiverTrailrelocationandCedarRiverbankstabilizationproject(referredto
hereinasthe“Agreement”);
Whereas,thePartieswishtoamendtheAgreementtochangethescopeofworkandchangethe
timeforperformanceinordertomoreaccuratelydescribetheprojectgoalsandtomatchthe
projectschedule.
NOWTHEREFORE,itismutuallyagreeduponthatCAGͲ21Ͳ006isamendedasfollows:
1. ScopeofWork:Section1,ScopeofWork,isamendedtorevisewrittendescriptionsof
‘trailrelocation’to‘constructionsitepreparation’and‘temporarytrailbypass,’as
appropriate,andtoremovereferencestopavingthe‘temporarytrailbypass’asspecified
inExhibit“AͲ1”,whichisattachedandincorporatedherein.
2. TimeofPerformance:Section3,TimeofPerformance,isamendedpursuanttothe
schedule(s)setforthinExhibit“BͲ1.”AllWorkshallbeperformedbynolaterthan
December31,2023.
3. AlltermsoftheAgreementnotexplicitlymodifiedhereinshallremaininfullforceand
effectandsuchtermsshallapplytoWorkperformedaccordingtothisAmendmentasif
fullysetforthherein.
INWITNESSWHEREOF,thePartieshavevoluntarilyenteredintothisAmendmentasofthedate
lastsignedbythePartiesbelow.
CAG-21-006, Adden #1-21
PAGE2OF2
CITYOFRENTON
By:_____________________________
GEOENGINEERS,INC.
By:____________________________
ArmondoPavone
Mayor
JoeCallaghan,PWS
Principal
_____________________________
Date
_____________________________
Date
Attest
_____________________________
JasonA.Seth
CityClerk
ApprovedastoLegalForm
By:__________________________
ShaneMoloney
CityAttorney
DĂLJϮϭ͕ϮϬϮϭ
(approved via email from Leslie Clark)
May 24, 2021
1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940
November 6, 2020
City of Renton
Community Services – Parks and Trails
1055 South Grady Way – 5th Floor
Renton, Washington 98057
Attention: Cailin Hunsaker
Subject: Proposal – Cedar River Bank Stabilization Project: Design, Permitting and Construction Support
Renton, Washington
File No. 0693-087-01
INTRODUCTION
Thank you for requesting this proposal from GeoEngineers, Inc. (GeoEngineers) to support the City of
Renton (City) with engineering design and permitting services for the Cedar River Trail Bank Stabilization
Project. The project objective is to stabilize an area of erosion on the left bank of the Cedar River at
approximately River Mile 2.5. The riverbank at this location is on the outside edge of a bend in the river
channel that eroded over a length of approximately 150 feet during the February 8, 2020 storm event.
Erosion from Cedar River floodwaters has damaged the integrity and function of the Cedar River Trail
system by undermining and weakening the trail structure and prism. The City is pursuing funding from
Federal Emergency Management Agency (FEMA) to complete the bank stabilization work. The trail is
currently partially open to the public.
The bank stabilization project has two phases. The first phase is to prepare a construction site and
temporary trail bypass approximately 20 feet landward (away from the river). The second phase of the
project is to complete the bank stabilization.
This proposal provides a Scope of Services and budget for design, permitting and construction support
services for both phases of work. Design work includes preliminary design to support permitting and final
design to produce bid-ready contract documents. Permitting work includes preparation of project
environmental documentation and permit applications, as well as assisting the City with agency
coordination and negotiation of final permit conditions. Construction services including bidding support,
plus construction observation and engineering/permitting support to assist the City’s construction
management and administration.
City of Renton | November 6, 2020 Page 2
File No. 0693-087-01
SCOPE OF SERVICES
PHASE 1 - CONSTRUCTION SITE PREPARATION AND TEMPORARY TRAIL BYPASS
Task 1. Pre-Design of Construction Site Preparation
Activities
■ Review site conditions information available for various on-line data sources, including geographic
information system (GIS) and other data sources, related to property parcel boundaries and
ownership, critical areas, utilities, fish barriers and other relevant information. Develop a project
base map based on available Light Detection and Ranging (LIDAR) data.
■ Visit the site to observe site conditions and survey identified site features.
Locate and survey ordinary high water (OHW) line along about 200 feet of riverbank and visually
locate the stakes and include the location on the project basemap. Complete a reconnaissance
in the general site vicinity for wetlands and critical area features (such as large trees) to be
avoided at the site and in the access and staging areas.
Complete a reconnaissance to confirm that no wetlands are present and to assess the
presence/absence of other critical areas and buffers and add approximate extents to base
map.
Identify and survey trees greater than 6 inches diameter at breast height (DBH) that may need
to be removed within the project impact area. Review City of Renton Tree Inventory map for
presence of significant trees.
Collect up to 10 spot elevations within the bank failure area to compare to LiDAR data.
■ Review GeoEngineers’ report Field Reconnaissance and Preliminary Geotechnical Evaluation,
Cedar River Bank Stabilization, River Mile 2.5, Renton, Washington, prepared for City of Renton,
May 29, 2020.
■ Coordinate with the One-Call utility locate service to locate and mark utilities in the project area.
GeoEngineers will complete a field sketch of utility locate marks.
■ Coordinate with the City to develop design criteria and/or applicable existing City standard plans
and specifications. Document design criteria including vehicle load ratings and other items.
■ Attend a City-initiated Pre-Application Meeting with City staff and other agencies as appropriate.
GeoEngineers will prepare a briefing packet with a one-page project summary and one figure. The
City will prepare a meeting summary identifying permits and approvals needed, including project
plan reviews.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ Changes in site conditions over time that affect the work may require additional budget.
■ The site does not contain contaminated soils or wetlands. The site does not have utilities
threatened by the eroding bank, or that need to be relocated.
■ The riverbank is not a flood control levee or revetment or critical channel migration boundary. U.S.
Army Corps of Engineers (USACE) PL84-99 coordination is not required.
City of Renton | November 6, 2020 Page 3
File No. 0693-087-01
■ The construction site preparation will not include work below the OHW line, and therefore a Joint
Aquatic Resources Permit Application (JARPA) submittal will not be required. OHW line will be
marked in field and added to drawings as an “approximate” feature.
■ Trail use is limited to non-motorized use by the public. If a fence is needed along the eroded bank
top of slope, the City will install and maintain it. Vehicle signage or guardrail is not required.
■ The City will obtain cultural resources documentation if needed.
■ The project impact area where potential for tree removal exists is in the immediate vicinity of the
eroded bank and construction site preparation.
■ Site topographic survey will be obtained from LiDAR. If additional site-specific topographic survey
is determined to be needed from spot elevations collected, the City will contract for the survey or
authorize budget for GeoEngineers’ to perform surveying services or retain an outside surveyor.
Deliverables
■ Briefing packet for pre-application meeting
Task 2. Environmental Documentation and Permitting Support
Activities
■ Develop a brief permitting plan that lists permits/approvals needed, with estimated schedule and
strategy for obtaining each permit/approval needed. List key stakeholders and coordinate
approach.
■ Prepare environmental documentation and permit applications, including:
A National Environmental Policy Act (NEPA) project description for use by FEMA in complying
with NEPA through a Categorical Exclusion.
No Effect Biological Evaluation (BE) for compliance with the Endangered Species Act (ESA).
A Hydraulic Project Approval (HPA) through the Washington Department of Fish and Wildlife
(WDFW).
Shoreline Management Act Exemption.
Assist the City with agency coordination and permit negotiations.
Task Assumptions
■ The City will lead agency/stakeholder coordination work to obtain permits/approvals. City will be
lead applicant for local permits, if required.
■ FEMA will be the NEPA lead using the information identified in the scope, above, which will be
provided to FEMA by GeoEngineers. NEPA approval during Phase 1 will also address Phase 2
activities.
■ The City will coordinate with FEMA to obtain cultural resources documentation for compliance with
NEPA; a cultural resource is not included in our scope.
■ Project will be State Environmental Policy Act (SEPA) exempt.
■ Construction stormwater permit from Washington State Department of Ecology (Ecology) will not
be required as the disturbed area will be less than 1 acre.
City of Renton | November 6, 2020 Page 4
File No. 0693-087-01
■ Clearing and Grading permit is not required.
Deliverables
■ Permitting plan and stakeholder list
■ NEPA Project Description Package, submitted to FEMA
■ Draft and Final BE, submitted to FEMA
■ HPA Application Package, submitted to WDFW
■ Shoreline Exemption Memo documenting that the project qualifies as an emergency action,
provided for City use
Task 3. Geotechnical Support
Activities
■ Prepare a final version of our Field Reconnaissance and Preliminary Geotechnical Evaluation
Report (dated May 29, 2020) to support design of the Phase 1 construction site preparation. Our
geotechnical report will include recommended trail setback distances and equipment setbacks
within the work area.
■ Support the permitting process by providing an assessment of potential Geologically Hazardous
Areas in the project vicinity and provide our opinion on how the proposed Phase 1 work may impact
these areas, if present.
■ Support preparation of geotechnical related drawings and specifications for Phase 1 of the project.
■ Provide additional geotechnical consultation as needed to support the project and attend
project meetings.
■ Complete up to five geotechnical related site visits during construction of the construction site
preparation.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ Geotechnical staff will attend two meetings with the client.
■ Site visits during construction assume up to 4 hours onsite plus travel time.
■ Project will be SEPA exempt.
Deliverables
■ Final geotechnical report for the construction site preparation.
■ Field report summarizing observations and recommendations for each site visit during
construction.
City of Renton | November 6, 2020 Page 5
File No. 0693-087-01
Task 4. Design of Construction Site Preparation
Activities
■ Complete stormwater design analysis including stormwater modeling to size a non-fish passable
stormwater drainage culvert approximately 200 feet long to convey stormwater under the trail
through the project site.
■ Prepare draft and revised draft preliminary design drawings to support project environmental
documentation and permit applications, including cover sheet, site preparation/demolition sheet,
site staging and access sheet, temporary erosion and sediment control (TESC) plan, temporary trail
bypass plan, temporary trail bypass profile and sections sheet, details sheet and final
restoration/hydroseeding sheet. The drawings will reference an attachment containing City
standard plans for trail section, base thicknesses, culvert and trench section, and other applicable
work. Prepare list of bid items and specifications. The design will avoid and minimize impacts to
trees where possible and trees to retain will be located on the design drawings.
■ Prepare a draft, draft final and final “bid packet”. Draft version is for City project staff review. Draft
final version is for City permit review. Final version is “for bid”. The bid packet will include drawings,
bid schedules, specifications and cost estimate integrated into the City’s standard bid package.
GeoEngineers’ additions to the bid packet will consist of:
Updating project name, dates and other project specific items.
Develop list of bid items and update bid form.
Update the City’s standard Division 1 specifications, including substantial edits to the Summary
of Work section and minor edits to other specification sections.
Review and update City technical specifications for earthwork, culvert, erosion control blanket,
hydroseed and other relevant work items.
Drawings stamped by Professional Engineer (PE). Final drawings will be signed.
Construction schedule and Engineer’s estimate of the cost to construct the work.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ Changes in site conditions over time that affect the work may require additional budget.
■ The riverbank is not a flood control levee or revetment or critical channel migration boundary.
USACE PL84-99 coordination is not required.
■ The construction site preparation will not include work below the OHW line, and therefore a JARPA
submittal/HPA permit will not be required. OHW locations will be marked in field and surveyed in
Task 1. An OHW line will be added to drawings.
■ Design of structures including retaining walls or utilities is not required.
■ Trail use is limited to non-motorized use by the public. A fence is not needed along the eroded bank
top of slope. Vehicle signage or guardrail is not required.
■ Site topographic survey will be obtained from LiDAR. If additional site-specific topographic survey
is determined to be needed from spot elevations collected in Task 1, the City will contract for the
City of Renton | November 6, 2020 Page 6
File No. 0693-087-01
survey or authorize budget for GeoEngineers’ to perform surveying services or retain an outside
surveyor.
■ A river hydraulic model is not needed for this project phase.
■ Specifications will be in Construction Specification Institute (CSI) format. The City will provide a
recent example bid package for GeoEngineers revision. The City will prepare the “front end”
portions of the bid documents and specifications, including instructions to bidders, bid form, other
forms, contract, general conditions and Division 1 administrative specifications. GeoEngineers will
revise the project description, bid form, Summary of Work specifications, recommend minor edits
to Division 1 administrative specifications and develop Division 2 technical specifications.
Deliverables
■ Draft and revised draft preliminary design drawings with list of bid items and specifications.
■ Draft, revised draft and final bid package.
Task 5. Bidding and Construction Support
Activities
■ Support the City during bidding process by attending pre-bid meeting and assisting City of
responding to bidder questions and preparing addenda.
■ Complete up to 20 hours for field observation of the contractor’s work and document the site visits
through five field reports and one punch list itemizing items to be corrected/completed.
■ Complete up to 20 hours of office engineering/permitting support including review of Contractor
work plans and submittals and responding to Contractor request for information (RFIs).
■ The design engineer will attend up to three virtual construction progress meetings and three site
construction progress meetings and will prepare meeting minutes for those meetings.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ The City will lead and complete bidding and change order negotiation and preparation, and overall
construction management (including correspondence with the contractor, review of pay requests
and close-out). GeoEngineers can provide additional bidding, construction, and/or
maintenance/warranty support (such as due to unusual events, a challenging contractor or
extensive/detailed issues) under a supplemental scope of services.
Deliverables
■ Draft and final meeting minutes for up to six meetings.
■ Construction support documentation including field reports, and suggested responses for submittal
reviews and RFIs for City to confirm/revise and send to Contractor.
City of Renton | November 6, 2020 Page 7
File No. 0693-087-01
PHASE 2 - BANK STABILIZATION
Task 6. Preliminary Design
Activities
■ Perform an updated survey next spring to identify changes in the bank erosion or changes in OHW
and other site features. Visit the site to observe site conditions and survey identified site features
including identifying site changes from previous survey.
Survey OHW line along about 200 feet of riverbank and update the location on the project
basemap,
collect up to 10 spot elevations within the bank failure area to compare to LiDAR data, and
survey trees greater than 6 inches DBH that may need to be removed within the project impact
area.
■ Perform desktop geomorphic assessment.
■ Hydrologic, Hydraulic and Scour Analysis:
Complete a flow magnitude and frequency analysis to estimate discharge values for the 2-, 10-
, 25-, 50- and 100-year recurrence discharges for the drainage area contributing to the project
reach.
Obtain the hydraulic model used for the most recent FEMA flood study, and update the model
as needed to support project analyses. Update hydrology based on recent flow records. Run
the WDFW Climate Change model and estimate future hydrology for one condition. Complete
a hydraulic model and analysis of the existing and proposed conditions to evaluate hydraulic
parameters at the bank failure location. The hydraulic models will be one-dimensional using
USACE’s Hydrologic Engineering Center – River Analysis System (HEC-RAS) software.
Use the results of the hydraulic modeling to develop proposed bank geometry, material sizing,
wood stability and scour countermeasures. Complete a scour analysis to calculate depth of
scour at the toe of the bank. We will use the calculated scour depth to inform scour
countermeasure design and material sizing for bank stabilization.
■ Complete preliminary design analyses based on desktop geomorphic assessment and hydraulic
model. Estimate rock size needed to be stable at the 100-year flood. Calculated anchorage
requirements for large wood.
■ Prepare preliminary 30-percent-level design, consisting of:
Preliminary drawings
o Cover Sheet
o General Notes sheet
o Access and Staging Plan
o Existing conditions, Demolition and Site Preparation plan
o TESC plan
o Proposed conditions plan
o Typical cross sections
o Typical details
o Temporary Trail Bypass Plan
City of Renton | November 6, 2020 Page 8
File No. 0693-087-01
o Trail Bypass sections and details
o Restoration plan
Draft list of technical specifications
Draft bid form
Preliminary Design-level estimate of construction cost.
■ 60-Percent Design Development
Prepare 60 percent design drawings, draft specifications, bid form and estimate of
construction cost. Estimated of construction cost.
■ Pre-Design Meetings
All meetings will be virtual. We anticipate four brief design project meetings, two 2-hour meetings to receive
City comments on the 30 percent and 60 percent design submittals, and two 2-hour meetings to receive
FEMA comments on the 30 percent and 60 percent design submittals. We will prepare meeting minutes
briefly summarizing key discussions and documenting key decisions and action items.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ The project impact area where potential for tree removal exists is in the immediate vicinity of the
eroded bank and construction site preparation.
■ The 30 and 60 percent submittals will be prepared as drafts for City review, and revised drafts for
FEMA review. No design report will be prepared for Preliminary Design.
■ Existing topographic information provided by the City can be used for topography and river
bathymetry provided the bank erosion remains similar to current conditions as depicted in the
LiDAR. If the bank topography or river bathymetry changes substantially, as identified during the
site visit in this task, then site-specific survey information will be needed to provide a current base
map for design analyses and drawings.
Deliverables
■ 30-Percent Design submittal (portable document format [pdf])
■ 60-Percent Design submittal (pdf)
■ Meeting minutes
Task 7. Geotechnical Engineering
Activities
■ Visit the project site to mark a location for the proposed exploration and contact the “One-Call”
Utility Notification Center, as required by Washington State law.
■ Advance one boring to a depth of about 60 feet below ground surface (bgs) in the bank stabilization
area. The boring will be completed by a licensed driller under subcontract to GeoEngineers. A
representative from our firm will continuously monitor the exploration, keep a detailed log of the
conditions encountered and collect representative soil samples for laboratory testing.
City of Renton | November 6, 2020 Page 9
File No. 0693-087-01
■ Perform laboratory testing on select samples from the boring. We anticipate our laboratory program
will consist of grain-size distribution tests, percent fines determinations and moisture content
determinations.
■ Provide preliminary geotechnical engineering recommendations for stabilization of the riverbank.
We anticipate that these recommendations will be reviewed by the City for selecting a preferred
stabilization method.
■ Once the preferred stabilization method is selected, we will complete supplemental geotechnical
analyses and provided recommendations to support final design.
■ Prepare a geotechnical engineering report for the project summarizing the results of our subsurface
explorations and analyses and our geotechnical recommendations for design.
■ Support development of the 30, 60, 90 and 100 percent design plans and specifications.
■ Provide ongoing geotechnical consultation as needed and attend project meetings.
■ Complete up to 10 geotechnical related site visits during construction.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ Permits, if required to complete our boring, will be provided by others.
■ Geotechnical staff will attend up to six meetings with the client
■ Site visits during construction assume up to 6 hours onsite plus travel time
Deliverables
■ Geotechnical Engineering Services Report
■ Field report summarizing observations and recommendations for each site visit during
construction.
Task 8. Environmental Documentation and Permitting Support
Activities
■ Delineate and mark wetlands and/or other critical area features (such as trees greater than
6 inches) as needed for permitting.
■ Locate/update the OHW line generated in Phase 1 along about 200 feet of riverbank and mark
with stakes for survey in Task 6.
■ Prepare environmental documentation and permit applications, including:
Wetland and Aquatic Areas Delineation Report
A JARPA
A BE for compliance with the ESA
A HPA permit application
Section 401 Water Quality Certification Pre-Application Meeting Request Form
City of Renton | November 6, 2020 Page 10
File No. 0693-087-01
Coastal Zone Management Consistency Form, if required
Shoreline Management Act Exemption
Assist the City with agency coordination and permit negotiations.
■ Submit permit applications to:
USACE for Section 404 Clean Water Act permit
Ecology for Section 401 Clean Water Act Certification
Ecology for Coastal Management Zone Consistency approval if not covered by USACE permit.
WDFW for HPA permit
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ NEPA compliance during Phase 1 will cover Phase 2 activities as well. No further NEPA coordination
is anticipated.
■ Project will be SEPA exempt.
■ Construction stormwater permit from Ecology will not be required as the disturbed area will be less
than 1 acre.
■ Clearing and Grading permit is not required.
■ Application fees, if any, will be provided by the City.
Deliverables
■ Wetland and Aquatic Areas Delineation Report, submitted with multiple permit applications
■ JARPA package, submitted to USACE and Ecology
■ HPA application, submitted online to WDFW
■ Section 401 Water Quality Certification Pre-Application Meeting Request Form, submitted to
Ecology
■ Coastal Zone Management Consistency Form, if required, submitted to Ecology
Task 9. Final Design
Activities
■ Prepare 90 percent design submittal including draft design report, drawings, specifications, bid
form and estimate of construction cost, for City review.
■ Prepare revised 90 percent design submittal including draft design report, drawings, specifications,
bid form and estimate of construction cost, for FEMA review.
■ Prepare draft 100 percent design submittal, including draft design report, drawings, specifications,
bid form and estimate of construction cost, for City and FEMA review.
■ Drawings stamped by PE. Final drawings will be signed.
City of Renton | November 6, 2020 Page 11
File No. 0693-087-01
■ Prepare final for bid submittal including stamped and signed bid package including bid form and
specifications, stamped and signed drawings, and appendices as needed. We will separately
submit the final stamped and signed design report and estimate of construction cost.
■ All design meetings will be virtual. We anticipate four brief design project meetings, a 2-hour
meeting to receive City comments on the 90 percent design submittal, and a 2-hour meeting to
receive FEMA comments on the 90 percent. We will prepare meeting minutes briefly summarizing
key discussions and documenting key decisions and action items.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ The site does not contain contaminated soils or wetlands. The site does not have utilities
threatened by the eroding bank, or that need to be relocated.
■ The project advances in a consistent manner building on prior phases. Comments on the draft
100 percent design submittal will be very minor. If substantive design changes occur that require
revising earlier design work, additional time and budget may be required.
■ Specifications will be in CSI format. The City will provide a recent example bid package for
GeoEngineers revision. The City will prepare the “front end” portions of the bid documents and
specifications, including instructions to bidders, bid form, other forms, contract, general conditions,
and Division 1 administrative specifications. GeoEngineers will revise the project description, bid
form, Summary of Work specifications, recommend minor edits to Division 1 administrative
specifications and develop Division 2 technical specifications.
Deliverables
■ Draft, revised draft 90-Percent Design (pdf) submittal
■ Draft 100-percent design submittal (pdf)
■ Final for bid submittal. Meeting minutes.
Task 10. Bidding and Construction Support
Activities
■ Support the City during bidding process by attending pre-bid meeting and assisting City of
responding to bidder questions and preparing addenda.
■ Complete up to 60 hours for field observation of the contractor’s work and document the site visits
through five field reports and one punch list itemizing items to be corrected/completed.
■ Complete up to 60 hours of office engineering/permitting support including review of Contractor
work plans and submittals and responding to Contractor RFIs.
■ The design engineer will attend up to six virtual construction progress meetings and six site
construction progress meetings and will prepare meeting minutes for those meetings.
City of Renton | November 6, 2020 Page 12
File No. 0693-087-01
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ The City will lead and complete bidding and change order negotiation and preparation, and overall
construction management (including correspondence with the contractor, review of pay requests
and close-out). GeoEngineers can provide additional bidding, construction, and/or
maintenance/warranty support (such as due to unusual events, a challenging contractor or
extensive/detailed issues) under a supplemental scope of services.
Deliverables
■ Draft and final meeting minutes for up to 12 meetings.
■ Construction support documentation including field reports, and suggested responses for submittal
reviews and RFIs for City to confirm/revise and send to Contractor.
Task 11. Project Management
Activities
■ Prepare brief Project Management Plan with project goals and objectives, key staff, key activities
and milestones for design and permitting,
■ Prepare detailed monthly status reports and pay requests (invoices).
■ Prepare overall project simple bar chart schedule. Update schedule three times during project.
■ Attend up to six virtual meetings/calls with City regarding project status. Prepare up to six sets of
meeting minutes.
Task Assumptions
Our scope and budget for this task are based on the following assumptions and exclusions:
■ The project duration is from November 2020 to April 2021.
Deliverables
■ Project management plan monthly status reports, schedule and updates, and meeting minutes.
FEE ESTIMATE, SCHEDULE AND CONTRACT TERMS
Fee Estimate
The fee for our services will be determined using the rates contained in our standard Schedule of Charges,
which is attached as part of this proposal. The total estimated fee for the work described above and a per-
task breakdown are included in Exhibit A, Consultant Fee Determination Summary Sheet.
Schedule
The general schedule specific to each task is identified in the task descriptions above. An overall schedule
for this contract will be produced in Task 11.
City of Renton | November 6, 2020 Page 13
File No. 0693-087-01
Contract Terms
The services described in this proposal will be completed and payment made according to the terms and
conditions of the Professional Services Agreement established between the City of Renton and
GeoEngineers, Inc.
CLOSURE
We appreciate the opportunity to present this proposal to provide design and permitting services on this
project. Please contact us if you have any questions concerning this proposal.
Sincerely,
GeoEngineers, Inc.
Theo Malone, PE Joseph O. Callaghan, PWS
Project Engineer Principal Biologist
TM:JOC:tlm:
Attachments:
Schedule of Charges—Redmond/Seattle/Tacoma 2020
Exhibit A. Consultant Fee Determination Summary Sheet
One copy submitted
Disclaimer: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy
of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record.
Copyright© 2020 by GeoEngineers, Inc. All rights reserved.
PROJECT OVERVIEW SCHEDULE Date:
Cedar River Bank Stabilization Project, City of Renton
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
1.1 Site Visit and Survey
1.2 Data Gathering and Pre-Meeting Preparation
1.3 Pre-Application Meeting (follows 4.1 & 6.2)X
2.1 Permitting Plan
2.2 Environmental Documentation
2.3 Permit Submittal (x) and Agency Review X
3.1 Geotechnical Analysis and Report
3.2 Drawing and Specifications
3.3 Meetings and Site Visits X
3.4 Permitting and Design Support
4.1 Preliminary Design Submittal and Revision
4.2 Final Design
4.3 For Bid Submittal
5.1 Bidding X
5.2 Construction Support (Field and Office)
6.1 Site Visit and Survey
6.2 Hydraulic Model and Analyses
6.3 30% Design Submittal and Revision
6.4 60% Design Submittal and Revision
7.1 Subsurface Exploration
7.2 Geotechnical Analysis and Report
7.3 Drawing and Specification Support
7.4 Geotechnical Site Visits During Construction
8.1 Field Delineation
8.2 Environmental Documentation and Permit Applications
8.3 Permit Submittal and Coordination X
9.1 90% Design Submittal and Revision
9.2 Final Design Submittal and Revision
9.3 For Bid Submittal
10.1 Bidding (includes FEMA approval of final docs)X X X
10.2 Construction - Field and office support
11.1 Brief Project Management Plan
11.2 Monthly Invoices and Status Reports X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
11.3 Schedule and Meeting Minutes
Q3
Task 11.0: Project Management
PHASE 2 - BANK STABILIZATION
Task 1.0: Pre-Design of Temporary Trail Bypass
Task 2.0: Environmental Documentation and Permitting Support
Task 3.0: Geotechnical Support
Task 4.0: Design of Temporary Trail Bypass
Task 5.0: Bidding and Construction Support
Task 6.0: Preliminary Design
Task 7.0: Geotechnical Engineering
Task 8.0: Environmental Documentation and Permitting Support
Task 9.0: Final Design
Task 10.0: Bidding and Construction Support
202320212022
5/21/2021
PHASE 1 - TEMPORARY TRAIL BYPASS
Q1 Q2 Q3 Q4 Q1Q2Q1 Q2 Q3 Q4Q4