HomeMy WebLinkAboutRenton_LRWWMP_AgencyDraftCITY OF RENTON
LONG-RANGE WASTEWATER MANAGEMENT PLAN
AGENCY DRAFT | March 2021
MAYOR
Armondo Pavone
PUBLIC WORKS DEPARTMENT ADMINISTRATOR
Martin Pastucha
WASTEWATER UTILITY SYSTEMS DIVISION STAFF
Joseph Stowell
Michael Benoit
Ann Fowler
John Hobson
Don Ellis
Rick Moreno
MAINTENANCE SERVICES DIVISION STAFF
Richard Marshall
Nathan Nelson
CITY COUNCIL
Randy Corman
Ryan McIrvin
Kim-Khánh Văn
Ruth Pérez
Angelina Benedetti
Ed Prince
Valerie O’Halloran
PREPARED BY
City of Renton
with the assistance of
Carollo Engineers, Inc.
RECEIVED
06/01/2021 BGillia
PLANNING DIVISION
City of Renton
Long-Range Wastewater Management Plan
REPORT
AGENCY DRAFT | March 2021
This document is released for the
purpose of information exchange review
and planning only under the authority of
Lara R. Kammereck, March 2021,
Washington State PE No. 34428.
CONTENTS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | i
pw:\\Carollo\Documents\Client/WA/Renton/9971A00/Deliverables\_Cover & TOC
Contents
Executive Summary
ES.1 Introduction ES-1
ES.2 Overview of Existing Sewer System ES-1
ES.3 Operational Policies and Criteria ES-1
ES.4 Planning Considerations ES-5
ES.5 System Analysis and Results ES-5
ES.5.1 Hydraulic Modeling Overview ES-6
ES.5.2 Capacity Criteria ES-7
ES.5.3 Capacity Evaluation ES-7
ES.6 Replacement and Rehabilitation Program ES-7
ES.7 Operations and Maintenance ES-8
ES.8 Capital Improvement Program ES-8
ES.9 Financial Analysis ES-9
Chapter 1 - Introduction
1.1 Introduction 1-1
1.2 Background and Goals 1-1
1.3 Referenced Documents 1-2
1.4 Washington State Requirements 1-2
1.5 Report Organization 1-5
1.6 Key Issues 1-6
1.7 SEPA and Approval Process 1-7
1.8 Acknowledgements 1-7
Chapter 2 - Overview of Existing Sewer System
2.1 Overview of Existing System 2-1
2.2 System Components 2-1
2.3 Wastewater Collection Basins 2-5
2.3.1 West Cedar River Basin 2-5
2.3.2 East Cedar River Basin 2-5
2.3.3 East Lake Washington Basin 2-5
2.3.4 Black River Basin 2-9
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CONTENTS
ii |MARCH 2021
2.3.5 Downtown Basin 2-9
2.3.6 May Valley Basin 2-9
2.4 Interceptors and Collection Systems 2-9
2.4.1 Existing Sewer System 2-9
2.4.2 Interceptors 2-10
2.5 Lift Stations and Force Mains 2-10
2.5.1 Airport Lift Station 2-13
2.5.2 Baxter Lift Station 2-13
2.5.3 Cottonwood Lift Station 2-13
2.5.4 Devil's Elbow Lift Station 2-13
2.5.5 East Valley Lift Station 2-13
2.5.6 Falcon Ridge Lift Station 2-13
2.5.7 Kensington Crest Lift Station 2-14
2.5.8 Lake Washington Beach Lift Station 2-14
2.5.9 Lake Washington Flush Lift Station 2-14
2.5.10 Lake Washington No. 2 Lift Station 2-14
2.5.11 Liberty Lift Station 2-14
2.5.12 Lind Avenue Lift Station 2-14
2.5.13 Long Lift Station 2-14
2.5.14 Misty Cove Lift Station 2-14
2.5.15 Pipers Bluff Lift Station 2-15
2.5.16 Shy Creek Lift Station 2-15
2.5.17 Stone Gate Lift Station 2-15
2.5.18 Talbot Crest Lift Station 2-15
2.5.19 Wedgewood Lift Station 2-15
2.5.20 Westview Lift Station 2-15
2.5.21 Force Mains 2-19
2.6 Water System 2-19
2.7 Operation and Maintenance 2-20
Chapter 3 - Operational Policies and Criteria
3.1 Introduction 3-1
3.2 Operational Goal 3-1
CONTENTS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | iii
3.3 Customer Service Objective 3-2
3.3.1 Policies 3-2
3.3.2 Implementation 3-2
3.4 Planning Objective 3-3
3.4.1 Policies 3-4
3.5 Service Area and Extension Objectives 3-5
3.5.1 Policies 3-5
3.5.2 Implementation 3-6
3.6 Financial Objective 3-7
3.6.1 Policies 3-7
3.6.2 Implementation 3-8
3.7 Facility Objective 3-8
3.7.1 Policies 3-8
3.7.2 Implementation 3-9
3.7.3 Analysis and Design Criteria 3-10
3.8 Operations Objective 3-14
3.8.1 Policies 3-14
3.8.2 Implementation 3-16
3.9 Recommendations 3-16
Chapter 4 - Planning Considerations
4.1 Introduction 4-1
4.2 Basis of Planning 4-1
4.3 Planning Area 4-1
4.3.1 Existing Service Area 4-2
4.3.2 Potential Annexation Areas 4-2
4.4 Land Use 4-7
4.4.1 City of Renton Land Use 4-7
4.4.2 City of Renton Land Use Designations 4-9
4.4.3 School Designations 4-13
4.4.4 Land Use Outside Renton’s PAA 4-14
4.4.5 Adjacent Utility Systems/Joint Use, Service Agreements, and Related Plans 4-15
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CONTENTS
iv |MARCH 2021
4.5 Demographic Analysis 4-18
4.5.1 Residential Population Projections 4-19
4.5.2 Employment 4-20
4.5.3 Schools 4-21
4-27
4-27
4-27
4-28
4-28
4-29
4-30
4-30
4-30
4-30
5-1
4.6 Sewer Collection System Flow Components
4.6.1 Dry Weather Flow Components
4.6.2 Wet Weather Flow Components
4.7 Flow Monitoring
4.8 Average Dry Weather Flow
4.8.1 Average Dry Weather Flow Development
4.9 Wet Weather Flows
4.9.1 Rainfall Data
4.9.2 Wet Weather Flow Data
4.10 Projected Flows
Chapter 5 - System Analysis and Result
5.1 Introduction
5.2 System-Wide Concerns 5-1
5.2.1 King County-Interceptor Surcharging 5-1
5.2.2 Adjacent Utility Systems 5-2
5.2.3 Hazard Mitigation Plan 5-2
5.2.4 Septic Systems 5-2
5.2.5 Wastewater Quality 5-2
5.2.6 Wastewater Quality Analysis and Recommendations 5-4
5.2.7 Aging Sanitary Sewers 5-5
5.2.8 Infiltration and Inflow 5-5
5.2.9 Other Concerns 5-6
5.3 Hydraulic Model 5-6
5.3.1 Model Development and Calibration 5-9
5.3.2 Model Evaluation Results 5-9
5.4 Capacity Evaluation 5-11
5.4.1 Analysis Criteria 5-12
5.4.2 Design Storm 5-12
CONTENTS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | v
5.4.3 Capacity Evaluation Results 5-14
5.4.4 Lift Station Capacity 5-14
5.4.5 Collection System Capacity 5-15
5.5 Recommendations 5-21
5.5.1 Piping Reconfiguration 5-23
5.5.2 I/I Evaluation 5-24
5.5.3 Programmatic Upsizing 5-29
5.5.4 Additional Long-Term Flow Monitoring 5-29
Chapter 6 - Replacement and Rehabilitation Program
6.1 Introduction 6-1
6.2 Replacement and Rehabilitation Plan Goals 6-1
6.2.1 Prioritizing Using Risk 6-1
6.3 Lift Station and Force Main Current R&R Program 6-2
6.4 Force Main R&R 6-2
6.4.1 Force Main Criteria 6-2
6.4.2 Force Main Risk Assessment 6-3
6.4.3 Force Main Recommendations 6-3
6.5 Lift Station R&R 6-4
6.5.1 Lift Station Criteria 6-4
6.5.2 Lift Station Criticality Assessment 6-5
6.5.3 Lift Station Vulnerability Assessment 6-5
6.5.4 Lift Station Risk Assessment 6-7
6.5.5 Risk Based Lift Station Recommendations 6-7
6.5.6 Rehabilitation Improvements 6-7
6.6 Gravity Sewer System R&R 6-12
6.6.1 Gravity Sewer Main Criteria 6-12
6.6.2 Gravity Sewer Criticality Assessment 6-15
6.6.3 Gravity Sewer Vulnerability Assessment 6-15
6.6.4 Gravity Sewer Mains Risk Assessment 6-27
6.7 Recommended R&R Program 6-28
Chapter 7 - Operations and Maintenance
7.1 Introduction 7-1
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CONTENTS
vi |MARCH 2021
7.2 Operations and Maintenance Programs 7-1
7.3 Organization 7-2
7.3.1 Wastewater Maintenance Services 7-2
7.3.2 Wastewater Utility Services 7-2
7.3.3 Communication 7-2
7.3.4 Divisional Coordination 7-3
7.4 Wastewater Operations Master Plan 7-3
7.5 Systems Inventory and Information Management 7-3
7.5.1 Information Management System 7-3
7.5.2 Business Process 7-6
7.6 Collection System Maintenance 7-6
7.6.1 Maintenance Priorities 7-7
7.6.2 Manhole Inspection and Maintenance 7-7
7.6.3 CCTV Inspection 7-7
7.6.4 Root Cutting 7-8
7.6.5 Grease Removal 7-9
7.6.6 Hydraulic Line Cleaning 7-9
7.6.7 Repair Sewers and Clear Plugs 7-9
7.6.8 Easements and Access Road Maintenance 7-10
7.7 Lift Station Operations and Maintenance 7-10
7.7.1 Lift Station Inspection and Maintenance 7-10
7.7.2 Telemetry (SCADA) 7-10
7.8 Predictive Repair and Replacement Program 7-11
7.9 Emergency Response 7-11
7.10 FOG Source Control 7-11
7.11 System Infrastructure Capacity 7-11
7.12 Design and Construction 7-12
7.12.1 Design 7-12
7.12.2 Construction 7-12
7.12.3 Inspection 7-12
7.13 Legal Authority 7-13
7.14 Safety, Training, and Certification 7-13
7.15 Interagency Coordination 7-13
CONTENTS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | vii
7.16 Financial Program 7-13
7.17 Administrative Duties and Facility/Equipment Maintenance 7-14
7.17.1 Administrative Duties 7-14
7.17.2 Tools and Equipment 7-14
7.18 Work Force Estimates 7-14
7.18.1 Future Resource Recommendations 7-14
7.18.2 Emergency Operations 7-15
7.18.3 Maintenance Services Staffing 7-15
7.18.4 Wastewater Utility Engineering Staff 7-17
7.19 Recommendations 7-17
Chapter 8 - Capital Improvement Program
8.1 Introduction 8-1
8.2 Cost Estimating Assumptions 8-1
8.2.1 Baseline Cost Assumptions 8-1
8.2.2 Total Capital Improvement Cost 8-3
8.3 Capital Improvement Program 8-3
8.3.1 Planning Periods 8-4
8.3.2 Project and Program Naming 8-4
8.3.3 Project Types 8-4
8.3.4 Capital Improvement Program by Year 8-4
8.4 Lift Station Projects 8-7
8.4.1 LS-01: Lift Station Rehabilitation 8-7
8.4.2 LS-02: Force Main Rehabilitation/Replacement 8-7
8.4.3 LS-03: Telemetry Upgrade 8-7
8.4.4 LS-04: Devil’s Elbow Stream Bank Study 8-7
8.4.5 LS-05: Kennydale Lake Line Sewer Upgrade 8-7
8.4.6 LS-06: Kennydale Lake Line Renewal 8-8
8.4.7 LS-07 Low and Moderately-Low Risk Lift Station and Force Main
Rehabilitation 8-8
8.4.8 LS-08: Moderately-High and High Risk Lift Station and Force Main
Rehabilitation 8-8
8.5 Pipeline Projects 8-9
8.5.1 Sanitary Sewer Main Replacement/Rehabilitation 8-9
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CONTENTS
viii |MARCH 2021
8.5.2 P-01: 2020 Sanitary Sewer Main Replacement/Rehabilitation 8-9
8.5.3 P-02: 2021 Sanitary Sewer Main Replacement/Rehabilitation 8-9
8.5.4 P-03: 2022 Sanitary Sewer Main Replacement/Rehabilitation 8-10
8.5.5 P-04: 2023 Sanitary Sewer Main Replacement/Rehabilitation 8-10
8.5.6 P-05: 2024 Sanitary Sewer Main Replacement/Rehabilitation 8-10
8.5.7 P-06: 2025 Sanitary Sewer Main Replacement/Rehabilitation 8-10
8.5.8 P-07: 2026-2029 Sanitary Sewer Main Replacement/Rehabilitation 8-10
8.5.9 P-08: 2030-2039 Sanitary Sewer Main Replacement/Rehabilitation 8-10
8.5.10 P-09: Sewer Capacity Improvements 2021-2024 8-13
8.5.11 P-10: Flow Monitoring Program 8-13
8.5.12 P-11: I/I Evaluation Program 8-14
8.6 General Projects 8-17
8.6.1 G-01: Wastewater Operations Master Plan 8-17
8.6.2 G-02: Long-Range Wastewater Master Plan 8-17
8.6.3 G-03: Sanitary Sewer Hydraulic Model 8-17
8.6.4 G-04: Miscellaneous / Emergency Projects 8-17
8.7 Summary of CIP 8-17
Chapter 9 - Financial Analysis
9.1 Introduction 9-1
9.2 Historical Financial Performance 9-1
9.2.1 Current Water Rates, Fees, and Charges 9-1
9.2.2 Historical Financial Operations 9-2
9.2.3 Wastewater Utility Fund 9-4
9.2.4 Outstanding Debt 9-4
9.3 Financial Analysis 9-4
9.3.1 Projected Capital Improvement Program Levels 9-4
9.3.2 Financial Analysis 9-4
9.4 Available Funding Assistance and Financing 9-7
9.4.1 Grants and Low Cost Loans 9-7
9.4.2 Bond Financing 9-7
9.5 Summary 9-7
CONTENTS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | ix
Appendices
Appendix A SEPA Checklist
Appendix B Agency Comment Letters and Responses
Appendix C Approvals
Appendix D Hydraulic Model and Deficiency Results
Appendix E Service Agreements
Appendix F Stantec Model Update and Capacity Analysis Report
Appendix G TM 1 - Rain and Flow Monitoring and Projections
Appendix H TM 2 - Model Development and Calibration
Appendix I TM 4 - Risk Findings
Appendix J Standard Plans and Specifications
Appendix K CIP Detail Sheets
Tables
Table ES.1 ES-5
Table ES.2 ES-6
Table ES.3 ES-7
Table ES.4 ES-8
Table 1.1 1-5
Table 2.1 2-10
Table 2.2 2-17
Table 2.3 2-19
Table 3.1 3-12
Table 3.2 3-14
Table 4.1 4-9
Table 4.2 4-14
Table 4.3 4-14
Table 4.4
4-23
Table 4.5 4-30
Table 5.1 5-3
Table 5.2 5-10
Table 5.3
Existing and Projected Modeled Wastewater Flows
Deficiency Recommendations
Risk Matrix for Lift Stations
Risk Matrix for Length of Gravity Mains
WAC Plan Requirements
Gravity Sewer Inventory
Existing Lift Station Inventory Summary
Collection System Force Main Inventory
Sanitary Sewer Design Criteria
Lift Station and Force Mains Design Criteria
Land Use of Renton’s Sewer Service Area
Schools Served by Renton
Land Use Designations for Areas Outside Renton
Demographic Projections (From Stantec 2015 Hydraulic Model Update
Report)
Design Event Projected Wet Weather Flow
Renton Summary of Active Industrial Waste Permits
Model Calibration
Modeled Design Storms by Mini-Basins 5-13
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CONTENTS
x |MARCH 2021
Table 5.4 5-16
Table 5.5 5-17
Table 5.6 5-23
Table 5.7 5-24
Table 5.8 5-24
Table 5.9 5-29
Table 5.10 5-30
Table 6.1 6-1
Table 6.2 6-4
Table 6.3 6-6
Table 6.4 6-7
Table 6.5 6-11
Table 6.6 6-13
Table 6.7 6-14
Table 6.8 6-15
Table 6.9 6-15
Table 6.10 6-19
Table 6.11 6-23
Table 6.12 6-23
Table 6.13 6-27
Table 6.14 6-27
Table 7.1 7-4
Table 7.2 7-16
Table 7.3 7-16
Table 7.4 7-17
Table 8.1 8-2
Table 8.2 8-2
Table 8.3 8-5
Table 8.4 8-8
Table 8.5 8-8
Table 8.6 8-13
Table 8.7 8-13
Table 8.8
Lift Station Evaluation
Buildout Deficiency Locations
Deficiency Recommendations
Piping Reconfiguration Locations
Micro-Monitoring Recommendations for I/I
Programmatic Upsizing Location and Additional Information
Long-Term Flow Monitoring Recommendations
Normalized Risk Ratings
Force Main Risk Assessment Summary
Lift Station Risk Assessment Summary
Risk Matrix for Lift Stations
Lift Station and Force Main Rehabilitation Program
Criticality Criteria
Vulnerability Criteria
Criticality Score Range
Vulnerability Score Range
Useful Life of Pipes
Remaining Useful Life
Remaining Useful Life by Length
Risk Matrix for Length of Gravity Mains
Pipe Length Totals Based on Risk Rating
Existing and Recommended Information System Improvements
Staffing Time for Maintenance Activities
Staffing Time for Operations Tasks
Wastewater Utility Engineering Staff Activities
Open-Cut Costs by Pipeline Diameter
CIPP Costs by Pipeline Diameter
Capital Improvement Program Summary
Moderately-Low and Low Risk Lift Stations
Moderately-High Risk Lift Stations
Upsizing and Reconfiguration Locations and Cost
Flow Monitoring Locations and Duration
I/I Evaluation, Quantity, and Duration 8-14
CONTENTS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | xi
Table 8.9 8-18
Table 8.10 8-19
Table 9.1 9-1
Table 9.2 9-1
Table 9.3 9-2
Table 9.4 9-3
Table 9.5 9-3
Table 9.6 9-4
Table 9.7 9-4
Table 9.8
CIP Planning Period Summary
CIP Summary by Facility Type
2020 Water Utility Monthly Rates
Construction Permit Fees
2019-2020 System Development Charge
Historical Operating Revenue
Historical Operating Expenses
Historical Utility Fund
CIP Planning Period Summary
Projected Future Operating Expenses 9-6
Figures
Figure ES.1 Existing System ES-3
Figure ES.2 Cost by Facility Type ES-9
Figure 1.1 Vicinity Map 1-3
Figure 2.1 Existing System 2-3
Figure 2.2 Wastewater Basins 2-7
Figure 2.3 Topography 2-11
Figure 2.4 Water Facilities and Aquifer Protection Areas 2-21
Figure 4.1 Study Area 4-3
Figure 4.2 Sewer Service Area and Adjacent Utility Systems 4-5
Figure 4.3 Comprehensive Plan Land Use 4-11
Figure 4.4 Typical Weekday vs Weekend Dry Weather Flow Variation (MH0537) 4-29
Figure 5.1 Flow Monitoring Locations 5-7
Figure 5.2 Updated Hydraulic Model 5-11
Figure 5.3 Design Storm Hydrographs 5-13
Figure 5.4 Current Deficiencies 5-19
Figure 5.5 Buildout Deficiencies 5-20
Figure 5.6 Recommendation Decision Flow Chart 5-22
Figure 5.7 Modeled I/I Overlaid with Deficiencies 5-25
Figure 5.8 Deficiency Improvement Recommendations 5-27
Figure 6.1 City of Renton Lift Stations 6-9
Figure 6.2 Criticality Criteria Results 6-17
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CONTENTS
xii |MARCH 2021
Figure 6.3 Vulnerability Criteria Results 6-21
Figure 6.4 Remaining Useful Life of System 6-25
Figure 6.5 Map of Criticality x Vulnerability 6-29
Figure 8.1 Overview of CIP Projects 8-11
Figure 8.2 High and Moderately-High Gravity Sewer Risk with Upsizing and
Reconfiguration 8-15
Figure 8.3 Cost by Facility Type 8-18
Figure 9.1 CIP Proposed and Rate Analysis Model 9-5
ABBREVIATIONS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | xiii
Abbreviations
$ U.S. Dollar
AACE American Associate of Cost Estimators
ADS ADS Environmental Services, LLC
ADU Accessory Dwelling Unit
ADWF average dry weather flow
APA Aquifer Protection Area
APWA American Public Works Association
ASCE American Society of Civil Engineers
ASTM American Society for Testing Methods
AWWA American Water Works Association
BOD Biochemical Oxygen Demand
BPS booster pump station
BWF Base Wastewater Flow
CAD computer-aided design
CALAMAR Calcul de lames d’eau a l’aide du radar
Carollo Carollo Engineers, Inc.
CAS corrugated aluminized steel
CCTV closed-circuit television
CD Center Downtown land use designation
cf cubic feet
CI Cast Iron
CIP Capital Improvement Program
CIPP cured-in-place pipe
City City of Renton
CIWEM Chartered Institution of Water and Environmental Management
CMMS Computerized Maintenance Management System
CO Commercial Office land use designation
CP Concrete Pipe
CRWSD Cedar River Water and Sewer District
CSI conveyance system improvement
CV Center Village land use designation
d/D depth to diameter ratio
DHI Danish Hydraulic Institute
DI Ductile Iron
DIP Ductile Iron Pipe
du/net acre dwelling units per net acre
DWF dry weather flow
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | ABBREVIATIONS
xiv |MARCH 2021
ECM Enterprise Content Management
Ecology Washington State Department of Ecology
EDMS Electronic Document Management System
E/G engine generator
EIS Environmental Impact Statement
ENR Engineering News Report
Equip. equipment
FM force main
FOG fats, oil, and grease
ft foot / feet
FTE full-time equivalent
GIS geographic information system
GMA Washington Growth Management Act
GMPC Growth Management Planning Council
GPAD gallons per acre per day
gpm gallons per minute
GWI groundwater Infiltration
HDPE high-density polyethylene
HGL hydraulic grade line
hp horsepower
IACC Infrastructure Assistance Coordinating Council
ID identification
I/I Infiltration and Inflow
IT information technology
KC King County
KCBHRR King County Board of Health Rules and Regulations
Lake Line Kennydale Lake Line Sewer System
LEHD Longitudinal Employer-Household Dynamics
LF linear feet
LID Local Improvement District
LN Lined Pipe
LRWWMP Long-Range Wastewater Management Plan
LS lift station
M million
mgd million gallons per day
MH manhole
mi2 square mile
Misc. miscellaneous
NA not applicable
ABBREVIATIONS | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | xv
NACWA National Association of Clean Water Agencies
NASSCO National Association of Sewer Service Companies
NAVD North American Vertical Datum
NE northeast
NEPA National Environmental Policy Act
NPDES National Pollution Discharge Elimination Systems
O&M operations and maintenance
OERP Overflow Emergency Response Plan
OMP Operations Master Plan
OSS on-site system
PAA Potential Annexation Area
PACP Pipeline Assessment Certification Program
PE Person Equivalent
PF Peaking Factor
PSC pre-stressed concrete pipe
PSRC Puget Sound Regional Council
Public Works City of Renton Public Works Department
PVC polyvinyl chloride
PWTF Public Works Trust Fund
PWWF peak wet weather flows
R&R repair and replacement
RFI Request for Information
RMC Renton Municipal Code
RMF residential multi-family
ROW Right-of-Way
RPM revolutions per minute
RSD King County Road Services Division
RUL remaining useful life
RWSP Regional Wastewater Services Plan
SAD Special Assessment District
SCADA supervisory control and data acquisition
SDC system development charges
SEPA Washington State Environmental Policy Act
SOP Standard Operating Procedure
SSO sanitary sewer overflow
SW southwest
SWD King County Solid Waste Division
TAZ Traffic Analysis Zone
TDH total dynamic head
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | ABBREVIATIONS
xvi |MARCH 2021
Telem. telemetry
Temp temporary
TM Technical Memorandum
UC Urban Center land use designation
UGA Urban Growth Area
UGB Urban Growth Boundary
US Urban Separator
VCP Vitrified Clay Pipe
VMAC Virginia Mason Athletic Center
WA Washington
WAC Washington Administrative Code
WEF Water Environment Federation
WRRM Wastewater Revenue Requirement Model
WSDOT Washington State Department of Transportation
WWF wet weather flow
XXX unknown material
yr(s) year(s)
EXECUTIVE SUMMARY | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | ES-1
ES
EXECUTIVE SUMMARY
ES.1 Introduction
The City of Renton (City) is updating its Long-Range Wastewater Management Plan (LRWWMP)
to provide a road map for redevelopment while maintaining a high level of service for existing
customers. The existing system is aging and will continue to require investment to maintain a
high level of service. The LRWWMP is intended to provide the City with a "living" plan that can
be used and adapted to assist in decision making for the next 20 years.
This LRWWMP was prepared in accordance with requirements of Washington Administrative
Code (WAC) 173-240-050, which is administered by the Washington State Department of
Ecology (Ecology), and meets the requirements of the Washington Growth Management
Act (GMA).
This chapter presents the objectives of this LRWWMP, and a brief overview of the City’s
wastewater collection system. A list of abbreviations is provided in the Table of Contents to
assist the reader in understanding the information presented in this LRWWMP.
ES.2 Overview of Existing Sewer System
Chapter 2 – Overview of Existing Sewer System provides a description of the City’s existing
collection system and an inventory of the City’s assets. The City's collection system consists of
approximately 247 miles of gravity sewer, 6.8 miles of force mains, and 20 pump stations that
collect and convey wastewater to King County’s (KC’s) Interceptors. These interceptors convey
the City’s flow to the KC owned and operated South Treatment Plant.
Each pump station is described in this chapter to provide framework for the condition
assessment and any related Capital Improvement Program project. Additionally, other
components of the system are broken down such as materials and diameters of the total gravity
sewer system. The City's collection system is shown in Figure ES.1.
ES.3 Operational Policies and Criteria
Polices and criteria regulate the manner that the City operates and plans for its future. The City's
policies and criteria are detailed in the Renton Municipal Code, the Comprehensive Plan, City
ordinance, and through adoption of this and other plans. The following policies and criteria are
summarized in Chapter 3 – Operational Policies and Criteria:
• Customer Service Objective
• Planning Objective
• Service Area Extension Objectives
• Financial Objective
• Facility Objective
• Operations Objective
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
East Renton Interceptor
East Side Interceptor
South Interceptor
South Renton Interceptor
May Creek Interceptor
Cedar River Trunk Interceptor
Shy CreekLiftstation
Devils ElbowLift Station
East ValleyLift Station
Talbot CrestLift Station
Long LiftStation
KensingtonCrest Lift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash.Flush Lift Station
Stone GateLift Station
Falcon RidgeLift Station
Liberty LiftStation
Lake WashingtonBeach LiftStation Pipers BluffLift Station
Baxter LiftStation
Misty CoveLift Station
Airport LiftStation 12''24''
12''42''12''
36''
1 2 ''8'
'
12 ''
2
4
''12''6''12''1 2 ''
12 ''
24''
12''
24''
18''
12''18''12''12''48''12'
'
12 ''12''12''12''12''1 2 ''12''12''12''24''12''18''12''12''12''18''12''
1 2 ''
8 ''15''12''12''12''12''12''
12''12''12''12''12''
15''
2
4''12''18''12''1 2 ''12''12''12''24''18''36''
36''12''12''12''10''12 ''
30 ''12''12''18''
12''12''12''12''12''12''12''12''
12''
1 2 ''5 4 ''72''24''12''1 2 ''12''12''12''12''18''1
2''
12''
12''
12''12''
12''48''36''27''
18''24''12''
4 8 ''
1 2 ''12''8''12''12''12''18''12''12''48''18''
1 8 ''12'
'12''2 4 ''12''
2
4''
2
4''
12''
18''36''12''
24''
18''18''
1 2 ''12''30''12''24''12''12''12''30''12''12''8'
'
18''24''60''12''15''
24 ''12''18'
'12''24''
3
6
''15''24''
1 2 ''24''12''
24''12''12''8''18''
60''
12''24''18''18''48''18''12''12''1 2 ''
12''
1
8
''18''18''12''1
0''
12''
1
2
''
12''24''1 2 ''12''30''
18''
1 8 ''12''15''60''12''30''18''36''30'
'12''24''
18''
12''12''12''24''
1 2 ''24''18''1
2''
36''12''12''18''
12''
12''
12''12''12''
8''
2
4''
12''
18 ''10''8''
12''12''12''36''1 2 ''
18''24''24''12''12''18''18''12''
60''
12''12''8''
12''
12''12''1
8''
1 2 ''12''12''18''30''1
2''30''12''24''12''12''10''
12''
12''18''1
2
''12''54''12''
21''
12''
1 5 ''24''24''24''12''12''36''1
5''
12''15''1
2''12''12''18''24''12''12''12''12''
2
4
''
12''
15''54''
18''
12''36''
8''12''12''
1
2
''60''60''36''12''12''24''12'
'48''12''12'
'12''1 2 ''12''12''12 ''24''1 2 ''12''1 2 ''
12''
12''
60''12''12''12''8''18''12''15''12''8''15''
12''12''36''3 6 ''1 2 ''1 2 ''8''
12''
12''
12''
12''
12''15'
'
15''30''36''18''12''18''18''12''
72''
12''18''48''
12''12''1 8 ''12''36''36''1
8''20''18''
1 2 ''8''18''4''18''36''12''
18''
12''
54''
36''
2 0 ''2 4 ''Last Revised: March 04, 2021
\\io-fs-1\Data\GIS\GISBackup\Renton\
WaterSystemPlan2017\Existing_System.mxd
O
0 10.5
Miles
Legend
Lift Station
3Ú City of Renton
3Ú King County
Gravity Pipeline by Diameter
Unknown
< 8"
8"
10" - 18"
> 18"
City of Renton Force Main
King County Gravity Main
Study Area
Renton City Boundary
Roads
Waterbodies
EXECUTIVE SUMMARY | LONG RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: City of Renton
Figure ES.1 Existing System
EXECUTIVE SUMMARY | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | ES-5
ES.4 Planning Considerations
Chapter 4 – Planning Considerations and Technical Memorandum (TM) No 1 describe the City’s
land use policies and demographic projections that are used to develop future wastewater flow
projections. The City's land use policies and sewer system are connected with adjacent sewer
systems' policies and systems including the KC interceptors and serving small areas of Kent and
Tukwila. Existing land use provides the basis for designing properly sized sewage facilities,
including trunks, interceptors, and lift stations. In most cases the City's sewers are downstream,
or at the receiving end of the effluent, from the systems adjacent to the City. Therefore, proper
planning for the City's sewers requires that the plans of these adjacent utilities be evaluated.
In addition to adjacent utility plans, the land use plans and policies of KC and the Growth
Management Planning Council (GMPC) were also considered. As discussed below, the entire
planning area is within the Urban Growth Boundary (UGB) established by the GMPC. The City
supports the countywide framework policies (F-255 and F-102) that call for the designated Urban
Area to be served with sanitary sewers and prefers cities as the provider of sewer services. The
entire study area has been designated Urban by the 2012 King County Comprehensive Plan with
2013 Amendments.
Two planning periods are evaluated in this LRWWMP:
• Existing system
• Build-out
The existing system is defined as the 2012 sanitary flows calibrated with 2018 flow data.
Currently, build-out is projected at 2040. Evaluations are performed for both average dry
weather flow (ADWF) and peak wet weather flows (PWWF). A summary of the modeled total
ADWF and PWWF flows for metered basins, for each planning period is shown in Table ES.1.
Table ES.1 Existing and Projected Modeled Wastewater Flows
Flow Condition Existing Conditions Build-out Conditions
ADWF (mgd) 8.50 13.3
PWWF (mgd) 54.2 64.74
Peaking Factor 6.38 4.87
Note:
Abbreviation: mgd – million gallons per day.
ES.5 System Analysis and Results
As growth occurs, additional customer flows can exceed sewer capacity. Future growth is
anticipated and is modeled through the existing hydraulic model of the collection system. The
model was used as a basis to perform a capacity analysis. Based on the severity of the
deficiencies identified, the most probable cause and the location, four types of
recommendations were developed to mitigate or confirm these problem areas:
• Additional long-term depth monitoring
• Infiltration and Inflow (I/I) Evaluation: Micro-monitoring for areas with elevated I/I
• Piping reconfiguration
• Programmatic upsizing
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | EXECUTIVE SUMMARY
ES-6 | MARCH 2021
Capacity deficiencies and proposed improvements to provide sufficient capacity for future
development are detailed below in Table ES.2.
Table ES.2 Deficiency Recommendations
Deficiency
ID(1) Reason Deficient Condition Risk Recommend
05A Capacity High Depth Monitoring
45A Capacity High I/I Evaluation
7A Capacity Moderately High I/I Evaluation
2A Capacity Moderately High I/I Evaluation
3A Capacity Moderately High I/I Evaluation
46A Capacity, diameters change High Depth Monitoring
37A Negative slopes High Piping Reconfiguration
48A Capacity, grade change High Depth Monitoring
24A Negative slopes High Piping Reconfiguration
20B Capacity, shallow slope Low Programmatic Upsizing
20A Capacity, shallow slope Low Programmatic Upsizing
22A Capacity, diameters change High Depth Monitoring
21A Capacity, shallow slope Moderately High Depth Monitoring
41A Capacity, shallow slope Moderately High I/I Evaluation
23A Capacity Moderately High Programmatic Upsizing
15A Capacity High Depth Monitoring
14A Capacity High Depth Monitoring
BA Pump Station backwater High Programmatic Upsizing or
Pump Station
Improvements
05B Capacity High Depth Monitoring or
I/I Evaluation
05C Capacity Moderately High Depth Monitoring or
I/I Evaluation
11A Negative slopes Moderately Low Piping Reconfiguration
25A Capacity, shallow slope Moderately High Programmatic Upsizing
Note:
Abbreviation: ID – identification.
(1) Deficiency ID based on associated mini basin number.
ES.5.1 Hydraulic Modeling Overview
The City’s collection system hydraulic model was constructed using a multi-step process utilizing
data from a variety of sources. The latest version (2016) of Danish Hydraulic Institute’s (DHI’s)
Mike Urban was used to update the hydraulic model. The City conducted temporary flow
monitoring to gain a better understanding of flows in the service area and calibrate hydraulic
model predicted flows to actual collection system flows. Additional information on the modeling
calibration is provided in Appendix H, TM No. 2.
EXECUTIVE SUMMARY | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | ES-7
ES.5.2 Capacity Criteria
The primary criterion used to identify capacity-deficient trunk sewers was the maximum flow
depth to pipe diameter ratio (d/D) less than or equal to one. The d/D value is defined as the
depth (d) of flow in a pipe during peak flow conditions divided by the pipe’s diameter (D).
ES.5.3 Capacity Evaluation
The capacity evaluation was performed for the system, Existing and Build-out, under
a 20 to 30 year design storm. Sewer improvements were sized to a d/D of 2, to prioritize
improvements for the most serious surcharging. For such large design storms much of the
system surcharges and improvements for all surcharging was infeasible.
ES.6 Replacement and Rehabilitation Program
Chapter 6 – Replacement & Rehabilitation Program documents the City's prioritized collection
system repair and replacement (R&R) program. R&R prioritization is based on a risk, which
identifies the criticality and vulnerability of an asset. Criticality represents the consequence of
failure, and the vulnerability represents the likelihood of failure. A consistent approach is used to
identify and prioritize force mains, lift stations, and gravity mains.
The risk associated with an asset (pipe, manhole, pump, etc.) is a measure of the impact of asset
failure on the overall system. Risk is calculated as the product of criticality and vulnerability, or:
Risk = Criticality x Vulnerability
Both force mains and lift stations were analyzed together. The criticality, vulnerability, and risk
ratings for each force main and lift station were quantified on a relative risk scale, with one
representing the lowest risk and four representing the highest risk. Each lift station and its
corresponding force main’s calculated risk are shown below in Table ES.3.
Table ES.3 Risk Matrix for Lift Stations
Normalized Risk Ranking Vulnerability Level 4
(severe) Lake WA No. 2
Lake WA Flush
3
(moderate) Talbot Crest Devil’s Elbow
Kensington Crest
2
(low)
East Valley
Shy Creek Long
Wedgewood
1
(negligible)
Falcon
Lind Avenue
Westview
Liberty
Lake WA Beach
Cottonwood
Pipers Bluff
Baxter
Stonegate
Airport
Misty Cove
1
(negligible)
2
(low)
3
(moderate)
4
(severe)
Criticality Level
Note:
Abbreviation: WA – Washington.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | EXECUTIVE SUMMARY
ES-8 | MARCH 2021
Using TM 3 – Pipe Risk Approach and Procedures from the Closed-Circuit Television (CCTV)
Phase 2 Project, gravity sewer risks were calculated similarly. Table ES.4 shows the final result of
the normalized risk ranking for the City’s pipe.
Table ES.4 Risk Matrix for Length of Gravity Mains (ft)
Normalized Risk Ranking Vulnerability Level 4
(severe) 1,805 7,061 10,061 2,935
3
(moderate) 44,840 63,075 103,884 44,551
2
(low) 76,510 100,541 148,925 58,546
1
(negligible) 210,622 180,371 186,199 61,306
1
(negligible)
2
(low)
3
(moderate)
4
(severe)
Criticality Level
ES.7 Operations and Maintenance
Regular Operation and Maintenance (O&M) is required to provide effective and efficient
maintenance services for utility rate payers. Delayed O&M may contribute to adverse sewer
events, including sewer backups, sanitary sewer overflows (SSOs), pipe breaks, etc.
Chapter 7 – Operations & Maintenance considers the City's existing and planned O&M activities
and programs and provides recommendations to improve existing or address future needs.
These activities are greater than the current level of service; therefore, additional workforce may
be required in the future to meet City goals.
ES.8 Capital Improvement Program
Chapter 8 – Capital Improvement Program of the LRWWMP assesses the City’s ability to fund
the recommended improvements from Chapter 5 – System Analysis and Results and
Chapter 6 – Replacement and Rehabilitation Program detailed in Tables ES.2, ES.3, and ES.4.
The projects include a financial status of the sewer utility, funding required to finance the
scheduled improvements, updating the system development charges (SDC), potential funding
sources, and the impacts of sanitary sewer improvements on sewer rates.
To aid in finding individual projects, projects have been separated in sections by facility type:
• “LS” = Lift Station
• “P” = Pipeline
• “G” = General
Figure ES.2 displays the various facility types of capital improvement program (CIP) allocation.
EXECUTIVE SUMMARY | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | ES-9
Figure ES.2 Cost by Facility Type
ES.9 Financial Analysis
A Wastewater Revenue Requirement Model (WRRM) was conducted in 2018 to analyze the
future finances of the City. The LRWWMP’s CIP differs from the WRRM CIP; therefore, the
LRWWMP analyzed the City’s financial capacity to implement the LRWWMP CIP. This analysis
showed the City has the financial capacity to execute the LRWWMP CIP. Differences between
the 2018 WRRM and LRWWMP CIP timing will create larger drawdowns of the reserve fund in
the coming years, but still remain above the City’s minimum requirements. By 2025 it is expected
that the reserve fund will begin building up again.
The City is not committed to CIP spending summarized in the LRWWMP. Per the City budgeting
policy, the Utility’s spending is based on a biannual budget approved by the City Council. Due to
COVID-19, short term revenue could not be predicted, but it is expected that this will likely not
heavily impact any long-term analysis. If reductions in revenue persist due to COVID-19 or other
economic factors, then CIP projects may be delayed.
CHAPTER 1 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 1-1
Chapter 1
INTRODUCTION
1.1 Introduction
The purpose of the City of Renton’s (City) Long-Range Wastewater Management
Plan (LRWWMP) is to present policy and an assessment of the system to recommend facility
improvements. The LRWWMP is intended to provide a road map for redevelopment and
maintaining a high level of service for existing customers. The existing system is aging and will
continue to require investment to maintain a high level of service. The LRWWMP is intended to
provide the City with a "living" plan that can be used and adapted to assist in decision making for
the next 20 years, both financially and for infrastructure capacity and condition.
The LRWWMP results from an evaluation of the existing sanitary sewer system which provides
the groundwork for recommendations to resolve existing deficiencies and concerns, as well as
accommodating growth. This chapter presents the objectives of this LRWWMP, and a brief
overview of the City’s wastewater collection system. A list of abbreviations is provided in the
Table of Contents to assist the reader in understanding the information presented in this
LRWWMP.
This LRWWMP and recommended improvements were prepared in accordance with
requirements of Washington Administrative Code (WAC) 173-240-050, which is administered by
the Washington State Department of Ecology (Ecology), and meets the requirements of the
Washington Growth Management Act (GMA).
1.2 Background and Goals
The City is located in King County (KC), near Seattle, Washington. It is southeast of downtown
Seattle and adjacent to Lake Washington and the Cedar River, as shown in Figure 1.1. The City
owns and operates most of the sewer collection system within the City limits, as well as in nearby
jurisdictions including Kent, Tukwila, and incorporated KC. The City discharges wastewater to
the KC Interceptor where it is conveyed to KC’s South Treatment Plant located in the City.
This LRWWMP is the fourth of plans developed previously in 1992, 1998, and 2010. The
LRWWMP provides a recognized framework for making decisions about Renton’s sanitary sewer
service area which includes properties both inside and outside the City limits. It is intended to aid
decision-makers as well as users, including the Wastewater Utility, City Council members, the
Mayor, City staff, builders, developers, community groups, and other government agencies. The
LRWWMP is a useful tool in the following ways:
• As a framework for improvements and operations that govern sanitary sewer system
developments in the Renton Wastewater Utility service area. The LRWWMP provides a
basis for the following:
- Allocating improvements
- Allocating costs to new sanitary sewer system users
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 1
1-2 | MARCH 2021
• To provide guidelines for improving the existing system to maintain a high quality of
service at a reasonable cost
• To provide a basis of accommodating changes that occur which can’t be forecasted. To
this end, the LRWWMP lists policy issues and operational criteria that can be used to
developed alternatives and directions for development, improvements, and operations
1.3 Referenced Documents
This update to the LRWWMP is inspired by the need to provide constant evaluation of the sewer
system and operating policies in order to meet the needs of the customers and to ensure
compatibility with the City’s comprehensive plans.
The following documents were referenced in the preparation of this LRWWMP:
• King County Comprehensive Plan 2016 (King County, Updated October 2018).
Establishes an overall direction for land use planning in KC. Note, land use used in the
hydraulic modeling was based on the 2012 Plan
• Criteria for Sewage Works Design (Ecology, 2008). Provides guidance for the design of
municipal sewer systems and establishes minimum requirements in the State of
Washington
• King County Countywide Planning Policies (King County, December 2012 Amended
June 2016). Provides framework for comprehensive plans for KC and cities within KC
• Washington Administrative Code, Title 173. Defines the structure of general sewer plans
• Stantec 2015 Model Update Report
• City of Renton 2010 Long-Range Wastewater Management Plan
• City of Renton 2015 Comprehensive Plan Amended December 2018
• King County Board of Health Code and Regulations
• City of Tukwila 2015 Comprehensive Plan
• City of Kent 2015 Comprehensive Plan
1.4 Washington State Requirements
The primary purpose of this LRWWMP is to develop a "living" document that is flexible and can
be readily modified to respond to ongoing redevelopment. The major objectives of the
LRWWMP are to identify capacity deficiencies in the wastewater collection system, develop
feasible alternatives to correct these deficiencies, and plan the infrastructure that will serve
future development.
The goals of this LRWWMP, to meet the requirements from the Washington State Criteria for
Sewage Works Design, include:
• Prepare the LRWWMP in compliance with WAC Chapter 173-240-050
• Prepare the LRWWMP to be consistent with KC Code 28.84.050 (pages 28-50). The
purpose and need for the proposed plan
Each WAC requirement is detailed in Table 1.1 as well as the location within the plan.
%&e
!"`
!"`
!"b
!"b
?ç
?è
?¿
?æ
?Æ ?¦
?í
Auburn
BeauxArts
BlackDiamond
Bellevue
Burien
Clyde Hill
Covington
Des Moines
Federal Way
HuntsPoint
Issaquah
King County KingCounty
KingCounty
King County
King County
King County
King County
King County
King County
King County
Kent
Kent
Kent
Kent
Medina
Mercer Island
Maple Valley
Newcastle
Redmond
Renton
Seattle
Sammamish
SeaTac
Tukwila
YarrowPoint
Last Revised: June 12, 2019F:\KRCD DRIVE\Renton\9971A00\Vicinity Map.mxd
Figure 1.1
Vicinity Map
CHAPTER 1 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
O
0 2 41Miles
Legend
City of Renton
Other City Boundaries
Roads
Waterbodies
CHAPTER 1 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 1-5
Table 1.1 WAC Plan Requirements
Requirement Location in Plan
Purpose and need for the proposed plan Chapter 1
Discussion of who will own, operate, and maintain the system Chapter 2
Existing and Proposed Service Boundaries Chapter 2
Layout map including:
• Proposed sewers and areas proposed to be served by each
• Boundary lines of municipality or district and vicinity
• Existing sewers and areas served by each
• Topography and elevations of existing and proposed ground
• Information on streams, lakes, other bodies of water, and discharges
• Information on water systems
Figures 2.1 and 2.2
Figure 1.1
Figure 2.2
Figure 2.3
Figure 2.4
Figure 2.4
Population trends and methods used to determine those trends Table 4.1
Information on existing wastewater facilities in the area Chapter 2
Discussion of infiltration and inflow problems Chapter 5
Discussion of the provisions for treatment, discharge, and reuse Not included, service
performed by KC
Information on facilities producing industrial wastewater Chapter 5
Information on existing wells or other water supply sources Chapter 2
Discussion of alternatives evaluated and alternatives chosen Chapter 6, Chapter 8
Information on existing and proposed cost per service Chapter 9
Statements regarding compliance with SEPA and, if applicable, NEPA Appendix A
Note:
Abbreviations: SEPA – Washington State Environmental Policy Act; NEPA – National Environmental Policy Act.
1.5 Report Organization
This LRWWMP contains nine chapters, followed by appendices that provide supporting
documentation for the information presented in the report. The chapters are briefly described
below:
Chapter 1 – Introduction: This chapter presents the need for this LRWWMP and the objectives
of the study. Lists of abbreviations and reference materials are also provided to assist the reader
in understanding the information presented.
Chapter 2 – Overview of Existing Sewer System: This chapter describes the existing
wastewater collection system.
Chapter 3 – Operational Policies and Criteria: This chapter presents the policies for ownership,
operations, and maintenance of the collection system. It also reviews the criteria for evaluating
the wastewater collection system.
Chapter 4 – Planning Considerations: This chapter presents a description of the study area,
defines the planning horizon for this study, and summarizes the land use classifications. Lastly,
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 1
1-6 | MARCH 2021
this chapter summarizes the methodology and results for estimating existing and future sanitary
sewer flows resulting from the flow monitoring program.
Chapter 5 – System Analysis and Results: This chapter discusses hydraulic evaluation of the
wastewater collection system.
Chapter 6 – Replacement and Rehabilitation Program: This chapter describes the City’s
prioritized rehabilitation and replacement program.
Chapter 7 – Operations and Maintenance: This chapter presents the operational and
maintenance programs from the 2012 Operations and Maintenance (O&M) Plan.
Chapter 8 – Capital Improvement Program: This chapter describes the improvements
necessary to resolve existing and future deficiencies and accommodate growth. The proposed
improvements are also listed by priority and project type.
Chapter 9 – Financial Analysis: This chapter evaluates the financial status of the City’s water
utility and the ability to finance CIP projects.
Additionally, Technical Memoranda (TMs) are included in the appendices as follows:
Appendix G – TM No 1: Rain and Flow Monitoring and Projections
Appendix H – TM No 2: Model Development and Calibration
Appendix I – TM No 4: Risk Findings
Other appendices included are as follows:
Appendix A – SEPA Checklist
Appendix B – Agency Comment Letters and Responses
Appendix C – Approvals
Appendix D – Hydraulic Model and Deficiency Results
Appendix E – Service Agreements
Appendix F – Stantec Model Update and Capacity Analysis Report
Appendix J – Standard Plans and Specifications
Appendix K – CIP Detail Sheets
1.6 Key Issues
This LRWWMP addresses the following key issues:
• The need and timing of the replacement of older, deteriorating sanitary sewer facilities
within large, neighborhood-size areas within the City
• The evaluation of the City’s system capacity to address both system deficiency and
potential development
• The evaluation of sanitary sewer lift stations and force mains for removal, rehabilitation,
and replacement
• The City’s Infiltration and Inflow (I/I) program in coordination with the overall KC
program to evaluate options and needs for I/I reduction
CHAPTER 1 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 1-7
• Review, monitoring, and coordination with the public to eliminate industrial waste and
grease discharges to the sewer system
• Implementation of recommended improvements by priority which maintains affordable
rates for the system users
Some of these issues were also addressed during preparations of the 1992, 1998, and 2010
LRWWMP.
1.7 SEPA and Approval Process
A SEPA Checklist has been prepared for this LRWWMP and is presented in Appendix A. It is
anticipated that this proposed LRWWMP will not have a probable significant adverse impact on
the environment and that an environmental impact statement (EIS) will not be required.
However, many of the projects proposed herein will require SEPA checklists and an engineering
determination will be made with each individual project.
This LRWWMP includes review by adjacent utility systems. All comments are included in
Appendix B, Agency Comment Letters and Responses.
1.8 Acknowledgements
Carollo Engineers, Inc. (Carollo) and their team members, including ADS Environmental
Services, LLC, would like to acknowledge and thank the following individuals for their efforts and
assistance in completing this LRWWMP. Their cooperation and courtesy in obtaining a variety of
necessary information were valuable components in completing and producing this report:
• David Christensen, City of Renton, Wastewater Utility Engineering Manager
• Don Ellis, City of Renton, Engineering Specialist – Geographic Information System (GIS)
• Ann Fowler, City of Renton, Senior Engineer
• Richard Marshall, City of Renton, Wastewater Maintenance Manager
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-1
Chapter 2
OVERVIEW OF EXISTING SEWER SYSTEM
2.1 Overview of Existing System
The City of Renton (City) currently provides sanitary sewer service to approximately 25.6 square
miles both inside and outside the City limits. Overall, the City’s collection system contains
approximately 14,000 customer connections. The City’s collection system is municipally owned,
operated, and maintained; the system is managed by the City’s Public Works Department (Public
Works).
The City's collection system consists of approximately 247 miles of gravity mains (1,304,160 feet),
over 6,700 manholes, 5.16 miles (27,433 linear feet [LF]) of force mains (FMs), and 20 lift stations
that collect and convey wastewater to King County’s (KC’s) regional transmission interceptors.
These interceptors convey the City’s flow to the KC owned and operated South Treatment Plant
for treatment.
Figure 2.1 presents the City's existing collection system. A more extensive description and
analysis of the system can be found in Chapter 5 – System Analysis and Results.
2.2 System Components
The purpose of a sanitary sewer is to convey wastewater from its source to a point of treatment.
Since the generation of wastewater can vary considerably, there is seldom any control over the
volume of wastewater that must be conveyed at any particular time. For this reason the sanitary
sewer system is designed to accommodate a wide range of wastewater flow rates.
The best method for conveying wastewater is a gravity sewer system. A gravity sewer system is
made up of collector sewers, which as their name implies, collect the wastewater from the
various sources. These collector sewers then convey the wastewater to interceptor sewers,
which convey it to the point of treatment. The sanitary sewer system must be capable of
transporting all of the constituents of the wastewater stream, which include the suspended
solids, floatable solids and liquid constituents. In general, most of the floating materials are
carried along with the flow stream; however, suspended solids have a tendency to settle out of
the waste stream, unless minimum carrying velocities are achieved. This requires that the
sanitary sewers be constructed with a minimum slope to create a gravity flow that will result in a
velocity that will continuously carry the suspended solids portion of the waste stream.
Another major sewer system component, and typically the most vulnerable, is the sewage lift
station. A lift station is needed when the sanitary sewer system must overcome topographic
restrictions that make it impossible or financially unfeasible to construct a gravity sewer.
However, some lift stations are temporary, used only until the gravity sewer system can be built.
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
East Renton Interceptor
East Side Interceptor
South Interceptor
South Renton Interceptor
May Creek Interceptor
Cedar River Trunk Interceptor
Shy CreekLiftstation
Devils ElbowLift Station
East ValleyLift Station
Talbot CrestLift Station
Long LiftStation
KensingtonCrest Lift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash.Flush Lift Station
Stone GateLift Station
Falcon RidgeLift Station
Liberty LiftStation
Lake WashingtonBeach LiftStation Pipers BluffLift Station
Baxter LiftStation
Misty CoveLift Station
Airport LiftStation 12''24''
12''42''12''
36''
1 2 ''8'
'
12 ''
2
4
''12''6''12''1 2 ''
12 ''
24''
12''
24''
18''
12''18''12''12''48''12'
'
12 ''12''12''12''12''1 2 ''12''12''12''24''12''18''12''12''12''18''12''
1 2 ''
8 ''15''12''12''12''12''12''
12''12''12''12''12''
15''
2
4''12''18''12''1 2 ''12''12''12''24''18''36''
36''12''12''12''10''12 ''
30 ''12''12''18''
12''12''12''12''12''12''12''12''
12''
1 2 ''5 4 ''72''24''12''1 2 ''12''12''12''12''18''1
2''
12''
12''
12''12''
12''48''36''27''
18''24''12''
4 8 ''
1 2 ''12''8''12''12''12''18''12''12''48''18''
1 8 ''12'
'12''2 4 ''12''
2
4''
2
4''
12''
18''36''12''
24''
18''18''
1 2 ''12''30''12''24''12''12''12''30''12''12''8'
'
18''24''60''12''15''
24 ''12''18'
'12''24''
3
6
''15''24''
1 2 ''24''12''
24''12''12''8''18''
60''
12''24''18''18''48''18''12''12''1 2 ''
12''
1
8
''18''18''12''1
0''
12''
1
2
''
12''24''1 2 ''12''30''
18''
1 8 ''12''15''60''12''30''18''36''30'
'12''24''
18''
12''12''12''24''
1 2 ''24''18''1
2''
36''12''12''18''
12''
12''
12''12''12''
8''
2
4''
12''
18 ''10''8''
12''12''12''36''1 2 ''
18''24''24''12''12''18''18''12''
60''
12''12''8''
12''
12''12''1
8''
1 2 ''12''12''18''30''1
2''30''12''24''12''12''10''
12''
12''18''1
2
''12''54''12''
21''
12''
1 5 ''24''24''24''12''12''36''1
5''
12''15''1
2''12''12''18''24''12''12''12''12''
2
4
''
12''
15''54''
18''
12''36''
8''12''12''
1
2
''60''60''36''12''12''24''12'
'48''12''12'
'12''1 2 ''12''12''12 ''24''1 2 ''12''1 2 ''
12''
12''
60''12''12''12''8''18''12''15''12''8''15''
12''12''36''3 6 ''1 2 ''1 2 ''8''
12''
12''
12''
12''
12''15'
'
15''30''36''18''12''18''18''12''
72''
12''18''48''
12''12''1 8 ''12''36''36''1
8''20''18''
1 2 ''8''18''4''18''36''12''
18''
12''
54''
36''
2 0 ''2 4 ''Last Revised: March 04, 2021
\\io-fs-1\Data\GIS\GISBackup\Renton\
WaterSystemPlan2017\Existing_System.mxd
O
0 10.5
Miles
Legend
Lift Station
3Ú City of Renton
3Ú King County
Gravity Pipeline by Diameter
Unknown
< 8"
8"
10" - 18"
> 18"
City of Renton Force Main
King County Gravity Main
Study Area
Renton City Boundary
Roads
Waterbodies
CHAPTER 2 | LONG RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: City of Renton
Figure 2.1 Existing System
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-5
2.3 Wastewater Collection Basins
The City is divided into six major wastewater collection basins and 67 mini-basins illustrated in
Figure 2.2 that consist of one or more model basins. Wastewater basins delineate large areas of
the conveyance system network that ultimately flow to one location, specifically the regional
interceptor running throughout the City's collection system. The basin boundaries almost always
follow topographic features, such as ridge lines, streams, and rivers, and capture each property
contributing flow to the sewer collectors in that basin.
The model basins were developed by KC’s Infiltration and Inflow (I/I) Program for the Renton
Sewer Service Area. These collection basins and model basins would ideally follow the natural
drainage patterns of the City’s service area. However, because of natural and service area
boundaries, the wastewater collection basins do not always follow drainage basins. The six major
basins are: West Cedar River, East Cedar River, East Lake Washington, Black River, Downtown,
and May Valley.
2.3.1 We st Cedar River Basin
The West Cedar River Basin includes the eastern portion of the City bordering the Cedar River.
The basin consists of primarily single-family and multi-family developments with some
commercial and light industrial land uses. West Cedar River Basin includes the Cottonwood,
Falcon Ridge, and Kensington Crest Lifts Stations. The wastewater collected in the basin is
transported to KC’s Cedar River Trunk Interceptor at several connection points.
2.3.2 East Cedar River Basin
The East Cedar River Basin is located at the east side of the City’s sanitary sewer service area.
The basin extends from approximately Bremerton Avenue NE to the Urban Growth Boundary
east of the City. The basin can be partially served by gravity through the East Renton Interceptor.
The East Cedar River Basin includes the Shy Creek and Liberty lift stations. The wastewater
collected in the basin is transported to KC’s Cedar River Trunk Interceptor at several connection
points.
2.3.3 East Lake Washington Basin
The East Lake Washington Basin is located in the northern part of the City. The City serves the
entire basin, which consists of a variety of land uses including single-family and multi-family
residential, and light commercial. The wastewater collected in the basin is transported to
KC’s East Side Interceptor at several connection points. The East Lake Washington Basin includes
the Devil’s Elbow, Lake Washington Beach, Lake Washington Flush, Lake Washington #2, Long,
Stone Gate, Pipers Bluff, Wedgewood, and Westview Lift Stations.
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
East Valley RdRai
ni
er Ave NS 133rd St
Oakesdale Ave SWBens
on Dr
SSW 7th St
140th Ave SENE SunsetBlvd
§¨¦405
Maple Valley Hwy 164th Ave SECedar River Trail
S E J o n e s R d
Lake Youngs Service RdSE May Valley Rd
Union Ave NESE Petrovitsky Rd
§¨¦5
Shy CreekLiftstation
Devils ElbowLift Station
East ValleyLift Station
Talbot CrestLift Station
Long LiftStation
KensingtonCrest Lift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash.Flush Lift Station
Stone GateLift Station
Falcon RidgeLift Station
Liberty LiftStation
Lake WashingtonBeach LiftStation Pipers BluffLift Station
Baxter LiftStation
Misty CoveLift Station
Airport LiftStation
41
40
23
54
U9
46
29
52
05
06
02
48
17 43
19
49
13
18
47
30B
30C
30C(West)
38A 38B
34
35
36
10
11
ESI1003
15
12
0809
24
37
01
07
45
03
RENT6504
CEDAR02A
32
39
30A
50
16
14
27
44
46(North)
U3
25
22
20
2133
42
26
U2
U8
U7
U4
U6
28
BA
U1
Last Revised: July 08, 2020 \\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Mini_Subasins.mxd
O
0 10.5 Miles
Legend
Lift Station
3Ú City of Renton
3Ú King County
Gravity Pipeline
City of Renton Force Main
King County Force Main
King County Gravity Main
2012 Renton Minibasins
Study Area
Renton City Boundary
Collection Basins
Black River Basin
Downtown Basin
East Cedar River Basin
East Lake Washington Basin
May Valley Basin
West Cedar River Basin
Roads
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton
CHAPTER 2 | LONG RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 2.2 Wastewater Basins
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-9
2.3.4 Black River Basin
The Black River Basin is a large drainage basin in the southwest part of the City. The higher
elevations in the Rolling Hills, Talbot Hill, and Panther Creek areas are generally single-family
and multi-family residential developments along with commercial uses surrounding
Valley Medical Center, while the valley floor is generally industrial and commercial land uses.
A portion of the south and west portions of the valley floor are un-modeled. The upper
elevations of the basin are served by Soos Creek Water and Sewer District. The Black River Basin
includes the East Valley, Lind Avenue, and Talbot Crest Lift Stations. The wastewater collected
in the basin is transported to KC’s East Side, South Renton, and South Interceptors at several
connection points.
2.3.5 Downtown Basin
The Downtown Basin is located in the northwest part of the City and includes the
Central Business District, West Hill, and North Renton Industrial areas. Land use within the basin
consists of single-family, multi-family, commercial, and heavy industrial land uses. The model
basin includes the Airport Lift Station. Skyway Water and Sewer District also provides sewer
service to parts of the West Hill that are within the Downtown Basin. The wastewater collected
in the basin is transported to KC’s East Side Interceptor at several connection points.
2.3.6 May Valley Basin
The May Valley Basin is located in the northeast part of the City on the periphery of the City's
current service boundary. The portion of the basin within the City’s service area is currently only
about half serviced with a sewer collection system. The remainder of the basin is within
Coal Creek Utility District’s service area. Land use within the basin consists of primarily
single-family and light commercial land uses. The May Valley Basin includes the Baxter and
Misty Cove Lift Stations. The wastewater collected in the basin is transported to KC’s May Creek
Interceptor and East Side Interceptor at several connection points.
2.4 Interceptors and Collection Systems
Interceptors are sewers that receive flow from collector sewers and convey wastewater to a
point for treatment or disposal. They are typically located in low lying or centralized areas in
order to facilitate the gravity flow of the wastewater. The interceptors and all other sewers make
up the collection system.
2.4.1 Existing Sewer System
Currently, the City’s gravity mains consist of approximately 60 percent polyvinyl chloride (PVC),
25 percent concrete pipe (CP), 5 percent ductile iron pipe (DIP), 3 percent vitrified clay
pipe (VCP), and 6 percent unknown pipes. The majority of pipe material within the existing
system is comprised of CP and PVC. Older sewers typically used concrete pipe, while PVC is
more common in newer sewer installations.
As shown in Table 2.1, a majority of the sanitary sewer system is constructed with 8-inch
diameter pipe. This is consistent with the Department of Ecology’s criteria for minimum sanitary
sewer sizing.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 2
2-10 | MARCH 2021
Table 2.1 Gravity Sewer Inventory
Diameter (inch) Length (LF) Percentage of System
6 42,426 3.2%
8 1,033,293 79.1%
10 52,746 4.0%
12 82,153 6.3%
14 1,001 0.1%
15 35,143 2.7%
16 358 0.0%
18 25,605 2.0%
20 745 0.1%
21 8,826 0.7%
22 3,751 0.3%
24 20,066 1.5%
Total (feet) 1,306,113 100%
Total (miles) 247.4 100%
Note:
(1) System only includes gravity mains and excludes private sewers and KC pipes.
The City’s sanitary sewer system also contains 6,735 manholes which join the various links of
sanitary sewer pipe. These manholes vary in construction type from brick manholes to precast
concrete manholes.
2.4.2 Interceptors
KC connections receive wastewater from the City’s collection system at more than 79 locations.
This sewage is then either conveyed to another drainage basin or directly to the South Treatment
Plant for treatment.
2.5 Lift Stations and Force Mains
Sewage lift stations are used to convey wastewater from a low point to a higher point through
the use of a pump and pressurized FM. The City owns and maintains 20 lift stations, which are
described in Table 2.2. The topography of the City’s service area is such that most of the system
is operated under gravity flow conditions with the exception of some areas that require pumping
to higher elevations. The topography of the system is shown in Figure 2.3. Details on FM and lift
station condition are in Chapter 6 – Replacement and Rehabilitation Program.
The most common type of lift station is comprised of a wet well which contains a submersible
pump located directly in the wet well. The second most common type of lift station is a
configuration with the mechanical and electrical equipment located above the ground surface
and over a large manhole wet well from which the wastewater is pumped. A wet well/dry well
configuration is the third most common type; this is comprised of electrical and mechanical
equipment located underground in a sealed enclosure adjacent to a large manhole which the
wastewater is pumped. Additionally, the West View Lift Station contains a grinder submersible
combination.
East Valley RdRai
ni
er Ave NS 133rd St
Oakesdale Ave SWBens
on Dr
SSW 7th St
140th Ave SENE SunsetBlvd
§¨¦405
Maple Valley Hwy 164th Ave SECedar River Trail
S E J o n e s R d
Lake Youngs Service RdSE May Valley Rd
Union Ave NESE Petrovitsky Rd
§¨¦5
O
0 10.5 Miles
Legend
Study Area
Roads
Waterbodies
DEM in FeetHigh : 180'
Low : 5'
Last Revised: August 20, 2019 \\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Topography.mxd
CHAPTER 2 | LONG RANG E WASTEWATER MANAG EMENT PLAN | CIT Y OF RENTON
Figure 2.3 Topography
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-13
2.5.1 Airport Lift Station
The Airport Lift Station is located on the west side of West Perimeter Road adjacent to the
Renton Municipal airport. This facility is a duplex submersible pump system in a wet well with an
adjacent valve vault and an on-site back-up emergency generator. This facility serves the
southern portion of the west side of the airport as well as approximately 37 acres of residential
and commercial properties west of Rainier Avenue South. The current lift station was
constructed in 2014.
2.5.2 Baxter Lift Station
The Baxter Lift Station is located in the former J.H. Baxter and Company pole yard near the
southeast corner of the southern-most football practice field of the Virginia Mason Athletic
Center (VMAC) Seattle Seahawks training facility and adjacent to the King County Trail. This
facility operates as a duplex submersible pump system in a wet well that also contains a third
pump that can be operated manually if needed. This station has an adjacent valve vault and an
on-site back-up emergency generator. This facility serves the VMAC Seattle Seahawks Training
facility as well as the Barbee Mill neighborhood to the south. The current lift station was
constructed in 2008.
2.5.3 Cottonwood Lift Station
The Cottonwood Lift Station is located west of the Riviera Apartments, south of the Maple Valley
Highway. This station is a submersible pump duplex station in a wet well with an adjacent valve
vault. This facility serves the area between the Maple Valley Highway and the Cedar River, east
of the former Stoneway concrete facilities. The current station was constructed in 1994. The FM
was also replaced at that time. Upgrades to this lift station are currently in design phase.
2.5.4 Devil's Elbow Lift Station
The Devil's Elbow Lift Station is located in NE 27th Street just northwest of where the road
crosses Honey Creek. This facility is a submersible pump duplex station in a wet well with an
adjacent valve vault that also contains the control system. There is a trailer-mounted emergency
back-up generator located in the cul-de-sac of NE 24th Street. This generator is setup to
automatically power this station but can also be transported to other sites is needed. The current
station was constructed in 2000. Upgrades to this lift station are currently in design phase.
2.5.5 East Valley Lift Station
The East Valley Lift Station is located on the northwest corner of the intersection of
SW 34th Street and the East Valley Road. This facility operates as a submersible pump duplex
station. A secondary wet well with a third submersible pump is available for high peak or
emergency situations. The station also has an adjacent valve vault and an on-site backup
generator. This facility serves the commercial areas north and west of the lift station. The
current station was built in 2003. Pumps were replaced in 2019 due to damage sustained from a
private construction project. Additional upgrades to this lift station are currently in design phase.
2.5.6 Falcon Ridge Lift Station
The Falcon Ridge Lift Station is located at the east end of SE 8th Place in the plat of
Falcon Ridge. This station is a submersible pump duplex station in a wet well with an adjacent
valve vault and an on-site emergency generator. This station serves the Falcon Ridge
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 2
2-14 | MARCH 2021
neighborhood exclusively. The current station was constructed in 2019. The FM associated with
this station is long and has an excessively high head.
2.5.7 Kensington Crest Lift Station
The Kensington Crest Lift Station is located at the northeast corner of the Kensington Crest
(A.K.A. Shadowhawk) multi-family complex and provides service to the complex. This facility is a
submersible pump duplex station. The station was built in 2002.
2.5.8 Lake Washington Beach Lift Station
The Lake Washington Beach Lift Station is located in the south parking lot at Coulon Beach Park.
This facility is a duplex wet well with adjacent valve vault. The station serves the restroom
facilities at the park. The current station was constructed in 2011.
2.5.9 Lake Washington Flush Lift Station
The Lake Washington Flush Lift Station is located at the south end of Mountain View Avenue North.
The facility is a submersible, single, non-clogging pump for pumping lake water into the gravity
sewer along the Kennydale lakefront for flushing purposes. The low-pressure sewer Lake Line then
discharges into Lake Washington No. 2 Lift Station. A new pump, along with a new valve vault was
installed in 2004.
2.5.10 Lake Washington No. 2 Lift Station
The Lake Washington No. 2 Lift Station is located at the north end of the Kennydale Beach Park Road.
This facility serves lakefront properties west of Lake Washington Boulevard North in the Kennydale
area. The station is a submersible pump duplex station in a rehabilitated wet well. The current station
was constructed in 1994.
2.5.11 Liberty Lift Station
The Liberty Lift Station is located at 16655 SE 136th Street at Liberty High School. This facility is
a duplex submersible lift station in a wet well with adjacent valve vault. The current station was
constructed in 2012.
2.5.12 Lind Avenue Lift Station
The Lind Avenue Lift Station is located on the west side of Lind Avenue SW near the intersection
with SW 19th Street. This station is a submersible pump duplex station in a wet well with an
adjacent valve vault and an on-site emergency generator. This station serves the commercial
and industrial areas in the vicinity of the lift station. The current station was constructed in 2014
(City Project No. S-3626).
2.5.13 Long Lift Station
The Long Lift Station is located on the east side of Union Avenue NE, just north of NE 27th Street.
This facility is a submersible pump duplex station, which serves the Caledon Plat. The lift station
was constructed in 2001.
2.5.14 Misty Cove Lift Station
The Misty Cove Lift Station is located in the northeast corner of the Misty Cove Condominium
complex. This station is a submersible pump duplex station in a wet well with an adjacent valve
vault. This facility serves the lakefront properties that are north of the VMAC Seattle Seahawks
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-15
Training facility. The current station, along with a new force main was constructed in 2014 (City
Project No. S-3627).
2.5.15 Pipers Bluff Lift Station
The Pipers Bluff Lift Station is located at 1160 Ilwaco Place NE. This station is a submersible pump
duplex station in a wet well with an adjacent valve vault. This station serves the Piper’s Bluff plat
exclusively. The current station was constructed in 2015.
2.5.16 Shy Creek Lift Station
This station is located at the northeast corner of the intersection of SE 136th Street
& 142nd Avenue SE. This station is a submersible pump duplex station in a wet well with an
adjacent valve vault. A secondary, overflow wet well with a manually-operated third submersible
pump is available for high peak or emergency situations. The current station was constructed
in 2008.
2.5.17 Stone Gate Lift Station
The Stonegate Lift Station is located at 2615 Nile Avenue NE. The station is within an easement
on an open space tract in the Stonegate neighborhood. This station is a submersible pump
duplex station in a wet well with an adjacent valve vault. The station also includes an
underground overflow vault and an on-site emergency back-up generator. The facility serves the
entire plat of Stone Gate as well as several plats to the east and south. The current station along
with a new force main was constructed in 2012.
2.5.18 Talbot Crest Lift Station
The Talbot Crest Lift Station is located under the roadway at 2511 Talbot Crest Drive. This
facility is a submersible pump duplex station in a wet well with an adjacent valve vault. The
station serves the plat of Talbot Crest exclusively. The current station was constructed in 2000.
2.5.19 Wedgewood Lift Station
The Wedgewood Lift Station is located at 5401 NE 10th Street. This facility is a submersible
pump duplex station in a wet well with an adjacent valve vault. The wet well contains an overflow
area that also contains a third pump that can be operated manually if needed. The station serves
the plat of Wedgewood, as well as the surrounding basin area. The station was constructed
in 2006.
2.5.20 Westview Lift Station
The Westview Lift Station is located on the west side of Monterey Avenue NE. This facility is a
duplex submersible lift station designed to serve the twelve-lot Westview Plat. This station was
originally constructed in 1995. Upgrades including a new adjacent valve vault, wet well lining,
new pumps and hardware and electrical were performed in 2010.
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-17
Table 2.2 Existing Lift Station Inventory Summary
Name Location Station Type No. of Pumps* Manufacturer Normal Operating
Capacity (gpm)
Normal
Operating
TDH (ft)
hp
Pump
Speed
(RPM)
Voltage
Emergency
Power
Connect
Telemetry FM Size
(inches)
Airport 451 West Perimeter Road / Airport Submersible 1-Duty
1-Standby
Flygt
Flygt
100
100
54
54
10
10
1735
1735 460 Yes Allen Bradley
Compact Logix 4
Baxter 4505 Ripley Lane Submersible
1-Duty
1-Standby
1-Flow Transfer
Flygt
Flygt
Flygt
450
450
250
21
21
15
5
5
3
1745
1745
1700
460 Yes Rugid 9 8
Cottonwood 2101 Maple Valley Highway Submersible
1-Duty
1-Standby
1-Flow Transfer
Hydromatic
Hydromatic
Paco
230
230
-
32.5
32.5
-
3
3
-
1750
1750
-
230 / 460
115 Yes Rugid 6 4
Devil's Elbow 3001 NE 27th Street Submersible 1-Duty
1-Standby
Flygt
Flygt
500
500
155
155
35
35
3520
3520 460 Yes Rugid 6 6
East Valley 3371 East Valley Road Submersible
1-Duty
1-Standby
1-Flow Transfer
Flygt
Flygt
Flygt
362
362
362
30.5
30.5
30.5
5
5
5
1735
1735
1735
230/460 Yes Rugid 9 8
Falcon Ridge 2471 SE 8th Place Submersible 1-Duty
1-Standby
Flygt
Flygt
230
230
82.7
82.7
11
11
3495
3495 460 Yes Allen Bradley
Compact Logix 4
Kensington Crest 3000 SE 8th Street Submersible 1-Duty
1-Standby
Flygt
Flygt
160
160
80
80
10
10
1745
1745 460 Yes Rugid 9 4
Lake Washington Beach 1201 Lake Washington Boulevard N Submersible Grinder 1-Duty
1-Standby
Vaughn
Vaughn
125
125
24
24
5
5
1725
1725 230 Yes Rugid 9 4
Lake Washington Flush 2725 Mountain View Avenue North Submersible 1-Duty Paco 400 6.5 2 1150 120/240 Yes Rugid 6 4
Lake Washington No. 2 3903 Lake Washington Boulevard N Submersible 1-Duty
1-Standby
Hydromatic
Hydromatic
385
385
35
35
7.5
7.5
1750
1750 480 Yes Rugid 6 6
Liberty 16655 SE 136th Street Submersible 1-Duty
1-Standby
Flygt
Flygt
617
617
69
69
20
20
1755
1755 460 Yes Allen Bradley
Compact Logix 8
Lind Avenue 1891 Lind Avenue SW Submersible Grinder 1-Duty
1-Standby
Vaughan
Vaughan
500
500
12
12
7.5
7.5
1170
1170 480 Yes Allen Bradley
Compact Logix 8
Long 5702 Union Avenue NE Submersible 1-Duty
1-Standby
Flygt
Flygt
100
100
90
90
10
10
1735
1735 230/460 Yes Rugid 6 4
Misty Cove 5023 Ripley Lane N Submersible 1-Duty
1-Standby
Flygt
Flygt
190
207
32
32
4
4
3430
3430 460 Yes Allen Bradley
Compact Logix 4
Pipers Bluff 1160 Ilwaco Place NE Submersible 1-Duty
1-Standby
Flygt
Flygt
106
105
66.7
66.7
4
4
3430
3430 460 Yes Allen Bradley
Compact Logix 4
Shy Creek 5110 SE 2nd Place Submersible
1-Duty
1-Standby
1-Flow Transfer
Flygt
Flygt
Flygt
550
550
275
40
40
15
10
10
3
1735
1735
1700
460 Yes Rugid 9 8
Stonegate 2615 Nile Avenue NE Submersible 1-Duty
1-Standby
Flygt
Flygt
425
425
172
172
85
85
1775
1775 460 Yes Rugid 9 8
Talbot Crest 2511 Talbot Crest Drive South Submersible 1-Duty
1-Standby
Flygt
Flygt
110
110
33
33
3
3
1700
1700 460 Yes Rugid 6 4
Wedgewood 5401 NE 10th Place Submersible
1-Duty
1-Standby
1-Flow Transfer
Flygt
Flygt
Flygt
505
511
400
67.2
67.2
11
15
15
3
1755
1755
1680
460 Yes Rugid 9 8
Westview 1149 Monterey Avenue NE Submersible 1-Duty
1-Standby
Flygt
Flygt
70
70
34
34
3.8
3.8
3395
3395 1740 Yes Rugid 6 Bastard 3
Note:
Abbreviations: gpm – gallons per minute; TDH – total dynamic head; ft – foot/feet; hp – horsepower; RPM – revolutions per minute.
CHAPTER 2 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 2-19
2.5.21 Force Mains
A summary of the FMs is provided in Table 2.3. Additional information regarding lift stations and
FMs is provided in Chapter 6 – Replacement and Rehabilitation Program.
Table 2.3 Collection System Force Main Inventory
Diameter (inch) Length (LF) Percentage of System
2 6,970 19.3%
3 1,863 5.2%
4 10,996 30.4%
6 2,979 8.2%
8 12,282 34.0%
10 1,026 2.8%
Total (feet) 36,116 100%
Total (miles) 6.8 100%
2.6 Water System
The City provides water service to City customers from a series of groundwater wells. As shown
in Figure 2.4, there are ten reservoirs and one operational storage/equalizing detention clearwell
at the Maplewood Treatment and Booster Pump Station (BPS) Facility. These storage facilities
within the City total 22,877,053 gross volume gallons of water. The City operates 12 BPS to
convey treated water from low pressure zones to high pressure zones. Altogether, the City’s
water system is 1,629,560 feet (308.6 miles) with a majority 8-inch DIPs.
In 1992, the City adopted an Aquifer Protection Ordinance to protect its water supply from being
contaminated. The water facilities and aquifer protection areas are shown on Figure 2.4. The
ordinance regulates land use within the aquifer recharge area in order to protect the aquifer from
contamination and are defined as Critical Areas. As part of aquifer protection the City has
designated an aquifer protection area (APA), which is that area within the zone of capture for the
City's aquifers and spring. The APA is divided into three zones:
• Zone 1 encompasses the 1-year groundwater capture zone for the downtown wells.
Regulations adopted for this zone provide the strongest protection for the area that is
very close to the most important and vulnerable wells
• Zone 1 Modified encompasses the 1-year capture zones for the Maplewood, Wellfield,
and Springbrook Springs, which are partially outside of the City limits. Regulations are
somewhat less strict than those in Zone 1 and are intended to provide appropriate
protection for important wells/springs that are deep and/or partially protected by
intervening layers of relatively impermeable earth materials
• Zone 2 provides a level of protection adequate for areas that are further away from the
most important sources but still within the capture zone or for deep backup wells.
Zone 2 encompasses:
- The portion of the capture zone for downtown wells that lies between the 1-year
capture zone boundary and the City limits
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 2
2-20 | MARCH 2021
- The portion of the capture zone for Well 5A that lies within City limits
- The portion of the capture zone for Springbrook Springs that lies between
the 1-year capture zone boundary and the 10-year boundary
Land use in Zone 1 is more strictly regulated than in Zone 1-Modified or Zone 2. All new
development within Zone 1 must connect to the sewer system. Existing development must
connect if it is within 330 feet of a sewer line. In Zone 2, all new platted single-family, multi-family,
and commercial development must connect to the sewer system. However, a single-family
residence is required to connect only if it is within 330 feet of a sewer line. A more detailed
description of the proposed aquifer protection policies can be found in Chapter 3 – Operational
Policies and Criteria.
2.7 Operation and Maintenance
The current operation and maintenance program for the sewer utility consists of four elements:
normal operations, emergency operations, preventive maintenance and staffing. Normal
operation of the sewer system is shared by the Maintenance Services and Utility Systems
divisions. The program is described and evaluated in more detail in Chapter 7 – Operations and
Maintenance.
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú UT
UT
UTUT
UT
UT
UT
UT
UT
UT
UT
UT
3Q
3Q
3Q
!ã!ã!ã!ã
!ã
!ã!ã!ã!ã!ã
!ã
!ã
East Valley RdRai
ni
er Ave NS 133rd St
Oakesdale Ave SWBens
on Dr
SSW 7th St
140th Ave SENE SunsetBlvd
§¨¦405
Maple Valley Hwy 164th Ave SECedar River Trail
S E J o n e s R d
Lake Youngs Service RdSE May Valley Rd
Union Ave NESE Petrovitsky Rd
§¨¦5
LakeBoren
LakeDesire
SpringLake
Lake Youngs
Shady Lake
Lake Jolie
Ham Lake
PantherLake
Cedar River
Lake Washington
PW-5A
Highlands Chlorination Facility
HighlandsReservoirs
HazenReservoir
Mt Olivet Reservoir
EW-3R, PW-9,RW-1,2 & 3, PW-83Q
CorrosionControl Facility
West Hill Reservoir
MaplewoodChlorinationFacility
PW-10
PW-12
PW-11, PW- 17Rolling Hills Reservoirs494 & 594
North TalbotReservoir
South TalbotReservoir
Southbrook SpringsTreatment Plant
PW-4
Shy CreekLiftstation
Devils ElbowLift Station
East ValleyLift Station
Talbot CrestLift Station
Dennys LiftStation
Long LiftStation
KensingtonCrest Lift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash.Flush Lift Station
Stone GateLift Station
Falcon RidgeLift Station
Liberty LiftStation
Lake WashingtonBeach LiftStation Pipers BluffLift Station
Baxter LiftStation
Misty CoveLift Station
Airport LiftStation
Last Revised: September 06, 2019 \\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Water Facilities and Aquifer Protections.mxd
O
0 10.5 Miles
Legend
!ã Production Well
UT Reservoir
3Q Water Treatment Plant
Aqu ifer Protectio n Zones
Zone 1
Zone 1 Modified
Zone 2
Lift Station
3Ú City of Renton
3Ú King County
Gravity Pipeline
City of Renton Force Main
King County Force Main
King County Gravity Main
Study Area
Renton City Boundary
Roads
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton
CHAPTER 2 | LONG RANG E WASTEWATER MANAG EMENT PLAN | CIT Y OF RENTON
Figure 2.4Water Facilities andAquifer Protection Areas
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-1
Chapter 3
OPERATIONAL POLICIES AND CRITERIA
3.1 Introduction
The existing sewer system is designed and operated according to specific ordinances,
regulations, and engineering standards (hereafter collectively referred to as policies and criteria).
All of the policies originate from eight sources, listed in descending order, from those with the
broadest authority to those with the narrowest:
• Federal Regulation – Environmental Protection Agency
• State Regulations – Department of Ecology (Ecology)
• King County (KC) Policies – Department of Natural Resources – Wastewater Treatment
Division
• City of Renton Comprehensive Plan
• City of Renton Ordinances – City Council
• Administrative Policies – Mayor
• Department Policies – Public Works Department
• Long-Range Wastewater Utility Policies – Wastewater Utility Staff
Federal regulation, state regulations, county policies, and city ordinances dictate requirements
that are set by law. Policies that originate in the Office of the Mayor, Public Works, or
Wastewater Utility cannot be less stringent or in conflict with other, broader laws. Those policies
and criteria referencing the Long-Range Wastewater Management Plan (LRWWMP) have or will
become official policies with the adoption of the LRWWMP by City of Renton (City) City Council.
3.2 Operational Goal
The goal of the City’s Wastewater Utility is to provide adequate, reliable sanitary sewer
services at a minimum cost to the customer.
Guiding the Wastewater Utility’s daily operations as well as its planning activities, the policies in
this LRWWMP stem from this goal. Objectives and policies that fall into six areas of emphasis
support this broad service goal:
1. Customer Service
2. Planning Objective
3. Service Area Extension
4. Financial
5. Facility
6. Operations
The policies and criteria supporting each objective are provided below. Note, given the nature of
the content, this chapter is presented in traditional policy format, rather than outline format that
is used in other chapters. For actual wording of a given policy and criteria, refer to the indicated
source for complete text.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-2 | MARCH 2021
3.3 Customer Service Objective
Ensure the availability of an adequate level of sanitary sewer service that is consistent with
land use, environmental protection, and annexation goals and policies.
3.3.1 Policies
• Sewer facilities and services should be consistent with the growth and development
concepts directed by the Comprehensive Plan (Policy U-1, 2018 City of Renton
Comprehensive Plan)
• Ensure and encourage the use of the sanitary sewer system within the urban areas in a
manner consistent with land use and environmental protection goals and policies
(LRWWMP)
• All new developments should be required to connect to the sanitary sewer system, except
properties that have adequate soils to support on-site septic systems, are zoned for low
density single family residential development, located away from environmentally
sensitive areas, and outside Aquifer Protection Areas (Policy U-21, 2018 City of Renton
Comprehensive Plan)
• Actively promote connection to the public sewers by all residents within the City’s
service area (LRWWMP)
• Public sewer expansions shall not occur in the Rural Area and on Natural Resource Lands
except where needed to address specific health and safety problems threatening the
existing structures and the use of septic or other onsite wastewater systems has been
determined by KC to be not feasible; or to serve a new school authorized to be located in
the Rural Area by R-327 (Policy F-264.A, 2018 King County Comprehensive Plan)
3.3.2 Implementation
• The owner of each house, building or property used for human occupancy, employment,
recreation or other purpose, situated within the City and abutting on a public sanitary
sewer of the City which said public is hereby required at the owner’s expense to install
suitable toilet facilities therein and to connect such facilities directly with the proper
public sewer in accordance with the provisions of this Chapter, within ninety days after
the date of official notice to do so (Renton Municipal Code [RMC] 4-6-040.A)
• Where a public sanitary or combined sewer is not available under the provisions of
Title IV Chapter 6 of the RMC, the building sewer shall be connected to a private sewage
disposal system complying with the provisions of this section (RMC 4-6-040.A.1)
• The owners of private sewerage disposal systems shall operate and maintain the
facilities in a sanitary manner at all times at no expense to the City (RMC 4-6-040.I.4)
• The owner or occupant of lands or premises located within the urban growth
area (UGA) (as defined in the King County Comprehensive Plan) undertaking new
residential or nonresidential construction, short subdivision or subdivision from which
sewage will originate shall connect to a public sewer, provided the sewer utility permits
such connection (King County Board of Health Rules and Regulations [KCBHRR]
No. 3, 13.04.050)
• Sanitary sewers, together with all appurtenances, shall be constructed or deferred
before a final short plat is submitted or a short subdivision is recorded. Sanitary sewers
shall be constructed to specifications and standards of the Wastewater Utility,
approved by the Department and in accordance with other standards of the City. A
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-3
separate construction permit will be required for any such improvements, along with
associated engineered plans prepared per the City’s drafting standards and associated
fees (RMC 4-7-100)
• Unless septic tanks are specifically approved by the Planning/Building/Public Works
Department and the KC Health Department, sanitary sewers shall be provided by the
developer at no cost to the City and designed in accordance with City standards. Side
sewer lines shall be installed eight feet into each lot if sanitary sewer mains are available,
or provided with the subdivision development (RMC 4-6-040F)
• Development that is within two hundred feet of a public sewer, where an on-site
system (OSS) is operating, connection to the public sewer is required when the sewering
authority permits such connection and when:
- Repair, modification, or replacement of the system is necessary, or the existing OSS
has failed and an OSS fully conforming to this title cannot be designed and installed
(KCBHRR 13.04.050)
- At such time that additional construction which in any way affects the on-site
sewage system is proposed (KCBHRR No. 3, 13.04.050)
- They are part of a sewer Local Improvement District (LID) (RMC 4-6-040.A)
• New development (residential and non-residential) in Zone 1 of the Aquifer Protection
Area (APA) shall be required to connect to the City sewer system (RMC 4-6-040J.1.a.i)
• All existing development (residential and non-residential) in Zone 1 of the APA that is
within the specified proximity of existing or future gravity sanitary sewer shall be
required to connect to the City sewer system within two years of the availability of the
new sewer line (RMC 4-6-040J.1.a.iii)
• Any new development (residential and non-residential) in Zone 2 of the APA shall be
required to connect to the City sewer system (new single-family residential development
on existing lots may be allowed to use on-site disposal systems until public sewer service
becomes available, as determined by the Wastewater Utility) (RMC 4-6-040J.2.a.i)
• The City, at the discretion of the Wastewater Utility, may defer compliance with
non-health related standards dealing with extension, design, or capacity for temporary
sanitary sewer service. Temporary sanitary sewer service may include pump tests,
temporary discharge permits, connections for temporary construction sites, or other
similar usage. The property owner will retain the responsibility and will execute an
agreement to either directly or financially meet said standards at the direction of the
City (LRWWMP)
• After connection to the sewer system, all private sewage disposal facilities shall be
abandoned and filled with suitable material; provided, however, the owner of the
subject premises may suitably clean the septic tank to utilize the same and any adjoining
drain field systems for the disposal of stormwater (RMC 4-6-040.I.6)
3.4 Planning Objective
Ensure that the City’s sewage collection system is consistent with the public health and water
quality goals of Washington State (Policy U-F, 2018 City of Renton Comprehensive Plan).
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-4 | MARCH 2021
3.4.1 Policies
• Sewer facilities and services should be consistent with the growth and development
concepts expressed in the Land Use Element. Extension of sewer service should be
coordinated with expected growth and development. (Policy U-20, 2018 City of Renton
Comprehensive Plan)
• Apply level of sanitary sewer service standards consistently throughout the service area
(LRWWMP)
• Sewer system improvements supporting areas of the City projected to experience high
levels of growth should be prioritized to ensure that sewer service is concurrent with
anticipated growth. (Policy U-25, 2018 City of Renton Comprehensive Plan)
• Timely and orderly extension of the sewer system should be provided within the City’s
existing and future service areas to meet public health requirements (Policy U-24,
2018 City of Renton Comprehensive Plan)
• Implementation and coordination of programs for the improvement, phasing and
financing of sewer infrastructure should be developed consistent with the Land Use
Element of the Comprehensive Plan (LRWWMP)
• Approval of development should be conditioned on the availability of adequate utility
service and should not result in decreases in local levels of service for existing
development. All new development should be required to pay their fair share of
construction costs for necessary utility system improvements (Policy U-5, 2018 City of
Renton Comprehensive Plan)
• Sewer facilities and services should be in place prior to occupancy of development
projects (LRWWMP)
• Sewer service should be expanded so that the current levels of service are maintained
through build-out of the adopted land use (LRWWMP):
- Note: While land use plans typically deal with twenty-year projections, the sewer
facilities installed today have a life expectancy of 75 to 100 years. A Sanitary Sewer
Utility has to consider the current Land Use Plan, historical trends, and predictions
for further growth when designing sewers. The Wastewater Utility may install a
facility larger than needed for the land use projected in the 20-year plan if additional
capacity needs are projected for the long-term future. It is in the best interests of
the ratepayers to obtain the longest use possible from a facility and not have to
replace newer facilities
• Continue coordination with KC Wastewater Treatment Division regarding
Inflow/Infiltration reduction initiatives, system improvements, and interconnections
between City and KC sewer infrastructure (Policy U-27, 2018 City of Renton
Comprehensive Plan)
• Protect surface and groundwater quality through coordination with KC to reduce
surcharging conditions that may cause wastewater overflows (Policy U-26, 2018 City of
Renton Comprehensive Plan)
• Coordinate with non-City sewer providers operating within the City and neighboring
jurisdictions to accommodate road construction and other public works projects (Policy
U-23, 2018 City of Renton Comprehensive Plan)
• For planning purposes, the Wastewater Utility should use sanitary sewer service
boundaries established by agreement with adjacent municipalities. Where boundaries
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-5
do not exist, the Wastewater Utility shall use natural basins, KC’s Urban Growth
Boundary (UGB), and negotiations with adjacent sewer service providers to determine
the ultimate service area (LRWWMP)
• Facilities should be planned and sized to serve natural basins to minimize the need for
pumping and inter-basin transfers (LRWWMP)
• Projected sewage flows from development should be calculated based on adopted land
use plans and policies. These projections should be used as a guide in developing the
wastewater Capital Improvement Program (CIP). The CIP should be updated as land use
plans and policies are revised (Policy U-22, 2018 City of Renton Comprehensive Plan)
3.5 Service Area and Extension Objectives
Ensure the availability of an adequate level of sanitary sewer service to areas annexing to
the City or areas within the City’s Potential Annexation Area (PAA).
3.5.1 Policies
• Support annexation where infrastructure and services allow for urban densities, service
providers would be consolidated, and/or it would facilitate the efficient delivery of
service. (Policy L-8, 2018 City of Renton Comprehensive Plan)
• Ensure the availability of an adequate level of sanitary sewer service through system
planning that is consistent with land use, environmental protection, and annexation
goals and policies (Goal U-E, 2018 City of Renton Comprehensive Plan)
• The City will follow state guidelines that define a City's ability to assume facilities in
annexation areas (LRWWMP)
• The City may assume existing portions of adjacent sanitary sewer systems, at the
discretion of the City Council, when such assumptions promote the logical and efficient
development of the City’s sanitary sewer system (LRWWMP)
• Allow the extension of sanitary sewer services within the City’s PAA according to such
criteria as the City may require. Sanitary sewer service shall not be established within
the boundaries of another sewer service provider’s district, except by agreement with
that provider
• As the service provider, the City is the point of contact or focal point. Not all regulations
or criteria originate with the City. Some regulations or criteria originate at the federal,
state, or county level. All applicable regulations will be followed in the provision of
service in unincorporated areas (LRWWMP)
• Areas annexed without existing municipal sanitary sewer service shall be served by the
City unless a service agreement exists or is negotiated with a neighboring utility
(LRWWMP)
• Areas annexed with existing sanitary sewer service must meet the City's sanitary sewer
service objectives. Upgrading of sanitary sewer facilities to City standards, within all or
portions of newly annexed areas will be required if there is a threat to public health and
safety. If improvements are necessary, they may be accomplished by developer
installation or LID as a condition of the annexation (LRWWMP)
• The City Council shall consider annexations without assumptions of existing sanitary
sewer facilities under the following conditions:
- The sanitary sewer facilities are or will be operated and maintained by an adjacent
municipal utility
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-6 | MARCH 2021
- The adjacent utility has executed a service boundary agreement with the City
- The annexation area is better served by the adjacent utility either because of
location within a drainage basin or because it is the most logical extension of
facilities (LRWWMP Policy)
• When areas outside of the city limits annex to the City, they must be provided with an
adequate level of sewer service. The City will serve annexed areas that do not have
sewer service unless a service agreement exists or is negotiated with a neighboring
utility. Annexed areas with existing sanitary sewer service must meet the City's sanitary
sewer service objectives as they are defined within the LRWWMP. However, upgrading
sanitary sewer facilities to all City sanitary sewer standards will be required only if there
is a threat to public health and safety. As a condition of the annexation, improvements
may be required, which can be constructed by developer installation or LID (LRWWMP
Policy)
• In the UGA all new development shall be served by public sewers, unless application of
this policy to a proposal for a single-family residence on an individual lot would deny all
reasonable use of the property; or sewer service is not available for a proposed short
subdivision of urban property in a timely or reasonable manner as determined by the
Utility Technical Review Committee. These onsite system shall be managed by one of
the following entities, in order or preference, the sewer utility whose service area
encompasses the proposed short subdivision, the provider most likely to serve the area,
or an Onsite Sewage System Maintainer certified by the Public Health – Seattle &
KC (2018 King County Comprehensive Plan, Policy F-255)
• KC shall work with cities, special purpose districts, other local service providers and
residents to identify and distinguish local, countywide and regional services. Over time,
cities will assume primary responsibility for coordinating the provision of local services
delivery in urban areas. In general, the county will continue to provide local services
delivery within the Rural Area and Natural Resource Lands. Special purpose districts
may still provide services, where appropriate. The county will also assume primary
responsibility for coordinating the provision of countywide services, including
countywide services that must be delivered within City boundaries. The county will also
work with cities, special purpose districts, and other counties to identify regional service
and facility needs and develop strategies to provide them. (2018 King County
Comprehensive Plan, Policy F-102)
3.5.2 Implementation
• Sanitary sewer service to properties outside the City’s corporate limits will not be
permitted except under the following conditions:
- Public Entity: The applicant is a municipal or quasi-municipal corporation including a
school, hospital or fire district, KC, or similar public entity
- Necessary Service: Service is necessary to convert from a failed or failing septic
system or in the area that has been defined by the Seattle-King County Health
Department as a health concern area
- Vested Service: Those properties for which the City has granted a valid sewer
availability certificate prior to July 21, 2008, and the project has a current vested
right to build
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-7
- In the City’s Sewer Service Area, Existing Legal Lot(s) Desiring to Construct One
Single-Family Residence or Connect One Existing Single-Family Residence: The
Administration may approve the connection of one single-family residence on an
existing legal lot
• In any case, as a condition of sewer service by the City, the property owner(s) shall
execute a covenant to annex for each parcel when the property being provided sewer
service is within the City’s PAA (RMC 4-6-040.C)
3.6 Financial Objective
Provide sound financial policies on which to base operations of the Wastewater Utility that
will allow the utility to meet its overall goal.
3.6.1 Policies
• Criteria should be established for developing the fees and rates necessary to maintain
the Wastewater Utility’s established level of service (LRWWMP)
• The Wastewater Utility shall be operated as an enterprise utility (financially
self-supporting) (LRWWMP)
• The Wastewater Utility should use a rate setting process that complies with standards
established by the American Public Works Association (LRWWMP)
• The Wastewater Utility should use cost-based rates and additional charges that:
- Recover current, historical, or future costs associated with the City's sanitary sewer
system and services
• Equitably charge utility customers to recover costs commensurate with the benefits
they receive
• Provide adequate and stable sources of funds to cover the current and projected annual
cash needs of the Wastewater Utility (LRWWMP)
• Portions of the revenue generated from sewer user rates will be used for wastewater
utility related capital improvement projects, including debt service for the projects
(RMC 8-5-15F)
• New customers seeking to connect to the sanitary sewer system shall be required to pay
charges for an equitable share of the cost of the system. Revenue from these charges is
used to finance part of the CIP (RMC 4-1-180.C)
• Customers should be charged for supplemental, special purpose services through
separate ancillary charges based on the cost to provide the service. Ancillary charges
create more equitable fees and increase operating efficiency for services to customers.
Revenue from ancillary charges should be used to offset operations and
maintenance (O&M) costs (LRWWMP)
• The utility should maintain information systems that provide sufficient financial and
statistical information to ensure conformance with rate-setting policies and objectives
(LRWWMP)
• Rates shall be developed using the cash basis to determine the total revenue
requirements of the Wastewater Utility (LRWWMP)
• User charges shall be sufficient to provide cash for the expenses of operating and
maintaining the Wastewater Utility. To ensure the fiscal and physical integrity of the
Wastewater Utility, an amount shall be set aside each year for capital expenditures from
retained earnings, that is, an amount shall be set aside to cover some portion of the
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-8 | MARCH 2021
depreciation of the physical plant. The amount may be transferred from the Sanitary
Sewer Fund to the Construction Fund for general purposes, or for specific purposes, such
as creating a reserve for main replacement (LRWWMP)
• A Working Capital Reserve will be maintained to cover emergencies, bad debts, and
fluctuations in cash flow (LRWWMP)
• The customer classes for the utility shall be single-family (including attached
single-family), commercial (including multi-family), and industrial (RMC 4-6-040.E.2)
• The inflation rate should be based on information provided by the Finance Department
(LRWWMP)
• Large industrial users should be charged for services on the same basis as all other users
(LRWWMP)
• The utility should use generally accepted cost allocation principles for all cost allocation
purposes (LRWWMP)
• The utility fees and charges should be calculated for the service area as a whole. Rates
should be the same regardless of location (except for the inside/outside City distinction
discussed below) (LRWWMP)
• When the City takes over existing service of properties outside the City limits by
agreement with an adjacent district, the City shall charge the normal in-city rates
(LRWWMP)
3.6.2 Implementation
• For customers residing outside the City limits, sanitary sewer rates are 1.5 times the
residential City rates (RMC 8-5-15C)
• Renton provides for a senior and/or disabled citizen discount on City sewer rates
(RMC 8-5-15D4)
• Owners of properties that have not been assessed or charged an equitable share of the
cost of the sanitary sewer system shall pay, prior to connection to the system, one or
more of four charges:
- System development charge
- Special assessment charge
- Latecomer's fees
• Inspection/approval fees
3.7 Facility Objective
Provide a wastewater collection system that ensures adequate capacity and system
reliability, is consistent with land use and environmental protection goals and policies, and is
well maintained.
3.7.1 Policies
• Protect the health and safety of City citizens from environmental hazards associated
with utility systems through the proper design and siting of utility facilities (LRWWMP)
• Promote the co-location of new utility infrastructure within rights-of-way and utility
corridors, and coordinate construction and replacement of utility systems with other
public infrastructure projects to minimize construction related costs and disruptions
(LRWWMP)
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-9
• Design criteria should be established to provide an optimum performance level and a
standard of quality for the sanitary sewer system (LRWWMP)
• All lift stations that will be converted to public maintenance shall have control and
telemetry systems that are consistent and compatible with the current City system
(LRWWMP)
• Joint use facilities will be pursued only in those areas where they would improve
reliability or reduce operating costs. All joint use facilities must comply with City policy
and design standards (LRWWMP)
3.7.2 Implementation
• Public sewers shall conform to the latest City standards, as adopted by City Code, as
well as Ecology Criteria for sewage works design and the Recommended Standards for
Sewage Works of the Great Lakes-Upper Mississippi River Board of State Sanitary
Engineers. The standards are subject to review by Ecology. All public sewer extensions
shall conform to City standards and be consistent with the City LRWWMP
(RMC 4-6-040.F.2)
• The public sewer shall be polyvinyl chloride (PVC) plastic pipe American Society for
Testing Methods (ASTM) D 3034. Rubber gaskets for PVC pipe shall meet ASTM 1869
standards. However, ductile iron (DI) American Water Works Association (AWWA) C151,
that is Type II push-on or Type III mechanical joints, together with cement mortar lining
that is 3/32 of an inch in accordance with AWWA C 104 and PVS C900 pipes can be used
for force mains or areas with external loading concerns. Also public sewers installed in
filled or unstable ground, in areas with high ground water levels, or in areas where the
potential for infiltration occurs, may be required to be either DI, or PVC plastic pipe.
Exact pipe material shall be as determined by the Wastewater Utility. Alternative pipe
materials may be considered by the Wastewater Utility on a case-by-case basis.
Minimum size shall be 8 inches in diameter (RMC 4-6-040.F.3)
• Manholes shall be installed at the end of each line, at all changes of grade, size or
alignment, and at distances no greater than 400 feet for 15-inch diameter sewers or
smaller. Greater spacing may be permitted in larger sewers. Manholes shall be a
minimum of 48 inches in diameter, shall be precast concrete or cast in place concrete,
with steel reinforcement. Steps shall be placed at 1-foot intervals, conforming to current
safety regulations
• The manhole covers shall be 24-inch diameter cast iron (CI) frame and lid. All
connections to the manhole shall match the existing inverts or have a drop connection in
accordance with current City standards (RMC 4-6-040.F.5)
• All private lift stations for commercial or multi-family use shall have alarm and standby
emergency operation systems, and meet or exceed Ecology specifications as detailed in
Recommended Standards for Sewage Works. All private single-family lift stations shall
meet or exceed City standards for that type of facility (RMC 4-6-040.F.6)
• All person(s) or local improvement districts desiring to extend sanitary sewer mains as
part of the City's system must extend said mains under the supervision of the
Wastewater Utility (RMC 4-6-040.F.7)
• No property shall be served by City sewer unless the sewer main is extended to the
extreme boundary limit of said property as required by this section. All extensions shall
extend and cross the full width of the property to be served by sewer except when
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-10 | MARCH 2021
shown by engineering methods, to the satisfaction of the Wastewater Utility, that future
extension is not possible or necessary. If an exemption is granted, the property owner is
not relieved of the responsibility to extend the main and shall execute a covenant
agreeing to participate in an extension if, in the future, the Wastewater Utility
determines that it is necessary (RMC 4-6-010.B)
• Any facility improvements, identified by the current adopted LRWWMP, that are not
installed or are being installed must be constructed by the property owner(s) or
developer(s) desiring service (RMC 4-6-040.B)
• Any party extending utilities that may serve other than that party's property may
request a latecomers' agreement from the City (RMC 9-5-1)
• Any party required to oversize utilities may request that the utility participate in the cost
of the project (RMC 4-6-010.C)
• Grease and oil interceptors or other approved methodology, shall be required on all
restaurant, garage, and gas station premises and shall be so situated as to intercept the
sources of grease and oil wastes but exclude domestic or human wastes. Grease, oil, and
sand interceptors shall be provided in any other case if, in the opinion of the Wastewater
Utility, they are necessary for the proper handling of liquid wastes. All interceptors shall
be of a type and capacity approved by the Wastewater Utility (RMC 8-5-11)
• Old building sewers may be used in connection with new buildings only when the
Wastewater Utility finds they meet all standards and specifications of the City. The
applicant / owner is required to provide testing / examination material (i.e. closed-circuit
television [CCTV]) prior to the City determination (RMC 4-6-040.G.13)
• The size and slope of the building sewer shall be subject to the approval of the
Wastewater Utility. The standard minimum sizes and slopes are (RMC 4-6-040.G.3):
- 4 inches at a 2 percent slope (1/4 inch per foot) for single-family residential
- 6 inches at a 2 percent slope (1/4 inch per foot) for multi-family, commercial, or
industrial
• In no event shall the diameter of the side sewer stub be less than 6 inches. The
Wastewater Utility may allow, under certain circumstances, a 6-inch side sewer to be
laid at no less than 1 percent (1/8 inch per foot). A grade release holding the City
harmless for the flatter slope will be required
• If a building cannot be served by a gravity system an approved, private lift station may
be utilized to provide service (RMC 4-6-040.G.5)
3.7.3 Analysis and Design Criteria
Wastewater Flow Rates: Wastewater flow rates will be established based on adopted land use
plans and policies as reflected in the Puget Sound Regional Council (PSRC) Land Use Baseline
projections. Per capita and employee flow rates will be calibrated to flow measurement data
(LRWWMP).
3.7.3.1 Sanitary Sewer Design Criteria
All sewer lines within the City shall be designed in accordance with good engineering practice by
a professional engineer with minimum design criteria presented in Chapter C1 of the "Criteria for
Sewerage Works Design," prepared by Ecology, November 2007, or as superseded by
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-11
subsequent updates. The sewer lines shall also conform to the latest City Standards and
Specifications. Detailed standards are included in Title 4, Chapter 6 of the City Code:
• Design Loading for Sanitary Sewer Facilities: Sanitary sewer system flows are
composed of residential, institutional, commercial, and industrial sewage, along with
infiltration and stormwater inflow. Sanitary sewer systems must be capable of
conveying the ultimate peak flows of these wastewater sources. No overflows shall be
permitted (LRWWMP):
- Design Period: The design period is the length of time that a given facility will
provide safe, adequate and reliable service. The period selected for a given facility is
based on its economic life, which is determined by the following factors: the
structural integrity of the facility, rate of degradation, cost of replacing the facility,
cost of increasing the capacity of the facility, and the projected population growth
rate serviced by the facility. Collection and interceptor sewers are designed for the
ultimate development of the contributing area. The life expectancy for new sanitary
sewers, using current design practices, is in excess of eighty years (LRWWMP)
• Design of Sanitary Sewer Facilities: Allowable sewer pipe shall be high-density
polyethylene (HDPE) or PVC. For normal depth, PVC is generally preferable, because it
has longer laying lengths, which results in fewer joints, reducing the potential for
infiltration. Table 3.1 summarizes sanitary sewer design criteria (LRWWMP):
- Gravity Sewer Sizing: Gravity sewers are sized to provide capacity for peak,
wet-weather flows. The smallest diameter sewer allowed is 8-inches, except for
limited conditions. All sewers will be laid on a grade to produce a mean velocity
when flowing half-full of at least two feet per second
- Manhole Sizing: Manholes will be at least 48-inches in diameter and will be spaced
at intervals not to exceed 400 feet on sewer lines 15-inches in diameter or less, and
500 feet on sewer lines 18-inches in diameter or larger. These distances are
consistent with most standards, but approval can be granted for longer distances
- Roughness Coefficient: The Manning equation shall be used to design and analyze
wastewater flow characteristics of the sanitary sewers. The Manning roughness
constant [n] shall vary depending on the pipe material. For sewer modeling, a
Manning’s equivalent of 0.013 will be used. Typical values are summarized in
Table 3.1
- Reference Datum: The North American Vertical Datum (NAVD) 1988 is the
standard datum used within the City for design and construction of sanitary sewer
facilities
- Separation between Sanitary and Other Facilities: Ecology requires a ten-foot
horizontal separation of water and sewer facilities for health reasons. Sanitary and
storm sewer facilities require seven feet separation per the Surface Water Design
Manual and shall have basic separation requirements for construction purposes. In
unusual conditions the separation distance can be shortened, but a minimum
horizontal separation of five feet between sanitary and other facilities shall be
maintained per Ecology. Wherever possible, a horizontal separation of seven feet is
desirable. These distances are measured edge to edge.
- Hydraulic Analysis: The hydraulics of the City’s sewer service area is modeled with
the Mike Urban software program by the Danish Hydraulic Institute (DHI). The
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-12 | MARCH 2021
model was calibrated and updated to reflect the system wet weather flows in 2018.
The City currently maintains and updates the model as needed
• All new developments, with the exception of developments involving less than five
single-family residences, may require a hydraulic analysis. The sanitary sewer system
hydraulic analyses will be performed using the City's hydraulic computer model. The
developer may be responsible for paying the cost of the analysis of the sanitary sewer
system. If the analysis concludes improvements need to be made, the developer and the
City may need to negotiate cost allocation
Table 3.1 Sanitary Sewer Design Criteria
Criteria Details
Sanitary Sewer Sizing: Peak Wet-Weather Flow
Minimum Sewer Size: 8 inches in Diameter
(6 inches for limited conditions)
Pipe Materials: PVC
HDPE
Manholes:
Maximum Spacing 400 feet for pipe < 15 inches
500 feet for pipe > 18 inches
Minimum Manhole Size 48 inches in diameter
Minimum Clear Opening 23 inches in diameter
Maximum Depth 20 feet (where possible)
Separation From Water Mains:
Horizontal Separation (Parallel) 10 feet
Minimum Horizontal Separation (Parallel) 5 feet
Minimum Vertical Separation (Perpendicular) 18 inches
Hydraulic Criteria:
Depth to Diameter Ratio 0.85
Minimum Scouring Velocity 2 feet per second
Manning Roughness Coefficient
Design 0.013
PVC 0.011
Concrete 0.012
Lined DI / CI 0.012
Vitrified Clay 0.013
Sewer Modeling 0.013
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-13
3.7.3.2 Lift Station Design Criteria
Sewage lift stations within the City shall be designed in accordance with good engineering
practice by a professional engineer using the minimum design criteria presented in Chapter C2 of
the "Criteria For Sewerage Works Design," prepared by Ecology, August 2008, or any subsequent
updates, and shall conform to the latest City standards and specifications. Detailed standards
are included in Title 4, Chapter 6 of the City Code. Table 3.2 summarizes Lift Station design
criteria (LRWWMP):
• Design Loading for Lift Stations: Lift stations shall be designed to handle the peak,
wet-weather flow from the contributing area. All lift stations, except for private stations
for a single-family home, shall have a minimum of two pump units, each with the
capacity to handle the expected maximum flow:
- Design Period: The design period for lift stations shall take into consideration
long-term needs, replacement or expansion difficulties, service area growth rate
and useful life. A lift station should have a minimum design period of twenty years
for the facility and ten years for mechanical and electrical equipment. Consideration
should be given to longer design periods for lift stations that are expected to serve
an indefinite life. Consideration must also be given to the ability of the consumers to
pay for the facilities
• Design of Lift Station Facilities: If wide variations in wastewater flow rates are
expected for the lift station, then consideration should be given to the use of three or
more pumping units. If three pumps are used, two of them must have the capacity to
convey peak wastewater flow rates. Each pump shall be capable of passing spheres of at
least three inches in diameter:
- Backup Power: Each lift station will be provided with an on-site power backup. The
City may allow the use of portable power backup for smaller stations. A lift station
designed for portable power backup shall be provided with sufficient wet-well
storage to allow adequate time for maintenance personnel to transport, setup, and
provide the necessary backup, during a power outage. Wet-well storage will be
designed on the basis of the peak, wet-weather flow
- Force Mains: Force mains shall be sized to maintain a minimum velocity of 2 feet
per second. The force main shall have a maximum velocity of 10 feet per second
when all pumps are operating together. Regardless of these velocity criteria,
minimum size shall be three inches in diameter. A minimum of four inches in
diameter is preferable
- Ownership: Each lift station to be owned by the City shall have control and
telemetry systems that are consistent and compatible with the current City system
• Elimination of Lift Station Facilities: Lift station facilities are typically eliminated
through the development of the gravity sewer system. Highest priority should be given
to elimination of lift station facilities because of their high degree of vulnerability and
high O&M costs. Considerations for the elimination of a lift station include
environmental risks, life-cycle costs, lift station impacts on downstream sanitary sewer
facilities, vulnerability to vandalism, and lift station accessibility (LRWWMP)
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-14 | MARCH 2021
Table 3.2 Lift Station and Force Mains Design Criteria
Criteria Details
General Design Criteria Criteria for Sewerage Works Design
Lift Station Sizing: Peak Wet Weather Flow
Number of Pumps: Minimum of two pumps.
Two Pumps Each pump to handle the peak flow rates
Three Pumps Two pumps to handle peak flow rates
Design Periods:
Facility 20 years
Mechanical and Electrical 10 years
Wet-well Storage: Sufficient wet-well storage to allow
adequate time for maintenance personnel
to transport, setup, and provide the
necessary backup, during a power outage
Reliability: On-site power backup
Elimination of Lift Stations: High Priority
Force Mains:
Minimum Diameter: 3 inches
Velocity:
Minimum 2 feet per second
Maximum 10 feet per second
3.8 Operations Objective
Maintain the sanitary sewer system in a safe, reliable, and efficient operating condition.
Provide the organizational structure and staff necessary to operate the City's Wastewater
Utility system efficiently.
3.8.1 Policies
• The City will use its Wastewater Operations Master Plan (OMP) to document current
activities and programs into an O&M procedures manual, review programs for
effectiveness and future regulatory requirements, analyze and recommend programs in
accordance with the City's long-range goals and objectives, and assist with the
development of an implementation strategy (LRWWMP)
• System Repair and Replacement shall be performed in a manner that includes risk
assessment, condition, and coordination with other Capital Projects as part of
determining when projects will be performed (LRWWMP)
• The City will maintain its wastewater collection system according to the following
guidelines:
- Maintenance shall be performed by the sanitary sewer maintenance staff and
supervised by the Field Superintendent
- All maintenance personnel shall be trained in the procedures and techniques
necessary to efficiently perform their job descriptions
- Dry, heated shop space shall be available to all maintenance personnel
CHAPTER 3 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 3-15
- Tools shall be obtained and maintained to repair all items whose failure will impact
the ability to meet other policy standards
- Spare parts shall be stocked for all equipment items whose failure will impact either
the ability to meet other policy standards or the inability to continue providing
service to customers
- Equipment and software to conduct condition assessments, including CCTV
Inspections (LRWWMP)
• The City should provide a preventive maintenance schedule for all facilities and
equipment. This schedule should be based on the functional and economically useful life
of the equipment and facilities as determined by the manufacturer or industry
experience:
- Worn parts should be repaired, replaced, or rebuilt before they have a high
probability for failure
- Pipelines should be replaced through a condition assessment that includes a risk
based prioritization
- Where feasible and practical, equipment should be replaced before it becomes
obsolete (LRWWMP)
• The City will maintain the wastewater collection system in a timely manner that
provides service continuity to the customer:
- Equipment breakdown repairs will be made even if overtime labor is involved
- Equipment that is taken out of service for maintenance will be returned to service as
soon as possible (LRWWMP)
• Written records and reports should be maintained on each facility and item of
equipment showing its O&M history (LRWWMP)
• The property owner shall own and maintain the side sewer from the house connection to
the wastewater main, including the building side sewer and the side sewer stub (that
portion of the side sewer within the right-of-way or easement). If a side sewer becomes
plugged, it is the property owner's responsibility to correct the problem. The City will
assist in locating the side sewer based on any as-built records it has. If it is determined
that the problem exists within the City sewer main, the City will provide professional
clean up and repair service (LRWWMP)
• A vulnerability analysis will be performed to determine a reasonable "worst case" failure
for each basin. The analysis will consider the failure of the interceptor and trunk sewers,
failure of the largest mechanical component, and power failure to a single power grid
(LRWWMP).
• The Wastewater Utility is responsible for operating the sanitary sewer system, including
its planning, design, O&M, records management, customer service, and construction
management (LRWWMP)
• The Wastewater Utility shall consist of two sections: Wastewater Utility Systems
Section and Surface Water / Wastewater Maintenance Services Section. The
Wastewater Utility Systems Section is responsible for project management of CIP
projects, planning and design, and customer service. Surface Water / Wastewater
Maintenance Services Section is responsible for inspection, testing and repair of
facilities, routine preventative maintenance, and responding to emergencies
(LRWWMP)
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 3
3-16 | MARCH 2021
• Wastewater Utility customer service is performed by the Development Services
Division (general) and by the Wastewater Utility staff (technical) (LRWWMP)
• Ensure wastewater utility staffing is sufficient to maintain the sewer system and
provide adequate service to City residents. Staffing levels should be commensurate
with the physical extent of the sewer system and the number of residents served (Policy
U-24, 2018 City of Renton Comprehensive Plan)
• Provide the levels of staffing and diversity of skills necessary to operate the City's
wastewater utility system (LRWWMP)
• The Wastewater Utility should utilize the expertise in other City departments, according
to inter-departmental agreements, to augment the Wastewater Utility's expertise
(LRWWMP)
3.8.2 Implementation
Restaurants and other food processing establishments, garages, and gas stations shall install and
maintain grease traps, grease and oil interceptors, or other approved methodology on their
premises as determined by the Wastewater Utility (RMC 8-5-11).
3.9 Recommendations
The City has robust policies and criteria to aid in providing adequate, reliable sanitary sewer
service at a minimum cost to the customer. These policies and criteria are found in the
Comprehensive Plan, RMC, reference manuals, and as LRWWMP policies. Through review of
these documents, a discrepancy in Section 3.3.2 was found in regard to the distance from an
OSS. We recommend the RMC is revised to be consistent with the KC Health Department. The
recommended policy would state:
"Existing development that is within three hundred and thirty feet of a public sewer, where
an on-site system (OSS) is operating, connection to the public sewer is required when the
sewering authority permits such connection and when:
• Repair, modification, or replacement of the system is necessary, or the existing OSS has
failed and an OSS fully conforming to this title cannot be designed and installed; or
• At such time that additional construction which in any way affects the on-site sewage
system is proposed (KCBHRR No. 3, 13.04.050).
• They are part of a sewer Local Improvement District (LID) (RMC 4-6-040.A).”
We recommend the City continue its regular review of policies and criteria to keep pace with
changing system and development conditions.
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-1
Chapter 4
PLANNING CONSIDERATIONS
4.1 Introduction
This chapter describes the City of Renton's (City’s) land use policies and demographic projections
that are used to develop future wastewater flow projections.
The City's land use policies and sewer system are connected with adjacent sewer systems'
policies and systems in several ways. Existing land use provides the basis for designing properly
sized sewerage facilities, including trunks, interceptors, and lift stations. Many of the basins at
the edges of the City's service area are also served in part by other cities or districts. In most
cases, the City's sewers are downstream, or at the receiving end of the effluent, from the
systems adjacent to the City. Therefore, proper planning for the City's sewers requires that the
plans of these adjacent utilities be evaluated.
In addition to adjacent utility plans, the land use plans and policies of King County (KC) and the
Growth Management Planning Council (GMPC) were also considered. As discussed below the
entire planning area is within the Urban Growth Boundary (UGB) established by the GMPC. This
area is referred to as the Potential Annexation Area (PAA) by the City. The City supports the
countywide framework policies (F-255 and F-102) that call for the designated Urban Area to be
served with sanitary sewers and prefers cities as the provider of sewer services. The entire study
area has been designated Urban by the 2018 King County Comprehensive Plan.
4.2 Basis of Planning
The Study Area, shown as a dashed green line in Figure 4.1, is the currently agreed-upon service
boundary considered for the Long-Range Wastewater Management Plan (LRWWMP). The Study
Area encompasses areas that coincide with the City limits and UGB.
Two planning periods are evaluated in this LRWWMP:
• Existing system
• Build-out
Evaluations are performed for both average dry weather flow (ADWF) and peak wet weather
flows (PWWF). The existing system is defined as 2012 sanitary flows calibrated with 2018 flow
data. Build-out conditions are projected to occur in 2040.
4.3 Planning Area
The planning area for this LRWWMP corresponds, for the most part, with the current City limits
and UGB, as shown in Figure 4.1. Service is provided consistent with regional planning and
agreements with adjacent utilities.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-2 | MARCH 2021
4.3.1 Existing Service Area
The City currently serves customers in the Existing Service Area. As described in
Chapter 2 – Overview of Existing Sewer System, the City serves six drainage basins: Black River,
Downtown, East Cedar River, East Lake Washington, May Valley, and West Cedar River. Several
basins are served by utilities other than the City: City of Renton, City of Tukwila, City of Kent, and
Soos Creek Water and Sewer District provide service within the Black River Basin; Soos Creek
Water and Sewer District also provides service within the West Cedar River Basin; Skyway Water
and Sewer District serves parts of the Downtown Basin; and May Valley Basin is partially served
by Coal Creek Water and Sewer District. Figure 4.2 shows the City of Renton’s service area and
the adjacent sewer systems that border the City.
The City has negotiated service area boundaries along the common borders in these Basins with
Coal Creek Water and Sewer District, Soos Creek Water and Sewer District, Skyway Water and
Sewer District, and Cedar River Water and Sewer District. Additionally, natural boundaries in
certain areas make the City the logical sanitary sewer provider to them, especially the area to the
east of the Green River within the City of Tukwila. Figure 4.2 reflects these agreed upon service
area boundaries.
4.3.2 Potential Annexation Areas
The PAA is the area between the existing City boundary, the dashed black line in Figure 4.1, and the
UGB, the gold line in Figure 4.1. Consistent with City policies outlined in Chapter 3 – Operational
Policies and Criteria, property owner(s) in the PAA will be required to execute a covenant to annex
for each parcel when the property is being provided sewer service. The total area of PAA for the City
is 7,603 acres.
142ND AVE SE144TH AVE SES 116TH ST
SE 196TH ST
NE 24TH ST
SE 148TH ST
172ND AVE SE88TH AVE SLAKE WASHINGTON BLVD NNE 21ST ST
UNION AVE NE121ST PL SESE 144TH ST
W JAMES ST
S 132ND ST BURNETT AVE NS 212TH WAYKLI
C
K
I
T
A
T
D
R
NE 19TH ST
S ORCAS ST
84TH AVE SEHARDIE AVE SWSOUTHCE
N
T
E
R
B
L
V
D
MAPL
E
V
A
L
L
E
Y
H
W
Y
S 208TH ST
120TH PL
SE
S 115TH PL
MAIN AVE SSE 141ST STTALBOT RD S84TH AVE S135TH AVE SES 1
3
0
T
H
P
L
CEDAR AVE S4TH AVE NSUNSET BLVD NE134TH AVE SEBENSON RD
S
S MORGAN ST
S FINDLAY ST
LINCOLN AVE NEHOQUIAM AVE NES LEO ST
SE 227TH PL
S 15TH STWILSON
AVE
S
S 134TH ST
160TH AVE SE126TH AVE SESE 218TH PL 148TH AVE SEN 30TH ST
S BANGOR ST
IN
T
E
R
U
R
B
A
N
A
V
E
S
S LUCILE ST
SR
5
1
8 W MERCER WAY112TH AVE SE94TH AVE SSE 179TH ST
S 190TH ST
S 178TH ST
120TH AVE SE130TH AVE SEW
A
T
E
R
S
A
V
E
S
59TH AVE SS 164TH ST 78TH AVE SES 115TH ST
76TH AVE SNE 7TH PL
S 130TH STCORNEL
L
A
V
E
S
S
O
M
E
R
S
E
T
B
L
V
D
S
E
CASCADE KY
127TH AVE SESE 60TH ST
EDMONDS AVE NEI-
5
FWY
SE 79TH
D
R
N 38TH ST
S
K
A
G
I
T
K
Y
CENTRAL AVE NNE 2ND ST
NE 12TH ST
S OTHELLO ST
NE 8TH ST
E JAMES ST
SE 56TH ST
NE 7TH ST
S LA
K
E
R
I
D
G
E
D
R
SE 192ND DR58TH AVE SS 200TH ST
S 116TH
P
L HARRINGTON AVE NES GRAHAM ST 143RD AVE SE100TH AVE SEBE
A
C
O
N
A
V
E
S
S MEAD ST
NE 6TH PL
131ST AVE SESE 235TH
S
T DUVALL AVE NES BRANDON ST
SE 64TH ST
SE 38TH ST
85TH PL SESE 145TH
P
L
S 2ND STLIND AVE NWSE 75TH PL
P
E
T
E
R
G
R
U
B
B
R
D
S
E
S HOLLY ST
155TH AVE SESE 61ST ST
104TH PL SE63RD AVE SSE 40TH
P
L
133RD AVE
SEWELLS AVE S137TH AVE
SE164TH WAY SEANACORTES AVE NE1
2
9
TH
P
L
S
E86TH AVE SE121ST AVE SESE 45TH ST
E MERCER WAYSE 200TH ST118TH AVE SE98TH AVE SREDMOND AVE NENE 6TH ST87TH AVE SS 124TH ST
SE 83
R
D
S
T
SE 158TH S
T
93RD AVE S52ND AVE SSE 46TH WAY
48TH AVE SSE 48TH DR
S 129TH
S
T 85TH AVE SSE 134TH ST
SE
1
7
0
T
H
S
T162ND AVE SE151ST AVE SES 19TH ST
164TH AVE SESE 46TH ST
OLYMPIA AVE NESE 160TH ST
S 14TH ST
S ROXBURY ST
W
E
S
T
L
A
K
E
S
A
M
M
A
M
I
S
H
P
K
W
Y
S
E
CRESTWOOD DR SMONROE AVE NE123RD AVE SEHAZEL AVE NS 117TH ST
W
A
B
A
S
H
A
V
E
S
128TH AVE SE54TH AVE SSE 183
R
D
D
RJERICHO AVE NESE 221ST ST 175TH AVE SESE 216TH ST
NE 9TH ST
S 220TH ST HOUSER WAY NKIRKLAND AVE NEN 5TH ST
N 6TH ST
S MYRTLE ST SE 71ST ST
SE PETRO
V
I
T
S
K
Y
R
D
66TH AVE SSE 223RD ST
SE 128TH ST
SE 156TH ST
124TH AVE SESE 244TH ST
SE 4TH ST
N 3RD ST
SE 73RD PL
S 127TH ST
S WILLOW ST
BREMERTON AVE NE168TH PL SESE 164TH ST
INDUSTRY DRFO
R
E
S
T
D
R
S
E
BRONSON WAY NES RYAN ST
S NORFOLK ST
TUKWILA PKWY
SE 228TH ST
SE 55TH ST
SE 142ND ST
S 3RD ST82ND AVE SESE CARR
R
D
S 216TH ST
S 128TH ST
SE 172ND ST
NE 16TH ST
SE R
E
N
T
O
N
-
I
S
S
A
Q
U
A
H
R
D
SE 202ND PL108TH AVE SE146TH AVE SE57TH AVE SSE 136TH STROSARIO PL NESE 116TH ST
SE 162ND ST
NE 22ND STAVALON DRSE 68TH ST
SE 40TH ST
SE 42ND ST
SE 72ND ST
S SU
N
N
Y
C
R
E
S
T
R
D
DIX
O
N
D
R
SFOREST AVE
SE
SE 212TH ST93RD AVE SESTRANDER BLVD
S 196TH ST
L
A
K
E
W
A
SH
ING
TON
B
L
VD
S
SE 138TH PLSW 4TH
P
L
SR 167SE 208TH ST 150TH AVE SENILE AVE NE104TH AVE SEN 10TH ST
VILL
A
G
E
P
A
R
K
D
R
S
E
S 218TH ST SOMERSET DR SEWEST
LAKE
DES
IRE
DR
SE177TH AVE SESE 224TH ST
S 112TH ST
SE 52ND S
T
ILWACO AVE NEBENSON DR SS 144TH ST
LIND AVE SW55TH AVE SNE 10TH STHIGHLAND DRMIL
L
AVE
S
S 212TH ST
SE 183RD ST
S 224TH ST
NE 23RD PL
ANDOVER PARK W50TH AVE S49TH AVE SS 113TH STSEWARD PARK AVE SNEWCASTLE GOLF CLUB
R
D
S HENDERSON ST
SE 47T
H
S
T
S 120TH ST
SE 219TH PL51ST AVE SNEW
C
A
S
T
L
E
W
A
Y
125TH AVE SESE 76TH ST
SHATTUCK AVE SPELLY AVE NSW 7TH ST 188TH AVE SES 121ST ST
S 237TH PL
N 29TH ST
53RD AVE SSE 51ST
S
T
129TH AVE SESE 233RD ST
SE 91ST ST
SE 176TH STBLAINE AVE NE127TH PL SESW 12TH ST
SE 223RD DR 161ST AVE SEHIGH AVE SSE 42ND PL
NE 4TH ST
SE 66TH ST
MONTEREY AVE NESE 225TH ST
SE LAKE YOUN
G
S
R
D
SE ALLEN RD
BURNETT AVE SSW 39TH ST
SE 221ST PL65TH AVE SSE FA
I
R
W
O
O
D
B
L
V
D
PARKSIDE WAY SEN 32ND ST
E SMITH ST
S LANGSTON RD
SOUTHCENTER PKWYL
A
K
E
S
I
D
E
B
L
V
D
E
SW 16TH ST
MINKLER BLVD 85TH AVE SEN 31ST ST
SW 10TH ST
S 192ND ST 171ST PL
SE
S 204TH ST
SE 5TH ST
SE 226TH ST
MERCER
W
O
O
D
D
R
SW 3RD P
L
SW SUNSET BLVD
SE 106TH ST
SE 192ND ST
68TH AVE S149TH AVE SESE 220TH PL77TH AVE SSE 80TH ST
78TH AVE S62ND AVE SSE 2ND PL
S
2
3
1
S
T
S
T47TH AVE SSE 180TH STPOWELL AVE SWS JUNEAU ST
SE 214TH ST171ST AVE SES 114TH ST
3RD AVE NSE 121ST PL
PARK AVE NSE 59TH ST89TH AVE SE88TH AVE SEGARDEN AVE NSE 186TH ST91ST AVE SE81ST AVE SE92ND AVE SE2ND AVE N1ST AVE NS TAFT ST
PASCO PL NENE SUNS
E
T
B
L
V
D
MACADAM RD
S136TH AVE SESE 241ST S
TMI
L
ITARY
RD
S
SE 80
T
H
W
A
Y
SE 188TH ST117TH AVE SES 50TH ST
S AVON ST
190TH AVE SE80TH AVE SESE 168TH ST
S 194TH ST
N 4TH ST
132ND AVE SE81ST PL SE116TH PL SE80TH AVE S102ND AVE SE126TH PL SEW SMITH ST
SE 65TH ST
UNION AVE SESE 110
T
H
S
T
SE 204TH ST
S PUGET DRRAIN
IER
AVE
N181ST AVE SE176TH AVE SE170TH PL
SE
S 160TH ST
SE 58TH ST
NE 3RD ST
SE 3RD PL
S 170TH ST
AIRPORT WAY
S TOBIN ST
SE 228TH PL
SE 4TH PL
SE 112TH ST
SE 49TH ST
SE 240TH ST
SE 184TH ST116TH AVE SEABERDEEN AVE NES 240TH ST
SW GRAD
Y
W
A
Y
64TH AVE SGRANT AVE SSE 149TH STISLAND CREST WAYALVORD AVE NS 32ND ST
SE 204TH WAY
R
E
N
T
O
N
A
V
E
S
SUNSET BLVD N56TH AVE
S
S 36TH PLOAKESDALE AVE SW180TH AVE SENE PARK DR
163RD PL SELOGAN AVE NSW 19TH ST
113TH AVE SESE 63RD ST
I-
4
0
5
FWY
RAINIER AVE S
PUGET DR SE50
T
H
P
L
S
SE
L
I
C
O
R
I
C
E
W
A
Y
NE 27TH ST
SE 44TH ST
COAL CREEK PKWY SE119TH AVE SESE
1
7
0
T
H
P
L
140T
H
W
A
Y
S
E
N 8TH ST
92ND AVE S80TH PL SESE 43RD ST
JONES AVE NE174TH AVE SEPATRIOT WAY SESE 232ND ST
SW 34TH ST
184TH AVE SE72ND AVE SLUMMI KY
106TH AVE SESW 41ST ST
S GRADY
W
A
Y FACTORIA BLVD SES 126TH STANDOVER PARK ES 228TH ST59TH PL SSE 53RD
PL
LAKEMONT BLVD SES 180TH ST
M
A
R
T
I
N
L
U
T
H
E
R
K
I
N
G
J
R
W
A
Y
S
S 188TH ST
SW 27TH ST
156TH AVE SE138TH AVE SE136TH PL SES 222ND ST
66T
H
L
N
S 152ND AVE SEWEST VALLEY HWY183RD AVE SESE 184TH PL
89TH AVE S16
6
T
H
W
A
Y
S
E
SE 8TH PL
W
O
O
D
S
I
D
E
D
R
S
ESR 599EAST VALLEY HWY SSE COU
G
A
R
M
O
U
N
T
A
I
N
D
R
SE MAY CRE
E
K
P
A
R
K
D
R
ORILLIA RD SSE 95TH WAY
SE 50TH ST
105TH AVE SES 199TH PL
6TH AVE NS 226TH STS 184TH PLSE 159TH PL
I-90 F
W
Y
RIPLEY LN SESE
1
7
1
S
T
W
A
Y
183RD WAY SE
SE 160TH PL
SW 43RD ST
56
T
H
P
L
S
SE ROYAL HILLS
D
R
SE 196TH D
R140TH AVE SESE
6
4
T
H
W
A
Y
154TH PL SERENTON-ISSAQUAH RD SENE 31ST ST
EAST VALLEY RDS 133RD ST
S 135TH ST
SE 65TH PL
N R
IVERS
IDE
DRNW VILLAGE PARK DRMONSTER RD SWM
U
N
A
O
M
E
M
O
R
I
A
L
D
R
SE NEW
P
O
R
T
W
A
Y
80TH PL
S
169
T
H
A
V
E
S
E
FRAGER RD
SRUSSELL RD SB
E
A
C
O
N
-
C
O
A
L
M
I
N
E
R
D
S
SE RENTON-MAPLE VA
L
L
E
Y
R
D
S
E
M
A
Y
V
A
L
L
E
Y
R
D
1
4
4
T
H
P
L
S
E
SE JONES RD
Last Revised: June 10, 2019F:\KRCD DRIVE\Renton\9971A00\Study_Area.mxd
O
0 1 20.5 Miles
Legend
Study Area
Renton City Boundary
Urban Growth Boudary
Roads
Waterbodies
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 4.1
Study Area
Renton
City of Tukwila
Cedar River Water and Sewer District
Coal CreekUtility District
City ofKent Soos Creek Waterand Sewer District
Skyway Water andSewer District
N 4TH ST
144TH AVE SESE 64TH ST
S 116TH ST
SE 148TH ST LAKEMONT BLVD SE88TH AVE SNE 21ST ST
HOQUIAM AVE NE121ST PL SE78TH AVE SESE 144TH ST
SE 204TH ST
S 2ND ST
NE 12TH ST
IN
T
E
R
U
R
B
AN
A
V
E
S
S 132ND ST
S 144TH ST 153RD AVE
SES 212TH WAYCORNEL
L
A
V
E
S
NE 19TH ST84TH AVE SELAKE WASHINGTON BLVD SEHARDIE AVE SWMAPLE VAL
L
E
Y
H
W
Y
K
L
I
C
K
I
T
A
T
D
R S 125TH STEDMONDS AVE NES 208TH ST GARDEN AVE NS 216TH ST
NE PARK DR
S ROXBURY ST
CEDAR AVE SS 19TH ST
SE 141ST ST
TALBOT RD S135TH AVE SEMAIN AVE SCOAL CREEK PKWY SES 1
3
0
T
H
P
L
84TH AVE SSUNSET BLVD NEBENSON RD
SLINCOLN AVE NEBREMERTON AVE NESE 227TH PL
100TH AVE SES 15TH ST
S 134TH ST
53RD PL S160TH AVE SE126TH AVE SESW 3RD
P
LW MERCER WAYI-5 FWY112TH AVE SESE 179TH ST
S 190TH ST
S 178TH
S
T
NE 1
S
T
S
T
S 7TH ST 130TH AVE SEW
A
T
E
R
S
A
V
E
S HIGHLAND DR59TH AVE SS 115TH ST
94TH AVE SSE 2ND PL86TH AVE SES 130TH ST
SE 183
R
D
D
R
S
O
M
E
R
S
E
T
B
L
V
D
S
E
127TH AVE SESE 200TH ST
SE 79TH DR
SE 44TH PL
NE 6TH ST
NE 2ND ST SE 56TH ST57TH AVE S164TH AVE SENE 8TH ST
R
A
I
N
I
E
R
A
V
E
S
SE 192ND DR
S 23RD ST
S 200TH ST
S 50TH ST 156TH AVE SEUNION AVE NES RYAN ST
58TH AVE S143RD AVE SEJERICHO AVE NEBE
A
C
O
N
A
V
E
S
133RD AVE
SE
NE 6TH PL
M
O
R
R
I
S
A
V
E
S
131ST AVE SESE PET
R
O
V
I
T
S
K
Y
R
D
SE 235TH
S
T 129TH PL SECENTRAL AVE NSE 172ND PL
SE 145TH
P
LHARRINGTON AVE NESE 75TH
P
L
LIND AVE NW155TH AVE SE104TH PL SESE 164TH ST
SE 78TH ST
137TH AVE
SE164TH WAY SES 38TH CT
FOR
E
S
T
A
V
E
S
SE 1
5
1
S
T
S
TOLYMPIA AVE NESE 45TH ST
FORE
S
T
D
R
S
E
LAKE
WASH
ING
TON
B
LVD
S76TH AVE SR
E
N
T
O
N
A
V
E
S
98TH AVE SREDMOND AVE NE121ST AVE SE93RD AVE SS 18TH
S
T
SE 186TH ST
SE 134TH ST
NE 9TH ST
SE 46TH WAY
SE 83
R
D
S
T
SE 158TH ST
SE 48TH DR
120TH AVE SE151ST AVE
SE128TH AVE SES 14TH ST MONROE AVE NE123RD AVE SE54TH AVE SSE 221ST ST
SE 216TH STE MERCER
WAY
S 220TH ST BURNETT AVE NSE 102ND ST
134TH AVE SEN 6TH ST
N 5TH ST
66TH AVE SSE 223RD ST
SE 128TH ST
SE 156TH STSHATTUCK AVE SHOUSER WAY NSE 4TH ST
SE 71ST ST
SE 60TH ST
INDUSTRY DR124TH AVE SE168TH PL SE68TH AVE SBE
A
C
O
N
W
A
Y
S
E
N 3RD ST BRONSON WAY NESE 142ND ST82ND AVE SESE CARR
R
D
S 128TH ST
SE 55TH ST
HIGH AVE SLAKE WASHINGTON BLVD NKIRKLAND AVE NESE 202ND PL53RD AVE SSE 196TH ST
S 3RD ST
NE 16TH ST
SE 136TH ST
SE 147TH ST
SE 116TH ST
9
2
N
D
A
V
E
S
E
MONTEREY AVE NEROSARIO PL NESE 162ND ST
118TH AVE SENE 7TH S
T
NE 22ND ST
162ND AVE SESE 44TH ST
SE 72ND ST
SW GRADY WA
Y
SE 68TH ST
78TH AVE SFOREST AVE
SEWILSON
AVE
S
SE 160TH ST
SE 234TH ST 143RD PL SES ORCAS ST
S 196TH ST
SE 138TH PLSW 4TH
P
L
SR 167NILE AVE NEN 10TH ST
VILL
A
G
E
P
A
R
K
D
R
S
E
S 218TH ST
104TH AVE SE65TH AVE SSE 172ND ST
WE
S
T
L
A
K
E
D
E
S
I
R
E
D
R
S
ERAYMOND AVE SWSOMERSET DR SE88TH AVE SEWOODSIDE DR SE177TH AVE SESE 224TH ST 167TH AVE SES 112TH ST ISLAND CREST WAYSE 52ND
S
T
ILWACO AVE NEBENSON DR S55TH AVE SNE 10TH ST
MI
L
L
AVE
S
NE 20TH ST
WOODLEY AVE SNE 24TH ST
SE 183RD ST
SE 63RD ST
NE 23RD PL
ANDOVER PARK W52ND AVE SSW LAN
G
S
T
O
N
R
D
NEWCASTLE GOLF CL
U
B
R
D
SE 47
T
H
S
T
SE 219TH PL
NEWCASTLE WAY
S LEO ST
SE 76TH ST 135TH PL
SE
F
R
A
G
E
R
R
D
S
S 115TH PL
SE 208TH ST
N 33RD ST
N 29TH ST
SE 51ST S
T
I-90
F
W
Y
S 237TH PL
SE 233RD ST
SE 91ST ST 129TH AVE SE108TH AVE SESE 176TH ST150TH AVE SEBLAINE AVE NE132ND AVE SESW 12TH ST
161ST AVE SENE SUN
S
E
T
B
L
V
D
L
A
K
E
S
I
D
E
B
L
V
D
E
SE 192ND ST
S 212TH ST
SE 66TH ST
SEWARD PARK AVE S172ND AVE SES HOLLY ST
S 31ST ST
125TH AVE SES MORGAN ST
63RD AVE SSE 225TH STWELLS AVE SSW 39TH ST77TH AVE SESE 221ST PLWILLIAMS AVE SSE 218TH PLBURNETT AVE SSE FAIRWOOD BLVD
PARKSIDE WAY SEN 32ND ST
SE 228TH ST
N 30TH ST
SE 82ND ST
SOUTHCENTER PKWYS LANGSTON RD
SW 7TH ST
N 31ST ST
SW 10TH ST 171ST PL
SE
SE 73RD PL
S LAK
E
R
I
D
G
E
D
R
S 204TH ST
SE 5TH ST61ST AVE S116TH AVE SE93RD AVE SESE 106TH ST
SE 168TH ST
SE 226TH ST 149TH AVE SES 192ND ST
77TH AVE SFIELD AVE NESE 80TH ST
62ND AVE SSE 220TH PL
S 231ST S
T
SE 180TH STPOWELL AVE SWW
A
B
A
S
H
A
V
E
S
171ST AVE SESE 214TH ST
S 113TH ST
S NORFOLK ST
SE 121ST PL
S 114TH ST
SW SUNSET BLVD
SE 184TH ST
SE 59TH ST89TH AVE SESE 61ST ST
S BANGOR ST
146TH AVE SE91ST AVE SEN 38TH ST
S 224TH ST PASCO PL NEDUVALL AVE NE94TH PL SS TAFT ST 136TH AVE
SE
SE 188TH ST117TH AVE
SE
S AVON ST
S 194TH ST
NE 4TH ST
S
S
U
N
N
Y
C
R
E
S
T
R
D81ST PL SE116TH PL SESW 5TH PL
80TH AVE S102ND AVE SECRESTWOOD DR SSE 65TH ST
SE 223RD DR UNION AVE SESE 110
T
H
S
T
S PUGET DRRAIN
IER
AVE
N181ST AVE SE176TH AVE SE170TH PL
SE
N LANDING WAY
SE 58TH ST
147TH AVE SENE 3RD ST
SE 3RD PL
AIRPORT WAY
S TOBIN ST
SE 228TH PL
SE 112TH ST
SE 4TH PL
SE 49TH ST
SE 133RD ST
MINKLER BLVD
S 152ND ST
64TH AVE SGRANT AVE SSTEVENS AVE NWSE 149TH ST
S 32ND ST
SE 204T
H
WAY56TH AVE SS 36TH PLOAKESDALE AVE SWLIND AVE SW180TH AVE SE163RD PL SELOGAN AVE NSW 19TH ST
140TH AVE SE113TH AVE SEDIX
O
N
D
R
S
PUGET DR SEISLAND DR SSE
L
I
C
O
R
I
C
E
W
A
Y
CASCADE KY
SE 70TH ST
NE 27TH ST
I
-405
FWY
SW 16TH ST
IND
E
X
A
V
E
S
E119TH AVE SESE
1
7
0
T
H
P
L
140T
H
W
A
Y
S
E
N 8TH ST
98TH PL SNE 17TH ST
92ND AVE S80TH PL SEJONES AVE NE174TH AVE SEN 28TH PL
N 33RD PLN 34TH STN 35TH ST
NE 5TH ST
N 36TH ST
PATRIOT WAY SESE 232ND ST
SW 34TH ST
S 228TH ST 184TH AVE SE72ND AVE SSW 41ST ST 106TH AVE SES GRADY
W
A
YS 126TH STANDOVER PARK E59TH PL SSE 53RD
PL
S 180TH ST
S 187TH ST
S 188TH ST
SW 27TH ST
85TH AVE SHAZELWOOD LN138TH AVE SE136TH PL SES 222ND STWEST VALLEY HWY152ND AVE SE183RD AVE SELAKEHURST LN89TH AVE S87TH AVE SSE 184TH PL
1
6
6
T
H
W
A
Y
S
E
SE 8TH PL
EAST VALLEY HWY SSE COU
G
A
R
M
O
U
N
T
A
I
N
D
R
SE MAY C
R
E
E
K
P
A
R
K
D
R132ND PL SESE 50TH S
T
SE 95TH WAY
105TH AVE SE148TH AVE SES 199TH PL
6TH AVE N4TH AVE NSTRANDER BLVD
S 226TH STS 184TH PLSE 159TH PLRIPLEY LN SESE
1
7
1
S
T
W
A
Y
183RD WAY
SE
SW 43RD ST
SE 160TH PL
56
T
H
P
L
S
SE ROYAL HILLS DR
SE 196TH DR154TH PL SENE 31ST ST
EAST VALLEY RDS 133RD ST
S 135TH ST
SE R
E
N
T
O
N
-
I
S
S
A
Q
U
A
H
R
D
N R
IVERS
IDE
DR
SE
N
E
W
P
O
R
T
W
A
Y
M
A
R
T
I
N
L
U
T
H
E
R
K
I
N
G
J
R
W
A
Y
S
MONSTER RD SW80TH PL S169
T
H
A
V
E
S
E
SE RENTON-MAP
L
E
V
A
L
L
E
Y
R
D
B
E
A
C
O
N
-
C
O
A
L
M
I
N
E
R
D
S
S
E
M
A
Y
V
A
L
L
E
Y
R
D
14
4
T
H
P
L
S
E
SE JONES RD
Last Revised: May 20, 2016E:\KRCD DRIVE\Renton\LRRWRP\Figure 4.1.mxd
O 0 1 20.5 Miles
Legend
City of Renton Wastewater Service Area
Neighboring Wastewater Service Areas
Renton City Boundary
Urban Growth Boudary
Roads
Waterbodies
Utility Systems
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 4.2
Sewer Service Area and Adjacent
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-7
4.4 Land Use
Land Use designations and regulations provide important information in evaluating sewer
system capacity. Existing and future land use information is an integral component in projecting
wastewater generation for the City and jurisdictions within the service area boundary, including
KC, City of Tukwila, and City of Kent.
The City designates parcels into twelve land use categories, as shown in Figure 4.3, these
categories include:
• Residential Single Family
• Residential Low Density
• Residential Medium Density
• Residential Multi-Family
• Center Village
• Urban Center Downtown
• Urban Center North
• Employment Area – Industrial
• Employment Area – Valley
• Commercial Neighborhood
• Commercial/Office/Residential
• Commercial Corridor
4.4.1 City of Renton Land Use
The existing land use pattern of the City reflects 100 years of settlement and expansion. The
original City was settled in the broad floodplain at the confluence of the Cedar and Black Rivers
along the shore of Lake Washington. Downtown Renton, the Renton Municipal Airport, and the
Boeing/PACCAR industrial area now occupy these lands. Since the 1950s, the hills and highlands
above the valley have been developed primarily for residential housing and accompanying retail
businesses.
4.4.1.1 Downtown Renton
The Landing Development sits on approximately 60 acres of former Boeing Industrial Land and
currently consists of various retail uses and a significant multi-family component. This
development will continue to expand within its existing 60-acres over time as current surface
parking is replaced by structured parking, thus permitting future infill of additional retail,
residential, and commercial office applications. Future phases of The Landing include an
additional approximate 30 acres of land for similar uses as the existing. The initial development
of The Landing was a partnership between the City and the developer Harvest Partners.
Areas immediately north and south of downtown are characterized by older, single-family
development interspersed with small-scale multi-family developments.
Outside of the central business district, commercial areas are concentrated along the major
arterials and freeway exchanges, including Rainier Avenue, Grady Way, Sunset Boulevard,
NE 4th Street, the NE 44th Street exit from Interstate 405, and SW 43rd Street. These areas are
generally characterized by low intensity, auto-oriented strip commercial, but also include the
City's automall along Grady Way and several large-scale retailers.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-8 | MARCH 2021
4.4.1.2 The Green River Valley
South of downtown to the city limits, the Green River Valley has developed with manufacturing,
office and warehouse uses. The south and eastern portions of the valley include some
commercial uses. New commercial and industrial development activity, as well as changes in
business type is expected to increase sewer flows in the Valley within the future.
4.4.1.3 Residential Growth
Significant residential development has occurred on the uplands above the Green River Valley,
downtown, and East Kennydale areas. These areas are primarily comprised of single-family
neighborhoods, although some concentrations of multi-family and commercial uses exist. West
of downtown, residential development extends seamlessly from the City up onto the West Hill of
unincorporated KC. On the east side of the service area, residential development extends from
downtown to the UGB, with the denser development closer to downtown and becoming less
dense as you travel east.
The City's PAA and sanitary sewer service area on the East Renton Plateau is generally
characterized by large-lot single-family, moderate density single-family developments, and
vacant, un-platted parcels. This area, known as the East Renton highlands, has seen significant
single-family growth occur over the past decade and anticipates continued expansion of the
sewer system.
4.4.1.4 Passive Land Use
The geography and hydrology of the City vicinity, as well as a proactive parks acquisition
program by the City, combine to provide significant open spaces that constitute a passive land
use. Some larger examples include lands adjacent to the Cedar River and May Creek,
Gene Coulon Park on Lake Washington, the Black River Riparian Wildlife Habitat area, and
habitat areas of the Green River Valley.
4.4.1.5 2015 Comprehensive Plan
The City has had a Comprehensive Plan since 1965. The current plan, adopted in 2015 and
annually amended, was developed and approved under the regulatory requirements of the
Washington Growth Management Act (GMA) and the policy framework of the KC Countywide
Planning Policies. While the plan includes Transportation, Housing, Capital Facilities, Utilities,
Downtown, Economic Development, and Environmental Elements, it is the policy decisions
expressed in the Land Use Element that gives the plan its primary direction and cohesiveness.
This LRWWMP proceeds from and supports the policies and Land Use Map of the
Comprehensive Plan. Utility Element policies have been addressed in Chapter 3 – Operational
Policies and Criteria.
To the extent that the City has jurisdiction or can require compliance, development within the
service area must be consistent with the City's Comprehensive Plan. Consistency with certain
elements of the Comprehensive Plan is required as a condition of sanitary sewer service outside
the city limits. The Comprehensive Plan is intended to provide the basis for all development
regulations, functional plans and other City plans and programs that may in some way support,
implement or derive from the City's land use plans. The Comprehensive Plan is a broad
statement of community goals and policies that direct the orderly and coordinated physical
development of the City. The Comprehensive Plan anticipates change and provides specific
guidance for future legislative and administrative actions. The Comprehensive Plan also serves
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-9
as a guide for designating land uses and infrastructure development as well as developing
community services.
4.4.1.6 Service Outside the City
Sewer service outside the City is outlined in the current code.
4.4.2 City of Renton Land Use Designations
For the purposes of the LRWWMP, the Land Use Map adopted on September 22, 2014 within the
Land Use Element of the Comprehensive Plan was assumed to represent the intended future
pattern of land uses in the planning area as shown in Figure 4.3 and areas are tabulated in
Table 4.1. The City’s Land Use schema identifies six types of land uses: Residential Low Density,
Residential Medium Density, Residential High Density, Commercial & Mixed Use, Employment
Area, and Commercial Office Residential. The service area addressed in the LRWWMP includes
most of the area within the existing city limits, the UGB, and one area outside the UGB. The area
outside of the City (dashed black line in Figure 4.1), and within the study area (solid green line in
Figure 4.1) includes 117 acres (0.18 square miles [mi2]) within the city limits of Tukwila,
approximately 15 acres (0.02 mi2) within the city limits of Kent, and 12 acres of unincorporated
areas in the City’s PAA (0.02 mi2).
Table 4.1 Land Use of Renton’s Sewer Service Area
Land Use Designation Within Existing City Boundaries
(Acres) PAA (Acres)
Residential Single Family 5,000 1,504
Employment Area 1,779 0
Residential Medium Density 925 73
Commercial Neighborhood 32 2
Commercial Corridor 1,046 144
Commercial/ Office / Residential 137 6
Residential Multi-Family 688 286
Employment Area - Industrial 528 47
Residential Low Density 3,782 5,538
Urban Center North 348 3
Urban Center Downtown 233 0
Center Village 216 0
Total 14,714 (23.0 mi2) 7,603 (11.9 mi2)
The district designations on the land use map correspond to policies in the Land Use Element
of the Comprehensive Plan and are implemented by the City's adopted Zoning Map and
Zoning Code. The land use designations are described below based on Renton Municipal
Code (RMC) 4-2-020.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-10 | MARCH 2021
4.4.2.1 Residential Designations
Residential Low Density Land Use Designation
The designation is intended to guide development on land appropriate for a range of low
intensity residential and employment where land is either constrained by sensitive areas or
where the City has the opportunity to add larger-lot housing stock, at urban densities of up to
four dwelling units per net acre (du/net acre), to its inventory.
Residential Medium Density Land Use Designation
The Residential Medium Density designation is for "neighborhoods based on a mix of single-family
and small to mid-sized multi-family developments built around amenities such as shopping
centers, recreation areas, and other community gathering places". Residential medium density
land use designations include between three and eight dwellings per acre (R-6 and R-8 Zoning).
Residential High Density Land Use Designation
The Residential High Density Land Use designation provides a mix of residential styles including
small lot detached dwellings or attached dwellings. Residential High Density is "intended to
increase opportunities for detached dwellings as a percent of the housing stock, as well as allow
some small-scale attached housing choices and to create high-quality infill development that
increases density while maintaining the single-family character of the existing neighborhood".
Higher density neighborhoods may "provide a mix of detached and attached dwelling structures
organized and designed to combine characteristics of both typical single-family and small-scale
multi-family developments." High density land use designations include between five and
fourteen dwellings per acre (R-10 and R-14 Zoning).
Residential Multi-Family Designation
The multi-family residential land use designation is intended to encourage a range of
multi-family living environments that provide shelter for a wide variety of people in differing
living situations, from all income levels, and in all stages of life. Densities range from 10
to 20 dwellings per acre (Residential Multi-Family [RMF] Zoning).
S 130TH PL144TH AVE SESE 211TH ST
S 116TH ST
SE 196TH ST
NE 24TH ST
SE 148TH STLAKE WASHINGTON BLVD NNE 21ST ST
UNION AVE NE121ST PL SESE 144TH STINTERURBAN
AVE
S
S 132ND ST BURNETT AVE NS 212TH WAY
NE 19TH ST84TH AVE SELAKE WASHINGTON BLVD SEHARDIE AVE SWSOUTHCEN
T
E
R
B
L
V
D
S 125
T
H
ST
S 208TH ST
120TH PL SES 115TH PL
MAIN AVE SSE 141ST ST
TALBOT RD S84TH AVE S135TH AVE SECEDAR AVE SSUNSET BLVD NE134TH AVE SES 202ND ST BENSON RD
SLINCOLN AVE NEHOQUIAM AVE NESE 227TH PL
100TH AVE SES 15TH ST
S 134TH ST
160TH AVE SE126TH AVE SESE 218TH PL 148TH AVE SEN 30TH ST
S BANGOR ST W MERCER WAY112TH AVE SESE 179TH ST
S 190TH ST
120TH AVE SENE
1
S
T
S
T
S 7TH ST 130TH AVE SESE 44TH PL
59TH AVE S78TH AVE SES 115TH ST
76TH AVE SNE 7TH PL
S 130TH STCORNELL AVE SSOMERSET BLVD
SE
C
A
S
C
A
D
E
K
Y
127TH AVE SEEDMONDS AVE NESE 79
T
H
D
R
N 38TH ST
S
K
A
G
I
T
K
Y
NE 12TH ST96TH AVE
SE
NE 8TH ST
SE 56TH ST
RA
I
N
I
E
R
A
V
E
S
NE 7TH ST
S L
A
K
E
R
I
D
G
E
D
R
SE 192ND DR
S 23RD ST58TH AVE SWILLIAMS AVE SS 200TH ST 156TH AVE SES 116
T
H
P
L HARRINGTON AVE NE94TH AVE SSE 60TH ST143RD AVE SEB
E
A
C
O
N
A
V
E
S
MORRIS
AVE
S
NE 6TH PL
131ST AVE SEDUVALL AVE NEWA
T
E
R
S
A
V
E
S
CENTRAL AVE NSE 64TH ST
85TH PL SESE 145
T
H
P
L
S 2ND STLIND AVE NWSE 75T
H
P
L
P
E
T
E
R
G
R
U
B
B
R
D
S
E155TH AVE SESE 61ST ST
104TH PL SE63RD AVE SSE 40
T
H
P
L
133RD AVE SEWELLS AVE S137TH AVE
SE164TH WAY SES 38TH CT ANACORTES AVE NE129TH PL
SE
SE
1
5
1
S
T
S
T
SE 38TH ST
86TH AVE SE121ST AVE SESE 45TH ST
E MERCER WAYSE 200TH ST118TH AVE SEREDMOND AVE NENE 6TH ST87TH AVE SS 124TH ST
SE 8
3
R
D
S
T
SE 158T
H
S
T
93RD AVE SSE PET
R
O
V
I
T
S
K
Y
R
D
S 1
8
T
H
S
T
SE 46TH WAY
SE 48TH DR
85TH AVE SSE 134TH ST
162ND AVE SE151ST AVE SES 19TH ST
SE 46TH ST
OLYMPIA AVE NESE 160TH ST
S 14TH S
T
W
E
S
T
L
A
K
E
S
A
M
M
A
M
I
S
H
P
K
W
Y
S
E
NE 20TH ST
CRESTWOOD DR SMONROE AVE NE123RD AVE SES 117TH ST
128TH AVE SESE 1
8
3
R
D
D
RJERICHO AVE NESE 221ST S
T 175TH AVE SESE 216TH ST
NE 9TH STWOODLEY AVE SS 220TH ST HOUSER WAY NKIRKLAND AVE NESE 102ND
S
T
N 5TH ST
N 6TH ST
SE 71ST ST
66TH AVE SSE 223RD ST
SE 128TH ST
SE 156TH S
T
124TH AVE SESHATTUCK AVE SSE 4TH ST
N 3RD ST
SE 73RD PL
S 127TH S
T BREMERTON AVE NE168TH PL SESE 164TH ST
INDUSTRY DRFOR
E
S
T
D
R
S
E
BRONSON WAY NES RYAN ST
TUKWILA PKWY
SE 55TH ST
SE 142ND ST82ND AVE SESE C
A
R
R
R
D
S 216TH ST
S 128TH ST
SE 172ND ST 167TH PL SENE 16TH ST
SE
R
E
N
T
O
N
-
I
S
S
A
Q
U
A
H
R
D
SE 202ND PL108TH AVE SE146TH AVE SE57TH AVE SSE 136TH STROSARIO PL NESE 116TH ST
NE 22ND ST
AVALO
N
D
R
SE 68TH ST
SE 40TH ST
SE 42ND ST
SE 72ND ST
SE 41ST ST
S S
U
N
N
Y
C
R
E
S
T
R
D
DI
X
O
N
D
R
SFOREST AVE SE
SE 212TH ST93RD AVE SESTRANDER BLVD
SE 204TH PL
S 196TH ST
SE 138TH PL
SR 167SE 208TH ST
S 218TH ST NILE AVE NE104TH AVE SEN 10TH ST
VIL
L
A
G
E
P
A
R
K
D
R
S
ESOMERSET DR SEWE
S
T
L
A
K
E
D
E
S
I
R
E
D
R
S
E177TH AVE SESE 224TH ST
S 112TH ST
SE 52N
D
S
T
ILWACO AVE NEBENSON DR SLIND AVE SWNE 10TH STHIGHLAND DRMILL
AVE
S
NE 2ND ST
S 212TH ST
SE 183RD ST
S 224TH ST
NE 23RD PL
ANDOVER PARK WS 113TH ST
NEWCASTLE GO
L
F
C
L
U
B
R
D
SE 4
7
T
H
S
T
S 120TH ST
SE 219TH PL
NE
W
C
A
S
T
L
E
W
A
Y
125TH AVE SE135TH PL
SE
SE 76TH ST
PELLY AVE NSW 7TH ST 188TH AVE SES 121ST ST
N 33RD ST
N 29TH ST
SE 51S
T
S
T
129TH AVE SESE 233RD ST
SE 91ST ST
SE 176TH ST150TH AVE SESE 213TH STBLAINE AVE NE127TH PL SESW 12TH ST
SE 223RD DR 161ST AVE SEHIGH AVE SSE 42ND PL
NE 4TH ST
SE 66TH ST
172ND AVE SEMONTEREY AVE NESE 225TH ST
SE ALLEN RD
60TH AVE SBURNETT AVE SSW 39TH ST77TH AVE SESE 221ST PL65TH AVE SSE
F
A
I
R
W
O
O
D
B
L
V
D
PARKSIDE WAY SEN 32ND ST
SE 82ND ST
S LANGSTON RD
SOUTHCENTER PKWYSW 16TH ST
MINKLER BLVD 85TH AVE SEN 31ST ST
SW 10TH S
T
S 192ND ST 171ST PL
SE
S 204TH ST
SE 5TH ST
SE LAK
E
Y
O
U
N
G
S
R
D
SE 226TH ST61ST AVE SMERCE
R
W
O
O
D
D
R
SW 3R
D
P
L
SW
S
U
N
S
E
T
B
L
V
D
SE 106TH ST
SE 192ND ST 149TH AVE SESE 220TH PL77TH AVE SSE 80TH ST
78TH AVE S62ND AVE SSE 2ND PL
S 231S
T
S
T
SE 180TH STPOWELL AVE SWSE 214TH ST171ST AVE SES 114TH ST
SE 121ST PL
PARK AVE NSE 59TH ST89TH AVE SE88TH AVE SEGARDEN AVE N91ST AVE SE81ST AVE SE92ND AVE SES
E
1
7
0
T
H
S
T
S TAFT ST
PASCO PL NENE SU
N
S
E
T
B
L
V
D
94TH PL S136TH AVE SESE
8
0
T
H
W
A
Y
SE 188TH ST
M
A
R
T
I
N
L
U
T
H
E
R
K
I
N
G
J
R
W
A
Y
S 117TH AVE SES 50TH ST 190TH AVE SE80TH AVE SESE 168TH ST
S 194TH ST
N 4TH ST
132ND AVE SE81ST PL SE116TH PL SE80TH AVE S164TH AVE SE102ND AVE SE126TH PL SESE 65TH ST
UNION AVE SESE 1
1
0
T
H
S
T
SE 204TH ST
S PUGET DRRAINIER AVE N181ST AVE SE176TH AVE SE170TH PL SESE 58TH ST
147TH AVE SE64TH AVE SNE 3RD
S
T
SE 3RD P
L
AIRPORT WAY
S TOBIN ST
SE 228TH PL
SE 4TH
P
L
SE 112TH ST
SE 49TH ST
SE 184TH ST116TH AVE SEABERDEEN AVE NESW GR
A
D
Y
W
A
Y
GRANT AVE SSE 149TH STISLAND CREST WAYS 32ND ST
SE 204
T
H
W
A
Y
REN
T
O
N
A
V
E
S
SUNSET BLVD NS 36TH PLOAKESDALE AVE SW180TH AVE SENE PARK DR
163RD PL SELOGAN AVE NSW 19TH ST
113TH AVE SESE 63RD ST
I-405 FWYPUGET DR SEISLAND DR SS
E
L
I
C
O
R
I
C
E
W
A
Y
NE 27TH ST
SE 44TH ST
COAL CREEK PKWY SE119TH AVE SES
E
1
7
0
T
H
P
L
140
T
H
W
A
Y
S
E
N 8TH ST
98TH PL S92ND AVE S80TH PL SESE 43RD ST
JONES AVE NE174TH AVE SEN 28TH PL
NE 5TH ST
N 33RD PLN 34TH STN 35TH STN 36TH ST
SE 232ND ST
SW 34TH ST
68TH AVE S75TH AVE S184TH AVE SE72ND AVE SLUMMI KY
106TH AVE SESW 41ST ST
S GRAD
Y
W
A
Y FACTORIA BLVD SES 126T
H
S
T
ANDOVER PARK ES 228TH ST59TH PL SSE 53R
D
P
L
LAKEMONT BLVD SE
S 180TH ST
S 187TH ST
S 188TH ST
SW 27TH ST
138TH AVE SE136TH PL SES 222ND ST
66
T
H
L
N
S 152ND AVE SEWEST VALLEY HWY183RD AVE SELAKEHURST LNSE 184TH PL
89TH AVE S1
6
6
T
H
W
A
Y
S
E
SE 8TH PL
WOODSIDE DR SEEAST VALLEY HWY SSE C
O
U
G
A
R
M
O
U
N
T
A
I
N
D
R
SE MAY
C
R
E
E
K
P
A
R
K
D
R
SE 95TH WAY
SE 50T
H
S
T
6TH AVE N88TH AVE S4TH AVE
N
S 199TH PL
SE 228TH ST
S 226TH ST
SE 159TH PL
I-90
F
W
Y
RIPLEY LN SES
E
1
7
1
S
T
W
A
Y
183RD WAY SESE 160TH PL
SW 43RD ST
SE ROYAL HILLS DR
SE 196TH
D
R140TH AVE SESE
6
4
T
H
W
A
Y
154TH PL SERENTON-ISSAQUAH RD SENE 31ST ST
EAST VALLEY RDMA
P
L
E
V
A
L
L
E
Y
H
W
Y
S 133RD ST
S 135TH ST
SE 65TH
P
L
N R
IVERS
IDE
DRNW VILLAGE PARK DRMONSTER RD SWSE NE
W
P
O
R
T
W
A
Y
80TH PL
S
16
9
T
H
A
V
E
S
E
B
E
A
C
O
N
-
CO
A
L
M
I
N
E
R
D
S
S
E
M
A
Y
V
A
L
L
E
Y
RD
SE RENTON
-
M
A
P
L
E
V
A
L
L
E
Y
R
D
1
4
4
TH
P
L
SE
SE JONE
S
R
D
Last Revised: July 05, 2019F:\KRCD DRIVE\Renton\LRRWRP_Figures\Figure 4.2.mxd
Figure 4.3
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
O 0 1 20.5 Miles
Legend
Renton City Boundary
Roads
Renton Wastewater Service Boundary
Waterbodies
Comprehensive Land Use Designations
Residential
Residential Low Density
Residential Single Family
Residential Medium Density
Residential Multi-Family
Center Designations
Center Village
Urban Center Downtown
Urban Center North
Employment Area Designations
Employment Area - Industrial
Employment Area - Valley
Commercial Designations
Commercial Neighborhood
Commercial/Office/Residential
Commercial Corridor
Comprehensive Plan Land Use
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-13
4.4.2.2 Commercial and Mixed Use Designations
Commercial Neighborhood Land Use Designation
The purpose of Commercial Neighborhood designation is for "small-scale convenience
retail/commercial areas offering incidental retail and service needs for the surrounding area.
Uses serving a larger area may be appropriate if they also serve the residents of the immediate
area and are compatible with the scale and character of the neighborhood".
Commercial/Office/Residential Land Use Designation
The Commercial Office (CO) designation is "established to provide areas appropriate for
professional, administrative, and business offices and related uses, offering high-quality and
amenity work environments. In addition, a mix of limited retail and service uses may be allowed
to primarily support other uses within the zone, subject to special conditions".
Center Village Land Use Designation
Center Village (CV) designations are characterized by an existing commercial and multi-family
core served by transit and set in the midst of suburban patterns of residential development or in
the City’s downtown. CV zoned lands are suitable for redevelopment into compact urban
development with a pedestrian-oriented, mixed-use center, and community focal point. The
zone is intended to revitalize an area, creating a vibrant, urban center where surface parking is
discouraged. CV zoning implements the Commercial and Mixed Use designation.
4.4.2.3 Center Downtown Land Use Designation
Center Downtown (CD) designation within downtown Renton is appropriate for the widest mix
of uses, is served by transit, and is suitable for intensive urban use within a pedestrian
environment. The CD zone is intended to revitalize the area by creating a vibrant, urban center in
the City’s historic downtown core. Surface parking is discouraged in this zone, except as a land
bank. CD zoning implements the Commercial and Mixed Use Land Use Designation.
4.4.2.4 Urban Center Land Use Designation
The Urban Center (UC) North land use designation include lands that are located within the
City’s Designated Regional Growth Center, if there is a potential for the creation of dense
employment, destination retail, recreation, or public gathering space with the UC zone. The UC
zoned areas have large parcels of land with the potential for large scale redevelopment
opportunities that will create a mixed-use retail, employment, and residential center. UC zoning
implements the Commercial Mixed Use land use designation.
4.4.3 School Designations
The City serves public elementary, middle, and high schools from the Issaquah and Renton
School districts, in addition to Renton Technical College. These schools are spread throughout
the City and can be found within each service basin, except for the May Valley Basin, as shown in
Table 4.2. There are two schools in the City’s service area, Maywood Middle School and
Briarwood Elementary School, which are not currently connected to the public sewers. Both of
these schools are in the East Cedar River Basin.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-14 | MARCH 2021
Table 4.2 Schools Served by Renton
Name Mini-basin Employment
(PE’s) Staff (PE’s)
Highlands Elementary 48 545 63
Honey Dew Elementary 26 525 62
Kennydale Elementary 33 559 66
Maplewood Elementary 44 612 56
Sierra Heights Elementary 21 618 63
Talbot Hill Elementary 7 526 50
Tiffany Park Elementary 4 466 52
McKnight Middle School 37 1159 105
Nelson Middle School 2 1041 70
Hazen High School 22 1380 124
Renton High School 15 1218 90
Renton Secondary Learning Center 14 298 34
Apollo Elementary School 22 576 69
Briarwood Elementary School U6 440 70
Liberty High School U6 1224 107
Maywood Middle School U9 905 80
Renton Technical College 27/29 3400 230
Note:
Abbreviation: PE – Person Equivalent.
4.4.4 Land Use Outside Renton’s PAA
A remaining 137 acres of jurisdiction is part of the service area beyond the city limits and PAA.
Table 4.3 displays the land use designations for those areas within the City's service area.
Table 4.3 Land Use Designations for Areas Outside Renton
Jurisdiction (Designation) Land Use (Density) Area (Acres)
Kent (US) Urban Separator (1 unit / acre maximum) 15
Tukwila (Commercial/
Light Industrial)
Commercial/Office/Light Industrial 82
Tukwila (Tukwila Urban Center) Commercial/Office/Light Industrial/
Multi-Family (22 du/net acre maximum)
40
Note:
Abbreviation: US – Urban Separator.
4.4.4.1 King County Land Use
For the purposes of the LRWWMP, the 2018 King County Comprehensive Plan was used to direct
Land use within the unincorporated portions of the study area. All of the service area in
unincorporated KC is designated "urban", with the exception of the service to Apollo Elementary
School just east of the urban growth areas (UGAs). UGAs are intended to develop at urban
densities and with urban service levels. The UGB is the division line between the designated
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-15
urban and rural areas that defines the eastern boundary of the City’s PAA. According to the KC
Countywide Planning Policies that provide a policy framework for all comprehensive plans in KC,
cities may not annex areas outside the UGB nor may they provide sewer service, except "where
needed to address specific health and safety problems or the needs of public facilities such as
schools (Policy F-264)”.
Unincorporated areas of KC are divided into community planning areas, each with a community
plan. For the purposes of the LRWWMP, community plans were based on those adopted as part
of the 2012 King County Comprehensive Plan. Where conflicts or inconsistencies between the
policies of the community plans and KC’s Comprehensive Plan occur, the Comprehensive Plan
takes precedence. Three community plans, Soos Creek, West Hill, and Newcastle, cover most of
the unincorporated areas within the study area of this LRWWMP.
4.4.4.2 City of Kent Land Use
City of Kent Planning Division assures quality in the land development process by effective
administration of land use codes and compliance with the GMA. The Comprehensive Plan Land
Use Map provides the general vision for the City's growth over the next twenty years, and
provides a framework for amendments to the City's official Zoning Districts Map.
Approximately 15 acres of the City’s sewer service area are within the City of Kent. This area is
designated as single-family residential.
4.4.4.3 City of Tukwila Land Use
Approximately 122 acres of the City’s sewer service area are within the City of Tukwila. Based on
the 2015 Comprehensive Plan, 40 acres are within the Tukwila Urban Center that contains an
intense diverse mix of use that will continue to evolve over time. The center is a regional
commercial/industrial area with limited mixed-use residential. The remaining area is designated
as Commercial/Light Industrial.
4.4.5 Adjacent Utility Systems/Joint Use, Service Agreements, and Related Plans
The City has entered into several joint use and service agreements with neighboring districts and
private customers when it has been economically beneficial. A list and a summary of these joint
use and service agreements are presented below. The full text for each of these agreements is
presented in Appendix E, Service Agreements:
• Coal Creek Utility District (formerly Water District No. 107):
- CAG-035-075, 1975 - Construction of an interceptor line from the City sewer service
area through Water District No. 107 to a collection trunk operated by the
Municipality of Metropolitan Seattle
- Sewer Utility Franchise, 1987 - The City granted Water District No. 107 the right to
install sewer lines within the service area of Water District No. 107
- CAG-01-031, 2001 - Sewer service boundary clarification
• City of Kent:
- CAG-012-83, 1983 - Provides for the installation of a sanitary sewer main that is
owned and operated by the City and allowing the City to provide sewer service to
the adjacent properties that are in the Kent service area
• King County:
- Franchise No. 14056, 2001 - Grants the City the right to construct sewer lines along
KC roads
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-16 | MARCH 2021
• Soos Creek Water and Sewer District, formerly called Cascade Sewer District:
- Resolution 1234 AG-764-64, 1964 - Interceptor sewer line from the Cascade sewer
system through portions of the City to the sewer system of the municipality of
Metropolitan Seattle. Addendum 1 and 2 were made in 2011 and 2014, respectively
- Agreement CAG-039-074, 1974 - Extension of the City’s sewer service to certain
areas within the Cascade sewer service area
- CAG-083-91, 1991 - Soos Creek Water and Sewer District to provide sewer service to
certain properties within City limits
- CAG - 097-164, 1997 - Revision of the water and sewer service boundary
- CAG -083-91 Addendum 1-04, 2004 - The Soos Creek Water and Sewer District may
connect certain properties (described in the 1991 agreement) to the City’s Sewer
System
• Skyway Water and Sewer District:
- CAG-03-197, 2003 - Sewer and water service boundary clarification
- CAG-06-170, 2006 - Skyway Water and Sewer District may connect a portion of
their service area into the City’s sewer facilities
• Cedar River Water and Sewer District:
- CAG-99-014, 1999 - Water and sewer service boundary clarification
The City is surrounded by seven adjoining sewer utility entities, as previously shown in Figure 4.1.
These adjacent utility entities are listed below.
4.4.5.1 Coal Creek Water and Sewer District
Coal Creek Water and Sewer District (formerly King County Water District No. 107) provides
sewer service in part of the May Valley Basin. The City and Coal Creek have made boundary
adjustments to remove previous service overlaps. This interlocal agreement provides for joint
use of a sewer main in Lincoln Avenue for the provision of service to that area and to allow for
another portion of the City’s service area to flow into Coal Creek’s system.
4.4.5.2 Cedar River Water and Sewer District
Cedar River Water and Sewer District (CRWSD) provides service to parts of the Lower Cedar
River Basin. However, only a small fraction of the wastewater from CRWSD ultimately flows
through the City's system by flowing through the Soos Creek Water and Sewer District. The
majority of sewage from CRWSD flows directly into KC’s Cedar River Interceptor located along
the Maple Valley Highway. CRWSD’s last Comprehensive Sewer Plan was adopted in 2016. The
City and CRWSD have entered into a 1999 interlocal agreement identifying the common service
boundary between the two service providers.
4.4.5.3 Soos Creek Water and Sewer District
Soos Creek Water and Sewer District adopted the Soos Creek Water and Sewer District Sewer
Comprehensive Plan in July of 2014. In 1997, the District and City entered into an interlocal
agreement revising the boundary between Soos Creek and the City that had been set by a 1991
agreement. Based upon these agreements, the City is the service provider to some areas
currently outside the City and Soos Creek provides service to some areas inside the city limits.
A 1964 agreement provides for joint use of a sewer interceptor in the Tiffany Park Subbasin, and
the 1991 agreement provides for joint use of the Springbrook Interceptor, located on
South 192nd Street. The Springbrook Interceptor will provide service to the southernmost
portions of the City.
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-17
4.4.5.4 City of Kent
SW 43rd Street is the principal dividing line between the Cities of Renton and Kent. The City has
an agreement with Kent to serve a small area south of SW 43rd Street east of 72nd Avenue Street
and west of the Puget Sound Electric Railway right-of-way. The City of Kent Comprehensive
Sewer Plan was adopted in 2002 (dated 2000). The Renton and Kent City limits adjoin each other.
There is a small portion of the City of Kent, south of South 55th Street and east of the Valley
Freeway that is in the City’s service area. There are no service area overlaps or gaps between the
two entities, except for that one small area.
4.4.5.5 City of Tukwila
The City serves a portion of the City of Tukwila east of the Burlington Northern Railroad and
south of Longacres. Tukwila also discharges from a lift station into the KC Sewer System within
the City along Monster Road SW. Tukwila prepared a Comprehensive Sewer Plan in 2014.
Approximately 122 acres of the City’s sewer service area is within the City of Tukwila.
4.4.5.6 Skyway Water and Sewer District
Skyway Water and Sewer District adopted a Comprehensive Plan in 2004 The Skyway sewer
service area is shown in Figure 4.1. The boundary between Skyway and the City has been set by
an interlocal agreement adopted in 1994. An area in the southern portion of the District, as well
as in the service area to the south of the District, could be served by gravity to the City’s sanitary
sewer system. An agreement to allow the district to route portions of this southern service area
through the City’s facilities was entered into in 2006. Skyway Water and Sewer District provides
sanitary sewer service to a small area of the City along Rainier Avenue near South 117th Place
and the northwest portion of the airport. Skyway sewage discharges into the KC System within
the City at the north end of the Renton Airport.
4.4.5.7 King County Regional Wastewater Services Plan
For more than 40 years, KC has protected water quality in the Puget Sound region by providing
wastewater treatment services to King, Pierce, and Snohomish counties, including the City. To
ensure the continuation of high quality wastewater treatment services in the future, KC carried
out an intensive planning effort, involving numerous elected officials, representatives from local
sewer agencies, organizations, and individuals from around the region.
The Regional Wastewater Services Plan (RWSP) resulted from these efforts, which was adopted
by the KC Council in November 1999, via Ordinance 13680. The RWSP outlines a number of
important projects, programs, and policies for KC to implement through 2030, and work is well
underway. A summary of the major components of the RWSP includes Brightwater Treatment
System, Conveyance System Improvements, Regional Infiltration and Inflow Control, Combined
Sewer Overflow Control, Odor Control Program, Biosolids Recycling, and Reclaimed Water. In
2013, KC completed a comprehensive review of RWSP. The Compressive Review found that full
expansion of the South Treatment Plan, located in the City, will likely occur in the 2030s based
on updated treatment capacity needs, not 2029 as previous planned.
In December 1999, as part of the RWSP, the KC Council approved the development of a Regional
Infiltration and Inflow (I/I) Control Program. The purpose of the program is to reduce the risk of
sanitary sewer overflows and the cost of adding capacity to facilities that convey wastewater to
KC treatment plants.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-18 | MARCH 2021
In 2000, KC’s Wastewater Treatment Division, in cooperation with the local component agencies
that it serves, of which the City is one of, launched an I/I Program. The recommendations of the
I/I Program represent the consensus reached by the KC and local agencies throughout the 6-year
program development process. Knowledge gained from flow monitoring, modeling, pilot
projects, and a benefit-cost analysis conducted during the I/I control study served as the basis for
consensus.
Recommendations are presented for both I/I reduction and long-term I/I control and for program
administration and policy. In addition to cost-effectively removing enough I/I from the collection
system to delay, reduce, or eliminate some otherwise needed conveyance system
improvement (CSI) projects, measures must be in place to maintain I/I reductions long-term and
to prevent future increases in I/I throughout the regional system. Long-term I/I control includes
policy, administrative, financial, and technical measures that promote an ongoing program of
review, maintenance, and repair of the collection and conveyance system.
4.4.5.8 King County Conveyance System Improvement Program
Since 1999, the CSI Program focuses on guiding major upgrades and improvements to
KC-owned facilities. A 2017 CSI program update was completed with conceptual projects
approved in 2017. As part of this effort, a Regional Needs Assessment report was completed
in 2015, where the City discharges are included in the South Lake Washington Planning Area. As
discussed in Chapter 5 – System Analysis and Results, surcharging in these interceptors impacts
capacity in the City's system.
4.4.5.9 King County Reclaimed Water Comprehensive Plan
The City is participating in the regional forum, consisting of King County, Cascade Water
Alliance, Seattle Public Utilities, and individual surrounding purveyors, in combined effort to
develop a master agreement for reclaimed water as well as reclaimed water planning and
policies. The forum represents a regional approach to strategic planning and system expansions
needed to accommodate the distribution, sale, supply, and reuse of reclaimed water that could
include the City's current and future service area.
The City will support the regional supplier's study of reclaimed water use opportunities and will
work with King County Department of Natural Resources to identify potential reclaimed water
users and demand. Any reclaimed water to be used as a source of supply should only be provided
through retail water suppliers. The City has identified several potential users of reclaimed water
for landscape irrigation uses, including the Boeing Longacres Facilities.
4.5 Demographic Analysis
Future sewer system requirements are based, in part, upon future demographic growth
projections within the sewer service area. Demographic growth projections were created for
areas within the City, unincorporated KC, and several small service areas that the City has agreed
to serve in adjacent jurisdictions. Most of the projected sewer area growth will occur in the areas
east of the current City limits, including a large non-sewered area within unincorporated KC in
the East Plateau service area, also known as the East Renton Highlands. This section summarizes
the demographic projections made as part of latest hydraulic model update documented in the
2012 Hydraulic Model Update (Stantec, 2015).
Demographic projections were sought for existing condition and build-out. The existing
condition was set as the year 2012 to correspond with the most recent flow monitoring effort.
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-19
Puget Sound Regional Council (PSRC) Land Use Baseline projections, which were developed
using the UrbanSims, provide demographic data through 2040. The City will likely reach
build-out by 2040 with future growth from redevelopment. Therefore, the City defined the
Ultimate projection as the PSRC 2040 projection plus a 25 percent factor as a margin of safety to
account for future redevelopment and changes to building practices.
Population, household, and employment data was derived from the PSRC Traffic Analysis
Zone (TAZ) projections for the years 2012 and 2040. The data obtained was provided in
geographic subdivisions based on the sewer mini-basin boundaries provided to PSRC by Stantec.
Consistent with other LRWWMP, demographic data and results in this chapter are summarized
based on sewer mini-basins, rather than TAZ.
4.5.1 Residential Population Projections
In total, existing populations were determined to be 43,869 single-family and 24,417 multi-family
using both PSRC residential and Baseline Land Use. The total future population was projected to
be 76,731 and 37,386 which is an increase of 32,862 and 12,452 single- and multi-family
households, respectively, over a period of 28 years. This is an approximately 1,174 single-family
and 445 multi-family increase in population annually.
Mini basins which see the greatest growth include basins 30B, 30C, and U9 at rates of
2,000 percent, 4,650 percent, and 2,582 percent, respectively, over the 28 year period.
4.5.1.1 Existing - 2012
The PSRC data provided 2012 residential projections for single-family and multi-family
populations. Stantec performed a review of the data to resolve any obvious inaccuracies
identified through the review of City geographic information system (GIS) data within each
mini-basin, including land-use, parcel count, and aerial photos. Additionally, larger multi-family
developments were reviewed using KC Assessor’s information.
Based on this review, populations for the following basins were modified as documented in the
2012 Hydraulic Modeling Update:
• Basin 5 – The Land Use Baseline projections list 126 parcels and a single-family
residential population of 169. City GIS data shows 170 parcels within the basin, with an
estimated 100 single-family lots. A multiplier of 2.5 persons per single-family lot was
used to estimate a single-family residential population of 250 for this basin. The
multi-family population supplied by PSRC is negligible, and is consistent with the City
GIS data
• Basin 20 – The estimate from PSRC for this mini-basin encompassed the Ultimate
mini-basin boundary. To estimate the population for the current boundary, the total
of 3,007 people was scaled on an area ratio of the current/ultimate basins for an adjusted
population of 2,390. The multi-family development and zoning is all within the current
mini-basin boundary, so this population was not modified
• Basin 25/Basin 43 – Both of these mini-basins include large mobile home parks, which
are not accounted for in the PSRC projections for either single-family or multi-family
populations. Basin 25 includes approximately 240 mobile homes, and Basin 43 includes
approximately 200 mobile homes. To account for these populations, a multiplier
of 1.8 (multi-family) was applied to each mobile home, and the populations were added
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-20 | MARCH 2021
to the projections supplied by PSRC. For Basin 25, the total residential population was
adjusted from 983 to 1,415. For Basin 43, the population was adjusted from 49 to 410
• Basin U1 - The Land Use Baseline projections list 58 parcels and a single-family
residential population of 255. City GIS data shows approximately 205 parcels within the
basin, with an estimated 197 single-family lots. A multiplier of 2.5 persons per
single-family lot was used to estimate a single-family residential population of 490 for
this basin. The multi-family population supplied by PSRC is negligible, and is consistent
with the GIS data
• Basin U6 – The estimate from PSRC for this mini-basin encompassed the ultimate
mini-basin boundary. To estimate the population for the current boundary, the total
of 2,050 people was scaled on an area ratio of the current/ultimate basins for an
adjusted population of 1,345. The multi-family population supplied by PSRC is
negligible, and is consistent with the GIS data. It was not modified
• Basin U9 – The estimate from PSRC for this mini-basin encompassed the ultimate
mini-basin boundary. To estimate the population for the current boundary, the total
of 1,268 people was scaled on an area ratio of the current/ultimate basins for an
adjusted population of 68. No multi-family population was projected. This is consistent
with the GIS data
All modifications were reviewed and accepted by City Planning Department staff.
4.5.1.2 Future
The PSRC 2040 residential projections estimated single-family and multi-family populations that
are aligned with the Vision 2040 Regional Growth Strategy. Ultimate projections were calculated
as the PSRC 2040 projection plus 25 percent to be conservative.
Unlike the 2012 projections, no changes were made to the PSRC output with one exception.
Recent detailed projections for mini-basin 45, which were made as part of the Thunder Hills
Sanitary Sewer Interceptor Design Project, were incorporated into the 2040 demographic
projection. Mini-basin 45 multi-family populations were increased using a higher growth rate
similar to the adjacent mini-basin 3 PSRC estimates.
4.5.2 Employment
The total existing employment is 44,506 using 2012 basin population estimates. The total future
employment was projected to be 104,414 which is an increase of 59,908 employees over a period
of 28 years. This is approximately a 2,140 increase in employment annually. Major regions of
growth for future employment are mini-basins 27, 32, 43, 48, 50, and U9 with growth rates of
10,891 percent, 5,017 percent, 2,400 percent, 4,700 percent, 3,447 percent, and 31,300 percent,
respectively.
Where employment projections were not released for several TAZ due to confidentiality
requirements by the Employment Securities Department, alternate methods were used in these
areas, which are discussed further in this section. In addition, the school enrollments were
estimated to account for sewer use by students, as they are not captured in the PSRC
employment projections. Note, the TAZ projections meet or exceed the City’s adopted GMPC
population and employment targets for the City and PAA. Demographic projections are
summarized in Table 4.4 and discussed further in the following sections.
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-21
4.5.2.1 Existing - 2012
PSRC employment projections, also based on the Baseline Land Use model, were throughout
the Sewer Service Area. As previously mentioned, projections were not available for
six mini basins due to confidentiality requirements by the Employment Securities Department:
Basins 30C, 32, 50, 52, U3, and U8. Therefore, demographic projections for those mini-basins
were developed using 2011 Longitudinal Employer-Household Dynamics (LEHD) data,
developed by the U.S. Census Bureau. Through a review of available GIS data, no obvious
discrepancies were found in either the PSRC or LEHD data.
4.5.2.2 Future
PSRC 2040 employment are based on local growth targets that are aligned with the Vision 2040
Regional Growth Strategy. Mini-basin employment allocations were made using the PSRC,
except where no data was available. For these six basins, Stantec produced custom allocations,
which were reviewed and accepted by City Planning Department staff. Ultimate projections
were calculated as the PSRC 2040 projection plus 25 percent.
4.5.3 Schools
The City serves public elementary, middle, and high schools from the Issaquah and Renton
School Districts in additional private schools, Renton Technical College, and the University of
Phoenix campus. These schools are spread throughout Renton and can be found within each
service basin except for the May Valley Basin. There are two schools in Renton’s service area,
Maywood Middle School and the Briarwood Elementary School, that are not currently
connected to the public sewers. These are located in the East Cedar River Basin.
4.5.3.1 Existing - 2012
School enrollment projections were determined for schools within the existing sewer service
area using published data from the local school districts, including the Renton School District
and Issaquah Schools. Student populations were generally developed using enrollment statistics
for the 2011-2012 school year. School staffing were not included in enrollment, as staff are
considered in the PSRC employment projection.
4.5.3.2 Future
School enrollment projections for 2040 are not available from the PSRC or school districts.
Therefore, school population estimates were projected to grow at the same rate as the
residential population. As with other categories, the resulting projection was increased
by 25 percent to create the Ultimate projection.
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-23
Table 4.4 Demographic Projections (From Stantec 2015 Hydraulic Model Update Report)
2012 Basin Population Estimates Ultimate Population Estimates
(2040 Population+25%) Area (acres)
Sewer Mini
basin
Single-
Family
Multi-
Family Employment Schools
Single-
Family
Multi-
Family Employment Schools 2012 Ult % Diff
1 180 82 22 0 554 420 29 0 71.79 71.79 0.00%
2 81 1,303 342 1,041 209 1,608 713 1,367 127.50 134.72 5.67%
3 1,012 1,307 95 0 1,660 1,836 248 0 194.52 194.52 0.00%
4 1,094 49 22 466 2,109 121 160 909 205.17 205.17 0.00%
5 250 1,823 4,126 0 701 2,238 5,633 0 213.91 233.53 9.18%
6 1,513 10 25 0 2,173 14 165 0 224.34 224.34 0.00%
7 1,232 27 67 526 1,936 31 88 822 162.60 162.60 0.00%
8 0 0 2,248 0 0 0 5,310 0 82.14 82.14 0.00%
9 0 0 272 0 0 0 645 0 111.02 111.02 0.00%
10 173 121 537 0 201 65 1,011 0 54.44 54.44 0.00%
11 803 461 1,140 0 1,148 559 2,201 0 163.83 163.83 0.00%
12 23 1,492 458 0 34 1,803 883 0 73.57 73.57 0.00%
13 402 438 698 0 398 498 1,301 0 81.08 81.08 0.00%
14 1,041 401 504 298 1,795 483 1,088 471 205.98 205.98 0.00%
15 110 456 736 1,218 139 576 1,504 1,539 92.33 92.33 0.00%
16 1,077 380 241 0 1,534 481 583 0 177.15 177.15 0.00%
17 545 149 202 0 765 355 379 0 122.66 122.66 0.00%
18 350 209 148 0 408 280 279 0 38.85 38.85 0.00%
19 0 0 1,480 0 0 0 3,496 0 144.37 144.37 0.00%
20 2,390 490 261 0 5,943 549 973 0 309.45 620.56 100.53%
21 1,425 17 59 618 1,998 35 335 871 143.52 176.54 23.00%
22 1,065 1,433 599 1,956 1,690 1,905 2,049 2,815 208.76 208.76 0.00%
23 858 393 52 0 1,228 500 98 0 111.83 111.83 0.00%
24 1,258 136 63 0 1,839 179 109 0 130.46 130.46 0.00%
25 1,583 35 111 0 1,321 90 200 0 179.79 179.79 0.00%
26 2,189 1,440 818 525 3,270 2,228 1,800 795 382.54 382.54 0.00%
27 1,097 62 11 1,135 1,434 86 1,209 1,489 102.98 102.98 0.00%
28 0 0 5,365 0 0 0 12,673 0 180.04 180.04 0.00%
29 574 120 16 2,265 770 188 44 3,127 85.78 85.78 0.00%
30A 787 835 60 0 941 1,688 139 0 133.61 133.61 0.00%
30B 38 3 0 0 55 63 0 0 4.68 4.68 0.00%
30C 2 324 12 0 95 499 106 0 21.21 21.21 0.00%
32 321 281 105 0 368 328 5,373 0 141.77 141.77 0.00%
33 3,184 11 218 559 4,903 18 398 861 320.61 375.94 17.26%
34 721 227 43 0 1,223 279 75 0 127.92 127.92 0.00%
35 328 224 113 0 438 314 313 0 60.08 60.08 0.00%
36 40 1,376 397 0 41 1,634 854 0 117.20 117.20 0.00%
37 256 352 257 1,159 341 494 451 1,592 69.08 69.08 0.00%
38A 642 253 469 0 808 370 1,091 0 91.24 91.24 0.00%
38B 47 17 2 0 55 63 0 0 16.72 16.72 0.00%
39 508 515 127 0 640 690 329 0 86.04 86.04 0.00%
40 593 87 33 0 776 113 63 0 74.87 74.87 0.00%
41 1,063 94 61 0 1,319 133 116 0 117.31 117.31 0.00%
42 0 0 147 0 0 0 329 0 20.06 20.06 0.00%
43 549 624 7 0 611 1,085 175 0 116.45 116.45 0.00%
44 282 578 487 0 361 835 909 0 127.88 127.88 0.00%
45 20 1,157 2,733 0 133 2,390 5,165 0 158.81 158.81 0.00%
46 1,994 615 679 0 2,431 741 1,469 0 389.97 389.97 0.00%
46 (North) 67 665 21 0 106 1,055 36 0 23.84 23.84 0.00%
47 777 1,496 606 0 1,089 2,628 1,269 0 196.30 196.30 0.00%
48 462 168 6 545 609 243 288 737 60.26 60.26 0.00%
49 12 0 544 0 15 0 1,284 0 71.85 71.85 0.00%
CHAPTER 4 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 4-25
2012 Basin Population Estimates Ultimate Population Estimates
(2040 Population+25%) Area (acres)
Sewer Mini
basin
Single-
Family
Multi-
Family Employment Schools
Single-
Family
Multi-
Family Employment Schools 2012 Ult % Diff
50 4 174 30 0 5 210 1,064 0 162.61 162.61 0.00%
52 597 6 187 0 1,054 5 1,028 0 148.12 148.12 0.00%
54 139 1,066 883 0 446 1,680 1,668 0 252.50 252.50 0.00%
A 4 0 4,975 0 5 571 11,753 0 857.19 857.19 0.00%
B 0 0 2,580 0 85 0 6,046 0 323.32 323.32 0.00%
CEDAR02A 302 146 318 0 370 211 599 0 48.59 48.59 0.00%
ESI1003 237 620 7,126 0 255 1,108 14,185 0 403.86 403.86 0.00%
RENT65 561 526 189 0 1,115 811 569 0 178.09 178.09 0.00%
U1 255 8 7 0 1,004 8 16 0 75.48 75.48 0.00%
U2 1,054 56 23 0 2,014 61 51 0 139.04 139.04 0.00%
U3 1,064 63 59 0 1,743 88 303 0 141.67 141.67 0.00%
U4 2,927 10 251 612 4,649 30 614 975 471.97 471.97 0.00%
U5 NA NA NA NA 976 75 36 0 NA 112.94
U6 1,345 6 32 1,664 4,055 33 544 3,309 219.90 615.17 179.75%
U7 NA NA NA NA 1,685 9 96 0 NA 173.66
U8 294 0 3 0 496 0 26 0 43.01 43.01 0.00%
U9 68 0 1 905 1,824 0 314 1,305 12.21 212.66 1641.94%
U10 NA NA NA NA 2,335 178 64 0 NA 354.03
Total 43,869 25,417 44,506 15,492 76,731 37,869 104,414 22,984 10,407.68 12,070.34
Note:
Abbreviation: NA – not applicable.
LONG RANGE WASTEWATER MANAGEMENT PLAN| CITY OF RENTON
MARCH 2021 | 4-27
4.6 Sewer Collection System Flow Components
The City has separate sewer and stormwater collection systems, where only wastewater is
conveyed in the sanitary sewer system. However, some groundwater and stormwater inevitably
enter the sanitary sewer through defects in pipes and manholes (MHs) and illicit storm drain
connections. Therefore, sewer flows may vary substantially between dry and wet weather.
The different flow components are described in the section below.
4.6.1 Dry Weather Flow Components
There are two components of dry weather flow:
• Base wastewater flow (BWF)
• Dry weather groundwater infiltration (GWI)
4.6.1.1 Base Wastewater Flow
The BWF is the sanitary flow generated by routine water usage of the City’s residential,
commercial, and mixed-use customers. Conveying this flow is the primary function of the
collection system. The flow has a diurnal pattern that varies by customer. Typically, a residential
diurnal pattern has two peaks with the more pronounced peak following the wake-up hours of
the day, and a less pronounced peak occurring in the evening. Commercial and mixed-use
patterns, though they vary depending on the type of use, typically have more consistent higher
flow patterns during business hours, and lower flows at night. Furthermore, the diurnal flow
pattern of a weekend may vary from the diurnal flow experienced during a weekday.
4.6.1.2 Groundwater Infiltration
Dry weather GWI enters the sewer system through defects such as cracks, misaligned joints, MH
defects, and broken pipelines. Dry weather GWI only occurs when the relative depth of the
groundwater table is higher than the depth of the pipeline and where there is a defect; therefore
it varies throughout the system. Dry weather GWI (or base infiltration) cannot easily be
separated from BWF by flow measurement techniques. Therefore, dry weather GWI is typically
grouped with BWF.
4.6.1.3 Average Dry Weather Flow
ADWF is the average flow that occurs on a daily basis during the dry weather season and is
representative of routine wastewater discharges into the collection system from customers as
well as baseline groundwater infiltration.
4.6.2 Wet Weather Flow Components
Wet Weather Flow (WWF) includes two components:
• Infiltration and Inflow (I/I)
• Wet weather GWI
4.6.2.1 Inflow and Infiltration
The stormwater I/I response in the sewer system to rainfall is seen immediately (inflow) or within
hours after the storm (infiltration).
Inflow is stormwater that enters the sewer system via a direct connection to the system, such as
roof drain and downspout connections, leaky MH covers, and illicit storm drain
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-28 | MARCH 2021
cross-connections. Infiltration is stormwater that enters the sewer system by percolating
through the soil and then through defects in pipelines, MHs, and joints. The adverse effects of I/I
entering the sewer system is that it increases both the flow volume and peak flows such that the
sewer system could be operating at or above its capacity. If too much I/I enters the sewer system,
sanitary sewer overflows (SSOs) could occur.
4.6.2.2 Wet Weather Groundwater Infiltration
Wet weather GWI is not specific to a single rainfall event, but rather to the effects on the sewer
system over the entire wet weather season. The depth of the groundwater table rising above the
pipe invert elevation causes GWI. Sewer pipes within close proximity to a body of water can be
greatly influenced by groundwater effects.
Wet weather GWI is associated with extraneous water entering the sewer system through
defects in pipes and MHs while the ground is saturated during the wet weather season. Wet
weather GWI may occur throughout the year, although rates are typically higher in the late
winter and early spring in the Pacific Northwest.
4.6.2.3 Peak Wet Weather Flow
PWWF is the highest observed hourly flow that occurs following the selected design storm
event. PWWF in a sewer system can be more than ten times the base flow, causing utilities to
construct high-capacity infrastructure to convey and treat these flows.
4.7 Flow Monitoring
As part of the Scope of Services for this LRWWMP, Carollo Engineers, Inc. (Carollo) contracted
with ADS Environmental Services, LLC (ADS) to conduct a Temporary Flow Monitoring Program
within the City's sanitary sewer collection system. The purposes of the flow monitoring program
were to correlate actual collection system flows to the hydraulic model predicted flows, evaluate
the system's capacity, and estimate basin I/I. The temporary flow monitoring data was collected
for a period of approximately four months from December 22, 2017 to April 22, 2018. The "ADS
Flow Monitoring Report" prepared by ADS summarizes the flow monitoring program and was
submitted to the City as a stand-alone report. The report can be found as an attachment to
Appendix G, TM 1.
4.8 Average Dry Weather Flow
Developing an accurate estimate of the future quantity of wastewater generated at build-out of
the collection system is an important step in maintaining and sizing sewer system facilities, for
both existing conditions and future scenarios.
Base flow can be estimated for a wastewater system by comparing dry weather flow and wet
weather flow at the various flow monitoring locations. To estimate ADWF for more specific
areas, such as individual wastewater basins, dry weather flows are typically estimated based on
the area contributing to flows and flow coefficients developed for each land use type. This
method is developed based on the assumption that areas with similar land uses, such as low
density residential parcels, produce equivalent quantities of wastewater flow. System-wide flows
can be compared to known flows at flow monitors, or at the treatment plant to verify accuracy.
This method of estimating base flows is an industry standard for planning and provides
sufficiently accurate data for planning purposes.
LONG RANGE WASTEWATER MANAGEMENT PLAN| CITY OF RENTON
MARCH 2021 | 4-29
4.8.1 Average Dry Weather Flow Development
Existing ADWFs for each basin were estimated using data from the Flow Monitoring Program for
each of the flow monitoring basins. ADWF was developed using the driest days from the flow
monitoring period based on the following set of minimum criteria:
• Less than 0.1 in of rain in the previous day
• Less than 0.4 in of rain in the previous 3 days
• Less than 1.0 in of rain in the previous 5 days
• Selected days must exhibit average-day flows within 85 percent to 115 percent of the
average-day flows of remaining dry days
• In addition, those dry days that exhibited unusual flow patterns were not used to
generate net dry day flow values for a basin
Characteristic dry weather 24-hour diurnal flow patterns for each site were developed based on
the hourly data. The hourly flow data were also used to calibrate the hydraulic model for the
observed dry weather flows during the flow monitoring period. Hourly patterns for weekday and
weekend flows vary and were separated to better understand dry weather flow. An example of
the dry weather flow diurnal patterns is shown in Flow Monitoring Basin MH0537, in Figure 4.4.
Carollo estimated the average weekday and weekend dry weather levels and velocities at each
site from the data provided by ADS for use in the model calibration process.
Figure 4.4 Typical Weekday vs Weekend Dry Weather Flow Variation (MH0537)
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHour
Weekday Diurnal Pattern
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHour
Weekend Diurnal Pattern
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-30 | MARCH 2021
4.9 Wet Weather Flows
PWWF in a wastewater collection system are caused by rainfall dependent I/I. Peak hour flows
can result in flows more than ten times the base flow, causing utilities to construct high-capacity
infrastructure to convey and treat these extraneous flows.
Existing and projected PWWFs are predicted using the hydraulic model and design storm used
for this LRWWMP. This analysis uses four separate multi-day, 20-30 year recurrence design
storms, illustrated in Chapter 5 – System Analysis and Results. These storms were identified in
the 2012 KC I/I Study and correspond to the recurrence interval within historical KC rainfall. To
represent typical Pacific Northwest winter rainfall conditions, antecedent rainfall was added
from historical data. Further detail on the development of the design storm can be found in
Chapter 5 – System Analysis and Results.
4.9.1 Rainfall Data
An important part of the flow monitoring program is the collection and analysis of rainfall data.
Three significant rainfall events occurred during the course of the flow monitoring period, as well
as a few other relatively minor events. The storms recorded during the Temporary Flow
Monitoring Program did present data in terms of the collection system’s I/I response to wet
weather flow events, and is appropriate for I/I analysis and model calibration purposes.
4.9.2 Wet Weather Flow Data
The flow monitoring data was evaluated to determine how the collection system responds to
wet weather events. A summary of the peak wet weather flow mini basin during current and
buildout conditions is shown in Table 4.5.
4.10 Projected Flows
A summary of the modeled PWWF flows for each planning period is shown in Table 4.5. As
previously described, these flows were calculated using land use data for the study area and an
average wastewater conveyance required per capita. These flows were calculated by simulating
the February 1996 design storm, described in Chapter 5 – System Analysis and Results. Flows
consider both I/I change and system expansion.
Table 4.5 Design Event Projected Wet Weather Flow
Sewer Mini basin Current PWWF (mgd)(1) Buildout PWWF (mgd)(1)
1 0.57 0.77
2 2.25 2.97
3 0.67 0.87
4 10.15 12.14
5 3.51 4.53
6 1.20 1.44
7 4.16 5.57
8 0.69 1.53
9 2.96 3.51
10 0.38 0.47
11 2.49 3.53
LONG RANGE WASTEWATER MANAGEMENT PLAN| CITY OF RENTON
MARCH 2021 | 4-31
Sewer Mini basin Current PWWF (mgd)(1) Buildout PWWF (mgd)(1)
12 0.70 0.88
13 2.26 2.79
14 2.87 3.03
15 5.80 6.68
16 1.20 1.67
17 0.20 0.37
18 0.52 2.70
19 0.32 0.52
20 0.97 2.20
21 1.35 1.51
22 3.00 4.66
23 1.29 2.04
24 1.95 2.45
25 1.25 1.61
26 2.32 2.90
27 0.36 0.52
28 2.00 2.89
29 0.80 0.86
30A 4.35 6.40
30B 3.14 4.90
30C 1.76 2.33
32 2.45 3.33
33 0.96 1.60
34 0.21 0.29
35 3.14 4.88
36 0.65 0.80
37 0.77 0.97
38A 0.21 0.27
38B 3.14 4.90
39 1.54 1.97
40 0.54 0.69
41 1.34 1.48
42 0.09 0.14
43 0.22 0.36
44 2.37 3.15
45 6.26 8.23
46 17.04 27.21
46 (North) 0.33 0.46
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 4
4-32 | MARCH 2021
Sewer Mini basin Current PWWF (mgd)(1) Buildout PWWF (mgd)(1)
47 8.89 11.89
48 2.41 3.23
49 0.42 0.60
50 3.14 4.06
52 0.41 0.55
54 5.92 7.71
A 15.27 20.07
B 6.75 8.51
CEDAR02A 25.41 36.72
ESI1003 59.19 83.48
RENT65 11.13 13.70
U1 0.01 0.02
U2 0.13 0.25
U3 0.30 0.61
U4 0.28 0.91
U5 0.00 0.00
U6 0.28 0.91
U7 0.00 0.00
U8 1.01 2.65
U9 0.00 0.00
U10 0.00 0.00
Notes:
Abbreviation: mgd – million gallons per day.
(1) PWWF Modeling Results are from the respective design storm.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-1
Chapter 5
SYSTEM ANALYSIS AND RESULTS
5.1 Introduction
This chapter summarizes the conveyance analysis of all aspects of the existing system and their
recommended improvements. It includes a summary of system-wide concerns and the hydraulic
analysis performed using the updated Danish Hydraulic Institute (DHI) MikeUrban hydraulic
model. The results are summarized at the end of the chapter for each sewer mini-basin and
within the entire system (system-wide) in Table 5.10.
This chapter builds on Chapter 4 – Planning Considerations and summarizes the detailed
technical information provided in Technical Memorandum (TM) No. 2 - Model Development and
Calibration that can be found in Appendix H.
5.2 System-Wide Concerns
The sewer system has system-wide concerns that are common throughout its mini-basins. These
concerns, summarized below, impact both the City of Renton’s (City’s) operations and capital
planning.
5.2.1 King County-Interceptor Surcharging
During peak flows, King County (KC) will use its interceptors for storage of wastewater and for
controlling flows in the South Treatment Plant. This may result in surcharging of the KC
interceptors. KC reserves the right to surcharge its interceptors to an elevation of 25 feet (ft).
KC has never reached this extreme, to the City’s knowledge; however, the City has experienced
sewer surcharge problems in the low-lying areas. As a result of KC's surcharging, it is possible
that additional wastewater could overflow in low-lying areas through manhole covers and side
sewer connections.
KC, as part of their regional conveyance system needs report (Report), dated December 2017,
identified long-term capacity concerns within this Long-Range Wastewater Management
Plan’s (LRWWMP’s) planning period within portions of the east-side interceptor in the City. The
Report identifies capacity projects to alleviate the capacity concerns; however, these projects are
not in KC’s 6 year capital improvement plan.
The City has not designed facilities to accommodate a sewer surcharge to an elevation of 25 ft.
The City's current position is that KC is responsible for providing adequate capacity within its
interceptors and wastewater treatment facilities. In addition, the City considers KC to be
responsible for proper effluent disposal. During the preparation of the LRWWMP, no specific
analysis was made of the effect of KC’s surcharging on the City's sewer system. KC should
continue to study and identify areas of potential risk and alternatives to mitigate this problem. In
the past, KC has increased the influent and effluent capacity at South Plant and has installed
parallel interceptor facilities. This has significantly reduced the chance of surcharging but does
not eliminate the problem.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-2 | MARCH 2021
5.2.2 Adjacent Utility Systems
For purposes of this LRWWMP, all of the comprehensive plans for the adjacent utility systems
described in Chapter 4 – Planning Considerations were examined. The hydraulic analysis utilized
the projected Ultimate Peak 20-year design flows, as computed by KC. These flows were
obtained from KC and assigned as constant inflow conditions. This conservative assumption
contributed to surcharging and capacity issues in portions of the system.
The City has several agreements with adjacent utilities that allow joint use of facilities within the
City, as summarized in Chapter 4 – Planning Considerations. If capacity limitations become
evident, through visual inspection or flow measurements, then the City and the adjacent utility
should work together to correct the limitation as specified in the joint use agreement.
5.2.3 Hazard Mitigation Plan
The City partnered with KC Emergency Management to update the Regional Hazard Mitigation
Plan. The City developed a city-specific plan – Hazard Mitigation Plan (Renton Annex) – as part
of the regional effort. The Regional and city-specific Hazard Mitigation Plan seek to mitigate
long-term risk to people and property from the effect of both natural and man-made hazards.
The City is subject to a number of natural and man-made hazards that could affect the city, such
as earthquakes, flooding, landslides, winter/wind storms, coal mine hazards, hazardous
materials release, and terrorism/civil disturbance. The sanitary sewer system may be vulnerable
to a variety of the identified hazards.
5.2.4 Septic Systems
There are still a small percentage of developed properties within City Limits that are served by
private septic systems. In addition, the developed properties within the sewer service area but
outside of the city limits are primarily served by private septic systems. The Seattle-King County
Department of Public Health has an approved Septic Management Plan (King County On-Site
Septic System Management Plan – July 2007) and has started revised the document, however,
the latest draft has not yet been approved (King County On-Site Sewage System Management
Plan – September 2016). The latest Septic Management Plan identifies East Hill in
unincorporated KC and Renton, potentially served by Cedar River Water and Sewer District and
to a much lesser extent the City. This area was identified as challenging for the proper
functioning of OSS due to high density development with smaller lots, poor soils, older septic
systems, and high or perched water tables. The latest OSS Plan states “work is needed to
document the environmental and current status of systems to develop competitive grant
applications to seek funding for sewer extension projects.”
5.2.5 Wastewater Quality
The quality of wastewater transported in the City sanitary sewer system varies considerably
depending on the wastewater source, detention time within the sanitary sewer system and the
volume of infiltration and inflow (I/I).
The quality of domestic wastewater varies and is a direct result of the type of water used within
the home. Some domestic sewage can be considered stronger than others can. One household
appliance, the garbage disposal, can greatly impact the quality of wastewater. Most new home
construction incorporates garbage disposal in its design. Use of these garbage disposals
increases both suspended solids and the biochemical oxygen demand (BOD), two common
results tested for when measuring contaminant concentrations.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-3
The total volume of industrial waste produced within the City is small compared with the volume
of domestic wastewater. However, an industrial or commercial development can have a
considerable impact on the sanitary sewer collection system immediately downstream of the
facility. Industrial waste can contain high concentrations of chemicals that can make the waste
highly corrosive or toxic. If discharge of an industrial waste to the sanitary sewer system creates
problems, then pretreatment of the industrial waste should be considered. Several federal, state,
and local regulations govern the pretreatment of industrial waste.
Several industries within the City have obtained National Pollution Discharge Elimination
Systems (NPDES) permits. The most recent list of industrial discharges is provided in Table 5.2.
The KC Industrial Waste Program is a state delegated authority to implement the Federal
Pretreatment Program and handles the industrial waste for the City. This program administers
the waste discharge permits, inspections, enforcements, compliance and collection of surcharge
monitoring fees. The program also works with businesses to help them implement pollution
prevention practices. The industrial dischargers submit monthly self-monitoring reports to the
KC Industrial Waste Program to confirm compliance with their NPDES permits. Additionally, KC
conducts twice yearly monitoring of the discharges.
Table 5.1 Renton Summary of Active Industrial Waste Permits
Industrial Discharger Industry Type
Alliance Packaging LLC CORRUGATED CONTAINER
Allpak Container Corporation CORRUGATED CONTAINER
Barbee Mill Company, Inc. GROUNDWATER REMEDIATION - METALS
Boeing Commercial Airplane - Renton METAL FINISHING - CFR 433
Boeing Electronics Center METAL FINISHING - CFR 433
Buchan Bros. VEHICLE WASHING
Cintas Corporation LAUNDRY-INDUSTRIAL
E&E Foods FOOD PROCESSING-FISH
Hartung Glass Industries - Flat Glass Products GLASS MANUFACTURING
Kenworth Truck Co. MANUFACTURING-MISC
King County RSD - Renton Decant Facility DECANT STATION
King County SWD - Renton Transfer Station SOLID WASTE - TRANSFER FAC
Northwest Gourmet Food Products Inc. -
Renton Facility FOOD PROCESSING-OTHER
Ocean Beauty Seafoods LLC - Renton FOOD PROCESSING-SEAFOOD
Phillips 66 Company - Renton Terminal GROUNDWATER REMEDIATION - ORGANICS
Phillips 66 Company - Renton Terminal GROUNDWATER REMEDIATION - ORGANICS
Renton Coil Spring Co. Inc. MANUFACTURING-MISC
Republic Services - Monster Road SW GENERAL TYPE
Schwartz Brothers Bakery - Renton FOOD PROCESSING-BAKERY
Service Linen Supply LAUNDRY - LINEN
Sheets Unlimited LLC CORRUGATED CONTAINER
Stoneway Concrete - Black River CEMENT/READYMIX
Stoneway Concrete - Houser Way CEMENT/READYMIX
Sweet Ambrosia LLC CANNABIS
Trojan Lithograph PRINTING
Valley Medical Center HOSPITAL
Note:
Abbreviations: RSD - Road Services Division; SWD - Solid Waste Division.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-4 | MARCH 2021
5.2.6 Wastewater Quality Analysis and Recommendations
A major problem associated with wastewater quality is the generation of hydrogen sulfide that
occurs during wastewater transport from its source to the point of treatment. The hydrogen
sulfide found in wastewater results from the anaerobic bacterial reduction of the sulfate ions
that are present. Hydrogen sulfide poses three serious problems: it is highly corrosive, has an
obnoxious odor, and, as a gas, is toxic to humans and has been known to cause death to sewer
maintenance workers. The production of hydrogen sulfide is directly related to the BOD of the
wastewater. Wastewater exhibiting a high BOD will tend to generate more hydrogen sulfide
than wastewater exhibiting a lower BOD.
Hydrogen sulfide is very corrosive to both sewers and pumping facilities. Hydrogen sulfide
released from the wastewater will tend to dissolve on condensation within the crown of a
sanitary sewer. The hydrogen sulfide retained in the condensation is converted to sulfuric acid
through oxidation by aerobic bacteria. This sulfuric acid will react with the cement bonding
material within concrete pipes, or iron within steel pipes, and can corrode a pipe to the point of
structural failure. Sanitary sewer pipes are most susceptible to this type of corrosion in their
crowns because that is where most condensation occurs.
Aeration, periodic cleaning, and use of non-corrosive pipe materials can control effects of
hydrogen sulfide. If excessive hydrogen sulfide production is evident at a lift station, aeration of
the wet well should be considered to reduce the hydrogen sulfide in the wastewater and reduce
the effects of anaerobic bacteria that produce the hydrogen sulfide. Periodic cleaning of the
sanitary sewers will also remove the biological slime that forms on the pipe walls and produces
the hydrogen sulfide. The most effective method of mitigating corrosion by hydrogen sulfide is
through the use of non-corrosive pipe materials, such as polyvinyl chloride (PVC), or high-density
polyethylene (HDPE). Existing pipes experiencing severe corrosion can be rehabilitated through
the use of various slip form liners or fiberglass resin liners.
In order to control the generation of hydrogen sulfide, the City conducts preventative
maintenance with routine cleaning sewer pipes with inadequate slopes. In addition, all pipes are
cleaned before video inspection is performed. Both of these tasks reduce biological growth on
the walls of the sewer pipes and reduce the hydrogen sulfide generation potential.
Excessive I/I will tend to reduce the production of hydrogen sulfide and the concentration of
contaminants in the wastewater. As the City works to reduce structural defects causing I/I, there
may be more impact by contaminants and hydrogen sulfide. The City may have to increase
efforts to reduce hydrogen sulfide and be more aware of potential contaminants.
The planning area for this LRWWMP corresponds, for the most part, with the current City limits
and urban growth boundary (UGB), as shown in Figure 4.1. Service is provided consistent with
regional planning and agreements with adjacent utilities. System-wide concerns present in the
wastewater infrastructure include some segments approaching the end of the Remaining Useful
Life and infiltration and inflow.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-5
5.2.7 Aging Sanitary Sewers
Sanitary sewer system installation began in earnest during the 1940’s and 1950’s as a federal
program to provide housing for workers at the Renton Boeing Plant and has continued through
today. Prior to this boom, the City also had significant sewer installations in the 1920s and 1930s
for the Central Business District. Some of these sewers have reached the end of their useful life.
This LRWWMP recommends a program to address condition issues of these aging sanitary
sewers through rehabilitation and replacement.
5.2.8 Infiltration and Inflow
I/I occur in all sanitary sewer systems. Infiltration is defined as water entering the sanitary sewer
system through pipes, joint connections, manhole (MH) covers, and walls. Inflow is defined as
water discharged to the sanitary sewer system through connections to roof drains, yard drains,
foundation drains, and cross connections with storm sewers and combined sewers. The
combination of I/I may be a major portion of the total wastewater flow which must be carried by
the sanitary sewer system. I/I problems in an existing sanitary sewer system can be studied to
determine their effect. Finding and correcting I/I sources can be challenging, as determining the
source can be evasive.
Elimination of storm inflow from the system is difficult due to conflicting concerns. Sealing MH
lids and maintaining the water tightness of the lids decreases inflow, but gas, particularly
hydrogen sulfide and methane, can collect in the sealed MHs. The City attempts to minimize
vent holes for the system, but inflow cannot be prevented completely. During the design and
construction of new main extensions, the City utilizes MH liners and coatings as well as sealed
MH covers in wet areas. The City also performs video inspections during the wet season on all
new gravity sewers to check for leaks.
5.2.8.1 Historical Infiltration and Inflow
In December 1999, as part of the Regional Wastewater Services Plan (RWSP), the KC Council
approved the development of a Regional I/I Control Program. The purpose of the program is
to reduce the risk of sanitary sewer overflows (SSOs) and the cost of adding capacity to facilities
that convey wastewater to KC treatment plants. KC installed over 800 flow meters to measure
flows throughout KC. The flow meters monitor depth of flow and velocity. Early flow monitoring
data between late 2000 and early 2001 were considered unrepresentative because of drought
conditions that lowered the groundwater table and therefore reduced I/I to the system.
Consequently, KC performed additional flow monitoring from late 2001 to early 2002. This effort
proved more productive as data from several storms was captured. Rainfall in the region was
also monitored by KC. The Calcul de lames d’eau a l’aide du radar system (CALAMAR) used a
combination of 73 rain gauges throughout the region, as well as the National Weather Service
radar, to generate rainfall quantities to an accuracy of plus or minus 10 percent.
In 2000, KC’s Wastewater Treatment Division, in cooperation with the local component agencies
that it serves, launched an I/I Program. Ten pilot projects were selected to evaluate the
effectiveness of various sewer rehabilitation technologies in reducing I/I in local agency
collection systems. The completion of the ten pilot projects in January 2004 marked a major
milestone in the KC study. The projects demonstrated that I/I could be effectively reduced,
depending on the location and method of rehabilitation. The results of the pilot projects, along
with other information, were used to prepare a long-term regional plan for reducing I/I in local
agency systems.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-6 | MARCH 2021
5.2.8.2 Current Infiltration and Inflow
Old and aging sewers contribute to excessive I/I into the sanitary sewer system. In conjunction
with KC’s program for reducing I/I, the City identified, through model analysis, areas of concern
for investigation, additional metering, and replacement or rehabilitation of the sewers. There are
certain portions of the sanitary sewer system that are known as having I/I in excess of the
1,500 gallons per acre per day (GPAD) identified as the acceptable amount as determined
through the joint planning effort between KC and the component agencies. The City works to
reduce the I/I in these portions of the system through its mainline and lateral replacement
program. If these systems are replaced, I/I will be reduced and KC’s requirements will be met. If a
system is not scheduled for replacement or a replacement is delayed, the City may have to
perform interim rehabilitation to reduce I/I if required for capacity needs.
The City is participating with KC on its program to gain knowledge and experience to determine
methods for I/I abatement. The additional data produced through the current effort occurring
will be used by the City in determining feasibility of using I/I improvements in lieu of upsizing
sewer systems where capacity restraints have been identified.
The modeled values of I/I are shown for every mini-basin in Figure 5.5. The sewer model has also
identified portions of the sewer system that have I/I or capacity problems during large storms
that may not be evident with physical signs during smaller storms. To better understand these
areas, the City will initiate I/I Metering, Investigation, and Rehabilitation and Replacement, as
needed.
5.2.9 Other Concerns
Additionally, combined sewers are designed to carry both stormwater and wastewater within a
single system. Current codes in the City do not allow combined sewers because it causes
stormwater, which is relatively clean, to be treated along with wastewater. Combined sewer
systems within the City have been replaced with separate sanitary and storm sewer systems.
5.3 Hydraulic Model
Wastewater collection system models are valuable tools used to assess the performance of
collection systems during dry and wet weather conditions and to plan for future improvements.
These models provide a means to simulate the impact of different storm sizes on the collection
system, and determine where future system deficiencies are likely to occur. In addition, a
well-calibrated model provides a method for testing alternative improvement scenarios. The
flow monitoring wastewater basins used in the model for calibration is shown in Figure 5.1.
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
g`
g`
g`
g`
g`
g`
g`
g`
g`
g`g`
g`
g`g`
g`g`
g`
g`East Valley RdRain
ier
Ave
N
S 133rd St
Oakesdale Ave SWBenson
D
r
S
SW 7th St
140th Ave SENE Sunset
B
lvd
§¨¦405
Maple
V
a
l
l
e
y
H
w
y 164th Ave SECedar River Trail
SE Jones Rd
Lake Youngs Service RdSE May Valley Rd
Union Ave NESE Petrovitsky Rd
§¨¦5
Shy CreekLiftstation
Devils ElbowLift Station
East ValleyLift Station
Talbot CrestLift Station
Long LiftStation
KensingtonCrest Lift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash.Flush Lift Station
Stone GateLift Station
Falcon RidgeLift Station
Liberty LiftStation
Lake WashingtonBeach LiftStation Pipers BluffLift Station
Baxter LiftStation
Misty CoveLift Station
Airport LiftStation
MH6704
MH0166
MH0286
MH0537
MH6041
MH1360
MH1763
MH2116
MH2171
MH2252
MH5302
MH2999
MH5519
MH3216
MH3625
MH5505
MH4628
MH4646
Last Revised: July 15, 2020\\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Flow_Monitoring_Basins.mxd
O
0 10.5 Miles
Legend
g`Flow Monitoring Locations
Flow Monitoring Basins
Lift Station
3Ú City of Renton
3Ú King County
Gravity Pipeline
Force Main
MAINTBY
City of Renton Force Main
King County Force Main
King County Gravity Main
Study Area
Renton City Boundary
Roads
Waterbodies
Figure 5.1Flow Monitoring Locations
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Disclaimer: Features shown in this figure are for planning purposes andrepresent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-9
5.3.1 Model Development and Calibration
A sewer collection system model is a simplified representation of the real sewer system.
Sewer system models can assess the conveyance capacity for a collection system. In addition,
sewer system models can perform “what if” scenarios to assess the impacts of future
developments and land use changes. The model was developed using the Mike Urban hydraulic
modeling software package, developed by DHI. The hydraulic model is a full pipe model and
includes 100 percent of the total system pipelines.
For this project, flow monitoring was conducted at 18 meter sites for a period of approximately
five months from December 2017 to April 2018. Flow monitoring data was used to calibrate the
updated hydraulic model for both dry and wet weather conditions. Dry weather flow (DWF)
calibration ensures an accurate depiction of base wastewater flow generated within the study
area. The wet weather flow (WWF) calibration process consists of calibrating the hydraulic model
to specific storm events to accurately simulate the peak and volume of I/I into the sewer system.
The hydraulic model was calibrated following the Chartered Institution of Water and
Environmental Management (CIWEM) code of practice. The updated hydraulic model is shown in
Figure 5.2.
5.3.2 Model Evaluation Results
The hydraulic model is well calibrated; simulating WWF storms accurately. A summary of dry
and wet weather flow model calibration is provided in Table 5.2. The percent difference in
volume is shown for each of the three storms that were used for calibration. The CIWEM
standards require the model to meet the calibration standards for two out of the three WWF
storms. The model is within calibration criteria for every site for DWF and for 16 of the 18 sites
for WWF. Calibration standards were not met for Site MH3216 and MH6041. Site MH3216
showed greater response in the model than in the meter; therefore the model is conservative.
Site MH6041 flow monitoring showed very little flow response to Storms 2 and 3, which made it
difficult to match across the season and be within typical parameters for the sewer system. For
this reason, the calibration focused on matching Storm 1. These sites are discussed in further
detail in TM 2: Model Update and Calibration, located in Appendix H of this LRWWMP. Appendix
H also discusses the level calibration and shows example calibration figures.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-10 | MARCH 2021
Table 5.2 Model Calibration
Flow Meter
ID
DWF Percent
Difference (%)
WWF Storm 1
Volume Flow
Percent
Difference (%)
WWF Storm 1
Peak Flow
Percent
Difference (%)
WWF Storm 2
Volume Flow
Percent
Difference (%)
WWF Storm 2
Peak Flow
Percent
Difference (%)
WWF Storm 3
Volume Flow
Percent
Difference (%)
WWF Storm 3
Peak Flow
Percent
Difference (%)
MH0166 -0.2% 31.1% -1.5% -3.0% 11.9% 15.4% -0.9%
MH0286 1.0% 7.2% -1.8% 0.1% -11.9% -7.8% -25.8%
MH0537 -0.7% 10.1% 2.0% 5.2% -6.6% 17.2% 13.3%
MH1360 5.0% 18.1% 9.7% -12.8% 7.2% 15.1% 2.5%
MH1763 -1.1% 13.0% 13.7% -38.9% -15.0% -0.3% -5.0%
MH2116 -8.1% - - -9.5% -12.6% 3.7% 7.3%
MH2171 -0.4% 6.8% 10.9% -6.7% 7.7% 17.3% 19.5%
MH2252 -0.8% -2.5% -5.8% -9.4% 12.2% 8.1% 58.3%
MH2999 -7.2% 11.0% -10.9% 11.3% 1.8% 16.8% 7.0%
MH3216 -0.4% 18.8% -4.4% -11.3% 25.2% 13.5% 47.8%
MH3625 -2.5% 4.7% 5.0% -14.7% -6.1% -1.7% -8.5%
MH4628 0.0% 10.4% 3.5% -21.2% 15.0% 10.9% -1.6%
MH4646 0.0% -1.9% -6.6% -18.3% -19.7% -2.2% 1.9%
MH5302 -8.6% -4.3% -8.7% -7.9% 6.7% -1.6% 0.8%
MH5505 0.4% 6.6% -1.9% -9.5% 6.3% -2.2% -14.7%
MH5519 3.7% 12.2% 33.1% 10.9% 24.0% 9.8% 1.3%
MH6041 -0.1% -14.5% -8.9% 16.5% 19.7% 39.3% 140.3%
MH6704 -0.2% -8.4% -19.1% 16.7% 21.8% 15.2% 3.0%
Note:
Abbreviation: ID – identification.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-11
Figure 5.2 Updated Hydraulic Model
5.4 Capacity Evaluation
Capacity problems are the result of inadequate pipe sizes or slopes, or backwater conditions.
These problems may concern lack of capacity in the sewer system or available capacity for future
development. A hydraulic analysis has been performed on the City‘s sewer system. This analysis
did not show capacity problems in the current system. Capacity problems do occur throughout
the system in various degrees at build-out.
As the City implements more water conservation programs, there may be a negative impact on
the operation of a sewer system. Reduction of the liquid component of wastewater could cause
problems in moving solids through the lines. Problems moving solids could impact the operation
of the system, increase the potential of SSOs and will increase the need for flushing. This section
describes the capacity evaluation performed as part of this LRWWMP. Deficiencies were
identified per the analysis criteria and presented in the following sections.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-12 | MARCH 2021
5.4.1 Analysis Criteria
Capacity evaluation of the wastewater collection system was performed in accordance with the
following criteria, using the hydraulic model developed for this LRWWMP:
• 20-year and 30-year, multi-day design storms are used for evaluating the City’s sewer
infrastructure. Essentially, these design storm have a three to five percent
chance (1/30 - 1/20) that a peak of 3.7 inches of rain will fall in any 24-hour period in a
given year
• It was assumed that system degradation is considered for this analysis. I /I degradation is
estimated at seven percent per decade, and 28 percent for buildout. This assumption is
based on KC’s Updated Planning Assumptions for Wastewater Flow Forecasting (2014)
• During Peak Wet Weather Flow (PWWF), water levels were allowed to rise no more than
three feet from the MH rim. Sewers were allowed to surcharge under these maximum
flow conditions during the design storms presented above. Additionally, pipes that
surcharged to a ratio of depth/diameter > 2 were flagged as well in the hydraulic model
results
• No surcharging was allowed for shallow MHs (shallow MHs consist of locations where
the difference between the MH rim and top of pipe was less than 3.5 ft)
• Areas that were identified as a deficiency based on the analysis criteria but were caused
by KC backwatering conditions are not included in the results presented in this section.
The City is unable to fix issues pertaining to KC’s interceptor backwater condition.
Additional information and figures showing the heightened hydraulic grade line (HGL)
due to KC Interceptors are shown in Appendix H, in this LRWWMP
• Modeled Lift Station influent is larger than firm capacity of lift station for the design
storm
5.4.2 Design Storm
This analysis uses four separate multi-day, 20-30 year recurrence design storms for the capacity
evaluation. These storms were identified in the 2012 KC I/I Study and correspond to the
recurrence interval within historical KC rainfall. There are five of these historical rain gauges
which are used in different areas of the system. Figure 5.3 shows each of the four design storms.
Table 5.3 outlines which design storm was used for the capacity analysis in each mini-basin.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-13
Figure 5.3 Design Storm Hydrographs
Table 5.3 Modeled Design Storms by Mini-Basins
Sewer Mini basin Design Storm
1 Nov-98
2 Nov-98
3 Nov-98
4 Jan-90
5 Nov-90
6 Nov-90
7 Nov-98
8 Feb-96
9 Feb-96
10 Feb-96
11 Feb-96
12 Feb-96
13 Feb-96
14 Feb-96
15 Feb-96
16 Feb-96
17 Nov-90
18 Feb-96
19 Feb-96
Sewer Mini basin Design Storm
20 Nov-90
21 Nov-90
22 Nov-90
23 Jan-90
24 Feb-96
25 Nov-90
26 Nov-90
27 Feb-96
28 Feb-96
29 Feb-96
30A Feb-96
30B Feb-96
30C Feb-96
32 Feb-96
33 Feb-96
34 Jan-90
35 Jan-90
36 Feb-96
37 Feb-96
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 20 40 60 80 100 120Rainfall (in/hr)Hours
Design Storms
Nov-98
Jan-90
Nov-90
Feb-96
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-14 | MARCH 2021
Sewer Mini basin Design Storm
38A Feb-96
38B Feb-96
39 Feb-96
40 Feb-96
41 Feb-96
42 Feb-96
43 Jan-90
44 Nov-90
45 Nov-90
46 Nov-98
46 (North) Nov-90
47 Nov-90
48 Nov-90
49 Feb-96
50 Feb-96
52 Feb-96
Sewer Mini basin Design Storm
54 Feb-96
A Feb-96
B Feb-96
CEDAR02A Nov-90
ESI1003 Feb-96
RENT65 Jan-90
U1 Feb-96
U2 Feb-96
U3 Feb-96
U4 Feb-96
U5 Feb-96
U6 Feb-96
U7 Feb-96
U8 Feb-96
U9 Feb-96
U10 Feb-96
5.4.3 Capacity Evaluation Results
A capacity analysis of the modeled collection system was performed with the City's calibrated
hydraulic model using the system performance criteria outlined above. The I/I degradation
assumption created a conservative scenario for projecting future system conditions. Capacity
analysis was performed for existing conditions (2012) and build-out conditions (2040) for Lift
Stations and the collection system.
5.4.4 Lift Station Capacity
The hydraulic model includes representations of all of the City’s major lift stations. The model
simulates the existing lift station pumps and, when required, allowing and tracking flow beyond
the existing capacity. The peak hourly flow during the design storm upstream of modeled lift
station was used to determine whether stations met the firm capacity of the station. Firm
capacity is defined as the capacity of the pump station with one pump offline. It is recommended
the City investigate lift station capacity as a separate project in the future.
The lift stations were evaluated for sufficient capacity under peak wet weather flow under
current and buildout conditions. Table 5.4 shows the lift station capacity, modeled flows, and
deficiencies. The City has two lift stations that are deficient:
• Airport
• Lind Avenue
At buildout, it is anticipated that the firm capacity of three additional stations will be deficient:
• Kingston
• Stonegate
• Baxter
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-15
These additional buildout deficiencies are due large anticipated increase in flow from new
development. The deficiencies at Lift Stations with current deficiencies are also anticipated to
grow worse with additional development. However, every lift station has sufficient total capacity
to convey both current and buildout total pump capacities, except buildout flows to the Airport
Lift Station. The City is currently working on upgrading the Airport lift station, which will address
the capacity issue.
Falcon Ridge accepts flows from Soos Creek Water and Sewer District, which may be a source of
model inaccuracy. It is recommended the City work with Soos Creek Water and Sewer District to
better understand both Utilities contributions to the Falcon Ridge Lift Station.
The City should further investigate flows at the Lind Avenue Lift Station to confirm station
performance in wet weather flows. The City has not historically observed capacity issues at this
station; therefore, it is anticipated the deficiency may only be in very large storms similar to
the 25- to 30-year design storm.
The City should continue to evaluate potential developments contributing to Kingston,
Stonegate, and Baxter lift stations. The City should make necessary lift station improvements
prior to granting a utility permit that exceeds its capacity.
5.4.5 Collection System Capacity
The capacity analysis identified areas in the sewer system where flow restrictions may occur or
where the pipe does not have sufficient capacity to convey design flows. Sewers that lack
sufficient capacity to convey design flows could produce backwater effects in the collection
system that increase the risk of SSOs. Potential system deficiencies were identified for PWWF
under both existing and build-out conditions and are highlighted in Figures 5.4 and 5.5,
respectively. Under buildout condition, twenty-two areas were considered potentially deficient
based on design storms and evaluation criteria. These locations and associated information are
presented in Table 5.5. Additional information on the deficiencies and proposed improvements
can be found in Chapter 8 – Capital Improvement Program.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-16 | MARCH 2021
Table 5.4 Lift Station Evaluation
Pump Station
Number Pump Station Name Storm Used
Pump Firm
Capacity
(gpm)
Total Pump
Capacity
(gpm)
Current
Modeled
PWWF (gpm)
Buildout
Modeled
PWWF (gpm)
Current
Modeled
Deficiency
(gpm)
Buildout
Modeled
Deficiency
(gpm)
L01 Shy Creek Feb 96 825 1375 18 180 807 7645
L02 Devil’s Elbow Jan-90 500 1000 119 237 381 263
L03 Airport Feb-96 100 200 174 216 -74 -116
L04 East Valley Feb-96 724 1086 492 548 232 176
L05 Talbot Crest Nov-90 110 220 35 35 75 75
L07 Long Nov-90 100 200 69 69 31 31
L08 Kensington Jan-90 160 320 56 182 104 -22
L09 Wedgewood Feb 96 905 1416 150 237 755 668
L25 Lind Avenue Feb-96 500 1000 542 630 -42 -130
L29 Stone Gate Nov-90 425 850 244 593 181 -168
L30 Falcon Ridge Jan-90 100 200 142 154 -42 -54
L32 Misty Cove Feb-96 190 397 125 160 65 30
L34 Liberty Feb 96 617 1234 1 184 616 433
L39 Baxter Feb-96 700 1150 548 817 152 -117
Note:
Abbreviation: gpm – gallons per minute.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-17
Table 5.5 Buildout Deficiency Locations
Deficiency
ID(1)
Upstream
MH
Downstream MH Mini
Basin
Storm
Event
Pipe
Sections
Length and
Diameter
Highest
Surcharged
MH
Description
of
Surcharge
Reason
Deficient
05A MH3043 RE*SRENT.R18-19 5 Nov-90 22 5,005' - 8" MH2998 Flooding Capacity
45A MH2252 MH4031 & MH
2672
45 Nov-98 30 2,242' - 8" & 246' - 10" &
526 - 12" & 636' - 15" &
4,670' - 18"
MH2257 Flooding Capacity
7A MH2276 SSMH009 7 Nov-98 8 2,082 - 8" MH2272 10.7 ft
from rim
Capacity
2A MH2681 &
MH2678
MH2676 2 Nov-98 4 987' - 8" MH2677 1.6 ft
from rim
Capacity
3A MH2369 MH2336 3 Nov-98 16 3,930 - 8" MH2337 8.5 ft
from rim
Capacity
46A MH4640 &
MH1854
RE*CEDAR1.R10-
05A
46 Nov-90 20 584' - 8" & 358' - 10" &
1,191' - 12" & 549' - 15" &
660' - 21" & 760' - 24"
MH4692 Flooding Capacity,
diameters
change
37A MH6042 &
MH0840
MH0825 37 Feb-96 15 2,989' & 8" MH0839 5.1 ft
from rim
Negative slopes
48A MH0887 MH0845 48 Feb-96 8 1,262 - 8" & 441 - 12" MH0847 17.2 ft from
rim
Capacity, grade
change
24A MH0927 MH0761 24 Feb-96 3 409' - 8" & 233' - 10" MH0924 0.8 ft
from rim
Negative slopes
20B MH6612 MH6613 20 Nov-90 1 282' - 8" MH6612 12.1 ft
from rim
Capacity,
shallow slope
20A MH5238 MH3726 20 Nov-90 11 1,253' - 8" MH5240 5.4 ft
from rim
Capacity,
shallow slope
22A MH3064 MH5504 22 Nov-90 26 2,732' - 8" & 463' - 10" &
1276' -12" & 1,067' - 15"
MH3615 0.5 ft
from rim
Capacity,
diameters
change
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-18 | MARCH 2021
Deficiency
ID(1)
Upstream
MH
Downstream MH Mini
Basin
Storm
Event
Pipe
Sections
Length and
Diameter
Highest
Surcharged
MH
Description
of
Surcharge
Reason
Deficient
21A MH4301 MH3625 21 Nov-90 47 9,778' - 8" MH3581 Flooding Capacity,
shallow slope
41A MH0925 MH0761 41 Feb-96 15 2,230 - 8"& 358' - 10" MH3329 Flooding Capacity,
shallow slope
23A MH3499 MH3497 23 Jan-90 2 700' - 8" MH3498 13.2 ft
from rim
Capacity
15A MH2469 2790 15 Feb-96 55 153' - 6" & 4,461' - 8" &
764' - 10" & 3,204' - 12"
& 2,284' - 15" & 272' - 18"
& 144' - 24"
MH2183 Flooding Capacity
14A MH5443 MH6332 14 Feb-96 6 1050' - 8" MH6337 8.7 ft
from rim
Capacity
BA MH2981 MH5188 B Feb-96 6 1,353' - 8" & 387' - 10" L04-East
Valley
9.5 ft
from rim
Capacity
05B MH3306 RE*SRENTON.R1
8-17
5 Nov-90 25 366' - 8" & 901' - 10" MH5531 4.8 ft
from rim
Capacity
05C MH3304 MH5523 5 Nov-90 21 3,462' - 8" MH3205 10.2 ft
from rim
Capacity
11A MH6825 MH5049 11 Feb-96 2 607' - 10" MH5050 10.1 ft
from rim
Negative slopes
25A MH1708 MH1660 25 Nov-90 25 3,326 - 8" MH1694 6.9 ft
from rim
Capacity,
shallow slope
Note:
(1) Deficiency ID based on associated mini basin number.
O
0 10.5
Miles
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: Fill in the name of
the data sources used in this map
including aerial imagery.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Legend
3 feet from rim
Flooding
King County
Force Mains
d/D Ratio
0 - 1
1 - 2
2 +
U Basin
Nov 1998 Storm
Nov 1990 Storm
Jan 1990 Storm
Feb 1996 Storm
Roads
Figure 5.4
Current Deficiencies
05A
45A
15A
37A
21A
22A24A
23A
48A
20A
20B
46A
14A
3A7A2A
BA
11A
41A
O
0 10.5
Miles
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: Fill in the name of
the data sources used in this map
including aerial imagery.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Legend
3 feet from rim
Flooding
King County
Force Mains
d/D Ratio
0 - 1
1 - 2
2 +
U Basin
Nov 1998 Storm
Nov 1990 Storm
Jan 1990 Storm
Feb 1996 Storm
Roads
Figure 5.5
Buildout Deficiencies
05A
45A
15A
37A
21A
22A24A
23A
48A
20A
20B
46A
14A
3A7A2A
BA
05B
25A
05C
11A
41A
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-21
5.5 Recommendations
This section describes recommendations for each of the deficiency areas identified in Table 5.5.
Deficiencies can be caused by a combination of local physical flow constraints and excessive
upstream flow from I/I. The design storms identified for system planning have return intervals
of 20-30 years, therefore, the City may not observe surcharging during normal WWF. Appendix D
shows the hydraulic grade lines at each deficiency. These are used to help identify possible
physical flow constraints in the vicinity of the deficiency, which includes negative slopes,
undersized pipes, and downstream backwater conditions. Therefore, a systematic approach was
taken to confirm and address capacity issues, as shown in in the flow chart shown in Figure 5.6
and outlined below:
• Piping reconfiguration: Identified the deficient pipe segment has a negative (reverse)
slope. It is recommended to replace these sections of pipe to create a positive slope, if
possible, to address both capacity and potential maintenance concerns
• I/I Evaluation: Considered if excess upstream flow from I/I was a major factor in the
deficiency. A criteria of 7,500 GPAD of I/I was used to delineate excess I/I areas.
7,500 GPAD represents the cutoff for the highest 10 percent of basins, ensuring the
worst I/I basins are prioritized. For these areas, an I/I evaluation, followed by
rehabilitation and replacement of structural deficiencies, is recommended to address
the deficiency
• Programmatic upsizing: If there is a clear undersized pipe segment without excess I/I in
the upstream mini-basin, then it is recommended the City upsize the pipe segments
causing the deficiency. These segments were relatively short
• Long-term flow monitoring: Long-term flow monitoring is recommended for the
remaining deficiencies to better understand the issues in order to identify the most
cost-effective improvements
All identified deficiencies and recommendations are detailed below in Table 5.6. Figure 5.8
shows the system wide improvement recommendations by deficiency.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-22 | MARCH 2021
Figure 5.6 Recommendation Decision Flow Chart
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-23
Table 5.6 Deficiency Recommendations
Deficiency
ID
Pipe Configuration
Constraint I/I (GPAD)
Downstream
Undersized Flow
Constraint
Recommendation
05A None 1,320 Unclear Long-term Flow
Monitoring
45A None 11,000 None I/I Evaluation
7A None 11,000 None I/I Evaluation
2A None 11,000 None I/I Evaluation
3A None 11,000 None I/I Evaluation
46A None 2,750 Unclear Long-term Flow
Monitoring
37A Negative slopes 1,910 None Piping
Reconfiguration
48A None 1,030 Unclear Long-term Flow
Monitoring
24A Negative slopes 1,035 None Piping
Reconfiguration
20B Negative slopes 1,230 Clear Constraint Programmatic
Upsizing
20A Negative slopes 1,230 Clear Constraint Programmatic
Upsizing
22A None 1,230 Unclear Long-term Flow
Monitoring
21A None 2,290 Unclear Long-term Flow
Monitoring
41A None 4,708 None Long-term Flow
Monitoring
23A None 480 Clear Constraint Programmatic
Upsizing
15A None 5,625 Unclear Long-term Flow
Monitoring
14A None 5,625 Unclear Long-term Flow
Monitoring
BA None 175 Clear Constraint Programmatic
Upsizing
05B None 9,570 None I/I Evaluation
05C None 2,450 None I/I Evaluation
11A Negative slopes 4,545 None Piping
Reconfiguration
25A None 1,310 None I/I Evaluation
5.5.1 Piping Reconfiguration
Pipeline reconfiguration was recommended for areas in the system that presented negative
slopes causing a capacity deficiency in the collection system. The negative slope also increases
the risk of solids accumulation in the pipe and other maintenance issues. The first action would
be to confirm the geographic information system (GIS) information and confirm that the
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-24 | MARCH 2021
modeled negative slopes and inverts are accurate. In the event where these are accurate, and
where physically possible, potential pipe replacement may be recommended to create a
positively sloped pipe.
Of the 22 deficiencies, five are at negative pipe slope segments. The location and inverts to
reconfigure are outlined in Table 5.7. Preliminary design evaluation of each location is
recommended to identify site specific constraints that may limit changes to slope. This may
require replacing pipe lengths upstream and/or downstream of the deficiency to achieve a
positive slope.
Table 5.7 Piping Reconfiguration Locations
Deficiency ID Location Invert ID Invert Elevation
37A Edmonds Avenue and
NE 9th Street MH0738 273.66
24A Monroe Avenue and
NE 7th Street MH0761 360.25
11A Grant Avenue and
SE 9th Street
MH5049, MH5050,
MH5052, MH5053 Unknown
20A SE 99th Court MH3726 321.86
20B Jericho Place and
NE 16th Street MH6616 453.85
5.5.2 I/I Evaluation
An I/I evaluation, followed by rehabilitation and replacement of structural deficiencies, is
recommended for deficiency in mini-basins with excessive I/I (defined as 7,500 GPAD). The
evaluation should incorporate micro-monitoring to focus rehabilitation and replacement
activities on areas with the greatest I/I. Micro-monitoring consists of installing multiple flow
monitors for a relatively short period of time in mini-basins to identify areas with relatively high
I/I. Flow meters are often moved to identify smaller and smaller areas with higher I/I. This allows
rehabilitation and repair activities to be focused on specific areas, rather than an entire
mini-basin.
Mini-basin I/I rates in GPAD is shown in Figure 5.7. Of the 22 deficiencies, seven occur in
mini-basins with high I/I (greater than 7500 GPAD). A total of seven upstream mini-basins
contribute to the deficiencies, as shown in Table 5.8, where mini-basins 2, 3, and 7 contribute to
multiple current system deficiencies. Deficiencies 05C and 25A became deficient during buildout
conditions. The upstream demographics of these areas were unchanged in buildout conditions,
so the deficiency is attributed to I/I despite I/I rates lower than 7500 GPAD.
Table 5.8 Micro-Monitoring Recommendations for I/I
Deficiency ID Manhole Location Upstream Mini-Basins with High I/I
45A MH2258 45, 7, 3, 2, 1
7A MH2480 7
2A MH2489 2
3A SSMH004 3
05B MH5516 5
05C MH5516 5
25A MH1696 25 & U3
O
0 10.5
Miles
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: Fill in the name of
the data sources used in this map
including aerial imagery.
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Legend
3 feet from rim
Flooding
King County
Force Mains
d/D Ratio
0 - 1
1 - 2
2 +
I/I (GPAD)
0 - 500
500-2,000
2,000-3,750
3,750 - 7,500
Greater than 7,500
Roads
Figure 5.7
Modeled I/I Overlaid with Deficiencies
g`
g`
g`
g`
g`
g`
g`g`
g`East Valley RdRainier Ave NS 133rd St
Oakesdale Ave SWBe
n
s
o
n
D
r
S
SW 7th St
140th Ave SEN E S u n set Blvd
§¨¦405
Maple
V
a
l
l
e
y
H
w
y 164th Ave SECedar River Trail
SE Jones Rd
Lake Youngs Service RdSE May Valley Rd
Union Ave NESE Petrovitsky Rd
5A & 5B: Mini-Basin 5
41A
14A
25A: Mini-Basin U3
2A: Mini-Basin 2
15A
48A
05A
21A
21A
22A22A
45A: Mini-Basin 1
25A: Mini-Basin 25
7A: Mini-Basin7
45A: Mini-Basin 45
3A: Mini-Basin3
46A
23A
BA
24A 20B37A20A
1
1
ALast Revised: September 18, 2019 \\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Fig5.6.mxd
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 5.8 Deficiency Improvement Recommendations
O
0 10.5 Miles
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton
Legend
g`Flow and Monitoring Program
Sewer Upsizing Projects
Pipe Reconfiguration Projects
I/I Evaluation Program
City Limits
Street Centerlines
CHAPTER 5 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 5-29
5.5.3 Programmatic Upsizing
For sites where modeling indicated that capacity issues were caused by short and undersized
stretches, upsizing was recommended. Programmatic upsizing was typically recommended for
areas without significant surcharging and where modeling allowed identification of a defined
segment responsible for the deficiency. These locations are described in additional detail in
Table 5.9, which shows the location, pipe, and pipe diameter.
Deficiencies 23A, BA, and 46A also all correspond to areas with high condition risk; therefore,
upsizing could be completed in conjunction with pipe rehabilitation and replacement program
activities.
Table 5.9 Programmatic Upsizing Location and Additional Information
Deficiency
ID Location Pipe ID’s
Current
Pipe
Diameter
Proposed
Pipe
Diameter
Upsizing
Length
(ft)
Comments
23A N 28th Place and
Park Avenue N
GM03987,
GM03986,
GM03985
8”
12”
12”
16” Reconfiguration at
MH3498 if possible
BA SE 24th Street and
E Valley Road
GM05178,
GM05179 8” 12”
Backwater from
Pump Station
influences
hydraulics
46A Sunset Boulevard N
and NE 3rd Street GM04391 8”
12”
12”
16”
Significant stretch
of pipe that is
deficient, but
change in
diameter appears
to be hydraulic
restriction
5.5.4 Additional Long-Term Flow Monitoring
Additional long-term flow monitoring was recommended for the remaining deficiencies. Of the
twenty-two deficient locations, five are recommended to undergo additional long-term flow
monitoring. The City reviewed these deficiencies and confirmed that they have not observed
capacity issues at these location in the field. Therefore, long-term flow monitoring is
recommended to determine the extent and possible causes of the deficiency. The recommended
quantity, type, duration, location, and priority of the monitoring is provided in Table 5.10.
The recommended duration is chosen based on the recurrence of the deficiency given the
surcharging seen in the model calibration events (6 months to 1 year storms) and design
storms (20 to 30 year storms). Based on the HGL under different storms, 2-5 years of monitoring
is recommended for Deficiency 05A; 1-2 years for deficiency 22A; 3-7 years for deficiency 14A,
15A, and 21A, 48A, and 41A.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 5
5-30 | MARCH 2021
Table 5.10 Long-Term Flow Monitoring Recommendations
Deficiency
ID Location Quantity Duration Manhole ID
05A Talbot Road S and
36th Street to 27th Place 1 2- 5 years MH2998
22A Whitman Court NE and
NE 12th Street 2 1-2 years MH3616,
MH3622
21A
Anacortes Avenue NE and
NE 17th Street to
NE 26th Street
2 3-7 years MH3542,
MH3581
15A Renton High School 1 3-7 years MH2118
14A West Sunset Blvd and
SW 4th Place 1 3-7 years MH6332
41A Lake Washington Boulevard
and Burnett Avenue N 1 3-7 years MH3381
48A NE 7th Street and
Harington Avenue NE 1 3-7 years MH0847
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-1
Chapter 6
REPLACEMENT AND REHABILITATION
PROGRAM
6.1 Introduction
This chapter documents the City of Renton's (City's) prioritized collection system replacement
and rehabilitation (R&R) program. R&R prioritization is based on a risk, which is based on the
criticality and vulnerability of an asset. Criticality represents the consequence of failure, and the
vulnerability represents the likelihood of failure. A consistent approach is used to identify and
prioritize force mains (FMs), lift stations, and gravity mains as documented in the following
sections.
6.2 Replacement and Rehabilitation Plan Goals
The City is implementing a risk-based R&R program that takes into account the criticality and
vulnerability of their system. Using this approach, the City can proactively replace or rehabilitate
infrastructure to reduce the System’s risk.
6.2.1 Prioritizing Using Risk
The risk associated with an asset (pipe, manhole [MH], pump, etc.) is a measure of the impact of
asset failure on the overall system. Risk is calculated as the product of criticality and
vulnerability, or:
Risk = Criticality x Vulnerability
Risk criteria were developed from the Halcrow Risk and Remaining Life Planning Tools (Weber
Davis Aqueduct, March 2011) and refined to meet the City’s objectives and available data
sources. Data sources and levels were chosen that represented the selected criteria, were readily
available, and that could be applied consistently across the entire system. Table 6.1 shows the
matrix of the normalized risk rankings that were used for this study.
Table 6.1 Normalized Risk Ratings
Normalized Risk Ranking Vulnerability Level 4 (severe) Moderately Low Moderately
High High High
3 (moderate) Moderately Low Moderately
High
Moderately
High High
2 (low) Low Moderately
Low
Moderately
High
Moderately
High
1 (negligible) Low Low Moderately
Low
Moderately
Low
1 (negligible) 2 (low) 3 (moderate) 4 (severe)
Criticality Level
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-2 | MARCH 2021
6.3 Lift Station and Force Main Current R&R Program
The Wastewater Utility operates 20 sewage lift stations in which each has its own FM that
delivers the flow to the gravity system (Fig.6.1). Since the 2010 Long-Range Wastewater
Management Plan (LRWWMP), six lift stations have been decommissioned and two lift stations
added. Over the past 25-years, the City has replaced, rehabilitated, or eliminated all previous
25 lift stations. However, their FMs often times were not. In 2016 the City conducted a risk
assessment of the Lift Stations and FMs. Based on this study, the City had developed and is near
completion on the lift station and FM R&R project that has systematically addressed or
mitigated potential risks to its existing infrastructure. Over the 20 year planning period, it is
anticipated that continued R&R will be needed and prioritized by the highest risk.
6.4 Force Main R&R
The City completed a preliminary condition assessment of its FMs in the 2016 Existing Force Main
Condition Assessment and Lift Station Evaluation Report (Carollo Engineers, Inc. [Carollo], 2016).
The 2016 project included developing an updated inventory of the lift stations and FMs,
performing a preliminary risk assessment of the FMs to identify those having the highest risk of
failure, field verifying the preliminary risk rankings, and preparing routine evaluation and
maintenance guidelines. This section summarizes the preliminary condition and risk assessment.
FM R&R recommendations are presented based on the 2016 project and improvements being
made as part of the Rehabilitation Program.
6.4.1 Force Main Criteria
A preliminary “desktop” risk assessment was performed for the City’s sewer FMs. Criticality and
vulnerability criteria used to establish risk are summarized below in Sections 6.4.1.1 and 6.4.1.2.
The criticality, vulnerability, and risk ratings for each FM were quantified on a relative risk scale,
with one representing the lowest risk and four representing the highest risk.
6.4.1.1 Force Main Criticality
Criticality describes the consequence of failure of a particular asset. Criticality factors used in the
desktop risk assessment for the FMs are:
• Cost to repair, which includes FM material, diameter, length, and excavation and backfill
costs
• Potential for life-threatening injuries or fatalities from FM break. Injuries or fatalities can
be of a pedestrian, a household, or a vehicle
• Ability to maintain flow using bypass pumps or a Vactor Truck
• Loss of critical infrastructure and transportation links. For example, a FM located
underneath a major highway is given a higher impact rating compared to one located in
a low-use road
• Emergency construction access constraints, such as FMs located in backyards, in a
wetland, or on a steep slope
• Damage to nearby property, based on the number of properties damaged from FM
leakage
• Environmental impact to waterways, wetlands, or other sensitive areas. A FM located
near an environmentally sensitive area is given a higher rating than one located further
away
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-3
6.4.1.2 Force Main Vulnerability
The vulnerability metric reflects the likelihood of asset failure. Physical or performance failure
and technological obsolescence qualify as asset failure; however, the desktop risk assessment
considered physical failure only asset mortality. Factors used to assess the physical vulnerability
of the FMs are:
• Material type. Cast iron (CI) and ductile iron (DI) pipes generally have a shorter useful life
compared to polyvinyl chloride (PVC) and high-density polyethylene (HDPE) FMs, and
thus have a higher vulnerability rating.
• Age. As the FM ages, its remaining useful life (RUL) decreases and becomes more likely
to fail
• History of failure. FMs having a history of frequent failures are more likely to fail again.
• Maintenance history. If routine maintenance is required to prevent FM failure, the FM is
considered to be in poor condition and is more likely to fail
• Pipe conditions based on closed-circuit television (CCTV) records
• Soil corrosivity based on soil classification from the United States Soil Conservation
Map. Electronic conductive soils such as peat, clay, and silt are more corrosive than
non-conductive soils such as sand and gravel for CI and DI FMs
• Cathodic protection for CI and DI FMs
• Potential of third-party damage from nearby construction or utility failures
No CCTV or cathodic protection data was available for the analysis. Accordingly, these factors
were excluded from the analysis, but should be included in the future if available.
6.4.2 Force Main Risk Assessment
A criticality and vulnerability level were assigned for each FM based on the available data and
input from City staff. Once levels were assigned for all criteria, a weighted average was used to
determine the overall rating. Normalized ratings were determined by allocating the weighted
average of criticality and vulnerability into quartiles. The results of the desktop risk assessment
are shown in Table 6.2.
6.4.3 Force Main Recommendations
The recommendations of the system inventory and risk assessment of the City’s sewer FMs were
incorporated into the Lift Station and FM Rehabilitation Program, summarized in Table 6.2,
including:
• It is recommended that the City conduct CCTV inspection of FMs after FM cleanouts are
installed as part of the Lift Station and FM Rehabilitation
• It is recommended that the City monitor the condition of the stream banks adjacent to
the Devil’s Elbow lift station and evaluate alternatives to armor the banks to protect the
lift station and FM
• It is recommended the City continue regular maintenance and its active rehabilitation
program for FMs
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-4 | MARCH 2021
Table 6.2 Force Main Risk Assessment Summary
Lift Station
Name
Force Main
Diameter (inches)
Force Main
Length
Normalized Risk
Ranking
Baxter 8" 155 LF High
Devil's Elbow 6" 506 LF High
Lake WA No. 2 6" 192 LF High
Falcon Ridge 4" 3,217 LF Moderately-High
Kensington Crest 4" 1,350 LF Moderately-High
Lake WA Beach 4" 337 LF Moderately-High
Lake WA Flush 4" 18LF Moderately-High
Long 4" 783 LF Moderately-High
Misty Cove 4" 175 LF Moderately-High
Wedgewood 8" 1,019 LF Moderately-High
Airport 4" 530 LF Moderately-Low
Cottonwood 4" 52 LF Moderately-Low
East Valley 8" 120 LF Moderately-Low
Stonegate 8" 4,944 LF Moderately-Low
Talbot Crest 4" 520 LF Moderately-Low
Westview 3" 340 LF Moderately-Low
Liberty 8" 900 LF Low
Lind Avenue 8" 180 LF Low
Pipers Bluff 4" 1,017 LF Low
Shy Creek 1'' 226 LF Low
Note:
Abbreviations: LF – linear feet; WA - Washington.
6.5 Lift Station R&R
Lift stations criticality and vulnerability are commonly assessed by individual components, such
as pump, wet well, electrical system, etc. Each component may be rehabilitated as it reaches its
usable life, rather than replacing the entire pump station. Regular maintenance conducted by
the City helps extend the useful life; however, the infrastructure will eventually reach the end of
its useful life and require rehabilitation or replacement.
6.5.1 Lift Station Criteria
Similar to the FM criteria, a risk assessment was performed for the City's 20 lift stations.
Vulnerability was established based on the RUL of the lift stations. Initial RUL was determined
based on the age of the facility. The initial RUL was then adjusted based on the past condition
assessments and the ongoing FM and Lift Station Rehabilitation Program. Lift station criticality
was based on the FM criticality.
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-5
6.5.1.1 Lift Station Criticality
The same criticality factors that influence FM impacts the lift station associated with it.
Therefore, the FM criticality factors were applied to the lift stations, as presented in Table 6.2.
6.5.1.2 Lift Station Vulnerability
The City's lift stations were assessed a vulnerability, or likelihood of failure, score based on RUL.
Since several lift stations have been rehabilitated in the past, RUL was calculated for both
structural integrity of the lift station and the components within the lift station, which include
mechanical and electrical coatings, roofing, etc. The structural usable life for a lift station was
selected as 75 years. The usable life for the components of a lift station was selected as 25 years,
which is consistent with the City’s capital improvement program (CIP) planning.
6.5.2 Lift Station Criticality Assessment
Lift Station criticality scores mirrored their FMs, as presented previously and detailed in
Table 6.3.
6.5.3 Lift Station Vulnerability Assessment
Vulnerability scores were calculated based on RUL. RUL was calculated using the construction or
renovation date of each lift station for structural and components within the lift station, which
are presented in Table 6.3. RUL was adjusted based on prior condition assessments and the FM
and Lift Station Rehabilitation Program:
• Lake WA No. 2 and Lake WA Flush Stations were assigned a Components RUL
of 0 to 5 years based on the findings of the Lake Line Project condition assessment
• Devil’s Elbow and Talbot Components RUL was adjusted upwards to 6 to 10 years based
on the FM and Lift Station Rehabilitation Program
• Cottonwood Lift Station was considered to be fully renovated as part of the
Rehabilitation Program
The RUL of each lift station was based on component RUL, as it was less than the structural RUL
in all cases.
The vulnerability levels for Lift Stations were determined from the RUL as follows:
• Level 1 (Negligible): RUL greater than 15 years
• Level 2 (Low): RUL between 11 and 15 years
• Level 3 (Moderate): RUL between 6 and 10 years
• Level 4 (Severe): RUL of 5 years and less
The results of the vulnerability scores for each lift station are found in Table 6.3.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-6 | MARCH 2021
Table 6.3 Lift Station Risk Assessment Summary
Lift Station
Name
Criticality
Score
Construction
Date
Renovation
Date
Structural RUL
(yrs)
Components RUL
(yrs)
Vulnerability
Score
Vulnerability
Designation
Risk Score
Baxter 3 2008 66 16 1 negligible (1,3)
Devil's Elbow 3 2000 58 6 to 10(1) 3 moderate (3,3)
Lake WA No. 2 4 1972 1994 30 0 to 5(2) 4 severe (4,4)
Falcon Ridge 1 1981 2019 37 24 1 negligible (1,1)
Kensington Crest 3 2002 60 10 3 moderate (3,3)
Lake WA Beach 2 2011 69 19 1 negligible (1,2)
Lake WA Flush 4 1972 2005 30 0 to 5(2) 4 low (4,4)
Long 3 2006 64 14 2 low (2,3)
Misty Cove 4 2014 72 22 1 negligible (1,4)
Wedgewood 3 2006 64 14 2 low (2,3)
Airport 4 2014 72 22 1 negligible (1,4)
Cottonwood 2 1994 2018(3) 53 26 1 negligible (1,2)
East Valley 1 2004 62 12 2 low (2,1)
Stonegate 3 2012 70 20 1 negligible (1,3)
Talbot Crest 2 2000 58 6 to 10(1) 3 moderate (3,2)
Westview 1 1996 2010 54 18 1 negligible (1,1)
Liberty 2 2012 70 20 1 negligible (1,2)
Lind Avenue 1 1978 2014 36 22 1 negligible (1,1)
Pipers Bluff 2 ? 3 moderate (3,2)
Shy Creek 1 2007 65 15 2 low (2,1)
Notes:
Abbreviation: yrs – years.
(1) Devil’s Elbow and Talbot RUL as adjusted upwards to 6 to 10 years based on the FM and Lift Station Rehabilitation Program.
(2) Lake WA No. 2 and Lake WA Flush Stations were assigned a RUL of 0 to 5 years based on the findings of the Lake Line Project condition assessment.
(3) Cottonwood Lift Station was considered to be fully renovated as part of the Rehabilitation Program.
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-7
6.5.4 Lift Station Risk Assessment
The risk score was calculated applying the same method as the FM risk assessment. A matrix of
the normalized risk rankings for the lift stations is shown in Table 6.4. Two lift stations which are
part of the Lake Line were categorized at the highest risk level. Five lift stations were
categorized in the moderately-high risk level including Devil’s Elbow, Kensington Crest,
Talbot Crest, Long, and Wedgewood. The remaining thirteen lift stations are categorized as low
to moderately-low risk level.
Table 6.4 Risk Matrix for Lift Stations
Normalized Risk Ranking Vulnerability Level 4
(severe) Lake WA No. 2
Lake WA Flush
3
(moderate) Talbot Crest Devil’s Elbow
Kensington Crest
2
(low)
East Valley
Shy Creek Long
Wedgewood
1
(negligible)
Falcon
Lind Avenue
Westview
Liberty
Lake WA Beach
Cottonwood
Pipers Bluff
Baxter
Stonegate
Airport
Misty Cove
1
(negligible)
2
(low)
3
(moderate)
4
(severe)
Criticality Level
6.5.5 Risk Based Lift Station Recommendations
The City's lift stations are well maintained and it is recommended the City continue regular
maintenance and rehabilitation to address aging equipment. The operation of lift stations with
moderate and severe criticality should be monitored closely, as the potential impacts from
failures at these stations are relatively higher than other stations. In addition to regular
maintenance, the City plans for a full rehabilitation of lift stations every 15 to 20 years to limit
vulnerability.
6.5.6 Rehabilitation Improvements
The Lift Station and FM Rehabilitation Project paired the 2016 risk findings with a detailed
condition assessment to generate comprehensive rehabilitation improvements to address
condition issues and enhance operations and maintenance (O&M). The improvements, shown in
Table 6.5, provides enhancements to aid in future O&M of the lift stations and FMs:
• FM cleanouts to allow access for inspection and rehabilitation
• Backup power (engine generator [E/G] install), where needed
• Telemetry Improvements, where needed
• Added Flow Meters, where needed
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-8 | MARCH 2021
Common rehabilitation items include wet well repair or recoating and structural improvements.
The Cottonwood and Baxter lift stations also will receive new pumps. The rehabilitation is
anticipated to provide approximately 15 years of useful life in all lift stations. Falcon Ridge was
not included in the Rehabilitation Project, so improvements are not included in Table 6.5.
The Lake WA No. 2 Lift Station and the Lake WA Flush Station, which serve the Kennydale
Lake Line Sewer System (Lake Line), are not included in the Rehabilitation Program. The Lake
Line evaluation provided a comprehensive analysis that addressed the City’s short- and
long-term issues concerning the system. Kennydale Lake Line Sewer System Evaluation
Technical Memorandum (TM) 1: Phase 1 Existing Conditions (Carollo, 2017) documents the
condition assessment of the stations and identified rehabilitation improvements for the lift and
flush stations. The City is waiting to implement these improvements until the long-term
approach for O&M of the Lake Line is determined in 2020-2021 through the completion of the
Kennydale Lake Line Sewer System Improvements Project, which may change the sizing and
extent of improvements needed.
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú
[Ú [Ú
[Ú
Piper's BluffLift Station
Shy CreekLift Station
Devil's ElbowLift Station
Airport LiftStation
East ValleyLift Station
Talbot CrestLift Station
Long LiftStation
Kensington CrestLift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash. FlushLift Station Stone GateLift Station
Falcon RidgeLift Station
MistyCove LiftStation
LibertyLiftStation
Lake WashingtonBeach LiftStation
Baxter Lift Station
%&e
Aè
Aæ
AÅ
Aç
Aè
%&e
Aí
Last Revised: July 15, 2020F:\KRCD DRIVE\Renton\LRRWRP_Figures\Fig_06_01LiftStations.mxd
Long-range Wastewater Management Plan | City of Renton
O
0 10.5 Miles
Legend
[Ú Lift Station
Renton City Boundary
Street Centerlines
Highway
Freeway
Street Centerline
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 6.1
City of Renton Lift Stations
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-11
Table 6.5 Lift Station and Force Main Rehabilitation Program
Group 1 Pump Replacement Motor Control Replacement Telemetry Improvements Add Flow Meter E/G Install Noise Abatement Slope Stabilization Wet Well Structural Assess Coatings Wet Well Recoat Temp Wet Well System/Pump FM Cleanouts FM Maintenance Equip. Evaluation FM Reconfiguration FM Replacement MH or Vault Improvements Structural E/G Pad or Vault Control Room Structural Misc. Structural (Telem.) Environmental/Agency Elements No. Lift Station Name
1 Cottonwood X X X X X X X X
2 Devil’s Elbow X X X X X X
3 East Valley X X X X X X
4 Misty Cove X X
5 Piper’s Bluff X X X X
6 Shy Creek X X X X X X X
7 Baxter X X X X
8 Stonegate X X X
9 Airport and Lind X
Group 2
10 Liberty X X X X
11 Wedgewood X X
12 Lake WA Beach X X X X X X
13 Talbot Crest X X X X X X X X X
14 Long X X X X X X
16 Westview X X X X X
17 Kensington Crest X X X X X X
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-12 | MARCH 2021
6.6 Gravity Sewer System R&R
A risk-based prioritization of gravity sewer mains was developed in 2016 and documented in
CCTV Program Phase 2 project's TM No. 4: Risk Findings, which is provided in Appendix I. This
section summarizes the findings that include criticality and vulnerability analysis, the RUL
analysis, a risk-based evaluation, and a recommended R&R program for the system's gravity
mains.
6.6.1 Gravity Sewer Main Criteria
Similar to the City's FM analysis, a risk assessment was performed for the City's gravity mains.
Criticality and vulnerability criteria were used to establish the assets risk of failure and are
summarized below.
6.6.1.1 Criticality
Once the criteria and data sources were found, each pipe segment was assigned a score-based
criteria rating found in Tables 6.6 and 6.7. The levels varied from negligible criticality or
vulnerability (Level 1) to severe (Level 4). The levels are represented numerically as 1 to 4.
Weighted factors, as discussed above, were applied to reflect the City’s priorities.
As discussed above, criticality represents the consequence of failure of a particular asset.
Table 6.6 shows the criteria, weighting, and description of each level for criticality of gravity
sewer mains. These criteria and data sources reflect an iterative refinement process that
reflected the City’s typical key decision factors and the perceived accuracy of the data. Criteria
were scored on four levels based on analysis of available geographic information system (GIS)
information that best represented each criterion. Where the decision factors or available data
did not support four levels of scoring, two levels of scoring were typically used. For example, the
criticality criterion for environmental impacts receives a level of 3 when within 50 feet (ft) from a
critical area and a level of 1 at greater distances. Given the high level of the critical area data, the
City was not comfortable in differentiating the criteria further without a site-specific
investigation (wetland delineation, geotechnical analysis, etc.). These site-specific analyses are
generally conducted as part of the design of the R&R program and could not be reasonably
completed City wide.
The weighting factor for each criterion in Table 6.6 was discussed with City staff and used to
identify certain criteria that would impact the system more than other criteria. For criticality, it
was agreed that the loss of critical infrastructure and transportation links should have a
weighting factor of 2, while the other criteria were kept at a factor of 1. The scoring of these
criteria was adjusted with respect to the weighting factor.
A total score was calculated for each criteria for all gravity collection pipes in the system. For
example, if a pipe segment was located in an arterial street, its Loss of Critical Infrastructure and
Transportation Links criteria was scored as Level 3, or moderate, rating. Multiplying the level of
three by a weight of two on Table 6.6, the final weighed level for that criteria would be 3 x 2 = 6.
The same calculation would be made for the remaining criteria and summed for an overall
criticality score. The same process was repeated for the vulnerability criteria.
6.6.1.2 Vulnerability
The likelihood of failure is known as the asset's vulnerability. Table 6.7 shows the criteria that
were used to determine the vulnerability of each asset. Similar to the criticality criteria in
Table 6.6, the criteria, weighting, and description of each level were used as a decision factor to
find the vulnerability of the asset.
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-13
Table 6.6 Criticality Criteria
Criteria Weighting Level 1 Level 2 Level 3 Level 4
Cost to Repair Failure 1 Small Repair Effort by City
Crew
Pipe Diameter: ≤ 12" AND
Pipe Depth: < 12 ft
Large Repair Effort by
City Crew
Pipe Diameter: > 12" AND
Pipe Depth: < 12 ft
Small Repair Effort by
Contractor
Pipe Diameter: ≤ 12" AND
Pipe Depth: ≥ 12 ft
Large Repair Effort by
Contractor
Pipe Diameter: > 12" AND
Pipe Depth: ≥ 12 ft
Loss of Critical
Infrastructure and
Transportation Links
2 Negligible
No Site of Interest OR
Non-arterials
Low
No Site of Interest OR
Collector Street
Moderate
Site of Interest OR
Arterial Street
Severe
Critical Infrastructure OR
Freeways
Damage to Property 1 Negligible
Distance to Building
Footprint: > 10 ft
Moderate
Distance to Building
Footprint: ≤ 10 ft
Environmental
Impacts to waterway,
wetland, or other
Sensitive Area
1 Negligible
Distance from Critical
Area: > 50 ft
Moderate
Distance to Critical
Area: < 50 ft
Loss of Service to
Customers
1 Negligible
Collection Line
Moderate
Trunk Line
Reputational Damage 1 Negligible
Outside Wellfield Capture
Zone OR
Distance to Critical Water
Body > 200 ft
Low
Within 5 year Wellfield
Capture Zone OR
2. Distance to Critical
Water Body > 100 ft and
≤ 200 ft
Moderate
Within 1 year Wellfield
Capture Zone OR
2. Distance to Critical
Water Body > 50 ft and
≤ 100 ft
Severe
Distance to Critical Water
Body < 50 ft OR
2. Distance from well
≤ 500 ft
Damage to Local
Business and
Economy
1 Negligible
Pipeline outside of
Overlay District
Moderate
Pipeline within Overlay
District
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-14 | MARCH 2021
Table 6.7 Vulnerability Criteria
Criteria Weighting Level 1(1) Level 2 Level 3 Level 4
Structural
Condition, CCTV
Inspection Results
1 Negligible
Pipe not yet inspected:
material is PVC or DIP
Structural NASSCO
Score: ≤ 2
Low
Pipe not yet inspected: all
other materials
Structural NASSCO
Score: > 2 and ≤ 3
Moderate
Structural NASSCO
Score: > 3 and ≤ 4
Severe
Structural NASSCO
Score: > 4
O&M Condition,
CCTV Inspection
Results
1 Negligible
Pipe not yet inspected:
material is PVC or DIP
O&M NASSCO Score: ≤ 2
Low
Pipe not yet inspected: all
other materials
O&M NASSCO Score: > 2
and ≤ 3
Moderate
O&M NASSCO Score > 3
and ≤ 4
Severe
O&M NASSCO Score: > 4
RUL Estimate 1 Negligible
RUL > 20 years
Low
RUL between 10 and
20 years
Moderate
RUL between 5 and
10 years
Severe
Less than 5 years RUL
Frequency of
Preventative
Maintenance
1 Negligible
No Cleaning
Low
Annual OR Biannual
Cleaning
Moderate
Monthly or Quarterly
Cleaning
Severe
Biweekly or Weekly
Cleaning
Slope of Pipe
Segment
1 Negligible
Slope > 0.5%
Low
Slope ≤ 0.5%
Moderate
Severe
Note:
Abbreviations: DIP – ductile iron pipe; NASSCO – National Association of Sewer Service Companies.
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-15
6.6.2 Gravity Sewer Criticality Assessment
Once the criteria and data sources were found, each pipe segment was assigned a score-based
criteria rating found in Tables 6.8 and 6.9.
The amount of pipe found in each criticality level was calculated and is shown in Table 6.8.
Figure 6.2 shows the map of the City's total criticality score results using the guidelines from
Table 6.1. To aid in review, a consistent color scheme is applied to the levels and scores in all
mapping, with light green showing the Level 1, or negligible pipes, dark green showing the
Level 2, or low criticality piping, orange representing the Level 3, or moderately critical piping,
and red showing the Level 4, or severe criticality piping.
Severe criticality mains make up 12.9 percent of the gravity collection system and are largely
located along major roadways or in the Valley. The majority (61.5 percent) of piping in the Valley
is either severe or moderate criticality. Low and negligible criticality piping is distributed
throughout the system and accounts for the remaining 25.7 percent.
Table 6.8 Criticality Score Range
Criticality Level Length (ft) Percent of Total
1 (negligible) 333,777 25.7%
2 (low) 352,977 27.1%
3 (moderate) 447,195 34.4%
4 (severe) 167,286 12.9%
6.6.3 Gravity Sewer Vulnerability Assessment
Using the criteria in Section 6.4.1.2, the length of pipe allocated to each vulnerability level was
calculated and is shown in Table 6.9. Figure 6.3 shows a map of the four vulnerability criteria
results. About three quarters of the City’s gravity mains have negligible or low vulnerability,
indicating they have substantial RUL and are without O&M issues. RUL is discussed in detail in
the following section. Moderate vulnerability pipes are largely in older portions of the system.
There are very few, approximately 2 percent, severe vulnerability pipes, which are spread
throughout the system.
Table 6.9 Vulnerability Score Range
Vulnerability Level Length (ft) Percent of Total
1 (negligible) 638,499 49.1%
2 (low) 384,523 29.6%
3 (moderate) 256,350 19.7%
4 (severe) 21,863 1.7%
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Legend
City of Renton
Criticality Criteria Rank
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Last Revised: August 03, 2017E:\KRC D DRIVE\Renton\Fig_06_04SumCriticality.mxd
Criticality Criteria
Figure
Results
6.2
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-19
6.6.3.1 Remaining Useful Life Analysis
Because the City has a limited amount of CCTV for their gravity mains, the main criteria used for
the vulnerability was a RUL estimate, or how many years a pipe with a certain material has
before it will most likely fail. Due to the importance of this criteria, detailed information is
presented below.
Pipe age and material type were used to determine the RUL of the collection system pipelines.
GIS data and field research were used to determine the type of material and year or decade that
pipe segments were installed.
Pipe manufacturers establish a theoretical useful life based on pipe material; however, the actual
useful life is commonly lower due to soil conditions, aggressive wastewater materials, roots,
installation errors, etc. The original useful life varies from 60 years for concrete pipe (CP) to
100 years for vitrified clay pipe (VCP). Since the age and material data for some of the pipelines
were unavailable, it is assumed that the original useful life for all unknown pipelines is 50 years.
Table 6.10 presents the estimated useful life of pipes of various materials.
Table 6.10 Useful Life of Pipes
Pipe Material Original Useful Life (Years)
Corrugated Aluminized Steel (CAS) 60
Concrete Pipe (CP) 75
Ductile Iron Pipe (DIP) 75
Polyethylene 90
Pre-stressed Concrete Pipe (PSC) 85
Polyvinyl Chloride Pipe (PVC) 100
Vitrified Clay Pipe (VCP) 100
Lined Pipe (LN) 75
Unknown Material (XXX) 50
Table 6.11 summarizes the City's gravity sewer system by material type into short, medium, and
long-term replacement. The cells are color-coded to show the three categories of RUL; red
indicates pipe that is expected to reach the end of their useful life in the next 10 years or has
reached its useful life, light orange represents pipe with a RUL of between 10 and 20 years, and
green represents pipe that has a RUL of over 20 years. In total, approximately nine percent of the
existing collection pipes with known installation year are expected to reach the end of their
useful lives by the year 2026.
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
Legend
City of Renton
Street Centerlines
Last Revised: September 20, 2017E:\KRC D DRIVE\Renton\Fig_06_05SumVulnerability.mxd
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 6.3
Vulnerability Criteria Results
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-23
Table 6.11 Remaining Useful Life
Feet of Pipeline (1)
Material >20 Years <=20 Years and
>10 Years
<=10 Years Grand Total
CAS 604 830 1,395 2,829
CP 265,992 49,683 55,824 371,499
DIP 58,591 0 186 58,777
Polyethylene 6,573 0 0 6,573
PSC 147 0 0 147
PVC 707,458 0 3,958 711,415
VCP 32,731 0 5,865 38,596
LN 16,653 265 0 16,918
XXX 7,716 36,485 50,236 94,438
Grand Total 1,096,464 87,263 117,465 1,301,192
Note:
(1) Feet of pipeline is specific to year installed per the City and not by decade.
Pipelines were assigned to one of four levels shown in Table 6.8 and Table 6.9. After discussing
the breakdown of the three replacement ranges with the City, it was agreed that the assets
with a RUL of less than, or equal to, 10 years could be split into two categories: between 5
and 10 years would be considered a "moderate" level, and assets that have less than 5 years of
RUL would be labeled as "severe". The resulting RUL levels were:
• Level 1 (Negligible) greater than 20 years
• Level 2 (Low) RUL between11 years and 20 years
• Level 3 (Moderate) RUL between 6 years and 10 years
• Level 4 (Severe) RUL less than 5 years
Table 6.12 shows the linear footage breakdown of these levels. Further detail on the RUL source
data can be found in CCTV Phase 2 Project’s TM 3 - Pipe Risk Approach and Procedures and RUL
scores can be found in TM 4 - Risk Findings (Carollo, 2017).
Figure 6.4 shows the map results of the RUL analysis, with the four levels color-coded similar to
the previous figures. Please note that the Sunset Lane project was completed in 2019 and
replaced and revised the layout of the pipe system around the new park, which is not reflected in
the figure.
Table 6.12 Remaining Useful Life by Length
RUL Level Length (ft) Percent
1 (negligible) 1,102,619 84.7%
2 (low) 86,030 6.6%
3 (moderate) 3,707 0.3%
4 (severe) 108,877 8.4%
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Legend
City of Renton
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
Last Revised: August 03, 2017E:\KRC D DRIVE\Renton\Fig_06_03RUL.mxd
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 6.
4
Remaining Useful Life of System
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 6-27
6.6.4 Gravity Sewer Mains Risk Assessment
A risk-based prioritization was developed for their R&R projects. As discussed above, risk is
calculated as the product of criticality and vulnerability. A risk ranking was developed for all
gravity collection pipelines in the system during the study. This assessment is at a conceptual
planning level and does not include survey, site inspections, or other detailed investigations.
Pipeline risk was determined by combining the vulnerability and criticality scores for each pipe
segment. Those two scores were then combined into 16 different "criticality, vulnerability"
combinations (for example: 1, 2; 2,3; or 4,4). Each combination was categorized with a risk
ranking of low, moderately-low, moderately-high, and high, as shown in Table 6.1. Table 6.13
shows how the linear feet of pipe was categorized into the 16 combinations using the normalized
risk rankings. Figure 6.5 shows the final result of the normalized risk ranking for the City's piping
system.
Table 6.13 Risk Matrix for Length of Gravity Mains (feet)
Normalized Risk Ranking Vulnerability Level 4
(severe) 1,805 7,061 10,061 2,935
3
(moderate) 44,840 63,075 103,884 44,551
2
(low) 76,510 100,541 148,925 58,546
1
(negligible) 210,622 180,371 186,199 61,306
1
(negligible)
2
(low)
3
(moderate)
4
(severe)
Criticality Level
Table 6.14 uses the results from Table 6.13 and shows the total lengths for the four colored risk
ratings.
Table 6.14 Pipe Length Totals Based on Risk Rating
Color Total Length (ft) % of Total Length
Low 467,504 36%
Moderately-Low 394,691 30%
Moderately-High 381,491 29%
High 57,548 4%
The following gravity main R&R is recommended based on the risk assessment:
• To confirm the condition of individual pipe’s RUL, the City should continue to conduct
ongoing monitoring through CCTV inspections and tracking of point repairs and other
maintenance issues. For the most critical or vulnerable pipelines, more advanced
condition assessment may be warranted
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 6
6-28 | MARCH 2021
• Approximately 57,500 LF of gravity mains are considered high risk and should be
rehabilitated in the short- and medium-term planning horizon (10 year period).
Individual capital projects will likely be warranted for long segments and large diameter
mains, while rehabilitation of smaller mains may be accomplished through annual R&R
program funding
• Approximately 381,500 LF of gravity sewers are considered moderately-high risk and
should be monitored in the short-term and medium-term planning horizon (10 year
period). Pipe segments in poor condition should be repaired, rehabilitated, or replaced
through an annual R&R program
• Remaining pipelines should be monitored in the medium-term planning horizon. Pipe
segments in poor condition should be repaired, rehabilitated, or replaced through an
annual R&R program
6.7 Recommended R&R Program
The recommended improvements for the replacement and rehabilitation program are
summarized below:
Force Mains
• It is recommended that the City conduct a CCTV inspection of FMs after FM cleanouts
are installed as part of the Lift Station and FM Rehabilitation
• It is recommended that the City monitor the condition of the stream banks adjacent to
the Devil’s Elbow lift station and evaluate alternatives to armor the banks to protect the
lift station and FM
• It is recommended the City continue regular maintenance and its active rehabilitation
program for FMs
Lift Stations
• The operation of lift stations with moderate and serve criticality should be monitored
closely and maintenance activities conducted promptly
• The Lake WA No. 2 Lift Station and Lake WA Flush Station, which both serve the
Lake Line Sewer System, have a severe risk and should be addressed in the short-term
• It is recommended that comprehensive R&R of Lift Stations and FMs be performed
during the long-term planning horizon
Gravity Sewer System
• To confirm the condition of individual pipe’s RUL, the City should continue to conduct
ongoing monitoring through CCTV inspections and tracking of point repairs and other
maintenance issues. For the most critical or vulnerable pipelines, more advanced
condition assessment may be warranted
• Approximately 57,500 LF of gravity mains are considered high risk and should be
rehabilitated in the short- and medium-term planning horizon (10 year period)
• Approximately 381,500 LF of gravity mains are considered moderately-high risk and
should be monitored in the short-term and medium-term planning horizon (10 year
period). Pipe segments in poor condition should be repaired, rehabilitated, or replaced
through an annual R&R program
• Remaining pipelines should be monitored in the medium-term planning horizon. Pipe
segments in poor condition should be repaired, rehabilitated, replaced through an
annual R&R program
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Legend
City of Renton
Critcality x Vulnerability Risk
1,1
1,2
1,3
1,4
2,1
2,2
2,3
2,4
3,1
3,2
3,3
3,4
4,1
4,2
4,3
4,4
Street Centerlines
CHAPTER 6 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Last Revised: August 03, 2017E:\KRC D DRIVE\Renton\Fig_06_06CriticalityXVulnerability.mxd
Map of Criticality x Vulnerability
Figure 6.5
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-1
Chapter 7
OPERATIONS AND MAINTENANCE
7.1 Introduction
This operation and maintenance (O&M) chapter summarizes the City of Renton’s (City)
Wastewater Operations Master Plan (OMP), which was developed in 2012 as a living document.
The OMP provides specific guidance on how to manage, maintain, and operate the system
assets with greater stewardship and effectiveness. This O&M chapter has been supplemented
and reorganized from the 2010 Long-Range Wastewater Management Plan (LRWWMP) for
consistency with the OMP.
7.2 Operations and Maintenance Programs
The O&M programs presented in this chapter are consistent with the "Wastewater Collection
Systems Management, Sixth Edition" by Water Environment Federation (WEF) Manual of
Practice No. 7 and “Core Attributes of Effectively Managed Wastewater Collection Systems”,
June 2010 (Appendix A), developed by the American Public Works Association (APWA),
American Society of Civil Engineers (ASCE), National Association of Clean Water
Agencies (NACWA), and WEF. These sources provided a foundation of good engineering
practices for O&M of sanitary sewer collection systems; providing guidance and direction.
Through development and implementation of a management program encompassing these
practices, the City can provide efficient and effective collection system O&M while protecting
public health and the environment. Where current City programs and practices are lacking,
enhancements have been recommended. In most cases, these program deficiencies were
identified in the OMP and are actively being developed by the City.
Based on the City's system and needs, O&M activities are divided into the following programs
and practices:
1. System Inventory and Information Management
2. Collection System Maintenance
3. Lift Station Operations and maintenance
4. Predictive Repair and Replacement (R&R) Program
5. Overflow Emergency Response
6. Fats, oil, and grease (FOG) Source Control
7. System Infrastructure Capacity
8. Design and Construction
9. Legal Authority
10. Safety, Training, and Certification
11. Interagency Coordination
12. Administration and Facility Maintenance
13. Financial Program
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-2 | MARCH 2021
The categories were formulated to be integrated within the organizational structure of the City
Public Works, which is presented in this chapter. Using this framework, a workforce estimate has
been developed to evaluate the staffing levels needed to perform the City's O&M functions at a
high level.
7.3 Organization
The City's O&M tasks are supported by the City's organization. The sewer utility operates under
the direction of the Public Works Administrator, as shown in Figure 7.1. Wastewater services are
provided under two divisions: Utility Systems and Maintenance Services. The Utility Systems
Director and the Maintenance Services Director both report to the Public Works Administrator.
The Surface/Waste Water Special Operations Services Manager reports to the Wastewater
Manager who in turn reports to the Maintenance Services Director. The Wastewater Utility
Engineering Manager reports to the Utility Systems Director.
The Surface/Waste Water Special Operations Services Manager and Wastewater Manager
evenly divide their duties, overseeing the O&M of the sanitary sewer and storm water systems.
7.3.1 Wastewater Maintenance Services
The Wastewater Maintenance staff focuses on preventative maintenance and troubleshooting of
the collection system. Maintenance staff works to prioritize and monitor issues to keep the
system operating in optimal conditions. Maintenance work may involve electronic, mechanical,
and other types of improvements to existing systems.
Currently, there are two Lift Station technicians and eight Maintenance Services workers
responsible for the continued operation of the sanitary sewer system.
7.3.2 Wastewater Utility Services
The Wastewater Utility staff is responsible for the design and management of capital
improvement program (CIP) projects, coordination of developer extensions of the sewer system,
and long-range planning for the Utility. The Wastewater Utility Engineering Manager oversees
the Wastewater Utility staff.
Currently, the Wastewater Utility staff consists of three engineering project managers, one
grease/industrial waste specialist, and a geographic information system (GIS) specialist.
7.3.3 Communication
Efficient and economical functioning of a team requires adequate provision for regular, effective
communication among its members. The normal channels of communication available to
maintain effective coordination are:
1. Vehicular two-way radios
2. Cellular Telephones
3. Daily work assignment meetings
4. Electronic records and GIS system inventory
5. Documentation in the Computerized Maintenance Management System (CMMS),
supplemented through more detailed work logs and inspection reports
6. Emergency phone numbers for "on-call" employees
7. Direct, City-owned telephone connection to City Hall
8. Weekly staff meetings
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-3
As the complexity of the system increases and the service area expands, the need for trained,
efficient staff to keep pace with public demand and advances in technology will become
imperative. New employees need orientation and basic training; while more experienced
employees can improve by continued training.
7.3.4 Divisional Coordination
The Wastewater Utility utilizes the services of other City departments, according to
inter-departmental agreements, to augment the Wastewater Utility’s expertise. The Finance and
Information Services Department is responsible for customer billing, payment collection, project
cost reporting, fund activity reporting, and basic computer needs. The Human Resource and Risk
Management Departments are responsible for employee records, union labor negotiations,
salary schedules, and risk management evaluation.
Within the Public Works Department, the Wastewater Utility utilizes the services of the
Technical Services Section. Technical Services provides support to Wastewater through Mapping
and Property Services. This includes computer-aided design (CAD) mapping, development of the
City’s GIS, surveys, and property management.
Within the Department of Community and Economic Development, the Wastewater Utility
utilizes the services of the Development Services Division. Development Services provides plan
review, permit issuance, and inspection for developer extensions. They also provide inspection
service for the Utility’s Capital Improvement Projects.
7.4 Wastewater Operations Master Plan
The OMP is summarized in this LRWWMP. There are two primary purposes of the OMP; 1) to
document current procedures and programs into an O&M manual, review existing programs for
effectiveness and compliance with potential future regulatory requirements; and 2) analyze and
recommend program improvements in accordance with the City’s long-term goals and
objectives, and assist with the development of an improvement implementation strategy.
The master copy of this document is maintained by the Wastewater Utility Engineering Manager
to be a living document. The Wastewater Utility Manager solicits updates, comments, and
recommendations from wastewater operations team members, which after review by the
wastewater operations management team are subsequently incorporated into the master
document.
7.5 Systems Inventory and Information Management
In recent years the City has made substantial investment in improving its system inventory and
information management.
7.5.1 Information Management System
Providing time for keeping and maintaining accurate records should be an integral consideration
in determining the time to be allotted to any departmental task. Adequate records are an
essential tool in utility management and operation, providing the supporting data for operations
assessment and long-term planning, while saving time and reducing difficulty when trouble
arises. The sewer utility has need for several types of records: facility operation, personnel,
customer contact, inventory, and facility maintenance and repair. These and other appropriate
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-4 | MARCH 2021
documents should be legible, concise, permanent, accurate and accessible. Their importance to
the efficient functioning of the utility is critical.
There are many different information systems that are currently used in the management, and
O&M of the City’s wastewater system. These information systems and recommended
improvements, as stated in the OMP, are shown in Table 7.1. Most of these information systems
are managed outside of the City’s Utility Systems Department and contain data for other
non-wastewater related functions and groups.
Information management is a key component of operating an effective and efficient wastewater
system. The City continues to work toward the vision of a seamless, integrated, information
management system. The benefits of developing this seamless, integrated, information
management vision are as follows:
• Improved budgeting, planning, and decision making for capital planning
• More efficient use of O&M staff
• Extended useful service life of assets
• Reduced risk of asset failures including overflows, breaks, and permit violations
• Better projections of asset lives and rehabilitation or replacement costs
• Enhanced customer service through reduced emergencies and improved response times
Since the 2010 LRWWMP, the City has integrated many information systems that have
increased the efficiency of wastewater business processes. These changes to information
systems are introduced gradually to allow City staff to learn and implement the benefits of the
upgrades. Further upgrades, especially in terms of automated scheduling, are anticipated in the
future as need arises.
GIS serves as a key user interface across multiple information systems and is used on a daily
basis. Since the 2010 LRWWMP, the wastewater utility has hired a full time GIS specialist to
assist with use of the information systems.
Table 7.1 Existing and Recommended Information System Improvements
Information
System
Existing
Software
Vendor
Description Recommended
Improvement
CMMS Cityworks GIS based Computerized maintenance
management system of sewer pipeline
assets, sewer manhole assets, sewer lift
station assets. Allows tracking of service
requests, work orders, preventive
maintenance, and work order costs.
Operators use Cityworks to track their time.
GIS ESRI ArcGIS Contains spatial data on sewer pipeline
assets, sewer manhole assets, sewer lift
station assets, lateral stubs, parcels,
addresses, FOG locations, zoning, and ROW
easements.
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-5
Information
System
Existing
Software
Vendor
Description Recommended
Improvement
CCTV CUES
Granite Net
Contains tabular and graphical data on
sewer assets, inspections, condition,
defects, and inspection photos and videos.
The City is currently planning to upgrade to
the latest version of CUES Granite Net with
additional modules for GIS integration and
NASSCO PACP standards.
Hydraulic Model DHI
MikeUrban
Contains tabular and spatial data on sewer
pipeline assets, sewer manhole assets,
sewer lift stations, modeled flows, pipeline
capacities, contributing areas, and
Infiltration and Inflow parameters.
SCADA Wonderware Contains real-time and historical tabular
data on influent/effluent flows, pump run
times, pump start times, and rain gauges.
Integrate with
Water Utility
FOG XC2 Contains tabular data on cross connection
and FOG locations, permits, and
inspections.
Integrate with
GIS.
Utility Billing /
Customer
Information
System
SpringBrook Contains tabular data on customers,
wastewater billing history, and
consumption records.
Permits
Management
EnerGov Contains tabular data on permits, planning,
business licenses, code compliance, side
sewer connections, and permit inspections.
Financial
Information
System
Tyler
Technologies
Eden
The City’s financial and accounting system
of record that contains all financial data
including budgets, revenues, capital and
operating expenses, and fixed assets.
SDC/SAD
Database
Contains tabular data on system
development charges and special
assessment district charges.
KC Assessors
Database
Microsoft
SQL
Database
Database that contains tabular data on
parcels, tax history, and property legal
descriptions.
Outside Data
Sources
Data Various outside data sources that including
the KC flow monitoring and rainfall data,
KC IMAP system, SeaTac Airport rainfall
data, and Renton Airport rain gauge data.
LaserFiche None This system is currently being implemented
by the City and will contain scanned,
electronic documents including record
drawings, as-built drawings, and other
relevant documents.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-6 | MARCH 2021
Information
System
Existing
Software
Vendor
Description Recommended
Improvement
ECM None This system is proposed to provide a
centralized web site for capturing and
linking to various data on projects, policies
and procedures, drawings, and other
electronic content. The existing hardcopy
O&M policies and procedures could be
scanned and populated into the ECM for
improved accessibility, ease of use, and
linking to other information systems.
Implement
with Microsoft
SharePoint.
Renton Results None This system is the City’s reporting tool for
outcome management and financial
performance measures. This system could
be expanded to include many of the same
functions as ECM above.
Implement
with Microsoft
SharePoint.
Note:
Abbreviations: CCTV - closed-circuit television; DHI - Danish Hydraulic Institute; ECM - Enterprise Change Management;
KC – King County; NASSCO - National Association of Sewer Service Companies; PACP - Pipe Assessment Certification
Program; ROW - right-of-way; SAD - Special Assessment District; SCADA – supervisory control and data acquisition;
SDC - Standard Development Charge.
7.5.2 Business Process
In addition to recommended information systems, the OMP documents business processes and
recommended improvements. Business processes reflect the ability to conduct O&M tasks by
streamlining and enhancing how the tasks are currently completed. A review of business
processes is recommended as part of the upcoming OMP update to incorporate the changes to
information systems discussed in the previous section.
7.6 Collection System Maintenance
The City maintains more than 191 miles of gravity sewer throughout the system. The
Wastewater Maintenance Services Crew’s primary goal is to maintain sewer pipelines to
minimize damage to property due to wastewater overflows. The collection system maintenance
program includes both preventive and corrective maintenance. The preventative maintenance
program includes: lift station inspection and maintenance, manhole inspection and
maintenance, CCTV inspection, root cutting, grease removal, and hydraulic line cleaning.
Corrective maintenance is that which improves the performance of existing equipment, facilities
and infrastructure. The corrective maintenance program is mainly composed of repairing sewers
and clearing plugs. Additionally, easement maintenance and minor road work is periodically
required to access the collection system. The following section briefly describes each O&M
program.
CCTV has undergone substantial changes since the last LRWWMP; therefore, it is presented in
more detail below in Section 7.6.3. Additionally, side sewer maintenance is a major problem
within a sanitary sewer system. It is the City’s policy that individual property owners are
responsible for maintaining their side sewers. If a problem occurs, it is the property owner’s
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-7
responsibility to contact a private plumber to investigate and correct the problem. Therefore, no
discussion of side sewers is provided below.
7.6.1 Maintenance Priorities
Wastewater Maintenance Services has developed a program to maintain the existing system.
First level of priority is the inspection and maintenance of the portions of the system that are
known to have problems if not handled on a weekly, monthly, quarterly, or annual basis. This
includes the inspection and maintenance of lift stations, areas of known root problems, and
areas of known grease problems.
The second level of priority is the routine inspection and maintenance that is required to identify
any additional high priority maintenance issues and to identify potentially unexpected
conditions that may cause problems for the customers. The second level of priority includes
CCTV inspection of the system and hydraulic line cleaning. It is typically recommended by
insurers involved with utility system management that, in order to minimize claims against the
utility, the entire system should be inspected approximately every five years. Since line cleaning
is performed prior to CCTV inspection, this means the system is cleaned on the same cycle as
CCTV inspection.
7.6.2 Manhole Inspection and Maintenance
The City has identified problem areas in the collection system. The City’s personnel inspect the
sanitary sewer manholes in those areas on a weekly, monthly, or quarterly basis - determined by
historical maintenance needs in the area - for the following situations:
1. A visual guarantee of proper sewage conveyance
2. Assessment of the state of solids buildup in manhole wet wells
3. Verification of the condition of the manhole lid/cover and support rings for wear and
stability
4. Visual affirmation of condition of sewer channels and ladder rings
Corrective actions are taken to address any issues that are found during the inspections. The City
inspects the remaining manholes/pipes in conjunction with the video inspection program. O&M
staff perform the same inspections and any required maintenance on those manholes at that
time. The City uses a line service truck for inspection and repair of manholes and lines. It carries
parts used in sewer line repair and repairs to manholes are made as needed.
7.6.3 CCTV Inspection
Routine video inspection of the sanitary sewer system is an essential part of the maintenance
responsibilities. The City uses the NASSCO PACP methodology to assess pipes during CCTV
Inspection. Structural correction and obstructions are the primary cause of line failure in sanitary
sewer pipes. Operational deficiencies, such as FOG build up, are also noted. Routine inspections
of the lines are crucial to be aware of potential trouble spots. Sewage spill claims have proven to
be a very costly type of litigation for municipalities to deal with and routing video inspection of
the sewer system is the first line of defense.
The City has recently implemented a new CCTV inspection program that includes purchase and
installation of the latest version of CUES Granite Net CCTV software, purchase of new CCTV
trucks and cameras, and the development of a risk-based condition assessment program.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-8 | MARCH 2021
7.6.3.1 CCTV Inspection Equipment
Since the 2012 OMP, the City has invested in a CCTV truck, camera equipment, updates to the
CUES Granite Net, and information technology (IT) to support the new equipment and software.
The City purchased a customized CCTV inspection truck that includes the following major
equipment: hybrid freightliner step van with inverter, safe entry/exit bumper,
transporter/camera lockable storage compartment, TV step van exterior lighting & viewing
room, roof top air conditioner with heat strip, file cabinet under viewing room desktop, wall
mounted storage cabinet mounted above desktop, and bench seat in viewing room. The
inspection truck included a new solid state color sewer TV camera with pan, rotate, and zoom
head. Additionally, the truck is equipped with a self-propelled lateral inspection / evaluation
system.
7.6.3.2 CCTV Software
The CUES Granite Net program contains tabular and graphical data on sewer assets, inspections,
conditions, defects and inspection photos and videos. The City’s IT and software allow the sewer
condition data, with associated photos and videos, to be collected via the Granite Net CCTV
process and automatically transferred and/or linked to ArcGIS for spatial analysis and reporting.
New and updated sewer pipeline and manhole asset data from ArcGIS is also automatically
transferred to Granite Net, along with the latest GIS spatial data, in order to provide the latest
information to the CCTV operations staff. The updated software also interfaces with modules for
a variety of different users and specialized functions.
7.6.3.3 NASSCO Rating and Scoring
The City uses the NASSCO system of rating the collection system to maintain consistent and
reliable data on condition. This includes standards of the PACP standard compatible mainline
information (Main Assets, Main Inspections and Main Observations). CCTV operators are trained
and well versed in NASSCO system coding. The City uses its own inspection methodology for
manholes and laterals that is focused on identifying assets for rehabilitation.
7.6.3.4 CCTV Driven Improvements
City operators make point repairs to critical pipe defects identified through the CCTV Inspection.
Repairs are made following the CCTV Inspection; depending on availability of necessary
operators, equipment, and customer notifications.
The City pursues preventative maintenance through its annual Pipe Replacement and
Rehabilitation program. The Program bids out a large replace or rehabilitate aging pipes project
each year to address aging infrastructure, typically in the same general area (rather than spread
out over the entire system). To assist with identifying areas, the City has developed a decision
support tool to help determine areas of pipes and structures to rehabilitate or replace based on
historical CCTV Inspection scoring.
7.6.4 Root Cutting
Routine sewer facility inspection commonly identifies root intrusion within both private and
public sewer mains. If the problem is within the City ROW, the City will correct the problem and
remove the root.
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-9
A hydraulic root cutter is used to routinely remove roots that accumulate within sewer lines
creating flow restrictions and blockages. Numerous lines throughout the City have been
examined and discovered to have had a history of problems created by roots. These particular
lines require root removal more frequently to ensure there is no interruption of flow.
7.6.5 Grease Removal
Grease problems are typically associated with major food processing operations, the majority of
which involves restaurants where grease is released into the conveyance system. Many of the
older restaurants within the City do not have grease removal systems while newer restaurants
have been and will continue to be required to install grease removal systems. Despite the
implementation of grease removal systems, many are not properly maintained. Grease buildup
problems occur most often in the side sewers; however, some grease buildup problems also
occur in the sanitary sewer collection system. When problems do occur, the City maintenance
crews are usually called out to investigate. A proper monitoring program reduces maintenance
time involved in removing grease buildup.
The City has achieved moderate success in noting problems and identifying the sources. The
Wastewater Utility has also worked with new construction and implemented tenant
improvements to ensure that these users are installing proper grease removal systems and/or
bio-agent facilities. The City has a grease removal program for standard food-services
establishments and multi-family housing to improve grease collection at these locations.
7.6.6 Hydraulic Line Cleaning
Jetting a sanitary sewer pipe is the principal means of cleaning the line portion of the sewer of
sludge, debris, or obstruction. Hydraulic Line Cleaning is a common means of addressing acute
and preventative maintenance concerns, as well as performed prior to CCTV Inspection. The
sewer lines are cleaned with a vacuum-high velocity cleaning/jetting truck which performs two
primary functions: vacuuming and jetting. A hose with a special end fitting is inserted into a pipe
and high-pressure water (up to 2,500 pounds per square inch) is sent through the hose. The
high-pressure water exits the small hole at the tip of the cone fitting, breaking down the sludge
and obstructions. The hose is propelled down the length of the pipe via the numerous other
holes found in the end fitting. The hose is inserted through a manhole into the pipe and the line
is jetted to the next manhole. The hose is then retracted via a motor driven reel system back to
the entry manhole. All of the sludge/debris is scoured toward the entry manhole because the
spraying water forces it in that direction and is vacuumed out as required.
There are a number of lines in the City that have inconsistent grades, creating septic conditions
within the lines. A part of the maintenance program is to use the Vac-Con to flush water through
these particular lines periodically to prevent those conditions from occurring until the inverted
slope can be reconfigured. The Vac-Con is the primary equipment used for emergency blockages
in the lines and is used to assist TV inspection.
7.6.7 Repair Sewers and Clear Plugs
When problems with the sewers are identified through the preventative maintenance program
described above, repairs are made to the infrastructure or clogs are removed. The preventative
maintenance program is efficient and typically represents only one percent of the maintenance
manhour allotment.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-10 | MARCH 2021
7.6.8 Easements and Access Road Maintenance
In addition to public roads, the City operates, maintains, repairs and constructs sewer mains, and
lines in, over, along, and under roads and easements located within the sewer service area. As
the utility performs work within the easements, minor roadwork and improvements are
necessary. All work done within the easements is done in accordance to any permits and City
and KC standards. Note, the Street and Surface Water Maintenance crews conduct maintenance
for the Wastewater Utility along road right of ways and other areas where work efforts overlap.
7.7 Lift Station Operations and Maintenance
The City maintains 20 lift stations throughout the system. The pump crew’s primary goal is to
maintain stations to minimize damage to property due to wastewater overflows. The
Wastewater has two operators dedicated to lift station maintenance that includes daily
inspections and regular preventative maintenance. The City maintains an O&M Manual for each
lift station. It is recommended the City review and update, as necessary, these manuals and
associated Standard Operating Procedures (SOPs) during the next OMP update.
7.7.1 Lift Station Inspection and Maintenance
Lift station inspection and maintenance involves weekly, monthly, and annual tasks which align
with preventative and corrective maintenance procedures. The following describes the
inspection and maintenance program for the sewage lift stations and wet well facilities:
7.7.1.1 Sewage Lift Stations
The City has on-call staff 24-hours per day. They also perform a daily inspection of the telemetry
at each station.
Every week the City performs an inspection of each lift station. This weekly inspection includes a
security check, recording pump motor hours, checking motor noise, temperature, and vibration.
The City changes all filters, cleans electrodes, exercises all valves, and runs each emergency
generator on a monthly basis.
On an annual basis, the City checks the pump bearings and seals, tests the entire electrical
system at each station, and performs an infrared test of the system.
7.7.1.2 Wet Well Facilities
On a weekly basis, the City checks the security, float settings, and operation of each wet well.
The City washes down, checks the interior condition, ladders, hatches, etc. in each wet well.
The City performs a pump down of each wet well once a year. They take this time to clean the
wet well.
The lift station crew uses a vehicle equipped with a crane to lift pumps, equipment, utility
compartments for parts, tools, etc. for the lift station maintenance program.
7.7.2 Telemetry (SCADA)
Successful operation of any municipal sewer system requires that the municipality maintains a
comprehensive maintenance program and that they obtain accurate sewage flow rate
information. A telemetry and control system is the means by which flow rates are measured and
maintenance needs are updated.
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-11
The SCADA system collects data from the City’s lift stations which is then continually stored on
servers at the shops. The SCADA information is only used when someone makes a query which is
usually related to lift station evaluation. Data compiled by SCADA includes inflow, outflow,
pump run times, and pump starts. The civil engineers have access to the SCADA and control
subconsultant (RH2 Engineering), which helps the City maintain the system. The current system
occasionally experiences communication failures and other issues that cause data errors. The
City has planned SCADA systems, in collaboration with the Water Utility, which is anticipated
resolve communication failures and provide additional monitoring and analysis features.
The master telemetry unit, located at the City Shop, includes an intelligent telephone dialer
alarm system, so that critical alarms can be relayed to on-duty maintenance personnel even
during a telemetry system failure.
7.8 Predictive Repair and Replacement Program
The City is currently expanding its Asset Management Program, which is described in more
detail in Chapter 6 – Replacement & Rehabilitation Program. The City's asset management
program prioritized asset renewal schedule and costs and is closely tied to O&M activities.
7.9 Emergency Response
The City’s Overflow Emergency Response Plan (OERP) provides measures to protect public
health and the environment in the event of a sanitary sewer overflow (SSO). Historically,
overflows have not been related to lack of capacity of the system. Instead, they are generally
related to disjointed pipe or blocking of pipes due to roots or FOG. The City may also develop
project specific emergency response plans, as required.
In addition to OERP, the Wastewater Utility participates in the City’s Comprehensive Emergency
Response Plan and the broader Regional Hazard Mitigation Plan. In the case of these wider
emergencies, the Wastewater Utility follows the direction of the Emergency Operation Center or
other responsible official.
7.10 FOG Source Control
Maintenance issues such as blockages and overflows can be caused or increased by FOG that is
discharged into the system. Controlling discharge into the collection system can assist in
enhancing and improving the collection system performance.
FOG buildup problems occur most often in the side sewers. However, some FOG buildup
problems also occur in the sanitary sewer collection system. When problems do occur, the City
maintenance crews are usually called out to investigate. A proper monitoring program reduces
maintenance time involved in removing grease buildup. Additionally, the City has worked with
new construction and tenant improvements to ensure that these users are installing proper
grease removal systems and/or bio-agent facilities. The OMP identified multiple items for future
effort with regard to the FOG program, including identifying regulatory requirements,
summarizing the FOG Control Plan and training, identifying performance measures, and
conducting a program evaluation.
7.11 System Infrastructure Capacity
The City has developed several tools and activities for determining system capacity such as
hydraulic models, flow monitoring, and field investigation. The key elements of the program are
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-12 | MARCH 2021
to identify existing areas of the system with capacity deficiencies and to confirm the available
hydraulic capacity for development. The City's hydraulic computer model is the main tool used
for this identification. The purpose of this model is 1) to evaluate the existing sanitary sewer
system and determine areas of capacity constraint, and 2) to provide a tool for planning future
improvements.
The analysis of the hydraulic capacity of the system is presented in Chapter 5 – System Analysis
and Results. The analysis includes evaluation of the City’s facilities for system capacity to address
both system deficiencies and potential development within the City’s sewer service area. The CIP
for capacity projects is developed from the LRWWMP and is maintained and updated annually
by Wastewater Utility Director.
7.12 Design and Construction
Utility Systems lead the City’s program to ensure proper design, construction, and inspection as
necessary to enable the collection system projects. Design involves converting the projects
identified in the planning process to paper to provide a set of documents (plans and
specifications) that will be used to construct the facilities. Construction involves building the
actual facilities that are planned and designed. Inspection helps resolve issues that arise during
construction and confirms that the facilities are constructed as planned and designed.
7.12.1 Design
Most designs are completed in house by the Utility Systems Project Managers. Projects may be
contracted out if the Utility Systems department is too overloaded, the project involves a lift
station, or it involves significant environmental issues. Design projects are selected based on this
Plan and follow the Washington State Department of Ecology (Ecology) Standards, the Orange
Book, Washington State Department of Transportation (WSDOT) Standards, and the City’s
adopted supplements and amendments. The pump station design standards are not
documented, but institutional design standards exist. The City has recently updated its standard
details and specifications, which are provided in Appendix J, Standard Details and Specifications.
This update, in part, coordinated the standard details between the City’s Development Services
and its Utilities.
All designs involve appropriate City staff, including Construction Inspectors, lift station
technicians, Maintenance Services, and Development Services.
7.12.2 Construction
The construction contractor is typically determined by competitive bidding; however, other
forms of selection such as emergency direct award or sole source are sometimes applied. The
project must be constructed as designed using the materials and procedures specified. The City
must approve any significant changes, and these changes should be documented.
7.12.3 Inspection
Utility Systems does not select the inspectors for construction observation. All inspections are
coordinated by the Development Services Department. Utility Systems allows the inspector
assigned to the project to dictate the level of involvement that the Utility Systems has during
construction.
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-13
The inspector’s main goal is to ensure that the project is constructed as designed and specified.
The inspection for a collection system project verifies that the pipe and appurtenances have
been installed correctly for line and grade and with the proper materials. The inspector witnesses
tests of installed pipe. Construction administration, including Requests for Information (RFIs)
and submittals, is typically lead by Wastewater Utility Engineers.
The City requires CCTV of new sewer lines to be completed after construction. Currently this
CCTV information is not used to establish a baseline for subsequent inspections.
7.13 Legal Authority
The City’s collection system is municipally owned, operated and maintained. It is managed by
the City’s Public Works Department. The customer is responsible for the maintenance and
condition of the laterals from the point of connection back to the property. The City has the
authority to operate, maintain, and administer a wastewater system through ordinances, service
agreements, or other legally binding procedures. Additional information on the City's legal
authority, policies, and standards can be found in Chapter 3 – Operational Policies and Criteria.
7.14 Safety, Training, and Certification
Training opportunities are of such high priority to effective operation of the system that the City
has linked them to its overall personnel evaluation program. Employees are evaluated and
promoted through a set of job categories with pay commensurate to the category. It is essential
that the promotional program continue to be closely linked with the training program, not only
because it promotes efficient operation, but also because mandatory certification of wastewater
utility workers is required by the state. The state Department of Health stipulates qualifications
and training requirements for obtaining and maintaining certification.
7.15 Interagency Coordination
Communication and outreach with customers, constituents, and other stakeholders is critical to
effectively manage a wastewater collection system. To be effective, communications must be
ongoing, open, timely, and two-way with reciprocal information sharing. Key stakeholders for
collection system operators include policymakers, customers, local residents and businesses,
regulatory agencies, local health officials, environmental organizations, community and business
groups, neighboring agencies and systems, and employees. Effective communications with each
of these groups will require different techniques that are tailored to specific interests,
perspectives, and each situation. Additional information on interagency communication can be
found in Chapter 1 – Introduction and Chapter 3 – Operational Policies and Criteria.
7.16 Financial Program
The City’s primary objective is to maintain an adequate revenue stream and implement effective
accounting practices to support the effective management of the system. This is accomplished
through financial programs such as the biennial budget process with mid-bi correction as
needed, the development of the CIP and Rehabilitation and Replacement Program. Additional
information on the financial program can be found in Chapter 8 – Capital Improvement Program.
The financial program is conducted in cooperation with the Administrative Services Division
based on input from Wastewater Utility staff.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-14 | MARCH 2021
7.17 Administrative Duties and Facility/Equipment Maintenance
Administrative duties as well as facility and equipment maintenance are crucial components to
the success of the Wastewater Utility. Administrative tasks are broad-sweeping and require
multiple skillsets of staff to complete. Additionally, the OMP maintains all new equipment and
facilities maintenances procedures.
7.17.1 Administrative Duties
The key administrative duty of the City’s O&M staff is to establish routine operation duties and
schedules. Routine operations involve the analysis, formulation, and implementation of
procedures to ensure that the sanitary sewer facilities are functioning efficiently. The utility's
maintenance procedures work well. Repairs are made promptly so customers do not experience
unnecessary inconvenience.
7.17.2 Tools and Equipment
Sewer O&M staff is equipped primarily with City-owned equipment. The equipment available for
daily use includes rolling stock, shop tools and incidental equipment, as well as other portable
equipment for field use. City Operators are responsible for cleaning, maintenance, and repair on
all non-rolling stock tools equipment. The rolling stock - specialized vehicles, such as Vacuum
Trucks and the CCTV Inspection Truck, and trucks/vehicles - repaired and maintained by the
Fleet Maintenance Section.
For Fleet Maintenance, the Wastewater Utility works with Fleet Services for procurement of parts
and to maintain a standard of service for each vehicle. IT has become an important tool for O&M,
including GIS based CMMS and asset inventory. As previously described, the IT department
maintains all information technology with assistance from Wastewater Utility Staff (as necessary),
including specialized software, database servers, etc.
7.18 Work Force Estimates
The wastewater utility is staffed by both Maintenance Services and Utility Systems teams. The
primary roles of each team, summary of programs, and estimated staffing levels have been
summarized in preceding sections.
7.18.1 Future Resource Recommendations
The LRWWMP evaluations have identified recommended projects and programs that will require
additional future resources. Resources that are responsible for the City’s wastewater operations
are currently divided across multiple department and divisions. These resources include the
following positions and area of responsibilities:
• Information and IT Support - Wastewater operations-related support functions that are
currently provided include approximately 0.1 full-time equivalent (FTE)
• Electronic Document Management System (EDMS)/ECM Support - It is recommended
the City provide 0.25 FTE of resources to support increased use of LaserFiche EDMS and
future ECM efforts (SharePoint)
• Hydraulic Model Support - It is recommended the City provide 0.25 FTE of resources to
support improved integration of the MikeUrban hydraulic model with GIS and SCADA
• Outside Support- Outside consultants and contractors currently provide support for the
MikeUrban hydraulic model and Wonderware SCADA system. These resources are
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-15
required on an interim basis when there are major upgrades to infrastructure, such as lift
stations, that require changes to SCADA, and when master plan updates are completed
that include changes to the hydraulic model
7.18.2 Emergency Operations
Emergency operations are the unplanned and unscheduled tasks needed to keep the system in
operation. The primary objectives of these procedures are to ensure public safety, restore
essential services as quickly as possible, and to provide assistance to other areas as required. This
would include responding to sewer blockages, pipes broken by construction, and damage to the
system by acts of nature. All of the O&M staff are also available to aid any of the other sections
with additional manpower or equipment.
The Wastewater O&M staff has the responsibility to keep the system operating when there are
power or mechanical failures at lift stations. The City’s telemetry system allows for 24-hour
remote monitoring and access to the system by the crew. With this access, they can be alerted to
a problem and correct it remotely, determine that it can wait until the next shift, or mobilize the
necessary manpower and equipment. The City follows all Ecology guidelines for emergency
notification procedures.
7.18.3 Maintenance Services Staffing
Currently, there are eight FTE, including supervisory personnel and maintenance workers, who
operate and maintain the wastewater system. The tasks that are performed by wastewater
utility staff include inspection, testing, installation and repair of system facilities and preventive
maintenance, corrective maintenance, record keeping, administrative tasks, training, and
response to emergencies.
The estimated FTE hours of work required to adequately maintain the sanitary sewer system are
shown in Table 7.2. For maintenance activities, the annual FTE hours total seven. The FTE hours
of work required for operational tasks for the sanitary sewer system are shown in Table 7.3. For
operational tasks, the annual FTE hours total two. For adequate maintenance of the sanitary
sewer system, the City would need a total of approximately 17,081 hours (the sum of O&M tasks)
worked per year. The City spends approximately 14,350 hours per year on O&M. This is
approximately 2,731 hours short of the hours estimated for O&M of the sanitary sewer system.
The size of the maintenance crew should be increased to carry the full workload of the Utility
without neglecting preventive maintenance, emergency preparedness, record keeping, or safety
precautions. Further staff increases should be tied to the actual growth of the sewer system. An
expansion of the system requiring new service connections and/or additional facilities, without
enlargement of the staff, will result in diminished levels of service for all maintenance programs.
In view of predicted population growth in the service area over the next several years and the
growing demand for sanitary sewer service, an increase in the size of the sewer system could be
projected to continue at a similar rate of growth. With that increase in demand, there may be a
need for additional staff.
As shown in Table 7.2, the City would like to add an additional two operators to increase their
maintenance activity FTE from 7 to 9. These operators would assist in doubling the amount of
CCTV inspection, which then increases the need for root cutting, grease removal, and hydraulic
line cleaning. Manhole inspections, sewer repairs, and unscheduled maintenance would not
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 7
7-16 | MARCH 2021
increase and would only be performed as needed. The City plans to use the CIP to repair
non-point source sewer in a cost effective matter.
The City also plans to increase staff time from 2 FTE to 2.5 FTE as shown in Table 7.3. By
doubling administrative duties, the City may have a separate full-time wastewater manager and
surface water manager.
Maintenance and technical staff additions may be accompanied by additions to the clerical,
secretarial, and other support staff needed to ensure that record keeping, billing, public
relations, communications, and other general functions of support staff are performed with the
accuracy and timeliness required.
Table 7.2 Staffing Time for Maintenance Activities
Preventative Maintenance Frequency of
Maintenance
Desired Time per
Year (FTE)
Existing Time
per Year (FTE)
Collection System
Maintenance
Manhole inspection, repair
and maintenance
As needed 0.5 0.5
CCTV inspection Continuous 2 1
Root cutting/grease removal Continuous 1.5 1
Hydraulic line cleaning Continuous 1.5 1
Repair sewers As needed 0.5 0.5
Unscheduled maintenance As needed 1 1
Lift Station O&M
Lift station inspection Twice per weekly 1 1
Lift station cleaning and
maintenance
monthly (cleaning),
annually (maintenance)
1 1
Total for Maintenance Activities 9 7
Table 7.3 Staffing Time for Operations Tasks
Operations Tasks Task Frequency Desired Time
per Year (FTE)
Existing Time
per Year (FTE)
Administrative duties Daily 1 0.5
Asset Management Annually 0.5 0.5
Tool and equipment cleaning Once per week 0.25 0.25
Staff meetings and Cleanup Daily 0.25 0.25
Training and conferences Annually 0.25 0.25
Total for Operations 2.5 2
CHAPTER 7 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 7-17
7.18.4 Wastewater Utility Engineering Staff
The City is not looking to increase their staff as number of capital projects are not anticipated to
increase in the next six years. They don’t work on their own, but in coordination with
“development” which is found on the organization chart.
The current engineering staff organization is described in Section 7.3 of this chapter. The
engineering staff is responsible for two major tasks, administrative and capital improvement
projects.
The various tasks and the hours of work are described in relevant sections within the chapter, as
summarized in Table 7.4. The number of hours required for each task is not easily defined.
Additional administrative tasks that are recommended in this LRWWMP are 1) prepare new
ordinances and revise existing ordinances, 2) setup and administer grease trap management and
certification ordinance, 3) inventory and update hydraulic computer model, and 4) perform
computer analyses using the sewer system hydraulic model. These tasks will require additional
City staff or other resource staffing alternatives.
Table 7.4 Wastewater Utility Engineering Staff Activities
Tasks/Projects
Administrative Tasks
Latecomer’s Agreement Administration
LRWWMP Review Support
Comprehensive Sewer Plan Update
Customer Service Support
Support to Other Divisions/Departments/Agencies
FOG / Industrial Waste Program
Engineering Tasks
Asset Management
System Infrastructure Capacity
Design and Construction
Major Capital Improvement Projects
7.19 Recommendations
The O&M staff requested purchasing equipment and tools for the department's crews, which are
currently shared with other City agencies. Additionally, acquisition of equipment for collection
system maintenance including a 10-yard dump truck, excavator/backhoe and trailer, shoring,
trench box, and a service truck was requested.
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-1
Chapter 8
CAPITAL IMPROVEMENT PROGRAM
8.1 Introduction
This chapter summarizes the Capital Improvement Program (CIP) for the City of Renton’s (City’s)
Long-Range Wastewater Management Plan (LRWWMP). The purpose of this chapter is to
describe the CIP projects and programs including pipeline, pump station, and general facility
types. The CIP consists of the cost estimates and schedules for the recommended
improvements.
The following sections present cost estimating assumptions, the recommended projects,
estimated costs of each individual project, and a summary of the CIP.
8.2 Cost Estimating Assumptions
The cost estimates presented in this CIP are opinions developed from bid tabulations, cost
curves, information obtained from previous studies, and Carollo Engineers, Inc.’s experience on
other projects. The cost estimates have been prepared for the general master planning
purposes. Capital costs, or “total project costs”, are presented in the CIP.
All costs are in 2019 dollars and were developed using a Class 5 budget estimate, as established
by the American Associate of Cost Estimators (AACE). The Engineering News Report (ENR)
Construction Cost Index for a 20-city average for July 2019 is 11293. This level of estimate is used
for master planning and assumes a 0 percent to 2 percent level or project definition. The
expected accuracy range is -30 percent to +50 percent.
8.2.1 Baseline Cost Assumptions
This is the total estimated construction cost, in dollars, of the proposed improvement for
pipelines and lift stations. All cost estimates provided in this CIP represent total project cost
including materials, construction, engineering, legal, and administrative costs. Costs were
represented as unit costs, as described in subsequent sections.
8.2.1.1 Gravity Sewer Unit Costs
For pipes, Baseline Construction Costs are calculated by multiplying the estimated new pipe
length by a proposed unit cost. These improvements involve a series of assumptions to develop
a cost per linear foot. All of the known pipelines involved in this CIP are between 6 inches
and 24 inches.
The gravity sewer unit costs provided are for typical open-cut installation with stable soil at an
average depth of 15 feet. Costs include manhole installation at every 300 foot interval,
excavation, hauling, soldier piles, wood lagging shoring, pipe materials and installation, backfill
material and installation, and pavement replacement for a two lane width roadway. Costs do not
include erosion and sediment control, individual side sewers, traffic control, or other general
conditions. Open-cut costs listed by pipeline diameter are available in Table 8.1
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
8-2 | MARCH 2021
Table 8.1 Open-Cut Costs by Pipeline Diameter
Pipeline Diameter Construction Cost per LF
6” $330
8” $341
10” $352
12” $363
14” $374
16” $385
18” $396
24” $407
Note:
Abbreviation: LF – linear feet.
Gravity sewer rehabilitation for typical right-of-way pipelines can be completed through
cost-effective cured-in-place pipe (CIPP) which varies in construction cost per linear foot. CIPP
estimates are shown in Table 8.2. CIPP costs include pre-inspection, installation, lateral
reinstatement, post-inspection closed-circuit television (CCTV), traffic control, and bypass
pumping. Traffic control is assumed for a collector street.
Table 8.2 CIPP Costs by Pipeline Diameter
Pipeline Diameter Construction Cost per LF
6” $52.80
8” $70.40
10” $88.00
12” $105.60
14” $123.20
16” $140.80
18” $158.40
21” $184.80
24” $211.20
8.2.1.2 Force Main Rehabilitation/Replacement Costs
Recent force main (FM) rehabilitation and replacement costs were obtained from the City’s
current Wastewater Utility Capital Improvement Program. An average cost per FM rehabilitation
was used for future cost estimating by using the total amount spent to-date by the City of
$2.28 million (M) for all 19 FMs. This determined the rehabilitation/replacement cost of $120,000
per FM.
FM assessment includes the same criteria as pump station assessment which may include one or
more of the following: addition of flow meters, engine generator installation, noise abatement,
slope stabilization, FM cleanouts, FM maintenance evaluation, FM replacement, manhole or
vault improvements, and environmental/agency elements.
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-3
8.2.1.3 Pump Station Unit Costs
Recent pump station rehabilitation projects completed by the City were compiled to create the
pump station rehabilitation cost. This cost was used to estimate pump station repair and
upgrade projects in the City’s CIP. As detailed in the 2019 Wastewater Utility Capital Investment
Program, all previous 20 lift stations were replaced, rehabilitated, or eliminated within
the 25-year span. The total amount spent on rehabilitation of all pump stations to-date by the
City is $2.8 M. This determined the rehabilitation cost of $140,000 per low to moderately-low
pump station. A similar cost will be derived by the City for high to moderately-high pump station
rehabilitation.
The assessment for rehabilitation of pump stations may include one or more of the following:
pump replacement, motor control replacement, telemetry improvements, addition of flow
meters, engine generator installation, noise abatement, slope stabilization, structural
adjustments to the wet well, assessment of coatings, wet well recoating, temp wet well system,
FM cleanouts, FM maintenance evaluation, FM replacement, manhole or vault improvements,
structural engine generator pad changes, structural control room changes, miscellaneous
structural improvements such as telemetry, and environmental/agency elements.
8.2.2 Total Capital Improvement Cost
The costs presented in this LRWWMP are high-level planning costs to help the City in making
financial decisions. A planning contingency cost will be added to the Total Allied Project Cost to
account for unforeseen events and unexpected conditions through the design process of these
projects.
As shown in the following sample calculation of the capital improvement cost, the total cost of
all project contingencies (construction and planning) and allied costs (engineering services,
construction management, and project administration) is 82 percent of the baseline construction
cost.
Example:
Baseline Construction Cost $1,000,000
City Administrative (10%) $100,000
Design (20%) $200,000
Construction (10%) $100,000
Admin, Design, & Construction $1,400,000
Scope Contingency (30%) $420,000
Total Capital Improvement Cost $1,820,000
8.3 Capital Improvement Program
As discussed in Chapter 5 – System Analysis and Results and Chapter 6 – Replacement and
Rehabilitation Program, the CIPs are prioritized based on their urgency and risk to mitigate
deficient systems. The timing for implementing these improvement projects is based on the
affordability and urgency of the project. It is recommended that the City monitor growth and
adjust project implementation accordingly.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
8-4 | MARCH 2021
8.3.1 Planning Periods
The following terms are used to define timing and prioritization into three planning periods:
• Short-term (2020 - 2025). Proposed facilities determined to be a high priority
• Medium-term (2026 - 2029). Proposed facilities determined to be a medium priority or
proposed facilities to service major growth areas to be developed in the medium-term
• Long-term (2030 - 2039). Proposed facilities determined to be a low priority or
proposed facilities to service major growth areas to be developed in the long-term
8.3.2 Project and Program Naming
The CIP projects were named based on the facility type.
8.3.3 Project Types
In the current Wastewater Utility Capital Investment Program, projects are categorized by type.
These types include the following:
• “M”= Maintenance
• “P” = Planning
• “C” = Cross Category
• “D” = Development
• “R” = Regulatory
• “A” = Acquisition
Maintenance projects are focused on renewing infrastructure in poor condition, as
recommended and prioritized in Chapter 6 – Replacement and Rehabilitation Program. Planning
projects focus on allocating miscellaneous/emergency funds or including funds for long-term or
operational planning. Development projects are designated based upon projected growth and
flow volume; no development projects were identified in this CIP. Similarly, no CIP projects are
listed under the acquisition or regulatory categories.
8.3.4 Capital Improvement Program by Year
An individual Project Sheet was generated for each CIP project and includes project identifiers,
description, costs, project type, and comments to aid in future implementation. A location map
is included for projects that are located in a specific area. To aid in finding individual projects,
Project Sheets have been separated in sections by facility type:
• “LS” = Lift Station
• “P” = Pipeline
• “G” = General
Lift Station projects addresses the City’s 20 traditional lift station / FM and the unique
Kennydale Lake Line System. Pipeline Projects address capacity and rehabilitation and
replacement of the gravity sewer system. General Sewer project support the capital projects
through long-term and operational planning, as well as various smaller miscellaneous projects.
A summary of all CIP projects by facility type and project type is shown in Table 8.3. A summary
of costs by project category and type is presented at the end of the chapter.
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-5
Table 8.3 Capital Improvement Program Summary
CIP Phasing (Current Dollars)
Project 2028 Short-term Medium-term Long-term
Enter Cost Type Here:Current Dollars (2020-2025)(2026-2029)(2030-2039)
$20,160,000 $3,000,000 $180,000 $0 $300,000 $0 $0 $650,000 $640,000 $640,000 $640,000 $3,480,000 $2,570,000 $14,110,000
LS-01 $900,000 $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000 $0 $0
LS-02 $400,000 $400,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $400,000 $0 $0
LS-03 $300,000 $0 $0 $0 $300,000 $0 $0 $0 $0 $0 $0 $300,000 $0 $0
LS-04 $180,000 $0 $180,000 $0 $0 $0 $0 $0 $0 $0 $0 $180,000 $0 $0
LS-05 $1,700,000 $1,700,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,700,000 $0 $0
LS-06 $8,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,000,000
LS-07 $6,110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,110,000
LS-08 $2,570,000 $0 $0 $0 $0 $0 $0 $650,000 $640,000 $640,000 $640,000 $0 $2,570,000 $0
Pipelines $71,230,000 $1,500,000 $3,450,000 $4,780,000 $3,730,000 $3,660,000 $3,750,000 $3,750,000 $3,540,000 $3,540,000 $3,540,000 $20,870,000 $14,370,000 $35,990,000
P-01 $1,500,000 $1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000 $0 $0
P-02 $2,000,000 $0 $2,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $2,000,000 $0 $0
P-03 $2,000,000 $0 $0 $2,000,000 $0 $0 $0 $0 $0 $0 $0 $2,000,000 $0 $0
P-04 $2,000,000 $0 $0 $0 $2,000,000 $0 $0 $0 $0 $0 $0 $2,000,000 $0 $0
P-05 $2,000,000 $0 $0 $0 $0 $2,000,000 $0 $0 $0 $0 $0 $2,000,000 $0 $0
P-06 $3,540,000 $0 $0 $0 $0 $0 $3,540,000 $0 $0 $0 $0 $3,540,000 $0 $0
P-07 $14,160,000 $0 $0 $0 $0 $0 $0 $3,540,000 $3,540,000 $3,540,000 $3,540,000 $0 $14,160,000 $0
P-08 $35,360,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,360,000
P-09 $5,800,000 $0 $1,450,000 $1,450,000 $1,450,000 $1,450,000 $0 $0 $0 $0 $0 $5,800,000 $0 $0
P-10 $1,190,000 $0 $0 $280,000 $280,000 $210,000 $210,000 $210,000 $0 $0 $0 $980,000 $210,000 $0
P-11 $1,680,000 $0 $0 $1,050,000 $0 $0 $0 $0 $0 $0 $0 $1,050,000 $0 $630,000
General $5,200,000 $500,000 $500,000 $500,000 $200,000 $500,000 $200,000 $200,000 $200,000 $200,000 $200,000 $2,400,000 $800,000 $2,000,000
G-01 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000 $0 $0
G-02 $300,000 $0 $0 $0 $0 $300,000 $0 $0 $0 $0 $0 $300,000 $0 $0
G-03 $600,000 $0 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $600,000 $0 $0
G-04 $4,000,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $1,200,000 $800,000 $2,000,000
CIP Total (Current Dollars)$96,590,000 $5,000,000 $4,130,000 $5,280,000 $4,230,000 $4,160,000 $3,950,000 $4,600,000 $4,380,000 $4,380,000 $4,380,000 $26,750,000 $17,740,000 $52,100,000
Annual Cost (Current Dollars)$4,830,000 $5,000,000 $4,130,000 $5,280,000 $4,230,000 $4,160,000 $3,950,000 $4,600,000 $4,380,000 $4,380,000 $4,380,000 $4,458,000 $4,435,000 $5,210,000
Wastewater Operations Master Plan
Devil's Elbow Stream Bank Study
2020 2021 2024 2029 2027
Capital Improvements Program Summary (Current Dollars)
2026 2022 2023 2025
Long-Range Wastewater Management Plan
Sanitary Sewer Hydraulic Model
Miscellaneous/Emergency Projects
Telemetry Upgrade
2020 Sanitary Sewer Main Replacement/Rehabilitation
2021 Sanitary Sewer Main Replacement/Rehabilitation
2022 Sanitary Sewer Main Replacement/Rehabilitation
2023 Sanitary Sewer Main Replacement/Rehabilitation
I/I Evaluation Program
Flow Monitoring Program
Forcemain Rehabilitation/Replacement
Total
CIP Cost
Estimate
Lift Station Rehabilitation
Pump Stations
2024 Sanitary Sewer Main Replacement/Rehabilitation
2025 Sanitary Sewer Main Replacement/Rehabilitation
Kennydale Lakeline Sewer Upgrade
Kennydale Lakeline Renewal
Low and Moderately-Low Risk Lift Station and FM
Rehabilitation
Moderately-High and High Risk Lift Station and FM
Rehabilitation
2026-2029 Sanitary Sewer Main
Replacement/Rehabilitation
2030-2039 Sanitary Sewer Main
Replacement/Rehabilitation
Sewer Capacity Improvements
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-7
8.4 Lift Station Projects
The City is completing the current series of lift station rehabilitation in 2020. It is anticipated the
City’s lift stations will require additional rehabilitation by the end of the planning period, given
the useful life of non-structural components and continued preventative maintenance of
structural elements Other major projects include the Kennydale Lake Line Upgrade and Renewal
projects will allow long-term operation of the system and renewal in the long-term. Prioritization
of long-term rehabilitation of the lift station and FM projects are based on risk.
8.4.1 LS-01: Lift Station Rehabilitation
The Wastewater Utility operates 20 lift stations throughout the City. At this point, the City is
going into the maintenance/rehabilitation phase for each of the stations. In 2016, the City
completed the process of evaluating the needs for each station. The second phase of full
rehabilitation of lift stations began in 2017 and will be completed in 2020. The cost for this has
been reported by the City at $900,000 in 2020.
8.4.2 LS-02: Force Main Rehabilitation/Replacement
The Wastewater Utility operates lift stations that each have their own FM that delivers the flow
to the gravity system. While many of the lift stations have been either rehabilitated or replaced,
their FMs often times were not. In 2016, a FM evaluation was completed that prioritized FMs.
The replacement and rehabilitation of FMs identified began in 2016 and will be complete
in 2020. The estimated cost is $400,000 in 2020.
8.4.3 LS-03: Telemetry Upgrade
The telemetry and control system records and stores flow rates and alarms for each lift station,
which is then monitored in a supervisory control and data acquisition (SCADA) system. SCADA
can then be accessed by the operations and maintenance (O&M) team, as well as engineers, to
help the City monitor infrastructure. This system occasionally experiences communication and
other issues that result in data errors which can be critical at times. Automatically generated
reports are a benefit of the updated SCADA. It is currently anticipated that the system will be
updated every five years. The cost for this has been reported by the City to be $300,000 and is
planned for 2023.
8.4.4 LS-04: Devil’s Elbow Stream Bank Study
It is recommended that the City monitor the condition of stream banks adjacent to the
Devil’s Elbow lift station and evaluate alternatives to armor the bank to protect the lift station
and FM. The timing for this project is recommended to be completed in the short-term. The
FM length is 506 LF with 6 inch diameter. The Level 5 AACE estimated cost for this project
is $180,000 in the short-term.
8.4.5 LS-05: Kennydale Lake Line Sewer Upgrade
The Kennydale Lake Line Sewer System Improvement Project will allow long-term operation of
the system. This program includes design and construction of a preferred alternative:
1) Lake Line System rehabilitation and repair or 2) Replacement with Individual Lift Stations. The
City has budgeted a total of $1.7 M for 2019 and $1.7 M for 2020 for a total of $3.4 M for this
effort.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
8-8 | MARCH 2021
8.4.6 LS-06: Kennydale Lake Line Renewal
The Kennydale Lake Line Sewer System Evaluation identified multiple options for the replacing
the system at the end of its usable life. For budgetary purposes, the least expensive option,
Individual Lift Stations, for $8 M will be budgeted in the long-term. For additional details, see the
2019 Kennydale Lake Line Sewer System Evaluation Phase 2B and 3 Summary Report.
8.4.7 LS-07 Low and Moderately-Low Risk Lift Station and Force Main Rehabilitation
This project addresses long-term renewal needs for existing facilities. Lift stations and FMs in the
moderately-low to low risk categories are recommended to be evaluated for rehabilitation in the
long-term, which are listed in Table 8.4. The recommended rehabilitation is consistent with the
City’s historical Lift Station rehabilitation schedule.
Table 8.4 Moderately-Low and Low Risk Lift Stations
Moderately-Low Risk Low Risk
Baxter East Valley
Stonegate Shy Creek
Airport Lind Avenue
Misty Cove Westview
Liberty
Lake WA Beach
Cottonwood
Pipers Bluff
Note:
Abbreviation: WA – Washington.
• The cost for rehabilitation of thirteen low and moderately-low risk lift stations is $3.27 M
in the long-term
• The cost for FM rehabilitation and replacement is $2.84 M in the long-term
Altogether, FM rehabilitation and replacement and lift station rehabilitation are estimated to
cost $6.11 M in the long-term planning horizon.
8.4.8 LS-08: Moderately-High and High Risk Lift Station and Force Main Rehabilitation
Lift stations and FMs that are moderately-high to high risk are recommended for rehabilitation
in the long-term, which are listed in Table 8.5. The recommended rehabilitation is consist with
the City’s historical Lift Station rehabilitation schedule.
Table 8.5 Moderately-High Risk Lift Stations
Moderately-High Risk
Talbot Crest
Long
Wedgewood
Devil’s Elbow
Kensington Crest
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-9
• The estimated cost of lift station rehabilitation is $1.26 M in the short-term and
medium-term horizon
• The cost for FM rehabilitation and replacement is $1.31 M in the long-term
Altogether, the planned cost is $2.57 M current value for the short-term and medium-term. This
does not include the rehabilitation of Lake WA No. 2 and Lake WA Flush stations.
8.5 Pipeline Projects
Pipeline projects address aging gravity sewer and the City’s relatively few pipe capacity
deficiencies. The rehabilitation and replacement is the largest City expense during the planning
period. These pipeline projects may involve full replacement with open-cut installation or
rehabilitation through CIPP. To identify and plan for replacement and rehabilitation activities,
the CIP includes condition assessments to identify deficiency and timing, infiltration and
inflow (I/I) micro-monitoring, and verification of capacity deficiencies through long-term
monitoring. All pipeline projects are shown in Figure 8.1.
8.5.1 Sanitary Sewer Main Replacement/Rehabilitation
The City’s annual Sanitary Sewer Main Replacement/Rehabilitation Program identifies and
repairs, rehabilitates, or replaces sewer pipe. Activities are mainly prioritized based on risk. Pipe
risk will be updated throughout the planning period through routine CCTV inspections and
required maintenance and any changes in criticality. More advanced condition assessment may
be conducted for high risk pipes.
The program currently prioritizes high and moderately-high risk pipes, as defined in this
LRWWMP and shown in Figure 8.2. However, lower risk pipes may be addressed when
cost-effective.
Program costs for the planning period are based on:
• Full open-cut replacement of all high-risk sewer pipes (54,000 LF) with a cost of
$35.16 M
• Rehabilitation (CIPP) of approximately half of the moderately-high sanitary
sewers (177,000 LF) with an annual cost of $27.32 M
• Gravity Sewer condition assessment budgetary placeholder of $50,000
The total cost of this program is $62.54 M in the short-, medium-, and long-term.
The actual method of sanitary sewer main replacement or rehabilitation will be determined
through site-specific design. The program is administered through separate annual budget line
items.
8.5.2 P-01: 2020 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $1.5 M in 2020.
8.5.3 P-02: 2021 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $2.0 M in 2021.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
8-10 | MARCH 2021
8.5.4 P-03: 2022 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $2.0 M in 2022.
8.5.5 P-04: 2023 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $2.0 M in 2023.
8.5.6 P-05: 2024 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $2.0 M in 2024.
8.5.7 P-06: 2025 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $3.54 M in 2025.
8.5.8 P-07: 2026-2029 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $3.54 M in the medium term.
The total cost is $14.14 M.
8.5.9 P-08: 2030-2039 Sanitary Sewer Main Replacement/Rehabilitation
This is an annual program that is performed to identify and either repair, rehabilitate, or replace
portions of sewer pipe that do not meet current standards. The program will be city-wide and
may consist of individual projects. The annual cost of this project is $3.54 M in the long-term. The
total cost is $35.36 M.
g`
g`
g`
g`
g`
g`
g`g`
g`East Valley RdRainier Ave NS 133rd St
Oakesdale Ave SWBe
n
s
o
n
D
r
S
SW 7th St
140th Ave SEN E S u n set Blvd
§¨¦405
Maple
V
a
l
l
e
y
H
w
y 164th Ave SECedar River Trail
SE Jones Rd
Lake Youngs Service RdSE May Valley Rd
SE Petro
v
i
t
s
k
y
R
d
5A & 5B: Mini-Basin 5
41A
25A: Mini-Basin 25
14A
25A: Mini-Basin U315A
48A
05A
21A
21A
22A22A
45A: Mini-Basin 1 2A: Mini-Basin 2
7A: Mini-Basin7
45A: Mini-Basin 45
3A: Mini-Basin3
24A 20B37A20A
1
1
A46A
23A
BA
Last Revised: September 18, 2019 \\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\9-2_Overview_of_CIP_Projects.mxd
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 8.1 Overview of CIP Projects
O
0 10.5 Miles
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton
Legend
LS-05 & LS-06: Kennydale Lakeline Upgrade and Renewal
PS-09: Sewer Capacity Improvements
g`P-10: Flow and Monitoring Program
P-11: I/I Evaluation Program
City Limits
Street Centerlines
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-13
8.5.10 P-09: Sewer Capacity Improvements 2021-2024
Pipe capacity improvements have been categorized together due to the need for infrastructure
replacement, rather than rehabilitation, due to lack of pipe hydraulic capacity. Pipe capacity
improvements were based on the City’s calibrated sewer hydraulic model to address either pipe
size or adverse slope segments. Details on the deficiencies, locations, and other parameters are
shown in Table 8.6 and Figure 8.2:
• The total length of pipe upsizing is 5,497 LF and will cost $3.64 M
• The cost for reconfiguration of 3,440 LF of adverse slope pipe is $2.17 M
The total $5.81 M in expenses are estimated for the short-, medium-, and long-term.
Table 8.6 Upsizing and Reconfiguration Locations and Cost
Deficiency ID Location
23 A North 28th Place and Park Avenue North
BA SE 24th Street and East Valley Road
46A Sunset Blvd North and NE 3rd Street
37A Edmonds Avenue and NE 9th Street
24A Monroe Avenue and NE 7th Street
11A Grant Avenue and SE 9th Street
20A SE 99th Court
20B Jericho Place and NE 16th Street
Note:
Abbreviation: ID – identification.
8.5.11 P-10: Flow Monitoring Program
The flow monitoring project is to verify deficiencies identified in the hydraulic model for the
specified pipe. These locations have typically not been observed deficient, so additional
monitoring over a specified period of time is recommended. All deficiency locations are shown
with details in Table 8.7. Altogether, the flow monitoring program is estimated to cost $1.49 M
and timing will be short-, medium-, and long-term.
Table 8.7 Flow Monitoring Locations and Duration
Deficiency
ID Location Meter
Quantity Duration Manhole ID
05A Talbot Road South and
36th Street to 27th Place 1 2- 5 years MH2998
22A Whitman Court NE and
NE 12th Street 2 1-2 years MH3616,
MH3622
21A Anacortes Avenue NE and
NE 17th Street to NE 26th Street 2 3-7 years MH3542,
MH3581
15A Renton High School 2 3-7 years MH2182,
MH2118
41A Lake Washington Boulevard and
Burnett Avenue North 1 3-7 years MH3324
Note:
Abbreviation: MH – manhole.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
8-14 | MARCH 2021
8.5.12 P-11: I/I Evaluation Program
Micro-monitoring is recommended for areas in wastewater basins that prior flow monitoring
indicated significant I/I in the collection system. This involves installing multiple flow monitors
where high I/I is observed and breaking larger areas into smaller basins to refine the location
of I/I. By micro-monitoring deficiencies identified in the hydraulic model, an isolated location
within the area will be identified for replacement. The downstream start location for
micro-monitoring is shown in Table 8.8. Repair or Replacement of identified I/I issues will be
allocated to Sanitary Sewer Main Replacement/Rehabilitation.
Table 8.8 I/I Evaluation, Quantity, and Duration
Deficiency
ID
Study
Quantity Locations Basins to Monitor
45A
5 SSMH004, MH2489,
MH2480, MH2258 45, 7, 3, 2, 1 7A
2A
3A
05B 1 MH5516 5
East Valley RdRainier Ave NS 133rd St
Oakesdale Ave SWBe
n
s
o
n
D
r
S
SW 7th St
140th Ave SEN E S u n set Blvd
§¨¦405
Maple
V
a
l
l
e
y
H
w
y 164th Ave SECedar River Trail
SE Jones Rd
Lake Youngs Service RdSE May Valley Rd
SE Petro
v
i
t
s
k
y
R
d
Last Revised: August 23, 2019 \\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Fig9-3_High_and_ModeratelyHigh_Gravity_Sewer_w_Upsizing_Reconfig.mxd
CHAPTER 8 | LONG RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Figure 8.2 High and Moderately-High Gravity Sewer Risk with Upsizing and Reconfiguration
O
0 10.5 Miles
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton
Legend
High Risk Pipes
Moderately High Risk Pipes
Pipe Upsize Projects
Pipe Reconfiguration Projects
City Limits
Street Centerlines
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-17
8.6 General Projects
General programmatic projects involve necessary funding which cannot be allocated to a specific
facility type. These projects involve implementation and compliance with regulatory
requirements such as the Wastewater Operations Master Plan (OMP). Additionally, future
miscellaneous and emergency projects for all infrastructure types have been allocated as general
projects.
8.6.1 G-01: Wastewater Operations Master Plan
This project will be an update to the Wastewater OMP created by the City. The purpose of the
OMP is to document current procedures and programs into an O&M manual and review existing
programs for effectiveness and compliance of potential future regulatory requirements.
Additionally, the OMP analyzes and recommends program improvements in accordance with
the City’s long-term goals and objectives. Based on the City’s existing resources and
implementation budget, it is recommended to implement this OMP over 5 years. The cost for
this OMP is estimated by the City as $600,000 in 2020.
8.6.2 G-02: Long-Range Wastewater Master Plan
The LRWWMP considers a 20-year planning period for the analysis of existing and projected
conditions. The sewage collection system’s operational and capital requirements are detailed to
achieve the City’s operational goals and fulfill regulatory requirements. The cost is estimated
at $300,000 in 2024.
8.6.3 G-03: Sanitary Sewer Hydraulic Model
As discussed in Chapter 7 – Operations and Maintenance in the System Infrastructure Capacity,
the City has a hydraulic model that allows them to evaluate the existing sanitary sewer system
and determine areas of capacity constraint, and provide a tool for planning future
improvements. The model needs to be updated as the system expands, and flow monitoring and
physical system data is collected by survey or field inspection. The cost is estimated by the City
as $600,000 over two years in the short-term for the model to be updated in 2021 and 2022.
8.6.4 G-04: Miscellaneous / Emergency Projects
This project is to perform small repairs, replacements, or installations of sewers that are not
scheduled in the CIP, but become a priority due to unexpected problems, failures, or
coordination with other projects. Based on historical spending, the cost is estimated by the City
as $200,000 annually, or $4.0 M, in the short-, medium-, and long-term planning horizon.
8.7 Summary of CIP
Altogether, recommend improvements include eight lift station projects, eleven pipelines, and
four general projects. The majority of projects are allocated as maintenance projects at $75.24 M
of the total $89.11 M. Cross category projects follow at $8.19 M, as well as planning projects
at $5.78 M. Seventy-seven percent of short-term project funding is allocated to pipelines with
general at nine percent. In the short-term, lift stations require the remaining fourteen percent of
funding.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
8-18 | MARCH 2021
The CIP recommends investing $26.11 M into the wastewater system during short-term. The
annual short-term cost for all recommended programs is approximately $4.38 M per year from
2020 to 2025. For medium-term, the CIP recommends an additional $17.75 M be invested to
continue these programs. The annual medium-term cost is approximately $4.35 M per year from
2026 to 2039. For long-term, the CIP recommends $51.47 M be invested to continue to maintain
the sewer system. The annual long-term cost is approximately $5.15 M.
Detailed sheets for each CIP project presented in this chapter can be found in Appendix K.
Table 8.9 summarizes the total cost and annual cost for each planning period.
Table 8.9 CIP Planning Period Summary
Planning Period Total Cost Annual Cost
Short-term (2020-2025) $26.75 M $4.46 M
Medium-term (2026-2029) $17.74 M $4.44 M
Long-term (2030-2039) $52.10 M $5.21 M
Pipelines account for a majority of the capital cost of planned projects (73 percent) at $70.17 M of
the $95.53 M. Pump stations account for $20.16 M (21 percent) of the total CIP. The remaining
$5.2 M (6 percent) is associated with general projects. Table 8.10 summarizes the total
estimated capital costs by facility type. Figure 8.3 shows the various facility types of CIP
allocation.
Figure 8.3 Cost by Facility Type
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021 | 8-19
Table 8.10 CIP Summary by Facility Type
Project
ID Title Total Capital Cost ($)
Planning Period
Short-term
(2020-2025)
Medium-term
(2026-2029)
Long-term
(2030-2039)
Lift Station
LS-01 Lift Station Rehabilitation $900,000 $900,000
LS-02 FM Rehabilitation/Replacement $400,000 $400,000
LS-03 Telemetry Upgrade $300,000 $300,000
LS-04 Devil's Elbow Stream Bank Study $180,000 $180,000
LS-05 Kennydale Lake Line Sewer Upgrade $1,700,000 $1,700,000
LS-06 Kennydale Lake Line Renewal $8,000,000 $8,000,000
LS-07 Low and Moderately-Low Risk Lift Station and
FM Rehabilitation
$6,110,000 $6,110,000
LS-08 Moderately-High and High Risk Lift Station and
FM Rehabilitation
$2,570,000 $2,570,000
Pipeline
P-01 2020 Sanitary Sewer Main Repl/Rehab $1,500,000 $1,500,000 $0 $0
P-02 2021 Sanitary Sewer Main Repl/Rehab $2,000,000 $2,000,000 $0 $0
P-03 2022 Sanitary Sewer Main Repl/Rehab $2,000,000 $2,000,000 $0 $0
P-04 2023 Sanitary Sewer Main Repl/Rehab $2,000,000 $2,000,000 $0 $0
P-05 2024 Sanitary Sewer Main Repl/Rehab $2,000,000 $2,000,000 $0 $0
P-06 2025 Sanitary Sewer Main Repl/Rehab $3,540,000 $3,540,000 $0 $0
P-07 2026-2029 Sanitary Sewer Main Repl/Rehab $14,160,000 $0 $14,160,000 $0
P-08 2030-2039 Sanitary Sewer Main Repl/Rehab $35,360,000 $0 $0 $35,360,000
P-09 Sewer Capacity Improvements $5,800,000 $5,800,000 $0 $0
P-10 Flow Monitoring Program $1,480,000 $1,220,000 $260,000 $0
P-11 I/I Evaluation Program $1,680,000 $1,050,000 $0 $630,000
General
G-01 Wastewater OMP $300,000 $300,000
G-02 Long-Range Wastewater Management Plan $300,000 $300,000
G-03 Sanitary Sewer Hydraulic Model $600,000 $600,000
G-04 Miscellaneous/Emergency Projects $4,000,000 $1,200,000 $800,000 $2,000,000
CHAPTER 9 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
DRAFT | MARCH 2021 | 9-1
Chapter 9
FINANCIAL ANALYSIS
9.1 Introduction
This chapter analyzes the financial status of the City of Renton’s (City’s) water utility for the
Long-Range Wastewater Management Plan (LRWWMP). The purpose of this chapter is to
provide a cursory evaluation to show the City’s ability to finance necessary Capital Improvement
Program (CIP) projects in Chapter 8 – Capital Improvement Program.
The following sections present the City’s financial status, funding required to finance the
scheduled improvements, potential funding sources, and the impact of water system
improvements on water rates.
9.2 Historical Financial Performance
9.2.1 Current Water Rates, Fees, and Charges
The City and King County (KC) wastewater rates are summarized in Table 9.1.
Table 9.1 2020 Water Utility Monthly Rates(1)
Category City KC
Single-Family $15.55 $28.51
Other Users
Base Charge $2.35 NA
Per 100 cf $1.76 NA
Per 750 cf NA $28.51
Minimum Charge $15.55 $28.51
Notes:
Abbreviations: cf – cubic feet; NA – not applicable.
(1) Outside City Limits: Rates are 1.5 times the above for the Renton rates.
Construction permit fees are summarized in Table 9.2 .
Table 9.2 Construction Permit Fees(1)
Type of Service 2019 2020
Residential $350 $375
Commercial $350 $375
Industrial $350 $375
Repair of any of the above $350 $375
Cut and Cap/Demolition Permit $350 $375
Ground Water Discharge (temporary connection
to wastewater system for one-time discharge of
contaminated ground water to 50,000 gallons)
$350 + KC sewer rate
discharged amount
$375 + KC sewer
rate discharged
amount
Note:
(1) Per Resolution 4359, fees for an Accessory Dwelling Unit (ADU) will be assessed at 50 percent; fees will be waived for
every third ADU created within a subdivision of ten or more lots and vested as of the adoption date of Res. 4359, through
December 13, 2020.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 9
9-2 | MARCH 2021 | DRAFT
The City pays for expansion of the sewer system through system development charges (SDCs).
The SDC allocation based on meter size is shown in Table 9.3.
KC also has a charge for first time connection to sanitary sewers in KC, including the City’s Sewer
Service Area, called the sewage treatment capacity charge. This charge pays for building sewage
treatment capacity to serve newly connected customers. Single-family customers pay $66.35 per
month for 15 years. It may also be paid as a lump sum of $9,927.44 to KC. This charge is
established annually and changes to the capacity charge apply only to new connections.
Table 9.3 2019-2020 System Development Charge(1)
Meter Size, inch 2019 2020
5/8 x 3/4 $3,100 $3,400
1 1/2 $15,500 $17,000
2 $24,800 $27,200
3 $49,600 $54,400
4 $77,500 $85,000
6 $155,000 $170,000
8 $248,000 $272,000
Note:
(1) Outside City Limits: Rates are 1.5 times the above for the Renton rates.
9.2.2 Historical Financial Operations
The City’s operating revenues and expenses for the years 2015 to 2019 are summarized in
Table 9.4 and Table 9.5, respectively. The tables present City and KC wholesale water services
(King County Metro Fund) revenue and expense.
WATER SYSTEM PLAN | CHAPTER 8 | CITY OF TUMWATER
DRAFT | MARCH 2021 | 9-3
Table 9.4 Historical Operating Revenue(1)
Operating Revenue 2015 2016 2017 2018 2019 Budget
City Revenue $ 10,880,141 $ 13,286,986 $ 15,143,808 $ 12,124,358 $ 11,582,615
King County Metro Fund $ 16,638,722 $ 16,142,469 $ 16,922,259 $ 16,886,297 $ 16,922,613
Total $ 27,518,863 $ 29,429,455 $ 32,066,067 $ 29,010,655 $ 28,505,228
Note:
(1) Source: City’s Financial Statements.
Table 9.5 Historical Operating Expenses(1)
Operating Expenses 2015 2016 2017 2018 2019 Budget
City Expense $ 6,832,715 $ 13,785,490 $ 11,593,468 $ 10,655,159 $ 13,858,678
King County Metro Fund $16,638,722 $ 15,140,189 $ 16,827,147 $ 16,463,648 $ 16,922,613
Total $ 23,471,437 $ 28,925,679 $ 28,420,615 $ 27,118,807 $ 30,781,291
Note:
(1) Source: City’s financial statements.
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
9-4 | MARCH 2021 | DRAFT
9.2.3 Wastewater Utility Fund
The City maintains substantial fund balances to ensure continued operation of the Utility. These
include operation, bond, and undesignated as shown in Table 9.6
Table 9.6 Historical Utility Fund
Utility Fund 2015 2016 2017 2018 2019 Budget
Operation $ 838,706 $ 838,706 $ 838,706 $ 661,227 $ 661,227
Bond $ 307,857 $ 806,900 $ 373,343 $ 949,646 $ 954,259
Undesignated $ 6,442,525 $ 9,990,909 $ 12,647,613 $ 15,799,129 $ 17,263,715
Total $ 7,589,088 $ 11,636,515 $ 13,859,662 $ 17,410,002 $ 18,879,201
9.2.4 Outstanding Debt
The City has outstanding debt through the Waterworks Revenue Bond debt and Public Works
Trust Fund Loans. As of 2019, the Waterworks Revenue Bond has $22.3 million (M) in
outstanding principal debt and the Public Works Trust Fund Loans have $1.9 M in outstanding
principal debt.
9.3 Financial Analysis
The City’s ability to fund its CIP was evaluated by comparing the historical and future funding
requirements.
9.3.1 Projected Capital Improvement Program Levels
Projected CIP is described in Chapter 8 – Capital Improvement Program and summarized in
Table 9.6 and Figure 9.1 below. The following terms are used to define timing and prioritization
into three planning periods:
• Short-term (2020 - 2025). Proposed facilities determined to be a high priority
• Medium-term (2026 - 2029). Proposed facilities determined to be a medium priority or
proposed facilities to service major growth areas to be developed in the medium-term
• Long-term (2030 - 2039). Proposed facilities determined to be a low priority or
proposed facilities to service major growth areas to be developed in the long-term
Table 9.6 shows the expected cost per planning period. Comparison of annual CIP cost.
Table 9.7 CIP Planning Period Summary
Planning Period Total Cost Annual Cost
Short-term (2020-2025) $ 26.27 M $ 4.38 M
Medium-term (2026-2029) $ 17.79 M $ 4.45 M
Long-term (2030-2039) $ 51.47 M $ 5.15 M
9.3.2 Financial Analysis
A Wastewater Revenue Requirement Model (WRRM) was conducted in 2018 to analyze the
future finances of the City. The LRWWMP’s CIP differs from the WRRM CIP; therefore, this
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
DRAFT | MARCH 2021 | 9-5
Section seeks to show the financial capacity of the LRWWMP CIP by comparing of the two CIP
costs. For the purpose of this analysis, all assumptions in the WRRM were considered applicable,
including expected rate increase of 2 percent from 2020 to 2024.
The differences between the proposed LRWWMP and WRRM CIP, as shown in Figure 9.1 and
Table 9.8. The proposed LRWWMP and WRRM CIP are both in current dollars. The annual
WRRM CIP spending is $4 M from 2021 through 2024 and then $4.5 M from 2025 through 2029,
as shown in Table 9.8. With the WRRM the fund balance does not get drawn down. The
LRWWMP CIP shows annual spending from 2021 through 2024 will be higher than the WRRM,
and from 2025 to 2029 the proposed CIP is lower than the WRRM. This results in a net drawdown
of approximately $1.5 M dollars of the 2018 $15.8 M undesignated wastewater funds. This
spending is additional planned to address existing repair and replacement (R&R) and capacity
needs in the system.
This analysis to show the City’s financial capacity in respect to the LRWWMP CIP. The City is not
committed to CIP spending summarized in the LRWWMP. Per the City budgeting policy, the
Utility’s spending is based on a biannual budget approved by the City Council.
Figure 9.1 CIP Proposed and Rate Analysis Model
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Revenue Analysis Model CIP Proposed CIP
CITY OF RENTON | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CHAPTER 8
9-6 | MARCH 2021 | DRAFT
Table 9.8 Projected Future Operating Expenses
CIP Analysis 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
WRRM
CIP $ 4,500,000 $ 4,000,000 $ 4,000,000 $ 4,000,000 $ 4,000,000 $ 4,500,000 $ 4,500,000 $ 4,500,000 $ 4,500,000 $ 4,500,000
Proposed
CIP $ 5,010,200 $ 4,130,000 $ 5,280,000 $ 4,230,000 $ 4,160,000 $ 3,950,000 $ 4,600,000 $ 4,380,000 $ 4,380,000 $ 4,380,000
Fund
Balance
Change
($510,200) ($ 130,000) ($ 1,280,000) ($ 230,000) ($ 160,000) $ 550,000 ($ 100,000) $120,000 $120,000 $120,000
CHAPTER 8 | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
DRAFT | MARCH 2021 | 9-7
9.4 Available Funding Assistance and Financing
The ten-year planning period shows the City will have adequate funding for the anticipated
short-term projects shown in the CIP, so more bonds and funding isn’t necessary. However,
there are bond assistance and grant options available if needed.
9.4.1 Grants and Low Cost Loans
The Infrastructure Assistance Coordinating Council (IACC) is a non-profit organization that helps
improve the delivery of infrastructure assistance, both financial and technical, to local
governments and tribes in Washington State. The IACC has put together a list of funding
opportunities that are currently available for drinking water and wastewater projects.
The Public Works Trust Fund (PWTF) is a potential loan for eligible projects including repair,
replacement, and construction of infrastructure for domestic water projects that improve public
health and safety, respond to environmental issues, promote economic development, or
upgrade system performance.
9.4.2 Bond Financing
Bond financing is obtained by issuing general obligation or revenue bonds. Revenue bonds do
not require voter approval and may be repaid with revenues from rates, miscellaneous fees or
connection charges.
9.5 Summary
Due to unusual circumstances from COVID-19, short term revenue cannot be predicted, but in
the long term, it is not expected to heavily impact the budget and long-term analysis. Over the
next five years, the City is anticipating spending approximately $22,810,000 in capital projects.
CIP spending as proposed for the short term can still be completed although it will draw down
the reserve fund. However, by 2025 it is expected that even with CIP spending, the reserve fund
will begin to build up again. Based on the City’s 2020 rate study, rates are expected to increase
at 2 percent from 2020 till 2024.
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix A
SEPA CHECKLIST
~~To be included at a later date.~~
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix B
AGENCY COMMENT LETTERS AND RESPONSES
~~To be included at a later date.~~
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix C
APPROVALS
~~To be included at a later date.~~
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix D
HYDRAULIC MODEL AND DEFICIENCY RESULTS
Appendix D
HYDRAULIC MODEL AND DEFICIENCY RESULTS
This Appendix goes through all the deficiencies presented in chapter 5 and shows the location and the
hydraulic profile where the surcharging and flooding occurs. The hydraulic grade line profiles can be used to
identify the cause of the deficiency. Physical flow constraints are primarily identified as negative sloped
pipes, undersized pipes, and downstream backwater conditions. Current and buildout system results are
shown for the February 96 storm event. For deficiencies that emerged only for buildout scenarios just the
buildout system HGL is shown.
A legend for all the HGL profiles is shown below:
O
0 10.5
Miles
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: Fill in the name of
the data sources used in this map
including aerial imagery.
APPENDIX D | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Legend
3 feet from rim
Flooding
King County
Force Mains
d/D Ratio
0 - 1
1 - 2
2 +
U Basin
Nov 1998 Storm
Nov 1990 Storm
Jan 1990 Storm
Feb 1996 Storm
Roads
Figure D.1
Current Deficiencies
05A
45A
15A
37A
21A
22A24A
23A
48A
20A
20B
46A
14A
3A7A2A
BA
11A
41A
Deficiency 05A:
Deficiency 45A:
Deficiency 7A, 2A, and 3A are upstream of this.
Deficiency 46A:
Deficiency 37A (drains through MH0825):
Deficiency 48A:
Deficiency 24A:
Deficiency 20A:
Deficiency 20B:
Deficiency 22A:
Deficiency 21A:
Deficiency 41A:
Deficiency 23A:
Deficiency 15A & 14A (just upstream):
Deficiency BA:
Deficiency 11A:
O
0 10.5
Miles
Disclaimer: Features shown in this
figure are for planning purposes and
represent approximate locations.
Engineering and/or survey accuracy
is not implied.
Data Sources: Fill in the name of
the data sources used in this map
including aerial imagery.
APPENDIX D | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
Legend
3 feet from rim
Flooding
King County
Force Mains
d/D Ratio
0 - 1
1 - 2
2 +
U Basin
Nov 1998 Storm
Nov 1990 Storm
Jan 1990 Storm
Feb 1996 Storm
Roads
Figure D.2
Buildout Deficiencies
05A
45A
15A
37A
21A
22A24A
23A
48A
20A
20B
46A
14A
3A7A2A
BA
05B
25A
05C
11A
41A
Deficiency 05B & 05C:
Deficiency 25A:
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix E
SERVICE AGREEMENTS
Exhibit No.Jurisdiction Agreement No.
E.1 Cascade Sewer District Agreement Resolution 1234
E.2 Cascade Sewer District Agreement CAG-039-74
E.3 Soos Creek Water and Sewer District Boundary Agreement CAG-91-083
E.3.1 Soos Creek Water and Sewer District Boundary Agreement CAG-91-083 Add 1-04
E.3.2 Soos Creek Water and Sewer District Boundary Agreement CAG-91-083 Add 2-08
E.4 Soos Creek Water and Sewer District Boundary Agreement CAG-97-164
E.5 Skyway Water and Sewer District Boundary Agreement CAG-03-197
E.6 Apollo Elementary School Service Agreement CAG-1636-70
E.7 Water District No. 107 Joint Use Agreement CAG-035-75
E.8 Renton Franchise to Water District No. 107 Resolution 2692
E.9 Coal Creek Utility District Boundary Agreement CAG-01-031
E.10 City of Kent Joint Use Agreement Resolution 2413
E.11 King County Franchise 14056 14056
E.12 Cedar River Water and Sewer District Boundary Agreement CAG-99-014
E.13 Skyway Water and Sewer District Coveyance Agreement CAG-06-170
E.14 Coal Creek Utility District Sewer Service Agreement CAG-19-182
s 1,
t"-.4 ` % G IC.I.L
r
Y ..
a so u2ro o. /.y
WHEREAS TA C 1SC DF. SEt 7ER DYSTRICT, a unicipal eorpai-ation, hereir a£ter referrecl
to as "BISTRICT", has heretofore made ppl ication to the CITY OF 1tEI'P6N, a city of th.e
second class under the laws and statutes of the State of ,Tashington, hereinafter refer-
red to as "CITY", to use certain street right of ways for the constructian, inst llat on
and r aintenanee of a cert2in interceptor sewer line which line extends fror the DZS-
TRICT'S present sewer system, through portions of the CITY OF REIVTON and connects_ to
the sewer syste of the Ljunicipality of I etropolitan Seattle, and
WHEREAS it is deemed advisable and of public benefit to provide for the connection
and hookup of properties located ti ithin the CITY to said interceptor sewer to be
constructed at the sole cost and expense of DISTRICTfand
WHEREAS DISTRICT, CITY and certain affected property owners whose properties
lie within the CITY have heretofore agreec to enter inta a certain greement, pursuant
to which CITY wouid colleet for and on behalf of DISTRICT, certain hookup charges fro:
any and alI property owners desiring to hookup to such interceptor line, a;ithout any
lizbility whatev r on the part of the CITY for such line except as to CITY'S obligation
to remit funds unto the DISTRiC'T so collected fror:a abutting owners desiring to tap on-
to such line, and said Agreement being recsonable nd proper and in the public interest,
NOW T LREFORE,
BE IT RESOLVGD BY Tt?E MElYOR AND THE CI'IY COUNCIL OF THE CI'IY OF REl`'I'ON 1 S FOLZOfA7S:
SBCTION I: A i the aforesaid r citals nd findings are hereby determined to be
true and correct in all respects.
SECTION IT: The Mayor and the City Clerk 2re hereby authorized and directed to
execute , on behalf of CITY, that certa in Agreer ent between DISTRICT and CITY datec
March ;; , 1964, a copy thereof being attae ed hereto, labeled Exhibit "A'• and by
reference incorporated herein as if f u11y set forth. The Mayor and Citq Clark 2rt fur-
ther authorized and dirccted to iseue such per nits f or the construction an instal ation
of said interceptor line within and under the CITY'S streets as specified in the 2for-
G -' ^-^T:nt anc as deter ined znd aporovad b y the CITY'S Engineer. Such lgree!:nt,
upon execution by all the parties thereto, shall thzn be recorded in the Off ice of the
Kin Count; Auditor at the expense of DIS TRICT, and copies thereof f urnished unto the
owners of property located within the CITY and abutting upon said interceptor s wer line
here inabove referred to.
PASSED BY THE CITY COUNCIL this 2nd dsy of March, 1964.
Helmie Nelson, City C.erlc
PPRO'ED BY 'FHE Nl YOR th i s 2nd d a y of Mar ch, 1964. i
PPROVED 1S TO FORAS: y,.i.//
Frank Aliment, Mayor _
i:.. ;;_ellan, City Attorney
E.1
4'
L.r 3
s
r a{.. .:..._ _. "'L,a,.ALl1f`:„G'rn`,^ii .l.e"}t„ {_,5'.`iLT. I
j.
i_. ::: C:i:i Q.L i.i: .t'_.wi s.:a'` .,'.::
c
4
C V. .. .. """'•,........ .
m.:a. ..:
e Ir..a.iv li.h .. _ _ n1v.. cT. ra..
a
a. r u'C E-4'
II AG RE I: i i T
r 7
T;II5 AGi2EEi AJT, r,tade and cnte ed into this 27th
ay of
i larch, 1J64, i y and bet veen CASC IDE SEiJETt DISTRICT, a murl.i a. carpor tion of
tIxe State of ,Jashingtori Iiereinafter c 11ed '}bIS'RIC'T", and the CI"I'Y OF RENT4N,
I
a nicinai carpo'ia» af th State af r ashington, iiereinafter called "CITY",
s'JI TNESSIiTiI:
T.iAT .J:IER AS, tlie District and the City are situated conti;zously in
I:ing Caunty, State of ':lashington, and
lIiEREAS, the District Iaas nrenared constructian nlans and called for
contract icis far constructian of an intercentor seseer 2ine to extend from the
nresent se ver system 4perated y the I}istrict, W1L 13.I2 a.ts boundaries, and to run
through certain portions of tlYe City ta collection trunk setaer lines constructed
by the t3unici ality of i ietronolitan Seattle, and
JiIEREA.S, certain areas hereinafter described situated within the boundaries
of the City may also be served byuse of said znterce tor line, thereby eliminating
the necessity of the City constructing such txunlc facilities, and
1:I-fERCAS, the District is aillin and able ta construct and pay for the
costs af said 2ine and the City is willzn and desirous ta reimburse the District
for an agxeeci u an portion of said constructian costs, according ta the terms and
conditions hereinafter set fortli.
30'J, TIiEREFORE, IT IS iIER BY P fUTUALLY COVENA'dTED AND AGREED by and between
tt e paxties hereto, as follacvs:
1. That the sntire constructzon cost of said interceritor Izne, accarding
to the en;ineering plans therefox, l eretafore nrepared by the District nd ap roved
by the City, shall be naid by the District.
2. That said Iine s1 a12 be constructed tizraugli and acrass certain areas
within the City of Renton, iiing County, rashingtan, described as foilows:
T7is follei+ring description located in :ing County, jJashingtan,
descxibed the centerline routs of the roposed Interce tor Se aer
fram its t oint of discharge into the Trunk Se vers of the i;unici ality
of i ietropolitan Seattle to tlie Soutiierly line of the 5eattle Cedar
River pipe line right-of-vay, vhich is also the city limi s of Renton:
i3eginning at the intersection of the idorth Iine of the NE i/4 af Section
21, Township 23 Noxth, Range S ast :+..t., and the toxthc resterly margin
of the City c f Seattle's texcex Isl.and pineline R/;, said intersectian
also being idoxth 894 0'24" l rest 1112.45 feet from the iJortheast corner
of said Sec. 21; thence South 28 23+,q++ ,st along said :Vorth ae teriy
maxgin 1,OQ8.02 feet; tt ence Souttz 61°3G'06" East pernendicular to said
Nort}xwesterly margin 5.00 feet to tlie true noint flf eginning; also
laeing existing 1letro ii.il. R-10-33;
1-
E.1
s
1 Thence Sauth 28°23'S4" ,lest 913.OQ £eet;
2) Thence Sauth 8°04'OJ'" 1Jest 84.50 feet;
3) Tiience Nor h 32°O1' 11" iJest 133.00 feet;
4) Thence iJorth 8Q°15'03" nJest 1,213.76 feet;
5) Thence South I4°I3'42" siest 321.J0 feet;
G} Thence 5autlt 36a27'ST" :est 428.J2 feet;
7} T7ience Sauth 40°52'44" t'Jest 295.G feet;
8) Thence Sauti 72°39'42" ',est 282.20 feet;
J) Thence South 48°08'23" tJest 3?.00 feet;
10) Tl ence South 14°2G'S9" slest 54.Q8 feet;
11) Thence South 41°51'37" East 742.00 feet;
12) T7ience South 47°41'q0" East 762,73 feet;
13) Thence Soutli 11°26'S4" i'Jest 603.91 feet;
14) Thence Soutli 11°03'08" 9est 104.00 feet.
The entire route of the interce tor sezvex iait in the City af Renton,
the centerline of ahich isdescribed above, is lacated an easements
I except the follacain;, which are on Public Riglit a£ ytTay:
City of Renton streets;
The most South esterly 105.QO feet of Caurse (9 ;
All of Caurse (10 ;
The most North uesterly 37.4J feet of Caurse (11) .
The City shall grant to the District a permit for the construction, oreration
and maintenance o£ said line, subject to the texms and canditions of this
Agreement.
3. That said line shall be used, o erated and rnaintained by the
I District and by the City for service of their pxesent and future customers fox
transferring secvage collected by the District and by tlie City ivithin their
respective territaries for delivery ta the I+letro trunk Iine and no payment or
service charge therefox shall be xequired by either of these axties one ta the
e of such use other than as hereinafter set forth hereinotherforthepxivilge
far reimbuxsement of construction costs, maintenance and repairs.
4. 'Fhat the City shall have thc right zo authorize connections ta
said line by praperty o vners of prot erty situated vithin the boundaries af the
City of Rentan, Kin County, Jashzn ton, described as fo].lows:
That portion af Sec. 21, Toti+mship 23 i arth, Range S
East t 3.t i, l,ying South af the Cedar River and i3oxth
of the Sauth line of the Seattle Cedar River Pine3ine RjtV,
exce t the East 1/2 of Sc utt east lJ4 and except the
Southeast 1i4 of dartheast 1/4 af said Section 21;
Alsa, that portion af the Easterly 1/2 of Sec. 20,
Township 23 PJorth, Range 5 East tV.P1, from which the
j sanitary sewage is carried asterly or Sautheastexly in
the future across 116th Ave. S.B. and into said Sec. 21
ar into Seco 28, Township 23 i doxth, Range S East t t.?.
uncter such erms and condiLions as the City r ay estab3ish for making such connec-
tions. The City shall alsa have the right to aut orize connactions to said line
by pro erty owners a property tivhich may hereafter annex to the Czty, under the
i same terms and conditions as provided hexein for roperties now situated within
the bt undaries of tlle City.
2-
E.1
r
ti
s
S. No nerson, firm or cornoration sha ll be granted a permit, or be author-
ized to tap into, hook onto, or use said sewer intercentor line, has hereinabove
described, during a period of thirty (30) years from date hereof c ithout first
naying unto the City; in addition to an'y and all other costs and charges made or
assessed for su"cli hoolctin, tap, or use, ai amouiit of not less than $.013 ner square
foot of area inc uiied in any 'such p operties fr r w3 ic3i connections are allowed by
the City. All amouiits eceit ed t y th ity 51ia11 be naid out by it unto the I
ti
District under the terms of tliis Agreement within sixty (60) days after receipt
thereof. ,rthermoi e, iri case any tag, hookup, or connection is made into any
such inte ito s wer, without such payment first having been made as hereinabove
set fc rth, the City Council of tlie City of Renton may remove, or cause to be
removed, such unauthorized tap, hool:up,,,.or connection, and all connecting tile
or pine located in tiie-- ility ri lit-o£-way, and dispose of unauthorized materials
so removed, without any liability whatsoever to any narty.
It isc cpressly understood that the aforesaid minimum charge per sauare
foot, (based on the provisions of R.C.d. 35.92.025} ,shall not prevent the City from
adding or imposing such other re.asonable charge for collection and boolckeening
services, including taxes, if any, that may reasonably be incurred by the City,
in providing for the collection service herein undertaken for and on hehalf of the
District; it being stipulated that the aforesaid per square foot rate is solely a
method of ineasurement of the amounts due and o oing to the District for properties
allowed to connect and use said intercentor line facility.
6. T}iat as betiveen these parties, it is stipulated that the n ronortionate
share of costs of said interceptor line, as located within the boundaries of the
City, is approximately 60,OQ0.00 and tliat it is the District's intent to be
reimbursed by the abutting property owners for sucli costs. It is exnressly agreed
and covenanted byand bet ueen the parties that the City does in no caay warrant I
rayment of any such sum, or sums, during the life of this Agreement, and that the
I
City's obligation hereunder shall be Iimited solely and exclusively to the collec-
II
tion of c}iarges, asabove stated, from property owners who wish to hook up and
connect to said interceptor sewer trunk line. No interest shall be charged the
City upon such sum, or any other sum, bythe District, and the City's aaency for
collection pur oses on behalf of the District shall not impose in any way any
liability or other costs unon the City, and the District hereby agrees to hold the
City harmless £rom any liaUility relating to the costs of installation, or the
District'sbonded indebtedness in connection theretoith.
3-
E.1
t
h
i
That maintenance costs, re a9.rs and o eration necessaxily incurred lirn
far said interce tor ,line within t1 e boundaxies c f the City shall be boxne on a
praportionate basis determined on the same ratio as the number of users served
by the Dist ict Uea'rs `t'ta t ie number of users served by the City usins; saic inter-
ceptor ,iri'e, Damage 0 5aid interceptor line which may be caused bythe neglip,ence
of either these ,arties, t ieir a ents or assigns, sha12 be xenaired by tlle
I respansible party.
I
8. That awnership of said line shall remain in the District unti.l the
I
expiration of a pexiod of thirty (30} years fram date hereof or ayment in full of I
the present bc nded indebtedness af the District ar subsequent bonded xndebtedness
i.ncurred far the pur ose of refinancin thereof shali have been paid in fuli,
whichever event shall came first, or as otherwise rovided by la4a. Ttrexea£ter,
the City sliall b under na further obligation to collect or remit any other or
further suins to the District as reimbursement fox construction costs and ocuner-
ship of said line s1 a11 be jointly vested in the Distxict and the City, aith fuli
and complete right of use thereof allo aed to each party and with expenses of
maintenance thereof continued unon the same prapartionate basis as hereinabove I
set fort z. I
9. In tlie event said iine shall become inadec uate to serve Lhe entire area
lying within the District and tl e City, preference sha12 be given ta the District
I
and its users and the City shall, as additional lines become availahle, divext
i
sewage collected vitha.n the District into naxall.el and additional trunk Iines,
c hich it is eontem Iated i oulc then be available as Iines necessarily constructed j
in development of said t ra erties to such extent.
IN C'JITNESS I^1IlEREOF, the parties nereto have set their izands and seals this
27thday of A arch, 1964.
CASCADE SE'' R DISTRICT
y: i
f
Cl2aixman`' '
Secretary
i
CITX OF ENTON
Y• I>'
Playor "
Attest:
i=v.J
City Clerk
4-
E.1
z
4,
L I
i
STATB OF t1ASHINGTON } I
ss. I
Ct UNTY 0 F I:I.i G
4n tl is 27th day of A]arch, 1964, before me, the undersi;r ed, a
Notary Public in and far the 5tate of !'Jashington, duly commissioned and
sworn, personally appeared L01"JELL V. LECIC NBY and GHARLES iJ. BAYLESS, to
me known to be the Chairman and Secretary, respectively, of CASCADE SE:J R
DISTRICT, a municipal corporation of t}xe State of ,Vashington, the corporatian
that executed the fore oing instrunent, and acknowledged the said instrument
ta be tl e free and voluntary act and deed of said coxporatian, far the uses
a d purposes therein mentioned, and on oat t stated that they are aut3.oxized
to execute the said instx ument and tl at the seal affixed isthe corpoxate IIssalofsaidcoxporation,
I
i JITNESS my hand and official seal hereto affixed the day and
year in this certificate abave ritten.
t . - _
b-4-_.------._
Notary Public in and for the State
af IJashington, rssiding at Rentan
STAT`E OF tJASHINGTON )
ss.
e r o xz c
T
Qn this j G day of• 1964, before me, the undersigned, a
Notary Public in and far the "r tr e !' hington, duly commissioned and
sworn, nexsanally appeared ,iE and IIELI IIE NELSON, ta me known
to be the layar and City Clerk, reSn ctively, of TI-IE CI"TY OF RENTON, a
municipal corporation of the State o£ ,Jashington, th e cor oration that
executed the foxegoing instrument and acknowled ed the said instrument i
to be he free and voluntary act and deed of said corporation, for the
uses and t urposes therein mentioned, and on oath stated that they are
authorized to execute tt e said instrument and that tl e seal affixed is
the corporate seal of said carporation,
JITIVESS my hand and official seal hexeto affixed the day fl
year in this certi£icate above written.
iz
Nota Pub2ic in and far the State
af tashington, residing at Renton
i
5-
I
E.1
I
4
RATIFICATIOi'1 OF AGRE A9Ei iT'
The undersigned, being the principal owners of properties
hereinabove described, situated within the boundaries of the City of
Renton, in consideration and reco nition of the obligations incurred by
the City of Renton under the terr.is and conditions of the £oregoing
Agreement, do hexeby ratify and acknowledge the obligations thereof to
the extent that said Agreement affects our real nronerty hereinabove
described.
l de do hereby ackno vledge uron behalf of ourselves, our
heirs, executors and assig,ns that none of our said nroperties may be
connee ed to the se uer trunlc main being constructed by Cascade Sewer
District until payment has been made to the City of Renton of such
connection and hook-up fees as may be established by the City, tahich
amount will include the .013 obligation of the City to the District as
hereinabove described.
DATED th is day of hlarch, 1964.
VIKING I:VESTD NT CO ORATION ,
By: _
Presi
B .
P'reasur(er
s
ARNE G. GOEDECICE, in i 'd.i lly.and as
Attorney-in-Fact for Louise h1. Goedecke,
his wife
6-
E.1
J
t
a .
STATE OF :ASIiINGTON )
ss.
couN r oF xlr c
On this 0-- day of P tarch, 1964, before r e, the undersigned; a
Notary Public in and for the State of 4Vashington, duly commissioned and
s vorn, personally appeared IC. A. SAND':'ICK, JR. and ROBERT C. DETRICH, to
me kno an to be the President and Treasurer, resrective2y, of VIKING
IiWESTA1Ei'tT CORPORATION, the coruoration that executed the foregoin
instrument, and acknowledged the said instrument to be the free and
voluntary act and deed of said corporation, for tlie uses and purposes
therein mentioned, and on oat}i stated that they are authorized to execute
the said instrument and that the seal affixed is the coxnorate seaZ of said
corporation.
tdITNESS my hand and official seal hereto affixed the day and year
in this certificate above vritten.
i-
i - ,Notary Public in nd for t ate
of 7ashington, r iding at
STATE OF iVASHINGTON )
ss.
COUNTY OF KING
On this ,6 -- day of Alarch, i964, before me, the undersigned, a
Notary Public in and for the State of :ashington, duly commissioned and
sworn, personally ap eared ARNE G. GOEDECKE, Individually and as Attorney-
in-Fact for Louise P•1. Goedecke, his tiaife, to me known to be the individual
that execufied the foregoing instrument and acknotivled;ed the said instrument
to be his free and voluntary act and deed, for the uses and purposes therein
mentioned.
s`lITNESS my hand and official seal hereto affixed the day and year
in this certificate above written.
I
n , , /
Notary Public in a d for th t„te
t-
of :Jashington, res ing at J
I
7—
E.1
E.2
E.2
E.2
E.2
E.2
E.2
E.2
r ! S CAG-083-91
CITY OF RENTON & SOOS CREEK WATER AND SEWER DISTRICT
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
I
THIS AGREEMENT, made and entered into thiskAL day of
1941, by and between SOOS CREEK WATER AND SEWER DISTRICT, a ashington
municipal corporation, hereinafter referred to as "THE DISTRICT", and the CITY OF
RENTON, a Washington municipal corporation, hereinafter referred to as "RENTON",
both being duly organized and existing under and by virtue of the laws of the State
of Washington,
WITNESSETH:
WHEREAS, THE DISTRICT is qualified to provide water and sewer service
within its prescribed area; and
WHEREAS, RENTON is qualified to provide public services, including water and
sewer service, within its prescribed area; and
WHEREAS, THE DISTRICT has constructed, and has managed, operated, and
maintained certain water and/or sewer facilities which exist in areas which have been
annexed by RENTON, and which can most efficiently be managed, operated, and
maintained by RENTON in conjunction with other facilities in the City; and
i
WHEREAS, bond covenants, resolutions, and other agreements of THE
DISTRICT require that certain steps be taken, and certain financial arrangements
made, as part of any transfer of facilities from THE DISTRICT to another party; and
WHEREAS, it is in the best interest of both parties to have RENTON administer
the collection of General Facilities Charges on behalf of, and to be passed on to, THE
DISTRICT for those areas herein described to be transferred to RENTON for
management, operation, and maintenance; and
WHEREAS, it is in the public interest for the parties herein to enter into an
agreement to provide for the efficient planning and development of new water and
sewer services in areas which may be served by either, or both, of the parties herein;
now therefore,
4-7:04O ft.00l Page 1 of 11
MAY 2 3 1991
E.3
tr, s
IT IS HEREBY AGREED by and between the parties hereto as follows:
1 . Water service by THE DISTRICT within RENTON City Limits. THE DISTRICT
shall provide water service to the properties within THE RENTON City Limits
described in attached Exhibit "A", and as shown in attached Figure 1 .
Any new construction within the current RENTON City Limits by THE DISTRICT
for water service shall be in compliance with RENTON requirements including;
materials, techniques, fire flow, and all other standards. Existing watermains
are excepted, provided that any upgrading or replacement shall be in compli-
ance with said RENTON requirements.
Future transfer of service areas shall be by mutual agreement to be determined
at that time. Any new or replacement facilities after the date of this agreement
shall be transferred to RENTON at no cost if constructed by developer, but
RENTON shall reimburse THE DISTRICT for the value of any DISTRICT
construction not yet fully depreciated, at an amount equal to the remaining
amount to be depreciated.
2. Water Service by THE DISTRICT Within RENTON City Limits Without
Annexation to THE DISTRICT. THE DISTRICT shall provide water service to the
following areas within the City Limits which are not within DISTRICT
boundaries, and by agreement will not require annexation (also shown in
attached Figure 1 ):
a) Spring Glen Elementary School.
b) The West 340.00 feet of the East 670.00 feet of the South 305.00 feet
of Section 20, Township 23 North, Range 5 East, W.M., less City and/or
County Road.
Any new construction within the RENTON City Limits by THE DISTRICT for
water service shall be in compliance with RENTON requirements including:
materials, techniques, fire flow, and all other standards. Future transfer of
service area shall be by mutual agreement to be determined at the time any
facilities change hands.
3. RENTON Provide Water Service Within DISTRICT Limits. The following areas
have already been transferred to RENTON for service, or are herein released to
RENTON for provision of water service by RENTON at no further charge for the
transfer of such service area. THE DISTRICT releases all claim to water service
within the areas described in Exhibit "B", and as shown in attached Figure 1 .
4-7:04W400g.001 Page 2 of 11
E.3
4. Water Service Area Boundary Between RENTON and THE DISTRICT. The
attached Exhibit "C" describes the line separating the RENTON water service
area from THE DISTRICT water service area. RENTON shall provide ultimate
service for the area North and West of the line described. THE DISTRICT shall
provide ultimate service for the area South and East of the line described. This
line is also shown in attached Figure 1 .
5. PONDEROSA ESTATES: Sale of Sewer System to RENTON. The facilities
listed below (and on As-Built page A-43 referenced) and the area as described
in attached Exhibit "D", and as shown in attached Figures 2 and 3, are hereby
transferred (sold) to RENTON by THE DISTRICT. THE DISTRICT agrees to
allow the Ponderosa Estates sewer mains to remain connected to lines
belonging to THE DISTRICT. THE DISTRICT further agrees not to charge
RENTON for any maintenance of the lines so impacted, so long as RENTON
agrees to, and continues to, notify THE DISTRICT whenever maintenance of
the lines in Ponderosa Estates will be performed. Furthermore, that the
RENTON maintenance crews take steps to minimize the amounts of solids or
chemicals which would otherwise be released into the downstream lines as a
result of such maintenance. This will allow THE DISTRICT to coordinate
maintenance with the action of RENTON maintenance operations. The lines so
included are as follows:
Soos Creek
Cascade) Manhole Run (Will
As-Built Include Upstream Length Diameter
Page No. Manhole) Feet) Inches) Street
PONDEROSA ESTATES
A-43 No. 104 to 207 400.0 8 Conc. 116th Ave. S.E.
A-43 No. 100 to 201 173.0 8 Conc. 118th Ave. S.E.
A-43 No. 201 to 202 96.0 8 Conc. 118th Ave. S.E.
A-43 No. 202 to 203 250.0 8 Conc. 118th Ave. S.E.
A-43 No. 203 to 204 210.0 8 Conc. S.E. 156th St.
A-43 No. 203 to 205 300.0 8 Conc. 118th Ave. S.E.
A-43 no. 205 to 206 308.0 8 Conc. 118th Ave. S.E.
a) Latecomers: None due.
b) General Facilities Charge: None due.
c) Portion of Monthly Service Charge to Cover Bond Indebtedness
4-7.04W400g.001 Page 3 of 11
E.3
S
As described in Soos Creek Water and Sewer District Resolution No.
0145C, based upon outstanding debt, the fraction of THE DISTRICT
represented by the area of concern, and the portion of the indebtedness
which is to be paid by the monthly service charges (and not by U.L.I.D.
assessments). That amount is:
Ponderosa Estates = $17,488.10
Amount calculated as follows:
Number of Connections in Ponderosa Estates: 35
Number of Connections in Sewer Area: 18,619
Debt Retirement in 1990: 1,881,554
Amount Retired by U.L.I.D. Assessments in 1990: 771,900
Amount Retired by Service Charge in 1990: 1,109,654 (Difference)
Amount Retired per Connection in 1990: 59.598
Debt Retired in Full in 2003. Remaining Years: 12
Present Value to Cover Indebtedness (6%): 35 Connections x $59.598 x
8.38384 = $17,488.10
RENTON agrees to compensate THE DISTRICT the amount of $17,488.10 as detailed
above, for this portion, within 60 days after the date of this agreement.
6. SPRINGBROOK AREA: Sale of Sewer System to RENTON. The facilities
involved are as listed below (and as shown in figure 4 and on As-built pages
referenced, Figures 5-10) and the area is as described in attached Exhibit "E".
Soos Creek Manhole Run
Cascade) Will Include Length Diameter
As-Built No. Upstream Manhole) Feet) Inches) Street
K-25 No. 80-14 to 80-15 242.0 18 Conc. SR 167
Crossing)
K-35 No. 80-15 to 34-OA 140.3 12 PVC S. 192nd St.
K-35 No. 34-OA to 34-1 25.9 12 PVC S. 192nd St.
K-35 No. 34-1 to 34-2 353.7 12 PVC S. 192nd St.
K-35 No. 34-2 to 34-3 375.0 12 PVC S. 192nd St.
K-35 No. 34-3 to 34-3A 105.5 12 PVC S. 192nd St.
K-35 No. 34-3A to 34-4 233.5 12 PVC S. 192nd St.
4-7:04OW00g•001 Page 4 of 11
I
E.3
Soos Creek Manhole Run
Cascade) Will Include Length Diameter
As-Built No. Upstream Manhole) Feet) Inches) Street
K-36 No. 34-4 to 34-5 368.0 12 PVC S. 192nd St.
K-36 No. 34-5 to 34-6 147.0 12 PVC S. 192nd St.
K-36 No. 34-6 to 34-16 399.0 8 PVC 96th Ave. S.
K-36 No. 34-16 to 34-17 249.1 8 PVC 96th Ave. S.
K-37 No. 34-6 to 34-7 400.0 8 PVC 96th Ave. S.
K-37 No. 34-6 to 34-12 403.0 12 PVC S. 192nd St.
K-37 No. 34-12 to 34 713 377.2 12 PVC S. 192nd St.
K-37 No. 34-13 to 34-14 192.9 12 DIP Easement
K-37 No. 34-14 to 34-15 288.0 12 PVC Easement
K-38 No. 34-7 to 34-8 400.0 8 PVC 97th Ave. S.
K-38 No. 34-8 to 34-9 400.0 8 PVC 97th Ave. S.
K-38 No. 34-9 to 34-10 400.0 8 PVC 97th Ave. S.
K-38 No. 34-10 to 34-11 400.0 8 PVC 97th Ave. S.
K-40 No. 34-17 to 34-26 179.0 8 PVC 96th Ave. S.
a) Latecomers (From U.L.I.D. No. 34)
Property 062205-9002 440 L.F. @ $35.89 per Lineal Foot
Property 793100-0120 170 L.F. @ $35.89 per Lineal Foot +
275.00 for Stub
Property 062205-9002 latecomer ($15,791 .60) to be collected by
RENTON and paid through to THE DISTRICT at the time of connection.
Property 793100-0120 is now RENTON property. However, it is in the
watershed" and will never be developed, and is therefore not benefitted
by the sewer. It is agreed that no payment need be made to Soos Creek
at this time. If the property is ever developed, or a facility requiring
sewers is placed on the property,then a latecomer amount of $6,376.30
shall be paid to THE DISTRICT by RENTON within 60 days after the date
of connection to the sewer.
4-7:04W400g.001 Page 5 of 11
E.3
b) General Facilities Charge
The 1991 General Facilities Charge for this basin is $0.0531 per square
foot, with a minimum of $531 .00 per unit, or customer equivalent.
Payable,at RENTON's discretion, to THE DISTRICT by RENTON, on the
schedule as listed below. THE DISTRICT shall advise RENTON of current
General Facilities Charges, and any changes to those charges as they
occur. Area is described in attached Exhibit "E", and shown in attached
Figure 4.
Tributary Area: 6,000,000 S.F. (Total area, less 25% for rights-of-
way.)
Option No. 1 -General Facilities Charge of $199,200 if paid by
June 1, 1991 .
Option No. 2 -General Facilities Charge of $258,900 if paid be-
tween June 2 and December 31, 1991 .
Option No. 3 -If payment has not been made by December 31,
1991, the current General Facility Charge must be
paid at the time of connection.
If not paid according to Option No. 1 or Option No. 2 above, RENTON
shall inform THE DISTRICT whenever an agreement is made for sewer
service in this area by RENTON, and RENTON shall pay said charges to
THE DISTRICT in accordance with Option No. 3, after the property
owner has made such payment to RENTON, as described in Section 7.
Total payment will be dependent upon when the charge is paid, the rate
at the time of connection, and the number of units developed.
c) Portion of Monthly Service Charge to Cover Bond Indebtedness
Amount for Springbrook Area: $7,994.56
Amount calculated as follows:
Number of Connections in Area: 16 (of 18,619 in Total
District)
Amount Retired by Service
Charges in 1990: 1,109,654 ($59.598 per
Connection)
4a:04W4 og.00i Page 6 of 11
E.3
Present Value of 12 Years of
Repayment: 16 Connections x $59.598 x 8.38384
7,994.56
RENTON agrees to compensate THE DISTRICT the amount of $7,994.56
as detailed above, for this portion effective the date of the agreement
and due within 60 days.
7. Notification of THE DISTRICT of New Connections, and Payment of THE
DISTRICT's General Facilities Charge. Notification shall be made by RENTON
to THE DISTRICT at the time of connection of any property in the Springbrook
Interceptor Service area. The notification shall be accompanied by a plot plan,
or letter, indicating the square footage of the property, and including payment
to THE DISTRICT of THE DISTRICT's General Facilities Charges, as described
in Section 6b, and based upon the then current rate, as reported to RENTON
by THE DISTRICT. The General Facilities Charge shall be based upon the area
of the property connected, or the number of dwelling units (or single-family
equivalents if not residential), whichever is larger; except that, unserviceable
and unusable portions of the property are not included in the calculation of the
General Facilities Charge, except for those portions which also benefit the
development of the property, such as being included in the normal setback
requirements, or landscape requirements. Included in this exempt category
are: roads and similar rights-of-way, open space required, wetlands, unusable
steep-slope areas, and the setbacks for these restrictive conditions.
8. Transfer of Easement and Right-of-Way Documents. THE DISTRICT shall
officially transfer the right-of-way documents for the facilities herein sold to
RENTON, and RENTON agrees to accept responsibility for all maintenance or
other actions required by said documents. THE DISTRICT shall not have any
liability for disputes arising over said rights-of-way or easements so transferred,
except that any disputes arising due to the actions of THE DISTRICT prior to
said transfer shall not be affected by this section.
9. Disclaimer From Third Party Liability. The DISTRICT shall disclose any and all
known defects or problems of or in the facilities herein transferred to RENTON.
THE DISTRICT shall not be liable for any claims by third parties arising from
acts or damages by RENTON or its customers in using the facilities sold to
RENTON pursuant to this Agreement.
i
4-7:040NON.001 Page 7 of 11
E.3
10. Sewer Service Area Boundary Between RENTON and THE DISTRICT. With the
above transfer (sale) of existing facilities and service area, and reasonable
service area limits corresponding to this action, the line separating the RENTON
service area from THE DISTRICT service area for sanitary sewers is described
in attached Exhibit "F", and is shown in attached Figure 11 . RENTON shall
provide ultimate service for the area north and west of the line shown. THE
DISTRICT shall provide ultimate service for the area south and east of the line
shown.
11 . Maintenance of Existing Facilities. THE DISTRICT and RENTON will each
provide maintenance for its own facilities. If there are any serious problems
due to a discharge which can be identified, and for which the source can be
identified, the individual or company responsible will be held liable for damage.
If a lack of maintenance, or if the type of maintenance by either RENTON or
THE DISTRICT is identified as the source of said problem, then the party
creating, or allowing, the situation shall be responsible and shall pay the costs
of repair. In case of dispute over the source or responsibility of said problems,
the Municipality of Metropolitan Seattle (Metro) shall serve as arbitrator in
identifying and quantifying said problems provided that said arbitration and/or
any reports generated by an investigation by Metro, shall be binding upon both
parties in resolution of the dispute.
12. Allowable Capacities in the Lines being Transferred, and at Points Further
Downstream. There are no restrictions on the capacity of the sewers from
Ponderosa Estates as long as they are consistent with the current use of the
properties. There are currently 35 single family residences, and the property
is fully developed. If this condition ever changes, a further review of the
capacity of the system shall be performed, and an additional agreement shall
be developed between the parties.
Capacity for the system in the Springbrook drainage basin shall be as follows:
AT TIMES OF SIMULTANEOUS PEAK FLOW
SOOS CITY OF RESERVED
CREEK RENTON FOR CITY OF
gpm) gpm) KENT (gpm)
S. 192nd Street, at and below 1500 600 0
M H 34-3
4-7.04W400g.001 Page 8 of 11
E.3
S. 192nd Street, at and below 1800 1500 0
MH 34-OA
S. 192nd Street, at and below 3900 1500 0
MH 80-14
West of MH 80-14 3900 1500 400
No connections, by either party, will be allowed between Manhole 34-OA and Manhole
80-15 except by mutual agreement.
Both parties agree that either may exceed this amount at the non-peak times,
as long as there are no negative impacts, and the combined capacity of the
system is not exceeded, and prior notification is given to the other party. It
shall be the responsibility of each part to monitor its flow as and when
necessary to determine what the flow rate characteristics of the system are.
If the combined capacity of the system is exceeded, the party exceeding its
allowable rate shall have the option of making revisions within its own system
to bring its flows into compliance with this Section, or of paying for improve-
ments to either system which will increase the available capacity of the
systems. If both parties exceed their allowable rate, the cost of any new
facilities will be divided based upon the ratio of the percentage by which each
party is exceeding its allowable rate. If the allowable rate is exceeded at only
one location, the ratio at that location will be used. If the rate is exceeded at
more than one location, the ratio will be based upon the furthest east point at
which the allowable rates are being exceeded. If a regular surcharge condition
exists that is not due to a blockage problem, a previously agreed upon
temporary situation such as re-routing for construction, or by either party
exceeding its capacity, the DISTRICT shall have the option of making revision
within its own system to bring its flows into compliance with this section, or
of paying for improvements to either system which will resolve the surcharge
condition. Both parties acknowledge and agree that the City of Kent is not a
party to this agreement, and the amount referenced for the City of Kent is for
reference only and could be the basis for a separate agreement in the future
involving THE DISTRICT and the City of Kent, and involving RENTON if their
rate allowance is at all to be affected.
13. Connection of THE DISTRICT to RENTON Facilities. or RENTON to THE
DISTRICT Facilities. Connection of facilities of either RENTON or THE
DISTRICT to facilities of the other, or to facilities tributary to facilities of the
other, shall be coordinated by both parties to assure:
a) Payment of appropriate charges,
b) up-to-date accounting of connections,
c) potential sources of debris, or construction damage, are identified, and
4-7:04W4Wg.001 Page 9 of 11
E.3
d) inspection of connection construction can be scheduled.
RENTON and THE DISTRICT shall each be responsible for maintenance of their
own facilities, except as described in Section 11 above. Should damage of the
facilities of one be traceable to a source within the jurisdiction of the other,
RENTON and THE DISTRICT agree to assist each other in whatever action is
necessary to identify, prosecute, fine, collect from, or otherwise deal with the
responsible party.
14. Future Annexations to RENTON. The service areas listed in sections 1-7 of this
AGREEMENT are the only areas of cross-service agreed to at this time.
RENTON shall serve all other areas within RENTON without challenge by THE
DISTRICT, based upon the City limits at the date of the agreement. THE
DISTRICT shall serve all areas within THE DISTRICT's limits at the time of this
agreement, except as previously detailed. Future annexation to RENTON shall
not limit THE DISTRICT providing water or sewer service to those areas within
THE DISTRICT limits to the standards of THE DISTRICT, even if there is
conflict with RENTON standards, unless this is altered by future agreements.
Future agreements may occur between RENTON and THE DISTRICT transfer-
ring additional, or future, services areas and/or facilities by mutual agreement.
15. DISTRICT Comprehensive Water and Sewer Planning. THE DISTRICT will
submit the current and all future Comprehensive Water and/or Sewerage Plans
and amendments thereto involving area and/or improvements within RENTON
City Limits. The Comprehensive Water and/or Sewerage Plans and amend-
ments shall be in compliance with RENTON requirements for service within
RENTON, except where existing facilities may differ from RENTON require-
ments. No replacement or augmenting of the system shall be required at this
time. As new facilities are planned and constructed within RENTON, they shall
comply with RENTON technical standards then in effect.
16. Extensions of Utilities Across Properties. RENTON and THE DISTRICT agree
that they will require property owners who m ust extend facilities to serve their
property to extend said facilities to the far side of the property to provide a
connection point for the future (or existing) facilities of the next property.
17. Recording of Agreement with King County. THE DISTRICT is hereby authorized
to record a copy of a resolution in which a copy of this Agreement is
incorporated with the office of the Auditor of King County, Washington, for the
purposes of giving notice to all present and future owners of the real property
described in Exhibit "E" that their properties are subject to the connection
charges specified herein.
4-7:04ON00g.001 Page 10 of 11
E.3
18. Submittal of Agreement to the Boundary Review Board. THE DISTRICT is
hereby authorized to prepare a submittal to the Washington State Boundary
Review Board for King County. THE DISTRICT and RENTON agree to be
coproponents of the submittal, and to provide any support requested or
required by King County or the Boundary Review Board in the review and
approval process. RENTON agrees to pay THE DISTRICT for one-half of all
costs involved in the submittal, review and approval process, to a maximum of
3,000 (50 percent of $6,000 estimated total expenses).
19. Sanctity of Agreement. This agreement constitutes the entire agreement of the
parties, and there are no representations or oral agreements other than those
listed herein, which vary the terms of this agreement. Future agreements may
occur between the parties to transfer additional, or future, service areas and/or
facilities by mutual agreement.
20. Obligations Intact. Nothing herein shall be construed to alter the rights,
responsibilities, liabilities, or obligations of either THE DISTRICT or RENTON
regarding provisions of water or sewer services to the properties described
herein, or other properties, except as specifically set forth herein.
DATED this Aday of A;4-A 19&-
Approved by Ordinance No. of the City Council of the City of RENTON,
Washington, at its regular meeting held on day of 19_.
CIT.OE RENTON
By:
Title: Mayor
ATTEST:
Ci erk
0666-S
Y
Approved by Resolution No. / of the Board of Commissioners of SHOOS CREEK
WATER AND SEWER DISTRICT of King County, Washington, adopted at its regular
meeting held on 18th day of *
jkZzS I
Bi.l , Presi d t
Title: Board of Commissioners
4-7:0400400g.001 Page 11 of 11
I
i
E.3
t l
EXHIBIT "A"
SOOS CREEK WATER & SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES AND FOR
y THE ESTABLISHMENT OF SERVICE BOUNDARIES
PROPERTIES WITHIN CITY LIMITS TO RECEIVE WATER SERVICE FROM DISTRICT)
May 23, 1991
a) The Easterly half of the Southeast quarter of Section 31, Township 23 North,
Range 5 East, W.M., less the Westerly 1,003.00 feet thereof.
b) Beginning at the Southwest corner of the Northwest quarter of Section 32,
Township 23 North, Range 5 East, W.M.;
Thence Northeasterly to a point 600.00 feet North and 550.00 feet East of said
Southwest corner;
Thence Northerly along a line parallel with and 550.00 feet East of the West
line of said Northwest quarter to a point 900.00 feet North and 550.00 feet
East of said Southwest corner;
Thence Northwesterly to a point on said West line of the Northwest quarter of
said Section 32, 1,200.00 feet North of the Southwest corner of said
Northwest quarter;
Thence Northerly along said West line to the Northerly right-of-way margin of
Carr Road;
Thence Easterly and Northeasterly along said Northerly right-of-way margin to
the East line of the West half of the Northwest quarter of said Section 32;
Thence Southerly along said East line to the South line of said Northwest
quarter;
Thence Westerly along said South line to the Southwest corner of said
Northwest quarter and the Point of Beginning.
c) Beginning at a point on the East line of the Southwest quarter of the Northwest
quarter of Section 29, Township 23 North, Range 5 East, W.M., 100.00 feet
South of the Northeast corner of said Southwest quarter;
Thence Westerly along the South line of the North 100.00 feet of said
Southwest quarter to the West line of the East 100.00 feet of the West half
of the Northwest quarter of said Section 29,
4-7:0400400G.007 1 of 4
E.3
EXHIBIT "A", Continued
M1
May 23, 1991)
Thence Northerly along said West line to the North line of the South 100.00
feet of the North half of the Northwest quarter of said Section 29;
Thence Easterly along said North line to its intersection with the Westerly
margin line of Benson Road;
Thence Southerly along said West margin line to its intersection with the South
line of the North half of the Northwest quarter of said Section 29;
Thence Easterly along said South line to its intersection with the Easterly
margin line of Benson Road;
Thence Northerly along said East margin line to the South line of the following
described parcel;
Beginning at a point located North 01'42'40" East, a distance of 749.65
feet and North 88 017'20" West, a distance of 191 .67 feet, more or less,
from a point on the centerline of South 27th Street (S.E. 164th Street)
255.00 feet East of the Easterly margin line of Benson Road;
Thence South 88°17'20" East, a distance of 191 .67 feet, more or less,
to a point located North 01°42'40" East, a distance of 749.65 feet,
more or less, from said point on the centerline of said South 27th Street;
Thence South 01042'40" West to a line parallel with and 400.00 feet
North of the South line of the Northeast quarter of the Northwest quarter
of said Section 29;
Thence West along said parallel line to the Easterly margin of Benson
Road;
Thence Northerly along said Easterly margin to the Point of Beginning of
this parcel's description;
Thence Easterly along said South line of the above-described parcel to the East
line of said parcel;
Thence Northerly along said East line of said parcel to a line parallel with and
700 feet, more or less, North of the South line of the Northeast quarter of the
Northwest quarter of said Section 29;
Thence Easterly along said parallel line to the North-South centerline of said
Section 29;
4-7:0400400G.007 2 of 4
E.3
EXHIBIT "A", Continued
May 23, 1991)
Thence Southerly along said North-South centerline to the centerline of South
27th Street (S.E. 164th Street);
Thence Wester) along said centerline to the Norther) extension of the EastY9Y
margin of 106th Place S.E.;
Thence Southeasterly along said East margin, its Northerly extension, and its
Southerly extension to the North margin of South 29th Street (S.E. 166th
Street);
Thence Easterly along said North margin and its Easterly extension to the East
margin of Kennewick Avenue S.E. (109th Avenue S.E.)
Thence Southerly along said East margin, and its Southerly extension to the
South Line of the Northeast quarter of said Section 29;
Thence Westerly along said South line to the Westerly margin of said Benson
Road;
Thence Northerly and Northwesterly along said Westerly margin to the North
line of the Southeast quarter of said Northwest quarter of said Section 29;
Thence Westerly along said North line to the West line of said Southeast
quarter, also being the East line of the Southwest quarter of the Northwest
quarter of said Section 29;
Thence Southerly along said East line 100.00 feet to the Point of Beginning.
d) Beginning at a point on the South line of the Southeast quarter of Section 20,
Township 23 North, Range 5 East, W.M., 930.00 feet West of the Southeast
corner of said Southeast quarter;
Thence Northerly along the West line of the East 930.00 feet of said Southeast
quarter to the North line of the South 200.00 feet of said Southeast quarter;
Thence Easterly along said North line to the West line of the East 670.00 feet
of said Southeast quarter;
Thence North 01 050'38" East, a distance of 105.01 feet, more or less, to the
North line of the South 305.00 feet of said Southeast quarter;
Thence South 88,46'15" East along said North line to the West line of the East
330.00 feet of said Southeast quarter;
4-7:0400400G.007 3 of 4
E.3
w
EXHIBIT "A", Continued
May 23, 1991)
Thence Northerly along said West line to the South line of the plat of Parkwood
South Division No. 3, as recorded in Volume 109 of Plats, pages 57 and 58,
records of King County, Washington;
Thence Easterly along said South line and its Easterly extension to the East line
of said Southeast quarter of Section 20;
Thence Southerly along said East line to said Southeast corner of said
Southeast quarter of Section 20;
Thence West along the South line of said Southeast quarter, a distance of
930.00 feet to the Point of Beginning.
4-7:0400400G.007 4 of 4
E.3
EXHIBIT "B"
SOOS CREEK WATER & SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES AND FOR
ESTABLISHMENT OF SERVICE BOUNDARIES
PROPERTIES WITHIN DISTRICT BOUNDARIES TO
RECEIVE WATER SERVICE FROM CITY OF RENTON)
May 23, 1991
a) The plat of Ponderosa Estates, Volume 70 of lots, pages 34 and 35, records
of King County, Washington.
b) The East 330.00 feet of the Southeast quarter of Section 20, Township 23
North, Range 5 East, W.M., less the South 345.00 feet thereof, more or less.
c) Beginning at the intersection of the West line of the Northwest quarter of the
Northeast quarter of Section 29, Township 23 North, Range 5 East, W.M., and
Westerly extension of the South margin of S.E. 160th Street;
Thence Easterly along said Westerly extension and said South margin to the
centerline of the Bonneville Power Line right-of-way;
Thence Southeasterly along said centerline to the Westerly extension of the
South margin of S.E. 162nd Street;
Thence Easterly along said extension and said South margin to the West line
of the East 330.00 feet of said Northwest quarter;
Thence North along said West line to the North line of said Northwest quarter;
Thence West along said North line to the Northwest corner of said Northwest
quarter;
Thence South along West line of said Northwest quarter to the point of
Beginning.
d) Beginning at the intersection of the South line of the Northeast quarter of the
Northwest quarter of Section 29, Township 23 North, Range 5 East, W.M., and
the Easterly margin of Benson Road;
4-7:04004008.004 Page 1 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence Northerly along said East margin line to a point located North
01'42'40" East, a distance of 749.65 feet and North 88 017'20" West, a
distance of 191 .67 feet, more or less, from a point on the centerline of South
27th Street (S.E. 164th Street) 255.00 feet East of the Easterly margin line of
Benson Road;
Thence South 88°17'20" East, a distance of 191 .67 feet, more or less, to a
point located North 01042'40" East, a distance of 749.65 feet, more or less,
from said point on the centerline of said South 27th Street;
Thence South 01 042'40" West, a distance of 749.65 feet, more or less, to said
point on the centerline of said South 27th Street, also being said South line of
the Northeast quarter of the Northwest quarter of said Section 29;
Thence Westerly along said South line to the Point of Beginning;
LESS the Southerly 400.00 feet thereof.
e) The West half of Lot 3, Block 2, of the Plat of Aker's Farms No. 5, recorded in
Volume 40 of Plats, page 27, records of King County, Washington.
f)The East 150.00 feet of the Southeast quarter of the Southwest quarter of the
Northwest quarter of Section 29, Township 23 North, Range 5 East, W.M.
g) Beginning at a point described as the intersection of the South margin line of
South 192nd Street, also described as a line parallel with and 30.00 feet South
of the North line of the Northwest quarter of Section 6, Township 22 North,
Range 5 East, W.M., in King County, Washington, with the Easterly right-of-
way margin of Primary State Highway No. 5 (State Route No. 167);
Thence Easterly along said parallel line to the North-South centerline of said
Section 6;
Thence Southerly along said centerline to the Northwest corner of Tract 1,
Spring Brook Acre Tracts, as recorded in Volume 12 of Plats, page 60, records
of King County, Washington;
Thence Easterly, Northerly, and Easterly along the North line of said Tract 1 to
the Westerly margin of 96th Avenue South , also known as John Langston
Road or Springbrook Road;
4-7:04004008.004 Page 2 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence Southerly along said Westerly margin, a distance of 320 feet± to the
Westerly extension of the most Northerly line of Tract 8, of said plat of Spring
Brook Acre Tracts;
Thence South 74 050'00" East along said extension to the Easterly margin of
said 96th Avenue Southeast and continuing South 74 050'00" East along said
most Northerly line, a distance of 189.00 feet;
Thence South 00°44'00" East, a distance of 188.40 feet;
Thence South 58 038'00" East, a distance of 89.35 feet along the line common
to Tracts 8 and 9, said plat of Spring Brook Acre Tracts;
i
Thence North 41022'00" East, a distance of 128.10 feet;
Thence South 64°22'00" East, a distance of 275.60 feet;
Thence South 16°58'00" West, a distance of 239.80 feet;
Thence South 31°43'00" East, a distance of 210.90 feet;
Thence South 68'25'00" East a distance of 99.50 feet;
Thence South 60 035'30" East, a distance of 28.17 feet to the most Northerly
corner of Tract 7, said plat of Spring Brook Acre Tracts;
Thence South 00 012'30" East, a distance of 396.04 feet;
Thence South 39°31'00" East, a distance of 383.85 feet;
Thence North 89 032'00" East, a distance of 340.00 feet to the East line of the
Northeast quarter of said Section 6, said East line also being the West line of
Section 5, Township 22 North, Range 5 East, W.M.;
Thence North along a line common to said Sections 5 and 6, a distance of
21 .50 feet to a point that lies North 00° 12'30" West, a distance of 241 .50
feet from the Southwest corner of the Southwest quarter of the Northwest
quarter of said Section 5;
Thence North 40 041'00" East, a distance of 230.30 feet;
4-7:04004008.004 Page 3 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence South 84°12'00" East, a distance of 245.90 feet;
Thence South 34 026'00" East, a distance of 147.30 feet;
Thence South 14°49'00" East, a distance of 257.44 feet to a line 30.00 feet
North of, as measured at right angles from, and lying parallel with, the South
line of the Northwest quarter of said Section 5:
Thence Easterly along said parallel line to the West line of the East one-half of
the Southwest quarter of the Northwest quarter of said Section 5;
Thence North 00 031'17" East along said West line, a distance of 190.00 feet;
Thence South 88 038'33" East, to the East line of the West 115.00 feet of the
East half of said Southwest quarter of the Northwest quarter;
Thence South 00°31'17" West along said East line, a distance of 190.00 feet
to the North margin of said Southeast 200th Street;
Thence South 88°38'33" East along said North margin, a distance of 377.82
feet to the West line of the East 156.00 feet of said Southwest quarter of the
Northwest quarter;
Thence North 00°39'11 " West along said West line, also being the West line
of the plat of Parkridge East 1, as recorded in Volume 132 of Plats, pages 45
and 46, records of King County, Washington, a distance of 918.18 feet to the
South line of Lot 2, Short Plat No. R877058, recorded under Auditor's File
No.'s 7803010983 and 7808100855, records of King County, Washington;
Thence North 89 020'49" West, a distance of 59.00 feet;
Thence South 85°17'46" West, a distance of 80.31 feet;
Thence North 89 024'30" West, a distance of 96.01 feet;
Thence North 05°09'11" West, a distance of 111 .45 feet;
Thence North 53 049'07" East, a distance of 198.22 feet;
i
4-7:0400400g.004 Page 4 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence South 48 037'32" East, a distance of 118.20 feet to the Northeast
corner of said Lot 2;
Thence North 69 021'46" East, a distance of 165.28 feet to the East line of the
Southwest quarter of the Northwest quarter of said Section 5;
Thence North 00039'111" East along said East line, a distance of 147.85 feet
to the North line of said Southwest quarter;
Thence Westerly along said North line to the West line of said Section 5, also
being the East line of said Tract 9, of said plat of Spring Brook Acre Tracts;
Thence Northerly along said East line to a point that lies 271 .50 feet South, as
measured along said East line from the Northeast corner of said Tract 9;
Thence North 78 021'42" West, a distance of 336.34 feet;
Thence North 26 009'56" West, a distance of 106.78 feet;
Thence North 83 020'02" West, a distance of 289.79 feet;
Thence North 70°34'46" West to an intersection with the Southerly extension
of the West line of the plat of Springbrook Terrace, as recorded in Volume 131
of Plats, pages 55 through 58 as amended, records of King County, Washing-
ton;
Thence Northerly along said Southerly extension to the Southwest corner of
said plat of Springbrook Terrace;
Thence North 86 000'00" West a distance of 509.65 feet to the East line of the
old right-of-way margin of 96th Avenue South, as established October 5, 1931;
also known as John Langston Road or Springbrook Road)
Thence Northwesterly and Northerly along said Easterly right-of-way margin to
the South line of the North 425 feet of the Northwest quarter of the Northeast
quarter of the Northeast quarter of said Section 6;
Thence South 88 027'05" East to the West line of said plat of Springbrook
Terrace;
4-7:04004008.004 Page 5 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence Northerly along said West line and its Northerly extension to the North
line of said Section 6, also being the South line of Section 31, Township 23
North, Range 5 East, W.M.;
Thence Easterly along said South line to the East line of the West 1,003.00
feetet hothe Southeast quarter of the Southeast quarter of Section 31, Township
23 North, Range 5 East, W.M.;
Thence Northerly along said East line to the North line of the Southeast quarter
of said Section 31;
Thence Easterly along said North line to the East quarter corner of said Section
31, of said East quarter corner also being the Southwest corner of the
Northwest quarter of Section 32, Township 23 North, Range 5 East;
Thence Northeasterly to a point 600.00 feet North and 550.00 feet East of said
Southwest corner;
Thence Northerly along a line parallel with and 550.00 feet East of the West
line of said Northwest quarter to a point 900.00 feet North and 550.00 feet
East of said Southwest corner;
Thence Northwesterly to a point on said West line of the Northwest quarter of
said Section 32, 1,200.00 feet North of the said Southwest corner;
Thence Northerly along said West line of said Northwest quarter, and the West
line of Section 29, Township 23 North, Range 5 East, W.M., to the North line
of the South half of the Southwest quarter of the Southwest quarter of said
Section 29;
Thence Easterly along said North line a distance of 802 feet, more or less, to
the Southerly extension of the West line of Lot 4 of King County Short Plat No.
577051, Recording No. 7902080736;
Thence North 01 052'36" East along said Southerly extension and the West line
of the said Lot 4 to the Northwest corner thereof;
Thence Easterly along the North line of said Lot 4 and its Easterly extension,
also being the North line of the South half of the North half of the Northwest
quarter of the Southwest quarter of said Section 29, to the East margin of
State Route 515 right-of-way;
4-7:04004008.004 Page 6 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence Northerly along said East margin to the North line of the Southwest
quarter of said Section 29;
Thence Westerly along said North line to the West line of said Section 29, said
line also being the East line of Section 30, Township 23 North, Range 5 East,
W.M.;
Thence Southerly along said East line to the South line of the North 100.00
feet of the Southeast quarter of said Section 30;
Thence Westerly along said South line to the West line of the East 750.00 feet
of said Southeast quarter;
Thence Southerly along said West line to the South line of the North half of the
North half of the Northeast quarter of said Southeast quarter of said Section
30;
Thence Westerly along said South line to the Westerly margin line of 96th
Avenue South, also known as Talbot Road or Springbrook Road;
Thence Southerly along said Westerly margin line to the South line of the
Northeast quarter of the Southeast quarter of said Section 30;
Thence Easterly along said South line to the centerline of said 96th Avenue
South;
Thence Southerly along said centerline to the South line of said Section 30,
said line also being the North line of Section 31, Township 23 North, Range 5
East, W.M.;
Thence continuing Southerly along said centerline of 96th Avenue South to the
South right-of-way line of South Carr Road, said right-of-way being 80.00 feet
in width;
Thence Northeasterly along said South right-of-way line of South Carr Road to
the North line of the Southeast quarter of the Northeast quarter of said Section
31;
4-7:04004008.004 Page 7 of 8
E.3
EXHIBIT "B", Continued
May 23, 1991)
Thence Easterly along said North line to the West line of the East half of the
East half of said Northeast quarter of Section 31;
Thence Southerly along said West line to the North line of the South half of the
South half of said Northeast quarter;
Thence Westerly along said North line to said centerline of 96th Avenue South;
Thence Southerly along said centerline to the South line of the North 133.00
feet of the South half of the South half of said Northeast quarter of said
Section 31;
Thence Westerly along said South line to the West line of the East 265.00 feet
of the West half of the Northeast quarter of said Section 31;
Thence Northerly along said West line to the North line of the South half of the
South half of the Northeast quarter of said Section 31;
Thence Westerly along said North line to the West line of the East half of the
Northeast quarter of the Southwest quarter of the Northeast quarter of said
Section 31;
Thence Northerly along said West line and continuing along its Northerly
extension to the North margin line of South 180th Street (also known as South
43rd Street);
Thence Westerly along said North margin line to the East margin line of P.S.H.
No. 5 (State Highway No. 167);
Thence Southerly along said East margin line to the South line of said Section
31, said line also being the North line of Section 6, Township 22 North, Range
5 East, W.M., and continuing Southerly along said East margin line to the Point
of Beginning on the South margin line of South 192nd Street and a terminus
of this boundary description.
4-7:0400400g.004 Page 8 of 8
E.3
EXHIBIT "C"
SOOS CREEK WATER & SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES AND FOR
ESTABLISHMENT OF SERVICE BOUNDARIES
WATER SERVICE BOUNDARY LINE)
May 23, 1991
Beginning at a point described as the intersection of a line parallel with and
180.00 feet South of the North line of the Northwest quarter of Section 6,
Township 22 North, Range 5 East, W.M., in King County, Washington, with
the Easterly right-of-way margin of Primary State Highway No. 5 (State Route
No. 167);
Thence Easterly along said parallel line to the North-South centerline of said
Section 6;
Thence Southerly along said centerline to the Northwest corner of Tract 1,
Spring Brook Acre Tracts, as recorded in Volume 12 of Plats, page 60, records
of King County, Washington;
Thence Easterly, Northerly, and Easterly along the North line of said Tract 1 to
the Westerly margin of 96th Avenue South, also known as John Langston Road
or Springbrook Road;
Thence Southerly along said Westerly margin, a distance of 320 feet ± to the
Westerly extension of the most Northerly line of Tract 8, of said plat of Spring
Brook Acre Tracts;
Thence South 74°50'00" East along said extension to the Easterly margin of
said 96th Avenue Southeast and continuing South 74°50'00" East along said
most Northerly line, a distance of 189.00 feet;
Thence South 00°44'00" East, a distance of 188.40 feet;
Thence South 58°38'00" East, a distance of 89.35 feet along the line common
to Tracts 8 and 9, of said plat of Spring Brook Acre Tracts;
Thence North 41'22'00" East, a distance of 128.10 feet;
Thence South 64 022'00" East, a distance of 275.60 feet;
4-7:04004008.005 Page 1 of 8
E.3
EXHIBIT "C", Continued
May 23, 1991)
Thence South 16°58'00" West, a distance of 239.80 feet;
Thence South 31'43'00" East, a distance of 210.90 feet;
Thence South 68°25'00" East, a distance of 99.50 feet;
Thence South 60°35'30" East, a distance of 28.17 feet to the most Northerly
corner of Tract 7, of said plat of Springbrook Acre Tracts;
Thence South 00°12'30" East, a distance of 396.04 feet;
Thence South 39°31'00" East, a distance of 383.85 feet;
Thence North 2 E distance f 4 f E line f he89300East, a d sta ce o 3 0 00 feet to the East e o the
Northeast quarter of said Section 6, said East line also being the West line of
Section 5, Township 22 North, Range 5 East, W.M.;
Thence North along a line common to said Sections 5 and 6, a distance of
21 .50 feet to a point that lies North 00° 12'30" West, a distance of 241 .50
feet from the Southwest corner of the Southwest quarter of the Northwest
quarter of said Section 5;
Thence North 40 041'00" East, a distance of 230.30 feet;
Thence South 84°12'00" East, a distance of 245.90 feet;
Thence South 34°26'00" East, a distance of 147.30 feet;
Thence South 14 049'00" East, a distance of 257.44 feet to a line 30.00 feet
North of, as measured at right angles from, and lying parallel with, the South
line of the Northwest quarter of said Section 5:
Thence Easterly along said parallel line to the West line of the East one-half of
the Southwest quarter of the Northwest quarter of said Section 5;
Thence North 00°31'17" East along said West line, a distance of 190.00 feet;
Thence South 88°38'33" East, to the East line of the West 115.00 feet of the
East half of said Southwest quarter of the Northwest quarter;
4-7:04004008.005 Page 2 of 8
E.3
EXHIBIT "C", Continued
May 23, 1991)
Thence South 00 031'17" West along said East line, a distance of 190.00 feet
to the North margin of said Southeast 200th Street;
Thence South 88°38'33" East along said North margin, a distance of 377.82
feet to the West line of the East 156.00 feet of said Southwest quarter of the
Northwest quarter;
Thence North 00039'111" West along said West line, also being the West line
of the plat of Parkridge East 1, as recorded in Volume 132 of Plats, pages 45
and 46, records of King County, Washington, a distance of 918.18 feet to the
South line of Lot 2, Short Plat No. R877058, recorded under Auditor's File
No.'s 7803010983 and 7808100855, records of King County, Washington;
Thence North 89 020'49" West, a distance of 59.00 feet;
Thence South 85°17'46" West, a distance of 80.31 feet;
Thence North 89°24'30" West, a distance of 96.01 feet;
Thence North 05009'111 West, a distance of 111 .45 feet;
Thence North 53 049'07" East, a distance of 198.22 feet;
Thence South 48 037'32" East, a distance of 118.20 feet to the Northeast
corner of said Lot 2;
Thence North 69 021'46" East, a distance of 165.28 feet to the East line of the
Southwest quarter of the Northwest quarter of said Section 5;
Thence North 00°39'11 " East along said East line, a distance of 147.85 feet
to the North line of said Southwest quarter;
Thence Westerly along said North line to the West line of said Section 5, also
being the East line of said Tract 9, of said plat of Spring Brook Acre Tracts;
Thence Northerly along said East line to a point that lies 271 .50 feet South, as
measured along said East line the from Northeast corner of said Tract 9;
Thence North 78°21'42" West, a distance of 336.34 feet;
4-7:04004008.005 Page 3 of 8
E.3
0
EXHIBIT "C", Continued
May 23, 1991)
Thence North 26 009'56" West, a distance of 106.78 feet;
Thence North 83°20'02" West, a distance of 289.79 feet;
Thence North 70 034'46" West to an intersection with the Southerly extension
of the West line of the plat of Springbrook Terrace, as recorded in Volume 131
of Plats, pages 55 through 58, as amended, records of King County,
Washington;
Thence Northerly along said Southerly extension to the Southwest corner of
said plat of Springbrook Terrace;
Thence North 86 000'00" West, a distance of 509.65 feet to the East line of
the old right-of-way margin of 96th Avenue South, also known as John
Langston Road or Springbrook Road;
Thence Northwesterly and Northerly along said Easterly right-of-way margin to
the South line of the North 425 feet of the Northwest quarter of the Northeast
quarter of the Northeast quarter of said Section 6;
Thence South 88°27'05" East to the West line of said plat of Springbrook
Terrace;
Thence Northerly along said West line and its Northerly extension to the North
line of said Section 6, also being the South line of Section 31, Township 23
North, Range 5 East, W.M.;
Thence Easterly along said South line to the East quarter corner of said Section
31, said East quarter corner also being the Southwest corner of the Northwest
quarter of Section 32, Township 23 North, Range 5 East;
Thence Northeasterly to a point 600.00 feet North and 550.00 feet East of said
Southwest corner;
Thence Northerly along a line parallel with and 550.00 feet East of the West
line of said Northwest quarter to a point 900.00 feet North and 550.00 feet
East of said Southwest corner;
Thence Northwesterly to a point on said West line of the Northwest quarter of
said Section 32, a distance of 1,200.00 feet North of the said Southwest
corner;
4-7:04004008.005 Page 4 of 8
E.3
EXHIBIT "C", Continued
May 23, 1991)
Thence Northerly along said West line of said Northwest quarter, and the West
line of Section 29, Township 23 North, Range 5 East, W.M., to the North line
of the South half of the Southwest quarter of the Southwest quarter of said
Section 29;
Thence Easterly along said North line, a distance of 802 feet, more or less to
the Southerly extension of the West line of the Lot 4 of King County Short Plat
No. 577051, Recording No. 790280736;
Thence North 01 05236" East along said southerly extension and the West line
of said Lot 4 to the Northwest corner thereof;
Thence Easterly along the North line of said Lot 4 and its Easterly extension,
also. being the North line of the South half of the North half of the Northwest
quarter of said Section 29, to the East margin of State Route 515 right-of-way;
Thence Northerly along said East margin to the North line of the Southwest
quarter of said Section 29;
Thence Easterly along said North line to the centerline of Cedar Avenue South
104th Avenue S.E.), said centerline also being the East line of the Southwest
quarter of the Northwest quarter of said Section 29;
Thence Northerly along said East line to the Westerly extension of the South
line of Lot 2 of City of Renton Short Plat No. 071-85;
Thence Easterly along the South line and said Westerly extension to the East
line of said lot;
Thence Northerly along said East line to the Northeast corner of said lot;
Thence continuing Northerly along the East line of Lot 1 of said Short Plat to
the Northeast corner of said Lot 1;
Thence Westerly along the North line of said lot and the Westerly extension
thereof to said East line of the Southwest quarter of the Northwest quarter of
said Section 29;
Thence Northerly along said East line to the South line of the North 100.00
feet of the Southwest quarter of the Northwest quarter of said Section 29;
4-7:04004008.005 Page 5 of 8
E.3
EXHIBIT "C", Continued
May 23, 1991)
Thence Westerly along said South line to the West line of the East 100.00 feet
of the West half of the Northwest quarter of said Section 29;
Thence Northerly along said West line to the North line of the South 100.00
feet of the North half of the Northwest quarter of said Section 29;
Thence Easterly along said North line to its intersection with the Westerly
margin line of Benson Road;
Thence Southerly along said West margin line to its intersection with the South
line of the North half of the Northwest quarter of said Section 29;
Thence Easterly along said South line to its intersection with the Easterly
margin line of Benson Road;
Thence Northerly along said East margin line to the South line of the following
described parcel:
Beginning at a point located North 01°42'40" East, a distance of 749.65
feet and North 88°17'20" West, a distance of 191 .67 feet, more or less,
from a point on the centerline of South 27th Street (S.E. 164th Street),
a distance of 255.00 feet East of the Easterly margin line of Benson
Road;
Thence South 88°17'20" East, a distance of 191 .67 feet, more or less,
to a point located North 01'42'40" East, a distance of 749.65 feet,
more or less, from said point on the centerline of said South 27th Street;
Thence South 01'42'40" West, to a line parallel with and 400.00 feet
North of the South line of the Northeast quarter of the Northwest quarter
of said Section 29;
Thence West along said parallel line to the Easterly margin of Benson
Road;
Thence Northerly along said Easterly margin to the Point of Beginning of
this parcel's description;
Thence Easterly along said South line of the above-described parcel to the East
line of said parcel;
4-7:0400400g.005 Page 6 of 8
E.3
EXHIBIT "C", Continued
May 23, 1991)
Thence Northerly along said East line of said parcel to a line parallel with and
700 feet, more or less, North of the South line of the Northeast quarter of the
Northwest quarter of said Section 29;
Thence Easterly along said parallel line to the North-South centerline of said
Section 29;
Thence Northerly along said North-South centerline to the South margin of S.E.
160th Street (BOW LAKE PIPELINE - CITY OF SEATTLE WATER DEPART-
MENT);
Thence Easterly along said South margin to the centerline of the Bonneville
Power Line right-of-way;
Thence Southeasterly along said right-of-way centerline to the Westerly
extension of the South margin of S.E. 162nd Street;
Thence Easterly along said extension and said South margin to the Southerly
extension of the West line of the East 330.00 feet of the Northwest quarter of
the Northeast quarter of said Section 29;
Thence North along said West line to the North line of the Northeast quarter of
said Section 29, also being the South line of Section 20, Township 23 North,
Range 5 East, W.M.;
Thence Easterly along said South line of said Section 20 to the West line of the
East 930.00 feet of the Southeast quarter of said Section 20;
Thence Northerly along said West line to the North line of the South 200.00
feet of said Southeast quarter;
Thence Easterly along said North line to the West line of the East 670.00 feet
of said Southeast quarter;
Thence North 01050'38" East, a distance of 105.01 feet to the North line of
the South 305 feet, more or less, of said Southeast quarter;
Thence South 88°46'15" East along said North line to the West line of the East
330.00 feet of said Southeast quarter;
4-7:04004008.005 Page 7 of 8
E.3
EXHIBIT "C", Continued
May 23, 1991)
Thence Northerly along said West line to the South line of the Plat of Parkwood
South Division No. 3, as recorded in Volume 109 of Plats, pages 57 and 58,
records of King County, Washington;
Thence Easterly along said South line to the East line of said Section 20, also
being the West line of Section 21, Township 23 North, Range 5 East, W.M.;
Thence Northerly along said West line to the Westerly extension of the South
line of the plat of Ponderosa Estates Addition, as recorded in Volume 70 of
Plats, pages 34 and 35, records of King County, Washington;
Thence Easterly along said extension and said South line to the Southerly
margin of the Cedar River Pipeline right-of-way;
Thence Southeasterly and Easterly along said Southerly right-of-way margin to
the West line of the East half of the Southeast quarter of said Section 21;
Thence Northerly along said West line to the North line of the Southeast quarter
of the Southeast quarter of said Section 21;
Thence Easterly along said North line to the East line of said Section 21, said
point being on the City of Renton City Limits as established by City Ordinance
3723, and the terminus of this boundary description.
4-7:04004008.005 Page 8 of 8
E.3
EXHIBIT "D"
SOOS CREEK WATER & SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
DESCRIPTION OF SEWER SYSTEM TO RENTON - PONDEROSA ESTATES)
May 23, 1991
The Plat of Ponderosa Estates as recorded in Volume 70 of Plats, pages 34 and 35,
records of King County, Washington.
4-7:0400400G.006 1 of 1
E.3
EXHIBIT "E"
SOOS CREEK WATER & SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
DESCRIPTION OF SALE OF SEWER SYSTEM TO RENTON - SPRINGBROOK AREA)
May 23, 1991
Beginning at a point described as the intersection of a line parallel with and 180.00
feet South of the North line of the Northwest quarter of Section 6, Township 22
North, Range 5 East, W.M., in King County, Washington, with the Easterly right-of-
way margin of Primary State Highway No. 5 (SR 167);
Thence Easterly along said parallel line to the North-South centerline of said Section
6;
Thence Southerly along said centerline to the Northwest corner of Tract 1 of Spring
Brook Acre Tracts as recorded in Volume 12 of Plats, Page 60, Records of King
County, Washington;
Thence Easterly, Northerly and Easterly along the North line of said Tract 1 to the
Westerly margin of 96th Avenue South also known as John Langston Road and
Springbrook Road;
Thence Southerly along said Westerly margin, a distance of 320 ± feet to its
intersection with the Westerly extension of the most Northerly line of Tract 8, of said
Plat of Spring Brook Acre Tracts;
Thence South 74°50'00" East along said extension to the intersection of said
extension and the Easterly margin of said 96th Avenue South;
Thence Northwesterly and Northerly along said Easterly right-of-way margin to the
South line of the North 425 feet of the Northwest quarter of the Northeast quarter of
the Northeast quarter of said Section 6;
Thence South 88°27'05" East to the West line of said plat of Springbrook Terrace,
as recorded in Volume 131, of Plats, pages 55 through 58, as amended, records of
King County, Washington;
Thence Northerly along said West line and its Northerly extension to the North line of
said Section 6, also being the South line of Section 31, Township 23 North, Range
5 East, W.M.;
Thence Easterly along said South line to the Southeast corner of the Southeast quarter
of Section 31;
4-7:0400400G.003 1 of 2
E.3
EXHIBIT "E", Continued
May 23, 1991)
Thence Northerly along the East line of said Section 31 to the North line of the South
half of North half of the South half of said Section 31;
Thence Westerly along said North line to its intersection with the Easterly margin of
Primary State Highway No. 5 (SR 167);
Thence Southerly along said Easterly margin, to the Point of Beginning and the
terminus of this boundary description.
i
4-7:0400400G.003 2 of 2
E.3
EXHIBIT "F"
SOOS CREEK WATER AND SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES AND FOR
ESTABLISHMENT OF SERVICE BOUNDARIES
SEWER SERVICE BOUNDARY LINE)
May 23, 1991
Beginning at a point described as the intersection of a line parallel with and 180.00
feet South of the North line of the Northwest quarter of Section 6, Township 22
North, Range 5 East, W.M., in King County, Washington, with the Easterly right-of-
way margin of Primary State Highway No. 5 (State Route No. 167);
Thence Easterly along said parallel line to the North-South centerline of said Section
6;
Thence Southerly along said centerline to the Northwest corner of Tract 1, Spring
Brook Acre Tracts, as recorded in Volume 12 of Plats, page 60, records of King Coun-
ty, Washington;
Thence Easterly, Northerly, and Easterly along the North line of said Tract 1 to the
Westerly margin of 96th Avenue South , also known as John Langston Road or Spr-
ingbrook Road;
Thence Southerly along said Westerly margin, a distance of 320 feet±to the Wester-
ly extension of the most Northerly line of Tract 8, of said plat of Spring Brook Acre
Tracts;
Thence South 74°50'00" East along said extension to the Easterly margin of said 96th
Avenue Southeast and continuing South 74°50'00" East along said most Northerly
line, a distance of 189.00 feet;
Thence South 00°44'00" East, a distance of 188.40 feet;
Thence South 58 038'00" East, a distance of 89.35 feet along the line common to
Tracts 8 and 9, of said plat of Spring Brook Acre Tracts;
Thence North 41'22'00" East, a distance of 128.10 feet;
Thence South 64°22'00" East, a distance of 275.60 feet;
Page 1 of 8
4-7:04004008.002- 1
E.3
Ya
0
EXHIBIT "F", Continued
May 23, 1991)
Thence South 16 058'00" West, a distance of 239.80 feet;
Thence South 31'43'00" East, a distance of 210.90 feet;
Thence South 68 025'00" East, a distance of 99.50 feet;
Thence South 60°35'30" East, a distance of 28.17 feet to the most Northerly corner
of Tract 7, of said plat of Spring Brook Acre Tracts;
Thence South 00°12'30" East, a distance of 396.04 feet;
Thence South 39°31'00" East, a distance of 383.85 feet;
Thence North 89 032'00" East, a distance of 340.00 feet to the East line of the North-
east quarter of said Section 6, said East line also being the West line of Section 5,
Township 22 North, Range 5 East, W.M.;
Thence North along a line common to said Sections 5 and 6, a distance of 21 .50 feet
to a point that lies North 000 12'30" West, a distance of 241 .50 feet from the
Southwest corner of the Southwest quarter of the Northwest quarter of said
Section 5;
Thence North 40 041'00" East, a distance of 230.30 feet;
Thence South 84 012'00" East, a distance of 245.90 feet;
Thence South 34 026'00" East, a distance of 147.30 feet;
Thence South 14049'00" East, a distance of 257.44 feet to a line 30.00 feet North
of, as measured at right angles from, and lying parallel with, the South line of the
Northwest quarter of said Section 5:
Thence Easterly along said parallel line to the West line of the East one-half of the
Southwest quarter of the Northwest quarter of said Section 5;
Thence North 00 031'17" East along said West line, a distance of 190.00 feet;
Thence South 88 038'33" East, to the East line of the West 115.00 feet of the East
half of said Southwest quarter of the Northwest quarter;
Page 2 of 8
4-7:0400400g.002-2
E.3
EXHIBIT "F", Continued
May 23, 1991)
Thence South 00°31'17" West along said East line, a distance of 190.00 feet to the
North margin of said Southeast 200th Street;
Thence South 88°38'33" East along said North margin, a distance of 377.82 feet to
the West line of the East 156.00 feet of said Southwest quarter of the Northwest
quarter;
Thence North 00°39'11 " West along said West line, also being the West line of the
plat of Parkridge East 1, as recorded in Volume 132 of Plats, pages 45 and 46, re-
cords of King County, Washington, a distance of 918.18 feet to the South line of Lot
2, Short Plat No. R877058, recorded under Auditor's File No.'s 7803010983 and
7808100855, records of King County, Washington;
Thence North 89 020'49" West a distance of 59.00 feet;
Thence South 85°1746" West, a distance of 80.31 feet;
Thence North 89°24'30" West, a distance of 96.01 feet;
Thence North 05 009'11" West, a distance of 111 .45 feet;
Thence North 53 049'07" East, a distance of 198.22 feet;
Thence South 48°37'32" East, a distance of 118.20 feet to the Northeast corner of
said Lot 2;
Thence North 69 021'46" East, a distance of 165.28 feet to the East line of the South-
west quarter of the Northwest quarter of said Section 5;
Thence North 00039'111 " East along said East line, a distance of 147.85 feet to the
North line of said Southwest quarter;
Thence Westerly along said North line to the West line of said Section 5, also being
the East line of said Tract 9, of said plat of Spring Brook Acre Tracts;
Thence Northerly along said East line to a point that lies 271 .50 feet South, as mea-
sured along said East line from the Northeast corner of said Tract 9;
Thence North 78 021'42" West, a distance of 336.34 feet;
Thence North 26 009'56" West, a distance of 106.78 feet;
Page 3 of 8
4-7:04004008.002-3
E.3
EXHIBIT "F", Continued
May 23, 1991)
Thence North 83 020'02" West, a distance of 289.79 feet;
Thence North 70 034'46" West to an intersection with the Southerly extension of the
West line of the plat of Springbrook Terrace, as recorded in Volume 131 of Plats, page
55 through 58, as amended, records of King County, Washington;
Thence Northerly along said Southerly extension to the Southwest corner of said plat
of Springbrook Terrace;
Thence North 86 000'00" West, a distance of 509.65 feet to the East line of the old
right-of-way margin of 96th Avenue South, also known as John Langston Road or
Springbrook Road;
Thence Northwesterly and Northerly along said Easterly right-of-way margin to the
South line of the North 425 feet of the Northwest quarter of the Northeast quarter of
the Northeast quarter of said Section 6;
Thence South 88 027'05" East to the West line of said plat of Springbrook Terrace;
Thence Northerly along said West line and its Northerly extension to the North line of
said Section 6, also being the South line of Section 31, Township 23 North, Range
5 East, W.M.;
Thence Easterly along said South line to the Southeast corner of the Southeast quarter
of Section 31;
Thence Northerly along the East line of said Southeast quarter to the Northeast corner
thereof, also being the Southeast corner of the Northwest quarter of Section 32,
Township 23 North, Range 5 East, W.M.;
Thence Easterly along the South line of said Northwest quarter to the Southwest
corner of the Southwest quarter of said Northwest quarter;
Thence Northerly along said East line of said Southwest quarter to the South line of
the North 200.00 feet thereof;
Thence Westerly along said South line to the East line of the West half of said South-
west quarter;
Thence Northerly along said East line to the North line of said Southwest quarter;
Page 4 of 8
4-7:04004008.002-4
E.3
EXHIBIT "F", Continued
May 23, 1991)
Thence Westerly along said North line to the West line of said Northwest quarter of
said Section 32, also being the East line of the Northeast quarter of said Section 31;
i
Thence Northerly along said East line to the Northerly margin of South 179th Street,
also known as Carr Road, est. 11-27-17;
Thence Westerly along said Northerly margin, said margin being a curve to the left,
the center of which bears South 00 001'50" West, having a radius of 1,462.69 feet,
through a central angle of 02°21'07", an arc distance of 60.04 feet to the Easterly
most corner of Lot 42, Plat of Scott's Terrace, (Recording No. 761680) as recorded
in Volume 72 of Plats, pages 39 and 40, records of King County, Washington;
Thence continuing along the Northeasterly boundary of said plat the following bear-
ings and distances:
Thence North 60 004'34" West, a distance of 250.34 feet;
Thence North 17 102'46" West, a distance of 112.00 feet;
Thence North 01'13'36" East, a distance of 268.68 feet;
Thence North 22 031'55" West, a distance of 180.92 feet;
Thence North 89 003'13" West, a distance of 565.00 feet to the centerline of
Talbot Road, also known as 96th Avenue South;
Thence Northerly along said centerline of Talbot Road to the North line of said Section
31, also being the South line of Section 30, Township 23 North, Range 5 East, W.M.;
Thence continuing Northerly along said centerline of Talbot Road to the South line of
the North 100.00 feet of the South half of the Northeast quarter of the Southeast
quarter of said Section 30;
Thence Easterly along said South line to the East line of said Southeast quarter of said
Section 30, also being the West line of Southwest quarter of Section 29, Township
23 North, Range 5 East, W.M.;
Thence Northerly along said West line to the North line of the South half of the North-
west quarter of the Southwest quarter of said Section 29;
Page 5 of 8
4-7:04004008.002-5
E.3
y
EXHIBIT "F", Continued
May 23, 1991
Thence North 88 039'49" East along said North line to the Easterly margin of State
Route 515;
Thence Northerly along said Easterly margin to the North line of said Southwest
quarter of said Section 29, also being the South line of the Northwest quarter of said
Section 29;
Thence East along said South line to the West line of the Southeast quarter of the
Northwest quarter of said Section 29;
Thence Northerly along said West line to the Westerly extension of the South line of
Lot 4, Block 2, plat of Aker's Farms No. 5, as recorded in Volume 40 of Plats, page
27, records of King County, Washington:
Thence Easterly along the South line of said Lot 4 to the East line of the West half of
said lot;
Thence Northerly along said East line, and the Northerly extension thereof, to the
South line of Lot 1, Block 2, of said plat of Aker's Farms No. 5;
Thence Easterly along said South line to the West line of the East 62.50 feet of said
Lot 1;
Thence Northerly along said West line to the Northerly line of said Lot 1, also being
the Southerly margin of Southeast 166th Street;
Thence Northeasterly to a point on the Northerly margin of said Southeast 166th
Street, which lies 237.41 feet East of said West line of the Southeast quarter of the
Northwest quarter of said Section 29, said point also described as the Southwest
corner of Lot 4 of Tract A, said plat of Aker's Farms No. 5;
Thence North 24 002'04" East, a distance of 364.47 feet along the Westerly line of
said Lot 4 to the Westerly margin of Benson Road, also known as Secondary State
Highway 5C;
Thence Southeasterly along said Westerly margin of Benson Road to the Westerly
extension of the South margin of South 29th Street;
Thence Easterly along said Westerly extension and said South margin of South 29th
Street to the Southerly extension of the Easterly margin line of 106th Place South-
east;
Page 6 of 8
4-7:04004008.002-6
E.3
EXHIBIT 7", Continued
May 23, 1991)
Thence Northerly along said Southerly extension and continuing Northerly along said
Easterly margin line and its Northerly extension to the centerline of Southeast 164th
Street, (also known as South 27th Street);
Thence Easterly along said centerline to the East line of said Northwest quarter of
Section 29, also being the West line of the Northeast quarter of said Section 29;
Thence Northerly along said West line to the North line of the South 430.00 feet of
the Northwest quarter of said Northeast quarter of Section 29;
Thence Easterly along said North line to the East line of the West 450.00 feet of said
Northwest quarter;
Thence Norther) along said East line to its intersection with the Wester) extensionY9Y
of the South margin of Southeast 162nd Street;
Thence Easterly along said Westerly extension and said South margin to the West line
of the East 330.00 feet of said Northwest quarter;
Thence Northerly along said West line to the North line of said Section 29, also being
the South line of Section 20, Township 23 North, Range 5 East, W.M.;
Thence Easterly along said South line of said Section 20, to the West line of the East
930.00 feet of the Southeast quarter of said Section;
Thence Northerly along said West line to the North line of the South 200.00 feet of
said Southeast quarter;
Thence Easterly along said North line to the West line of the East 670.00 feet of said
Southeast quarter;
Thence North 01050'38" East, a distance of 105.01 feet to the North line of the
South 305 feet, more or less, of said Southeast quarter;
Thenceece South 88 46 15 East along said North line to the West line of the East 330.9
00 feet of said Southeast quarter;
Thence Northerly along said West line to the South line of the plat of Parkwood South
Division No. 3, as recorded in Volume 109 of Plats, pages 57 and 58, records of King
County, Washington;
Page 7 of 8
4-7:04004008.002-7
E.3
EXHIBIT "F", Continued
May 23, 1991)
Thence Easterly along said South line to the East line of said Section 20, also being
the West line of Section 21, Township 23 North, Range 5 East, W.M.;
Thence Northerly along said West line to the Westerly extension of the South line of
the plat of Ponderosa Estates Addition, as recorded in Volume 70 of Plats, pages 34
and 35, records of King County, Washington;
Thence Easterly along said extension and said South line to the Southerly margin of
the Cedar River Pipeline right-of-way;
Thence Southeasterly and Easterly along said Southerly right-of-way margin to the
West line of the East half of the Southeast quarter of said Section 21 ;
Thence Northerly along said West line to the North line of the Southeast quarter of the
Southeast quarter of said Section 21;
Thence Easterly along said North line to the East line of said Section 21, said point
being on the City of Renton City Limits, as established by City Ordinance 3723, and
the terminus of this boundary description.
Page 8of8
4-7:04004000.002-8
E.3
ft C ' ',y".J' _ .s Q7rn W ,r q _J-...
e,.
I . .. ..... ,, .
y"11111`1`O• _ . ,6}' ¢sr`o%-Q`
J•'///••
r M ,
I
l.I.
n
i ,
1 r
1
a
o
W
za
3t
o J
Jt
Z b 1 1 11 8 6tti:t N ' .
C . L
G Q
7TH I 5?. —___ S. T H
JIM
Y 9TH sT
SAY s"-
FF
Et
R-1 1 SiSUbsto.x OiA l) '\ r lv' /•
16 co
I RCNTONVn1Abt
I PS p S `- ---__ _-_ PNS•, 1 HEV/LLE 3jt
r / v
PL.L ESMT TR s
E B.P.A.-
L
J, SEA i•a:.•
c 'yo r
I
I \
J.Ali I r-
yJ _
B_P A _
Z 0--ISTM
N
ST 4
VALLEY SUBS TA.
s a f
Y,. (
1
t h I al 1Cc
r I TH unrCORR.-1 ESMT.
y. a 11
S.ib H.1?
Q i..ijyi 7 v /
E 1e vL. 5.e. ry \,P TIFF CZ,PR a s
S q °PAR y
1 I
V \
nls i'TN S Pp 0./ 7F \\\ fC f `^ ` a 1 1
V
s W s.i.n X c
S HO a9 uq 1 O
PIP
v
a C 0\---J S. ISTH ST e
Qg s.IerX 3T a :
7 J 1
7i1.tejly Pork
T 22 9 1 u
ry °`'
W:,.O'y, a,. o 7 j>r >,F4 O-Pj` 'v0 QT /.L .
213T cf.
P`V
W
3 '•
N-_..
C_q
6
s4
r
W'
y
J. —
P
ra'
P
y,
03F0PACIFICN.W PIPE LINE s.E 160THSEA o T 3 ArS'
ky/F%
4 B5
d l b'
O
F\o4Q'"ah
4 I s ^ I z (p S
Hill Cyp a o 3
5T_04 2 Q' -
O E . Park:. I •- 5 4 W5`0
r5bl
3
4 \.. \\
6 Q tip 3
oOA
5 a
s 6
1 x 3
Js c f. ^ ~ E I ST. I IL r N 2 u
5
164TH -A LY
3
V XA
J SyA ,y 'T
I
T a4 i yr
Q
S v
x 2 `
PJ L 11.1
l 3 N tT 2 i
F
5
4
S.E.167TH tsi. a
2
1•-
168TH ti ST.
6 tl- 37 S?
r\\
F
5W> o
z
o
a SE.169 1 N.Sb T to GR 1
sr ^
L v !Q..••k4.:: •E1l:E 6
4 9 9 1 fl K
x 5. 16 FTHRi9 QO Ul
r 13.r::::•
la U n LEGEND
Q y ~ 12 12 I S 170'` /?
x
pf r
y
Q f
24 s_Mw-
W 3 1aWh
SODS CREEK CORPORATE BOUNDARY
SST°
er$:I W(Fm: 9 HE6-
ER /34 Q 8eANERF
mmmum RENTON CITY LIMITS G o W
Q:
r
T 4fS WAR:: S 4 I N i i z T
t I SS CO a T z 1
a rrRST
e 7 6 s W CARL
s 3 t• 62 SO o JE naTH s 72
o// PROPOSED SERVICE BOUNDARY BET14EEN
2 AART I O
15
i° 4Z(`- CITY OF RENTON AND S.C.W.S.D. jl
f'4 92 c AREA INSIDE S.C.W.S.D. SERVED OR fs a/ i!
LE N 6 TO BE SERVED BY RENTON. o y f i. o
LUND t 7 Q' , /oz 120 9T C 1 DEM In J> 1
ti AREA INSIDE RENTON SERVED OR TO BE SERVED TF91f CORP z" z &
5'4 ° '•h BY S.C.W.S.D. UNDER A FRANCHISE AGREEMENT
242
S7 9a
WITH RENTON. 4 ROY WVHUNTER
24 6S BI AREA INSIDE RENTON TO BE SERVED BY S.C.W.S.D. 62
777
76-6F-/OUTSIDE DISTRICT BOUNDARIES UNDER A FRANCHISE
I. iitJ:++?': U 20' AGREEMENT Wllll RENTON. EF D 0 .3 FrT h i
Gp ri^: Q H\, a RENTON WATERSHED. NO SERVICE IN THIS AREA, j L 7_ _43. 4
AMESBL
x>,:`'' a W 1 CI DEM cam
COULON2£K6. flEt::::: ' wN w 56
82 /4 p ,>
E. jcY: ANARD 1 i 6 e . T o CORP t
P1NA A t$ A'I:'#: `:;:s 9S s 71 5 184 F
16 J 70 82 196 C I T 184 33 t6
1AD E HE' :: ;.;::.•..•:::::.AL BOUR- o ED S &
l
7W Ic
Ri:Q: ED 1$ /2/ Y W 3 A HA Q W
MA - :•:1Q' •:'•:•:
r. ''•\+.;
17/ r
L,,,I S.[. I TX ST
3
W ScEftif : IfL'i!: LEO l!8 J J s Q •a 4/
ERSON 97 WERT zJ 94
r 0.ON :; ;; : ::•:•:;: 6d 8.5 /33 WM
i;. :E:: :• S:3 [ W 232 RUTH l2
37
138 I NV CSQ NILL
8 y y T 6
s 9 0 ^+m
A $RUTH 8 N SCNO
H : /
7
27 FALL =
7 "
T
4
3
2E
11)z ^j ^ 114 Z I 2 I
xo S
o ;. : Nw 17 1 5
EB6 I w0 T 3
ti4N
Q N::::
I 8 G ,, h S L K z J ao
341 s •
2
F
3 O•
F,'1
HN OH H R -.
HURC \ v J
lip::;: :•T :::• ::•:•:
0 27.6 239132 9 -
11 C S w ><w =
6 7
13
51 IATCHI
80: t'. >;• ,\
1
224 JG i 1
12 13 S. by 0 9 9 fS B 9 10 11
tiu.'',a•,. ,.w' :.tip. c._.__l ra.a.un.__._..
5.
HAN GS a3 ' 73 I
w W w IQRP. F39.1 J ,. 3 7 t Ft' 4J Jb
5 4.... •. D L.(ALO /36 r. h- 16 IS 14 W 1 al CA q.0LIC 1
KJ'f 71 137 3 6 // z W 5 ARM BISHOP 4/ '.
PPE,85 46 Z
2 At\ .
25 3 14 I r Eu f:i
z e e ERNE I c226L716ir9Q26931 _NMAURER Q 12
r.. T
O 30-L Ie
8 87
s6 qrab ` ?18 1 21 ' 2 SCALE 1`:200' 4 6.5
i 81;
2
7 3-' 'r 0
14 1 51'9 I20( a'eO / 33 1\ 9 f I n1,1 nI1 p \
A M 4f:
y o
F21tIGEiR00K
AalSOrl - 34 CITY OF RENTON & SOOS CREEK FAR4 N r ,-
4 4p' 4 sil
X
35 36 WATER AND SEWER DISTRICT
SERVICE AGREEMENT.
95B 710 0} 3.90
3S? O WATER
@2 o u Z
N
Ql9
w 14 =o X23 I . / B6 Sz s -MAP14 6/
L
ON
u.FIGURE 1
1
36
Ulli
f
y IDI11S a
JOHN;::: VICTOR
a 4Q oq SlOAM LAPPELLO
NSIIUEI DIAMBRI gfo I_'S _i I '7 i_ Hedges & Roth Engineering, Inc. `IZO; 1s
Q$ 04 3C 2 I `I 2. 8 CA- 100 6 _ !?3c 7/66 & CONSULTING ENGINEERS • PLANNERS • SURVEYORS j
Z
IzOZ CADE LANG v 0 3&Q5 KIRKLAND.WASHINGTON (206)827-8793 (206)682-7426 1-8048350292
a ":' 6 ND APT- HOL
1 11 o N fil N 246 97 I- 1n `'•' W a: =6 xQ F.RAV.0I Ol -9'
28
z I 31 391 -- , i w Q_ 9 -2 .75 nT
1 13 vTE pDDIs 16
CLOSKEY
t 8 Ix 7S 4 Z0CI/ H 69 E• ,..HBO
E.3
113th P
4th",17 AVE S E
T 119
07
J B—//9
AREA A DAYTON-DR•
c
N H EDMONDS C?R.
s E r-RENTON
a—g o--e- x
N x'•,43
co 117th AVE S E m: s
s-
ZA
rTi2 x Cn m
g 7 oa
o
n a
s
Z Cn //
gGtc v -i 5 a J,
cc
NO
o D
a m
3 mm0 F Gj v
e
w
Z
e'
co
a In m F
ZO
0 m Q m. D rn QC:.o z 10 10 5
y s:
Z SmmD' p. ,.rn rn Q1o
m Q
i z 0 WIM0 121 A S
m o
1 g m >
x:rnCDC0 s
N N z—i c)
P . ®
yam.
mn r
z m 0
AV cn I rn J,o.
fit<
m
y 24” o
SE
23rE r AVE S 45
Ix
E.3
r
a
e ft a
i I- '-L-J4- - }— -T-
N 6' f/ Pr
M ca
30 77
Z O
m n
A
Wr
m uL_
I I lil
116th AVE. S. E.
Ilk
OD a
60 to
3
Y
Ji nva' s.r•'.
Q S. ®
q
n*.+
y\
ts SE
o
s t. .1_. .... ..11
v
5
w f IF
19
N K.1 ` 4
1.
l
i A o o
as
I Iior •
N
i IA
I I
z
D
i i I
ds ' rye b E
iN
I
rD
cn i
O
i
rn Z I ,•
M rn t
To
Mi
o rn
Ztj -- - ---- --- — ---- -- - -- - -
sl I I
y iY
GT 07- i
zm i I
D D oi nv
m m p 2 yo j\ 2" ,
I
e= Z -v U) b c)Y a
r rn C p N
a D m 3 Joao rr 8
Zm m 3e _ a ' I I
O S?o m
m m 0
U
r cn rn m
a mD7Om 'v O
rn Mi
E.3
aa8
aaaa a
4S
a a a
Vass
arIta
Ra
aaaaaa:
X.
museums ,'
Gj 1Js
N
Q
D
r
4 m
J
12.A
h AV E -i O
a
s
3
Ro
as rn a'•t
Z
m — s
N Qi
0 c S >e a 3
mZ-2 Z.1 ahZwzv
rn
m O g
M a c
z>a m.v Nm i WTv
N J CC it'O G
V m fia0M.Im • as m
9
M v m n a
0 rn
D 1 v ,1 — --
0. S
Oi
Z D rn
2z z M CO A s;Z
m Z'M 3 A.i
N N iZVn
rn
rnr"
N
i
a O m IY 4Za
WQjDY -m
D o
N N 9 th AVE.'S.
z-a
a
E.3
MEM E®EAMM®i M
NIIINIIIIIilllllllllllllNNNIIIIIINIIIIINNIIIIIINIIIIlIIIUNII
i INNIIIIIIINIINNIINIINIINIIIIIIIIIINII IIIIIIIIIIIINIIININ
8 IIfNII fNNINIIIIIIIIIIIIINIIINIII N iIIIIIIIIIIIININN
INNI IINIIINNN NIIII IiIIIIIINNN fI
NNIIIIIIINIINNIN IINININIlIIIIIIINNIINIlIIIIIIIINlNIIIINN
IIIIININII IINII IIIIIIIIIIIINIIIIIIINIIIINIIIINIIIIIIIIIIII
1111111 NNN NNINNIINIIIIIIINIIIINIiiI IIIIIIIIIIIIIIIIININ
IINII( IINNII IIIIIfNNiNIIIiII IIINlllllll IIII IIII I IIlIIINN
IIIIINI III IN IINIIIIIIIIn:!!!!!!!!!!!!!!!Il nllll:!!!!sllllll
r NINIII II IIINIIIIIIIillll llll IIINIIIIIIIIIIINIIIIIIIIIINIIIN
III I INNIIINIIIfG41111i1IINIIIl111NIIII IIIIIIIIIIIN ME
INNNEN IN INIIIINiNIr3M IIIIMI 111111111N illimmo
IN long
roINNIIIlI:IIIIIIIIIIINIIIIIIIIIIIIIIIIIIIIIINNN
i-
N IIINIIINIIIIIII (IIIIIIIIIIII IIIIIIIININNIIfN
ONE NNIINIII BNINNIIIIIIIIIIIIIIIIIII Timm 1
I NIIINIIIIINIINNIIN IINIINIII JIIIIIIIIIIIINIIIINIIIIIIIIIfIg
E.3
IINIIIIIIN I IIIIINIIIIII mIN mN ulNl
INNIIIIIIN I Ililllllllllll III _ ;;.. . mN mllllm i1
i1,• NI i iIINIiINl 811 INIiiIUIINI N NmumluN N
G .c : _ illlllllillllllll IIIIIIIIIIIIN NN INm11NINm
IN..l
E1
111'I Iii ...... ^ ,.
Fill N
111m r HIIIIIIIIIIINI I II O N m0
IIIIINlINIIIIIIImNNm
II ii111111i1i ll ii` iiiii' llllml
INI!Nlii i 11 ' 1 lllllll 1 IINmNIImIIImNm
IIIIIIII , Iii 11 iiiillllml
111l I I i,l lu IIIIIIIIIINIIIIIIImN
I.1 j f IIINI 11111111 NII NNmll NNNNI
ml ill 11 IIINI IIIIIIIII IIII NINm mlNm
111111±IIN II moiIIIIIIIHilll11 m Nm11mmN
111111111! 1111111111111111111111m oil lNNm,,
E 111111 IINNIIIIII tillllillllllllllllllllll NIIN
1111111 II III NI11111111111111ROOM 1111111
INNlllm
1 loll uml ul Nm
INIIII N NIIIIII'N11 1111111111111111iiiiiiiiniiiiiimIIINImN
1111111111111111 NIIIIIII111 IIIIIN111111111111IIIIm1111111I1111Imimm
IImNIiIIIN
1
111111111 II IIIIIIIIIIIIIIIIII
HOUR 111111111111
IIIIIIIIIIIIIIIIIIIINIINIIu
IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIINmillIIN
NIIN IIIINIIIIII IIIIINIIIIIIIIIIIIIIIIINIIIIINIINIIIII 111111 NIIIII
m I II IIIIIIIIIIIIII IIIIIIIIIIIIIIilllllllllllllllllllllllllll NIIIII 1111111
1111111 IN IIIIIII_IIII...11;1;1IIIIIIIIGiIIlIIIZGIGIIIIIIIII 111 IIIIIIIIIII 1111111
11111111111111 POUND II IIIIIII
II I 10 lIIIII IIIIIIINIII"lIFIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIINIIIIIIIINIIoilII1'illliimii IIiiiii 1i1IIIIIIIIIIIIIIIIilullllllllllllllilillllllllu
1111118 iilllO ii
e NIIII IIIINIll1
111111111111111111111111 OR I liiiiiiilI
11l1l1l1l1l1l1l1l1l1l
111111!IN'
i!IIIuiN
u11111hll
1111111 hill II Illlllllilllllllllllllilllllillllllllllillllllllllilllli 11,`-11111
1 NmINI 1111 N IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIHIM IINIIII11HE IIJIIII
I INN IN II IIII IIIIN IIII I II NI IIIIIIIII III I III! I I
I I IIIII
Ili
111 111 I I I I II III IIIIIIIII III I illi I I
I Ilm III IIII I II N I 111111
I I II I N 1 II 1111111
mll u1111111111Ii'IIIIIIIillllllllllllilllllllllllillllllllilllllllll
mN I 11111111 111111111111111111111111111111111NIINIIIIIIIIIIIIII
1 IIII N II
IIIIIIIII IlllulIN11111 I III1II II
1
II
1II1I
IIilllllilllll
1111111 Ilk, mi.1111111111111111 IINIIIIIIIIII
N II 111111PIIIII1 111!ll1 IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIINIIIIllilll
III II 111 1 IIIlirl I'IIIIIIIIIIIIIIIIIIIIIIIIIIIIImNNNilllllll
NI 111111111 NI11101`111 111111 liiiiiiiiiiiiiiiiiiiiillillillillolI
III III IIII I I Ili 1• IIIIIIII I,.....!!iIIIlIIl1 l11 lIIIIIIIIIIINIIIIIIII
8 I I it (IIII Iill ll illlllllllli!IIIIIIIIIIIIIIIIIIIIIiliillllllllllllllllll
NI NIII IIIII IIIIIj:111.,IIIIIIIIIIIIIIINIIIIIIIINIIIIIIIINIIII
IIIINIIIIIIIIINIIII IIIIIilllllllhlllll111i!1111111 111111111111111111NIIIIIIIIIII
Illllllllllilllllllllllllllllllllll,Nlllllllli!IIIII IIIIIIIIIIIIIIIIIIIIIIIIIIII
IIIIIIIIIIINIIIIIIIIIIIIIIIIINIIIiillllllllll lllll IIIIIIIIIIIIIIIIIIININIIN
IINIIIIIIINNIIIIIIIIIIIIIIIIIIIIIiIIIIIIIIIINII iIIIIIIINIII111111111NNIINIIII
1111111 IIIN 1 NIIIIIIIIIINIIIIIIIIIIIIIIIIif'.l 1 11111111111111111111111mNINlI
Up 11 11111;11 IINNI IIIIIIIIIIIIIIIIIIIIIIIi111 1111iiGIIIII111111mNNlllll
IIIII IIII IIII :IIIIIIIII IIIIIIIIIIIIIIIilllllll 1 1 II 1111111111 III INIIIIII
pp
II
IIIIIINNIIIIIIIIIIIIIIIIIIIIIIIIIIIIlillliiuiiii111111 11f1111N111
IIIIIIII 11 IM IIIIINIIIIINIIIIIIIINIIIIIIIIG1111IIIIIIIIIIIIIIII111uuiimii
1111111 Illlll: I IIINIIIillllilllilliillllllll IIIIIIIINIiIIIINI11111NINNl1
ORION
NI
mmuiiiiii111111IINIINN111 II:l, IIIIIINIIIIIUNINIIIIINIIIII
NINIIIIImINIIIIIIIIIIIIIIINNINU III:INIININIIINNNIIIIIIIININ
NNIINIIIIIIIIIIIIIIIIINIIIIIIIIIUIININiImmIIIIIIIiIm11111uIIIINNIim
IIIIIIIIIIIIIIImIIIiINIIIIiHIIIINNIINImNIIIiImIIIIIIINIUIIIIIIININUI
co
fn
liiiiiiiiellilloilillililillipNI,.NIINII..IIIIIIIL.NIIIIIL.III IIIM...' i U111ONlllmummu NIII
ii III INilim 111 lipII IIIIIINIINIIIIIIINIImuuml Nm
0 M• - ' IINI Ilmlllll IIIIIIIIII HilillIINIl11mNIlilIlNli o INU m
1111111 II 1111111 IIII ml NN N IIIN 1 NI
pull l 11 IIII NIN NN INN 1111,11 11111 Illlll IINU I III
INII II mu NCI mi mmuuiNlmiluiiuuiimmill
E.3
Rm 111111IlillllllllIIIINI11111 I I I
milli 1111mmul I Nllfl i Inlll N Ifil
II 1 111111'li!IllHIPI
I
II I NI
I
I I i
w III I IIIINi1111!IIIIII n I IN N II N I 1
11111,11111
IlHIM
11 ,
11 1 I NI III 1111
IIIIII IIIIII1,11111111111111 11111 II 111 II IIIR
I IINIIIIIIII IIIIIIIIII 11 IIIIIIiIII I II I it N IIII Nllm
v
s , I INIIIIIIII111 IIIIIIII Illi;lllllll, II IIIIIIII mllll I
II Iill IIII INII II 1111111 !1!IN 1111111 I II I I III N
III NI IIIII IIIIIIIIIIIII IIIII II I III IIII
i
IIIIIIII I III IIINIIII III I I II NIIIII!I II fill ININN
NIIlillll I II NIIIIIII III I I II Illlllllli,ll 111N Ii l I
mllllll I I N II IINII 111 IIII '111i!1111111111 IINI
mllllll III III II IIII 110 IIII1111111 111Nili,l 1IIIII NI
IIIIIII1111111111 I I111111i
1I±
IIIIIII 1111 1111ilP III P I I I 1111111111111
1 11111111111111 II II 11111111 III IIIIIIII 11 1111111!!1111111111111111111111
1 1111111111111 II II IIIIIIII III IIIIIIII 111111111111 e3111111111111111111i11
1111111 (IIIIIIII IIIII IIIIIIII11111111 IIII 11I fIIIIIIIIIiIIIUIIN
11Hill 1111 1111111111111111 II 11111111111111!:fil IIIIIIIIIIIIIIIl11116
o - -
111111111111 i I II 11 II IIIlilll 1111111 1111111111111fflllllllll'
1111111 IIIII : IIIII 111 II IIIIIIII IIIII( Ill OR IIIIIIIIIIf 1
1111111111111 IIII IIIII IIIII it IIIIIIIIIillllllllllllllllllll j111111111111 1
Iml1111111 'I I I 111
r%fir 111111111 f1111 1 1111 IIIII 1111111111 I IIIIIIIfII;r 11111111 1111
111111111 . fll II 111111111 I (IIIIIIIIII I IIII!IIIII IINIIIIIIilllli
IIIIIIII lip I 1 11111111 11111 Illlllllllli I'lllilillllll 1111111WIMAN11111111 : 1111 IIII 11111 1111IIIIIIIIIIIIIIIIIIIIII 1111111
1NII111111 111111 1 11111111111111 III IIIIIIIIIIIIIIIIIIIII
111111111 N N IIII I I II 1111111111 NI IIIIIIIIIIIIIIIIIIIII
J;;``'•
I VIII 11 I NIII NI II II II I I I!111111 IIIIIIII 11111 III
mll I I I Illi111111111 IIII III
NI I m 111111111 I I II III IIIIII10111111111111111111 1111111111
III 11 III 1111111 I I II III IIII I IIi 11111 Iillllllll'lllllllllll
r ,' 1111111 II I IIII 1111111 IIIII Till IIII I Illlll il ail;IIIIIIIIIIIIIIIIIINII
a < • 111111 II I NII 111111 IIII IIII IIII i IIINIii i ll 111111111pllllllllllll
11111111 INII I I IIIIIIIIIIIIIIIIIIIIINIIIIIIIIIIIIIIIIIIIIIIIIIiil: 111111111
i Illlllllll IIII l i lllllllllllllllllllllllllllllllllllli lllllllllllilrlliilllllli
v
1111N111111111111111111111IIII11111III111111111111111111 I1111111111 I1111111111
OWN IIIIIIIIII IIIIIIII:;IIIIIIII 11111111111111111111111111111 IIIIIIIIIIIIIIIIIIII
Illlllllll Ill III111!IIIII IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII
NIIIII1fi 111 !!111111111NIIIIIIIIIIililll lllllllllllllllll illlllllllllllllllllll
11111111 IllllflMIIIIIIIilllllllllllllllllllllllllllllll IIIIIIIIIIIIIIIININI
II 1C III II I le!I I, 1111111 111111 Illkllll;ll 1111111 I II II I
IIIII IIIIIIIIII 111111 Il;ai11 111111 IIIIIIIIIIIIIIIIIIE IIIHIIIIII!1111 (IIII
r IRN IIIIIIII 1111111 IINI,i1 I®
I
I I
IIIIIII
I
IIIIIIIIIIIIIIINIIIIIIIIIIII
I
II
II'IIlIIlIIINIII'
i.
11111 i1 _ _ _Is
I
1
ill IIC'i llllilll II ""II !!II 1111
III 111111 II Ill; IIIII,,I
IIIIIIIIIIIIIIII illlllllllllllllllllll!10!11 IIIIIIIICI111CIIIl!! ii IIII
INIIIIIIIRIIII IIIIIIIIIIIIIIIGi llllllllll!Illl flllilllllIIII I ljllN
1111111111 111111111111111111180.IIIIIIIIIilh lllll'll llllillll6lf;lif+IIII
IIIIIIIIII IIIIIIIIIIIIIIIIIIIII I:IIIIilllllllll:i,111111 111111111111 III_illll
IIIIIIRIIINII1111111111OR II IIIIIIIIIIIIII, 14IINI
111111111111111111111111111111111111111111111111111 111111111111EIfl 1111111
m `0' 111111 IImIIIINIIIIIIIllll1111111111111111111111i!1lIIIIIII IIIINIIN
IIIIIIII 11111NIII1111111111 mml 1111111111111NI1i!iIIIIIN i
111111 mNl 111 ININ I I 1 Ili!nllmll
1 Im1 N IR 111NR I R INII N111NIIII
I 111 I 1 111 , m
m II !II!I N
Im I i_.._____' Ili! Iili R'
R iml 111111 IIII '
Im.
E.3
g Hill lMllimiiiii Ili
IINIiIIIIIIIUNm, .IFINONE ,i•! Illflllll:al iliIIIIIIII
1 1 IIIEIIIIIINI dmIIN
IiI11i I(IIIIIIII IfmNl
liiiillll'IlNlllllllllllm
y IIIIIIIIIIIIIIIIIIHIfmIN
IIIIIINI IIIIIII NNml l
IIIIIIII I IIIINIIINNIf I
s
IIIIIIII lillllllllllillll!
IIINIII IIINIIIIIII, IIIIIIIIIIIIIIIIII iIIIIIIIIIIIIIIhINNIIIIIIIIIIIINIINIIl!
IIINNIIIN NINII:11111111IIIIIIIh INIIIIIIIIIII I! 111111 IIIINII,NNImll 1
IIININIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIINIIIIIIIE 111111111111!NI IINIidI
INNllllllllllllllllllllllillllllllllllllllllllllll.IIIII1111EI,IIIII 6NIIINIIIIN
1111111 Illllllllilfllllllll!'I IIE I Illl!11191mlllllllINNIIIIAIIIIIIIIIlh,
MI
IIIIIIE 1.Ili!,11111111ii It'
ll!
111111111111111111111111NII I IIII IIII fiIJ1NNN!
111111li lltl':II Illlllilillli!Illllli!Illllllli;iiiiiiiiiiiiiiiiiiiHl IliiaiililiN
IIIIII 11171611 1 :111111111111111 l111111'IIIIIIIIIIIIN111P.I.,11111lII:II;IIII:;IIINI
Illllfiiilllia III:IIIIIII1111111NI1!Itil IIIIIIIIIII I IIIIIIIIIIIIIII Illll lllm
IIIIINIIIIIIi lil111111llllllllllllli;ll Ill lllllllf;E'111111111111111111mlf IM
IIIIIIIIIIIIIIII IIlllllffllllllllllllllll!IIIIII 11111:i lllllllllillllllllNIIIIIII
INIIIIIIIIIINIIIIIIIIIIIIIIIIIIINIIIIIi!111111lIIIIIIIIIIIIIrllllllllllllllilll
IlIIIIIINIIIIIIIIII IIIIIIIIIIIIIIIIIIllllfllll illlll!IIIIIIl II+?IIIIIIIIIIIIIIIIIII
IIIIIIIIIIIINIIIIII IIIIIIIIIIIIIIIIIIIIIIIIIIIII!IlfllIIIIII III!Illlllllllllllllfll
1111111111 IIIIIIIf li111111 Illlllllllllllllllllli;IIIIIII IIoiIIIlNllllllllllll!
lll
1111111111111111NI11111111lIIIIIIIIIIIIIIIIIIIIIIIIIIII!II II 1I IIIIIIIIINIIIIIIIN
IIIIIIIIIIIII IINIIIIIIIIIIIIIIIIIIIlI1111111Illlllllllllh,Il Illllllllllllllllllll
IIIIIIIIIIIIaffflllli;!IIIilEli1111111111111111111111111111111i!IIIIIi IIIIIN'lllllllll
IIIIIIIIIIEallllllllll l;IIIII IIIIIIIIIIIIIIIIIIIIIIIIIII Rh IIII111111 IINIIIN
IIIIIIIINIIIINlllllllllflii!!Illllilllllllllllllllllllllllllliili;IIIIIII;iINllllll
IIIIIINII(;IIIIIIII IIIIIIIIIIlIIi!!IIII IIIIIIIIII IIIIIIIIII II II IIIII Ililllllli ullllll
1111111111 1111111111111111111111111!Illlllillllllllllllll: II lIII I IIIIII Nlllt
3 I u mN II i !;III IIIIImIIINIINll1 l IIIIIII IIIN
II II IIIIIIIIIIII IIIII III ii!IN 1141111111111lIIIIIIIIEI illllllllll
V ' NIIIIINIIIIIIlfllllllllllllllllllllllllllllli!IIlIIii'111111!111f111,!N!IIIIIIIIIII
INNIIIIIIIIIIilfllllllllllllllllllllllllllllllllli,.Ir1. I I Illlllel lIIIIIIIIII
IIIN Illlllllalll IIIIIIIIIIIIIIIIIIIIIIIIIIlIIIIII,!Illlll llll llpl lllllllllll,JIM INIIIIII!11111 IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII,IIIIIIII I!IIIIIIIIIINI
IINIIIIIIIIIIl:I'fllllllllllllllllllllllllllllllllllllllallllk,IIIIIIII lllllllllllll
IIIIIIIIIIIIIIltl III III1111 111111 IIIIIIIIIIIIIN IINlllli!IIIIIli11111111!I
IIINlllllllllhilll 111111 111111 Illllllllllll llllfallll lIIIIII,N 1!
ti IIIIIIIIIIIIIIIII II ' 111111,;,111111 ' IINIIIIIIINIIIII llllllli fli;llllll
IIIINIIIIIIIIIINII lliiii;IE I!filllllll flillli lllll Illllllllllellllllllll
IIIIIIIIIIIIIIIINIIII IIIIIIIIIdiI ... IIII IIllllllllll lflll llllf!.iilll:ll,.11llll
is• . r`,R'I I iii' i r ..'
i 1 IIIINIIIIIIIIIIIIIIIt lllllllllli h t ! i lf.11ffllffl l llllllllyllffillf 111
IIIIIIIIIIIIIIINIIIII 111111111111111MIE 1 I3.;QEI IE I!IIIIIIIIIIII I:IuIIIIaI;NTr
IIIIIIIIIIIIIIIIINIlIIIIIIIIIIIIIIIIIIIIIIIIINIIilli !IIliif!Illlllll lilllfillll!
ORION"III1111iilIIIIINiili1111111111111111NIIIIrlllllll!!!A QliNiNl,111
INNIIIIlNIIIIINI"'4.. .IIIII'111 El''!l EIIIllllhl-1111IINllINitE i°I Ilil
nmm la r r.ImIINIIINIINIIIIl i iiin iIIIIIIIIIINNIIIN llllllllml IIINlliillll N
i Nmlmlllml Nlllr l i1 1111111,1 111m1mi;;1111111111! :;NI 1N.1
NNImIINmNfll IIN D lIIINIIIIIInglNllli i.IIIIIlIlIIIII INIIN .:NI
Nmlmlmll!!VII 11111E111 IIm NIIIIIIII
NIII INIIIINIIII;:IIIIINIIIIIIINIIm11 I: f111111 1NIIIIIN
i . - ' mIIIINIi mlll INIImIINllli!IIIIIIIIII II!!lIIIIIcII?±IllNlllllllmll
immilNNlllulll llllllllNfllllfll11 1 lllliu111lIIIIIIyIIJAINlll 1illllllllll
co-
NNIINIIIIINIINIIII!IIIIIIIIIIIIIIIIIilllli lIIIIINI'lllll lliillllllllllllllllllt
f ,IINIIIIIIINIIIIIIIIIII111111111111111IIINIIIIIIIi;!IIIIIII'Illilllll lllllmlNllll
1111111111111111111111111111
IIIINN11NINmNIIINIIIIIIIIIII111111111111111111i1li!IIIIfIi l1yllll11lNlllit
IINININNmINNINNIIIIIIIIN1 IllIIIIIIIIIIlIIINIIIIINIIIilllIh 11111""
sellIImiNNIINNIIIIIIIIIINNI!IIIINIIIIIIIIIIIII I::IIINIII:lIIIlNI::II
IIINNIIIIIINNmNNINIIIINIIIEIIINNIIIIINIII lilillllllliillll1111ii
A III! Ilmiu11lIIINI IINlIIIGIIIINIIIINIIIII IIIIIIIINIIII NmNNI
I
E.3
1
ml 11Nounmumm'Mqmpl I
millHERE
A I I I HII Nol
I IN11,, 11111 in oil I I MI
HIM 91
uf
11 NO I
I I I OR 1
III
IN 11 pull I I Jill 1111
101 11 Hill UP 11 I I
IINI. ` :
UP
IN 111111111
IN 11 1111111 41111111111111111111 UP I 11111111 illioul
lull IN 1111-1 oil III polill
NN IIIIIIII-11111milill mi. 11 16,1T I ON
I Hill I UP
1111 11111m, " 11"OPIUM
III R UP
HI, oil IIIoil11111111
111IM1111111
11
11 ,?,1
0 Rill 1111111111 oil I I I m DRUM
IN
d
IN
NOEL
E.3
t•
3
t.
i
tal
TI
fb
ost
d ( / /,•tea
I i i i
3
z to
JS
N I3IttFn
lz
t
4 ro 1
o
rfl
ILL
Z iI
t
t
6 mob'® f: _. I _ --•1--t-•
4 m N:
1
0
a
OD
1
cam: tj lon m y
HZ Z
r_fn 1.R 00
A ICP
r• a m 111
v 9I ;r m
IA
f• :z .p ) li j ' Z 4,•
i d K C
E.3
D
D
f'J4 AV
K t- C*Ll
wuoD
5 TH 711
T
F
ITN In
0ArIaNME
PS.PSL.CO EUT..aWAYSubsto.
iN
CO-A F5 LEMF'TrL7 CO.7!--AAA -
RE N70N Vit I AGE EVILLE
1 MTPCL.
p eklm,
NNK
0 Subst PONDEROSA ESTATES AREA
S Pt A. _QlABU
W J
E T.ha
w i, SM TRANSFERRED TO RENTON
t j
SUBSTA.VALLL V
CORR. "I Esmr.ts lb
ui 0
11TH ST I@IN3T.J\
0 -Ar7-
3 a Pork
z
I
3i zV .11 DR.
FO PACIFIC N.W PIPE LINE
TH SEA** 2
160TH Si
v., sw
4 C15Alf
z (Q fz 3T.
4-413liCly'diA,Slop E 162 ND 5T.
4
Span f*6' x
lul ".C? I I w
Lr-4f 3 0 36049
A 3T. I %L PC I•
1 57
13
43 N 3
3 lz
2
m
j
x33IA5 C
51.16710t
6
1 4 5
1p
168TH T
u
6 4 S.E.169THTG1145 > z V)
I
a ID 3T U)
B SIRONDLE23EVERETT.
WIATT 19
4
3 PL
0C6_ Q(
T
41 Z 0 ul40
CL kp F_
Az
n II
12 15 ILI?
lo:
13 1 NEILL b 7:Vff END STII ;TOO
cn THOMAS 39 LL. w>\In M HERBERT 34 I NER FLO N- z
asCffA-IRT L'E-9 N 10- 0z 3 c) G
31,
m 9 ,n
U`)!V) \
V)-i DIVELBIS CO O'n . ! -,16
uJ u_ 1)
k
IDS
cr -w
AHL
UJ A
w
0 ENir_ Y. 15
1411
48 FOE I vi
3 2 1 27 4461 - 1 6 5TG1 r
a_j I Z7026ALEN CIDEM 2,LUND 120 w
j>Cb q _J X
44 In CORPLd Z_Z & I
1,54 m 4
44
7B
z
7 m
51
U, ROY vy
go t u 9 HUNTER —
I /(JJ 1 UN !24 6 45r/ 62
I I \4D r NNED6BE0S.E. I 90TH ST
46 METR030 34 FS.... d4\' 20* 16
A N or AV P.
0 FED. I
2 LISui
C,3 14 xC,GP4 e687L131
STA Ni(
nL
6.::..Jo4mS8?,
ROCKEY a/
Ct; 111" 9 CIDEM
COULON
41H KMAN 6
w
CORP
0+ ,p
PINA ALL NBACH 0---MR EL166 LEGEND V.
16 6 F-OURNIE 70
OR H
c_
IF
AL 80 R- 0
41
M EAP
D i x HARRIET" 40
AA S, 171 W SODS CREEK CORPORATE BOUNDARY ar
H;'6HRSSE KELLY LEO 118 "t,NO j
tl--R50N 97 WERT
WM m nouns RENTON CITY LIMITS
C60:•3 W 232 RUTH
RUTH 183 1 PROPOSED SERVICE BOUNDARY BETWEEN se
7 FK.31 I CITY OF RENTON AND S.C.W.S.D. 17 1?9A.
27 FALL
N ELI ILI UNIOR
j <0 4 H Rz -
1 In l H SCH.0 a-cxe26239132 q Fi4r b.l. 6 ATCH I F _
a n 13
ET,60 6,SPRINGBROOK AREA
3
HAN d' 1 w
3 QRP )F 1,
10 PTRANSFERRED TO RENTON N
kN C IL 110LIC
4 7
14- K, A c BISHOP
1 13 1) L I IN C.
J., 16
14fit I TYE .1
Ln
Vi.,MR 1
zoC,
IMAURER
I9 l-i44E.8 87 e3o 4
2 30 11,9
SCALE 1':200'
6 ci 1201 1- T1,1111 n4irrk (p
M ql.il
0 33
ARLSON..
CI Y 0
CITY OF RENTON & SOOS CREEK
IMUGBROOK
34-FAR
35 36 WAT E R AND SEWER DISTRICT
r
6
Z-600-- SERVICE AGREEMENT
7 1-1 L . '
L
d q
a "1_
j,
CC
so
35 2k 3 -6-o 71
Iii Z C3 q 2-" SEWER16 >.--K Ng uj Cl 5I
j ng FR k-.Nf.v
6/N i-) ul 252
7 24 176 116 j _`44
36
1
38 TK FIGURE 11"
luix C.S.: ulsOHC.S.:VICTOR 14 CAPPELLOSLOANN5HUi( 12<
Z 48DIAMBRI 1 37
45
ry Ll SE 4_5 Hedges & Roth Engineering! Inc. ` 20
Q¢I .P CAS AA /00 7/66 CONSULTING ENGINEERS • PLANNERS • SURVEYORS
3
U;3&2 KIRKLAND,WASHINGTON (206)827-8793 (206)682-7426 1-800-835-0292W
J_
Att
8 CADE LA
JAD 7 691 Si APTS H L It
r-
f 3 =) v5v PH C,9,
31 ki a: a:6 RAN TI 10W 3
1 s
m
4
a 753vaspD15a
OSKE 1* f 208rH
1(,-,l I I I I J?71 1 11 tm, I I LA 11 1 1 17 1-
E.3
ORIGINAL'
CAG-91-083 Addendum 1-04
FIRST ADDENDUM TO
CITY OF RENTON & SOOS CREEK WATER AND SEWER DISTRICT
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
THIS ADDENDUM, made and entered into this -°6 day of
2004,by and between the CITY OF RENTON,a Washington
muni 1pal corporation, hereinafter referred to as "the City", and SOOS CREEK WATER
AND SEWER DISTRICT, a Washington municipal corporation, hereinafter referred to as j
the District", both being duly organized and existing under and by virtue of the laws of the
State of Washington,
WITNESSETH:
WHEREAS,with effective date of the
6th
day of August, 1991,the City and the District
entered into the following agreement:
CITY OF RENTON & SOOS CREEK WATER AND SEWER DISTRICT
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
1991 AGREEMENT); and
WHEREAS, by mutual agreement, in 1997 the City and the District amended the
boundaries as contained in the Agreement by the execution of the following agreement
CITY OF RENTON and SOOS CREEK WATER AND SEWER DISTRICT
1NTERLOCAL AGREEMENT FOR THE
ESTABLISHMENT OF SERVICE BOUNDARIES
1997 AGREEMENT); and
WHEREAS, the 1997 AGREEMENT left all obligations of the 1991 AGREEMENT
intact, changing only the service area descriptions of the 1991 AGREEMENT; and
First Addendum to Renton/Soos Creek Agreement for the
Transfer of Facilities and Establishment of Service Area Boundaries- 1
E.3.1
WHEREAS,the parties now desire to modify the 1991 AGREEMENT as to both terms
and service area; and
WHEREAS,the 1991 AGREEMENT as modified by the 1997 AGREEMENT,and by
this Addendum, will continue to provide for maximum efficient use of existing and future
facilities, and orderly and efficient water and sanitary sewer system planning.
NOW, THEREFORE:
IT IS HEREBY AGREED by and between the parties hereto as follows:
1. Sale of Springbrook Area Sewer System to Renton. The parties have agreed that in
consideration of the mutual agreements contained herein,that all payment obligations contained
in Section 6. and Section 7. of the 1991 AGREEMENT regarding the sale of the Springbrook
Sewer System to Renton shall be deemed to have been satisfied in full, and Renton shall have
no further payment or accounting obligation there for.
2. Amended Terms for Service and Payment by District for Stonehaven Area. The
parties agree that as an alternative the District may connect the Stonehaven and adjacent area,
as shown on Exhibit "A" which is by reference incorporated herein, to the South 47th Street
sewer line of Renton, generally in the manner shown on said Exhibit. In the event of such
alternate connection,and in consideration thereof,the District shall pay one half of the General
Facilities Charges it collects from such area to Renton,after the property owner has made such
payment to the District. Total payment will be dependent upon the number of units utilizing
such alternate connection, when the charge is paid,the rate at the time of connection,and the
number of units developed.
3. Termination on Build-out. The terms hereof with regard to the Stonehaven and
adjacent area shall terminate and be of no further force or effect upon completion of build-out
within that area.
4. Remaining Obligations Intact. Nothing herein shall be construed to alter the rights,
responsibilities,liabilities,or obligations of either the City or the District pursuant to either the
1991 AGREEMENT or the 1997 AGREEMENT,previously executed by the parties, except
as specifically set forth herein.
Approved by Resolution No. 3681 of the City Council of the CITY OF
RENTON, Washington, at its regular meeting held on the 22nd day of
December 2t)r)4 2003
First Addendum to Renton/Soos Creek Agreement for the
Transfer of Facilities and Establishment of Service Area Boundaries- 2
E.3.1
0
CITY OF RENTON
By: G
Title: Kathy Keolker-Wheeler, Mayor
Attest:
City Clerk - Bonnie I. Walton
Approved by Resolution No. 2545-S of the Board of Commissioners of SOOS
CREEK WATER AND SEWER DISTRICT of King County, Washington, at its regular
meeting held on the 7th day of January 3
2004
SOOS CREE "ER D SE R DISTRICT
w
By.
Philip Su Ivan, President of Board
By:
etr m a uzl Secretary of Board
Randy Reece', Acting
First Addendum to Renton/Soos Creek Agreement for the
Transfer of Facilities and Establishment of Service Area Boundaries - 3
E.3.1
CAG-91-083 Addendum 1-04
R
S. 47TH ST
000,
SE 185TH
j
SEA 186TH S
LU
r i
iI
t 187TH PL
Q
SE 188TH ST. 1
N
TH SEi LOTS
TEMP(SRARILY
SERVED BY
GRINDER PUMP5
lie
SE 1bOTH:. ST
r SE T9. ST
F
P4
r i
CITY OF RENTON/SCWSD
INIEFLLO AL I
Cl
I
SERVICE
1 tE 11926, ST I
I
BOUNDARIES.
EXHIBIT A
LEGEND
asoun.a.wai
r • Y.PwYwa.wu t--
t,Q
ice Usnc ar.nn runFJ
M—tsrro vein 1
uumn nns+vn i
wu rro
r.
E.3.1
OAG-91-083, Adden #2-08
2008 ADDENDUM TO
CITY OF RENTON & SOOS CREEK WATER AND SEWER DISTRICT
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
THIS ADDENDUM, made and entered into this A8'
A
day of
QA,Q44 2008,by and between the CITY OF RENTON,a Washington
inunicipif core ration, hereinafter referred to as "the City", and SOOS CREEK WATER
AND SEWER DISTRICT, a Washington municipal corporation,hereinafter referred to as
the District", both being duly organized and existing under and by virtue of the laws of the
State of Washington,
WITNESSETH:
WHEREAS,with effective date of the 6`
h day of August, 1991,the City and the District
entered into the following agreement:
CITY OF RENTON & SOOS CREEK WATER AND SEWER DISTRICT
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND FOR
THE ESTABLISHMENT OF SERVICE BOUNDARIES
1991 AGREEMENT); and
WHEREAS,by mutual agreement,the Agreement has been modified from time to time
as to the boundaries of the City and District service areas to reflect service issues regarding the
timing of various developments by the City and the District; and
WHEREAS, the parties now desire to again modify the AGREEMENT as to service
area; and
WHEREAS,the 1991 AGREEMENT,as modified by this Addendum,will continue to
provide for maximum efficient use of existing and future facilities, and the orderly and
efficient water and sanitary sewer system planning.
NOW, THEREFORE:
i
i
i
2008 Addendum to Renton/Soos Creek Agreement for the
Transfer of Facilities and Establishment of Service Area Boundaries - 1
E.3.2
IT IS HEREBY AGREED by and between the parties hereto as follows:
1. Service Area Boundaries. The parties have agreed that in consideration of the
mutual agreements contained herein, the service area boundaries between the City and the
District shall be modified as shown in Exhibit A hereto, which is incorporated herein by this
reference.
2. Amended Terms for Service by District. The parties agree that the District
may install a mainline sewer line in South 28`'Street,which may serve into the City's sewer
collection system.
3. Amended Terms of Payment by District. In consideration of the foregoing,
the District will pay 50%of the collected General Facility Charges collected for the lots that
connect to a mainline sewer line to be installed in South 28`h
Street to the City; such lots are
identified in Exhibit B hereto, which is incorporated herein by this reference.
3. Remaining Obligations Intact. Nothing herein shall be construed to alter the rights,
responsibilities,liabilities,or obligations of either the City or the:District pursuant to either the
1991 AGREEMENT, or any amendments thereto, except as specifically set forth herein.
Approved by Resolution No. 3957 of the City Council of the CITY OF
RENTON, Washington, at its regular meeting held on the J
M day of
2008.
CITY OF REN ON
By:
Title: Denis Law, Mayor
Attest: l(JCz—Ori-
CityClerk — Bonnie I . Walton
2008 Addendum to Renton/Soos Creek Agreement for the
Transfer of Facilities and Establishment of Service Area Boundaries-2
E.3.2
Approved by Motion of the Board of Commissioners of SOOS CREEK WATER
AND SEWER DISTRICT of King County, Washington, at its regular meeting held on the
S day of /' Al2008.
SOOS CREEK WATER AND SEWER DISTRICT
By: r L
Ron Speer, Dist ' t Manager
I
2008 Addendum to Renton/Soos Creek Agreement for the
Transfer of Facilities and Establishment of Service Area Boundaries - 3
E.3.2
EXHIBIT "A"
EXISTING SERVICE BOUNDARY
REVISED SERVICE BOUNDAR l'
EE AREA TRANSFERRED FROM SICSWD
TO RENTON
S 27th St
tE , E3'tE Etf 4'E"t
4E E
SEE IB)3rd. EI _ E 1, ;g
a t.
W
1e5 h St
E'.
S 9 h St
W
Q
0 0 400
1 4,800
n
E.3.2
EXHIBIT "B"
EXISTING SERVICE BOUNDARY
REVISED SERVICE BOUNDARY
3 AREA OF SCSWD TO SERVE INTO
E
RENTON SYSTEM
S 27th St
O MOP
k
j
mill,
o
O
00
S
S 9hSt
W
0 0 100
f
1418
E.3.2
E.4
E.4
E.4
1CAG03 97
CITY OF RENTON AND
SKYWAY WATER AND SEWER DISTRICT
FOR THE ESTABLISHMENT OF WATER AND SANITARY SEWER SERVICE
BOUNDARIES
THIS AGREEMENT is entered into this day of 0 c' ,
200 .3 , by and between SKYWAY WATER AND SEWER DISTRICT, a Washington
municipal corporation, hereinafter referred to as "SWSD", and the CITY OF RENTON, a
Washington municipal corporation, hereinafter referred to as "RENTON".
WITNESSETH:
WHEREAS, SWSD is qualified to provide water and sanitary sewer service
within its prescribed area; and
WHEREAS, RENTON is qualified to provide public services, including water and
sanitary sewer service, within its prescribed areas; and
WHEREAS, the former Skyway Water and Sewer and Bryn Mawr-Lakeridge
Water and Sewer Districts have officially merged, with the district subsequently
retaining the name of Skyway Water and Sewer District; and
WHEREAS, the former Skyway Water and Sewer District had existing water and
sewer boundary agreements with RENTON; and
WHEREAS, SWSD provides water and sanitary sewer service in an area
adjacent to and within RENTON's corporate boundaries and it is in the public interest
for the parties herein to enter into an agreement to provide for the efficient planning and
development of new water and sanitary sewer services in areas which may be served
by either, or both, of the parties; now, therefore,
IT IS HEREBY AGREED by and between the parties hereto as follows:
1. Water Service Area Boundary Between RENTON and SWSD.The attached
legal description, Exhibit A, describes the line separating the RENTON water
service area from SWSD water service area. The attached map, Exhibit B,
depicts the line separating the RENTON water service area from SWSD water
service area. RENTON shall provide water service for the area generally South
and East of the line illustrated. SWSD shall provide water service for the area
generally North and West of the line illustrated.
Any new construction, upgrading, or replacements within the RENTON City
Limits by SWSD for water service shall be in compliance with RENTON design
and construction standards then in effect or SWSD design and construction
standards, whichever are the higher design and construction standards
including: materials, techniques, and fire flow.
Page 1 of 5
E.5
2. City of Seattle Water Service Area: The City of Seattle (SEATTLE) currently
provides direct water service to portions of the service area being discussed in
this agreement. These areas are not contiguous to the remainder of SEATTLE's
service area, but have been served by SEATTLE for some time. These areas,
herinafter the "Transfer Area", are identified in the Skyway Coordinated Water
System Plan, as to be transferred to the appropriate purveyors as feasible and /
or required by new development or annexation.
SEATTLE is not a party to this agreement and the agreement should have no
direct effect on SEATTLE. This agreement does not directly discuss the transfer
of the SEATTLE service areas. This agreement only identifies the boundaries of
the local purveyors to whom the service areas would belong to when transferred.
3. Overlaps in Water Service Within Transfer Area: Any overlaps in water service
in the Transfer Area will be addressed at the time of the actual transfer and will
not be determined as part of this agreement. RENTON and SWSD mutually
agree to notify the other and receive concurrence from the other prior to
providing service to any additional customers within the Transfer Area.
Properties within the transfer area are depicted on Exhibit B
4. Transfer of certain Seattle Public Utilities Water Mains Within and Along the
Transfer Area to RENTON: SWSD agrees that RENTON and Seattle Public
Utilities have the right and would not be violating the intent of this agreement to
transfer the ownership of the following water mains from Seattle Public Utilities
to RENTON:
a) the twelve inch diameter water main which runs southeasterly along
Martin Luther King Way from the intersection of
68th Avenue South and
Martin Luther King Way to the intersection of Martin Luther King Way and
South 135th Street then northerly within an easement to South 133`
d Street
then easterly along South 133`d Street to the intersection of South 133`d
Street South 132"d Street, and South 134th Street where it is reduced to
an eight inch diameter water main, and
b) the eight inch diameter water main which runs easterly along South 132"
d
Street from the twelve inch by eight inch reducer at the intersection of
South 133`d Street South 132nd Street, and South 134th Street to the
intersection.of South Langston Road and South 134th Street, and
c) the water main that varies in diameter from eight inches to four inches to
six inches which runs easterly along South 135th Street from the
intersection of South
135th Street and Martin Luther King Way to the
intersection of South
135th Street and
80th Avenue South then northerly
along
80th Avenue South to the intersection of
80th Avenue South and
South 134th Street.
Page 2 of 5
E.5
0 0
5.Existing SWSD Water Service Connections in RENTON Service Area: SWSD
currently provides water service to properties inside RENTON's water service
area. RENTON consents to SWSD continuing to provide water service to these
properties. The properties are listed in Exhibit E and depicted in Exhibit B.
6.Existing RENTON Water Service Connections in SWSD Service Area: RENTON
currently provides water service to properties inside SWSD's water service area.
SWSD consents to RENTON continuing to provide water service to these
properties. The properties are listed in Exhibit F and depicted in Exhibit B.
7. Overlap Areas: It is understood that RENTON and SWSD will continue providing
service within the service area boundaries of the adjacent water utility, as
defined in Sections 5 and 6 of this agreement, and which shall be known as
overlap areas. RENTON and SWSD agree that any retail water service line
extending outside of the service area boundary, as set forth in Section 1, shall
be phased out and service transferred to the adjacent utility by mutual
agreement.
8. Sewer Service Area Boundary Between RENTON and SWSD. The attached
legal description, Exhibit C, describes the line separating the RENTON sewer
service area from SWSD sewer service area. The attached map, Exhibit D,
depicts the line separating the RENTON sewer service area from SWSD sewer
service area. RENTON shall provide sanitary sewer service for the area
generally South and East of the line illustrated. SWSD shall provide sanitary
sewer service for the area generally North and West of the line illustrated.
Any new construction, upgrading, or replacements within the RENTON City
Limits by SWSD for sewer service shall be in compliance with RENTON design
and constructions standards then in effect, or SWSD design and construction
standards, whichever are the higher design and construction standards
including: materials and techniques.
9. RENTON's Service Area Boundaries Overlap SWSD's Corporate Boundary:
There are areas where RENTON's service area boundaries and SWSD's
corporate boundary overlap. RENTON and SWSD acknowledge that, with
regard to providing service, it is the water and sanitary sewer service boundaries
which govern, not the corporate boundaries.
10. Rescission of Prior Agreements: The former Skyway Water and Sewer District
and RENTON entered into an agreement relating to water service area
boundaries between the two jurisdictions dated February 2, 1998. That
boundary has been incorporated into the SWSD boundary adopted by this
document and the agreement is hereby rescinded.
The former Skyway Water and Sewer District and RENTON entered into an
agreement relating to sanitary sewer service area boundaries between the two
jurisdictions dated June 9, 1994. That boundary has been incorporated into the
Page 3 of 5
I
E.5
a
SWSD boundary adopted by this document and the agreement is hereby
rescinded.
11. Maintenance of Existing Facilities: SWSD and RENTON will each maintain their
own facilities, according to industry standards.
12. SWSD Comprehensive Water and Sewer Planning. SWSD will submit, to
RENTON, all future Comprehensive Water and Sewerage Plans and
amendments thereto involving area and/or improvements within RENTON City
Limits. Said submission of the SWSD Plan(s) is to assure consistency with
adopted city plans, policies, and land use controls, assist in the review of new
development proposals and right-of-way construction permits, and to fulfill the
responsibilities set forth in RCW 57 and King County Title 13. As new facilities
are planned, constructed, maintained, and/or replaced within RENTON, they
shall comply with RENTON design and construction standards then in effect, or
SWSD design and construction standards, whichever are the higher design and
construction standards.
13. Extension of Utilities Across Properties. RENTON and SWSD agree that they
will require property owners who must extend facilities to service their property in
a comprehensive fashion up to and including extending said facilities to the far
side of the property, when appropriate, to provide a connection point for the
future (or existing)facilities of the next property.
14. Franchise Agreement. Upon RENTON annexing property within the SWSD
service area, RENTON shall grant SWSD, for the purposes of continuing use of
rights-of-way, a temporary franchise for utility facilities within the annexed
territory. This franchise shall have the same provisions as stated in the
franchise between King County and SWSD and have a term not to exceed 3
three) years.
RENTON and SWSD will immediately begin negotiations for a new franchise for
the purposes of rights-of-way use for SWSD service area within RENTON. The
new franchise shall be negotiated within three years.
Upon any subsequent annexations by RENTON within the SWSD service area,
RENTON shall amend the franchise to include the annexed area, in order to
maintain one franchise agreement. The franchise shall maintain the remaining
balance of the term of the franchise. The franchise should include any updated
provisions as approved by RENTON and agreed to by SWSD.
Any franchise agreement issued hereunder shall be consistent with the
respective comprehensive plans of the parties and State law.
15. Governmental Approvals. The parties will give notice of the adoption of this
Agreement to Metropolitan King County, to the Department of Ecology, to the
Department of Health, and to any other agency with jurisdiction, and shall
Page 4 of 5
E.5
0
cooperate and assist in any reasonable manner in procuring any necessary
l
approvals hereof by those agencies.
16. Miscellaneous. This Agreement constitutes the entire agreement of the parties,
concerning the subject matter herein, and there are no representations or oral
agreements other than those listed herein, which vary the terms of this
Agreement. Future agreements may occur between the parties to identify, agree
upon, or transfer service areas and/or facilities. This Agreement shall have a
term of 25 (twenty-five) years.
17. Obligations Intact. Nothing herein shall be construed to alter the rights,
responsibilities, liabilities, or obligations of either SWSD or RENTON regarding
provisions of water or sewer services to the properties described herein, or other
properties, except as specifically set forth herein.
DATED this 31 st
day of kJ,200..x.
Authorized by Resolution No. 3675 of the City Council of the City of Renton,
Washington, at its regular meeting held on 8th day of December
200 3.
CITY OF NTON
C:;Z a-3/aoo3
Jesse 1fdriner, Mayor Date
ATTEST:
Q_y-
Bonnie I. Walton, City Clerk Date
APP ED A AL FORM:
Lawrence J. Wa en, City Attorney
Approved by Resolution No. 03 - -3`/ of the Board of Commissioners of
SKYWAY WATER AND SEWER DISTRICT of King County, lyvashington,
adopted at its regular meeting held on day of 2gL 20(5.
SKYWAY WATER AND SEWER DISTRICT
By:
4'
Title: 6e4
Page 5of5
E.5
CAG-03-197
EXHIBIT A
SKYWAY WATER AND SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND ESTABLISHMENT OF SERVICE BOUNDARIES
WATER SERVICE BOUNDARY LINE)
A water service area boundary line between Skyway Water and Sewer District and the City of Renton
through C.E. Brownell Donation Land Claim No. 41 in Sections 13 and 14,Government Lot 8 and the
Northeast quarter of Section 13,the Southeast quarter of Section 12, all in Township 23 North, Range 4
East,W.M., and the Southwest quarter and Northwest quarter of Section 7,all in Township 23 North,
Range 5 East,W.M.,described as follows:
Beginning the aforementioned water service boundary line in the Southeast quarter of said Section 14, at
the intersection of the northeasterly right of way margin of Burlington Northern Railroad with the
northwesterly right of way margin of the vacated street adjoining Lot 33 of Junction Addition to Seattle,as
recorded in Volume 12 of Plats,Page 75, Records of King County,Washington, all situated in C.E.
Brownell Donation Claim No. 41,as recorded in the Records of King County,Washington, said
intersection also being the existing City limits of Renton as annexed by Ordinance No. 4578 and the
existing City limits of Tukwila as annexed by Ordinance Nos. 1503 and 1515;
Thence northerly along said northwesterly right of way margin of said vacated street and said existing City
limits of Tukwila and Renton,to an intersection with the southwesterly right of way margin of Beacon Coal
Mine Road S. Rev.;
Thence northwesterly and northerly along said southerly right of way margin, and said existing City limits
of Tukwila,to an intersection with the south line of the north half of said Donation Claim No. 41;
Thence westerly along said south line,and said existing City limits of Tukwila,to an intersection with the
easterly right of way margin of the Union Pacific Railroad;
Thence northwesterly along said easterly right of way margin and said existing City limits of Tukwila,to
an intersection with the north boundary line of said Donation Claim No. 41;
Thence easterly along said north boundary line and said existing City limits of Tukwila,to an intersection
with the southwesterly right of way margin of Beacon Coal Mine Road S. Rev.;
Thence continuing easterly along said north boundary line, crossing said right of way,to an intersection
with the northeasterly right of way margin of Beacon Coal Mine Road S. Rev.;
Thence southeasterly, southerly,westerly, southerly and southeasterly, along said northeasterly right of
way margin,to the most southwesterly corner of Lot A, King County Lot Line Adjustment No. 8612009,
as approved by King County,Washington on February 4, 1987;
Thence northeasterly along the southerly line of said Lot A,to an intersection with the south line of the
north half of said Donation Claim No. 41;
Page 1
E.5
i
Thence easterly along said south line of the north half of said Donation Claim No. 41,to an intersection
with the westerly right of way margin of 68th Avenue S.;
Thence northeasterly along said westerly right of way margin,to an intersection with the southerly right of
way margin of Martin Luther King Junior Way South(State Road No. 2),the center line of said Martin
Luther King Junior Way South right of way being 110 feet northerly of, as measured perpendicular to, said
southerly right of way margin;
Thence easterly along the easterly extension of said southerly right of way margin,crossing said 68`b
Avenue S.,to an intersection with the easterly right of way margin of said 68`''Avenue S.;
Thence northerly along said easterly right of way margin,to an intersection with the southerly right of way
margin of said Martin Luther King Junior Way South,the centerline of said Martin Luther King Junior
Way South right of way being 50 feet northerly, as measured perpendicular to, said southerly right of way
margin;
Thence southeasterly along said southerly right of way margin,to an intersection with the east line of the
west 419.61 feet of the northwest quarter of said Section 13;
Thence northerly along said east line,crossing said Martin Luther King Junior Way South,to an
intersection with the southerly right of way margin of South 133rd Street;
Thence easterly along said southerly right of way margin,to an intersection with the southerly right of way
margin of S. 134`h Street;
Thence northwesterly, crossing S. 134th Street,to the point of intersection of the northerly right of way
margin of S. 134th Street and the southerly right of way margin of S. 132nd Street;
Thence northeasterly along said southerly right of way margin of S. 132nd Street,to an intersection with
the westerly right of way margin of 76th Avenue S., said westerly right of way margin also being the west
line of the northeast quarter of said Section 13;
Thence northerly along said westerly right of way margin and said west line of the northeast quarter,
crossing S. 132nd Street,to an intersection with the southerly right of way margin of S. Langston Road
also known as John Langston Road No. 3 and 78th Avenue S. Extension Revision);
Thence easterly,northeasterly and northerly along said southerly right of way margin of S. Langston Road,
crossing said 76th Avenue S. and S. 13& Street,to the northwest comer of Lot 6, Block 7 of Earlington
Acre Tracts,as recorded in Volume 15 of Plats, Page 84, Records of King County,Washington;
Thence easterly along the north line of Block 7 of said plat,to the northwest comer of Lot 2 of said Block
7;
Thence southerly along the west line of said Lot 2,to an intersection with the south line of the north 100
feet of said Lot 2;
Thence easterly along said south line,to an intersection with the east line of said Lot 2;
Page 2
E.5
w
Thence northerly along said east line,to the northeast comer of said Lot 2 and a point on the north line of
said Block 7;
Thence easterly along said north line,to the northeast corner of Lot 1 of said Block 7, said northeast corner
also being a point on the westerly right of way margin of 80th Avenue S.,
Thence northeasterly, crossing 80th Avenue S.,to the point of intersection of the easterly right of way
margin of said 80th Avenue S. with the northeasterly right of way margin of Renton Avenue S., said point
of intersection also being a point on the west line of Lot 6, Block 2 of said plat;
Thence southeasterly along said northeasterly right of way margin,to an intersection with the west line of
Lot 3, Block 8 of said plat;
Thence northerly along the west line of said Lot 3,to the northwest corner thereof,
Thence easterly along the north line of said Block 8 and Block 9 of said plat,to the northwest comer of Lot
6 of said Block 9, said northwest corner also being the southwest corner of Lot 6, Block 1 of said plat;
Thence northerly along the west line of said Lot 6 of said Block 1, a distance of 88.16 feet;
Thence easterly, crossing said Lot 6 and Lots 5,4, 3 and 2 of said Block 1,to a point on the east line of
said Lot 2 being 95.86 feet northerly of the southeast comer thereof,
Thence northerly along the east line of said Lot 2, said east line also being the west line of Lot 1 of said
Block 1,to an intersection with the south line of the north 70 feet of said Lot 1;
Thence easterly along said south line,to an intersection with the east line of said Lot 1, said east line also
being the westerly right of way margin of 84th Avenue S.;
Thence northerly along said east line and said westerly right of way margin,to the northeast corner of said
Lot 1;
Thence northerly,crossing S. 128th Street,to the southeast comer of Lot 20 of the vacated.plat of
Clinkingbeards One Fourth Acre Tracts, as recorded in Volume 21 of Plats, Page 26,Records of King
County,Washington,in the Southeast quarter of Section 12,Township 23 North, Range 4 East,W.M.;
Thence northerly along the east line of said Lot 20 and said westerly right of way line of 84th Avenue S.,to
an intersection with the south line of the north 7 feet of said Lot 20;
Thence westerly along said south line and the westerly extension of said south line,to an intersection with
the west line of Lot 19 of said plat;
Thence northerly along the west line of said Lot 19 and Lot 2 of said plat,to the northwest corner of said
Lot 2 and the north line of said plat;
Page 3
E.5
Thence easterly along said north line,to an intersection with the east line of the west 195 feet of the south
half of the Northeast quarter of the Southeast quarter of the Southeast quarter of the Southeast quarter of
said Section 12;
Thence northerly along said east line,to an intersection with the north line of said subdivision;
Thence easterly along said north line,to an intersection with said westerly right of way margin of 84th
Avenue S.;
Thence northerly along said westerly right of way margin and its northerly extension, and in part,the east
line of Tract A of Mountain View Home Tracts,as recorded in Volume 74 of Plats, Page 28, Records of
King County,Washington,crossing S. 126`h Street,to an intersection with the easterly extension of the
northerly right of way margin of S. 126 'Street;
Thence westerly along said easterly extension and said northerly right of way margin,said margin also
being,in part,the south line of Lot 17 of Hilltop's Suburban Club,as recorded in Volume 77 of Plats,
Page 51, Records of King County,Washington,to the southwest corner of said Lot 17;
Thence northerly along the west line of said Lot 17,to the northwest corner thereof, said northwest corner
also being a point on the south line of Lot 16 of said plat;
Thence westerly along said south line of Lot 16,to the southwest comer thereof, said southwest corner also
being the southeast comer of Tract A of said plat;
Thence northerly along the east line of Tract A,to the northeast corner thereof, said northeast corner also
being the northwest comer of Lot 10 of said plat;
Thence easterly along the north line of said Lot 10,to the southwest comer of Lot 9 of said plat;
Thence northerly along the west line of said Lot 9,to the northwest comer thereof, said northwest comer
also being a point on the southerly right of way margin of S. 124th Street;
Thence northwesterly, crossing S. 124th Street,to the southwest corner of Lot 23, Block 60 of Bryn Mawr,
as recorded in Volume 5 of Plats,Page 58, Records of King County,Washington, said southwest comer
being a point on the northerly right of way margin of S. 124th Street;
Thence northerly along the west line of said Lot 23,to the northwest corner thereof,
Thence easterly along the north line of said Lot 23 and the north line of Lots 22 and 21 of said plat,to the
northeast corner of said Lot 21, said northeast comer also being a point on the westerly right of way
margin of said 84th Avenue S.;
Thence easterly, crossing said 84th Avenue S.,to the northwest corner of Lot 28, Block 61 of said plat,
said northwest comer also being a point on the easterly right of way margin of said 84th Avenue S.;
Page 4
E.5
0
Thence easterly alo the north line of said Lot 28 and the north line of Lots 27-15,inclusive,of said Block
61,to the northeast comer of said Lot 15,said northeast comer also being a point on the westerly right of
way margin of 85th Avenue S.;
Thence northerly along said westerly right of way margin, crossing S. 123rd Place, S. 123" Street and S.
122nd Street,to the northeast comer of Lot 15, Block 48 of said plat;
Thence easterly,crossing said 85th Avenue S.,to the northwest comer of Lot 38,Block 47 of said plat,
said northwest comer being a point on the easterly right of way margin of said 85th Avenue S.;
Thence continuing easterly along the north line of said Lot 38 and the north line of Lot 37 of said Block 47,
to the northeast comer of said Lot 37;
Thence southerly along the east line of said Lot 37,to the southeast comer thereof,
Thence easterly along the south line of said Block 47,to an intersection with the west line of Lot 25 of
King County Boundary Line Adjustment No. L96L0074,as recorded under King County Recording No.
9709189007;
Thence northerly along the west line of said Lot 25,to the northwest comer thereof,
Thence easterly along the north line of said Lot 25,to the northeast comer thereof
Thence southerly along the east line of said Lot 25,to the northwest corner of Lot 28 of said boundary line
adjustment;
Thence easterly along the north line of said Lot 28,to the northeast corner thereof, said northeast corner
also being the northwest corner of Lot 21 of said Block 47;
Thence easterly along the north line of said Lot 21,to the northeast comer thereof, said northeast corner
also being a point on the westerly right of way margin of 87th Avenue S.;
Thence southerly along said westerly right of way margin,to an intersection with the westerly extension of
the south line of Tract 1 of N.H. Latimer's Lake Washington Plat, as recorded in Volume 6 of Plats, Page
70, Records of King County,Washington;
Thence easterly along said westerly extension,crossing said 87th Avenue S.,to the southwest corner of
said Tract 1, said southwest comer also being a point on the northerly right of way margin of S. 122nd
Street;
Thence easterly along the south line of said Tract 1 and the south line of Tracts 2 and 3 of said plat and
said northerly right of way margin,to an intersection with the east line of the west half of vacated 90th
Avenue S.;
Thence northerly along said east line and the northerly extension of said east line,crossing S. 1215`St., and,
in part, along the existing City limits of Renton as annexed by Ordinance No. 2426,to an intersection with
Page 5
E.5
the south line of Lot 12, Lenz Farmette Tracts, as recorded in Volume 37 of Plats, Page 36, Records of
King County,Washington, said south line also being the northerly right of way margin of S. 121 st Street;
Thence westerly along said south line and said northerly right of way margin and, in part,said existing City
limits,to an intersection with the east line of the west 32 feet of said Lot 12;
Thence northerly along said east line and said existing City limits,to an intersection with the south line of
Lot 11 of said plat;
Thence westerly along said south line and said existing City limits,a distance of 32 feet,to the southwest
comer of said Lot 11;
Thence northerly along the west line of said Lot 11 and said existing City limits,to the northwest corner
thereof,
Thence easterly along the north line of said Lot 11 and said existing City limits,to the northeast corner of
said Lot 11, said northeast comer also being on the westerly right of way margin of Rainier Avenue N.;
Thence northerly along said westerly right of way margin and said existing City limits,to an intersection
with the south line of the Northwest quarter of said Section 7;
Thence westerly along said south line and the existing City limits of Renton as annexed by Ordinance No.
2019,to an intersection with the southerly extension of the west line of Lot 12, Block 40 of said plat of
Bryn Mawr;
Thence northerly along said southerly extension and along the west line of Lot 12, Block 40 of said plat,
and said existing City limits, crossing vacated S. 120th Street,to the northwest corner of said Lot 12, said
northwest corner also being the southeast corner of Lot 22 of said Block 40;
Thence westerly along the south line of said Lot 22, and Lots 23 and 24 of said Block 40,and the westerly
extension of said south line,and said existing City limits,to an intersection with a line lying 8 feet westerly
of and parallel with the west line of said Lot 24 and Lots 9 and 24 of Block 35 of said plat;
Thence northerly along said parallel line and said existing City limits,and in part,the existing City limits of
Renton as annexed by Ordinance No. 4090, crossing vacated S. 119th Street,to an intersection with the
southerly right of way margin of S. 118th Street;
Thence easterly along said southerly right of way margin and said existing City limits,to the northwest
comer of Lot 24 of Block 35 of said plat;
Thence northerly along the northerly extension of the.west line of said Lot 24, and said existing City limits,
to an intersection with the centerline of that portion of S. 118th Street(Irving Avenue,Wallace Street)as
vacated by Superior Court No. 156371;
Thence easterly along said centerline and said existing City limits,to an intersection with the southerly
extension of the west line of Lot 13, Block 30 of said plat;
Page 6
E.5
0
Thence northerly along said southerly extension and the west line of said Lot 13 and said existing City
limits,to the northwest comer of said Lot 13;
Thence easterly along the north line of said Lot 13 and the north line of Lot 14 of said Block 30 and said
existing City limits,to the northeast comer of said Lot 14,said northeast comer also being the southwest
comer of Lot 18 of said Block 30;
Thence northerly along the west line of said Lot 18,to the northwest corner thereof, said northwest corner
also being a point on the southerly right of way margin of Hawthorne Street;
Thence easterly along the north line of said Lot 18,and said southerly right of way margin,to an
intersection with the southerly extension of the west line of the east 15 feet of Lot 15, Block 25 of said plat;
Thence northerly along said southerly extension, crossing said Hawthorne Street,to an intersection with the
south line of said Lot 15 and the northerly right of way margin of said Hawthorne Street;
Thence easterly along the south line of said Lot 15 and the south line of Lot 16 of said Block 25,and the
easterly extension of said south line and said northerly right of way margin,to an intersection with the
centerline of 89th Avenue S.,as vacated by Superior Court No. 156371;
Thence northerly along said centerline,to an intersection with the westerly extension of the north line of Lot
5, Block 26 of said plat;
Thence easterly along said westerly extension,to the northwest corner of said Lot 5;
Thence continuing easterly along the north line of said Lot 5 and the easterly extension of said Lot 5, said
north line and easterly extension also being said existing City limits, crossing Rainier Avenue N. (Primary
State Highway No. 5, State Road 167),to an intersection with the easterly right of way margin of said
Rainier Avenue N., said intersection also being a point on the existing City limits of Renton as annexed by
Ordinance No. 1300;
Thence northerly along said easterly right of way margin and said existing City limits,to an intersection
with a line which is 5 feet south of and parallel with the common line between Lots 7 and 8, Block 18,Bryn
Mawr,as recorded in Volume 5 of Plats,Page 58, Records of King County,Washington;
Thence South 88°27'28"East, along said parallel line and said existing City limits, a distance of 89.23
feet,to the west line of Defense Plant Corp. 5-2443;
Thence North 05°16'51"East, along said existing City limits, a distance of 438.90 feet,to an intersection
with a line which is 2 feet south of and parallel with the common line between Lots 1 and 2, Block 17 of
said plat;
Thence North 40°09'47"East, along said existing City limits, a distance of 188.55 feet;
Thence North,along said existing City limits, a distance of 60 feet;
Thence North 29°00'40"West,along said existing City limits,a distance of 197.07 feet;
Page 7
E.5
0 s
Thence South 88 027'28"East, along said existing City limits,a distance of 355.00 feet,to a point on the
Inner Harbor Line of Lake Washington,as shown upon Sheet No. 26 of the Plat of Lake Washington Shore
Lands Survey 1921,as said plat was filed with the Auditor of King County,Washington, September 19,
1921,under Recording No. 1552504, said point being a distance of 92.62 feet along said Inner Harbor
Line from the angle point"862"on said plat, and the terminus of the herein described water service
boundary line.
Page 8
E.5
to5010011 111 1 1 1,/ III.
111 11© ..n,
mill
OM
i 111111
I$L01
ate milli
OEM
MISS'
111 N
I r p Ir,1=--''-111 11- ®1/ 11
III arm RIE ME
illll i MA mmnu 1 111111111 m=m ii I '°11 .. .r: _rte `
I IUl IrL I tJ ll lulu C' 11 .1111 11 11 11 111:.1 I!1 ill 1 !!1: i ii 0
1/ 111111 IIIII: 11. :ti 1111 1111 1 1 1111 .tl REW =-T-I°na- 1 l. OWES FIX7:1 .•d .-: .r_r 111 ® -i" _® •,•j` '\,
rClJiii 1 l] '
1 a .R7 _' .. .
r I ,ma® ltd , ,
IL'' +111 s• . , - i :
1 11111= il= ="! ! : :- ! Dill 1 : 1 1 oil
EMT will
V.
y l• : i
V.
1
w •• „ ice
111111111 - :sum 11 II r •1
111111111
s°r111 1111/ `' t/. ,wi' , ,/••
i 111 — . =
rf. ©11 'IIIE ` ` ` _ 1''
SEES
a i C :1 :111111/ ' 1111f1 11'11111!!, r 111 1 ii11111: 1111111111 111111111: +`'' , E c iii11111 oil 11 1r1F t , r r r
Nor
111111111 y 11W c i111e ' ;
1==:
i' .. 1111111111 1111111111 .,•`''.1i1 i1 i i=
11111111111 ' :;, ,.s FA
I
iw'
i
Div i, V s1, " .
rryl
IIIII r ://1111 ,,i ii i, 1
1111111.. = ='" 11 i y .. 1I _
iiiiii = iiiii l , s I il'1 .- ii 1 j
sliElfi!!. - i ysl[I I R yr%1111 : IIIIIIIIIIri, : r j I
111 _ r
7111 11
1111111 m
Iii ' 1 .. 1 .
Ida 1111111 , 1
1 r' 7 Imo, ..
may• i.:ii I film
row
Me.
01 .,
MEN
SO V
NO
i1 1 rte
E.5
CAG-03-197
EXHIBIT C
SKYWAY WATER AND SEWER DISTRICT AND CITY OF RENTON
AGREEMENT FOR THE TRANSFER OF FACILITIES
AND ESTABLISHMENT OF SERVICE BOUNDARIES
SEWER SERVICE BOUNDARY LINE)
A sanitary sewer service area boundary line between the Skyway Water and Sewer District and the City of
Renton through C.E. Brownell Donation Land Claim No. 41 in Sections 13 and 14,Government Lot 8 and
the Northeast quarter of Section 13,all in Township 23 North, Range 4 East,W.M., King County,
Washington and the Southwest quarter and the Northwest quarter of Section 7,both in Township 23 North,
Range 5 East,W.M.,King County Washington,described as follows:
Beginning the aforementioned sanitary sewer boundary line in the Southeast quarter of said Section 14, at
the intersection of the northeasterly right of way margin of Burlington Northern Railroad with the
northwesterly right of way margin of the vacated street adjoining Lot 33 of Junction Addition to Seattle, as
recorded in Volume 12 of Plats,page 75,Records of King County,Washington, all situated in C.E.
Brownell Donation Claim No. 41, as recorded in the Records of King County,Washington, said
intersection also being the existing City limits of Renton as annexed by Ordinance No. 4578 and the
existing City limits of Tukwila as annexed by Ordinance Nos. 1503 and 1515;
Thence northeasterly along the northwesterly right of way margin of said vacated street and said existing
City limits of Tukwila and Renton,to an intersection with the southwesterly right of way margin of Beacon
Coal Mine Road S. Rev.;
Thence northeasterly along said existing City limits of Renton at an angle perpendicular to said southerly
right of way margin,a distance of 40 feet,to an intersection with the northerly right of way line of said
Beacon Coal Mine Road S. Rev.,
Thence southeasterly along said northerly right of way margin and existing City limits,to an intersection
with a line dividing Lot 32 of said plat as described by a deed of conveyance to Charles Monster by Oregon
and Washington Railroad Company dated June 19, 1923;
Thence northeasterly along said dividing line and the existing City limits,crossing 68th Avenue South,to
an intersection with the easterly right of way margin of said 68th Avenue South;
Thence continuing northeasterly along said dividing line and the existing City limits of Renton as annexed
by Ordinance No. 4642,to the northeast comer of said Lot 32, said northeast comer also being a point on
the north line of said plat and also being a point on the northerly right of way margin of South 137th Street;
Thence easterly along said north line of said plat and said northerly right of way margin,to the southwest
corner of the condominium plat of Empire Estates, as recorded in Volume 28 of Condominiums,Pages
106-120,inclusive,Records of King County,Washington, in the Southwest quarter of said Section 13;
Page 1
E.5
Thence northerly,,easterl and northerly along the west line of said condominium plat,to an intersection
with the southerly right of way margin of Martin Luther King Way South(also known as Empire Way
South and State Road No. 2), in the Northwest quarter of said Section 13;
Thence continuing northerly along the northerly extension of said west line,to an intersection with the
centerline of said Martin Luther King Way South;
Thence southeasterly along said centerline,to an intersection with the southerly extension of the west line of
Lot 1, Block 2 of Stiles View Tracts, as recorded in Volume 46 of Plats, Page 85, Records of King County,
Washington;
Thence northerly along said extension and the west line of said Lot 1,to an intersection with the south line
of the north 180 feet of said Block 2;
Thence easterly along said south line,through Lots 1-7, inclusive,of said Block 2,to an intersection with
the east line of said Lot 7, said east line also being the east line of said Donation Claim and the west line of
Lot 8, Block 4 of R.L. Haddock Addition to Earlington,as recorded in Volume 38 of Plats, Pages 4-5,
Records of King County in Government Lot 8 of said Section 13;
Thence northerly along said west line of said Lot 8 and said east line of said Donation Claim,to the
southwest corner of Lot 1 of King County Short Plat No. 982004, recorded under King County Recording
No. 8301040882;
Thence easterly along the south line of said Lot 1 and the easterly extension of said south line,through Lots
8-6, inclusive,of said Block 4,to an intersection with the east line of said Lot 6;
Thence northerly along said east line to the northeast corner of said Lot 6;
Thence northerly,crossing S. 135th Street,to the southwest comer of Lot 5,Block 3 of said plat;
Thence northerly along the west line of said Lot 5 and the northerly extension of said west line, crossing S.
134th Street and the Cedar River Pipeline right of way,to an intersection with the northerly right of way
margin of said street and said pipeline;
Thence southeasterly along said right of way margin of said street and pipeline,to an intersection with the
westerly right of way margin of 76th Avenue S., said westerly right of way margin also being the west line
of the Northeast quarter of said Section 13;
Thence northerly along said westerly right of way margin and said west line,crossing S. 132nd Street,to
an intersection with the southerly right of way margin of S. Langston Road(also known as John Langston
Road No. 3 and 78`h Avenue S. Extension Revision);
Thence easterly,northeasterly and northerly along said southerly right-of-way margin of S. Langston Road,
crossing said 76th Avenue S. and S. 130th Street,to the northwest comer of Lot 6, Block 7 of Earlington
Acre Tracts,as recorded in Volume 15 of Plats, Page 84, Records of King County,Washington;
Page 2
E.5
Thence easterly along the north line of Block 7 of said Plat to the northwest corner of Lot 4 of said Block
being common with the southwest corner of Lot 4,Block 3 of said Plat;
Thence northerly along said west line of said Lot 4 of said Block 3 to the southerly margin of Renton
Avenue;
Thence southeasterly along said margin to the southeast corner of Lot 1 of said Block 3, said southeast
corner also being a point on the westerly right of way margin of 80`h Avenue South;
Thence northerly along said westerly right of way margin,to the north line of said Northeast quarter; said
north line also being the centerline of S. 128th Street;
Thence easterly along said north line and said centerline,to the northeast comer of said Section 13, said
northeast comer also being the southwest corner of said Section 7 and a point of intersection with the
centerline of 84th Avenue S.;
Thence continuing easterly along the south line of said Section 7,crossing said 84th Avenue S.,to an
intersection with the easterly right of way margin of said 84th Avenue S.;
Thence northerly along said easterly right of way margin,to an intersection with the south line of the north
125 feet of the south 270 feet of the west half of the Southwest quarter of the Southwest quarter of said
Section 7;
Thence easterly along said south line,a distance of 98 feet,to an intersection with the east line of the west
128 feet of said subdivision;
Thence northerly along said east line,to the north line of said south 270 feet of said subdivision;
Thence easterly along said north line,to the southwest comer of Lot 2 of City of Renton Short Plat No.
023-87, as recorded under King County Recording No. 8712299017, Records of King County,
Washington;
Thence northerly along the west line of said Lot 2 and the existing City limits of Renton as annexed by
Ordinance No. 3801,to the southeast comer of Lot 1 of said short plat;
Thence westerly along the south line of said Lot 1 and said existing City limits,to the southwest corner
thereof, said southwest corner being a point on the easterly right of way margin of said 84th Avenue S.;
Thence northerly along the west line of said Lot 1 and said existing City limits and said easterly right of
way margin,to the northwest comer thereof;
Thence continuing northerly along said easterly right of way margin and the existing City limits of Renton
as annexed by Ordinance No. 1669,to the southwest corner of Lot 3, Block A of Conner's Lake View Park
No. 2,as recorded in Volume 78 of Plats, Page 64, Records of King County,Washington;
Page 3
E.5
Thence continuing northerly along the west line of said plat, said easterly right of way margin and said
existing City limits,to the northwest comer of said plat;
Thence easterly along the north line of said plat and said existing City limits,to an intersection with the
southerly extension of the west line of Lot A of King County Boundary Line Adjustment No. L96L0145,as
recorded under King County Recording No. 9704091385,Records of King County,Washington;
Thence northerly along said extension and the west line of Lots A and B of said boundary line adjustment,
to the northwest corner of said Lot B;
Thence easterly along the north line of said Lot B and the easterly extension of said Lot B, crossing Stevens
Avenue NW(87th Avenue S.),to an intersection with the easterly right of way margin of said Stevens
Avenue NW, said intersection being a point on the existing City limits of Renton as annexed by Ordinance
No. 1461;
Thence northerly along said easterly right of way margin and existing City limits,crossing Taylor Place
NW,to the northwest corner of Lot 3, Block 1 of Latimers Lake Park Addition, as recorded in Volume 18
of Plats, Page 63, Records of King County,Washington;
Thence easterly along the north line of said Lot 3 and its easterly extension, crossing Lind Avenue NW,to
the southwest corner of Lot 2, Block 14 of said plat;
Thence northerly along the west line of said Lot 2 and along the west line of Lot 1 of said Block 14,to the
northwest comer of said Lot 1, said northwest corner also being a point on the southerly right of way
margin of NW 7th Street(S. 122nd Street);
Thence easterly along said southerly right of way margin and said existing City limits,crossing Taylor
Avenue NW,to the northwest comer of Lot 1, Block 16 of said plat;
Thence northerly along the northerly extension of the west line of said Lot 1,to the centerline of that
portion of NW 7th Street vacated under City of Renton Vacation Ordinance No. 3455;
Thence easterly along said centerline,to an intersection with the westerly right of way margin of Rainier
Avenue North;
Thence northerly along said westerly right of way margin, crossing S. 121st Street,to the northeast corner
of Lot 11 of Lenz Farmette Tracts,as recorded in Volume 37 of Plats,Page 36, Records of King County,
Washington;
Thence easterly along the easterly extension of the north line of said Lot 11,crossing Rainier Avenue
North,to an intersection with the easterly right of way margin of said Rainier Avenue North;
Thence northerly along said easterly right of way margin, following the tangent and curving courses
thereof, said easterly right of way margin being, in part,the existing City limits of Renton as annexed by
Ordinance No. 1300,to an intersection with a line which is 5 feet south of and parallel with the common
Page 4
E.5
0
line between Lots 7 and 8, Block 18, Bryn Mawr,as recorded in Volume 5 of Plats, Page 58, Records of
King County,Washington;
Thence South 88 027'28"East,along said parallel line and said existing City limits,a distance of 89.23
feet,to the west line of the Defense Plant Corp. 5-24-43;
Thence North 05°16'51"East, along said existing City limits,a distance of 438.90 feet,to an intersection
with a line which is 2 feet south of and parallel with the common line between Lots 1 and 2, Block 17 of
said plat;
Thence North 40°09'47"East,along said existing City limits,a distance of 188.55 feet;
Thence North, along said existing City limits,a distance of 60 feet;
Thence North 29°00'40"West,along said existing City limits,a distance of 197.07 feet;
Thence South 88°27'28"East,along said existing City limits, a distance of 355.00 feet,to a point on the
Inner Harbor Line of Lake Washington,as shown upon Sheet No. 26 of the Plat of Lake Washington Shore
Lands Survey 1921, said plat being filed with the Auditor of King County,Washington, September 19,
1921, under Recording Number 1552504, said point being a distance of 92.62 feet along said Inner Harbor
Line from angle point"862"on said plat,and the terminus of said sewer service area boundary line.
Page 5
I
E.5
Nonni
Mal
oil
PA
l l Ira`I r NINE 'lei I
WA on ilk IWO VEFjW[HM
IMEWN
EN a NOW
I IIIIIIIIII NINE
M20 SamiWINonMENMENon
All"
111 ! ! a F .atE,E/ r 1
w INS
SEM ONE
rJ ter! w !i i w IIIIIIN tom S . _
NEW
Ali WE
MAP
WE
SIMON
As
i ' •,0 won
Naomi
lIIIsoning
ills '
Kmi,lliIIIIIIBill
on 1111111111 i,`: %.
amp
mop'
WS
OURMill
i
a—
PE
LOS IN
MINI
NEW
IlIFA
I IA I' C: C Off,1 11 ii I.: — 1!' i II ,.
HOW
PON
111
N ME
IIIII - - "
i c ll Illll la I 1 I i r
rA
a P-M pm
hqq
EmOman1 I ICI , \
RI
1 Muff,0
HIM
WWWWrld rd"WA
E.5
EXHIBIT E
CAG-03-197
Existing SWSD Water Service Connections in RENTON Service Area:
ADDRESS KING COUNTY PARCEL NUMBER
8543 S 124 Street i.e., King County tax lot 072305-9049
12424 84 Avenue S i.e., King County tax lot 072305-9058
12620 84 Avenue S , i.e., King County tax lot 072305-9061
12426 84 Avenue S i.e., King County tax lot 072305-9068
8423 S 124 Street i.e., King County tax lot 072305-9069
8547 S 124 Street i.e., King County tax lot 072305-9072
8539 S 124 Street i.e., King County tax lot 072305-9073
12422 84 Avenue S i.e., King County tax lot 072305-9074
8435 S 124 Street i.e., King County tax lot 072305-9075
12540 84 Avenue S i.e., King County tax lot 072305-9077
8537 S 124 Street i.e., King County tax lot 072305-9081
8428 S 124 Street i.e., King County tax lot 072305-9088
12200 85 Avenue S i.e., King County tax lot 118000-5471
12117 87 Avenue S i.e., King County tax lot 118000-5520
12116 85 Avenue S i.e., King County tax lot 118000-5600
12121 87 Avenue S i.e., King County tax lot 118000-5601
12133 87 Avenue S i.e., King County tax lot 118000-6780
12308 85 Avenue S i.e., King County tax lot 118000-6890
8556S123
I
Place i.e., King County tax lot 118000-6980
8550S123 I Place i.e., King County tax lot 118000-6990
8544 S 123` Place i.e., King County tax lot 118000-7005
8540 S 123d i.e., King County tax lot 118000-7015
8532 S 123d i.e., King County tax lot 118000-7026
8524 S 123` Place i.e., King County tax lot 118000-7036
8518 S 123d i.e., King County tax lot 118000-7045
12320 85 Avenue S i.e., King County tax lot 118000-7055
12314 85 Avenue S i.e., King County tax lot 118000-7056
vacant i.e., King County tax lot 118000-8225
8525 S 123d i.e., King County tax lot 118000-8235
8529 S 123d i.e., King County tax lot 118000-8245
8535 S 123d i.e., King County tax lot 118000-8255
8541 S
123d
i.e., King County tax lot 118000-8265
8547 S 123d i.e., King County tax lot 118000-8270
8553S123 I Place i.e., King County tax lot 118000-8275
8554 S 124 Street i.e., King County tax lot 118000-8290
8548 S 124 Street i.e., King County tax lot 118000-8295
8542 S 124 Street i.e., King County tax lot 118000-8315
E.5
EXHIBIT E
CA G-03-197
8536 S 124 Street i.e., King County tax lot 118000-8325
8530 S 124 Street i.e., King County tax lot 118000-8335
8524 S 124 Street i.e., King County tax lot 118000-8345
8518 S 124 lh Street i.e., King County tax lot 118000-8355
1282084 th Avenue S i.e., King County tax lot 182305-9204
12811 84
th Avenue S i.e., King County tax lot 214480-0005
1282384
th
Avenue S i.e., King County tax lot 214480-0006
1281984 th
Avenue S i.e., King County tax lot 214480-0007
12852 80th Avenue S i.e., King County tax lot 214480-0225
7830 S Langston Road i.e., King County tax lot 214480-0336
7840 S Langston Road i.e., King County tax lot 214480-0341
7835 S 1301h Street i.e., King County tax lot 214480-0342
7931 S 130th Street i.e., King County tax lot 214480-0345
8531 S124 lh Street i.e., King County tax lot 796140-0025
E.5
EXHIBIT F
CAG-03-197
Existing RENTON Water Service Connections in SWSD Service Area:
ADDRESS KING COUNTY PARCEL NUMBER
8231 S 121 s' Street i.e., King County tax lot 118000-5795
8246S 122 nd Street i.e., King County tax lot 118000-5850
8324S 122 nd Street i.e., King County tax lot 118000-5855
8240S 122" Street i.e., King County tax lot 118000-5880
8232S 122" Street i.e., King County tax lot 118000-5890
8222S 122 nd Street i.e., King County tax lot 118000-5900
8218S122 n Street i.e., King County tax lot 118000-5910
8208S 122 nd Street i.e., King County tax lot 118000-5915
Vacant i.e., King County tax lot 118000-5930
1220982 n Avenue S i.e., King County tax lot 118000-6230
Vacant i.e., King County tax lot 118000-6250
Vacant i.e., King County tax lot 118000-6350
8207S122 n Street i.e., King County tax lot 118000-6360
8217S 122 nd Street i.e., King County tax lot 118000-6375
8223S 122 nd Street i.e., King County tax lot 118000-6390
8239S 122 nd Street i.e., King County tax lot 118000-6405
8241 S 122'
d
Street i.e., King County tax lot 118000-6415
8247S 122 nd Street i.e., King County tax lot 118000-6425
8323S122
n Street i.e., King County tax lot 118000-6445
8254 S 123 rd Street i.e., King County tax lot 118000-6460
8246 S 123rd Street i.e., King County tax lot 118000-6475
8240 S 123
rd Street i.e., King County tax lot 118000-6477
8228 S 123 rd Street i.e., King County tax lot 118000-6500
8220 S 123rd Street i.e., King County tax lot 118000-6520
8214 S 123
rd Street i.e., King County tax lot 118000-6530
8202 S 123rd Street i.e., King County tax lot 118000-6550
12202 84 Avenue S i.e., King County tax lot 118000-6560
8411 S122 n Street i.e., King County tax lot 118000-6570
Vacant i.e., King County tax lot 118000-6650
Vacant i.e., King County tax lot 118000-6660
8412 S 123
rd
Street i.e., King County tax lot 118000-6670
12212 84 Avenue S i.e., King County tax lot 118000-6685
12300 84 Avenue S i.e., King County tax lot 118000-7080
8411 S 123d
Street i.e., King County tax lot 118000-7095
Vacant i.e., King County tax lot 118000-7105
8432S 123d Street i.e., King County tax lot 118000-7106
12309 85 Avenue S i.e., King County tax lot 118000-7108
E.5
EXHIBIT F is
CAG-03-197
8438 S 123` Place i.e., King County tax lot 118000-7120
8426 S 123'0 Place i.e., King County tax lot 118000-7140
8416 S 123d i.e., King County tax lot 118000-7185
12312 84 Avenue S i.e., King County tax lot 118000-7200
8410 S 123d i.e., King County tax lot 118000-7210
Vacant i.e., King County tax lot 118000-7220
8211S 123d i.e., King County tax lot 118000-7230
8217S
123d
i.e., King County tax lot 118000-7245
8223S123 I Street i.e., King County tax lot 118000-7255
8241 S123 r Street i.e., King County tax lot 118000-7265
8229S123 r Street i.e., King County tax lot 118000-7275
8235 S 123rd Street i.e., King County tax lot 118000-7285
12309 84 Avenue S i.e., King County tax lot 118000-7295
12315 84 Avenue S i.e., King County tax lot 118000-7300
12311 84 Avenue S i.e., King County tax lot 118000-7315
vacant i.e., King County tax lot 118000-7316
8230S123 r Place i.e., King County tax lot 118000-7375
8222S123
r
Place i.e., King County tax lot 118000-7405
8216S 123 rd Place i.e., King County tax lot 118000-7410
8210 S 123rd Place i.e., King County tax lot 118000-7415
8200 S 123` Place i.e., King County tax lot 118000-7420
8205S123 r Place i.e., King County tax lot 118000-7850
8211 S 123` Place i.e., King County tax lot 118000-7865
8223S123 r Place i.e., King County tax lot 118000-7875
8217 S 123` Place i.e., King County tax lot 118000-7880
8233 S 123rd Place i.e., King County tax lot 118000-7900
8243 S
123rd
Street i.e., King County tax lot 118000-7915
12333 84 Avenue S i.e., King County tax lot 118000-7931
12408 84 Avenue S i.e., King County tax lot 118000-8060
8409S123 r Place i.e., King County tax lot 118000-8070
8415 S
123rd
Place i.e., King County tax lot 118000-8080
8427 S 123rd
Place i.e., King County tax lot 118000-8090
12323 85 Avenue S i.e., King County tax lot 118000-8105
E.5
E.6
E.6
E.6
E.6
E.7
E.7
E.7
E.7
E.7
E.7
CITY OF RENTON, WASHINGTON
i
RESOLUTION NO. 2692
A RESOLUTION OF THE CITY OF RENTON, WASHINGTON,
ADOPTING UTILITY FRANCHISES
WHEREAS Water District No . 107 currently owns water mains
and sewer lines within the City of Renton rights-of-way, and
WHEREAS Water District No . 107 has applied to the City of
Renton for a water franchise and a sewer franchise to install ,
construct, maintain, and operate water mains and sewer lines in
the City rights-of-way, and
WHEREAS the City Council has reviewed the .franchise
agreements negotiated between City Staff and Water District No .
107 and finds them to be in acceptable form, now therefore,
THE CITY COUNCIL OF THE CITY OF RENTON, DO RESOLVE AS
FOLLOWS :
SECTION. I : The findings , recitals and determinations are
hereby found to be true and correct in all respects.
SECTION II: The Utility Franchises for Water District No.
107 as they relate to water mains, a copy of which is attached
hereto as Exhibit "A" and incorporated by this reference, and
sewer lines, a copy of which is attached hereto as Exhibit "B"
and incorporated by this reference, are hereby approved and
adopted , subject to the laws and ordinances of the City of
II
E.8
f
y
RESOLUTION NO. 2692
Renton, and the Mayor and City Clerk are hereby authorized to
sign the franchise agreements .
PASSED BY THE CITY OF RENTON this 2nd day of Nov.ember..,
1987 .
Maxine E. Motor, City Clerk. .. .
APPROVED BY THE MAYOR this 2nd day of November
1987 .
Barbara Y. Shinpoch, Mayor
Approved as to form:
Lawrence J. Warr4nj City Attorney
CITY3 : 46/10/27/87/nd
E.8
f; '`'- _
A
g IBIT "A"
s 1
E ;,; .;: . .• UTIL-JTY FRANCHISE
THIS UTILITY FRANCHISE is given this day of
1987, by the City of Renton, King County,
Washington, a municipal corporation ( "Renton" or "Grantor" )
to King County Water District No. 107, a municipal
corporation ( "District" or "Grantee" ) .
i
SECTION l: RECITALS
1 . 01. The District has applied to Renton for a water
utility franchise to install , construct, maintain d
operate water lines, including mains, lateral , appurtenances
and service pipe along, under and across such city roads,
streets , avenues, boulevards , alleys and public places
hereinafter called "rights-of-way" , within the District' s
service area.
1 . 02 . The Renton City Council ( "Council" ) has reviewed
and considered such application for water utility franchise.
WHEREFORE , in consideration of the terms and conditions
herein, Renton hereby grants to the District a water utility
franchise as follows :
SECTION 2: WATER UTILITY FRANCHISE
2. 01. Renton, pursuant to Resolution No. , duly
and regularly enacted by its Council on the ay of
1987, hereby grants to the district and to its
successors and assigns, for the term of twenty-five (25 )
years from the date hereof, the right, privilege, authority
and franchise for itself, its successors and assigns , to
install , construct, maintain and operate water mains,
laterals and service lines along , under and across such City
rights-of-way, together with all necessary equipment of
every sort necessary , subject to all the terms and
conditions herein.
2 .02. This Utility franchise shall apply to those
portions of the District' s water lines and appurtenances
within the City of Renton' s present rights-of-way as
referenced in paragraph 1. 01 above.
SECTION 3 : GENERAL TERMS AND CONDITIONS APPLICABLE TO THE
UTILITY FRANCHISE
3 . 02 . Definitions :
a) . Right-of-way . The term "right-of-way" shall
be understood to include any and every Renton City road ,
1
E.8
street, avenue , alley or other public place designated or
specified in this franchise in, upon, under, over, across
and along which rights are, or are intended to be vested in
the Grantee, its successors and assigns, under and by virtue
of this franchise.
b) . Director . The term "director" shall be the
City of Renton Director of Public works.
c) . Utility. The term "utility" shall be
understood to mean, as the context may require, either the
Grantee herein, or any other person, firm or corporation,
either public or private, which may hold a franchise to
maintain and operate similar facilities in, upon, under ,
over , across and along any of the public rights-of way , or
portions thereof, within the area specified.
d ) . Other Governing Body. The term "other
governing body" shall be understood to mean such public
O
official or other public board or body as may have power and
jurisdiction over the rights-of-way and be legally vested
with jurisdiction and authority to permit or regulate the
installation, maintenance of lines and other facilities, in,
upon, under, over, across and along the rights-of-way within
the specified area.
3 . 02. Acceptance by Grantee of Terms and conditions.
Grantee shall be deemed to have abandoned and forfeited all
the rights, privileges and authority hereby granted, unless
within thirty (30 ) days from the date hereof Grantee shall
file with the Council its written acceptance of this
franchise, subject to all of the terms, conditions,
stipulations and other obligations herein contained and
enclosed, and in case the Grantee shall fail to do so within
the time aforesaid, this franchise shall be null and void
and of no effect.
3 . 03 . Exclusive Franchise Unconstitutional. This
franchise shall not be deemed or held to be an exclusive
franchise, and shall not in any manner prohibit the Council
from granting other and further franchises of any kind or
character that it may deem proper , in, upon, under, over ,
across and along any right-of-way within the area described
herein, and this franchise shall in no way prohibit or
prevent the public from using any such rights-of-way or
affect the jurisdiction of Renton over such rights-of-way or
any part thereof , or its power to make all necessary
ti
improvements, repairs or changes therein.
3 . 04 .Jurisdiction.this document shall not be
construed by Grantee, or any other person, persons or
corporations, as a warrant of title or interest in City
roads or rights-of-way but is intended to convey such
2
E.8
only as to those roads andrights-of-way and interests
rights-of-way in which the City has an actual interest.
3 . 05.Regulation of Use and Control.The City
granting this franchise does not waive any rights which it
now has or may hereafter acquire with respect to City .roads,
rights-of-way or other City property and this franchise
shall not be construed to deprive the City of any powers,
rights or privileges which it now has or may hereafter
acquire . to regulate the use of and to control the City
roads, rights-of-way and any other City property covered by
this franchise.
3 . 06 . Vacation. If at any time the City shall vacate
any City road, rights-of-way or other City property which is
subject to rights granted by this franchise, the City shall
not be _liable for any damages or loss to the Grantee by
reason of such vacation.
03 . 07.Responsibility for Damages. The Grantee agrees
for itself, its successors and assigns, to indemnify and
V4 hold the City harmless, its appointed and elected officials
V-4 and employees from and against all .loss or expense,
V-4 including attorney' s fees and costs arising out of any
negligent act, error or omission by the District, its agents
or employees related to this Franchise.
3. 08 . Requirement of Construction Permits. The said
Grantee, its successors or assigns, shall have the right and
authority to enter upon the City roads and rights-of-way
described herein for the purpose of constructing,
extending, repairing or replacing, servicing and/or
operating .and maintaining its lines and facilities and
connecting the same with consumer service lines, upon the
condition that prior to such work within the City roads or
rights-of-way, the Grantee shall first obtain the necessary
permits approved by the Director of Public Works.
Applications for said permits shall first be presented-
to the Department of Public Works which may require
copies of plans, blueprints, cross-sections or such .further
detail of the work to be done as is , or may be required by
ordinance in other instances. Such work, whether done by
the Grantee, its contractors or third parties connecting to
the Grantee ' s lines or facilities, shall include necessary
paving, patching , grading and any other reasonable and
necessary repair or restoration to the pre-existing City
roads , rights-of-way and shall be to the satisfaction of the
director .
All permits shall be applied for and given in the name
of the Grantee who shall be held responsible for all work
done thereunder , whether the work done thereunder is by the
3
E.8
forces of the Grantee, its contractors or by third parties
connecting to the lines or facilities of Grantee.
Before any work is performed under the permit, the
Grantee shall establish two or more reference marks to all
monuments and markers of every nature relating to
subdivision, plats, right-of-way and all other surveys
within the permitted area. The reference points shall be so
located that they will not be disturbed during the Grantee' s
operation under the permit. The method of referencing these
monuments or other points to be referenced shall be approved
by the director before placement. The replacement of all
such monuments or markers disturbed during construction
shall be made as expeditiously as conditions permit and as
directed by the director. The cost of monuments or other
qj markers lost, destroyed or disturbed and the expense of
C replacement by approved monuments shall be borne by the
Grantee.
Grantor_ shall be named as an additional obligee on
performance bonds required by the District for any work
within the franchise area herein.
3 . 09 Providing "As Built" Drawings The
developer/contractor shall maintain on the jobsite project
plans marked to indicate City-approved plan revisions made
in the field and other details of construction.The
drawings shall be made available upon completion of the
project to the District for use in preparation of "as built"
records. The developer shall be responsible for the cost of
any required "as built" drawings . A copy of these "as
built" drawings shall be provided to the City.
3 . 10 . Restoration of Right-of-Way. The Grantee shall
be responsible for and leave all City roads and rights-of-
way in good condition , after work on, under or adjacent to
the City roads or rights-of-way as the same were before such
work. In the event that the Grantee, its contractors or
third parties connecting to Grantee' s lines or facilities
under work permit, shall fail to restore the City roads or
rights-of-way to the condition that pre-existed such work to
the satisfaction of the director, the City reserves the
right to make such repairs or restoration to such roads or
rights-of-way,. and upon presentation of an itemized bill for
such repairs or restoration, including the cost of labor and
equipment, the Grantee shall pay the said bill within thirty
30 ) days. In the event that suit is brought upon failure
to pay the bill within thirty (30 ) days, and upon judgment
being entered in favor of the City , Grantee shall further
pay all the actual costs, disbursements and attorney' s fees
incurred thereby.
3. 11 A. Removal or Relocation of. Facilities Installed
by Grantee. Upon the relocation or change of grade by the
4
E.8
public authorities of any right-of-way described herein, any
lines or facilities, erected upon or within any portion of
such right-of-way, shall, if necessary, be removed by the
Grantee at its own expense so that it shall not interfere
with the work of relocation or change of grade and shall be
reset in accordance with the provisions above set forth so
that the location and elevation of such line or facility
shall conform to the new grade and location of the right-of-
way. Grantee shall likewise, at its own expense, upon
demand of the director , relocate any line or facility which
shall interfere with a reasonably located driveway giving
access to abutting property. The City shall in no event be
held liable for any damages to said Grantee that may occur
by reason of the City' s improvements, repairs or maintenance
or by the exercise of any rights are reserved in this
section.
3 . 11 B. Competing Service Areas. The parties
acknowledge that they have existing water lines parallel to
one another. Subject to Chapter 35. 13A, et seq and further
O
subject to any assertion of jursidiction by the Boundary
Review Board and any subsequent decision of the Boundary
Review Board, the parties agree that should the Water
District need to replace a water line or perform such
substantial repairs to the water line that the cost of
repairs is equivalent to the value of the water line, then
GQ the City of Renton shall have the right to provide service
to the customers in the City limits in that service area.
3 . 11 C. Installation Codes: Grantee agrees that any
new water line installation or replacement done pursuant to
this agreement shall meet all fire flow and hydrant
requirements as set out in the current or subsequently
adopted
Uniform Fire Code;
City Ordinance ( current Ordinance is 4007 ) ;
Insurance Service Office Standards ( current edition
1974) ;
National Fire Protection Association, National Fire
Codes;
King County Water District No . 107 Design and Technical
Specifications;
Parts II .and III : Technical Specifications - Water
Extension;
Part IV - Technical specifications. - Water
Details;
Standard Specifications for Municipal Public Works
Construction of the American Public works Association;
5
E.8
Standard specifications for Municipal Public Works
Construction of the American Water Works Association;
Standard Specifications for Municipal Public Works
Construction of the ASTM;
Washington Administrative Code section 248-54 , "Public
Water Supplies" (DSHS) ;
All other applicable county , state and federal
regulations and statutes regarding water works
specifications and design.
All fire hydrants shall beinstalled by grantee in
compliance with the City of Renton Department of Public
Works Construction Standards.
C 2 3 . 12 . Blasting Requirements. The laying,
construction maintenance and operation of the Grantee ' sP
Os st m of lines and facilities granted under this franchise
XJ shall not preclude the City , its accredited agents, or its
contractors from blasting grading or doing other necessary
roadwork contiguous tothe Grantee ' s lines and facilities,g
seventy-two 72 hours1havesevenprovidedthattheGranteeshally
notice of said blasting or excavating in order that Grantee
may protect its lines, facilities and property.
3 . 13 .Assignment of Rights to Third Party. The
Grantee shall have the right to assign its franchise
provided, however, no such assignment shall be of any force
or effect unless written notice of such assignment shall be
filed with the Clerk of the Council within thirty ( 30 ) days
thereafter , together with an acceptance by the assignee in
writing of all the terms, covenants and conditions of this
franchise and an agreement of such assignee to perform, and
be bound by all the terms and conditions of this franchise.
All the provisions, conditions, regulations and
requirements herein contained shall be binding upon the
successors and assigns of the Grantee, and all privileges,
as well as all obligations and liabilities of the Grantee,
shall inure to its successors and assigns equally as if they
were specifically mentioned wherever the Grantee is
mentioned .
3 . 14 . Expiration and Renewal . All rights granted by
this franchise to City roads and rights-of-way shall apply
to all existing City roads and rights-of-way whether
improved or unimproved , and shall further include City roads
and rights-of-way acquired by the City after the date of
execution of this document.
6
E.8
If , upon expiration of this franchise, Grantee shall
not have applied for renewal of same, the City shall have
the right to remove such lines or facilities of the Grantee
as are reasonably necessary for the safe condition of the
roads or rights-of-way or facilities of other franchise
holders and such are reasonably necessary to remove for the
construction., renewing , altering or improving of such roads
or rights-of--way, and such as are reasonably necessary to
remove for the installation of .lines and/or facilities of
other franchise holders. Grantee shall be liable for the
costs incurred in such removal including the cost of labor
and equipment; provided that such removal is affected with
two (2 ) years from the expiration date hereof.
3 .15. Right to Amend. The City reserves for itself
the right at any time upon ninety ( 90 ) days written notice
to the Grantee, to so change, amend, modify or amplify any
of the provisions or conditions herein enumerated to conform
to any state statute or regulation relating to the public
welfare, health, safety or right-of-way regulation as may
Q hereafter be enacted, adopted or promulgated and this
franchise may be terminated at any time if the Grantee' s
lines and facilities , are not operated or maintained in
accordance with such statutes or regulations.
3.16. Environmental Compliance. Grantee must conform
to the Washington State Environmental Policy Act and any
amendments thereto.
3 . 17. No Discrimination in Employment. In connection
with the performance of any work by the District or its
agents addressed herein, the District and its agents shall.
comply with all federal , . state and local codes, statutes and
ordinances prohibiting discrimination.
3 . .18. Penalty for Violation of Conditions. If the
Grantee shall violate or fail to comply with any of the
terms, conditions or responsibilities of this franchise
through neglect or failure to heed or comply with any notice
given the Grantee under the provisions of this franchise,
the Council may revoke amend alter , change or supplement
this franchise provided, however , that the Council shall
give thirty (30 ) days written notice of its intention to do
so, during which period the Grantee shall have the
opportunity to remedy the failure to comply.
3. 19. Franchise Fee. The Grantee shall annually pay
to the City a franchise fee of five cents ( $0. 05 ) per lineal
foot of transmission water lines owned by the Grantee lying
within City rights of way as described in paragraph 2. 02
herein. City and Grantee agree that Grantee owns
transmission and service lines and is responsible for
maintenance thereof.
7
E.8
1
3 . 20 . Severance. This agreement shall be construed to
give effect to such purposes- and uses under this franchise
which are consistent with economical and efficient service
rendered in the public interest. If any provision of this
franchise, or its application is determined to be invalid by
court of law, then the remaining provisions of the franchise
shall continue and be valid unless the dominant purpose of
the franchise or the public interest herein is thwarted
thereby.
3 . 21 . Recording. This agreement shall be recorded
with the King County Office of Records and Elections
immediately upon its execution by the parties herein.
SECTION 4: RESERVATION OF RIGHTS; RENTON UTILITY TAX
4 . 01 . The City and the District acknowledge
disagreement over the City' s right to impose water utility
taxes on the District' s gross revenues derived from parties
receiving service from the District located within Renton' s
corporate boundaries. The parties acknowledge the
C District' s refusal to collect and transmit such utility tax
to the City. Therefore, the City hereby expressly reserves
rd all rights to make claim against the District for the
payment of such utility taxes.
SECTION 5: RESERVATION OF RIGHTS; COMPREHENSIVE PLAN
APPROVAL
5 . 01 . The parties herein reserve all rights
provided under applicable Washington law to approve ,
conditionally approve, or reject the general Comprehensive
Plan as submitted by the other party.
CITY OF RENTON ( "Renton" ) KING COUNTY WATER DISTRICT
NO. 107 ( "Distr,ict°'
Z.
B y &h)D O X_a) Sh yk' • fLCJc(}v B
Its Mayor Its rca<r nJSr-'•
The undersigned hereby accepts all the rights and
privileges of the above granted franchise subject to all the
terms, conditions, stipulations and obligations contained
herein.
KING COUNTY WATER DI RICT CITY OF RENTON ( "Renton" )
NO.
10L
Di tr ct" )
ATTEST:
By
i
Its lzss© /r'T City Clerk
Dated this day of November, 1987.
8
E.8
A Y1 f
I I I I I .^, lEXHIBITBNOV q
LJ
ti :'` : : ;i
1d
I
UTILITY FRANCHISE
THIS UTILITY FRANCHISE is given this qday of
1987, by the City of Renton, King County,Washington, a municipal corporation ( "Renton" or "Grantor" )
to King County Water District No. 107, a municipal
corporation ( "District" or "Grantee" ) .
SECTION 1: RECITALS
Q? 1 . 01. The District has applied to Renton for a. sewer
utility franchise to install, construct, maintain and
O
operate sewer lines, including mains, lateral , appurtenances
0
and side sewers along, under and across such city roads,
X streets , avenues, boulevards , alleys and public places
q-4 hereinafter called "rights-of-way" , within the District' s
service area.
Q 1 . 02. The Renton City Council ( "Council" ) has reviewed
and considered such application forPP sewer utility franchise.
WHEREFORE, in consideration of the terms and conditions
herein, Renton hereby grants to the District a sewer utilityfranchiseasfollows:
SECTION 2: SEWER UTILITY FRANCHISE
2 . 01. Renton, pursuant to Resolution No. , oZ,6 9 42, duly
and regularly enacted by its Council on the __,, d day of
1987, hereby grants to the district and to its
successors and assigns, for the term of twenty-five (25)
years from the date hereof, the right, privilege, authority
and franchise for itself, its successors and assigns, to
install, construct, maintain and operate sewer lines,
including mains, laterals , appurtenances, and side sewers
along, under and across such City rights-of-way, together
with all necessary equipment of every sort necessary,
subject to all the terms and conditions herein.
2 . 02. This Utility franchise shall apply to those
portions of the District' s sewer lines and appurtenances
within the City of Renton' s present rights-of-way as
referenced in paragraph 1 . 01 above.
CITY3: 50/10/28/87
Fii° P AWE
ii_!
1
E.8
SECTION 3 : GENERAL TERMS AND CONDITIONS APPLICABLE TO THE
UTILITY FRANCHISE.
3. 02 Definitions :
a) Right-of-Way. The term "right-of-way" shall
be understood to include any and every Renton City road ,
street , avenue , alley or other public place designated or
specified in this franchise in, upon, under , over , across and
along which rights are , or are intended to be vested in the
Grantee , its successors and assigns , under and by virtue of
this franchise .
b) Director. The term "director" shall be the
City of Renton Director of Public Works .
c) Utility . The term "utility" shall be
understood to mean, as the context may require , either the
C1 Grantee herein, or any other person, firm or corporation,
either public or private , which may hold a franchise to
C
maintain and operate similar facilities in, upon, under , over ,
across and along any of the public rights-of-way, or portions
thereof , within the area specified.
d) Other Governing Body. The term "other
governing body" shall be understood to mean such public
Qa official or other public board or body as may have power and
jurisdiction over the rights-of-way and be legally vested with
jurisdiction and authority to permit or regulate the
installation, maintenance of lines and other facilities , i n,
upon, under , over , across and along the rights -of-way within
the specified area.
3. 02 Acceptance by Grantee of Terms and Conditions .
Grantee shall be deemed to have abandoned and forfeited all the
rights ,g s , and authority hereby granted , unless within
thirty (30) days from the date hereof Grantee shall file with
the Council its written acceptance of this franchise , subject
to all of the terms , conditions , stipulations and other
obligations herein contained and enclosed , and in case the
Grantee shall fail to do so within the time aforesaid , this
franchise shall be null and void and of no effect .
3. 03 Exclusive Franchise Unconstitutional . This
franchise shall not be deemed or held to be an exclusive
franchise , and shall not in any manner prohibit the Council
from granting other and further franchises of any kind or
character that it may deem proper , in, upon, under , over ,
across and along any right-of-way within the area described
herein, and this franchise shall in no way prohibit or prevent
2 -
E.8
the public from using any such rights-of-way or affect the
jurisdiction of Renton over such- rights-of-way or any part
thereof , or its power to make all necessary improvements ,
repairs or changes therein.
3 . 04 Juri sdi cti oil. This document shall not be
construed by Grantee , or any other person, persons or
corporations , as a warrant of title or interest in City roads
or rights-of-way but is intended to convey such rights-of-way
and interests only as to those roads and rights-of-way in which
the City has an actual interest .
3 . OS Regulation of Use and Control . The City granting
this franchise does not waive any rights which it now has or
may hereafter acquire with respect to City roads , rights-of-way
or other City property and this franchise shall not be
construed to deprive the City of any powers , rights or
privileges which it now has or may hereafter acquire to
regulate the use of and to control the City roads ,
rights-o£-way and any other City property covered by this
franchise .
3. 06 Vacation. If at any time the City shall vacate
any City road , rights-of-way or other City property which is
subject to rights granted by this franchise , the City shall not
be liable for any damages or loss to the Grantee by reason of
such vacation.
3 . 07 Responsibility for Damages . The Grantee agrees
for itself , its successors and assigns, to indemnify and hold
the City harmless , its appointed and elected officials and
employees from and against all loss or expense , including
attorney' s fees and costs arising out of any negligent act ,
error or omission by the District , its agents or employees
related to this Franchise.
3 . 08 Requirement of Construction Permits . The said
Grantee , its successors or assigns , shall have the right and
authority to enter upon the City roads and rights-of-way
described herein for the purpose of constructing , extending ,
repairing or replacing , servicing and/or operating and
maintaining its lines and facilities and connecting the same
with consumer service lines , upon the condition that prior to
such work within the City roads or rights-of-way, the Grantee
shall first obtain the necessary permits approved by the
Director of Public Works .
Applications for said permits shall first be presented to
the Department of Public Works which may require copies of
plans , blueprints , cross -sections or such further detail of the
3-
E.8
work to be done as i s , or may be required by ordinance in other
instances . Such work, whether done by the Grantee , its
contractors or third parties connecting to the Grantee ' s lines
or facilities , shall include necessary paving , patching ,
grading and any other reasonable and necessary repair or
restoration to the pre-existing City roads , rights-of-way and
shall be to the satisfaction of the director.
All permits shall be applied for and given in the name of
the Grantee who shall be held responsible for all work done
thereunder , whether the work done thereunder is by the forces
of the Grantee , its contractors or by third parties connecting
to the lines or facilities of Grantee .
Before any work is performed under the permit , the
Grantee shall establish twowo or more reference marks to all
monuments and markers of every nature relating to subdivision,
plats , right-of-way and all other surveys within the permitted
area . The reference points shall be so located that they will
not be disturbed during the Grantee ' s operation under the
permit . The method of referencing these monuments or other
points to be referenced shall be approved by the director
before placement . The replacement of all such monuments or
Xmarkers disturbed during construction shall be made as
V4 expeditiously as conditions permit and as directed by the
W4
director. The cost of monuments or other markers lost ,
destroyed or disturbed and the expense of replacement by
approved monuments shall be borne by the Grantee .
Grantor shall be named as an additional obligee on
performance bonds required by the District for any work within
the franchise area herein.
3. 09 Providing "As -Built" Drawings . The developer/
contractor shall maintain on the jobsite project plans marked
to indicate City-approved plan revisions made in the field and
other details of construction. The drawings shall be made
available upon completion of the project to the District for
use and preparation of "as -built" records. The developer shall
be responsible for the cost of any required "as -built"
drawings . A copy of these "as-built" drawings shall be
provided to the City.
3 . 10 Restoration of Right-of-Way. The Grantee shall be
responsible for and leave all City roads and rights-of-way in
good condition, after work on, under or adjacent to the City
roads or rights-of-way as the same were before such work. In
the event that the Grantee , its contractors or third parties
connecting to Grantee ' s lines or facilities under work permit ,
4-
E.8
JP iw
t
shall fail to restore the City roads or rights-of-way to the
condition that pre-existed such .work to the satisfaction of thedirector , the City reserves the right to make such repairs or
restoration to such roads or rights -of-way, and upon
presentation of an itemized bill for such repairs or
restoration, including the cost of 'Labor and equipment , theGranteeshallpaythesaidbillwithinthirty (30) days . In
the event that suit is brought upon failure to pay the bill
within thirty (30) days , and upon judgment being entered infavoroftheCity, Grantee shall further pay all the actual
costs , disbursements and attorney' s fees incurred thereby.
3 . 11A Removal or Relocation of Facilities Installed bGrantee . Upon the relocation or change of grade by the public
authorities of any right-of-way described herein, any lines orfacilities , erected upon or within any portion of such
right-of-way, shall , if necessary, be removed by the Grantee at
its own expense so that it shall not interfere with the work of
relocation or change of rade andgg shall be reset in accordance
with the provisions above set forth so that the location and
elevation of such line or facility shall conform to the new
grade and location of the right-of-way. Grantee shallQlikewise , at its own expense , upon demand of the director ,X relocate any line or facility which shall interfere with a
V4 reasonably located driveway giving access to abutting
property. The City shall in no event be held liable for anydamagestosaidGranteethatmayoccurbyreasonoftheCity' simprovements , repairs or maintenance or by the exercise of anyrightsarereservedinthissection.
3. 11B Competing Service Areas . In the event that the
parties have existing sewer lines parallel to one another and
subject to Chapter 35 . 13A, et seq. and further subject to any
assertion of jurisdiction by the Boundary Review Board and anysubsequentdecisionoftheBoundaryReviewBoard , the parties
agree that should the Water District need to replace a sewer
line or perform such substantial repairs to the sewer line thatthecostofrepairsisequivalenttothevalueofthesewerline , then the City of Renton shall have the right to provide
service to the customers in the City limits in that service
area.
3 . 11C Installation Codes . Grantee agrees that any newsewerlineinstallationorreplacementdonepursuanttothis
agreement shall meet all requirements as set out in the current
or subsequently adopted :
S- I
E.8
r
King County Water District No. 107 - Metro
Service Agreement and Specifications ;
King County Water District No. 107 Design and
Technical Specifications :
Parts II and III : Technical Specifications
Sewer Extension ;
Part IV: Technical Specifications
Standard Sewer Details ;
Standard Specifications for Municipal Public
Works Construction of the American Public Works
Association ;
Criteria for Sewage Works Design, " State of
Washington Department of Ecology - Revised Oct .
1985 ;
O Washington Administrative Code Section 173-240 ,
Submi.ssion of Plans and Reports for Construction
of Wastewater Facilities" (DOE) ;
All other applicable state and federal
regulations and statutes regarding sewage works ,
design and hazardous waste disposal .
3. 12 Blasting Requirements . The laying , construction ,
maintenance and operation of the Grantee ' s system of lines and
facilities granted under this franchise shall not preclude the
City, its accredited agent , or its contractors from blasting ,
grading or doing other necessary roadwork contiguous to the
Grantee ' s lines and facilities , provided that the Grantee shall
have seventy-two ( 72) hours notice of said blasting or
excavating in order that Grantee may protect its lines ,
facilities and property.
3 . 13 Assignment of Rights to Third Party. The Grantee
shall have the right to assign its franchise provided , however ,
no such assignment shall be of any force or effect unless
written notice of such assignment shall be filed with the Clerk
of the Council within thirty (30) days thereafter , together
with an acceptance by the assignee in writing of all the terms ,
covenants and conditions of this franchise and an agreement of
such assignee to perform and be bound by all the terms and
conditions of this franchise .
All the provisions , conditions , regulations and
requirements herein contained shall be binding upon the
successors and assigns of the Grantee , and all privileges , as
6-
E.8
K
S •« L
well as all obligations and liabilities of the Grantee , shall
inure to its successors and assigns equally as if they were
specifically mentioned wherever the Grantee is mentioned .
3. 14 Expiration and Renewal . All rights granted by this
franchise to City roads and rights-of-way shall apply to all
existing City roads and rights-of-way whether improved or
unimproved , and shall further include City roads and
rights-of-way acquired by the City after the date of execution
of this document .
If , upon expiration of this franchise , Grantee shall not
have applied for renewal of same , the City shall have the right
to remove such lines or facilities of the Grantee as are
reasonably necessary for the safe condition of the roads or
rights-of-way or facilities of other franchise holders and such
are reasonably necessary to remove for the construction,
renewing , altering or improving of such roads or rights-of-way,
and such as are reasonably necessary to remove for the
Q installation of lines and/or facilities of other franchise
Cit holders . Grantee shall be liable for the costs incurred in
0 such removal including the cost of labor and equipment ; .
provided that such removal is affected with two (2) years from
the expiration date hereof .
3 . 15 Right to Amend . The City reserves for itself the
right at any time upon ninety (90) days written notice to the
Grantee , to so change , amend , modify or amplify any of the
provisions or conditions herein enumerated to conform to any
state statute or regulation relating to the public welfare ,
health, safety or right-of-way regulation as may hereafter be
enacted , adopted or promulgated and this franchise may be
terminated at any time. if the Grantee ' s lines and facilities
are not operated or maintained in accordance with such statutes
or regulations .
3 . 16 Environmental Compliance . Grantee must conform to the
Washington State Environmental Policy Act and any amendments
thereto .
3 . 17 No Discrimination in Employment . In connection with
the performance of any work by the District or its agents
addressed herein, the District and its agents shall comply with
all federal , state and local codes , statutes and ordinances
prohibiting discrimination.
3 . 18 Penalty for Violation of Conditions . If the Grantee
shall violate or fail to comply with any of the terms ,
conditions or responsibilities of this franchise through
neglect or failure to heed or comply with any notice given the
7-
E.8
Grantee under the provisions of this franchise, the Council
may revoke, amend, alter,. change or supplement this
franchise provided , however , that the Council shall give
thirty (30 ) days written notice of its intention to do so,
during which period the Grantee shall have the opportunity
to remedy the failure to comply.
3 . 13 Franchise Fee. The Grantee shall annually pay to
the City a .franchise fee of five cents ( $ . 05 ) per lineal
foot of transmission sewer lines owned by the Grantee, lying
within City rights of way as described in paragraph 2. 02
herein. City and Grantee agree that Grantee owns
transmission and service lines and is responsible for
maintenance thereof.
3 . 20 Severance. This agreement shall be construed to
give effect to such purposes and uses under this franchise
which are consistent with economical and efficient service
rendered in the public interest. If any provision of this
franchise, or its application is determined to be invalid by
0 court of law, then the remaining provisions of the franchise
X shall continue and be valid unless the dominant purpose of
T-4 the franchise or the public interest herein is thwarted
9.4 thereby..
N 3 . 21 Recording. This agreement shall be recorded with
the King County Office of Records and Elections immediately
upon its execution by the parties herein.
ES CTION 4: RESERVATION OF RIGHTS; RENTON UTILITY TAX
4 . 01 The City and the District acknowledge disagreement
over the City' s right to impose water utility taxes on the
District' s gross revenues derived from parties receiving
service from the District located within Renton' s corporate
boundaries. The parties acknowledge the District' s refusal
to collect and transmit such utility tax to the City.
Therefore, the City hereby expressly reserves all rights to
make claim against the District for the payment of such
utility taxes.
SECTION 5: RESERVATION OF RIGHTS ; COMPREHENSIVE PLAN
APPROVAL
5 . 01 The parties herein reserve all rights provided
under applicable Washington law to approve, conditionally
approve, or reject the general Comprehensive Plan as
submitted by the other party.
CITY OF RENTON ( "Renton" ) KING COUNTY WATER DISTR T
NO. 107 ( °Di ;&Ct" )
By , s Lil t7FX` By
Its Ma'vor Its
ATTEST:
City Clerk
E.8
a as
The undersigned hereby accepts all the rights and privileges
of the above granted franchise subject to all the terms,
conditions, stipulations and obligations contained herein.
KING COUNTY WATER DIST T
NO 107 ( "Dist iq)t )
By
Its r
Dated this 11"4 day. of November , 1987.
CITY3 :51/10/30/87
t
L
9
E.8
t
CAG-01-031
CITY OF RENTON & COAL CREEK UTILITY DISTRICT
FOR THE ESTABLISHMENT OF SANITARY SEWER SERVICE BOUNDARIES
THIS AGREEMENT is entered into this day of 4t"4.,1
20 &/ , by and between COAL CREEK UTILITY DISTRICT, a Washington municipal
corporation, hereinafter referred to as "CCUD", and the CITY OF RENTON, a
Washington municipal corporation, hereinafter referred to as "RENTON".
WITNESSETH:
WHEREAS, CCUD is qualified to provide sanitary sewer service within its
prescribed area; and
WHEREAS, RENTON is qualified to provide public services, including sanitary
sewer service, within its prescribed areas; and
WHEREAS, CCUD provides sanitary sewer service in an area adjacent to and
within RENTON's corporate boundaries and it is in the public interest for the parties
herein to enter into an agreement to provide for the efficient planning and development
of new sanitary sewer services in areas which may be served by either, or both, of the
parties herein;'now, therefore,
IT IS HEREBY AGREED by and between the parties hereto as follows:
1. Sewer Service Area Boundary Between RENTON and CCUD. The attached
legal description, Exhibit A describes the line separating the RENTON sewergp9
service area from CCUD sewer service area. The attached map, Exhibit B,
depicts the line separating the RENTON sewer service area from CCUD sewer
service area. RENTON shall provide service for the area generally South and
West of the line illustrated. CCUD shall provide service for the area generally
North and East of the line illustrated.
Any new construction, upgrading, or replacements within the RENTON City
Limits by CCUD for sewer service shall be in compliance with RENTON design
and constructions standards then in effect, or CCUD design and construction
standards, whichever are the higher design and construction standards
including: materials and techniques.
2. DISTRICT Comprehensive Sewer Planning. CCUD will submit, to RENTON, all
future Comprehensive Sewerage Plans and amendments thereto involving area
and/or improvements within RENTON City Limits. Said submission of the CCUD
Plan is to assure consistency with adopted city plans, policies, and land use
controls, assist in the review of new development proposals and right-of-way
construction permits, and to fulfill the responsibilities set forth in RCW 57 and
King County Title 13. As new facilities are planned, constructed, maintained,
i and/or replaced within RENTON, they shall comply with RENTON design and
construction standards then in effect, or CCUD design and construction
standards, whichever are the higher design and construction standards.
E.9
3. Extension of Utilities Across Properties. RENTON and CCUD agree that they
will require property owners who must extend facilities to service their property in
a comprehensive fashion up to and including extending said facilities to the far
side of the property, when appropriate, to provide a connection point for the
future (or existing) facilities of the next property.
4. Joint Use Facilities. The existing 8-inch facility as shown on Exhibit "C" shall be
a joint use facility. CCUD shall own and operate the facility. RENTON shall be
able to make connection to and utilize this sewer line to provide service to the
properties west of the facility that are in RENTON's service area.
RENTON will acquire permits for connection to said sewer. The acquisition of the
permit will include collection and payment to CCUD of the latecomers charge, as
legally adopted, for the reimbursement of a pro rata portion of the original costs
of the facility.
5. Maintenance of Existing Facilities: CCUD and RENTON will each maintain their
own facilities, according to industry standards. If there are serious problems due
to a discharge which can be identified, and for which the source can be
identified, the individual or company responsible will be held liable for damage. If
a lack of maintenance, or if the type of maintenance by either RENTON or CCUD
is identified as the source for said problem, then the party creating, or allowing,
the situation shall be responsible for the costs of repair and/or damages.
6. Governmental Approvals. The parties will give notice of the adoption of this
Agreement to Metropolitan King County, to the Department of Ecology, and to
any other agency with jurisdiction, and shall cooperate and assist in any
reasonable manner in procuring any necessary approvals hereof by those
agencies.
7. Sanctity of Agreement. This Agreement constitutes the entire agreement of the
parties, concerning the subject matter herein, and there are no representations
or oral agreements other than those listed herein, which vary the terms of this
Agreement. This agreement shall not alter the rights of Renton of assumption of
Water and Sewer Districts as is provided under RCW 35.13A. Future
agreements may occur between the parties to identify, agree upon, or transfer
service areas and/or facilities. This Agreement shall have a term of 25 (twenty-
five) years.
8. Obligations Intact. Nothing herein shall be construed to alter the rights,
responsibilities, liabilities, or obligations of either CCUD or RENTON regarding
provisions of sanitary sewer services to the properties described herein, or other
properties, except as specifically set forth herein.
DATED this 7th day of March 200 1 .
E.9
Authorized by Resolution No. 3489 of the City Council of the City of Renton,
Washington, at its regular meeting held on 26th day of February
200 1 .
CITY RENTON
7,0
Jes anner, Mayor Date
ATTEST:
Marilyn J. a en, City Clerk Da e
AP OVED AS TO LEGAL FORM:
Lawrence J. Wa , City Attorney
Approved by Resolution No. /5_7y/ -of the Board of Commissioners of
COAL CREEK UTILITY DISTRICT of King County, Washington, adopted at its
regular meeting held on /OP'day of I,s. , 200 .
COAL CREEK UT DISTRICT
By:
Title:
V
E.9
EXHIBIT"A"
NEW SEWER SERVICE
BOUNDARY LINE
LEGAL DESCRIPTION
A sanitary sewer service area boundary line between the Coal Creek Utility District and the City of
Renton through the Southeast quarter of Section 29,the East half(1/2)of Section 32,the South half(1/2)
of Section 33,all in Township 24 North, Range 5 East,W.M.,King County,Washington,and the North
half(1/2)of Section 4 in Township 23 North,Range 5 East,W.M.,King County, Washington, and the
common boundary line between Section 34 in said Township 24 and Section 3 in said Township 23,
described as follows:
Beginning at the intersection of the southerly right of way line of NE 48th St.with the existing
northernmost northwest corner of Tract 185 of C.D.Hillman's Lake Washington Garden of Eden No.3,
according to the Plat thereof, recorded in Volume 11,Page 81,Records of King County,Washington, in
the Southeast quarter of said Section 29;
Thence easterly along said southerly right of way line and north line of said Tract 185,to the northeast
corner of said Tract 185,said northeast corner also being the northwest corner of Lot 2 of King County
Short Plat No.485069,as recorded under King County Recording No. 8612231555,Records of King
County,Washington;
Thence southerly along the east line of said Tract 185 and the west line of said short plat,to the southwest
corner of Lot 1 of said short plat;
Thence easterly along the south line of said short plat,to the southeast corner thereof, said southeast
corner also being the northeast corner of Tract 183 of said plat;
Thence southerly along the common boundary line of said Tract 183 and Tract 166 of said plat,said
common boundary line also being the existing limits of City of Renton as annexed under Ordinance No.
1823,to an intersection with the northeasterly right of way line of NE 44th St.;
Thence continuing southerly along said common boundary line,crossing NE 44th St.,to the southwest
corner of said Tract 166;
Thence easterly along the south line of said Tract 166,to an intersection with the northerly extension of
the westerly right of way line of Monterey Pl.NE;
Thence southerly along said northerly extension and the westerly right of way line of Monterey Pl.NE,to
an intersection with the north line of Lot 8, Block 4 of said plat;
Thence westerly along said north line,to the northwest corner of said Lot 8;
Thence southerly along the west line of said Lot 8,to the southwest corner thereof, said southwest corner
also being the northeast corner of Lot 10, Block 4 of said plat;
Thence westerly along the north line of said Lot 10, to the northwest corner thereof, said northwest corner
also being a point on the easterly right of way line of Lincoln Ave.NE;
C ENTRAL\SYS2\DEPTS\PBP W\F LE.SYS\LND\O 1\0005-DOC
Page 1 of 3
E.9
EXHIBIT"A", Continued
Thence southerly along the west line of said Lot 10 and said easterly right of way line,to the southwest
corner of said Lot 10;
Thence southerly along the southerly extension of said west line of Lot 10 and said easterly right of way
line, crossing NE 36th St.,to an intersection with the southerly right of way line of said NE 36th St. in the
Southeast quarter of said Section 32;
Thence westerly along said southerly right of way line,to an intersection with the west line of the east
350 feet of Tract 70 of C.D. Hillman's Lake Washington Garden of Eden No. 1, according to the Plat
thereof, recorded in Volume 11,Page 63,Records of King County, Washington;
Thence southerly along said west'tine,to an intersection with the south line of said Tract 70;
Thence easterly along the south line of said Tract 70,said south line also being the north line of Tract 73
of said plat,to an intersection with the west line of the east 200 feet of said Tract 73;
Thence southerly along said west line,to an intersection with the south line of said Tract 73,said south
line also being the north line of Tract 74 of said plat;
Thence southerly along the west line of the east 200 feet of said Tract 74,to an intersection with the south
line of said Tract 74,said south line also being the north line of Tract 77 of said plat;
Thence southerly along the southerly extension of the west line of the east 200 feet of said Tract 74,to an
intersection with the westerly extension of the south line of the north 300 feet of Tract 364 of C.D.
Hillman's Lake Washington Garden of Eden No. 6,according to the Plat thereof,recorded in Volume 11,
Page 84,Records of King County,Washington;
Thence easterly along said westerly extension,exiting said Tract 77 and crossing Tract 76 of said C.D.
Hillman's Lake Washington Garden of Eden No. 1,to an intersection with the west line of said Tract 364
of C.D. Hillman's Lake Washington Garden of Eden No. 6;
Thence continuing easterly along the south line of the north 300 feet of said Tract 364,to an intersection
with the east line of said Tract 364;
Thence northerly along said east line,to the northeast comer thereof, said northeast corner also being a
point on the southerly right of way line of NE 33rd St.;
Thence easterly along the north line of Tracts 367 and 371 of said plat and said southerly right of way
line,to the northeast corner of said Tract 371 and said plat, in the Southwest quarter of said Section 33;
Thence southerly and westerly along the east line of said plat,to an intersection with the west line of said
Southwest quarter, said intersection being a point on the existing limits of the City of Renton, as annexed
under Ordinance No. 1835;
Thence southerly along said west line and said existing City limits, to an intersection with the south line
of the abandoned Pacific Coast Railroad right of way, said right of way being 200 feet in width, said
south line also being the north line of Tract 369 of said plat;
Thence easterly along said north line and along the existing limits of the City of Renton, as annexed
under Ordinance No. 1828, to the easternmost northeast corner of said Tract 369;
CENTRAL\SYS2\DEPTS\PBP W\FI L.E.SYS\LND\O I\0005.DOC
Page 2 of 3
E.9
EXHIBIT"A",Continued
Thence southeasterly along the east line of said Tract 369 and said existing City limits,to an intersection
with the north line of the Northwest quarter of said Section 4;
Thence easterly along said north line and the existing limits of the City of Renton, as annexed under
Ordinance No. 1796 and Ordinance No.4095,to an intersection with the westerly right of way line of
120th Pl. SE(County designation);i
Thence southerly along said westerly right of way line and said existing City limits,to an intersection
with the south line of the north 30 feet of said Northwest quarter;
d
Thence easterly along said south line and said existing City limits,to an intersection with the northerly
extension of the west line of Paradise Estates,according to the Plat thereof,recorded in Volume 95, Page
93,Records of King County, Washington;
Thence southerly along said northerly extension and west line of said plat and said existing City limits,to
the southwest corner of said plat;
Thence easterly along the south line of said plat and, in part,said existing City limits,to the southeast
corner thereof,said southeast corner also being the southwest corner of Paradise Estates No.2,according
to the Plat thereof,recorded in Volume 102,Page 31,Records of King County,Washington;
a
Thence easterly along the south line of said plat to an intersection with the east line of said Northwest
quarter;
Thence northerly along said east line of said Northwest quarter,to the quarter corner common to said
Section 4 and said Section 33;
Thence easterly along the common boundary line between said Section 4 and Section 33,to the northwest
corner of said Section 3 and the southwest corner of said Section 34;
Thence easterly along said common boundary line between said Section 3 and Section 34,to the
northeast corner of said Section 3 and southeast corner of said Section 34 and the terminus of this
boundary line.
i
CENTRAL\SYS2\DEP"I'S\PI3PW\FILF.SYS\1-ND\01\0005.DOC
Page 3 of 3
E.9
a r i ',e I pia'
in
as
t
in
r
i'i r jS
ELI
Mill
in
POWN
ON INS
rte,1 i 1 1 11. ...-::= - .
eN% i •
II 1111
A .G' •a t,! . •: @01ii/1Tl m rt ....: E
v vr'r. . 1 'ry MMM t/mMYYD moss 11 1
1
In
own
1! l/S rte i t I /iii.its
I VIII f1 "- . • /I'? j r
1/.Tru 11 i i,rrsca a /I r All«i
ON
16111 no'nsollsome w Ell,
rp.wage
inAge
Eli[ m
1111/11 ; *uZi
w i era
II :. :r...i 1: 711 :!lilliil IN
MEN' o .'. . I
2an
Ell - MEN
sue• j!l) I il ...
1 111 : 1 i
i 111
lli 11,i ME---,
C 111 il
f rn,,
Ell
111 .1r 111;x— Irn O
301 n, 1'-' i ice r7 ..' ,. .;_-•
nil-
O IVI111/,
1, /1 Cam.. .. . __
NI c,1/ ice 'i i'
E.9
EXHIBIT C CITY OF RENTON
NEW SEWER SERVICE BOUNDARY
JOINT USE 8" FACILITY
JOINT USE FACILITIES
0 500 1000
1 :6000
A
SE 80th
NE 3th I
i
i
1
w
NE 40th St
Z7
cCi
NE 36th
0
E.9
4
d'
c w`
CITY OF RENTON , WASHINGTON
RESOLUTION N0 . 2413
WHEREAS the City of Kent has within its municipal
boundaries a portion of land bordering S . 180th , also known as
S .W. 43rd, which area is not presently served by sewers ,, and
WHEREAS the City of Kent does not have at present the
ability to provide sewer service to that portion of lard , and
WHEREAS as part of the widening project on S . lV"h
Street (S .W. 43rd) , the City of Renton plans to install sanital.y
sewers , and
WHEREAS the City of Kent has previously recuested the
City of Renton to serve previously described land with the City of
Renton-' s sanitary sewer , and
WHEREAS it is agreed between the City of Renton and the
City of Kent that the City of Renton shall have the right to provide
sanitary sewer service to the City of Kent parcel along S . 180th
S .W. 43rd) described as Parcels 36 through 40 on the Exhibit
attached-.hereto and it is further agreed that the City of Renton
shall have the riglit to charge one and one-half times the normal
sewer service rate plus its normal connection charges , System
Development Charges , tap-in charges , and Community Facility Charges
as are applicable , now therefore
THE CITY COUNCIL OF THE CITY OF RENTON , WASHINGTON , DO
RESCLVE AS FOLLOWS :
SECTION I : The above recitals are found to be true
and correct in all resnects .
SECTION II : The Mayor and City Clerk are hereby authorized
to enter into an Interlocal Agreement with the City of Kent to
provide sewer service to those parcels along S . 180th Street as
per Exhibit "A" attached.
PASSED BY THE CITY COUNCIL this 3rd day of August , 1981 .
eo s A. Mea City Clerk
E.10
APPROVED BY THE -MAYOR this 3rd day of August , 1981 .
Frn p o:—
Approved as to form;
Laurence J . Warren , city Attorney
E.10
I
E
Resolution No. 2413
Exhibit
a
721m ,A-,V,. ENUE SOUTH g pp L
u
J
W
N' O
O
30 TA
i
h F i
I
V
0
O
f
j
IO
9
O
i
i 2"v
I
f
E.10
0161400
FRANCHISE NO. 14056
In the matter of the application for a franchise to operate, maintain, repair, and construct
sewer mains and service lines, and appurtenances in, over, along, and under County roads and
rights-of-way in King County, Washington.
The application of the City of Renton for a franchise to operate, maintain, repair and
construct sewer mains and service lines, and appurtenances in, over, along, and under County roads
and rights-of-way located within the area described in attached Exhibit "A" has been heard on this
day of MQ)7,h 91pp1 All of the property described in Exhibit "A" lies
outside the limits of any incorporated Town or City.
Legal notice of the franchise application and of the hearing has been given as is required by
law.
The King County Council, having considered the interests proposed and advanced, and
finding that the granting of this franchise is in the public interest, ORDERS that a franchise be
granted to the City of Renton, the Grantee, subject to the conditions set forth in Exhibit "B"
attached hereto, this franchise and Ordinance No. qO6 This franchise grants the right, privilege,
authority and franchise to operate, maintain, repair and construct mains and service lines and
appurtenances as a part of its distribution system in, over, along, and under County roads and rights-
of-way located within the area described in Exhibit "A".
1
03/12/01
E.11
iswe 4 4056
This franchise is granted subject to all of the terms and conditions contained herein, within
Ordinance No.10%and Exhibit "B",and shall expire in twenty-five years on 20 Z.z
Dated this day of
KING COUNTY, WASHINGTON
Ci-
BY
TITLE n h
U
The undersigned accepts all the rights, privileges, and duties of this franchise subject to all terms,
conditions, stipulations, and obligations contained herein, within Ordinance 1400 (o and Exhibit
B"
CITY OF RENTON
GRANTEE
BY
Jesse Tanner
TITLE Mayor
Marilyn J. _ersan, :;ity Clerk
Dated this /-3X day of 4.9 dt o
2
03/12/01
E.11
AMW wol 4056
Exhibit "A"
Area"A"
The lands included within Area "A" of the Sanitary Sewer Franchise are situated in the
Northwest quarter of Section 3 and the Northeast and Northwest quarters of Section 4, all in
Township 23 North, Range 5 East, W.M., King County, Washington, said Area "A" more
particularly described as bounded on the east, south and west by the existing City limit line of the
City of Renton and lying southerly of the following described line:
Beginning said line at the southwest corner of the plat of Paradise Estates No. 2, as recorded in
Volume 102 of Plats, Page 31, records of King County, Washington, said southwest corner also
being a point on the City limit line of the City of Renton as annexed under Ordinance No. 4337
in the Northwest quarter of said Section 4;
Thence easterly along the south line of said plat, to the southeast corner thereof, said southeast
corner also being a point on the west line of the Northeast quarter of said Section 4;
Thence northerly along said west line of said Northeast quarter to the northwest corner thereof;
Thence easterly along the north line of said Northeast quarter, to the northeast corner thereof,
said northeast corner also being a point on the centerline of Union Ave. NE (132nd
Ave. SE) and
also being the northwest corner of the Northwest quarter of said Section 3;
Thence continuing easterly along the north line of said Northwest quarter, crossing Union Ave.
NE (132nd
Ave. SE), to an intersection with the easterly right-of-way margin of Union Ave. NE
132nd
Ave. SE), said intersection also being a point on the City limit line of the City of Renton
as annexed under Ordinance No. 4780 and the termination of the herein before described line.
Area`B"
The lands included within Area "B" of the Sanitary Sewer Franchise are situated in the North
half(1/2) of Section 3, Township 23 North, Range 5 East, W.M., King County, Washington, said
Area"B" more particularly described as bounded on the east, south and west by the existing City
limit line of the City of Renton and lying southerly of the following described line:
Beginning said line at the intersection of the southwesterly right-of-way margin of SE 95th
Way
and the north line of said Section 3, said intersection also being a point on the City limit line of
the City of Renton as annexed under Ordinance No. 4195;
Thence easterly along said north line, crossing SE
95th
Way and Coal Creek Parkway SE, to the
northwest corner of Tract A of Stonegate, as recorded in Volume 177, Pages 62-88, inclusive,
1
03/12/01
E.11
I%W 14055
records of King County, Washington, said northwest corner also being a point on the City limit
line of the City of Renton as annexed under Ordinance No. 4510 and the termination of the
herein before described line.
Area"C"
The lands included within Area "C" of the Sanitary Sewer Franchise are situated in that portion
of the Northeast quarter of the Southwest quarter of Section 3, Township 23 North, Range 5 East,
W.M., King County, Washington, described as follows:
Beginning at the northwest corner of the south half (1/2) of Tract 13 of Joseph P. Marshall
Tracts, as recorded in Volume 38 of plats, Page 30, records of King County, Washington, said
northwest corner also being a point on the west line of said Northeast quarter of the Southwest
quarter;
Thence easterly along the north line of said south half(1/2), said north line also being the City
limit line of the City of Renton as annexed under Ordinance No. 2824, to the northeast corner of
said south half(1/2), said northeast corner also being a point on the westerly right-of-way margin
of Duvall Ave. NE (138th
Ave. SE);
Thence continuing easterly along the easterly extension of said north line of said south half(1/2),
crossing Duvall Ave. NE,to an intersection with the east margin of said Duvall Ave. NE;
Thence southerly along said east margin, to an intersection with the south line of said Northeast
quarter of the Southwest quarter;
Thence westerly along said south line and, in part, the City limit line of the City of Renton as
annexed under Ordinance No. 2894, to the southwest corner of said subdivision;
Thence northerly along the west line of said subdivision and the City limit line of the City of
Renton as annexed under Ordinance No. 2000, to an intersection with said northwest corner of
the south half(1/2) of Tract 13 of Joseph P. Marshall Tracts, and the point of beginning.
LESS that portion thereof annexed to the City of Renton under City of Renton Ordinance No.
2945
Area"D"
The lands included within Area"D" of the Sanitary Sewer Franchise are situated in Section 2,
Section 3, Section 10, Section 11, Section 12, Section 13, Section 14, Section 15, Section 21,
Section 22, Section 23 and Section 24, all in Township 23 North, Range 5 East, W.M. and
Section 18 and Section 19, both in Township 23 North, Range 6 East, W.M., all in King County,
Washington, said Area"D" being more particularly described as bounded on the west by the
existing City limit line of the City of Renton and lying southerly, westerly and northerly of the
2
03/12/01
E.11
ftov 400, 1403S
following described line:
Beginning at the intersection of the north line of the Northeast quarter of said Section 3 and the
westerly right-of-way margin of
148th
Ave. SE (Orcas Ave. NE) said intersection also being a
point on the City limit line of the City of Renton as annexed under Ordinance No. 4510;
Thence westerly along said north line of the Northeast quarter, crossing a portion of
148th
Ave.
SE, to the Northeast corner thereof, said Northeast corner also being the Northwest corner of said
Section 2 and also being the centerline of
148th
Ave. SE;
Thence continuing westerly along the north line of said Section 2,to an intersection with the
northerly extension of the easterly right-of-way margin of
148th
Ave. SE;
Thence southerly along said northerly extension and the easterly right-of-way margin of
148th
Ave. SE, to an intersection with the north line of the Southwest quarter of said Section 11;
Thence easterly along said north line, to the northeast corner of said Southwest quarter;
Thence southerly along the east line of said Southwest quarter,to an intersection with the
northerly right-of-way margin of SE 128th
Street;
Thence easterly along the courses of the northerly right-of-way margin of SE 128th
Street,
crossing
160th
Ave. SE,
164th
Ave. SE and
169th
Ave. SE,to an intersection, in the Southwest
quarter of said Section 12, with the northerly extension of the east line of the west half(1/2) of
the east half(1/2) of the west half(1/2) of the Northeast quarter of the Northwest quarter of said
Section 13;
Thence southerly along said northerly extension, and said east line of said subdivision, to an
intersection with a line 30 feet north of the south line of said Northeast quarter of the Northwest
quarter of said Section 13;
Thence easterly along said north line, to an intersection with the east line of said subdivision,
said east line also being the west line of the north half(1/2) of the Northeast quarter of said
Section 13;
Thence continuing easterly alonthe north line of the south 30 feet of said north half(1/2),
crossing
172nd
Ave. SE and
175t
Ave. SE, to an intersection with the east line of said
subdivision, said east line also being the west line of the Northwest quarter of the Northwest
quarter of said Section 18;
Thence continuing easterly along the north line of the south 30 feet of said Northwest quarter of
the Northwest quarter, to an intersection with the northerly extension of the easterly right-of-way
margin of
182n
Ave. SE;
3
03/12/01
E.11
W MW J4056 _
4"
Thence southerly along said northerly extension and the easterly right-of-way margin of
182nd
Ave. SE, crossing SE
132nd
Street, to an intersection with the northerly right-of-way margin of
SE
134th
Street in the Southwest quarter of the Northwest quarter of said Section 18;
Thence easterly along said northerly right-of-way margin and the easterly extension of said
northerly right-of-way margin, crossing
184th
Ave. SE, to an intersection with the easterly right-
of-way margin of
184th
Ave. SE in the Southeast quarter of the Northwest quarter of said
Sectionl 8;
Thence southerly along said easterl right-of-way margin of
184th
Ave. SE and the southerly
extension thereof, crossing SE 1351
Street, SE 136th
Street and SE 144th
Street, to an intersection
with the southerly right-of-way margin of SE 144th
Street, as deeded to King County per King
County Recording No. 3000495 in the Northwest quarter of said Section 19;
Thence continuing southerly along said southerly extension, to an intersection with the north line
of Lot 1 of King County Short Plat No. 681066, as recorded under King County Recording No.
8301240686;
Thence easterly along the north line of said Lot 1 and the north line of Lot 2 of said short plat, to
the northeast corner of said Lot 2;
Thence southerly along the east line of said Lot 2 and the east line of Lot 3 of said short plat, to
the southeast corner of said Lot 3, said southeast corner also being the northeast corner of Lot 3
of King County Short Plat No. 681067, as recorded under King County Recording No.
8301240687;
Thence southerly along the east line of said Lot 3 and the east line of Lot 2 of said short plat, to
the southeast corner of said Lot 2;
Thence westerly along the south line of said Lot 2 and the south line of Lot 1 of said short plat, to
the southwest corner of said Lot 1, said southwest corner also being the southeast corner of the
plat of Renton-Suburban Tracts Division No. 8, as recorded in Volume 69 of plats, Pages 74-76,
inclusive, records of King County, Washington, in Government Lot 1 of said Section 19;
Thence westerly along the courses of the south boundary of said plat, to an intersection with the
south line of the plat of Renton-Suburban Tracts Div. No. 6, as recorded in Volume 66 of plats,
Pages 33-35, inclusive, records of King County, Washington in the Northeast quarter of said
Section 24;
Thence westerly along the south line of said plat, to the most southwest corner thereof, said
southwest corner also being the northeast corner of Government Lot 5 of said Section 24;
Thence southerly along the east line of said Government Lot 5, to the northeast corner of Lot 31
of the plat of Renton-Suburban Tracts Div. No. 7, as recorded in Volume 69, Pages 39-41,
4
03/12/01
E.11
I%W r r
A
1 ,01
inclusive, records of King County, Washington;
Thence southwesterly and northwesterly along the courses of the south boundary of said plat, to
an intersection with the east line of Government Lot 10 of said Section 24, said east line also
being the east line of Tract A of the plat of Briarwood South No. 6, as recorded in Volume 97,
Pages 68-69, records of King County, Washington;
Thence northerly along said east line of said Government Lot 10 and said Tract A, to an
intersection with the southerly right-of-way margin of SE
1491h
Street;
Thence westerly along said right-of-way margin and the courses of the north boundary of said
Tract A, to the northwest corner thereof, said northwest corner also being a point on the east line
of the Northeast quarter of said Section 23;
Thence northerly along said east line,to the most northeast corner of Tract C of Skyfire Ridge
Div. No. 1, as recorded in Volume 141, Pages 93-99, inclusive, records of King County,
Washington;
Thence westerly along the courses of the north boundary of said Tract C, to the northwest corner
thereof, said northwest corner also being a point on the east line of the Southwest quarter of the
Northeast quarter of said Section 23;
Thence northerly along said east line, to the northeast corner of said subdivision;
Thence westerly along the north line of said subdivision, to the northwest corner of said
subdivision, said northwest corner also being the northeast corner of Government Lot 7 of said
Section 23;
Thence North 88° 00'30" West along the north line of said Government Lot 7, a distance of 100
feet;
Thence South 31° 31'00" West, a distance of 648 feet;
Thence North 55°51'30" West, a distance of 250 feet;
Thence South 31°31'00" West, a distance of 150 feet;
Thence North 55°51'30" West, to an intersection with the southeasterly right-of-way margin of
154th
Place SE (Orton County Road);
Thence southwesterly along said southeasterly right-of-way margin and the southwesterly
extension of said southeasterly right-of-way margin, crossing SE Jones Road (JE Jones Road)to
an intersection with the southwesterly right-of-way margin of SE Jones Road (JE Jones Road);
5
03/12/01
E.11
A. 4 0 ' 6 'taw
Thence southwesterly, crossing the Cedar River and SE Renton-Maple Valley Highway(SR 169,
P.S.H. No. 5), to the point on the southwesterly right-of-way margin of said right-of-way
opposite Station 368+02, per Sheet 5 of 9, Cedar Grove Park Vicinity to Maplewood Golf
Course Vicinity, State of Washington Highway Maps;
Thence northwesterly along the courses of the southwesterly right-of-way margin of SE Renton-
Maple Valley Highway(SR 169, P.S.H. No. 5), crossing
152nd
Ave. SE and
140th
Way SE, to an
intersection with the thread of the Cedar River in the Northwest quarter of said Section 22;
Thence southwesterly, westerly and northwesterly along said thread of the Cedar River, to the
intersection with the City limit line of the City of Renton as annexed under Ordinance No. 3723
in the Southeast quarter of said Section 21 and the termination of the herein before described
line.
Area"E"
The lands included within Area "E" of the Sanitary Sewer Franchise are situated in Sections 12,
13 and 14, all in Township 23 North, Range 4 East, W.M., and Sections 7 and 18, Township 23
North, Range 5 East, W.M., all in King County, Washington, bounded on the east and south by
the existing City limit line of the City of Renton and lying southerly and easterly of the following
described line:
Beginning at the northeast corner of Lot 32 of Junction Addition to Seattle, as recorded in
Volume 12 of Plats, Page 75, records of King County, Washington, said northeast corner also
being a point on the City limit line of the City of Renton as annexed under Ordinance No. 4642
and also being a point on the northerly right-of-way margin of South
137th
Street in said Section
14;
Thence easterly along the north line of said plat and said northerly right-of-way margin, to the
southwest corner of condominium plat of Empire Estates, as recorded in Volume 28 of
Condominiums, Pages 106-120, inclusive, records of King County, Washington in said Section
13;
Thence northerly, easterly and northerly along the west line of said condominium plat, to an
intersection with the southerly right-of-way margin of Martin Luther King Way South (also
known as Empire Way South and State Road No. 2);
Thence continuing northerly along the northerly extension of said west line, crossing Martin
Luther King Way South, to an intersection with the northerly right-of-way margin of Martin
Luther King Way South;
6
03/12/01
E.11
NWO, maw 4 0 ,5 s
Thence southeasterly along the courses of said northerly right-of-way margin, crossing S. 135th
Street, to an intersection with the west line of Lot 1, Block 2 of Stiles View Tracts, as recorded in
Volume 46 of Plats, Page 85, records of King County, Washington;
Thence northerly along said west line, to an intersection with the south line of the north 180 feet
of said Block 2;
Thence easterly along said south line, crossing Lots 1-7, inclusive, of said Block 2, to an
intersection with the east line of said Lot 7, said east line also being the west line of Lot 8, Block
4 of R.L Haddock Addition to Earlington, as recorded in Volume 38 of Plats, Pages 4-5, records
of King County, Washington;
Thence northerly along said west line of said Lot 8, to the southwest corner of Lot 1 of King
County Short Plat No. 982004, recorded under King County Recording No. 8301040882;
Thence easterly along the south line of said Lot 1 and the easterly extension of said south line,
crossing Lots 8-6, inclusive, of said Block 4, to an intersection with the east line of said Lot 6;
Thence northerly along said east line, to the northeast corner of said Lot 6;
Thence northerly, crossing S. 135th
Street, to the southwest corner of Lot 5, Block 3 of said plat;
Thence northerly along the west line of said Lot 5 and the northerly extension of said west line,
crossing S. 134th
Street and the Cedar River Pipeline right-of-way, to an intersection with the
northerly right-of-way margin of said street and said pipeline;
Thence southeasterly along said northerly right-of-way margin of said street and pipeline, to an
intersection with the westerly right-of-way margin of
76th
Avenue S., said westerly right-of-way
margin also being the west line of the Northeast quarter of said Section 13;
Thence northerly along said westerly right-of-way margin and said west line, crossing S. 132nd
Street and S. Langston Road (also known as John Langston Road No. 3 and
78th
Avenue S.
Extension Revision), to an intersection with the northerly right-of-way margin of said S.
Langston Road;
Thence northeasterly along said northerly right-of-way margin, crossing
76th Avenue S., to an
intersection with the westerly extension of the north line of Block 7 of Earlington Acre Tracts, as
recorded in Volume 15 of Plats, Page 84, records of King County, Washington;
Thence easterly along said westerly extension and the north line of said Block 7, to the northwest
corner of Lot 2 of said Block 7;
Thence southerly along the west line of said Lot 2, to an intersection with the south line of the
north 100 feet of said Lot 2;
7
03/12/01
E.11
Now, e 14
Thence easterly along said south line, to an intersection with the east line of said Lot 2;
Thence northerly along said east line, to the northeast corner of said Lot 2 and a point on the
north line of said Block 7;
Thence easterly along said north line, to the northeast corner of Lot 1 of said Block 7, said
northeast corner also being a point on the westerly right-of-way margin of
80th
Avenue S.;
Thence northerly along said westerly right-of-way margin and the northerly extension of said
westerly right-of-way margin crossing Renton Avenue S. and S. 128th
Street, to an intersection
with the westerly extension of the northerly right-of-way margin of S. 128th
Street in the
Southeast quarter of said Section 12;
Thence easterly along said westerly extension and the northerly right-of-way margin of S. 128th
Street, crossing
80th
Avenue S. and
82nd
Avenue S., to an intersection with the westerly right-of-
way of
84th
Avenue S.;
Thence northerly along said westerly right-of-way margin, crossing S. 126th
Street, to an
intersection with the westerly extension of the north boundary of the plat of Conner's Lake View
Park No. 2, as recorded in Volume 78 of Plats, Page 64, records of King County, Washington;
Thence easterly along said westerly extension and the north boundary of said plat, crossing
84th
Avenue S., to the northeast corner of said plat in the Southwest quarter of said Section 7, said
north boundary also being the City limit line of the City of Renton as annexed under Ordinance
No. 1669 and said northeast corner also being the northwest corner of the plat of Conner's Lake
View Park, as recorded in Volume 72 of Plats, Page 31, records of King County, Washington;
Thence easterly along said north boundary and said existing City limit line, to an intersection
with the west line of the east 140 feet of the Southwest quarter of the Southwest quarter of said
Section 7;
Thence northerly along said west line, to an intersection with the south line of the north 145.575
feet of said subdivision;
Thence easterly along said south line, to an intersection with the westerly right-of-way margin of
Stevens Avenue S. (87th
Avenue S.);
Thence northerly along said westerly right-of-way margin, crossing S. 124th
Street and S. 123rd
Street, to an intersection with the westerly extension of the northerly right-of-way margin of NW
7th
Street (S. 122nd Street);
Thence easterly along said westerly extension and the northerly right-of-way margin of NW
7th
Street (S. 122nd Street), crossing Stevens Avenue S. (87th
Ave. S.), to the end of the right-of-way
8
03/12/01
E.11
4 0
for said street as determined by City of Renton Street Vacation Ordinance No. 3455 and the
termination of the herein before described line, said termination point also being the City limit
line of the City of Renton as annexed under Ordinance No. 2426.
Area"F"
The lands included within Area "E" of the Sanitary Sewer Franchise are situated in Sections 12,
13 and 14, all in Township 23 North, Range 4 East, W.M., and Sections 7 and 18, Township 23
North, Range 5 East, W.M., all in King County, Washington, bounded on the east and south by
the existing City limit line of the City of Renton and lying southerly and easterly of the following
described line:
Beginning at the northeast corner of Lot 32 of Junction Addition to Seattle, as recorded in
Volume 12 of Plats, Page 75, records of King County, Washington, said northeast corner also
being a point on the City limit line of the City of Renton as annexed under Ordinance No. 4642
and also being a point on the northerly right-of-way margin of South 137`x'
Street in said Section
14;
Thence easterly along the north line of said plat and said northerly right-of-way margin, to the
southwest corner of condominium plat of Empire Estates, as recorded in Volume 28 of
Condominiums, Pages 106-120, inclusive, records of King County, Washington in said Section
13;
Thence northerly, easterly and northerly along the west line of said condominium plat, to an
intersection with the southerly right-of-way margin of Martin Luther King Way South (also
known as Empire Way South and State Road No. 2);
Thence continuing northerly along the northerly extension of said west line, crossing Martin
Luther King Way South, to an intersection with the northerly right-of-way margin of Martin
Luther King Way South;
Thence southeasterly along the courses of said northerly right-of-way margin, crossing S. 135th
Street,to an intersection with the west line of Lot 1, Block 2 of Stiles View Tracts, as recorded in
Volume 46 of Plats, Page 85, records of King County, Washington;
Thence northerly along said west line, to an intersection with the south line of the north 180 feet
of said Block 2;
Thence easterly along said south line, crossing Lots 1-7, inclusive, of said Block 2, to an
intersection with the east line of said Lot 7, said east line also being the west line of Lot 8, Block
4 of R.L Haddock Addition to Earlington, as recorded in Volume 38 of Plats, Pages 4-5, records
of King County, Washington;
9
03/12/01
E.11
14 0 , 6
Thence northerly along said west line of said Lot 8, to the southwest corner of Lot 1 of King
County Short Plat No. 982004, recorded under King County Recording No. 8301040882;
Thence easterly along the south line of said Lot 1 and the easterly extension of said south line,
crossing Lots 8-6, inclusive, of said Block 4, to an intersection with the east line of said Lot 6;
Thence northerly along said east line, to the northeast corner of said Lot 6;
Thence northerly, crossing S. 135th
Street, to the southwest corner of Lot 5, Block 3 of said plat;
Thence northerly along the west line of said Lot 5 and the northerly extension of said west line,
crossing S. 134th
Street and the Cedar River Pipeline right-of-way, to an intersection with the
northerly right-of-way margin of said street and said pipeline;
Thence southeasterly along said northerly right-of-way margin of said street and pipeline, to an
intersection with the westerly right-of-way margin of
76th
Avenue S., said westerly right-of-way
margin also being the west line of the Northeast quarter of said Section 13;
Thence northerly along said westerly right-of-way margin and said west line, crossing S. 132nd
Street and S. Langston Road (also known as John Langston Road No. 3 and
78th
Avenue S.
Extension Revision), to an intersection with the northerly right-of-way margin of said S.
Langston Road;
Thence northeasterly along said northerly right-of-way margin, crossing
76th
Avenue S., to an
intersection with the westerly extension of the north line of Block 7 of Earlington Acre Tracts, as
recorded in Volume 15 of Plats, Page 84, records of King County, Washington;
Thence easterly along said westerly extension and the north line of said Block 7, to the northwest
corner of Lot 2 of said Block 7;
Thence southerly along the west line of said Lot 2, to an intersection with the south line of the
north 100 feet of said Lot 2;
Thence easterly along said south line,to an intersection with the east line of said Lot 2;
Thence northerly along said east line, to the northeast corner of said Lot 2 and a point on the
north line of said Block 7;
Thence easterly along said north line, to the northeast corner of Lot 1 of said Block 7, said
northeast corner also being a point on the westerly right-of-way margin of
80th
Avenue S.;
Thence northerly along said westerly right-of-way margin and the northerly extension of said
westerly right-of-way margin crossing Renton Avenue S. and S. 128th Street, to an intersection
10
03/12/01
E.11
E.11
40
with the westerly extension of the northerly right-of-way margin of S. 128th
Street in the
Southeast quarter of said Section 12;
Thence easterly along said westerly extension and the northerly right-of-way margin of S.
128th
Street, crossing
80th
Avenue S. and
82nd
Avenue S., to an intersection with the westerly right-of-
way of
84th
Avenue S.;
Thence northerly along said westerly right-of-way margin, crossing S.
126th
Street, to an
intersection with the westerly extension of the north boundary of the plat of Conner's Lake View
Park No. 2, as recorded in Volume 78 of Plats, Page 64, records of King County, Washington;
Thence easterly along said westerly extension and the north boundary of said plat, crossing
84th
Avenue S., to the northeast corner of said plat in the Southwest quarter of said Section 7, said
north boundary also being the City limit line of the City of Renton as annexed under Ordinance
No. 1669 and said northeast corner also being the northwest corner of the plat of Conner's Lake
View Park, as recorded in Volume 72 of Plats, Page 31, records of King County, Washington;
Thence easterly along said north boundary and said existing City limit line, to an intersection
with the west line of the east 140 feet of the Southwest quarter of the Southwest quarter of said
Section 7;
Thence northerly along said west line, to an intersection with the south line of the north 145.575
feet of said subdivision;
Thence easterly along said south line, to an intersection with the westerly right-of-way margin of
Stevens Avenue S. (87th
Avenue S.);
Thence northerly along said westerly right-of-way margin, crossing S. 124th
Street and S.
123rd
Street, to an intersection with the westerly extension of the northerly right-of-way margin of NW
7th Street (S. 122nd
Street);
Thence easterly along said westerly extension and the northerly right-of-way margin of NW 7th
Street(S.
122nd
Street), crossing Stevens Avenue S. (
87th Ave. S.), to the end of the right-of-way
for said street as determined by City of Renton Street Vacation Ordinance No. 3455 and the
termination of the hereinbefore described line, said termination point also being the City limit
line of the City of Renton as annexed under Ordinance No. 2426.
Area"G"
The lands included within Area "G" of the Sanitary Sewer Franchise are situated in that portion
of the Southeast quarter of the Northwest quarter of Section 29, Township 23 North, Range 5
East, W.M., King County, Washington, described as follows:
Beginning at the northwest corner of the Southeast quarter of the Northwest quarter of said
11
03/12/01
E.11
E.11
AW 4056 t05
Section 29;
Thence easterly along the north line of said subdivision and the City limit line of the City of
Renton as annexed under Ordinance No. 1909, to an intersection with the westerly right-of-way
margin of Benson Road S. (previously Secondary State Hwy 5C);
Thence southeasterly along said westerly right-of-way margin and the City limit line of the City
of Renton as annexed under Ordinance No. 1971, crossing
106th
Ave. SE, to an intersection with
a line 20 feet westerly of, and parallel with, the east line of Lot 2, Block 4, Aker's Farms No. 5,
as recorded in Volume 40, Page 27, records of King County, Washington;
Thence southerly along said parallel line, to an intersection with a line 120 feet north of, and
parallel with,the south line of said Lot 2;
Thence westerly along said parallel line, to an intersection with the west line of said Lot 2, said
west line also being the east line of Lot 1 of said Block 4;
Thence northerly along said west line and said east line, to an intersection with the north line of
the south 273 feet of said Lot 1;
Thence westerly along said north line, to an intersection with the west line of said Lot 1, said
west line also being the easterly right-of-way margin of
106th
Ave. SE;
Thence northwesterly, crossing
106th
Ave. SE, to the southeast corner of Lot 5, Block A of said
plat, said southeast corner also being a point on the westerly right-of-way margin of
106th Ave.
SE;
Thence northerly along the east line of said Lot 5 and said westerly right-of-way margin, to a
point 107 feet southerly of the northeast corner of said Lot 5;
Thence northwesterly, to a point on the northwesterly line of said Lot 5, said point being 107 feet
southwesterly of the northwest corner of said Lot 5 and also being a point on the southeasterly
line of Lot 4 of said Block A;
Thence southwesterly along said southeasterly line, to a point equidistant from the northeast and
southeast corners of said Lot 4;
Thence northwesterly, to an point on the northwesterly line of said Lot 4, said point being
equidistant from the northwest and southwest corners of said Lot 4 and said northwesterly line
also being the southeasterly line of Lot 2 of said Block A;
Thence southwesterly along said southeasterly line, to an intersection with the northerly right-of-
way margin of SE 166th
Street;
12
03/12/01
E.11
140 -19 :
Thence southwesterly, crossing SE
166th
Street, to an intersection with the southerly right-of-way
margin of SE
166th
Street and the north line of Lot 1, Block 2 of said plat, at a point 62.5 feet
westerly of the northeast corner of said Lot 1;
Thence southerly along a line 62.5 feet westerly of, and parallel with, the east line of said Lot 1,
to an intersection with the south line of said Lot 1, said south line also being the north line of Lot
2 of said Block 2;
Thence westerly along said north line, to an intersection with a line 127 feet east of, and parallel
with, the west line of said Lot 2;
Thence southerly along said parallel line, to an intersection with the south line of said Lot 2, said
south line also being the north line of Lot 3 of said Block 2;
Thence easterly along said north line, to an intersection with the east line of the west half(1/2) of
said Block 2;
Thence southerly along said east line, crossing Lots 3 and 4 of said Block 2, to an intersection
with the south line of said Lot 4;
Thence westerly along said south line, to the southwest corner thereof, said southwest corner also
being a point on the easterly right-of-way margin of Cedar Ave. S. (104th
Ave. SE);
Thence continuing westerly along the westerly extension of said south line, to the west line of
said Southeast quarter of the Northwest quarter, said west line also being the centerline of Cedar
Ave. S. (104th
Ave. SE);
Thence northerly along, in part, said centerline and along said west line, said west line also being,
in part, the City limit line of the City of Renton as annexed under Ordinance No. 1971, to the
northwest corner of said subdivision and the point of beginning.
LESS that portion thereof annexed to the City of Renton under City of Renton Ordinance No.
3864.
Area"H"
The lands included within Area "H" of the Sanitary Sewer Franchise are situated in that portion
of the Northeast quarter of the Northeast quarter of Section 31, Township 23 North, Range 5
East, W.M., King County, Washington, described as follows:
Beginning at the intersection of the north line of said Northeast quarter of the Northeast quarter
and the easterly right-of-way margin of Talbot Road S. (Springbrook Rd.);
Thence southerly along said easterly right-of-way margin, to the northwest corner of the plat of
13
03/12/01
E.11
4 0 5
Scott's Terrace, as recorded in Volume 72, Pages 39-40, records of King County, Washington;
Thence easterly along the north line of said plat, to the northeast corner thereof,
Thence southeasterly, southerly and southeasterly along the east boundary of said plat, to the
southeast corner thereof, said southeast corner also being a point on the northerly right-of-way
margin of Carr Road (S.
179th
Street) and also being a point on the City limit line of the City of
Renton as annexed under Ordinance No. 4142;
Thence westerly, southwesterly and westerly along said northerly right-of-way margin and said
existing City limit line, crossing
98th
Ave. S., to the beginning of a curve to the right, having a
radius of 44.50 feet;
Thence northerly along said curve and said existing City limit line, an arc length of 24.54 feet, to
a point on the easterly right-of-way margin of Talbot Road S.;
Thence northwesterly radically to said easterly right-of-way margin and along said existing City
limit line, a distance of 65 feet, to a point on a curve to the right on the former westerly right-of-
way margin of Talbot Road S., said curve having a radius of 830.00 feet;
Thence northerly along said former right-of-way margin and the City limit line of the City of
Renton as annexed under Ordinance No. 1743, to an intersection with the existing westerly right-
of-way margin of Talbot Road S.;
Thence continuing northerly along said westerly right-of-way margin and said existing City limit
line, to an intersection with the north line of said Northeast quarter of the Northeast quarter, said
north line also being, in part, the City limit line of the City of Renton as annexed under
Ordinance No. 4476;
Thence easterly along said north line and said existing City limit line, crossing Talbot Road S., to
an intersection with the easterly right-of-way margin of Talbot Road S. and the point of
beginning.
Area"I"
he lands included within Area "I" of the Sanitary Sewer Franchise are situated in that portion of
the Northeast quarter of Section 6, Township 22 North, Range 5 East, W.M., King County,
Washington, described as follows:
That portion of Tract 11 of Springbrook Acre Tracts, as recorded in Volume 12 of plats, Page 60,
records of King County, Washington, lying northerly and westerly of the plat of Talbot Estates,
as recorded in Volume 172 of plats, Pages 1 through 3, inclusive, records of King County,
Washington, easterly of Talbot Road S. (96th
Ave. S.) and the City limit line of the City of
Renton as annexed under Ordinance No. 3751, and southerly of the County Road and the City
14
03/12/01
E.11
bpi
14056
limit line of the City of Renton as annexed under Ordinance No. 3268.
Area"J"
The lands included within Area "J" of the Sanitary Sewer Franchise are situated in the Northeast
quarter of Section 6, Township 22 North, Range 5 East, W.M., King County, Washington,
described as follows:
Beginning at the intersection of the southerly right-of-way margin of S.
55th
Street (S. 192°
a
St.,
John Krumm Rd. No. 195) and the west line of said Northeast quarter;
Thence easterly along said southerly right-of-way margin, said right-of-way margin also being
the City limit line of the City of Renton as annexed under Ordinance No. 3268, to the beginning
of a curve to the right having a radius of 25 feet;
Thence southerly along said curve an arc length of 38.58 feet, to a point on the westerly right-of-
way margin of Talbot Road S.;
Thence southerly along said westerly right-of-way margin, said right-of-way margin also being
the City limit line of the City of Renton as annexed under Ordinance No. 3 75 1, to an angle point
in said existing City limit line;
Thence easterly along said existing City limit line, crossing Talbot Road S., to an intersection
with the easterly right-of-way margin of Talbot Road S., said intersection also being a point of
intersection with the westerly right-of-way margin of a 40 feet wide county road as shown on the
plat of Springbrook Acre Tracts, as recorded in Volume 12 of plats, Page 60, records of King
County, Washington;
Thence southeasterly and southwesterly along said westerly right-of-way margin of said county
road and said existing City limit line, to an intersection with the easterly right-of-way margin of
Talbot Road S.;
Thence southerly along said easterly right-of-way margin and, in part, said existing City limit
line, to an intersection with the easterly extension of the north line of the south 132 feet of Tract
1 of said plat;
Thence westerly along said easterly extension and the north line of the south 132 feet of Tract 1
of said plat, crossing Talbot Road S., to an intersection with a line lying 660 feet westerly of said
county road, as measured along the south line of said Tract 1, and perpendicular to said south line
of said Tract 1;
Thence southerly along said perpendicular line, to an intersection with the south line of said
Tract 1;
15
03/12/01
E.11
r.,, 14 0 5 6 4 ;:
Thence westerly along said south line, to the southwest corner of said Tract 1, said southwest
corner also being a point on the west line of said Northeast quarter;
Thence northerly along said west line of said Northeast quarter, to an intersection with the
southerly right-of-way margin of S. 55th
Street, and the point of beginning.
Area"K"
Beginning at the southeast corner of the plat of Talbot Estates, as recorded in Volume 172 of
plats, Pages 1 through 3, inclusive, records of King County, Washington, said southeast corner
also being a point on the north line of Tract 9 of Springbrook Acre Tracts, as recorded in Volume
12 of plats, Page 60, records of King County, Washington;
Thence southerly along the southerly extension of the east line of said plat of Talbot Estates, to
an intersection with the City limit line of the City of Renton as annexed under Ordinance No.
3109 within said Tract 9;
Thence northwesterly along said existing City limit line, to an intersection with the south line of
said plat of Talbot Estates and the north line of said Tract 9 of the plat of Springbrook Acre
Tracts;
Thence easterly along said south line and said north line,to the southeast corner of said plat of
Talbot Estates, and the point of beginning.
16
03/12/01
E.11
14 0 6
EXHIBIT`B"
TERMS AND CONDITIONS APPLICABLE TO UTILITIES FRANCHISES GRANTED BY
KING COUNTY
THIS FRANCHISE is subject to the following terms and conditions:
1. DEFINITIONS
References to any County official or office also refers to any office that succeeds to any or all of the
responsibilities of the named office or official. References to laws or "applicable laws" include
federal, state, and local laws and regulations adopted pursuant to those laws; unless otherwise
stated, references to laws include laws now in effect, as the same may be amended from time to
time during the operation of this franchise. In addition,the following definitions shall apply:
Cable Services. The term "Cable Services" is used as defined in 47 United States Code 522 (5), as
amended.
Cable System. The term "Cable System" is used as defined in 47 United States Code 522 (6), and
King County Code 6.a.010 (J)as amended.
County Road Rights-of-Way. The term "County Road Rights-of-Way" includes any road, street,
avenue, or alley located within the area described in the attached Exhibit "A", it does not include
recreational or nature trails except where the trails intersect or are within roads, streets, avenues or
alleys.
Director. The term 'Director" refers to the chief executive of the King County Department of
Transportation.
Grantee. The term "Grantee" refers to the CITY OF RENTON its successors and those assignees
approved pursuant to paragraph 16 herein.
Utili . The term "utility" refers either to the Grantee or, depending on the context, to any other
person, firm, or corporation, public or private, which may hold a franchise to maintain and operate
similar facilities in, under, over, across, and along any of the County property described in Exhibit
Alf.
Council. The term "Council" refers to the King County Council, acting in its official capacity.
17
03/12/01
E.11
14056 1
Other Governing Body. The term "Other Governing Body" refers to any public official or other
public board or body as may have the power and jurisdiction to permit or regulate the installation
and maintenance of utilities and other facilities in, under, over, across, and along any of the county
property described in Exhibit "A".
2. ACCEPTANCE BY GRANTEES OF TERMS AND CONDITIONS
The full acceptance of this franchise and all of its terms and conditions shall be filed with the Clerk
of the Council within thirty (30) days from 19 , by the Grantee. Full
acceptance of this franchise is a condition precedent to its taking effect, and unless this franchise is
accepted within the time specified,this grant will be null and void and have no force or effect.
3. NON-EXCLUSIVE FRANCHISE
This franchise is not exclusive. It does not prohibit King County from granting franchises for other
public or private utilities, in, under, over, across, and along any County property, including County
road rights-of-way.
This franchise does not prevent or prohibit King County from constructing, altering, maintaining or
using any County road rights-of-way covered by this franchise. King County retains full power to
make all changes,relocations,repair,maintenance, etc. as it may deem fit.
4. JURISDICTION
This franchise is intended to convey limited rights and interest only as to those roads and rights- of-
way in which King County has an actual interest. It is not a warranty of title or of interest in County
road rights-of-way.
Whenever any of the County road rights-of-way as designated in this franchise, by reason of the
subsequent incorporation of any Town or City or extension of the limits of any Town or City, shall
later fall within the City or Town limits, this franchise shall continue in force and effect until such
time as the incorporation and/or annexation is complete according to applicable State law, after
which time the County will no longer have any responsibility for maintenance of any County roads,
rights-of-way or other County property within the area of annexation/incorporation.
None of the rights granted to the Grantee shall affect the jurisdiction of King County over County
road rights-of-way or the County's power to perform work upon its roadways, rights-of-way or
appurtenant drainage facilities including by constructing, altering, renewing, paving, widening,
grading, blasting or excavating.
All of the rights herein granted shall be subject to and governed by this franchise; provided,
however, that nothing in this franchise may be construed in any way as limiting King County's
rights to adopt ordinances which are necessary to protect the health, safety and welfare of the
general public.
18
03/12/01
E.11
Nose 0 4 Q
5. REGULATION OF USE AND CONTROL
This franchise does not deprive King County of any powers, rights, or privileges it now has or may
later acquire in the future to regulate the use of and to control the County road rights-of-way
covered by this franchise.
This franchise authorizes the use of County rights-of-way solely for the delivery by the Grantee of
sewer to it customers. Additional uses of County rights-of-way by the Grantee, including for cable
communication services, shall first require a separate franchise from King County which conforms
to the requirements of K.C.C. 6.27 as amended, or K.C.C. 6.27A as amended, and other applicable
law.
Any use of the Grantee's equipment of facilities in County rights-of-way by others, including for
telecommunication or cable communication services, is prohibited unless separately authorized and
approved in writing by King County. The Grantee agrees that prior to authorizing any person to use
the Grantee's equipment or facilities located in County rights-of-way, the Grantee will require the
user to provide the Grantee with an affidavit that it has obtained the necessary franchise or other
approval from the County to operate and provide the proposed service in County rights-of-way. At
least thirty (30) day prior to executing any agreement with a potential user for the use of the
Grantee's equipment or facilities, the Grantee shall fax the affidavit to the King County Office of
Cable Communication at 206-296-0842.
6. EMINENT DOMAIN
This franchise and the limited rights and interests for the operation, maintenance, repair, and
construction of Grantee's transmission and service lines and appurtenances are subject to the
exercise of eminent domain. In the event of an exercise of eminent domain by King County, the
value to be attributed to all the rights and interests granted under this franchise shall not exceed the
actual amount the Grantee paid to King County in obtaining this franchise.
7. ENFORCEMENT
Failure of King County, on one or more occasions to exercise a right or to require compliance or
performance under this franchise or any applicable law, shall not be deemed to constitute a waiver
of such right or a waiver of compliance or performance, unless such right has been specifically
waived in writing. Failure of King County to enforce or exercise its rights under any provision of
this franchise or applicable law does not constitute a waiver of its rights to enforce or exercise a
right in any other provision of this franchise or applicable law.
8. INDEMNITY AND HOLD HARMLESS
The Grantee agrees to indemnify and hold harmless King County as provided herein to the
maximum extent possible under law. Accordingly, the Grantee agrees for itself, its successors, and
assigns to defend, indemnify and hold harmless King County, its appointed and elected officials,
19
03/12/01
E.11
AW 14 Q 5 6
and employees from and against liability for all claims, demands, suits, and judgments, including
costs of defense thereof, for injury to persons, death, or property damage which is caused by, arises
out of, or is incidental to Grantee's exercise of rights and privileges granted by this franchise. The
Grantee's obligations under this section shall include:
a) Indemnification for such claims whether or not they arise from the sole negligence
of the Grantee, the concurrent negligence of both parties, or the negligence of one or
more third parties.
b) The duty to promptly accept tender of defense and provide defense to the County at
the Grantee's own expense.
c) Indemnification of claims made by the Grantee's own employees or agents.
d) Waiver of the Grantee's immunity under the industrial insurance provisions of Title
51 RCW, which waiver has been mutually negotiated by the parties.
In the event it is necessary for the County to incur attorney's fees, legal expenses, or other costs to
enforce the provisions of this section, all such fees, expenses and costs shall be recoverable from
the Grantee.
In the event it is determined that RCW 4.24.115 applies to this franchise agreement, the Grantee
agrees to defend, hold harmless and indemnify King County to the maximum extent permitted
thereunder, and specifically for its negligence concurrent with that of King County to the full extent
of Grantee's negligence. Grantee agrees to defend, indemnify and hold harmless the County for
claims by Grantee's employees and agrees to waiver of its immunity under Title 51 RCW, which
waiver has been mutually negotiated by the parties.
King County shall give the Grantee timely written notice of the making of any claim or of the
commencement of any such action, suit, or other proceeding covered by the indemnity in this
section. In the event any such claim arises, the County or any other indemnified party shall tender
the defense thereof to the Grantee and the Grantee shall have the duty to defend, settle, or
compromise any claims arising hereunder and the County shall cooperate fully therein.
Notwithstanding the above, the County shall have no obligation to tender a defense as a condition
of the indemnity where there is a material conflict between the interests of the Grantee and King
County.
9. VACATION
If at any time King County vacates any County road rights-of-way covered by this franchise, King
County will not be held liable for any damages or loss to the Grantee by reason of such vacation.
King County may, after giving thirty (30) days written notice to the Grantee, terminate this
franchise with respect to any County road rights-of-way vacated.
20
03/12/01
E.11
r
4 0 6
10. REPAIR, REMOVAL OR RELOCATION
The Grantee hereby covenants, at its own expense, to repair, remove, or relocate existing facilities
including all appurtenant facilities and service lines connecting its system to users, within King
County road rights-of-way if such repair, removal, or relocation is required by King County for any
County road purpose. Such repair, removal, or relocation shall not be unreasonably required.
The grantee shall, at no expense to the County, adjust, remove or relocate existing facilities within
County road rights-of-way, including all appurtenant facilities and service lines connecting its
system to users, if the County determines such adjustment, removal or relocation is reasonably
necessary to allow for an improvement or alteration planned by the County in such road right-of-
way. The County shall give the Grantee written notice of such requirement as soon as practicable,
at the beginning of the pre-design stage for projects that are part of the County's capital
improvement program, including such available information as is reasonably necessary for the
Grantee to plan for such adjustment,removal or relocation.
For projects that are a part of the County's capital improvement program, in addition to any other
notice given to the Grantee, the County shall provide a vertical and horizontal profile of the
roadway and drainage facilities within it, both existing and as proposed by the County, and the
proposed construction schedule; notwithstanding any permit conditions that may later be applied to
the County project, this initial design information shall be given at least 180 days before
construction is scheduled to begin, except in cases of urgent construction or emergencies. The
Grantee shall respond to this notice, and to any later notices of revised designs based on permit
conditions, within no more than thirty (30) days by providing to the County the best available
information as to the location of all of the Grantee's facilities, including all appurtenant facilities
and service lines connecting its system to users and all facilities that it has abandoned, within the
area proposed for the public works project.
The County shall offer the Grantee the opportunity to participate in the preparation of bid
documents for the selection of a contractor to perform the public works project as well as all
required adjustments, removals or relocations of the Grantee's facilities. Such bid documents shall
provide for an appropriate cost allocation between the parties. The County shall have sole authority
to choose the contractor to perform such work. The Grantee and the County may negotiate an
agreement for the Grantee to pay the County for its allocation of costs, but neither party shall be
bound to enter into such an agreement. Under such an agreement, in addition to the Grantee's
allocation of contractor costs, the Grantee shall reimburse the County for cost, such as for
inspections or soils testing, related to the Grantee's work and reasonably incurred by the County in
the administration of such joint construction contracts. Such costs shall be calculated as the direct
salary cost of the time of County professional and technical personnel spent productively engaged
in such work, plus overhead costs at the standard rate charged by the County on other similar
projects, including joint projects with other County agencies.
11. REQUIREMENT OF CONSTRUCTION PERMITS
21
03/12/01
E.11
err
400,016
The Grantee, its successors or assigns, has the right, privilege, and authority to enter the County
road rights-of-way for the purpose of operating, maintaining, repairing or construction its
transmission and service lines and appurtenances on the condition that it obtains permits approved
by the Director and Property Services Division and, when applicable, by the Department of
Development and Environmental Services. Applications for work permits shall be presented to the
Property Services Division which may require copies of plans, blueprints, cross-sections, or further
detailing of work to be done. In the event of an emergency, the Grantee may immediately
commence the necessary work and shall apply the next business day for the work permit. Any
work done, whether by Grantee, its contractors, or third parties will include necessary paving,
patching, grading and any other reasonably necessary repair or restoration to the County road rights-
of-way. All work shall be done to the satisfaction of the Director.
All equipment, lines and appurtenances which are used in the operation, maintenance, repair or
construction of the Grantee's service and which are located within the County road rights-of-way
shall be considered to be part of the Grantee's system and shall be the responsibility of the Grantee.
All permits for the operation,maintenance,repair or construction of said system shall be applied for
and given in the name of the Grantee, who will be responsible for all work done under the permit.
The Grantee remains responsible whether the work is done by the Grantee, its contractors, or by
third parties.
The Grantee shall, at no expense to the County, assume the following obligations with respect to
the facilities connected to its system that are within County road rights-of-way and which it does
not own, including appurtenant facilities and service lines connecting its system to users:
a) The Grantee shall apply for, upon request and on behalf of the owner of the
facilities, a County right-of-way construction permit for any repairs required for
such facilities; provided such owner agrees to reimburse the Grantee for all costs
incurred by the Grantee and any other reasonable conditions the Grantee requires as
a precondition to applying for the permit. All work to be performed in the County
right-of-way shall comply with all conditions of the County permit and all
applicable County requirements. The Grantee may at its option perform any part of
the repair with its own forces or require the owner to employ a contractor for that
purpose,provided such contractor is approved by the County;
b) In the event that the County determines emergency repair of such facilities is
necessary to halt or prevent significant damage to County road rights-of-way or
significant threats to the health, safety and welfare of parties other than the owner or
the occupants of the building served by such facilities,the Grantee shall take prompt
remedial action to correct the emergency to the County's approval, which the County
shall not unreasonably withhold;
c) When the County or its contractor provides notice to the Grantee, pursuant to RCW
19.122, of its intent to excavate within County road rights-of-way, the Grantee shall
22
03/12/01
E.11
T 4 0 "" 6
provide to the County or its contractor the best information available from the
Grantee's records or, where reasonable, from the use of locating equipment as to the
location of such facilities, including surface markings where these would reasonably
be of use in the excavation. If the Grantee fails to make good faith efforts to provide
the above information within the deadlines provided by RCW 19.122, the Grantee
shall hold the County harmless for all reasonable costs that result from damage to
such facilities if such damage occurs as a result of the failure to provide such
information. Nothing in this subsection is intended or shall be construed to create
any rights in any third party or to form the basis for any obligation or liability on the
part of the County or the Grantee toward any third party, nor is anything in this
subsection intended to be construed to alter the rights and responsibilities of the
parties under RCW 19.122, as amended.
12. RESTORATION OF COUNTY ROAD RIGHTS-OF-WAY
After work on, under or adjacent to County road rights-of-way, the Grantee is responsible for and
will leave all County road rights-of-way in as good a condition as they were in before any work was
done. In the event that the Grantee, its contractors, or third parties working under permit should fail
to restore County road rights-of-way to the satisfaction of the Director, King County may make
such repairs or restorations as are necessary to return the County road rights-of-way to its pre-work
condition. Upon presentation of an itemized bill for repairs or restorations, including the costs of
labor and equipment, the Grantee will pay the bill within thirty (30) days. If suit is brought upon
the Grantee's failure to pay for repair and restoration, and if judgment in such a suit is entered in
favor of King County, then the Grantee shall pay all of the actual costs, including interest from the
date the bill was presented,disbursements, and attorney's fees and litigation related costs incurred.
13. PERFORMANCE OF WORK
The Grantee covenants that in consideration for the rights and privileges granted by this franchise,
all work performed by the Grantee on County road rights-of-way shall conform to all County
requirements including, but not limited to, the requirements of the current edition of the County
Road Standards in force when the work is performed and all traffic control shall also conform to the
current edition of the Manual of Uniform Traffic Control Devices in force when the work is
performed.
14. BLASTING REQUIREMENTS
The right to operate, maintain, repair and construct Grantee's distribution and service lines and
appurtenances granted by this franchise does not preclude King County, its agents or contractors
from blasting, grading, or doing other road work to the Grantee's lines and appurtenances. Except
in the case of an emergency, the Grantee will be given ten (10) business days written notice of any
blasting so that the Grantee may protect its lines and appurtenances. If the Grantee notifies the
County within ten (10) business days that the facilities will have to be relocated to protect them
from blasting, the County will defer the blasting for up to ninety (90) days from the date of the
23
03/12/01
E.11
WOW 4 0 a
Pw
6
original notice. In no event will the Grantee be given less than two (2) business days written notice
of any blasting. Notification of any excavation shall be provided through the One-Call System as
provided by RC W 19.122, as hereinafter amended.
15. SURVEY MARKERS AND MONUMENTS
It shall be the responsibility of the Grantee performing any construction work in the County road
rights-of-way to restore any survey markers or monuments disturbed by such construction in
accordance with RCW 58.09.130, and as hereinafter amended.
16. ASSIGNMENT
The Grantee shall not have the right to assign this franchise without the consent of the Metropolitan
King County Council given by Ordinance. No assignment shall be effective unless an acceptance
by the assignee of all rights, conditions, terms, provisions, and responsibilities contained within the
franchise, as well as surety bonds which the Council deems necessary to be posted are received.
Council approval of the assignment may be made subject to the assignee's acceptance of new or
modified terms of the franchise.
17. EXPIRATION AND RENEWAL
To the extent described in Exhibit "A", all rights granted by this franchise to County road rights-of-
way outside incorporated Towns and Cities apply to all existing County road rights-of-Way
improved and unimproved and to all County road rights-of-way acquired by King County during
the term of this franchise.
If the Grantee has initiated a renewal of this franchise before it expires, the County may, at its sole
discretion, extend the term of the franchise on a month to month basis for up to one year. Should
the County elect to extend the franchise, written notice shall be provided to the Grantee before the
franchise expiration date.
If the Grantee has not applied for a renewal of this franchise before it expires, King County has the
right to remove or relocate any lines and appurtenances of the Grantee as is reasonably necessary
for the public's health, welfare, safety, or convenience including, but not limited to, the safe
operation of County roads, franchise holders, or for the construction, renewing, altering, or
improving of any County road right-of-way, or for the installation of lines and/or facilities of other
franchise holders. Grantee shall be liable for the costs incurred in any removal or relocation of its
lines and appurtenances under this section. Costs include the expense of labor and equipment.
Upon expiration of this franchise, the Grantee shall continue to be responsible for the operation and
maintenance of existing facilities in the County road rights-of-way until removed, assigned to
another franchised utility or abandoned; however, the Grantee shall not have the right to provide
additional services or construct new facilities. King County will issue permits required for the
repair and maintenance of the existing facilities in accordance with K.C.C. 14.44.055 as amended
24
03/12/01
E.11
44056
and Section 11 of this franchise. This section and sections 8, 10-13 and 15 of this franchise shall
continue in force until such time as the lines are removed from County road rights-of-way, assigned
to another franchised utility, or abandoned in place with the approval of the Manager of the
Department of Transportation, Road Services Division.
18. RESERVATION OF RIGHTS
King County specifically reserves for itself the right to impose a utility tax on the Grantee if such
taxing authority is granted by State of Washington and the local option is exercised by the King
County Council.
King County also specifically reserves the right to exercise authority it has or may acquire in the
future to secure and receive fair market compensation for the use of its property, pursuant to an
ordinance. If King County elects to exercise such authority, the fair market compensation
requirement for Grantee shall be imposed by ordinance not less than one hundred eighty(180) days
after written notice("Compensation Notice") is delivered to the Grantee, said Compensation Notice
identifying with specificity the definition, terms and/or formula to be used in determining such fair
market compensation. Acceptance of King County's definition terms and/or formula identified in
the Compensation Notice will occur if the Grantee accepts in writing within thirty (30) days of
receipt of the Compensation Notice; or, if Grantee takes no action in writing within thirty (30) days
of receipt of the Compensation Notice; in which case the applicable ordinance that the King County
Council passes will be determinative.
Nothing in this section shall be construed as an agreement by the Grantee of King County's right to
exercise authority it has or may acquire in the future to secure and receive fair market compensation
for the use of property. Nothing in this section shall be construed to prohibit the Grantee from
challenging, in King County Superior Court or a court of competent jurisdiction,the legality of such
right.
Grantee's rejection of the definition, terms, and/or formula identified in the Compensation Notice
will only occur if such rejection is in written form, identifying with specificity the grounds for such
rejection, and delivered to King County within thirty (30) days after receipt of the Compensation
Notice, in which case the below identified arbitration terms will apply:
a) The Grantee and King County will select one arbitrator each, and the two selected
arbitrators will select a third arbitrator. If the two arbitrators have not selected a
third arbitrator within thirty (30) days after the selection of the last selection of the
two, either the Grantee or King County may apply to the presiding judge of the King
County Superior Court for the appointment of a third arbitrator. The three
arbitrators will determine the method for determining the fair market compensation
for the County property used by the Grantee. The arbitration procedure employed
shall be consistent with the rules and procedures of the American Arbitration
Association. The decision of a majority of the arbitrators will bind both the Grantee
and King County. At the conclusion of the arbitration, the arbitrators will submit
25
03/12/01
E.11
J 4
des
6 4
written reports to the Grantee and King County which shall contain all pertinent
evidence that led to their conclusion together with an explanation of their reasoning
for such conclusion.
b) The fees of the arbitrators selected by each party shall be paid by that party, and the
fees of the third arbitrator shall be paid one-half by the County and the Grantee. The
other costs of the proceeding shall be shared equally by the County and the Grantee.
c) In event that the question of,fair market compensation is not resolved prior to the
effective date specified by the ordinance authorizing said compensation, the
arbitration decision will be applied retroactively to the effective date in the
ordinance. The Grantee will pay the retroactive sum plus interest in the amount of
twelve percent(12%)per annum.
Nothing in this franchise may be construed to limit the exercise of authority now or later possessed
by the County or any other governing body having competent jurisdiction to fix just,reasonable and
compensatory rates or other requirements for services under this franchise. Nothing in this section
shall be construed to prohibit the Grantee from challenging, in King County Superior Court or a
court of competent jurisdiction, the authority of the County or any other governing body to fix rates
or other requirements for services.
19. COMPLIANCE WITH LAWS
Grantee shall conform to all applicable federal, state and local laws and regulations including, but
not limited to, the State Environmental Policy Act and King County environmental standards and
ordinances.
20. NON-DISCRIMINATION CLAUSE
In all hiring or employment made possible or resulting from this franchise agreement, there shall be
no discrimination against any employee or applicant for employment because of sex, sexual
orientation, age, race, color, creed, national origin, marital status or the presence of any sensory,
mental, or physical handicap, unless based upon a bona fide occupational qualification, and this
requirement shall apply to but not be limited to the following: employment, advertising, lay-off or
termination, rates of pay or other forms of compensation, and selection for training, including ap-
prenticeship.
No person shall be denied, or subjected to discrimination in receipt of the benefit of any services or
activities made possible by or resulting from this agreement on the grounds of sex, sexual
orientation, race, color, creed, national origin, age except minimum age and retirement provisions,
marital status, or the presence of any sensory, mental or physical handicap.
Any violation of this provision shall be considered a violation of a material provision of this
agreement and shall be grounds for cancellation, termination or suspension in whole or in part, of
26
03/12/01
E.11
4056
the agreement by the County and may result in ineligibility for further County agreements.
The Grantee shall make the best efforts to make opportunities for employment and/or contracting
services available to women and minority persons. The Grantee recognizes that King County has a
policy of promoting affirmative action, equal opportunity and has resources available to assist
Grantee in these efforts.
21. PENALTY FOR VIOLATION OF CONDITIONS
If the Grantee shall violate or fail to comply with any of the material terms, conditions, or
responsibilities of this franchise through neglect or failure to obey or comply with any notice given
the Grantee under the provisions of this franchise or if the Grantee abandons its franchise, the
Council may revoke this franchise. King County shall give written notice of its intent to revoke this
franchise. A public hearing shall be scheduled within forty-five (45) days following the
notification. The decision to revoke this franchise will become effective ninety(90) days following
the public hearing if the County,by ordinance, finds:
A. That the Grantee has not substantially cured the violation or failure to comply which
was the basis of the notice; or
B. that the violation or failure to comply which was the basis of the notice is incapable
of cure; or
C. that the Grantee has repeatedly violated or failed to comply with any of the material
terms, conditions, or responsibilities of the franchise, even though the individual
violations have been cured; and
D. that the revocation of the franchise is in the public interest.
During the forty-five (45) days following the notification, the Grantee shall have the opportunity to
remedy the failure to comply.
22. RIGHT OF APPEAL
Decisions, requirements, or approvals of the Director are binding on the parties to this document.
Appeals from the Director's determinations will be made by filing a complaint with the King
County Superior Court.
23. SEVERANCE
This franchise gives effect to purposes and uses which are consistent with economical and efficient
services rendered in the public interest. If any provision of this franchise, or its application is
determined to be invalid by a court of law, then the remaining provisions of this franchise shall
continue and remain valid unless the dominant purpose of the franchise would be prevented or the
27
03/12/01
E.11
Moe
4 0
public interest is no longer served.
Revised 07/25/96
28
03/12/01
E.11
1111 r
gym. i. t
a.
NJ MENOil-
Room
RMMEN
MISM
WME
Egli!/L rte MINOR
N-MOR MW
SII w Il'l:R l
C /1
ilii
1 11 ill
a
1 • i 1
E.11
nieiA C
S
W
Q W u
C:
ctf
r--
SF9S
z
tea•"'.. ,' .`,'•. _ '':c_gx+-a,_.- '€,'m;:::.,.a.' 7?u x., •-,
r, uk 'k`
Y,= :n``• '?.''.4:,:,,•'-c.>:
o'iCx.. :k x. -{
a_.' SY' _, z>._;.
Ex +'
c'}'i-• _•• "•1,$xY'`f T..iS+}•-'S !r'+:`ems' re '`G L'fT."r.x.-
y'y 'ad, Ty
4t
z•
y_4 5,. :'m:-= '' s.F_" - 3,• .:.[_
1?
s:, •kms:J-r-'-.•4• •...
ate,.
Ss :x. -.- ,y-•
4.>" w,
r. :
xa.-'
4. _ -.St`.r .5i.'x-:."'-s;iv.-.?" >. _,r•ars. ..•..
3y.•;
rTT_,; •'.zC-.6-:{L -.• ,.;r_ =-ni''!'t'> >D %'`"..'., -:.`;` <h ..t fir_- _ -E`-Y'k^ ". ..
s '
sem • v.x,`' t
5`__2„ -`i'c,<''a' it:r:.atw.;._ '. y:.•< i`. • ,.,.•ti s'3s=5a.. t;. L
r-•`nom• '•',`-'-. s+,.-_.r`
x o 5:,,A4
i
gym+ ' 5'-'t .. '".' _', '£'•a'. 1•„ `,' "y c
Malls_
ss^"_.:.F:e` >• ;e- "5:>. :r'&." : ..`£_s.'•.-;. . ''•, . .'%•'-
3 'fit_<s'..
u: :.c:: rt
t..r _•"" '-:.ra4`et .
y...'3, L'k i-' FZ-`i.'n x•`35.°'>t: `_:`
x. -'bV-:' :.tea .. T^ti"- '
a:4•.
E 10 nc
d
2d
r-
L-Li tr
0 300 600
I" = 600' FIGURE 3
S O CITY LIMITS
URBAN GROWTH BOUNDARY
PROPOSED
CITY OF RENTON
o z}Y FRANCHISE AREA 'a• SANITARY SEWER FRANCHIS]
E.11
ILI
son INNER I
pe/1 ia
I I c-a /.w ' I1 r /VIII+
fill
MCI
RSA cis 1! r
F
mall rte , 1 •i
low
oil I
i ,_ Flo
t!
s
Gas u O __
E.11
11
to tO 71,.. n,
Jf '
e.. _r'
1i11 uru. r nq ttox nsua[it f6u,to+w-FCS-
9i.71'.y .Al rtiPIO
i"_ _m '" :sunu l/\u9rron,m it e_-
rI Cillfhu
rsr.6 fl,,:Irri r`1iti- •/.I':
1L:: a•O.,,lq'.tII eri``.,-•
nup+4:p:'.p0•.'iii?A.l.v e.W A,=,,din iL ..rt€aruu .•.,:: .r• ..A•i N n76Jn e Cdw•..:-'.!19119!1 ilr:,r-i0es!u tr e r. tl- ii tll. u_ry.:.`:u:re•,+G .1• rL I ear..
i':,/n! f,l.,._::nun ,i'.=`'11'u '• t1,r_r:ti:/t iiu:,r_..O•i-
lI ter 1/Fi.w/
o :0\O•••w D• .•
u !1 \Ii%/i i:.3;Y.,.' j `
j` 1F..,
u.;i•1
Ilflir 7i '.b uul.':'-."'
t.ar,.. •......•- _.,..r.
t/11 moi.+lG ll lH r '11t11A u.u.uueur,u..o. 1 i:111 ii l rO rii j
5. '` f r icy
0 Nj tea'=7+ -F at..V,ra:.:,n:+-- ,.®sem"', 1
0+`in: I4:u uo i+-• ':+:7•,t•IIC...ki,.,-Ij ,
ING
All
t `
O, •
u,,
r• !1111111 ®•.!'
LG_,IFl1',1..,I I.A,,', l'., ,",
uu un,wauu,•
nn.IIID°i.\is [su W=L ®®111°:ill!!- ilk r' .
a,'.m e1 IR OIu• nn a e9ui1,
1 o , I ;11,:.,,,.rrr,,:ur::,„7 p1t” .. r r...rO-1 1 7
II It1 111'll•'-'..."=''a qc:slzr:n4^rcJ•-silfi ®.sr. rC'. ,
t+( iu'1 !nm r .ems Its'arel_C!•
AIG•1'111'1 N``•'% Ips Ilt Ittle6l®It®-11.a
f:"•' \ilt3•/u0 IL®_®® a_ IIIIIII. 1f/,-
e',•:,
tii%.c s ,'!'-i111)'su1lV IlttiCs'ofGllq It11
u,..w„a 'd;5 rr not+ s„ea
1.
t
j - `-
1 i moi 'al an
e.r iii..
rn'il_i 1!f E I s>
F_
I 11
e:If ,-a.lv_ r, ate: •t =
e."r' c ,
Iql!
S_ :11 I1 1 1 1'i 1 nr • i:
11111'111 7 11 !®rr} ' ®® JM—ilLt'1:•:' `'1 ' ' -
e>• lehtcn::
o•' #
yann':r®'1'lil E 4 te uu® IIIIto,hum,:
un
i 11
1 ]'j=
unuu ro ,.• 6u 111;'.i•-,mtae 1 Its a•err.. ;i3?®rarf<v®:® 11111111/1110®a, t®
r -`
1 a
IIE,
qc u,ur p,
d=-e.t0 plsn 1® S r•r Fi[1.9C'J111111,11„
a nrO.•C P alii e.lof•mlu•.7t`'i p C IRIIII a re.:,.
t t,\.•>;.b:A'afe %%/blsL ase z9ts.:1 c•.te111j` p- -- 1 is 11111/11 rrr
u...e,•.,,...m i:C a uu[:: 1l uus ,t
Itll i11a ails...X111111 111sll s :®'I c'i,.p.tr` aei. : E?iE3L4l-.O®®__ 'uuu®s{'.i1111 Iqq-,Illl`i@'f v111i31:
i ptt"..1'p • if® so\III.\IIIIII.° .CGtttpb+it, t' a s , h trna9.1 e ®1®i®11111 L1
w
R:+,uiP a e - a BI®, e3E714 s ar s 11e_ it% 1
nuut/'p.p+t't,. = a HIY. IC 9!i r-^....r"' 0 11]I)P 1= ennao.estttwen s
u-::`.`.:'•"o..at'' : nn:e.•nua lan P s®PIt::7, ,s. ®!111:
pat 11 1 EIn.'le o1•,ta!,xe,a
1 netafl iN 1! u ria
e.•.;.a.fltalUtl IRS -111111® n i,
G .IIII filoOle.,._. .- •`
L•••r, y ®. 1s IIIf1 r ®!D iltd=1. it G``-.n\_-::i a E. , fad.
p'
oii
nletlillli,.,y a 9•leal.:rnu aa .af,t3,v,lC. 1:_uanea••_a.e
r..aa
rig* '•. 0io:•.• uluu 7_ ,.Asn yli p` su s®®I _ +•
r•®. t e u®®wr;'•. a U ` Oily C ri _-°'ems s e en e'-. 1.,lr:'''t
a®e tuv .r
s i s Tres s.r
ttpQAi e 1 re y pq.v::::e._..!,•..I Itek'k .e/o eessa eee,r:In C si-a' ®113ft:E31G,-toss
ti,•t J OI.1111 Ib_!tY:\. t: -•. AI ( !.®rr0[Na•: 1I/,-io sI , •4j s C mi d•1/uM...1 1"i+a[u_Irlrt[e ue al If " t' .., e1 1111, 1
9 N "s. sue 111rr 11_11 as:«:e_I_I-.a i o{: ti j' _t11 _uu-.-Illi]1 p q e.•r uur+ s1 OSI a
p s..11(11 '! O r4:aR- ..
s siaa i r, .
v,•mrp
1/tturyyl ve ®l s ^ a 11u n 7 s o;• t1 y lIIOF1/\ c,,
gt /'raE.L,r1 r; i1
41s,o' i u. 9:rE>•E ::;iE 1 iYir i•aa
a::% O.•.ai P' _a'ra e ilue_tt:.n ICS p v ... 1' IIlI 11'o% lt , 1 i1.... .;.1111 :.
dj 4di'a<Ai'i. f l//It/11 sem•: 1/a 1 / i aa1 1 per!
tri t.
r Ii\moi•Iq. i1/I/1u®
A... ! i(Iiiillii ii 1' ii: jpt l/
1r\.:i•i:::•':1 O/611•
nnmu•t1S tt\.w u'w nnm. nnnAliti!3i311111;UI, Biu iv le- •••
1 1 11
11
1
r r • i
E.11
1•+ rte-
MORM
m = LiY i
C. D0 x71111111 .`
VON
I
no
low
i a 'r SAG I r lYllili,a i
rr ' I Fir
J 1 ,/' ;11 I ''1111
ter ..— . I i O 11
r x r r. Iii rt 1 w 1 tn 1 C•
1-. ul: ,v r4 ll ii arL'1 W A O`=
moi rr 1•
tl/111111 orb D a1
111/11/111 1111111111graor..
t,,,riiiii 1,,p; IHnIT11yO11 IIIIIII 1 "'
11111/11 111111111/ ../ . .... .
11111:311 R -1.1111
E5111un111Ir.11wnrrtr11Ii1rl'PILJla ki1C 111111 C 111
1... r.F' LOU goo x•11111111 N=1111111_ .C•at tc >ra /:,.(uDIl1/ 11-/111111111 ..r
11111115W mx j r
11/1 m r r iii
1 1 I r// e e a>
r
ei W u+u a 1111 'r rl/IIIi
1 ,
WINN
ISM
SII t i
X11on
MEN1 /
tl%err ir`1 0 Mrlll`
y 'll//` ,&°v t i wi N n.+ M r rr r
r r.
G' J1/ , /
Cr iii rr rr
wry w ii
gi
I'
I'a il.-
r,/ ill [i7 n rr r
r rr rr rel
au a w . rr rr
1 p'1 i aim r r
G - ,
ii.A I` + ' 111 l=/err. r..., - . r : :xi A nr/ .IIA 1r7 — it w rr r rr .E I 1R IEyIi'1'r LW '1 tr/1 1 T" X111© IIy RI 1 1 Ir/1w•SII 1--i I r r rrr.r rrrr+r rural 1 1/t 11111111rr'ua'ur.rtlruir. t rrr 11111 111 X11 r r`
@: I r11 1111111/rr11I (.1 w ur
w.. E ' k --.u;rrr 1111/111// 1 v w en u
r
ONS !!.rr.i rr Ili A A i
w
E.11
11,4 ! 1§.:_/
NOW
W-4 q:FZ,4&T4gAj&M4
1 i1 .,s DSI
fall
fn 1
I Iris
t!7/t ;
rte i1/
IFS `v
1 111 i i 1 .
tl 111 i
A i1 1111 p
E.11
it17 !
EMIRloss
t
moi i I r r ,qtr
KAREN
IMM
07sip.
i tai : 1 1
IMP 11MI/\
0IIIN
t111 •.ilii ..
Oft
OWL
r ter* I! - 1
son
it iiia + : .. •..
r. !' Hill i< 11. `III1In , y ._
1111 i 1-
iin ir'
1 ' 11111111111 .. 1•••S
21
USE
r
111
E.11
1li.1
ti Ilii/ + " '
c-I i f I iii
a
11 '
r% t
j(f,t7 ( .,
i
a
e.w1
4
J, -.
11
t
1 . 1
E.11
W
O
j Z7
E -SE th
S 55th St
co
0
o
l g th p,
a;
CCl
9
E 0 t StS
0300 60i =i!
0 14
1" = 600' FIGURE 10
t CITY UMITS
URBAN GROWTH BOUNDARY
PROPOSED
CITY OF RENTON
FRANCHISE AREA .I. SANITARY SEWER FRANCHISE
E.11
0
S 55th St
Y h S
f
li Y
J
i
l
F Kr }
x t Fzs i
3 -
4
I
O
v
IgthP/
9
0
S
ijI L_
n
0 300 600
in =
600,
FIGURE i I
y CITY UMITS
PROPOSED
t . URBAN GROW-M BOUNDARY CITY OF RENTON
FRANCHISE AREA SANITARY SEWER FRANCHISE
April 7, 2000
E.11
trrr wrr+"
i
0
1g th p
0 1
0 150 300
1" = 300' 405f; FIGURE 12
CITY LIMITS
PROPOSED— — — — —
URBAN cRownl BOUNDARY
CITY OF RENTON
FRANCHISE AREA 'K' SANITARY SEWER FRANCHISE
April 7, 2000
E.11
46* 4'
PROPOSED ORDINANCE 2001 -0021
ATTACHMENT M
FIGURE 1
PROPOSED CITY OF RENTON
SANITARY SEWER FRANCHISE
APRIL 7, 2000
A TTA CHMENT(S) A VAILA BLE IN CLERK'S
MASTER FILES
E.11
CAG09-014
CITY OF RENTON & CEDAR RIVER WATER AND SEWER DISTRICT
FOR THE ESTABLISHMENT OF SERVICE BOUNDARIES
THIS AGREEMENT is entered into this Stn day of February
19 99, by and between CEDAR RIVER WATER AND SEWER DISTRICT, a
Washington municipal corporation, hereinafter referred to as "CRWSD", and the CITY
OF RENTON, a Washington municipal corporation, hereinafter referred to as
RENTON".
WITNESSETH:
WHEREAS, CRWSD is qualified to provide water and sewer service within its
prescribed area; and
WHEREAS, RENTON is qualified to provide public services, including water and
sewer service, within its prescribed areas; and
WHERE, it is in the public interest for the parties herein to enter into an
agreement to provide for the efficient planning and development of new water and
sewer services in areas which may be served by either, or both, of the parties herein;
now, therefore,
IT IS HEREBY AGREED by and between the parties hereto as follows:
1. Water Service Area Boundary Between RENTON and CRWSD. The attached
Figure "A" illustrates the line separating the RENTON water service area from
CRWSD water service area. RENTON shall provide service for the area
generally North and West of the line illustrated. CRWSD shall provide service for
the area generally South and East of the line illustrated.
Any new construction, upgrading, or replacements within the RENTON City
Limits by CRWSD for water service shall be in compliance with RENTON design
and construction standards then in effect or CRWSD design and construction
standards, whichever are the higher design and construction standards
including: materials, techniques, and fire flow.
2. Sewer Service Area Boundary Between RENTON and CRWSD. The attached
Figure "B" illustrates the line separating the RENTON sewer service area from
CRWSD sewer service area. RENTON shall provide service for the area
generally North and West of the line illustrated. CRWSD shall provide service for
the area generally South and East of the line illustrated.
Any new construction, upgrading, or replacements within the RENTON City
Limits by CRWSD for sewer service shall be in compliance with RENTON design
and constructions standards then in effect, or CRWSD design and construction
standards, whichever are the higher design and construction standards
including: materials and techniques.
E.12
3. Maintenance of Existing Facilities: CRWSD and RENTON will each maintain
their own facilities, according to industry standards.
4. DISTRICT Comprehensive Water and Sewer Planning. CRWSD will submit, to
RENTON, all future Comprehensive Water and Sewerage Plans and
amendments thereto involving area and/or improvements within RENTON City
Limits. Said submission of the CRWSD Plan(s) is to assure consistency with
adopted city plans, policies, and land use controls, assist in the review of new
development proposals and right-of-way construction permits, and to fulfill the
responsibilities set forth in RCW 57 and King County Title 13. As new facilities
are planned, constructed, maintained, and/or replaced within RENTON, they
shall comply with RENTON design and construction standards then in effect, or
CRWSD design and construction standards, whichever are the higher design
and construction standards.
5. Extension of Utilities Across Properties. RENTON and CRWSD agree that they
will require property owners who must extend facilities to service their property in
a comprehensive fashion up to and including extending said facilities to the far
side of the property, when appropriate, to provide a connection point for the
future (or existing) facilities of the next property.
6. Franchise Agreement. Upon RENTON annexing property within the CRWSD
service area, RENTON shall grant CRWSD, for the purposes of continuing use
of rights-of-way, a temporary franchise for utility facilities within the annexed
territory. This franchise shall have the same provisions as stated in the franchise
between King County and CRWSD and have a term not to exceed 3 (three)
years.
RENTON and CRWSD will immediately begin negotiations for a new franchise
for the purposes of rights-of-way use for CRWSD service area within RENTON.
The new franchise shall be negotiated within three years.
Upon any subsequent annexations by RENTON within the CRWSD service area,
RENTON shall amend the franchise to include the annexed area, in order to
maintain one franchise agreement. The franchise shall maintain the remaining
balance of the term of the franchise. The franchise should include any updated
provisions as approved by RENTON and agreed to by CRWSD.
Any franchise agreement issued hereunder shall be consistent with the
respective comprehensive plans of the parties and State law.
7. Governmental Approvals. The parties will give notice of the adoption of this
Agreement to Metropolitan King County, to the Department of Ecology, to the
Department of Health, and to any other agency with jurisdiction, and shall
cooperate and assist in any reasonable manner in procuring any necessary
approvals hereof by those agencies.
E.12
8. Sanctity of Agreement. This Agreement constitutes the entire agreement of the
parties, concerning the subject matter herein, and there are no representations
or oral agreements other than those listed herein, which vary the terms of this
Agreement. Future agreements may occur between the parties to identify, agree
upon, or transfer service areas and/or facilities. This Agreement shall have a
term of 25 (twenty-five) years.
9. Obligations Intact. Nothing herein shall be construed to alter the rights,
responsibilities, liabilities, or obligations of either CRWSD or RENTON regarding
provisions of water or sewer services to the properties described herein, or other
properties, except as specifically set forth herein.
DATED this 8th day of February 1999 .
Authorized by Resolution No. P571 of the City Council of the City of Renton,
Washington, at its regular meeting held on 8th day of February
199 9.
OF RENTON
sse Tanner, Mayor Date/
TTEST:
w
Marilyn J. et rs n, City Clerk Dat
APPROVE TO LE M.
Lawrence J. Warren, City"Attorney
Approved by Resolution No. 3740 / of the Board of Commissioners of
CEDAR RIVER WATER AND SEWER DISTRICT of King County, Washington,
adopted at its regular meeting held on 19th day of January 1999 .
CEDAR RIVER WATER AND SEWER DISTRICT
By:
Title:
E.12
t LU
ul t
It 1
CO M
LL
aw
PRO
PIN
t
j
r,
0 /s f
WEER
iiiiiiif%%
I il J/ j I1 i,'o ' '// /.
ii/iii'
or
Ri/101.0zzM4
I C///.//'•
AW,1/I '0 f
Ai
1 iiiiiiii6 s
r II/1 J/JJ/
PRIME
1y
11111111111 ASS/` j /////• / ! VIII 1 II O`% j i%%'' e.:•.:i!
11111111.!'`1011 j J
I/ J/
I i
AM 1 l11
11111111
11 t
r ;;
4 I
a1 11111 1j iL/1F i jr
1 i 1/ 74OFFER jr
r/
rp /
004.
tl.11tn111..t1f
I_W110000
7 1• r s.,ALI,I I Ilen.r.o,f
I•„%5d7 7Ei./.}i%•1/• iP.L••1,
3srj?.r%
i tnuunty/i-I v I 115 p.nair/.! /. fol sr ..C a.
II.l I i,
st1..lei •sJ1_s11!N.i•d/i j!I.r ..v.:.
J
1
r
i /
l, l/I,.y i!/9 f i/ O'..r 1tr!p•s.I1 •... -n.nM I
L ji.,.' iq.../y L/,Jr.?Li i if!i[/:4 tN gum.
a.. /ZI%;I
I O! /,FF-0 /;y.-.0/'.; Ll /••-•.,.<I..J..p d:/". jtty bIIlti111•I1/ °. OS.•f.il0ir IS"A ii il''iaa.'ili.!%:uu.not •
9, -- II 11.iiIE..rssni/GI.i!Lrf'.',i'i:'li1 L': .In as pn1
IIV Y,j ;il j ar l.liatli/e ...ri,.:' :
umint
t
s:
II l >l,i1 •.%I///'II/ y`•ici h'..1..'I••gi.i.a/.rE Ip/O,;'•'/:a3' %7t a I t nu
111111: r/.1i'G a/ //:"•./%l''%l.a-!ji%I :• ..•g;. :
y
nn=:
IIIIIIIItttnl i, l.Oi+•y i'•/ l// /OiG.v.l"•:1..,%`'/!a..61i.:.''.tti••.'i:.p , i.• ..I:C
r 9sr/ /! // •iS/I.IS/y0ya%i'
I Iy1..'.:'Gl. i i G L •ih -.\.:
nIn11 P I I/E/ //i Y•s'.I:,ri.i ri.9,.1:.,,:IL'. •'.A• 1, w::.i C7V i,iiI'1 I i// i i 1.;•IO I•II. i r%i',• 1
I,, p.- o.nn•inv ..n.r/ /
i°I •115 I/iy 7•s=J••I•f. ,.• _i i did •t C• 1,1 s !• ,••ili rsie.:``re1n.IS/.el'i19!i a i O V t
1O.n.tl- IyI' •s.I'/i.'ilir.nTe/v'IVI•,.''.- t sp • t1::
IIU i.s/i.
SIy
i/?T;rs, ..•.*.i Q . •1 C 1/ I
1y1 Imo.. 1' ..
j J'ifi l0:•• /Ili• ''!%:% II i is iyi:AC,.,'•O
1 1/1I//
j
s//i.J :nu.nn 1 L '1 j •1'.
111111 yt-•.ry nrl//Li77 f .i9y
If_7 Ilii a 'I'.' / Pia 1 r
09 Wl Elmosi fir, ,10' '
r J / 1. Is•
1.. • . .._
iii S ;•`°//7 f ' ',:::1 I I/j•I - - - r - _ = i f
KV
J/ I/Ii"/,/ f VIII"•70-•/ I'I!/i j %j/, ,i 11..... is t , - n C”
ie:;rii/
s; /FI' • i I/I'''O i/. ' 7
11 C I''r! •i r i 1
f' ii 2/00.' j• %.//rte.•1/. 1-_ 1111 01:--_.
u nV I.r!ir r• 1. jID.D'r
I• . l...r/',.r•i./ p y.iri JJ r . O-.QnI1_:I
1 I J// r Ii,••///
d!'S 'i•:r,
J• srt••°
I/ ,\t'Inn//. -
r
i nmO an rtei''. :r;, :... ./:i. I•r'•br'••Oio,• i./` y L 1:U A 4ii •/•°' / .1/.. .. i nrt. ,. , i.ull. 111 1Il/'i i'i/,//•lam/.'.!`.• ry 9'i•.I'''i I/ /r L:O t C ' I n1111111 nAOi.Nr m n-
r.'..-.- .O.i//"ilF./;. •'.../` s: ::'v I. ::1 , unuuumn
Q 1. /.,I: r
I I / •" I!/':•%' /II\ '•.o` •. I'I'C,' l i•i /'i r' .ti' O t. t O I1 7 . 11
l'O'/ 'sue///J% '.. •e/% r /i- / ••
F/ ./
f'ilo i Z' fi•/ /
i/i/jI/. / II r•/• 1 ' + nn 1i Ct1.pry' ,• '•/1/%r O°
I
s i, /
s%if/,il, i.-
11, I t , : :`
t;:I C:.; 11,
s.•L;I .y 1 1_:61111 1,11 :L li II 1-11111116r.SICr:1..::5s a
I' .,
r l 1, • iT
j
I%'/%I•'/
1y0,.."./•
I•/ ../ .:rdr7i:i•.niE r Iin
1
M E ./i
gi /
Lli •
I,
i}i•f//
soona\OI/ .
e/, s, // 111.
t
1,.\./I//
I_/I/!//% j%I /.I%
a,
O.
r/
I
i//,/iII,
f
T
I-;ioI%p
iI.
i:/
l/.%
1l//.
i/:'•
r.•/
r/
I=I1/_
p/
I,/_/
Iz%
p•
i
I,.%ij.j%l%/I/IZ!/Iad
iIi
iii//•J:
L///
r.::
i rQ t,lril t II
u.\m
i.
mr..nu
t
I/,, ,`
nL
n
U IlVIntrlr Int ll.
1I,1n
1
pt!
1
I1nA
1 m tn•I'
L.I i. /d j mar nqp._7
I••i .t.1\1.
II S '.:p
tfi/
l<°./ r f.. U/I G:e//l/r.
151 . 1a1 yyI a , atat/q p.C
i.tt 4'•I'•' . //rr': •/ i'I/ uu tuntTit p vn..war p.:.c q_
I 1 r;Ile I,r 11 Illf— • in11 • :
toice // j .!"/.,ynrer0/0</ i:::;0'i I -.p 11:._-p Ih r X1111 1 1 =. p1 11:::uaa,
1•\E9 i/I%ri/"•.a% 1 .r7i.iOl//i..itc7a7zi7 3Lr/iii 11 7ti•Ii:6•;.olll:•t!'
17S
I_u iu.nnulir'7
1 E.i
1 r. r nu uuuunr
Ilnm.n 1 nmInuui D
V `
1 1— tarn t 1111111111111'1
D: I. p- vim ..
4•.O`"i.a\\\ C. yi• I fin.- irl—i
t 37•.r •y I i.
911
j .'. U n- G nn t n i 1rp•7.,a/•1. I
i;\\\\`` .Siii. p Ci 1 un 11111 111 111 11111 1 .1 IIi•=i ii::i
1
1 \ I n i Opt y/•nnu: 11 w11111
will,g1n11
IIn111111I 1 Q•r/i11P tpNt rin• d0:
1 c\ A.nnnmm.un rtnut•... um
nn: m i.'i'
E.12
OW
Ljj
z cc > .a
co w
LL
LU
w co
J J I/
j i s',
o Ilp'p`'•all
f> I+'. /J"//r Or 9 Ise,0000 v
p: . -! N
Ogg
iri d/i Pr i jO I'I,/
I ///t*°ia's'i,
i f 3B
dd, vo
no
0 q0" ,/I /
I/ 4•. ``',. •ice t
igg
III
of>./ . , /! f >• 1
r`mod/'rrl i
I ./'
I . Yn C,
RN 0.
011
R N o ,++ /1
oll ". /` // i"
moll
IT /
1
j/. L 0-_?C •,•:-4 n n1111 t• r
i Ildl //
i'j/' o'Il1'101/-y/• INS /I'/ I'I g1'u•yna .ra. n r r
Z Zu•Z 1 , nnT uv.i.Y..
C
i/rid'de:
r i:P
1 i l / j I !S u C.:
1111 MINI C 1 '
L ii..S S-
I/ i. E Iti•
I
L' ,1 11 ':
i•: S
3
E.12
CAG-06-170
CITY OF RENTON AND
SKYWAY WATER AND SEWER DISTRICT
FOR THE ESTABLISHMENT OF AGREEMENT FOR CONVEYANCE OF
WASTEWATER
THIS AGREEMENT is entered into this /S'
M
day of
200, by and between SKYWAY WATER AND SEWER DISTRI T, a Washington
municipal corporation, hereinafter referred to as "SWSD", and the CITY OF RENTON, a
Washington municipal corporation, hereinafter referred to as "RENTON".
WITNESSETH:
WHEREAS, SWSD is qualified to provide sanitary sewer service within its
prescribed area; and
WHEREAS, RENTON is qualified to provide public services, including sanitary
sewer service, within its prescribed areas; and
WHEREAS, SWSD provides sanitary sewer service in an area adjacent to and
within a portion of RENTON's corporate boundaries; and
WHEREAS, the SWSD and RENTON have an existing sewer boundary
agreement dated December 31, 2003; and
WHEREAS, it is in the public interest for the parties herein to enter into an
agreement to provide for the efficient planning and development of new sanitary sewer
services in areas which may be served by either, or both, of the parties; now, therefore,
IT IS HEREBY AGREED by and between the parties hereto as follows:
1. SWSD Sewer Service Transferrina Wastewater Into RENTON Sewer Svstem:
The parties agree that, as an alternative to SWSD providing sanitary sewer service
to their customers by constructing stand-alone gravity and / or pumping facilities,
SWSD may connect a portion of their service area, known as the AGREEMENT
SERVICE AREA and shown in exhibit "A", which by reference is incorporated
herein, to RENTON's sanitary sewer facilities.
2. Conditions of SWSD Utilizinq Said Alternative For Sanitarv Sewer Service: In
the event of such alternate connection, and in consideration thereof, SWSD shall
meet the following requirements:
A. SWSD shall collect and pass on RENTON's system development charge
for properties connecting to a wastewater facility that flows into
RENTON's sanitary sewer system.
06/06/2006 Page 1
E.13
B. SWSD shafl include RENTON review, for fand use compliance to Renton
Municipal Code 4-6-040C, of all development within the AGREEMENT
SERVICE AREA, other than one single-family home on an existing lot, as
part of its sewer availability process.
3. Transfer of Service Area Upon Annexation: SWSD agrees that RENTON may
choose, following the completion of annexation of all or part of the AGREEMENT
SERVICE AREA to have a portion of the AGREEMENT SERVICE AREA turned
over to RENTON as its sewer service area. At such time that RENTON notifies
SWSD, in writing, that it intends to assume all or part of the AGREEMENT
SERVICE AREA that has been annexed to RENTON, said written notice,
including legal description and/or exhibit map describing the revised sanitary
sewer service boundary within the AGREEMENT SERVICE AREA, shall be
incorporated into this agreement as an addendum and officially revise the
service boundary between RENTON and SWSD.
4. Timefine for Transfer: Upon written notification of assumption, SWSD shall,
within sixty (60) calendar days, coordinate with RENTON, prepare and mail
notification to the property owners, and transfer the account information and the
sewer main facilities to RENTON.
5. Sewaqe Flows and Down Stream Capacitv: The sewage flows from the
AGREEMENT SERVICE AREA, at build out, is calculated to be 312,742 gallons
per day (GPD) with a peak flow of 1.45 cubic feet per second (cfs). If the flows
from the AGREEMENT SERVICE AREA exceed these estimates, RENTON has
the ability to re-evaluate this agreement and may require additional conditions.
6. Construction and Maintenance of Sanitarv Sewer Facilities: SWSD and
RENTON will each construct and maintain their own facilities, according to
industry standards.
7. Remaininq Obliaations Intact: Nothing herein shall be construed to alter the
rights, responsibilities, liabilities or obligations of either RENTON or SWSD
pursuant to the 2003 Agreement, previously executed by the parties, except as
specifically set forth herein.
8. Miscellaneous: This Agreement constitutes the entire agreement of the parties,
concerning the subject matter herein, and there are no representations or oral
agreements other than those listed herein, which vary the terms of this
Agreement. Future agreements may occur between the parties to identify, agree
upon, or transfer service areas and/or facilities.
9 Term of Aareement: This Agreement shall have a term of 50 (Fifty) years.
10. Obliqations Intact: Nothing herein shall be construed to alter the rights,
responsibilities, liabilities, or obligations of either SWSD or RENTON regarding
provisions of sewer service to the properties described herein, or other
properties, except as specifically set forth herein.
06/06/2006 Page 2
E.13
DATED this S day of 200.
Authorized by Resolution No. 38 7 of the City Council of the City of Renton,
Washington, at its regular meeting held on loth day of Julv
2006 .
CITY OF RENTON
1 -l q/r P/aoa
Kathy K olker, Mayor Date
ATTEST:
4
i
Bonnie I. Walton, City Clerk Date
APP ED A AL FORM:
G w,n?•H t t/
Lawrence J. Wa n, City Attorney
Approved by Resolution No. D(- O,CS-y31 of the Board of Commissioners of
SKYWAY WATER AND SEWER DISTRICT of King County, Washington,
adopted at its regular meeting held on c'''"day of ,4„_. 200 f.
U
SKYWAY WATER AND SEWER DISTRICT
sy: C i.e.„c_, ,
0
Title:7'
U
O6/06/2006 Page 3
E.13
C
a1
il
i
1
TM
T
y`
L=
i
a
F..-...-
f-
L
n
I
I
11
e+'
o''
Fi
xd
tl2,
u,,€
t ,
Z
I
i `' - ,
1 .¢-
r
z.,
a , __• -
S '
Ms
a
y_'-:--„
esTM
eT _
l.--
i.
a "
ii
M`
f '
1._
Z_._
i
t
i
nas
Tns '`+
xa
u
nsu
z.
w
p
f _,
zi
i
i
t1aN'
W
ilD
pMa ']
r
tN
11'
M....
o
z
N/'
e'
z
3'
iz.
e
i.
w ,
z.
a
e
Yio
g
i++
y
r
izs
yup
y7
xa='
i .._.,.__
R
i1
2M1
i2-
2
1
3T',
P
ARK ..
yr
nyt ,
M
1 ,
x+
z.
rt ,
x'
rl
2,
N___._
n.-•
p-
sa
s _-
I
M.
f
E
6
215f
f
P.& '
w
n.
s,
rn, »
m .„
n
y(
iTy ,
T," \+
ea"
V
m_""
o! ,.
n
J ,
x..
o
x,;,
o ;
2
i'
i
s /
N
OF "\
wTMa
ssxx
ARK} . ''
s'
na> >
xs
u \
nss
fi
nu „
rT
qh
E.
q-.
zz
aw .
yi
111'''
ss
6n10
e
iha
j
t]
Sw ,
o .
h ,
r,
t5z1
S
sq
69W
f+
i15)
4'.
i
T_.
p
AY $
S/
F
k.
TNl
M
i2W5
w
xxs+
y
t]
2
69W
N*
690e-
ry
i'
D5e
y '
1 )
1 . '
Y
1e -
n*
1
CiT
nit
i
u
e2n
ex
11
q
ti
QI
1161U
J67i
lC
N11
I,
y
8
1
l.
b.
nn
i
1iuc'..
n
s
ixs
e
m+
ntu
M' -
vn
gTM
a
A[++
n
yzs
n
n«
m
r
A
D
xW
sz
Y
isi
nio
xs
µw
typ.?
s
y
rim
v ;
kay
n.
x
x
o
v,
c
co'
x
lt5
az
w
ron
r, "
xss
ro °
e-
e
eyy
e
nsn
sz '
zs'
S `
JA.
W- `
py
TP
YN
J
25
ffi
a.,
j °
N
tE°
16]
a
1°
3
roo '
resi
x , .,
Pg• '
na
n,
ns'
ClrY
nas
s°'
aw*_„
9
6 /.
1'%
it
ias
m' /,
na
n • "
c
R$
n . "
s
xro -.
m,
x ''
e
rnb
rRqN
Seq
e ,
xsµ
x
ex••
at
a}
1 ,,::
t:.
au
rn
Ti'
J
neN .'"
fi
U
i
S{
SSTt
f
4
ia
y
asz
3
R
s `
s
arm
ar '
l
u
aru
rnw
N
4
Skqcr
ri».
ro / '
s
au
sd'
M
y
41 ]
W
v+
teri
s000
ryE'
T
w/
i
J
im
C '.
n
1 ,
o
i.
e
t.
0
a
s
Taei '
xu,.
p
E,
s
nr
is
g,
xa
1
2
T
73
11t15
1116Y
2t11
t
M .
4
J
i°°
t
µ"
3
ua!
nn ,
i
taxx
xm.
xrn ,
cn
t
zsr
ti. `
U(
l.
S
ER
SERV
RY _
2' /•
a
e
rn
r
zni
5 '
W
eav \
N
I
xtr
r
I,
s,
xs9r
2' "°
m+ '
n
i«
k
a
wm
s.
zes
em,
ms • +
O •'
D '.
i ,
w
t
x'
27
J
o
6
r' ' ' ` -
6R
T._
Rs+ --
K
T,
1
026
5
4
S'
2
zso: '
1
ma
n°°
N
t%
T
irib
M
m
1,
5,\
f
Y02y '
M1Il+ . ..
tM
t
r. '
t.
a •
zs
Ta1,
xa+
b ° '
ten ,,
xen
z
iSS. <
E,
xe» :
n
p
i,
j..•
tri .
nx '
a
o
M
i.
0
rr,
e4 '
xe"
tese !*
M
i
i1e+
Y
io
exio '
t'
i ,9+
i
r
i
nm '
r'
Tp'`
a':.
1
i» ' ' ' . ' ----_----
iysa
r..-,_------"'
tow -
roz
oi'
e»
w.
w
n
b
T1a6 '
2
TKl
M+
Rb*
5
2N
t»
N'
y
y
23
IE
U
i161 '.
TtM
t
ttA
f190
Ill+]
T61t
b
1°
o
i°
z° __;• •
am '
nn- '
J
ie„
0
y
rtx° °
mt .
n+
xr .__ _
s
ets
wn
Y
2,
yyos
r
my
n
n
nsn
rns'._.-
L.
tt
e
pn'
wx\_.----- \
S
sy,
i '-,
xen
n
rn`
i—
ns
yiu
y
1,
roys °
oss
e2` \
xnn
x
m
TiYFn'
s
e
tt3
ns
p,
u
P
u
wy
e
u°' »
3
mi
D
s
aM+
rie'
A
i.
p
t _--
t.
0 .___-__--- ]=_
a.
d
R,
i3o...__
ey+
i
69
6
ltOY
1t13
T119
x.
tVM
9
9
p
1'
A
1J014.
tJ9M
t
UM
R
1291d
t2M56
12t1 .
i19] ---
p
11fA
7
17M
y!
W
6
9
69Y1
iWA
mtT
i29
5
i
fli
r
t141> ,___-__
4
N
n
69
l' i
e'
Mi''
ttTt
INI ,
I
ACK{
iMR
t},
yyo•
enx
wa°
n'
i'
xs+
o
cr+
scNo'`
a
ma' -_- .'
x++
m::
t. „,, ...
L29_-_----'
y ,
s
sTM'? '
ro,
a
tws
n,
r.
uiwm+
ne
t
q
s
r,.
iOC`
U
avu
o+
y
y
y
t1
E7
y
iizH
S
svnq
mztt
nm »
iT -. '='
S .
m '
n3s
3
y
iD
TW
Pfbp
lltt
it
yy
6y,
yy
6MT
6f9
6925
C8
T
01
r
i
lJa .'
t
Si
F
m' ,_.__'
1555 .,___.,.
tl
2
iNl
T9
5
1!)
5-
M'.
aa4 '
w _-
o+
4 °
0'
2
I
i
em
TIE'
BGc
uM
ttES
cRM
4
731s
i,
as
n,
s ,
c
s
y .
o
N
5
i
T
N
OSE
p
FtE
a"' '""
pRpP
G
AREA
I _
yHEE1.
1N ____----
r
i
ise ,
v.
eeso " _.---
oyy
rn
rxa
nn
nez
na
nsa
a
mn'
m,
y
ios'
r`
ED 69
s
4.
E.13
CAG-19-182
AGREEMENT
FOR INTERIM SEWER SERVICE BETWEEN COAL CREEK
UTILITY DISTRICT AND CITY OF RENTON
This Agreement ("Agreement") is made and entered into by and between Coal Creek
Utility District, a Washington municipal corporation ("District"), and the City of Renton, a
Washington municipal code city ("City"), (individually a "Party" and collectively the "Parties")
for the purposes set forth herein.
RECITALS
Whereas, the District is authorized pursuant to RCW 57.08.005 (3) and (5) to provide
public water and sanitary sewer service to real property located within and outside the District;
and
Whereas, the City is authorized to provide public water and sanitary sewer service to real
property located within the City's water and sewer service areas; and
Whereas, certain real property, as legally described on Exhibit A and depicted on Exhibit
B attached hereto and incorporated herein by this reference (the "Property"), is being developed
as a residential subdivision referred to as Christelle Ridge; and the Property is located within the
City's water and sewer service areas; and
Whereas, development of the Property will require extensions of the public water and
sanitary sewer systems to make those utility services available to the Property; and
Whereas, the City can provide water and sewer service to the Property by extension of its
public water and sanitary sewer systems to the Property; however, it is not presently financially
feasible to extend the City's sanitary sewer system to the Property; and
Whereas, the District's sewer system is located adjacent to the Property, and the District is
willing to provide sewer service to the Property on an interim basis, and the City will agree to
allow the District to provide sanitary sewer service to the Property on an interim basis, on certain
terms and conditions set forth in this Agreement; now, therefore,
AGREEMENT
In consideration of the terms and conditions set forth in this Agreement, the Parties agree
as follows:
A. The City agrees that the District may provide and District agrees to provide interim
sanitary sewer service to the Property under the following terms and conditions:
1. The District's sanitary sewer system shall be extended to and through the Property by
the owner of the Property pursuant to the District's developer extension process
incorporating the District's standards and specifications for sewer extensions;
E.14
7. Following its execution by the Parties, this Agreement shall be recorded in the King
County Recorder's Office or posted on the City's and the District's respective
websites listed by subject matter.
8. The Parties represent and warrant that the individuals executing this Agreement on
behalf of their respective party have the authority and are authorized to do so.
COAL CREEK UTILITY DISTRICT CITY OF RENTON
By: ; ,' 'r74. -By: f e2'-----,'
giName: ir''f0 5 $.t// Name: Grm erman
Its: General Mann /
1'?
ager Its: Public Works Administrator
Dated: ,I Z' Dated: 5// I
Approved as to form:
Shane Moloney,City Att rney
E.14
provided the District shall provide the City the proposed sewer extension plans for
the Property for the City's review and comment prior to final approval of such plans
by the District.
2. The District shall provide sanitary sewer service to the Property on the same terms and
conditions as it provides service to similar property within the District's boundaries
and according to the District's resolutions, rules and regulations, and as such
resolutions, rules and regulations may be amended and superseded.
3. Whenever the City, in its sole discretion, determines the City may provide permanent
sanitary sewer service to the Property, the City shall provide written notice to the
District and the then present owner(s) of the Property of its intent to provide sanitary
sewer service to the Property and the effective date of such sewer service to the
Property, and upon the effective date of such notice, title to and ownership of the
sanitary sewer system located on and serving the Property will be transferred by the
District to the City. Disconnection of the sewer system from the District's sewer
system and connection to the City's sanitary sewer system shall be at the City's
expense. Thereafter the sanitary sewer system located on the Property shall be
maintained and operated by the City as part of its sanitary sewer system and the City
shall provide sanitary sewer service to the Property in accordance with the City's
ordinances, resolutions, rules and regulations, and as such ordinances, resolutions,
rules and regulations may be amended and superseded. All fees and charges collected
by the District for connection or sewer service,prior to such transfer,shall be retained
by the District.
4. As a condition of service and prior to the connection of the Property to the District's
sanitary sewer system, the owner(s) of the Property shall provide the District with an
agreement with terms and conditions as required by the District for interim sewer
service from the District to the Property.
5. This Agreement shall be effective on the date by which both Parties have executed
this Agreement("Effective Date").
6. Unless provided otherwise in this Agreement, notices provided pursuant to this
Agreement shall be delivered to each Party as follows:
To the District: Coal Creek Utility District
Attn: General Manager
6801 132nd Place SE
Newcastle,WA 98059
To the City: City of Renton
Attn: David Christensen
Wastewater Utility Engineering Manager
1055 South Grady Way
Renton,WA 98057
E.14
Exhibit A
LEGAL DESCRIPTION:
THAT PORTION OF THE NORTHWEST QUARTER OF THE NORTHWEST QUARTER OF SECTION 3,
TOWNSHIP 23 NORTH, RANGE 5 EAST,W.M., KING COUNTY, WASHINGTON, DESCRIBED AS
FOLLOWS:
COMMENCING AT THE NORTHWEST CORNER OF SAID SUBDIVISION;THENCE SOUTH 88°23'35"
EAST ALONG THE NORTH LINE OF THE SECTION 863.71 FEET TO THE TRUE POINT OF
BEGINNING; THENCE CONTINUING SOUTH 88°29'35" EAST 130.96 FEET TO THE
SOUTHWESTERLY MARGIN OF COUNTY ROAD;THENCE SOUTH 47°50'49" EAST ALONG SAID
MARGIN 424.84 FEET;THENCE SOUTH 01°40'08" WEST 164.42 FEET;THENCE NORTH 89°13'51"
WEST 430.43 FEET; THENCE NORTH 01°47'48" EAST 128.90 FEET;THENCE NORTH 89°13'51
WEST 24.76 FEET; THENCE NORTH 01°48'21" EAST 318.12 FEET TO THE TRUE POINT OF
BEGINNING;
ALSO KNOWN AS LOT 3 OF LOT LINE ADJUSTMENT NO. LLA 010-90, RECORDED OCTOBER 16,
1990 UNDER RECORDING NO. 9010169012 AND REVISED BY INSTRUMENT RECORDED
FEBRUARY 12, 1991 UNDER RECORDING NO. 902129004, IN KING COUNTY, WASHINGTON).
E.14
EXHIBIT B
NW COR SEC. 3-23-5
N 88'29'35" W (KCAS) 1317.81' (CAL)
N 88'29'33" W (DEED) 1317.92' (DEED)
NORTH LINE OF 3-23-5
LT...863.71' z ' 5"S
E 130.96'
F
N. `"A,
IIN
s
Iw
In
so,
Ir9,
t
N
F
R?
ir
O
Z CHRISTELLE RIDGE SITE
PARCEL NO. 0323059096 GL a
kfl
N 8913'51" N
W 24.76' oil-4
I• _N
I5w
z
N 89'13'51" W 430.43' rt
E.14
1 1 I1 f l
Ali6oi
IAl
e
II
4
s.:
94:t'
c
0
li.
NE,27th
r-
10 Homes
Future)J
i
NE 26th eti C
iii.:.- ___._ a, NE 25thPt t
EZ
NE25th° r°' 20 Homes
Future)Ct
9- 9- s-
o W
o ,
mQ t I1
e Iett
at I
i
NE'24ihS1
e t.
co
r V:1:: V µJ I 1
1
I t NE`23rd Gt i I ! I I .
COAL CREEK UTILITY DISTRICT SERVICE AGREEMENT - CHRISTELLE RIDGE
Proposed Service Line with Coal Creek UD 0 City Manholes Coal Creek Utility District,Cleanout
ODevelopable Properties City Cleanout 0 Coal Creek Utility District, Manhole
Or 4 Developer Property City Gravity Mains , Coal Creek Utility District, Lift Station
ptit9 Renton City Limits Coal Creek Utility District Sewer Main
E.14
Instrument Number:20190530000187 Document:AG Rec:$105.00 Page-1 of 7
Record Date:5/30/2019 10:32 AM
King County,WA
Coal Creek Utility District
6801 132nd PL SE
Newcastle,WA 98059
WASHINGTON STATE RECORDER'S Cover Sheet (RCW 65.04)
Document Title(s)
Agreement of Interim Sewer Service
Reference Number(s)of Documents assigned or released:
Number of Pages: 7
Grantor(s)
City of Renton
Grantee(s)
Coal Creek Utility District
Legal description
POR OF NW 1/4 OF NW 1/4-BEGIN NW CORNER OF NW 1/4 OF NW 1/4 TH S 88-29-35 E 863.71 FT TO POB TH S
88-29-35 E 130.96 FT TO SWLY MGN OF CO ROAD TH S 47-50-49 E 424.84 FT TH S 01-40-08 W 164.42 FT TH N
89-13-51 W 430.43 FT TH N 01-47-48 E 128.90 FT TH N 89-13-51 W 24.76 FT TH N 01-48-21 E 318.12 FT TO POB-
AKA LOT 3 OF REVISED CITY OF RENTON LOT LINE ADJ NO 010-90 RECORDING NO 9102129004
Assessor's Property Tax Parcel/Account Number UAssessors Tax#not yet
032305-9096
The Auditor/Recorder will rely on the information provided on this form. The staff will not read the
document to verify the accuracy or completeness of the indexing information provided herein.
I am signing below and Paying a additional$50 recording Fee(as provided in RCW 36.18.010 and
referred to as an emergency nonstandard document),because this document does not meet margin and ,
formatting requirements. Futhermore,I herby understand that the recording process may cover up or
otherwise obscure some part of the text of the original document as a result of this request."
Signature of Requesting Party
Note to submitter: Do not Sign above nor pay additional$50 fee If the document meets margin/formatting requirements
E.14
Instrument Number:20190530000187 Document:AG Rec: $105.00 Page-2 of 7
Record Date:5/30/2019 10:32 AM King County,WA
AGREEMENT
FOR INTERIM SEWER SERVICE BETWEEN COAL CREEK
UTILITY DISTRICT AND CITY OF RENTON
This Agreement ("Agreement") is made and entered into by and between Coal Creek
Utility District, a Washington municipal corporation ("District"), and the City of Renton, a
Washington municipal code city ("City"), (individually a "Party" and collectively the "Parties")
for the purposes set forth herein.
RECITALS
Whereas, the District is authorized pursuant to RCW 57.08.005 (3) and (5) to provide
public water and sanitary sewer service to real property located within and outside the District;
and
Whereas, the City is authorized to provide public water and sanitary sewer service to real
property located within the City's water and sewer service areas; and
Whereas, certain real property, as legally described on Exhibit A and depicted on Exhibit
B attached hereto and incorporated herein by this reference (the "Property"), is being developed
as a residential subdivision referred to as Christelle Ridge; and the Property is located within the
City's water and sewer service areas; and
Whereas, development of the Property will require extensions of the public water and
sanitary sewer systems to make those utility services available to the Property; and
Whereas, the City can provide water and sewer service to the Property by extension of its
public water and sanitary sewer systems to the Property; however, it is not presently financially
feasible to extend the City's sanitary sewer system to the Property; and
Whereas, the District's sewer system is located adjacent to the Property, and the District is
willing to provide sewer service to the Property on an interim basis, and the City will agree to
allow the District to provide sanitary sewer service to the Property on an interim basis,on certain
terms and conditions set forth in this Agreement;now,therefore,
AGREEMENT
In consideration of the terms and conditions set forth in this Agreement,the Parties agree
as follows:
A. The City agrees that the District may provide and District agrees to provide interim
sanitary sewer service to the Property under the following terms and conditions:
1. The District's sanitary sewer system shall be extended to and through the Property by
the owner of the Property pursuant to the District's developer extension process
incorporating the District's standards and specifications for sewer extensions;
E.14
Instrument Number: 20190530000187 Document:AG Rec:$105.00 Page-3 of 7
Record Date:5/30/2019 10:32 AM King County,WA
provided the District shall provide the City the proposed sewer extension plans for
the Property for the City's review and comment prior to final approval of such plans
by the District.
2. The District shall provide sanitary sewer service to the Property on the same terms and
conditions as it provides service to similar property within the District's boundaries
and according to the District's resolutions, rules and regulations, and as such
resolutions,rules and regulations may be amended and superseded.
3. Whenever the City, in its sole discretion, determines the City may provide permanent
sanitary sewer service to the Property, the City shall provide written notice to the
District and the then present owner(s) of the Property of its intent to provide sanitary
sewer service to the Property and the effective date of such sewer service to the
Property, and upon the effective date of such notice, title to and ownership of the
sanitary sewer system located on and serving the Property will be transferred by the
District to the City. Disconnection of the sewer system from the District's sewer
system and connection to the City's sanitary sewer system shall be at the City's
expense. Thereafter the sanitary sewer system located on the Property shall be
maintained and operated by the City as part of its sanitary sewer system and the City
shall provide sanitary sewer service to the Property in accordance with the City's
ordinances, resolutions, rules and regulations, and as such ordinances, resolutions,
rules and regulations may be amended and superseded. All fees and charges collected
by the District for connection or sewer service,prior to such transfer,shall be retained
by the District.
4. As a condition of service and prior to the connection of the Property to the District's
sanitary sewer system,the owner(s)of the Property shall provide the District with an
agreement with terms and conditions as required by the District for interim sewer
service from the District to the Property.
5. This Agreement shall be effective on the date by which both Parties have executed
this Agreement("Effective Date").
6. Unless provided otherwise in this Agreement, notices provided pursuant to this
Agreement shall be delivered to each Party as follows:
To the District: Coal Creek Utility District
Attn: General Manager
6801 132' Place SE
Newcastle,WA 98059
To the City: City of Renton
Attn: David Christensen
Wastewater Utility Engineering Manager
1055 South Grady Way
Renton,WA 98057
E.14
Instrument Number:20190530000187 Document:AG Rec:$105.00 Page-4 of 7
Record Date:5/30/2019 10:32 AM King County,WA
7. Following its execution by the Parties, this Agreement shall be recorded in the King
County Recorder's Office or posted on the City's and the District's respective
websites listed by subject matter.
8. The Parties represent and warrant that the individuals executing this Agreement on
behalf of their respective party have the authority and are authorized to do so.
COAL CREEK UTILITY DISTRICT CITY OF RENTON
By: v,4 By:
Name: 'Wiattt/'f'O Z s $`/, Name: Gre immerman
Its: General Manager Its: Public Works Administrator
Dated: 5/2T tt Dated: Sl 1 111
Approved as to form:
Shane Moloney,City Att ineS y
E.14
Instrument Number: 20190530000187 Document:AG Rec:$105.00 Page-5 of 7
Record Date:5/30/2019 10:32 AM King County,WA
Exhibit A
LEGAL DESCRIPTION:
THAT PORTION OF THE NORTHWEST QUARTER OF THE NORTHWEST QUARTER OF SECTION 3,
TOWNSHIP 23 NORTH, RANGE 5 EAST,W.M., KING COUNTY, WASHINGTON, DESCRIBED AS
FOLLOWS:
COMMENCING AT THE NORTHWEST CORNER OF SAID SUBDIVISION;THENCE SOUTH 88°23'35"
EAST ALONG THE NORTH LINE OF THE SECTION 863.71 FEET TO THE TRUE POINT OF
BEGINNING;THENCE CONTINUING SOUTH 88°29'35" EAST 130.96 FEET TO THE
SOUTHWESTERLY MARGIN OF COUNTY ROAD;THENCE SOUTH 47°50'49" EAST ALONG SAID
MARGIN 424.84 FEET;THENCE SOUTH 01°40'08"WEST 164.42 FEET;THENCE NORTH 89°13'51"
WEST 430.43 FEET;THENCE NORTH 01°47'48"EAST 128.90 FEET;THENCE NORTH 89"13'51
WEST 24.76 FEET;THENCE NORTH 01°48'21" EAST 318.12.FEET TO THE TRUE POINT OF
BEGINNING;
ALSO KNOWN AS LOT 3 OF LOT LINE ADJUSTMENT NO. LLA 010-90, RECORDED OCTOBER 16,
1990 UNDER RECORDING NO. 9010169012 AND REVISED BY INSTRUMENT RECORDED
FEBRUARY 12, 1991 UNDER RECORDING NO. 902129004, IN KING COUNTY,WASHINGTON).
E.14
Instrument Number: 20190530000187 Document:AG Rec: $105.00 Page-6 of 7
Record Date:5/30/2019 10:32 AM King County,WA
EXHIBIT B
NW COR SEC. 3-23-5
N 68'29'35" W (KCAS) 1317.81' (CAL)
N 88.29'33" W (DEED) 1317.92' (DEED)
NORTH LINE OF 3-23-5
863.71'
N
S 88'29'35"
E130.96' 9
4,
IN
I sue.
F‘
N elf\
I Z CHRISTELLE RIDGE SITE OG t+I PARCEL NO. 0323059096 4
Li—N 8913'51"
N y
W 24.76' c
5; 8.1
I ••N I
I a c
Z W
NLIIIIIIi0 =MD MEW MIIIMWM,A=M=. 1MM MOM ====IIIIMiMM MED illiM
N 8913'51" W 430.43'
E.14
Instrument Number: 20190530000187 Document:AG Rec: $105.00 Page-7 of 7
Record Date:5/30/2019 10:32 AM King County,WA
kJ
F CDm
C3• ci
V j
6.'
27th N\ ,
i.
44//\..
41.,:
t....
T--'a j \,,
10 Homes *;d,J•4 ,•,4,.
Future)
W In i -. . . -,...,
E
Q NE 26th.;
e,..:- NE 25 PI eLCt
t
oZ __. f.
El) 0m
1111
NE
m 20 Homes
26th
P1111
Cry Future)
C
ll: "...it„:.
Q m
IIii,,
8
111E'24thSf o
01N m
111
Co ?tea NE 23rd Ct
r
O.
COAL CREEK UTILITY DISTRICT SERVICE AGREEMENT m CHRISTELLE RIDGE
Mil- Proposed Service Line with Coal Creek UD 0 City Manholes 0 Coal Creek Utility District,Cleanout
ODevelopable Properties O City Cleanout 0 Coal Creek Utility District,Manhole
Developer Property City Gravity Mains ® Coal Creek Utility District,Lift Station
psis
Renton City Limits Coal Creek Utility District Sewer Main
E.14
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix F
STANTEC MODEL UPDATE AND CAPACITY
ANALYSIS REPORT
TABLE OF CONTENTS
Page No.
Chapter 1 INTRODUCTION ............................................................................................................. 1.1
PROJECT UNDERSTANDING ............................................................................................................... 1.1
MODELING SOFTWARE ....................................................................................................................... 1.2
Chapter 2 PHYSICAL MODEL UPDATE ........................................................................................... 2.1
2012 PHYSICAL MODEL DEVELOPMENT ........................................................................................... 2.1
Data Source .................................................................................................................................. 2.1
Manholes and Nodes .................................................................................................................. 2.1
Pipes ............................................................................................................................................... 2.1
Lift Stations and Force Mains ...................................................................................................... 2.1
Extent of 2012 Hydraulic Model ................................................................................................. 2.3
Model Pipe and Manhole ID Updates ...................................................................................... 2.3
ULTIMATE PHYSICAL MODEL DEVELOPMENT ................................................................................... 2.4
Pipe, Manhole and Node Additions ......................................................................................... 2.4
Chapter 3 PLANNING DATA .......................................................................................................... 3.1
MODEL SANITARY FLOW DETERMINATION ...................................................................................... 3.1
Dry Weather Flow Determination by Mini-Basin ...................................................................... 3.1
Diurnal Curve Development ...................................................................................................... 3.1
MODEL PLANNING DATA ................................................................................................................... 3.1
Planning Area/Basin Boundaries ............................................................................................... 3.2
2012 Model ......................................................................................................................... 3.2
Ultimate Model ................................................................................................................... 3.2
Land Use and Zoning ................................................................................................................... 3.5
Data Projections ........................................................................................................................... 3.5
Residential .......................................................................................................................... 3.5
Employment ....................................................................................................................... 3.7
Schools ................................................................................................................................ 3.7
Future Population Projections .................................................................................................... 3.7
Residential .......................................................................................................................... 3.7
Employment ....................................................................................................................... 3.8
Schools ................................................................................................................................ 3.9
POPULATION AND SANITARY SEWAGE FLOW ASSIGNMENT TO MODEL .................................. 3.10
Population Assignment .............................................................................................................. 3.10
Determination of Sanitary Sewer Flow Rates ......................................................................... 3.11
Page i
City of Renton 2015 Hydraulic Model Update
Summary Report
Table of Contents
Input to Model ............................................................................................................................ 3.15
Area Assignments ............................................................................................................ 3.15
RAINFALL AND EVAPORATION ASSIGNMENTS.............................................................................. 3.16
Rainfall Assignments ................................................................................................................... 3.16
Evaporation ................................................................................................................................. 3.16
External Boundary Flows ............................................................................................................ 3.16
Chapter 4 MODEL CALIBRATION .................................................................................................. 4.1
2012 MODEL DRY WEATHER CALIBRATION ..................................................................................... 4.2
Sanitary Flow Calibration ............................................................................................................ 4.2
2012 MODEL WET WEATHER CALIBRATION ..................................................................................... 4.6
Infiltration and Inflow Calibration .............................................................................................. 4.6
Non-Calibrated Model Basins .................................................................................................... 4.8
Ultimate Model Inflow and Infiltration Parameters ................................................................. 4.9
Chapter 5 ANALYSIS AND RESULTS ............................................................................................... 5.1
2012 MODEL PEAK FLOW AND CAPACITY ANALYSIS .................................................................... 5.1
External Boundary Flows .............................................................................................................. 5.1
Peak Storm ..................................................................................................................................... 5.1
Analysis Results .............................................................................................................................. 5.3
ULTIMATE MODEL PEAK FLOW AND CAPACITY ANALYSIS .......................................................... 5.17
Peak Storm ................................................................................................................................... 5.17
Analysis Results ............................................................................................................................ 5.17
LIFT STATION AND FORCE MAIN ANALYSIS .................................................................................... 5.33
INFILTRATION AND INFLOW ANALYSIS ............................................................................................ 5.34
PEAK BOUNDARY FLOW ANALYSIS ................................................................................................. 5.37
Chapter 6 RECOMMENDATIONS AND SUMMARY ....................................................................... 6.1
FLOW MONITORING RECOMMENDATIONS .................................................................................... 6.1
KING COUNTY COMPATIBILITY .......................................................................................................... 6.3
LIMITATIONS OF THE MODEL .............................................................................................................. 6.6
TABLES
Table 2-1 Pipe Material Summary .................................................................................................... 2.4
Table 3-1 Population Projections by Sewer Mini-Basins: Values Assigned to 2012 and
Ultimate Models ................................................................................................................................ 3.12
Table 4-1 Dry Weather Calibration Summary ................................................................................ 4.4
Table 4-2 Per Capita Flow Rate (ft2/PE/day) ................................................................................. 4.5
Table 4-3 Wet Weather Calibration Summary ............................................................................... 4.8
Page ii
City of Renton 2015 Hydraulic Model Update
Summary Report
Table of Contents
Table 4-4 City Mini-Basins Not Calibrated for Dry and Wet Weather ........................................ 4.9
Table 5-1 Selected Storm Events Per Model Basin ........................................................................ 5.3
Table 5-2 Capacity Analysis for 2012 Sewer Model - Problem Areas ........................................ 5.5
Table 5-3 City of Renton Sewer Model 2012 and Ultimate Peak Flow at Mini-Basin Outlet,
Including Storm Event ...................................................................................................................... 5.18
Table 5-4 Capacity Analysis for Ultimate Sewer Model - Problem Areas ............................... 5.21
Table 5-5 Lift Station and Force Main Analysis Summary ........................................................... 5.33
Table 5-6 Peak Infiltration and Inflow per Mini-Basin .................................................................. 5.35
Table 5-7 Peak Boundary Flows ...................................................................................................... 5.37
Table 6-1 City of Renton Sewer Model Proposed Flow Monitor Locations ............................... 6.2
FIGURES
Figure 3.1 2012 Sewer Mini-Basin Boundaries ................................................................................. 3.3
Figure 3.2 Ultimate Sewer Mini-Basin Boundaries .......................................................................... 3.4
Figure 5.1 Selected Storm Events Per Model-Basin ....................................................................... 5.2
Figure 5.2 2012 Sewer Model Analysis Results .............................................................................. 5.38
Figure 5.3 Ultimate Sewer Model Analysis Results ....................................................................... 5.39
Figure 6.1 Proposed Flow Monitor Locations ................................................................................. 6.8
APPENDIX
APPENDIX A – Dry Weather Flow Calibration Time Series .............................................................. A
APPENDIX B – Wet Weather Flow Calibration Time Series .............................................................. B
APPENDIX C – Figure 5-2A Through Figure 5-2S: 2012 Sewer Model Analysis Results ............... C
APPENDIX D – Figure 5-3A Through Figure 5-3W: Ultimate Sewer Model Analysis Results ....... D
Page iii
City of Renton 2015 Hydraulic Model Update
Summary Report
CHAPTER 1 INTRODUCTION
PROJECT UNDERSTANDING
The City of Renton retained the services of Stantec to update the existing hydraulic
model to evaluate the capacity of the existing sewer system and to analyze the
system for future development scenarios. Steps in the development of the sewer
model included:
1.Updates of the physical model that involved obtaining, formatting, and
inputting into the physical system data such as manholes, pipes and lift
stations.
2.O btaining and analyzing the population and employment data to input as
flow assignments to each sewer basin with the precipitation and evaporation
data.
3.Calibration of the model to 2012 conditions.
4.Analyzing the 2012 and Ultimate Model Peak Flow Scenarios.
The methodology and numerous assumptions associated with developing the
model are detailed herein, with supporting documents associated with the project.
The r eport includes the following sections:
•Chapter 1 – Introduction
•Chapter 2 – Physical Model Updates
•Chapter 3 – Planning Data
•Chapter 4 – Model Calibration
•Chapter 5 – Analysis and Results
•Chapter 6 – Recommendations and Summary
Two primary models were used during this project. T he 2012 Model was updated
from previous versions of the model, and was calibrated to King County’s 2008-2011
flow-monitoring data. Discussion of the original model development can be found
in the City of Renton Sanitary Sewer Model Development and Analysis Summary
Report, September 2006. T he Ultimate Model was then developed, which
incorporates all of the projected flow assignments for the analysis.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 1.1
INTRODUCTION CHAPTER 1
MODELING SOFTWARE
The model was analyzed using the MIKE URBAN software program by the Danish
Hydraulic Institute (DHI), and was originally developed using MOUSE, also by DHI.
DHI assisted King County with the 2001 regional Infiltration and Inflow (I&I) study,
and King County also used MOUSE for the 2012 I/I study, and has assisted the City
and Stantec with the development of the original MOUSE model, conversion of the
MOUSE model to MIKE URBAN, and development of the City’s sewer system
geodatabase.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 1.2
CHAPTER 2 PHYSICAL MODEL UPDATE
The development of the two primary models (2012 and Ultimate) is summarized
below.
2012 PHYSICAL MODEL DEVELOPMENT
Data Source
The basis for the M IKE U RBAN model update was primarily the City’s GIS database,
and includes system data from 2008 through March 201 2 . Additional data was
provided from topographic survey data and sewer record drawings. To be
consistent with the previous model development and updates, the following rules
were applied when adding new facilities to the model:
Manholes and Nodes
• Cleanouts and connected piping were generally excluded from the model.
• The correct manhole diameters were assigned to the model where available.
Manholes were generally assumed to be 4-foot diameter if no other
information was available.
• Outlet loss for manholes in the model was assumed to be “round-edged.” To
remain conservative yet more realistic, the outlet loss was assigned as
“round-edged” to the manholes, and the default loss value “Km” was
reduced from 0.25 to 0.1.
• At a few locations, the new sewer information was joined the older portions
of the model. I nterpolations and/or datum shifts of elevations were
necessary during the original model development. In many of these cases, it
was necessary to re-interpolate or re-work the existing manhole elevations to
match the new data.
Pipes
• Specific pipe lengths were generally not input into the model; instead the
pipe lengths were scaled based on the coordinates from the City’s GIS.
Lift Stations and Force Mains
• Best available pumping rate data was used to input flow rates for single
pumps in duplex stations. Pumps were assumed to operate at a constant
rate (the design flow rate) throughout the ranges of operation. The pump
City of Renton 2015 Hydraulic Model Update
Summary Report Page 2.1
PHYSICAL MODEL DEVELOPMENT CHAPTER 2
data originated from pumping tests and flow monitoring data supplied by
the City. Pump curves were not used for the lift stations in the model.
Generally, the magnitude of flow rates from the lift stations relative to the
larger system flows were considered to be small enough to neglect the
effects of wet well fluctuations for modeling purposes.
• The pump controls (on/off) are based on actual level settings obtained from
the City. The second pump in each station is activated based on the wet
well level, and a very rough estimate was made for the flow rates with both
pumps running. For the backup pumps within lift stations, where no other
information was available, the second pump was assumed to produce
approximately 1/4 to 1/3 of the flow rate of the first pump when the pumps
operate simultaneously. It is recognized that per DOH requirements for
duplex stations, a single pump must be sized to handle the entire peak flow
of the design storm event. The flow rate from the second pump is defined as
the difference between the first pump operating alone, and the combined
pumping rate (e.g., Pump 1 pumps 1.0 cfs throughout operation range, Pump
2 pumps 0.25 cfs throughout its operating range).
• The alignment, size, and material of f orce mains is physically defined in the
model. However, intermittent grade changes along the alignment are not
represented.
• Appropriate lift stations were added and abandoned in the model for the
different scenarios and timeframes analyzed, as described below, and in the
sections discussing the Ultimate Models.
The following lift stations were added or modified in the 2012 Model:
• Denny’s Lift Station (L07) Improvements
• Airport Lift Station (L25) Replacement
• Stoneg ate Lift Station (L27) Replacement
• Shy Creek Lift St ation (L01)
• Liberty Lift Station (L3 4)
The following lift stations, which have been removed from service, were removed in
the 2012 Model:
• Summer Wind Lift Station
• Earlington Lift Station
• East Renton Lift Station
• High Gate Lift Station
City of Renton 2015 Hydraulic Model Update
Summary Report Page 2.2
PHYSICAL MODEL DEVELOPMENT CHAPTER 2
• Highland Estates Lift Station
• Evendell Lift Station
A few of the improvements described above, including the Liberty Lift Station and
Airport Lift Station Improvements, were not active until after 2012. These
improvements were added after the calibration was complete.
Extent of 2012 Hydraulic Model
The majority of the City’s sewer system as it existed in 2012 was incorporated into
the hydraulic model. Clean-outs, dead-end portions of the system with
missing/errant information, and some portions of private system were not included.
Although present in the physical model, a portion of the City’s system south of Mini-
Basin 5 did not include flow assignments, per direction from City staff (this portion of
the system is “dry” piping in the model), since it is tributary to another purveyor’s
Mini-Basin (SOO039). This area is located in the South portion of the City, primarily
serving customers on South 55th Street (between 99th Place South and SR-167) and
on Talbot Road South (between South 50th Street and South 194th Street ).
Isolated areas where small portions of the City’s piping are tributary to sewer
purveyors other than King County were generally not modeled.
Model Pipe and Manhole ID Updates
The City updated its geodatabase in 2014. Included in this update was a revision
to the naming conventions for the sewer infrastructure, including manholes,
cleanouts, gravity pipes, force mains, and lift stations. In order to more easily
identify and discuss the analysis of the sewer system, the City requested that we
update the City sewer identifiers (MUIDs) within the model to be consistent with the
geodatabase. This included updates to the pipe material identifications , which
were adjusted to conform to NASSCO standards for pipe inspection.
With the assistance of DHI, Stantec imported and updated the MUIDs and pipe
materials . Small isolated areas of the City sewer system were not updated. These
locations were typically updates to the geodatabase that occurred after 2012, or
were locations where the model included horizontal and vertical bends in the pipe
not adequately represented in the GIS. The King County interceptor sewer pipes
were not updated during this procedure. Table 2-1 lists the pipe materials and
associated Manning’s roughness values.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 2.3
PHYSICAL MODEL DEVELOPMENT CHAPTER 2
Table 2-1
Pipe Material Summary
Pipe Material
Manning's
Roughness
Legacy MOUSE model material descriptions
Concrete (Smooth) 0.013
Plastic 0.011
NASSCO Material Descriptions
CAS - Cast Iron 0.0143
CP - Concrete Pipe (non-
reinforced) 0.0133
DIP - Ductile Iron Pipe 0.012
PE - Polyethylene 0.011
PSC - Plastic/Steel Composite 0.011
PVC - Polyvinyl Chloride 0.011
VCP - Vitrified Clay Pipe 0.014
XXX - Not Known 0.0143
A small number of pipes and manholes from sewer improvements after 2012 were
added to the model in order successfully complete the ID updates.
ULTIMATE PHYSICAL MODEL DEVELOPMENT
Pipe, Manhole and Node Additions
The 2012 Model was used as the base to create the Ultimate physical model.
Development of the Ultimate Model included working with City Staff to determine
and include future system improvements, such as:
• T he proposed diversion sewer for Heather Downs/Maplewood Heights was
added. The proposed sewer will begin south of the Union Avenue SE/SE 4th
Street Intersection and will drain sewage flows down a steep slope, and
connect to the existing sewer located in the Maplewood Golf Course.
• The proposed Talbot Hills Sewer relocation was added. This involves
r elocation of the sewer from South 14th Street and redirection of the sewer to
flow by gravity to Smithers Avenue S. This also includes installation of a new
sewer crossing under I-405 at the extension of Smithers Avenue S to S Renton
Village Place.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 2.4
PHYSICAL MODEL DEVELOPMENT CHAPTER 2
• The proposed Thunder Hills diversion sewer, located on S 18th Street between
Grant Avenue S and Eagle Ridge Drive S, was added. The downstream
sewers between Eagle Ridge Drive and Smithers Avenue S were upsized to
accommodate increased flow rates.
In addition to the improvements listed above, “dummy” nodes were added to
represent portions of the “U” Basins or other existing sub-basins not currently served
by sewer. To represent future service, nodes were added for each mini-basin or
sub-b asin, generally a single node each for residential, employment, and any
school populations.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 2.5
CHAPTER 3 PLANNING DATA
The planning data section includes the populations and areas assigned to each
mini-basin, the assumptions used to model sanitary sewer flow, peak flow
generating storm events assigned to each model basin, and I&I assignments.
MODEL SANITARY FLOW DETERMINATION
Unlike the flow monitoring performed for the original 2001 Infiltration and Inflow
study performed by King County, the decennial flow monitoring used for the 2012
study did not include each of the City’s mini-basins. Instead, flow monitors were
placed at fewer locations. T ypically, the locations were at the outlet of each
Model Basin, although a small number of mini-basins were also assigned a flow
monitor. There were 25 flow monitors placed which recorded flows generated
within the City’s sewer service area.
Dry Weather Flow Determination by Mini-Basin
Dry weather flow data from the 2009-2010 flow monitoring season was generally
used to determine total average sanitary sewage flows for each mini-basin. King
County staff identified the periods meeting their criteria for dry weather flow. For
model basins receiving flow from upstream tributary basins , time series using the
flow monitoring data were developed and added to the model as boundary
conditions to examine the total flow through the basin.
Diurnal Curve Development
The diurnal curves developed during the creation of the 2001 Mouse m odel were
not modified for the 2012 or U l t imate models.
MODEL PLANNING DATA
Population projections were compiled for the City of Renton Sewer Service Area for
current and future conditions. The populations are divided into four categories;
single-family residential, multi-family residential, employment, and schools.
Most of the projections for the three categories (not including schools) were taken
from the Puget Sound Regional Council (PSRC) Land Use Baseline projections,
which were developed using the UrbanSims model, and cut to the City of Renton
sewer mini-basin boundaries by PSRC staff. Due to confidentially requirements
established by the Employment Securities Department, employment populations
could not be provided for six sewer mini-basin boundaries. Because of this, two
different methods, which are described later in the chapter, were used to estimate
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.1
PLANNING DATA CHAPTER 3
the employment populations for current and future conditions. A small number of
residential populations were also modified after our review of the PSRC data.
School populations were derived from enrollment data published by the school
districts located within the City sewer service area.
Planning Area/Basin Boundaries
2012 Model
Population and employment data was assigned to the hydraulic model based on
City of Renton mini-basins. There are 6 7 sewer drainage mini-basins. The mini-
basins vary in size and span the entire City. These include the 57 King County Mini-
Basins delineated for the year 2001-2002 flow monitoring, which were modified to
more accurately represent the City’s service area and to exclude non-developable
areas, and to also add Mini-Basins A and B. Mini-Basin 38 was split into two sub-
basins, as discussed in the September 2006 report, and Mini-Basins U1, U2, U3, U4,
U6, U8, and U9 were added to address the development in the eastern portions of
the City Sewer Service Area. These were originally delineated for the previous
Ultimate analysis, but have incorporated some development since that time. Mini-
Basin 30C, which was formerly part of Basin 30A, was created, and Basin 46 was
split into two sub-basins, Mini-Basin 46 and 46-N orth. Other minor adjustments were
made to some of the basins boundaries due to additional development and
improvements to the network.
Figure 3-1 displays the mini-basin boundaries used in conjunction with the 2012
model.
Ultimate Model
The planning area boundaries are determined by physical service area
agreements between the City and other jurisdictions, including adjacent Cities and
Sewer Utility Districts. The Urban Growth Boundary designated by the King County
Comprehensive Plan determines much of the easterly planning boundary areas.
Most of the projected sewer area growth will occur to the areas east of the current
City limits, including a large non-sewered area within unincorporated King County
in the East Plateau service area.
S everal Mini-Basin boundaries were expanded to include the City’s sewer planning
area for the “Ultimate” conditions, so that the entire population projected to be
served by the City and the resultant sanitary sewage flows would be represented.
Topography and other geographic features were taken into account when
creating the new boundaries.
Three Basins east of the City, identified as U5, U7, and U10 included in the Ultimate
model, were also delineated for the previous Ultimate analysis. Basins U5, U10, and
the eastern portion of U9 are outside the East Plateau Service Area but
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.2
CHAPTER 3 PLANNING DATA
Figure 3.1 2012 Sewer Mini-Basin Boundaries
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.3
PLANNING DATA CHAPTER 3
Figure 3.2
Ultimate Sewer Mini-Basin Boundaries
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.4
PLANNING DATA CHAPTER 3
within the Ultimate Sewer Service Area. The areas of proposed future growth were
represented in the model, as a “skeletonized” system. Large portions of the other
U -Basins, including U4 and U6, are also currently without sewer.
Undeveloped portions of the U-Basins were generally represented in the model by
single nodes in the approximate centers of the proposed service areas, connected
to the appropriate discharge locations. Additionally, single nodes were assigned
as “point” loads at various locations in the model, where significant proposed
future service area is projected to connect to the existing system.
Figure 3-2 shows the mini-basin boundaries used in conjunction with the Ultimate
Model.
Land Use and Zoning
The land use and zoning map, adopted September 22, 2014, was obtained from
the City’s geodatabase and used for the planning data. The land use and zoning
designations within the City include single-family residential (generally ranging from
1 to 14 dwelling units per acre), several classifications of multifamily residential,
office, commercial, business, urban-center, and industrial zoning. There are also
many parks and open spaces in and around the City. Population assigned to the
model was grouped into the following four categories: single-family residential,
multifamily residential, employment, and schools. For the 2012 model, population
was assigned to the appropriate categories in the model by overlaying the land
use and zoning map with the map of the sewer system, and separating the
manholes into the four categories. Population was generally not assigned to
manholes within parks and open areas.
Future land use and zoning patterns used in the Ultimate Model for the planning
area were assumed to very closely correspond to existing uses (with a few
exceptions), based on discussions with the City Planning Department and
Planning/Building/Public Works Staff.
Data Projections
Population, household, and employment data was provided by the PSRC for the
years 2012 and 2040 for the entire sewer planning area (both inside and outside
current City limits). The data obtained for these years was provided in geographic
subdivisions based on the based on the sewer Mini-Basin boundaries provided to
PSRC by Stantec. With a few exceptions, each Mini-Basin included projected
growth of households and employment.
Residential
PSRC provided 2012 residential projections for the entire City of Renton Sewer
Service Area utilizing Land Use Baseline data. These projections included estimated
populations for single family and multi-family populations.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.5
PLANNING DATA CHAPTER 3
The Land Use Baseline projections are available down to the parcel level.
However, the data was not been verified at this precision, and may contain some
inaccuracies. Also, PSRC did not provide verification for its cut of the data at the
mini-basin level, so we reviewed the data to determine if there were any obvious
inaccuracies. This was done by reviewing City GIS data within each mini-basin,
including land-use, parcel count, and aerial photos. King County Assessor’s
information, via King County’s online GIS interface, iMap, was also checked to
estimate volume of larger multi-family developments. Based on this review, the
populations for the following basins were modified:
• Basin 5 – The Land Use Baseline projections list 126 parcels and a single family
residential population of 169. City GIS data shows 170 parcels within the
basin, with an estimated 100 single family lots. A multiplier of 2.5 persons per
single family lot was used to estimate a single family residential population of
250 for this basin. The multi-f amily population supplied by PSRC is negligible,
and is consistent with the city GIS data.
• Basin 20 – The estimate from PSRC for this mini-basin encompassed the
Ultimate mini-basin boundary. T o estimate the population for the current
boundary, the total of 3,007 people was scaled on an area ratio of the
current/ultimate basins for an adjusted population of 2,390. The multi-family
development and zoning is all within the current mini-basin boundary, so this
population was not modified.
• Basin 25/Basin 43 – Both of these mini-basins include large mobile home
parks, which are not accounted for in the PSRC projections for either single-
family or multi-family populations. Basin 25 includes approximately 240
mobile homes, and Basin 43 includes approximately 200 mobile homes. T o
account for these populations, a multiplier of 1.8 (multi-family) was applied
to each mobile home, and the populations were added to the projections
supplied by PSRC. For Basin 25, the total residential population was adjusted
from 983 to 1,415. For Basin 43, the population was adjusted from 49 to 410.
• Basin U1 - The Land Use Baseline projections list 58 parcels and a single family
residential population of 255. City GIS data shows approximately 205 parcels
within the basin, with an estimated 197 single family lots. A multiplier of 2.5
persons per single family lot was used to estimate a single family residential
population of 490 for this basin. The multi-family population supplied by PSRC
is negligible, and is consistent with the GIS data.
• Basin U6 – The estimate from PSRC for this mini- basin encompassed the
ultimate mini-basin boundary. T o estimate the population for the current
boundary, the total of 2,050 people was scaled on an area ratio of the
current/ultimate basins for an adjusted population of 1,345. The multi-family
population supplied by PSRC is negligible, and is consistent with the GIS data.
It was not modified.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.6
PLANNING DATA CHAPTER 3
• Basin U9 – The estimate from PSRC for this mini-basin encompassed the
ultimate mini-basin boundary. T o estimate the population for the current
boundary, the total of 1,268 people was scaled on an area ratio of the
current/ultimate basins for an adjusted population of 68. No multi-family
population was projected. This is consistent with the GIS data.
These modifications were reviewed by City of Renton Planning Department staff
and accepted.
Employment
Using Land Use Baseline data, PSRC provided 2012 employment projections for all
but six mini-basins within City of Renton Sewer Service Area. Projections were not
released for Basins 30C, 32, 50, 52, U3, and U8 due to confidentiality requirements
by the Employment Securities Department.
For those six basins, Longitudinal Employer-Household Dynamics (LEHD) data,
developed by the U.S. Census Bureau, was cut to the mini-basin boundaries. The
data listed is for the year 2011, which was the most recent data available.
As with the residential data, the employment data was reviewed. However, since it
is difficult to estimate employment populations for each business without
performing a detailed analysis of each min-basin, no obvious discrepancies
between the PSRC/LEHD projections and the GIS data were identified.
Schools
Using published data from the local school districts, including the Renton School
District and Issa q uah Schools, populations were determined for schools within the
existing sewer service area. Student populations were generally developed using
enrollment statistics for the 2011-2012 school year. Where available, school staffing
data was also collected and used to allocate employment population to the
schools in the model.
Future Population Projections
Residential
PSRC provided 2040 residential projections, using the Land Use Baseline data, for
the entire City of Renton Sewer Service Area. These projections included estimated
populations for single family and multi-family populations. Since these projections
were modeled using a large number of factors, it is difficult to review them solely
on zoning and land use designations. Because of this, none of the residential
projections were modified from the PSRC output, with the following exception:
• As part of the Thunder Hills Sanitary Sewer Interceptor analysis, A detailed
review of the projections for the the tributary areas was performed. It was
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.7
PLANNING DATA CHAPTER 3
determined that The PSRC projections for Mini-Basin 45 (which is tributary to
the Thunder Hills interceptor) for the year 2040 showed large decreases in
single and multi-family residential population, which is inconsistent with the
City’s Comprehensive Plan land use designations and current development
activity for the basin. Because of this, Stantec developed Ultimate
populations for the portions of Mini-Basin 45 tributary to the Thunder Hills
Interceptor by applying the growth percentages calculated for adjacent
Mini-Basin 3 based on PSRC estimates.
Employment
Future employment projections fall under the same restrictions as the current
population data, so PSRC provided 2040 employment projections, using the Land
Use Baseline data, for all but Basins 30C, 32, 50, 52, U3, and U8. Long-term LEHD
data is not developed, so this methodology could not be used for future
projections.
PSRC provided employment projections for its Land Use Targets dataset, which are
based on local growth targets that are aligned with the Vision 2040 Regional
Growth Strategy. This data is divided by TAZ (Traffic Analysis Zone), which is the
smallest delineation of the data made available to the public by PSRC. No similar
data set is available for the Land Use Baseline data. The long-term horizon for
these projections varies by city, since they were based on each City's
comprehensive planning period. For the City of Renton, year 2035 was the longest-
term projection.
To allocate this population data to the future sewer mini-basins, we divided the
populations for each TAZ into the mini-basins and using an area percentage of
each mini-basin within the overlapping TAZ. A TAZ may still include multiple basins,
city boundaries, and the UGA boundary in some cases. Each TAZ may also include
areas of varying residential and employment density due to land-use designations.
Because of this, a strict area to population ratio may not be an adequate
representation of the employment population. T h e projections for two of the six
mini-b asins appeared to be reasonable. However, t here were concerns about the
projections for the other four mini-basins. C oncerns and comments for the six mini-
basins, which were presented with the population projections to the City Planning
Department staff, are described below:
• Basin 30C – This basin is located in portions TAZ Zones 325, 324, and 325. The
developable areas within this basin are entirely residential at this time, and
have residential zoning and land use designations. A low or negligible
employment population would be anticipated.
• Basin 32 – Almost this entire basin is located in a portion TAZ Zone 324.
Approximately 50% of the basin has industrial land use designations, while the
rest of the basin is a mixture of urban center, residential and commercial
land-use designations. Much of the TAZ Zone 324 is south of Basin 32, and
includes large areas with Commercial Corridor and Urban Center Downtown
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.8
PLANNING DATA CHAPTER 3
land use designations, where more of the employment population is likely to
be located. Because of this, it appears that the employment projections for
Basin 32 are high.
• Basin 50 – Most of this basin is located in a part of TAZ Zone 323, with a small
portion in Zone 335. The land use designations are Urban Center North,
Industrial, and Commercial Corridor. Although there are commercial and
industrial land use designations outside of Basin 50 for both TAZ zones, the
employment population distribution does not appear to be disproportionate.
• Basin 52 - This basin is located in portions of TAZ Zones 322, 323, 324 and 325.
The land use designations within the basin are residential and industrial. The
area within Basin 325 is not developable. The employment population within
Zone 323 does not appear to be disproportionate. However, the
employment population projections for Zones 322 and 324 appear to be
high, for similar reasons as for Basin 32.
• Basin U3 – This Basin is located within parts of TAZ Zones 327 and 328. The
land use designations within the basin are primarily residential, but there is a
small area of the basin within Zone 322 with a commercial designation. Zone
327 contains a large cross-section of residential and commercial land-use
designations, so it is difficult to assess whether the employment population
projections within Basin U3 are accurate.
• Basin U8 - This basin covers a comparatively small area in relation to the
other basins. It is located within TAZ Zone 328, and the land use designation
is all single-family. Zone 328 included only single family residential land use
designations, so the employment population should be negligible.
The comments and data were reviewed by City of Renton Planning Department
staff, and the population data was accepted.
The 2040 data is considered to be Ultimate built-out population by City Planning
Staff. For hydraulic modeling purposes, most populations assigned to the model
were increased by an additional 25% per the City’s direction, to ensure an
adequate level of conservatism for the Ultimate scenario.
Schools
Since school enrollment projections are not available for 2040, school population
estimates were determined by applying the residential growth rate between 2012
and Ultimate conditions from the surrounding mini-basin. School staffing was
similarly adjusted to compensate for adjustments in school population.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.9
PLANNING DATA CHAPTER 3
POPULATION AND SANITARY SEWAGE FLOW ASSIGNMENT TO MODEL
Population Assignment
I ndividual (per capita) flow rates were assigned to the residential and employment
population, consistent with the flow rate assigned to each Mini-Basin in the original
model, and later adjusted during the dry weather calibration process. Allowances
were made for large concentrations of population or employment. The following
outlines some of the main considerations for the process of population assignment
to the model:
• Population was generally assigned to manholes in four main categories:
residential single-family, residential multifamily, employment
(commercial/industrial, etc.), and schools. Population and employment
numbers for each composite mini-basin were apportioned among each
zoning category to achieve uniform flow distribution.
• Population was generally assigned to most of the nodes in the model.
Population was usually not assigned to the nodes associated with parks/open
space, non-served areas (transmission areas), lift stations, and bends
(population was assigned to Tees); these nodes were separated from the
others and excluded from the population assignments.
• Per the City, typical sewage flows for the residential category are generally
in the 60 to 100 gpcd range (not including I&I). Sewage flows from
multifamily individuals are typically about 2/3 of the flows from single family
individuals.
• Sewage flows for the employment category were generally assumed to be
10 gpcd (not including I&I), unless other information about higher demands
was available or apparent, or as necessary for calibration.
• Sewage flows for the school category were generally assumed to be 10 to 15
gpcd (not including I&I), unless other information about higher demands was
available or apparent. These values were roughly consistent with average
school flow rates from Table 2-4 of Wastewater Engineering by Metcalf and
Eddy (1991).
In areas where the mini-basin boundaries remained constant (no increase in area),
and no significant sewer improvements were added, generally the projected
population was evenly distributed among the existing nodes. Where mini-basin
boundaries expanded for the Ultimate Model, the population was often increased
by 25-50% for the existing manholes, and new area and new projected population
was generally assigned to new manholes or projected single point-loads outside of
and connected to the existing system. These populations were estimated based on
zoning and area.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.10
PLANNING DATA CHAPTER 3
Table 3-1 summarizes the population and area assignments by mini-basin in the
2012 Model and the Ultimate Model. The population was separated into residential
single-family, residential multifamily, employment, and school categories. This
table updated the population assignments provided in the “City of Renton
Hydraulic Model Update – Population Projections” memo dated June 18, 2014.
Determination of Sanitary Sewer Flow Rates
The per capita sanitary sewage flow rates developed during the creation of the
2001 Mouse model were generally used in the 2012 and Ultimate models. A
description of the process for flow rate development is included in the text of the
documentation report. Flows for new catchments within existing basin were initially
assigned the same flows as existing adjacent areas based on development, a nd
adjustments were made during the model dry weather calibration.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.11
PLANNING DATA CHAPTER 3
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.12
Table 3-1
Population Projections by Sewer Mini-Basins:
Values Assigned to 2012 and Ultimate Models
2012 Basin Population Estimates
Ultimate Population Estimates
(2040 Population+25%) Area (acres)
Sewer
Mini-Basin
Single
Family
Multi-
Family Employment Schools
Single
Family
Multi-
Family Employment Schools 2012 Ult % Diff
1 180 82 22 0 554 420 29 0 71.8 71.8 0.0%
2 81 1,303 342 1,041 209 1,608 713 1,367 127.5 134.7 5.7%
3 1,012 1,307 95 0 1,660 1,836 248 0 194.5 194.5 0.0%
4 1,094 49 22 466 2,109 121 160 909 205.2 205.2 0.0%
5 250 1,823 4,126 0 701 2,238 5,633 0 213.9 233.5 9.2%
6 1,513 10 25 0 2,173 14 165 0 224.3 224.3 0.0%
7 1,232 27 67 526 1,936 31 88 822 162.6 162.6 0.0%
8 0 0 2,248 0 0 0 5,310 0 82.1 82.1 0.0%
9 0 0 272 0 0 0 645 0 111.0 111.0 0.0%
10 173 121 537 0 201 65 1,011 0 54.4 54.4 0.0%
11 803 461 1,140 0 1,148 559 2,201 0 163.8 163.8 0.0%
12 23 1,492 458 0 34 1,803 883 0 73.6 73.6 0.0%
13 402 438 698 0 398 498 1,301 0 81.1 81.1 0.0%
14 1,041 401 504 298 1,795 483 1,088 471 206.0 206.0 0.0%
15 110 456 736 1,218 139 576 1,504 1,539 92.3 92.3 0.0%
16 1,077 380 241 0 1,534 481 583 0 177.2 177.2 0.0%
17 545 149 202 0 765 355 379 0 122.7 122.7 0.0%
18 350 209 148 0 408 280 279 0 38.9 38.9 0.0%
19 0 0 1,480 0 0 0 3,496 0 144.4 144.4 0.0%
20 2,390 490 261 0 5,943 549 973 0 309.5 620.7 100.5%
21 1,425 17 59 618 1,998 35 335 871 143.5 176.5 23.0%
22 1,065 1,433 599 1,956 1,690 1,905 2,049 2,815 208.8 208.8 0.0%
23 858 393 52 0 1,228 500 98 0 111.8 111.8 0.0%
24 1,258 136 63 0 1,839 179 109 0 130.5 130.5 0.0%
25 1,583 35 111 0 1,321 90 200 0 179.8 179.8 0.0%
26 2,189 1,440 818 525 3,270 2,228 1,800 795 382.5 382.5 0.0%
27 1,097 62 11 1,135 1,434 86 1,209 1,489 103.0 103.0 0.0%
PLANNING DATA CHAPTER 3
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.13
Table 3-1
Population Projections by Sewer Mini-Basins:
Values Assigned to 2012 and Ultimate Models
2012 Basin Population Estimates
Ultimate Population Estimates
(2040 Population+25%) Area (acres)
28 0 0 5,365 0 0 0 12,673 0 180.0 180.0 0.0%
29 574 120 16 2,265 770 188 44 3,127 85.8 85.8 0.0%
30A 787 835 60 0 941 1,688 139 0 133.6 133.6 0.0%
30B 38 3 0 0 55 63 0 0 4.7 4.7 0.0%
30C 2 324 12 0 95 499 106 0 21.2 21.2 0.0%
32 321 281 105 0 368 328 5,373 0 141.8 141.8 0.0%
33 3,184 11 218 559 4,903 18 398 861 320.6 375.9 17.3%
34 721 227 43 0 1,223 279 75 0 127.9 127.9 0.0%
35 328 224 113 0 438 314 313 0 60.1 60.1 0.0%
36 40 1,376 397 0 41 1,634 854 0 117.2 117.2 0.0%
37 256 352 257 1,159 341 494 451 1,592 69.1 69.1 0.0%
38A 642 253 469 0 808 370 1,091 0 91.2 91.2 0.0%
38B 47 17 2 0 55 63 0 0 16.7 16.7 0.0%
39 508 515 127 0 640 690 329 0 86.0 86.0 0.0%
40 593 87 33 0 776 113 63 0 74.9 74.9 0.0%
41 1,063 94 61 0 1,319 133 116 0 117.3 117.3 0.0%
42 0 0 147 0 0 0 329 0 20.1 20.1 0.0%
43 549 624 7 0 611 1,085 175 0 116.5 116.5 0.0%
44 282 578 487 0 361 835 909 0 127.9 127.9 0.0%
45 20 1,157 2,733 0 133 2,390 5,165 0 158.8 158.8 0.0%
46 1,994 615 679 0 2,431 741 1,469 0 390.0 390.0 0.0%
46
(North) 67 665 21 0 106 1,055 36 0 23.8 23.8 0.0%
47 777 1,496 606 0 1,089 2,628 1,269 0 196.3 196.3 0.0%
48 462 168 6 545 609 243 288 737 60.3 60.3 0.0%
49 12 0 544 0 15 0 1,284 0 71.9 71.9 0.0%
50 4 174 30 0 5 210 1,064 0 162.6 162.6 0.0%
52 597 6 187 0 1,054 5 1,028 0 148.1 148.1 0.0%
54 139 1,066 883 0 446 1,680 1,668 0 252.5 252.5 0.0%
A 4 0 4,975 0 5 571 11,753 0 857.2 857.2 0.0%
B 0 0 2,580 0 85 0 6,046 0 323.3 323.3 0.0%
PLANNING DATA CHAPTER 3
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.14
Table 3-1
Population Projections by Sewer Mini-Basins:
Values Assigned to 2012 and Ultimate Models
2012 Basin Population Estimates
Ultimate Population Estimates
(2040 Population+25%) Area (acres)
CEDAR
02A 302 146 318 0 370 211 599 0 48.6 48.6 0.0%
ESI1003 237 620 7,126 0 255 1,108 14,185 0 403.9 403.9 0.0%
RENT65 561 526 189 0 1,115 811 569 0 178.1 178.1 0.0%
U1 255 8 7 0 1,004 8 16 0 75.5 75.5 0.0%
U2 1,054 56 23 0 2,014 61 51 0 139.0 139.0 0.0%
U3 1,064 63 59 0 1,743 88 303 0 141.7 141.7 0.0%
U4 2,927 10 251 612 4,649 30 614 975 472.0 472.0 0.0%
U5 N/A1 N/A1 N/A1 N/A1 976 75 36 0 N/A1 112.9
U6 1,345 6 32 1,664 4,055 33 544 3,309 219.9 615.2 179.8%
U7 N/A1 N/A1 N/A1 N/A1 1,685 9 96 0 N/A1 173.7
U8 294 0 3 0 496 0 26 0 43.0 43.0 0.0%
U9 68 0 1 905 1,824 0 314 1,305 12.2 212.7 1641.9%
U10 N/A1 N/A1 N/A1 N/A1 2,335 178 64 0 N/A1 354.0
Total 43,869 25,417 44,506 15,492 76,731 37,869 104,414 22,984 10,407.7 12,070.3
1. Basin U5, U7, and U10 are not located within
the existing sewer service area.
PLANNING DATA CHAPTER 3
The same per capita flow rates and diurnal curves were used in both the 2012 and
Ultimate Models for the portions of the system common to both models. These per
capita flow rates were computed as part of the dry weather calibration for the
2012 Model. For population assigned to manholes located in the U-Basins, 100
gallons per person per day was assumed for residential population, and a peaking
factor of 2.0 was globally applied to this flow rate. Twenty (20) gallons per person
per day was assigned for employment population, per direction from the City Staff.
For new schools in the projected service area, 15 gallons per person per day was
assigned to the model. With this methodology, calibrated diurnal curves were
applied to the existing manholes, and an averaged flow rate was applied to
population assigned to new manholes.
Input to Model
Flows for the newly-added portions of sewer system were assigned to new
catchments. Numbering methodology is consistent with the original model
development, and was assigned in sequential order. In cases where portions of the
sewer system were upgraded or re-routed, existing catchment information w as re-
assigned to new manholes.
Area Assignments
For the older portions of the model, area assignments were generally not modified
from the original MOUSE model development. A description of the process for area
assignment is included in the text of the documentation report.
For portions of the 2012 model developed in Mike Urban, the City parcel GIS data
w as overlaid in the model, and catchments were drawn directly over the se
developments. Where the new development included multiple manholes, a
routine in Mike Urban automatically divided the catchments among the manholes
within the development boundary. I f additional manholes were added to a mini-
basin with a constant boundary, the areas of the older surrounding catchments
were reduced.
Areas assigned to the Ultimate Model were generally consistent with the
methodology used for area assignments to the 2012 Model. Additionally, “dummy”
nodes were added to represent future projected growth areas within the proposed
service area boundaries. Large areas (point loads) were added to these dummy
nodes to represent the discharges to the system from future growth. For example,
s everal dummy nodes were used in the portions of the U-Basins where gravity sewer
systems have not yet been constructed.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.15
PLANNING DATA CHAPTER 3
RAINFALL AND EVAPORATION ASSIGNMENTS
Rainfall Assignments
King County developed model basin specific precipitation time series as part of its
2001 I&I study by using Doppler radar to identify the varying precipitation patterns
between rain gauges and factoring the gauge data accordingly. These
precipitation data sets were developed for a 60-year period based from SeaTac
d ata, and spliced with local rain gauge data for the period of time the County flow
monitors were in place, resulting in a specific precipitation data set for each
monitoring basin. Each Model Basin was assigned 60 years of factored data
coupled with two years of more exact measured precipitation data. These rainfall
time series were used in the original MOUSE model analysis, and most of the
subsequent model analyses performed for the City. King County used these time
series for its recent anal ysis, so they were also used for the City’s 2012 models.
For system improvements constructed within the U-Basins, a global I&I assignment
of 1,500 gallons per acre per day was assumed and connected to the model.
Evaporation
Evaporation data was obtained from the historical Puyallup pan evaporation data
record. The data is no longer collected at that location and no other known
sources of evaporation data exist in the area. As a result, historical monthly
averages of the Puyallup data were determined and input to the model. The
County adopted a similar average monthly approach to input evaporation data
into the model. A standard pan evaporation factor of 0.75 has been applied to
the data. King County provided an updated evaporation time series which
extends through 2015.
The rainfall and evaporation assignments assigned to the Ultimate Model were
consistent with those applied to the 2012 Model. This rainfall data included 60-
years of data spliced with two years of more specific rainfall data from King
County’s flow monitoring program. Each model basin had a separate targeted
rainfall assignment which was applied consistently to all of nodes (catchments)
contained within.
External Boundary Flows
Boundary flows enter the City of Renton Sewer Service area at multiple points in the
system. Some of these flows discharge from other sewer systems into the City’s
sewers, while others flow into the King County sewers within the City’s Sewer Service
Area boundary. These boundary flows are described below:
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.16
PLANNING DATA CHAPTER 3
• TUK 015 – This boundary flow discharges through the Tukwila T runkline into the
South I nterceptor on the west side of Mini-Basin A, and includes flows from
King County Model Basins TUK015, TUK002, TUK004, VAL002, and VAL020 in
southwestern King County. There is no direct discharge into City of Renton
facilities. However, these flows can potentially impact the hydraulic grade
line in City sewers tributary to the Tukwila Tr unkline and South Interceptor.
• SINT020 - This boundary flow discharges into the South Interceptor on the
south side of Mini-Basin A, and includes flows from King County Model Basins
SINT020,AUBRN002, ULID066, ULID57C, ULIDN001, ULIDN003, SOO039, KNT035,
KNT036, KNT042, and KNT047 located in south King County. T here is no direct
discharge into City of Renton facilities. However, these flows can potentially
affect the hydraulic grade line in City sewers tributary to the South
Interceptor.
• SOO021 - This boundary flow discharges into the South Renton Interceptor on
the east side of Mini-Basin 5 from the Soos Creek Water and Sewer District,
and includes flows from King County Model Basin SOO021. There is no direct
discharge into City of Renton facilities. However, these flows can potentially
affect the hydraulic grade line in City sewers tributary to the South Renton
Interceptor.
• SOO003 - This boundary flow discharges into the City of Renton facilities on
the south side of Mini-Basin 4 from the Soos Creek Water and Sewer District,
and includes flows from King County Model Basins SOO003. SOOS67,
NSOOS384, SOO051, SOOS62, and SOO011.
• CEDAR039A - This boundary flow discharges into the Cedar River Trunkline to
the southeast of the City sewer s ervice area, and includes flows from King
County Model Basins CEDAR039, CEDAR010, CEDAR011, and CEDAR 012.
There is no direct discharge into City of Renton facilities. However, these
flows can potentially affect the hydraulic grade line in City sewers tributary
to the Cedar River Trunk.
• RNT042 - This boundary flow discharges into the City of Renton facilities on
the north side of Mini-Basin 42 , and includes flows from King County Model
Basin RENT042. Mini-Basin 42 is actually located within King County Model
Basin RENT042. However, the City of Renton sewer service area flows are not
modeled as boundary flows.
• ESI4024 - This boundary flow discharges into the Eastside Interceptor at the
north end of the City Sewer Service area, and includes a tributary area
encompassing Belle vue, Kirkland, and much of the area east of Lake
Washington.
• BLS043B - This boundary flow discharges into the Bryn Mawr Trunkline on the
northwest side of Mini Basin 50, and includes flows from King County Model
Basins BLS007 and BLS43B. There is no direct discharge into City of Renton
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.17
PLANNING DATA CHAPTER 3
facilities. However, these flows can potentially affect the hydraulic grade line
in City sewers tributary to the Bryn Mawr Trunk.
Locations where the boundary flows enter the City of Re nton Sewer Service Area
are included in t he model analysis results, F igure 5 -2 and Figure 5-3 . Methods for
simulating the boundary flows during the calibration and capacity anal ysis are
discussed in Chapter 4 and Chapter 5.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 3.18
CHAPTER 4 MODEL CALIBRATION
Model calibration consists of two primary tasks: sanitary and I&I calibration. It is
important to distinguish between these separate components, to more accurately
simulate future scenario changes in pipe flows related to changing population and
employment as well as assumptions about I&I changes over time. Understanding
the characteristics of these individual components of pipe flow is a key element in
developing the model.
Calibration parameters were generally based on the guidelines found in the 2002
Wastewater Planning Users Group Code of Practice for the Hydraulic Modeling of Sewer
Systems.
The code recommends that sanitary flow verification should be carried out for two dry
weather days and the predicted flows/depths compared to the observed flows/depths.
The two flow hydrographs should closely follow each other both in shape and in
magnitude. In addition to the shape, as a general guide, the flow hydrographs should
meet the following criteria:
• The timing of the peaks and troughs should be within 1 hour.
• The peak flow rate should be in the range ± 10%.
• The volume of flow should be in the range ±10%. Care should be taken to exclude
periods of missing or inaccurate data.
For wet weather calibration, modeled flows/depths should be compared to the observed
flows/depths. The two flow hydrographs should closely follow each other both in shape
and in magnitude, until the flow has substantially returned to dry weather flow rates. In
addition to the shape, as a general guide, the observed and modeled hydrographs should
meet the following criteria in at least two of the three events:
• The timing of the peaks and troughs should be similar inregard to the duration of
the event.
• The peak flow rates at each significant peak should be in the range + 25% to -
15% and should be generally similar throughout the event.
• The volume of flow should be in the range +20% to -10%. Care should be taken to
exclude periods of missing or inaccurate data.
• The depth of surcharge should be in the range +0.5 m to - 0.1 m.
• The unsurcharged depth at any key points, where this is important regarding the
objectives of the model (e.g. at combined sewer overflows), should be within the
range ±100 mm.
Where rainfall induced infiltration is modeled, the use of a single verification period
incorporating a number of rainfall events should be considered instead of a number of
discrete events.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.1
MODEL CALIBRATION CHAPTER 4
For the purposes of this model calibration, for both sanitary and wet weather, peak flow
and volume parameters for the model were verified against the flow monitoring data, as
well as a comparison of general flow patterns and timing of peaks.
2012 MODEL DRY WEATHER CALIBRATION
Sanitary Flow Calibration
Sanitary calibration consists of two primary elements: the total flow produced per
person over a 24-hour (diurnal) period and the definition of how that flow
fluctuates over the same period. This information, combined with the previously
discussed population and employment data, generate the total sanitary flow
simulated in the model.
Prior to determining per capita flow rates and diurnal fluctuations, periods of “dry
weather” flow have to be identified for the County flow monitoring data. A dry
weather period in September 2010 was analyzed for the dry weather calibration.
Since dry weather flow typically includes a component of low level or base I&I, it
must be estimated and subtracted from the total flow, leaving presumably sanitary
flow only. Base I&I values were determined by estimating typical minimum (nightly)
sanitary flow as a percent of average and assuming the balance is base I&I. Base
I&I was assumed to be constant throughout the day.
Residential flow typically varies throughout the day in a different manner than
commercial/industrial sanitary flow. Residential flow generally peaks twice during
the day, while commercial/industrial flow typically increases in the morning, stays
relatively constant during the day, and decreases in the evening. Numerous
exceptions exist to these generalized variations however. Commercial/industrial
flow for example can exhibit all manner of daily variations, depending on the
nature of the business conducted at the location. A thorough understanding of
these businesses is required to accurately simulate the daily fluctuations and
achieve a detailed sanitary flow calibration. It is possible however, to achieve an
accurate calibration by applying the composite diurnal variation recorded at the
flow monitor to both residential and commercial/industrial development
throughout the basin represented by the flow monitor. Lacking extensive
knowledge of commercial/industrial developments and additionally to expedite
the calibration process, this was the method selected to determine the sanitary
flow calibration. This method allows for a quick, accurate calibration, but could
potentially result in misrepresentation of diurnal fluctuations in future scenarios, if
the balance between residential and commercial/industrial populations changes
significantly. The potential shortcomings are considered to be negligible however,
especially since it is difficult to accurately forecast how anticipated additional
commercial/industrial flows will vary in the future.
Dry weather calibration was verified by performing a sanitary flow model
simulation, using the data assigned to the catchments and dry weather flow
entries. External boundary flows were simulated by attaching time series of the
flow monitoring data from the August-September 2010 period. The resulting basin
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.2
MODEL CALIBRATION CHAPTER 4
outlet flows were compared to the County “dry day” flow monitoring data. If the
curve shape generated by the model (Model Output) generally matched the
metered curve shape (Model Input) and the total daily volume was within 10%, the
basin was considered calibrated for sanitary flow. Output graphs of the computed
dry weather flows versus the measured King County flows (excluding the base I&I)
were generated for each mini-basin. The dry calibration resulted in computed
model peak flows and volumes that closely simulated the measured flows in six of
the ele ven locations analyzed. In some cases, including RNT41, RNT43, and
SRENT002, the modeled peaks and volumes were much higher than the recorded
flows. However, in these basins, the modeled peak per capita flow rates were
already low based on population and land use. These were not adjusted further to
match the flow monitoring data. Some of the discrepancy in overall volume in
these basins is due to significant “noise”, or small peaks, in the flow monitoring
data, in addition to the per capita flow rate assumptions. T he model output is
much smoother, which leads to significant differences in volume. Because of this,
the overall shape of the model output was compared against the flow monitoring
data. We were generally more focused on closely simulating the peak dry weather
flows rather than the volumes, to be conservative, and also due to the “noise” and
drop-outs in the flow monitoring results. Overall, the shape and timing of the
patterns adequately matches the flow monitoring data.
Flow monitoring data was not available for the boundary flows at SINT020 and
BLS043, so constant dry weather flows were estimated. These two boundary flows
do not flow through City sewers, so the impact to the dry weather calibration is
negligible.
A number of model basins were not calibrated with 2010 flow monitoring data, a s
are noted in the next section in Table 4-4 . For those, the per capita flow rates from
the original model calibration were maintained in this model. T h e basins that were
calibrated as part of this project were calibrated in 2015, while the others were
calibrated in 2005.
T h e calibration for RNT030B and RNT047 were only partially successful. Since RNT035
is upstream of both RNT030B, and could not be recalibrated, it was difficult to
adjust the dry weather flow parameters within RNT035. There were similar difficulties
with RNT047.
A dry weather calibration summary is provided in Table 4-1 . The summary lists the
percentage deviation of the calibration model results from the flow monitoring
data for peak flow and total volume of flow over the duration of the analysis.
Annotated plots of the dry weather calibration time series are provided in the
A ppendix A .
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.3
MODEL CALIBRATION CHAPTER 4
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.4
Table 4-1
Dry Weather Calibration Summary
Model
Basin
Pipe
Diameter
(in)
September 1, 2010 to September 8, 2010
Peak Flow (%) Volume (%)
RNT017 15 -1.8% -4.7%
RNT023 8 10.5% 6.0%
RNT025 12 4.4% 6.4%
RNT028 24 -9.1% -0.9%
RNT030A 21 -9.4% 11.3%
RNT030B 18 27.1% 23.9%
RNT041 8 26.3% 96.6%
RNT043 8 15.0% 54.6%
RNT047 24 27.0% 58.2%
RENT65 20 6.1% 12.2%
SRENT002 36 19.6% 45.6%
Peak weekday per capita flow rates for residential, employment and school
populations in each mini basin are provided in Tabl e 4-2. Employment flow rates for
Mini-Basins 9 and 11 greatly exceed the flow rates in other basins. These were
calibrated in 2005. Flow monitoring data was not av ailable to re-calibrate these
Mini-basins in 2015.
MODEL CALIBRATION CHAPTER 4
Table 4-2
Per Capita Flow Rate (ft2 /PE/day)
Sewer
Mini-Basin Residential Employment Schools
Calibration
Year(1)
1 13.77 N/A N/A 2015
2 10.49 1.34 2.01 2015
3 12.21 N/A N/A 2015
4 13.37 N/A 1.34 2015
5 10.69 N/A N/A 2015
6 10.69 2.67 N/A 2015
7 10.45 1.34 1.34 2015
8 14.20 N/A N/A 2005
9 N/A 21.05 N/A 2005
10 8.71 1.34 N/A 2005
11 13.37 69.35 N/A 2005
12 13.37 2.12 N/A 2005
13 10.87 1.34 N/A 2005
14 10.69 5.85 2.01 2005
15 13.37 2.55 2.01 2005
16 8.69 1.34 N/A 2005
17 10.23 1.34 N/A 2015
18 8.86 1.34 N/A 2005
19 N/A 5.24 N/A 2015
20 6.31 1.34 N/A 2015
21 12.88 N/A 1.34 2015
22 7.13 1.34 1.00 2015
23 12.17 1.34 1.34 2015
24 8.60 1.34 N/A 2015
25 8.02 1.34 N/A 2015
26 10.51 1.34 1.34 2005
27 8.02 1.34 1.33 2015
28 N/A 3.80 N/A 2005
29 9.80 1.34 1.34 2015
30A 9.36 1.34 N/A 2015
30B N/A 1.34 N/A 2015
30C 9.36 1.34 N/A 2015*
32 11.53 1.34 1.34 2005
33 11.34 1.34 1.34 2015
34 12.03 1.34 N/A 2015
35 10.69 2.70 N/A 2015
36 11.18 1.34 N/A 2015
37 10.23 1.34 1.34 2015
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.5
MODEL CALIBRATION CHAPTER 4
Table 4-2
Per Capita Flow Rate (ft2 /PE/day)
Sewer
Mini-Basin Residential Employment Schools
Calibration
Year(1)
38A 9.36 1.34 N/A 2015
38B 9.36 1.34 N/A 2015
39 12.67 1.34 N/A 2015
40 8.25 1.34 N/A 2005
41 10.14 1.34 N/A 2015
42 N/A 2.67 N/A 2005
43 1.34 9.90 N/A 2015
44 9.36 1.34 N/A 2005
45 8.25 1.37 N/A 2015
46 9.36 1.34 N/A 2005
47 8.06 0.67 N/A 2015
48 9.84 1.34 1.00 2015
49 0.67 8.06 N/A 2015
50 N/A 3.23 N/A 2005
52 10.56 1.34 N/A 2005
54 12.17 2.67 N/A 2005
A N/A 2.67 N/A 2005**
B N/A 2.67 N/A 2005**
CEDAR02A 10.69 2.67 N/A 2005
ESI1003 10.69 2.67 N/A 2005
RENT65 15.33 N/A N/A 2015
(1) Per capita flow rates determined in the 2005 dry weather calibration were set using DWF at the Mini-Basin level.
Those modified in the 2015 calibration were set at the model basin level.
* Basin 30C was calibrated with Basin 30A.
** Per capita flow rates for Basins A and B were not calibrated. During the 2005 model development, standard per
capita flow rates based on land use were assigned, and diurnal curves from adjacent basins with similar land use
were assigned.
2012 MODEL WET WEATHER CALIBRATION
Infiltration and Inflow Calibration
Infiltration and inflow is represented in the Mike Urban model as two individual
components. The fast response component (FRC) is characterized by a rapid
increase in pipe flow corresponding to a rainfall event. The rapid increase results in
a sharp peak and is followed by a rapid decrease in flow. This type of flow
typically comes from a direct hydraulic connection between an impervious or
nearly impervious surface and the piping system. The slow response component
(SRC) is characterized by a somewhat delayed response to a rainfall event, a
smaller, broader peak and a relatively slower decrease in pipe flow. SRC flow is
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.6
MODEL CALIBRATION CHAPTER 4
generated from overland flow, near surface and groundwater intrusion into the
piping system. SRC flow includes base I&I.
Mike Urban contains a choice of multiple options or models for generating I&I.
Given the wealth of flow monitoring and precipitation data, it was decided to use
the more complex RDII module to generate the SRC, consistent with the
methodology employed by King County, and that used in the original MOUSE
model development. The RDII module requires calibration to a number of
parameter values that govern the algorithms defining the hydrologic process and
the resulting potential inflow into the sewer collection system. When properly
calibrated, the RDII module provides the best overall representation of the SRC.
The FRC was generated using the “A” model, with simplified algorithms governing
the timing, shape and volume of the hydrologic response.
The I&I calibration involved identification of parameter values for the SRC
component (after sanitary calibration was completed) then development of the
FRC component parameters, which essentially “finish off” the hydrographs. The
County’s 2008 through 2011 flow monitoring data was used for I&I calibration.
There were a few significant storms over this period, including the December 1 2 /1 3 ,
2010 storm, which produced a rainfall of approximately 2.5 inches over a 24-hour
period, which is equivalent to a 1 0 -year storm, based on King County Drainage
Manual rainfall isopluvials.
External boundary flows were simulated by attaching time series of the flow
monitoring data from the December 12/13, 2010 storm. Other peak flow events
were also considered. However, this was the only one were usable flow monitoring
data was available for most of the model basins. As with the dry weather
calibration, flow monitoring data was not available for the boundary flows at
SINT020 and BLS043, so constant wet weather flows were estimated and assigned.
Mike Urban RDII parameters are typically adjusted to match base I&I first, then
peak flows resulting from rainfall events. Possibly the most important parameter
controlling base I&I is the percent of total basin area contributing to pipe flow. A
high base I&I, for example, can be simulated in the model by assuming a relatively
high contributing area percentage, then adjusting additional parameter values to
contribute a higher percentage of runoff to base flow versus surface runoff.
A wet weather calibration summary is provided in Table 4-3 . The summary lists the
percentage deviation between the model results and the flow monitoring data for
peak flow and total volume of flow over the duration of the analysis. Six of the
eleven model basins met standards for volume. The calibration for volume for
RNT028 and RNT043 was not as successful, deviating from acceptable standards by
approximately 5%. The volume deviation is significantly greater for RNT017. As with
the dry weather calibration, t his is due to significant “noise” in the flow monitoring
data. RNT017 especially contains a lot of small peaks, whereas the model output is
much smoother. This contributes to the large discrepancy in volume. Because of
this, the overall shape of the model output RNT017, RNT028, and RNT043 was
compared against the flow monitoring data. Overall, the shape and timing of the
patterns matches the flow monitoring data. T h e flow monitor for RENT65 failed
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.7
MODEL CALIBRATION CHAPTER 4
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.8
Table 4-3
Wet Weather Calibration Summary
Model Basin Pipe
Diameter
(in)
December 10, 2010 to December 18, 2010
Peak Flow (%) Volume (%)
RNT017 15 3.0% 48.5%
RNT023 8 2.9% 17.8%
RNT025 12 1.2% 31.4%
RNT028 24 -4.0% -16.1%
RNT030A 21 -6.9% 9.9%
RNT030B 18 4.7% 7.2%
RNT041 8 -6.5% -10.7%
RNT043 8 9.4% 26.9%
RNT047 24 -9.7% -11.1%
RENT65 20 N/A N/A
SRENT002 36 5.7% 4.5%
Annotated plots of the wet weather calibration time series are provided in the
Appendix B.
Non-Calibrated Model Basins
Several of the King County model basins had complic ations including faulty or
missing flow-monitoring data, and inconsistent dry weather flow. Table 4-4 identifies
the City mini-basins that were not calibrated for dry and wet weather, with a brief
explanation for each:
MODEL CALIBRATION CHAPTER 4
Table 4 -4
City Mini-Basins Not Calibrated for Dry and Wet Weather
Model
Basin
Mini-Basins Reason Not Calibrated
19 19 Errant dry and wet weather flow monitor data,
impossible to calibrate
45 1,3,7,35 Wet weather calibration not possible due to faulty
flow monitoring data
35 20,21,22,35 Wet weather calibration not possible due to faulty
flow monitoring data
Cedar02A Cedar02A, 46 Errant dry and wet weather flow monitor data,
impossible to calibrate
ESI1006 8,9,11,12,
13,14,15,16,32,49,50,54,
ESI1003
Large geographic area. Could not isolate from
upstream flow. Calibration not performed.
For the above-listed mini-basins, since wet weather calibration was not attainable,
the RDII parameters from the original model calibration were maintained in this
model, with minor adjustments to address increased I/I due to pipe degradation.
Ultimate Model Inflow and Infiltration Parameters
The calibrated I&I parameters used for the 2012 Model were applied to the
Ultimate Model for the calibrated portion of model (sewer system constructed prior
to mid-2002), except that the I&I was globally increased per King County’s previous
methodology, which assumes a 7.0% increase per decade, to a maximum
degradation of 28.0% for Ultimate conditions. The ramifications of the system
degradation-related I&I assumptions are discussed further in this report. For system
improvements constructed for the Ultimate model, a global I&I assignment of 1500
gallons per acre per day was assumed and connected to the model.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 4.9
CHAPTER 5 ANALYSIS AND RESULTS
2012 MODEL PEAK FLOW AND CAPACITY ANALYSIS
External Boundary Flows
In order to model in flows into the County’s piping systems within the approximate
City limits, discharge time series for the peak storms were developed from the
County’s 2012 I/I study MOUSE output, and assigned at upstream locations in the
King County interceptors. For the boundary flows from SOO003 and RNT042, where
output model data was not available, peak 20-year design inflows were assigned
as constant inflow conditions. Although use of the County model output better
simulates flows from upstream areas within the County system, variations between
the King County Model and the Renton model contributed to some surcharging
and capacity issues in portions of the system not shown in the County’s results.
Peak Storm
For the prior analysis, the County provided a chart ranking the six highest peak
flow-generating storm events within each model basin in the vicinity of the City.
The peak storm events were determined by the County by routing 60 years of
rainfall data through the County’s calibrated model. The storms identified on the
chart were assumed to roughly correspond (in decreasing ranking) to the 60, 30,
20, 15, 12, and 10-year design flow events.
Of the eleven model basins within the City boundaries, the County identified nine
different storm events which generated the 20-year peak flows (third-ranked peak
flow generating events) for the basins. Rather than running the model nine
separate times to capture all of the 20-year events, four separate storm events
were selected to generate the either the 20-year or 30-year peak flow rates for all
eleven model basins. This simplified methodology was acceptable to the City staff.
The selected rainfall events are summarized in Table 5-1 below by model basin.
Although King County modified some of its model basin boundaries for it 2012 I/I
analysis, for the purposes of the City of Renton models, the original model basin
boundaries developed for the 2001 I/I study were applied to the 2012 analysis.
Figure 5-1 shows the selected storm events for each model basin.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.1
Chapter 5 ANALYSIS & RESULTS
Figure 5.1
Selected Storm Events Per Model-Basin
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.2
Chapter 5 ANALYSIS & RESULTS
Table 5-1
Selected Storm Events Per Model Basin
Model Basin
Storm Event
Modeled
Recurrence Interval
Peak Flow
CEDAR02A November 24, 1990 30-Year
ESI1006 February 8, 1996 30-Year
RNT023 January 9, 1990 30-Year
RNT030 February 8, 1996 20-Year
RNT035 November 24, 1990 30-Year
RNT042 January 9, 1990 20-Year
RNT045 November 4, 1998 20-Year
RNT054 February 8, 1996 20-Year
RENT65 January 9, 1990 30-Year
SINT001 February 8, 1996 30-Year
SRENT002 November 24, 1990 30-Year
In addition to the assignments listed in the table above, there were four mini-basins
not calibrated by King County, and not included with the model basins (Mini-Basins
RNT08, RNT09, A, and portions of Mini-Basin B), all of which are independently
tributary to King County interceptors near the treatment plant. All four of these
mini-basins were in the proximity of Model Basins ESI1003 and SINT001, and were
similarly assigned the February 8, 1996 storm event.
Analysis Results
Figure 5-2 displays the overall modeled system with pipes color-coded by peak
flows divided by maximum capacity (Q/Full) based on Manning’s equation for the
model analysis period. The map was color-coded as listed below:
Peak Q/full Color
0.0 to 0.6 Gray
0.6 to 0.8 Blue
0.8 to 1.0 Green
1.0 to 1.2 Orange
Greater than 1.2 Red
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.3
ANALYSIS & RESULTS Chapter 5
All pipes with ratios greater than 0.8 are considered to be exceeding their
capacity. Pipes colored blue indicate pipes that are close to but not exceeding
this capacity standard. The map has individual areas with capacity problems
identified. The problem areas were labeled based on mini-basins within the City.
For example, if Mini-Basin 65 has two problem areas, they would be identified as
65A and 65B, respectively. Only City piping was identified in the problem areas.
Areas where County piping exceeded 0.8 were not labeled.
Problem areas were classified by the degree of surcharging and summarized in
Table 5-2 , which is arranged by profile and includes a location des cription, the
duration of surcharging above the crown of the pipe (where applicable), the
duration of surcharging above manhole rims (where applicable), a brief listing of
the suspected cause of the problem or any special conditions, and a ranking of
the severity of the problem. The surcharging issues are ranked as Minor, Moderate,
or Severe. Minor problems were classified as pipes with insignificant to no
surcharging (often in the 0.8 to 1.0 Q/Q F ull category). Moderate problems
represent areas with surcharging to more significant levels or durations, but
contained within the sewer system. Severe problems represent areas with
significant surcharging heights and durations and any areas with where the flow
overtops the manholes. Figures 5-2A to 5-2S (which are referenced in the Table)
are included in Appendix C , and provide zoomed-in views of the problem areas
s h own in Figure 5-2.
Attaching constant peak inflows for the boundary flows was conservative, as
mentioned above. The constant inflows caused the discharge in some of the mini-
basins to look non-standard, including Mini-Basins 4, 42, 46, and 65. For each of
these mini-basins, the incoming constant peak boundary flow dominates the local
flows, such that the peaks caused by the individual mini-basins do not appear to
contribute as significantly to the total flow as may appear at some of the other
mini-basins. Additionally, Mini-Basin 50 has severe surcharging issues in the King
County trunk sewer, which significantly influences flows in the downstream system.
The County has indicated it is aware of the capacity issues and is working to
resolve them.
A table and figures detailing the discharge at the outlet of each mini-basin are
summarized in the next section in Table 5-3 , along with the output from the Ultimate
Model.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.4
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
04A MH2795 MH2790 January 9, 1990 Minor 4 4 1083'-24" Entire run 0 0.5' Includes
upstream flows
from SCWSD.
Pipe nearing
capacity.
Backwater due
to downstream
capacity issues.
MH2790 MH2819 Minor 4 4 1140'-24" Entire run 0 0.5' Includes
upstream flows
from SCWSD.
Minor capacity
issues due to
pipe size.
Location: See Figure 5 -2A. Index Ct SE south of SE 16th St, off-road easement from Index Ct SE to Kirkland Ave SE to Beacon Way ROW.
05A MH2998 RE*SRENT.R18-19 November 24, 1990 Severe 5 3 807'-8" 15 14 5' Capacity issues
due to pipe
size, backwater
due to sharp
bend at
MH2996,
MH2997
Location: See Figure 5-2B. Shattuck Ave S north of S 37th St near Talbot Rd S.
05B MH3217 RE*SRENT.R18-25 November 24, 1990 Moderate 5 2 672'-8" 4 0 1.5' Capacity issues
due to pipe
size.
Location: See Figure 5-2B. Talbot Road S between SE Carr Rd and S 177th St.
05C MH3198 MH5523 November 24, 1990 Severe 5 9 1645'-8" 8 0 10' Capacity issues
due to pipe
size, backwater
due to sharp
bend at
MH3193,
MH3194.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.5
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
MH5519 RE*SRENT.R18-17 November 24, 1990 Moderate 5 3 902'-12" 11 0 1.5' Capacity issues
due to pipe
size.
Location: See Figure 5-2B. Davis Ave S off of S 43rd St near Talbot Rd S, and north through off-road easement towards S 37th St.
5D MH3205 MH3198 November 24, 1990 Minor/
Severe
5 2 474'-8" 7 0 9' Pipe nearing
capacity.
Severe
surcharging
due to
backwater in
DS system.
Location: See Figure 5-2B. Off-road easement south of Davis Ave S off of S 43rd St near Talbot Road S.
06A MH3016 MH3004 November 24, 1990 Severe 6 7 2166'-8" 10 1 8' Capacity issues
due to pipe
size, backwater
d ue to sharp
bend at
MH3004,
MH3009.
Location: See Figure 5-2C. Talbot Road S from S 27th Pl south toward 32nd St and off-road easement west of Talbot Rd S.
07A MH2479 MMH2257 November 4, 1998 Moderate 7 6 1551'-12" 1 0 4' Minor capacity
issues due to
pipe size,
bends. Minor
surcharging
from capacity
problems in DS
system.
Location: See Figure 5-2D. S 14th St from Shattuck Ave S to Smithers Ave S.
07B MH2270 MH2269 November 4, 1998 Minor 7 1 338'-8" 0 0 0' Pipe nearing
capacity.
Location: See Figure 5 -2D. S 14th St from S 15th St and north on S 14th St toward Shattuck Ave S.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.6
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
11A MH3522 MH5360 February 8, 1996 Minor 11 1 180'-12" 5 0 0.5' Capacity issues
due to pipe
size, backwater
due to bend at
MH5360.
MH1903 MH2170 February 8, 1996 Moderate 11 3 892'-12" 8 0 2' Capacity issues
due to pipe
size, backwater
due to multiple
bends.
Location: See Figure 5-2E. S 5th St between Wells Ave S and Main Ave S, from S Grady Way across Williams Ave S to Burnett Ave S.
11B MH1940 MH1939 February 8, 1996 Minor/
Moderate
11 1 249'-10" 8 0 1.5' Pipes
nearing/slightly
over capacity.
Surcharging
due to capacity
problems in DS
system.
Location: See Figure 5-2E. Williams Ave S north of S Grady Way and south of S 5th St.
14A MH2183 MH0066 February 8, 1996 Severe 14 5 1284'-12" 27 0 4' Minor capacity
issues due to
pipe size and
slope, bends.
Severe
surcharging
from capacity
problems in DS
system.
Location: See Figure 5-2F. Off-road easement from the intersection of Rainier Ave S, SW Sunset Blvd, and S 3rd St and north through private property and along S 2nd St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.7
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
15A MH2115 KC2790 February 8, 1996 Minor/
Severe
15 6 1252'-15" 16 0 2.5' Minor capacity
issues due to
pipe size and
bends. Severe
surcharging
from capacity
problems in DS
East Side
Interceptor.
Location: See Figure 5-2F. S Tobin Street from Shattuck Ave S to Logan Ave S.
15B MH5330 MH2115 February 8, 1996 Minor/
Severe
15 5 926'-15" 34 0 3' Pipe nearing
capacity.
Severe
surcharging
from capacity
problems in DS
Renton sewer
and East Side
Interceptor.
Location: See Figure 5-2F. Off-road easement from S Tobin St to S 2nd St.
15C MH5209 MH2147 February 8, 1996 Minor 15 3 656'-8" 0 0 0' Negligible
capacity issues
due to pipe
size.
Location: See Figure 5-2F. Easement along S 2nd St between Rainier Ave S and Shattuck Ave.
16A MH5398 MH5395 February 8, 1996 Minor 16 2 340'-8" 16 0 2' Pipe nearing
capacity.
Backwater due
to capacity
issues in DS
system.
MH5395 MH2111 February 8, 1996 Severe 16 1 417'-8" 16 0 2' Capacity issues
due to pipe
size.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.8
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
Location: See Figure 5-2F. Renton Ave Ext from Hayes Pl SW to Rainier Ave S, Rainier Ave S from Renton Ave Ext/Airport Way to S Tobin St.
21A MH3547 MH3582 November 24, 1990 Minor 21 5 1141'-8" 0 0 0' Pipe nearing
capacity.
NH3582 MH3587 November 24, 1990 Minor/
Severe
21 5 890'-8" 8 0 3' Pipe nearing
capacity.
Surcharging
due to capacity
problems in DS
system.
Location: See Figure 5-2G. Anacortes Ave NE from NE 23rd Ct to NE 17th St.
21B MH3587 MH5504 November 24, 1990 Moderate 21 3 5 18'-8" 9 0 3' Capacity issues
due to pipe
size.
Location: See Figure 5-2G. NE 17th St east of Anacortes Ave NE.
22A MH3614 MH3615 November 24, 1990 Minor 22 1 118'-12" 0 0 0' Pipe nearing
capacity for
short duration.
No surcharging.
MH3622 MH3624 November 24, 1990 Minor 22 1 172'-12" 0 0 0' Pipe at
capacity for
short duration.
No surcharging.
Location: See Figure 5-2G. NE Sunset Blvd from unnamed Access Road east toward Duvall Ave NE.
23A MH3498 MH3497 January 9, 1990 Severe 23 1 400'-8" Entire run 0 0 -6.5' Capacity issues
due to pipe
size. Surcharge
is intermittent
over entre run.
Typically 0'-
2.5;. Peak
surcharge for 7
hours.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.9
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
Location: See Figure 5-2H. N 28th Pl between Burnett Ave N and Meadow Ave N.
23B MH0495 MH0383 January 9, 1990 Moderate 23 2 49'-8", 251'-12" 115 0 1' Capacity issues
due to pipe
size. Surcharge
is intermittent
over entire run.
Typically 0'-1'.
Peak surcharge
for 6 hours.
Location: See Figure 5-2H. Lake Washington Blvd N between Burnett Ave N and N 20th St.
25A MH1177 MH1158 November 24, 1990 Severe 25,46 5 315'-10", 651'-12" 8 3 3' Moderate
capacity issues
due to pipe
size, backwater
due to sharp
bend at
MH1773,
MH1772. Severe
surcharging
from capacity
problems in DS
system.
Location: See Figure 5-2I. Off-road easement north of SE 5th St between Newport Ave SE and Pierce Ave SE, Pierce Ave SE from SE 5th St to SE 6th St.
25B MH1172 MH1175 November 24, 1990 Moderate 25 3 653'-10" 12 0 2' Capacity issues
due to pipe
size, backwater
due to sharp
bend at
MH1174.
Location: See Figure 5-2I. Off-road easement south of Sunnydale Mobile Home Park Access Rd west of Union Ave SE.
25C MH1660 MH1663 November 24, 1990 Minor 25 3 1285'-10" 12 0 0 Pipe nearing
capacity.
MH1651 MH1650 November 24, 1990 Minor 25 1 310'-10" 12 0 0 Pipe nearing
capacity.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.10
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
Location: See Figure 5-2I. SE 4th St from Chelan Ave SE to Union Ave SE, south on Union Ave SE from SE 4th St.
25D MH1695 MH1673 November 24, 1990 Minor 25 2 475'-8" 2 0 0.5 Pipe nearing
capacity.
Surcharging
due to bend at
MH 1672,
capacity issues
in DS system.
MH1672 MH1660 November 24, 1990 Minor 25 2 506'-8" 9 0 0.6' Capacity issues
due to pipe
size, backwater
due to sharp
bends at
MH1660.
Location: See Figure 5-2I. From Bremerton Ave SE through easement to SE 2nd Pl north of SE 3rd Pl.
26A MH1506 MH1741 November 24, 1990 Minor 26 7 78'-8", 1322'-12" 0 0 0 Pipe nearing
capacity.
Location: See Figure 5-2J. Duvall Ave NE from NE 4th St to NE 6th St.
27A MH1114 MH1112 February 8, 1996 Minor 27 2 594'-8" 0 0 0 Pipes at
capacity for
short duration.
Negligible
surcharging.
MH1107 MH1102 February 8, 1996 Minor 27 1 307'-8" 0 0 0 Pipe at
capacity for
short duration.
Negligible
surcharging.
Location: See Figure 5-2K. NE 7th Pl from NE 6th Pl to Monroe Ave NE, off-road easement from NE 6th Pl to Jefferson Ave NE.
28A MH5350 MH2548 February 8, 1996 Minor 28 1 301'-15" 0 0 0 Pipe nearing
capacity.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.11
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
MH2537 MH2536 February 8, 1996 Minor 28 1 281'-18" 0 0 0 Pipe nearing
capacity.
Location: See Figure 5-2L. Lind Ave SW between SW 19th St and SW 16th St, SW 16th St from Lind Ave SW toward Seneca Ave SW.
33A MH0518 MH0394 January 9, 1990 Minor 33 1 87'-8" 0 0 0 Pipe at
capacity for
short duration.
Location: See Figure 5-2H. Easement parallel to I-405 and Jones Ave NE south of NE 28th St.
36A MH0805 MH0812 February 8, 1996 Moderate/
Severe
36 3 696'-8" 9 0 4' Moderate
capacity issues
due to pipe
size.
MH0813 MH0467 February 8, 1996 Moderate 36 2 377'-8" 7 0 4' Minor capacity
issues due to
pipe size.
Severe
surcharging
from capacity
problems in DS
system.
Location: See Figure 5-2M. Harrington Ave NE from NE 12th St to NE Sunset Blvd.
36B MH6006 MH0909 February 8, 1996 Moderate 36 1 388'-8" 1 0 0 Minor capacity
issues due to
pipe size.
Negligible
surcharging.
Location: See Figure 5-2M. Kirkland Ave NE north of NE 12th St.
38A-1 MH0467 MH0470 February 8, 1996 Moderate 38 4 287'-8" 17 0 3' Capacity issues
due to pipe
size.
Location: See Figure 5-2M. Harrington Ave NE between Glennwood Ave NE and Sunset Blvd NE.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.12
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
39A MH6043 MH0826 February 8, 1996 Minor
/Severe
37,39 4 512'-8" 4 0 2.5' Pipe nearing
capacity.
Backwater due
to capacity
issues in DS
system.
MH0826 MH0825 February 8, 1996 Moderate 39 299'-8" 36 0 3' Capacity issues
due to pipe
s ize.
Location: See Figure 5-2M. Edmonds Ave NE from NE 9th St and north toward Sunset Blvd NE.
41A MH3327 MH3510 February 8, 1996 Severe 41 6 727'-8", 328'-10" 9 2 5' Minor to severe
capacity issues
due to pipe
size.
Location: See Figure 5-2N. Lake Washington Blvd N between N 33rd Pl and N 37th St.
45A MH2257 MH2252 November 4, 1998 Minor 45 5 1532'-18" 1 0 1' Capacity issues
due to pipe
size.
Location: See Figure 5-2D. Off-road easement between S Renton Village Pl to S Grady Way.
46A MH1158 RE*CEDAR2.R10-26A November 24, 1990 Moderate 46 14 2620'-15" 10 0 1.5' Pipe nearing
capacity,
surcharging in
DS portion do to
water levels in
Cedar River
Trunk,
backwater due
to multiple
bends.
Location: See Figure 5-2O. SE 6th St between SE 5th St and Pierce Ave SE.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.13
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
47A MH4692 RE*CEDAR1.R10-05A November 24, 1990 Minor 47 8 155'-12". 660'-22",
760'-24"
36 0 1 Pipe nearing
capacity.
Surcharging
from capacity
problems in DS
Cedar River
Trunk.
Location: See Figure 5-2P. N 4th St west of I-405.
4 7B MH0639 MH0627 November 24, 1990 Moderate/
Severe
47 4 129'-6", 459'-8" 11 4 7 Capacity issues
due to pipe
size.
Location: See Figure 5-2P. Bronson Way NE between Grandley Way NE and Windsor Way NE.
47C MH1976 MH1975 November 24, 1990 Minor 47 1 310'-8" 6 0 0.5 Minor capacity
issues due to
pipe size.
Location: See Figure 5-2P. NE 4th St between Brighton Ridge Apartments Access Rd and Edmonds Ave SE.
48A MH0847 MH1360 February 8, 1996 Severe 48 2 360'-8" 162 0 13' Capacity issues
due to pipe
size.
Location: See Figure 5-2P. NE 7th St between Ferndale Pl NE and Harrington Ave NE.
50A MH0418 MH420 February 8, 1996 Minor 50 2 460'-8" 5 0 1' Capacity issues
due to pipe
size. Minor
surcharging
due to capacity
problems in DS
Bryn Mawr
Interceptor.
Location: See Figure 5-2Q. Easement along Cedar River south of N 6th St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.14
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
65A MH2818 MH2760 January 9, 1990 Minor 4,65 3 517'-24" Entire run 0 0 Includes
upstream flows
from SCWSD.
Pipe at
capacity.
Location: See Figure 5-2A. SE 16th St from Index Ct SE to Index Ave SE.
65B MH5300 MH5302 January 9, 1990 Minor/
Severe
65 1 500'-20" 0 0 0 Pipe nearing
capacity.
Includes
upstream flows
from SCWSD.
Location: See Figure 5-2A. Off-road easement north of Royal Hills Dr SE and east of Harrington Pl SE.
ESI1003A MH1923 MH1921 February 8, 1996 Minor ESI1003 3 674'-8" 0 0 0 Full pipe for
short duration.
Location: See Figure 5-2Q. Wells Alle y N from N 1st St to N 3rd St.
A1 MH0216 KC1735 February 8, 1996 Minor A 6 837'-15", 70'-16" 7 0 0.5 Minor capacity
issues due to
pipe slope.
Minor
surcharging in
DS East Side
Interceptor.
Location: See Figure 5-2L. Off-road easement between SW Grady Way and I-405 parallel to Oakesdale Ave SW.
A2 MH6188 MH6191 February 8, 1996 Minor A 3 1175'-8" 2 0 0.5' Minor capacity
issues due to
pipe size.
Surcharging
due to bend at
MH6190.
Location: See Figure 5-2R. Off-road easement between Oaksdale Ave SW and SW 39th St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.15
ANALYSIS & RESULTS Chapter 5
Table 5-2
Capacity Analysis for 2012 Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
A3 MH0275 MH0286 February 8, 1996 Severe A 13 396'-8", 2000'-10" 32 5 11' Severe
capacity issues
due to pipe
size. Minor
surcharging
due to capacity
problems in DS
South
Interceptor.
Location: See Figure 5-2R. Off-road easement between Oaksdale Ave SW and Interurban Trail north of S 180th St.
B1 MH5190 MH2982 February 8, 1996 Minor/
Moderate
B 2 489'-8" 3 0 0.5 Minor capacity
issues due to
pipe size.
Location: See Figure 5-2R. SW 34th St from Lind Ave SW to East Valley Road.
B2 MH3173 RE*SRENTON.R18-05 February 8, 1996 Minor B 2 245'-8" 1 0 0 Minor capacity
issues due to
pipe size.
Negligible
surcharging.
Location: See Figure 5-2R. 84th Ave S from SW 43rd St towards SW 41st St.
U6A MH4717 MH4713 N/A Minor U6 3 587'-8" Intermittent
entire run
0 0 Negligible
intermittent
surcharging
due to LS 34
(Liberty). Model
contains
constant flow
rate inputs for
U -Basins.
Location: See Figure 5-2S. SE 137th Terrace from 160th Ave SE to 161st Pl SE, 161st Pl SE south from SE 137th Terrace.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.16
ANALYSIS & RESULTS Chapter 5
ULTIMATE MODEL PEAK FLOW AND CAPACITY ANALYSIS
Peak Storm
The peak storm rainfall events assigned to the 2012 Model were assigned to the
U l timate model using the same methodology.
The County did not conduct hydraulic modeling for its future development
scenarios. Instead, it determined the 20-year peak flows for locations within its
sewer system, and appl ied a growth factor to determine to 20-year peak flows at
10-year intervals. So to use the boundary time series developed for the 2012
analysis for the external boundary flows, the flow rates were multiplied by a fact or
based on a ratio of the County’s 2010 and 2060 20-year peak flow rates. As with
the 2012 model, 20-year constant peak flow rates were assigned at the other
locations. This conservative assumption contributed to surcharging and capacity
issues in portions of the system.
Analysis Results
Table 5-3 summarizes the peak flow at the outlet from each mini-basin and the
corresponding storm events from the 2012 and Ultimate Model analysis. For some
of the mini-basins, the peak flow from the 2012 Model exceeds the peak flow from
the Ultimate Model, or does not significantly increase for the Ultimate Model. In
some of these cases, changes in the sewer system or assumptions rerouted or
decreased flow to certain mini-basins.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.17
ANALYSIS & RESULTS
Table 5-3
City of Renton Sewer Model - 2012 and Ultimate Peak Flow at Mini-
Basin Outlet, Including Storm Event
Mini- 2012 Peak Flow
Ultimate
Peak Flow
Basin Outlet MH# (cfs) (gpm) (cfs) (gpm) Storm Event Used
1 MH2493 (5319095) 0.62 278 0.91 408 November 4, 1998
2 MH2481 (5319084) 1.03 462 2.53 1,135 November 4, 1998
3 MH2323 (5320049) 1.73 776 1.01** 453** November 4, 1998
4 MH2814 (5321024) 8.81* 3,954* 18.72* 8,402* January 9, 1990
5 RE*SRENTON.R18-15 8.26* 3,707* 10.48* 4,703* November 24, 1990
6 MH2999 (5330059) 1.54 691 1.69 758 November 24, 1990
7 MH2257 (5319035)1 3.39 1,521 5.77 2,590 November 4, 1998
8 MH0169 (4324017) 0.70 314 1.48 664 February 8, 1996
9 MH0167 (4324012) 1.40 628 1.72 772 February 8, 1996
10 MH2161 (5318106) 0.37 166 0.42 189 February 8, 1996
11 RE*ESI1.RO1-14 3.83 1,719 5.02 2,253 February 8, 1996
12 MH2440 (5318226) 0.45 202 0.53 238 February 8, 1996
13 MH2247 (5319020) 2.12 951 2.36 1,059 February 8, 1996
14 MH2373 (5318148) 1.94 871 2.17 938 February 8, 1996
15 MH2118 (5318047) 4.41 1,979 4.89 2,195 February 8, 1996
16 MH2113(5318042) 1.16 521 1.39 6.24 February 8, 1996
17 MH1851 (5317033) 0.34 153 0.41 184 November 24, 1990
18 MH1825 (5317002) 1.52 682 9.03*** 4,052*** February 8, 1996
19 MH0246 (4325005) 0.36 162 0.51 229 February 8, 1996
20 MH4301 (5303426) 1.04 467 2.17 974 November 24, 1990
21 MH5503(5303093) 1.01 453 1.44 646 November 24, 1990
22 MH3625 (5303102) 2.60 1,166 4.27 1,916 November 24, 1990
23 MH0383 (5305041) 2.10 943 2.98 1,337 January 9, 1990
24 MH0923 (5309169) 1.38 619 1.53 686 February 8, 1996
25 MH1156 (5316015) 1.99 893 1.12** 502** November 24, 1990
26 MH1244(5316115) 3.10 1,391 4.02 1,804 November 24, 1990
27 MH1365 (5309478) 0.74 332 0.87 390 February 8, 1996
28 MH0205 (4324060) 1.68 754 2.27 1,018 February 8, 1996
29 MH0448 (5308252) 0.70 314 0.81 363 February 8, 1996
30A MH4653 (5308327) 3.00 1346 4.80 2,154 February 8, 1996
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.18
ANALYSIS & RESULTS
Table 5-3
City of Renton Sewer Model - 2012 and Ultimate Peak Flow at Mini-
Basin Outlet, Including Storm Event
Mini- 2012 Peak Flow
Ultimate
Peak Flow
Basin Outlet MH# (cfs) (gpm) (cfs) (gpm) Storm Event Used
30B MH4651(5308329) 5.98 2,684 8.11 3,640 February 8, 1996
30C MH0714 (5308161) 3.00 1,346 3.42 1,535 February 8, 1996
32 RE*ESI1.RO1-32A 3.45 1,548 4.00 1,795 February 8, 1996
33 MH0490 (5305008) 1.60 718 2.31 1,037 January 9, 1990
34 MH0362 (5304207) 0.34 152 0.53 237 January 9, 1990
35 MH0368 (5304230) 2.87 1,289 4.64 2,083 November 24, 1990
36 MH0467 (5309128) 1.29 579 1.52 682 February 8, 1996
37 MH6044 (5309028) 0.82 368 1.01 453 February 8, 1996
38A MH0472 (5309133) 1.57 705 1.86 834 February 8, 1996
38B MH0371 (5304234) 2.46 1,104 4.06 1,822 February 8, 1996
39 MH6074 (5308236) 3.06 1,373 3.66 1,642 February 8, 1996
40 RE*ESI4.RO2-19 0.53 238 0.77 346 February 8, 1996
41 MH3511 (5432141) 1.12 503 1.53 687 February 8, 1996
42 MH3386 (5432004) 1.20* 539* 4.86* 2,181* January 9, 1990
43 MH1206 (5316068) 0.31 139 0.47 211 November 24, 1990
44 MH1264 (5316136) 3.22 1,445 4.34 1,948 November 24, 1990
45 MH2253 (5319027) 5.38 2,414 7.09 3,182 November 4, 1998
46 RE*CEDAR1.R10-11A 31.98* 14,354* 47.54* 21,337* November 24, 1990
47
MH2014 (5317243)/
MH1966 (5317183) 9.20 4,129 12.13 5,444 November 24, 1990
48 MH6075 (5308059) 2.22 996 2.38 1,068 February 8, 1996
49 MH0196 (4324044) 0.41 184 0.54 242 February 8, 1996
50 RE*BRYNMAWR.RO1-57 15.86* 7,118* 27.39* 12,293* February 8, 1996
52 MH5833 (5308169) 0.39 175 0.50 224 February 8, 1996
54 RE*ESI2.RO2-08 209.70* 94,120* 239.6* 107,540* February 8, 1996
65 MH5302 (5321007) 14.47* 6,495* 19.07* 8,559* January 9, 1990
*Includes upstream flows from adjacent sewer purveyor
**Decrease in peak flow rates from 2012 to Ultimate Analysis due to future sewer diversion
projects described in Chapter 2.
***Large increase in peak flows at Mini-Basin 18 outlet to overflow at MH1966 from Mini-
Basin 47.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.19
ANALYSIS & RESULTS
Figure 5-3 identifies pipes color-coded by the ratios of peak flow rates to maximum
pipe capacities (Q/Q Full) for the ultimate analysis, consistent with the
methodology and format used for the 2012 Model analysis. Where possible, the
same exact problem area labels were used from the 2012 Model analysis, with
additional problem areas identified within each mini-basin as needed. Only City
piping was identified in the problem areas; areas where County piping exceeded a
Q -ratio of 0.8 were not labeled. The problem areas were summarized and
classified in Table 5-4 based on the degree of surcharging. This table includes a
location description, the duration of surcharging above the crown of the pipe
(where applicable), the duration of surcharging above manhole rims (where
applicable), a brief listing of the suspected cause of the problem or any special
conditions for severe problems, and a ranking of the severity of each problem.
Figures 5-3A to 5-3S, which are referenced in the Table, are included in Appendix
D . Blow-ups of the problem areas are s h own in Figure 5-3.
Surcharging problems in the system are generally the result of insufficient capacity
in the City’s pipes, compounded by backwater from the County’s trunk lines in
some instances. There are several connections in Mini-Basins A and B where
sections of the City’s pipe are modeled below the hydraulic grade line of the
County system. These problem areas in Mini-Basins A and B could potentially be
related to the vertical datum assumptions.
Assigning the constant peak inflows for the boundary flows was conservative, as
mentioned above. The constant inflows caused the discharge in some of the mini-
basins to look non-standard, including Mini-Basins 4, 42, 46, and 65. For each of
these mini-basins, the incoming constant peak boundary flow dominates the local
flows, such that the peaks caused by the individual mini-basins do not appear to
contribute as significantly to the total flow as may appear at some of the other
mini-basins. Additionally, Mini-Basin 50 has severe surcharging issues in the King
County trunk sewer, which significantly influences flows in the downstream system.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.20
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
03A MH2367 MH2364 November 4, 1998 Minor 3 3 716'-8" 0 0 0 Pipe nearing capacity
Location: See Figure 5-3A. SE 19th St from Rolling Hills Ave SE to Aberdeen Pl SE.
04A MH2795 MH2819 January 9, 1990 Severe 4 8 2222'-24" Entire run 0 17' Includes upstream flows
from SCWSD. Capacity
issues due to pipe size.
Location: See Figure 5-3B. Index Ct SE south of SE 16th St, off-road easement from Index Ct SE to Kirkland Ave SE and to Beacon Way ROW.
05A MH2999 RE*SRENT.R18-19 November 24, 1990 Severe 5 4 921'-8" 17 14 6' Capacity issues due to
pipe size, backwater due
to sharp bend at MH2996,
MH2997
Location: See Figure 5-3C. Off-road easement parallel to Shattuck Ave S north of S 37th St.
05B MH3218 RE*SRENT.R18-25 November 24, 1990 Severe 5 3 960'-8" 6 0 5' Capacity issues due to
pipe size
Location: See Figure 5-3C. Talbot Road S from S 177th St to S Carr Rd/S 43rd St.
05C MH3198 MH5523 November 24, 1990 Severe 5 9 1645'-8" 9 0 10' Capacity issues due to
pipe size, backwater due
to sharp bend at MH3193,
MH3194
MH5519 RE*SRENT.R18-17 November 24, 1990 Severe 5 3 902'-12" 11 0 8' Capacity issues due to
pipe size. Severe
surcharging due to
backwater in South
Renton Interceptor
Location: See Figure 5-3C. Davis Ave S south of S 43rd St.
5D MH3205 MH3198 November 24, 1990 Minor/
Severe
5 2 474'-8" 8 0 9' Pipe nearing capacity.
Severe surcharging due
to backwater in DS
system
Location: See Figure 5-3C. Off-road easement south of Davis Ave S along Copper Ridge Apt Access Rd.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.21
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
06A MH3017 MH3004 November 24, 1990 Severe 6 8 2604'-8" 13 6 9' Capacity issues due to
pipe size, backwater due
to sharp bend at MH3004,
MH3009
Location: See Figure 5-3D. Talbot Rd S between S 27th Pl and S 32nd St, Off-road easement parallel to Talbot Road S.
07C MH2275 Prop. Talbot Hill MH November 4, 1998 Minor 7 6 1593'-8" 0 0 0.5' Pipe sections nearing or
at capacity. Negligible
surcharging
Location: See Figure 5-3E. Lake Ave S between S 14th St and S 19th St.
9A MH0166 MH0167 February 8, 1996 Minor/
Moderate
9 1 390'-12" 75 0 2' Pipe nearing capacity.
Surcharging due to
backwater from DS
Eastside Interceptor
Location: See Figure 5-3F. Black River Trail parallel to Oaksdale Ave SW north of SW Grady Way.
11A MH1910 MH2170 February 8, 1996 Severe 11 8 1720'-12" 50 9 5.5' Capacity issues due to
pipe size, backwater due
to multiple bends.
Location: See Figure 5-3G. S 5th St from Main Ave S to Wells Ave S, Wells Ave S between S 5th St and S Grady Way, off-road easement from Wells Ave S across Williams Ave S to Burnett Ave S.
11B MH1941 MH1939 February 8, 1996 Moderate/
Severe
11 2 531'-10" 50 9 6' Capacity issues due to
pipe size, severe
surcharging in DS system
Location: See Figure 5-3G. Williams Ave S between S 5th St and S Grady Way.
14A MH2183 MH0066 February 8, 1996 Moderate/
Severe
14 5 1284'-12" 62 3 11' Capacity issues due to
pipe size, slope, and
bends. Severe
surcharging from
capacity problems in DS
system
Location: See Figure 5-3H. Off-road easement from Rainier Ave S and north parallel to S 2nd St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.22
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
15A MH2115 KC2790 February 8, 1996 Moderate/
Severe
15 6 1252'-15" 66 0 8.5' Capacity issues due to
pipe size and bends.
Severe surcharging from
capacity problems in DS
East Side Interceptor
Location: See Figure 5-3H. S Tobin St between Shattuck Ave S and Burnett Ave S.
15B MH5330 MH2115 February 8, 1996 Minor/
Severe
15 5 926'-15" 64 0 9.5' Pipes nearing/at
capacity. Severe
surcharging from
capacity problems in DS
Renton sewer and East
Side Interceptor
Location: See Figure 5-3H. Off-road easement following Shattuck Ave S between S Tobin St and S 2nd St.
15C MH5209 MH2147 February 8, 1996 Minor/
Severe
15 3 656'-8" 12 0 3' Capacity issues due to
pipe size. Severe
surcharging from
capacity problems in DS
Renton sewer and East
Side Interceptor
Location: See Figure 5-3H. S 2nd St between Rainier Ave S and Shattuck Ave S.
16A MH5398 MH2111 February 8, 1996 S evere 16 3 756'-8" 18 0 4' Capacity issues due to
pipe size
Location See Figure 5-3H. Renton Ave Ext from Hayes Pl SW to Rainier Ave S, Rainier Ave S from Renton Ave Ext/Airport Way to S Tobin St.
18A MH1966 MH1826 February 8, 1996 Minor 18 8 2039'-22" 5 0 1' Pipes nearing/over
capacity.
Location: See Figure 5-3I. N 4th St from Burnett Ave N to Factory Ave N.
20A MH3728 MH5270 November 24, 1990 Minor 20 1 403'-8" 0 0 0 Pipe nearing capacity.
Location: See Figure 5-3J. Lyons Ave NE between NE 26th St and 148th Ave SE.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.23
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
21A MH3547 MH3582 November 24, 1990 Minor/
Severe
21 5 1141'-8" 7 0 3' Pipe nearing capacity.
Surcharging due to
capacity problems in DS
system.
MH3582 MH3587 November 24, 1990 Minor/
Severe
21 5 758'-8" 30 0 6' Pipe nearing/at capacity.
Surcharging due to
capacity problems in DS
system.
Location: See Figure 5-3K. Anacortes Ave NE between NE 22nd Ct and NE 17th St.
21B MH3587 MH5504 November 24, 1990 Severe 21 3 518'-8" 30 0 6' Capacity issues due to
pipe size
Location: See Figure 5-3K. NE 17th St between Anacortes Ave NE and Duvall Ave NE.
22A MH3614 MH3624 November 24, 1990 Severe 22 6 963'-12" 13 0 6' Capacity issues due to
pipe size
MH3624 MH3626 November 24, 1990 Minor 22,35 2 255'-15" 3 0 0 Pipe over capacity for
short duration. Negligible
surcharging.
Location: See Figure 5-3K. NE Sunset Blvd from Anacortes Ave NE to Union Ave NE.
23A MH0490 MH3500 January 9, 1990 Minor 23 6 842'-12" 4 0 1' Minor capacity issues due
to pipe size
MH3499 MH3497 January 9, 1990 Severe 23 2 701'-8" Entire run 0 0'-17' Capacity issues due to
pipe size. Surcharge is
intermittent over entire
run. Typically 0'-8'. Peak
surcharge for 7 hours
Location: See Figure 5-3L. N 28th Pl east of Burnett Ave N to Park Ave N, N 28th St from Park Ave N to I-405.
23B MH0495 MH0383 January 9, 1990 Moderate 23 2 49'-8", 251'-12" Entire run 0 2' Capacity issues due to
pipe size. Surcharge is
intermittent over entire
run. Typically 0'-1'. Peak
surcharge for 6 hours
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.24
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
Location: See Figure 5-3L. Lake Washington Blvd N between Burnett Ave N and N 20th St.
25A MH1177 MH1158 November 24, 1990 Minor/
Severe
25,46 5 315'-10", 651'-12" 66 38 5' Pipes near/slightly over
capacity. Backwater due
to sharp bend at MH1773,
MH1772. Severe
surcharging from
capacity problems in DS
system
Location: See Figure 5-3M. Off-road easement north of SE 5th St between Newport Ave SE and Pierce Ave SE, Pierce Ave SE from SE 5th St to SE 6th St.
25B MH1173 MH1174 November 24, 1990 Minor 25 1 323'-10" 3 0 0.5' Minor capacity issues due
to pipe size, backwater
due to sharp bend at
MH1174
Location: See Figure 5-3M. Off-road easement south of Sunnydale Mobile Home Park Access Rd west of Union Ave SE.
25C MH1660 MH1650 November 24, 1990 Minor 25 6 2116'-10" 2 0 0 Pipe nearing/at capacity.
Negligible surcharging
Location: See Figure 5-3M. SE 4th St from Chelan Ave SE to Union Ave SE, south on Union Ave SE from SE 4th St.
25D MH1695 MH1660 November 24, 1990 Moderate 25 5 1211'-8" 8 0 2' Capacity issues due to
pipe size, backwater due
to sharp bends at MH1660
Location: See Figure 5-3M. From Bremerton Ave SE through easement to SE 2nd Pl north of SE 3rd Pl.
25E MH1706 MH1695 November 24, 1990 Minor/
Moderate
25 5 487'-8" 8 0 2' Pipes nearing capacity.
Surcharging from
capacity problems in DS
system
Location: See Figure 5-3M. Bremerton Ave SE from 135th Ave SE to Bremerton Pl NE, Bremerton Pl NE from Bremerton Ave SE to NE 1st Pl.
26A MH1437 MH1741 November 24, 1990 Minor 26 5 991'-12" 1 0 0 Pipes nearing/slightly
over capacity. Negligible
surcharging
Location: See Figure 5-3N. Duvall Ave NE from NE 6th St to NE 4th St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.25
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
27A MH0976 MH1112 February 8, 1996 Minor 27 3 825'-8" 3 0 0.5' Pipes nearing/slightly
over capacity.
MH1107 MH1365 February 8, 1996 Minor 27 2 569'-8" 4 0 0.5' Pipes nearing/slightly
over capacity.
Location: See Figure 5-3O. NE 7th Pl from NE 6th Pl to Monroe Ave NE, off-road easement from NE 7th St to Jefferson Ave NE.
28A MH5350 MH2548 February 8, 1996 Minor 28 1 301'-15" 0 0 0 Pipe nearing capacity.
MH2537 MH2536 February 8, 1996 Minor 28 1 281'-18" 0 0 0 Pipe nearing capacity.
Location: See Figure 5-3P. Lind Ave SW between SW 19th St and SW 16th St, SW 16th St from Lind Ave SW to Raymond Ave SW.
32A MH0445 MH0726 February 8, 1996 Minor/
Severe
32 1 286'-24" 52 0 2.5' Pipes nearing capacity.
Surcharging from
capacity problems in DS
East Side Interceptor
Location: See Figure 5-3I. N 6th St between Park Ave N and Garden Ave N.
33A MH0518 MH0519 January 9, 1990 Minor 33 2 213'-8" 2 0 0 Pipes nearing/slightly
over capacity. Negligible
surcharging
Location: See Figure 5-3L. Off-road easement parallel to I-405.
36A MH0805 MH0467 February 8, 1996 Severe 36 6 1314'-8" 8 0 7' Capacity issues due to
pipe size. Surcharging
from capacity problems
in DS system
Location: See Figure 5-3Q. Harrington Ave NE from NE 12th St to NE Sunset Blvd.
36B MH6006 MH0907 February 8, 1996 Minor 36 3 983'-8" 1 0 1' Minor capacity issues due
to pipe size. Surcharging
from capacity problems
in DS system
Location: See Figure 5-3Q. NE 12th St from Harrington Ave NE to NE Sunset Blvd, Kirkland Ave NE from NE 12th St to NE 13th St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.26
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
38A-1 MH0467 MH0470 February 8, 1996 Moderate 38 4 287'-8" 22 0 3' Capacity issues due to
pipe size
Location: See Figure 5-3Q.
39A MH6042 MH0825 February 8, 1996 Severe 37,39 6 1130'-8" 4 0 4' Capacity issues due to
pipe size.
Location: See Figure 5-3Q. Edmonds Ave NE from NE Sunset Blvd to NE 9th St.
41A MH3329 MH3510 February 8, 1996 Severe 41 8 1035'-8", 328'-10" 66 60 8' Capacity issues due to
pipe size. Severe
surcharging from
capacity problems in DS
East Side Interceptor
Location: See Figure 5-3R. Lake Washington Blvd N from N 33rd St to N 36th St.
45A MH2257 MH2252 November 4, 1998 Moderate 45 5 1532'-18" 2 0 2' Capacity issues due to
pipe size
Location: See Figure 5-3E. Off-road easement from S Grady Way to S Renton Village Pl.
46A MH1158 RE*CEDAR2.R10-26A November 24, 1990 Minor/
Severe
46 14 2620'-15" 10 0 1.5 Severe surcharging in DS
portion due to water
levels in Cedar River
Trunk. No capacity
problems in pipe.
Location: See Figure 5-3S. SE 6th St between SE 5th St and Pierce Ave SE.
47A MH4692 RE*CEDAR1.R10-05A November 24, 1990 Minor/
Severe
47 8 155'-12", 660'-22",
720'-24"
36 0 2.5' Minor capacity issues due
to pipe size. Surcharging
from capacity problems
in DS Cedar River Trunk
Location: See Figure 5-3T. N 4th St west of Houser Way N.
47B MH0622 MH0639 November 24, 1990 Minor/
Severe
47 2 394'-8" 18 0 2' Pipe nearing capacity.
Surcharging from
capacity problems in DS
system
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.27
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
MH0639 MH0627 November 24, 1990 Severe 47 4 129'-6", 429'-8" 13 10 7' Capacity issues due to
pipe size
Location: See Figure 5-3T. Bronson Way NE from Grandley Way NE to Windsor Way NE.
47C MH1976 MH1975 November 24, 1990 Minor 47 1 311'-8" 8 0 1 Capacity issues due to
pipe size
Location: See Figure 5-3T. NE 4th St west of Edmonds Ave NE.
47D MH1851 MH1968 November 24, 1990 Minor/
Severe
47 1 469'-15" 55 0 3' Pipe nearing capacity.
Surcharging from
capacity problems in DS
system
Location: See Figure 5-3T. Houser Way N between Factory Pl N and N 4th St.
47E MH4645 MH4644 November 24, 1990 Minor 47 1 100'-15" 0 0 0 Pipe nearing capacity.
Location: See Figure 5-3T. Sunset Blvd NE between Bronson Way NE and I-405.
48A MH0847 M H1360 February 8, 1996 Severe 48 2 360'-8" Entire run 0 14' Capacity issues due to
pipe size
Location: See Figure 5-3T. NE 7th St between Ferndale Pl NE and Harrington Ave NE.
50A MH0418 MH420 February 8, 1996 Moderate/
Severe
50 2 460'-8" 67 57 6' Capacity issues due to
pipe size. Severe
surcharging due to
capacity problems in DS
Bryn Mawr Interceptor
Location: See Figure 5-3I. Cedar River Trail south of N 6th St.
65A MH2818 MH2760 January 9, 1990 Moderate 4,65 3 517'-24" Entire run 0 3' Includes upstream flows
from SCWSD. Capacity
issues due to pipe size.
MH5275 MH5299 January 9, 1990 Severe 65 3 432'-18", 322'-20" Entire run 132 12' Includes upstream flows
from SCWSD. Capacity
issues due to pipe size.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.28
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
Location: See Figure 5-3B. SE 16th St from Lake Youngs Way SE and north of SE Royal Hills Dr.
65B MH5301 MH5303 January 9, 1990 Severe 65 4 134'-15", 1001'-20" Entire run Entire run 21' Capacity issues due to
pipe size. Backwater due
to bend at MH 5302.
Includes upstream flows
from SCWSD
Location: See Figure 5-3B. Off-road easement north of Royal Hills Dr SE and east of Harrington Pl SE.
ESI1003A MH1923 MH1921 February 8, 1996 Minor/
Severe
ESI1003 3 674'-8" 54 0 3' Capacity issues due to
pipe size. Surcharging
due to backwater in East
Side Interceptor
Location: See Figure 5-3I. Wells Al l e y N from N 3rd St to N 1st St.
ESI1003B MH4635 RE*ESI2.RO2-01 February 8, 1996 Moderate/
Severe
ESI1003 7 944'-10" 84 82 11.5' Capacity issues due to
pipe size. Severe
surcharging due to
backwater in East Side
Interceptor
Location: See Figure 5-3V. Off-road easement from Lake Washington Blvd N northwest toward Lake Washington.
ESI1003C MH0192 RE*ESI2.RO1-03 February 8, 1996 Minor ESI1003 4 934'-8" 2 0 0.5' Minor capacity issues due
to pipe size
Location: See Figure 5-3F. Thomas Ave SW from SW 7th St to SW 10th St.
ESI1003D MH2440 MH2244 February 8, 1996 Minor/
Severe
ESI1003 1 240'-8" 58 0 2' Minor capacity issues due
to pipe size. Surcharging
due to backwater in East
Side Interceptor
Location: See Figure 5-3F. Hardie Ave SW between SW 5th Pl and SW 7th St.
A1 MH0216 KC1735 February 8, 1996 Minor/
Moderate
A 6 837'-15", 70'-16" 66 0 2' Capacity issues due to
pipe slope. Surcharging in
DS East Side Interceptor
Location: See Figure 5-3F. Off-road easement parallel to Oakesdale Ave SW north of SW Grady Way.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.29
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
A2 MH6188 MH6191 February 8, 1996 Minor/
Severe
A 3 1175'-8" 22 10 5' Pipes nearing/slightly
over capacity.
Surcharging due to bend
at MH6190 and
backwater in DS South
Interceptor
Location: See Figure 5-3U. Off-road easement between Oaksdale Ave SW and SW 39th St.
A3 MH0275 MH0286 February 8, 1996 Severe A 13 396'-8", 2000'-10" 39 31 12' Severe capacity issues
due to pipe size. Severe
surcharging due to
capacity problems in DS
South Interceptor
Location: See Figure 5-3U. Off-road easement between Oaksdale Ave SW and Interurban Trail north of S 180th St.
A4 MH0186 RE*ESI2.RO1-04 February 8, 1996 Minor A 2 275'-8" 2 0 0 Pipe over capacity for
short duration. Negligible
surcharging.
Location: See Figure 5-3F. SW 10th St from Powell Ave SW towards Thomas Ave SW.
B1 MH5191 MH2982 February 8, 1996 Minor/
Severe
B 5 1367'-8" 5 0 2.5' Capacity issues due to
pipe size. Additional
surcharging due to
possible pump capacity
issues in Lift Station.
Location: See Figure 5-3U. SW 34th St from Lind Ave SW to E Valley Rd.
B2 MH3172 RE*SRENTON.R18-05 February 8, 1996 Minor/
Severe
B 3 645'-8" 33 0 8' Pipe nearing capacity.
Severe surcharging from
capacity problems in DS
South Renton Interceptor
Location: See Figure 5-3U. 84th Ave S from SW 43rd St towards SW 41st St.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.30
ANALYSIS & RESULTS Chapter 5
Table 5-4
Capacity Analysis for Ultimate Sewer Model - Problem Areas
Problem Manhole No. Storm Event Rating Mini Pipe Length and
Diameter
Manhole Manhole Max Surcharge Comments
Area Upstream Downstream Basin Sections Surcharge (hrs) Overtopping (hrs) Height (ft)
B3 MH2987 RE*SRENTON.R18-11 February 8, 1996 Minor/
Severe
B 7 2012'-12" 26 7 7' Pipes nearing/slightly
over capacity. Severe
surcharging from
capacity problems in DS
South Renton Interceptor
Location: See Figure 5-3U. East Valley Rd from SW 34th St to SW 41st St,
U6A MH4717 MH4713 N/A Minor U6 3 587'-8" Intermittent
entire run
0 0.5' Intermittent surcharging
due to LS 34 (Liberty).
Model contains constant
flow rate inputs for U -
Basins
Location: See Figure 5-3W. SE 137th Terrace from 160th Ave SE to 161st Pl SE, 161st Pl SE south from SE 137th Terrace.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.31
ANALYSIS & RESULTS Chapter 5
Based on discussions with Bruce Nairn of King County, the County’s interceptor
located in Mini-Basin 50 has significant potential surcharging issues, primarily due to
severe I&I problems in the upstream County-owned system. S urcharging potential
was evident in the 2012 Model Analysis, and significantly more pronounced in the
Ultimate Model Analysis. T he County plans to install a storage facility to dampen
peak flows or implement an I&I repair and reduction program for the upstream
system, or both. For the Ultimate Model analysis, it was assumed that this County
trunk line would be at capacity (rather than significantly exceeding capacity)
during the 20-year design flow-generating event, resulting from the future
improvements. As a result of this assumption, the County’s trunk sewer would not
cause backwater effects in the City’s sewer mains within Mini-Basin 50. Further
coordination with the County is recommended with regard to the significant future
zoning densification projected in the City, adjacent to their trunk sewer, within Mini-
Basin 50.
During the Ultimate Model analysis, some lift stations overtopped significantly; to
the extent that the model could not complete its computations. These lift stations
include East Valley (L04), Airport (L03), Stoneg ate (L29), and Long (L07). T he pumps
in each of these cases were upsized to accommodate the peak flow rate with a
single pump in operation to allow MIKE URBAN to complete the computations. The
Airport and Stonegate pumps were modeled based on projected peak pump
capa cities with as-designed impelle r upgrades. Since most or all of the City’s lift
stations appear to only contain two duty pumps, any of the duplex stations
operating with more than one pump would function beyond their design capacity.
The I&I increase assumption of 7% per decade and a maximum of 28% for the
Ultimate Model may be overly conservative for newer portions of the City
constructed primarily with PVC and ductile iron pipes. These system degradation
assumptions may be reasonable for the older portions of the system. During future
analysis, pipe material and age should be taken into consideration in addition to
flow monitoring. Also, the degree of I&I reduction efforts by the City should be
taken into consideration for flow modeling. It may be more practical to assume
lower degradation rates for some of the newer portions of the system. For sewer
system locat ed in the “U” Basins, standard I&I assumptions (1500 gallons per day
per acre) were used, with no applied degradation. It may be desirable to
incorporate some degradation (such as 7%) for the newer system in future analyses.
No flow monitors were associated with Mini-Basin A and a portion of B, which have
multiple discharges to KC trunks; there was no check on the accuracy of these
flows. The flows were generated from standard sanitary and I&I assumptions rather
than subtracted from the South Interceptor. I&I parameters used by KC from an
adjacent Model Basin were assigned, which may or may not be representative of
actual conditions. Further monitoring and analysis is recommended (see Cha p t e r
6 ).
Although flows were calibrated to reasonable accuracy based on King County’s
2008 -2011 flow monitoring data, all of the flows in the Ultimate Model are more
heavily based on assumptions and projections, as detailed herein. It is advisable to
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.32
ANALYSIS & RESULTS Chapter 5
conduct additional flow monitoring and analysis to verify the existence and extent
of projected problem areas in the City’s system.
LIFT STATION AND FORCE MAIN ANALYSIS
A review of lift station and force main capacity was conducted for the 2012 and
Ultimate model analysis. In each case, the model results were reviewed to
determine the number of pumps operating during the peak storm event, and the
maximum velocity of the flow in each force main. Typically, lift stations are
designed so that a single pump is able to convey the peak 20-year flow. Flow
velocities in the force main should be a maximum of 8 feet per second. Results are
shown in Table 5-5.
Table 5-5
Lift Station and Force Main Analysis Summary
Lift Station Mini-
Basin Force Main
2012 Analysis Ultimate Analysis
Max.
Pumps
On
Max. Force
Main
Velocity
(fps)
Max.
Pumps On
Max. Force
Main
Velocity
(fps)
L01-Shy Creek U4 8" PVC 1 3.5 1 3.5
L02-Devils Elbow 33 6" PVC 1 4.7 1 4.7
L03-Airport 16 5" PVC 1 2.8 1* 4.7
L04-East Valley B 12" DI 2 1.27 2 1.27
L05-Talbot Crest 6 3" PVC 1 4.3 1 4.3
L07-Long 21 6" PVC 1 0.97 1 0.97
L08-Kensington 65 3" PVC 1 5 1 5
L09-Wedgewood 22 10" DIP 1 1.3 1 1.3
L25-Lind Ave 28 8" PVC 1 4.4 1 4.4
L29-Stone Gate 20 8" PVC 1 1.7 1* 3.4
L30-Falcon Ridge 4 10" PVC 1 1.4 1 1.4
L32-Misty Cove 54 Not
Modeled 2 N/A 2 N/A
L34-Liberty U6 8" PVC 1 3.9 1 3.9
L39-Baxter 54 6" PVC 2 4.8 2 4.8
*Lift stations modeled to include pump impeller upgrades provided in lift station design
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.33
ANALYSIS & RESULTS Chapter 5
Results of the analysis show that most of the lift stations and all of the force mains
are capable of conveying projected flows for 2012, as well as u ltimate scenarios.
There are three lift stations which may have capacity problems based on the
analysis. Misty Cove and Baxter Lift Stations are located in Mini Basin 54, which was
calibrated in 2005. The service area for Baxter Lift Station includes large multi-
family development which was added since the model calibration, and may be
simulating sanitary flows that are larger than what actually occurs. The second
p ump for Misty Cove Lift Station only activated 3 times during the peak storm
event.
East Valley Lift Station also exceeded its capacity during both simulations. T he City
provided data for this lift station during the calibration process. This data indicated
that a second pump did activate a few times during the December 2010 storm
used in the Calibration.
T he second pump did not activate for Long Lift Station7. However, the station was
close to its single pump capacity during the ultimate model simulation. Therefore, it
is possible that the l ift s tation will eventually exceed its capacity if the service area
sees significant population growth.
INFILTRATION AND INFLOW ANALYSIS
The runoff simulations for the 2012 model analysis were reviewed to estimate the
peak inflow to the sewer system due to infiltration and inflow. This was done by
determining the peak modeled RDII flow rate for the catchments in each
calibrated mini-basin and dividing this by the area. Results of this analysis are
provided in Table 5-6 .
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.34
ANALYSIS & RESULTS Chapter 5
Table 5-6
Peak Infiltration and Inflow per Mini-Basin
Sewer Mini-Basin Peak Storm Event Peak I/I(1)
(gpad) Calibration Year(2)
1 November 4, 1998 4,580 2005
2 November 4, 1998 3,902 2005
3 November 4, 1998 4,062 2005
4 January 9, 1990 1,700 2015
5 November 24, 1990 19,223 2015
6 November 24, 1990 3,436 2015
7 November 4, 1998 6,618 2005
8 February 8, 1996 1,330 2005
9 February 8, 1996 7,718 2005
10 February 8, 1996 4,009 2005
11 February 8, 1996 7,724 2005
12 February 8, 1996 2,076 2005
13 February 8, 1996 17,189 2005
14 February 8, 1996 6,595 2005
15 February 8, 1996 9,248 2005
16 February 8, 1996 3,725 2005
17 November 24, 1990 6,17 2015
18 February 8, 1996 5,927 2005
19 February 8, 1996 1,140 2015
20 November 24, 1990 1,650 2005
21 November 24, 1990 2,443 2005
22 November 24, 1990 585 2005
23 January 9, 1990 539 2015
24 February 8, 1996 6,616 2015
25 November 24, 1990 4,400 2015
26 November 24, 1990 2,251 2005
27 February 8, 1996 3,595 2015
28 February 8, 1996 4,907 2005
29 February 8, 1996 3,924 2015
30A February 8, 1996 860 2015
30B February 8, 1996 329 2015
30C February 8, 1996 860 2015*
32 February 8, 1996 2,413 2005
33 January 9, 1990 798 2015
34 January 9, 1990 842 2015
35 November 24, 1990 1,199 2005
36 February 8, 1996 6,824 2015
37 February 8, 1996 7,085 2015
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.35
ANALYSIS & RESULTS Chapter 5
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.36
Table 5-6
Peak Infiltration and Inflow per Mini-Basin
Sewer Mini-Basin Peak Storm Event Peak I/I(1)
(gpad) Calibration Year(2)
39 February 8, 1996 3,985 2015
40 February 8, 1996 3,891 2005
41 February 8, 1996 6,712 2015
42 January 9, 1990 2,804 2005
43 November 24, 1990 548 2015
44 November 24, 1990 37 2005
45 November 4, 1998 602 2005
46 November 24, 1990 3,081 2005
47 November 24, 1990 7,326 2015
48 February 8, 1996 2,065 2015
49 February 8, 1996 3,331 2015
50 February 8, 1996 12,370 2005
52 February 8, 1996 1,468 2005
54 February 8, 1996 4,429 2005
A February 8, 1996 10,232 2005**
B February 8, 1996 3,932 2005**
CEDAR02A November 24, 1990 3,088 2005
ESI1003 February 8, 1996 10,225 2005
RENT65 January 9, 1990 1,450 2015
1) RDII parameters determined in the 2005 wet weather calibration were set using wet weather at the Mini-Basin level.
Those modified in the 2015 calibration were set at the model basin level.
* Mini-Basin Basin 30C was calibrated with Basin 30A.
** RDII parameters for Mini-Basins A and B were not calibrated. During the 2005 model development, RDII parameters
from adjacent basins with similar land use were assigned.
Peak I/I flow rates for a 15 basins are very high, exceeding 6,000 gallons per acre
per day. The calibration for many of these basins was performed in 2005. The I/I
flow rates for Mini-Basin 5 and 13 exceed 15,000 gallons per acre per day.
Although the calibration for Mini-Basin 5 was performed in 2015, it was done at the
model basin level, and included decreases in the I/I parameters from the prior
calibration. Mini-Basin 13 was calibrated in 2005. The 2012 and Ultimate model
results show pipe capacity problems for many of the basins with high I/I flow rates..
Therefore, we recommend additional flow monitoring to verify the calibration in
these basins. The Mini-Basin 44 I/I flow rate is extremely low, so flow-monitoring is
also recommended to for this basin. See Chapter 6 for further discussion.
PEAK BOUNDARY FLOW ANALYSIS
The peak flow rates for each of the external boundary flows are tabulated below in
Table 5-7. The flow rates for SOO003 and RNT042 were constant flow inputs. The
rest of the flows were time series inputs. Since four separate storm events were
ANALYSIS & RESULTS Chapter 5
PEAK BOUNDARY FLOW ANALYSIS
The peak flow rates for each of the external boundary flows are tabulated below in
Table 5-7 . The flow rates for SOO003 and RNT042 were constant flow inputs. The
rest of the flows were time series inputs . Since four separate storm events were
used in the model analysis, the peaks were different magnitudes for each event.
The peaks were also from different events depending on the boundary condition.
For this table, the largest peak event was listed.
Table 5-7
Peak Boundary Flows
Boundary Flow Peak 2012 Flow
(cfs)
Peak Ultimate
Flow (cfs)
TUK015 24.16 34.50
SINT020 156.11 291.24
SOO021 2.62 4.42
SOO003 7.90 17.20
Cedar039A 13.56 21.02
RNT042 1.1 3.6
ESI4024 261.13 428.46
BLS043B 24.67 34.17
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.37
ANALYSIS & RESULTS Chapter 5
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.38
Figure 5.2
2012 Sewer Model Analysis Results
ANALYSIS & RESULTS Chapter 5
City of Renton 2015 Hydraulic Model Update
Summary Report Page 5.39
Figure 5.3
Ultimate Sewer Model Analysis Results
CHAPTER 6 RECOMMENDATIONS AND SUMMARY
This section of the report includes the recommendations for future flow
monitoring and model updates. A summary of the King County hydraulic
model compatibility and limitations of the model have also been included.
FLOW MONITORING RECOMMENDATIONS
As mentioned previously in this report, additional flow monitoring and
analysis can be a worthwhile supplement to hydraulic modeling and
verification of capacity deficiencies. Figure 6-1 (located at the end of this
chapter) i dentifies recommended future modeling locations, and Table 6-1
lists the specific recommended locations for future monitors in addition to
the general categories of the monitors. Figure 6-1 includes the following
four categories of flow meters:
1.Locations of King County flow monitors from 2008-2011 (Black Rings ):
These are locations where flow moni toring was conducted by King
County for the decennial monitoring program, but much of the
recorded data was missing or errant due to flow monitor issues.
Additional monitoring is warranted at these locations to verify the
flows in the tributary basins.
2.L ocations which King County did not monitor from 2008-2011
(Orange Rings): These locations include large tributary basin areas,
and were not monitored. In some cases, downstream monitors did
collect these tributary flow data, but the data is not detailed enough
to examine the smaller upstream areas. Other locations are newer
Mini-Basins or S ub-B asins, which have seen substantial growth since
the model was developed. Monitoring is warranted at these
locations to verify the flows in the tributary basins.
3.New flow meter locations to monitor specific 2012 Model problem
areas (Violet Rings ): These locations would provide targeted
monitoring to isolate and verify some of the more serious problem
areas as identified by the 2012 Model Peak Flow Analysis. These
areas are typically not immediately adjacent to previous flow
monitor locations, or would be used to separate large branches of
upstream sewer to help identify the cause and location of problems.
Where feasible, attempts were made to select locations where a
single meter could be used to help verify more than one problem
area.
4.New f low m eter l ocations to m onitor s pecific Ultimate Model p roblem
a reas (Blue Rings): These locations would provide targeted
monitoring to isolate and verify some of the more serious problem
areas as identified by the Ultimate Model Peak Flow Analysis. These
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.1
RECOMMENDATIONS & SUMMARY Chapter 6
areas are typically not immediately adjacent to previous flow
monitor locations, or would be used to separate large branches of
upstream sewer to help identify the cause and location of problems.
Where feasible, attempts were made to select locations where a
single meter could be used to help verify more than one problem
area.
It might be wise to install flow monitors for suspected problem areas using a
phased approach, rather than installing all of the meters at the same time.
This would allow more opportunity for evaluation of the metering to make
sure useful and reliable data is being provided.
Installation of flow meters at new locations or locations where data
previously collected by King County was errant may potentially be a
collaborative effort with King County, with each party sharing information
and possibly expenses. Targeted use of flow meters could help locate areas
with higher than normal I&I issues, which could potentially be repaired to
avoid downstream piping upsizing and modifications. Flow monitors can be
used to verify or refute projected capacity problems, potentially eliminating
costly projects or providing confidence that improvements are warranted.
Table 6-1
City of Renton Sewer Model
Propo sed Flow Monitor Locations
Basin Flow Monitor MH* Category** Problem Area
3 MH0084 (SE) 2
5 RE*SRENTON.R18-25 (S) 3 5B
5 RE*SRENTON.R18-17 (S) 3 5C
6 MH2999 3 5A, 6A
11 RE*ESI1.RO1-14 (E) 3 11A, 11B
13 MH2247 (N) 2
14 MH0066 (W) 3 14A
15 MH2120 (W) 3 15A, 15B, 15C
16 MH2113 (W) 4 16A
19 MH0246 (E) 1
21 MH5503 (N) 3 21A, 21B
22 MH3626 (E) 4 22A
23 MH0383 (NE) 1,3 23A, 23B
25 MH1650 (N) 4 2BC, 25D, 25E
26, U2 MH1746 (E) 2
26 MH1741 (N) 4 26A
38A MH0466 (N) 3 36A, 36B, 38A
39 MH0825 (N) 3 39A
40 RE*ESI4.RO2-19 (E) 1
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.2
RECOMMENDATIONS & SUMMARY Chapter 6
Table 6-1
City of Renton Sewer Model
Propo sed Flow Monitor Locations
Basin Flow Monitor MH* Category** Problem Area
41 MH3511 (SW) 1,3 41A
42 MH3386 (N) 1
44 MH1264 (E) 2
45 MH2253 (E) 3 45A
47 MH4646 (E) 3 47B, 47C
47 MH2014 (N)
48 MH0843 (E) 3 48A
50 MH0420 (S) 4 50A
RENT65 MH5302 (W) 2,4 65B
RENT65 MH2760 (SW) 2,3 4a, 65A
ESI1003 MH4629 (W) 4 ESI1003B
ESI1003 MH1924 (S) 4 ESI1003A
A MH0211 (S) 3 A1
A MH6191 (E) 3 A2
A MH0286 (W) 3 A3
B MH2982 (S) 3 B1
B MH3187 (N) 2,4 B3
U3 MH1709 (E) 2
U4, U6, U8
& U9
RE*CENTRALPLAT.MH-5
(N) 1
U6 MH4712 (E) 4 U6A
* Proposed flow monitor locations include the necessary orientation. For example
“(E)” indicates that the monitor would be installed in the pipe entering the
identified manhole to the East.
**Categories are as follows:
1)King County flow monitors with errant data
2)No Prior flow monitors – Mini-Basin flow verification
3)2012 Model problem areas
4)Ultimate Model problem areas
KING COUNTY COMPATIBILITY
The model was updated with the intent of achieving general compatibility
with the models developed by King County during the Regional I&I study.
Many of the assumptions and methodologies employed by the City and
County models are consistent. Overall, the models are fairly compatible,
and data can be shared between the models in a relatively straightforward
fashion. Some of the main similarities between the models are listed below:
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.3
RECOMMENDATIONS & SUMMARY Chapter 6
•B oth models use the MOUSE hydraulic engine (MIKE URBAN r uns on the
MOUSE engine).
•The same formula was used for computing the base I&I for each mini-
basin in the two models.
•Both models include population projections based on PSRC planning
data.
•Both models use similar RDII parameters.
•Both models were calibrated to the same dry weather and wet
weather flow monitoring data.
•DHI worked on calibrating the County’s and City’s original models for
the wet weather season, and employed a similar methodology for
both.
•Both models use similar rainfall gauge assignments.
•Both models feature detailed representations of King County trunklines
within the City boundaries.
•Boundary flow assignments to the City’s model conservatively
represent boundary flow rates computed by King County.
•Both models incorporate an assumed system degradation resulting in
an I&I increase of 7.0 percent per decade. The City of Renton
assumes a maximum increase of 28.0 percent for the Ultimate Models,
whereas King County does not apply a cap for future projections.
•Both models use the same hydraulic engine and computations, and
both feature a similar overall set-up.
There are some key differences between the City’s model and the King
County models. The City’s model is much more detailed than any of the
County’s models in terms of the representation of the physical system. The
majority of the City’s system is included in the model, with flow present in all
of the pipes. The physical detail in the City’s model allows it to be a
powerful hydraulic tool for evaluation of system capacity at a local level.
With the City’s model, it is possible to evaluate pipes as small as 8-inch
diameter to evaluate capacity, throughout the City. The County’s model is
intended to be a regional tool used to evaluate I&I and system capacity at
a much broader and less refined level. With the models developed by the
County, hydraulic evaluation of large sewer trunks is possible, but generally
not smaller pipes. The County’s models are primarily hydrology models, with
hydraulics for trunks. The City’s model is both a hydrologic and hydraulic
model throughout. Some other key differences in the models are
summarized below:
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.4
RECOMMENDATIONS & SUMMARY Chapter 6
•The population is assigned more representatively to the City’s model,
by zoning categories. The City’s model has individual populations
assigned to manholes by zone, while the County’s model feature lump
net flow assignments, not targeted to specific zoning categories by
individual manholes. The net results at the outlet of each mini-basin
should be similar, but the flow in the local system is more
representative in the City’s model.
•A conservative factor of 25% was added to all of the projected
populations within the City’s model. The County may have applied
different measures of conservatism into their models, but it is believed
that they did not apply a 25% increase to the population assignments.
•Efforts were made in the City’s model to check to make sure realistic
per capita flow rates were assigned, and adjustments to projected
population distributions were made as deemed appropriate.
•The area assignments between the models differ. King County
applied several discount factors reducing the area assigned to each
mini-basin. In the City’s model, the overall areas (generally not
including parks and open space) were equally assigned to all of the
manholes within each mini-basin. As a result, much larger overall
areas were assigned to the 2012 Renton Model. This does not create
a difference in the calibrated wet weather flows for the 2012 model,
but may have an impact to flows in the Ultimate Model and future
scenarios.
•The City’s model has the ability to accurately simulate lift station
operation and settings, whereas the County’s models did not
generally include that level of detail. The County did not model lift
station operation, focusing instead on the larger picture.
•The original wet weather calibration for Renton’s model started with
similar RDII parameters to King County, but these were refined by DHI,
and further refined by Stantec to provide a more representative and
system specific calibration.
•The County performed complex statistical analyses and developed
synthetic storm events to represent 20-year peak flows within the
various basins. The scope and budget of the City’s model did not
support this level of analysis. Per the County’s suggestion, events
ranked by the County were assumed to represent the various storm
events used for the City’s analyses.
•The County’s Ultimate models do not use diurnal sanitary flows;
instead, they use a constant average sanitary flow rate throughout
the model simulations.
•Due to the system-specific detail in the City’s model, it takes
significantly longer to perform computations.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.5
RECOMMENDATIONS & SUMMARY Chapter 6
•The County generally uses more conservative I&I assumptions (such as
2,000 gallons per acre per day) for areas projected to be served in
the future (the City generally used 1500 gallons per acre pre day for
new projected areas).
LIMITATIONS OF THE MODEL
The limitations of the model generally relate to limitations in the data and
assumptions used to develop the model, the budget used to develop the
model, and limitations of the software. Some of the main limitations are
summarized below:
•The data used to develop the City’s model was found to contain a
large volume of missing information, incorrect information, and
inconsistencies. Numerous assumptions were used to correct this
data, including interpolations and datum assumptions. Although the
piping in the model all flows downhill, there is certainly a portion of
model data that is inaccurate to some extent.
•The diurnal curves assigned to the model apply to the overall mini-
basins. Targeted diurnal curves used for each zoning category were
not used; therefore, although flow is represented in all of the piping
throughout the model, it can be considered an average of the
upstream flow generation at any point. The diurnal curve applied to
any node within a mini-basin will have the average flow values for the
total system, but may not represent the actual specific flow patterns
from an individual area, such as a school. The diurnal patterns
generally represent the overall make-up of the mini-basins (residential
versus employment, etc.).
•Although I&I is assigned to most of the manholes in each mini-basin,
weighted areas to each manhole were not assigned; most manholes
typically receive the average area for the mini-basin. This functions to
distribute average mini-basin I&I rates to each manhole, but does not
isolate I&I issues within each mini-basin, since only the total flow at the
downstream monitors were used to calibrate the flows.
•The RDII parameters used to develop the antecedent soil and
groundwater conditions are very complex, and difficult to accurately
represent. The County performed more extensive research and
evaluation when determining their parameters, the results of w hich
were largely applied to the City’s model. However, the specific
conditions defining how surface water and groundwater enter the
sewage system are extremely complex, and the RDII parameters
assigned to the model will not necessarily be able to accurately
predict future performance, even though they were determined and
estimated using flow monitoring data from a couple of seasons.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.6
RECOMMENDATIONS & SUMMARY Chapter 6
•The storm events assigned to the model may or may not provide
representative 20/30-year design flows within the system. The extent
of the rainfall data analyzed by King County was approximately 60
years, and there are no guarantees that the storm flow rankings
correspond to the appropriate storm events over that limited period
of data.
•There were many inconsistencies, gaps, and a lot of “noise” in the
flow monitoring data obtained by the County, and calibration was
anything but an exact science. For some b asins, the data was non-
existent or inadequate to provide accurate calibrations. Without
further flow monitoring efforts, there should be limited confidence in
any of the projected flow rates from non-calibrated basins/mini-
basins.
•The flow monitoring data obtained from the County was collected a
the model basin level, which was at a much broader scale than the
data collected for the 2001 I/I study, which was collected at the mini-
basin level. Without more refined flow data, changes to the
calibration of the model were less precise than the prior effort, and
may have significant impacts on the analysis results.
•The large volume of data compiled from numerous sources and the
extensive estimations, judgment, and assumptions used to create the
model make it a very powerful tool, but common sense and sound
engineering judgment should be applied to all results.
The data provided by model analysis is simply a planning level tool to
determine areas that will need further analysis prior to implementation of
any capital improvements. A dditional analysis and flow-monitoring may be
prudent prior to proceeding with large-scale system improvements in many
parts of the system, as described earlier in this report in more detail. It is
always advisable to apply sound engineering judgment coupled with real-
world perspective to make sure that modeling results make sense and fit the
appropriate conditions being studied. The physical components of
projected “problem areas” such as manhole invert elevations, pipe slopes,
and pipes sizes should be verified to ensure that the model is an accurate
representation of the actual system.
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.7
RECOMMENDATIONS & SUMMARY Chapter 6
Figure 6.1
Proposed Flow Monitor Locations
City of Renton 2015 Hydraulic Model Update
Summary Report Page 6.8
APPENDICES
APPENDIX A – Dry Weather Flow Calibration Time Series
City of Renton 2015 Hydraulic Model Update
Summary Report Page A
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.23.43.6[cfs]Time Series Link DischargeLink DischargeGM05310 (MH5304 -> MH2759) 74.47External TS 1Rent 65 DryDry Calibration - Model Basin 65(Model Output)(Flow Monitor Data)
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.000.010.020.030.040.050.060.070.080.090.100.110.120.130.140.150.160.170.180.190.200.210.220.23[cfs]Time Series Link DischargeLink DischargeGM02800 (MH1852 -> MH1851) 120.91External TS 1RNT 17 DryDry Calibration - Model Basin 17(Flow Monitor Data)(Model Output)Note: Model output includes approximately 0.06 cfs of peak I/I flow modeled as dryweather flow.
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.10.20.30.40.50.60.70.80.91.01.11.21.31.4[cfs]Time Series Link DischargeLink DischargeGM01571 (MH0520 -> MH0383) 24.48External TS 1RNT 23 DryDry Calibration - Model Basin 23(Model Output)(Flow Monitor Data)Note: Model output includes approximately 0.14 cfs of peak I/I flow modeled as dryweather flow.
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.000.050.100.150.200.250.300.350.400.450.500.550.60[cfs]Time Series Link DischargeLink DischargeGM02237 (MH1773 -> MH1156) 109.94External TS 1RNT 25 DryDry Calibration - Model Basin 25(Model Output)(Flow Monitor Data)Note: Model output includes approximately 0.12 cfs of peak I/I flow modeled as dryweather flow.
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.000.050.100.150.200.250.300.350.400.450.500.55[cfs]Time Series Link DischargeLink DischargeGM00108 (MH0206 -> MH0205) 108.45External TS 1RNT 28 DryDry Calibration - Model Basin 28(Model Output)(Flow Monitor Data)
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.10.10.20.20.30.30.40.40.50.50.60.60.70.70.80.80.90.91.0[cfs]Time Series Link DischargeLink DischargeGM01793 (MH0715 -> MH0714) 90.57External TS 1RNT 30A DryDry Calibration - Basin 30A(Model Output)(Flow Monitor Data)
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.2[cfs]Time Series Link DischargeLink DischargeGM04481 (MH4653 -> MH4652) 99.98External TS 1RNT 30B DryDry Calibration - Basin 30B(Model Output)(Flow Monitor Data)Note: Basin 30B flows into Basin 47. Therewere inconsistencies between the data of thetwo flow monitors.
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.10.20.30.40.50.60.70.80.91.01.11.21.31.41.51.61.7[cfs]Time Series Link DischargeLink DischargeGM01350 (MH3756 -> MH0368) 113.70External TS 1RNT 35 DryDry Calibration - Basin 35(Model Output)(Flow Monitor Data)Note: Model output includes approximately 0.29 cfs of peak I/I flow modeled as dryweather flow.
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.000.020.040.060.080.100.120.140.160.180.200.220.240.260.280.300.32[cfs]Time Series Link DischargeLink DischargeGM05921 (MH5705 -> MH3511) 83.15External TS 1RNT 41 DryDry Calibration - Basin 41(Model Output)(Flow Monitor Data)Note: Calibration is conservative
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.000.050.100.150.200.250.300.350.400.450.500.550.600.65[cfs]Time Series Link DischargeLink DischargeGM01059 (MH1205 -> MH1206) 79.00External TS 1RNT 43 DryDry Calibration - Basin 43(Model Output)(Flow Monitor Data)
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.23.43.63.84.04.24.44.6[cfs]Time Series Link DischargeLink DischargeGM03455 (MH2254 -> MH2253) 87.38External TS 1RNT 45 DryDry Calibration - Basin 45(Model Output)(Flow Monitor Data)Note: Per discussions with City,no modifications were madefrom previous (2005) dryweather per capita flow rates.
00:00:001-9-201000:00:002-9-201000:00:003-9-201000:00:004-9-201000:00:005-9-201000:00:006-9-201000:00:007-9-201000:00:008-9-20100.00.20.40.60.81.01.21.41.61.82.02.22.42.62.83.03.23.43.63.8[cfs]Time Series Link DischargeLink DischargeGM03057 (MH2009 -> MH2014) 82.81External TS 1RNT 47 DryDry Calibration - Basin 47(Model Output)(Flow Monitor Data)Note: Basin 30B flows into Basin 47. Therewere inconsistencies between the data of thetwo flow monitors.
1-9-20103-9-20105-9-20107-9-20100.00.20.40.60.81.01.21.41.61.82.02.22.42.62.8[cfs]Time Series Link DischargeLink DischargeRE*SRENTON.R18-03l1 (RE*SRENTON.R18-03 -> RE*SRENTON.R18-02) 98.66External TS 1SRENT002 DryDry Calibration - SRENT002(Model Output)(Flow Monitor Data)Note: Calibration is conservative. Percapita flow rates were loweredsignificantly from previous (2005)calibration.
APPENDICES
APPENDIX B – Wet Weather Flow Calibration Time Series
City of Renton 2015 Hydraulic Model Update
Summary Report Page B
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.000.020.040.060.080.100.120.140.160.180.200.220.240.260.280.300.320.34[cfs]Time Series Link DischargeLink DischargeGM02800 (MH1852 -> MH1851) 120.91External TS 1RNT017Wet Calibration - Model Basin 17(Model Output)(Flow Monitor Data)
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.10.20.30.40.50.60.70.80.91.01.11.21.31.41.51.61.71.8[cfs]Time Series Link DischargeLink DischargeGM01571 (MH0520 -> MH0383) 24.48External TS 1RNT023Wet Calibration - Model Basin 23(Model Output)(Flow Monitor Data)
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.10.20.30.40.50.60.70.80.91.01.11.21.31.41.5[cfs]Time Series Link DischargeLink DischargeGM02237 (MH1773 -> MH1156) 109.94External TS 1RNT025Wet Calibration - Model Basin 25(Model Output)(Flow Monitor Data)
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.10.10.20.20.30.30.40.40.50.50.60.60.70.70.80.80.90.91.01.0[cfs]Time Series Link DischargeLink DischargeGM00108 (MH0206 -> MH0205) 108.45External TS 1RNT028Wet Calibration - Model Basin 28(Model Output)(Flow Monitor Data)
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.20.40.60.81.01.21.41.61.82.02.22.42.62.8[cfs]Time Series Link DischargeLink DischargeGM01793 (MH0715 -> MH0714) 90.57External TS 1RNT030AWet Calibration - Model Basin 30A(Model Output)(Flow Monitor Data)
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.51.01.52.02.53.03.54.04.55.05.56.06.5[cfs]Time Series Link DischargeLink DischargeGM04481 (MH4653 -> MH4652) 99.98External TS 1RNT030BWet Calibration - Model Basin 30B(Model Output)(Flow Monitor Data)Note: Basin 30B flows into Basin 47. Therewere inconsistencies between the data of thetwo flow monitors.
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.51.01.52.02.53.03.54.04.55.0[cfs]Time Series Link DischargeLink DischargeGM01350 (MH3756 -> MH0368) 113.70External TS 1RNT035Wet Calibration - Model Basin 35(Model Output)(Flow Monitor Data)Note: Per discussions with City,no modifications were madefrom previous (2005) RDIIparameters.
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.00.10.20.30.40.50.60.70.80.91.01.11.21.31.4[cfs]Time Series Link DischargeLink DischargeGM05921 (MH5705 -> MH3511) 83.15External TS 1RNT041Wet Calibration - Model Basin 41(Model Output)(Flow Monitor Data)
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.000.050.100.150.200.250.300.350.400.450.500.550.600.650.700.750.800.85[cfs]Time Series Link DischargeLink DischargeGM01059 (MH1205 -> MH1206) 79.00External TS 1RNT043
10-12-201012-12-201014-12-201016-12-201018-12-20100.00.51.01.52.02.53.03.54.04.55.05.56.06.57.07.58.0[cfs]Time Series Link DischargeLink DischargeGM03057 (MH2009 -> MH2014) 82.81External TS 1RNT047Wet Calibration - Model Basin 47(Model Output)(Flow Monitor Data)Note: Basin 30B flows into Basin 47. Therewere inconsistencies between the data of thetwo flow monitors.
00:00:0010-12-201000:00:0011-12-201000:00:0012-12-201000:00:0013-12-201000:00:0014-12-201000:00:0015-12-201000:00:0016-12-201000:00:0017-12-20100.01.02.03.04.05.06.07.08.09.010.011.012.0[cfs]Time Series Link DischargeLink DischargeGM05309 (MH5303 -> MH5304) 33.19External TS 1RENT65Wet Calibration - Model Basin 65(Model Output)(Flow Monitor Data)
10-12-201012-12-201014-12-201016-12-20100.00.51.01.52.02.53.03.54.04.55.05.56.06.57.07.58.08.59.0[cfs]Time Series Link DischargeLink DischargeRE*SRENTON.R18-03l1 (RE*SRENTON.R18-03 -> RE*SRENTON.R18-02) 98.66External TS 1SRENT002
APPENDICES
APPENDIX C –
Figure 5-2A through Figure 5-2S: 2012 Sewer Model Analysis Results
City of Renton 2015 Hydraulic Model Update
Summary Report Page C
APPENDICES
APPENDIX D –
Figure 5-3A through Figure 5-3W: Ultimate Sewer Model Analysis Results
City of Renton 2015 Hydraulic Model Update
Summary Report Page D
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix G
TM 1 - RAIN AND FLOW MONITORING AND
PROJECTIONS
TITLE | TM 1 | CLIENT
City of Renton
LRWWMP
Technical Memorandum ͭ
RAIN AND FLOW MONITORING &
PROJECTIONS
DRAFT | September ͮͬͭ͵
City of Renton
LRWWMP
Technical Memorandum ͭ
RAIN AND FLOW MONITORING & PROJECTIONS
DRAFT | September ͮͬͭ͵
This document is released for the
purpose of information exchange review
and planning only under the authority of
Daniel L. Reisinger, September ͮͬ, ͮͬͭ͵
Washington PE License No. ͱͯͲͱͳ.
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | iii
Contents
Technical Memorandum 1 Rain and Flow Monitoring & Projections 1-1
ͭ.ͭ Study Area ͭ‐ͭ
ͭ.ͮ Sewer Collection System Flows ͭ‐ͭ
ͭ.ͮ.ͭ Dry Weather Flow Components ͭ‐ͭ
ͭ.ͮ.ͮ Wet Weather Flow ͭ‐Ͱ
ͭ.ͯ Flow Monitoring Program ͭ‐ͳ
ͭ.ͯ.ͭ Program Description ͭ‐ͳ
ͭ.ͯ.ͮ Flow Monitoring Results ͭ‐ͭͮ
ͭ.ͯ.ͯ Dry Weather Flow Projections ͭ‐ͭͳ
ͭ.ͯ.Ͱ Wet Weather Flow Projections ͭ‐ͭ͵
Attachments
Attachment A ADS ͮͬͭʹ‐ͮͬͭ͵ Flow Monitoring Report
Attachment B ADWF Development Review Packet
Tables
Table ͭ.ͭ Flow Meter General Information ͭ‐ͳ
Table ͭ.ͮ Dry Weather Flow Summary ͭ‐ͭͯ
Table ͭ.ͯ Rainfall Event Summary for Calibration (ͮͬͭͳ‐ͮͬͭʹ) ͭ‐ͭͯ
Table ͭ.Ͱ Flow Meter Basins ADWF Development ͭ‐ͭʹ
Table ͭ.ͱ Wet Weather Flow Development ͭ‐ͮͬ
Figures
Figure ͭ.ͭ Study Area Boundary ͭ‐ͭ
Figure ͭ.ͮ Typical Wastewater Flow Components ͭ‐ͯ
Figure ͭ.ͯ Typical Sources of Inflow and Infiltration ͭ‐ͱ
Figure ͭ.Ͱ Typical Effects of Inflow and Infiltration ͭ‐Ͳ
Figure ͭ.ͱ Flow Monitoring Locations ͭ‐͵
Figure ͭ.Ͳ Flow Monitoring Schematic ͭ‐ͭͭ
Figure ͭ.ͳ Typical Weekday vs Weekend Dry Weather Flow Variation (MHͬͱͯͳ) ͭ‐ͭͰ
Figure ͭ.ʹ Typical Rainfall Activity over Flow Monitoring Period ͭ‐ͭͱ
CITY OF RENTON | TM 1 | LRWWMP
iv | SEPTEMBER ͮͬͭ͵ | DRAFT
Figure ͭ.͵ Rainfall Accumulation Plot ͭ‐ͭͲ
Figure ͭ.ͭͬ Example of Wet Weather Flow Response (MHͭͯͲͬ) ͭ‐ͭͳ
Figure ͭ.ͭͭ LRWWMP Design Storms ͭ‐ͭ͵
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | v
Abbreviations
ADWF Average Dry Weather Flow
BI base infiltration
BWF base wastewater flow
Carollo Carollo Engineers, Inc.
City City of Renton
d/D depth vs diameter
DEQ Department of Environmental Quality
DWF dry weather flow
gpd/ac gallons per day per acre
GWI Groundwater Infiltration
I/I Inflow and Infiltration
LRWWMP Long Range Wastewater Management Plan
mgd million gallons per day
PE Person Equivalent
PWWF Peak Wet Weather Flow
SSOs sanitary sewer overflows
TM Technical Memorandum
WWF wet weather flow
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͭ
Technical Memorandum 1
RAIN AND FLOW MONITORING & PROJECTIONS
This Technical Memorandum (TM) reviews the existing wastewater flows and presents the
projected wastewater flows for future conditions within the City of Renton’s (City) wastewater
collection system. Existing flows are based on data collected by ADS’s flow monitoring program
(further detail in Attachment A) and the Person Equivalent (PE) developed by Stantec (further
detail in Appendix F).
1.1 Study Area
The collection system area is served, owned and operated by the City. The City's existing
wastewater service area is illustrated in Figure ͭ.ͭ, and mostly follows City limits. The flow
projections for this study only include the portion of the system within the service area identified
in Figure ͭ.ͭ. The extent of the future wastewater service area matches the exiting wastewater
service area. No additional area will be included to the City's existing wastewater service area in
the ͮͬ‐year planning horizon. The Service Area boundary on Figure ͭ.ͭ will be called Study Area
for the remainder of this project.
1.2 Sewer Collection System Flows
Sewer collections systems are intended to convey sanitary flows from customers (dry weather
flow [DWF]), but frequently have additional flows from other sources (wet weather flow [WWF]).
The different flow components are described in the section below and illustrated in Figure ͭ.ͮ.
1.2.1 Dry Weather Flow Components
There are two primary components of DWF.
1.2.1.1 Base Wastewater Flow
The base wastewater flow (BWF) is the sanitary flow generated by routine water usage of the
City’s residential, commercial, and industrial customers. Conveying this flow is the primary
function of the collection system. The flow has a diurnal pattern that varies by customer.
Typically, a residential diurnal pattern has two peaks with the more pronounced peak following
the wake‐up hours of the day, and a less pronounced peak occurring in the evening. Commercial
and industrial patterns, though they vary depending on the type of use, typically have more
consistent higher flow patterns during business hours, and lower flows at night. Furthermore,
the diurnal flow pattern of a weekend may vary from the diurnal flow experienced during a
weekday.
142ND AVE SE144TH AVE SES 116TH ST
SE 196TH ST
NE 24TH ST
SE 148TH ST
172ND AVE SE88TH AVE SLAKE WASHINGTON BLVD NNE 21ST ST
UNION AVE NE121ST PL SESE 144TH ST
W JAMES ST
S 132ND ST BURNETT AVE NS 212TH WAYKLI
C
K
I
T
A
T
D
R
NE 19TH ST
S ORCAS ST
84TH AVE SEHARDIE AVE SWSOUTHCE
N
T
E
R
B
L
V
D
MAPL
E
V
A
L
L
E
Y
H
W
Y
S 208TH ST
120TH PL
SE
S 115TH PL
MAIN AVE SSE 141ST STTALBOT RD S84TH AVE S135TH AVE SES 1
3
0
T
H
P
L
CEDAR AVE S4TH AVE NSUNSET BLVD NE134TH AVE SEBENSON RD
S
S MORGAN ST
S FINDLAY ST
LINCOLN AVE NEHOQUIAM AVE NES LEO ST
SE 227TH PL
S 15TH STWILSON
AVE
S
S 134TH ST
160TH AVE SE126TH AVE SESE 218TH PL 148TH AVE SEN 30TH ST
S BANGOR ST
IN
T
E
R
U
R
B
A
N
A
V
E
S
S LUCILE ST
SR
5
1
8 W MERCER WAY112TH AVE SE94TH AVE SSE 179TH ST
S 190TH ST
S 178TH ST
120TH AVE SE130TH AVE SEW
A
T
E
R
S
A
V
E
S
59TH AVE SS 164TH ST 78TH AVE SES 115TH ST
76TH AVE SNE 7TH PL
S 130TH STCORNEL
L
A
V
E
S
S
O
M
E
R
S
E
T
B
L
V
D
S
E
CASCADE KY
127TH AVE SESE 60TH ST
EDMONDS AVE NEI-
5
FWY
SE 79TH
D
R
N 38TH ST
S
K
A
G
I
T
K
Y
CENTRAL AVE NNE 2ND ST
NE 12TH ST
S OTHELLO ST
NE 8TH ST
E JAMES ST
SE 56TH ST
NE 7TH ST
S LA
K
E
R
I
D
G
E
D
R
SE 192ND DR58TH AVE SS 200TH ST
S 116TH
P
L HARRINGTON AVE NES GRAHAM ST 143RD AVE SE100TH AVE SEBE
A
C
O
N
A
V
E
S
S MEAD ST
NE 6TH PL
131ST AVE SESE 235TH
S
T DUVALL AVE NES BRANDON ST
SE 64TH ST
SE 38TH ST
85TH PL SESE 145TH
P
L
S 2ND STLIND AVE NWSE 75TH PL
P
E
T
E
R
G
R
U
B
B
R
D
S
E
S HOLLY ST
155TH AVE SESE 61ST ST
104TH PL SE63RD AVE SSE 40TH
P
L
133RD AVE
SEWELLS AVE S137TH AVE
SE164TH WAY SEANACORTES AVE NE1
2
9
TH
P
L
S
E86TH AVE SE121ST AVE SESE 45TH ST
E MERCER WAYSE 200TH ST118TH AVE SE98TH AVE SREDMOND AVE NENE 6TH ST87TH AVE SS 124TH ST
SE 83
R
D
S
T
SE 158TH S
T
93RD AVE S52ND AVE SSE 46TH WAY
48TH AVE SSE 48TH DR
S 129TH
S
T 85TH AVE SSE 134TH ST
SE
1
7
0
T
H
S
T162ND AVE SE151ST AVE SES 19TH ST
164TH AVE SESE 46TH ST
OLYMPIA AVE NESE 160TH ST
S 14TH ST
S ROXBURY ST
W
E
S
T
L
A
K
E
S
A
M
M
A
M
I
S
H
P
K
W
Y
S
E
CRESTWOOD DR SMONROE AVE NE123RD AVE SEHAZEL AVE NS 117TH ST
W
A
B
A
S
H
A
V
E
S
128TH AVE SE54TH AVE SSE 183
R
D
D
RJERICHO AVE NESE 221ST ST 175TH AVE SESE 216TH ST
NE 9TH ST
S 220TH ST HOUSER WAY NKIRKLAND AVE NEN 5TH ST
N 6TH ST
S MYRTLE ST SE 71ST ST
SE PETRO
V
I
T
S
K
Y
R
D
66TH AVE SSE 223RD ST
SE 128TH ST
SE 156TH ST
124TH AVE SESE 244TH ST
SE 4TH ST
N 3RD ST
SE 73RD PL
S 127TH ST
S WILLOW ST
BREMERTON AVE NE168TH PL SESE 164TH ST
INDUSTRY DRFO
R
E
S
T
D
R
S
E
BRONSON WAY NES RYAN ST
S NORFOLK ST
TUKWILA PKWY
SE 228TH ST
SE 55TH ST
SE 142ND ST
S 3RD ST82ND AVE SESE CARR
R
D
S 216TH ST
S 128TH ST
SE 172ND ST
NE 16TH ST
SE R
E
N
T
O
N
-
I
S
S
A
Q
U
A
H
R
D
SE 202ND PL108TH AVE SE146TH AVE SE57TH AVE SSE 136TH STROSARIO PL NESE 116TH ST
SE 162ND ST
NE 22ND STAVALON DRSE 68TH ST
SE 40TH ST
SE 42ND ST
SE 72ND ST
S SU
N
N
Y
C
R
E
S
T
R
D
DIX
O
N
D
R
SFOREST AVE
SE
SE 212TH ST93RD AVE SESTRANDER BLVD
S 196TH ST
L
A
K
E
W
A
SH
ING
TON
B
L
VD
S
SE 138TH PLSW 4TH
P
L
SR 167SE 208TH ST 150TH AVE SENILE AVE NE104TH AVE SEN 10TH ST
VILL
A
G
E
P
A
R
K
D
R
S
E
S 218TH ST SOMERSET DR SEWEST
LAKE
DES
IRE
DR
SE177TH AVE SESE 224TH ST
S 112TH ST
SE 52ND S
T
ILWACO AVE NEBENSON DR SS 144TH ST
LIND AVE SW55TH AVE SNE 10TH STHIGHLAND DRMIL
L
AVE
S
S 212TH ST
SE 183RD ST
S 224TH ST
NE 23RD PL
ANDOVER PARK W50TH AVE S49TH AVE SS 113TH STSEWARD PARK AVE SNEWCASTLE GOLF CLUB
R
D
S HENDERSON ST
SE 47T
H
S
T
S 120TH ST
SE 219TH PL51ST AVE SNEW
C
A
S
T
L
E
W
A
Y
125TH AVE SESE 76TH ST
SHATTUCK AVE SPELLY AVE NSW 7TH ST 188TH AVE SES 121ST ST
S 237TH PL
N 29TH ST
53RD AVE SSE 51ST
S
T
129TH AVE SESE 233RD ST
SE 91ST ST
SE 176TH STBLAINE AVE NE127TH PL SESW 12TH ST
SE 223RD DR 161ST AVE SEHIGH AVE SSE 42ND PL
NE 4TH ST
SE 66TH ST
MONTEREY AVE NESE 225TH ST
SE LAKE YOUN
G
S
R
D
SE ALLEN RD
BURNETT AVE SSW 39TH ST
SE 221ST PL65TH AVE SSE FA
I
R
W
O
O
D
B
L
V
D
PARKSIDE WAY SEN 32ND ST
E SMITH ST
S LANGSTON RD
SOUTHCENTER PKWYL
A
K
E
S
I
D
E
B
L
V
D
E
SW 16TH ST
MINKLER BLVD 85TH AVE SEN 31ST ST
SW 10TH ST
S 192ND ST 171ST PL
SE
S 204TH ST
SE 5TH ST
SE 226TH ST
MERCER
W
O
O
D
D
R
SW 3RD P
L
SW SUNSET BLVD
SE 106TH ST
SE 192ND ST
68TH AVE S149TH AVE SESE 220TH PL77TH AVE SSE 80TH ST
78TH AVE S62ND AVE SSE 2ND PL
S
2
3
1
S
T
S
T47TH AVE SSE 180TH STPOWELL AVE SWS JUNEAU ST
SE 214TH ST171ST AVE SES 114TH ST
3RD AVE NSE 121ST PL
PARK AVE NSE 59TH ST89TH AVE SE88TH AVE SEGARDEN AVE NSE 186TH ST91ST AVE SE81ST AVE SE92ND AVE SE2ND AVE N1ST AVE NS TAFT ST
PASCO PL NENE SUNS
E
T
B
L
V
D
MACADAM RD
S136TH AVE SESE 241ST S
TMI
L
ITARY
RD
S
SE 80
T
H
W
A
Y
SE 188TH ST117TH AVE SES 50TH ST
S AVON ST
190TH AVE SE80TH AVE SESE 168TH ST
S 194TH ST
N 4TH ST
132ND AVE SE81ST PL SE116TH PL SE80TH AVE S102ND AVE SE126TH PL SEW SMITH ST
SE 65TH ST
UNION AVE SESE 110
T
H
S
T
SE 204TH ST
S PUGET DRRAIN
IER
AVE
N181ST AVE SE176TH AVE SE170TH PL
SE
S 160TH ST
SE 58TH ST
NE 3RD ST
SE 3RD PL
S 170TH ST
AIRPORT WAY
S TOBIN ST
SE 228TH PL
SE 4TH PL
SE 112TH ST
SE 49TH ST
SE 240TH ST
SE 184TH ST116TH AVE SEABERDEEN AVE NES 240TH ST
SW GRAD
Y
W
A
Y
64TH AVE SGRANT AVE SSE 149TH STISLAND CREST WAYALVORD AVE NS 32ND ST
SE 204TH WAY
R
E
N
T
O
N
A
V
E
S
SUNSET BLVD N56TH AVE
S
S 36TH PLOAKESDALE AVE SW180TH AVE SENE PARK DR
163RD PL SELOGAN AVE NSW 19TH ST
113TH AVE SESE 63RD ST
I-
4
0
5
FWY
RAINIER AVE S
PUGET DR SE50
T
H
P
L
S
SE
L
I
C
O
R
I
C
E
W
A
Y
NE 27TH ST
SE 44TH ST
COAL CREEK PKWY SE119TH AVE SESE
1
7
0
T
H
P
L
140T
H
W
A
Y
S
E
N 8TH ST
92ND AVE S80TH PL SESE 43RD ST
JONES AVE NE174TH AVE SEPATRIOT WAY SESE 232ND ST
SW 34TH ST
184TH AVE SE72ND AVE SLUMMI KY
106TH AVE SESW 41ST ST
S GRADY
W
A
Y FACTORIA BLVD SES 126TH STANDOVER PARK ES 228TH ST59TH PL SSE 53RD
PL
LAKEMONT BLVD SES 180TH ST
M
A
R
T
I
N
L
U
T
H
E
R
K
I
N
G
J
R
W
A
Y
S
S 188TH ST
SW 27TH ST
156TH AVE SE138TH AVE SE136TH PL SES 222ND ST
66T
H
L
N
S 152ND AVE SEWEST VALLEY HWY183RD AVE SESE 184TH PL
89TH AVE S16
6
T
H
W
A
Y
S
E
SE 8TH PL
W
O
O
D
S
I
D
E
D
R
S
ESR 599EAST VALLEY HWY SSE COU
G
A
R
M
O
U
N
T
A
I
N
D
R
SE MAY CRE
E
K
P
A
R
K
D
R
ORILLIA RD SSE 95TH WAY
SE 50TH ST
105TH AVE SES 199TH PL
6TH AVE NS 226TH STS 184TH PLSE 159TH PL
I-90 F
W
Y
RIPLEY LN SESE
1
7
1
S
T
W
A
Y
183RD WAY SE
SE 160TH PL
SW 43RD ST
56
T
H
P
L
S
SE ROYAL HILLS
D
R
SE 196TH D
R140TH AVE SESE
6
4
T
H
W
A
Y
154TH PL SERENTON-ISSAQUAH RD SENE 31ST ST
EAST VALLEY RDS 133RD ST
S 135TH ST
SE 65TH PL
N R
IVERS
IDE
DRNW VILLAGE PARK DRMONSTER RD SWM
U
N
A
O
M
E
M
O
R
I
A
L
D
R
SE NEW
P
O
R
T
W
A
Y
80TH PL
S
169
T
H
A
V
E
S
E
FRAGER RD
SRUSSELL RD SB
E
A
C
O
N
-
C
O
A
L
M
I
N
E
R
D
S
SE RENTON-MAPLE VA
L
L
E
Y
R
D
S
E
M
A
Y
V
A
L
L
E
Y
R
D
1
4
4
T
H
P
L
S
E
SE JONES RD
Last Revised: June 10, 2019
F:\KRCD DRIVE\Renton\9971A00\Study_Area.mxd
O
0 1 20.5
Miles
Legend
Study Area
Renton City Boundary
Urban Growth Boudary
Roads
Waterbodies
LRWWMP | TM01 | CITY OF RENTON
Study Area Boundry
Figure 1.1
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͯ
Figure ͭ.ͮ Typical Wastewater Flow Components
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐Ͱ | SEPTEMBER ͮͬͭ͵ | DRAFT
1.2.1.2 Dry Weather Groundwater Infiltration
Dry weather Groundwater Infiltration (GWI) will enter the sewer system when the relative depth
of the groundwater table is higher than the depth of the pipeline and the sanitary sewer pipe
allows infiltration through defects such as cracks, misaligned joints, and broken pipelines. Dry
weather GWI (or base infiltration) cannot easily be separated from BWF by flow measurement
techniques. Therefore dry weather GWI is typically grouped with BWF.
1.2.1.3 Average Dry Weather Flow
Average Dry Weather Flow (ADWF) is the average flow that occurs on a daily basis during the dry
weather season, and is estimated from the DWFs during the monitoring period. Based on the
flow monitoring, the ADWF is approximately ʹ.͵ͳ million gallons per day (mgd). The ADWF
serves as the baseline flow in the hydraulic model. Diurnal (ͮͰ‐hour) patterns are applied to
ADWFs, and cumulatively make up the flows experienced at the outfalls of the collection system.
The diurnal patterns utilized for the City’s collection system basins are developed in Section ͭ.ͯ
and described in detail in the ADS Flow Monitoring Report, Attachment A.
1.2.2 Wet Weather Flow
WWF includes two components:
ͭ. Inflow and Infiltration (I/I): The stormwater I/I response in the sewer system to rainfall is
seen immediately (inflow) or within hours after the storm (infiltration).
ͮ. GWI: Wet weather GWI is not specific to a single rainfall event, but rather to the effects
on the sewer system over the entire wet weather season. The depth of the groundwater
table rising above the pipe invert elevation causes GWI. Sewer pipes within close
proximity to a body of water can be greatly influenced by groundwater effects.
1.2.2.1 Inflow and Infiltration
Inflow is stormwater that enters the sewer system via a direct connection to the system, such as
roof drain and downspout connections, leaky manhole covers, and inappropriate storm drain
connections. Infiltration is stormwater that enters the sewer system by percolating through the
soil and then through defects in pipelines, manholes, and joints. Some of the most common
sources of I/I are shown in Figure ͭ.ͯ. The adverse effects of I/I entering the sewer system is that
it increases both the flow volume and peak flows such that the sewer system could be operating
at or above its capacity, as illustrated in Figure ͭ.Ͱ. If too much I/I enter the sewer system,
sanitary sewer overflows (SSOs) could occur.
LRWWMP | TM 1 | CITY OF RENTON DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͱ Figure ͭ.ͯ Typical Sources of Inflow and Infiltration
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐Ͳ | SEPTEMBER ͮͬͭ͵ | DRAFT
Figure ͭ.Ͱ Typical Effects of Inflow and Infiltration
Maximum Pipe Capacity
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͳ
1.2.2.2 Groundwater Infiltration
GWI, one of the components of I/I, is associated with extraneous water entering the sewer
system through defects in pipes and manholes while the ground is saturated during the wet
weather season. GWI is related to the condition of the sewer pipes, manholes, and groundwater
levels. GWI may occur throughout the year, although rates are typically higher in the late winter
and early spring in the Pacific Northwest.
1.3 Flow Monitoring Program
As part of the Scope of Services for this LRWWMP, Carollo Engineers, Inc. (Carollo) contracted
with ADS to conduct a temporary flow monitoring program within the City's sanitary sewer
collection system. The purposes of the flow monitoring program were to correlate actual
collection system flows to the hydraulic model predicted flows, evaluate the system's capacity,
and estimate basin I/I. The temporary flow monitoring data was collected for a period of
approximately Ͱ months from December ͮͮ, ͮͬͭͳ to April ͮͮ, ͮͬͭʹ. The "ADS Flow Monitoring
Report" prepared by ADS summarizes the flow monitoring program and was submitted to the
City as a stand‐alone report. A copy of the report is included in Attachment A.
1.3.1 Program Description
1.3.1.1 Flow Monitoring Sites and Tributary Areas
Eighteen (ͭʹ) sewer basins were monitored during the flow monitoring period. The meter sites
were selected to best isolate and model the critical areas and subareas within the sewer system.
The ͭʹ flow monitoring locations, as well as the area tributary to each site, are shown on
Figure ͭ.ͱ. Table ͭ.ͭ lists the flow monitoring locations and the diameters for the sewers where
the meters were installed. Figure ͭ.Ͳ provides a schematic illustrating the flow monitoring
locations to help understand how the basins connect. In the figure the color of the flow meter
represents the accuracy level of the data, blue meters have high quality data while green meters
moderate quality data that was considered acceptable for model calibration. The model inflows
from outside of the City’s collection system are indicated by the orange boxes.
Table ͭ.ͭ Flow Meter General Information
Meter ID/Manhole ID Pipe ID Pipe Diameter (in.) Pipe Slope (%)
MHͬͭͲͲ GMͬͬͳͳͰ ͭͮ ͬ.ͮͱ
MHͬͮʹͲ GMͬͬͲͰͰ ͭͬ ͬ.ͱ͵
MHͬͱͯͳ GMͬͯ͵ʹͯ ʹ ͵.͵ͭ
MHͭͯͲͬ GMͬͭͱͬͰ ͭͬ.ͳͱ ͬ.ͭ͵
MHͭͳͲͯ GMͬͮͮͮ͵ ͭͱ ͬ.ͭͲ
MHͮͭͭͲ GMͬͮʹͱͳ ͭͰ.ͱ ͬ.ͮͳ
MHͮͭͳͭ GMͬͮʹͯͮ ͭͭ.ͮͱ ͬ.ͭͰ
MHͮͮͱͮ GMͬͯͰͱͰ ͭʹ ͬ.ͮʹ
MHͮ͵͵͵ GMͬͰͭͬͬ ʹ ͯ.ͯͮ
MHͯͮͭͲ GMͬͯͳʹ͵ ͳ.ͯʹ ͬ.ͱͱ
MHͯͲͮͱ GMͬͬ͵Ͱͮ ͭͮ ͬ.ͯͮ
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐ʹ | SEPTEMBER ͮͬͭ͵ | DRAFT
Table ͭ.ͭ Flow Meter General Information (continued)
Meter ID/Manhole ID Pipe ID Pipe Diameter (in.) Pipe Slope (%)
MHͰͲͮʹ GMͬͭͳͳͲ ͭͬ.ͯʹ ͮ.͵ͱ
MHͰͲͰͲ GMͬͰͯʹͰ ʹ ͭͮ.ͬͮ
MHͱͯͬͮ GMͬͱͯͭͭ ͭͰ ͬ.ͳ
MHͱͱͬͱ GMͬͱͳͭͭ ͭͬ ͯ.͵
MHͱͱͭ͵ GMͬͱͳͰͰ ͭͬ.ͮͱ Ͱ.ͱͮ
MHͲͬͰͭ GMͬͱʹͰͮ ʹ Ͳ.ͭ
MHͲͳͬͰ GMͬͳͱͮͰ ͭͮ ͬ.ͬʹ
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú 3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú
3Ú3Ú
g`
g`
g`
g`
g`
g`
g`
g`
g`
g`g`
g`
g`g`
g`g`
g`
g`East Valley RdRain
ier
Ave
N
S 133rd St
Oakesdale Ave SWBenson
D
r
S
SW 7th St
140th Ave SENE Sunset
B
l
vd
§¨¦405
Maple
V
a
l
l
e
y
H
w
y 164th Ave SECedar River Trail
SE Jones Rd
Lake Youngs Service RdSE May Valley Rd
Union Ave NESE Petrovitsky Rd
§¨¦5
Shy CreekLiftstation
Devils ElbowLift Station
East ValleyLift Station
Talbot CrestLift Station
Dennys LiftStation
Long LiftStation
KensingtonCrest Lift Station
WedgewoodLift Station
WestviewLift Station
Lind AveLift Station
Lake Washington#2 Lift Station
CottonwoodLift Station
Lake Wash.Flush Lift Station
Stone GateLift Station
Falcon RidgeLift Station
Liberty LiftStation
Lake WashingtonBeach LiftStation Pipers BluffLift Station
Baxter LiftStation
Misty CoveLift Station
Airport LiftStation
MH6704
MH0166
MH0286
MH0537
MH6041
MH1360
MH1763
MH2116
MH2171
MH2252
MH5302
MH2999
MH5519
MH3216
MH3625
MH5505
MH4628
MH4646
Last Revised: September 06, 2019\\io-fs-1\Data\GIS\GISBackup\Renton\WaterSystemPlan2017\Flow_Monitoring_Locations.mxd
Figure 1.5FlowMonitoringLocations
O
0 10.5 Miles
Legend
g`Flow Monitoring Locations
Lift Station
3Ú City of Renton
3Ú King County
Gravity Pipeline By Diameter
< 8"
8"
10" - 18"
> 18"
City of Renton Force Main
King County Gravity Main
Study Area
Renton City Boundary
Roads
Waterbodies
Figure 1.5 Flow Monitoring Locations
LRWWMP | TM01 | CITY OF RENTON
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracyis not implied.
Data Sources: City of Renton
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͭͭ
Figure ͭ.Ͳ Flow Monitoring Schematic
1.3.1.2 Flow Monitoring Installation and Flow Calculation
ADS installed eighteen ADS Triton+TM Wireless Open Channel Flow Monitors. These meters use
a pressure transducer to collect depth readings and ultrasonic Doppler sensors on the probe to
determine the average fluid velocity. The flow meters used are non‐contact meters that use
radar to measure velocity and down‐looking ultrasonic sensors to measure depth. ADS selected
the optimal type of flow meter to use on a site‐to‐site basis based on the hydraulic
characteristics at each site, as well as other factors.
ADS conducted an analysis of the data retrieved from each flow meter, and made adjustments
as needed for calibration based on the field measurements. The flow at each meter was then
calculated at ͭͱ‐minute intervals based on the continuity equation:
Q = V x A
where,
Q = Pipeline flow rate, cfs
V = Average velocity, ft/s
A = Cross sectional flow area, ftͮ
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐ͭͮ | SEPTEMBER ͮͬͭ͵ | DRAFT
1.3.1.3 Rain Gauges
One rain gauge was installed by ADS to capture rainfall that occurred throughout the flow
monitoring program.
1.3.2 Flow Monitoring Results
This section summarizes the results of the flow monitoring program, including DWF data, rainfall
data, and WWF data. Data collected from flow meters MHͬͱͯͳ and MHͭͯͲͬ is presented
throughout this TM as an example of the type of data and the results from the flow monitoring
program. Refer to Attachment A for additional data summaries and other information
associated with the remaining meter sites.
1.3.2.1 Dry Weather Flow Data
During the flow monitoring period, depth and velocity data were collected at each meter at
ͭͱ‐minute intervals. Carollo aggregated the ͭͱ‐minute data to hourly data for use in the
hydraulic model.
ADWF was developed using the driest days from the flow monitoring period defined based on
the following set of minimum criteria:
Less than ͬ.ͭ in of rain in the previous day.
Less than ͬ.Ͱ in of rain in the previous ͯ days.
Less than ͭ.ͬ in of rain in the previous ͱ days.
Selected days must exhibit average‐day flows within ʹͱ percent to ͭͭͱ percent of the
average‐day flows of remaining dry days.
In addition, those dry days that exhibited unusual flow patterns were not used to
generate net dry day flow values for a basin.
Characteristic dry weather ͮͰ‐hour diurnal flow patterns for each site were developed based on
the hourly data. The hourly flow data were used to calibrate the hydraulic model for the
observed ADWFs during the flow monitoring period.
Typically, a diurnal pattern with mostly residential uses has two peaks with the more pronounced
peak following the wake‐up hours of the day, and a less pronounced peak occurring in the
evening. Commercial and industrial oriented‐patterns, though they vary depending on the type
of use, typically have more consistent higher flow patterns during business hours, and lower
flows at night. Hourly patterns for weekday and weekend flows vary and were separated to
better understand ADWF.
In addition, Carollo estimated the average weekday and weekend dry weather levels and
velocities at each site from the data provided by ADS, which are used in the ADWF calibration.
Figure ͭ.ͳ illustrates a typical variation of weekday and weekend flow in the City, which is based
on the data collection from MHͬͱͯͳ. Similar graphics associated with the remaining sites are
included in Attachment A. Table ͭ.ͮ summarizes the ADWFs at each meter, and the different
components of ADWF at each meter.
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͭͯ
Table ͭ.ͮ Dry Weather Flow Summary
Meter ID/
Manhole ID
Average Daily
Flow (mgd)
Minimum
Daily Flow
(mgd)
Maximum
Daily Flow
(mgd)
Base
Infiltration
Base
Infiltration/
ADWF (%)
MHͬͭͲͲ ͬ.ͬͳͲ ͬ.ͬͯͲ ͬ.ͭͯʹ ͬ.ͬͭͭ ͭͯ
MHͬͮʹͲ ͬ.ͯͳ͵ ͬ.ͮʹʹ ͬ.Ͱ͵ͬ ͬ.ͮͳͯ ͳͭ
MHͬͱͯͳ ͭ.ͲͳͲ ͭ.ͬ͵ͯ ͮ.ͭͭͮ ͬ.ʹͲͲ ͱͮ
MHͭͯͲͬ
(ͭͯͲͬ – ͰͲͮʹ)
ͬ.ͮͭͲ ͬ.ͬͯͲ ͯ.ͯͭͭ ͬ.ͬͬͬ <ͱ
MHͭͳͲͯ ͬ.ʹʹͲ ͬ.ͯͳʹ ͭ.ͮͰͯ ͬ.ͮʹͳ ͯͮ
MHͮͭͭͲ ͯ.ͬͯͯ ͮ.ͭͲͳ ͯ.ͰͳͲ ͭ.Ͳͱʹ ͱͱ
MHͮͭͳͭ ͬ.͵Ͳͮ ͬ.Ͱ͵ͯ ͭ.ͰͲͰ ͬ.ͯʹͱ ͯ͵
MHͮͮͱͮ ͯ.Ͱͯͯ ͮ.ͮͳͭ Ͱ.ͰͱͲ ͭ.Ͳͮ͵ Ͱʹ
MHͮ͵͵͵ ͬ.͵ͮʹ ͬ.ͲͰͲ ͭ.ͭͯͲ ͬ.ͱͲͭ Ͳͭ
MHͯͮͭͲ ͬ.ͮͲͯ ͬ.ͭͭͳ ͬ.ͯͳͭ ͬ.ͭͬͲ Ͱͬ
MHͯͲͮͱ
(ͯͲͮͱ – ͱͱͬͱ)
ͭ.ͳͭͳ ͬ.Ͳ͵ʹ ͮ.ͲͲͯ ͬ.ͮ͵͵ ͭͳ
MHͰͲͮʹ ͬ.ʹͲͰ ͬ.Ͳͮͯ ͭ.ͬͰͭ ͬ.ͱͰ͵ ͲͰ
MHͰͲͰͲ ͭ.ͱͯ͵ ͬ.͵ͬͯ ͭ.ͮͭͱ ͬ.ʹͯͰ ͱͯ
MHͱͯͬͮ ʹ.͵ͮʹ ͱ.Ͳͳͬ ͭͬ.Ͳͱͱ ͯ.ͮ͵Ͱ ͯͳ
MHͱͱͬͱ ͭ.ͭͭͲ ͬ.ʹʹͬ ͭ.ͮͲͭ ͬ.ͳʹ͵ ͳͭ
MHͱͱͭ͵ ͭ.Ͳʹͬ ͬ.͵ʹͱ ͮ.ͬͯ͵ ͬ.ͳͰʹ Ͱͱ
MHͲͬͰͭ ͬ.ͮͰͳ ͬ.ͬ͵ͬ ͬ.ͯͱͮ ͬ.ͬͳͰ ͯͬ
MHͲͳͬͰ ͬ.Ͳͬͳ ͬ.ͯͯͰ ͬ.ʹͯ͵ ͬ.ͮʹͬ ͰͲ
1.3.2.2 Rainfall Data
An important part of the study is the collection and analysis of rainfall data. One tipping bucket
type rain gauge was temporarily set up for this LRWWMP. Four significant rainfall events
occurred during the course of the flow monitoring period, as well as a few other relatively minor
events. The rainfall data recorded over the course of the flow monitoring program is illustrated in
Figure ͭ.ʹ. Figure ͭ.͵ illustrates the total accumulation of rainfall over the course of the flow
monitoring period for the ADS tipping bucket type rain gauge. Table ͭ.ͯ summarizes the total
rainfall recorded at the ADS rain gauge during the main rainfall event, as well as over the entire
flow monitoring period.
Table ͭ.ͯ Rainfall Event Summary for Calibration (ͮͬͭͳ‐ͮͬͭʹ)
Event ID Start Date End Date Duration
(hours)
Total
Rainfall (in)
Avg.
Rainfall
(in/day)
Peak
Rainfall
(in/hr)
ͭ ͭͮ/ͮͲ/ͭͳ ͭ/ͯ/ͭʹ ͮͭͲ ͮ.ͬͮ ͬ.ͮͮ ͬ.ͭͲ
ͮ ͭ/ͮͯ/ͭʹ ͮ/ͳ/ͭʹ ͯʹͰ Ͱ.Ͱͱ ͬ.ͮʹ ͬ.ͮͯ
ͯ Ͱ/Ͳ/ͭʹ Ͱ/ͮͮ/ͭʹ Ͱͬʹ ͱ.ͭͭ ͬ.ͯͬ ͬ.ͮͳ
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐ͭͰ | SEPTEMBER ͮͬͭ͵ | DRAFT
Figure ͭ.ͳ Typical Weekday vs Weekend Dry Weather Flow Variation (MHͬͱͯͳ)
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
01234567891011121314151617181920212223Hourly MultiplierHour
Weekday Diurnal Pattern
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHour
Weekend Diurnal Pattern
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͭͱ
Figure ͭ.ʹ Typical Rainfall Activity over Flow Monitoring Period
0
0.05
0.1
0.15
0.2
0.25
0.3
12/18/201712/25/20171/1/20181/8/20181/15/20181/22/20181/29/20182/5/20182/12/20182/19/20182/26/20183/5/20183/12/20183/19/20183/26/20184/2/20184/9/20184/16/20184/23/20184/30/2018Rainfall Intensity (inch/hour)
CITY OF RENTON | TM 1 | LRWWMP
Figure ͭ.͵ Rainfall Accumulation Plot
The storms presented in Table ͭ.ͯ, correspond to the most significant rainfall events that were
then used for model calibration. Additional storms did provide data in terms of the collection
system’s I/I response to WWF events, and is appropriate for I/I analysis and model calibration
purposes.
1.3.2.3 Wet Weather Flow Data
The flow monitoring data were also evaluated to determine how the collection system responds
to wet weather events. As mentioned above, the flow monitoring program captured three main
rainfall events. The rainfall event that occurred on April ͭͱ, ͮͬͭʹ was associated with the largest
I/I response during the flow monitoring period, and is the most appropriate to be used for wet
weather flow analysis.
Figure ͭ.ͭͬ shows an example of the wet weather response at MHͭͯͲͬ during the April ͮͬͭʹ
rainfall event. This figure also illustrates the volume of I/I that entered the system from the
collection system upstream of MHͭͯͲͬ. The light grey line is the base sanitary flow while the
dark blue line is the measured flow from the flow monitoring period. As can be seen in the figure,
discernible amounts of I/I do enter the system during wet weather events. Similar graphs were
generated for the remaining monitoring sites and can be found in Attachment B, as well as
capacity indicators in the collection system during the flow monitoring period, such as the depth
vs diameter (d/D) ratio.
ͭ‐ͭͲ | SEPTEMBER ͮͬͭ͵ | DRAFT
0.00
5.00
10.00
15.00
20.00
25.00
12/22/2017 1/22/2018 2/22/2018 3/22/2018 4/22/2018Cummulative Rainfall (in)
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͭͳ
Figure ͭ.ͭͬ Example of Wet Weather Flow Response (MHͭͯͲͬ)
1.3.3 Dry Weather Flow Projections
Developing an accurate estimate of the future quantity of wastewater generated at build‐out of
the collection system is an important step in maintaining and sizing sewer system facilities, for
both existing conditions and future scenarios.
GWI can be estimated for a sewer system by comparing ADWF and WWF at the various flow
monitoring locations. To estimate ADWF for more specific areas, such as individual wastewater
basins, ADWFs are typically estimated based on the PE’s contributing to flows and flow factors
developed for each land use type. These values were considered unchanged and PE’s were taken
from Stantec’s ͮͬͭͲ Model Update Report, Appendix F. This method is developed based on the
assumption that areas with similar land uses, such as low density residential parcels, produce
equivalent quantities of wastewater flow. System‐wide flows can be compared to known flows
at flow monitors, or at the treatment plant to verify accuracy. This method of estimating GWI is
an industry standard for planning and provides sufficiently accurate data for planning purposes.
1.3.3.1 Existing Average Dry Weather Flows and Existing Flow Factors
This section presents the existing flow data available for this LRWWMP. Overall ADWF, BWP,
and GWI were estimated using data from the Flow Monitoring Program for each of the eighteen
flow monitoring basins. After reviewing the flow monitoring data, BWP and BI were estimated
for each flow monitoring basin and were presented in Section ͭ.ͯ.ͮ.ͯ in Table ͭ.ͯ.
ADWFs were developed for each of the eighteen flow meters. Table ͭ.Ͱ lists the flow factors and
ADWF developed, while Figure ͭ.ͳ illustrates a typical variation of weekday and weekend flow in
the system, which is based on the data collection from Meter MHͬͱͯͳ. Similar graphs for each
meters site can be found in Attachment A.
0.00000
0.10000
0.20000
0.30000
0.40000
0.50000
0.600000.0
0.2
0.4
0.6
0.8
1.0
1.2
12/241/71/212/42/183/43/184/14/15Rain (inches/hour)Flow (mgd)Rain
ADWF
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐ͭʹ | SEPTEMBER ͮͬͭ͵ | DRAFT
Table ͭ.Ͱ Flow Meter Basins ADWF Development
Meter ID Total PE(ͭ) Flow Factor
(ft^ͯ/PE/day)
Existing
ADWF (mgd) Future PE Future ADWF
(mgd)
MHͬͭͲͲ ͮʹͲ ͱ.Ͳʹ ͬ.ͬͭ ͲͰͱ ͬ.ͬͯ
MHͬͮʹͲ ͭ,ͭʹͰ ͳ.ͰͰ ͬ.ͬͳ ͮ,ͬͰʹ ͬ.ͭͳ
MHͬͱͯͳ Ͱ,ͱͳͭ ͵.ͮͳ ͬ.ͯͮ ͳ,ͲͱͰ ͬ.ͱͭ
MHͭͯͲͬ ͮ,ͬͭ͵ ͭͯ.ͱ͵ ͬ.ͮͭ Ͳ,ͭͯͱ ͬ.ͬ͵
MHͭͳͲͯ ͯ,͵͵ͭ ͱ.ͳ ͬ.ͭͳ ͯ,ͳͱͳ ͬ.ͮͬ
MHͮͭͭͲ Ͱ,ͬͮͳ ͭ͵.ͬͯ ͬ.ͱͳ ͳ,ͯ͵ͳ ͬ.ͳͮ
MHͮͭͳͭ ͮ,ͮͬͳ ͭͬ.Ͱ͵ ͬ.ͭͳ ͯ,ͯͬͳ ͬ.ͮ͵
MHͮͮͱͮ ͭͭ,Ͱͬͱ ͳ.Ͳʹ ͬ.ͲͲ ͭʹ,ͱͮʹ ͭ.ͬʹ
MHͮ͵͵͵ ͮ,ͭͬͰ ͭͭ.ͯͮ ͬ.ͭʹ ͮ,ͭͱͬ ͬ.ͮͱ
MHͯͮͭͲ ͭ,Ͳͳͯ ͯ.͵ ͬ.ͬͱ ͮ,ͭͯͬ ͬ.ͬʹ
MHͯͲͮͱ ʹ,Ͳͬͬ ʹ.ͱͯ ͬ.ͱͱ ͭͯ,ʹͰͯ ͬ.ͳͰ
MHͰͲͮʹ ͭ,ͮͬͮ ͭʹ.ͯʹ ͬ.ͭͳ ͭ,ʹͭ͵ ͬ.ͮͰ
MHͰͲͰͲ ͮ,ͯͯͲ ͭͭ.ͳͯ ͬ.ͮͭ ͮ,ʹͬͱ ͬ.ͯͳ
MHͱͯͬͮ ͮ,ʹͬͱ ʹͬ.ͱͭ ͭ.Ͳ͵ ͳ,ͮͱͯ ͭ.ͮͱ
MHͱͱͬͱ ͮ,ͭʹͲ ͭͮ.͵ͮ ͬ.ͮͭ ͯ,ͭͯͳ ͬ.ͯͬ
MHͱͱͭ͵ ͯ,ͯͯʹ ͭͮ.ͱͮ ͬ.ͯͭ Ͱ,ͱͲͰ ͬ.ͰͲ
MHͲͬͰͭ ͭ,ͮͲͱ Ͱ.ͳ͵ ͬ.ͬͱ ͭ,ͳͮ͵ ͬ.ͬͱ
MHͲͳͬͰ ͮ,ͳͮͯ ͱ.ʹͭ ͬ.ͭͮ ͮ,ʹͱʹ ͬ.ͭͳ
Unmetered
Basins Ͳ͵,ͲͯͲ ͯ.ͮͱ ͭͰͱ,ͭͳͮ Ͳ.ͯͭ
Modeled
Total ͭͮͳ,ͱͱʹ ʹ.͵ͳ ͮͯͲ,͵ͯͭ ͭͯ.ͯ
Notes:
(ͭ) Total PE is not directly equivalent to City’s population, Chapter Ͱ, Stantec ͮͬͭͲ Model Update Report – Appendix F.
1.3.3.2 Projected Dry Weather Flows
Developing an accurate estimate of the future quantity of wastewater generated at build‐out of
the collection system is an important step in maintaining and sizing sewer system facilities, for
both existing conditions and future scenarios. GWI can be estimated for a sewer by comparing
ADWF and WWF at the various flow monitoring locations. To estimate ADWF for more specific
areas, such as individual wastewater basins, ADWFs are typically estimated based on the PE
contributing to flows and flow factors developed for each land use type.
The future build‐out ADWFs were developed by projecting the planning GWI to the build‐out
planning year land uses. The PE’s for each catchment were developed for existing and buildout
conditions and a constant flow factor was used to relate this to ADWF Additional information
can be found in Chapter Ͱ of the LRWWMP and Attachment F – Stantec’s Model Update Report.
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͭ‐ͭ͵
1.3.4 Wet Weather Flow Projections
1.3.4.1 Peak Wet Weather Flows and Design Storms
Peak wet weather flows (PWWF) in a wastewater collection system are caused by rainfall
dependent I/I. Peak hour flows can result in flows more than ten times the GWI, causing utilities
to construct high‐capacity infrastructure to convey and treat these extraneous flows.
Existing and projected PWWFs are predicted using the hydraulic model and design storm used
for this LRWWMP. This analysis uses four separate multi‐day, ͮͬ‐ͯͬ year recurrence design
storms, illustrated in Figure ͭ.ͭͭ. These storms were identified in the ͮͬͭͮ King County (KC) I/I
Study and correspond to the recurrence interval within historical KC rainfall. To represent typical
winter Pacific Northwest antecedent conditions, typical rainfall was added from historical data
prior to the design storm in the hydraulic model. Further detail on the development of the design
storm can be found in Appendix H, TM ͮ.
Figure ͭ.ͭͭ LRWWMP Design Storms
1.3.4.2 Future PWWF Assumptions
To predict future PWWF, I/I in the future service area must be defined. A direct inflow technique
is used. Instead of simulating I/I using an I/I unit hydrograph, I/I is simulated by assuming a
constant I/I flow factor per acre of new development. I/I flow factors can range from ͭ,ͬͬͬ to
over ͭͬ,ͬͬͬ gallons per day per acre (gpd/ac) in the northwest. An I/I Flow Factor of ͭ,ͱͬͬ gpd/ac
was selected for estimating I/I in areas of new development to reflect improved construction
methods and integrity of new materials. Additionally, this value also meets the Department of
Environmental Quality (DEQ) recommendation.
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 20406080100120Rainfall (in/hr)Hours
Design Storms
Nov‐98
Jan‐90
Nov‐90
Feb‐96
CITY OF RENTON | TM 1 | LRWWMP
ͭ‐ͮͬ | SEPTEMBER ͮͬͭ͵ | DRAFT
Existing pipe I/I is assumed to degrade over time, for the purpose of this LRWWMP, a value of
ͳ percent degradation per ͭͬ years was used. This corresponded to a ͮʹ percent degradation for
build out conditions in the model. The PWWF for buildout and current conditions at each of the
monitored sites and the entire system is shown in Table ͭ.ͱ.
Table ͭ.ͱ Wet Weather Flow Development
Meter ID Current Peak Wet Weather Flow
(mgd)
Buildout Peak Wet Weather Flow
(mgd)
MHͬͭͲͲ ͭ.ʹͲ ͮ.ͭ͵
MHͬͮʹͲ ͬ.ͯͭ ͬ.ͯͯ
MHͬͱͯͳ ͬ.ʹͳ ͬ.͵ʹ
MHͭͯͲͬ ͭ.͵ͯ ͮ.ͯͲ
MHͭͳͲͯ ͭ.ͬͭ ͭ.ͮͰ
MHͮͭͭͲ ͯ.ͳͭ Ͱ.ͬͯ
MHͮͭͳͭ ͭ.ͯͭ ͭ.ͱ͵
MHͮͮͱͮ Ͱ.ͳͳ ͱ.ʹͭ
MHͮ͵͵͵ ͬ.ʹͳ ͭ.ͬͮ
MHͯͮͭͲ ͬ.ͯͬ ͬ.ͯͲ
MHͯͲͮͱ ͮ.ͮͮ ͮ.ͱͭ
MHͰͲͮʹ ͭ.Ͱͳ ͭ.ʹͮ
MHͰͲͰͲ ͬ.ͱͱ ͬ.Ͳͬ
MHͱͯͬͮ ͯ.ͰͰ Ͱ.ͳͱ
MHͱͱͬͱ ͬ.͵ͭ ͭ.ͬͭ
MHͱͱͭ͵ ͬ.ʹͭ ͬ.͵ͬ
MHͲͬͰͭ ͬ.ͱͱ ͬ.Ͳʹ
MHͲͳͬͰ ͬ.ͱͱ ͬ.ͲͰ
Unmetered Basins ͮͲ.ͳʹ ͯͭ.͵Ͱ
Modeled Total ͱͰ.ͮͬ ͲͰ.ͳͰ
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment A
ADS ͮͬͭʹ‐ͮͬͭ͵ FLOW MONITORING REPORT
Renton, WA
Temporary Flow Monitoring and RDII
Analysis
December 22, 2017 – April 22, 2018
Report Submitted
May 29, 2018
May 29, 2018
Daniel Reisinger, P.E.
Carollo Engineering
1218 Third Ave, Suite 1600
Seattle, WA 98101
Re: City of Renton Results and Analysis of 2017/18 Flow Monitoring Data
Dear Mr. Reisinger,
Thank you for the opportunity to complete this flow monitoring work effort for Renton, WA.
Please find attached the electronic report of results and conclusions based on the flow
monitoring study conducted between December 2017 and April 2018.
Hydrographs and scattergraphs of the data are available in the report. The Excel raw and
edited data is being provided in addition to the report.
Daniel, we certainly look forward to other opportunities to work on wastewater flow
monitoring projects as they arise. If you have any questions regarding the content of this
report, please do not hesitate to call me at (206) 255 6904.
Sincerely,
Mike Pina
Senior Project Manager
mpina@idexcorp.com
Methodology
Introduction
Background
Carollo Engineers entered into agreement with ADS Environmental Services to conduct
flow monitoring at (18) eighteen metering points and (1) rain gauge located in the City of
Renton, WA. The study was contracted for a four month monitoring period. The
objective of this study was to measure depth, velocity, and quantify flows and identify
capacity restrictions. A basin map and drawings for the pump stations are available in
the appendix.
Project Scope
The scope of this study involved using temporary flow monitors to quantify wastewater flow
at the designated locations. Specifically, the study included the following key components.
Investigate the proposed flow-monitoring sites for adequate hydraulic conditions
Flow monitor installations
Flow monitor confirmations and data collections
Flow data analysis
I/I Analysis
Equipment installation was accomplished starting in December 22, 2017. The
monitoring period was completed on April 22, 2018.
Equipment and Methodology
Flow Quantification Methods
There are two main equations used to measure open channel flow: the Continuity Equation
and the Manning Equation. The Continuity Equation, which is considered the most accurate,
can be used if both depth of flow and velocity are available. In cases where velocity
measurements are not available or not practical to obtain, the Manning Equation can be used
to estimate velocity from the depth data based on certain physical characteristics of the pipe
(i.e. the slope and roughness of the pipe being measured). However, the Manning equation
assumes uniform, steady flow hydraulic conditions with non-varying roughness, which are
typically invalid assumptions in most sanitary sewers. The Continuity Equation was used
exclusively for this study.
Continuity Equation
The Continuity Equation states that the flow quantity (Q) is equal to the wetted cross-
sectional area (A) multiplied by the average velocity (V) of the flow.
Q = A * V
This equation is applicable in a variety of conditions including backwater, surcharge, and
reverse flow. Most modern flow monitoring equipment, including the ADS Models, measure
both depth and velocity and therefore use the Continuity Equation to calculate flow
quantities.
Flow Monitoring Equipment
The ADS Triton+ monitor was selected for this project. This flow monitor is an area
velocity flow monitor that uses both the Continuity and Manning's equations to
measure flow.
The ADS Triton+ monitor consists of data acquisition sensors and a battery-powered
microcomputer. The microcomputer includes a processor unit, data storage, and an on-
board clock to control and synchronize the sensor recordings. The monitor was
programmed to acquire and store depth of flow and velocity readings at 1-minute intervals.
The Triton+ monitor features cross-checking using multiple technologies in each sensor
for continuous running of comparisons and tolerances. The sensor option used for this
project was the peak combo sensor.
ThePeakComboSensor installed at the bottom of the pipe includes three types of data
acquisition technologies. The up looking ultrasonic depth uses sound waves from two
independent transceivers to measure the distance from the sensor upward toward the flow
surface; applying the speed of sound in the water and the temperature measured by sensor
to calculate depth. The pressure depth is calculated by using a piezo-resistive crystal to
determine the difference between hydrostatic and atmospheric pressure. The pressure
sensor is temperature compensated and vented to the atmosphere through a desiccant filled
breather tube. To obtain peak velocity, the sensor sends an ultrasonic signal at an angle
upward through the widest cross-section of the oncoming flow. The signal is reflected by
suspended particles, air bubbles, or organic matter with a frequency shift proportional to the
velocity of the reflecting objects. The reflected signal is received by the sensor and
processed using digital spectrum analysis to determine the peak flow velocity.
Installation
Installation of flow monitoring equipment typically proceeds in four steps. First, the site is
investigated for safety and to determine physical and hydraulic suitability for the flow
monitoring equipment. Second, the equipment is physically installed at the selected
location. Third, the monitor is tested to assure proper operation of the velocity and depth of
flow sensors and verify that the monitor clock is operational and synchronized to the
master computer clock. Fourth, the depth and velocity sensors are confirmed and line
confirmations are performed. A typical flow monitor installation is shown in Figure 1.
The installations depicted in Figure 1 are typical for circular or oval pipes up to
approximately 104-inches in diameter or height. In installations into pipes 42-inches or less
in diameter, combo sensors are mounted on an expandable stainless steel ring and
installed one to two pipe diameters upstream of the pipe/manhole connection in the
incoming sewer pipe. This reduces the effects of turbulence and backwater caused by the
connection. In pipes larger than 42 inches in diameter, a special installation is made using
two sections of the ring installed one to two feet upstream of the pipe/manhole connection;
one bolted to the crown of the pipe for the surface combo sensor and the other bolted to
the bottom of the pipe (bolts are usually placed just above the water
line) to hold the peak combo sensor.
Figure 1 Typical Installation
Large Pipe ( > 42" Diameter) Small Pipe ( 8" to 42" Diameter)
Data Collection, Confirmation, and Quality Assurance
During the monitoring period data collects from the meters were done remotely via
wireless connection. Quality assurance taken to assure the integrity of the data
collected included:
Measure Power Supply: The monitor is powered by a dry cell battery pack. Power
levels are recorded and battery packs replaced, if necessary. A separate battery
provides back-up power to memory, which allows the primary battery to be replaced
without the loss of data.
Perform Pipe Line Confirmations and Confirm Depth and Velocity: Once
equipment and sensor installation is accomplished, a member of the field crew
descends into the manhole to perform a field measurement of flow rate, depth and
velocity to confirm they are in agreement with the monitor. Since the ADS V-3 velocity
sensor measures peak velocity in the wetted cross-sectional area of flow, velocity
profiles are also taken to develop a relationship between peak and average velocity in
lines that meet the hydraulic criteria.
Measure Silt Level: During site confirmation, a member of the field crew descends
into the manhole and measures and records the depth of silt at the bottom of the
pipe. This data is used to compute the true area of flow.
Confirm Monitor Synchronization: The field crew and data analyst checks the
flow monitor's clock for accuracy.
Upload and Review Data: Data collected by the monitor is uploaded and reviewed
for comparison with previous data. All readings are checked for consistency and screened
for deviations in the flow patterns, which may indicate system anomalies or equipment
failure.
Data Analysis and Presentation
Data Analysis
A flow monitor is typically programmed to collect data at either 15-minute or 5-minute
intervals throughout the monitoring period. The monitor stores raw data consisting of (1)
the updepth (distance from sensor to top of flow) for each active ultrasonic depth
sensor, (2) the peak velocity and (3) the pressure depth. The data is imported into
ADS's proprietary software and is examined by a data analyst to verify its integrity. The
data analyst also reviews the daily field reports and site visit records to identify
conditions that would affect the collected data.
Velocity profiles and the line confirmation data developed by the field personnel are
reviewed by the data analyst to identify inconsistencies and verify data integrity. Velocity
profiles are reviewed and an average to peak velocity ratio is calculated for the site. This
ratio is used in converting the peak velocity measured by the sensor to the average
velocity used in the Continuity equation. The data analyst selects which depth sensor
entity will be used to calculate the final depth information. Silt levels present at each site
visit are reviewed and representative silt levels established.
Occasionally the velocity sensor's performance may be compromised resulting in invalid
readings sporadically during the monitoring period. This is generally caused by excessive
debris (silt) blocking the sensor's crystals, shallow flows (~< 2") that may drop below the top
of the sensor or very clear flows lacking the particles needed to measure rate. In order to
use the Continuity equation to quantify flow during during such brief (in respect to overall
study duration) periods of velocity sensor "fouling", a Sr. Analyst and/or Engineer will use the
site's historical pipe curve (depth vs. velocity) data along with valid field confirmations to
reconstitute and replace the false velocity recordings with expected velocity readings for a
given historical depth along the curve.
Selections for the above parameters can be constant or can change during the
monitoring period. While the data analysis process is described in a linear manner, it
often requires an iterative approach to accurately complete.
REN_MH0166
Located At: Springbrook Trail, Renton (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 11.5”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the downward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 0.65 0.00 0.000 6%
Maximum 28.29 3.47 1.429 100%
Average 1.74 0.77 0.070 15%
Latitude: 47.470098°
Longitude:-122.235586°
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
PVC
20''
NormalUnbolted
20''
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.25''
Peak Velocity (fps)
Silt (in)
~10'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Renton.Carollo.I&I.WA17
LightWalk (Wooded)
Site Access Details:
Site Address /Location:
Site Name
Springbrook Trail, Renton. East of Wastewater Treatment Area.
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.20.17
Upstream 0-5 FT Manhole
MH0166 Other
Map
Flow Monitoring
Site Report
Temporary
12.00'' x 12.00''
REN_MH0166
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe ShapeAccess / Park SW 7th St Outside Treatment plant and
walkdown trail/ bike path. Located just off trail.
Sensors / Devices:
12.00'' x 12.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
10:00:00 AM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~3.50''
Velocity Sensor Offset (in)
~ 1 FPS
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Manhole frame slightly elevated. White fungus of some kind growing in pipe.
Smooth, slow flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Additional Photos
Flow Direction
Monitoring Point
Location
Upstream Downstream Overflow
Top Down Location Location
ADS Environmental Services
Pipe Height: 11.50
REN_MH0166\mp1\DFINAL (inches) REN_MH0166\mp1\VFINAL (feet/sec) REN_MH0166\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 1:25 0.9 12:40 4.2 1.5 11:05 0.3 12:40 2.7 0.9 1:25 0.006 12:40 0.428 0.046 0.046 0.10
12/23/2017 23:45 0.7 11:35 3.6 1.0 23:50 0.0 11:35 2.4 0.4 23:50 0.000 11:35 0.308 0.012 0.012 0.00
12/24/2017 17:40 0.7 0:55 3.3 0.9 18:15 0.0 0:55 2.3 0.3 18:15 0.000 0:55 0.266 0.011 0.011 0.00
12/25/2017 6:25 0.7 15:45 3.8 1.2 6:25 0.0 15:45 2.5 0.5 6:25 0.000 15:45 0.356 0.022 0.022 0.14
12/26/2017 7:10 0.9 20:30 3.6 1.3 4:45 0.2 20:30 2.4 0.7 4:45 0.005 20:30 0.303 0.026 0.026 0.17
12/27/2017 4:55 0.7 11:45 3.5 1.1 4:55 0.0 11:45 2.4 0.5 4:55 0.000 11:45 0.293 0.017 0.017 0.00
12/28/2017 7:45 1.2 20:55 4.3 1.6 1:00 0.4 20:55 2.8 1.0 1:00 0.013 20:55 0.468 0.048 0.048 0.25
12/29/2017 23:20 1.8 11:05 9.4 4.1 23:20 1.1 10:45 3.5 2.5 23:20 0.054 11:05 1.429 0.436 0.436 1.57
12/30/2017 8:15 0.9 19:20 4.2 1.6 8:05 0.3 19:20 2.7 1.0 8:05 0.006 19:20 0.435 0.059 0.059 0.02
12/31/2017 23:30 1.0 6:10 3.7 1.3 22:20 0.3 16:30 2.5 0.6 22:30 0.006 6:10 0.336 0.023 0.023 0.00
ReportAvg 1.6 0.8 0.070
ReportTotal 0.700 2.25
ADS Environmental Services
Pipe Height: 11.50
REN_MH0166\mp1\DFINAL (inches) REN_MH0166\mp1\VFINAL (feet/sec) REN_MH0166\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 13:05 0.9 5:20 3.5 1.2 11:15 0.3 5:20 2.4 0.5 11:15 0.006 5:20 0.294 0.018 0.018 0.00
1/2/2018 2:55 0.9 7:25 3.7 1.2 23:00 0.2 7:25 2.5 0.6 1:35 0.003 7:25 0.335 0.020 0.020 0.01
1/3/2018 5:20 0.8 13:25 2.6 1.2 5:20 0.2 17:00 1.9 0.6 5:20 0.002 13:25 0.155 0.022 0.022 0.00
1/4/2018 7:20 0.8 23:40 3.4 1.2 22:30 0.2 23:35 2.4 0.6 22:30 0.003 23:40 0.279 0.025 0.025 0.09
1/5/2018 23:15 1.1 10:40 5.1 2.2 23:15 0.2 10:40 3.0 1.5 23:15 0.006 10:40 0.628 0.118 0.118 0.42
1/6/2018 23:40 1.1 5:40 4.4 2.2 23:35 0.4 5:40 2.7 1.5 23:40 0.010 5:40 0.461 0.135 0.135 0.24
1/7/2018 6:40 1.0 21:25 2.3 1.5 3:55 0.3 19:05 1.9 0.9 6:40 0.007 19:05 0.128 0.044 0.044 0.38
1/8/2018 21:00 1.2 9:30 7.4 1.6 19:05 0.5 9:25 3.4 0.9 19:05 0.016 9:35 1.095 0.053 0.053 0.14
1/9/2018 12:05 1.5 15:10 6.6 2.2 8:10 0.8 15:40 3.2 1.6 8:10 0.031 15:10 0.919 0.125 0.125 0.46
1/10/2018 6:40 1.4 23:20 3.3 1.7 6:40 0.8 20:10 2.3 1.3 6:40 0.025 23:20 0.252 0.066 0.066 0.22
1/11/2018 0:45 2.0 15:00 13.6 5.9 15:45 0.5 12:15 3.3 2.4 5:25 0.068 18:05 1.179 0.600 0.600 1.04
1/12/2018 16:15 1.1 0:00 4.2 1.8 23:45 0.6 0:00 2.7 1.4 23:45 0.016 0:00 0.434 0.083 0.083 0.20
1/13/2018 2:45 1.0 17:05 15.6 1.6 17:05 0.3 17:35 3.2 0.8 2:45 0.008 17:25 1.177 0.054 0.054 0.02
1/14/2018 23:50 1.0 13:30 1.3 1.1 22:45 0.3 13:25 0.9 0.5 22:45 0.006 13:30 0.026 0.013 0.013 0.00
1/15/2018 22:55 1.0 13:15 1.8 1.1 0:40 0.2 13:15 1.3 0.5 0:40 0.005 13:15 0.065 0.014 0.014 0.04
1/16/2018 23:55 1.0 1:35 2.4 1.4 23:30 0.2 1:50 1.7 0.8 23:30 0.004 1:35 0.117 0.032 0.032 0.26
1/17/2018 2:50 0.9 18:25 7.0 2.4 7:50 0.4 11:10 3.3 1.5 7:35 0.008 18:20 0.979 0.196 0.196 0.79
1/18/2018 23:50 1.8 5:40 6.9 3.4 23:20 1.0 5:40 3.2 2.2 23:20 0.051 5:40 0.979 0.299 0.299 0.40
1/19/2018 21:05 1.4 15:40 2.7 1.7 21:00 0.7 15:40 2.2 1.2 21:00 0.023 15:40 0.189 0.059 0.059 0.10
1/20/2018 23:45 1.3 4:10 2.8 1.6 17:10 0.5 4:05 2.2 1.0 17:10 0.017 4:05 0.204 0.043 0.043 0.10
1/21/2018 16:15 1.3 17:05 7.2 1.6 11:40 0.6 17:00 3.2 1.0 11:40 0.018 17:15 0.978 0.061 0.061 0.16
1/22/2018 23:55 1.4 6:05 5.9 2.4 23:35 0.6 6:05 3.1 1.6 23:35 0.022 6:05 0.764 0.149 0.149 0.34
1/23/2018 4:00 1.3 16:15 6.9 3.2 9:00 0.7 16:00 3.4 1.9 1:15 0.022 16:10 1.022 0.295 0.295 0.79
1/24/2018 7:20 1.7 16:25 28.3 6.7 19:55 0.0 22:25 3.3 1.9 19:55 0.000 21:45 1.417 0.376 0.376 0.51
1/25/2018 6:15 1.3 10:50 5.0 2.2 6:15 0.7 10:50 2.9 1.5 6:15 0.020 10:50 0.594 0.119 0.119 0.14
1/26/2018 7:55 1.3 12:05 5.5 2.3 7:55 0.7 12:30 3.1 1.6 7:55 0.021 12:30 0.692 0.145 0.145 0.36
1/27/2018 23:55 1.2 1:35 7.0 3.2 21:05 0.4 2:30 3.4 2.0 21:05 0.011 1:40 1.027 0.290 0.290 0.61
1/28/2018 23:55 1.1 0:10 4.5 1.7 14:10 0.4 0:10 2.9 1.0 16:10 0.011 0:10 0.517 0.060 0.060 0.07
1/29/2018 1:45 1.1 16:05 7.5 3.9 4:10 0.3 14:35 3.5 2.0 4:10 0.007 14:35 1.141 0.441 0.441 0.90
1/30/2018 23:55 1.2 1:05 4.2 1.8 23:15 0.4 3:40 2.6 1.1 23:55 0.011 3:40 0.403 0.067 0.067 0.00
1/31/2018 3:55 1.0 5:00 3.6 1.4 4:45 0.3 15:25 2.5 0.7 4:45 0.006 15:25 0.315 0.030 0.030 0.00
ReportAvg 2.2 1.2 0.131
ReportTotal 4.053 8.79
ADS Environmental Services
Pipe Height: 11.50
REN_MH0166\mp1\DFINAL (inches) REN_MH0166\mp1\VFINAL (feet/sec) REN_MH0166\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 4:05 1.1 4:50 3.4 1.9 5:55 0.4 21:35 2.3 1.0 4:05 0.010 4:50 0.266 0.069 0.069 0.66
2/2/2018 6:35 1.4 8:20 7.4 1.9 23:50 0.5 8:10 3.4 1.0 23:50 0.018 8:20 1.074 0.067 0.067 0.04
2/3/2018 0:10 1.5 19:05 3.2 1.9 4:35 0.5 19:10 2.2 1.0 9:15 0.018 19:10 0.237 0.057 0.057 0.31
2/4/2018 20:10 1.4 7:45 2.4 1.5 20:10 0.7 7:45 1.6 0.8 20:10 0.024 7:45 0.122 0.034 0.034 0.02
2/5/2018 22:45 1.1 13:30 2.3 1.5 5:35 0.4 13:30 1.1 0.7 22:45 0.010 13:30 0.078 0.026 0.026 0.04
2/6/2018 23:35 1.1 10:55 8.4 1.5 23:35 0.3 10:55 3.2 0.7 23:35 0.007 10:55 1.224 0.059 0.059 0.00
2/7/2018 5:35 1.0 10:00 1.9 1.2 5:35 0.2 9:55 1.2 0.5 5:35 0.005 9:55 0.063 0.014 0.014 0.00
2/8/2018 5:20 1.0 15:20 1.9 1.2 5:20 0.2 21:50 1.1 0.5 5:20 0.004 21:50 0.056 0.015 0.015 0.09
2/9/2018 23:20 0.9 14:25 3.5 1.2 23:20 0.1 14:25 2.3 0.4 23:20 0.001 14:25 0.295 0.019 0.019 0.01
2/10/2018 19:05 0.8 12:00 1.0 0.8 0:30 0.0 12:00 0.2 0.0 0:30 0.000 12:00 0.004 0.001 0.001 0.01
2/11/2018 16:10 0.8 12:20 1.5 0.8 0:00 0.0 12:25 0.6 0.0 0:00 0.000 12:20 0.022 0.001 0.001 0.00
2/12/2018 2:20 0.8 16:30 1.4 1.0 0:00 0.0 16:25 0.7 0.2 0:00 0.000 16:25 0.025 0.007 0.007 0.00
2/13/2018 2:05 0.8 23:55 2.2 1.1 1:20 0.0 23:55 1.7 0.3 1:20 0.000 23:55 0.107 0.011 0.011 0.17
2/14/2018 23:55 1.0 1:15 2.5 1.5 6:10 0.2 0:05 1.7 0.7 8:45 0.005 1:15 0.127 0.031 0.031 0.15
2/15/2018 6:55 0.8 10:30 6.7 1.4 6:55 0.0 10:30 3.2 0.4 6:55 0.001 10:30 0.941 0.036 0.036 0.00
2/16/2018 3:30 1.0 3:40 2.4 1.4 3:30 0.2 3:40 1.4 0.5 3:30 0.005 3:40 0.106 0.020 0.020 0.15
2/17/2018 4:35 1.0 9:30 3.3 1.6 4:35 0.2 6:15 1.9 0.7 4:35 0.004 9:30 0.218 0.041 0.041 0.32
2/18/2018 23:50 1.0 16:15 1.2 1.1 18:50 0.2 16:05 0.5 0.3 23:50 0.003 16:05 0.013 0.007 0.007 0.01
2/19/2018 3:00 0.9 10:15 7.5 1.3 23:55 0.0 10:25 3.2 0.5 23:55 0.000 10:15 1.083 0.033 0.033 0.00
2/20/2018 6:40 1.0 15:50 4.5 1.4 6:40 0.2 15:50 2.5 0.4 6:40 0.003 15:50 0.435 0.017 0.017 0.00
2/21/2018 5:35 0.9 16:10 1.7 1.3 5:35 0.1 16:10 0.6 0.4 5:35 0.003 16:10 0.028 0.012 0.012 0.00
2/22/2018 4:25 1.0 9:30 1.9 1.3 4:25 0.2 9:30 0.7 0.4 4:25 0.004 9:30 0.038 0.012 0.012 0.07
2/23/2018 7:25 0.8 11:30 6.8 1.5 5:55 0.0 11:30 3.2 0.5 5:55 0.000 11:30 0.974 0.040 0.040 0.01
2/24/2018 2:10 1.5 10:20 2.8 1.6 0:30 0.4 10:35 1.2 0.5 0:30 0.015 10:25 0.106 0.023 0.023 0.13
2/25/2018 1:05 1.5 5:50 4.0 1.9 23:55 0.4 5:50 2.2 0.7 23:55 0.016 5:50 0.323 0.049 0.049 0.11
2/26/2018 22:05 1.5 9:00 2.3 1.7 7:05 0.3 15:30 0.8 0.5 7:05 0.012 9:00 0.053 0.024 0.024 0.00
2/27/2018 4:30 1.5 16:10 2.1 1.7 23:55 0.4 16:10 0.8 0.5 23:55 0.014 16:10 0.048 0.025 0.025 0.19
2/28/2018 3:45 1.4 22:25 4.3 1.8 3:55 0.2 22:25 2.4 0.6 3:55 0.008 22:25 0.404 0.039 0.039 0.35
ReportAvg 1.4 0.5 0.028
ReportTotal 0.786 2.84
ADS Environmental Services
Pipe Height: 11.50
REN_MH0166\mp1\DFINAL (inches) REN_MH0166\mp1\VFINAL (feet/sec) REN_MH0166\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 23:55 1.1 16:20 7.5 1.5 8:00 0.2 16:25 3.2 0.5 23:55 0.006 16:20 1.078 0.031 0.031 0.01
3/2/2018 3:25 1.0 5:30 2.6 1.5 3:25 0.2 4:50 1.2 0.4 3:25 0.003 4:50 0.101 0.020 0.020 0.07
3/3/2018 23:55 1.0 18:50 1.6 1.2 17:15 0.2 15:30 0.5 0.3 23:55 0.004 18:50 0.020 0.007 0.007 0.00
3/4/2018 15:55 1.0 16:45 2.9 1.1 15:55 0.2 16:45 1.3 0.3 15:55 0.003 16:45 0.130 0.009 0.009 0.12
3/5/2018 6:55 1.0 15:00 7.6 1.5 6:55 0.2 15:10 3.2 0.4 6:55 0.003 15:00 1.089 0.036 0.036 0.00
3/6/2018 7:25 0.9 18:20 2.8 1.3 6:25 0.1 18:20 1.5 0.3 7:25 0.002 18:20 0.141 0.011 0.011 0.00
3/7/2018 7:00 1.1 10:00 7.5 1.5 7:00 0.2 10:05 3.2 0.5 7:00 0.005 10:00 1.083 0.030 0.030 0.03
3/8/2018 7:25 0.9 11:05 6.5 1.7 9:05 0.1 11:05 3.1 0.7 7:25 0.003 11:05 0.884 0.053 0.053 0.37
3/9/2018 23:55 1.0 10:00 7.4 1.6 23:55 0.2 9:55 3.2 0.5 23:55 0.003 10:00 1.061 0.043 0.043 0.00
3/10/2018 21:05 0.8 3:10 3.6 1.2 19:15 0.0 3:05 2.1 0.3 19:15 0.000 3:10 0.272 0.012 0.012 0.00
3/11/2018 17:30 0.8 22:15 1.0 0.8 0:00 0.0 22:15 0.2 0.0 0:00 0.000 22:15 0.003 0.000 0.000 0.00
3/12/2018 4:45 0.8 17:35 7.2 1.3 0:00 0.0 17:40 3.2 0.4 0:00 0.000 17:35 1.032 0.029 0.029 0.00
3/13/2018 5:55 0.8 13:40 6.3 1.5 2:20 0.0 17:25 3.0 0.5 2:20 0.000 13:40 0.797 0.035 0.035 0.31
3/14/2018 6:15 0.9 13:45 7.4 1.4 4:40 0.1 13:45 3.2 0.4 6:15 0.002 13:45 1.071 0.027 0.027 0.04
3/15/2018 0:35 0.9 9:35 3.6 1.5 0:25 0.1 9:35 2.0 0.4 0:35 0.002 9:35 0.257 0.020 0.020 0.00
3/16/2018 4:30 0.8 6:55 3.4 1.2 0:05 0.0 6:55 1.9 0.3 0:05 0.000 6:55 0.236 0.010 0.010 0.00
3/17/2018 23:30 0.8 13:25 1.3 1.0 4:10 0.0 13:25 0.3 0.1 4:10 0.000 13:25 0.010 0.003 0.003 0.00
3/18/2018 3:00 0.8 14:05 1.8 1.1 0:00 0.0 13:50 0.6 0.2 0:00 0.000 13:50 0.025 0.007 0.007 0.00
3/19/2018 23:55 1.1 14:55 7.3 1.5 13:35 0.2 14:50 3.2 0.4 23:55 0.005 14:55 1.057 0.032 0.032 0.00
3/20/2018 23:55 0.8 17:30 6.0 1.2 23:10 0.0 17:30 2.8 0.4 23:10 0.000 17:30 0.730 0.018 0.018 0.00
3/21/2018 3:50 0.7 10:45 5.1 1.1 0:00 0.0 10:45 2.8 0.3 0:00 0.000 10:45 0.588 0.012 0.012 0.10
3/22/2018 6:05 0.7 12:00 6.9 1.6 0:00 0.0 12:05 3.3 0.5 0:00 0.000 12:00 0.987 0.057 0.057 0.48
3/23/2018 5:25 0.8 8:45 6.5 1.9 0:00 0.0 8:45 3.1 0.7 0:00 0.000 8:45 0.888 0.098 0.098 0.31
3/24/2018 23:55 0.8 5:15 2.4 1.3 15:40 0.0 5:25 1.6 0.4 15:40 0.000 5:25 0.119 0.018 0.018 0.28
3/25/2018 7:50 0.8 10:20 1.7 1.0 0:00 0.0 10:20 0.9 0.1 0:00 0.000 10:20 0.037 0.003 0.003 0.01
3/26/2018 2:35 0.8 9:10 6.4 1.5 0:00 0.0 9:05 3.2 0.6 0:00 0.000 9:05 0.867 0.059 0.059 0.17
3/27/2018 5:10 1.0 7:15 6.1 1.5 4:35 0.0 7:15 3.1 0.6 4:35 0.000 7:15 0.792 0.036 0.036 0.02
3/28/2018 23:55 0.8 10:15 4.1 1.3 5:25 0.0 10:10 2.5 0.4 5:25 0.000 10:15 0.396 0.021 0.021 0.01
3/29/2018 5:15 0.7 10:25 9.9 2.1 0:00 0.0 9:30 3.3 0.8 0:00 0.000 10:30 1.311 0.167 0.167 0.00
3/30/2018 5:25 0.7 11:40 6.0 1.2 0:00 0.0 11:40 3.0 0.3 0:00 0.000 11:40 0.773 0.023 0.023 0.00
3/31/2018 5:10 0.9 12:25 1.1 1.0 0:35 0.0 12:25 0.2 0.0 0:35 0.000 12:25 0.004 0.001 0.001 0.00
ReportAvg 1.4 0.4 0.030
ReportTotal 0.929 2.33
ADS Environmental Services
Pipe Height: 11.50
REN_MH0166\mp1\DFINAL (inches) REN_MH0166\mp1\VFINAL (feet/sec) REN_MH0166\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 22:35 0.9 23:30 1.1 0.9 0:00 0.0 23:30 0.2 0.0 0:00 0.000 23:30 0.004 0.000 0.000 0.10
4/2/2018 1:20 1.0 10:10 6.1 1.7 0:25 0.0 10:05 3.1 0.7 0:25 0.000 10:05 0.798 0.050 0.050 0.00
4/3/2018 23:55 1.1 14:00 6.2 1.6 23:55 0.1 14:00 3.2 0.7 23:55 0.003 14:00 0.845 0.047 0.047 0.00
4/4/2018 1:20 1.0 14:00 6.6 1.7 0:20 0.0 14:00 3.2 0.7 0:20 0.000 14:00 0.922 0.053 0.053 0.39
4/5/2018 6:35 1.1 10:45 6.7 1.7 6:35 0.2 10:45 3.2 0.7 6:35 0.004 10:45 0.949 0.051 0.051 0.25
4/6/2018 22:30 1.0 10:30 6.4 1.6 21:40 0.0 10:30 3.1 0.6 21:40 0.000 10:30 0.858 0.051 0.051 0.00
4/7/2018 1:20 1.1 3:10 6.3 2.2 1:20 0.1 3:10 3.1 1.1 1:20 0.003 3:10 0.847 0.102 0.102 0.88
4/8/2018 23:55 1.2 8:35 2.6 1.8 23:55 0.3 8:35 1.5 0.9 23:55 0.009 8:35 0.125 0.049 0.049 0.45
4/9/2018 23:55 1.0 9:50 6.4 1.7 23:55 0.1 9:35 3.3 0.7 23:55 0.002 9:35 0.899 0.053 0.053 0.00
4/10/2018 1:20 1.0 9:10 6.3 1.6 0:10 0.0 9:10 3.3 0.7 0:10 0.000 9:10 0.913 0.059 0.059 0.23
4/11/2018 1:00 0.9 8:30 5.0 1.6 0:45 0.0 8:30 2.9 0.8 0:45 0.000 8:30 0.602 0.049 0.049 0.31
4/12/2018 23:55 0.9 15:05 6.3 1.6 22:55 0.0 15:25 3.2 0.7 22:55 0.000 15:05 0.866 0.056 0.056 0.11
4/13/2018 1:20 0.9 16:10 6.4 2.2 0:00 0.0 16:10 3.2 1.3 0:00 0.000 16:10 0.871 0.114 0.114 0.51
4/14/2018 12:25 1.6 23:45 13.8 5.0 12:25 0.6 15:35 3.4 2.1 12:25 0.026 20:15 1.287 0.432 0.432 1.52
4/15/2018 23:55 1.7 0:05 13.4 5.4 23:30 0.8 4:05 3.3 2.2 23:45 0.037 3:05 1.314 0.465 0.465 0.21
4/16/2018 6:40 1.7 13:50 6.3 2.6 23:15 0.6 14:25 3.3 1.6 0:10 0.030 13:40 0.889 0.161 0.161 0.71
4/17/2018 23:55 1.3 7:05 6.5 2.1 21:55 0.2 7:05 3.4 1.0 21:55 0.008 7:05 0.953 0.082 0.082 0.01
4/18/2018 0:10 1.3 14:45 3.4 1.8 22:15 0.2 9:20 2.3 0.7 23:20 0.006 9:20 0.273 0.047 0.047 0.12
4/19/2018 23:55 1.2 14:05 6.1 1.7 20:50 0.2 14:05 3.0 0.7 20:50 0.006 14:05 0.773 0.042 0.042 0.00
4/20/2018 22:35 1.1 1:00 3.6 1.7 22:35 0.2 1:00 2.3 0.7 22:35 0.004 1:00 0.300 0.041 0.041 0.00
4/21/2018 23:55 1.1 13:05 3.5 1.7 23:15 0.2 13:05 2.3 0.7 23:55 0.005 13:05 0.293 0.040 0.040 0.05
4/22/2018 5:00 1.0 21:30 3.2 1.5 2:10 0.0 13:10 2.1 0.5 2:10 0.000 21:30 0.225 0.025 0.025 0.00
ReportAvg 2.1 0.9 0.094
ReportTotal 2.071 5.85
REN_MH0286
Located At: 3000 SE 5th St (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 9.88”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized both the pressure sensor and upward
ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 2.72 0.36 0.028 28%
Maximum 5.93 1.06 0.212 60%
Average 3.40 0.66 0.072 34%
Latitude: 47.477311°
Longitude:-122.179048°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Site located in roadway. Traffic control required.
Moderate, slow flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Located in roadway, at intersection. Requires traffic
control.
Sensors / Devices:
15.00'' x 15.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
3:17:00 PM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~8.00''
Velocity Sensor Offset (in)
.3 FPS
Temporary
15.00'' x 15.00''
REN_MH1763
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
3000 SE 5th St
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.13.17
Upstream 0-5 FT Manhole
MH1763 Residential
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.25''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
Concrete
20''
NormalUnbolted
20''
Additional Photos
Flow Direction
Monitoring Point
Top Down Location Location
Upstream Downstream Side Inlet
ADS Environmental Services
Pipe Height: 9.88
REN_MH0286\mp1\DFINAL (inches) REN_MH0286\mp1\VFINAL (feet/sec) REN_MH0286\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 23:55 2.9 12:40 3.7 3.2 23:55 0.5 13:45 0.8 0.7 23:55 0.044 13:45 0.095 0.065 0.065 0.10
12/23/2017 6:40 2.7 15:15 3.1 2.8 8:10 0.5 20:05 0.7 0.5 6:30 0.037 15:15 0.060 0.044 0.044 0.00
12/24/2017 0:50 2.7 16:45 3.3 2.9 3:35 0.4 18:00 0.7 0.5 3:35 0.036 16:55 0.072 0.044 0.044 0.00
12/25/2017 16:40 2.9 17:05 3.2 3.0 22:30 0.5 23:20 0.7 0.6 22:30 0.043 23:15 0.069 0.051 0.051 0.14
12/26/2017 5:05 2.9 9:15 3.8 3.2 5:00 0.5 15:55 0.8 0.6 5:00 0.044 9:15 0.097 0.062 0.062 0.17
12/27/2017 21:50 3.1 13:30 4.4 3.4 22:10 0.6 13:35 0.9 0.8 21:50 0.061 13:30 0.133 0.082 0.082 0.00
12/28/2017 4:20 3.0 16:50 4.1 3.5 3:40 0.6 15:40 1.0 0.8 3:40 0.054 16:45 0.131 0.083 0.083 0.25
12/29/2017 22:00 3.3 10:00 4.4 3.7 23:50 0.6 9:10 1.0 0.8 23:50 0.067 10:00 0.142 0.101 0.101 1.57
12/30/2017 23:50 2.9 8:05 3.4 3.1 12:00 0.5 8:20 0.8 0.6 23:50 0.045 8:20 0.084 0.060 0.060 0.02
12/31/2017 22:30 2.8 14:10 3.1 2.9 23:00 0.5 14:15 0.6 0.5 22:30 0.039 14:10 0.059 0.046 0.046 0.00
ReportAvg 3.2 0.6 0.064
ReportTotal 0.638 2.25
ADS Environmental Services
Pipe Height: 9.88
REN_MH0286\mp1\DFINAL (inches) REN_MH0286\mp1\VFINAL (feet/sec) REN_MH0286\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 21:20 2.7 22:55 3.5 2.9 12:15 0.5 22:55 0.8 0.5 12:15 0.037 22:55 0.090 0.045 0.045 0.00
1/2/2018 0:05 3.0 11:50 4.0 3.3 0:05 0.6 15:55 0.9 0.7 0:05 0.052 11:50 0.116 0.074 0.074 0.01
1/3/2018 4:55 3.0 15:05 4.2 3.4 4:50 0.6 15:10 0.9 0.7 4:50 0.050 15:10 0.133 0.076 0.076 0.00
1/4/2018 5:30 3.0 14:25 4.5 3.5 0:00 0.5 14:20 1.0 0.7 4:55 0.051 14:25 0.150 0.081 0.081 0.09
1/5/2018 2:45 3.2 12:35 4.2 3.6 4:50 0.6 13:30 1.0 0.7 4:50 0.059 13:30 0.132 0.085 0.085 0.42
1/6/2018 3:35 3.2 7:25 3.5 3.3 10:00 0.5 15:40 0.7 0.6 23:40 0.053 16:20 0.079 0.064 0.064 0.24
1/7/2018 13:45 3.1 9:05 3.5 3.3 5:40 0.5 18:45 0.8 0.6 5:40 0.052 18:45 0.080 0.062 0.062 0.38
1/8/2018 21:40 3.3 10:50 5.3 3.7 0:50 0.7 10:45 1.1 0.8 0:50 0.067 10:50 0.200 0.095 0.095 0.14
1/9/2018 5:10 3.3 16:00 4.6 3.7 6:05 0.7 16:05 1.0 0.8 5:20 0.068 16:00 0.153 0.095 0.095 0.46
1/10/2018 3:40 3.2 9:05 4.5 3.6 5:20 0.6 13:05 1.0 0.8 5:20 0.057 14:25 0.136 0.089 0.089 0.22
1/11/2018 5:25 3.4 11:15 4.8 3.9 4:40 0.6 11:15 1.0 0.8 4:40 0.069 11:15 0.164 0.102 0.102 1.04
1/12/2018 4:45 3.3 12:55 4.2 3.7 4:45 0.7 10:20 0.9 0.8 4:45 0.068 15:20 0.130 0.095 0.095 0.20
1/13/2018 23:55 3.4 12:20 4.2 3.6 14:20 0.7 2:25 0.9 0.8 23:55 0.073 2:25 0.126 0.085 0.085 0.02
1/14/2018 23:20 3.3 8:00 3.8 3.4 5:25 0.7 8:00 0.8 0.7 5:25 0.069 8:00 0.102 0.074 0.074 0.00
1/15/2018 0:35 3.4 10:45 4.6 3.7 4:00 0.6 11:30 1.0 0.8 3:05 0.061 10:45 0.156 0.094 0.094 0.04
1/16/2018 23:05 3.4 10:00 4.3 3.7 20:00 0.6 1:05 0.9 0.8 19:55 0.067 10:00 0.131 0.096 0.096 0.26
1/17/2018 3:00 3.2 19:40 4.3 3.7 4:50 0.6 19:10 1.0 0.8 4:55 0.061 19:40 0.137 0.094 0.094 0.79
1/18/2018 2:25 3.4 13:15 4.4 3.8 2:00 0.6 13:15 0.9 0.8 2:00 0.065 13:15 0.142 0.101 0.101 0.40
1/19/2018 23:55 3.1 13:50 4.3 3.6 23:55 0.6 5:25 0.9 0.8 23:55 0.054 13:50 0.133 0.087 0.087 0.10
1/20/2018 2:20 3.0 19:35 3.5 3.2 6:25 0.5 19:35 0.7 0.6 6:25 0.044 19:35 0.082 0.056 0.056 0.10
1/21/2018 4:25 3.0 17:40 3.6 3.1 3:55 0.4 17:20 0.8 0.5 3:55 0.040 17:25 0.088 0.051 0.051 0.16
1/22/2018 5:10 3.2 15:25 4.2 3.6 4:15 0.6 15:10 1.0 0.8 4:15 0.059 15:15 0.132 0.089 0.089 0.34
1/23/2018 22:30 3.2 15:50 4.2 3.6 7:25 0.6 15:50 0.9 0.8 5:40 0.059 15:50 0.127 0.086 0.086 0.79
1/24/2018 6:00 3.2 14:45 4.5 3.6 6:10 0.6 14:10 1.0 0.7 6:10 0.059 14:45 0.146 0.087 0.087 0.51
1/25/2018 5:50 3.1 10:55 4.0 3.4 2:05 0.6 11:05 1.0 0.8 1:20 0.057 11:05 0.124 0.081 0.081 0.14
1/26/2018 1:30 3.1 9:10 4.6 3.4 1:20 0.6 9:10 1.0 0.7 1:20 0.053 9:10 0.156 0.078 0.078 0.36
1/27/2018 10:10 3.1 11:20 3.8 3.2 14:55 0.5 11:25 0.8 0.6 10:10 0.051 11:25 0.102 0.062 0.062 0.61
1/28/2018 6:15 2.9 20:35 3.4 3.0 23:55 0.5 17:15 0.7 0.6 7:25 0.046 20:35 0.072 0.053 0.053 0.07
1/29/2018 3:50 3.0 15:10 4.6 3.6 0:00 0.5 14:55 1.0 0.7 0:00 0.046 15:10 0.148 0.087 0.087 0.90
1/30/2018 2:45 3.3 12:30 4.6 3.5 22:05 0.5 12:30 1.0 0.7 21:25 0.056 12:30 0.152 0.082 0.082 0.00
1/31/2018 2:55 3.2 16:55 4.0 3.5 23:30 0.6 9:55 1.0 0.7 23:30 0.058 9:55 0.130 0.083 0.083 0.00
ReportAvg 3.5 0.7 0.080
ReportTotal 2.490 8.79
ADS Environmental Services
Pipe Height: 9.88
REN_MH0286\mp1\DFINAL (inches) REN_MH0286\mp1\VFINAL (feet/sec) REN_MH0286\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:05 3.2 14:00 4.5 3.6 5:30 0.5 13:55 1.0 0.8 5:30 0.052 13:55 0.157 0.090 0.090 0.66
2/2/2018 4:55 3.3 13:45 4.3 3.6 4:20 0.6 11:35 0.9 0.7 4:55 0.060 13:45 0.133 0.088 0.088 0.04
2/3/2018 23:05 3.1 11:50 3.8 3.3 23:30 0.5 11:50 0.8 0.6 23:30 0.046 11:50 0.100 0.064 0.064 0.31
2/4/2018 6:10 3.0 12:25 3.4 3.1 6:10 0.5 15:45 0.6 0.5 6:10 0.043 12:25 0.061 0.049 0.049 0.02
2/5/2018 0:15 3.0 15:30 4.4 3.5 1:00 0.5 15:30 0.9 0.7 1:00 0.043 15:30 0.136 0.077 0.077 0.04
2/6/2018 3:10 3.2 12:25 5.8 3.5 2:00 0.5 12:30 1.0 0.7 2:00 0.052 12:25 0.204 0.075 0.075 0.00
2/7/2018 2:45 3.2 8:15 4.0 3.5 1:30 0.5 8:15 0.8 0.7 1:30 0.050 8:15 0.111 0.075 0.075 0.00
2/8/2018 5:40 3.2 15:25 4.2 3.6 19:30 0.6 15:25 0.9 0.7 5:40 0.059 15:25 0.127 0.081 0.081 0.09
2/9/2018 23:10 3.0 13:30 4.1 3.5 23:00 0.4 13:30 0.9 0.7 23:00 0.039 13:30 0.119 0.074 0.074 0.01
2/10/2018 7:45 2.9 1:25 3.3 3.0 7:10 0.4 17:35 0.7 0.5 11:45 0.034 17:35 0.065 0.047 0.047 0.01
2/11/2018 16:15 2.9 12:10 3.5 3.1 21:20 0.4 12:10 0.7 0.5 21:30 0.038 12:10 0.074 0.050 0.050 0.00
2/12/2018 2:55 3.0 12:10 4.1 3.4 0:25 0.4 12:10 0.9 0.6 0:25 0.041 12:10 0.119 0.068 0.068 0.00
2/13/2018 2:30 3.0 11:15 3.9 3.4 2:30 0.5 11:15 0.8 0.7 2:30 0.047 11:15 0.101 0.071 0.071 0.17
2/14/2018 21:35 3.0 10:15 4.2 3.4 21:25 0.5 10:15 0.9 0.7 21:25 0.042 10:15 0.123 0.071 0.071 0.15
2/15/2018 23:55 3.2 13:25 4.1 3.5 22:45 0.6 13:25 0.9 0.7 23:55 0.056 13:25 0.119 0.075 0.075 0.00
2/16/2018 0:20 3.1 15:15 4.0 3.4 6:15 0.5 15:15 0.8 0.7 0:20 0.052 15:15 0.109 0.071 0.071 0.15
2/17/2018 4:05 3.1 8:10 3.5 3.3 4:05 0.6 8:10 0.7 0.6 4:05 0.053 8:10 0.077 0.065 0.065 0.32
2/18/2018 23:20 3.1 17:25 3.7 3.2 17:30 0.5 10:45 0.7 0.6 23:20 0.051 17:25 0.075 0.059 0.059 0.01
2/19/2018 3:15 3.1 11:30 3.8 3.4 20:40 0.6 11:30 0.8 0.6 3:15 0.053 11:30 0.094 0.068 0.068 0.00
2/20/2018 21:55 3.0 14:45 3.8 3.4 21:05 0.5 10:00 0.8 0.6 21:05 0.047 10:00 0.096 0.067 0.067 0.00
2/21/2018 2:35 3.2 13:45 4.1 3.5 7:40 0.6 13:45 0.9 0.7 2:35 0.058 13:45 0.120 0.079 0.079 0.00
2/22/2018 23:15 3.2 14:25 4.0 3.5 22:05 0.6 14:25 0.8 0.7 22:05 0.059 14:25 0.108 0.076 0.076 0.07
2/23/2018 22:30 3.1 11:35 3.9 3.4 22:30 0.5 11:35 0.8 0.7 22:30 0.050 11:35 0.103 0.073 0.073 0.01
2/24/2018 23:40 2.9 15:25 3.3 3.0 21:20 0.5 15:25 0.6 0.5 23:40 0.042 15:25 0.062 0.049 0.049 0.13
2/25/2018 0:15 2.9 12:45 3.3 3.1 20:45 0.4 12:45 0.6 0.5 20:45 0.039 12:45 0.061 0.050 0.050 0.11
2/26/2018 3:30 3.2 14:35 5.1 3.6 3:35 0.5 14:35 1.0 0.7 3:35 0.048 14:35 0.179 0.084 0.084 0.00
2/27/2018 22:25 3.3 11:05 4.0 3.6 21:35 0.5 11:05 0.8 0.7 21:35 0.055 11:05 0.110 0.079 0.079 0.19
2/28/2018 5:00 3.2 13:15 4.1 3.5 0:55 0.5 13:15 0.9 0.7 0:55 0.053 13:15 0.118 0.078 0.078 0.35
ReportAvg 3.4 0.6 0.070
ReportTotal 1.951 2.84
ADS Environmental Services
Pipe Height: 9.88
REN_MH0286\mp1\DFINAL (inches) REN_MH0286\mp1\VFINAL (feet/sec) REN_MH0286\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 5:10 3.2 16:05 4.1 3.5 22:40 0.5 16:05 0.9 0.7 22:40 0.055 16:05 0.115 0.079 0.079 0.01
3/2/2018 21:50 3.0 16:00 4.0 3.4 19:45 0.5 16:00 0.8 0.6 21:50 0.049 16:00 0.107 0.068 0.068 0.07
3/3/2018 5:30 2.9 12:05 3.4 3.1 9:25 0.4 12:05 0.7 0.5 9:25 0.040 12:05 0.072 0.050 0.050 0.00
3/4/2018 4:50 2.8 17:40 3.3 2.9 5:35 0.4 17:40 0.6 0.5 5:35 0.029 17:40 0.066 0.041 0.041 0.12
3/5/2018 1:05 3.1 14:15 4.9 3.5 19:50 0.6 14:15 1.0 0.7 1:05 0.054 14:15 0.170 0.076 0.076 0.00
3/6/2018 23:30 3.1 11:25 4.4 3.5 23:40 0.5 11:25 0.9 0.7 23:40 0.048 11:25 0.133 0.076 0.076 0.00
3/7/2018 2:40 3.0 14:05 5.2 3.5 2:40 0.4 14:05 1.0 0.7 2:40 0.039 14:05 0.185 0.075 0.075 0.03
3/8/2018 2:20 3.1 15:20 4.1 3.5 2:15 0.5 15:20 0.9 0.7 2:15 0.043 15:20 0.115 0.073 0.073 0.37
3/9/2018 22:10 3.0 13:00 4.4 3.4 22:55 0.5 13:00 0.9 0.6 22:55 0.043 13:00 0.139 0.069 0.069 0.00
3/10/2018 3:55 2.9 14:55 3.3 3.1 2:55 0.4 18:30 0.6 0.5 2:55 0.037 18:30 0.062 0.048 0.048 0.00
3/11/2018 0:45 2.9 15:00 3.4 3.0 2:35 0.4 15:00 0.7 0.5 2:35 0.035 15:00 0.070 0.046 0.046 0.00
3/12/2018 1:40 3.1 14:20 4.1 3.5 0:35 0.5 14:20 0.9 0.7 0:35 0.046 14:20 0.116 0.073 0.073 0.00
3/13/2018 2:05 3.2 14:15 4.2 3.5 23:30 0.5 14:15 0.9 0.7 23:30 0.053 14:15 0.124 0.077 0.077 0.31
3/14/2018 23:15 3.0 9:05 3.9 3.5 23:15 0.5 6:50 0.8 0.6 23:15 0.042 6:50 0.099 0.071 0.071 0.04
3/15/2018 1:30 3.0 9:40 4.3 3.5 2:10 0.5 9:40 0.9 0.6 2:10 0.042 9:40 0.128 0.072 0.072 0.00
3/16/2018 23:40 3.1 13:15 4.1 3.5 23:50 0.5 13:15 0.9 0.7 23:50 0.044 13:15 0.120 0.073 0.073 0.00
3/17/2018 23:25 3.0 13:25 3.9 3.1 4:25 0.4 13:25 0.7 0.5 4:25 0.038 13:25 0.092 0.050 0.050 0.00
3/18/2018 23:45 2.9 17:05 3.2 3.0 23:05 0.4 17:05 0.6 0.5 11:05 0.038 17:05 0.061 0.046 0.046 0.00
3/19/2018 2:00 2.9 13:35 4.0 3.4 3:55 0.4 13:35 0.8 0.7 3:55 0.034 13:35 0.107 0.073 0.073 0.00
3/20/2018 5:10 3.2 9:15 4.3 3.5 22:15 0.5 9:15 0.9 0.7 22:15 0.050 9:15 0.132 0.075 0.075 0.00
3/21/2018 23:55 3.0 12:50 4.2 3.4 2:20 0.5 12:50 0.9 0.6 2:20 0.041 12:50 0.124 0.066 0.066 0.10
3/22/2018 2:20 2.8 10:20 4.7 3.4 2:15 0.4 10:20 1.0 0.6 2:15 0.029 10:20 0.161 0.069 0.069 0.48
3/23/2018 4:15 2.9 9:35 4.1 3.4 4:25 0.5 9:35 0.8 0.7 4:25 0.041 9:35 0.115 0.072 0.072 0.31
3/24/2018 22:50 2.8 9:20 3.6 3.1 22:45 0.4 9:20 0.7 0.6 22:50 0.036 9:20 0.082 0.052 0.052 0.28
3/25/2018 0:05 2.8 19:00 3.2 2.9 21:00 0.4 12:50 0.6 0.5 21:00 0.032 12:50 0.062 0.042 0.042 0.01
3/26/2018 3:20 2.8 10:15 4.4 3.4 3:20 0.4 10:15 0.9 0.6 3:20 0.028 10:15 0.137 0.068 0.068 0.17
3/27/2018 0:10 3.1 11:50 4.3 3.5 0:10 0.5 11:50 0.9 0.7 0:10 0.044 11:50 0.129 0.075 0.075 0.02
3/28/2018 23:55 3.0 12:00 4.0 3.4 23:35 0.4 12:00 0.8 0.6 23:35 0.041 12:00 0.112 0.066 0.066 0.01
3/29/2018 1:55 2.9 12:55 4.1 3.4 1:55 0.4 12:55 0.9 0.6 1:55 0.034 12:55 0.120 0.068 0.068 0.00
3/30/2018 1:40 3.0 12:15 4.0 3.4 1:40 0.4 12:15 0.8 0.6 1:40 0.039 12:15 0.108 0.068 0.068 0.00
3/31/2018 23:10 2.9 12:55 3.3 3.1 23:10 0.4 10:15 0.6 0.5 23:10 0.036 10:15 0.063 0.050 0.050 0.00
ReportAvg 3.3 0.6 0.065
ReportTotal 2.006 2.33
ADS Environmental Services
Pipe Height: 9.88
REN_MH0286\mp1\DFINAL (inches) REN_MH0286\mp1\VFINAL (feet/sec) REN_MH0286\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 23:15 2.9 17:25 3.2 3.0 23:15 0.4 17:25 0.6 0.5 23:15 0.033 17:25 0.059 0.045 0.045 0.10
4/2/2018 2:35 2.9 10:45 5.9 3.4 1:55 0.4 10:50 1.0 0.7 1:55 0.033 10:45 0.212 0.073 0.073 0.00
4/3/2018 2:05 2.9 17:55 4.1 3.5 2:00 0.4 17:55 0.9 0.7 2:00 0.036 17:55 0.120 0.078 0.078 0.00
4/4/2018 1:55 3.1 14:50 4.1 3.5 21:55 0.5 14:50 0.9 0.7 21:55 0.045 14:50 0.115 0.073 0.073 0.39
4/5/2018 4:25 3.2 12:55 4.0 3.5 2:30 0.5 12:55 0.8 0.7 2:30 0.056 12:55 0.113 0.077 0.077 0.25
4/6/2018 23:55 2.9 12:40 4.1 3.4 21:45 0.5 12:40 0.8 0.7 21:45 0.041 12:40 0.115 0.071 0.071 0.00
4/7/2018 0:25 2.9 9:30 3.6 3.2 1:05 0.4 9:30 0.7 0.6 1:05 0.034 9:30 0.085 0.059 0.059 0.88
4/8/2018 16:40 3.0 10:55 3.4 3.2 17:05 0.5 10:55 0.7 0.6 17:05 0.042 10:55 0.072 0.058 0.058 0.45
4/9/2018 0:00 3.0 11:05 4.2 3.6 0:30 0.5 11:05 0.9 0.7 0:05 0.043 11:05 0.125 0.084 0.084 0.00
4/10/2018 22:15 3.3 10:30 4.5 3.7 22:15 0.6 10:30 0.9 0.8 22:15 0.063 10:30 0.145 0.091 0.091 0.23
4/11/2018 2:05 3.4 6:45 4.4 3.8 2:05 0.7 6:45 0.9 0.8 2:05 0.068 6:45 0.140 0.094 0.094 0.31
4/12/2018 4:30 3.5 14:25 4.3 3.8 4:30 0.7 14:25 0.9 0.8 4:30 0.074 14:25 0.130 0.097 0.097 0.11
4/13/2018 23:55 3.3 15:05 4.3 3.7 21:50 0.5 15:05 0.9 0.7 21:50 0.056 15:05 0.132 0.090 0.090 0.51
4/14/2018 2:55 3.1 13:20 4.5 3.5 4:45 0.5 13:20 0.9 0.7 4:45 0.049 13:20 0.142 0.076 0.076 1.52
4/15/2018 20:30 3.3 6:50 4.2 3.6 19:45 0.6 6:50 0.9 0.7 19:45 0.060 6:50 0.121 0.081 0.081 0.21
4/16/2018 2:30 3.3 14:55 5.0 3.8 4:20 0.6 14:55 1.0 0.8 4:20 0.060 14:55 0.174 0.095 0.095 0.71
4/17/2018 22:30 3.3 11:15 4.2 3.7 22:15 0.6 11:15 0.9 0.7 22:15 0.057 11:15 0.127 0.089 0.089 0.01
4/18/2018 3:45 3.2 15:50 4.4 3.6 4:05 0.5 15:50 0.9 0.7 4:05 0.053 15:50 0.138 0.084 0.084 0.12
4/19/2018 1:55 3.1 9:45 4.3 3.5 5:40 0.5 9:45 0.9 0.7 5:40 0.053 9:45 0.129 0.079 0.079 0.00
4/20/2018 23:55 3.1 9:50 4.2 3.5 21:15 0.5 9:50 0.9 0.7 21:15 0.050 9:50 0.122 0.078 0.078 0.00
4/21/2018 7:30 2.9 19:20 3.8 3.1 7:20 0.5 19:20 0.8 0.6 7:20 0.041 19:20 0.096 0.055 0.055 0.05
4/22/2018 6:50 2.8 2:25 3.2 3.0 10:35 0.4 2:25 0.6 0.5 8:25 0.033 2:25 0.058 0.046 0.046 0.00
ReportAvg 3.5 0.7 0.076
ReportTotal 1.671 5.85
REN_MH0537
Located At: 2803 Burnett Ave (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 8”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.21 6.33 0.141 15%
Maximum 2.90 10.62 0.766 36%
Average 1.77 8.86 0.336 22%
Latitude:47.516545°
Longitude:-122.207103°
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
Concrete
20''
NormalUnbolted
20''
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.38''
Peak Velocity (fps)
Silt (in)
~10'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Renton.Carollo.I&I.WA17
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
ADJ 2803 Burnett Ave Nth
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.19.17
Upstream 0-5 FT Manhole
MH0537 Other
Map
Flow Monitoring
Site Report
Temporary
8.00'' x 8.00''
REN_MH0537
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe ShapeLocated in roadway, at intersection. Requires traffic
control.
Sensors / Devices:
8.00'' x 8.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
1:05:00 PM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~1.75''
Velocity Sensor Offset (in)
9.60 FPS
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Site located in roadway. Traffic control required.
Low, fast flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Additional Photos
Flow Direction
Monitoring Point
Upstream Downstream Overflow
Top Down Location Location
ADS Environmental Services
Pipe Height: 8.00
REN_MH0537\mp1\DFINAL (inches) REN_MH0537\mp1\VFINAL (feet/sec) REN_MH0537\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 4:40 1.3 10:15 2.6 1.8 3:55 7.2 10:15 10.0 8.9 3:55 0.182 10:15 0.630 0.356 0.356 0.10
12/23/2017 4:40 1.3 9:55 2.6 1.8 4:30 6.9 7:55 10.0 8.9 4:30 0.167 9:55 0.630 0.344 0.344 0.00
12/24/2017 6:40 1.2 10:45 2.7 1.8 4:15 7.0 10:40 10.2 8.9 5:10 0.159 10:45 0.665 0.347 0.347 0.00
12/25/2017 3:10 1.2 11:40 2.6 1.8 4:05 6.8 11:45 10.1 8.8 4:05 0.158 11:40 0.629 0.354 0.354 0.14
12/26/2017 5:15 1.3 10:40 2.5 1.8 4:20 6.6 9:15 10.0 8.7 5:15 0.156 11:10 0.581 0.342 0.342 0.17
12/27/2017 5:45 1.3 20:45 2.5 1.8 4:10 6.6 9:30 9.9 8.7 4:10 0.155 20:45 0.599 0.331 0.331 0.00
12/28/2017 4:30 1.3 8:20 2.7 1.7 4:50 6.7 20:05 10.2 8.8 4:50 0.155 8:20 0.652 0.328 0.328 0.25
12/29/2017 3:25 1.4 10:25 2.8 1.9 2:40 7.6 10:25 10.5 9.2 3:20 0.194 10:25 0.753 0.387 0.387 1.57
12/30/2017 5:00 1.4 10:40 2.8 1.8 5:00 7.5 10:40 10.4 9.1 5:00 0.192 10:40 0.722 0.357 0.357 0.02
12/31/2017 4:00 1.3 17:25 2.6 1.8 3:55 7.3 10:05 10.4 9.1 3:55 0.176 17:25 0.659 0.339 0.339 0.00
ReportAvg 1.8 8.9 0.349
ReportTotal 3.486 2.25
ADS Environmental Services
Pipe Height: 8.00
REN_MH0537\mp1\DFINAL (inches) REN_MH0537\mp1\VFINAL (feet/sec) REN_MH0537\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 5:50 1.3 21:00 2.4 1.7 5:50 7.3 11:35 10.3 9.1 5:50 0.174 21:00 0.590 0.334 0.334 0.00
1/2/2018 3:20 1.2 20:15 2.6 1.7 4:05 6.9 7:40 10.5 9.0 3:15 0.159 20:15 0.630 0.330 0.330 0.01
1/3/2018 2:35 1.3 20:25 2.7 1.8 4:00 6.7 6:45 10.2 9.0 4:00 0.163 20:25 0.673 0.345 0.345 0.00
1/4/2018 3:45 1.3 20:35 2.6 1.8 3:45 6.6 8:20 10.1 8.7 3:45 0.163 20:35 0.619 0.352 0.352 0.09
1/5/2018 3:20 1.3 20:45 2.6 1.9 4:00 6.6 20:45 10.0 8.6 4:00 0.161 20:45 0.632 0.355 0.355 0.42
1/6/2018 3:40 1.3 12:25 2.8 1.9 3:35 6.9 10:45 9.9 8.8 3:35 0.176 12:25 0.684 0.377 0.377 0.24
1/7/2018 3:55 1.3 11:25 2.8 1.9 3:55 6.6 21:00 9.9 8.7 3:55 0.162 11:25 0.696 0.377 0.377 0.38
1/8/2018 3:40 1.4 20:15 2.6 1.9 4:20 6.8 21:50 10.0 8.7 4:20 0.178 20:15 0.618 0.357 0.357 0.14
1/9/2018 4:40 1.4 21:00 2.6 1.9 4:40 7.0 19:05 10.3 9.0 4:40 0.179 21:00 0.646 0.366 0.366 0.46
1/10/2018 4:55 1.4 19:25 2.7 1.8 3:35 7.2 19:25 10.3 9.0 3:40 0.184 19:25 0.675 0.354 0.354 0.22
1/11/2018 4:10 1.4 22:00 2.8 1.9 3:35 7.1 7:20 10.3 9.2 3:35 0.186 22:00 0.694 0.399 0.399 1.04
1/12/2018 3:30 1.4 9:25 2.7 1.9 2:30 7.5 9:00 10.3 9.3 3:00 0.205 7:55 0.658 0.391 0.391 0.20
1/13/2018 2:35 1.3 9:50 2.7 1.9 6:20 7.5 11:15 10.3 9.3 2:35 0.195 9:50 0.682 0.385 0.385 0.02
1/14/2018 4:30 1.4 9:55 2.8 1.8 4:30 7.3 9:15 10.3 9.1 4:30 0.187 9:55 0.691 0.362 0.362 0.00
1/15/2018 2:45 1.4 20:15 2.8 1.9 3:55 7.1 20:55 10.3 9.1 4:30 0.183 20:55 0.705 0.373 0.373 0.04
1/16/2018 3:30 1.3 21:55 2.7 1.8 4:00 7.3 19:15 10.3 9.2 3:30 0.185 21:55 0.666 0.367 0.367 0.26
1/17/2018 3:00 1.3 20:20 2.8 1.9 4:10 7.1 20:00 10.6 9.2 3:00 0.177 20:20 0.710 0.378 0.378 0.79
1/18/2018 0:05 1.3 20:50 2.8 1.9 0:05 6.9 20:10 10.4 9.3 0:05 0.155 20:50 0.694 0.399 0.399 0.40
1/19/2018 2:10 1.4 8:00 2.7 1.9 4:20 7.4 8:00 10.3 9.2 3:50 0.194 8:00 0.675 0.374 0.374 0.10
1/20/2018 6:10 1.4 12:20 2.9 1.8 3:20 7.3 12:20 10.1 9.1 3:20 0.186 12:20 0.742 0.364 0.364 0.10
1/21/2018 5:20 1.3 9:50 2.8 1.8 3:35 7.2 9:50 10.2 8.9 5:20 0.180 9:50 0.700 0.353 0.353 0.16
1/22/2018 3:50 1.4 8:55 2.7 1.9 3:50 7.1 17:50 10.2 9.0 3:50 0.180 8:55 0.686 0.365 0.365 0.34
1/23/2018 3:35 1.3 20:50 2.8 1.9 3:00 7.0 7:40 10.3 9.2 3:00 0.173 20:50 0.701 0.376 0.376 0.79
1/24/2018 3:30 1.4 8:15 2.8 1.9 3:30 7.7 8:15 10.5 9.2 3:30 0.207 8:15 0.733 0.385 0.385 0.51
1/25/2018 3:35 1.4 7:50 2.7 1.9 4:30 7.7 7:50 10.4 9.3 3:35 0.216 7:50 0.717 0.396 0.396 0.14
1/26/2018 3:55 1.4 8:40 2.6 1.9 3:25 7.5 9:05 10.3 9.2 3:55 0.206 8:40 0.661 0.388 0.388 0.36
1/27/2018 2:55 1.5 10:20 2.8 1.9 4:40 8.2 8:55 10.4 9.3 4:40 0.254 10:20 0.728 0.399 0.399 0.61
1/28/2018 6:05 1.4 10:15 2.8 1.8 4:40 7.7 7:35 10.2 9.0 4:40 0.220 10:15 0.724 0.347 0.347 0.07
1/29/2018 4:55 1.4 21:55 2.7 1.9 3:50 7.9 22:35 10.4 9.3 4:55 0.218 21:55 0.712 0.387 0.387 0.90
1/30/2018 4:10 1.5 9:10 2.7 1.9 6:45 8.1 18:00 10.6 9.4 3:40 0.237 21:10 0.706 0.396 0.396 0.00
1/31/2018 2:30 1.4 21:40 2.8 1.9 3:30 8.0 17:25 10.5 9.3 2:30 0.219 21:40 0.716 0.386 0.386 0.00
ReportAvg 1.9 9.1 0.372
ReportTotal 11.52 8.79
ADS Environmental Services
Pipe Height: 8.00
REN_MH0537\mp1\DFINAL (inches) REN_MH0537\mp1\VFINAL (feet/sec) REN_MH0537\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 4:10 1.4 21:00 2.9 1.9 4:10 7.8 6:40 10.4 9.3 4:10 0.205 21:00 0.766 0.383 0.383 0.66
2/2/2018 5:15 1.4 8:25 2.7 1.9 3:15 7.8 8:05 10.4 9.3 3:45 0.218 8:25 0.707 0.387 0.387 0.04
2/3/2018 6:05 1.4 13:10 2.6 1.8 6:05 7.8 8:35 10.4 9.1 6:05 0.202 13:10 0.663 0.354 0.354 0.31
2/4/2018 5:10 1.4 15:45 2.7 1.8 5:10 7.6 8:30 10.3 9.1 5:10 0.202 15:45 0.675 0.361 0.361 0.02
2/5/2018 4:40 1.4 21:40 2.7 1.9 3:05 7.5 21:40 10.5 9.2 4:40 0.201 21:40 0.708 0.372 0.372 0.04
2/6/2018 3:00 1.4 7:10 2.7 1.8 3:30 7.3 7:10 10.6 9.2 3:30 0.190 7:10 0.704 0.361 0.361 0.00
2/7/2018 3:20 1.4 7:35 2.7 1.8 2:45 7.4 6:45 10.3 9.1 3:20 0.187 7:35 0.663 0.359 0.359 0.00
2/8/2018 4:35 1.3 8:25 2.7 1.8 3:25 7.2 8:05 10.2 9.0 3:25 0.181 8:25 0.668 0.356 0.356 0.09
2/9/2018 4:35 1.3 7:45 2.6 1.8 2:00 7.2 7:45 10.3 9.0 2:40 0.183 7:45 0.649 0.349 0.349 0.01
2/10/2018 5:55 1.3 9:10 2.7 1.8 5:15 6.9 9:10 10.4 8.9 5:15 0.170 9:10 0.689 0.344 0.344 0.01
2/11/2018 4:10 1.3 20:40 2.5 1.8 3:25 7.0 9:25 10.0 8.9 4:50 0.171 20:40 0.599 0.341 0.341 0.00
2/12/2018 4:40 1.3 21:15 2.6 1.8 3:55 6.8 7:30 10.3 8.8 4:40 0.161 21:15 0.643 0.332 0.332 0.00
2/13/2018 4:00 1.3 7:55 2.5 1.7 4:00 6.9 7:55 10.2 8.9 4:00 0.164 7:55 0.621 0.329 0.329 0.17
2/14/2018 3:30 1.3 20:20 2.7 1.8 4:10 6.9 6:25 10.2 8.9 4:10 0.171 20:20 0.644 0.334 0.334 0.15
2/15/2018 4:00 1.3 21:30 2.6 1.7 2:20 6.9 21:30 10.1 8.8 3:10 0.166 21:30 0.638 0.327 0.327 0.00
2/16/2018 4:35 1.3 7:40 2.6 1.7 4:30 6.9 7:40 10.3 8.8 4:30 0.167 7:40 0.652 0.322 0.322 0.15
2/17/2018 4:20 1.3 10:10 2.8 1.8 2:50 6.7 9:50 10.2 8.8 2:50 0.161 10:10 0.688 0.333 0.333 0.32
2/18/2018 4:55 1.3 20:25 2.6 1.8 4:55 7.0 9:10 10.1 8.8 4:55 0.170 9:10 0.626 0.331 0.331 0.01
2/19/2018 3:50 1.3 18:50 2.5 1.7 3:50 6.8 21:30 10.0 8.8 3:50 0.159 18:50 0.609 0.323 0.323 0.00
2/20/2018 4:05 1.3 10:20 2.5 1.7 3:15 6.8 10:20 10.2 8.8 3:15 0.166 10:20 0.611 0.319 0.319 0.00
2/21/2018 4:00 1.3 20:40 2.7 1.7 4:00 6.7 20:20 10.1 8.7 4:00 0.156 20:40 0.682 0.311 0.311 0.00
2/22/2018 3:15 1.3 7:15 2.4 1.7 4:55 6.6 19:05 10.2 8.8 3:20 0.160 7:15 0.588 0.315 0.315 0.07
2/23/2018 3:30 1.3 10:15 2.5 1.7 3:30 6.6 7:25 10.0 8.7 3:30 0.154 10:15 0.585 0.312 0.312 0.01
2/24/2018 4:05 1.3 10:10 2.6 1.7 5:05 6.6 10:40 9.9 8.6 5:05 0.155 10:10 0.627 0.313 0.313 0.13
2/25/2018 5:10 1.2 21:30 2.6 1.8 4:20 6.7 11:05 10.1 8.6 5:10 0.156 11:05 0.652 0.329 0.329 0.11
2/26/2018 2:55 1.3 21:15 2.6 1.7 3:45 6.6 21:15 9.9 8.5 2:55 0.157 21:15 0.618 0.316 0.316 0.00
2/27/2018 3:35 1.3 20:25 2.6 1.7 3:30 6.5 19:05 10.2 8.6 3:30 0.151 20:25 0.639 0.315 0.315 0.19
2/28/2018 3:25 1.3 7:35 2.6 1.7 3:20 6.7 19:20 10.2 8.8 3:20 0.157 7:35 0.623 0.318 0.318 0.35
ReportAvg 1.8 8.9 0.337
ReportTotal 9.447 2.84
ADS Environmental Services
Pipe Height: 8.00
REN_MH0537\mp1\DFINAL (inches) REN_MH0537\mp1\VFINAL (feet/sec) REN_MH0537\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 3:55 1.3 20:55 2.6 1.7 3:30 6.7 6:55 10.3 8.8 3:30 0.159 6:55 0.655 0.324 0.324 0.01
3/2/2018 4:00 1.3 7:20 2.5 1.7 3:15 7.1 7:50 10.1 8.8 4:00 0.172 7:20 0.609 0.316 0.316 0.07
3/3/2018 2:10 1.3 11:25 2.6 1.7 4:55 6.6 9:45 10.4 8.8 5:50 0.157 9:15 0.652 0.320 0.320 0.00
3/4/2018 5:25 1.3 21:35 2.7 1.7 5:15 6.8 11:45 10.2 8.7 5:15 0.156 11:45 0.667 0.315 0.315 0.12
3/5/2018 1:55 1.3 19:30 2.6 1.7 4:00 6.6 19:30 10.4 8.8 4:50 0.154 19:30 0.658 0.322 0.322 0.00
3/6/2018 3:40 1.3 20:35 2.6 1.7 3:40 6.7 20:35 10.4 8.8 3:40 0.154 20:35 0.677 0.317 0.317 0.00
3/7/2018 2:30 1.3 7:50 2.6 1.7 3:25 6.9 7:25 10.1 8.8 3:25 0.166 7:50 0.648 0.324 0.324 0.03
3/8/2018 4:25 1.3 21:55 2.5 1.7 4:25 6.8 6:50 10.1 8.7 4:25 0.155 21:55 0.602 0.319 0.319 0.37
3/9/2018 2:55 1.3 8:05 2.6 1.7 2:50 6.9 8:00 10.2 8.7 2:50 0.164 8:00 0.642 0.323 0.323 0.00
3/10/2018 4:25 1.3 10:25 2.6 1.7 5:20 6.6 10:30 10.1 8.7 5:20 0.155 10:25 0.654 0.319 0.319 0.00
3/11/2018 5:30 1.3 18:50 2.5 1.7 4:25 6.6 20:50 10.1 8.5 5:30 0.148 18:50 0.588 0.298 0.298 0.00
3/12/2018 4:25 1.2 20:25 2.4 1.7 2:25 6.6 20:50 10.0 8.6 2:25 0.150 20:25 0.584 0.302 0.302 0.00
3/13/2018 2:45 1.3 18:20 2.7 1.7 2:40 6.5 18:20 10.4 8.6 2:40 0.149 18:20 0.709 0.303 0.303 0.31
3/14/2018 3:50 1.3 21:45 2.5 1.7 2:00 6.4 7:25 10.2 8.5 3:50 0.148 7:25 0.583 0.297 0.297 0.04
3/15/2018 3:45 1.3 19:10 2.4 1.7 2:40 6.3 12:20 10.0 8.5 2:40 0.151 19:10 0.551 0.306 0.306 0.00
3/16/2018 2:50 1.3 6:45 2.5 1.7 2:30 6.5 7:45 9.9 8.5 2:50 0.147 6:45 0.574 0.300 0.300 0.00
3/17/2018 1:50 1.2 9:10 2.6 1.7 2:55 6.4 8:15 10.1 8.5 2:55 0.145 9:10 0.650 0.303 0.303 0.00
3/18/2018 4:45 1.3 20:25 2.7 1.7 4:35 6.5 17:45 10.0 8.5 4:35 0.149 20:25 0.652 0.300 0.300 0.00
3/19/2018 5:00 1.2 6:50 2.4 1.6 3:00 6.5 6:50 10.0 8.5 3:00 0.148 6:50 0.569 0.290 0.290 0.00
3/20/2018 4:50 1.3 19:10 2.5 1.6 2:40 6.6 6:45 10.3 8.6 2:40 0.150 19:10 0.630 0.294 0.294 0.00
3/21/2018 22:25 1.2 7:45 2.5 1.6 2:35 6.5 5:40 10.2 8.6 2:35 0.147 18:00 0.589 0.291 0.291 0.10
3/22/2018 2:35 1.3 19:15 2.6 1.7 2:40 6.4 7:35 10.2 8.7 2:30 0.148 19:15 0.659 0.312 0.312 0.48
3/23/2018 2:15 1.3 6:35 2.3 1.7 2:05 6.6 8:05 10.1 8.7 2:05 0.152 8:05 0.547 0.308 0.308 0.31
3/24/2018 3:20 1.3 9:35 2.6 1.7 2:25 6.7 9:40 9.9 8.6 3:20 0.156 9:35 0.631 0.307 0.307 0.28
3/25/2018 5:25 1.3 8:10 2.6 1.7 5:15 6.7 7:30 10.2 8.6 5:25 0.154 8:10 0.636 0.303 0.303 0.01
3/26/2018 2:45 1.3 18:20 2.8 1.7 2:45 6.6 20:30 10.3 8.7 2:45 0.150 18:20 0.698 0.308 0.308 0.17
3/27/2018 5:05 1.2 20:45 2.6 1.7 5:05 6.6 5:50 10.4 8.7 5:05 0.141 20:45 0.633 0.311 0.311 0.02
3/28/2018 0:45 1.3 19:40 2.6 1.7 2:45 6.7 19:40 10.2 8.7 2:45 0.153 19:40 0.640 0.311 0.311 0.01
3/29/2018 4:15 1.3 6:15 2.6 1.7 3:10 6.6 6:15 10.2 8.6 4:15 0.152 6:15 0.648 0.310 0.310 0.00
3/30/2018 3:20 1.3 20:55 2.4 1.7 3:30 6.5 8:05 9.9 8.5 2:25 0.152 8:05 0.571 0.303 0.303 0.00
3/31/2018 4:20 1.3 10:25 2.5 1.7 3:15 6.6 7:45 10.0 8.6 4:20 0.149 7:45 0.603 0.312 0.312 0.00
ReportAvg 1.7 8.6 0.309
ReportTotal 9.569 2.33
ADS Environmental Services
Pipe Height: 8.00
REN_MH0537\mp1\DFINAL (inches) REN_MH0537\mp1\VFINAL (feet/sec) REN_MH0537\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 4:00 1.3 8:40 2.7 1.7 4:15 6.5 8:15 9.9 8.6 4:15 0.150 8:40 0.673 0.318 0.318 0.10
4/2/2018 4:00 1.3 7:35 2.4 1.7 2:55 6.4 7:35 10.0 8.6 4:00 0.158 7:35 0.584 0.304 0.304 0.00
4/3/2018 3:50 1.3 18:15 2.4 1.7 2:30 6.4 19:15 10.0 8.5 3:50 0.155 18:15 0.582 0.300 0.300 0.00
4/4/2018 1:20 1.3 18:00 2.5 1.7 2:25 6.6 20:30 10.0 8.6 1:20 0.156 18:00 0.586 0.302 0.302 0.39
4/5/2018 4:05 1.3 6:40 2.5 1.7 2:55 6.5 6:40 10.0 8.5 4:05 0.160 6:40 0.591 0.298 0.298 0.25
4/6/2018 2:00 1.3 8:15 2.5 1.6 3:00 6.7 7:20 10.0 8.6 2:00 0.155 8:15 0.604 0.294 0.294 0.00
4/7/2018 1:40 1.2 10:10 2.7 1.7 1:40 6.8 10:40 10.0 8.8 1:40 0.147 10:10 0.645 0.320 0.320 0.88
4/8/2018 1:50 1.3 10:45 2.6 1.7 2:45 6.9 18:55 9.9 8.7 2:45 0.162 9:10 0.627 0.316 0.316 0.45
4/9/2018 2:50 1.3 18:50 2.5 1.7 2:45 6.8 18:50 10.2 8.7 2:45 0.161 18:50 0.616 0.311 0.311 0.00
4/10/2018 5:20 1.3 22:10 2.6 1.6 2:35 6.8 17:20 10.3 8.5 2:50 0.159 22:10 0.628 0.295 0.295 0.23
4/11/2018 5:05 1.3 19:10 2.5 1.7 2:25 6.7 6:50 10.2 8.7 2:25 0.158 19:10 0.609 0.311 0.311 0.31
4/12/2018 4:40 1.3 6:40 2.5 1.7 2:10 7.0 6:45 10.2 8.7 4:40 0.164 6:40 0.606 0.303 0.303 0.11
4/13/2018 4:15 1.3 14:45 2.6 1.7 1:40 6.8 14:45 10.2 8.8 1:45 0.166 14:45 0.651 0.311 0.311 0.51
4/14/2018 4:25 1.3 19:50 2.8 1.7 23:35 7.2 22:25 10.5 8.9 23:35 0.171 19:50 0.712 0.325 0.325 1.52
4/15/2018 18:40 1.4 14:00 2.7 1.7 18:40 7.8 21:30 10.4 9.0 18:40 0.213 21:30 0.688 0.330 0.330 0.21
4/16/2018 6:30 1.4 19:45 2.6 1.8 6:30 7.5 6:50 10.4 9.2 6:30 0.189 19:45 0.652 0.357 0.357 0.71
4/17/2018 19:40 1.3 6:05 2.7 1.8 19:40 7.0 6:45 10.4 9.1 19:40 0.162 6:45 0.700 0.341 0.341 0.01
4/18/2018 20:15 1.3 8:00 2.6 1.7 20:15 7.1 19:30 10.4 9.0 20:15 0.166 8:00 0.660 0.332 0.332 0.12
4/19/2018 20:45 1.3 6:30 2.5 1.7 20:45 7.2 6:30 10.5 9.0 20:45 0.173 6:30 0.652 0.330 0.330 0.00
4/20/2018 3:15 1.3 8:30 2.4 1.7 1:20 7.5 6:55 10.5 9.1 1:20 0.186 8:30 0.599 0.333 0.333 0.00
4/21/2018 12:00 1.2 8:20 2.5 1.7 12:00 6.7 7:05 10.4 9.0 12:00 0.146 8:20 0.635 0.322 0.322 0.05
4/22/2018 13:25 1.3 12:40 2.6 1.7 13:25 6.9 8:50 10.3 8.8 13:25 0.159 12:40 0.623 0.313 0.313 0.00
ReportAvg 1.7 8.8 0.317
ReportTotal 6.964 5.85
REN_MH1360
Located At: Intersection of Ferndale and 7th St (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 10.75”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 98%
Velocity (f/s) 100% 98%
Quantity (mgd) 100% 98%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.49 2.26 0.082 14%
Maximum 5.28 5.41 1.013 49%
Average 2.75 3.86 0.338 26%
Latitude: 47.494057°
Longitude:-122.183210°
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
Concrete
20''
NormalUnbolted
20''
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.25''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Renton.Carollo.I&I.WA17
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
Intersection of Ferndale Pl NE and NE 7th St
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.13.17
Upstream 0-5 FT Manhole
MH1360 Other
Map
Flow Monitoring
Site Report
Temporary
10.75'' x 10.75''
REN_MH1360
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe ShapeLocated in roadway, at intersection. Requires traffic
control.
Sensors / Devices:
10.75'' x 10.75''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
9:20:00 AM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~2.00''
Velocity Sensor Offset (in)
2.5 FPS
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Site located in roadway. Traffic control required.
Low, fast flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Additional Photos
Flow Direction
Monitoring Point
Upstream Downstream Overflow
Top Down Location Location
ADS Environmental Services
Pipe Height: 10.75
REN_MH1360\mp1\DFINAL (inches) REN_MH1360\mp1\VFINAL (feet/sec) REN_MH1360\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 3:40 2.2 12:00 2.8 2.5 3:40 2.9 12:00 4.3 4.0 3:40 0.170 12:00 0.365 0.293 0.293 0.10
12/23/2017 4:45 2.1 12:35 2.9 2.4 2:50 2.9 9:45 4.3 3.9 2:50 0.167 12:35 0.391 0.274 0.274 0.00
12/24/2017 4:30 2.0 15:25 3.0 2.4 3:40 2.7 11:25 4.2 3.7 4:35 0.144 11:25 0.366 0.257 0.257 0.00
12/25/2017 5:05 1.9 14:30 2.8 2.3 4:40 2.6 14:30 4.1 3.6 5:15 0.131 14:30 0.340 0.234 0.234 0.14
12/26/2017 2:55 1.9 18:15 2.7 2.3 2:50 2.6 12:45 4.1 3.6 2:50 0.128 18:15 0.317 0.237 0.237 0.17
12/27/2017 4:15 1.9 20:20 2.7 2.3 3:55 2.5 18:20 4.0 3.5 3:55 0.120 20:20 0.308 0.223 0.223 0.00
12/28/2017 4:10 1.9 18:40 2.6 2.3 2:30 2.5 18:25 4.0 3.5 4:15 0.122 18:25 0.293 0.228 0.228 0.25
12/29/2017 0:40 2.2 15:15 4.9 3.9 0:35 3.0 15:00 5.1 4.5 0:35 0.190 15:05 0.924 0.635 0.635 1.57
12/30/2017 23:55 3.2 0:00 4.0 3.6 3:00 4.3 0:20 4.9 4.6 23:55 0.447 0:30 0.663 0.547 0.547 0.02
12/31/2017 5:20 2.8 10:45 3.4 3.1 5:50 3.7 14:15 4.7 4.3 5:50 0.316 11:55 0.525 0.423 0.423 0.00
ReportAvg 2.7 3.9 0.335
ReportTotal 3.351 2.25
ADS Environmental Services
Pipe Height: 10.75
REN_MH1360\mp1\DFINAL (inches) REN_MH1360\mp1\VFINAL (feet/sec) REN_MH1360\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 23:55 2.5 13:10 3.2 2.8 4:25 3.3 13:10 4.4 4.1 4:25 0.248 13:10 0.452 0.351 0.351 0.00
1/2/2018 3:35 2.3 19:30 2.9 2.6 2:20 3.3 21:55 4.3 4.0 3:55 0.214 19:30 0.383 0.307 0.307 0.01
1/3/2018 3:50 2.2 10:50 3.3 2.5 3:30 2.9 10:50 4.6 3.9 3:30 0.172 10:50 0.485 0.284 0.284 0.00
1/4/2018 2:55 2.1 11:40 3.8 2.5 3:20 2.7 11:40 4.9 3.8 3:20 0.153 11:40 0.630 0.285 0.285 0.09
1/5/2018 3:20 2.1 20:05 2.8 2.5 3:55 2.8 12:45 4.1 3.7 3:55 0.155 20:05 0.334 0.265 0.265 0.42
1/6/2018 3:00 2.3 11:55 3.2 2.8 4:00 2.9 10:15 4.3 3.9 4:00 0.181 11:55 0.442 0.329 0.329 0.24
1/7/2018 4:45 2.4 19:25 3.4 2.9 3:55 3.0 19:10 4.5 3.9 3:55 0.199 19:25 0.492 0.352 0.352 0.38
1/8/2018 4:10 2.7 19:15 3.3 3.0 4:00 3.3 20:15 4.4 4.1 4:00 0.267 19:10 0.445 0.380 0.380 0.14
1/9/2018 0:05 2.9 10:15 4.0 3.3 3:25 3.5 10:15 4.8 4.3 3:25 0.305 10:15 0.667 0.446 0.446 0.46
1/10/2018 10:50 2.8 14:10 3.8 3.1 3:25 3.7 14:10 4.7 4.2 3:25 0.319 14:10 0.596 0.414 0.414 0.22
1/11/2018 1:50 2.8 14:15 4.8 3.9 2:05 3.7 14:10 5.2 4.7 2:05 0.305 14:10 0.900 0.645 0.645 1.04
1/12/2018 23:55 3.6 0:00 4.2 3.9 23:35 4.6 7:30 5.0 4.8 23:50 0.562 7:50 0.716 0.640 0.640 0.20
1/13/2018 23:55 3.3 11:20 3.8 3.5 6:05 4.2 13:10 4.8 4.6 6:05 0.461 11:20 0.606 0.536 0.536 0.02
1/14/2018 5:00 3.0 10:50 3.6 3.2 5:05 3.8 11:30 4.7 4.4 5:05 0.348 10:35 0.558 0.453 0.453 0.00
1/15/2018 3:35 2.7 19:45 3.3 3.0 2:40 3.5 13:45 4.5 4.2 2:40 0.280 19:45 0.465 0.396 0.396 0.04
1/16/2018 4:25 2.5 19:10 3.2 2.9 2:45 3.6 9:45 4.4 4.1 2:45 0.276 20:35 0.435 0.364 0.364 0.26
1/17/2018 3:15 2.4 21:15 3.9 3.0 1:55 3.3 21:05 4.8 4.2 3:30 0.236 21:05 0.636 0.394 0.394 0.79
1/18/2018 2:35 3.3 7:05 4.1 3.8 2:20 4.1 10:30 4.9 4.7 2:20 0.438 7:00 0.687 0.595 0.595 0.40
1/19/2018 23:55 3.2 8:20 3.7 3.5 3:40 4.1 6:40 4.7 4.5 23:55 0.426 8:20 0.574 0.509 0.509 0.10
1/20/2018 3:05 3.0 11:05 3.5 3.2 6:00 3.8 11:10 4.6 4.3 6:00 0.347 11:10 0.535 0.448 0.448 0.10
1/21/2018 5:35 2.8 11:50 3.5 3.1 4:00 3.6 10:35 4.6 4.2 4:00 0.306 11:50 0.523 0.421 0.421 0.16
1/22/2018 1:45 2.7 7:40 3.4 3.1 3:10 3.5 19:00 4.5 4.2 3:10 0.285 7:40 0.501 0.415 0.415 0.34
1/23/2018 3:05 2.7 20:25 4.3 3.4 2:55 3.5 19:25 4.8 4.3 2:55 0.287 19:25 0.717 0.484 0.484 0.79
1/24/2018 4:15 3.9 20:50 4.7 4.3 3:30 4.3 21:50 4.8 4.6 3:30 0.576 20:25 0.830 0.700 0.700 0.51
1/25/2018 23:55 3.7 7:35 4.3 4.0 2:00 4.2 9:05 4.9 4.6 23:50 0.553 9:05 0.729 0.646 0.646 0.14
1/26/2018 3:55 3.4 18:55 3.9 3.7 4:55 4.1 17:15 4.7 4.5 4:55 0.444 19:35 0.628 0.559 0.559 0.36
1/27/2018 0:15 3.7 12:15 4.9 4.4 0:25 4.5 10:45 5.0 4.8 0:25 0.555 11:15 0.893 0.759 0.759 0.61
1/28/2018 23:55 3.6 11:45 4.3 3.9 4:25 4.4 10:30 4.8 4.6 23:55 0.542 11:45 0.723 0.631 0.631 0.07
1/29/2018 3:55 3.3 19:15 5.3 4.2 3:05 4.1 16:35 5.1 4.7 3:05 0.443 18:35 1.013 0.699 0.699 0.90
1/30/2018 23:55 3.7 0:00 4.6 4.2 23:40 4.6 5:30 4.9 4.7 23:45 0.573 0:00 0.808 0.693 0.693 0.00
1/31/2018 23:50 3.3 7:40 3.8 3.6 3:35 4.1 17:40 4.7 4.5 23:45 0.450 7:40 0.607 0.538 0.538 0.00
ReportAvg 3.4 4.3 0.482
ReportTotal 14.94 8.79
ADS Environmental Services
Pipe Height: 10.75
REN_MH1360\mp1\DFINAL (inches) REN_MH1360\mp1\VFINAL (feet/sec) REN_MH1360\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:15 3.0 21:40 4.1 3.4 3:50 3.8 21:45 4.8 4.4 3:50 0.357 21:45 0.687 0.490 0.490 0.66
2/2/2018 23:45 3.5 8:00 4.0 3.7 16:30 4.0 8:05 4.7 4.5 23:55 0.500 8:05 0.642 0.570 0.570 0.04
2/3/2018 3:30 3.1 20:25 3.9 3.6 5:40 4.0 10:05 4.6 4.3 5:40 0.402 19:55 0.588 0.513 0.513 0.31
2/4/2018 23:55 3.3 12:05 4.0 3.6 4:55 4.0 11:40 4.7 4.3 4:55 0.433 12:05 0.646 0.528 0.528 0.02
2/5/2018 3:15 3.0 19:00 3.6 3.3 3:10 3.5 10:10 4.4 4.1 3:10 0.330 19:05 0.522 0.440 0.440 0.04
2/6/2018 3:40 2.8 10:35 3.8 3.1 3:25 3.4 10:40 4.3 4.0 3:25 0.286 10:40 0.558 0.388 0.388 0.00
2/7/2018 3:10 2.6 21:05 3.3 2.9 3:15 3.2 20:10 4.2 3.8 3:15 0.246 20:55 0.433 0.343 0.343 0.00
2/8/2018 3:45 2.5 20:40 3.2 2.8 2:45 3.2 9:05 4.1 3.8 3:35 0.232 20:40 0.403 0.324 0.324 0.09
2/9/2018 4:05 2.4 10:15 3.0 2.7 3:20 3.1 18:20 4.0 3.6 3:20 0.214 7:35 0.364 0.301 0.301 0.01
2/10/2018 4:35 2.3 11:00 3.1 2.7 4:20 3.0 11:15 4.0 3.6 4:20 0.196 11:15 0.392 0.293 0.293 0.01
2/11/2018 5:00 2.3 12:05 3.1 2.7 5:15 2.9 11:45 4.0 3.6 5:15 0.186 11:50 0.386 0.293 0.293 0.00
2/12/2018 3:30 2.1 20:20 2.9 2.5 2:10 2.7 20:25 3.9 3.5 3:35 0.157 20:20 0.351 0.253 0.253 0.00
2/13/2018 2:30 2.0 19:40 2.8 2.5 3:10 2.7 18:25 3.9 3.5 2:30 0.145 21:20 0.326 0.247 0.247 0.17
2/14/2018 4:25 2.1 19:30 2.8 2.5 3:10 2.9 6:40 3.9 3.5 3:10 0.170 19:15 0.314 0.251 0.251 0.15
2/15/2018 2:20 2.0 21:05 2.8 2.4 2:55 2.7 17:00 3.9 3.5 2:55 0.142 19:00 0.321 0.239 0.239 0.00
2/16/2018 2:15 2.0 19:55 2.7 2.4 1:10 2.7 19:45 3.9 3.5 3:40 0.150 19:50 0.316 0.238 0.238 0.15
2/17/2018 3:00 2.0 10:55 3.1 2.6 3:10 2.6 10:30 4.1 3.6 3:10 0.138 10:30 0.397 0.272 0.272 0.32
2/18/2018 4:10 2.1 10:45 3.0 2.5 4:10 2.7 10:35 4.1 3.5 4:10 0.150 10:35 0.370 0.254 0.254 0.01
2/19/2018 3:45 2.0 19:20 2.9 2.4 3:45 2.5 11:05 3.9 3.5 3:45 0.129 19:20 0.337 0.240 0.240 0.00
2/20/2018 2:50 1.9 19:35 2.7 2.3 2:45 2.5 19:10 4.0 3.5 2:45 0.119 19:10 0.298 0.223 0.223 0.00
2/21/2018 3:35 1.9 20:30 2.6 2.3 3:55 2.4 7:00 3.9 3.4 3:55 0.114 20:30 0.289 0.219 0.219 0.00
2/22/2018 3:50 1.8 19:10 2.6 2.3 3:15 2.4 20:40 3.8 3.4 3:15 0.111 19:10 0.282 0.212 0.212 0.07
2/23/2018 2:15 1.8 17:45 2.5 2.2 4:05 2.5 17:40 3.8 3.4 4:05 0.110 17:40 0.271 0.208 0.208 0.01
2/24/2018 4:30 1.8 10:40 2.7 2.3 3:55 2.4 10:35 3.8 3.4 3:50 0.109 10:35 0.307 0.212 0.212 0.13
2/25/2018 3:55 1.8 11:25 2.7 2.3 4:40 2.5 9:50 3.9 3.4 4:40 0.114 10:20 0.315 0.226 0.226 0.11
2/26/2018 3:20 1.8 19:00 2.6 2.2 3:40 2.3 19:45 3.9 3.3 3:40 0.100 19:45 0.285 0.203 0.203 0.00
2/27/2018 3:15 1.7 19:50 2.6 2.2 2:25 2.3 18:10 3.9 3.3 2:25 0.099 19:50 0.294 0.204 0.204 0.19
2/28/2018 3:10 1.8 19:15 2.9 2.3 3:55 2.3 21:00 4.0 3.4 3:50 0.105 19:15 0.336 0.222 0.222 0.35
ReportAvg 2.7 3.7 0.300
ReportTotal 8.405 2.84
ADS Environmental Services
Pipe Height: 10.75
REN_MH1360\mp1\DFINAL (inches) REN_MH1360\mp1\VFINAL (feet/sec) REN_MH1360\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 4:10 1.9 21:10 2.7 2.4 2:35 2.6 20:45 4.0 3.5 2:35 0.130 20:45 0.314 0.234 0.234 0.01
3/2/2018 1:40 1.9 20:00 2.7 2.3 1:30 2.6 18:45 4.0 3.5 1:30 0.133 20:00 0.309 0.232 0.232 0.07
3/3/2018 3:55 1.9 10:40 2.8 2.3 2:25 2.6 10:40 4.1 3.5 3:20 0.128 10:40 0.341 0.231 0.231 0.00
3/4/2018 4:45 1.8 10:25 2.8 2.3 4:50 2.4 10:30 4.0 3.5 4:50 0.107 10:30 0.326 0.228 0.228 0.12
3/5/2018 4:05 1.8 21:15 2.6 2.2 2:50 2.4 21:40 3.9 3.4 2:50 0.110 21:15 0.284 0.214 0.214 0.00
3/6/2018 3:05 1.8 21:05 2.6 2.2 1:45 2.3 21:05 3.9 3.4 1:45 0.105 21:05 0.293 0.209 0.209 0.00
3/7/2018 3:15 1.8 19:15 2.6 2.2 4:00 2.4 7:35 3.9 3.4 4:00 0.108 19:50 0.285 0.207 0.207 0.03
3/8/2018 4:10 1.8 21:15 2.7 2.2 2:20 2.3 22:00 3.9 3.4 2:20 0.104 21:15 0.301 0.209 0.209 0.37
3/9/2018 3:35 1.8 7:40 2.5 2.2 2:45 2.5 19:00 3.9 3.5 2:45 0.117 7:40 0.281 0.214 0.214 0.00
3/10/2018 3:55 1.8 9:40 2.6 2.2 3:05 2.3 10:25 3.9 3.5 4:05 0.102 10:35 0.295 0.214 0.214 0.00
3/11/2018 4:45 1.7 11:50 2.6 2.2 3:15 2.3 18:45 4.0 3.4 4:45 0.099 11:30 0.295 0.215 0.215 0.00
3/12/2018 3:10 1.7 19:05 2.6 2.2 2:50 2.4 19:55 3.9 3.4 2:50 0.100 19:05 0.289 0.200 0.200 0.00
3/13/2018 2:20 1.7 18:55 2.7 2.2 2:05 2.3 17:35 3.9 3.4 2:05 0.097 20:10 0.297 0.201 0.201 0.31
3/14/2018 1:35 1.7 19:55 2.6 2.2 2:00 2.3 20:35 3.9 3.4 2:00 0.096 19:55 0.285 0.200 0.200 0.04
3/15/2018 1:30 1.7 19:45 2.5 2.1 1:30 2.4 19:45 3.9 3.4 1:30 0.100 19:45 0.279 0.200 0.200 0.00
3/16/2018 1:10 1.7 17:35 2.4 2.1 1:25 2.5 7:40 3.8 3.4 1:25 0.106 17:35 0.254 0.194 0.194 0.00
3/17/2018 3:10 1.7 11:05 2.7 2.2 3:00 2.5 10:50 3.8 3.3 3:00 0.104 11:05 0.295 0.198 0.198 0.00
3/18/2018 3:45 1.7 10:25 2.6 2.2 4:25 2.4 10:25 3.9 3.3 4:25 0.097 10:25 0.298 0.198 0.198 0.00
3/19/2018 0:25 1.7 19:25 2.5 2.1 23:50 2.5 20:25 3.8 3.4 23:50 0.110 19:25 0.273 0.192 0.192 0.00
3/20/2018 2:55 1.6 20:05 2.5 2.0 2:05 2.4 20:40 3.8 3.3 2:05 0.095 20:05 0.273 0.180 0.180 0.00
3/21/2018 3:05 1.6 13:00 2.7 2.1 3:45 2.4 9:55 4.0 3.4 1:20 0.093 13:00 0.324 0.191 0.191 0.10
3/22/2018 1:50 1.6 6:35 2.5 2.1 2:45 2.3 6:35 3.9 3.4 2:45 0.091 6:35 0.278 0.192 0.192 0.48
3/23/2018 2:55 1.7 17:55 2.5 2.2 3:15 2.5 9:20 4.0 3.5 3:15 0.099 9:40 0.288 0.207 0.207 0.31
3/24/2018 2:45 1.7 9:25 2.8 2.3 2:35 2.5 10:05 4.1 3.6 2:35 0.106 9:30 0.343 0.227 0.227 0.28
3/25/2018 4:20 1.7 9:25 2.8 2.3 2:40 2.5 9:30 4.1 3.6 2:40 0.110 9:25 0.341 0.229 0.229 0.01
3/26/2018 2:40 1.7 20:40 2.6 2.2 3:45 2.5 6:25 4.0 3.5 3:45 0.112 20:40 0.297 0.214 0.214 0.17
3/27/2018 3:15 1.7 19:45 2.5 2.2 3:30 2.6 18:25 4.0 3.5 3:30 0.110 21:00 0.287 0.209 0.209 0.02
3/28/2018 3:00 1.7 19:30 2.6 2.2 1:50 2.5 20:25 3.9 3.5 1:50 0.107 19:15 0.286 0.206 0.206 0.01
3/29/2018 3:05 1.7 19:55 2.6 2.1 3:10 2.4 18:10 4.0 3.4 3:10 0.098 19:55 0.280 0.197 0.197 0.00
3/30/2018 2:45 1.7 18:05 2.4 2.1 3:15 2.5 7:00 3.9 3.4 2:20 0.102 18:05 0.259 0.191 0.191 0.00
3/31/2018 2:55 1.6 11:15 2.7 2.1 2:55 2.3 11:15 3.9 3.4 2:55 0.090 11:15 0.306 0.200 0.200 0.00
ReportAvg 2.2 3.4 0.208
ReportTotal 6.433 2.33
ADS Environmental Services
Pipe Height: 10.75
REN_MH1360\mp1\DFINAL (inches) REN_MH1360\mp1\VFINAL (feet/sec) REN_MH1360\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 2:40 1.6 11:10 2.7 2.0 3:20 2.5 11:10 4.0 3.3 2:45 0.101 11:10 0.321 0.186 0.094 0.10
4/2/2018 -- 0.00
4/3/2018 -- 0.00
4/4/2018 23:50 1.6 20:15 2.7 2.2 23:55 2.7 18:50 4.0 3.5 23:55 0.104 20:15 0.304 0.206 0.171 0.39
4/5/2018 1:10 1.5 19:15 2.7 2.1 1:20 2.4 19:10 4.0 3.3 1:10 0.082 19:15 0.316 0.196 0.196 0.25
4/6/2018 3:05 1.6 6:50 2.6 2.1 3:05 2.6 6:50 3.9 3.4 3:05 0.093 6:50 0.291 0.199 0.199 0.00
4/7/2018 1:15 1.7 9:50 3.0 2.4 1:15 2.7 11:40 4.1 3.7 1:15 0.110 9:50 0.373 0.263 0.263 0.88
4/8/2018 2:45 2.0 11:00 3.1 2.7 2:25 2.6 17:35 4.6 3.9 2:25 0.141 10:25 0.415 0.307 0.307 0.45
4/9/2018 3:05 2.2 20:20 2.9 2.5 2:20 3.1 18:05 4.2 3.9 2:20 0.188 18:05 0.369 0.290 0.290 0.00
4/10/2018 3:15 2.0 20:25 2.9 2.5 1:30 3.0 20:30 4.3 3.9 1:55 0.168 20:30 0.375 0.276 0.276 0.23
4/11/2018 1:30 2.0 21:30 2.8 2.5 1:05 2.9 21:15 4.2 3.8 1:05 0.162 21:15 0.349 0.271 0.271 0.31
4/12/2018 2:10 2.1 19:45 2.8 2.5 2:20 3.0 11:55 4.4 3.8 2:20 0.166 11:55 0.352 0.273 0.273 0.11
4/13/2018 1:55 2.0 18:25 2.9 2.5 0:40 2.8 18:30 4.2 3.8 0:40 0.155 18:30 0.364 0.281 0.281 0.51
4/14/2018 2:35 2.5 23:45 4.8 3.6 3:50 3.4 19:40 5.1 4.4 3:50 0.253 22:30 0.894 0.550 0.550 1.52
4/15/2018 23:50 3.7 9:15 4.8 4.5 22:40 4.8 10:05 5.2 5.1 23:55 0.596 9:20 0.921 0.817 0.817 0.21
4/16/2018 3:45 3.5 18:15 4.4 4.0 3:20 4.6 18:55 5.4 5.0 3:20 0.539 18:15 0.844 0.678 0.678 0.71
4/17/2018 23:55 3.2 5:45 4.1 3.8 23:50 4.5 5:40 5.2 5.0 23:55 0.467 5:45 0.735 0.630 0.630 0.01
4/18/2018 23:55 2.9 6:40 3.6 3.3 3:05 4.1 6:50 4.9 4.6 23:55 0.374 6:50 0.574 0.487 0.487 0.12
4/19/2018 23:40 2.6 7:15 3.3 3.0 23:40 3.9 6:50 4.7 4.4 23:40 0.293 6:50 0.493 0.407 0.407 0.00
4/20/2018 23:55 2.5 6:50 3.1 2.8 2:05 3.6 7:25 4.5 4.2 2:05 0.270 6:50 0.431 0.353 0.353 0.00
4/21/2018 2:30 2.3 10:20 3.0 2.6 3:20 3.3 8:05 4.4 4.0 3:20 0.216 10:25 0.403 0.316 0.316 0.05
4/22/2018 23:50 2.2 9:05 3.1 2.6 4:40 3.1 9:10 4.3 3.9 4:05 0.189 9:10 0.409 0.302 0.302 0.00
ReportAvg 2.8 4.1 0.370
ReportTotal 7.160 5.85
REN_MH1763
Located At: 3000 SE 5th St (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 15”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the pressure sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 98%
Velocity (f/s) 100% 98%
Quantity (mgd) 100% 98%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 4.06 0.17 0.035 27%
Maximum 17.41 0.95 0.749 100%
Average 9.59 0.47 0.257 64%
Latitude: 47.477311°
Longitude:-122.179048°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Site located in roadway. Traffic control required.
Moderate, slow flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Located in roadway, at intersection. Requires traffic
control.
Sensors / Devices:
15.00'' x 15.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
3:17:00 PM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~8.00''
Velocity Sensor Offset (in)
.3 FPS
Temporary
15.00'' x 15.00''
REN_MH1763
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
3000 SE 5th St
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.13.17
Upstream 0-5 FT Manhole
MH1763 Residential
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.25''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
Concrete
20''
NormalUnbolted
20''
ADS Environmental Services
Pipe Height: 15.00
REN_MH1763\mp1\DFINAL (inches) REN_MH1763\mp1\VFINAL (feet/sec) REN_MH1763\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
12/22/2017 4:10 6.8 11:45 12.3 10.0 16:40 0.2 8:10 0.6 0.4 22:30 0.133 11:45 0.305 0.193 0.193
12/23/2017 23:55 8.6 11:10 12.8 10.0 8:35 0.2 22:55 0.6 0.3 8:35 0.115 22:55 0.285 0.185 0.185
12/24/2017 5:05 6.0 11:50 12.7 9.1 15:00 0.2 22:15 0.7 0.4 4:55 0.090 11:55 0.355 0.188 0.188
12/25/2017 5:40 5.5 10:55 11.6 8.5 14:10 0.3 6:15 0.7 0.5 6:40 0.120 11:05 0.388 0.233 0.233
12/26/2017 4:55 5.7 12:20 12.1 8.8 14:10 0.2 3:00 0.6 0.4 7:20 0.098 9:40 0.241 0.171 0.171
12/27/2017 5:20 5.7 11:40 11.4 8.6 10:00 0.2 8:00 0.6 0.4 3:20 0.090 21:40 0.255 0.177 0.177
12/28/2017 4:25 5.4 11:40 11.6 8.5 11:50 0.2 21:55 0.6 0.4 5:25 0.094 12:25 0.305 0.195 0.195
12/29/2017 3:20 7.8 11:30 17.4 13.4 7:30 0.4 14:05 0.8 0.6 3:25 0.201 14:05 0.656 0.398 0.398
12/30/2017 23:55 10.1 11:40 14.6 12.5 14:35 0.3 0:15 0.6 0.4 22:50 0.168 0:15 0.444 0.298 0.298
12/31/2017 5:30 8.1 11:45 13.5 11.0 14:45 0.3 9:05 0.6 0.4 7:20 0.185 12:55 0.330 0.251 0.251
ReportAvg 10.1 0.4 0.229
ReportTotal 2.290
ADS Environmental Services
Pipe Height: 15.00
REN_MH1763\mp1\DFINAL (inches) REN_MH1763\mp1\VFINAL (feet/sec) REN_MH1763\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
1/1/2018 23:55 8.8 12:25 13.1 10.9 20:00 0.3 23:10 0.6 0.4 23:45 0.169 12:25 0.303 0.241 0.241
1/2/2018 4:50 6.5 9:35 11.5 9.2 13:05 0.3 6:25 0.6 0.5 3:55 0.132 20:25 0.336 0.229 0.229
1/3/2018 5:05 6.3 21:20 12.2 9.8 15:05 0.2 5:55 0.6 0.4 5:15 0.128 23:25 0.303 0.201 0.201
1/4/2018 23:55 8.2 8:10 11.7 10.0 0:45 0.2 20:45 0.7 0.4 0:45 0.115 20:45 0.344 0.244 0.244
1/5/2018 4:50 5.7 9:35 11.5 8.9 10:30 0.4 19:55 0.7 0.6 4:05 0.151 19:30 0.357 0.275 0.275
1/6/2018 4:40 7.1 10:25 12.9 9.9 7:45 0.5 21:55 0.7 0.6 4:35 0.227 10:15 0.463 0.321 0.321
1/7/2018 5:30 6.8 10:30 12.7 10.0 11:30 0.3 4:40 0.7 0.5 11:30 0.203 10:40 0.454 0.282 0.282
1/8/2018 4:25 7.6 9:30 12.3 10.0 10:35 0.3 0:55 0.6 0.5 3:55 0.168 8:05 0.331 0.253 0.253
1/9/2018 1:35 8.5 8:30 13.0 10.4 12:20 0.3 6:00 0.6 0.5 0:00 0.175 7:45 0.370 0.285 0.285
1/10/2018 4:35 7.4 21:45 13.0 10.5 19:00 0.4 6:25 0.7 0.5 3:15 0.173 7:55 0.362 0.283 0.283
1/11/2018 4:35 10.2 14:40 16.0 13.2 1:15 0.3 19:45 0.8 0.5 5:40 0.184 19:45 0.612 0.394 0.394
1/12/2018 4:50 10.1 21:10 13.5 12.2 23:20 0.5 9:40 0.8 0.7 23:20 0.330 9:40 0.547 0.455 0.455
1/13/2018 23:50 10.0 10:40 14.1 12.0 1:20 0.5 23:10 0.7 0.6 6:15 0.294 11:05 0.492 0.384 0.384
1/14/2018 5:35 8.0 12:20 13.7 11.1 18:05 0.4 10:00 0.8 0.6 6:20 0.276 11:20 0.501 0.376 0.376
1/15/2018 23:55 9.2 11:40 12.9 11.0 10:30 0.4 21:00 0.8 0.6 4:05 0.238 11:35 0.455 0.349 0.349
1/16/2018 4:30 7.4 21:45 12.6 10.6 12:40 0.4 6:10 0.7 0.6 4:00 0.234 8:30 0.428 0.337 0.337
1/17/2018 4:45 9.6 21:10 13.4 11.3 8:40 0.4 18:45 0.8 0.5 3:20 0.235 21:05 0.514 0.342 0.342
1/18/2018 3:20 9.4 21:05 14.3 12.4 16:05 0.4 0:05 0.7 0.6 3:00 0.294 20:55 0.527 0.416 0.416
1/19/2018 23:55 9.8 9:10 13.9 11.9 11:45 0.5 19:55 0.8 0.6 4:20 0.331 9:10 0.486 0.412 0.412
1/20/2018 5:40 8.0 10:40 13.4 10.3 7:25 0.5 16:50 0.8 0.7 5:25 0.297 12:40 0.523 0.405 0.405
1/21/2018 5:35 7.4 12:25 13.4 10.8 17:50 0.3 10:10 0.8 0.6 17:50 0.230 19:40 0.524 0.384 0.384
1/22/2018 23:55 9.4 8:10 13.3 11.3 12:45 0.3 1:05 0.6 0.4 23:35 0.167 7:10 0.412 0.271 0.271
1/23/2018 4:40 7.5 21:15 12.8 10.7 1:10 0.4 21:00 0.9 0.6 4:05 0.159 21:00 0.633 0.381 0.381
1/24/2018 5:00 10.0 20:30 15.0 12.7 13:35 0.5 20:50 0.8 0.7 13:35 0.354 20:50 0.655 0.493 0.493
1/25/2018 23:55 10.2 8:10 14.2 12.5 8:25 0.5 21:45 0.9 0.7 5:10 0.398 8:05 0.592 0.486 0.486
1/26/2018 4:15 8.3 20:55 13.6 11.4 23:00 0.5 9:10 0.8 0.7 4:35 0.319 20:15 0.550 0.438 0.438
1/27/2018 23:55 11.1 11:15 15.8 13.5 22:35 0.4 12:40 0.9 0.7 22:35 0.294 12:40 0.675 0.525 0.525
1/28/2018 6:05 9.3 12:10 14.4 12.1 23:15 0.4 9:10 0.8 0.7 23:15 0.296 12:00 0.608 0.461 0.461
1/29/2018 4:30 10.5 15:40 15.2 12.8 10:05 0.4 18:30 0.9 0.6 1:45 0.297 18:30 0.749 0.467 0.467
1/30/2018 4:25 9.6 20:45 13.9 12.1 5:25 0.6 20:45 0.7 0.7 4:40 0.320 20:45 0.548 0.459 0.459
1/31/2018 23:55 9.6 8:20 13.6 11.6 23:40 0.7 8:20 0.7 0.7 23:40 0.351 8:20 0.528 0.438 0.438
ReportAvg 11.2 0.6 0.364
ReportTotal 11.29
ADS Environmental Services
Pipe Height: 15.00
REN_MH1763\mp1\DFINAL (inches) REN_MH1763\mp1\VFINAL (feet/sec) REN_MH1763\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
2/1/2018 4:05 7.6 8:30 12.7 10.3 7:15 0.6 4:05 0.7 0.7 4:05 0.280 8:30 0.459 0.376 0.376
2/2/2018 3:50 8.9 11:15 12.8 10.9 16:00 0.6 0:00 0.6 0.6 3:50 0.310 11:15 0.426 0.369 0.369
2/3/2018 5:20 8.1 10:55 13.5 10.6 9:00 0.6 5:20 0.6 0.6 5:20 0.281 10:55 0.467 0.359 0.359
2/4/2018 4:55 8.3 10:45 13.8 10.8 12:15 0.6 4:55 0.6 0.6 4:55 0.288 10:45 0.484 0.366 0.366
2/5/2018 4:05 7.7 20:15 13.1 10.9 18:25 0.6 4:05 0.6 0.6 4:05 0.267 20:15 0.442 0.369 0.369
2/6/2018 15:30 8.9 0:00 11.6 9.9 6:20 0.6 15:30 0.6 0.6 17:55 0.301 7:20 0.394 0.338 0.338
2/7/2018 4:15 6.9 8:55 12.0 9.3 8:25 0.6 4:55 0.7 0.6 3:15 0.229 8:55 0.401 0.317 0.317
2/8/2018 4:15 6.4 9:00 12.2 9.2 13:05 0.5 7:15 0.8 0.6 4:15 0.212 9:00 0.439 0.316 0.316
2/9/2018 4:45 6.5 19:20 11.8 9.8 22:45 0.3 6:10 0.8 0.5 16:55 0.177 8:15 0.368 0.271 0.271
2/10/2018 23:55 8.1 0:00 11.0 9.3 6:05 0.2 22:10 0.6 0.4 6:05 0.096 13:35 0.316 0.214 0.214
2/11/2018 5:00 5.8 11:35 12.4 8.9 16:40 0.2 21:35 0.6 0.5 16:40 0.108 21:35 0.341 0.222 0.222
2/12/2018 4:40 5.5 9:25 11.2 8.5 12:45 0.3 6:55 0.6 0.4 2:55 0.086 21:25 0.276 0.189 0.189
2/13/2018 3:45 5.4 8:25 11.2 8.3 11:30 0.3 23:40 0.8 0.5 3:55 0.092 23:40 0.352 0.204 0.204
2/14/2018 5:05 5.6 8:20 11.4 8.5 11:15 0.2 22:45 0.7 0.4 3:55 0.100 22:45 0.336 0.199 0.199
2/15/2018 4:40 5.3 8:30 11.4 8.2 17:30 0.2 23:25 0.6 0.4 17:30 0.091 8:50 0.279 0.177 0.177
2/16/2018 3:40 5.4 8:25 11.3 9.3 11:25 0.3 5:30 0.6 0.4 2:50 0.119 8:35 0.294 0.219 0.219
2/17/2018 5:10 8.2 10:55 12.7 9.6 16:05 0.4 19:55 0.7 0.5 16:50 0.185 18:30 0.341 0.256 0.256
2/18/2018 5:55 6.1 11:20 12.5 9.1 18:35 0.3 0:00 0.6 0.5 5:35 0.124 12:50 0.403 0.235 0.235
2/19/2018 4:30 5.9 11:40 11.9 8.6 20:00 0.2 5:00 0.6 0.4 2:50 0.083 11:20 0.308 0.174 0.174
2/20/2018 4:40 5.5 10:10 11.8 8.4 0:10 0.2 5:55 0.6 0.4 0:10 0.074 10:15 0.359 0.197 0.197
2/21/2018 4:00 5.3 9:40 10.8 8.2 12:45 0.2 18:00 0.6 0.5 3:50 0.102 21:00 0.278 0.195 0.195
2/22/2018 4:10 5.2 11:40 10.9 8.1 13:35 0.2 0:40 0.6 0.4 3:25 0.087 20:45 0.274 0.193 0.193
2/23/2018 4:10 5.2 10:10 10.9 8.0 10:40 0.3 0:35 0.5 0.4 5:20 0.078 11:25 0.281 0.156 0.156
2/24/2018 4:35 5.3 11:00 11.9 8.3 20:35 0.3 9:50 0.4 0.4 4:05 0.077 11:00 0.246 0.160 0.160
2/25/2018 5:25 5.4 10:50 12.1 8.6 2:05 0.3 5:50 0.4 0.3 5:25 0.091 10:50 0.220 0.164 0.164
2/26/2018 4:35 5.3 21:10 11.6 9.2 21:00 0.3 0:55 0.4 0.3 4:35 0.090 21:10 0.211 0.170 0.170
2/27/2018 15:55 7.2 0:00 10.0 8.4 15:20 0.3 18:05 0.6 0.4 16:00 0.118 20:55 0.264 0.174 0.174
2/28/2018 3:45 5.3 8:30 11.1 8.2 3:15 0.3 19:50 0.5 0.4 3:15 0.071 9:45 0.249 0.156 0.156
ReportAvg 9.1 0.5 0.240
ReportTotal 6.734
ADS Environmental Services
Pipe Height: 15.00
REN_MH1763\mp1\DFINAL (inches) REN_MH1763\mp1\VFINAL (feet/sec) REN_MH1763\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
3/1/2018 3:45 5.9 8:10 11.7 8.5 11:20 0.3 21:40 0.6 0.4 4:20 0.095 21:40 0.334 0.201 0.201
3/2/2018 4:25 5.7 8:55 11.6 8.4 7:30 0.3 19:40 0.7 0.5 3:55 0.087 19:40 0.336 0.223 0.223
3/3/2018 5:05 5.4 10:45 12.3 8.5 22:35 0.2 3:35 0.6 0.4 22:35 0.095 11:35 0.342 0.178 0.178
3/4/2018 5:15 4.6 10:50 11.5 8.1 2:45 0.2 10:50 0.5 0.4 5:15 0.047 10:50 0.308 0.182 0.182
3/5/2018 4:10 4.7 9:15 10.6 7.7 4:10 0.2 9:15 0.5 0.4 4:10 0.051 9:15 0.277 0.169 0.169
3/6/2018 4:00 4.6 8:40 10.7 7.5 4:00 0.2 8:40 0.5 0.4 4:00 0.046 8:40 0.280 0.163 0.163
3/7/2018 4:20 4.6 8:20 10.8 7.6 4:20 0.2 8:20 0.5 0.4 4:20 0.047 8:20 0.281 0.164 0.164
3/8/2018 4:15 4.6 8:35 11.0 7.6 4:15 0.2 19:40 0.5 0.4 4:15 0.046 8:35 0.290 0.161 0.161
3/9/2018 4:40 5.0 11:40 10.2 7.7 1:55 0.2 20:50 0.5 0.4 2:00 0.061 13:05 0.261 0.168 0.168
3/10/2018 5:25 4.7 9:40 11.1 7.8 7:25 0.2 0:35 0.5 0.4 4:25 0.069 9:35 0.292 0.173 0.173
3/11/2018 4:15 4.8 9:30 10.8 8.0 4:15 0.3 9:30 0.5 0.4 4:15 0.056 9:30 0.284 0.180 0.180
3/12/2018 3:55 4.7 8:25 10.6 7.6 2:25 0.2 21:15 0.5 0.4 3:55 0.050 8:25 0.275 0.165 0.165
3/13/2018 3:30 4.7 8:25 10.4 7.6 3:30 0.2 8:25 0.5 0.4 3:30 0.052 8:25 0.271 0.168 0.168
3/14/2018 4:55 4.7 7:55 10.6 7.6 4:55 0.2 21:05 0.6 0.4 4:55 0.051 21:05 0.274 0.167 0.167
3/15/2018 3:45 4.4 7:50 10.7 7.3 8:50 0.3 19:00 0.6 0.5 3:50 0.075 19:00 0.276 0.174 0.174
3/16/2018 3:25 4.3 8:15 10.8 7.2 9:25 0.3 23:00 0.6 0.5 3:00 0.074 21:45 0.251 0.168 0.168
3/17/2018 4:35 4.1 9:00 10.2 7.4 5:25 0.3 11:05 0.7 0.5 2:20 0.075 11:05 0.344 0.184 0.184
3/18/2018 1:40 4.9 0:20 6.3 5.7 1:30 0.4 1:25 0.6 0.5 1:30 0.103 0:00 0.159 0.131 0.010
3/19/2018 --
3/20/2018 23:55 5.9 9:35 9.6 7.8 11:10 0.2 7:10 0.7 0.4 23:55 0.093 7:15 0.273 0.173 0.125
3/21/2018 3:45 4.1 7:40 10.5 7.2 9:30 0.2 19:05 0.6 0.4 3:10 0.051 19:40 0.240 0.147 0.147
3/22/2018 2:55 4.3 8:15 10.8 7.5 3:00 0.2 19:25 0.5 0.4 3:00 0.035 7:55 0.275 0.153 0.153
3/23/2018 3:00 4.5 9:40 10.7 7.7 1:50 0.3 5:10 0.5 0.4 1:50 0.067 9:40 0.251 0.160 0.160
3/24/2018 3:50 5.2 8:50 11.4 8.4 17:35 0.2 3:55 0.6 0.4 2:05 0.095 8:40 0.243 0.161 0.161
3/25/2018 4:15 5.3 8:45 11.1 8.4 5:40 0.2 21:40 0.6 0.4 4:30 0.076 21:40 0.286 0.170 0.170
3/26/2018 3:20 5.0 8:25 10.7 7.9 20:35 0.3 6:15 0.7 0.5 2:50 0.084 6:55 0.286 0.190 0.190
3/27/2018 3:05 4.9 7:40 11.1 7.8 0:45 0.2 7:40 0.5 0.4 3:05 0.058 7:40 0.292 0.174 0.174
3/28/2018 2:35 4.9 7:45 11.0 7.8 2:35 0.3 18:40 0.5 0.4 2:35 0.057 7:25 0.269 0.165 0.165
3/29/2018 3:10 4.8 7:35 10.9 7.7 0:10 0.2 19:15 0.5 0.4 3:00 0.052 20:40 0.265 0.149 0.149
3/30/2018 3:45 4.6 8:20 11.2 7.8 4:15 0.2 21:10 0.5 0.4 4:15 0.047 8:05 0.290 0.170 0.170
3/31/2018 3:35 4.8 8:45 10.5 8.0 5:45 0.2 0:00 0.4 0.3 4:25 0.043 9:00 0.217 0.147 0.147
ReportAvg 7.8 0.4 0.170
ReportTotal 4.909
ADS Environmental Services
Pipe Height: 15.00
REN_MH1763\mp1\DFINAL (inches) REN_MH1763\mp1\VFINAL (feet/sec) REN_MH1763\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
4/1/2018 4:30 4.6 9:00 11.1 8.0 5:15 0.2 20:25 0.5 0.4 4:30 0.046 9:00 0.294 0.176 0.176
4/2/2018 3:05 4.5 8:35 10.6 7.5 3:05 0.2 8:35 0.5 0.4 3:05 0.044 8:35 0.275 0.162 0.162
4/3/2018 4:00 4.5 8:05 10.8 7.4 4:00 0.2 7:05 0.5 0.4 4:00 0.045 7:40 0.285 0.157 0.157
4/4/2018 2:55 4.4 7:30 10.8 7.6 2:55 0.2 7:30 0.5 0.4 2:55 0.041 7:30 0.282 0.167 0.167
4/5/2018 3:20 4.6 7:30 10.8 7.6 3:20 0.2 7:30 0.5 0.4 3:20 0.048 7:30 0.284 0.167 0.167
4/6/2018 3:25 4.8 8:10 11.2 9.1 3:25 0.3 8:10 0.5 0.4 3:25 0.056 8:10 0.297 0.221 0.221
4/7/2018 3:15 7.5 10:40 13.5 10.9 3:15 0.4 10:40 0.5 0.5 3:15 0.165 10:40 0.400 0.290 0.290
4/8/2018 6:25 8.1 10:30 12.1 10.0 6:25 0.4 10:30 0.5 0.5 6:25 0.188 10:30 0.329 0.257 0.257
4/9/2018 3:20 6.9 9:25 11.7 9.2 3:20 0.4 9:25 0.5 0.4 3:20 0.140 9:25 0.316 0.224 0.224
4/10/2018 3:15 6.3 8:30 12.2 9.1 1:10 0.3 20:05 0.5 0.4 1:10 0.125 8:40 0.332 0.217 0.217
4/11/2018 3:30 6.2 8:30 11.5 9.0 3:30 0.4 17:35 0.5 0.4 3:30 0.111 8:30 0.307 0.210 0.210
4/12/2018 3:15 6.7 20:55 12.1 10.3 3:20 0.4 5:15 0.5 0.4 3:20 0.130 20:55 0.332 0.261 0.261
4/13/2018 2:55 9.2 19:55 12.1 11.0 14:15 0.4 0:20 0.5 0.5 2:55 0.227 19:55 0.332 0.292 0.292
4/14/2018 3:50 10.2 21:30 15.9 13.5 0:10 0.4 21:30 0.7 0.6 3:50 0.264 21:30 0.580 0.426 0.426
4/15/2018 23:55 10.5 0:00 15.0 13.1 21:15 0.3 0:00 0.6 0.5 6:15 0.216 0:00 0.501 0.335 0.335
4/16/2018 3:40 9.0 21:25 14.7 12.0 1:40 0.4 21:25 0.6 0.5 4:15 0.220 21:25 0.484 0.333 0.333
4/17/2018 23:55 11.7 20:40 14.4 13.1 7:40 0.4 20:40 0.6 0.5 23:45 0.300 20:40 0.462 0.373 0.373
4/18/2018 3:15 10.7 7:10 13.6 12.2 6:30 0.3 8:35 0.5 0.4 6:30 0.226 7:45 0.399 0.309 0.309
4/19/2018 23:55 8.2 7:05 13.0 11.2 21:25 0.4 7:05 0.5 0.4 23:50 0.168 7:05 0.374 0.284 0.284
4/20/2018 2:05 7.1 7:40 12.5 10.6 8:00 0.3 11:15 0.5 0.4 2:05 0.148 7:15 0.346 0.259 0.259
4/21/2018 6:10 7.7 0:00 10.7 9.4 16:30 0.4 12:50 0.6 0.5 5:50 0.176 12:50 0.345 0.246 0.246
4/22/2018 3:40 6.2 8:50 11.5 9.1 2:55 0.3 20:10 0.6 0.4 3:40 0.111 20:10 0.320 0.223 0.223
ReportAvg 10.1 0.4 0.254
ReportTotal 5.588
REN_MH2116
Located At: Shattuck Ave and Tobin St (see attached site report for details)
Monitoring Period: January 17, 2018 – April 22, 2018
Pipe Dimensions: 14.38”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. This location was installed on January 17, 2018 after the official monitoring period had begun as
directed by the client. Based upon the quality and consistency of the observed flow depth and velocity
data, the Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 3.57 2.15 0.309 25%
Maximum 20.21 3.36 2.248 100%
Average 6.09 2.86 0.844 42%
Latitude: 47.483765°
Longitude:-122.211201°
REN_MH2116
TRITON+
System Characteristics
Location Type
Pipe ShapeSite located in middile of street in front of
school
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
Shattuck Ave S and S Tobin St
Flow Monitoring
Site Report
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, January 17, 2018
Access
Temporary
14.38 X 14.50
Traffic
MH2116 Residential / Commercial
Map
Installation Type:
Monitoring Location (Sensors):
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
1.38"
Peak Velocity (fps)
Silt (in)
2:11:00 PM 14.38 X 14.50Site Sketch Profile View or Photo
Straight, Some Ripples
0 - 5 psi
Depth of Flow (Wet DOF) (in)
6.50''
Velocity Sensor Offset (in)
3.36
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
PVC Good
15'
Manhole Condition:
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
No
Vitrified Clay Pipe
NormalUnbolted
Fair
Active Connections
Renton traffic control required.
Air Quality:
Communication Type
Normal
Additional Photos
Flow Direction
Monitoring Point
Google Map KEY
Top Down Location
Inlet Outlet Location Map
ADS Environmental Services
Pipe Height: 14.38
REN_MH2116\mp1\DFINAL (inches) REN_MH2116\mp1\VFINAL (feet/sec) REN_MH2116\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
1/1/2018 --
1/2/2018 --
1/3/2018 --
1/4/2018 --
1/5/2018 --
1/6/2018 --
1/7/2018 --
1/8/2018 --
1/9/2018 --
1/10/2018 --
1/11/2018 --
1/12/2018 --
1/13/2018 --
1/14/2018 --
1/15/2018 --
1/16/2018 --
1/17/2018 15:35 6.4 18:35 13.8 9.0 16:45 2.4 15:10 2.8 2.6 15:55 0.866 18:30 1.870 1.251 0.469
1/18/2018 1:45 6.7 5:30 11.9 8.6 6:25 2.6 2:10 2.9 2.7 1:45 0.904 5:30 1.748 1.233 1.233
1/19/2018 3:55 6.8 8:10 8.7 7.6 11:50 2.6 16:05 3.0 2.8 23:30 0.943 8:10 1.314 1.085 1.085
1/20/2018 6:00 6.4 12:05 8.5 7.2 12:15 2.5 9:40 2.9 2.8 6:05 0.893 13:00 1.292 1.022 1.022
1/21/2018 4:20 6.1 17:00 10.6 7.1 19:25 2.6 7:25 3.0 2.8 6:25 0.832 16:55 1.573 1.004 1.004
1/22/2018 1:45 6.2 6:25 9.3 7.3 13:50 2.5 4:40 3.1 2.7 23:45 0.852 6:05 1.328 1.022 1.022
1/23/2018 3:55 6.0 16:00 12.3 8.2 19:15 2.4 6:00 3.0 2.7 3:00 0.795 16:00 1.771 1.169 1.169
1/24/2018 4:15 8.1 18:30 13.6 9.7 13:25 2.5 5:50 2.8 2.7 5:30 1.147 18:30 1.937 1.410 1.410
1/25/2018 23:25 7.8 11:55 10.3 8.8 7:45 2.6 20:05 2.9 2.7 23:40 1.098 11:55 1.526 1.278 1.278
1/26/2018 1:40 7.2 12:30 10.0 8.3 23:10 2.5 8:40 2.9 2.7 6:10 0.950 11:00 1.502 1.196 1.196
1/27/2018 23:00 8.2 10:55 13.5 9.8 14:55 2.5 21:30 2.8 2.7 23:05 1.177 10:55 1.947 1.445 1.445
1/28/2018 23:40 7.5 11:40 9.9 8.5 12:35 2.5 2:55 2.8 2.7 4:50 1.027 9:05 1.460 1.218 1.218
1/29/2018 2:15 6.9 16:40 20.2 10.3 9:35 2.3 16:35 3.1 2.7 4:20 0.952 16:35 2.248 1.435 1.435
1/30/2018 23:55 7.8 0:00 10.7 9.1 20:05 2.5 21:05 2.8 2.7 23:20 1.078 0:00 1.571 1.318 1.318
1/31/2018 23:45 6.9 20:15 9.2 7.9 17:45 2.5 8:40 2.8 2.7 23:45 0.951 20:15 1.348 1.115 1.115
ReportAvg 8.5 2.7 1.212
ReportTotal 17.42
ADS Environmental Services
Pipe Height: 14.38
REN_MH2116\mp1\DFINAL (inches) REN_MH2116\mp1\VFINAL (feet/sec) REN_MH2116\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
2/1/2018 3:15 6.4 21:45 13.0 8.2 22:50 2.4 3:00 2.9 2.7 5:25 0.878 21:45 1.801 1.149 1.149
2/2/2018 23:55 7.2 8:40 9.8 8.4 20:50 2.4 15:30 2.8 2.6 23:55 0.965 11:10 1.406 1.165 1.165
2/3/2018 4:40 6.6 18:55 9.7 8.0 22:55 2.4 0:50 2.8 2.6 2:55 0.879 18:55 1.376 1.101 1.101
2/4/2018 3:20 6.7 13:20 9.7 7.9 11:55 2.4 2:30 2.7 2.6 3:50 0.881 13:20 1.359 1.069 1.069
2/5/2018 3:55 6.2 14:45 8.6 7.3 10:45 2.3 4:10 2.8 2.6 3:10 0.800 14:45 1.196 0.968 0.968
2/6/2018 3:30 5.9 18:45 8.4 6.9 18:25 2.5 4:20 2.8 2.7 3:55 0.772 12:15 1.173 0.934 0.934
2/7/2018 4:20 5.7 13:15 8.0 6.7 14:50 2.4 4:25 3.0 2.7 3:05 0.738 14:15 1.103 0.894 0.894
2/8/2018 3:30 5.6 18:15 7.9 6.5 18:15 2.4 4:05 2.9 2.7 2:30 0.699 8:10 1.140 0.864 0.864
2/9/2018 3:40 5.4 11:15 7.9 6.3 19:10 2.5 0:45 2.9 2.7 3:40 0.687 11:15 1.120 0.833 0.833
2/10/2018 4:25 5.3 13:30 8.0 6.3 11:10 2.4 5:15 3.1 2.7 4:15 0.658 14:35 1.117 0.836 0.836
2/11/2018 4:50 5.5 13:40 8.1 6.4 11:25 2.4 0:55 3.0 2.7 5:10 0.666 13:40 1.120 0.849 0.849
2/12/2018 2:20 5.2 19:30 7.5 6.0 13:35 2.6 23:05 3.1 2.8 2:15 0.646 14:00 1.110 0.822 0.822
2/13/2018 3:55 5.0 23:25 7.9 5.9 18:00 2.6 7:20 3.1 2.8 3:55 0.585 23:25 1.152 0.816 0.816
2/14/2018 4:40 5.2 17:20 7.7 6.1 19:10 2.6 9:45 3.2 2.9 3:55 0.653 17:20 1.129 0.864 0.864
2/15/2018 3:05 5.0 11:15 7.1 5.7 9:30 2.6 21:25 3.2 2.9 3:10 0.620 11:10 1.034 0.783 0.783
2/16/2018 1:45 4.7 9:30 7.1 5.7 8:35 2.7 23:45 3.2 2.9 1:40 0.580 9:30 1.066 0.801 0.801
2/17/2018 4:00 4.7 9:05 9.6 6.6 10:55 2.5 5:00 3.2 2.9 3:25 0.593 9:05 1.468 0.934 0.934
2/18/2018 5:40 5.0 12:00 7.8 6.0 14:05 2.6 23:45 3.2 3.0 4:25 0.669 13:00 1.177 0.863 0.863
2/19/2018 4:40 4.7 11:30 7.1 5.7 2:05 2.8 7:50 3.3 3.0 5:20 0.589 12:35 1.080 0.810 0.810
2/20/2018 4:00 4.6 13:10 7.5 5.4 13:15 2.7 15:30 3.2 3.0 2:40 0.567 13:10 1.151 0.762 0.762
2/21/2018 2:00 4.5 20:15 6.4 5.2 2:45 2.7 23:50 3.2 3.0 2:45 0.548 20:10 0.963 0.719 0.719
2/22/2018 3:30 4.5 12:35 6.7 5.3 4:55 2.7 17:05 3.2 3.0 4:55 0.539 12:30 0.995 0.725 0.725
2/23/2018 3:05 4.6 13:30 6.2 5.0 3:05 2.5 13:30 3.3 3.0 3:05 0.501 13:30 0.989 0.686 0.686
2/24/2018 4:45 4.4 11:40 6.6 5.2 7:25 2.8 20:10 3.3 3.0 4:15 0.557 11:40 1.003 0.730 0.730
2/25/2018 4:30 4.5 11:25 6.9 5.4 4:35 2.8 20:00 3.2 3.0 4:35 0.561 14:30 1.073 0.777 0.777
2/26/2018 3:50 4.4 16:35 6.5 5.0 3:30 2.8 9:10 3.3 3.0 3:30 0.536 16:30 1.021 0.702 0.702
2/27/2018 3:20 4.2 20:20 6.7 5.0 3:00 2.7 10:55 3.3 3.0 3:15 0.500 20:15 0.980 0.682 0.682
2/28/2018 4:00 4.3 19:10 7.4 5.3 1:10 2.8 9:40 3.3 3.0 3:55 0.525 19:10 1.154 0.738 0.738
ReportAvg 6.2 2.8 0.853
ReportTotal 23.88
ADS Environmental Services
Pipe Height: 14.38
REN_MH2116\mp1\DFINAL (inches) REN_MH2116\mp1\VFINAL (feet/sec) REN_MH2116\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
3/1/2018 3:40 4.5 13:50 6.3 5.1 1:10 2.8 19:50 3.3 3.0 3:10 0.563 13:50 0.973 0.722 0.722
3/2/2018 1:15 4.5 9:00 6.5 5.2 2:50 2.8 7:50 3.2 3.1 1:10 0.569 9:00 1.019 0.741 0.741
3/3/2018 3:05 4.4 10:40 6.4 5.0 4:10 2.7 13:45 3.2 3.0 4:10 0.524 10:40 0.960 0.695 0.695
3/4/2018 4:20 4.2 16:15 7.2 5.0 4:10 2.5 9:55 3.2 2.9 4:15 0.440 16:10 1.115 0.684 0.684
3/5/2018 3:55 4.1 12:00 5.8 4.8 3:30 2.6 19:30 3.3 2.9 3:55 0.460 8:40 0.882 0.640 0.640
3/6/2018 3:30 3.9 19:00 5.7 4.6 3:35 2.5 16:55 3.2 2.9 3:35 0.401 20:55 0.839 0.597 0.597
3/7/2018 3:30 3.9 9:35 5.5 4.6 1:10 2.5 17:30 3.3 2.9 4:15 0.406 9:35 0.784 0.582 0.582
3/8/2018 4:15 3.8 21:15 8.9 4.9 2:55 2.4 12:40 3.2 2.9 2:55 0.389 21:15 1.393 0.650 0.650
3/9/2018 3:25 4.2 9:05 5.9 4.7 2:15 2.5 11:15 3.3 2.9 2:15 0.459 9:05 0.869 0.626 0.626
3/10/2018 4:00 3.8 10:45 6.0 4.6 5:00 2.4 12:15 3.2 2.9 5:15 0.389 12:15 0.911 0.596 0.596
3/11/2018 3:50 3.7 10:50 6.0 4.6 4:15 2.4 14:45 3.3 2.9 3:50 0.371 10:50 0.903 0.591 0.591
3/12/2018 2:25 3.7 10:15 5.6 4.4 3:30 2.3 14:15 3.2 2.8 3:30 0.346 10:15 0.824 0.554 0.554
3/13/2018 2:50 3.7 18:55 7.0 4.7 1:00 2.3 6:55 3.2 2.9 1:00 0.353 18:55 1.055 0.595 0.595
3/14/2018 3:00 3.8 19:55 5.6 4.6 4:05 2.5 7:10 3.2 2.9 2:20 0.395 12:25 0.813 0.589 0.589
3/15/2018 2:25 3.8 11:00 5.7 4.5 1:20 2.4 6:40 3.3 2.8 2:00 0.375 6:40 0.872 0.570 0.570
3/16/2018 2:20 3.7 17:45 5.6 4.5 3:45 2.3 18:30 3.2 2.8 3:45 0.360 17:45 0.801 0.554 0.554
3/17/2018 3:05 3.7 10:30 5.7 4.4 2:30 2.3 16:10 3.1 2.8 5:30 0.351 10:30 0.842 0.544 0.544
3/18/2018 3:25 3.7 10:20 5.8 4.4 2:20 2.3 15:10 3.2 2.8 2:40 0.351 10:20 0.881 0.547 0.547
3/19/2018 2:55 3.6 8:15 5.7 4.4 2:25 2.2 8:15 3.1 2.8 2:25 0.321 8:15 0.849 0.534 0.534
3/20/2018 1:45 3.6 9:25 6.2 4.5 2:05 2.2 9:05 3.1 2.8 2:05 0.309 9:25 0.940 0.545 0.545
3/21/2018 2:35 3.6 10:45 5.0 4.3 3:00 2.2 9:50 3.1 2.8 3:00 0.331 9:50 0.680 0.516 0.516
3/22/2018 3:25 3.7 8:45 6.6 4.8 1:45 2.3 9:40 3.3 2.9 1:45 0.355 8:50 0.967 0.628 0.628
3/23/2018 3:10 3.7 9:50 7.8 4.9 3:35 2.4 17:50 3.2 2.9 3:05 0.372 9:20 1.183 0.649 0.649
3/24/2018 1:50 4.2 9:20 6.1 5.1 2:45 2.5 15:25 3.3 3.0 2:45 0.458 9:20 0.932 0.700 0.700
3/25/2018 3:10 4.1 9:35 5.9 4.8 2:00 2.5 13:40 3.3 3.0 3:15 0.437 13:40 0.883 0.641 0.641
3/26/2018 2:40 3.8 12:35 6.4 4.8 1:50 2.4 19:00 3.2 2.9 1:50 0.376 12:35 0.955 0.632 0.632
3/27/2018 1:55 3.8 19:50 5.5 4.7 1:50 2.5 16:55 3.2 2.9 1:55 0.396 19:50 0.794 0.608 0.608
3/28/2018 2:50 3.9 16:55 5.2 4.6 3:05 2.5 9:55 3.2 2.9 2:50 0.406 16:55 0.745 0.589 0.589
3/29/2018 2:20 3.8 17:25 5.3 4.5 3:10 2.5 7:35 3.2 2.9 3:10 0.384 9:25 0.760 0.576 0.576
3/30/2018 2:05 3.7 12:10 6.1 4.5 2:00 2.3 13:05 3.2 2.9 2:00 0.346 12:10 0.926 0.569 0.569
3/31/2018 2:35 3.7 12:50 5.8 4.5 2:55 2.4 11:25 3.3 2.9 2:55 0.362 11:25 0.858 0.577 0.577
ReportAvg 4.7 2.9 0.608
ReportTotal 18.84
ADS Environmental Services
Pipe Height: 14.38
REN_MH2116\mp1\DFINAL (inches) REN_MH2116\mp1\VFINAL (feet/sec) REN_MH2116\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
4/1/2018 4:10 3.7 10:05 5.6 4.5 4:05 2.3 17:05 3.2 2.9 4:05 0.346 10:05 0.824 0.572 0.572
4/2/2018 2:05 3.6 19:45 5.6 4.5 2:35 2.4 7:10 3.2 2.8 1:55 0.353 19:45 0.812 0.555 0.555
4/3/2018 3:15 3.7 16:35 5.3 4.4 1:40 2.3 20:45 3.1 2.8 1:40 0.350 17:40 0.729 0.527 0.527
4/4/2018 1:40 3.7 13:35 6.4 4.7 0:10 2.4 7:20 3.2 2.8 1:40 0.356 13:35 0.902 0.592 0.592
4/5/2018 2:20 3.8 18:45 7.5 4.9 0:55 2.4 17:55 3.1 2.8 2:15 0.381 18:45 1.140 0.633 0.633
4/6/2018 2:45 3.9 18:15 6.3 4.8 2:30 2.4 7:20 3.2 2.9 2:40 0.387 18:15 0.933 0.610 0.610
4/7/2018 1:05 4.2 5:20 10.3 6.6 0:20 2.6 22:55 3.2 2.9 1:05 0.468 5:20 1.541 0.965 0.965
4/8/2018 2:30 5.6 8:50 9.5 7.0 11:00 2.7 2:35 3.3 3.0 2:30 0.803 8:50 1.466 1.054 1.054
4/9/2018 23:55 5.4 13:40 7.4 6.1 20:05 2.8 21:35 3.2 3.1 1:40 0.736 18:05 1.154 0.907 0.907
4/10/2018 2:10 4.9 8:55 7.5 5.9 8:35 2.7 11:35 3.2 3.1 1:55 0.640 8:45 1.156 0.862 0.862
4/11/2018 1:35 4.8 20:00 7.4 5.8 10:30 2.8 0:35 3.3 3.0 1:35 0.638 19:55 1.125 0.844 0.844
4/12/2018 2:55 4.8 10:45 6.9 5.7 3:55 2.7 6:00 3.2 3.1 23:10 0.616 10:45 1.115 0.822 0.822
4/13/2018 1:35 4.7 19:10 8.1 6.0 22:05 2.8 8:45 3.4 3.0 1:10 0.574 19:10 1.243 0.875 0.875
4/14/2018 3:15 6.0 19:35 16.0 9.9 16:50 2.5 3:25 3.2 2.8 3:15 0.867 19:40 2.183 1.460 1.460
4/15/2018 23:10 7.7 1:05 13.8 10.1 0:25 2.6 21:35 3.1 2.8 23:00 1.160 0:00 2.026 1.526 1.526
4/16/2018 4:15 7.1 14:35 13.3 8.9 6:50 2.6 0:50 3.1 2.9 3:50 1.071 14:35 1.972 1.368 1.368
4/17/2018 23:55 7.0 6:30 9.4 8.0 20:35 2.7 13:15 3.2 3.0 23:10 1.045 10:35 1.515 1.236 1.236
4/18/2018 23:55 6.3 16:55 8.5 7.2 7:55 2.7 10:20 3.2 3.0 4:35 0.934 16:50 1.326 1.103 1.103
4/19/2018 23:45 5.9 16:20 8.2 6.9 12:55 2.7 3:20 3.2 2.9 2:00 0.848 17:40 1.255 1.019 1.019
4/20/2018 3:15 5.6 8:35 7.7 6.6 10:55 2.7 2:55 3.2 3.0 2:45 0.797 13:15 1.160 0.965 0.965
4/21/2018 3:40 5.5 10:10 7.8 6.4 15:45 2.5 0:30 3.2 2.9 4:10 0.742 10:10 1.170 0.921 0.921
4/22/2018 3:35 5.1 11:00 7.3 6.2 10:35 2.7 23:00 3.1 3.0 3:55 0.670 18:00 1.118 0.899 0.899
ReportAvg 6.4 2.9 0.923
ReportTotal 20.31
REN_MH2171
Located At: 540 Burnett Ave S (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 11.25”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 2.66 0.80 0.067 24%
Maximum 8.34 2.40 0.840 74%
Average 4.37 1.32 0.222 39%
Latitude: 47.475159°
Longitude:-122.207887°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Site located in walkway. Monitoring point is in a recessed pipe entry.
Moderate, slow flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Located in sidewalk infront of home.
Sensors / Devices:
11.25'' x 11.25''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
1:42:00 PM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~4.50''
Velocity Sensor Offset (in)
~1.5 FPS
Temporary
11.25'' x 11.25''
REN_MH2171
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
540 Burnett Ave S
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.14.17
Upstream 0-5 FT Manhole
MH2171 Residential
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
0
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
PVC
20''
NormalUnbolted
20''
Additional Photos
Flow Direction
Monitoring Point
Top Down Location Location
Upstream Downstream Side Inlet
ADS Environmental Services
Pipe Height: 11.25
REN_MH2171\mp1\DFINAL (inches) REN_MH2171\mp1\VFINAL (feet/sec) REN_MH2171\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 3:35 3.8 10:10 6.0 4.7 3:15 1.1 8:50 1.7 1.4 3:35 0.142 10:10 0.392 0.247 0.247 0.10
12/23/2017 4:50 3.6 11:10 4.8 4.1 3:45 1.0 11:10 1.3 1.2 3:45 0.125 11:10 0.244 0.171 0.171 0.00
12/24/2017 5:00 3.5 12:30 4.7 4.0 5:10 1.0 12:35 1.4 1.1 4:00 0.115 12:40 0.236 0.164 0.164 0.00
12/25/2017 4:10 3.4 10:10 4.5 3.9 3:40 0.9 10:15 1.3 1.1 4:10 0.106 10:15 0.213 0.153 0.153 0.14
12/26/2017 3:20 3.4 9:25 5.9 4.5 3:15 0.9 9:20 1.6 1.3 3:15 0.104 9:25 0.374 0.219 0.219 0.17
12/27/2017 3:20 3.3 10:00 6.0 4.4 3:25 0.9 10:00 1.7 1.3 3:25 0.097 10:00 0.410 0.209 0.209 0.00
12/28/2017 2:10 3.4 11:35 5.7 4.5 1:10 0.9 11:20 1.7 1.3 2:10 0.106 11:20 0.377 0.222 0.222 0.25
12/29/2017 0:05 4.1 10:45 8.3 6.3 0:00 1.1 10:35 2.4 1.8 0:00 0.161 10:35 0.840 0.486 0.486 1.57
12/30/2017 23:40 4.4 10:00 5.2 4.9 3:30 1.3 12:45 1.5 1.4 23:40 0.213 10:05 0.307 0.260 0.260 0.02
12/31/2017 5:10 4.0 11:05 4.9 4.5 5:45 1.2 11:05 1.4 1.3 5:45 0.168 11:05 0.269 0.211 0.211 0.00
ReportAvg 4.6 1.3 0.234
ReportTotal 2.343 2.25
ADS Environmental Services
Pipe Height: 11.25
REN_MH2171\mp1\DFINAL (inches) REN_MH2171\mp1\VFINAL (feet/sec) REN_MH2171\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 4:30 3.8 16:10 4.9 4.3 6:15 1.0 17:10 1.3 1.2 5:10 0.137 16:10 0.247 0.183 0.183 0.00
1/2/2018 3:20 3.6 8:00 5.9 4.6 3:20 1.0 8:25 1.7 1.3 3:20 0.124 8:25 0.408 0.238 0.238 0.01
1/3/2018 3:15 3.5 10:55 5.9 4.6 23:55 1.0 10:55 1.7 1.4 2:50 0.121 10:55 0.407 0.237 0.237 0.00
1/4/2018 3:45 3.2 12:40 5.7 4.5 2:10 0.9 8:55 1.7 1.3 3:45 0.099 8:55 0.370 0.225 0.225 0.09
1/5/2018 3:30 3.4 12:15 7.1 4.6 3:35 1.0 12:10 2.0 1.4 3:20 0.113 12:15 0.587 0.239 0.239 0.42
1/6/2018 3:00 3.7 14:05 4.7 4.3 3:05 1.1 10:20 1.4 1.3 3:00 0.137 14:05 0.246 0.198 0.198 0.24
1/7/2018 4:55 3.5 20:15 4.9 4.3 4:55 1.0 18:55 1.4 1.2 4:55 0.123 20:25 0.260 0.196 0.196 0.38
1/8/2018 1:20 3.9 8:55 7.1 4.8 1:40 1.2 8:55 2.0 1.4 2:00 0.163 8:55 0.605 0.261 0.261 0.14
1/9/2018 0:00 4.1 8:15 6.4 5.1 23:55 1.2 8:10 1.8 1.5 23:55 0.181 8:15 0.469 0.301 0.301 0.46
1/10/2018 2:05 3.9 7:25 6.0 4.8 1:45 1.1 10:30 1.7 1.5 2:10 0.161 7:25 0.411 0.271 0.271 0.22
1/11/2018 2:00 3.9 13:25 7.8 6.0 1:35 1.2 13:20 2.3 1.7 1:45 0.164 13:20 0.748 0.439 0.439 1.04
1/12/2018 23:40 4.6 9:05 6.6 5.5 23:35 1.4 9:05 2.0 1.6 23:40 0.244 9:05 0.541 0.356 0.356 0.20
1/13/2018 3:45 4.2 10:10 5.1 4.6 6:40 1.3 10:50 1.5 1.4 5:00 0.204 10:50 0.292 0.245 0.245 0.02
1/14/2018 5:20 4.0 11:50 5.1 4.5 23:50 1.2 11:15 1.4 1.3 4:40 0.170 11:15 0.270 0.216 0.216 0.00
1/15/2018 2:55 4.0 10:40 6.5 4.9 2:15 1.1 10:40 1.7 1.4 2:50 0.157 10:40 0.458 0.265 0.265 0.04
1/16/2018 23:50 3.8 7:40 5.8 4.7 23:40 1.1 8:45 1.7 1.4 23:45 0.149 8:45 0.389 0.249 0.249 0.26
1/17/2018 2:45 3.6 18:35 6.2 4.9 2:40 1.0 8:15 1.8 1.5 2:45 0.126 18:55 0.434 0.282 0.282 0.79
1/18/2018 2:05 4.4 7:15 6.6 5.4 1:30 1.3 9:05 1.9 1.6 2:05 0.218 7:10 0.518 0.339 0.339 0.40
1/19/2018 3:15 4.2 7:00 6.1 4.8 23:25 1.2 6:40 1.8 1.5 23:25 0.190 9:05 0.433 0.272 0.272 0.10
1/20/2018 5:20 3.8 10:30 4.7 4.3 5:15 1.1 9:35 1.4 1.3 5:15 0.152 9:35 0.250 0.202 0.202 0.10
1/21/2018 4:25 3.8 17:00 5.2 4.3 4:00 1.1 17:00 1.6 1.3 4:00 0.140 17:00 0.325 0.198 0.198 0.16
1/22/2018 1:20 3.7 8:10 6.3 4.9 0:45 1.1 7:45 1.8 1.5 1:15 0.139 7:45 0.465 0.283 0.283 0.34
1/23/2018 2:25 3.7 16:00 6.6 5.2 3:40 1.1 16:10 1.8 1.5 3:00 0.143 16:00 0.491 0.321 0.321 0.79
1/24/2018 3:35 4.9 14:00 7.0 5.9 2:50 1.5 14:05 2.1 1.7 3:35 0.280 14:05 0.593 0.406 0.406 0.51
1/25/2018 23:55 4.5 10:55 6.6 5.4 23:30 1.3 7:15 1.9 1.6 23:55 0.226 10:55 0.520 0.347 0.347 0.14
1/26/2018 3:20 4.3 10:30 7.1 5.3 1:35 1.3 10:35 1.9 1.6 3:20 0.202 10:30 0.566 0.329 0.329 0.36
1/27/2018 0:15 4.7 11:05 6.3 5.6 0:10 1.4 10:55 1.8 1.7 0:10 0.251 11:00 0.464 0.367 0.367 0.61
1/28/2018 5:25 4.5 11:20 5.3 4.9 6:15 1.4 13:00 1.6 1.5 6:15 0.232 12:55 0.332 0.283 0.283 0.07
1/29/2018 2:50 4.3 15:25 8.0 5.9 3:45 1.3 16:15 2.3 1.7 3:40 0.203 15:25 0.773 0.417 0.417 0.90
1/30/2018 23:45 4.5 8:15 7.1 5.6 23:45 1.4 9:10 2.1 1.7 23:45 0.233 9:10 0.583 0.372 0.372 0.00
1/31/2018 23:55 4.2 7:40 6.2 5.0 23:45 1.3 7:45 1.8 1.5 23:50 0.196 7:45 0.465 0.299 0.299 0.00
ReportAvg 5.0 1.5 0.285
ReportTotal 8.837 8.79
ADS Environmental Services
Pipe Height: 11.25
REN_MH2171\mp1\DFINAL (inches) REN_MH2171\mp1\VFINAL (feet/sec) REN_MH2171\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:05 4.0 7:10 6.2 5.1 3:10 1.2 7:10 1.7 1.5 3:35 0.166 7:10 0.439 0.306 0.306 0.66
2/2/2018 23:55 4.4 8:30 6.3 5.1 23:25 1.3 6:40 1.8 1.5 23:40 0.218 6:40 0.457 0.309 0.309 0.04
2/3/2018 5:50 4.0 11:00 5.1 4.5 2:55 1.2 18:15 1.5 1.4 4:35 0.177 18:35 0.296 0.233 0.233 0.31
2/4/2018 3:50 4.1 13:00 5.1 4.5 23:55 1.2 11:10 1.5 1.3 23:55 0.179 13:00 0.290 0.225 0.225 0.02
2/5/2018 3:45 3.9 7:55 6.1 4.8 2:30 1.1 7:15 1.7 1.4 3:45 0.157 7:10 0.410 0.258 0.258 0.04
2/6/2018 23:55 3.7 8:50 6.2 4.6 3:10 1.1 18:10 1.7 1.4 3:10 0.140 8:50 0.432 0.245 0.245 0.00
2/7/2018 3:40 3.5 7:20 5.9 4.4 1:30 1.1 7:30 1.8 1.4 3:00 0.130 7:30 0.406 0.228 0.228 0.00
2/8/2018 3:20 3.5 8:30 5.6 4.4 2:20 1.0 6:35 1.7 1.3 2:20 0.124 6:35 0.378 0.219 0.219 0.09
2/9/2018 3:30 3.4 9:35 5.6 4.3 3:25 1.0 8:20 1.6 1.3 3:30 0.113 9:35 0.352 0.212 0.212 0.01
2/10/2018 4:20 3.2 10:40 4.6 3.8 3:10 0.9 10:00 1.3 1.2 4:20 0.100 10:00 0.219 0.157 0.157 0.01
2/11/2018 3:35 3.2 14:30 4.9 3.8 5:55 1.0 14:30 1.5 1.2 3:35 0.102 14:30 0.276 0.153 0.153 0.00
2/12/2018 2:25 3.2 13:15 5.5 4.1 3:40 0.9 13:15 1.6 1.2 3:40 0.096 13:15 0.351 0.187 0.187 0.00
2/13/2018 2:50 3.0 7:15 5.3 4.1 2:30 0.9 7:15 1.6 1.3 2:30 0.091 7:15 0.330 0.189 0.189 0.17
2/14/2018 3:20 3.2 13:15 5.3 4.2 3:40 1.0 9:45 1.6 1.3 3:20 0.104 9:45 0.322 0.205 0.205 0.15
2/15/2018 3:15 3.2 17:15 5.2 4.1 3:20 1.0 8:15 1.6 1.2 2:25 0.101 6:50 0.308 0.188 0.188 0.00
2/16/2018 2:05 3.3 10:40 5.6 4.2 1:40 1.0 7:15 1.6 1.2 1:50 0.106 7:15 0.352 0.192 0.192 0.15
2/17/2018 3:15 3.2 9:20 5.2 4.0 4:00 0.9 9:25 1.4 1.2 3:55 0.093 9:20 0.285 0.171 0.171 0.32
2/18/2018 4:50 3.2 10:20 4.3 3.7 5:45 1.0 10:05 1.4 1.2 4:50 0.110 10:20 0.219 0.156 0.156 0.01
2/19/2018 3:30 3.1 13:30 5.7 4.2 3:15 1.0 9:05 1.6 1.3 3:15 0.096 13:30 0.373 0.200 0.200 0.00
2/20/2018 3:30 3.0 14:40 5.6 4.1 4:10 0.9 14:45 1.7 1.3 3:40 0.090 14:45 0.375 0.188 0.188 0.00
2/21/2018 3:00 3.0 7:25 5.2 4.0 3:25 1.0 8:10 1.6 1.3 3:25 0.093 8:10 0.314 0.187 0.187 0.00
2/22/2018 2:55 3.0 14:15 5.2 4.1 2:20 0.9 12:10 1.6 1.3 2:55 0.086 12:10 0.316 0.190 0.190 0.07
2/23/2018 3:20 2.9 11:00 5.5 4.0 2:15 0.9 12:20 1.6 1.2 3:20 0.086 11:00 0.351 0.178 0.178 0.01
2/24/2018 5:05 2.9 10:20 4.1 3.6 6:00 1.0 9:10 1.3 1.1 5:05 0.088 10:20 0.191 0.138 0.138 0.13
2/25/2018 4:15 2.9 18:50 4.3 3.7 4:25 1.0 10:45 1.3 1.2 4:15 0.091 18:50 0.203 0.147 0.147 0.11
2/26/2018 3:00 3.0 6:35 5.5 4.0 3:00 0.9 6:35 1.6 1.2 3:00 0.089 6:35 0.351 0.184 0.184 0.00
2/27/2018 3:50 2.9 8:30 5.7 3.9 3:35 1.1 14:35 1.8 1.3 3:50 0.095 14:35 0.390 0.187 0.187 0.19
2/28/2018 3:30 3.0 17:20 5.2 4.1 3:05 1.0 17:20 1.7 1.4 3:45 0.098 17:20 0.339 0.207 0.207 0.35
ReportAvg 4.2 1.3 0.201
ReportTotal 5.640 2.84
ADS Environmental Services
Pipe Height: 11.25
REN_MH2171\mp1\DFINAL (inches) REN_MH2171\mp1\VFINAL (feet/sec) REN_MH2171\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 2:25 3.1 9:20 5.5 4.1 3:40 1.1 9:20 1.7 1.3 3:00 0.108 9:20 0.368 0.200 0.200 0.01
3/2/2018 1:20 3.1 8:15 5.7 4.1 1:40 1.1 8:15 1.7 1.3 1:20 0.106 8:15 0.388 0.205 0.205 0.07
3/3/2018 5:30 2.9 10:20 4.3 3.6 23:50 1.0 10:25 1.4 1.2 4:35 0.095 10:20 0.208 0.146 0.146 0.00
3/4/2018 4:45 3.0 17:35 4.5 3.7 6:15 0.9 17:00 1.4 1.1 4:35 0.091 17:35 0.219 0.145 0.145 0.12
3/5/2018 2:45 3.0 15:55 5.2 4.1 1:10 0.9 7:50 1.6 1.3 3:15 0.087 7:50 0.311 0.190 0.190 0.00
3/6/2018 2:25 3.0 21:10 5.3 4.0 3:30 1.0 13:10 1.7 1.3 3:35 0.099 13:10 0.343 0.196 0.196 0.00
3/7/2018 4:05 3.0 15:10 5.4 4.0 2:40 1.0 15:15 1.7 1.3 2:40 0.098 15:15 0.353 0.192 0.192 0.03
3/8/2018 3:10 3.0 9:15 5.4 4.3 0:30 0.9 20:40 1.7 1.4 3:10 0.090 20:40 0.356 0.222 0.222 0.37
3/9/2018 3:40 3.0 10:40 5.5 4.1 2:10 1.0 10:40 1.7 1.3 3:40 0.102 10:40 0.361 0.197 0.197 0.00
3/10/2018 5:15 2.8 19:15 4.2 3.5 3:10 0.9 10:10 1.3 1.1 5:25 0.085 10:15 0.187 0.137 0.137 0.00
3/11/2018 2:55 3.0 9:45 4.7 3.5 4:25 0.9 9:40 1.5 1.1 2:55 0.088 9:40 0.255 0.136 0.136 0.00
3/12/2018 3:15 3.0 13:25 5.4 4.0 1:25 0.9 6:10 1.6 1.2 1:20 0.085 13:25 0.329 0.184 0.184 0.00
3/13/2018 2:25 2.9 12:05 5.4 4.1 3:10 0.9 15:15 1.6 1.3 2:25 0.083 12:05 0.326 0.200 0.200 0.31
3/14/2018 2:55 2.9 9:45 6.1 4.1 2:55 1.0 9:45 1.8 1.3 2:55 0.089 9:45 0.445 0.197 0.197 0.04
3/15/2018 1:55 2.8 8:50 6.1 4.1 2:15 1.0 8:45 1.8 1.3 2:00 0.085 8:50 0.447 0.202 0.202 0.00
3/16/2018 3:05 2.9 12:00 6.3 4.1 1:50 0.8 11:45 1.9 1.3 1:50 0.079 12:00 0.488 0.210 0.210 0.00
3/17/2018 3:40 2.8 10:25 4.2 3.5 4:40 0.9 11:40 1.3 1.1 4:00 0.080 11:05 0.183 0.133 0.133 0.00
3/18/2018 4:55 2.7 8:50 4.2 3.4 2:45 0.9 10:05 1.3 1.1 4:55 0.079 8:50 0.194 0.132 0.132 0.00
3/19/2018 2:35 2.8 8:40 6.4 3.9 1:50 0.9 8:40 1.9 1.3 2:35 0.082 8:40 0.502 0.188 0.188 0.00
3/20/2018 0:50 2.8 6:15 5.3 3.8 23:50 0.9 6:10 1.7 1.2 23:50 0.078 6:10 0.349 0.164 0.164 0.00
3/21/2018 2:00 2.7 7:20 5.3 3.9 3:00 0.8 7:20 1.6 1.2 1:55 0.069 7:20 0.333 0.171 0.171 0.10
3/22/2018 2:45 2.9 11:50 6.3 4.1 2:35 0.9 11:45 1.8 1.3 2:45 0.079 11:45 0.448 0.196 0.196 0.48
3/23/2018 2:25 2.8 8:40 6.0 4.2 3:05 0.9 9:05 1.8 1.3 2:25 0.077 9:05 0.420 0.201 0.201 0.31
3/24/2018 2:05 3.1 10:35 4.2 3.7 1:55 1.0 9:55 1.3 1.1 2:05 0.096 10:35 0.193 0.147 0.147 0.28
3/25/2018 3:30 2.8 13:50 4.8 3.5 3:35 0.9 13:50 1.4 1.1 3:35 0.080 13:50 0.245 0.134 0.134 0.01
3/26/2018 3:05 2.8 6:10 5.9 4.1 3:10 0.9 11:15 1.7 1.2 3:15 0.078 11:15 0.396 0.185 0.185 0.17
3/27/2018 3:00 2.8 5:55 5.5 4.0 2:00 0.9 16:35 1.6 1.2 3:00 0.080 5:55 0.337 0.178 0.178 0.02
3/28/2018 2:50 2.9 13:10 5.7 4.0 1:15 0.9 13:10 1.7 1.2 2:45 0.084 13:10 0.375 0.177 0.177 0.01
3/29/2018 1:35 2.8 10:10 5.7 3.9 2:05 0.9 10:10 1.6 1.2 2:05 0.074 10:10 0.365 0.174 0.174 0.00
3/30/2018 3:00 2.8 13:40 5.4 3.9 3:05 0.9 13:40 1.6 1.2 3:00 0.077 13:40 0.345 0.169 0.169 0.00
3/31/2018 2:20 2.7 8:35 4.1 3.4 2:20 0.9 8:30 1.3 1.0 2:20 0.070 8:30 0.184 0.120 0.120 0.00
ReportAvg 3.9 1.2 0.175
ReportTotal 5.429 2.33
ADS Environmental Services
Pipe Height: 11.25
REN_MH2171\mp1\DFINAL (inches) REN_MH2171\mp1\VFINAL (feet/sec) REN_MH2171\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 2:55 2.7 9:30 4.0 3.4 2:30 0.8 9:35 1.2 1.0 2:55 0.070 9:30 0.175 0.121 0.121 0.10
4/2/2018 2:55 2.7 14:55 5.2 3.8 1:45 0.8 14:55 1.5 1.2 2:55 0.067 14:55 0.306 0.165 0.165 0.00
4/3/2018 1:50 2.8 17:20 5.2 3.9 1:20 0.9 6:15 1.6 1.2 1:40 0.075 17:25 0.303 0.169 0.169 0.00
4/4/2018 0:20 2.7 6:05 5.3 3.9 2:20 0.8 12:00 1.6 1.2 1:25 0.068 6:10 0.321 0.176 0.176 0.39
4/5/2018 1:35 2.9 15:25 5.0 4.0 2:20 0.9 15:30 1.5 1.2 2:40 0.078 15:25 0.290 0.184 0.184 0.25
4/6/2018 2:05 2.9 8:40 5.0 3.8 23:30 0.9 7:10 1.5 1.2 2:55 0.086 6:00 0.283 0.163 0.163 0.00
4/7/2018 1:50 3.0 5:15 5.8 4.1 1:05 0.8 5:15 1.7 1.2 1:05 0.083 5:15 0.393 0.190 0.190 0.88
4/8/2018 2:10 3.4 9:40 4.9 4.2 23:55 1.1 9:55 1.5 1.3 2:10 0.120 8:15 0.281 0.196 0.196 0.45
4/9/2018 23:05 3.3 7:10 5.7 4.2 2:10 1.0 7:10 1.7 1.3 23:05 0.112 7:10 0.380 0.205 0.205 0.00
4/10/2018 23:55 3.1 7:35 5.9 4.1 23:55 1.0 7:35 1.8 1.3 23:55 0.096 7:35 0.413 0.200 0.200 0.23
4/11/2018 0:00 3.1 7:05 5.5 4.1 1:40 0.9 7:05 1.7 1.3 2:30 0.091 7:05 0.358 0.197 0.197 0.31
4/12/2018 23:50 3.3 8:40 5.2 4.1 2:30 0.9 8:40 1.7 1.3 1:55 0.104 8:40 0.338 0.193 0.193 0.11
4/13/2018 1:00 3.1 8:10 5.1 4.2 0:40 0.9 8:25 1.6 1.3 1:00 0.096 8:25 0.297 0.205 0.205 0.51
4/14/2018 2:45 3.9 17:00 7.0 5.5 4:25 1.2 19:15 2.0 1.6 2:45 0.168 17:00 0.574 0.353 0.353 1.52
4/15/2018 23:45 4.6 0:00 6.6 5.6 20:25 1.5 1:00 1.9 1.7 23:55 0.258 1:00 0.516 0.366 0.366 0.21
4/16/2018 2:45 4.4 15:00 6.7 5.6 2:40 1.4 14:30 2.0 1.7 2:40 0.224 14:15 0.531 0.369 0.369 0.71
4/17/2018 23:45 4.2 5:50 6.1 5.2 23:05 1.3 5:25 1.8 1.6 23:45 0.201 5:45 0.433 0.315 0.315 0.01
4/18/2018 2:30 4.0 6:15 5.8 4.7 23:15 1.2 6:40 1.7 1.4 23:25 0.172 5:50 0.385 0.259 0.259 0.12
4/19/2018 2:30 3.8 6:00 5.7 4.6 2:35 1.1 5:55 1.7 1.4 2:35 0.145 5:55 0.387 0.246 0.246 0.00
4/20/2018 2:05 3.5 8:40 5.5 4.4 2:00 1.0 8:40 1.6 1.3 2:05 0.123 8:40 0.355 0.226 0.226 0.00
4/21/2018 3:55 3.4 9:00 4.6 3.9 0:40 1.0 9:00 1.4 1.2 4:05 0.115 9:00 0.246 0.161 0.161 0.05
4/22/2018 23:50 3.3 19:50 4.5 3.8 3:40 0.9 19:50 1.4 1.2 3:40 0.102 19:50 0.226 0.157 0.157 0.00
ReportAvg 4.3 1.3 0.219
ReportTotal 4.814 5.85
REN_MH2252
Located At: NE Corner of Rainier and Grady Way (see attached site report for
details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 18”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 2.49 3.39 0.326 14%
Maximum 6.65 7.64 2.865 37%
Average 3.57 5.10 0.847 20%
Latitude: 47.471006°
Longitude:-122.207887°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Site located in pedestrian walkway area.
Moderate, fast flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Located in sidewalk infront of large parking area. Park
in parking lot and carry equipment to location.
Sensors / Devices:
18.00'' x 18.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
8:50:00 AM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~3.50''
Velocity Sensor Offset (in)
~6.00 FPS
Temporary
18.00'' x 18.00''
REN_MH2252
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
Northeast Corner of Rainier Ave and S Grady Way
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.01.17
Upstream 0-5 FT Manhole
MH2252 Other
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.38''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
Concrete
20''
NormalUnbolted
20''
Additional Photos
Flow Direction
Monitoring Point
Top Down Location Location
Upstream Downstream Side Inlet
ADS Environmental Services
Pipe Height: 18.00
REN_MH2252\mp1\DFINAL (inches) REN_MH2252\mp1\VFINAL (feet/sec) REN_MH2252\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 3:35 2.7 12:55 4.1 3.3 3:45 4.2 12:50 6.4 5.2 3:45 0.445 12:50 1.258 0.759 0.759 0.10
12/23/2017 5:20 2.7 12:40 3.7 3.2 4:10 4.0 11:20 5.7 5.0 4:10 0.425 11:20 0.954 0.707 0.707 0.00
12/24/2017 4:40 2.6 12:05 3.9 3.3 4:30 3.7 12:30 5.6 4.8 4:30 0.370 12:30 1.004 0.696 0.696 0.00
12/25/2017 4:25 2.7 14:10 3.9 3.4 4:30 3.6 14:10 5.6 4.9 4:30 0.392 14:10 1.034 0.750 0.750 0.14
12/26/2017 2:40 3.1 14:20 4.7 3.8 2:40 4.6 14:20 6.3 5.4 2:40 0.599 14:20 1.488 0.961 0.961 0.17
12/27/2017 3:55 3.0 11:10 4.0 3.7 3:55 4.5 11:10 5.7 5.4 3:55 0.573 11:10 1.095 0.927 0.927 0.00
12/28/2017 3:20 3.0 16:05 4.3 3.7 3:20 4.5 16:05 6.0 5.4 3:20 0.562 16:05 1.242 0.934 0.934 0.25
12/29/2017 1:15 3.7 11:05 6.7 4.8 2:45 5.1 12:35 7.6 6.5 2:45 0.869 11:10 2.865 1.643 1.643 1.57
12/30/2017 5:25 3.4 11:25 4.1 3.7 5:30 5.2 10:25 6.4 5.8 5:30 0.782 10:25 1.241 0.994 0.994 0.02
12/31/2017 5:40 3.1 11:05 4.0 3.5 5:25 4.5 11:25 6.0 5.3 5:25 0.593 11:25 1.117 0.844 0.844 0.00
ReportAvg 3.7 5.3 0.921
ReportTotal 9.215 2.25
ADS Environmental Services
Pipe Height: 18.00
REN_MH2252\mp1\DFINAL (inches) REN_MH2252\mp1\VFINAL (feet/sec) REN_MH2252\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 4:55 2.9 12:45 4.0 3.5 6:05 4.0 12:45 5.8 5.0 5:20 0.499 12:45 1.103 0.795 0.795 0.00
1/2/2018 3:45 2.8 19:25 3.8 3.4 3:40 3.9 12:05 5.5 4.8 3:40 0.446 20:40 0.935 0.749 0.749 0.01
1/3/2018 2:15 2.9 20:40 3.9 3.4 2:40 3.9 20:40 5.5 4.8 2:40 0.467 20:40 0.991 0.719 0.719 0.00
1/4/2018 4:00 2.8 18:40 3.8 3.4 5:45 4.2 21:45 5.4 4.8 4:00 0.491 18:35 0.930 0.737 0.737 0.09
1/5/2018 3:00 2.9 10:35 4.1 3.6 2:45 4.0 10:45 5.8 5.1 3:00 0.476 10:45 1.121 0.833 0.833 0.42
1/6/2018 3:35 3.2 11:35 4.4 3.9 4:00 4.4 11:35 6.0 5.5 4:00 0.619 11:35 1.291 0.992 0.992 0.24
1/7/2018 3:35 3.1 20:45 4.7 4.0 3:35 4.6 20:45 6.3 5.6 3:35 0.607 20:45 1.513 1.104 1.104 0.38
1/8/2018 4:00 3.8 8:55 4.8 4.1 4:00 5.4 8:55 6.4 5.8 4:00 0.943 8:55 1.563 1.150 1.150 0.14
1/9/2018 4:00 3.7 8:40 5.1 4.4 4:00 5.3 8:40 6.6 6.0 4:00 0.896 8:40 1.756 1.307 1.307 0.46
1/10/2018 3:45 3.8 7:00 4.6 4.2 3:45 5.5 7:00 6.2 5.9 3:45 0.957 7:00 1.439 1.184 1.184 0.22
1/11/2018 2:50 3.8 13:40 6.4 4.9 2:50 5.4 14:10 7.3 6.4 2:50 0.948 13:40 2.669 1.627 1.627 1.04
1/12/2018 4:10 3.6 8:25 4.8 3.9 2:20 5.1 8:20 6.8 5.8 4:10 0.823 8:20 1.644 1.074 1.074 0.20
1/13/2018 5:10 3.3 11:55 4.2 3.8 5:10 4.8 11:00 6.3 5.5 5:10 0.688 11:50 1.263 0.964 0.964 0.02
1/14/2018 4:40 3.2 10:30 4.2 3.7 4:15 4.4 19:20 6.1 5.3 4:20 0.608 10:30 1.186 0.912 0.912 0.00
1/15/2018 3:30 3.1 19:55 3.9 3.6 2:55 4.3 18:40 5.7 5.2 2:55 0.569 19:50 1.042 0.861 0.861 0.04
1/16/2018 5:05 3.2 7:10 4.0 3.6 0:45 4.5 7:20 5.9 5.2 4:30 0.628 7:20 1.097 0.862 0.862 0.26
1/17/2018 4:05 2.9 18:40 5.1 3.7 4:30 4.0 18:35 6.6 5.3 4:30 0.492 18:35 1.761 0.910 0.910 0.79
1/18/2018 2:45 3.5 7:10 4.9 4.1 2:35 4.8 7:55 6.5 5.7 2:35 0.734 7:30 1.600 1.125 1.125 0.40
1/19/2018 4:05 3.3 9:35 3.9 3.7 2:45 4.7 9:40 6.0 5.5 2:45 0.684 9:40 1.088 0.935 0.935 0.10
1/20/2018 3:20 3.1 11:40 4.1 3.7 2:45 4.7 10:45 6.1 5.3 3:20 0.642 10:45 1.164 0.909 0.909 0.10
1/21/2018 5:45 3.0 17:20 4.7 3.9 3:50 4.4 17:20 6.4 5.5 3:50 0.576 17:20 1.530 1.031 1.031 0.16
1/22/2018 4:20 3.3 7:55 5.3 4.1 4:10 4.6 7:55 6.7 5.7 4:10 0.684 7:55 1.901 1.116 1.116 0.34
1/23/2018 3:40 3.2 18:35 5.8 4.5 4:00 4.4 18:35 7.0 6.0 4:15 0.617 18:35 2.247 1.366 1.366 0.79
1/24/2018 3:40 4.5 18:40 5.4 4.9 21:35 6.0 18:40 6.8 6.4 3:40 1.345 18:40 1.986 1.603 1.603 0.51
1/25/2018 23:50 4.0 12:25 5.1 4.3 4:40 5.3 12:25 6.6 5.9 3:55 1.017 12:25 1.750 1.249 1.249 0.14
1/26/2018 3:25 3.5 9:35 4.8 4.0 3:00 4.8 9:35 6.5 5.6 3:15 0.765 9:35 1.574 1.076 1.076 0.36
1/27/2018 0:35 3.8 11:45 6.0 4.4 0:30 5.3 11:45 7.2 6.1 0:30 0.942 11:45 2.384 1.336 1.336 0.61
1/28/2018 6:40 3.7 10:40 4.4 4.0 4:35 5.0 12:15 6.3 5.7 5:40 0.844 12:15 1.368 1.099 1.099 0.07
1/29/2018 4:05 3.3 16:40 6.5 4.4 3:40 4.7 15:15 7.5 6.1 3:40 0.668 16:35 2.735 1.392 1.392 0.90
1/30/2018 23:55 3.6 8:40 4.7 4.0 23:45 5.0 8:35 6.6 5.8 23:50 0.825 8:35 1.571 1.102 1.102 0.00
1/31/2018 3:35 3.3 8:55 4.2 3.7 2:45 4.7 8:55 6.4 5.6 3:35 0.671 8:55 1.304 0.932 0.932 0.00
ReportAvg 4.0 5.6 1.066
ReportTotal 33.05 8.79
ADS Environmental Services
Pipe Height: 18.00
REN_MH2252\mp1\DFINAL (inches) REN_MH2252\mp1\VFINAL (feet/sec) REN_MH2252\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:40 3.0 3:35 4.6 3.6 2:45 4.5 21:05 6.5 5.7 3:40 0.569 3:35 1.467 0.946 0.946 0.66
2/2/2018 4:15 3.3 8:50 4.1 3.7 2:55 5.0 6:55 6.4 5.9 2:55 0.745 8:45 1.250 1.000 1.000 0.04
2/3/2018 5:25 3.1 12:50 4.1 3.6 3:30 4.9 9:45 6.4 5.8 5:15 0.638 12:50 1.223 0.949 0.949 0.31
2/4/2018 5:55 3.1 13:20 4.1 3.6 5:00 5.0 11:00 6.3 5.7 5:00 0.639 13:15 1.232 0.936 0.936 0.02
2/5/2018 3:45 2.9 15:20 3.9 3.4 1:50 4.8 12:45 6.1 5.6 4:35 0.596 15:20 1.083 0.852 0.852 0.04
2/6/2018 3:20 2.8 21:00 3.8 3.4 3:15 4.6 19:25 5.9 5.3 3:15 0.526 19:25 1.011 0.805 0.805 0.00
2/7/2018 2:55 2.8 21:00 4.0 3.4 1:45 4.3 6:50 5.7 5.1 1:45 0.513 21:05 1.053 0.789 0.789 0.00
2/8/2018 3:15 2.8 20:55 4.0 3.5 2:25 4.2 20:55 5.7 5.1 3:25 0.486 20:55 1.102 0.805 0.805 0.09
2/9/2018 4:35 3.1 12:35 4.0 3.6 4:40 4.2 12:35 5.7 5.2 4:40 0.540 12:35 1.100 0.856 0.856 0.01
2/10/2018 6:45 3.1 11:45 4.2 3.7 7:10 4.4 11:45 5.9 5.3 6:45 0.601 11:45 1.219 0.894 0.894 0.01
2/11/2018 6:40 3.0 11:20 4.2 3.6 6:45 4.1 11:20 5.9 5.2 6:45 0.530 11:20 1.191 0.875 0.875 0.00
2/12/2018 3:45 3.0 20:30 3.7 3.4 0:30 4.3 19:35 5.4 4.8 3:45 0.560 19:35 0.919 0.720 0.720 0.00
2/13/2018 4:25 2.7 17:50 3.7 3.3 4:35 3.7 17:25 5.2 4.7 4:35 0.410 17:55 0.875 0.670 0.670 0.17
2/14/2018 4:15 2.8 19:50 3.7 3.4 4:35 3.9 21:20 5.4 4.8 4:10 0.458 21:20 0.922 0.714 0.714 0.15
2/15/2018 3:30 2.8 14:15 3.9 3.3 4:35 3.8 14:10 5.7 4.7 4:35 0.445 14:10 1.023 0.684 0.684 0.00
2/16/2018 2:15 2.6 20:00 3.5 3.2 1:25 3.7 8:25 5.2 4.6 2:10 0.387 20:10 0.814 0.648 0.648 0.15
2/17/2018 2:50 2.6 12:15 4.4 3.6 2:55 3.6 12:15 6.1 5.1 2:55 0.374 12:15 1.319 0.834 0.834 0.32
2/18/2018 5:15 2.7 10:45 3.9 3.4 5:35 3.7 11:25 5.5 4.8 5:05 0.404 11:25 0.974 0.717 0.717 0.01
2/19/2018 3:35 2.6 20:00 3.8 3.3 3:35 3.5 12:25 5.3 4.7 3:35 0.369 12:25 0.894 0.685 0.685 0.00
2/20/2018 4:35 2.7 20:40 3.7 3.2 3:50 3.6 20:45 5.4 4.6 3:50 0.388 20:45 0.923 0.651 0.651 0.00
2/21/2018 4:55 2.8 19:45 3.8 3.3 5:25 3.8 19:45 5.5 4.8 4:45 0.438 19:45 0.958 0.709 0.709 0.00
2/22/2018 4:50 2.9 19:00 3.6 3.3 4:50 4.0 19:00 5.2 4.8 4:50 0.473 19:00 0.838 0.699 0.699 0.07
2/23/2018 5:30 2.8 10:10 3.6 3.2 1:05 3.7 10:10 5.2 4.7 5:30 0.418 10:10 0.831 0.666 0.666 0.01
2/24/2018 3:35 2.7 11:55 3.9 3.3 3:25 3.7 11:55 5.6 4.8 3:25 0.405 11:55 1.038 0.719 0.719 0.13
2/25/2018 2:05 2.8 11:00 3.9 3.4 3:20 3.9 11:00 5.6 4.9 3:20 0.448 11:00 1.019 0.763 0.763 0.11
2/26/2018 1:20 2.8 20:05 3.7 3.2 1:35 3.8 20:05 5.3 4.6 1:35 0.424 20:05 0.902 0.652 0.652 0.00
2/27/2018 4:00 2.7 20:30 3.8 3.2 1:25 3.8 20:25 5.5 4.7 5:05 0.426 20:25 0.959 0.660 0.660 0.19
2/28/2018 5:10 2.7 18:55 4.0 3.3 5:10 3.8 18:55 5.6 4.8 5:10 0.411 18:55 1.053 0.708 0.708 0.35
ReportAvg 3.4 5.0 0.772
ReportTotal 21.61 2.84
ADS Environmental Services
Pipe Height: 18.00
REN_MH2252\mp1\DFINAL (inches) REN_MH2252\mp1\VFINAL (feet/sec) REN_MH2252\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 4:30 2.7 19:25 3.6 3.2 4:25 3.7 19:50 5.3 4.6 4:25 0.400 19:50 0.846 0.645 0.645 0.01
3/2/2018 3:30 2.7 8:10 3.6 3.3 1:55 3.6 7:45 5.2 4.6 1:55 0.383 8:10 0.811 0.653 0.653 0.07
3/3/2018 4:15 2.6 10:55 3.8 3.2 4:05 3.5 11:20 5.4 4.6 4:05 0.356 11:20 0.945 0.655 0.655 0.00
3/4/2018 3:45 2.6 11:35 3.8 3.3 3:50 3.5 11:10 5.5 4.7 3:50 0.362 11:10 0.960 0.702 0.702 0.12
3/5/2018 2:25 2.7 20:15 3.7 3.2 2:05 3.7 20:20 5.3 4.6 2:05 0.388 20:20 0.871 0.648 0.648 0.00
3/6/2018 1:35 2.7 20:30 3.7 3.2 1:15 3.6 20:35 5.3 4.6 1:15 0.395 20:35 0.897 0.638 0.638 0.00
3/7/2018 5:15 2.7 16:35 4.9 3.2 1:35 3.8 16:35 6.4 4.7 1:35 0.413 16:35 1.602 0.662 0.662 0.03
3/8/2018 4:55 2.7 21:30 4.4 3.3 3:40 3.7 21:10 5.8 4.7 3:40 0.414 21:30 1.241 0.690 0.690 0.37
3/9/2018 4:40 2.7 12:05 3.6 3.3 5:05 3.7 12:10 5.2 4.6 4:40 0.410 12:10 0.824 0.655 0.655 0.00
3/10/2018 4:25 2.6 11:35 3.8 3.2 4:20 3.5 11:40 5.4 4.6 4:20 0.348 11:40 0.938 0.643 0.643 0.00
3/11/2018 4:15 2.6 11:15 3.8 3.3 2:55 3.5 11:15 5.4 4.7 4:15 0.364 11:15 0.938 0.675 0.675 0.00
3/12/2018 4:00 2.6 10:00 3.9 3.2 4:05 3.5 10:05 5.6 4.7 4:05 0.366 10:05 1.017 0.670 0.670 0.00
3/13/2018 4:05 2.7 18:45 3.9 3.3 1:30 3.8 18:45 5.6 4.7 4:20 0.421 18:45 1.019 0.686 0.686 0.31
3/14/2018 2:55 2.7 19:40 3.7 3.3 3:50 3.7 19:40 5.4 4.7 3:40 0.394 19:40 0.930 0.680 0.680 0.04
3/15/2018 3:40 2.7 19:45 3.6 3.2 3:45 3.6 19:40 5.3 4.6 3:45 0.375 19:40 0.866 0.633 0.633 0.00
3/16/2018 2:50 2.6 8:55 3.5 3.2 3:15 3.6 8:55 5.2 4.5 3:15 0.366 8:55 0.820 0.621 0.621 0.00
3/17/2018 5:05 2.5 10:05 3.8 3.2 3:45 3.4 10:05 5.5 4.6 3:45 0.339 10:05 0.985 0.665 0.665 0.00
3/18/2018 1:45 2.6 11:10 3.8 3.3 5:15 3.5 11:10 5.5 4.7 5:15 0.365 11:10 0.986 0.694 0.694 0.00
3/19/2018 3:25 2.7 8:55 3.9 3.2 0:55 3.6 9:00 5.5 4.6 0:55 0.380 9:00 0.981 0.636 0.636 0.00
3/20/2018 2:45 2.5 20:10 3.7 3.2 2:15 3.5 20:10 5.4 4.6 2:15 0.355 20:10 0.926 0.637 0.637 0.00
3/21/2018 4:00 2.7 19:25 3.6 3.2 2:35 3.7 19:20 5.3 4.6 2:35 0.396 19:20 0.865 0.649 0.649 0.10
3/22/2018 4:20 2.7 7:30 4.0 3.3 4:15 3.7 7:45 5.6 4.8 4:15 0.398 7:45 1.020 0.721 0.721 0.48
3/23/2018 4:00 2.7 9:45 4.1 3.4 4:10 3.7 9:40 5.8 4.8 4:10 0.407 9:40 1.124 0.734 0.734 0.31
3/24/2018 3:00 2.7 10:10 3.9 3.4 2:30 3.7 10:30 5.5 4.7 2:55 0.397 10:10 0.986 0.709 0.709 0.28
3/25/2018 3:50 2.6 9:40 3.8 3.3 3:40 3.5 11:40 5.4 4.6 3:45 0.350 11:40 0.926 0.679 0.679 0.01
3/26/2018 3:05 2.5 19:20 3.7 3.3 2:35 3.4 19:30 5.4 4.6 2:35 0.341 19:30 0.905 0.666 0.666 0.17
3/27/2018 3:05 2.5 20:05 3.6 3.2 2:15 3.5 19:55 5.3 4.5 2:15 0.347 19:55 0.872 0.621 0.621 0.02
3/28/2018 1:50 2.5 19:55 3.7 3.2 1:50 3.4 20:00 5.3 4.5 1:50 0.335 20:00 0.895 0.615 0.615 0.01
3/29/2018 3:20 2.6 19:50 3.7 3.2 3:00 3.5 19:50 5.4 4.5 3:00 0.357 19:50 0.914 0.633 0.633 0.00
3/30/2018 3:50 2.5 18:35 3.5 3.1 2:40 3.5 18:35 5.1 4.5 2:45 0.346 18:35 0.785 0.604 0.604 0.00
3/31/2018 3:25 2.5 10:30 3.8 3.2 3:30 3.4 10:30 5.5 4.6 3:30 0.326 10:30 0.977 0.650 0.650 0.00
ReportAvg 3.2 4.6 0.660
ReportTotal 20.47 2.33
ADS Environmental Services
Pipe Height: 18.00
REN_MH2252\mp1\DFINAL (inches) REN_MH2252\mp1\VFINAL (feet/sec) REN_MH2252\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 5:15 2.5 10:10 3.9 3.2 5:55 3.4 10:10 5.5 4.7 5:55 0.341 10:10 0.992 0.675 0.675 0.10
4/2/2018 2:20 2.6 20:10 3.6 3.2 4:30 3.6 20:10 5.3 4.6 4:30 0.377 20:10 0.874 0.621 0.621 0.00
4/3/2018 2:20 2.6 20:25 3.7 3.2 4:15 3.5 20:25 5.4 4.6 4:15 0.350 20:25 0.919 0.631 0.631 0.00
4/4/2018 2:15 2.6 18:30 3.9 3.4 3:40 3.5 18:30 5.6 4.9 3:40 0.371 18:30 1.010 0.752 0.752 0.39
4/5/2018 2:15 2.7 18:50 4.1 3.4 2:15 3.8 18:50 5.8 4.9 2:15 0.408 18:50 1.119 0.745 0.745 0.25
4/6/2018 4:30 2.8 14:30 3.5 3.3 3:55 4.1 14:30 5.2 4.8 4:30 0.474 14:30 0.822 0.699 0.699 0.00
4/7/2018 2:40 2.7 8:40 4.8 3.9 2:45 3.8 8:40 6.4 5.4 2:45 0.409 8:40 1.569 1.013 1.013 0.88
4/8/2018 2:55 3.1 9:40 4.5 3.8 3:00 4.3 10:35 6.2 5.4 3:00 0.568 10:35 1.384 0.961 0.961 0.45
4/9/2018 2:45 3.0 6:35 3.8 3.4 23:50 4.1 19:40 5.4 4.8 3:50 0.508 6:35 0.922 0.737 0.737 0.00
4/10/2018 3:00 2.8 8:20 3.7 3.4 2:15 3.8 19:45 5.4 4.8 2:40 0.441 8:20 0.917 0.722 0.722 0.23
4/11/2018 2:35 2.7 19:35 3.9 3.4 2:35 3.7 19:25 5.5 4.7 2:35 0.401 19:35 0.971 0.703 0.703 0.31
4/12/2018 2:00 2.8 19:50 3.7 3.4 2:40 3.9 20:05 5.3 4.8 2:40 0.451 19:40 0.887 0.705 0.705 0.11
4/13/2018 1:30 2.8 15:10 4.3 3.6 1:10 3.7 19:20 5.9 5.0 1:10 0.419 15:10 1.211 0.826 0.826 0.51
4/14/2018 3:10 3.5 19:25 5.6 4.6 4:50 4.8 19:25 7.0 6.0 4:50 0.756 19:25 2.121 1.437 1.437 1.52
4/15/2018 23:55 3.9 9:30 5.3 4.8 23:15 5.3 8:50 6.8 6.2 23:55 0.998 10:25 1.860 1.545 1.545 0.21
4/16/2018 3:20 3.6 19:35 5.1 4.4 4:20 5.0 20:25 6.7 6.0 4:00 0.851 19:35 1.744 1.302 1.302 0.71
4/17/2018 23:50 3.5 7:20 4.7 4.1 22:35 5.0 7:35 6.4 5.6 23:50 0.774 7:35 1.517 1.078 1.078 0.01
4/18/2018 23:55 3.1 8:45 4.3 3.7 23:50 4.3 8:45 6.1 5.2 23:50 0.581 8:45 1.298 0.890 0.890 0.12
4/19/2018 23:55 3.0 7:15 4.3 3.5 1:40 4.1 7:10 6.4 5.0 1:40 0.515 7:10 1.312 0.786 0.786 0.00
4/20/2018 2:50 2.7 10:10 4.2 3.3 1:55 3.9 9:40 6.0 4.8 1:55 0.430 9:55 1.218 0.708 0.708 0.00
4/21/2018 3:50 2.7 9:10 3.8 3.3 3:35 3.9 10:20 5.5 4.8 3:35 0.414 9:35 0.971 0.701 0.701 0.05
4/22/2018 3:05 2.7 11:05 3.8 3.3 5:05 3.9 8:40 5.5 4.8 5:05 0.417 10:55 0.946 0.704 0.704 0.00
ReportAvg 3.6 5.1 0.861
ReportTotal 18.94 5.85
REN_MH2999
Located At: 3431 Shattuck Ave S (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 8”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.28 3.51 0.087 16%
Maximum 3.28 7.12 0.609 41%
Average 1.81 5.58 0.218 23%
Latitude: 47.448386°
Longitude:-122.212824°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Traffic control required.
Fast, low flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Located in roadway at end of residential
neighborhood.
Sensors / Devices:
8.00'' x 8.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
9:22:00 AM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~2.63''
Velocity Sensor Offset (in)
~7.5 FPS
Temporary
8.00'' x 8.00''
REN_MH2999
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
3431 Shattuck Ave S
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
12.19.17
Upstream 0-5 FT Manhole
MH2999 Other
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.25''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
Concrete
20''
NormalUnbolted
20''
Additional Photos
Flow Direction
Monitoring Point
Top Down Location Location
Upstream Downstream Side Inlet
ADS Environmental Services
Pipe Height: 8.00
REN_MH2999\mp1\DFINAL (inches) REN_MH2999\mp1\VFINAL (feet/sec) REN_MH2999\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 1:20 1.6 13:25 2.2 1.8 3:00 5.1 9:35 6.8 5.9 1:20 0.171 11:30 0.335 0.232 0.232 0.10
12/23/2017 5:25 1.5 9:55 2.1 1.8 5:25 5.0 11:05 6.5 5.7 5:25 0.147 9:55 0.310 0.211 0.211 0.00
12/24/2017 5:10 1.4 10:45 2.2 1.8 3:40 4.8 10:45 6.5 5.7 5:05 0.136 10:45 0.326 0.210 0.210 0.00
12/25/2017 5:45 1.5 12:10 2.2 1.8 5:45 4.8 12:10 6.4 5.6 5:45 0.136 12:10 0.317 0.209 0.209 0.14
12/26/2017 4:35 1.4 18:30 2.2 1.8 4:35 4.7 13:00 6.3 5.4 4:35 0.130 18:30 0.314 0.204 0.204 0.17
12/27/2017 3:55 1.4 19:50 2.1 1.7 3:05 4.6 19:50 6.3 5.4 4:00 0.128 19:50 0.291 0.195 0.195 0.00
12/28/2017 2:15 1.4 9:45 2.1 1.8 4:10 4.6 20:10 6.2 5.5 4:10 0.127 20:10 0.288 0.204 0.204 0.25
12/29/2017 0:45 1.7 10:40 3.3 2.4 1:05 5.1 11:55 7.1 6.4 1:05 0.185 10:40 0.609 0.383 0.383 1.57
12/30/2017 23:35 1.9 0:25 2.6 2.1 5:30 5.8 16:55 6.7 6.2 23:35 0.250 12:05 0.401 0.298 0.298 0.02
12/31/2017 3:05 1.8 10:40 2.4 2.0 5:05 5.4 10:40 6.6 6.0 5:20 0.206 10:40 0.371 0.260 0.260 0.00
ReportAvg 1.9 5.8 0.241
ReportTotal 2.407 2.25
ADS Environmental Services
Pipe Height: 8.00
REN_MH2999\mp1\DFINAL (inches) REN_MH2999\mp1\VFINAL (feet/sec) REN_MH2999\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 6:35 1.6 10:30 2.4 1.9 6:05 5.1 11:25 6.8 5.9 7:20 0.171 10:30 0.381 0.238 0.238 0.00
1/2/2018 2:50 1.5 6:55 2.1 1.8 1:50 4.9 6:55 6.4 5.7 2:50 0.147 6:55 0.296 0.215 0.215 0.01
1/3/2018 2:50 1.5 18:45 2.1 1.8 23:00 4.9 18:45 6.4 5.6 2:40 0.141 18:45 0.292 0.206 0.206 0.00
1/4/2018 3:35 1.4 9:55 2.1 1.7 3:50 4.6 8:35 6.4 5.4 3:50 0.129 9:55 0.292 0.192 0.192 0.09
1/5/2018 2:10 1.5 20:05 2.2 1.8 4:05 4.6 16:05 6.3 5.5 2:20 0.134 20:05 0.312 0.221 0.221 0.42
1/6/2018 2:50 1.6 11:05 2.4 2.0 3:00 4.9 9:15 6.3 5.7 2:50 0.157 11:05 0.359 0.247 0.247 0.24
1/7/2018 3:10 1.6 12:15 2.5 2.0 4:25 4.9 10:20 6.6 5.7 5:10 0.154 12:15 0.393 0.249 0.249 0.38
1/8/2018 2:40 1.7 8:45 2.3 2.0 2:35 5.0 11:45 6.4 5.8 2:35 0.179 8:45 0.345 0.254 0.254 0.14
1/9/2018 3:25 1.8 6:55 2.4 2.0 3:30 5.3 6:55 6.4 5.9 3:30 0.209 6:55 0.362 0.268 0.268 0.46
1/10/2018 4:10 1.7 22:35 2.2 2.0 2:50 5.1 9:20 6.3 5.7 2:55 0.181 22:35 0.318 0.247 0.247 0.22
1/11/2018 2:40 1.7 15:10 3.0 2.3 2:10 5.2 13:05 6.7 6.1 2:35 0.181 15:10 0.515 0.331 0.331 1.04
1/12/2018 23:55 2.0 19:10 2.7 2.2 2:40 5.6 19:55 6.5 6.0 23:55 0.261 19:10 0.421 0.302 0.302 0.20
1/13/2018 4:25 1.9 11:35 2.4 2.1 4:10 5.3 12:25 6.5 5.9 4:25 0.221 12:25 0.372 0.277 0.277 0.02
1/14/2018 5:50 1.7 10:05 2.5 2.0 2:50 5.0 10:05 6.5 5.7 5:50 0.176 10:05 0.392 0.254 0.254 0.00
1/15/2018 4:05 1.6 19:40 2.2 1.9 1:55 4.8 19:40 6.4 5.6 2:50 0.155 19:40 0.320 0.232 0.232 0.04
1/16/2018 3:35 1.6 20:45 2.2 1.9 3:35 4.8 7:15 6.3 5.6 3:35 0.155 20:45 0.318 0.232 0.232 0.26
1/17/2018 3:40 1.6 19:05 2.8 2.0 3:10 4.6 19:05 6.6 5.6 3:10 0.148 19:05 0.462 0.246 0.246 0.79
1/18/2018 1:30 1.9 9:00 2.7 2.2 1:55 5.3 9:00 6.4 6.0 1:35 0.229 9:00 0.421 0.297 0.297 0.40
1/19/2018 3:20 1.9 8:30 2.5 2.1 3:15 5.1 18:45 6.5 5.8 3:15 0.205 18:45 0.381 0.267 0.267 0.10
1/20/2018 3:10 1.7 10:30 2.4 2.0 2:15 4.9 10:30 6.3 5.6 3:10 0.180 10:30 0.349 0.253 0.253 0.10
1/21/2018 6:00 1.6 9:45 2.4 2.0 4:20 4.8 11:35 6.4 5.6 2:50 0.161 9:45 0.364 0.249 0.249 0.16
1/22/2018 2:20 1.6 10:40 2.5 2.0 4:30 4.8 7:45 6.4 5.7 2:20 0.162 10:40 0.373 0.255 0.255 0.34
1/23/2018 2:15 1.7 18:45 2.7 2.1 3:55 4.8 20:10 6.5 5.8 3:55 0.165 18:45 0.419 0.274 0.274 0.79
1/24/2018 4:30 2.0 6:30 2.7 2.2 3:20 5.6 19:25 6.6 6.2 4:30 0.258 6:30 0.443 0.314 0.314 0.51
1/25/2018 2:45 2.0 20:35 2.6 2.1 3:35 5.6 20:35 6.6 6.1 2:40 0.250 20:35 0.425 0.294 0.294 0.14
1/26/2018 4:30 1.9 23:20 2.4 2.1 3:10 5.4 13:00 6.5 6.0 3:35 0.218 23:20 0.374 0.277 0.277 0.36
1/27/2018 0:05 2.0 10:50 2.6 2.2 0:10 5.9 20:55 6.9 6.4 0:10 0.261 10:50 0.440 0.323 0.323 0.61
1/28/2018 5:20 1.9 10:05 2.5 2.0 5:30 5.7 10:05 6.7 6.2 5:20 0.236 10:05 0.398 0.282 0.282 0.07
1/29/2018 2:45 1.8 16:50 3.0 2.2 3:15 5.3 18:05 7.1 6.3 3:15 0.204 16:55 0.540 0.317 0.317 0.90
1/30/2018 23:35 1.9 16:20 2.4 2.0 23:15 6.0 22:35 6.8 6.3 23:30 0.243 16:20 0.389 0.287 0.287 0.00
1/31/2018 4:00 1.8 6:30 2.3 1.9 3:30 5.4 6:30 6.7 6.0 3:45 0.200 6:30 0.363 0.249 0.249 0.00
ReportAvg 2.0 5.9 0.263
ReportTotal 8.150 8.79
ADS Environmental Services
Pipe Height: 8.00
REN_MH2999\mp1\DFINAL (inches) REN_MH2999\mp1\VFINAL (feet/sec) REN_MH2999\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:40 1.7 21:55 2.5 1.9 4:05 5.3 22:50 6.9 6.0 3:40 0.180 21:55 0.400 0.246 0.246 0.66
2/2/2018 3:00 1.8 8:15 2.4 2.0 23:00 5.8 11:00 6.8 6.2 3:00 0.223 8:15 0.373 0.265 0.265 0.04
2/3/2018 3:45 1.7 10:20 2.3 1.9 4:10 5.3 12:55 6.7 6.0 4:10 0.187 10:20 0.352 0.249 0.249 0.31
2/4/2018 3:50 1.7 20:35 2.3 1.9 4:30 5.3 11:05 6.7 6.0 3:05 0.186 20:35 0.352 0.247 0.247 0.02
2/5/2018 3:40 1.6 20:55 2.3 1.8 2:50 5.0 12:55 6.6 5.8 3:15 0.164 20:55 0.338 0.224 0.224 0.04
2/6/2018 3:30 1.6 17:50 2.1 1.8 1:45 4.9 17:50 6.5 5.7 1:45 0.160 17:50 0.307 0.217 0.217 0.00
2/7/2018 2:45 1.5 10:25 2.2 1.8 3:30 4.8 10:25 6.5 5.6 3:00 0.147 10:25 0.330 0.209 0.209 0.00
2/8/2018 2:40 1.5 18:20 2.1 1.7 2:45 4.7 18:20 6.4 5.5 2:45 0.136 18:20 0.300 0.197 0.197 0.09
2/9/2018 3:20 1.4 8:55 2.0 1.7 2:15 4.8 8:00 6.3 5.5 3:15 0.132 8:55 0.270 0.194 0.194 0.01
2/10/2018 4:00 1.4 10:25 2.1 1.7 5:20 4.8 10:20 6.4 5.5 3:55 0.130 10:25 0.298 0.194 0.194 0.01
2/11/2018 5:20 1.4 13:50 2.1 1.7 3:15 4.6 16:50 6.3 5.5 5:05 0.125 13:50 0.291 0.197 0.197 0.00
2/12/2018 3:30 1.4 8:55 2.0 1.6 2:20 4.4 21:30 6.2 5.3 4:25 0.118 8:55 0.275 0.178 0.178 0.00
2/13/2018 3:05 1.4 20:55 1.9 1.6 4:30 4.3 20:55 6.2 5.3 2:50 0.111 20:55 0.253 0.173 0.173 0.17
2/14/2018 4:35 1.4 7:35 2.0 1.7 4:30 4.6 7:35 6.3 5.4 4:35 0.124 7:35 0.277 0.189 0.189 0.15
2/15/2018 2:55 1.4 21:20 1.9 1.6 2:45 4.4 21:20 6.2 5.3 2:50 0.115 21:20 0.256 0.178 0.178 0.00
2/16/2018 2:55 1.4 10:00 2.0 1.7 1:20 4.5 17:35 6.3 5.3 1:20 0.119 10:00 0.272 0.181 0.181 0.15
2/17/2018 3:25 1.4 10:45 2.2 1.8 3:25 4.5 11:30 6.6 5.6 3:25 0.117 10:45 0.328 0.211 0.211 0.32
2/18/2018 5:00 1.5 9:25 2.1 1.8 5:00 4.9 9:25 6.3 5.6 5:00 0.139 9:25 0.296 0.206 0.206 0.01
2/19/2018 2:55 1.4 21:25 2.0 1.7 2:55 4.7 21:25 6.3 5.4 2:55 0.127 21:25 0.286 0.191 0.191 0.00
2/20/2018 3:35 1.4 19:45 1.9 1.7 3:35 4.5 21:00 6.3 5.4 3:35 0.120 19:45 0.260 0.183 0.183 0.00
2/21/2018 3:15 1.4 21:25 1.9 1.6 4:05 4.3 21:25 6.2 5.3 3:10 0.114 21:25 0.260 0.177 0.177 0.00
2/22/2018 3:00 1.4 17:35 2.0 1.6 3:45 4.4 20:05 6.2 5.2 2:50 0.114 17:35 0.277 0.177 0.177 0.07
2/23/2018 3:15 1.4 22:45 2.0 1.6 3:25 4.2 9:10 6.0 5.2 3:25 0.109 22:50 0.267 0.170 0.170 0.01
2/24/2018 5:00 1.4 10:10 2.1 1.7 4:45 4.2 10:15 6.2 5.2 4:45 0.111 10:10 0.293 0.177 0.177 0.13
2/25/2018 4:40 1.4 9:50 2.1 1.7 3:15 4.3 14:10 6.2 5.4 3:15 0.115 9:50 0.294 0.193 0.193 0.11
2/26/2018 4:05 1.4 21:10 2.0 1.6 4:10 4.3 19:40 6.1 5.2 4:10 0.111 21:10 0.264 0.174 0.174 0.00
2/27/2018 2:40 1.3 20:35 2.0 1.6 2:15 4.2 7:45 6.1 5.2 2:40 0.101 20:35 0.264 0.168 0.168 0.19
2/28/2018 3:40 1.4 19:05 2.1 1.7 4:15 4.1 19:05 6.3 5.3 3:35 0.106 19:05 0.297 0.181 0.181 0.35
ReportAvg 1.7 5.5 0.198
ReportTotal 5.546 2.84
ADS Environmental Services
Pipe Height: 8.00
REN_MH2999\mp1\DFINAL (inches) REN_MH2999\mp1\VFINAL (feet/sec) REN_MH2999\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 3:50 1.4 21:20 2.0 1.7 3:05 4.5 21:20 6.2 5.3 2:55 0.124 21:20 0.278 0.186 0.186 0.01
3/2/2018 2:00 1.4 7:40 2.0 1.7 1:30 4.5 8:55 6.2 5.4 1:30 0.122 7:40 0.273 0.194 0.194 0.07
3/3/2018 3:30 1.4 9:15 2.1 1.7 3:20 4.5 9:20 6.2 5.4 3:20 0.122 9:20 0.298 0.190 0.190 0.00
3/4/2018 4:20 1.4 9:50 2.1 1.7 2:35 4.3 13:20 6.2 5.4 2:35 0.116 9:50 0.294 0.196 0.196 0.12
3/5/2018 3:50 1.4 9:40 2.1 1.7 2:30 4.4 19:55 6.1 5.3 3:50 0.116 9:40 0.281 0.188 0.188 0.00
3/6/2018 3:10 1.4 18:15 2.1 1.6 1:40 4.3 19:55 6.1 5.2 2:45 0.112 18:15 0.285 0.174 0.174 0.00
3/7/2018 2:40 1.4 9:00 2.1 1.6 2:30 4.2 7:40 6.1 5.2 2:30 0.109 9:00 0.279 0.174 0.174 0.03
3/8/2018 2:30 1.4 21:05 2.1 1.7 2:30 4.1 21:10 6.1 5.2 2:30 0.104 21:05 0.290 0.179 0.179 0.37
3/9/2018 3:25 1.4 9:20 2.1 1.7 3:15 4.4 18:50 6.1 5.2 3:15 0.117 18:50 0.286 0.179 0.179 0.00
3/10/2018 3:00 1.4 11:35 2.2 1.7 2:45 4.1 8:40 6.1 5.2 2:45 0.107 11:40 0.292 0.182 0.182 0.00
3/11/2018 2:20 1.4 10:10 2.2 1.7 2:10 4.0 19:05 6.0 5.1 2:10 0.103 21:35 0.293 0.179 0.179 0.00
3/12/2018 2:40 1.4 20:00 2.1 1.6 1:55 3.9 20:00 6.0 5.1 1:55 0.099 20:00 0.278 0.167 0.167 0.00
3/13/2018 2:10 1.4 18:50 2.2 1.6 1:20 4.0 18:00 6.2 5.1 1:20 0.105 18:50 0.304 0.174 0.174 0.31
3/14/2018 23:55 1.4 9:25 2.0 1.7 2:05 4.3 5:35 6.1 5.2 2:05 0.117 5:35 0.278 0.177 0.177 0.04
3/15/2018 2:55 1.4 7:50 2.1 1.6 2:30 4.1 19:35 6.1 5.2 2:30 0.107 7:50 0.279 0.173 0.173 0.00
3/16/2018 2:25 1.4 19:35 2.0 1.6 1:10 4.0 19:30 6.0 5.0 1:10 0.102 19:35 0.271 0.163 0.163 0.00
3/17/2018 3:20 1.3 11:20 2.1 1.6 2:25 3.8 8:25 6.1 5.0 2:25 0.096 11:20 0.282 0.165 0.165 0.00
3/18/2018 3:10 1.3 18:05 2.1 1.6 4:25 3.7 9:40 6.1 5.0 3:10 0.094 18:05 0.286 0.168 0.168 0.00
3/19/2018 2:00 1.3 18:35 2.0 1.6 1:45 3.7 18:35 6.1 4.9 2:00 0.093 18:35 0.278 0.156 0.156 0.00
3/20/2018 2:55 1.3 9:05 2.2 1.6 1:45 3.6 9:05 6.2 5.0 2:15 0.091 9:05 0.306 0.155 0.155 0.00
3/21/2018 2:00 1.3 7:15 2.0 1.5 0:45 3.5 7:15 6.0 4.9 0:45 0.087 7:15 0.259 0.152 0.152 0.10
3/22/2018 2:45 1.3 19:45 2.0 1.6 2:15 3.9 21:00 6.3 5.3 2:15 0.097 19:45 0.270 0.179 0.179 0.48
3/23/2018 2:00 1.4 10:30 2.1 1.7 2:25 4.3 11:20 6.3 5.4 2:25 0.114 10:30 0.296 0.192 0.192 0.31
3/24/2018 2:45 1.4 10:10 2.2 1.8 2:15 4.6 14:10 6.3 5.6 2:15 0.127 10:10 0.317 0.210 0.210 0.28
3/25/2018 2:55 1.4 9:05 2.1 1.7 2:55 4.7 8:15 6.4 5.5 2:55 0.126 9:05 0.311 0.196 0.196 0.01
3/26/2018 2:35 1.4 7:50 2.1 1.7 1:35 4.3 18:50 6.4 5.5 1:35 0.111 7:50 0.304 0.190 0.190 0.17
3/27/2018 2:20 1.4 8:20 2.2 1.7 0:30 4.6 8:20 6.4 5.4 2:05 0.125 8:20 0.314 0.185 0.185 0.02
3/28/2018 2:40 1.4 7:15 1.9 1.6 0:15 4.3 18:10 6.3 5.4 2:40 0.116 7:15 0.250 0.176 0.176 0.01
3/29/2018 2:50 1.4 18:50 2.0 1.6 2:40 4.5 17:35 6.2 5.3 2:40 0.116 18:50 0.275 0.174 0.174 0.00
3/30/2018 2:20 1.3 8:45 2.3 1.6 1:10 4.4 8:45 6.4 5.2 1:55 0.112 8:45 0.347 0.172 0.172 0.00
3/31/2018 3:05 1.4 15:05 2.0 1.6 2:05 4.2 9:45 6.2 5.2 2:05 0.108 15:05 0.276 0.175 0.175 0.00
ReportAvg 1.6 5.2 0.178
ReportTotal 5.518 2.33
ADS Environmental Services
Pipe Height: 8.00
REN_MH2999\mp1\DFINAL (inches) REN_MH2999\mp1\VFINAL (feet/sec) REN_MH2999\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 5:40 1.3 12:35 2.0 1.7 3:25 4.1 12:35 6.2 5.2 3:25 0.104 12:35 0.284 0.179 0.179 0.10
4/2/2018 2:30 1.3 18:30 2.0 1.6 2:30 3.9 20:15 6.2 5.1 2:30 0.096 20:15 0.264 0.167 0.167 0.00
4/3/2018 23:55 1.4 21:05 1.9 1.6 0:35 3.6 19:35 6.1 5.0 0:35 0.102 7:35 0.252 0.164 0.164 0.00
4/4/2018 2:10 1.3 20:10 2.0 1.6 2:00 3.7 18:50 6.2 5.1 2:00 0.091 20:10 0.269 0.168 0.168 0.39
4/5/2018 3:05 1.4 18:45 2.0 1.7 2:00 4.1 19:40 6.3 5.2 2:00 0.107 19:40 0.282 0.178 0.178 0.25
4/6/2018 2:40 1.4 8:40 2.0 1.7 2:35 4.4 8:40 6.2 5.3 2:40 0.122 8:40 0.279 0.182 0.182 0.00
4/7/2018 2:10 1.4 9:05 2.5 1.9 2:00 4.3 9:05 6.6 5.8 2:00 0.114 9:05 0.387 0.240 0.240 0.88
4/8/2018 2:35 1.7 10:50 2.5 2.0 3:00 5.0 7:55 6.8 6.0 3:05 0.172 10:50 0.408 0.260 0.260 0.45
4/9/2018 2:35 1.6 19:40 2.2 1.8 2:35 5.1 18:45 6.7 5.8 2:35 0.169 19:40 0.337 0.230 0.230 0.00
4/10/2018 3:00 1.6 8:30 2.3 1.8 1:20 5.0 8:30 6.7 5.8 3:00 0.160 8:30 0.354 0.223 0.223 0.23
4/11/2018 3:20 1.6 19:20 2.2 1.8 2:50 5.0 19:15 6.7 5.7 3:20 0.155 19:20 0.336 0.216 0.216 0.31
4/12/2018 3:25 1.6 7:40 2.1 1.8 2:00 5.1 7:40 6.5 5.7 2:00 0.163 7:40 0.312 0.218 0.218 0.11
4/13/2018 1:30 1.5 22:45 2.3 1.8 1:45 4.9 22:45 6.5 5.7 1:45 0.148 22:45 0.351 0.224 0.224 0.51
4/14/2018 3:30 1.7 20:40 2.9 2.3 3:25 5.3 21:55 6.9 6.3 3:25 0.195 19:25 0.500 0.340 0.340 1.52
4/15/2018 23:55 1.9 1:00 2.9 2.3 23:40 5.8 9:20 6.9 6.5 23:55 0.249 1:00 0.505 0.349 0.349 0.21
4/16/2018 3:20 1.9 16:35 2.6 2.1 1:45 5.7 16:35 7.0 6.3 3:05 0.230 16:35 0.443 0.300 0.300 0.71
4/17/2018 23:40 1.8 20:45 2.3 2.0 23:20 5.7 6:15 6.8 6.2 23:25 0.220 7:05 0.366 0.276 0.276 0.01
4/18/2018 23:50 1.7 7:30 2.2 1.9 2:25 5.4 20:25 6.6 5.9 23:50 0.195 7:30 0.341 0.244 0.244 0.12
4/19/2018 2:35 1.6 7:35 2.2 1.8 2:00 5.0 7:35 6.6 5.8 2:35 0.166 7:35 0.322 0.223 0.223 0.00
4/20/2018 1:35 1.6 8:35 2.1 1.8 3:40 4.9 7:30 6.3 5.6 3:40 0.155 8:35 0.298 0.213 0.213 0.00
4/21/2018 3:55 1.5 9:15 2.2 1.8 3:55 4.9 9:10 6.4 5.5 3:55 0.149 9:15 0.317 0.212 0.212 0.05
4/22/2018 4:30 1.5 8:55 2.2 1.8 23:50 4.7 17:50 6.3 5.5 4:30 0.138 8:55 0.316 0.210 0.210 0.00
ReportAvg 1.8 5.7 0.228
ReportTotal 5.019 5.85
REN_MH3216
Located At: West of 4022 Talbot Rd S (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 7.38”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor and the pressure
sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 94%
Velocity (f/s) 100% 94%
Quantity (mgd) 100% 94%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.41 0.33 0.011 19%
Maximum 6.76 2.41 0.445 92%
Average 2.55 0.96 0.059 35%
Latitude: 47.444195°
Longitude:-122.216122°
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
PVC
20''
NormalVented
20''
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.38''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
West of 4033 Talbot Rd S, Renton, WA 98055, USA
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Special Installation
Manhole #
Installation Date:
12.14.17
Upstream 0-5 FT Manhole
MH5519 Other
Map
Flow Monitoring
Site Report
Temporary
10.25'' x 10.25''
REN_MH5519
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe ShapeOff of Talbot Rd, down brush area from parking lot
west of Valley Medical Center
Sensors / Devices:
10.25'' x 10.25''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4)
Pipe Size (HxW)
-
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~2.25''
Velocity Sensor Offset (in)
~6.00 FPS
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Off trail. Confirmation information available from ADS.
Low, fast flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Additional Photos
Flow Direction
Monitoring Point
Side Inlet
Second Side Inlet (usually dry)Top Down Secondary Top Down - Outlet Oriented
Location
Upstream Downstream
ADS Environmental Services
Pipe Height: 7.38
REN_MH3216\mp1\DFINAL (inches) REN_MH3216\mp1\VFINAL (feet/sec) REN_MH3216\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
12/22/2017 3:45 2.1 19:30 4.4 3.0 4:15 0.7 18:20 1.9 1.2 3:45 0.031 19:30 0.218 0.098 0.098
12/23/2017 23:55 2.3 4:50 4.7 4.0 23:15 0.8 4:50 2.1 1.7 23:55 0.040 4:50 0.265 0.182 0.182
12/24/2017 4:10 1.9 13:40 3.2 2.4 3:30 0.6 13:40 1.3 0.9 4:10 0.024 13:40 0.100 0.049 0.049
12/25/2017 4:15 1.8 12:20 3.3 2.3 4:20 0.5 12:20 1.4 0.8 4:20 0.019 12:20 0.120 0.045 0.045
12/26/2017 3:25 1.8 9:40 6.8 3.0 3:50 0.5 9:40 2.4 1.1 3:50 0.016 9:40 0.445 0.095 0.095
12/27/2017 2:00 2.0 16:00 3.7 2.7 4:25 0.3 7:15 1.3 0.8 2:00 0.021 7:15 0.121 0.052 0.052
12/28/2017 3:10 2.2 17:50 3.9 2.8 23:25 0.5 13:25 1.5 0.8 3:10 0.026 13:25 0.144 0.056 0.056
12/29/2017 1:25 2.5 11:05 4.3 3.4 1:20 0.4 12:50 1.2 0.6 1:20 0.024 10:50 0.113 0.057 0.057
12/30/2017 5:05 2.9 13:10 3.8 3.3 20:25 0.4 10:05 0.8 0.6 23:00 0.029 10:00 0.069 0.046 0.046
12/31/2017 3:15 2.8 16:45 3.7 3.2 6:05 0.4 8:45 0.7 0.5 6:05 0.024 8:45 0.069 0.044 0.044
ReportAvg 3.0 0.9 0.072
ReportTotal 0.723
ADS Environmental Services
Pipe Height: 7.38
REN_MH3216\mp1\DFINAL (inches) REN_MH3216\mp1\VFINAL (feet/sec) REN_MH3216\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
1/1/2018 6:55 2.7 13:05 3.7 3.1 6:55 0.4 10:25 0.8 0.5 6:55 0.025 10:25 0.066 0.040 0.040
1/2/2018 3:30 2.7 15:40 3.7 3.2 3:50 0.4 9:35 0.9 0.5 3:30 0.025 9:35 0.083 0.044 0.044
1/3/2018 4:25 3.0 12:45 3.6 3.3 2:50 0.3 9:00 0.9 0.6 2:50 0.026 9:00 0.085 0.046 0.027
1/4/2018 --
1/5/2018 --
1/6/2018 --
1/7/2018 --
1/8/2018 --
1/9/2018 --
1/10/2018 --
1/11/2018 21:15 2.8 11:05 5.5 3.3 10:55 0.5 11:55 1.7 1.2 23:30 0.056 11:55 0.165 0.095 0.054
1/12/2018 2:45 2.5 8:40 4.2 3.2 23:50 0.6 8:40 1.4 0.9 23:50 0.042 8:40 0.156 0.075 0.075
1/13/2018 20:55 2.2 7:00 3.9 2.8 3:55 0.5 12:20 1.6 1.0 3:55 0.034 7:00 0.157 0.065 0.065
1/14/2018 4:50 2.0 9:10 3.5 2.5 6:30 0.6 10:20 1.5 1.0 4:30 0.026 9:10 0.114 0.059 0.059
1/15/2018 4:25 1.9 10:40 3.8 2.8 2:45 0.7 10:40 1.7 1.2 3:00 0.029 10:40 0.173 0.085 0.085
1/16/2018 22:35 2.2 10:55 3.5 2.7 22:35 0.8 12:00 1.7 1.2 22:35 0.041 10:55 0.149 0.080 0.080
1/17/2018 2:40 2.0 18:35 3.7 2.6 3:00 0.7 16:35 1.7 1.1 3:00 0.029 19:05 0.161 0.072 0.072
1/18/2018 2:55 2.3 9:35 3.9 2.8 2:20 0.9 9:35 1.9 1.2 2:40 0.045 9:35 0.191 0.085 0.085
1/19/2018 3:25 2.2 10:10 3.5 2.7 1:15 0.8 14:35 1.7 1.2 1:15 0.038 14:35 0.154 0.076 0.076
1/20/2018 4:15 2.1 10:00 3.7 2.5 0:40 0.7 9:20 1.7 1.1 23:35 0.037 9:20 0.162 0.065 0.065
1/21/2018 5:00 1.9 13:10 3.4 2.6 4:10 0.6 11:55 1.6 1.1 4:10 0.024 11:55 0.132 0.065 0.065
1/22/2018 3:10 2.1 9:30 3.5 2.7 2:15 0.7 9:30 1.6 1.1 2:15 0.033 9:30 0.150 0.073 0.073
1/23/2018 3:35 2.2 15:00 3.8 2.7 2:15 0.7 15:00 1.6 1.1 2:15 0.035 15:00 0.160 0.073 0.073
1/24/2018 3:45 2.4 15:00 3.7 2.9 3:20 0.9 15:00 1.7 1.2 3:20 0.047 15:00 0.160 0.086 0.086
1/25/2018 1:30 2.4 9:30 3.8 2.8 1:20 0.9 9:30 1.8 1.2 1:25 0.052 9:30 0.176 0.086 0.086
1/26/2018 2:25 2.3 10:15 3.8 2.8 3:10 0.8 11:15 1.6 1.2 3:15 0.041 10:15 0.163 0.079 0.079
1/27/2018 23:15 2.3 10:40 3.7 2.8 23:55 0.8 10:40 1.7 1.2 23:55 0.044 10:40 0.157 0.078 0.078
1/28/2018 3:45 2.2 9:35 3.4 2.6 4:00 0.8 14:15 1.5 1.1 4:00 0.036 9:35 0.133 0.068 0.068
1/29/2018 3:10 2.0 14:55 4.0 2.7 3:00 0.8 14:55 1.8 1.1 3:00 0.033 14:55 0.196 0.075 0.075
1/30/2018 23:25 2.2 13:10 3.8 2.7 3:20 0.9 10:40 1.7 1.2 3:20 0.044 9:15 0.158 0.076 0.076
1/31/2018 2:35 2.1 12:15 3.6 2.7 23:50 0.8 12:15 1.7 1.1 2:35 0.038 12:15 0.157 0.071 0.071
ReportAvg 2.8 1.1 0.072
ReportTotal 1.658
ADS Environmental Services
Pipe Height: 7.38
REN_MH3216\mp1\DFINAL (inches) REN_MH3216\mp1\VFINAL (feet/sec) REN_MH3216\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
2/1/2018 4:30 1.9 15:10 3.6 2.6 4:00 0.6 15:10 1.6 1.1 4:00 0.029 15:10 0.153 0.069 0.069
2/2/2018 3:00 2.2 10:05 3.9 2.7 3:45 0.8 10:35 1.7 1.2 3:45 0.040 10:35 0.164 0.075 0.075
2/3/2018 3:15 2.2 19:55 3.4 2.6 4:45 0.8 10:55 1.5 1.1 4:45 0.044 19:55 0.124 0.068 0.068
2/4/2018 23:55 2.1 10:10 4.0 2.6 2:40 0.8 10:10 1.9 1.1 23:55 0.040 10:10 0.201 0.068 0.068
2/5/2018 4:20 2.0 15:05 3.7 2.6 2:25 0.7 15:05 1.8 1.1 2:25 0.028 15:05 0.177 0.069 0.069
2/6/2018 3:40 2.0 12:10 3.4 2.6 1:35 0.7 12:10 1.6 1.1 1:35 0.033 12:10 0.137 0.066 0.066
2/7/2018 23:40 2.1 19:50 3.7 2.6 0:45 0.8 16:00 1.6 1.1 0:45 0.039 19:50 0.152 0.066 0.066
2/8/2018 3:50 1.9 11:50 3.7 2.5 2:55 0.8 11:50 1.6 1.1 2:55 0.031 11:50 0.158 0.064 0.064
2/9/2018 4:10 1.9 13:55 3.7 2.5 1:40 0.7 13:55 1.6 1.1 1:40 0.029 13:55 0.159 0.066 0.066
2/10/2018 3:25 2.1 13:45 3.5 2.5 20:45 0.8 13:45 1.6 1.1 3:25 0.035 13:45 0.146 0.061 0.061
2/11/2018 3:45 1.9 12:20 3.5 2.4 1:25 0.6 12:20 1.7 1.0 1:30 0.026 12:20 0.147 0.056 0.056
2/12/2018 0:40 1.8 11:10 3.7 2.4 0:30 0.5 14:25 1.6 1.0 0:30 0.019 11:10 0.148 0.057 0.057
2/13/2018 3:10 1.7 17:25 3.5 2.3 3:05 0.4 17:25 1.6 0.9 3:05 0.012 17:25 0.142 0.051 0.051
2/14/2018 1:25 1.8 14:10 3.6 2.5 1:55 0.5 14:10 1.7 1.0 1:55 0.020 14:10 0.155 0.061 0.061
2/15/2018 22:55 2.0 8:50 3.4 2.5 23:55 0.7 8:50 1.6 1.0 23:55 0.027 8:50 0.137 0.061 0.061
2/16/2018 1:40 1.6 17:15 3.7 2.4 2:50 0.6 17:15 1.6 1.0 2:50 0.020 17:15 0.160 0.057 0.057
2/17/2018 3:15 1.7 23:00 3.3 2.4 4:00 0.5 23:00 1.4 1.0 4:00 0.020 23:00 0.116 0.057 0.057
2/18/2018 3:55 2.0 9:00 3.5 2.5 5:20 0.7 9:00 1.6 1.0 3:20 0.031 9:00 0.140 0.059 0.059
2/19/2018 3:40 1.9 11:40 3.3 2.5 3:15 0.8 9:55 1.5 1.0 3:40 0.030 11:40 0.121 0.059 0.059
2/20/2018 2:45 1.7 7:15 3.8 2.4 4:15 0.5 7:15 1.8 1.0 4:15 0.018 7:15 0.181 0.055 0.055
2/21/2018 1:40 1.8 19:25 3.4 2.4 2:10 0.6 19:25 1.6 1.0 2:10 0.021 19:25 0.133 0.056 0.056
2/22/2018 4:55 1.7 13:40 3.6 2.4 3:25 0.5 15:00 1.5 0.9 3:25 0.017 15:00 0.135 0.052 0.052
2/23/2018 3:55 1.8 10:15 4.0 2.4 2:55 0.6 10:15 1.7 1.0 3:45 0.024 10:15 0.184 0.054 0.054
2/24/2018 4:20 1.8 14:30 3.2 2.3 3:45 0.6 14:30 1.4 0.9 3:45 0.022 14:30 0.109 0.047 0.047
2/25/2018 3:15 1.6 18:25 3.6 2.3 1:30 0.5 18:25 1.5 0.9 1:30 0.017 18:25 0.137 0.046 0.046
2/26/2018 3:05 1.7 15:20 3.6 2.4 0:30 0.5 15:20 1.5 0.9 2:25 0.018 15:20 0.143 0.053 0.053
2/27/2018 23:50 1.9 10:20 3.6 2.4 0:45 0.6 10:20 1.6 0.9 0:45 0.028 10:20 0.150 0.053 0.053
2/28/2018 1:15 1.6 10:55 3.5 2.4 2:25 0.6 10:55 1.4 0.9 0:40 0.020 10:55 0.129 0.051 0.051
ReportAvg 2.5 1.0 0.059
ReportTotal 1.657
ADS Environmental Services
Pipe Height: 7.38
REN_MH3216\mp1\DFINAL (inches) REN_MH3216\mp1\VFINAL (feet/sec) REN_MH3216\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
3/1/2018 2:40 1.8 10:25 3.7 2.4 4:05 0.5 10:00 1.5 0.9 2:40 0.020 10:25 0.140 0.051 0.051
3/2/2018 4:00 1.7 10:45 3.6 2.4 3:50 0.5 10:45 1.6 1.0 3:50 0.020 10:45 0.149 0.056 0.056
3/3/2018 2:55 1.7 11:10 3.1 2.2 4:35 0.4 11:10 1.3 0.8 4:35 0.015 11:10 0.100 0.043 0.043
3/4/2018 4:55 1.6 13:30 3.3 2.3 4:45 0.5 15:10 1.4 0.9 4:45 0.015 15:10 0.115 0.045 0.045
3/5/2018 23:55 1.6 10:40 3.2 2.1 2:30 0.4 10:25 1.3 0.8 2:30 0.014 10:40 0.099 0.038 0.038
3/6/2018 4:35 1.4 12:05 3.6 2.3 4:35 0.4 12:05 1.5 0.9 4:35 0.011 12:05 0.142 0.047 0.047
3/7/2018 3:25 1.7 13:10 3.4 2.3 3:25 0.4 13:10 1.3 0.9 3:25 0.013 13:10 0.116 0.048 0.048
3/8/2018 3:05 1.8 13:30 3.5 2.4 3:00 0.5 10:05 1.4 0.9 3:00 0.018 13:30 0.127 0.048 0.048
3/9/2018 4:10 1.7 10:55 3.5 2.3 2:00 0.5 10:55 1.4 0.9 4:10 0.018 10:55 0.126 0.048 0.048
3/10/2018 3:15 1.7 8:45 3.3 2.2 3:25 0.5 8:45 1.3 0.8 3:25 0.017 8:45 0.112 0.043 0.043
3/11/2018 2:45 1.6 9:25 3.2 2.3 2:35 0.5 9:25 1.4 0.8 2:35 0.015 9:25 0.112 0.044 0.044
3/12/2018 3:05 1.7 14:15 3.6 2.4 1:15 0.6 14:15 1.5 0.9 3:05 0.020 14:15 0.136 0.052 0.052
3/13/2018 2:25 1.7 11:15 3.5 2.3 2:25 0.5 11:15 1.5 0.9 2:25 0.018 11:15 0.135 0.048 0.048
3/14/2018 2:05 1.6 14:05 3.4 2.4 3:30 0.5 12:05 1.5 0.9 2:05 0.017 16:05 0.124 0.049 0.049
3/15/2018 23:55 1.7 10:20 3.8 2.4 2:40 0.6 10:20 1.6 0.9 23:55 0.021 10:20 0.162 0.051 0.051
3/16/2018 3:50 1.6 9:35 3.7 2.3 3:50 0.5 7:15 1.4 0.9 3:50 0.015 9:35 0.138 0.046 0.046
3/17/2018 2:25 1.8 7:40 3.4 2.3 2:25 0.6 8:20 1.4 0.9 2:25 0.023 7:40 0.119 0.047 0.047
3/18/2018 3:45 1.7 11:25 3.4 2.3 4:10 0.5 11:25 1.4 0.9 4:10 0.019 11:25 0.120 0.047 0.047
3/19/2018 3:00 1.8 13:45 3.7 2.4 3:20 0.6 13:45 1.6 0.9 3:00 0.021 13:45 0.154 0.048 0.048
3/20/2018 23:10 1.7 9:10 3.5 2.3 23:55 0.5 11:00 1.4 0.9 23:55 0.018 9:10 0.121 0.047 0.047
3/21/2018 1:50 1.5 13:55 3.5 2.2 3:15 0.5 15:30 1.5 0.8 2:35 0.015 13:55 0.133 0.042 0.042
3/22/2018 2:35 1.5 7:50 3.6 2.3 3:10 0.4 7:50 1.6 0.9 3:10 0.012 7:50 0.147 0.048 0.048
3/23/2018 1:30 1.6 8:35 3.8 2.4 1:20 0.5 8:35 1.6 0.9 1:20 0.016 8:35 0.159 0.053 0.053
3/24/2018 2:25 1.9 8:20 3.3 2.4 2:25 0.7 8:20 1.4 0.9 2:25 0.025 8:20 0.121 0.052 0.052
3/25/2018 23:30 1.7 13:25 3.3 2.3 3:55 0.5 13:25 1.5 0.9 23:30 0.018 13:25 0.124 0.048 0.048
3/26/2018 3:05 1.6 15:35 3.4 2.4 3:20 0.5 15:35 1.4 0.9 3:05 0.016 15:35 0.120 0.049 0.049
3/27/2018 23:40 1.7 13:40 3.4 2.4 23:40 0.6 8:25 1.4 0.9 23:40 0.020 8:25 0.122 0.049 0.049
3/28/2018 2:10 1.6 9:55 3.5 2.3 2:25 0.5 8:55 1.4 0.9 2:25 0.016 9:55 0.116 0.046 0.046
3/29/2018 0:45 1.7 9:20 3.6 2.4 0:45 0.6 9:20 1.5 0.9 0:45 0.019 9:20 0.137 0.047 0.047
3/30/2018 3:25 1.6 11:50 3.2 2.3 0:05 0.4 12:10 1.3 0.9 0:05 0.015 11:50 0.102 0.046 0.046
3/31/2018 3:25 1.6 8:45 3.5 2.2 4:35 0.5 8:45 1.4 0.8 4:35 0.016 8:45 0.129 0.043 0.043
ReportAvg 2.3 0.9 0.047
ReportTotal 1.470
ADS Environmental Services
Pipe Height: 7.38
REN_MH3216\mp1\DFINAL (inches) REN_MH3216\mp1\VFINAL (feet/sec) REN_MH3216\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
4/1/2018 2:20 1.6 8:55 3.2 2.2 3:30 0.4 8:55 1.2 0.8 3:30 0.012 8:55 0.098 0.042 0.042
4/2/2018 2:05 1.6 10:45 3.4 2.3 2:05 0.4 10:45 1.5 0.8 2:05 0.013 10:45 0.128 0.044 0.044
4/3/2018 23:45 1.7 12:15 3.4 2.3 1:30 0.5 12:15 1.4 0.9 23:45 0.018 12:15 0.127 0.047 0.047
4/4/2018 2:00 1.5 12:50 3.4 2.3 2:00 0.5 12:50 1.4 0.8 2:00 0.014 12:50 0.120 0.044 0.044
4/5/2018 2:05 1.6 9:45 3.4 2.4 2:05 0.5 9:55 1.4 0.9 2:05 0.017 9:45 0.119 0.050 0.050
4/6/2018 2:10 1.8 11:20 3.6 2.4 1:20 0.6 11:20 1.5 0.9 23:45 0.023 11:20 0.143 0.049 0.049
4/7/2018 2:35 1.7 10:00 3.3 2.4 0:25 0.5 10:00 1.4 0.9 2:30 0.018 10:00 0.114 0.053 0.053
4/8/2018 1:45 1.9 12:15 3.4 2.5 1:50 0.7 12:15 1.4 0.9 1:45 0.028 12:15 0.120 0.056 0.056
4/9/2018 2:45 1.9 11:55 3.5 2.5 2:10 0.6 11:55 1.4 0.9 2:10 0.025 11:55 0.132 0.054 0.054
4/10/2018 3:05 1.9 11:45 3.6 2.5 2:50 0.7 11:45 1.5 0.9 3:05 0.026 11:45 0.141 0.054 0.054
4/11/2018 3:00 1.9 15:45 3.5 2.5 0:20 0.6 11:20 1.5 1.0 0:20 0.027 15:45 0.127 0.058 0.058
4/12/2018 2:25 1.9 9:05 3.5 2.5 1:00 0.6 12:00 1.5 0.9 1:00 0.026 12:00 0.135 0.056 0.056
4/13/2018 2:00 1.8 11:00 3.6 2.5 0:30 0.6 11:00 1.5 0.9 3:05 0.024 11:00 0.140 0.054 0.054
4/14/2018 3:35 2.0 19:00 3.6 2.7 3:35 0.7 7:50 1.5 1.0 3:35 0.028 7:50 0.134 0.067 0.067
4/15/2018 23:40 2.2 9:35 3.5 2.8 23:40 0.8 13:10 1.5 1.1 23:40 0.038 9:35 0.130 0.073 0.073
4/16/2018 3:20 2.1 7:40 4.0 2.8 2:25 0.7 7:40 1.8 1.1 2:25 0.032 7:40 0.195 0.072 0.072
4/17/2018 23:40 2.1 8:00 4.1 2.7 23:35 0.8 8:00 1.8 1.0 23:40 0.035 8:00 0.199 0.064 0.064
4/18/2018 23:40 2.0 12:50 3.6 2.6 3:10 0.7 13:10 1.4 1.0 3:10 0.031 13:10 0.131 0.060 0.060
4/19/2018 22:15 2.0 11:25 3.6 2.6 22:25 0.6 11:25 1.5 1.0 22:15 0.026 11:25 0.136 0.060 0.060
4/20/2018 2:00 1.9 14:40 3.7 2.5 2:00 0.6 14:40 1.6 0.9 2:00 0.023 14:40 0.150 0.057 0.057
4/21/2018 2:05 1.8 6:35 3.3 2.4 1:55 0.6 6:35 1.3 0.9 2:05 0.023 6:35 0.114 0.051 0.051
4/22/2018 23:55 1.9 9:55 3.3 2.4 23:55 0.6 9:55 1.3 0.9 23:55 0.024 9:55 0.111 0.050 0.050
ReportAvg 2.5 0.9 0.055
ReportTotal 1.217
REN_MH3625
Located At: 4201 NE Sunset Blvd (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 12”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 3.28 1.71 0.198 27%
Maximum 11.73 3.67 1.855 98%
Average 5.86 2.78 0.702 49%
Latitude: 47.503555°
Longitude:-122.163503°
REN_MH3625
TRITON+
System Characteristics
Location Type
Pipe ShapeSite located between trees and bus top, park
in lot
Renton. Carollo.I&I.WA17
NoneDrive
Site Access Details:
Site Address /Location:
Site Name
4201 NE Sunset Blvd
Flow Monitoring
Site Report
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, November 29, 2017
Access
Temporary
12.00" x 12.00"
Traffic
MH5505 Residential / Commercial
Map
Installation Type:
Monitoring Location (Sensors):
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
1.38"
Peak Velocity (fps)
Silt (in)
11:50:00 AM 12.00" x 12.00"Site Sketch Profile View or Photo
Smooth flow with some ripples
0 - 5 psi
Depth of Flow (Wet DOF) (in)
4.38''
Velocity Sensor Offset (in)
3.27'
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Brick Good
11'
Manhole Condition:
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton. Carollo.I&I.WA17
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
Yes, Inside
Vitrified Clay Pipe
NormalSteel
Fair
Active Connections
None.
Air Quality:
Communication Type
Normal
Additional Photos
Flow Direction
Monitoring Point
KEY
Top Down Location Location Map
Inlet Outlet
ADS Environmental Services
Pipe Height: 12.00
REN_MH3625\mp1\DFINAL (inches) REN_MH3625\mp1\VFINAL (feet/sec) REN_MH3625\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 3:40 4.5 10:40 8.6 5.8 2:55 2.4 11:35 3.3 2.8 3:40 0.418 10:40 1.237 0.683 0.683 0.10
12/23/2017 3:40 4.3 11:50 8.6 5.7 4:55 2.1 11:00 3.3 2.7 4:55 0.346 13:35 1.243 0.656 0.656 0.00
12/24/2017 4:30 3.9 11:10 9.0 5.5 4:20 2.2 14:15 3.3 2.7 4:20 0.320 11:10 1.324 0.625 0.625 0.00
12/25/2017 4:55 3.8 10:50 8.4 5.3 5:45 2.2 13:15 3.3 2.7 4:55 0.306 10:50 1.229 0.595 0.595 0.14
12/26/2017 4:30 3.9 9:20 7.9 5.3 5:10 2.1 20:05 3.3 2.6 4:25 0.301 17:55 1.147 0.579 0.579 0.17
12/27/2017 3:50 3.7 20:30 7.8 5.2 3:45 2.1 18:00 3.1 2.5 3:45 0.279 20:30 1.066 0.546 0.546 0.00
12/28/2017 4:05 3.6 22:20 7.8 5.2 4:15 2.0 11:55 3.2 2.5 4:15 0.264 22:20 1.098 0.553 0.553 0.25
12/29/2017 2:50 4.6 11:50 11.4 7.8 2:05 2.3 11:50 3.5 3.0 2:50 0.418 11:50 1.746 1.043 1.043 1.57
12/30/2017 23:50 6.3 10:20 10.3 7.4 5:40 2.8 10:20 3.3 3.1 5:35 0.798 10:20 1.544 0.995 0.995 0.02
12/31/2017 4:50 5.3 13:30 9.6 6.6 6:40 2.7 22:00 3.4 3.0 5:45 0.592 14:15 1.400 0.852 0.852 0.00
ReportAvg 6.0 2.8 0.713
ReportTotal 7.126 2.25
ADS Environmental Services
Pipe Height: 12.00
REN_MH3625\mp1\DFINAL (inches) REN_MH3625\mp1\VFINAL (feet/sec) REN_MH3625\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 6:25 4.7 15:25 9.0 6.1 3:35 2.5 21:30 3.4 2.9 6:20 0.476 21:30 1.324 0.751 0.751 0.00
1/2/2018 3:45 4.5 20:35 8.5 5.7 3:30 2.3 19:35 3.4 2.8 3:30 0.400 19:35 1.300 0.666 0.666 0.01
1/3/2018 3:50 4.1 20:35 8.7 5.5 5:05 2.1 20:35 3.4 2.7 3:50 0.330 20:35 1.337 0.636 0.636 0.00
1/4/2018 3:45 4.2 19:40 8.2 5.4 3:45 2.2 19:40 3.3 2.7 3:45 0.342 19:40 1.227 0.617 0.617 0.09
1/5/2018 2:20 4.0 18:40 8.2 5.5 3:20 2.2 18:40 3.4 2.8 3:20 0.326 18:40 1.253 0.632 0.632 0.42
1/6/2018 3:10 4.4 12:05 9.1 6.0 3:20 2.5 10:40 3.3 2.9 3:10 0.421 12:05 1.277 0.745 0.745 0.24
1/7/2018 4:20 4.4 19:45 9.4 6.1 2:55 2.5 9:55 3.4 2.9 4:20 0.440 9:55 1.387 0.764 0.764 0.38
1/8/2018 3:00 5.0 20:40 9.2 6.4 16:30 2.6 19:55 3.3 2.9 3:00 0.526 19:00 1.340 0.808 0.808 0.14
1/9/2018 4:00 5.2 19:30 9.7 6.7 4:20 2.5 17:35 3.3 3.0 4:20 0.539 6:00 1.419 0.875 0.875 0.46
1/10/2018 4:15 5.5 21:55 9.4 6.6 15:00 2.7 0:25 3.4 2.9 4:25 0.630 19:10 1.313 0.850 0.850 0.22
1/11/2018 3:20 5.2 20:45 11.6 7.6 4:40 2.6 19:55 3.5 3.1 3:20 0.552 20:45 1.730 1.047 1.047 1.04
1/12/2018 4:00 6.7 8:00 10.3 7.5 22:40 2.9 11:55 3.4 3.2 4:15 0.880 7:15 1.536 1.061 1.061 0.20
1/13/2018 5:10 6.0 10:50 10.8 7.1 7:00 2.8 11:00 3.3 3.1 3:30 0.723 10:50 1.591 0.959 0.959 0.02
1/14/2018 4:40 5.4 11:10 9.7 6.7 4:10 2.6 9:40 3.4 3.0 4:05 0.594 10:25 1.388 0.872 0.872 0.00
1/15/2018 3:50 5.0 11:10 9.0 6.4 5:50 2.6 16:30 3.3 2.9 3:25 0.523 19:15 1.298 0.802 0.802 0.04
1/16/2018 4:05 4.7 19:40 9.0 6.1 4:30 2.5 18:45 3.3 2.9 4:20 0.479 7:30 1.285 0.750 0.750 0.26
1/17/2018 3:35 4.5 22:05 9.9 6.2 14:55 2.5 6:40 3.3 2.9 3:35 0.437 22:05 1.444 0.770 0.770 0.79
1/18/2018 1:50 5.8 7:15 10.2 7.4 13:30 2.8 7:25 3.3 3.0 2:45 0.682 7:15 1.522 0.981 0.981 0.40
1/19/2018 3:20 5.8 7:15 9.5 6.9 3:30 2.8 12:20 3.3 3.0 3:20 0.682 7:15 1.325 0.905 0.905 0.10
1/20/2018 3:55 5.4 10:05 9.6 6.7 2:25 2.6 10:10 3.3 2.9 4:15 0.587 10:05 1.347 0.852 0.852 0.10
1/21/2018 4:15 4.9 18:55 9.3 6.5 4:10 2.4 19:00 3.3 2.9 4:10 0.472 20:30 1.347 0.818 0.818 0.16
1/22/2018 1:20 4.9 21:05 9.2 6.4 1:30 2.5 10:40 3.3 2.9 2:25 0.486 21:05 1.295 0.799 0.799 0.34
1/23/2018 2:30 4.9 21:20 10.2 6.7 3:10 2.5 14:45 3.3 3.0 3:10 0.501 21:20 1.460 0.859 0.859 0.79
1/24/2018 3:00 6.5 19:15 10.8 7.8 0:40 2.8 9:30 3.4 3.1 3:05 0.840 19:15 1.602 1.087 1.087 0.51
1/25/2018 23:35 6.5 8:05 10.3 7.4 10:05 2.9 23:55 3.3 3.1 3:45 0.827 8:05 1.527 1.018 1.018 0.14
1/26/2018 3:20 5.7 21:10 9.4 6.9 2:55 2.6 13:25 3.4 3.1 2:55 0.642 13:20 1.402 0.924 0.924 0.36
1/27/2018 0:55 6.5 11:35 11.2 8.0 23:55 2.9 11:35 3.5 3.2 23:55 0.836 11:35 1.731 1.138 1.138 0.61
1/28/2018 4:55 6.5 12:10 10.7 7.4 4:55 2.9 22:05 3.4 3.1 4:55 0.797 12:10 1.588 1.029 1.029 0.07
1/29/2018 2:30 5.7 20:45 11.7 7.6 12:40 2.7 20:45 3.5 3.1 2:30 0.673 20:45 1.791 1.061 1.061 0.90
1/30/2018 23:40 6.5 7:15 10.3 7.5 6:50 2.8 17:55 3.4 3.2 23:55 0.840 7:15 1.517 1.055 1.055 0.00
1/31/2018 2:30 5.9 21:15 9.6 6.7 12:50 2.6 5:55 3.3 3.1 2:10 0.726 21:15 1.411 0.899 0.899 0.00
ReportAvg 6.7 3.0 0.872
ReportTotal 27.03 8.79
ADS Environmental Services
Pipe Height: 12.00
REN_MH3625\mp1\DFINAL (inches) REN_MH3625\mp1\VFINAL (feet/sec) REN_MH3625\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 2:35 5.2 21:20 9.8 6.5 13:35 2.6 13:55 3.3 3.0 2:40 0.555 21:20 1.434 0.835 0.835 0.66
2/2/2018 4:05 5.9 6:50 9.2 6.8 4:05 2.8 23:25 3.4 3.1 4:05 0.694 7:35 1.318 0.916 0.916 0.04
2/3/2018 4:20 5.4 9:55 9.8 6.8 4:45 2.7 18:05 3.3 3.0 4:10 0.611 9:55 1.422 0.896 0.896 0.31
2/4/2018 4:20 5.7 14:30 10.1 7.0 6:40 2.6 9:20 3.4 3.0 4:20 0.652 14:30 1.487 0.934 0.934 0.02
2/5/2018 3:15 5.2 20:35 9.1 6.4 2:20 2.6 13:50 3.3 3.0 3:15 0.561 20:35 1.286 0.818 0.818 0.04
2/6/2018 3:50 4.8 20:40 9.0 6.1 3:10 2.5 6:50 3.3 2.9 3:10 0.488 6:50 1.338 0.753 0.753 0.00
2/7/2018 2:30 4.6 7:30 8.6 5.8 2:35 2.5 1:20 3.3 2.9 2:35 0.453 8:25 1.207 0.708 0.708 0.00
2/8/2018 4:10 4.4 20:25 8.7 5.7 2:30 2.4 8:50 3.3 2.8 3:25 0.420 20:25 1.256 0.678 0.678 0.09
2/9/2018 3:30 4.3 8:15 8.4 5.5 2:20 2.4 18:45 3.3 2.8 2:15 0.399 8:15 1.242 0.648 0.648 0.01
2/10/2018 3:50 4.2 10:25 9.0 5.6 3:05 2.3 20:20 3.3 2.7 3:50 0.366 10:25 1.211 0.653 0.653 0.01
2/11/2018 4:15 4.0 18:40 8.3 5.6 4:05 2.1 19:30 3.3 2.8 4:05 0.323 18:40 1.199 0.659 0.659 0.00
2/12/2018 2:05 3.9 7:20 8.1 5.3 2:50 2.1 11:25 3.2 2.7 3:50 0.310 7:20 1.172 0.582 0.582 0.00
2/13/2018 3:50 3.8 21:15 7.8 5.2 2:10 2.1 16:20 3.3 2.7 2:10 0.297 21:15 1.106 0.572 0.572 0.17
2/14/2018 3:00 3.8 21:10 8.5 5.2 4:05 2.1 21:10 3.3 2.7 2:40 0.302 21:10 1.251 0.584 0.584 0.15
2/15/2018 2:20 3.9 7:15 8.0 5.2 2:45 2.1 18:25 3.3 2.6 2:40 0.307 7:15 1.110 0.565 0.565 0.00
2/16/2018 4:15 3.9 19:50 7.5 5.2 1:50 2.1 6:05 3.3 2.6 2:30 0.314 6:05 1.010 0.564 0.564 0.15
2/17/2018 2:55 3.9 9:50 8.1 5.6 3:25 2.1 10:40 3.3 2.7 3:25 0.304 9:50 1.154 0.645 0.645 0.32
2/18/2018 4:25 4.0 11:35 8.2 5.5 6:30 2.3 16:35 3.2 2.7 4:25 0.344 11:35 1.159 0.619 0.619 0.01
2/19/2018 3:30 4.0 20:10 7.9 5.3 3:55 2.1 14:35 3.3 2.7 3:55 0.313 20:10 1.116 0.597 0.597 0.00
2/20/2018 3:20 3.8 9:50 7.2 5.1 4:50 2.2 18:00 3.2 2.7 3:20 0.312 16:55 1.002 0.561 0.561 0.00
2/21/2018 3:00 3.7 18:50 7.2 5.0 3:00 2.1 22:00 3.2 2.6 3:00 0.273 18:50 1.020 0.536 0.536 0.00
2/22/2018 3:25 3.7 20:15 7.2 5.0 2:40 2.0 13:45 3.2 2.6 2:40 0.276 20:15 0.999 0.531 0.531 0.07
2/23/2018 2:55 3.5 19:50 7.3 4.9 3:15 2.0 18:45 3.2 2.6 3:30 0.251 19:50 1.027 0.517 0.517 0.01
2/24/2018 3:00 3.6 10:45 8.1 4.9 0:20 2.1 12:35 3.2 2.7 3:00 0.270 10:45 1.178 0.534 0.534 0.13
2/25/2018 4:30 3.6 11:20 8.1 5.2 3:25 2.2 10:35 3.3 2.7 4:10 0.294 10:35 1.199 0.586 0.586 0.11
2/26/2018 3:20 3.5 6:55 7.9 5.0 3:05 1.9 21:05 3.3 2.6 3:05 0.247 21:05 1.168 0.524 0.524 0.00
2/27/2018 3:45 3.4 20:10 8.2 4.9 3:15 2.1 7:15 3.3 2.6 3:15 0.249 20:10 1.096 0.524 0.524 0.19
2/28/2018 3:25 3.5 20:40 8.8 5.2 3:05 2.1 15:30 3.2 2.6 3:05 0.259 20:40 1.181 0.556 0.556 0.35
ReportAvg 5.6 2.7 0.646
ReportTotal 18.10 2.84
ADS Environmental Services
Pipe Height: 12.00
REN_MH3625\mp1\DFINAL (inches) REN_MH3625\mp1\VFINAL (feet/sec) REN_MH3625\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 3:40 4.0 20:55 8.3 5.4 3:25 2.1 19:05 3.2 2.7 3:25 0.304 20:05 1.102 0.593 0.593 0.01
3/2/2018 3:20 4.0 20:40 7.7 5.3 3:00 2.2 9:05 3.2 2.7 3:05 0.328 9:05 1.076 0.593 0.593 0.07
3/3/2018 4:05 4.0 9:45 8.1 5.4 3:15 2.1 16:50 3.2 2.7 3:15 0.309 9:45 1.135 0.600 0.600 0.00
3/4/2018 4:45 3.8 20:35 8.1 5.4 4:50 2.0 14:15 3.2 2.7 4:50 0.279 10:00 1.089 0.606 0.606 0.12
3/5/2018 3:45 3.8 21:15 8.0 5.1 4:15 2.0 20:20 3.1 2.6 3:40 0.278 21:15 1.121 0.553 0.553 0.00
3/6/2018 2:45 3.7 8:10 7.8 5.1 2:40 2.0 7:20 3.2 2.6 2:40 0.263 7:20 1.102 0.540 0.540 0.00
3/7/2018 2:40 3.6 21:05 7.6 5.1 1:50 2.0 6:40 3.1 2.6 2:40 0.260 21:05 1.046 0.532 0.532 0.03
3/8/2018 2:00 3.7 21:05 8.0 5.2 5:10 2.0 6:25 3.2 2.6 3:25 0.277 19:20 1.118 0.555 0.555 0.37
3/9/2018 2:45 3.8 20:25 7.7 5.2 2:55 2.2 8:40 3.1 2.6 2:55 0.305 8:40 1.060 0.566 0.566 0.00
3/10/2018 4:15 3.8 10:20 8.7 5.3 3:15 2.1 8:45 3.1 2.6 3:50 0.296 10:20 1.163 0.578 0.578 0.00
3/11/2018 4:35 3.6 19:45 7.8 5.3 4:25 2.0 18:05 3.2 2.6 4:25 0.261 19:45 1.104 0.576 0.576 0.00
3/12/2018 1:25 3.6 20:00 8.3 5.1 3:35 2.0 20:50 3.1 2.5 1:55 0.258 20:00 1.142 0.529 0.529 0.00
3/13/2018 2:35 3.5 18:40 8.4 5.1 2:50 1.8 17:50 3.1 2.5 2:50 0.231 18:40 1.124 0.522 0.522 0.31
3/14/2018 2:20 3.6 20:35 7.9 5.1 2:15 1.9 6:30 3.1 2.5 2:15 0.247 20:35 1.045 0.528 0.528 0.04
3/15/2018 2:25 3.6 20:10 7.7 5.1 2:55 2.0 20:10 3.2 2.5 2:25 0.259 20:10 1.089 0.532 0.532 0.00
3/16/2018 2:20 3.4 17:15 7.5 5.0 2:10 1.9 5:30 3.1 2.5 2:10 0.228 17:15 1.006 0.514 0.514 0.00
3/17/2018 4:20 3.7 8:55 8.6 5.2 1:40 1.8 21:10 3.1 2.5 1:25 0.245 8:55 1.153 0.537 0.537 0.00
3/18/2018 3:30 3.3 19:15 7.8 5.2 1:45 1.9 10:30 3.2 2.5 3:30 0.233 10:30 1.105 0.538 0.538 0.00
3/19/2018 2:00 3.4 19:30 7.6 4.9 2:25 1.7 18:45 3.2 2.4 2:25 0.203 19:30 1.007 0.486 0.486 0.00
3/20/2018 2:50 3.3 20:50 7.7 4.8 2:20 1.7 5:35 3.1 2.4 2:20 0.198 20:50 1.068 0.474 0.474 0.00
3/21/2018 2:10 3.3 19:25 7.6 4.8 1:15 1.9 18:30 3.1 2.4 1:30 0.213 18:30 1.011 0.467 0.467 0.10
3/22/2018 2:25 3.3 20:00 8.3 5.0 1:30 1.8 20:00 3.1 2.4 2:25 0.210 20:00 1.158 0.500 0.500 0.48
3/23/2018 2:15 3.5 18:10 7.8 5.1 1:15 1.8 21:25 3.1 2.5 2:15 0.221 15:55 1.043 0.523 0.523 0.31
3/24/2018 2:10 3.8 9:55 8.8 5.5 2:30 2.0 8:15 3.2 2.6 2:10 0.282 9:55 1.150 0.602 0.602 0.28
3/25/2018 3:30 3.8 18:30 8.1 5.5 3:05 2.1 20:55 3.1 2.6 3:15 0.295 18:30 1.124 0.599 0.599 0.01
3/26/2018 2:35 3.8 21:00 8.8 5.2 2:20 2.0 5:25 3.1 2.5 2:20 0.282 21:00 1.241 0.552 0.552 0.17
3/27/2018 2:50 3.9 19:40 8.1 5.1 0:45 1.9 19:40 3.2 2.6 0:45 0.273 19:40 1.155 0.544 0.544 0.02
3/28/2018 2:00 3.8 19:40 7.8 5.1 0:45 2.0 19:40 3.1 2.6 2:35 0.277 19:40 1.102 0.540 0.540 0.01
3/29/2018 2:25 3.6 17:50 7.7 5.0 0:40 2.1 7:35 3.2 2.6 2:20 0.277 5:55 1.014 0.534 0.534 0.00
3/30/2018 2:20 3.6 7:50 7.1 4.9 1:30 2.1 19:55 3.1 2.7 2:15 0.269 7:50 0.952 0.528 0.528 0.00
3/31/2018 2:55 3.3 8:55 8.0 5.0 3:15 2.0 9:40 3.3 2.8 3:15 0.261 8:10 1.091 0.569 0.569 0.00
ReportAvg 5.1 2.6 0.546
ReportTotal 16.91 2.33
ADS Environmental Services
Pipe Height: 12.00
REN_MH3625\mp1\DFINAL (inches) REN_MH3625\mp1\VFINAL (feet/sec) REN_MH3625\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 2:00 3.4 10:00 7.6 5.2 3:45 2.1 9:15 3.3 2.7 3:45 0.254 8:35 1.054 0.573 0.573 0.10
4/2/2018 2:15 3.6 20:05 7.7 5.0 2:35 1.9 18:30 3.3 2.5 2:35 0.243 20:05 1.119 0.522 0.522 0.00
4/3/2018 2:55 3.5 19:35 7.6 4.8 3:25 2.0 10:10 3.4 2.7 0:50 0.255 19:35 1.034 0.515 0.515 0.00
4/4/2018 2:25 3.4 20:10 7.5 4.9 2:45 2.0 7:30 3.1 2.6 2:20 0.237 20:10 1.018 0.522 0.522 0.39
4/5/2018 2:50 3.5 19:05 7.6 5.0 4:25 2.0 21:45 3.2 2.6 2:40 0.256 19:55 1.003 0.525 0.525 0.25
4/6/2018 2:15 3.6 6:55 7.2 4.9 4:00 2.1 19:05 3.4 2.8 2:50 0.278 21:10 0.951 0.556 0.556 0.00
4/7/2018 1:00 3.5 9:55 8.4 5.6 1:05 2.4 23:10 3.4 2.9 1:05 0.309 9:55 1.190 0.690 0.690 0.88
4/8/2018 0:55 4.5 11:20 9.8 6.3 23:15 2.7 13:40 3.3 3.0 0:45 0.521 11:20 1.455 0.806 0.806 0.45
4/9/2018 23:50 4.6 20:25 8.3 5.9 2:15 2.5 16:00 3.2 2.8 23:50 0.458 21:20 1.159 0.708 0.708 0.00
4/10/2018 2:30 4.6 20:05 8.2 5.8 23:10 2.3 6:20 3.3 2.8 2:05 0.429 6:20 1.219 0.673 0.673 0.23
4/11/2018 0:15 4.6 20:05 8.4 5.7 3:40 2.2 17:05 3.4 2.8 3:40 0.420 18:15 1.208 0.680 0.680 0.31
4/12/2018 0:30 4.4 20:10 8.1 5.7 1:20 2.4 21:10 3.3 2.8 0:30 0.430 6:00 1.198 0.669 0.669 0.11
4/13/2018 1:20 4.5 18:50 8.2 5.8 1:15 2.3 16:35 3.3 2.8 1:20 0.402 16:35 1.132 0.675 0.675 0.51
4/14/2018 2:10 4.9 19:45 11.7 7.7 1:35 2.5 19:45 3.6 3.0 2:10 0.517 19:45 1.811 1.045 1.045 1.52
4/15/2018 23:15 6.7 8:30 11.7 8.9 23:05 2.9 9:55 3.7 3.2 23:20 0.875 9:55 1.855 1.284 1.284 0.21
4/16/2018 2:45 6.2 21:00 11.3 7.7 9:15 2.8 10:20 3.5 3.1 2:20 0.779 21:00 1.669 1.080 1.080 0.71
4/17/2018 23:55 6.1 7:00 10.4 7.3 23:45 2.8 18:55 3.4 3.1 23:55 0.736 5:25 1.532 1.018 1.018 0.01
4/18/2018 23:55 5.3 20:45 9.8 6.9 23:40 2.7 16:15 3.5 3.1 23:40 0.590 12:00 1.415 0.930 0.930 0.12
4/19/2018 23:55 4.8 6:15 9.1 6.4 23:55 2.6 8:55 3.5 3.0 23:55 0.490 6:15 1.381 0.816 0.816 0.00
4/20/2018 3:10 4.5 8:35 8.7 5.9 0:25 2.4 6:45 3.4 2.8 3:15 0.442 6:45 1.309 0.720 0.720 0.00
4/21/2018 4:05 4.3 7:15 8.8 5.9 4:20 2.4 7:15 3.4 2.8 4:20 0.402 7:15 1.353 0.706 0.706 0.05
4/22/2018 3:20 4.4 11:15 8.7 5.9 0:45 2.2 8:50 3.3 2.8 4:05 0.389 12:05 1.240 0.704 0.704 0.00
ReportAvg 6.0 2.8 0.746
ReportTotal 16.42 5.85
REN_MH4628
Located At: 766 Monroe Ave NE (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 10.38”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.45 2.46 0.086 14%
Maximum 3.86 6.75 0.787 37%
Average 2.11 4.64 0.261 20%
Latitude: 47.495741°
Longitude:-122.175081°
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
Yes, Inside
Vitrified Clay Pipe
NormalSteel
Fair
Active Connections
Renton traffic control required.
Air Quality:
Communication Type
Normal
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete Good
13'
Manhole Condition:
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
1.38"
Peak Velocity (fps)
Silt (in)
2:50:00 PM 10.38" x 10.00"Site Sketch Profile View or Photo
Straight, Some Ripples
0 - 5 psi
Depth of Flow (Wet DOF) (in)
2.38''
Velocity Sensor Offset (in)
3.00'
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, November 29, 2017
Access
Temporary
10.38" x 10.00"
Traffic
MH4628 Residential / Commercial
Map
Installation Type:
Monitoring Location (Sensors):
REN_MH4628
TRITON+
System Characteristics
Location Type
Pipe ShapeSite located In roadway
Renton.Carollo.I&I.WA17
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
766 Monroe Ave NE
Flow Monitoring
Site Report
Additional Photos
Flow Direction
Monitoring Point
Inlet Outlet Side connect
Top Down Location Location Map
KEY
ADS Environmental Services
Pipe Height: 10.38
REN_MH4628\mp1\DFINAL (inches) REN_MH4628\mp1\VFINAL (feet/sec) REN_MH4628\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 0:10 1.8 17:30 2.2 2.0 0:10 4.2 16:15 5.1 4.8 0:10 0.184 17:30 0.272 0.233 0.233 0.10
12/23/2017 23:00 1.8 6:55 2.1 2.0 23:55 4.1 8:35 5.1 4.6 23:55 0.179 8:35 0.266 0.227 0.227 0.00
12/24/2017 0:25 1.6 9:00 2.1 1.9 0:25 3.5 8:45 5.1 4.4 0:25 0.131 8:45 0.260 0.201 0.201 0.00
12/25/2017 2:40 1.5 9:25 2.1 1.9 4:00 3.2 10:25 4.8 4.2 2:40 0.112 9:20 0.246 0.194 0.194 0.14
12/26/2017 3:35 1.5 17:40 2.0 1.8 1:30 3.0 13:40 4.8 4.1 3:40 0.112 13:40 0.234 0.182 0.182 0.17
12/27/2017 1:05 1.6 13:05 2.1 1.8 0:20 3.0 17:25 4.7 3.9 2:30 0.112 17:25 0.235 0.172 0.172 0.00
12/28/2017 0:20 1.7 17:55 2.0 1.9 0:20 3.3 17:55 4.7 4.1 0:20 0.128 17:55 0.235 0.191 0.191 0.25
12/29/2017 0:05 1.9 13:40 3.7 3.0 1:10 4.0 14:40 6.7 6.0 1:10 0.184 13:40 0.768 0.549 0.549 1.57
12/30/2017 23:55 2.3 0:05 2.9 2.7 23:55 5.6 9:30 6.2 6.0 23:55 0.333 0:05 0.525 0.446 0.446 0.02
12/31/2017 23:00 2.0 11:55 2.4 2.2 23:00 5.1 11:55 6.0 5.5 23:00 0.244 11:55 0.389 0.318 0.318 0.00
ReportAvg 2.1 4.8 0.271
ReportTotal 2.713 2.25
ADS Environmental Services
Pipe Height: 10.38
REN_MH4628\mp1\DFINAL (inches) REN_MH4628\mp1\VFINAL (feet/sec) REN_MH4628\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 23:40 1.9 11:35 2.2 2.0 22:40 4.6 11:35 5.5 5.2 23:35 0.209 11:35 0.302 0.253 0.253 0.00
1/2/2018 3:55 1.9 5:55 2.0 1.9 23:35 4.5 17:50 5.4 4.9 23:40 0.200 17:50 0.263 0.226 0.226 0.01
1/3/2018 23:55 1.8 18:30 1.9 1.9 23:30 4.3 19:10 5.1 4.7 23:30 0.184 18:20 0.235 0.213 0.213 0.00
1/4/2018 0:20 1.8 20:35 1.9 1.9 0:50 4.0 19:45 5.0 4.6 0:50 0.175 19:45 0.234 0.207 0.207 0.09
1/5/2018 3:15 1.8 19:45 2.0 1.9 4:15 3.9 20:25 5.0 4.6 4:15 0.164 20:25 0.244 0.213 0.213 0.42
1/6/2018 2:55 1.9 12:30 2.2 2.0 3:35 4.4 11:55 5.4 5.0 3:35 0.200 12:35 0.307 0.253 0.253 0.24
1/7/2018 5:00 1.9 19:15 2.3 2.1 3:55 4.4 21:30 5.4 5.1 3:55 0.213 19:20 0.322 0.265 0.265 0.38
1/8/2018 4:05 2.0 20:10 2.3 2.1 3:10 5.0 20:10 5.4 5.3 3:10 0.254 20:10 0.327 0.283 0.283 0.14
1/9/2018 0:30 2.0 20:05 2.7 2.4 0:30 5.1 20:00 5.8 5.5 0:30 0.262 20:05 0.443 0.347 0.347 0.46
1/10/2018 15:15 2.1 7:30 2.4 2.2 15:00 5.2 8:10 5.5 5.3 13:50 0.277 7:30 0.350 0.305 0.305 0.22
1/11/2018 2:05 2.1 15:50 3.6 2.9 4:00 5.1 14:40 6.4 5.9 3:30 0.270 15:50 0.709 0.499 0.499 1.04
1/12/2018 18:25 2.8 0:00 3.1 3.0 18:30 5.7 0:00 6.1 5.9 18:30 0.450 0:00 0.568 0.506 0.506 0.20
1/13/2018 23:35 2.4 10:45 2.8 2.6 23:30 5.3 9:50 5.8 5.5 23:35 0.340 9:50 0.464 0.407 0.407 0.02
1/14/2018 23:55 2.1 10:45 2.6 2.3 23:30 5.1 11:20 5.6 5.3 23:30 0.280 10:45 0.399 0.320 0.320 0.00
1/15/2018 2:10 2.1 12:50 2.3 2.2 23:55 4.6 10:20 5.3 5.1 23:55 0.255 10:40 0.311 0.282 0.282 0.04
1/16/2018 0:50 2.1 13:15 2.2 2.2 2:10 4.4 21:05 5.3 4.9 2:10 0.239 19:20 0.298 0.275 0.275 0.26
1/17/2018 2:30 2.1 20:20 2.8 2.3 4:45 4.4 21:10 5.8 5.0 3:50 0.236 20:25 0.466 0.304 0.304 0.79
1/18/2018 2:35 2.5 7:20 3.0 2.8 1:50 5.3 7:45 5.9 5.7 2:35 0.360 7:05 0.527 0.465 0.465 0.40
1/19/2018 23:35 2.3 0:00 2.7 2.5 4:05 5.3 7:50 5.6 5.4 23:35 0.322 0:00 0.434 0.376 0.376 0.10
1/20/2018 3:20 2.2 11:05 2.6 2.3 5:20 5.2 10:15 5.5 5.3 5:20 0.291 11:05 0.385 0.319 0.319 0.10
1/21/2018 1:40 2.2 11:05 2.4 2.2 23:40 4.8 9:35 5.4 5.2 3:15 0.271 11:05 0.350 0.300 0.300 0.16
1/22/2018 1:10 2.2 7:10 2.4 2.2 5:00 4.6 18:35 5.5 5.2 1:20 0.259 7:15 0.340 0.301 0.301 0.34
1/23/2018 1:50 2.2 19:45 3.0 2.5 3:55 4.6 19:55 5.9 5.3 3:55 0.266 19:55 0.523 0.365 0.365 0.79
1/24/2018 0:15 3.0 20:55 3.4 3.2 2:25 5.6 16:00 6.3 5.9 0:15 0.485 20:50 0.643 0.555 0.555 0.51
1/25/2018 23:55 2.8 0:00 3.2 3.0 23:15 5.4 0:25 6.0 5.8 23:50 0.434 0:00 0.585 0.515 0.515 0.14
1/26/2018 4:10 2.5 18:50 2.9 2.8 3:50 5.3 13:25 5.7 5.5 3:55 0.371 18:50 0.475 0.430 0.430 0.36
1/27/2018 0:00 2.8 12:45 3.4 3.2 0:10 5.5 9:50 6.3 6.0 0:10 0.445 12:45 0.665 0.590 0.590 0.61
1/28/2018 23:55 2.7 9:50 3.1 3.0 23:40 5.5 9:15 5.9 5.7 23:55 0.412 9:10 0.538 0.493 0.493 0.07
1/29/2018 3:55 2.5 19:10 3.9 3.1 3:40 5.3 19:35 6.4 5.8 3:55 0.364 19:10 0.787 0.531 0.531 0.90
1/30/2018 23:50 2.8 0:05 3.4 3.1 23:45 5.5 0:20 6.2 5.8 23:45 0.441 0:05 0.642 0.545 0.545 0.00
1/31/2018 23:40 2.4 7:35 2.8 2.6 23:05 5.3 6:55 5.6 5.4 23:40 0.336 6:55 0.452 0.393 0.393 0.00
ReportAvg 2.5 5.4 0.366
ReportTotal 11.34 8.79
ADS Environmental Services
Pipe Height: 10.38
REN_MH4628\mp1\DFINAL (inches) REN_MH4628\mp1\VFINAL (feet/sec) REN_MH4628\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:55 2.2 22:05 3.0 2.5 4:50 5.1 22:40 5.8 5.3 3:55 0.294 22:05 0.522 0.358 0.358 0.66
2/2/2018 23:40 2.6 6:45 3.0 2.8 22:10 5.3 9:10 5.7 5.5 23:40 0.374 7:40 0.496 0.443 0.443 0.04
2/3/2018 5:40 2.4 21:35 2.9 2.6 5:35 5.1 10:00 5.4 5.3 5:35 0.326 21:35 0.441 0.381 0.381 0.31
2/4/2018 23:45 2.5 10:35 3.1 2.7 23:30 5.0 10:35 5.5 5.2 23:40 0.341 10:35 0.492 0.388 0.388 0.02
2/5/2018 23:50 2.4 5:30 2.5 2.5 3:30 4.7 19:10 5.3 5.0 23:50 0.307 7:50 0.358 0.336 0.336 0.04
2/6/2018 2:45 2.3 7:40 2.4 2.4 3:55 4.4 18:50 5.2 4.8 3:55 0.269 7:00 0.325 0.302 0.302 0.00
2/7/2018 3:30 2.1 7:55 2.3 2.2 4:10 4.4 19:10 5.2 4.8 4:10 0.238 19:20 0.303 0.271 0.271 0.00
2/8/2018 2:05 2.1 7:30 2.2 2.1 3:50 4.3 19:00 5.0 4.7 3:50 0.223 22:05 0.282 0.254 0.254 0.09
2/9/2018 4:00 2.0 19:35 2.2 2.1 4:00 4.2 10:05 5.0 4.6 4:00 0.208 10:05 0.281 0.239 0.239 0.01
2/10/2018 2:15 2.1 17:50 2.3 2.2 4:35 3.8 10:35 5.0 4.4 2:15 0.206 11:05 0.285 0.246 0.246 0.01
2/11/2018 4:35 2.1 21:05 2.4 2.3 4:40 3.6 9:20 4.7 4.3 4:40 0.195 18:50 0.280 0.252 0.252 0.00
2/12/2018 2:10 1.9 20:15 2.4 2.2 3:50 3.5 20:20 4.4 4.0 3:50 0.162 20:20 0.289 0.230 0.230 0.00
2/13/2018 2:55 1.9 8:10 2.4 2.2 4:10 3.4 19:10 4.4 4.0 4:10 0.153 19:10 0.281 0.221 0.221 0.17
2/14/2018 4:35 1.9 7:35 2.3 2.1 3:10 3.6 19:20 4.6 4.2 4:15 0.175 7:35 0.277 0.229 0.229 0.15
2/15/2018 3:50 1.9 7:35 2.2 2.0 2:55 3.5 20:10 4.5 4.2 2:55 0.158 7:35 0.243 0.209 0.209 0.00
2/16/2018 23:50 1.8 8:50 2.2 2.0 0:55 3.7 19:35 4.5 4.2 2:10 0.164 7:55 0.249 0.207 0.207 0.15
2/17/2018 4:30 1.7 9:40 2.3 2.0 2:50 3.7 10:25 4.8 4.4 2:50 0.149 9:40 0.284 0.222 0.222 0.32
2/18/2018 4:15 1.8 10:40 2.1 1.9 4:55 4.0 10:35 4.9 4.4 4:15 0.164 10:40 0.250 0.207 0.207 0.01
2/19/2018 3:00 1.6 19:15 2.0 1.8 2:35 3.8 19:15 4.8 4.3 3:00 0.134 19:15 0.231 0.189 0.189 0.00
2/20/2018 2:40 1.6 20:25 1.9 1.8 2:25 3.6 21:30 4.6 4.2 2:25 0.128 20:25 0.213 0.179 0.179 0.00
2/21/2018 5:05 1.6 19:20 1.9 1.8 3:40 3.3 19:05 4.6 4.1 3:40 0.127 19:15 0.217 0.176 0.176 0.00
2/22/2018 5:40 1.6 10:35 1.9 1.8 3:10 3.0 17:05 4.5 4.0 3:10 0.113 20:25 0.201 0.169 0.169 0.07
2/23/2018 5:20 1.6 19:40 1.9 1.8 2:15 2.8 18:50 4.5 4.0 1:50 0.106 18:50 0.199 0.163 0.163 0.01
2/24/2018 0:30 1.6 10:35 1.9 1.8 4:05 2.8 17:25 4.6 4.0 4:05 0.108 10:15 0.210 0.167 0.167 0.13
2/25/2018 0:20 1.6 10:15 2.0 1.8 2:05 2.7 10:10 4.7 4.0 2:05 0.109 10:10 0.232 0.178 0.178 0.11
2/26/2018 3:00 1.7 21:05 2.0 1.8 2:05 2.5 21:15 4.5 3.8 2:05 0.104 21:15 0.215 0.161 0.161 0.00
2/27/2018 10:45 1.7 19:55 2.0 1.8 2:20 2.7 19:40 4.6 3.8 1:35 0.106 19:55 0.221 0.161 0.161 0.19
2/28/2018 3:25 1.7 19:35 2.1 1.9 2:20 2.8 19:30 4.8 4.0 2:20 0.112 19:30 0.253 0.184 0.184 0.35
ReportAvg 2.1 4.4 0.240
ReportTotal 6.722 2.84
ADS Environmental Services
Pipe Height: 10.38
REN_MH4628\mp1\DFINAL (inches) REN_MH4628\mp1\VFINAL (feet/sec) REN_MH4628\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 2:40 1.7 21:20 2.1 1.9 4:00 3.5 19:40 4.9 4.3 3:25 0.147 21:15 0.244 0.199 0.199 0.01
3/2/2018 2:55 1.7 8:05 2.0 1.9 3:25 3.6 8:05 4.9 4.3 2:55 0.147 8:05 0.240 0.195 0.195 0.07
3/3/2018 1:30 1.7 9:55 2.0 1.9 4:00 3.4 13:40 4.7 4.2 1:10 0.142 9:45 0.230 0.191 0.191 0.00
3/4/2018 1:05 1.7 11:35 2.0 1.9 4:40 3.2 9:45 4.8 4.2 3:00 0.133 11:35 0.238 0.188 0.188 0.12
3/5/2018 0:50 1.7 19:50 1.9 1.8 4:15 3.0 20:05 4.6 4.0 4:15 0.118 20:05 0.214 0.175 0.175 0.00
3/6/2018 2:50 1.6 19:45 1.9 1.8 2:15 3.0 19:40 4.6 4.0 2:50 0.114 19:40 0.219 0.170 0.170 0.00
3/7/2018 2:15 1.7 19:45 2.0 1.8 2:10 2.7 21:25 4.6 4.0 2:10 0.105 21:25 0.218 0.171 0.171 0.03
3/8/2018 4:05 1.7 21:30 2.0 1.8 3:05 2.9 21:25 4.7 4.0 3:00 0.113 21:25 0.237 0.174 0.174 0.37
3/9/2018 23:35 1.8 9:25 2.0 1.9 3:20 3.3 9:25 4.6 4.1 3:20 0.137 9:25 0.222 0.182 0.182 0.00
3/10/2018 3:25 1.7 10:40 2.0 1.9 3:50 3.0 10:45 4.6 4.0 3:50 0.117 10:45 0.234 0.180 0.180 0.00
3/11/2018 5:10 1.7 9:25 2.0 1.9 3:50 2.7 9:10 4.7 4.0 3:50 0.110 9:30 0.224 0.178 0.178 0.00
3/12/2018 14:15 1.7 19:15 2.0 1.8 2:45 2.5 18:40 4.6 3.9 2:45 0.099 18:40 0.215 0.164 0.164 0.00
3/13/2018 11:00 1.7 18:55 2.0 1.8 1:25 2.5 18:15 4.6 3.9 2:40 0.097 18:45 0.223 0.164 0.164 0.31
3/14/2018 1:25 1.7 20:30 2.0 1.8 2:50 2.7 7:30 4.6 3.9 1:25 0.108 7:30 0.222 0.168 0.168 0.04
3/15/2018 1:25 1.7 19:55 2.0 1.8 1:20 2.8 17:45 4.5 3.8 1:20 0.105 19:50 0.224 0.170 0.170 0.00
3/16/2018 3:00 1.7 16:40 2.0 1.8 1:45 2.8 16:40 4.4 3.7 1:45 0.111 16:40 0.210 0.162 0.162 0.00
3/17/2018 22:30 1.7 11:05 2.1 1.8 4:25 2.5 9:15 4.5 3.7 3:35 0.102 9:15 0.230 0.165 0.165 0.00
3/18/2018 4:00 1.4 9:35 2.0 1.8 4:55 2.6 10:50 4.5 3.6 4:00 0.086 10:50 0.221 0.160 0.160 0.00
3/19/2018 2:05 1.5 19:30 2.0 1.8 1:55 2.6 19:20 4.5 3.6 1:55 0.086 19:25 0.215 0.150 0.150 0.00
3/20/2018 3:00 1.5 20:05 1.9 1.7 1:40 2.6 18:25 4.4 3.5 2:25 0.088 18:25 0.208 0.142 0.142 0.00
3/21/2018 3:00 1.5 18:35 2.0 1.7 0:05 2.8 18:50 4.4 3.5 3:40 0.098 18:50 0.215 0.144 0.144 0.10
3/22/2018 1:40 1.5 20:30 1.9 1.8 0:50 2.5 19:10 4.3 3.7 0:50 0.093 16:55 0.196 0.151 0.151 0.48
3/23/2018 4:25 1.6 9:45 1.9 1.8 3:20 2.5 18:20 4.5 3.8 3:20 0.096 18:00 0.208 0.165 0.165 0.31
3/24/2018 2:55 1.6 9:00 2.0 1.8 1:10 3.0 9:55 4.7 4.1 2:55 0.114 9:55 0.232 0.182 0.182 0.28
3/25/2018 4:20 1.6 9:15 1.9 1.8 23:55 3.2 9:15 4.8 4.2 4:20 0.124 9:15 0.226 0.180 0.180 0.01
3/26/2018 2:40 1.6 18:40 1.9 1.8 3:45 3.2 18:35 4.7 4.1 2:35 0.116 18:35 0.208 0.173 0.173 0.17
3/27/2018 3:50 1.6 16:50 1.8 1.8 3:15 3.2 16:40 4.7 4.1 3:15 0.118 16:50 0.204 0.169 0.169 0.02
3/28/2018 1:55 1.5 19:25 1.8 1.7 2:40 3.2 17:45 4.7 4.1 2:40 0.109 17:45 0.205 0.166 0.166 0.01
3/29/2018 3:00 1.5 18:30 1.8 1.7 1:00 3.1 19:50 4.6 4.0 3:00 0.101 18:30 0.202 0.160 0.160 0.00
3/30/2018 2:30 1.5 20:55 1.8 1.7 1:05 3.1 9:15 4.5 3.9 3:15 0.103 7:20 0.190 0.156 0.156 0.00
3/31/2018 2:05 1.5 9:50 1.9 1.7 0:25 2.9 9:45 4.8 4.0 2:25 0.101 9:45 0.221 0.161 0.161 0.00
ReportAvg 1.8 3.9 0.170
ReportTotal 5.255 2.33
ADS Environmental Services
Pipe Height: 10.38
REN_MH4628\mp1\DFINAL (inches) REN_MH4628\mp1\VFINAL (feet/sec) REN_MH4628\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 2:15 1.5 9:30 1.9 1.7 3:25 2.8 9:05 4.7 4.0 2:20 0.097 9:30 0.214 0.162 0.162 0.10
4/2/2018 0:00 1.5 7:25 1.8 1.7 0:35 2.7 20:30 4.5 3.8 0:35 0.094 20:30 0.194 0.145 0.145 0.00
4/3/2018 22:40 1.6 20:20 1.8 1.7 3:10 2.6 21:10 4.6 3.7 2:45 0.094 21:10 0.199 0.141 0.141 0.00
4/4/2018 1:45 1.5 20:10 1.9 1.7 0:55 2.6 20:10 4.7 3.7 1:45 0.088 20:10 0.217 0.147 0.147 0.39
4/5/2018 0:25 1.6 18:55 1.9 1.7 3:00 2.6 18:55 4.6 3.9 3:00 0.096 18:55 0.208 0.155 0.155 0.25
4/6/2018 23:35 1.6 19:40 1.8 1.7 1:55 2.9 7:50 4.5 3.9 2:25 0.106 19:40 0.196 0.156 0.156 0.00
4/7/2018 3:30 1.6 9:40 2.0 1.8 1:40 2.9 9:45 5.0 4.4 1:40 0.107 9:40 0.257 0.196 0.196 0.88
4/8/2018 4:35 1.8 10:20 2.2 1.9 2:15 4.1 10:20 5.4 4.9 2:15 0.174 10:20 0.315 0.232 0.232 0.45
4/9/2018 23:55 1.8 19:35 1.9 1.9 0:50 4.4 18:35 5.2 4.8 23:55 0.194 20:20 0.245 0.218 0.218 0.00
4/10/2018 2:45 1.8 19:05 1.9 1.9 3:05 4.2 17:20 5.1 4.7 3:05 0.178 19:05 0.238 0.211 0.211 0.23
4/11/2018 2:30 1.8 20:50 1.9 1.8 2:55 4.2 9:05 5.1 4.7 2:55 0.177 20:50 0.235 0.208 0.208 0.31
4/12/2018 12:15 1.7 11:50 3.0 1.9 2:05 4.4 11:50 6.3 4.7 12:20 0.179 11:50 0.545 0.211 0.211 0.11
4/13/2018 3:30 1.8 20:50 1.9 1.9 2:15 4.2 20:50 5.2 4.8 2:15 0.176 20:50 0.242 0.212 0.212 0.51
4/14/2018 0:45 1.9 23:55 3.5 2.6 2:10 4.9 23:40 6.7 5.8 2:10 0.223 23:55 0.725 0.431 0.431 1.52
4/15/2018 23:55 2.7 2:10 3.6 3.3 23:00 6.1 1:30 6.7 6.5 23:40 0.467 1:35 0.759 0.644 0.644 0.21
4/16/2018 3:35 2.7 18:00 3.1 2.9 3:35 5.9 20:55 6.6 6.2 3:35 0.445 20:05 0.612 0.511 0.511 0.71
4/17/2018 23:50 2.4 0:05 2.9 2.7 23:50 5.8 5:30 6.4 6.1 23:50 0.366 5:40 0.534 0.470 0.470 0.01
4/18/2018 23:55 2.1 6:35 2.5 2.4 23:55 5.3 6:05 6.0 5.7 23:55 0.280 6:20 0.411 0.360 0.360 0.12
4/19/2018 23:55 1.9 6:55 2.4 2.1 23:40 5.1 6:05 5.7 5.4 23:55 0.232 6:55 0.355 0.288 0.288 0.00
4/20/2018 2:30 1.9 6:30 2.1 2.0 23:55 4.7 18:15 5.5 5.1 23:55 0.212 6:30 0.293 0.244 0.244 0.00
4/21/2018 5:00 1.9 9:05 2.0 1.9 2:00 4.5 9:05 5.4 4.9 2:00 0.203 9:05 0.273 0.227 0.227 0.05
4/22/2018 2:10 1.8 9:10 2.0 1.9 2:25 4.3 11:20 5.2 4.8 2:25 0.187 9:10 0.252 0.219 0.219 0.00
ReportAvg 2.0 4.9 0.263
ReportTotal 5.788 5.85
REN_MH4646
Located At: 582 Bronson Way NE (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 8”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the downward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.02 6.57 0.138 13%
Maximum 1.82 11.44 0.387 23%
Average 1.34 9.28 0.225 17%
Latitude: 47.491659°
Longitude:-122.190337°
REN_MH4646
TRITON+
System Characteristics
Location Type
Pipe Shapelocated in turn lane
RENTON
Medium Drive
Site Access Details:
Site Address /Location:
Site Name
582 Bronson Way NE
Flow Monitoring
Site Report
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, December 13, 2017
Access
Temporary
8.00" x 7.75"
Traffic
MH4646 Residential
Map
Installation Type:
Monitoring Location (Sensors):
Peak Combo (CS4), Smart Depth (CS5)
4
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
Peak Velocity (fps)
Silt (in)
12:28:00 PM 8.00" x 7.75"Site Sketch Profile View or Photo
low flow
0 - 5 psi
Depth of Flow (Wet DOF) (in)
1.13
Velocity Sensor Offset (in)
10.75
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete Good
10
Manhole Condition:
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
Yes, Inside
Vitrified Clay Pipe
NormalSteel
Fair
Active Connections
Renton traffic control Needed
Air Quality:
Communication Type
Normal
Additional Photos
Flow Direction
Monitoring Point
Side inlet KEY Google Earth Map
Top Down Location Location Map
Inlet Outlet Location Map
ADS Environmental Services
Pipe Height: 8.00
REN_MH4646\mp1\DFINAL (inches) REN_MH4646\mp1\VFINAL (feet/sec) REN_MH4646\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 1:10 1.2 11:40 1.6 1.4 4:10 8.5 16:15 10.0 9.2 4:10 0.174 17:00 0.280 0.232 0.232 0.10
12/23/2017 6:05 1.1 10:45 1.6 1.4 3:40 8.2 12:05 10.2 9.1 6:05 0.163 10:45 0.301 0.230 0.230 0.00
12/24/2017 3:50 1.2 10:40 1.6 1.3 2:30 7.7 11:00 10.3 9.0 2:30 0.161 10:40 0.301 0.218 0.218 0.00
12/25/2017 2:10 1.2 9:05 1.5 1.3 4:40 7.7 10:20 10.6 8.9 2:10 0.157 11:20 0.287 0.210 0.210 0.14
12/26/2017 4:25 1.2 14:30 1.5 1.3 5:20 7.6 12:25 9.8 8.9 4:50 0.155 14:30 0.273 0.210 0.210 0.17
12/27/2017 2:05 1.1 11:45 1.5 1.3 4:10 7.5 10:35 10.0 9.0 2:05 0.144 11:45 0.286 0.214 0.214 0.00
12/28/2017 2:40 1.1 14:55 1.5 1.3 2:35 7.2 17:55 10.2 8.9 2:40 0.140 14:55 0.262 0.205 0.205 0.25
12/29/2017 2:45 1.1 10:25 1.6 1.4 2:05 8.3 13:00 11.3 9.7 2:45 0.166 10:25 0.329 0.248 0.248 1.57
12/30/2017 5:30 1.2 13:30 1.6 1.4 4:10 8.7 17:00 10.5 9.6 5:30 0.182 13:30 0.317 0.238 0.238 0.02
12/31/2017 3:10 1.2 13:00 1.5 1.4 4:05 8.8 11:20 10.6 9.5 4:10 0.186 12:55 0.306 0.236 0.236 0.00
ReportAvg 1.3 9.2 0.224
ReportTotal 2.241 2.25
ADS Environmental Services
Pipe Height: 8.00
REN_MH4646\mp1\DFINAL (inches) REN_MH4646\mp1\VFINAL (feet/sec) REN_MH4646\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 21:20 1.2 11:05 1.5 1.3 6:15 8.7 10:45 11.3 9.5 7:50 0.184 10:45 0.308 0.229 0.229 0.00
1/2/2018 5:00 1.2 19:40 1.5 1.3 3:40 8.2 19:40 10.5 9.3 3:40 0.167 19:40 0.294 0.221 0.221 0.01
1/3/2018 4:25 1.2 18:00 1.5 1.3 3:50 8.3 16:30 10.3 9.2 23:45 0.171 19:45 0.285 0.225 0.225 0.00
1/4/2018 0:45 1.2 19:00 1.5 1.3 3:35 8.1 19:15 10.4 9.1 1:50 0.170 19:15 0.279 0.219 0.219 0.09
1/5/2018 1:40 1.2 19:55 1.5 1.3 3:35 7.8 13:00 10.2 9.1 3:35 0.157 19:55 0.270 0.210 0.210 0.42
1/6/2018 3:05 1.2 13:10 1.6 1.4 2:40 8.2 11:35 10.2 9.2 3:05 0.168 11:35 0.297 0.225 0.225 0.24
1/7/2018 2:50 1.1 10:25 1.5 1.3 3:55 7.9 23:10 10.4 9.1 2:55 0.157 9:15 0.270 0.214 0.214 0.38
1/8/2018 1:20 1.1 18:45 1.5 1.3 2:35 8.1 9:35 9.9 9.1 3:45 0.157 18:45 0.268 0.206 0.206 0.14
1/9/2018 1:50 1.2 9:40 1.5 1.3 3:10 8.2 17:15 10.1 9.2 3:10 0.169 22:20 0.274 0.219 0.219 0.46
1/10/2018 3:35 1.1 13:50 1.5 1.3 2:10 8.2 20:35 10.5 9.3 4:35 0.161 16:10 0.286 0.225 0.225 0.22
1/11/2018 3:20 1.3 11:10 1.7 1.5 1:45 8.6 16:40 10.7 9.7 1:40 0.204 20:15 0.346 0.276 0.276 1.04
1/12/2018 16:55 1.3 6:20 1.8 1.5 2:55 9.1 18:40 10.7 9.7 5:20 0.229 6:20 0.359 0.275 0.275 0.20
1/13/2018 2:45 1.3 9:05 1.7 1.5 4:10 8.9 9:55 10.6 9.6 2:45 0.203 9:00 0.326 0.266 0.266 0.02
1/14/2018 3:00 1.3 11:30 1.7 1.5 3:35 8.7 16:10 10.5 9.5 3:00 0.196 11:50 0.338 0.258 0.258 0.00
1/15/2018 5:00 1.3 18:35 1.6 1.5 23:55 8.6 18:05 10.7 9.5 23:55 0.199 18:35 0.339 0.257 0.257 0.04
1/16/2018 2:35 1.2 19:50 1.7 1.4 3:45 8.5 21:35 10.6 9.3 2:35 0.187 19:50 0.329 0.243 0.243 0.26
1/17/2018 0:50 1.2 18:30 1.6 1.4 3:05 8.4 20:15 10.6 9.3 3:15 0.180 18:40 0.329 0.236 0.236 0.79
1/18/2018 12:35 1.2 18:20 1.6 1.4 2:20 8.7 18:35 10.2 9.6 2:30 0.185 18:20 0.312 0.246 0.246 0.40
1/19/2018 13:45 1.2 9:45 1.6 1.4 2:50 8.6 12:00 10.5 9.5 3:10 0.188 9:45 0.298 0.237 0.237 0.10
1/20/2018 1:00 1.2 10:05 1.7 1.4 5:15 8.6 11:45 11.0 9.5 3:10 0.178 10:05 0.335 0.250 0.250 0.10
1/21/2018 4:10 1.2 14:50 1.7 1.4 3:00 8.4 13:35 10.5 9.4 4:10 0.176 14:50 0.361 0.246 0.246 0.16
1/22/2018 8:30 1.2 6:50 1.6 1.4 3:45 8.4 6:20 10.5 9.4 8:30 0.186 20:00 0.324 0.246 0.246 0.34
1/23/2018 0:10 1.2 19:00 1.6 1.5 2:35 8.9 19:10 10.4 9.6 0:10 0.190 19:10 0.332 0.261 0.261 0.79
1/24/2018 23:55 1.2 19:50 1.8 1.5 3:40 9.1 20:25 10.6 9.8 23:55 0.207 19:50 0.380 0.285 0.285 0.51
1/25/2018 2:50 1.2 20:00 1.7 1.5 4:10 9.2 20:20 10.7 9.8 2:50 0.195 19:45 0.351 0.279 0.279 0.14
1/26/2018 1:50 1.3 20:00 1.7 1.5 3:05 8.9 10:20 10.6 9.7 3:05 0.203 13:05 0.344 0.275 0.275 0.36
1/27/2018 18:20 1.4 9:30 1.8 1.6 2:20 9.4 12:50 11.3 10.1 3:40 0.248 9:30 0.379 0.300 0.300 0.61
1/28/2018 0:40 1.3 13:50 1.8 1.5 5:00 9.2 9:35 11.1 10.0 0:40 0.236 13:50 0.387 0.294 0.294 0.07
1/29/2018 11:05 1.3 19:50 1.7 1.5 3:00 9.0 21:40 11.4 10.0 5:15 0.210 16:50 0.369 0.280 0.280 0.90
1/30/2018 11:40 1.2 5:55 1.7 1.5 23:35 9.5 18:25 11.1 10.1 11:40 0.205 8:35 0.352 0.276 0.276 0.00
1/31/2018 17:20 1.2 7:10 1.7 1.4 3:25 9.1 12:50 10.6 9.8 23:45 0.189 7:10 0.345 0.259 0.259 0.00
ReportAvg 1.4 9.5 0.250
ReportTotal 7.740 8.79
ADS Environmental Services
Pipe Height: 8.00
REN_MH4646\mp1\DFINAL (inches) REN_MH4646\mp1\VFINAL (feet/sec) REN_MH4646\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:50 1.1 16:35 1.8 1.4 3:25 9.0 19:05 10.8 9.7 3:50 0.160 16:35 0.354 0.249 0.249 0.66
2/2/2018 5:20 1.1 6:15 1.6 1.4 2:50 9.1 10:45 10.7 9.7 5:20 0.183 16:30 0.329 0.237 0.237 0.04
2/3/2018 2:20 1.2 13:15 1.8 1.5 3:45 8.7 14:45 10.8 9.6 2:20 0.175 13:15 0.373 0.261 0.261 0.31
2/4/2018 0:05 1.2 16:00 1.7 1.5 3:10 8.7 11:45 10.8 9.7 0:05 0.190 9:55 0.338 0.270 0.270 0.02
2/5/2018 2:25 1.1 16:40 1.7 1.4 1:55 8.9 19:00 10.4 9.7 2:25 0.168 16:40 0.343 0.260 0.260 0.04
2/6/2018 3:45 1.1 17:55 1.7 1.5 2:55 8.7 10:15 10.4 9.5 3:45 0.174 17:55 0.338 0.259 0.259 0.00
2/7/2018 12:40 1.1 19:25 1.5 1.3 2:15 8.5 19:35 10.3 9.5 2:10 0.165 6:25 0.286 0.228 0.228 0.00
2/8/2018 0:05 1.1 6:20 1.6 1.3 3:10 8.5 20:25 10.7 9.4 2:25 0.178 6:20 0.302 0.226 0.226 0.09
2/9/2018 0:55 1.1 8:40 1.6 1.4 3:10 8.3 16:25 10.3 9.2 1:00 0.159 8:40 0.305 0.227 0.227 0.01
2/10/2018 3:10 1.2 13:50 1.6 1.4 1:55 8.6 12:50 10.7 9.3 3:10 0.172 10:35 0.306 0.234 0.234 0.01
2/11/2018 23:50 1.1 10:30 1.6 1.4 5:15 8.2 11:45 10.6 9.3 23:50 0.169 11:55 0.321 0.234 0.234 0.00
2/12/2018 0:25 1.1 22:10 1.6 1.3 3:10 7.7 19:20 10.0 9.0 3:35 0.153 22:10 0.305 0.211 0.211 0.00
2/13/2018 3:40 1.1 21:30 1.5 1.3 2:20 8.2 20:05 10.1 9.1 3:40 0.153 21:30 0.276 0.209 0.209 0.17
2/14/2018 23:40 1.1 22:30 1.6 1.3 3:15 7.9 19:00 10.5 9.2 2:55 0.152 22:30 0.291 0.203 0.203 0.15
2/15/2018 9:05 1.1 8:00 1.5 1.2 2:50 7.8 18:10 9.9 9.1 4:05 0.144 8:00 0.266 0.194 0.194 0.00
2/16/2018 22:00 1.1 9:15 1.5 1.2 2:45 7.8 20:45 10.5 9.1 1:10 0.145 9:15 0.277 0.198 0.198 0.15
2/17/2018 18:30 1.1 23:10 1.5 1.3 3:55 7.9 10:55 11.1 9.3 2:55 0.150 10:55 0.320 0.208 0.208 0.32
2/18/2018 5:15 1.1 21:25 1.5 1.2 4:35 7.9 14:20 10.9 9.3 5:15 0.138 14:25 0.291 0.202 0.202 0.01
2/19/2018 23:35 1.1 21:20 1.6 1.3 3:45 7.9 12:15 10.3 9.1 4:45 0.153 21:20 0.305 0.219 0.219 0.00
2/20/2018 0:25 1.1 20:20 1.4 1.3 2:20 7.7 20:50 10.3 9.0 0:30 0.153 20:30 0.249 0.201 0.201 0.00
2/21/2018 1:15 1.1 0:00 1.6 1.3 4:10 7.6 13:30 10.2 9.0 1:15 0.144 0:00 0.280 0.206 0.206 0.00
2/22/2018 8:55 1.1 20:00 1.6 1.3 2:30 7.3 16:55 10.2 8.9 2:30 0.153 20:00 0.304 0.211 0.211 0.07
2/23/2018 0:50 1.1 21:35 1.5 1.3 3:10 7.6 9:05 10.3 9.0 3:55 0.147 21:35 0.269 0.210 0.210 0.01
2/24/2018 3:55 1.1 14:25 1.6 1.3 4:05 7.5 9:55 10.3 9.0 3:50 0.140 14:25 0.303 0.217 0.217 0.13
2/25/2018 7:30 1.2 10:40 1.6 1.4 3:20 7.6 10:25 10.0 9.1 3:20 0.156 10:40 0.299 0.223 0.223 0.11
2/26/2018 2:15 1.2 19:25 1.5 1.3 3:50 7.5 19:30 10.6 8.9 2:15 0.160 18:35 0.269 0.206 0.206 0.00
2/27/2018 2:20 1.2 20:30 1.6 1.3 2:20 7.3 21:40 10.0 8.9 2:20 0.144 20:30 0.309 0.216 0.216 0.19
2/28/2018 3:15 1.2 0:00 1.6 1.3 2:10 7.3 19:55 10.1 9.0 3:50 0.155 21:35 0.281 0.216 0.216 0.35
ReportAvg 1.3 9.2 0.223
ReportTotal 6.233 2.84
ADS Environmental Services
Pipe Height: 8.00
REN_MH4646\mp1\DFINAL (inches) REN_MH4646\mp1\VFINAL (feet/sec) REN_MH4646\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 4:45 1.2 21:30 1.5 1.3 2:05 7.5 17:15 10.4 9.0 1:55 0.155 21:30 0.268 0.199 0.199 0.01
3/2/2018 3:25 1.2 9:05 1.5 1.3 2:55 7.8 18:45 10.3 9.0 2:50 0.156 9:05 0.262 0.204 0.204 0.07
3/3/2018 4:35 1.2 10:40 1.6 1.3 4:30 7.2 10:25 10.4 8.9 4:35 0.143 10:25 0.328 0.209 0.209 0.00
3/4/2018 12:20 1.1 9:25 1.7 1.3 5:50 7.4 15:35 10.8 9.0 5:50 0.143 9:30 0.318 0.200 0.200 0.12
3/5/2018 3:25 1.1 18:30 1.4 1.3 3:10 7.4 12:10 10.5 8.9 3:45 0.146 18:30 0.249 0.198 0.198 0.00
3/6/2018 0:55 1.1 6:40 1.4 1.2 3:30 7.3 18:30 10.6 8.9 3:30 0.142 7:10 0.247 0.189 0.189 0.00
3/7/2018 16:05 1.2 17:05 1.5 1.3 1:50 7.4 18:45 9.9 8.9 3:00 0.155 17:05 0.263 0.200 0.200 0.03
3/8/2018 3:35 1.2 20:55 1.6 1.3 3:30 7.6 20:45 10.4 9.0 3:35 0.150 20:55 0.304 0.200 0.200 0.37
3/9/2018 4:35 1.2 18:05 1.6 1.3 2:05 7.7 19:00 10.2 9.0 5:15 0.162 18:05 0.298 0.206 0.206 0.00
3/10/2018 15:45 1.2 10:20 1.5 1.3 4:25 7.1 10:40 10.7 9.1 4:25 0.156 10:20 0.274 0.204 0.204 0.00
3/11/2018 5:10 1.2 10:10 1.4 1.3 4:10 7.4 9:40 10.8 9.1 4:05 0.150 9:40 0.277 0.201 0.201 0.00
3/12/2018 0:10 1.2 20:30 1.4 1.2 2:00 7.0 17:20 10.8 9.0 2:00 0.148 20:30 0.256 0.195 0.195 0.00
3/13/2018 3:00 1.2 18:00 1.4 1.2 1:50 7.8 17:05 10.3 9.2 2:25 0.158 18:00 0.261 0.200 0.200 0.31
3/14/2018 0:20 1.2 20:25 1.5 1.3 2:05 7.7 9:10 10.6 9.2 1:05 0.154 20:25 0.265 0.202 0.202 0.04
3/15/2018 3:20 1.2 19:45 1.4 1.3 1:50 7.7 9:30 10.3 9.1 3:20 0.151 19:45 0.257 0.199 0.199 0.00
3/16/2018 0:50 1.2 6:00 1.5 1.3 2:55 7.5 9:50 10.2 9.1 1:35 0.154 6:00 0.262 0.202 0.202 0.00
3/17/2018 1:15 1.2 12:45 1.5 1.3 0:25 7.8 8:55 10.8 9.1 5:15 0.153 12:45 0.277 0.204 0.204 0.00
3/18/2018 1:20 1.2 9:30 1.6 1.3 4:35 7.1 11:20 10.2 9.0 4:35 0.149 9:30 0.310 0.202 0.202 0.00
3/19/2018 23:55 1.2 17:45 1.5 1.2 2:35 7.2 20:40 10.1 8.9 2:20 0.145 17:45 0.270 0.194 0.194 0.00
3/20/2018 1:25 1.2 20:15 1.5 1.2 23:45 7.8 7:45 10.2 8.9 23:50 0.151 20:15 0.255 0.192 0.192 0.00
3/21/2018 1:15 1.2 19:20 1.5 1.2 0:20 7.2 11:55 9.8 8.8 1:45 0.145 19:20 0.275 0.188 0.188 0.10
3/22/2018 0:45 1.2 4:35 1.5 1.3 2:05 7.4 12:25 9.9 8.9 3:10 0.151 19:15 0.280 0.206 0.206 0.48
3/23/2018 0:45 1.2 5:20 1.6 1.3 1:00 7.5 8:20 10.0 9.0 0:50 0.158 10:10 0.285 0.207 0.207 0.31
3/24/2018 2:45 1.2 11:40 1.6 1.3 2:40 7.7 11:20 10.1 9.0 1:05 0.163 11:40 0.288 0.208 0.208 0.28
3/25/2018 4:35 1.2 19:35 1.6 1.3 4:15 7.5 19:05 10.4 8.9 3:25 0.152 19:25 0.293 0.208 0.208 0.01
3/26/2018 0:25 1.2 17:30 1.6 1.3 1:10 7.3 8:40 10.3 9.0 2:40 0.152 20:35 0.286 0.205 0.205 0.17
3/27/2018 4:40 1.2 19:15 1.5 1.3 0:45 7.7 19:40 10.3 9.1 1:00 0.164 19:15 0.283 0.206 0.206 0.02
3/28/2018 1:15 1.2 4:40 1.5 1.3 2:00 8.0 19:50 10.2 9.1 1:15 0.164 18:55 0.262 0.216 0.216 0.01
3/29/2018 1:15 1.2 8:20 1.4 1.3 1:35 7.9 14:25 10.1 9.1 1:45 0.175 18:00 0.256 0.217 0.217 0.00
3/30/2018 0:00 1.2 7:40 1.4 1.3 2:00 7.4 17:55 9.7 9.0 2:40 0.164 7:40 0.248 0.214 0.214 0.00
3/31/2018 1:25 1.2 9:20 1.4 1.3 1:55 7.8 11:40 10.2 9.0 0:15 0.164 9:15 0.254 0.211 0.211 0.00
ReportAvg 1.3 9.0 0.203
ReportTotal 6.289 2.33
ADS Environmental Services
Pipe Height: 8.00
REN_MH4646\mp1\DFINAL (inches) REN_MH4646\mp1\VFINAL (feet/sec) REN_MH4646\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 0:30 1.2 7:55 1.4 1.3 2:55 7.2 16:25 10.4 8.9 4:00 0.155 8:50 0.257 0.206 0.206 0.10
4/2/2018 23:50 1.1 17:15 1.4 1.3 2:30 7.1 17:20 10.5 8.7 23:50 0.154 17:20 0.261 0.201 0.201 0.00
4/3/2018 22:45 1.1 6:00 1.4 1.3 2:00 6.6 10:45 10.1 8.7 2:00 0.142 6:00 0.233 0.195 0.195 0.00
4/4/2018 22:45 1.2 19:40 1.4 1.3 1:30 6.9 18:05 9.7 8.8 0:10 0.154 17:20 0.232 0.196 0.196 0.39
4/5/2018 23:50 1.1 3:25 1.3 1.3 1:45 7.1 18:25 10.4 8.9 2:35 0.149 18:25 0.223 0.195 0.195 0.25
4/6/2018 13:15 1.1 2:50 1.3 1.2 1:50 7.3 8:25 10.1 8.9 23:45 0.153 6:20 0.225 0.189 0.189 0.00
4/7/2018 20:45 1.0 5:55 1.3 1.2 0:20 7.5 14:40 10.4 9.2 20:45 0.153 8:50 0.245 0.190 0.190 0.88
4/8/2018 1:15 1.0 9:20 1.4 1.3 2:30 8.2 13:00 10.9 9.4 1:15 0.141 16:30 0.259 0.213 0.213 0.45
4/9/2018 20:30 1.2 6:25 1.4 1.3 2:15 8.1 17:00 10.3 9.2 2:15 0.185 17:00 0.247 0.216 0.216 0.00
4/10/2018 23:35 1.2 8:05 1.4 1.3 2:40 8.2 12:30 10.0 9.2 2:45 0.181 8:05 0.264 0.217 0.217 0.23
4/11/2018 19:25 1.2 8:00 1.4 1.3 2:45 7.9 21:15 10.6 9.5 2:45 0.181 8:00 0.264 0.225 0.225 0.31
4/12/2018 0:35 1.2 4:55 1.5 1.3 1:50 8.1 13:25 10.3 9.4 1:50 0.179 7:00 0.273 0.227 0.227 0.11
4/13/2018 21:00 1.3 21:20 1.4 1.3 1:30 8.0 15:20 10.7 9.3 1:40 0.184 15:20 0.264 0.223 0.223 0.51
4/14/2018 11:50 1.1 22:45 1.5 1.3 1:55 8.7 17:15 11.4 9.9 0:40 0.185 22:25 0.302 0.235 0.235 1.52
4/15/2018 13:25 1.2 3:40 1.5 1.4 22:00 9.6 13:20 11.3 10.3 19:15 0.216 18:40 0.285 0.252 0.252 0.21
4/16/2018 0:30 1.2 20:05 1.5 1.4 1:55 9.5 14:30 11.4 10.2 0:30 0.203 20:05 0.309 0.264 0.264 0.71
4/17/2018 21:15 1.3 8:35 1.5 1.4 23:45 9.7 19:00 10.8 10.2 22:25 0.235 17:10 0.305 0.272 0.272 0.01
4/18/2018 21:35 1.3 4:30 1.5 1.4 2:40 9.3 19:30 10.6 10.0 1:05 0.220 7:35 0.292 0.261 0.261 0.12
4/19/2018 2:45 1.3 5:35 1.5 1.4 1:25 9.3 12:40 10.6 9.9 2:45 0.212 5:40 0.290 0.252 0.252 0.00
4/20/2018 23:25 1.2 23:30 1.4 1.4 2:05 9.0 23:25 11.0 9.8 3:00 0.208 7:50 0.271 0.240 0.240 0.00
4/21/2018 13:20 1.3 23:55 1.4 1.3 4:00 8.8 18:30 11.3 9.8 4:25 0.202 18:30 0.280 0.237 0.237 0.05
4/22/2018 11:05 1.2 7:40 1.5 1.4 2:40 8.8 16:45 11.0 9.9 1:20 0.207 7:40 0.277 0.244 0.244 0.00
ReportAvg 1.3 9.4 0.225
ReportTotal 4.951 5.85
REN_MH5302
Located At: Royal Hills and SE Harrington Pl S (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 19.88”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots below the Froude =1 curve indicating subcritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 5.87 2.33 0.826 30%
Maximum 13.86 5.18 5.184 70%
Average 9.08 3.54 2.169 46%
Latitude: 47.471174°
Longitude:-122.180840°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Off trail. Confirmation information available from ADS.
Moderate, smooth flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Access via trail going under power lines, off main
road.
Sensors / Devices:
14.00'' x 14.00''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4)
Pipe Size (HxW)
11:04:00 AM
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
10.00''
Velocity Sensor Offset (in)
~4.63 FPS .50''
Temporary
14.00'' x 14.00''
REN_MH5302
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
Acces Via Royal Hills + SE Harrington Pl S
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Special Installation
Manhole #
Installation Date:
12.20.17
Upstream 0-5 FT Manhole
MH3216 Other
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
-
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
PVC
20''
NormalVented
20''
Additional Photos
Flow Direction
Monitoring Point
Location
Upstream Downstream Side Inlet
Top Down Location
ADS Environmental Services
Pipe Height: 19.88
REN_MH5302\mp1\DFINAL (inches) REN_MH5302\mp1\VFINAL (feet/sec) REN_MH5302\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 3:50 8.2 9:25 9.9 9.3 2:55 3.4 9:25 4.1 3.7 4:40 1.804 9:25 2.735 2.301 2.301 0.10
12/23/2017 5:30 7.8 10:55 9.8 9.0 6:40 3.3 14:40 4.0 3.6 5:45 1.619 12:45 2.606 2.158 2.158 0.00
12/24/2017 4:45 7.4 11:25 9.8 8.7 3:50 3.1 11:15 4.1 3.6 4:40 1.460 11:25 2.669 2.050 2.050 0.00
12/25/2017 5:25 7.3 12:15 9.5 8.5 7:05 3.1 16:30 3.9 3.5 5:00 1.419 16:30 2.433 1.956 1.956 0.14
12/26/2017 4:30 7.3 11:55 9.4 8.5 4:10 3.1 11:50 3.9 3.5 4:15 1.383 11:50 2.447 1.948 1.948 0.17
12/27/2017 4:10 7.2 12:20 9.3 8.4 4:05 3.0 12:20 3.8 3.5 4:10 1.337 12:20 2.395 1.895 1.895 0.00
12/28/2017 4:20 7.2 23:55 9.6 8.6 6:30 3.0 19:35 4.0 3.5 4:15 1.323 19:35 2.550 2.004 2.004 0.25
12/29/2017 0:55 9.1 12:20 13.9 11.9 2:40 3.5 12:00 5.2 4.5 2:40 2.144 12:00 5.184 3.849 3.849 1.57
12/30/2017 23:55 10.2 0:35 11.4 10.7 21:10 3.6 0:35 4.5 4.1 21:10 2.613 0:35 3.577 3.022 3.022 0.02
12/31/2017 5:05 9.7 12:10 10.6 10.1 6:40 3.6 17:15 4.2 3.8 6:40 2.345 17:15 2.999 2.649 2.649 0.00
ReportAvg 9.4 3.7 2.383
ReportTotal 23.83 2.25
ADS Environmental Services
Pipe Height: 19.88
REN_MH5302\mp1\DFINAL (inches) REN_MH5302\mp1\VFINAL (feet/sec) REN_MH5302\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 6:00 8.6 13:30 10.3 9.6 6:50 3.2 13:30 3.9 3.7 6:50 1.778 13:30 2.766 2.369 2.369 0.00
1/2/2018 4:35 8.1 20:55 9.8 9.2 3:10 3.1 12:15 3.9 3.5 3:10 1.641 20:55 2.588 2.136 2.136 0.01
1/3/2018 4:40 7.7 20:50 9.6 8.9 3:10 3.1 18:55 3.9 3.5 3:10 1.541 18:55 2.470 2.032 2.032 0.00
1/4/2018 4:10 7.4 18:40 9.5 8.6 3:30 3.1 21:40 3.9 3.5 3:30 1.446 21:40 2.430 1.954 1.954 0.09
1/5/2018 4:20 7.4 18:35 9.7 8.9 3:45 3.1 18:35 3.9 3.5 3:45 1.446 18:35 2.534 2.076 2.076 0.42
1/6/2018 4:10 8.4 10:35 10.3 9.5 4:25 3.3 12:00 4.1 3.7 4:25 1.776 12:00 2.894 2.393 2.393 0.24
1/7/2018 5:35 8.2 20:35 10.4 9.5 6:05 3.2 18:50 4.1 3.7 5:25 1.718 20:35 2.868 2.366 2.366 0.38
1/8/2018 4:20 9.0 19:55 10.2 9.7 3:05 3.4 21:45 4.0 3.8 4:20 2.035 19:55 2.777 2.475 2.475 0.14
1/9/2018 0:25 9.5 19:10 10.5 9.9 0:25 3.6 20:50 4.2 3.9 0:25 2.309 20:50 2.970 2.648 2.648 0.46
1/10/2018 3:55 8.8 21:25 10.0 9.6 5:00 3.3 12:25 4.0 3.7 3:20 1.933 21:25 2.694 2.395 2.395 0.22
1/11/2018 4:25 9.1 15:20 13.2 11.1 2:15 3.4 14:40 5.1 4.3 2:15 2.102 14:50 4.733 3.401 3.401 1.04
1/12/2018 23:55 10.3 0:00 11.1 10.6 14:55 4.0 0:10 4.4 4.2 14:55 2.853 0:00 3.427 3.059 3.059 0.20
1/13/2018 4:20 9.9 10:20 10.8 10.2 4:20 3.8 11:55 4.3 4.0 4:20 2.560 10:20 3.144 2.781 2.781 0.02
1/14/2018 4:35 9.3 10:30 10.4 9.8 3:55 3.4 10:25 4.2 3.8 3:55 2.151 10:25 3.005 2.542 2.542 0.00
1/15/2018 4:45 8.6 19:00 10.0 9.4 3:55 3.4 20:30 4.0 3.7 3:55 1.901 20:30 2.681 2.335 2.335 0.04
1/16/2018 4:30 8.6 9:05 10.0 9.4 3:15 3.3 6:50 4.1 3.7 3:15 1.892 6:50 2.736 2.344 2.344 0.26
1/17/2018 4:45 8.2 20:00 11.6 9.6 3:35 3.3 20:05 4.6 3.8 4:20 1.760 20:05 3.669 2.447 2.447 0.79
1/18/2018 2:50 10.1 7:25 11.6 10.7 23:15 3.9 7:10 4.5 4.2 2:50 2.755 7:25 3.635 3.120 3.120 0.40
1/19/2018 23:20 9.8 8:40 10.5 10.1 23:15 3.8 6:45 4.2 4.0 23:15 2.528 8:40 3.009 2.747 2.747 0.10
1/20/2018 3:45 9.4 10:20 10.4 9.9 3:10 3.6 11:55 4.1 3.9 3:10 2.265 11:55 2.941 2.593 2.593 0.10
1/21/2018 5:10 8.8 17:15 10.3 9.7 4:35 3.4 10:40 4.1 3.8 4:35 1.996 17:15 2.857 2.466 2.466 0.16
1/22/2018 4:05 8.7 7:30 10.4 9.7 2:10 3.3 7:10 4.2 3.8 2:10 1.891 7:10 2.962 2.511 2.511 0.34
1/23/2018 4:25 8.7 19:35 11.4 10.0 3:30 3.4 19:55 4.5 3.9 3:30 1.937 19:55 3.515 2.699 2.699 0.79
1/24/2018 3:55 10.4 19:45 11.7 10.8 13:15 3.9 19:50 4.5 4.3 13:15 2.862 19:50 3.744 3.198 3.198 0.51
1/25/2018 23:55 10.2 7:40 10.8 10.5 10:55 3.8 7:40 4.3 4.1 10:55 2.738 7:40 3.229 2.959 2.959 0.14
1/26/2018 3:15 9.8 18:25 10.7 10.2 2:25 3.8 22:50 4.3 4.0 2:25 2.516 22:50 3.111 2.800 2.800 0.36
1/27/2018 0:15 10.3 7:55 12.2 11.2 23:25 3.9 11:00 4.7 4.3 0:15 2.843 11:05 4.073 3.388 3.388 0.61
1/28/2018 23:50 10.1 17:15 10.7 10.4 23:45 3.7 11:20 4.3 4.0 23:50 2.515 11:20 3.157 2.872 2.872 0.07
1/29/2018 4:15 9.6 16:55 13.0 10.9 3:40 3.2 20:20 4.7 3.9 3:40 2.096 20:20 4.253 2.997 2.997 0.90
1/30/2018 23:55 10.1 0:20 11.3 10.6 20:40 3.9 0:20 4.4 4.1 23:50 2.715 0:20 3.463 2.992 2.992 0.00
1/31/2018 23:55 9.7 19:40 10.4 10.1 23:10 3.5 8:05 4.1 3.8 23:10 2.342 8:05 2.890 2.627 2.627 0.00
ReportAvg 9.9 3.9 2.636
ReportTotal 81.72 8.79
ADS Environmental Services
Pipe Height: 19.88
REN_MH5302\mp1\DFINAL (inches) REN_MH5302\mp1\VFINAL (feet/sec) REN_MH5302\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 3:20 8.9 22:25 11.3 9.9 3:25 3.3 22:30 4.2 3.7 3:20 1.957 22:25 3.346 2.519 2.519 0.66
2/2/2018 23:55 10.1 8:15 10.8 10.5 22:25 3.7 13:35 4.2 3.9 23:50 2.580 13:35 3.114 2.844 2.844 0.04
2/3/2018 4:50 9.4 21:30 10.6 10.1 5:50 3.5 18:10 4.1 3.8 5:50 2.208 18:10 2.978 2.632 2.632 0.31
2/4/2018 5:15 9.4 11:45 10.8 10.2 17:15 3.4 11:35 4.0 3.7 5:15 2.206 11:50 2.944 2.568 2.568 0.02
2/5/2018 4:30 8.9 8:05 10.5 9.6 1:35 3.3 8:00 3.8 3.5 4:00 1.995 8:00 2.773 2.290 2.290 0.04
2/6/2018 4:15 8.6 20:40 10.2 9.2 3:25 3.2 20:40 3.7 3.5 3:25 1.836 20:40 2.586 2.132 2.132 0.00
2/7/2018 4:25 8.4 7:55 10.1 9.0 2:45 3.0 19:50 3.7 3.5 2:45 1.669 19:50 2.500 2.058 2.058 0.00
2/8/2018 4:10 8.1 21:05 9.8 8.9 4:40 3.1 21:05 3.6 3.4 4:35 1.614 21:05 2.412 1.999 1.999 0.09
2/9/2018 4:25 7.9 9:20 9.6 8.8 4:15 3.0 8:55 3.6 3.4 4:15 1.542 9:25 2.292 1.945 1.945 0.01
2/10/2018 5:30 7.7 10:40 10.1 8.7 7:05 2.9 10:45 3.6 3.4 7:05 1.468 10:45 2.462 1.923 1.923 0.01
2/11/2018 6:10 7.6 12:20 9.7 8.7 5:25 2.8 15:45 3.6 3.4 5:25 1.351 12:25 2.349 1.902 1.902 0.00
2/12/2018 3:55 7.2 20:05 9.4 8.4 5:10 2.5 20:05 3.5 3.3 4:00 1.155 20:05 2.233 1.788 1.788 0.00
2/13/2018 4:10 7.0 18:55 9.3 8.4 3:30 2.5 18:55 3.5 3.2 3:30 1.079 18:55 2.183 1.756 1.756 0.17
2/14/2018 4:15 7.8 20:10 9.4 8.6 4:10 2.8 10:30 3.6 3.3 4:10 1.360 20:10 2.249 1.870 1.870 0.15
2/15/2018 4:25 7.2 19:05 9.3 8.5 3:50 2.6 22:20 3.5 3.2 4:00 1.192 22:25 2.150 1.793 1.793 0.00
2/16/2018 4:05 7.3 8:05 9.3 8.5 3:25 2.5 9:55 3.6 3.3 3:25 1.140 19:45 2.179 1.824 1.824 0.15
2/17/2018 4:45 7.3 10:35 10.5 9.0 4:25 2.5 12:10 3.9 3.4 4:25 1.140 12:10 2.788 2.052 2.052 0.32
2/18/2018 6:00 7.9 10:30 10.1 8.9 5:40 3.0 12:45 3.7 3.4 5:40 1.488 10:30 2.527 2.011 2.011 0.01
2/19/2018 4:05 7.6 12:45 10.1 8.6 4:15 2.9 12:45 3.7 3.3 4:15 1.379 12:45 2.526 1.872 1.872 0.00
2/20/2018 4:05 7.3 19:05 9.3 8.4 3:10 2.7 20:35 3.6 3.3 4:05 1.204 19:05 2.145 1.796 1.796 0.00
2/21/2018 4:15 6.9 18:40 9.1 8.3 2:50 2.7 20:10 3.6 3.3 3:50 1.131 22:20 2.150 1.769 1.769 0.00
2/22/2018 4:25 6.9 20:25 9.1 8.3 4:20 2.6 20:25 3.6 3.2 4:20 1.095 20:25 2.169 1.734 1.734 0.07
2/23/2018 4:10 6.8 20:20 8.9 8.2 3:55 2.5 12:45 3.6 3.2 3:55 1.033 12:45 2.030 1.714 1.714 0.01
2/24/2018 5:45 6.9 10:20 9.6 8.3 7:20 2.6 12:00 3.6 3.2 5:45 1.111 10:25 2.340 1.738 1.738 0.13
2/25/2018 5:15 6.8 10:30 9.7 8.3 5:20 2.6 13:00 3.7 3.3 5:20 1.083 13:00 2.365 1.802 1.802 0.11
2/26/2018 4:25 6.7 20:40 9.0 8.2 4:40 2.6 20:30 3.6 3.2 4:40 1.048 20:50 2.073 1.710 1.710 0.00
2/27/2018 3:40 6.6 20:55 9.3 8.2 4:20 2.5 20:55 3.6 3.2 4:20 0.997 20:55 2.223 1.693 1.693 0.19
2/28/2018 4:05 6.5 18:45 9.7 8.3 4:25 2.5 21:30 3.7 3.3 4:05 0.972 18:45 2.374 1.764 1.764 0.35
ReportAvg 8.8 3.4 1.982
ReportTotal 55.50 2.84
ADS Environmental Services
Pipe Height: 19.88
REN_MH5302\mp1\DFINAL (inches) REN_MH5302\mp1\VFINAL (feet/sec) REN_MH5302\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 4:25 7.3 20:50 9.5 8.5 3:20 2.7 20:55 3.7 3.3 3:20 1.222 20:55 2.367 1.854 1.854 0.01
3/2/2018 3:45 7.1 8:20 9.6 8.5 4:30 2.7 9:55 3.6 3.3 3:30 1.209 8:20 2.301 1.859 1.859 0.07
3/3/2018 4:30 7.0 10:10 9.7 8.5 4:40 2.7 12:45 3.6 3.3 4:30 1.126 10:10 2.332 1.827 1.827 0.00
3/4/2018 5:30 6.7 21:25 9.8 8.4 5:35 2.6 21:30 3.7 3.3 5:35 1.042 21:25 2.424 1.806 1.806 0.12
3/5/2018 4:15 6.7 19:15 9.3 8.3 4:40 2.6 10:10 3.6 3.3 4:15 1.041 19:15 2.167 1.749 1.749 0.00
3/6/2018 4:05 6.6 20:40 9.2 8.2 4:20 2.5 20:35 3.6 3.2 4:20 0.970 20:40 2.216 1.718 1.718 0.00
3/7/2018 4:10 6.6 20:00 9.1 8.2 3:05 2.6 8:25 3.6 3.2 4:15 1.036 20:00 2.149 1.705 1.705 0.03
3/8/2018 4:05 6.5 20:45 9.6 8.2 3:05 2.5 20:45 3.6 3.2 4:05 0.972 20:45 2.340 1.716 1.716 0.37
3/9/2018 4:10 6.5 12:45 9.1 8.2 2:35 2.5 22:00 3.6 3.2 4:00 0.971 12:45 2.124 1.694 1.694 0.00
3/10/2018 5:20 6.4 10:25 9.4 8.1 5:05 2.4 11:50 3.6 3.2 5:05 0.931 11:50 2.262 1.683 1.683 0.00
3/11/2018 5:45 6.3 20:15 9.4 8.1 4:10 2.4 13:55 3.6 3.2 4:10 0.886 20:15 2.274 1.684 1.684 0.00
3/12/2018 3:25 6.2 20:05 9.1 8.0 3:05 2.5 20:05 3.6 3.2 3:05 0.900 20:05 2.143 1.628 1.628 0.00
3/13/2018 3:00 6.2 19:00 9.5 8.0 4:15 2.4 19:00 3.7 3.2 3:05 0.886 19:00 2.362 1.664 1.664 0.31
3/14/2018 3:10 6.6 20:00 9.2 8.2 4:05 2.6 17:50 3.6 3.3 3:00 1.023 20:00 2.177 1.717 1.717 0.04
3/15/2018 3:00 6.4 19:55 9.3 8.1 3:00 2.5 19:55 3.6 3.2 3:00 0.956 19:55 2.221 1.675 1.675 0.00
3/16/2018 2:40 6.3 8:15 8.9 8.0 3:10 2.5 20:50 3.5 3.2 3:10 0.936 8:15 2.022 1.632 1.632 0.00
3/17/2018 4:00 6.2 10:45 9.2 7.9 3:50 2.5 14:20 3.6 3.2 3:50 0.888 10:45 2.141 1.627 1.627 0.00
3/18/2018 4:20 6.2 19:20 9.2 7.9 5:00 2.3 12:10 3.6 3.2 5:00 0.833 19:20 2.180 1.629 1.629 0.00
3/19/2018 2:55 5.9 19:55 9.0 7.8 2:40 2.4 20:30 3.6 3.1 2:40 0.831 19:55 2.095 1.572 1.572 0.00
3/20/2018 3:35 6.0 19:00 8.9 7.8 3:35 2.4 20:35 3.6 3.1 3:35 0.826 19:00 2.093 1.543 1.543 0.00
3/21/2018 3:50 6.0 20:50 8.9 7.7 5:05 2.5 20:50 3.5 3.1 3:50 0.866 20:50 2.082 1.539 1.539 0.10
3/22/2018 3:40 6.1 19:50 9.1 8.1 4:50 2.5 13:20 3.7 3.2 3:10 0.899 21:45 2.190 1.688 1.688 0.48
3/23/2018 3:05 6.3 12:45 9.9 8.3 2:45 2.5 12:50 3.7 3.3 2:45 0.936 12:45 2.450 1.767 1.767 0.31
3/24/2018 3:10 7.0 9:30 10.1 8.6 3:25 2.6 9:20 3.9 3.4 3:00 1.132 9:20 2.669 1.916 1.916 0.28
3/25/2018 4:20 7.0 11:35 9.7 8.5 4:45 2.8 19:35 3.7 3.4 4:45 1.187 11:35 2.413 1.855 1.855 0.01
3/26/2018 3:05 6.7 18:05 9.6 8.3 2:50 2.6 18:05 3.7 3.3 2:50 1.044 18:05 2.357 1.796 1.796 0.17
3/27/2018 2:50 6.9 19:50 9.4 8.3 2:50 2.6 9:45 3.7 3.3 2:50 1.084 19:50 2.304 1.768 1.768 0.02
3/28/2018 3:15 6.7 19:20 9.2 8.3 2:55 2.6 7:30 3.6 3.2 3:20 1.030 19:10 2.161 1.732 1.732 0.01
3/29/2018 3:10 6.6 18:45 9.1 8.1 3:25 2.5 19:00 3.6 3.3 3:20 0.976 18:45 2.171 1.704 1.704 0.00
3/30/2018 3:20 6.5 19:30 9.1 8.0 3:15 2.5 7:40 3.6 3.3 3:15 0.955 19:30 2.148 1.676 1.676 0.00
3/31/2018 4:35 6.3 8:50 9.3 8.0 3:40 2.5 10:25 3.7 3.3 4:25 0.954 8:50 2.284 1.684 1.684 0.00
ReportAvg 8.2 3.2 1.713
ReportTotal 53.11 2.33
ADS Environmental Services
Pipe Height: 19.88
REN_MH5302\mp1\DFINAL (inches) REN_MH5302\mp1\VFINAL (feet/sec) REN_MH5302\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 5:15 6.2 11:15 9.6 8.0 5:30 2.6 11:20 3.7 3.3 4:50 0.933 11:20 2.391 1.694 1.694 0.10
4/2/2018 3:35 6.2 19:45 8.9 7.8 3:15 2.6 19:55 3.6 3.2 3:40 0.938 19:45 2.107 1.611 1.611 0.00
4/3/2018 2:50 6.1 19:35 9.0 7.8 3:05 2.6 20:10 3.6 3.2 2:50 0.913 19:35 2.113 1.571 1.571 0.00
4/4/2018 3:35 6.1 21:15 9.1 7.9 3:25 2.4 21:20 3.6 3.2 3:25 0.850 21:15 2.163 1.632 1.632 0.39
4/5/2018 3:05 6.3 18:40 9.5 8.1 4:05 2.6 18:40 3.7 3.3 3:20 0.966 18:40 2.353 1.700 1.700 0.25
4/6/2018 3:15 6.7 7:45 9.2 8.2 3:10 2.7 20:15 3.6 3.3 3:10 1.067 7:45 2.177 1.743 1.743 0.00
4/7/2018 3:00 6.8 10:10 10.7 9.5 3:00 2.7 10:00 4.2 3.7 3:00 1.119 10:10 3.118 2.416 2.416 0.88
4/8/2018 3:40 8.5 11:45 10.9 9.9 3:05 3.3 9:50 4.3 3.8 3:40 1.850 11:50 3.196 2.595 2.595 0.45
4/9/2018 3:40 8.7 20:05 10.2 9.5 23:40 3.2 20:05 3.9 3.6 23:40 1.855 20:05 2.712 2.304 2.304 0.00
4/10/2018 3:20 8.2 20:15 10.1 9.3 7:35 3.2 18:20 3.9 3.5 3:25 1.719 18:25 2.660 2.169 2.169 0.23
4/11/2018 3:35 7.9 20:05 10.2 9.1 3:05 3.1 20:00 3.9 3.5 3:05 1.559 20:00 2.745 2.120 2.120 0.31
4/12/2018 3:10 8.3 18:20 10.2 9.2 2:45 3.2 20:20 3.8 3.5 2:45 1.740 18:20 2.610 2.162 2.162 0.11
4/13/2018 3:15 8.0 16:50 10.1 9.2 1:55 3.2 21:00 3.8 3.5 1:55 1.654 16:50 2.611 2.166 2.166 0.51
4/14/2018 3:35 9.4 19:50 13.0 11.2 4:40 3.4 21:30 4.9 4.2 4:40 2.173 19:50 4.537 3.334 3.334 1.52
4/15/2018 23:55 10.5 0:45 12.8 11.9 23:00 4.0 0:25 4.8 4.4 23:15 2.940 0:25 4.436 3.747 3.747 0.21
4/16/2018 1:45 10.4 19:35 12.1 11.1 4:45 3.8 17:25 4.5 4.2 4:45 2.765 15:55 3.836 3.215 3.215 0.71
4/17/2018 23:55 10.2 7:15 11.3 10.6 23:25 3.7 5:30 4.3 4.0 23:25 2.599 7:20 3.313 2.965 2.965 0.01
4/18/2018 23:55 9.5 6:25 10.6 10.2 23:45 3.5 6:25 4.2 3.8 23:45 2.199 6:25 3.061 2.661 2.661 0.12
4/19/2018 3:15 8.9 6:20 10.4 9.7 23:55 3.4 6:25 3.9 3.6 23:55 1.980 6:25 2.796 2.387 2.387 0.00
4/20/2018 3:15 8.3 9:10 10.1 9.2 3:30 3.1 19:35 4.0 3.5 3:30 1.700 19:35 2.713 2.156 2.156 0.00
4/21/2018 4:30 8.0 11:20 10.2 9.0 5:05 3.1 8:25 3.8 3.5 4:30 1.607 8:25 2.606 2.068 2.068 0.05
4/22/2018 3:50 7.9 9:10 10.0 8.9 5:05 2.9 10:40 3.7 3.4 5:05 1.430 10:40 2.544 2.008 2.008 0.00
ReportAvg 9.3 3.6 2.292
ReportTotal 50.42 5.85
REN_MH5505
Located At: 4444 NE Sunset Blvd (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 10”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.29 4.30 0.132 13%
Maximum 5.86 8.11 0.954 59%
Average 1.83 6.45 0.293 18%
Latitude: 47.504955°
Longitude:-122.159403°
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
No
Vitrified Clay Pipe
NormalSteel
Fair
Active Connections
None.
Air Quality:
Communication Type
Normal
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Brick Good
11'
Manhole Condition:
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
1.38"
Peak Velocity (fps)
Silt (in)
11:50:00 AM 10.00" x 10.00"Site Sketch Profile View or Photo
Straight, Some Ripples
0 - 5 psi
Depth of Flow (Wet DOF) (in)
0.38''
Velocity Sensor Offset (in)
3.27'
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, December 13, 2017
Access
Temporary
10.00" x 10.00"
Traffic
MH5505 Residential / Commercial
Map
Installation Type:
Monitoring Location (Sensors):
REN_MH5505
TRITON+
System Characteristics
Location Type
Pipe ShapeSite located between trees, park in lot
Renton.Carollo.I&I.WA17
NoneDrive
Site Access Details:
Site Address /Location:
Site Name
4444 NE Sunset Blvd
Flow Monitoring
Site Report
Additional Photos
Flow Direction
Monitoring Point
Inlet Outlet
Top Down Location Location Map
Utility Map KEY
ADS Environmental Services
Pipe Height: 10.00
REN_MH5505\mp1\DFINAL (inches) REN_MH5505\mp1\VFINAL (feet/sec) REN_MH5505\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
12/22/2017 3:30 1.6 10:55 2.0 1.8 3:30 6.3 11:30 7.2 6.7 3:30 0.231 10:55 0.369 0.296 0.296
12/23/2017 5:40 1.5 10:55 2.0 1.8 5:25 6.1 9:45 7.2 6.6 5:35 0.214 10:55 0.365 0.276 0.276
12/24/2017 4:30 1.5 11:10 2.0 1.7 5:45 6.0 9:55 7.1 6.5 3:50 0.204 11:05 0.362 0.262 0.262
12/25/2017 7:30 1.5 12:25 2.0 1.7 4:15 5.7 12:20 7.2 6.4 2:45 0.205 12:20 0.356 0.252 0.252
12/26/2017 8:00 1.5 10:20 1.9 1.7 5:25 5.7 10:15 6.9 6.3 5:55 0.206 10:15 0.328 0.242 0.242
12/27/2017 7:05 1.5 11:10 1.9 1.6 2:40 5.7 19:00 6.8 6.2 4:30 0.205 11:10 0.311 0.234 0.234
12/28/2017 7:50 1.5 21:20 1.9 1.7 4:10 5.6 14:35 6.9 6.2 4:10 0.201 21:20 0.313 0.238 0.238
12/29/2017 1:55 1.6 17:15 2.7 2.3 0:55 6.0 12:00 7.9 7.2 1:30 0.214 17:15 0.601 0.447 0.447
12/30/2017 23:55 2.1 10:10 2.4 2.3 23:45 7.1 12:00 7.8 7.3 23:55 0.370 0:40 0.502 0.447 0.447
12/31/2017 23:20 1.9 10:40 2.3 2.1 23:25 6.8 10:35 7.4 7.1 23:25 0.324 10:35 0.450 0.369 0.369
ReportAvg 1.9 6.7 0.306
ReportTotal 3.063
ADS Environmental Services
Pipe Height: 10.00
REN_MH5505\mp1\DFINAL (inches) REN_MH5505\mp1\VFINAL (feet/sec) REN_MH5505\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
1/1/2018 5:15 1.8 19:45 2.2 1.9 5:45 6.5 19:45 7.3 6.8 7:45 0.270 19:45 0.423 0.327 0.327
1/2/2018 3:35 1.6 20:40 2.0 1.8 3:15 6.2 19:25 7.2 6.6 3:25 0.231 20:40 0.362 0.291 0.291
1/3/2018 4:30 1.6 8:20 5.9 1.8 8:35 4.3 7:40 7.1 6.4 8:40 0.207 8:20 0.954 0.274 0.274
1/4/2018 2:00 1.6 18:50 2.0 1.7 2:30 5.9 20:10 6.9 6.4 5:00 0.216 18:50 0.347 0.254 0.254
1/5/2018 0:40 1.6 18:40 2.0 1.7 3:25 5.7 10:30 6.8 6.4 1:35 0.221 18:40 0.337 0.262 0.262
1/6/2018 3:30 1.6 10:20 2.1 1.9 4:05 6.1 11:30 7.3 6.7 4:05 0.227 10:20 0.385 0.313 0.313
1/7/2018 6:25 1.6 22:00 2.1 1.9 5:00 6.2 22:00 7.3 6.8 6:25 0.237 22:00 0.386 0.319 0.319
1/8/2018 3:10 1.8 7:45 2.1 2.0 1:50 6.6 10:40 7.3 6.9 3:10 0.286 7:50 0.386 0.341 0.341
1/9/2018 2:55 1.9 22:40 2.4 2.1 2:55 6.6 18:40 7.4 7.1 2:55 0.300 22:40 0.464 0.378 0.378
1/10/2018 3:15 2.0 7:25 2.2 2.1 4:05 6.8 7:25 7.3 7.1 3:15 0.341 7:25 0.429 0.374 0.374
1/11/2018 3:05 1.9 18:45 3.0 2.3 4:05 6.7 19:30 7.9 7.4 3:05 0.312 18:45 0.680 0.458 0.458
1/12/2018 23:55 2.3 8:30 2.6 2.4 23:55 7.4 8:30 7.7 7.6 23:55 0.461 8:30 0.551 0.500 0.500
1/13/2018 23:55 2.2 10:55 2.4 2.3 23:55 7.3 10:55 7.6 7.4 23:55 0.413 10:55 0.504 0.454 0.454
1/14/2018 5:10 2.1 10:20 2.3 2.2 5:10 7.0 10:20 7.5 7.2 5:10 0.366 10:20 0.472 0.409 0.409
1/15/2018 3:10 1.9 19:30 2.2 2.1 3:10 6.7 19:30 7.4 7.0 3:10 0.311 19:30 0.435 0.370 0.370
1/16/2018 2:35 1.8 9:35 2.2 2.0 2:35 6.5 9:35 7.3 7.0 2:35 0.281 9:35 0.419 0.354 0.354
1/17/2018 3:55 1.8 19:50 2.4 2.1 3:55 6.6 19:50 7.5 7.0 3:55 0.289 19:50 0.487 0.369 0.369
1/18/2018 2:50 2.2 6:40 2.5 2.3 23:50 7.2 18:10 7.6 7.4 2:50 0.404 6:40 0.507 0.455 0.455
1/19/2018 23:15 2.0 8:30 2.4 2.1 23:35 6.9 8:35 7.5 7.2 23:15 0.349 8:30 0.475 0.396 0.396
1/20/2018 6:45 1.9 11:10 2.3 2.0 4:35 6.7 11:10 7.4 7.0 6:45 0.308 11:10 0.463 0.360 0.360
1/21/2018 5:15 1.7 12:00 2.3 2.0 3:55 6.4 12:00 7.2 6.9 3:55 0.264 12:00 0.432 0.339 0.339
1/22/2018 2:20 1.7 18:40 2.1 1.9 2:30 6.4 20:35 7.2 6.8 2:30 0.249 18:40 0.399 0.327 0.327
1/23/2018 3:20 1.7 19:20 2.4 2.0 3:15 6.3 19:15 7.4 6.9 3:15 0.250 19:20 0.479 0.354 0.354
1/24/2018 2:50 2.2 20:55 2.5 2.4 2:30 7.2 23:25 7.6 7.4 2:50 0.413 20:55 0.527 0.474 0.474
1/25/2018 23:55 2.2 8:05 2.4 2.3 23:55 7.2 7:45 7.6 7.4 23:55 0.407 8:00 0.503 0.458 0.458
1/26/2018 3:45 2.0 8:55 2.3 2.2 3:05 6.8 13:55 7.5 7.2 3:30 0.350 8:50 0.454 0.405 0.405
1/27/2018 0:50 2.1 12:50 2.6 2.4 0:50 7.1 11:30 7.8 7.5 0:50 0.384 10:45 0.560 0.491 0.491
1/28/2018 23:55 2.1 11:05 2.4 2.3 6:30 7.1 11:00 7.7 7.3 23:55 0.370 11:00 0.508 0.442 0.442
1/29/2018 3:30 2.0 20:35 2.7 2.3 2:50 6.8 19:35 8.0 7.3 3:30 0.332 20:35 0.590 0.444 0.444
1/30/2018 23:55 2.1 7:05 2.5 2.4 12:40 7.2 8:25 7.7 7.4 23:55 0.392 7:05 0.531 0.475 0.475
1/31/2018 23:35 1.9 7:10 2.3 2.1 23:55 6.8 8:20 7.4 7.1 23:35 0.328 7:10 0.454 0.378 0.378
ReportAvg 2.1 7.1 0.382
ReportTotal 11.84
ADS Environmental Services
Pipe Height: 10.00
REN_MH5505\mp1\DFINAL (inches) REN_MH5505\mp1\VFINAL (feet/sec) REN_MH5505\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
2/1/2018 3:45 1.8 21:10 2.3 2.0 2:40 6.5 21:55 7.4 6.9 3:45 0.281 21:55 0.454 0.345 0.345
2/2/2018 4:15 2.0 8:40 2.4 2.1 4:10 6.9 8:45 7.4 7.2 4:10 0.347 8:40 0.476 0.393 0.393
2/3/2018 4:00 1.9 10:35 2.3 2.1 4:15 6.7 21:30 7.3 7.1 4:10 0.314 10:35 0.461 0.375 0.375
2/4/2018 5:10 1.9 12:05 2.4 2.1 23:25 6.7 12:05 7.5 7.1 23:25 0.325 12:05 0.487 0.387 0.387
2/5/2018 3:40 1.8 18:05 2.1 2.0 3:35 6.5 18:05 7.5 6.9 3:45 0.278 18:05 0.414 0.336 0.336
2/6/2018 3:40 1.7 21:10 2.0 1.8 3:40 6.3 7:20 7.2 6.7 3:40 0.246 21:05 0.368 0.302 0.302
2/7/2018 3:55 1.6 20:25 2.0 1.8 3:50 6.1 9:45 7.1 6.6 3:50 0.220 20:25 0.354 0.276 0.276
2/8/2018 3:55 1.6 18:30 2.0 1.7 3:30 6.0 7:45 7.0 6.4 3:55 0.217 18:30 0.341 0.260 0.260
2/9/2018 2:35 1.6 8:05 1.9 1.7 3:30 5.9 8:05 7.0 6.4 2:35 0.215 8:05 0.337 0.253 0.253
2/10/2018 6:50 1.6 10:25 1.9 1.7 4:25 5.8 10:25 6.8 6.3 5:00 0.217 10:25 0.330 0.252 0.252
2/11/2018 1:10 1.6 11:00 2.0 1.7 5:05 5.6 9:35 6.8 6.3 5:05 0.206 10:55 0.335 0.251 0.251
2/12/2018 2:55 1.5 20:40 1.8 1.6 3:15 5.5 21:25 6.7 6.1 3:15 0.190 20:40 0.288 0.231 0.231
2/13/2018 3:15 1.5 19:50 1.8 1.6 2:30 5.5 19:45 6.8 6.1 3:15 0.185 19:50 0.291 0.225 0.225
2/14/2018 3:35 1.5 19:25 1.9 1.7 2:15 5.6 8:30 6.6 6.1 3:35 0.186 19:25 0.298 0.233 0.233
2/15/2018 3:20 1.6 7:10 1.9 1.7 2:10 5.5 7:10 6.7 6.0 2:10 0.207 7:10 0.312 0.245 0.245
2/16/2018 1:25 1.6 8:00 2.0 1.7 2:30 5.4 7:50 6.5 6.0 1:25 0.200 7:55 0.312 0.245 0.245
2/17/2018 3:05 1.6 11:50 2.0 1.7 4:50 5.5 10:05 6.7 6.0 3:05 0.192 11:50 0.327 0.248 0.248
2/18/2018 3:35 1.6 12:35 1.9 1.7 3:25 5.5 12:40 6.4 5.9 3:25 0.207 12:35 0.306 0.245 0.245
2/19/2018 3:25 1.5 19:10 1.9 1.7 2:55 5.3 19:10 6.6 5.9 3:25 0.187 19:10 0.299 0.234 0.234
2/20/2018 3:30 1.5 8:15 1.8 1.7 3:10 5.4 19:55 6.4 5.8 3:30 0.183 8:15 0.269 0.223 0.223
2/21/2018 3:15 1.5 20:20 1.7 1.6 3:20 5.3 20:20 6.5 5.8 3:20 0.168 20:20 0.268 0.217 0.217
2/22/2018 2:40 1.4 20:15 1.8 1.6 3:20 5.2 13:15 6.4 5.7 2:40 0.165 20:15 0.267 0.211 0.211
2/23/2018 3:10 1.4 8:10 1.7 1.6 3:35 5.1 19:40 6.4 5.7 3:10 0.154 19:45 0.253 0.204 0.204
2/24/2018 4:00 1.4 11:35 1.8 1.6 2:50 5.1 10:20 6.4 5.7 4:00 0.155 11:30 0.275 0.210 0.210
2/25/2018 3:45 1.4 12:55 1.9 1.6 5:05 5.2 15:05 6.4 5.8 3:40 0.159 12:55 0.289 0.218 0.218
2/26/2018 4:05 1.4 20:25 1.7 1.6 4:20 5.1 19:15 6.3 5.7 4:15 0.152 20:25 0.257 0.208 0.208
2/27/2018 3:40 1.4 20:35 1.8 1.6 2:25 5.1 19:00 6.5 5.8 2:25 0.149 20:35 0.272 0.207 0.207
2/28/2018 3:45 1.4 20:40 1.9 1.6 2:45 5.2 20:40 6.6 5.9 2:45 0.160 20:40 0.297 0.218 0.218
ReportAvg 1.7 6.2 0.259
ReportTotal 7.250
ADS Environmental Services
Pipe Height: 10.00
REN_MH5505\mp1\DFINAL (inches) REN_MH5505\mp1\VFINAL (feet/sec) REN_MH5505\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
3/1/2018 3:40 1.5 18:35 1.8 1.6 2:30 5.6 18:30 6.6 6.1 3:40 0.193 18:35 0.290 0.233 0.233
3/2/2018 3:15 1.5 8:45 1.8 1.6 3:25 5.6 8:00 6.7 6.1 3:25 0.192 8:05 0.292 0.234 0.234
3/3/2018 3:15 1.5 10:20 1.9 1.7 4:10 5.5 10:20 6.7 6.1 4:10 0.189 10:20 0.322 0.233 0.233
3/4/2018 4:30 1.5 20:30 1.8 1.6 4:30 5.4 20:30 6.7 6.0 4:30 0.177 20:30 0.292 0.228 0.228
3/5/2018 3:40 1.5 19:45 1.8 1.6 3:40 5.4 19:45 6.7 6.0 3:40 0.172 19:45 0.285 0.221 0.221
3/6/2018 2:35 1.4 20:20 1.7 1.6 2:35 5.3 20:20 6.8 5.9 2:35 0.166 20:20 0.281 0.215 0.215
3/7/2018 3:50 1.4 19:55 1.8 1.6 2:25 5.3 19:50 6.8 6.0 2:25 0.164 19:50 0.285 0.214 0.214
3/8/2018 3:20 1.4 21:10 1.8 1.6 3:15 5.4 21:10 6.8 6.0 3:15 0.162 21:10 0.287 0.212 0.212
3/9/2018 4:30 1.5 8:05 1.8 1.6 2:30 5.5 8:00 6.7 6.0 4:30 0.176 8:05 0.295 0.217 0.217
3/10/2018 3:40 1.4 9:15 1.9 1.6 4:35 5.5 11:05 6.8 6.1 3:35 0.172 11:05 0.309 0.220 0.220
3/11/2018 4:05 1.4 19:30 1.8 1.6 2:45 5.4 19:25 6.7 6.0 4:45 0.166 19:30 0.294 0.218 0.218
3/12/2018 2:10 1.4 20:50 1.8 1.6 2:55 5.3 20:10 6.6 5.9 2:55 0.159 20:50 0.287 0.209 0.209
3/13/2018 2:50 1.4 19:30 1.8 1.6 2:50 5.3 19:30 6.7 5.9 2:50 0.158 19:30 0.279 0.206 0.206
3/14/2018 1:20 1.4 20:10 1.7 1.6 2:05 5.3 20:05 6.6 5.9 2:05 0.160 20:05 0.261 0.209 0.209
3/15/2018 2:05 1.4 19:05 1.7 1.6 1:45 5.3 8:15 6.6 5.9 2:05 0.162 20:30 0.260 0.211 0.211
3/16/2018 2:00 1.4 8:40 1.7 1.6 2:25 5.4 13:40 6.6 5.8 2:00 0.155 8:40 0.271 0.205 0.205
3/17/2018 3:20 1.4 8:30 1.9 1.6 2:50 5.2 8:30 6.6 5.9 3:20 0.151 8:30 0.296 0.206 0.206
3/18/2018 4:35 1.3 10:40 1.8 1.6 3:30 5.2 10:40 6.6 5.8 4:15 0.146 10:40 0.293 0.206 0.206
3/19/2018 1:40 1.3 18:50 1.8 1.5 1:05 5.1 18:50 6.6 5.8 1:50 0.141 18:50 0.274 0.198 0.198
3/20/2018 2:35 1.3 20:25 1.7 1.5 1:30 5.1 18:05 6.4 5.7 1:30 0.141 20:25 0.247 0.193 0.193
3/21/2018 2:05 1.3 6:10 1.7 1.5 0:55 5.0 18:55 6.4 5.7 1:55 0.137 6:10 0.244 0.189 0.189
3/22/2018 2:20 1.3 19:50 1.7 1.5 1:40 4.8 19:50 6.4 5.7 1:35 0.132 19:50 0.258 0.198 0.198
3/23/2018 2:40 1.3 7:00 1.8 1.6 1:35 5.2 11:00 6.5 5.9 2:40 0.147 7:00 0.273 0.211 0.211
3/24/2018 3:40 1.5 10:35 2.0 1.7 3:00 5.4 10:35 7.0 6.0 3:15 0.173 10:35 0.361 0.249 0.249
3/25/2018 2:15 1.7 10:20 2.0 1.8 2:15 5.3 13:00 6.6 6.0 2:15 0.205 13:00 0.330 0.265 0.265
3/26/2018 2:10 1.7 19:20 2.0 1.8 2:45 5.3 20:20 6.6 5.9 2:45 0.209 19:20 0.336 0.256 0.256
3/27/2018 23:40 1.5 9:35 2.0 1.7 2:10 5.3 9:35 6.6 5.9 23:45 0.184 9:35 0.325 0.235 0.235
3/28/2018 2:30 1.4 18:05 1.8 1.6 1:35 5.2 18:00 6.6 5.9 1:35 0.168 18:00 0.276 0.217 0.217
3/29/2018 2:10 1.4 20:10 1.7 1.6 2:05 5.3 20:10 6.7 5.9 2:05 0.162 20:10 0.277 0.214 0.214
3/30/2018 2:15 1.4 8:15 1.7 1.6 1:45 5.2 8:15 6.6 5.8 2:15 0.155 8:15 0.272 0.211 0.211
3/31/2018 3:55 1.4 11:35 1.8 1.6 3:50 5.2 13:00 6.5 5.8 3:50 0.150 11:35 0.273 0.209 0.209
ReportAvg 1.6 5.9 0.217
ReportTotal 6.742
ADS Environmental Services
Pipe Height: 10.00
REN_MH5505\mp1\DFINAL (inches) REN_MH5505\mp1\VFINAL (feet/sec) REN_MH5505\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
4/1/2018 4:20 1.3 8:25 1.8 1.6 3:50 5.1 8:25 6.7 5.8 4:20 0.144 8:25 0.297 0.216 0.216
4/2/2018 2:05 1.4 8:20 1.7 1.6 1:10 5.1 20:55 6.5 5.7 2:05 0.149 8:20 0.260 0.205 0.205
4/3/2018 2:25 1.3 19:00 1.7 1.5 2:25 5.0 19:00 6.5 5.7 2:25 0.140 19:00 0.265 0.200 0.200
4/4/2018 2:25 1.3 20:55 1.9 1.7 10:20 5.0 20:55 6.5 5.7 2:20 0.140 20:55 0.306 0.219 0.219
4/5/2018 1:05 1.5 19:35 1.9 1.7 0:40 5.2 19:35 6.6 5.8 1:05 0.174 19:35 0.301 0.237 0.237
4/6/2018 2:40 1.5 19:15 1.8 1.7 2:00 5.2 21:00 6.5 5.9 2:40 0.181 19:15 0.290 0.240 0.240
4/7/2018 1:25 1.4 9:50 2.1 1.8 2:00 5.3 19:00 7.1 6.3 1:25 0.170 9:50 0.369 0.279 0.279
4/8/2018 3:55 1.7 11:10 2.3 2.0 2:40 6.1 11:10 7.3 6.8 2:40 0.247 11:10 0.453 0.336 0.336
4/9/2018 23:55 1.7 20:00 2.1 1.9 1:15 6.3 7:05 7.2 6.7 23:55 0.252 20:00 0.389 0.304 0.304
4/10/2018 23:50 1.6 19:10 2.0 1.8 1:35 6.1 21:10 7.3 6.6 1:35 0.228 21:10 0.358 0.281 0.281
4/11/2018 1:55 1.6 21:05 2.0 1.7 1:50 6.0 20:15 7.0 6.5 1:55 0.217 21:05 0.338 0.265 0.265
4/12/2018 1:25 1.6 7:50 2.0 1.7 3:00 6.1 10:45 7.1 6.5 3:00 0.224 21:10 0.338 0.270 0.270
4/13/2018 1:40 1.6 18:50 1.9 1.7 1:15 6.0 9:30 7.1 6.5 1:25 0.217 9:35 0.340 0.268 0.268
4/14/2018 1:00 1.7 19:40 2.9 2.2 2:30 6.4 20:55 8.1 7.4 0:35 0.257 19:40 0.671 0.441 0.441
4/15/2018 23:40 2.3 8:45 2.9 2.6 23:45 7.5 0:15 8.1 7.9 23:45 0.462 8:45 0.670 0.580 0.580
4/16/2018 3:00 2.3 19:45 2.6 2.4 3:10 7.3 19:45 8.0 7.6 3:10 0.437 19:45 0.579 0.485 0.485
4/17/2018 23:40 2.0 6:20 2.4 2.3 23:35 6.9 6:20 7.8 7.5 23:35 0.355 6:20 0.517 0.462 0.462
4/18/2018 23:50 1.9 6:20 2.3 2.1 23:55 6.6 17:40 7.3 6.9 23:55 0.309 17:40 0.443 0.370 0.370
4/19/2018 23:55 1.8 7:35 2.3 2.0 23:55 6.4 20:40 7.1 6.8 23:55 0.273 7:35 0.422 0.330 0.330
4/20/2018 23:55 1.7 7:20 2.1 1.8 23:55 6.2 8:25 7.0 6.6 23:55 0.240 7:20 0.373 0.291 0.291
4/21/2018 23:45 1.6 8:20 2.1 1.8 2:30 5.9 12:00 6.9 6.4 2:30 0.212 8:20 0.362 0.267 0.267
4/22/2018 4:50 1.5 9:45 2.0 1.7 4:25 5.5 20:25 6.9 6.3 4:25 0.189 9:45 0.344 0.256 0.256
ReportAvg 1.9 6.5 0.309
ReportTotal 6.803
REN_MH5519
Located At: Access via Talbot Rd S (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 10.25”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the upward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 1.25 0.38 0.073 12%
Maximum 25.79 7.68 0.932 100%
Average 3.59 5.32 0.319 35%
Latitude:-
Longitude:-
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Off trail. Confirmation information available from ADS.
Low, fast flow
Good
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete
Wireless
Pipe Material
Off of Talbot Rd, in brush area.
Sensors / Devices:
10.25'' x 10.25''
0.25"
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Peak Combo (CS4)
Pipe Size (HxW)
-
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
~2.25''
Velocity Sensor Offset (in)
~6.00 FPS
Temporary
10.25'' x 10.25''
REN_MH5519
Access Traffic
TRITON+
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
Access Via Talbot Rd S
0 - 5 psi
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Special Installation
Manhole #
Installation Date:
12.14.17
Upstream 0-5 FT Manhole
MH5519 Other
Map
Flow Monitoring
Site Report
0
Downlooker Physical Offset (in)Measurement Confidence (in)
1.38''
Peak Velocity (fps)
Silt (in)
~8'
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Good
Manhole Pick / Vent Hole
Manhole Condition:
No
PVC
20''
NormalVented
20''
Additional Photos
Flow Direction
Monitoring Point
Secondary Top Down - Outlet Oriented
Location
Upstream Downstream Side Inlet
Second Side Inlet (usually dry)Top Down
ADS Environmental Services
Pipe Height: 10.25
REN_MH5519\mp1\DFINAL (inches) REN_MH5519\mp1\VFINAL (feet/sec) REN_MH5519\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 2:15 1.7 18:45 2.4 2.0 2:35 4.2 10:30 7.1 5.8 2:35 0.164 18:45 0.467 0.302 0.302 0.10
12/23/2017 5:10 1.6 11:30 2.3 2.0 5:10 4.1 8:50 7.0 5.7 5:10 0.155 8:50 0.434 0.293 0.293 0.00
12/24/2017 4:00 1.6 12:55 2.4 2.0 4:00 3.7 14:05 7.3 5.6 4:00 0.131 14:05 0.484 0.286 0.286 0.00
12/25/2017 4:05 1.6 18:40 2.4 2.0 4:00 4.1 10:35 7.1 5.7 4:00 0.154 10:35 0.452 0.291 0.291 0.14
12/26/2017 3:20 1.6 14:15 2.4 2.0 3:00 3.6 13:25 7.5 5.8 3:20 0.129 13:25 0.492 0.307 0.307 0.17
12/27/2017 3:20 1.7 13:10 2.5 2.0 1:50 4.2 13:10 7.2 5.9 3:30 0.165 13:10 0.498 0.315 0.315 0.00
12/28/2017 2:50 1.6 16:15 2.5 2.1 3:15 3.9 9:35 7.2 5.9 2:35 0.145 16:15 0.507 0.317 0.317 0.25
12/29/2017 3:10 1.7 10:55 2.7 2.2 3:10 4.5 10:55 7.6 6.2 3:10 0.183 10:55 0.610 0.358 0.358 1.57
12/30/2017 5:05 1.7 9:45 2.3 2.0 5:00 4.5 20:55 6.9 5.9 5:05 0.178 10:50 0.430 0.309 0.309 0.02
12/31/2017 4:55 1.6 11:35 2.4 2.0 5:20 4.1 12:05 7.1 5.7 5:20 0.152 11:35 0.468 0.294 0.294 0.00
ReportAvg 2.0 5.8 0.307
ReportTotal 3.072 2.25
ADS Environmental Services
Pipe Height: 10.25
REN_MH5519\mp1\DFINAL (inches) REN_MH5519\mp1\VFINAL (feet/sec) REN_MH5519\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 5:15 1.6 9:05 2.4 2.0 5:15 3.7 15:15 7.2 5.7 5:15 0.132 15:15 0.474 0.298 0.298 0.00
1/2/2018 4:45 1.6 12:15 2.6 2.0 1:55 3.9 12:15 7.3 5.8 1:55 0.146 12:15 0.537 0.307 0.307 0.01
1/3/2018 3:00 1.6 13:05 2.6 2.0 2:50 3.8 9:40 7.0 5.8 4:30 0.144 13:05 0.520 0.309 0.309 0.00
1/4/2018 4:10 1.6 13:05 2.6 2.1 4:00 4.2 12:05 7.2 5.9 4:10 0.157 13:05 0.534 0.317 0.317 0.09
1/5/2018 3:20 1.6 11:05 2.7 2.0 2:50 3.9 11:05 7.3 5.8 2:50 0.146 11:05 0.557 0.305 0.305 0.42
1/6/2018 2:45 1.6 13:00 2.4 2.0 1:25 4.3 11:25 7.0 5.7 2:45 0.167 13:00 0.438 0.296 0.296 0.24
1/7/2018 4:50 1.6 19:05 2.5 2.0 4:35 3.7 19:05 7.3 5.9 4:45 0.135 19:05 0.508 0.315 0.315 0.38
1/8/2018 2:35 1.6 12:05 2.5 2.1 2:15 4.2 19:15 7.3 5.9 2:15 0.158 12:05 0.502 0.322 0.322 0.14
1/9/2018 3:40 1.7 11:15 2.5 2.1 3:40 4.5 11:15 7.3 6.0 3:40 0.177 11:15 0.524 0.327 0.327 0.46
1/10/2018 2:55 1.6 17:35 2.4 2.0 2:30 4.0 18:30 7.1 5.9 2:30 0.155 18:30 0.473 0.316 0.316 0.22
1/11/2018 2:30 1.7 13:10 3.0 2.1 2:30 3.9 13:10 7.6 6.1 2:30 0.152 13:10 0.675 0.352 0.352 1.04
1/12/2018 4:50 1.7 16:05 2.9 2.1 3:35 4.5 16:05 7.5 5.9 3:35 0.186 16:05 0.636 0.318 0.318 0.20
1/13/2018 4:35 1.7 11:30 2.4 2.0 1:45 4.1 11:30 7.1 5.8 1:45 0.163 11:30 0.463 0.305 0.305 0.02
1/14/2018 5:30 1.6 9:40 2.4 2.0 3:55 4.1 16:40 7.1 5.8 3:55 0.158 9:40 0.470 0.304 0.304 0.00
1/15/2018 4:00 1.6 11:25 2.5 2.1 3:05 4.1 14:45 7.3 5.8 3:05 0.156 14:45 0.515 0.322 0.322 0.04
1/16/2018 4:45 1.7 11:20 2.5 2.1 4:30 4.4 11:20 7.2 5.9 4:30 0.179 11:20 0.502 0.323 0.323 0.26
1/17/2018 4:10 1.6 18:35 2.6 2.1 4:10 4.2 18:35 7.2 5.9 4:10 0.156 18:35 0.530 0.331 0.331 0.79
1/18/2018 1:40 1.7 13:40 2.6 2.1 1:30 4.3 13:40 7.3 6.0 1:30 0.176 13:40 0.536 0.336 0.336 0.40
1/19/2018 3:30 1.6 19:20 2.5 2.1 3:30 4.0 12:35 7.1 6.0 3:30 0.151 19:20 0.490 0.323 0.323 0.10
1/20/2018 4:40 1.6 15:05 2.4 2.0 4:00 4.1 15:05 7.0 5.8 4:40 0.161 15:05 0.469 0.298 0.298 0.10
1/21/2018 3:40 1.6 20:00 2.5 2.0 4:10 3.9 11:55 7.1 5.8 4:10 0.141 20:00 0.500 0.309 0.309 0.16
1/22/2018 2:15 1.6 19:05 2.6 2.1 2:35 3.7 18:25 7.2 5.9 4:35 0.138 18:25 0.508 0.321 0.321 0.34
1/23/2018 3:55 1.6 14:35 2.7 2.1 3:25 4.0 14:35 7.4 5.9 3:25 0.154 14:35 0.587 0.327 0.327 0.79
1/24/2018 4:05 1.7 12:20 2.5 2.1 2:40 4.7 12:20 7.2 6.0 2:40 0.192 12:20 0.508 0.339 0.339 0.51
1/25/2018 2:30 1.7 14:05 2.4 2.1 1:55 4.5 14:00 7.0 6.0 2:30 0.184 14:05 0.467 0.330 0.330 0.14
1/26/2018 3:00 1.7 18:40 2.5 2.1 2:25 4.1 14:15 7.1 5.9 2:25 0.161 18:40 0.476 0.324 0.324 0.36
1/27/2018 5:20 1.8 15:20 2.4 2.1 6:10 5.0 17:40 7.0 6.1 6:10 0.214 15:20 0.462 0.331 0.331 0.61
1/28/2018 4:20 1.7 11:35 2.5 2.0 5:40 4.4 11:35 7.1 5.9 5:40 0.175 11:35 0.487 0.314 0.314 0.07
1/29/2018 2:35 1.6 13:35 2.7 2.1 2:20 4.0 13:35 7.5 6.1 2:20 0.157 13:35 0.592 0.342 0.342 0.90
1/30/2018 3:45 1.7 15:05 2.6 2.1 3:45 4.5 14:05 7.4 6.1 3:45 0.181 15:05 0.525 0.330 0.330 0.00
1/31/2018 3:25 1.6 10:10 2.6 2.1 2:45 3.8 10:10 7.5 6.0 2:45 0.148 10:10 0.560 0.324 0.324 0.00
ReportAvg 2.1 5.9 0.320
ReportTotal 9.914 8.79
ADS Environmental Services
Pipe Height: 10.25
REN_MH5519\mp1\DFINAL (inches) REN_MH5519\mp1\VFINAL (feet/sec) REN_MH5519\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 2:55 1.6 20:20 2.7 2.1 3:15 4.0 20:20 7.4 6.0 3:15 0.155 20:20 0.579 0.329 0.329 0.66
2/2/2018 3:30 1.7 19:40 2.6 2.1 3:55 4.3 19:40 7.4 6.0 3:55 0.168 19:40 0.537 0.323 0.323 0.04
2/3/2018 4:40 1.7 13:30 2.4 2.0 2:30 4.1 13:30 7.0 5.8 2:30 0.161 13:30 0.458 0.305 0.305 0.31
2/4/2018 4:55 1.6 14:35 2.5 2.0 4:35 4.2 14:35 7.1 5.9 4:35 0.163 14:35 0.490 0.313 0.313 0.02
2/5/2018 3:30 1.6 20:40 2.6 2.1 3:30 3.8 15:10 7.2 5.9 3:30 0.140 20:40 0.534 0.318 0.318 0.04
2/6/2018 3:35 1.6 20:00 2.5 2.0 3:45 3.7 11:20 7.1 5.8 3:45 0.141 20:00 0.493 0.311 0.311 0.00
2/7/2018 3:00 1.6 11:35 2.5 2.0 2:25 4.0 11:35 7.3 5.8 3:00 0.151 11:35 0.514 0.312 0.312 0.00
2/8/2018 4:00 1.6 20:50 2.4 2.1 3:55 4.1 9:30 7.0 5.9 3:55 0.157 16:25 0.435 0.315 0.315 0.09
2/9/2018 2:50 1.6 14:55 2.4 2.0 2:50 3.8 14:55 7.1 5.7 2:50 0.143 14:55 0.481 0.303 0.303 0.01
2/10/2018 3:05 1.6 10:35 2.4 2.0 2:40 3.7 12:00 7.5 5.7 2:40 0.137 12:00 0.493 0.294 0.294 0.01
2/11/2018 4:20 1.6 9:00 2.5 2.0 4:45 3.1 12:55 7.3 5.7 4:45 0.109 9:00 0.482 0.301 0.301 0.00
2/12/2018 1:50 1.6 9:15 2.5 2.0 3:50 3.4 7:30 7.1 5.7 3:50 0.122 9:15 0.493 0.304 0.304 0.00
2/13/2018 3:45 1.6 14:40 2.5 2.0 2:30 3.9 14:40 7.2 5.7 2:30 0.143 14:40 0.492 0.302 0.302 0.17
2/14/2018 4:40 1.6 18:00 2.5 2.1 4:25 3.9 17:20 7.1 5.8 4:25 0.145 18:00 0.500 0.316 0.316 0.15
2/15/2018 3:55 1.6 17:40 2.4 2.0 3:40 3.8 18:00 7.4 5.8 3:40 0.141 18:00 0.480 0.306 0.306 0.00
2/16/2018 2:50 1.6 15:00 2.5 2.0 2:50 3.9 15:00 7.2 5.8 2:50 0.144 15:00 0.504 0.305 0.305 0.15
2/17/2018 4:15 1.5 11:55 2.7 2.1 4:10 3.4 11:55 7.4 5.9 4:10 0.120 11:55 0.568 0.327 0.327 0.32
2/18/2018 4:45 1.6 11:15 2.7 2.0 1:45 3.6 13:30 7.4 5.7 1:45 0.136 13:30 0.562 0.304 0.304 0.01
2/19/2018 4:05 1.6 11:40 2.6 2.1 4:05 3.7 15:10 7.4 5.9 4:05 0.133 15:10 0.551 0.324 0.324 0.00
2/20/2018 2:55 1.6 13:45 2.5 2.1 2:55 3.9 11:20 7.0 5.8 2:55 0.143 13:45 0.489 0.314 0.314 0.00
2/21/2018 4:00 1.6 10:25 2.5 2.0 4:05 4.0 12:50 7.3 5.8 4:05 0.156 12:50 0.505 0.313 0.313 0.00
2/22/2018 4:35 1.6 17:45 2.5 2.1 2:55 4.1 17:45 7.3 5.9 4:15 0.161 17:45 0.505 0.319 0.319 0.07
2/23/2018 4:25 1.6 13:20 2.6 2.0 4:45 4.2 13:20 7.2 5.9 5:05 0.163 13:20 0.530 0.313 0.313 0.01
2/24/2018 4:05 1.6 12:20 2.6 2.0 4:05 4.0 12:45 7.2 5.7 4:05 0.145 12:20 0.527 0.298 0.298 0.13
2/25/2018 3:10 1.6 12:15 2.8 2.1 4:15 3.9 12:15 7.4 5.8 3:10 0.143 12:15 0.601 0.317 0.317 0.11
2/26/2018 3:40 1.6 12:35 2.5 2.1 4:40 3.9 10:40 7.4 5.9 4:40 0.143 12:35 0.509 0.323 0.323 0.00
2/27/2018 3:00 1.7 15:05 2.6 2.1 4:20 4.0 15:05 7.2 5.9 4:20 0.157 15:05 0.525 0.318 0.318 0.19
2/28/2018 3:50 1.6 19:05 2.6 2.0 3:30 3.9 19:05 6.9 5.8 3:30 0.149 19:05 0.504 0.311 0.311 0.35
ReportAvg 2.0 5.8 0.312
ReportTotal 8.738 2.84
ADS Environmental Services
Pipe Height: 10.25
REN_MH5519\mp1\DFINAL (inches) REN_MH5519\mp1\VFINAL (feet/sec) REN_MH5519\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 3:30 1.6 18:45 2.9 2.1 2:25 4.0 18:45 7.6 5.9 2:25 0.155 18:45 0.649 0.321 0.321 0.01
3/2/2018 2:10 1.7 14:00 2.6 2.1 1:20 4.4 14:00 7.2 5.9 4:05 0.179 14:00 0.517 0.317 0.317 0.07
3/3/2018 4:00 1.6 8:40 2.6 2.0 4:00 3.9 8:45 7.2 5.7 4:00 0.145 8:45 0.541 0.292 0.292 0.00
3/4/2018 3:20 1.6 11:55 2.5 2.0 2:25 4.0 12:30 7.2 5.8 2:25 0.148 11:55 0.487 0.304 0.304 0.12
3/5/2018 3:05 1.6 11:30 2.5 2.1 3:05 3.7 11:30 7.3 5.9 3:05 0.135 11:30 0.517 0.320 0.320 0.00
3/6/2018 3:15 1.6 7:05 2.7 2.1 3:00 3.9 7:05 7.3 6.0 3:00 0.142 7:05 0.571 0.334 0.334 0.00
3/7/2018 3:20 1.6 17:45 2.5 2.1 3:15 4.1 18:30 7.2 5.9 3:15 0.155 17:45 0.507 0.318 0.318 0.03
3/8/2018 3:30 1.6 18:35 2.8 2.1 1:05 4.0 18:45 7.4 6.0 1:05 0.151 18:35 0.604 0.333 0.333 0.37
3/9/2018 2:55 1.6 14:25 2.7 2.0 2:55 4.1 14:25 7.3 5.9 2:55 0.157 14:25 0.564 0.313 0.313 0.00
3/10/2018 5:15 1.6 10:05 2.5 2.0 3:25 4.0 10:35 7.2 5.7 3:25 0.152 10:35 0.507 0.297 0.297 0.00
3/11/2018 4:20 1.6 12:30 2.4 2.0 3:05 3.7 19:15 7.1 5.7 3:05 0.136 12:30 0.464 0.296 0.296 0.00
3/12/2018 3:20 1.6 13:30 2.5 2.1 2:30 3.8 14:45 7.2 5.8 2:30 0.140 14:45 0.500 0.314 0.314 0.00
3/13/2018 1:10 1.6 9:05 2.6 2.1 1:10 3.9 9:05 7.2 6.0 1:10 0.143 9:05 0.543 0.328 0.328 0.31
3/14/2018 3:00 1.6 17:05 3.0 2.1 2:55 4.0 17:05 7.7 6.0 2:55 0.150 17:05 0.693 0.342 0.342 0.04
3/15/2018 2:20 1.6 10:10 2.3 2.0 0:40 4.0 19:15 7.2 5.8 0:40 0.153 10:10 0.429 0.308 0.308 0.00
3/16/2018 2:10 1.6 7:35 2.5 2.0 2:05 4.1 7:35 7.2 5.8 2:05 0.159 7:35 0.499 0.312 0.312 0.00
3/17/2018 3:55 1.6 12:00 2.5 2.0 3:55 3.6 12:00 7.1 5.7 3:55 0.131 12:00 0.505 0.294 0.294 0.00
3/18/2018 1:40 1.6 10:25 2.7 2.0 1:40 3.8 10:25 7.2 5.8 1:40 0.141 10:25 0.562 0.304 0.304 0.00
3/19/2018 1:10 1.6 9:25 2.5 2.1 1:10 3.7 16:15 7.3 5.8 1:10 0.134 9:25 0.505 0.319 0.319 0.00
3/20/2018 2:45 1.6 16:20 2.7 2.1 2:45 3.7 12:45 7.2 5.9 2:45 0.137 16:20 0.549 0.329 0.329 0.00
3/21/2018 1:40 1.7 20:00 2.8 2.1 1:15 4.1 16:25 7.4 5.9 1:40 0.161 20:00 0.612 0.327 0.327 0.10
3/22/2018 2:20 1.6 10:20 2.6 2.1 2:20 3.9 10:20 7.3 5.9 2:20 0.147 10:20 0.550 0.327 0.327 0.48
3/23/2018 2:30 1.7 14:40 2.5 2.1 1:35 4.0 14:40 7.3 5.9 2:20 0.158 14:40 0.516 0.322 0.322 0.31
3/24/2018 3:30 1.6 11:00 2.6 2.0 3:20 4.2 11:00 7.4 5.8 3:20 0.166 11:00 0.535 0.311 0.311 0.28
3/25/2018 4:05 1.6 11:40 2.5 2.0 2:45 3.7 19:20 7.4 5.7 2:45 0.139 11:40 0.487 0.305 0.305 0.01
3/26/2018 2:15 1.6 13:00 2.8 2.1 1:05 3.6 13:00 7.4 5.9 1:05 0.140 13:00 0.619 0.339 0.339 0.17
3/27/2018 2:50 1.7 16:40 2.6 2.1 1:35 3.8 10:15 7.2 5.9 1:35 0.153 16:40 0.536 0.335 0.335 0.02
3/28/2018 2:25 1.7 9:55 2.6 2.1 1:35 4.1 9:55 7.2 5.9 1:35 0.168 9:55 0.548 0.335 0.335 0.01
3/29/2018 2:40 1.6 15:50 2.6 2.1 2:30 4.0 12:35 7.1 5.8 2:30 0.155 12:35 0.515 0.324 0.324 0.00
3/30/2018 2:25 1.7 8:50 2.5 2.1 2:55 4.1 8:50 7.0 5.8 2:25 0.167 8:50 0.494 0.312 0.312 0.00
3/31/2018 2:25 1.6 10:30 6.0 2.4 2:15 3.9 19:00 6.8 5.5 2:15 0.148 10:30 0.932 0.373 0.373 0.00
ReportAvg 2.1 5.8 0.320
ReportTotal 9.906 2.33
ADS Environmental Services
Pipe Height: 10.25
REN_MH5519\mp1\DFINAL (inches) REN_MH5519\mp1\VFINAL (feet/sec) REN_MH5519\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 3:30 1.6 18:35 3.1 2.3 1:15 4.2 10:40 7.4 5.7 3:30 0.154 10:50 0.618 0.351 0.351 0.10
4/2/2018 1:45 1.6 9:10 2.8 2.1 1:45 3.5 8:55 7.3 5.9 1:45 0.124 8:55 0.583 0.337 0.337 0.00
4/3/2018 2:25 1.7 22:55 4.8 2.2 23:45 3.3 10:05 7.5 5.8 2:25 0.171 21:55 0.689 0.345 0.345 0.00
4/4/2018 2:25 1.9 10:20 6.6 4.2 23:50 1.9 1:25 4.0 2.8 2:25 0.154 12:25 0.758 0.387 0.387 0.39
4/5/2018 2:30 2.2 13:50 8.4 5.5 18:40 0.9 6:35 3.0 1.6 2:00 0.109 6:35 0.646 0.295 0.295 0.25
4/6/2018 1:45 3.6 16:00 17.4 9.8 9:10 0.5 2:10 1.4 1.0 2:50 0.111 23:25 0.434 0.304 0.304 0.00
4/7/2018 1:45 7.8 10:00 24.9 17.3 1:45 0.6 8:30 1.4 0.9 1:45 0.173 8:30 0.533 0.336 0.336 0.88
4/8/2018 3:05 8.8 15:25 25.8 18.8 4:10 0.5 10:45 1.6 0.9 4:10 0.184 10:45 0.598 0.345 0.345 0.45
4/9/2018 3:10 9.8 18:45 25.2 20.4 3:10 0.5 12:50 1.7 1.0 3:10 0.188 12:50 0.634 0.356 0.356 0.00
4/10/2018 0:30 8.0 9:55 25.4 19.9 3:10 0.5 13:40 1.6 1.0 0:30 0.181 13:40 0.584 0.358 0.358 0.23
4/11/2018 23:55 7.6 9:35 24.9 20.0 23:55 0.5 13:00 1.3 0.9 23:55 0.161 13:00 0.481 0.343 0.343 0.31
4/12/2018 1:25 6.8 10:50 25.7 18.7 1:30 0.5 10:50 1.5 0.9 1:30 0.144 10:50 0.570 0.332 0.332 0.11
4/13/2018 1:05 4.8 13:10 24.4 18.1 1:10 0.5 13:10 1.2 0.8 1:05 0.108 13:10 0.442 0.301 0.301 0.51
4/14/2018 3:30 6.4 17:20 24.3 17.9 2:35 0.5 17:20 1.4 0.9 2:35 0.141 17:20 0.517 0.326 0.326 1.52
4/15/2018 23:55 6.4 9:40 23.9 16.6 23:55 0.4 10:10 1.2 0.8 23:55 0.105 10:10 0.435 0.290 0.290 0.21
4/16/2018 2:20 5.3 14:40 25.2 18.3 2:20 0.4 14:40 1.6 0.9 2:20 0.073 14:40 0.578 0.314 0.314 0.71
4/17/2018 12:50 1.3 11:25 24.8 10.3 2:05 0.5 19:15 7.1 3.3 2:05 0.139 10:35 0.566 0.335 0.335 0.01
4/18/2018 2:30 1.7 6:45 2.7 2.2 1:50 3.8 16:05 7.4 5.9 1:50 0.163 16:05 0.570 0.344 0.344 0.12
4/19/2018 3:55 1.7 17:45 2.7 2.1 2:25 3.8 17:45 7.3 6.0 2:25 0.162 17:45 0.577 0.334 0.334 0.00
4/20/2018 2:00 1.7 6:45 2.6 2.1 2:05 4.0 6:05 7.0 5.9 2:00 0.164 6:45 0.516 0.321 0.321 0.00
4/21/2018 3:20 1.7 11:45 2.5 2.0 2:20 4.0 11:45 7.4 5.8 2:20 0.163 11:45 0.517 0.305 0.305 0.05
4/22/2018 3:50 1.7 11:40 2.7 2.0 4:10 3.5 11:35 7.4 5.8 4:10 0.144 11:40 0.553 0.312 0.312 0.00
ReportAvg 10.6 2.9 0.330
ReportTotal 7.270 5.85
REN_MH6041
Located At: Edmonds Ave and NE Sunset Blvd (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 8”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the pressure sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 0.15 0.56 0.002 2%
Maximum 5.66 8.17 0.640 71%
Average 0.91 3.76 0.056 11%
Latitude: 47.501053°
Longitude:-122.185562°
REN_MH6041
TRITON+
System Characteristics
Location Type
Pipe ShapeSite located In road, near pedestrian crosswalk
Renton.Carollo.I&I.WA17
HeavyDrive
Site Access Details:
Site Address /Location:
Site Name
Edmonds ave NE and NE Sunset Blvd
Flow Monitoring
Site Report
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, December 13, 2017
Access
Temporary
8" x 8"
Traffic
MH6041 Residential / Commercial
Map
Installation Type:
Monitoring Location (Sensors):
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
1.25"
Peak Velocity (fps)
Silt (in)
~10:00 AM 8" x 8"Site Sketch Profile View or Photo
low flow
0 - 5 psi
Depth of Flow (Wet DOF) (in)
2''
Velocity Sensor Offset (in)
2.7 FPS
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Concrete Good
10'
Manhole Condition:
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
No
Concrete
NormalSteel
Fair
Active Connections
Renton traffic control Needed
Air Quality:
Communication Type
Normal
Additional Photos
Flow Direction
Monitoring Point
Google Earth Map KEY
Top Down Location Location Map
Inlet Outlet Zoomed out inlet
ADS Environmental Services
Pipe Height: 8.00
REN_MH6041\mp1\DFINAL (inches) REN_MH6041\mp1\VFINAL (feet/sec) REN_MH6041\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
12/22/2017 1:35 1.5 13:30 2.8 1.8 14:05 1.3 19:15 4.5 2.5 1:35 0.040 7:05 0.176 0.097 0.097
12/23/2017 1:45 1.2 21:15 2.1 1.6 2:55 0.7 11:15 4.9 2.6 2:55 0.017 21:15 0.194 0.086 0.086
12/24/2017 4:55 1.3 17:00 2.3 1.7 6:20 0.6 16:20 5.3 2.9 6:20 0.015 16:20 0.243 0.110 0.110
12/25/2017 4:25 1.1 8:00 1.9 1.5 5:05 0.7 10:55 4.8 2.4 5:05 0.012 15:35 0.138 0.071 0.071
12/26/2017 3:25 1.1 12:30 2.2 1.7 1:30 0.7 14:25 4.1 2.7 1:30 0.014 12:35 0.198 0.103 0.103
12/27/2017 4:55 0.9 18:20 2.8 1.5 8:35 0.9 9:00 4.1 2.2 4:55 0.016 13:15 0.185 0.066 0.066
12/28/2017 2:20 1.1 15:00 2.5 1.5 1:50 0.7 20:55 3.9 2.3 1:50 0.014 15:00 0.185 0.077 0.077
12/29/2017 22:55 1.6 15:00 2.8 2.1 22:50 2.9 12:10 6.1 4.0 22:55 0.098 15:45 0.349 0.189 0.189
12/30/2017 20:55 1.3 13:30 2.7 1.6 3:15 1.9 13:30 5.5 3.1 3:15 0.055 13:30 0.362 0.105 0.105
12/31/2017 4:50 1.0 13:05 2.2 1.4 3:00 0.8 12:25 4.4 2.4 5:30 0.013 13:05 0.198 0.072 0.072
ReportAvg 1.6 2.7 0.097
ReportTotal 0.973
ADS Environmental Services
Pipe Height: 8.00
REN_MH6041\mp1\DFINAL (inches) REN_MH6041\mp1\VFINAL (feet/sec) REN_MH6041\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
1/1/2018 3:50 1.2 18:00 2.2 1.5 3:35 0.7 9:00 4.3 2.2 3:35 0.016 16:55 0.195 0.073 0.073
1/2/2018 3:30 1.0 6:50 2.2 1.4 4:35 0.8 6:50 5.5 2.5 4:35 0.015 6:50 0.286 0.067 0.067
1/3/2018 3:05 1.0 6:40 1.8 1.3 4:50 0.8 12:00 5.2 2.7 4:50 0.015 12:00 0.189 0.065 0.065
1/4/2018 12:30 0.7 10:30 5.7 1.2 3:10 0.9 19:55 6.5 3.4 3:10 0.020 10:30 0.640 0.069 0.069
1/5/2018 5:15 0.6 20:50 1.1 0.9 3:15 1.8 13:20 6.3 3.7 4:15 0.017 13:20 0.120 0.054 0.054
1/6/2018 1:35 0.7 11:15 1.2 0.9 3:20 2.3 18:25 6.8 4.0 1:40 0.024 11:15 0.147 0.061 0.061
1/7/2018 7:30 0.7 22:20 1.3 1.0 5:30 2.1 10:50 6.3 4.1 5:30 0.022 10:50 0.153 0.066 0.066
1/8/2018 4:55 0.7 21:20 1.3 1.0 3:50 2.3 20:40 6.6 4.3 3:50 0.026 20:40 0.150 0.077 0.077
1/9/2018 3:00 0.7 17:50 1.4 1.0 4:05 2.6 18:30 6.4 4.5 3:00 0.029 11:10 0.143 0.075 0.075
1/10/2018 20:50 0.7 16:00 1.5 1.0 3:05 2.4 22:40 6.3 4.0 20:00 0.035 11:15 0.118 0.066 0.066
1/11/2018 2:40 0.5 22:00 1.3 1.0 2:55 2.0 9:15 6.7 5.1 2:40 0.011 22:00 0.140 0.087 0.087
1/12/2018 4:45 0.6 0:10 1.3 1.0 4:45 2.4 7:25 6.8 4.8 4:45 0.017 7:25 0.136 0.085 0.085
1/13/2018 7:20 0.6 20:40 1.7 0.9 4:40 2.3 20:50 7.7 3.7 5:40 0.021 20:40 0.269 0.056 0.056
1/14/2018 4:25 0.5 18:45 1.3 0.9 6:00 2.4 18:45 6.9 4.1 5:00 0.017 18:45 0.158 0.058 0.058
1/15/2018 5:25 0.5 22:35 1.2 0.9 3:55 2.6 16:20 6.4 3.9 1:15 0.017 22:35 0.129 0.055 0.055
1/16/2018 5:15 0.6 11:10 1.2 0.9 4:40 2.2 12:05 6.3 4.2 5:15 0.018 18:05 0.115 0.063 0.063
1/17/2018 4:25 0.5 21:35 1.2 0.9 2:50 2.5 18:35 6.8 4.4 4:25 0.017 21:35 0.144 0.066 0.066
1/18/2018 4:10 0.7 12:35 1.1 0.9 1:30 2.6 19:55 7.1 4.8 4:35 0.028 20:35 0.120 0.063 0.063
1/19/2018 6:05 0.5 14:00 1.2 0.8 4:05 2.8 10:20 7.4 4.4 4:35 0.017 14:00 0.138 0.054 0.054
1/20/2018 6:30 0.4 15:05 1.0 0.8 1:50 2.2 20:05 6.6 4.1 4:10 0.012 9:45 0.103 0.050 0.050
1/21/2018 4:30 0.3 21:45 1.2 0.8 5:30 2.0 15:00 6.7 4.1 4:30 0.007 13:30 0.101 0.051 0.051
1/22/2018 1:30 0.6 23:50 1.7 0.9 3:15 2.6 10:10 6.4 4.3 1:30 0.019 23:40 0.130 0.061 0.061
1/23/2018 3:50 0.4 0:30 1.5 0.9 3:00 2.3 21:20 6.8 4.7 3:50 0.012 21:20 0.153 0.069 0.069
1/24/2018 0:10 0.7 12:10 1.2 1.0 4:15 3.5 17:25 7.1 5.2 4:45 0.046 12:10 0.153 0.087 0.087
1/25/2018 4:00 0.6 10:45 1.1 1.0 23:20 3.1 18:50 6.6 4.9 4:00 0.026 8:15 0.118 0.076 0.076
1/26/2018 1:45 0.6 18:50 1.1 0.9 2:30 2.7 8:50 6.7 4.7 1:45 0.028 18:50 0.121 0.067 0.067
1/27/2018 4:25 0.7 15:15 1.1 0.9 0:20 3.9 11:50 6.9 5.3 4:25 0.044 15:15 0.115 0.081 0.081
1/28/2018 2:00 0.6 20:50 1.3 1.0 4:05 3.0 10:20 7.2 4.8 3:05 0.030 10:20 0.162 0.083 0.083
1/29/2018 4:00 0.7 13:55 1.3 1.1 4:10 2.8 19:55 8.2 5.0 4:00 0.027 19:55 0.170 0.091 0.091
1/30/2018 2:55 0.7 11:20 1.0 0.9 3:15 3.3 15:20 6.5 5.1 3:15 0.029 11:30 0.104 0.070 0.070
1/31/2018 2:35 0.5 14:00 1.3 0.8 2:05 2.9 19:50 7.5 4.7 2:35 0.020 14:00 0.159 0.061 0.061
ReportAvg 1.0 4.2 0.068
ReportTotal 2.107
ADS Environmental Services
Pipe Height: 8.00
REN_MH6041\mp1\DFINAL (inches) REN_MH6041\mp1\VFINAL (feet/sec) REN_MH6041\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
2/1/2018 2:45 0.4 21:40 1.1 0.8 2:55 2.4 14:15 7.2 4.7 2:45 0.012 21:40 0.116 0.063 0.063
2/2/2018 5:50 0.6 9:50 1.2 0.9 1:40 3.1 6:35 6.6 4.8 5:50 0.030 19:20 0.119 0.072 0.072
2/3/2018 6:15 0.4 21:30 1.3 1.0 2:50 2.7 12:10 7.2 4.6 6:15 0.013 20:05 0.147 0.074 0.074
2/4/2018 5:10 0.6 13:20 1.3 1.0 3:55 2.5 11:35 6.7 4.5 5:10 0.022 11:35 0.141 0.077 0.077
2/5/2018 4:55 0.5 14:35 1.1 0.9 2:05 2.3 12:40 7.0 4.4 4:10 0.015 12:40 0.114 0.063 0.063
2/6/2018 5:05 0.4 21:10 1.2 0.9 2:05 2.5 16:00 7.2 4.4 5:05 0.010 21:10 0.145 0.063 0.063
2/7/2018 5:20 0.3 19:35 1.3 1.0 2:35 2.0 13:45 6.8 4.3 5:20 0.012 20:40 0.141 0.072 0.072
2/8/2018 23:10 0.5 9:35 1.2 0.9 3:05 2.0 20:55 6.3 4.2 3:05 0.012 9:35 0.116 0.065 0.065
2/9/2018 22:05 0.3 14:50 1.0 0.8 22:05 1.9 17:40 7.0 4.0 22:05 0.005 13:15 0.104 0.047 0.047
2/10/2018 4:10 0.3 21:45 1.0 0.7 3:30 1.7 9:20 7.1 3.8 4:10 0.005 15:00 0.103 0.040 0.040
2/11/2018 5:40 0.2 20:30 0.9 0.6 6:00 1.4 7:50 5.9 3.0 5:40 0.003 7:50 0.084 0.026 0.026
2/12/2018 1:45 0.3 20:05 1.0 0.6 4:10 1.3 12:40 6.4 2.8 1:45 0.004 20:05 0.089 0.024 0.024
2/13/2018 1:45 0.2 17:35 1.1 0.7 3:35 1.3 17:35 6.5 3.2 1:45 0.003 17:35 0.129 0.036 0.036
2/14/2018 3:15 0.3 14:20 1.2 0.7 4:05 1.3 14:20 7.0 3.5 3:15 0.003 14:20 0.148 0.042 0.042
2/15/2018 4:05 0.2 16:35 1.0 0.8 1:40 1.2 21:30 6.0 3.7 1:45 0.003 21:30 0.096 0.043 0.043
2/16/2018 6:05 0.3 13:40 0.9 0.7 22:20 1.7 12:10 5.8 3.1 6:05 0.006 13:40 0.075 0.030 0.030
2/17/2018 1:55 0.2 11:15 1.0 0.7 2:40 1.4 11:15 5.9 2.8 1:55 0.002 11:15 0.091 0.027 0.027
2/18/2018 23:55 0.4 13:25 1.0 0.7 3:00 1.6 13:25 5.9 3.0 23:55 0.012 13:25 0.094 0.031 0.031
2/19/2018 23:20 0.3 18:30 1.0 0.7 23:50 1.4 13:10 5.7 2.8 23:20 0.004 18:30 0.090 0.026 0.026
2/20/2018 6:00 0.2 20:00 1.0 0.6 1:25 1.1 19:40 5.3 2.4 6:00 0.003 20:00 0.070 0.020 0.020
2/21/2018 4:00 0.3 17:35 1.4 0.6 3:10 1.0 17:35 7.2 2.8 4:00 0.004 17:35 0.183 0.029 0.029
2/22/2018 22:30 0.3 7:20 1.7 0.7 22:30 1.9 7:20 7.9 3.5 22:30 0.005 7:20 0.279 0.040 0.040
2/23/2018 1:30 0.2 20:15 1.1 0.7 4:55 1.6 20:00 5.6 3.4 1:30 0.004 20:00 0.091 0.036 0.036
2/24/2018 12:25 0.5 14:00 1.0 0.8 5:15 1.7 14:00 6.2 3.6 5:05 0.015 14:00 0.108 0.040 0.040
2/25/2018 5:45 0.3 12:10 1.0 0.7 3:45 1.3 11:00 6.7 3.8 5:45 0.005 18:15 0.094 0.042 0.042
2/26/2018 23:15 0.3 18:20 1.0 0.7 4:00 2.0 18:20 5.5 3.7 23:15 0.005 18:20 0.088 0.036 0.036
2/27/2018 4:25 0.2 13:00 0.9 0.6 3:20 1.4 18:55 5.4 3.0 3:50 0.004 13:00 0.074 0.026 0.026
2/28/2018 1:45 0.2 5:55 1.0 0.6 2:15 1.5 9:15 5.4 3.2 5:00 0.003 19:45 0.090 0.028 0.028
ReportAvg 0.8 3.6 0.043
ReportTotal 1.218
ADS Environmental Services
Pipe Height: 8.00
REN_MH6041\mp1\DFINAL (inches) REN_MH6041\mp1\VFINAL (feet/sec) REN_MH6041\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
3/1/2018 23:00 0.4 12:40 1.0 0.7 3:25 2.6 12:35 5.7 3.5 23:00 0.013 12:40 0.096 0.033 0.033
3/2/2018 3:05 0.4 18:10 1.0 0.7 1:15 2.8 13:15 6.2 3.7 5:00 0.016 18:10 0.091 0.037 0.037
3/3/2018 1:25 0.4 8:35 1.2 0.7 5:50 2.3 8:50 5.4 3.4 1:25 0.015 8:50 0.095 0.034 0.034
3/4/2018 17:45 0.4 21:10 1.1 0.7 6:05 2.1 11:45 5.8 3.1 17:45 0.014 12:55 0.085 0.030 0.030
3/5/2018 6:55 0.4 16:55 1.4 0.8 3:10 1.5 13:45 6.2 2.9 6:55 0.011 13:45 0.107 0.034 0.034
3/6/2018 17:00 0.4 23:15 1.6 0.9 23:50 2.1 10:15 5.8 3.3 17:00 0.014 23:40 0.095 0.044 0.044
3/7/2018 17:25 0.4 0:00 1.6 0.9 4:50 1.7 21:45 5.8 3.3 23:50 0.015 5:35 0.104 0.042 0.042
3/8/2018 7:20 0.4 20:30 1.1 0.7 2:00 2.7 20:30 5.9 3.7 7:20 0.012 20:30 0.107 0.040 0.040
3/9/2018 4:50 0.3 18:20 1.0 0.6 3:25 1.2 18:20 5.9 3.0 4:50 0.004 18:20 0.096 0.026 0.026
3/10/2018 7:15 0.3 11:00 1.0 0.7 16:35 2.1 9:20 5.9 3.1 7:15 0.005 11:00 0.089 0.028 0.028
3/11/2018 1:15 0.2 18:20 1.1 0.7 5:25 1.4 18:40 6.4 3.0 1:15 0.003 18:40 0.114 0.033 0.033
3/12/2018 3:15 0.3 20:25 1.1 0.8 23:50 1.5 10:45 6.1 3.2 3:15 0.004 10:45 0.109 0.037 0.037
3/13/2018 0:25 0.3 0:50 1.2 0.8 1:20 1.1 18:45 6.0 3.0 0:20 0.005 18:45 0.080 0.034 0.034
3/14/2018 0:10 0.3 10:30 1.9 0.8 2:40 1.9 10:40 7.9 3.8 0:05 0.007 10:30 0.319 0.054 0.054
3/15/2018 15:55 0.4 17:30 1.1 0.8 3:05 1.6 17:30 5.6 3.6 15:55 0.013 17:30 0.099 0.046 0.046
3/16/2018 2:15 0.4 18:50 0.9 0.8 3:10 1.7 16:55 6.2 3.6 2:15 0.009 16:55 0.085 0.041 0.041
3/17/2018 5:25 0.4 8:15 1.0 0.7 3:50 1.4 8:15 6.6 3.6 5:25 0.008 8:15 0.109 0.037 0.037
3/18/2018 1:35 0.3 13:15 1.0 0.7 3:05 1.6 7:25 7.2 3.6 1:55 0.008 7:25 0.092 0.041 0.041
3/19/2018 4:25 0.3 18:55 1.1 0.8 2:10 1.5 17:30 6.9 3.7 0:00 0.007 22:10 0.094 0.043 0.043
3/20/2018 0:20 0.4 15:20 1.0 0.8 2:20 1.4 20:15 6.3 3.6 0:20 0.007 20:15 0.101 0.044 0.044
3/21/2018 3:20 0.4 20:55 1.1 0.8 1:45 1.7 18:55 6.7 3.8 2:05 0.008 18:55 0.106 0.046 0.046
3/22/2018 3:40 0.4 8:10 1.1 0.8 3:15 1.6 8:10 6.0 3.9 0:50 0.010 8:10 0.106 0.050 0.050
3/23/2018 1:05 0.3 6:35 1.0 0.8 3:30 1.5 12:15 6.4 3.9 1:05 0.007 12:15 0.106 0.047 0.047
3/24/2018 1:15 0.3 10:05 1.1 0.8 1:30 1.9 9:25 6.0 3.9 1:15 0.007 10:05 0.105 0.046 0.046
3/25/2018 3:55 0.4 11:05 1.0 0.8 5:25 1.9 10:35 7.1 3.9 2:30 0.009 10:40 0.105 0.047 0.047
3/26/2018 2:20 0.4 19:15 1.0 0.8 2:40 1.9 12:50 6.7 4.0 1:10 0.009 12:50 0.105 0.048 0.048
3/27/2018 1:05 0.3 17:50 1.1 0.8 1:35 1.6 14:55 6.6 3.8 1:05 0.006 19:45 0.107 0.052 0.052
3/28/2018 0:45 0.4 15:10 1.1 0.8 2:20 1.6 20:45 6.1 3.8 2:25 0.008 20:45 0.105 0.050 0.050
3/29/2018 0:55 0.5 20:35 1.2 0.8 1:35 1.5 18:55 6.2 3.7 1:35 0.010 18:55 0.127 0.050 0.050
3/30/2018 2:30 0.4 17:25 1.2 0.9 3:20 1.5 17:25 6.2 3.6 2:10 0.008 17:25 0.126 0.050 0.050
3/31/2018 2:30 0.4 19:55 1.2 0.9 1:40 1.6 7:25 6.8 3.6 2:30 0.007 7:25 0.106 0.051 0.051
ReportAvg 0.8 3.5 0.042
ReportTotal 1.294
ADS Environmental Services
Pipe Height: 8.00
REN_MH6041\mp1\DFINAL (inches) REN_MH6041\mp1\VFINAL (feet/sec) REN_MH6041\mp1\QFINAL (MGD - Total MG)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total
4/1/2018 1:10 0.4 19:20 1.1 0.9 4:05 1.4 9:30 6.7 3.8 1:10 0.009 18:10 0.114 0.052 0.052
4/2/2018 23:50 0.5 19:20 1.1 0.9 0:20 2.6 8:10 5.8 3.8 23:50 0.020 20:05 0.100 0.052 0.052
4/3/2018 1:40 0.4 18:55 1.1 0.9 2:00 1.4 11:45 6.8 3.8 1:40 0.006 11:45 0.124 0.055 0.055
4/4/2018 1:25 0.5 21:10 1.1 0.9 1:20 1.5 19:30 6.3 3.9 2:15 0.010 21:10 0.117 0.056 0.056
4/5/2018 2:30 0.4 19:15 1.1 0.9 2:40 1.6 9:00 5.9 3.9 1:55 0.008 19:15 0.114 0.056 0.056
4/6/2018 3:45 0.4 20:10 1.1 0.9 3:45 2.0 20:40 6.6 3.7 3:45 0.009 20:40 0.121 0.053 0.053
4/7/2018 1:30 0.4 12:55 1.2 1.0 1:30 2.0 19:30 7.2 4.2 1:30 0.010 19:30 0.143 0.067 0.067
4/8/2018 1:45 0.6 19:25 1.1 0.9 2:25 2.9 12:30 7.3 4.4 1:45 0.021 12:30 0.117 0.064 0.064
4/9/2018 3:35 0.4 21:05 1.1 0.8 2:35 2.7 9:50 7.1 3.9 3:35 0.016 21:05 0.115 0.051 0.051
4/10/2018 5:50 0.5 7:10 1.1 0.9 2:00 2.2 21:35 5.7 3.7 5:50 0.018 20:50 0.107 0.051 0.051
4/11/2018 2:25 0.4 17:00 1.0 0.8 2:25 1.7 20:00 5.7 3.7 2:25 0.006 20:00 0.094 0.047 0.047
4/12/2018 2:25 0.3 19:05 0.9 0.8 4:00 2.6 20:40 6.9 3.7 2:25 0.010 19:30 0.090 0.041 0.041
4/13/2018 0:45 0.4 9:30 0.9 0.7 2:50 2.5 21:20 6.1 3.7 1:35 0.011 21:20 0.075 0.040 0.040
4/14/2018 4:00 0.6 21:10 1.1 0.9 4:00 2.9 14:25 6.4 4.8 4:00 0.021 21:10 0.112 0.072 0.072
4/15/2018 18:55 0.7 20:15 1.1 1.0 23:25 3.8 19:05 7.8 5.4 23:35 0.053 10:40 0.119 0.085 0.085
4/16/2018 2:15 0.6 9:20 1.0 0.9 4:20 3.3 18:15 8.2 5.0 2:15 0.029 17:35 0.122 0.073 0.073
4/17/2018 22:50 0.6 6:40 1.0 0.9 23:55 3.1 13:15 6.0 4.6 22:50 0.032 12:05 0.092 0.062 0.062
4/18/2018 2:25 0.4 19:35 1.0 0.8 2:50 3.1 17:05 6.3 4.4 2:25 0.012 9:45 0.090 0.054 0.054
4/19/2018 0:55 0.3 11:15 1.0 0.8 1:00 2.9 16:25 6.8 4.1 0:55 0.006 16:25 0.108 0.054 0.054
4/20/2018 0:05 0.4 5:35 1.0 0.8 2:15 2.7 10:30 5.8 3.9 0:05 0.012 10:30 0.092 0.047 0.047
4/21/2018 4:50 0.3 14:35 1.0 0.8 2:30 2.2 7:50 6.3 3.7 4:50 0.010 14:35 0.099 0.045 0.045
4/22/2018 23:15 0.4 17:10 1.1 0.8 2:15 1.8 12:05 5.9 3.7 23:15 0.011 17:10 0.110 0.043 0.043
ReportAvg 0.9 4.1 0.055
ReportTotal 1.221
REN_MH6704
Located At: 2623 NE Sunset Blvd (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
Pipe Dimensions: 12”
Finalized Silt Level: 0 mm
Site Data Characteristics: This site is located in a sanitary sewer pipe. The scattergraph indicates site
operated in free flow conditions. The site did not surcharge during the monitoring period. The dry
weather data plots above the Froude =1 curve indicating supercritical flow.
Site Data Bias & Editing: The depth and velocity measurements recorded by the flow monitor were
consistent with field confirmations conducted to date and supported the relative accuracy of the flow
monitor at this location. The finalized depth data utilized the downward ultrasonic sensor.
Site Data Uptime: The data uptime achieved during the monitoring period is provided in the table
below. Based upon the quality and consistency of the observed flow depth and velocity data, the
Continuity equation was used to calculate the flow rate for the monitoring period.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Site Data Summary: The average flow depth, velocity, and quantity data observed during the
monitoring period along with observed minimum and maximum data, are provided in the following
table. The minimum and maximum rates recorded in the tables are based on 5‐minute data intervals.
Item Depth (in) Velocity (f/s) Quantity (mgd) % Full
Minimum 0.53 3.62 0.035 4%
Maximum 1.74 9.94 0.441 15%
Average 1.02 6.14 0.132 9%
Latitude: 47.499488°
Longitude:-122.184027°
REN_MH6704
TRITON+
System Characteristics
Location Type
Pipe ShapeWill have to park off road and walk to site,
Renton.Carollo.I&I.WA17
NoneWalk (Residential)
Site Access Details:
Site Address /Location:
Site Name
2623 NE Sunset Blvd
Flow Monitoring
Site Report
Installation Information
Circular
Monitor Series
Monitor Location:
Doppler Standard Ring and Crank
Manhole #
Installation Date:
Pipe Size (H x W)
Topside / Area Photo
Wednesday, December 13, 2017
Access
Temporary
12 X 12
Traffic
MH6704 Residential / Commercial
Map
Installation Type:
Monitoring Location (Sensors):
Peak Combo (CS4), Smart Depth (CS5)
Pipe Size (HxW)
0.00''
CS5 Physical Offset (in)Measurement Confidence (in)
1.38"
Peak Velocity (fps)
Silt (in)
2:50:00 PM 12 X 12Site Sketch Profile View or Photo
Straight, Some Ripples
0 - 5 psi
Depth of Flow (Wet DOF) (in)
1.00''
Velocity Sensor Offset (in)
6.9
Downstream 0-5 FT Manhole
Sensors / Devices:
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
0''
Sanitary Sewer Overflow
0.25"
Manhole / Pipe Information:
Pressure Sensor Range (psi)
Confirmation Time:
20''20''
Manhole Cover Manhole Frame
Pipe Condition:
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
PVC Good
13'
Manhole Condition:
22275.11.325
Additional Site Info. / Comments:
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Wireless
Pipe Material
Antenna Location
Communication Information:
Manhole Pick / Vent Hole
No
Vitrified Clay Pipe
NormalBolted
Fair
Active Connections
None.
Air Quality:
Communication Type
Normal
Additional Photos
Flow Direction
Monitoring Point
KEY
Top Down Location Location Map
Inlet Outlet Location Map
ADS Environmental Services
Pipe Height: 12.00
REN_MH6704\mp1\DFINAL (inches) REN_MH6704\mp1\VFINAL (feet/sec) REN_MH6704\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
12/22/2017 1:20 0.8 11:55 1.3 1.1 3:25 5.1 11:55 9.2 7.3 2:50 0.082 11:55 0.287 0.172 0.172 0.10
12/23/2017 23:25 0.8 10:25 1.3 1.0 5:45 4.5 10:40 8.9 7.2 3:10 0.079 10:25 0.255 0.159 0.159 0.00
12/24/2017 4:15 0.6 9:05 1.2 1.0 3:35 4.5 10:40 9.2 7.1 4:30 0.047 10:40 0.252 0.141 0.141 0.00
12/25/2017 3:50 0.8 11:10 1.3 1.0 6:05 4.4 15:15 8.8 6.7 4:00 0.063 12:35 0.244 0.137 0.137 0.14
12/26/2017 23:15 0.7 16:45 1.4 1.0 3:40 4.3 15:15 8.8 7.1 3:35 0.055 16:10 0.276 0.160 0.160 0.17
12/27/2017 3:25 0.7 20:25 1.3 1.0 1:20 4.4 15:55 8.7 7.0 1:20 0.053 11:35 0.250 0.142 0.142 0.00
12/28/2017 2:50 0.7 21:30 1.5 1.0 4:50 4.3 13:40 8.8 7.1 2:50 0.067 21:35 0.280 0.154 0.154 0.25
12/29/2017 23:10 0.9 12:50 1.7 1.3 2:45 6.2 12:00 9.9 8.2 23:10 0.126 12:00 0.441 0.247 0.247 1.57
12/30/2017 2:15 0.8 12:25 1.5 1.1 2:30 4.9 12:15 9.0 7.4 2:30 0.081 11:00 0.310 0.182 0.182 0.02
12/31/2017 20:50 0.7 15:00 1.3 1.0 5:05 4.7 13:05 9.5 7.5 5:05 0.068 15:00 0.270 0.150 0.150 0.00
ReportAvg 1.1 7.3 0.164
ReportTotal 1.645 2.25
ADS Environmental Services
Pipe Height: 12.00
REN_MH6704\mp1\DFINAL (inches) REN_MH6704\mp1\VFINAL (feet/sec) REN_MH6704\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
1/1/2018 0:40 0.7 18:25 1.2 1.0 4:55 5.6 18:20 9.2 7.7 0:40 0.073 18:20 0.237 0.153 0.153 0.00
1/2/2018 2:45 0.7 18:40 1.2 1.0 3:30 4.8 15:25 9.1 7.5 1:40 0.067 18:40 0.226 0.151 0.151 0.01
1/3/2018 4:40 0.8 19:00 1.3 0.9 2:55 5.0 19:00 9.3 7.4 2:55 0.073 19:00 0.290 0.139 0.139 0.00
1/4/2018 2:25 0.7 12:40 1.2 0.9 2:25 4.3 12:40 8.9 7.1 2:25 0.050 12:40 0.242 0.138 0.138 0.09
1/5/2018 23:35 0.8 12:35 1.2 1.0 2:05 4.9 17:05 9.4 7.4 2:05 0.077 12:55 0.230 0.150 0.150 0.42
1/6/2018 23:05 0.8 15:05 1.2 1.0 3:05 5.3 15:05 9.2 7.6 3:00 0.085 15:05 0.242 0.155 0.155 0.24
1/7/2018 6:00 0.7 13:45 1.4 1.0 3:20 4.5 18:30 9.7 7.5 6:00 0.060 18:30 0.301 0.162 0.162 0.38
1/8/2018 2:05 0.8 16:55 1.2 1.0 2:30 4.6 14:20 9.0 7.3 2:40 0.062 16:55 0.235 0.141 0.141 0.14
1/9/2018 4:05 0.8 20:15 1.2 1.0 3:30 4.9 20:15 9.0 7.4 3:30 0.072 20:15 0.236 0.151 0.151 0.46
1/10/2018 0:15 0.8 12:25 1.3 1.0 1:20 4.6 13:25 9.1 7.3 1:20 0.065 12:25 0.267 0.146 0.146 0.22
1/11/2018 3:35 0.8 14:40 1.4 1.1 3:55 4.7 14:40 9.0 7.2 3:55 0.075 14:40 0.314 0.167 0.167 1.04
1/12/2018 5:35 0.8 10:30 1.3 1.0 4:20 4.7 10:30 8.7 6.8 4:20 0.076 10:30 0.269 0.149 0.149 0.20
1/13/2018 4:05 0.8 12:35 1.2 1.0 4:25 4.2 11:40 8.5 6.5 4:25 0.063 11:50 0.223 0.141 0.141 0.02
1/14/2018 3:30 0.8 14:00 1.3 1.0 3:15 4.2 19:00 8.7 6.3 3:50 0.060 14:00 0.247 0.133 0.133 0.00
1/15/2018 3:30 0.8 11:05 1.2 1.0 3:45 4.3 17:00 8.1 6.4 3:30 0.060 12:40 0.199 0.135 0.135 0.04
1/16/2018 5:10 0.8 18:25 1.2 1.0 0:40 4.3 12:40 8.2 6.1 3:40 0.064 18:25 0.209 0.123 0.123 0.26
1/17/2018 2:50 0.7 18:10 1.3 1.0 1:45 4.2 15:40 8.2 6.2 2:50 0.055 20:50 0.232 0.132 0.132 0.79
1/18/2018 1:25 0.8 15:30 1.3 1.1 1:50 4.4 15:15 8.9 6.5 1:25 0.068 15:15 0.264 0.157 0.157 0.40
1/19/2018 23:15 0.7 17:30 1.3 1.1 1:55 4.3 18:00 8.2 6.1 23:15 0.063 18:00 0.223 0.143 0.143 0.10
1/20/2018 2:15 0.7 21:20 1.2 1.0 5:40 4.3 13:15 8.4 6.4 2:15 0.059 13:35 0.221 0.128 0.128 0.10
1/21/2018 4:20 0.6 11:25 1.2 1.0 5:50 4.3 18:10 9.0 6.4 4:20 0.044 18:10 0.235 0.131 0.131 0.16
1/22/2018 23:55 0.6 19:05 1.3 1.0 3:15 4.3 16:50 8.6 6.1 23:55 0.047 16:50 0.234 0.129 0.129 0.34
1/23/2018 3:50 0.5 18:40 1.4 0.9 1:20 4.2 12:20 8.9 6.2 3:55 0.035 18:40 0.268 0.116 0.116 0.79
1/24/2018 23:50 0.8 22:05 1.4 1.1 4:35 4.7 12:45 8.5 6.7 1:45 0.077 12:45 0.269 0.168 0.168 0.51
1/25/2018 23:10 0.8 20:05 1.3 1.1 2:30 4.7 17:25 8.0 6.4 23:20 0.083 16:50 0.224 0.144 0.144 0.14
1/26/2018 23:55 0.7 20:20 1.2 1.0 4:15 4.5 11:20 8.4 6.4 0:45 0.065 11:20 0.234 0.141 0.141 0.36
1/27/2018 0:05 0.7 21:25 1.2 1.0 4:10 4.8 16:35 8.5 6.8 0:05 0.065 16:35 0.213 0.133 0.133 0.61
1/28/2018 23:25 0.9 15:00 1.4 1.1 4:50 4.6 15:10 8.6 6.8 5:25 0.082 18:35 0.269 0.152 0.152 0.07
1/29/2018 9:25 0.8 20:25 1.4 1.0 3:20 4.3 18:55 8.8 6.5 4:40 0.073 20:25 0.264 0.142 0.142 0.90
1/30/2018 2:35 0.7 18:05 1.4 1.0 1:50 4.4 14:05 8.1 6.3 2:35 0.061 18:05 0.261 0.130 0.130 0.00
1/31/2018 8:35 0.9 20:35 1.4 1.1 3:10 4.4 20:10 8.5 6.0 3:15 0.078 20:10 0.266 0.144 0.144 0.00
ReportAvg 1.0 6.8 0.143
ReportTotal 4.426 8.79
ADS Environmental Services
Pipe Height: 12.00
REN_MH6704\mp1\DFINAL (inches) REN_MH6704\mp1\VFINAL (feet/sec) REN_MH6704\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
2/1/2018 2:50 0.7 20:40 1.2 1.0 2:45 4.1 20:50 8.3 6.2 2:55 0.053 20:50 0.212 0.125 0.125 0.66
2/2/2018 3:45 0.7 12:25 1.2 0.9 3:10 4.6 7:40 8.7 6.3 4:05 0.061 12:25 0.234 0.114 0.114 0.04
2/3/2018 2:20 0.7 19:25 1.2 0.9 5:35 4.3 14:30 8.5 6.4 4:10 0.053 19:20 0.211 0.125 0.125 0.31
2/4/2018 3:40 0.7 8:15 1.3 1.0 3:15 4.5 15:25 8.6 6.4 3:40 0.057 15:15 0.218 0.130 0.130 0.02
2/5/2018 3:50 0.6 17:45 1.2 1.0 4:20 4.4 12:00 8.1 6.0 3:50 0.043 16:50 0.201 0.120 0.120 0.04
2/6/2018 2:55 0.6 9:50 1.7 1.0 3:20 4.2 9:50 9.0 6.0 2:55 0.040 9:50 0.381 0.119 0.119 0.00
2/7/2018 2:25 0.6 19:05 1.2 0.9 4:15 4.3 20:25 8.0 5.7 2:25 0.042 19:05 0.197 0.109 0.109 0.00
2/8/2018 3:25 0.6 17:05 1.2 0.9 4:35 4.1 20:15 8.0 5.6 3:25 0.041 17:05 0.188 0.102 0.102 0.09
2/9/2018 3:40 0.6 16:05 1.1 0.9 3:25 4.2 13:05 7.9 5.8 3:40 0.043 16:05 0.181 0.103 0.103 0.01
2/10/2018 4:05 0.6 10:45 1.2 0.9 5:40 4.1 21:40 8.7 5.9 4:05 0.041 21:40 0.198 0.114 0.114 0.01
2/11/2018 3:50 0.7 16:25 1.4 1.0 3:50 4.0 14:00 8.3 5.9 3:50 0.043 14:05 0.224 0.120 0.120 0.00
2/12/2018 4:10 0.7 9:00 1.2 0.9 2:00 4.2 21:00 8.0 5.6 4:05 0.048 21:00 0.191 0.102 0.102 0.00
2/13/2018 1:20 0.6 7:20 1.3 0.9 1:25 4.1 18:45 7.8 5.6 1:25 0.044 7:00 0.186 0.108 0.108 0.17
2/14/2018 4:00 0.6 19:45 1.2 0.9 2:30 4.1 12:40 8.2 5.6 4:00 0.043 13:00 0.215 0.105 0.105 0.15
2/15/2018 1:45 0.6 16:55 1.2 0.9 3:05 4.1 17:30 7.5 5.7 1:45 0.043 16:55 0.191 0.104 0.104 0.00
2/16/2018 4:45 0.6 11:05 1.3 0.9 4:45 4.2 11:00 8.6 5.7 4:45 0.043 11:05 0.224 0.103 0.103 0.15
2/17/2018 3:35 0.6 15:25 1.3 1.0 1:50 4.1 12:10 8.3 6.1 3:35 0.044 15:25 0.226 0.123 0.123 0.32
2/18/2018 4:55 0.6 11:30 1.2 1.0 5:25 4.2 11:45 8.1 6.0 5:10 0.045 11:45 0.228 0.122 0.122 0.01
2/19/2018 0:30 0.6 11:00 1.3 1.0 4:35 4.1 15:30 8.1 5.6 0:30 0.038 15:30 0.221 0.113 0.113 0.00
2/20/2018 5:00 0.6 16:35 1.3 1.0 3:30 4.0 19:35 7.7 5.6 2:40 0.041 16:35 0.210 0.110 0.110 0.00
2/21/2018 1:45 0.6 18:55 1.2 0.9 1:30 4.1 20:40 7.4 5.4 1:50 0.040 20:25 0.194 0.103 0.103 0.00
2/22/2018 2:40 0.6 18:10 1.2 0.9 4:45 4.1 15:05 7.7 5.5 2:40 0.043 18:10 0.188 0.102 0.102 0.07
2/23/2018 0:45 0.7 9:05 1.3 1.0 3:50 4.0 16:55 7.4 5.4 0:45 0.050 8:55 0.173 0.104 0.104 0.01
2/24/2018 2:55 0.7 10:55 1.2 0.9 4:50 4.1 12:30 7.9 5.6 1:45 0.051 10:55 0.202 0.106 0.106 0.13
2/25/2018 4:45 0.7 20:20 1.3 1.0 3:10 4.2 9:40 8.7 5.9 4:45 0.049 20:20 0.247 0.120 0.120 0.11
2/26/2018 0:15 0.7 13:30 1.4 1.0 4:15 4.0 9:30 8.1 5.6 0:15 0.050 13:30 0.254 0.120 0.120 0.00
2/27/2018 13:40 0.7 17:50 1.4 1.0 1:40 3.8 17:55 7.7 5.6 4:35 0.064 17:50 0.249 0.118 0.118 0.19
2/28/2018 0:50 0.7 18:40 1.3 1.0 2:55 3.8 17:20 7.9 5.6 3:55 0.048 19:05 0.207 0.116 0.116 0.35
ReportAvg 1.0 5.8 0.113
ReportTotal 3.157 2.84
ADS Environmental Services
Pipe Height: 12.00
REN_MH6704\mp1\DFINAL (inches) REN_MH6704\mp1\VFINAL (feet/sec) REN_MH6704\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
3/1/2018 2:45 0.6 18:00 1.3 1.0 3:00 4.0 17:50 7.9 5.7 2:45 0.039 17:45 0.224 0.119 0.119 0.01
3/2/2018 3:55 0.8 19:10 1.2 1.0 3:15 4.1 18:55 7.6 5.6 3:55 0.056 18:55 0.202 0.116 0.116 0.07
3/3/2018 4:35 0.8 11:05 1.3 1.0 2:35 4.2 13:15 8.3 5.8 2:30 0.059 13:15 0.231 0.130 0.130 0.00
3/4/2018 3:30 0.7 13:30 1.3 1.0 4:05 3.7 11:50 8.1 5.9 3:30 0.049 13:30 0.231 0.135 0.135 0.12
3/5/2018 2:40 0.8 12:40 1.3 1.0 3:05 3.9 19:25 8.0 5.7 2:40 0.054 20:15 0.206 0.116 0.116 0.00
3/6/2018 4:05 0.6 20:15 1.3 1.0 3:25 3.9 20:40 8.0 5.5 4:00 0.041 20:40 0.219 0.106 0.106 0.00
3/7/2018 1:55 0.6 19:55 1.4 1.1 2:10 3.9 10:20 7.8 5.5 2:05 0.039 19:55 0.266 0.133 0.133 0.03
3/8/2018 2:30 0.8 21:05 1.5 1.2 2:45 3.8 18:15 8.5 5.7 2:30 0.061 18:15 0.293 0.153 0.153 0.37
3/9/2018 13:10 0.8 17:20 1.3 1.1 2:20 4.0 19:40 7.9 5.6 2:15 0.068 19:40 0.243 0.124 0.124 0.00
3/10/2018 2:55 0.8 11:10 1.5 1.1 3:35 3.6 13:55 8.3 5.5 2:55 0.050 11:10 0.280 0.141 0.141 0.00
3/11/2018 5:25 0.8 11:05 1.4 1.1 4:55 3.8 11:35 7.5 5.4 5:25 0.061 11:05 0.247 0.134 0.134 0.00
3/12/2018 4:20 0.8 18:20 1.4 1.1 1:50 3.8 20:05 7.5 5.3 2:35 0.061 19:45 0.228 0.122 0.122 0.00
3/13/2018 3:50 0.8 19:35 1.3 1.0 3:15 3.8 19:40 7.7 5.5 3:50 0.059 17:45 0.219 0.119 0.119 0.31
3/14/2018 1:05 0.8 20:05 1.3 1.0 0:55 3.9 6:45 7.4 5.5 0:55 0.061 20:05 0.215 0.121 0.121 0.04
3/15/2018 0:45 0.8 11:45 1.4 1.1 1:30 4.3 20:45 7.4 5.4 0:45 0.064 20:45 0.222 0.127 0.127 0.00
3/16/2018 3:25 0.9 17:10 1.3 1.1 0:35 4.1 9:10 7.2 5.5 3:25 0.070 17:25 0.215 0.134 0.134 0.00
3/17/2018 4:30 0.8 20:05 1.5 1.1 4:05 4.3 19:05 7.9 5.7 4:30 0.070 19:50 0.241 0.142 0.142 0.00
3/18/2018 3:45 0.8 10:05 1.5 1.2 2:30 4.2 13:30 8.6 6.0 3:45 0.061 11:00 0.299 0.157 0.157 0.00
3/19/2018 0:25 0.8 19:00 1.4 1.1 1:50 4.1 12:35 8.5 5.5 23:30 0.065 19:00 0.232 0.128 0.128 0.00
3/20/2018 23:30 0.8 19:45 1.3 1.1 2:25 3.8 10:55 7.8 5.4 2:25 0.057 10:55 0.232 0.126 0.126 0.00
3/21/2018 3:35 0.8 19:40 1.3 1.0 22:50 4.0 18:05 7.7 5.4 3:35 0.057 18:05 0.217 0.117 0.117 0.10
3/22/2018 2:20 0.8 18:35 1.3 1.1 1:35 4.0 9:40 7.6 5.5 3:20 0.060 9:40 0.218 0.125 0.125 0.48
3/23/2018 1:05 0.8 11:30 1.3 1.0 2:10 3.9 7:15 7.9 5.5 2:35 0.059 11:30 0.236 0.121 0.121 0.31
3/24/2018 0:50 0.8 16:35 1.3 1.1 4:55 4.1 13:35 8.5 5.7 2:10 0.061 13:35 0.246 0.136 0.136 0.28
3/25/2018 5:50 0.7 19:30 1.3 1.1 4:40 4.1 10:45 8.1 5.7 5:50 0.053 11:15 0.241 0.131 0.131 0.01
3/26/2018 23:15 0.8 16:40 1.3 1.0 1:10 4.1 20:10 7.7 5.6 23:35 0.056 19:50 0.221 0.121 0.121 0.17
3/27/2018 0:05 0.7 19:40 1.3 1.0 1:25 4.1 19:40 8.0 5.5 0:05 0.054 19:40 0.242 0.119 0.119 0.02
3/28/2018 23:55 0.7 19:25 1.3 1.0 3:20 4.1 18:25 7.9 5.5 0:10 0.055 18:25 0.219 0.116 0.116 0.01
3/29/2018 0:00 0.7 13:40 1.3 1.0 4:05 4.2 18:00 8.7 5.5 0:00 0.055 13:40 0.220 0.115 0.115 0.00
3/30/2018 0:05 0.7 19:20 1.3 1.0 1:25 4.1 10:55 7.5 5.5 0:05 0.052 17:55 0.203 0.120 0.120 0.00
3/31/2018 4:10 0.8 7:35 1.3 1.1 0:55 4.1 11:20 8.0 5.7 0:45 0.059 11:20 0.222 0.130 0.130 0.00
ReportAvg 1.1 5.6 0.127
ReportTotal 3.935 2.33
ADS Environmental Services
Pipe Height: 12.00
REN_MH6704\mp1\DFINAL (inches) REN_MH6704\mp1\VFINAL (feet/sec) REN_MH6704\mp1\QFINAL (MGD - Total MG) REN_RG\mp1\RAIN (inches)
Date Time Min. Time Max. Average Time Min. Time Max. Average Time Min. Time Max. Average Total Total
4/1/2018 18:30 0.8 10:45 1.3 1.0 3:45 4.0 10:20 8.1 5.7 3:45 0.059 10:20 0.242 0.128 0.128 0.10
4/2/2018 22:35 0.7 19:20 1.3 1.0 2:35 4.0 19:20 7.9 5.6 22:30 0.056 19:20 0.244 0.122 0.122 0.00
4/3/2018 7:10 0.8 18:20 1.3 1.0 1:00 4.1 17:10 7.7 5.5 0:45 0.060 9:20 0.205 0.110 0.110 0.00
4/4/2018 23:25 0.6 19:20 1.4 1.0 0:20 4.0 16:30 7.8 5.5 23:25 0.040 19:20 0.238 0.120 0.120 0.39
4/5/2018 12:20 0.7 20:20 1.2 0.9 0:50 4.1 19:10 8.2 5.6 22:05 0.057 19:25 0.190 0.108 0.108 0.25
4/6/2018 23:20 0.8 16:20 1.3 1.0 3:45 4.0 16:20 8.4 5.6 23:20 0.063 16:20 0.251 0.118 0.118 0.00
4/7/2018 13:55 0.7 5:25 1.4 1.0 1:15 4.1 10:15 8.2 5.8 1:15 0.058 8:55 0.237 0.130 0.130 0.88
4/8/2018 19:10 0.9 10:20 1.4 1.1 2:35 4.2 9:55 8.6 6.0 2:40 0.069 10:10 0.253 0.145 0.145 0.45
4/9/2018 21:55 0.8 9:45 1.3 1.0 1:15 4.2 10:30 7.7 5.7 3:30 0.066 9:50 0.227 0.125 0.125 0.00
4/10/2018 23:30 0.6 8:05 1.2 0.9 2:15 4.1 9:20 7.9 5.7 23:30 0.045 8:10 0.195 0.101 0.101 0.23
4/11/2018 0:20 0.6 15:35 1.2 0.9 0:45 4.0 20:20 8.0 5.7 0:30 0.041 15:30 0.186 0.095 0.095 0.31
4/12/2018 0:15 0.6 13:10 1.4 1.0 0:15 4.1 7:55 8.0 5.6 0:15 0.042 13:10 0.245 0.108 0.108 0.11
4/13/2018 0:30 0.7 5:50 1.3 1.0 4:45 4.2 13:55 8.2 5.9 0:30 0.053 9:30 0.202 0.115 0.115 0.51
4/14/2018 0:35 0.8 19:30 1.5 1.1 3:50 4.1 16:05 8.5 6.7 0:35 0.062 19:25 0.311 0.169 0.169 1.52
4/15/2018 23:35 1.0 10:25 1.5 1.2 4:10 4.9 13:40 8.7 7.0 23:40 0.102 10:25 0.300 0.189 0.189 0.21
4/16/2018 0:00 0.9 12:10 1.5 1.2 3:10 4.5 12:10 8.3 6.5 0:00 0.089 12:10 0.312 0.177 0.177 0.71
4/17/2018 22:40 0.9 7:05 1.4 1.2 2:05 4.5 12:15 8.4 6.5 22:40 0.083 7:05 0.246 0.168 0.168 0.01
4/18/2018 20:35 0.9 17:35 1.4 1.1 0:05 4.4 10:45 8.2 6.3 1:35 0.077 17:35 0.248 0.157 0.157 0.12
4/19/2018 21:25 0.9 8:35 1.4 1.1 1:25 4.4 18:25 8.3 6.3 1:35 0.083 18:25 0.259 0.148 0.148 0.00
4/20/2018 22:25 0.6 14:30 1.3 1.0 3:50 4.4 12:05 8.0 6.2 22:25 0.054 9:10 0.225 0.120 0.120 0.00
4/21/2018 23:45 0.5 9:35 1.3 1.0 3:45 4.3 17:05 8.1 6.3 23:45 0.036 9:35 0.247 0.125 0.125 0.05
4/22/2018 0:40 0.5 9:35 1.2 0.9 3:35 4.2 13:55 8.3 6.1 0:40 0.037 11:05 0.193 0.107 0.107 0.00
ReportAvg 1.0 6.0 0.131
ReportTotal 2.886 5.85
REN_RG
Located At: 3555 Ne 2nd St (see attached site report for details)
Monitoring Period: December 22, 2017 – April 22, 2018
RG Data Uptime: The data uptime achieved during the monitoring period is provided in the table below.
Entity Percentage Uptime
Raw
Percentage Uptime
Final
Depth (in) 100% 100%
Velocity (f/s) 100% 100%
Quantity (mgd) 100% 100%
Latitude: 47.484465°
Longitude:-122.171921°
Site Sketch Plan View or Photo
Additional Site Info. / Comments:
Located on paved goal of horseshoe tossing area outside of building.
NA
Antenna Location
Communication Information:
Active Drop Connections Air Quality:
Communication Type
Normal
22275.11.325
ADS Project Name:
ADS Project Number:
Renton.Carollo.I&I.WA17
Manhole Cover Manhole Frame
Manhole Material:
Manhole Diameter (Approx.):
Manhole Depth (Approx. FT):Manhole Configuration
Wireless
Pipe Material
Renton Public Works Maintenance division, in field on
horseshoe goal.
Sensors / Devices:
NA
Manhole / Pipe Information:
Installation Type:
Pressure Sensor Range (psi)
Confirmation Time:
Site Sketch Profile View or Photo
Pipe Size (H x W)
Topside / Area Photo
Rain Gauge Tipping Bucket
Pipe Size (HxW)
-
Monitoring Location (Sensors):
Depth of Flow (Wet DOF) (in)Range (Air DOF) (in)
-
Velocity Sensor Offset (in)
-
Temporary
NA
REN_RG
Access Traffic
Rain Alert III
System Characteristics
Location Type
Pipe Shape
Renton.Carollo.I&I.WA17
LightDrive
Site Access Details:
Site Address /Location:
Site Name
3555 NE 2nd St
Installation Information
Non-Standard
Monitor Series
Monitor Location:
Rain Gauge
Manhole #
Installation Date:
12.22.17
Rooftop Building
Rain Gauge Other
Map
Flow Monitoring
Site Report
-
Downlooker Physical Offset (in)Measurement Confidence (in)
-
Peak Velocity (fps)
Silt (in)
-
Installation Confirmation:
Manhole Opening Diameter (in)
Silt Type
Hydraulic Comments:
Pipe Condition:
Single
Manhole Condition:
--
ADS Environmental Services
REN_RG\mp1\RAIN (inches)
Date Total
12/22/2017 0.10
12/23/2017 0.00
12/24/2017 0.00
12/25/2017 0.14
12/26/2017 0.17
12/27/2017 0.00
12/28/2017 0.25
12/29/2017 1.57
12/30/2017 0.02
12/31/2017 0.00
ReportAvg
ReportTotal 2.25
ADS Environmental Services
REN_RG\mp1\RAIN (inches)
Date Total
1/1/2018 0.00
1/2/2018 0.01
1/3/2018 0.00
1/4/2018 0.09
1/5/2018 0.42
1/6/2018 0.24
1/7/2018 0.38
1/8/2018 0.14
1/9/2018 0.46
1/10/2018 0.22
1/11/2018 1.04
1/12/2018 0.20
1/13/2018 0.02
1/14/2018 0.00
1/15/2018 0.04
1/16/2018 0.26
1/17/2018 0.79
1/18/2018 0.40
1/19/2018 0.10
1/20/2018 0.10
1/21/2018 0.16
1/22/2018 0.34
1/23/2018 0.79
1/24/2018 0.51
1/25/2018 0.14
1/26/2018 0.36
1/27/2018 0.61
1/28/2018 0.07
1/29/2018 0.90
1/30/2018 0.00
1/31/2018 0.00
ReportAvg
ReportTotal 8.79
ADS Environmental Services
REN_RG\mp1\RAIN (inches)
Date Total
2/1/2018 0.66
2/2/2018 0.04
2/3/2018 0.31
2/4/2018 0.02
2/5/2018 0.04
2/6/2018 0.00
2/7/2018 0.00
2/8/2018 0.09
2/9/2018 0.01
2/10/2018 0.01
2/11/2018 0.00
2/12/2018 0.00
2/13/2018 0.17
2/14/2018 0.15
2/15/2018 0.00
2/16/2018 0.15
2/17/2018 0.32
2/18/2018 0.01
2/19/2018 0.00
2/20/2018 0.00
2/21/2018 0.00
2/22/2018 0.07
2/23/2018 0.01
2/24/2018 0.13
2/25/2018 0.11
2/26/2018 0.00
2/27/2018 0.19
2/28/2018 0.35
ReportAvg
ReportTotal 2.84
ADS Environmental Services
REN_RG\mp1\RAIN (inches)
Date Total
3/1/2018 0.01
3/2/2018 0.07
3/3/2018 0.00
3/4/2018 0.12
3/5/2018 0.00
3/6/2018 0.00
3/7/2018 0.03
3/8/2018 0.37
3/9/2018 0.00
3/10/2018 0.00
3/11/2018 0.00
3/12/2018 0.00
3/13/2018 0.31
3/14/2018 0.04
3/15/2018 0.00
3/16/2018 0.00
3/17/2018 0.00
3/18/2018 0.00
3/19/2018 0.00
3/20/2018 0.00
3/21/2018 0.10
3/22/2018 0.48
3/23/2018 0.31
3/24/2018 0.28
3/25/2018 0.01
3/26/2018 0.17
3/27/2018 0.02
3/28/2018 0.01
3/29/2018 0.00
3/30/2018 0.00
3/31/2018 0.00
ReportAvg
ReportTotal 2.33
ADS Environmental Services
REN_RG\mp1\RAIN (inches)
Date Total
4/1/2018 0.10
4/2/2018 0.00
4/3/2018 0.00
4/4/2018 0.39
4/5/2018 0.25
4/6/2018 0.00
4/7/2018 0.88
4/8/2018 0.45
4/9/2018 0.00
4/10/2018 0.23
4/11/2018 0.31
4/12/2018 0.11
4/13/2018 0.51
4/14/2018 1.52
4/15/2018 0.21
4/16/2018 0.71
4/17/2018 0.01
4/18/2018 0.12
4/19/2018 0.00
4/20/2018 0.00
4/21/2018 0.05
4/22/2018 0.00
ReportAvg
ReportTotal 5.85
RDII Analysis This section describes an evaluation of wet weather impacts on system flows by summarizing excess flow rates and volumes from the studied sewer shed areas (basins) associated with each flow monitoring site during rain events that occurred during the study period. This section also describes an evaluation of dry weather flow data for purposes of determining base wastewater flows (to compare wet weather flows against).
Base Dry Weather Analysis Prior to conducting a wet weather analysis, a dry weather analysis must first be performed by reviewing data obtained during dry weather conditions. For this analysis, a dry day is defined as any day in which there was less than 0.10 in. of rain in the previous day, less than 0.40 in. of rain in the previous three days, and less than 1.00 in. of rain in the previous five days. This process automatically eliminates the selection of most wet weather events and the periods associated with recovery from these events. Once the initial dry days are selected, they are compared to one another to make sure that the flow pattern for each day is repeatable. Any days that have an inconsistent flow pattern are removed from consideration. The resulting dry days are then averaged to establish an average diurnal flow pattern from the site. The dry weather analysis evaluates the weekday pattern separate from the weekend pattern to account for differences often observed. Dry weather flows were evaluated for each basin during the study period. Recorded flow rates from the sanitary sewer monitoring location for each dry day are overlaid on a hydrograph, enabling a typical or average dry day flow (ADF) and minimum daily flow (MDF) to be determined for Weekdays and Weekends (gross flow basis) as depicted in Figure 1.1 for basin REN_MH1360. .
Figure 1.1 summarizes the gross flow values for ADF for weekdays and weekends. It is possible to estimate the volume of flow from each sewer shed area that is attributable to groundwater infiltration (or Base Infiltration – BI) based on an evaluation of ADF and MDF values against expected wastewater flow generation rates from sewer shed areas
comprised of typical residential/commercial land uses. The most refined empirical method to estimate BI is the Stevens/Schutzbach equation. The Equation below is the Stevens/Schutzbach equation that was used to estimate BI from these areas.
BI = ______0.4 * MDF________
1- 0.6 (MDF/ADF) ^ ADF 0.7 Reliability of BI calculations decreases in non-residential basins and in basins where the flow meter measures flow from cycling pump stations or other unusual flow patterns. It is important to understand that when only using flow data, BI is considered an estimate and only through more rigorous means of flow isolations (e.g. plugging all lateral connections in isolated small areas of the system and physically measuring continued flow during the plugging period) can actual BI values be determined. The BI as a percentage of average daily flow is presented below is Tables 1.1 and Table 1.2. The dry day weather flow for each site’s tributary area (or gross flow which includes any upstream basins) is presented in Table 1.1 below. Weekday dry days were calculated separately from weekend dry days due to the sites having different hydraulic patterns on weekdays compared to weekends. Table 1.2 presents the net dry weather flow summary for each basin (or net flow which subtracts flow from upstream basins). In order to isolate flows from Basins REN_MH3625 and REN_MH1360 subtraction of upstream site flows was required. To calculated net flow for these basins the following calculations were made: REN_MH1360 = REN_MH1360 - REN_MH4628; Also, REN_MH3625 = REN_MH3625 - REN_MH5505.
Base
Infiltration/ADF (%)
Basin Weekdays Weekends Weekdays Weekends Weekdays Weekends Weekdays Weekends Weekdays
REN_MH0166 0.015 0.005 0.007 0.002 0.027 0.011 0.002 0.002 13%
REN_MH0286 0.073 0.048 0.055 0.045 0.095 0.053 0.052 0.045 71%
REN_MH0537 0.317 0.317 0.207 0.204 0.399 0.408 0.164 0.161 52%
REN_MH1360 0.203 0.211 0.126 0.121 0.257 0.283 0.104 0.096 51%
REN_MH1763 0.167 0.178 0.071 0.080 0.233 0.273 0.054 0.061 32%
REN_MH2116 0.574 0.571 0.411 0.391 0.654 0.721 0.315 0.292 55%
REN_MH2171 0.184 0.146 0.093 0.098 0.282 0.188 0.072 0.086 39%
REN_MH2252 0.648 0.674 0.432 0.390 0.838 0.930 0.311 0.259 48%
REN_MH2999 0.175 0.186 0.122 0.126 0.214 0.232 0.106 0.108 61%
REN_MH3216 0.050 0.046 0.022 0.023 0.070 0.072 0.020 0.020 40%
REN_MH3625 0.533 0.587 0.301 0.313 0.738 0.817 0.206 0.205 39%
REN_MH4628 0.163 0.171 0.118 0.117 0.196 0.214 0.104 0.101 64%
REN_MH4646 0.296 0.205 0.171 0.168 0.229 0.246 0.158 0.153 53%
REN_MH5302 1.689 1.690 1.078 0.981 2.012 2.084 0.628 0.540 37%
REN_MH5505 0.211 0.212 0.167 0.157 0.238 0.250 0.150 0.138 71%
REN_MH5519 0.319 0.297 0.187 0.174 0.385 0.399 0.142 0.133 45%
REN_MH6041 0.047 0.041 0.017 0.017 0.067 0.060 0.014 0.015 30%
REN_MH6704 0.114 0.129 0.063 0.066 0.157 0.190 0.053 0.054 46%
Dry Weather Flow Summary (Gross)
Average Daily Flow
(mgd)
Minimum Daily Flow
(mgd)
Maximum Daily Flow
(mgd)
Base Infiltration
(mgd)
Table 1.1 Summarizes the base infiltration and minimum, average, and maximum daily flows.
Base
Infiltration/ADF (%)
Basin Weekdays Weekends Weekdays Weekends Weekdays Weekends Weekdays Weekends Weekdays
REN_MH0166 0.015 0.005 0.007 0.002 0.027 0.011 0.002 0.002 13%
REN_MH0286 0.073 0.048 0.055 0.045 0.095 0.053 0.052 0.045 71%
REN_MH0537 0.317 0.317 0.207 0.204 0.399 0.408 0.164 0.161 52%
REN_MH1360
(REN_MH1360‐REN_MH4628)0.041 0.040 0.007 0.002 0.620 0.740 0.000 0.000 <5%
REN_MH1763 0.167 0.178 0.071 0.080 0.233 0.273 0.054 0.061 32%
REN_MH2116 0.574 0.571 0.411 0.391 0.654 0.721 0.315 0.292 55%
REN_MH2171 0.184 0.146 0.093 0.098 0.282 0.188 0.072 0.086 39%
REN_MH2252 0.648 0.674 0.432 0.390 0.838 0.930 0.311 0.259 48%
REN_MH2999 0.175 0.186 0.122 0.126 0.214 0.232 0.106 0.108 61%
REN_MH3216 0.050 0.046 0.022 0.023 0.070 0.072 0.020 0.020 40%
REN_MH3625
(REN_MH3625‐REN_MH5505)0.322 0.375 0.131 0.152 0.500 0.572 0.056 0.067 17%
REN_MH4628 0.163 0.171 0.118 0.117 0.196 0.214 0.104 0.101 64%
REN_MH4646 0.296 0.205 0.171 0.168 0.229 0.246 0.158 0.153 53%
REN_MH5302 1.689 1.690 1.078 0.981 2.012 2.084 0.628 0.540 37%
REN_MH5505 0.211 0.212 0.167 0.157 0.238 0.250 0.150 0.138 71%
REN_MH5519 0.319 0.297 0.187 0.174 0.385 0.399 0.142 0.133 45%
REN_MH6041 0.047 0.041 0.017 0.017 0.067 0.060 0.014 0.015 30%
REN_MH6704 0.114 0.129 0.063 0.066 0.157 0.190 0.053 0.054 46%
Dry Weather Flow Summary (Net)
Average Daily Flow
(mgd)
Minimum Daily Flow
(mgd)
Maximum Daily Flow
(mgd)
Base Infiltration
(mgd)
Table 1.2 Summarizes the net base infiltration and net minimum, average, and maximum daily flows.
Wet Weather Analysis A wet weather analysis is performed by comparing specific wet weather events to average dry weather flows (ADF). Four (4) rain events larger than one (1) inch were recorded and evaluated during the monitoring period. Based on these events, an analysis was conducted to characterize the impact of wet weather on flow measured in the basins. Rain totals for each of the Four (4) storms are presented in Table 1.3.
Rain Event Totals
RG
(in)
1/23/2018 1.48
3/21/2018 1.17
4/7/2018 1.33
4/15/2018 2.95 Table 1.3 Storm Event Rain Totals Recorded flow rates for a specific storm event are plotted against average dry weather conditions. The difference observed represents the rain-dependent inflow and infiltration (RDII or I/I) entering the sanitary sewer system upstream from this monitoring location and is called a storm hydrograph. Figure 1.2 depicts a storm hydrograph for site/basin REN_MH1360 during the storm on April 13, 2018.
Figure 1.2
Figure 1.2 Storm hydrograph for site REN_MH1360 I/I calculations are made for each storm event, as shown in the colored bands above. The first period following the onset of rain is referred to as the Storm Period. The following period is referred to as Recovery 1, and the next period is referred to as Recovery 2. The Recovery 2 period was restricted as needed to not overlap the next storm. The entire period including storm and events 1 and 2 is thie Event period. The storm hydrograph for this location showed a somewhat delayed but significant flow response to the rainfall during the April 13, 2018 storm. The brown line shown above displays the Gross I/I, while the lighter blue line displays the Net I/I contributed at the site after the flow was isolated from the upstream basin by subtracting flows upstream. For each storm event a pre-compensation (or “precomp”) of the ADF data pattern occurs just before the storm and is highlighted by the gray bar in Figure 1.2. The average dry weekend or weekday is moved up or down as necessary to obtain the best fit with the flow in the sewer just before the storm. This is done to estimate and compare against the dry flow pattern that “would have” occurred if the storm did not occur. In Figure 1.2, the upward shift or positive “precomp+” of the comparator ADF data is evident. This effectively isolates only the truly rain storm dependent I/I (or RDII) by ignoring the already elevated flow rate present at the onset of the storm.
RDII Once the calculations were complete for each storm, the Net RDII per storm event were graphed. The RDII results per storm event (MG) are show in Figures 1.3 and Table 1.4 and are based on the entire event periods (storm periods plus recovery periods). Figure 1.3 is sorted from high to low based on the largest storm that occurred on April 13, 2018.
Figure 1.3
NetII Volume Event for Various Storms (MG)
1/23/2018
(1.48 in)
3/21/2018
(1.17 in)
4/7/2018
(1.33 in)
4/13/2018
(2.95 in)
REN_MH0166 0.64 0.14 0.18 1.21
REN_MH0286 0.02 0.01 0.04 0.12
REN_MH0537 0.22 0.04 0.07 0.20
REN_MH1360 0.06 <0.01 0.85 0.48
REN_MH1763 0.47 0.05 0.06 0.34
REN_MH2116 0.97 0.40 1.11 2.82
REN_MH2171 0.30 0.08 0.19 0.85
REN_MH2252 1.08 0.19 0.58 2.92
REN_MH2999 0.13 0.10 0.17 0.43
REN_MH3216 0.03 0.02 0.02 0.07
REN_MH3625 0.28 0.09 0.25 1.05
REN_MH4628 0.57 0.05 0.17 1.42
REN_MH4646 0.09 0.05 0.07 0.20
REN_MH5302 1.49 0.66 2.12 5.47
REN_MH5505 0.34 0.06 0.20 1.03
NetII Volume Event for Various Storms (MG)
1/23/2018
(1.48 in)
3/21/2018
(1.17 in)
4/7/2018
(1.33 in)
4/13/2018
(2.95 in)
REN_MH5519 0.04 0.02 0.13 0.04
REN_MH6041 0.09 0.01 0.05 0.16
REN_MH6704 0.10 0.03 0.06 0.28
Total 6.92 2.00 6.32 19.08
Table 1.4 Net II Volume Events for Various Storms (MG).
Normalized RDII To enable a comparison of RDII between basins of differing sizes, the RDII volumes for each basin were normalized by dividing each basin’s net RDII values by the area of each basin (acres); then dividing by inches of rainfall to yield volume of rainfall. This yielded the % rainfall entering the basin collection system. Table 1.5 summarizes the Acreage (used in this analysis) and pipe length associated with each basin. A summary of the normalized RDII in each basin during each storm event is summarized in Figure 1.4 and Table 1.6. Figure 1.4 is sorted from high to low based on the largest storm that occurred on April 13, 2018.
Basin Pipe Length Acreage
MH0166 7848 124
MH0286 7199 138
MH0537 59708 353
MH1360 30805 171
MH1763 53835 323
MH2116 76537 463
MH2171 27132 158
MH2252 40774 722
MH2999 27711 224
MH3216 6244 56
MH3625 86021 594
MH4628 20489 113
MH4646 15397 96
MH5302 36717 383
MH5505 23462 144
MH5519 12905 93
MH6041 13162 64
MH6704 20191 91Table 1.5 Basin Acreage and Pipe Length.
Figure 1.4
Normalized NetII Volume Event for Various Storms (%Rainfall)
1/23/2018
(1.48 in)
3/21/2018
(1.17 in)
4/7/2018
(1.33 in)
4/13/2018
(2.95 in)
REN_MH0166 12.84 3.65 4.01 12.20
REN_MH0286 0.31 0.29 0.83 1.09
REN_MH0537 1.53 0.35 0.54 0.70
REN_MH1360 0.92 <0.01 1.38 3.48
REN_MH1763 3.63 0.52 0.54 1.30
REN_MH2116 5.22 2.70 6.61 7.59
REN_MH2171 4.67 1.52 3.30 6.70
REN_MH2252 3.71 0.81 2.22 5.04
REN_MH2999 1.49 1.35 2.10 2.38
REN_MH3216 1.22 1.36 1.17 1.56
REN_MH3625 1.18 0.49 1.17 2.20
REN_MH4628 12.56 1.34 4.17 15.65
REN_MH4646 2.22 1.70 1.96 2.59
REN_MH5302 9.71 5.43 15.30 17.84
REN_MH5505 5.87 1.31 3.85 8.89
REN_MH5519 1.15 0.67 3.71 0.55
REN_MH6041 3.55 0.69 2.23 3.18
REN_MH6704 2.72 0.90 1.95 3.83
Table 1.6 Normalized Net II Volume Events for Various Storms (%rainfall).
Wet Season Peaking Factors A hydraulic analysis was performed at each flow-monitoring site using gross wastewater flows to evaluate the entire tributary area for contribution of excess flow. The basis of this evaluation was to compare the peak-hour to average dry day flow ratios over the study period. The weekend or weekday ADF was selected for comparison based depending on if the peak hour occurred on a weekday or weekend. These flows are presented in Table 1.7. The Gross RDII peaking factors (defined as Gross Peak Hour / Gross ADF) are shown in Figure 1.5
Basin Gross ADF
(mgd)
Gross
Peak Hour
(mgd)
Day Peak
Hour
Occurred
MH0166 0.010 1.21 Weekday
MH0286 0.073 0.13 Weekday
MH0537 0.317 0.55 Weekday
MH1360 0.203 1.00 Weekday
MH1763 0.167 0.68 Weekday
MH2116 0.574 2.21 Weekday
MH2171 0.184 0.78 Weekday
MH2252 0.648 2.80 Weekday
MH2999 0.175 0.56 Weekday
MH3216 0.050 0.22 Weekday
MH3625 0.587 1.56 Weekend
MH4628 0.163 0.76 Weekday
MH4646 0.296 0.34 weekend
MH5302 1.689 5.11 Weekday
MH5505 0.212 0.64 Weekend
MH5519 0.319 0.39 Weekday
MH6041 0.047 0.30 Weekday
MH6704 0.114 0.38 Weekday Table 1.6 ADF and Peak Hour Flow
Figure 1.5 Peak Hour to Average Ratio
The net RDII peaking factors for these locations range from 1.2 to 80.3. REN_MH0166 had the most significant peaking factor due to a combination of RDII response and occasional dry weather flow surges that may have been coincident with rain responses.
Wet Weather RDI/I Volume Summary and Prioritization
RDII was evaluated for each basin during the four principal storm events. The evaluation of these basins was done based on the normalized RDII volumes for each basin.
Table 1.7 summarizes the BI as the percentage of ADF, net RDII, peaking factor (Gross Peak/ADF) and Normalized net RDII that occurred in each basin during the largest storm event which occurred on April 13, 2018.
Basin
Base
Infiltration/ADF
(%)
Gross Peak
Hour/ADF
Net RDII
(MG)
Normalized Net
RDII (%Rainfall )
REN_MH0166 13% 80.3 1.21 12.20
REN_MH0286 71% 1.8 0.12 1.09
REN_MH0537 52% 1.7 0.20 0.70
REN_MH1360 <5% 4.9 0.48 3.48
REN_MH1763 32% 4.1 0.34 1.30
REN_MH2116 55% 3.9 2.82 7.59
REN_MH2171 39% 4.3 0.85 6.70
Basin
Base
Infiltration/ADF
(%)
Gross Peak
Hour/ADF
Net RDII
(MG)
Normalized Net
RDII (%Rainfall )
REN_MH2252 48% 4.3 2.92 5.04
REN_MH2999 61% 3.2 0.43 2.38
REN_MH3216 40% 4.4 0.07 1.56
REN_MH3625 17% 2.7 1.05 2.20
REN_MH4628 64% 4.6 1.42 15.65
REN_MH4646 53% 1.2 0.20 2.59
REN_MH5302 37% 3.0 5.47 17.84
REN_MH5505 71% 3.0 1.03 8.89
REN_MH5519 45% 1.2 0.04 0.55
REN_MH6041 30% 6.4 0.16 3.18
REN_MH6704 46% 3.4 0.28 3.83
Table 1.7 RDII Results summary There are seven locations with greater than 50% of their ADF comprised of BI. This suggests that groundwater infiltration is a predominant issue in these locations. The above net flow peaking factor yields basin REN_MH0166 as the highest priority basin for future evaluation for possible direct sources of inflow (e.g. areas drains or storm connection directly leading to the sanitary sewer). The normalized net RDII suggest basins REN_MH0166, REN_MH4628, REN_MH5302 and REN_MH4628 are the highest priority basins for future evaluation for RDII reduction. This may include CCTV verification of live leaks and lining of pipes, manholes and lateral connections.
LRWWMP | TM 1 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment B
ADWF DEVELOPMENT REVIEW PACKET
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix H
TM 2 - MODEL DEVELOPMENT AND
CALIBRATION
TITLE | TM 1 | CLIENT
City of Renton
LRWWMP
Technical Memorandum ͮ
MODEL DEVELOPMENT AND
CALIBRATION
DRAFT | September ͮͬͭ͵
City of Renton
LRWWMP
Technical Memorandum ͮ
MODEL DEVELOPMENT AND CALIBRATION
DRAFT | September ͮͬͭ͵
This document is released for the
purpose of information exchange review
and planning only under the authority of
Daniel L. Reisinger, September ͮͬ, ͮͬͭ͵
Washington PE License No. ͱͯͲͱͳ.
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | iii
Contents
Technical Memorandum 2 Model Development and Calibration 2-1
ͮ.ͭ Hydraulic Model Overview ͮ‐ͭ
ͮ.ͭ.ͭ Hydraulic Modeling Software ͮ‐ͭ
ͮ.ͭ.ͮ Elements of the Hydraulic Model ͮ‐ͭ
ͮ.ͮ Hydraulic Model Expansion and refinement ͮ‐ͮ
ͮ.ͮ.ͭ Model Update Process ͮ‐ͯ
ͮ.ͮ.ͮ Wastewater Flow Allocation ͮ‐Ͱ
ͮ.ͮ.ͯ Inflow and Infiltration: Time‐Area Model A and RDI ͮ‐ͱ
ͮ.ͯ Hydraulic Model Calibration ͮ‐ͳ
ͮ.ͯ.ͭ Calibration Standards ͮ‐ͳ
ͮ.ͯ.ͮ Wet Weather Calibration Standards ͮ‐ͳ
ͮ.ͯ.ͯ Dry Weather Flow Calibration ͮ‐ʹ
ͮ.ͯ.Ͱ Wet Weather Flow Calibration ͮ‐ͭͬ
ͮ.ͯ.ͱ Hydraulic Model Calibration Summary ͮ‐ͭͱ
Attachments
Attachment C RDII Parameters
Attachment D Negative Slope Pipelines List
Attachment E Basin Diurnal Patterns
Attachment F Dry Weather Calibration Results
Attachment G Wet Weather Calibration Results
Tables
Table ͮ.ͭ Dry Weather Flow Calibration Results ͮ‐͵
Table ͮ.ͮ Wet Weather Flow Calibration Results ͮ‐ͭͯ
Figures
Figure ͮ.ͭ Updated Model ͮ‐ͯ
Figure ͮ.ͮ Model A and RDI Model ͮ‐Ͳ
Figure ͮ.ͯ Example of Dry Weather Calibration (Site MHͱͯͬͮ) ͮ‐ͭͬ
Figure ͮ.Ͱ Example of Wet Weather Calibration (Site MHͱͯͬͮ) ͮ‐ͭͰ
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | v
Abbreviations
ADWF Average Dry Weather Flow
BWF base wastewater flow
City City of Renton
CIWEM Chartered Institution of Water and Environmental Management
DWF dry weather flow
FRC fast response corresponding
gpd/ac gallons per day per acre
I/I Inflow and Infiltration
LRWWMP Long Range Wastewater Management Plan
mgd million gallons per day
PE Person Equivalent
RDI Rainfall Dependent Infiltration
RDII Rainfall Derived Infiltration and Inflows
SRC slow response corresponding
TM Technical Memorandum
TP treatment plant
UDG Urban Drainage Group
WaPUG Wastewater Planning Users Group
WWF wet weather flow
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͭ
Technical Memorandum 2
MODEL DEVELOPMENT AND CALIBRATION
This Technical Memorandum (TM) describes the City of Renton’s (City) collection system
infrastructure, as well as the update and calibration of the City's collection system hydraulic
model.
2.1 Hydraulic Model Overview
A wastewater collection system model is a simplified representation of the real sewer system.
Wastewater system models can assess the conveyance capacity of the collection system. The
model can be used to size new infrastructure. In addition, sewer system models can perform
“what if” scenarios to assess the impacts of future developments and land use changes. The
City’s collection system hydraulic model was updated and expanded using a multi‐step process
utilizing data from a variety of sources. This section summarizes the hydraulic model
development process, including a description of the modeled collection system, the hydraulic
model elements, and the model creation process.
2.1.1 Hydraulic Modeling Software
The City's system hydraulic model was developed using the Mike Urban hydraulic modeling
software package, developed by DHI. The latest version (ͮͬͭͲ) of Mike Urban was used for the
hydraulic model update. More information about the modeling software can be found in the
Mike Urban Collection Systems Guide1. The Mike Urban model is a full pipe model including all of
the City’s GIS. The hydraulic modeling engine used within the Mike Urban software package is
MOUSE, which is widely used throughout the world for planning, analysis, and design related to
stormwater runoff, combined sewers, sanitary sewers, and other drainage systems.
2.1.2 Elements of the Hydraulic Model
The following provides a brief overview of the various elements of the hydraulic model and the
required input parameters associated with each. Figure ͮ.ͭ shows the hydraulic model, and
associated infrastructure described above.
Junctions: Sewer manholes, cleanouts, and other locations where pipe sizes change or
where pipelines intersect are represented by junctions in the hydraulic model. Required
inputs for junctions include rim elevation, invert elevation, diameter, and surcharge
depth (used to represent pressurized systems). Junctions are also used at locations
where flows are split or diverted between two or more downstream links.
Pipes: Gravity sewers and force mains are represented as pipes in the hydraulic model.
Input parameters for pipes include length, friction factor (e.g., Manning’s n for gravity
1 Collection System Guide, Mike Urban ͮͬͭͲ.
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐ͮ | SEPTEMBER ͮͬͭ͵ | DRAFT
mains, Hazen Williams C for force mains), invert elevations, diameter, shape, and
whether or not the pipe is a force main.
Storage Nodes: For sewer system modeling, storage nodes typically are used to
represent pump station wet wells (although other storage basins, etc., can be modeled
as storage nodes). Input parameters for storage nodes include invert elevation, wet well
depth, and wet well cross section or a depth area relationship.
Pumps: Pumps are included in the hydraulic model as links. Input parameters for pumps
include pump curves and operational controls.
Outfalls: Outfalls represent areas where flow leaves the system. For sewer system
modeling, an outfall typically represents an overflow point or the connection to the
influent pump station at a wastewater treatment plant (TP).
Rain Gauges: Rain gauges are rainfall input locations for the hydraulic model for
simulation of wet weather flows (WWF) that are historical, projected, or theoretical
hourly rainfall events.
Subcatchments: Subcatchments represent the hydrologic units of land area whose
topography and drainage characteristics direct flow into a single discharge point in the
sewer system. Subcatchments can be used to route rainfall runoff to the system, using
parameters that determine how much and how fast stormwater inflow and infiltration
(I/I) enters the sewer system.
Inflows: There are two primary flow sources that enter into the collection system, which
are input through individual junctions (and storage nodes) in the model:
- Dry Weather. Dry weather inflows simulate base sanitary wastewater flows and
represent the average flow. The dry weather flows (DWF) can be multiplied by up to
four patterns that vary the flow by month, day, hour, and day of the week (e.g.,
weekday or weekend). The dry weather diurnal patterns are adjusted during the dry
weather calibration process to match the known daily flow fluctuations. Two diurnal
patterns were developed for each basin, respectively representing weekday and
weekend days (see Appendix G, TM ͭ).
- Rainfall Derived Infiltration and Inflows (RDII). RDII are flows into the collection
system originating from rainfall. Several models are available in Mike Urban to
capture these effects. The models have a number of parameters that are adjusted
during the wet weather calibration process (see Section ͮ.ͮ.ͯ) to model the flows
into the collection during different storm events.
2.2 Hydraulic Model Expansion and refinement
This section describes the multi‐step process used to update the hydraulic model using recent
GIS data information and other sources, such as field surveys and as‐built drawings.
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͯ
Figure ͮ.ͭ Updated Model
2.2.1 Model Update Process
The City’s hydraulic model combines information on the physical and operational characteristics
of the wastewater collection system, and performs calculations to solve a series of mathematical
equations to simulate flows in pipes. The model update focused on adding new infrastructure
and updating diameter ad material information based on the City’s GIS.
Step ͭ: The City’s GIS shape files for the wastewater collection system were obtained.
Step ͮ: The GIS data was reviewed and formatted in Excel to allow easy update of the
Mike Urban modeling platform.
Step ͯ: The City’s GIS data was separated based on existing, modeled pipes to be
updated to match GIS data and new pipes to import into the model.
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐Ͱ | SEPTEMBER ͮͬͭ͵ | DRAFT
Step Ͱ: The collection system pipeline data and facility data were imported into the
modeling software and verified. Physical and operational data for the City’s wastewater
collection facilities was not available from the GIS data. This type of data, such as wet
well dimensions, pump stations, and other special features, was verified manually based
on calibration.
- Once all the relevant data was updated and input into the hydraulic model, the
model was reviewed to verify that the model data was input correctly and that the
flow direction and size of the modeled pipelines were logical. Additionally, the
modeled pump stations were checked to verify that they operated correctly.
- The GIS data showed several negative slope pipes. These pipelines are listed in
Attachment D. The City should field check these pipe inverts when the opportunity
arises. If numerous deficiencies are predicted in the vicinity of these pipes, a field
investigation may be warranted prior to developing projects to verify the system
deficiency.
Step ͱ: Dry weather wastewater flows were then allocated to the appropriate model
junctions. Eighteen separate flow factors were used and updated for flow monitoring
basins. These flows were scaled up or down, as necessary, to match the DWFs recorded
during the flow monitoring period during the dry weather calibration. Unmetered basins
were not updated at this time.
Step Ͳ: The hydraulic model contains run parameters that need to be set by the user at
the beginning of the project. These include run dates, time steps, reporting parameters,
output units, and flow routing method. Once the run parameters were established, the
model was debugged to ensure that it ran without errors or critical warnings.
2.2.2 Wastewater Flow Allocation
Defining the quantity of dry weather wastewater flows generated by a municipality and how the
flows are distributed throughout the collection system is an important component of the
hydraulic modeling process. Various techniques can be used to assign wastewater flows to
individual model junctions, depending on the type of data that is available. Adequate estimates
of the volume of sanitary wastewater flows are important in maintaining and sizing sewer
system facilities, both for present and future conditions. Baseline wastewater flows were
allocated (assigned to specific nodes) in the hydraulic model based on land use data provided by
the City and wastewater flow coefficients developed previously (these are described in detail in
TMͬͭ).
The flow coefficients for specific land use category were used to estimate an average DWF, as
described below:
Step ͭ: The City’s service area was broken up into ͱ,Ͱͳʹ catchments based on tax parcels
and land use. Figure ͮ.ͭ shows the catchments developed to allocate flows in the
hydraulic model, and the entirety of the hydraulic model. Each catchment represents
the geographic area that contributes flows into a single model node (i.e., trunk system
manhole).
Step ͮ: The baseline flows were calculated for each loading polygon using a Person
Equivalent (PE). The PE for each catchment was based on zoning and employment data
developed in Stantec’s ͮͬͭͱ Model Update Report, Appendix F, and additional
information can be found in Chapter Ͱ of the Long Range Wastewater Management
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͱ
Plan (LRWWMP). The total PE for each flow monitoring basin was determined based on
upstream catchments. Using the total PE in each basin, a flow factor was developed for
every basin to relate PE to Average Dry Weather Flow (ADWF) (see Appendix G, TM ͭ
for additional detail).
Step ͯ: The hydraulic model’s load allocation assigned the calculated average DWF to
the appropriate node in the sewer system model.
Step Ͱ: The allocated flows were adjusted as necessary during the DWF calibration
process (see Section ͮ.ͯ.ͯ) to closely match the actual measured DWFs recorded during
the flow monitoring period.
2.2.3 Inflow and Infiltration: Time-Area Model A and RDI
Mike Urban has several modules to estimate the wet weather I/I in each basin. For this study, the
MOUSE Time‐Area Model A (Inflow) and Rainfall Dependent Infiltration (RDI) methods were
chosen to model I/I respectively. The MOUSE Model A includes three primary factors including:
time of concentration, a reduction factor representing flow losses, and an initial loss. The model
also includes curves representing basin rain response. Basin rain response is essentially how fast
flow from different parts of the catchment basin reaches the collection system.
The infiltration component of the RDI flow comes from three sources, conceptually represented
by different storage zones through the soil column. Figure ͮ.ͮ shows the conceptual RDI model,
from DHI (ͮͬͭͲ). The three sources of flow that enter the collection system as RDI are Overland
Flow that enters the system rapidly after a storm, Interflow with a medium response time, and
Base Flow with a slower response, which is different than the sanitary Base Flow coming from
wastewater customers.
The volume of water stored in each zone, the response time, and how water moves between the
zones are described by a series of related equations. The equations include ͭ͵ parameters that
are not directly measurable and must be determined through model calibration. An
evapotranspiration term is included to simulate drying of the zones. Attachment C present the
resulting parameters after model calibration.
Two important I/I parameters are the areas of “connected pervious” and “connected impervious”
land contributing flow to each basin’s collection system. These areas represent the equivalent
area of land accumulating rainfall that produce the WWF measured at the downstream flow
meter. For example, if a flow meter measures a fast response to a storm event, there may be a
lot of impervious land that is accumulating rainfall and contributing surface runoff to the
collection system. Connected pervious land represents the equivalent amount of land absorbing
rainfall and slowly contributing WWF to the collection system when the ground is saturated.
The RDI and Model A flow components combine to create a continuous hydrograph of rainfall
derived flows (RDII) for each basin from each storm event. Often during wet periods, additional
storms occur while tailing components of the preceding storm are still entering the system,
creating complex hydrographs.
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐Ͳ | SEPTEMBER ͮͬͭ͵ | DRAFT
Figure ͮ.ͮ Model A and RDI Model
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͳ
2.3 Hydraulic Model Calibration
Hydraulic model calibration is a crucial component of the hydraulic modeling effort. Calibrating
the model to match data collected during the flow monitoring program ensures the most
accurate results possible. The calibration process consists of calibrating to both dry and wet
weather conditions.
For this project, both dry and wet weather monitoring were conducted at the ͭʹ metering sites
presented in Appendix G, TM ͭ. DWF calibration ensures an accurate depiction of base
wastewater flow (BWF) generated within the study area. WWF calibration consists of calibrating
the hydraulic model to a specific storm event or events to accurately simulate the peak flow and
volume of I/I into the sewer system. The amount of I/I is essentially the difference between the
WWF and DWF components.
2.3.1 Calibration Standards
The hydraulic model was calibrated in accordance with international modeling standards. The
Urban Drainage Group (UDG), formerly known as Wastewater Planning Users Group (WaPUG), a
section of the Chartered Institution of Water and Environmental Management (CIWEM), has
established generally agreed upon principles for model verification. The dry weather and wet
weather calibration focused on meeting the recommendations on model verification contained
in the “Code of Practice for the Hydraulic Modeling of Urban Drainage Systems,” published by
the CIWEM UDG2, as summarized below.
2.3.1.1 Dry Weather Calibration Standards
Dry weather calibration should be carried out for two dry weather days and the modeled flows
and depths should be compared to the field‐measured flows and depths. Both the modeled and
field‐measured flow hydrographs should closely follow each other in both shape and magnitude.
In addition to the shape, the flow hydrographs should also meet the following criteria as a
general guide:
The timing of flow peaks and troughs should be within ͭ hour.
The peak flow rate should be within the range of ±ͭͬ percent.
The volume of flow (or the average rate of flow) should be within the range of
±ͭͬ percent. If applicable, care should be taken to exclude periods of missing or
inaccurate data.
2.3.2 Wet Weather Calibration Standards
For each meter, three separate storms need to be run through the model. For at least two storms
out of the three events from the flow monitoring period, the model‐simulated flows and depths
should match the field‐measured flows and depths within the accepted criteria. The modeled
and field flow hydrographs for the calibration storms should closely follow each other in both
shape and magnitude, until the flow has substantially returned to DWF rates.
2 UDG, Code of Practice for the Hydraulic Modelling of Urban Drainage Systems, ͭst Edition CIWEM
ͮͬͭͳ www.ciwem.org.
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐ʹ | SEPTEMBER ͮͬͭ͵ | DRAFT
In addition to the shape, the flow hydrographs should also meet the following criteria as a
general guide:
The timing of the peaks and troughs should be similar with regard to the duration of the
events.
The peak flow rates at significant peaks should be in the range of +ͮͱ percent
to ‐ͭͱ percent and should be generally similar throughout.
Modeled volume of flow should be within +ͮͬ percent to ‐ͭͬ percent of measured
volume of flow.
The depth of surcharge should be in the range of +ͮͬ‐inches to ‐Ͱ‐inches.
The unsurcharged depth should be within the range of ± Ͱ‐inches.
The UDG recommends that for wet weather calibration, the use of a single calibration period
incorporating a number of rainfall events should be considered whenever possible. In other
words, if the flow monitoring program captured several back to back storms, it may be
preferable to use the back to back storms events as the calibration storms, as opposed to
calibrating to two separate storms that have occurred weeks or months apart.
Model calibration simulations should be run for a duration long enough that the I/I response is no
longer apparent in the measured data.
2.3.3 Dry Weather Flow Calibration
2.3.3.1 Dry Weather Calibration Process
The DWF calibration process consists of several elements:
Divide the system into areas tributary to each flowmeter. The first step in the calibration
process was to divide the City into flow meter tributary areas. Eighteen tributary areas
were created, one for each flowmeter from the flow monitoring program. A map
showing the locations of each flow monitoring site and their associated tributary area is
provided in Appendix G, TM ͭ, along with a schematic of the flow meters.
Define flow volumes within each area. The next step was to define the flow volumes
within each area, which was accomplished in the flow allocation step (see Section ͮ.ͮ.ͮ).
Create diurnal patterns to match the temporal distribution of flow. A diurnal curve is a
pattern of hourly multipliers that are applied to the base flow to simulate the variation in
flow that occurs throughout the day. Two diurnal curves were developed for each flow
monitoring tributary area, one representing weekday flow and one representing
weekend flow. The diurnal patterns were initially developed based on the flow
monitoring data and adjusted as part of the calibration process until the model‐
simulated flows closely matched the field‐measured flows. Figure ͮ.ͯ shows the
calibrated weekday and weekend diurnal patterns for the area tributary to Meter Site
MHͱͯͬͮ. Similar diurnal curves were developed for each of the meters and its tributary
area. These additional curves are available in Attachment E.
2.3.3.2 Dry Weather Calibration Results
Table ͮ.ͭ provides a summary of the DWF calibration using the average and daily peak flow
results for both weekday and weekend conditions. As shown on Table ͮ.ͭ, with a few exceptions,
the model‐simulated average and peak flows for both weekday and weekend DWF were all
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐͵
within ͭͬ percent. In general, the percent difference between the overall modeled and measured
DWF ranged between ‐ʹ.ͳ and ͵.Ͳ percent, with most differences being less than ͱ percent.
Attachment F contains a detailed DWF calibration summary sheet for each of the ͭʹ metering
sites. Each calibration sheet provides plots that compare the model‐simulated and field‐
measured flow data for both weekday and weekend conditions. An example of the dry weather
calibration for Meter Site MHͱͯͬͮ is shown on Figure ͮ.ͯ.
Modeled level results were also checked against the recorded flow monitoring data at each of
the ͭʹ sites. All sites meet the DUG criteria and are within Ͱ inches during unsurcharged
conditions. Of the ͭʹ sites, ten of the flow meters were located on segments with steep slopes
causing supercritical hydraulic conditions. These supercritical conditions are difficult to measure
in the field, as well as simulate in the model. During calibration, modeling parameters, such as
the node headlosses, were adjusted to meet calibration criteria. However, the model remains
highly sensitivity at these sites to changes in level and flow changes.
There is good overall correlation of the field‐measured data to the model output results. All ͭʹ of
the sites are within a ͭͬ percent range of both peak and volume, and therefore meet CiWEM
criteria. Therefore the model was considered calibrated for DWF.
Table ͮ.ͭ Dry Weather Flow Calibration Results
Flow Meter
ID
Weekday
Flow
Volume
Difference
(%)
Weekday
Peak Flow
Difference
(%)
Weekday
Max Level
Diff (in)
Weekend
Flow
Volume
Difference
(%)
Weekend
Peak Flow
Difference
(%)
Weekend
Max Level
Diff (in)
MHͬͭͲͲ ‐ͭ.ͯ ‐Ͳ.Ͱ ͬ.ͮͰ ͳ.ʹ ‐ͭ.ͳ ͬ.Ͱͱ
MHͬͮʹͲ ͬ.ͳ ͬ.Ͳ ͬ.ͳͲ ͮ.ͭ ͭ.ͱ ͬ.ͳʹ
MHͬͱͯͳ ‐ͬ.ͳ ‐ͯ.ͭ ͬ.Ͱͳ ‐ͬ.ͳ ‐ͳ.ͬ ͬ.Ͱͳ
MHͭͯͲͬ Ͳ.ͭ ͮ.ͯ ͭ.ͱͱ ͮ.Ͱ ‐ͯ.ͭ ͭ.ͱͳ
MHͭͳͲͯ ͬ.͵ ͭ.ͳ ͯ.ͱ͵ ‐ͱ.Ͳ ‐Ͳ.Ͱ ͯ.Ͳͳ
MHͮͭͭͲ ‐ʹ.ͱ ͬ.ͭ ͭ.ͱͰ ‐ͳ.ͭ ͮ.͵ ͭ.ʹͯ
MHͮͭͳͭ ‐ͬ.Ͱ ‐ͭ.ͳ ͭ.ͯͬ ‐ͬ.ͱ ‐ͭ.ͮ ͬ.ͳͲ
MHͮͮͱͮ ͬ.ͮ ‐ͭ.ͬ ͬ.ͮͭ ‐ͯ.Ͱ ‐Ͱ.ͭ ͬ.ͮͯ
MHͮ͵͵͵ ‐ʹ.Ͱ Ͳ.ͱ ͬ.ͳͱ ‐Ͱ.Ͱ ‐ͬ.͵ ͬ.Ͳ͵
MHͯͮͭͲ ‐ͮ.Ͱ ‐ͯ.ͯ ͬ.ͯʹ ͱ.ͬ Ͱ.ͯ ͬ.ͱͳ
MHͯͲͮͱ ͬ.Ͱ ‐ͳ.ͳ ͬ.ʹͳ ‐͵.ͭ ‐ͱ.Ͱ ͭ.ͮͬ
MHͰͲͮʹ ͭ.Ͱ ͭ.ͭ ͬ.ͮʹ ‐ͯ.Ͱ ‐ͯ.ͳ ͬ.ͯͮ
MHͰͲͰͲ ͬ.ͬ ‐ͬ.ͭ ͯ.ͳͮ ͬ.ͬ ‐ͬ.ͮ ͯ.ͳͰ
MHͱͯͬͮ ‐ʹ.ͳ ‐ͭ.ͳ ͮ.ͭͲ ‐ʹ.ͱ ͵.ʹ ͮ.Ͱͯ
MHͱͱͬͱ ͬ.Ͳ ͭ.ͯ ͬ.ͱͲ ‐ͬ.ͭ ͬ.ͱ ͬ.ͱͳ
MHͱͱͭ͵ ͭ.ͳ ͭ.ͱ ͬ.͵ͭ ͵.ͭ ʹ.͵ ͭ.ͬͱ
MHͲͬͰͭ ‐ͯ.ͱ ‐Ͱ.ͱ ͭ.ͱͮ ͵.Ͳ ͵.ͬ ͭ.Ͳͮ
MHͲͳͬͰ ͯ.Ͳ ͮ.ͳ ͭ.ͮͰ ‐ʹ.Ͳ ‐͵.ͳ ͭ.ͮͭ
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐ͭͬ | SEPTEMBER ͮͬͭ͵ | DRAFT
Figure ͮ.ͯ Example of Dry Weather Calibration (Site MHͱͯͬͮ)
2.3.4 Wet Weather Flow Calibration
2.3.4.1 Wet Weather Calibration Process
The WWF calibration enables the hydraulic model to accurately simulate I/I entering the
collection system during a large storm. As outlined below, the WWF calibration process consists
of several elements:
Identify calibration rainfall events. The WWF calibration process consists of running
model simulations of historic rainfall events based on data collected as part of a system
flow monitoring program. The goal of any WWF monitoring program is to capture and
characterize a system’s response to a significant rainfall event, preferably during wet
antecedent moisture conditions.
The selection of a particular calibration storm or group of storms is based on a review of
the flow and rainfall data. There is a good range of different event types available for the
different meters. Major events were identified as part of Chapter No. ͮ. This section
refines the analysis and shows the different storms selected for calibration for all meter
sites. Data was recorded between ͮͬͭͳ and ͮͬͭʹ.
0.00
0.50
1.00
1.50
2.00
2.50
3.00
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)Hour
Flow Calibration
Measured Flow
Weekday Weekend
0.0
1.0
2.0
3.0
4.0
024681012141618202224262830323436384042444648Velocity (ft/s)Hour
Velocity Calibration
Measured Velocity
Weekday Weekend
0.0
2.0
4.0
6.0
8.0
10.0
024681012141618202224262830323436384042444648Level (in)Hour
Level Calibration
Measured Level
Weekday Weekend
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͭͭ
Define RDII tributary areas. For the WWF calibration, RDII flows are added to the DWF.
The model calculates two types of response: a slow response corresponding (SRC)
mainly to infiltration and a fast response corresponding (FRC) mainly to direct inflow.
Impervious area, which is the fraction of the catchment considered to contribute to FRC
runoff, and RDI Area, which is the fraction of the total catchment area that contributes
to the SRC runoff component are two major model‐specific data in the model
calculation of WWFs. These values were initially set based on engineering judgment, as
well as the previously used values, and then adjusted until the model‐simulated flows
(both peak flows and total volume) matched closely with the field‐measured flows.
Create I/I parameter database and modify to match field‐measured flows. The main step
in the WWF calibration process involves adjusting both Model A and RDI parameters for
each flow monitoring tributary area. The most important parameters were described in
Section ͮ.ͮ.ͯ and Attachment C summarizes all calibrated parameters by flow
monitoring site. As with the dry weather calibration, the wet weather calibration process
compared the meter data with the model output. Comparisons were made for average
and peak flows as well as the temporal distribution of flow until flows returned to their
baseline levels. According to the UDG, a hydraulic model is generally considered to be
satisfactorily calibrated to WWF conditions if the modeled peak flows are within
+ͮͱ percent to ‐ͭͱ percent of the field‐measured data, and if the average modeled flows
are within +ͮͬ percent to ‐ͭͬ percent of the field‐measured data.
Adjust model variables to match field‐measured velocity and flow depths. Once the
model‐simulated flows matched the field‐measured flows within the acceptable limits,
the model‐simulated velocity and flow depth were compared to the field‐measured
velocity and flow depth. Adjustments were made to various model parameters until the
modeled and measured velocity and depth closely matched one another. The primary
varied parameters for this process are pipeline roughness (Manning’s n), although other
parameters can also be adjusted as calibration results are generated. Sediment buildup
and movement in the pipe will also influence the level and depth, but these are very
difficult to quantify and can change frequently, therefore they are not included in the
calibration.
- Manning’s roughness coefficients, or n values, have industry accepted ranges based
on a number of variables. Roughness coefficients can increase over time depending
on the construction methods, installation quality, system maintenance, and other
environmental factors. Certain factors can result in roughness coefficients that differ
from the typical range. These could include joint misalignment, cracks, and debris
(e.g., root intrusion, etc.) that lead to increased turbulence in a pipe and an increase
in the apparent Manning’s n factor.
- If the model is unable to reasonably match the field‐measured flow depth and
velocity within the acceptable range of Manning’s roughness coefficients, further
investigation should be conducted to help determine the cause of the discrepancy.
Some issues that could cause such a discrepancy can include errors in the slope or
diameter of a pipeline, downstream blockages, pipeline sags, and, in some cases,
influences from downstream pump station operations.
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐ͭͮ | SEPTEMBER ͮͬͭ͵ | DRAFT
2.3.4.2 Wet Weather Calibration Results
Attachment H contains a detailed WWF calibration summary sheet for each of the ͭʹ meter
sites. Each calibration sheet provides plots that compare the model‐simulated and field‐
measured flow, velocity, and level data for the calibration storms. An example of the wet
weather calibration for Meter Site MHͱͯͬͮ is shown on Figure ͮ.Ͱ.
Table ͮ.ͮ provides a summary of the WWF calibration using the average and peak flow results.
As shown on Table ͮ.ͮ, the model‐simulated average and peak flows at ͭͲ of ͭʹ meter sites were
within the acceptable tolerances for the calibration storms, and therefore the model was
considered calibrated and ready to use for capacity analysis purposes.
LRWWMP | TM 2 | CITY OF RENTON DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͭͯ Table ͮ.ͮ Wet Weather Flow Calibration Results Flow Meter ID Pipe Dia. (in) Storm ͭ Storm ͮ Storm ͯ Vol. Flow (%) Peak Flow (%) Level Diff. (ins) Vol. Flow (%) Peak Flow (%) Level Diff. (ins) Vol. Flow (%) Peak Flow (%) Level Diff. (ins) MHͬͭͲͲ ͭͮ ͯͭ.ͭ ‐ͭ.ͱ ͱ.ͭ ‐ͯ.ͬ ͭͭ.͵ ͮͭ.ͬ ͭͱ.Ͱ ‐ͬ.͵ ͳ.Ͱ MHͬͮʹͲ ͭͬ ͳ.ͮ ‐ͭ.ʹ ͭ.ͱ ͬ.ͭ ‐ͭͭ.͵ ͭ.ͳ ‐ͳ.ʹ ‐ͮͱ.ʹ ͭ.ʹ MHͬͱͯͳ ʹ ͭͬ.ͭ ͮ.ͬ ͬ.ͮ ͱ.ͮ ‐Ͳ.Ͳ ͬ.͵ ͭͳ.ͮ ͭͯ.ͯ ͭ.ͭ MHͭͯͲͬ ͭͬ.ͳͱ ͭʹ.ͭ ͵.ͳ ͱ.ͳ ‐ͭͮ.ʹ ͳ.ͮ ͱ.ʹ ͭͱ.ͭ ͮ.ͱ Ͳ.ͬ MHͭͳͲͯ ͭͱ ͭͯ.ͬ ͭͯ.ͳ Ͳ.ͮ ‐ͯʹ.͵ ‐ͭͱ.ͬ Ͳ.Ͱ ‐ͬ.ͯ ‐ͱ.ͬ ͱ.ͯ MHͮͭͭͲ ͭͰ.ͱ ‐ ‐ ‐ ‐͵.ͱ ‐ͭͮ.Ͳ Ͳ.ͬ ͯ.ͳ ͳ.ͯ Ͱ.ͬ MHͮͭͳͭ ͭͭ.ͮͱ Ͳ.ʹ ͭͬ.͵ ͯ.ͱ ‐Ͳ.ͳ ͳ.ͳ ͮ.Ͱ ͭͳ.ͯ ͭ͵.ͱ ͯ.ʹ MHͮͮͱͮ ͭʹ ‐ͮ.ͱ ‐ͱ.ʹ ͭ.Ͳ ‐͵.Ͱ ͭͮ.ͮ ͭ.Ͳ ʹ.ͭ ͱʹ.ͯ ͮ.ͬ MHͮ͵͵͵ ʹ ͭͭ.ͬ ‐ͭͬ.͵ ͭ.ͯ ͭͭ.ͯ ͭ.ʹ ͭ.ͯ ͭͲ.ʹ ͳ.ͬ ͭ.Ͱ MHͯͮͭͲ ͳ.ͯʹ ͭʹ.ʹ ‐Ͱ.Ͱ ͮ.͵ ‐ͭͭ.ͯ ͮͱ.ͮ ͭ.ͳ ͭͯ.ͱ Ͱͳ.ʹ ͭ.͵ MHͯͲͮͱ ͭͮ Ͱ.ͳ ͱ.ͬ ͯ.ͭ ‐ͭͰ.ͳ ‐Ͳ.ͭ ͯ.ʹ ‐ͭ.ͳ ‐ʹ.ͱ ͯ.ͳ MHͰͲͮʹ ͭͬ.ͯʹ ͭͬ.Ͱ ͯ.ͱ ͮ.ͮ ‐ͮͭ.ͮ ͭͱ.ͬ ͮ.Ͳ ͭͬ.͵ ‐ͭ.Ͳ ͮ.ͯ MHͰͲͰͲ ʹ ‐ͭ.͵ ‐Ͳ.Ͳ ͱ.Ͱ ‐ͭʹ.ͯ ‐ͭ͵.ͳ ͱ.Ͱ ‐ͮ.ͮ ͭ.͵ ͱ.Ͳ MHͱͯͬͮ ͭͰ ‐Ͱ.ͯ ‐ʹ.ͳ ͯ.ʹ ‐ͳ.͵ Ͳ.ͳ Ͱ.ͱ ‐ͭ.Ͳ ͬ.ʹ Ͱ.ͯ MHͱͱͬͱ ͭͬ Ͳ.Ͳ ‐ͭ.͵ ͭ.ͱ ‐͵.ͱ Ͳ.ͯ ͭ.ͮ ‐ͮ.ͮ ‐ͭͰ.ͳ ͮ.ʹ MHͱͱͭ͵ ͭͬ.ͮͱ ͭͮ.ͮ ͯͯ.ͭ ͭ.ͱ ͭͬ.͵ ͮͰ.ͬ ͭ.Ͱ ͵.ʹ ͭ.ͯ ͮͭ.ͯ MHͲͬͰͭ ʹ ‐ͭͰ.ͱ ‐ʹ.͵ ͮ.Ͳ ͭͲ.ͱ ͭ͵.ͳ ͮ.Ͳ ͯ͵.ͯ ͭͰͬ.ͯ ͯ.ͱ MHͲͳͬͰ ͭͮ ‐ʹ.Ͱ ‐ͭ͵.ͭ ͭ.͵ ͭͲ.ͳ ͮͭ.ʹ ͮ.ͬ ͭͱ.ͮ ͯ.ͬ ͭ.͵
CITY OF RENTON | TM 2 | LRWWMP
ͮ‐ͭͰ | SEPTEMBER ͮͬͭ͵ | DRAFT
Figure ͮ.Ͱ Example of Wet Weather Calibration (Site MHͱͯͬͮ)
2.3.4.3 Wet Weather Calibration Discussion
Every meter data was compared to three storms recorded during the flow monitoring period for
calibration, with the exception of MHͮͭͭͲ which had two, because the meter failed to record
data during the initial storm event.
0.00000
0.10000
0.20000
0.30000
0.40000
0.50000
0.600000.8
1.3
1.8
2.3
2.8
3.3
3.8
4.3
4.8
5.3
5.8
12/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow Calibration
Rai
n
0.00000
0.10000
0.20000
0.30000
0.40000
0.50000
0.600000.0
1.0
2.0
3.0
4.0
5.0
6.0
12/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity Calibration
Rain
0.00000
0.10000
0.20000
0.30000
0.40000
0.50000
0.600000
2
4
6
8
10
12
14
16
12/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level Calibration
Rain
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵ | ͮ‐ͭͱ
Of the ͭʹ meters, ͭͲ had two or more storm events response within calibration standards for
flows. Of the ͭʹ meters, ͭͮ met the level calibration standard of a maximum difference of four
inches. As discussed previously in the dry weather calibration section, sites with super critical
remain sensitive to flow and level changes in the hydraulic model.
The following are discussions on specific sites:
Site MHͯͮͭͲ only reached calibration standards for one of the three storms. In general
the model could not match the peak flows measured for the first two upfront storm
events. The City’s collection system showed a more significant rainfall response in the
first half of the flow monitoring period. Note, the flow monitoring was stopped for a two
week period in January, and following this the meter showed less response than before
the period of inactivity. Calibration parameters were calibrated to match Storm ͭ
response, so the hydraulic model is more conservative.
Site MHͲͬͰͭ also only met calibration standards for one of the three calibration storms.
Similar to Site MHͯͮͭͲ, MHͲͬͰͭ had significant changes in rainfall response throughout
the flow monitoring period. Storm ͭ occurred in December and caused significant I/I
response in the collection system, while Storms ͮ and ͯ showed almost no response in
the later part of the season. The change in rainfall response made it difficult to match
across the season, for this reason conservative parameters were used and the hydraulic
model was calibrated to Storm ͭ.
As a result of calibration, I/I metrics were estimated from the model results for existing
conditions at the ͭʹ flow monitoring sites. Results show a large variation of I/I response
throughout the system, from ͭͮ gallons per day per acre (gpd/ac) to ͭͯ,Ͱͬͬ gpd/.
2.3.5 Hydraulic Model Calibration Summary
Calibration of the City’s hydraulic model was a multi‐step process that involved comparing
model‐simulated flow to the actual field‐measured data for both dry and wet weather
conditions. Results indicated that the model correlated well with the field‐measured data for
flows. All sites met the DUG standards for ADWF. PWWF calibration was achieved at ͭͲ of the
ͭʹ meter sites used for model calibration, which is typical for this level of calibration. This
provides a high level of confidence in the model’s accuracy such that the model can be
considered calibrated and ready to use for subsequent capacity analysis.
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment C
RDII PARAMETERS
Table 1 Connected Basin Area
Basin Area (acres) Connected Impervious (acres)
Connected Pervious Total Connected Total Connected (acres) (acres) (%)
MH0166 195.7 18.1 9.8 27.9 14.3%
MH0286 374.5 0.4 1.9 2.2 0.6%
MH0537 904.8 1.8 18.1 19.9 2.2%
MH1360 757.8 2.3 47.7 50.0 6.6%
MH1763 425.0 3.0 19.6 22.5 5.3%
MH2116 418.6 8.8 79.1 87.9 21.0%
MH2171 251.1 5.5 23.9 29.4 11.7%
MH2252 760.5 16.7 47.1 63.9 8.4%
MH2999 391.5 2.0 32.3 34.3 8.8%
MH3216 46.0 0.0 2.1 2.1 4.5%
MH3625 643.1 6.4 20.6 27.0 4.2%
MH4628 187.7 7.5 33.8 41.3 22.0%
MH4646 173.4 0.5 3.1 3.6 2.1%
MH5302 698.5 6.3 52.4 58.7 8.4%
MH5505 224.9 4.0 15.5 19.6 8.7%
MH5519 47.6 0.0 2.5 2.5 5.3%
MH6041 122.7 0.2 9.4 9.6 7.8%
MH6704 180.0 1.2 9.7 10.9 6.1%
Table 2 Model A Parameters
Basin Impervious Time of Concentration Reduction Factor Initial Loss
(%) (min) (in)
MH0166 9.25 15 0.9 0.024
MH0286 0.1 15 0.9 0.024
MH0537 0.195 15 0.9 0.024
MH1360 0.3 15 0.9 0.024
MH1763 0.7 15 0.9 0.024
MH2116 2.1 15 0.9 0.024
MH2171 2.2 15 0.9 0.024
MH2252 2.2 15 0.9 0.024
MH2999 0.5 15 0.9 0.024
MH3216 0 15 0.9 0.024
MH3625 1 15 0.9 0.024
MH4628 4 15 0.9 0.024
MH4646 0.3 15 0.9 0.024
MH5302 0.9 15 0.9 0.024
MH5505 1.8 15 0.9 0.024
MH5519 0 15 0.9 0.024
MH6041 0.17 15 0.9 0.024
MH6704 0.65 15 0.9 0.024
Table 3 RDI Parameters
Basin
Percent RDI Area (%)
Surface Storage (Umax)
Root Zone Storage (Lmax)
Overland Coefficient Groundwater Coefficient (Carea)
TC Overland Flow (CKof)
TC Interflow (CKif)
TC Baseflow (CKbf)
Overland Flow Threshold (Tof)
Interflow Threshold (Tif)
Groundwater Threshold (Tg)
Initial Surface Storage (U)
Initial Root Zone Moisture (L)
Initial Groundwater Depth (GWL)
Initial Overland Flow (OF)
Initial Interflow (IF)
Specific Yield (Sy)
Minimum Groundwater Depth (GWLmin)
Max GW depth causing Baseflow
(GWLbf0)
GW Depth for Unit Capillary flux
(GWLfl1) (CQof)
MH0166 5 0.5 4 0.45 1 12 360 1000 85 85 0 0.3 3 7 0 0 0.2 0 7 1
MH0286 0.5 0.5 4 0.45 1 12 360 1000 85 85 0 0.3 3 7 0 0 0.2 0 7 1
MH0537 2 0.5 4 0.3 1 10 160 1000 60 60 10 0.25 2.5 14 0 0 0.2 0 14 0.8
MH1360 6.3 0.5 8 0.3 1 10 80 1000 0 0 0 0.3 3 10 0 0 0.2 0 10 1
MH1763 4.6 0.55 6 0.25 1 7 210 1000 5 38 6 0.27 3.4 17 0 0 0.2 0 17 0.66
MH2116 18.9 0.5 4 0.35 1 7 80 2300 52 80 22 0.28 2.8 11.5 0 0 0.2 0 9 0.93
MH2171 9.5 0.48 4 0.35 1 6 165 2400 0 71 75 0.25 2.5 14 0 0 0.2 0 11 0.84
MH2252 6.2 0.3 3 0.2 1 8 790 3000 0.5 0.5 0 0.1 2.4 10 0 0 0.2 0 10 0
MH2999 8.25 0.5 4 0.2 1 7 100 3000 0 0 0 0.3 3 7 0 0 0.2 0 7 1
MH3216 4.5 0.5 4 0.9 1 8 200 2000 0 0 0 0.3 3 10 0 0 0.2 0 20 1
MH3625 3.2 0.6 4.8 0.18 1 15 340 3055 52 52 46 0.2 2 18 0 0 0.2 0 18 0.66
MH4628 18 0.5 4 0.3 1 15 100 1000 0 0 0 0.3 3 10 0 0 0.2 0 10 1
MH4646 1.8 0.6 7 0.4 1 7 20 300 60 80 10 0.4 5 10 0 0 0.2 0 10 1
MH5302 7.5 0.5 4 0.3 1 20 375 1150 0 25 0 0.3 3 10 0 0 0.2 0 10 1
MH5505 6.9 0.5 4 0.3 1 20 300 600 20 20 10 0.3 3 10 0 0 0.2 0 10 1
MH5519 5.3 0.5 4 0.6 1 6.4 260 1400 0 0 0 0.18 1.8 17 0 0 0.16 0 17 0.6
MH6041 7.65 0.8 4 0.9 1 15 600 6000 0 95 0 0.3 3 10 0 0 0.1 0 10 1
MH6704 5.4 0.5 4 0.3 1 8 400 5000 58 0 0 0.3 3 10 0 0 0.2 0 10 1
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment D
NEGATIVE SLOPE PIPELINES LIST
MUID FROMNODE TONODE Up Level Down Level Diameter (ft) Length (ft) Slope
186l1 186 RE*SINT.R18A-09 0.7 0.8 9.00 41.00 0.00
188l1 188 RE*SINT.R18A-08 0.7 0.8 9.00 38.80 0.00
3234l3 MH1130 3234 357.6 357.7 0.67 35.05 0.00
439l1 439 440 2.3 2.4 7.00 13.52 -0.01
439l2 439 441 2.3 2.4 7.00 13.89 -0.01
443l1 443 444 2.3 2.4 7.00 13.52 -0.01
444l1 444 445 2.3 2.4 7.00 13.90 -0.01
5304275l1 5304275 MH5935 308.6 308.7 0.67 53.70 0.00
81l1 81 RE*SINT.R18-09 0.8 0.9 6.00 27.47 0.00
GM00020 MH0470 MH1376 314.9 315.0 1.33 16.13 0.00
GM00106 MH0204 MH0203 6.2 6.3 2.00 79.02 0.00
GM00117 MH4744 MH0051 339.6 339.7 1.25 93.40 0.00
GM00269 MH0820 MH6710 325.6 326.9 0.67 181.69 -0.01
GM00318 8bend MH3694 415.9 415.9 0.67 48.74 0.00
GM00378 MH4425 MH4463 434.0 434.0 0.67 50.04 0.00
GM00406 MH4367 MH4366 395.7 395.8 0.67 62.73 0.00
GM00506 MH0245 MH0244 2.3 2.4 1.00 54.42 0.00
GM00589 MH4366 MH4701 395.7 395.8 0.67 21.03 -0.01
GM00644 MH0285 MH0286 3.3 3.4 0.83 6.54 -0.02
GM00676 MH2239 MH2241 12.7 12.8 0.67 119.97 0.00
GM00727 MH0105 5318252 63.1 63.2 0.67 143.00 0.00
GM00757 MH0135 MH0134 21.5 21.6 1.00 64.40 0.00
GM00856 MH0526 MH2756 230.1 230.2 1.50 57.18 0.00
GM00886 MH3702 MH3636 385.4 385.4 0.67 43.68 0.00
GM01147 MH3631 MH3630 410.9 410.9 0.67 19.58 0.00
GM01258 MH3060 MH3601 411.8 411.9 0.67 49.21 0.00
GM01413 MH0460 MH0459 362.6 362.7 0.67 153.13 0.00
GM01479 MH1130 3234 357.6 357.7 0.67 35.05 0.00
GM01514 MH0839 MH0738 270.6 273.7 0.67 341.55 -0.01
GM01571 MH0520 MH0383 43.1 43.1 0.67 48.96 0.00
GM01609 MH1039 MH1040 420.1 420.2 0.67 47.36 0.00
GM01757 MH0678 MH0677 225.6 225.7 0.67 59.30 0.00
GM01797 MH0719 MH0445 21.7 21.7 0.83 38.71 0.00
GM01852 MH1064 MH1153 360.1 360.2 0.67 93.00 0.00
GM01896 MH0996 MH0995 406.7 406.8 0.67 126.24 0.00
GM01916 MH1007 MH1008 407.1 407.2 0.67 152.94 0.00
GM01922 MH1131 MH1129 363.6 363.7 0.67 86.83 0.00
GM02810 MH1862 MH1861 38.6 38.6 0.83 15.00 0.00
GM03035 MH2541 MH2539 14.4 14.4 0.50 70.34 0.00
GM03145 MH2373 MH0066 17.9 21.6 1.00 62.41 -0.06
GM03252 MH2127 MH2128 18.7 18.8 2.00 70.08 0.00
GM03254 MH2129 MH2130 18.4 18.4 2.00 50.00 0.00
GM03258 MH2133 MH2134 17.9 17.9 2.00 60.42 0.00
GM03323 MH2162 MH2161 31.6 31.7 1.00 84.99 0.00
GM03375 MH2418 MH2194 12.8 12.9 1.50 34.74 0.00
GM03787 MH3214 MH3213 142.2 142.3 0.67 157.69 0.00
GM03855 MH2907 MH2906 383.0 383.1 0.67 134.02 0.00
GM03960 MH3042 MH3034 105.8 105.9 0.67 128.45 0.00
GM04264 MH3307 MH3308 96.4 96.4 0.67 89.84 0.00
GM04664 MH4862 MH2210 307.5 307.7 0.67 86.65 0.00
GM04975 MH5053 MH5052 359.2 359.3 0.67 160.69 0.00
GM04976 MH5052 MH6825 359.2 359.3 0.83 160.43 0.00
GM04978 MH5050 MH5049 304.4 318.3 0.83 300.22 -0.05
GM04979 MH5049 MH2715 318.2 327.9 0.83 351.34 -0.03
GM05144 MH5167 MH5168 407.0 409.9 0.67 68.10 -0.04
GM05191 MH5195 MH5194 416.4 416.5 0.67 55.50 0.00
GM05245 MH5240 MH3726 319.9 322.0 0.67 134.80 -0.02
GM05417 MH5331 MH5332 28.5 28.6 1.00 89.96 0.00
MUID FROMNODE TONODE Up Level Down Level Diameter (ft) Length (ft) Slope
GM05425 MH5330 MH5339 16.9 17.0 1.25 61.76 0.00
GM05478 MH2134 RE*BOERENT.RO1-36 17.8 17.9 2.00 56.61 0.00
GM05481 MH1762 RE*CEDAR2.R10-26A 52.1 55.8 1.25 50.03 -0.07
GM05760 MH5543 MH5542 150.6 150.7 0.67 138.22 0.00
GM05890 MH6259 MH5672 478.2 489.0 0.67 117.05 -0.09
GM05974 MH5738 MH5898 286.2 286.2 0.67 62.40 0.00
GM06289 MH5940 MH5943 315.9 317.2 0.67 265.23 0.00
GM06311 MH5959 MH5958 376.3 376.4 0.67 77.18 0.00
GM06618 MH6212 MH6217 390.1 390.2 0.67 195.30 0.00
GM06803 MH1638 MH1637 369.7 370.4 1.00 75.97 -0.01
GM06889 MH0924 MH0761 357.7 360.4 0.67 15.78 -0.17
GM07042 MH6360 MH6361 394.8 395.9 0.67 91.44 -0.01
GM07332 MH6612 MH6613 439.0 454.9 0.67 282.49 -0.06
GM07333 MH6613 MH6614 454.8 456.1 0.67 121.59 -0.01
GM07334 MH6614 MH6615 456.0 458.0 0.67 207.78 -0.01
GM07355 MH6626 MH6356 393.7 399.4 0.67 45.41 -0.13
Link_91 MH3090 FM0043-TEE 404.8 404.9 1.25 32.00 0.00
R18-01l1 R18-01 RE*SINT.RO1-68 -2.3 -2.1 7.50 123.83 0.00
R18A-13l1 RE*SINT.R18A-13 184 0.9 1.1 9.00 9.97 -0.01
RE*BOERENT.RO1-34l1 RE*BOERENT.RO1-34 RE*BOERENT.RO1-33 17.2 17.2 2.00 65.37 0.00
RE*CEDAR1.R10-25l1 RE*CEDAR1.R10-25 RE*CEDAR1.R10-24A 55.3 55.4 3.50 73.94 0.00
RE*CEDAR2.R10-26Al1 RE*CEDAR2.R10-26A RE*CEDAR1.R10-26 52.0 55.8 3.50 73.03 -0.05
RE*CEDAR3.R10-32Al1 RE*CEDAR3.R10-32A RE*CEDAR2.R10-32 61.5 61.6 3.50 84.06 0.00
RE*CEDAR3.R10-36l1 RE*CEDAR3.R10-36 RE*CEDAR3.R10-35 62.8 62.9 3.50 110.68 0.00
RE*ESI1.RO1-01Al1 1814 RE*ESI1.RO1-01 -2.3 -2.2 9.00 152.67 0.00
RE*ESI1.RO1-01Bl1 1735 RE*ESI1.RO1-01A -2.3 -2.2 9.00 43.26 0.00
RE*ESI1.RO1-18l1 RE*ESI1.RO1-18 RE*ESI1.RO1-17 4.0 4.1 9.00 76.23 0.00
RE*ESI1.RO1-25l1 RE*ESI1.RO1-25 RE*ESI1.RO1-25A 5.9 6.0 9.00 32.09 0.00
RE*ESI1.RO1-32l1 RE*ESI1.RO1-32 RE*ESI1.RO1-32A 6.8 6.8 9.00 61.79 0.00
RE*ESI2.RO2-16l1 RE*ESI2.RO2-16 RE*ESI2.RO2-15A 14.0 14.1 8.00 72.17 0.00
RE*SINT.R18-01l1 RE*SINT.R18-01 R18-01 -2.3 -2.2 7.50 21.63 -0.01
RE*SINT.R18-02l1 RE*SINT.R18-02 RE*SINT.R18-01 -2.3 -2.2 6.00 74.93 0.00
RE*SINT.R18-09l1 RE*SINT.R18-09 RE*SINT.R18-08B 0.8 0.8 6.00 73.99 0.00
RE*SINT.R18-18** RE*SINT.R18-18 RE*SINT.R18A-21 2.7 3.2 6.00 50.90 -0.01
RE*SINT.R18A-09l1 RE*SINT.R18A-09 188 0.7 0.8 9.00 106.38 0.00
RE*SINT.R18A-12l1 RE*SINT.R18A-12 RE*SINT.R18A-11 1.2 1.3 9.00 26.86 0.00
RE*SINT.R18A-13l1 184 RE*SINT.R18A-12 1.0 1.3 9.00 85.28 0.00
RE*SINT.R18A-18l1 RE*SINT.R18A-18 439 2.3 2.4 9.00 29.97 0.00
RE*SINT.R18A-21l1 RE*SINT.R18A-21 RE*SINT.R18A-20 3.1 3.2 4.50 20.25 0.00
RE*TUK.R18-20Al1 RE*TUK.R18-20A RE*TUK.R18-20 6.3 6.5 3.00 72.38 0.00
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment E
BASIN DIURNAL PATTERNS
MH 0166
MH 0286
MH 0537
MH 1360
MH 1763
MH 2116
MH 2171
MH 2252
MH 2999
MH 3216
MH 3625
MH 4628
MH 4646
MH 5302
MH 5505
MH 5519
MH 6041
MH 6704
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment F
DRY WEATHER CALIBRATION RESULTS
Table 1 Dry Weather Flow Calibration Results
Long-range Wastewater Management Plan
City of Renton
Pipe Avg. Peak Avg. Avg. Avg. Peak Avg. Avg. Avg. Peak Max
Meter Diameter Flow Flow Velocity Level Flow Flow Velocity Level Flow Flow Level Diff
Number (in) (mgd) (mgd) (ft/s) (in) (mgd) (mgd) (ft/s) (in) (%) (%) (in)
MH0166 12 0.015 0.026 0.30 1.2 0.014 0.024 0.73 1.1 -1.3% -6.4% 0.24
MH0286 9.88 0.073 0.095 0.66 3.5 0.073 0.095 0.98 2.9 0.7% 0.6% 0.76
MH0537 8 0.317 0.392 8.73 1.7 0.315 0.379 7.32 2.1 -0.7% -3.1% 0.47
MH1360 10.75 0.203 0.255 3.40 2.2 0.216 0.260 1.91 3.6 6.1% 2.3% 1.55
MH1763 15 0.167 0.231 0.40 7.8 0.168 0.234 0.74 6.1 0.9% 1.7% 3.59
MH2116 14.38 0.574 0.648 2.86 4.5 0.525 0.648 2.59 5.7 -8.5% 0.1% 1.54
MH2171 11.25 0.184 0.278 1.25 4.0 0.184 0.273 1.29 4.7 -0.4% -1.7% 1.30
MH2252 18 0.648 0.837 4.62 3.2 0.649 0.829 2.79 3.3 0.2% -1.0% 0.21
MH2999 8 0.175 0.208 5.22 1.6 0.160 0.221 3.99 2.0 -8.4% 6.5% 0.75
MH3216 7.38 0.050 0.069 0.89 2.4 0.048 0.066 1.02 2.5 -2.4% -3.3% 0.38
MH3625 12 0.533 0.729 2.57 5.0 0.535 0.673 2.74 4.7 0.4% -7.7% 0.87
MH4628 10.38 0.163 0.195 4.27 1.8 0.165 0.197 3.73 1.6 1.4% 1.1% 0.28
MH4646 8 0.205 0.229 9.02 1.3 0.205 0.228 7.95 4.5 0.0% -0.1% 3.72
MH5302 19.88 1.689 2.009 3.22 8.1 1.542 1.974 3.76 6.4 -8.7% -1.7% 2.16
MH5505 10 0.211 0.238 5.85 1.6 0.212 0.241 4.03 2.1 0.6% 1.3% 0.56
MH5519 10.25 0.319 0.380 5.84 2.1 0.325 0.386 5.14 2.8 1.7% 1.5% 0.91
MH6041 8 0.047 0.065 3.75 0.8 0.045 0.062 1.53 2.1 -3.5% -4.5% 1.52
MH6704 12 0.114 0.154 5.58 1.0 0.118 0.158 5.57 2.0 3.6% 2.7% 1.24
Notes:
1. Source: City of Renton 2018 Temporary Flow Monitoring Program, ADS
2. Average flow, level, and velocity are computed from hydraulic modeling results. Maximum flow values are hourly peaks.
3. Percent Difference = (Modeled - Measured)/Measured*100.
Measured Data(1)Modeled Data(2)Percent Error(3)
Weekday Dry Weather Flow
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.009 0.9 0.12 0.010 0.9 0.66 0.06 0.75 0.61 0.611 0.009 0.9 0.10 0.009 0.8 0.64 0.06 0.75 0.61 0.612 0.009 0.9 0.09 0.009 0.8 0.64 0.04 0.75 0.61 0.613 0.009 0.9 0.08 0.009 0.8 0.64 0.03 0.75 0.61 0.614 0.009 0.9 0.07 0.009 0.8 0.64 0.02 0.75 0.61 0.615 0.009 0.8 0.07 0.009 0.8 0.64 0.00 0.84 0.68 0.686 0.010 0.9 0.07 0.009 0.9 0.65 -0.01 0.75 0.61 0.617 0.009 0.9 0.08 0.009 0.9 0.65 0.00 1.00 0.82 0.828 0.012 1.1 0.22 0.011 0.9 0.68 0.12 1.67 1.36 1.369 0.020 1.2 0.31 0.016 1.1 0.77 0.02 1.51 1.23 1.2310 0.018 1.2 0.39 0.018 1.2 0.79 0.03 1.51 1.23 1.2311 0.018 1.3 0.43 0.018 1.2 0.78 0.13 1.42 1.16 1.1612 0.017 1.4 0.41 0.017 1.2 0.78 0.22 1.51 1.23 1.2313 0.018 1.4 0.41 0.018 1.2 0.78 0.23 1.93 1.57 1.5714 0.023 1.4 0.49 0.021 1.3 0.83 0.12 2.18 1.77 1.7715 0.026 1.5 0.48 0.024 1.4 0.86 0.06 1.93 1.57 1.5716 0.023 1.5 0.56 0.024 1.4 0.85 0.16 1.93 1.57 1.5717 0.023 1.5 0.56 0.022 1.3 0.84 0.15 1.51 1.23 1.2318 0.018 1.4 0.51 0.020 1.2 0.80 0.20 1.34 1.09 1.0919 0.016 1.3 0.42 0.017 1.1 0.76 0.19 1.09 0.89 0.8920 0.013 1.3 0.38 0.014 1.1 0.73 0.22 1.09 0.89 0.8921 0.013 1.2 0.36 0.013 1.0 0.71 0.24 0.84 0.68 0.6822 0.010 1.1 0.26 0.011 0.9 0.69 0.19 0.92 0.75 0.7523 0.011 1.1 0.23 0.010 0.9 0.67 0.20 0.75 0.61 0.6124 0.004 0.9 0.07 0.010 0.9 0.66 0.01 0.25 0.58 0.5825 0.003 0.9 0.06 0.007 0.7 0.58 0.17 0.25 0.58 0.5826 0.003 0.9 0.06 0.004 0.6 0.49 0.34 0.29 0.68 0.6827 0.004 0.9 0.05 0.003 0.5 0.48 0.35 0.21 0.49 0.4928 0.003 0.9 0.04 0.003 0.5 0.48 0.34 0.29 0.68 0.6829 0.004 0.8 0.03 0.003 0.5 0.48 0.34 0.25 0.58 0.5830 0.003 0.8 0.03 0.003 0.5 0.48 0.34 0.17 0.39 0.3931 0.002 0.8 0.03 0.003 0.5 0.47 0.36 0.21 0.49 0.4932 0.003 0.9 0.07 0.003 0.5 0.45 0.42 0.29 0.68 0.6833 0.004 0.9 0.11 0.003 0.5 0.47 0.45 0.42 0.97 0.9734 0.005 1.0 0.12 0.004 0.6 0.51 0.42 0.50 1.17 1.1735 0.006 1.0 0.15 0.005 0.7 0.56 0.39 0.54 1.27 1.2736 0.007 1.1 0.22 0.006 0.7 0.58 0.38 0.50 1.17 1.1737 0.006 1.1 0.19 0.006 0.7 0.58 0.36 0.54 1.27 1.2738 0.007 1.1 0.20 0.006 0.7 0.58 0.39 0.71 1.66 1.6639 0.009 1.1 0.17 0.007 0.8 0.61 0.29 0.84 1.95 1.9540 0.010 1.0 0.15 0.009 0.8 0.65 0.19 0.63 1.46 1.4641 0.008 1.0 0.13 0.009 0.8 0.64 0.17 0.67 1.56 1.5642 0.008 1.0 0.13 0.008 0.8 0.62 0.21 0.54 1.27 1.2743 0.007 1.0 0.14 0.007 0.8 0.60 0.24 0.42 0.97 0.9744 0.005 0.9 0.11 0.006 0.7 0.57 0.25 0.54 1.27 1.2745 0.007 0.9 0.11 0.006 0.7 0.57 0.26 0.54 1.27 1.2746 0.007 0.9 0.11 0.006 0.7 0.58 0.24 0.38 0.88 0.8847 0.005 0.9 0.07 0.006 0.7 0.56 0.24 0.29 0.68 0.68Weekday 0.015 1.2 0.30 0.014 1.1 0.73 1.23 1.00 1.00Weekend 0.005 1.0 0.11 0.006 0.7 0.55 0.43 1.00 1.00ADWF(1)0.012 1.1 0.24 0.012 0.9 0.68 1.00 1.00 1.00Weekday-1.3% 0.24Weekend7.8% 0.45Note:WeekdayWeekendAverage% ErrorCity of RentonLong-range Wastewater Management PlanMeasured DataModeled DataDiurnalFLOW MONITORING SITE MH0166 DRY WEATHER FLOW CALIBRATION0.000.010.010.020.020.030.03024681012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekend0.00.20.40.60.81.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocityWeekday Weekend0.00.51.01.52.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelWeekday Weekend0.00.51.01.52.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.52.02.501234567891011121314151617181920212223Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.058 3.2 0.58 0.051 2.465 0.75 0.76 0.84 0.76 0.77 0.771 0.056 3.2 0.58 0.056 2.553 0.91 0.66 0.86 0.77 0.78 0.782 0.057 3.2 0.57 0.058 2.579 0.92 0.61 0.89 0.80 0.81 0.813 0.059 3.2 0.58 0.060 2.604 0.92 0.61 0.88 0.79 0.80 0.804 0.058 3.2 0.59 0.061 2.630 0.84 0.60 0.97 0.88 0.89 0.895 0.064 3.3 0.60 0.064 2.766 0.89 0.50 1.08 0.97 0.98 0.986 0.071 3.4 0.64 0.070 2.902 0.99 0.48 1.19 1.07 1.08 1.087 0.078 3.5 0.67 0.080 3.009 1.03 0.49 1.26 1.14 1.15 1.158 0.083 3.6 0.71 0.085 3.098 1.07 0.52 1.35 1.21 1.22 1.229 0.089 3.7 0.72 0.090 3.184 1.10 0.50 1.42 1.28 1.29 1.2910 0.094 3.8 0.75 0.094 3.251 1.12 0.51 1.43 1.29 1.30 1.3011 0.094 3.8 0.75 0.095 3.265 1.13 0.52 1.44 1.29 1.31 1.3112 0.095 3.8 0.76 0.095 3.266 1.13 0.54 1.41 1.27 1.29 1.2913 0.093 3.8 0.76 0.093 3.226 1.11 0.58 1.34 1.21 1.22 1.2214 0.088 3.8 0.75 0.088 3.140 1.08 0.61 1.27 1.14 1.16 1.1615 0.084 3.7 0.72 0.084 3.064 1.06 0.60 1.22 1.10 1.11 1.1116 0.081 3.6 0.71 0.080 2.977 1.03 0.65 1.11 1.00 1.01 1.0117 0.073 3.5 0.68 0.074 2.851 0.99 0.69 1.05 0.95 0.95 0.9518 0.069 3.4 0.65 0.070 2.771 0.96 0.68 1.01 0.91 0.92 0.9219 0.067 3.4 0.64 0.067 2.708 0.92 0.70 0.95 0.86 0.86 0.8620 0.063 3.4 0.62 0.063 2.639 0.94 0.71 0.92 0.83 0.84 0.8421 0.061 3.3 0.60 0.062 2.613 0.88 0.66 0.90 0.82 0.82 0.8222 0.060 3.3 0.60 0.060 2.587 0.90 0.67 0.87 0.78 0.79 0.7923 0.057 3.2 0.58 0.058 2.528 0.84 0.68 0.87 0.70 0.70 0.7024 0.048 3.1 0.53 0.050 2.425 0.75 0.64 0.71 0.97 0.90 0.9025 0.047 3.0 0.51 0.046 2.273 0.75 0.77 0.71 0.96 0.96 0.9626 0.047 3.0 0.51 0.048 2.315 0.80 0.71 0.69 0.93 0.94 0.9427 0.046 3.0 0.51 0.047 2.306 0.71 0.70 0.69 0.93 0.94 0.9428 0.046 3.0 0.51 0.046 2.310 0.75 0.69 0.70 0.95 0.95 0.9529 0.046 3.0 0.51 0.048 2.324 0.76 0.67 0.71 0.97 0.98 0.9830 0.047 3.0 0.51 0.049 2.338 0.81 0.69 0.72 0.98 0.99 0.9931 0.048 3.0 0.52 0.049 2.334 0.88 0.71 0.72 0.98 0.99 0.9932 0.048 3.1 0.52 0.050 2.323 0.86 0.73 0.73 0.99 1.00 1.0033 0.048 3.1 0.52 0.048 2.320 0.83 0.74 0.74 1.00 1.01 1.0134 0.049 3.1 0.53 0.050 2.327 0.74 0.74 0.75 1.01 1.02 1.0235 0.049 3.1 0.52 0.051 2.331 0.74 0.74 0.75 1.02 1.03 1.0336 0.050 3.1 0.53 0.051 2.348 0.82 0.75 0.78 1.05 1.06 1.0637 0.051 3.1 0.53 0.052 2.376 0.82 0.75 0.78 1.05 1.06 1.0638 0.051 3.1 0.53 0.050 2.374 0.82 0.75 0.75 1.02 1.03 1.0339 0.050 3.1 0.53 0.052 2.370 0.82 0.74 0.79 1.07 1.08 1.0840 0.052 3.1 0.54 0.051 2.407 0.80 0.71 0.78 1.05 1.06 1.0641 0.051 3.1 0.55 0.050 2.396 0.82 0.72 0.78 1.06 1.07 1.0742 0.052 3.1 0.55 0.053 2.393 0.87 0.73 0.75 1.02 1.03 1.0343 0.050 3.1 0.54 0.051 2.355 0.75 0.77 0.73 0.99 1.00 1.0044 0.048 3.1 0.52 0.047 2.325 0.71 0.76 0.71 0.97 0.98 0.9845 0.047 3.1 0.52 0.049 2.309 0.79 0.78 0.72 0.98 0.99 0.9946 0.048 3.0 0.52 0.047 2.330 0.77 0.72 0.72 0.98 0.99 0.9947 0.048 3.0 0.51 0.049 2.336 0.79 0.69 0.73 0.99 1.00 1.00Weekday 0.073 3.5 0.66 0.073 2.9 0.98 1.11 0.99 1.00 1.00Weekend 0.048 3.1 0.52 0.049 2.3 0.79 0.74 0.99 1.00 1.00ADWF(1)0.066 3.4 0.62 0.066 2.7 0.93 1.00 0.99 1.00Weekday0.7% 0.76Weekend2.1% 0.78Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH0286 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.020.040.060.080.100 2 4 6 8 1012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.00.20.40.60.81.01.20 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.00.51.01.52.02.53.03.54.00 2 4 6 8 1012141618202224262830323436384042444648Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.224 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.247 1.6 8.22 0.266 1.9 6.95 -0.38 0.71 0.711 0.225 1.5 7.89 0.236 1.8 6.71 -0.34 0.68 0.682 0.217 1.4 7.65 0.219 1.8 6.56 -0.33 0.69 0.693 0.219 1.4 7.58 0.216 1.8 6.55 -0.33 0.75 0.754 0.240 1.5 7.90 0.231 1.8 6.69 -0.35 1.00 1.005 0.317 1.6 8.41 0.280 2.1 7.21 -0.47 1.20 1.206 0.380 1.8 9.04 0.347 2.3 7.62 -0.47 1.23 1.237 0.392 1.9 9.29 0.379 2.3 7.77 -0.43 1.14 1.148 0.363 1.9 9.20 0.370 2.3 7.65 -0.41 1.10 1.109 0.350 1.8 9.07 0.352 2.2 7.55 -0.42 1.02 1.0210 0.325 1.8 8.98 0.332 2.2 7.43 -0.40 0.99 0.9911 0.316 1.7 8.86 0.319 2.1 7.33 -0.40 0.99 0.9912 0.313 1.7 8.78 0.314 2.1 7.29 -0.41 0.97 0.9713 0.308 1.7 8.76 0.308 2.1 7.28 -0.41 0.99 0.9914 0.313 1.7 8.76 0.310 2.1 7.32 -0.43 0.99 0.9915 0.314 1.7 8.80 0.314 2.1 7.35 -0.43 1.04 1.0416 0.329 1.7 8.85 0.321 2.2 7.43 -0.46 1.08 1.0817 0.343 1.8 8.96 0.335 2.2 7.51 -0.46 1.15 1.1518 0.364 1.8 9.13 0.353 2.3 7.63 -0.46 1.18 1.1819 0.374 1.9 9.15 0.367 2.3 7.68 -0.45 1.20 1.2020 0.382 1.9 9.20 0.374 2.3 7.71 -0.44 1.16 1.1621 0.370 1.9 9.21 0.369 2.3 7.69 -0.41 1.06 1.0622 0.336 1.8 9.01 0.346 2.2 7.50 -0.40 0.90 0.9023 0.285 1.7 8.72 0.307 2.1 7.22 -0.37 0.78 0.7824 0.257 1.6 8.39 0.266 1.9 6.93 -0.34 0.74 0.7425 0.234 1.5 8.10 0.241 1.9 6.80 -0.36 0.69 0.6926 0.220 1.5 7.84 0.225 1.8 6.64 -0.34 0.66 0.6627 0.210 1.4 7.67 0.212 1.8 6.53 -0.32 0.67 0.6728 0.214 1.4 7.61 0.210 1.8 6.53 -0.34 0.75 0.7529 0.237 1.4 7.75 0.227 1.8 6.69 -0.38 0.89 0.8930 0.283 1.5 8.27 0.261 2.0 6.99 -0.43 1.10 1.1031 0.351 1.7 8.87 0.315 2.2 7.44 -0.47 1.25 1.2532 0.397 1.9 9.19 0.367 2.3 7.72 -0.46 1.12 1.1233 0.356 1.9 9.16 0.369 2.3 7.67 -0.43 1.17 1.1734 0.373 1.9 9.10 0.364 2.3 7.67 -0.42 1.13 1.1335 0.359 1.9 9.04 0.361 2.3 7.62 -0.41 1.12 1.1236 0.356 1.8 9.01 0.356 2.2 7.57 -0.44 1.10 1.1037 0.349 1.8 8.97 0.350 2.2 7.55 -0.42 1.09 1.0938 0.346 1.8 9.02 0.346 2.2 7.54 -0.42 1.08 1.0839 0.343 1.8 8.98 0.344 2.2 7.54 -0.43 1.11 1.1140 0.353 1.8 8.98 0.347 2.2 7.57 -0.45 1.07 1.0741 0.339 1.8 9.06 0.345 2.2 7.53 -0.41 1.15 1.1542 0.364 1.8 8.95 0.353 2.3 7.59 -0.43 1.12 1.1243 0.357 1.8 9.01 0.357 2.3 7.59 -0.44 1.14 1.1444 0.363 1.8 9.00 0.358 2.3 7.62 -0.43 1.12 1.1245 0.355 1.8 9.06 0.354 2.3 7.60 -0.43 1.01 1.0146 0.320 1.8 8.98 0.333 2.2 7.43 -0.38 0.90 0.9047 0.286 1.7 8.59 0.301 2.1 7.21 -0.40 0.81 0.81Weekday 0.317 1.7 8.73 0.315 2.1 7.32 1.00 #DIV/0! 1.00Weekend 0.317 1.7 8.69 0.315 2.1 7.31 1.00 #DIV/0! 1.00ADWF(1)0.317 1.7 8.72 0.315 2.1 7.32 1.00 #DIV/0! 1.00Weekday-0.7% 0.47Weekend-0.7% 0.47Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH0537 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.100.200.300.400.500 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.02.04.06.08.010.012.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.00.51.01.52.02.53.0024681012141618202224262830323436384042444648Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.140 1.9 3.06 0.166 3.2 1.76 -1.29 0.62 0.621 0.128 1.8 2.92 0.156 3.1 1.73 -1.30 0.61 0.612 0.126 1.8 2.89 0.153 3.1 1.72 -1.32 0.65 0.653 0.135 1.8 2.92 0.160 3.2 1.76 -1.39 0.84 0.844 0.173 1.9 3.16 0.188 3.4 1.85 -1.55 1.05 1.055 0.215 2.1 3.45 0.221 3.7 1.94 -1.55 1.14 1.146 0.234 2.3 3.61 0.240 3.8 1.98 -1.50 1.14 1.147 0.234 2.3 3.62 0.243 3.8 1.98 -1.45 1.09 1.098 0.224 2.3 3.57 0.237 3.7 1.96 -1.42 1.07 1.079 0.221 2.3 3.52 0.231 3.7 1.95 -1.41 1.04 1.0410 0.214 2.3 3.49 0.224 3.6 1.93 -1.37 1.02 1.0211 0.211 2.2 3.44 0.219 3.6 1.92 -1.38 1.03 1.0312 0.213 2.2 3.46 0.216 3.6 1.91 -1.34 1.00 1.0013 0.207 2.2 3.45 0.212 3.6 1.90 -1.34 0.98 0.9814 0.203 2.2 3.43 0.213 3.6 1.91 -1.37 1.03 1.0315 0.213 2.2 3.39 0.224 3.7 1.94 -1.46 1.11 1.1116 0.228 2.3 3.51 0.236 3.7 1.97 -1.46 1.18 1.1817 0.242 2.4 3.56 0.248 3.8 2.00 -1.48 1.24 1.2418 0.254 2.4 3.62 0.258 3.9 2.02 -1.47 1.24 1.2419 0.255 2.5 3.65 0.260 3.9 2.02 -1.44 1.21 1.2120 0.248 2.4 3.62 0.254 3.8 2.00 -1.41 1.09 1.0921 0.224 2.4 3.57 0.234 3.7 1.95 -1.32 0.92 0.9222 0.189 2.2 3.42 0.207 3.5 1.87 -1.27 0.76 0.7623 0.157 2.0 3.21 0.183 3.3 1.81 -1.29 0.68 0.6824 0.148 2.0 3.15 0.166 3.2 1.75 -1.21 0.63 0.6325 0.130 1.8 3.00 0.153 3.1 1.72 -1.23 0.59 0.5926 0.122 1.8 2.78 0.147 3.0 1.70 -1.25 0.62 0.6227 0.127 1.8 2.86 0.146 3.0 1.70 -1.27 0.63 0.6328 0.131 1.8 2.89 0.151 3.1 1.72 -1.32 0.72 0.7229 0.148 1.8 3.00 0.163 3.2 1.77 -1.39 0.89 0.8930 0.183 1.9 3.29 0.192 3.4 1.87 -1.50 1.12 1.1231 0.230 2.2 3.48 0.232 3.7 1.97 -1.57 1.30 1.3032 0.268 2.4 3.67 0.261 3.9 2.03 -1.53 1.34 1.3433 0.276 2.5 3.75 0.269 4.0 2.05 -1.43 1.35 1.3534 0.278 2.6 3.75 0.267 3.9 2.04 -1.39 1.25 1.2535 0.258 2.5 3.67 0.257 3.9 2.01 -1.35 1.21 1.2136 0.250 2.4 3.63 0.248 3.8 1.99 -1.35 1.19 1.1937 0.245 2.4 3.60 0.244 3.8 1.98 -1.37 1.17 1.1738 0.241 2.4 3.61 0.244 3.8 1.98 -1.39 1.17 1.1739 0.240 2.4 3.57 0.241 3.8 1.98 -1.39 1.17 1.1740 0.240 2.4 3.58 0.241 3.8 1.98 -1.40 1.20 1.2041 0.247 2.4 3.59 0.241 3.8 1.98 -1.39 1.23 1.2342 0.253 2.4 3.64 0.246 3.8 1.99 -1.38 1.20 1.2043 0.248 2.4 3.62 0.247 3.8 1.99 -1.37 1.16 1.1644 0.239 2.4 3.58 0.239 3.7 1.97 -1.33 1.05 1.0545 0.217 2.3 3.53 0.218 3.6 1.91 -1.24 0.90 0.9046 0.186 2.2 3.39 0.196 3.4 1.84 -1.21 0.81 0.8147 0.167 2.0 3.19 0.178 3.3 1.79 -1.24 0.72 0.72Weekday 0.203 2.2 3.40 0.216 3.6 1.91 0.99 #DIV/0! 0.99Weekend 0.211 2.2 3.41 0.216 3.6 1.90 1.03 #DIV/0! 1.03ADWF(1)0.206 2.2 3.40 0.216 3.6 1.91 1.00 #DIV/0! 1.00Weekday6.1% 1.55Weekend2.4% 1.57Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH1360 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250.300.350.400 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.00.51.01.52.02.53.03.54.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.07.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.524 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.113 6.5 0.39 0.149 5.5 0.71 0.95 0.52 0.521 0.089 5.7 0.35 0.119 4.8 0.69 0.92 0.44 0.442 0.075 5.2 0.32 0.096 4.3 0.65 0.91 0.42 0.423 0.072 5.0 0.31 0.083 4.1 0.61 0.83 0.54 0.544 0.092 5.0 0.33 0.077 4.3 0.58 0.73 0.76 0.765 0.130 5.7 0.40 0.093 5.1 0.58 0.58 1.11 1.116 0.189 7.3 0.42 0.127 5.8 0.69 1.48 1.34 1.347 0.229 9.2 0.43 0.182 6.5 0.77 2.65 1.35 1.358 0.231 10.2 0.40 0.221 6.8 0.84 3.44 1.32 1.329 0.225 10.3 0.40 0.234 6.7 0.85 3.59 1.23 1.2310 0.210 9.9 0.39 0.221 6.7 0.83 3.22 1.13 1.1311 0.193 9.3 0.39 0.207 6.5 0.82 2.81 1.08 1.0812 0.184 8.8 0.39 0.200 6.5 0.77 2.31 1.00 1.0013 0.170 8.3 0.40 0.181 6.3 0.77 2.00 0.91 0.9114 0.156 7.8 0.40 0.168 6.3 0.72 1.46 0.93 0.9315 0.159 7.5 0.39 0.162 6.2 0.72 1.33 1.00 1.0016 0.170 7.5 0.42 0.163 6.3 0.71 1.22 1.07 1.0717 0.182 7.7 0.43 0.172 6.5 0.72 1.22 1.17 1.1718 0.199 8.1 0.44 0.185 6.8 0.74 1.36 1.25 1.2519 0.212 8.5 0.44 0.201 6.9 0.77 1.61 1.27 1.2720 0.216 8.8 0.45 0.214 6.9 0.80 1.91 1.18 1.1821 0.200 8.7 0.44 0.214 6.8 0.80 1.89 1.01 1.0122 0.171 8.2 0.42 0.195 6.5 0.78 1.69 0.84 0.8423 0.143 7.4 0.40 0.176 6.1 0.74 1.27 0.66 0.6624 0.140 6.8 0.45 0.141 5.5 0.72 1.28 0.66 0.6625 0.112 6.0 0.42 0.127 4.9 0.70 1.11 0.57 0.5726 0.097 5.3 0.40 0.107 4.3 0.72 1.06 0.50 0.5027 0.085 5.0 0.38 0.096 4.0 0.70 0.99 0.51 0.5128 0.087 4.8 0.37 0.087 3.9 0.67 0.93 0.70 0.7029 0.120 5.6 0.37 0.087 3.9 0.70 1.64 0.98 0.9830 0.168 7.3 0.38 0.109 4.6 0.74 2.71 1.19 1.1931 0.202 8.5 0.39 0.149 5.5 0.79 3.06 1.48 1.4832 0.252 9.8 0.41 0.197 6.6 0.80 3.27 1.59 1.5933 0.270 10.7 0.44 0.235 7.1 0.84 3.67 1.58 1.5834 0.270 10.6 0.46 0.253 7.4 0.85 3.19 1.40 1.4035 0.239 10.0 0.47 0.246 7.3 0.84 2.73 1.28 1.2836 0.217 9.3 0.44 0.225 7.1 0.80 2.19 1.15 1.1537 0.196 8.8 0.43 0.203 6.9 0.77 1.95 1.08 1.0838 0.184 8.5 0.40 0.188 6.7 0.74 1.84 1.06 1.0639 0.180 8.3 0.41 0.177 6.6 0.71 1.67 1.08 1.0840 0.184 8.2 0.40 0.172 6.5 0.72 1.62 1.13 1.1341 0.192 8.2 0.42 0.175 6.7 0.72 1.53 1.11 1.1142 0.189 8.3 0.42 0.179 6.6 0.73 1.68 1.16 1.1643 0.197 8.4 0.42 0.181 6.8 0.72 1.59 1.20 1.2044 0.204 8.6 0.44 0.186 6.8 0.74 1.80 1.06 1.0645 0.180 8.5 0.42 0.186 6.7 0.74 1.77 0.95 0.9546 0.162 7.9 0.40 0.171 6.3 0.73 1.67 0.91 0.9147 0.155 7.2 0.41 0.159 5.9 0.72 1.30 0.82 0.82Weekday 0.167 7.8 0.40 0.168 6.1 0.74 0.98 #DIV/0! 0.98Weekend 0.178 7.9 0.41 0.168 6.0 0.75 1.05 #DIV/0! 1.05ADWF(1)0.170 7.8 0.40 0.168 6.0 0.74 1.00 #DIV/0! 1.00Weekday0.9% 3.59Weekend-5.6% 3.67Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH1763 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250.300 2 4 6 8 1012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.00.20.40.60.81.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.02.04.06.08.010.012.014.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.51.01.50 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.52.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.439 4.1 2.66 0.399 4.8 2.46 -0.74 0.74 0.741 0.422 4.0 2.59 0.385 4.6 2.40 -0.68 0.72 0.722 0.414 3.9 2.56 0.344 4.9 2.50 -0.98 0.75 0.753 0.432 3.9 2.59 0.405 4.6 2.37 -0.65 0.85 0.854 0.485 4.1 2.65 0.377 4.8 2.44 -0.73 0.98 0.985 0.560 4.3 2.78 0.427 5.1 2.52 -0.82 1.09 1.096 0.624 4.6 2.94 0.482 5.5 2.57 -0.90 1.11 1.117 0.639 4.8 2.97 0.537 5.8 2.62 -1.01 1.12 1.128 0.640 4.8 2.96 0.585 6.1 2.71 -1.33 1.11 1.119 0.639 4.8 2.97 0.588 6.2 2.66 -1.36 1.11 1.1110 0.639 4.8 2.97 0.648 6.0 2.64 -1.20 1.09 1.0911 0.626 4.8 2.96 0.584 6.3 2.69 -1.54 1.09 1.0912 0.623 4.8 2.95 0.570 6.0 2.64 -1.20 1.08 1.0813 0.618 4.7 2.94 0.625 5.9 2.63 -1.16 1.05 1.0514 0.604 4.7 2.93 0.565 6.2 2.67 -1.50 1.07 1.0715 0.613 4.7 2.94 0.553 5.9 2.62 -1.23 1.10 1.1016 0.629 4.7 2.96 0.559 5.9 2.63 -1.17 1.13 1.1317 0.648 4.8 2.98 0.615 5.9 2.64 -1.14 1.13 1.1318 0.648 4.8 2.99 0.633 6.2 2.71 -1.36 1.12 1.1219 0.644 4.8 2.98 0.595 6.2 2.66 -1.36 1.08 1.0820 0.617 4.8 2.96 0.561 5.9 2.63 -1.11 1.00 1.0021 0.573 4.6 2.90 0.526 5.6 2.60 -1.01 0.91 0.9122 0.523 4.5 2.83 0.559 5.8 2.65 -1.35 0.84 0.8423 0.483 4.2 2.72 0.484 5.4 2.55 -1.15 0.77 0.7724 0.447 4.1 2.67 0.444 5.2 2.52 -1.06 0.70 0.7025 0.403 3.9 2.58 0.353 4.6 2.37 -0.66 0.69 0.6926 0.398 3.8 2.56 0.332 4.4 2.33 -0.60 0.70 0.7027 0.403 3.8 2.53 0.321 4.4 2.32 -0.58 0.69 0.6928 0.397 3.8 2.56 0.319 4.4 2.31 -0.52 0.76 0.7629 0.434 3.8 2.56 0.345 4.8 2.44 -1.01 0.90 0.9030 0.518 4.1 2.72 0.395 4.9 2.48 -0.84 1.07 1.0731 0.615 4.4 2.91 0.469 5.4 2.56 -0.97 1.16 1.1632 0.664 4.8 3.00 0.537 5.9 2.65 -1.08 1.25 1.2533 0.716 5.1 3.03 0.618 6.3 2.72 -1.27 1.24 1.2434 0.714 5.2 3.03 0.737 6.6 2.71 -1.40 1.21 1.2135 0.692 5.1 3.03 0.673 6.8 2.75 -1.75 1.20 1.2036 0.686 5.0 3.02 0.678 6.8 2.78 -1.83 1.16 1.1637 0.663 4.9 3.00 0.682 6.7 2.78 -1.75 1.15 1.1538 0.660 4.9 3.01 0.687 6.3 2.71 -1.47 1.13 1.1339 0.650 4.8 3.00 0.681 6.2 2.67 -1.41 1.12 1.1240 0.644 4.8 3.01 0.615 6.4 2.69 -1.59 1.13 1.1341 0.646 4.8 2.99 0.608 6.1 2.65 -1.25 1.13 1.1342 0.646 4.8 3.00 0.632 6.4 2.71 -1.61 1.10 1.1043 0.633 4.8 3.00 0.583 6.0 2.64 -1.24 1.02 1.0244 0.585 4.7 2.94 0.556 5.8 2.62 -1.11 0.96 0.9645 0.553 4.5 2.89 0.562 6.0 2.64 -1.41 0.87 0.8746 0.497 4.3 2.77 0.478 5.4 2.56 -1.06 0.80 0.8047 0.457 4.2 2.67 0.433 5.1 2.52 -0.95 0.78 0.78Weekday 0.574 4.5 2.86 0.525 5.7 2.59 1.00 #DIV/0! 1.00Weekend 0.572 4.5 2.85 0.531 5.7 2.59 1.00 #DIV/0! 1.00ADWF(1)0.573 4.5 2.86 0.527 5.7 2.59 1.00 #DIV/0! 1.00Weekday-8.5% 1.54Weekend-7.1% 1.83Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH2116 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.200.400.600.801.000 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.00.51.01.52.02.53.03.54.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.07.08.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.101 3.2 1.00 0.101 3.4 1.12 -0.22 0.55 0.52 0.551 0.095 3.1 0.97 0.097 3.4 1.11 -0.26 0.59 0.56 0.592 0.103 3.0 0.96 0.110 3.6 1.16 -0.58 0.95 0.89 0.953 0.165 3.5 1.09 0.160 4.5 1.26 -1.01 0.99 0.93 0.994 0.171 3.9 1.23 0.179 4.7 1.29 -0.84 1.28 1.21 1.285 0.223 4.1 1.27 0.226 5.4 1.37 -1.30 1.54 1.46 1.546 0.268 4.6 1.44 0.266 5.8 1.42 -1.19 1.60 1.51 1.607 0.278 4.9 1.50 0.273 5.9 1.43 -1.03 1.52 1.44 1.528 0.264 4.8 1.49 0.260 5.7 1.41 -0.92 1.41 1.33 1.419 0.244 4.7 1.43 0.240 5.5 1.38 -0.84 1.28 1.21 1.2810 0.223 4.5 1.39 0.220 5.2 1.35 -0.74 1.21 1.15 1.2111 0.211 4.3 1.34 0.210 5.1 1.34 -0.78 1.22 1.15 1.2212 0.212 4.3 1.33 0.210 5.1 1.34 -0.86 1.19 1.12 1.1913 0.206 4.3 1.32 0.207 5.1 1.34 -0.83 1.24 1.17 1.2414 0.215 4.3 1.32 0.211 5.1 1.34 -0.86 1.14 1.07 1.1415 0.197 4.3 1.32 0.199 5.0 1.32 -0.72 1.18 1.11 1.1816 0.204 4.2 1.30 0.199 5.0 1.32 -0.79 1.05 0.99 1.0517 0.183 4.2 1.30 0.179 4.7 1.28 -0.53 0.93 0.88 0.9318 0.161 3.9 1.20 0.163 4.5 1.26 -0.57 0.95 0.90 0.9519 0.165 3.9 1.20 0.163 4.5 1.26 -0.60 0.91 0.86 0.9120 0.159 3.9 1.19 0.156 4.4 1.24 -0.51 0.84 0.79 0.8421 0.146 3.8 1.17 0.143 4.2 1.21 -0.39 0.73 0.69 0.7322 0.126 3.6 1.11 0.126 3.9 1.17 -0.31 0.65 0.61 0.6523 0.112 3.4 1.05 0.112 3.6 1.14 -0.28 0.58 0.55 0.5824 0.113 3.3 1.06 0.102 3.4 1.12 -0.12 0.61 0.72 0.6125 0.106 3.2 1.03 0.105 3.5 1.13 -0.30 0.59 0.70 0.5926 0.102 3.2 1.00 0.102 3.5 1.12 -0.30 0.57 0.68 0.5727 0.099 3.1 0.99 0.099 3.4 1.11 -0.30 0.58 0.69 0.5828 0.100 3.1 0.99 0.101 3.5 1.12 -0.36 0.63 0.75 0.6329 0.110 3.2 1.00 0.111 3.6 1.15 -0.49 0.73 0.87 0.7330 0.127 3.3 1.05 0.129 4.0 1.19 -0.62 0.88 1.05 0.8831 0.153 3.6 1.12 0.154 4.4 1.25 -0.75 1.01 1.21 1.0132 0.176 3.9 1.22 0.175 4.7 1.28 -0.76 1.08 1.29 1.0833 0.188 4.0 1.26 0.185 4.8 1.30 -0.76 1.05 1.25 1.0534 0.182 4.1 1.28 0.181 4.7 1.29 -0.65 1.01 1.21 1.0135 0.176 4.0 1.26 0.174 4.6 1.28 -0.64 0.97 1.16 0.9736 0.169 3.9 1.24 0.168 4.5 1.27 -0.62 0.96 1.14 0.9637 0.166 3.9 1.22 0.166 4.5 1.26 -0.63 0.95 1.13 0.9538 0.165 3.9 1.22 0.164 4.5 1.26 -0.62 0.94 1.12 0.9439 0.163 3.8 1.21 0.163 4.5 1.26 -0.62 0.93 1.11 0.9340 0.162 3.8 1.21 0.161 4.4 1.25 -0.59 0.93 1.11 0.9341 0.161 3.8 1.21 0.162 4.5 1.26 -0.64 0.97 1.15 0.9742 0.168 3.9 1.20 0.168 4.5 1.27 -0.67 0.98 1.17 0.9843 0.170 3.9 1.22 0.167 4.5 1.26 -0.61 0.91 1.09 0.9144 0.159 3.9 1.22 0.156 4.4 1.24 -0.49 0.83 0.99 0.8345 0.144 3.7 1.17 0.142 4.1 1.21 -0.40 0.74 0.88 0.7446 0.129 3.6 1.12 0.128 3.9 1.18 -0.35 0.69 0.82 0.6947 0.120 3.4 1.06 0.119 3.8 1.16 -0.36 0.65 0.77 0.65Weekday 0.184 4.0 1.25 0.184 4.7 1.29 1.06 1.00 1.06Weekend 0.146 3.6 1.15 0.145 4.2 1.22 0.84 1.00 0.84ADWF(1)0.173 3.9 1.22 0.173 4.6 1.27 1.00 1.00 1.00Weekday-0.4% 1.30Weekend-0.5% 0.76Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH2171 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250.300.350.400 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.00.51.01.52.02.53.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.51.01.52.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.20 1 2 3 4 5 6 7 8 9 1011121314151617181920212223Hourly MultiplierHourWeekday Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.457 2.8 4.13 0.474 2.9 2.54 -0.04 0.66 0.661 0.434 2.8 3.97 0.443 2.8 2.50 -0.06 0.66 0.662 0.433 2.7 3.96 0.435 2.8 2.49 -0.07 0.67 0.673 0.438 2.7 3.95 0.440 2.8 2.50 -0.08 0.74 0.744 0.483 2.8 4.00 0.479 2.9 2.58 -0.16 0.93 0.935 0.611 3.0 4.31 0.590 3.2 2.74 -0.21 1.09 1.096 0.711 3.3 4.68 0.688 3.4 2.87 -0.12 1.09 1.097 0.716 3.4 4.83 0.715 3.5 2.88 -0.07 1.08 1.088 0.710 3.4 4.82 0.712 3.5 2.88 -0.09 1.08 1.089 0.707 3.4 4.78 0.710 3.5 2.88 -0.10 1.09 1.0910 0.714 3.4 4.81 0.713 3.5 2.88 -0.10 1.07 1.0711 0.702 3.4 4.80 0.705 3.5 2.87 -0.09 1.05 1.0512 0.685 3.3 4.79 0.689 3.4 2.85 -0.10 1.02 1.0213 0.667 3.3 4.74 0.672 3.4 2.83 -0.10 1.00 1.0014 0.658 3.2 4.68 0.663 3.4 2.82 -0.12 1.04 1.0415 0.683 3.3 4.71 0.680 3.4 2.85 -0.13 1.08 1.0816 0.706 3.3 4.78 0.705 3.5 2.88 -0.13 1.14 1.1417 0.750 3.4 4.83 0.746 3.5 2.92 -0.15 1.23 1.2318 0.805 3.5 4.97 0.797 3.6 2.98 -0.14 1.28 1.2819 0.837 3.6 5.11 0.829 3.7 3.02 -0.11 1.22 1.2220 0.800 3.6 5.12 0.802 3.6 2.98 -0.05 1.09 1.0921 0.716 3.5 4.97 0.727 3.5 2.88 -0.02 0.93 0.9322 0.608 3.2 4.69 0.628 3.3 2.75 -0.01 0.79 0.7923 0.517 3.0 4.39 0.538 3.0 2.63 -0.02 0.70 0.7024 0.445 2.8 4.09 0.471 2.9 2.53 -0.05 0.62 0.6225 0.405 2.7 3.91 0.411 2.7 2.43 -0.02 0.60 0.6026 0.392 2.6 3.83 0.383 2.6 2.40 -0.01 0.60 0.6027 0.391 2.6 3.80 0.377 2.6 2.39 -0.01 0.60 0.6028 0.395 2.6 3.80 0.381 2.6 2.40 -0.02 0.65 0.6529 0.428 2.6 3.87 0.409 2.7 2.46 -0.10 0.81 0.8130 0.534 2.8 4.11 0.496 3.0 2.62 -0.19 1.09 1.0931 0.714 3.1 4.62 0.655 3.4 2.84 -0.23 1.31 1.3132 0.855 3.5 5.03 0.798 3.6 3.00 -0.13 1.40 1.4033 0.918 3.7 5.24 0.872 3.8 3.06 -0.04 1.41 1.4134 0.927 3.8 5.34 0.888 3.8 3.07 -0.02 1.37 1.3735 0.900 3.8 5.32 0.868 3.8 3.05 -0.01 1.32 1.3236 0.862 3.7 5.26 0.834 3.7 3.01 -0.03 1.24 1.2437 0.814 3.6 5.16 0.792 3.6 2.97 -0.03 1.20 1.2038 0.788 3.5 5.05 0.763 3.6 2.93 -0.05 1.17 1.1739 0.766 3.5 5.02 0.742 3.5 2.91 -0.04 1.15 1.1540 0.754 3.4 4.93 0.730 3.5 2.90 -0.06 1.17 1.1741 0.764 3.5 4.94 0.736 3.5 2.91 -0.06 1.21 1.2142 0.790 3.5 4.97 0.756 3.6 2.93 -0.07 1.23 1.2343 0.804 3.5 5.04 0.768 3.6 2.95 -0.04 1.17 1.1744 0.767 3.5 5.02 0.739 3.5 2.90 0.00 1.03 1.0345 0.676 3.4 4.86 0.664 3.3 2.80 0.06 0.89 0.8946 0.582 3.2 4.58 0.578 3.1 2.69 0.03 0.76 0.7647 0.501 3.0 4.34 0.500 3.0 2.58 0.01 0.68 0.68Weekday 0.648 3.2 4.62 0.649 3.3 2.79 0.99 #DIV/0! 0.99Weekend 0.674 3.3 4.67 0.650 3.3 2.78 1.03 #DIV/0! 1.03ADWF(1)0.655 3.2 4.63 0.649 3.3 2.79 1.00 #DIV/0! 1.00Weekday0.2% 0.21Weekend-3.4% 0.23Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH2252 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal-0.100.100.300.500.700.901.101.300 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.01.02.03.04.05.06.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.07.0024681012141618202224262830323436384042444648Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 1011121314151617181920212223Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.524 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.136 1.5 4.78 0.070 1.4 3.19 0.08 0.71 0.711 0.126 1.5 4.64 0.065 1.4 3.13 0.09 0.71 0.712 0.126 1.4 4.53 0.065 1.4 3.17 0.05 0.78 0.783 0.139 1.5 4.72 0.070 1.4 3.23 0.03 0.86 0.864 0.153 1.5 4.86 0.081 1.5 3.33 -0.01 1.01 1.015 0.179 1.6 5.20 0.096 1.6 3.41 0.04 1.08 1.086 0.193 1.7 5.34 0.187 2.2 4.25 -0.57 1.12 1.127 0.199 1.7 5.49 0.212 2.3 4.28 -0.55 1.14 1.148 0.204 1.7 5.51 0.200 2.3 4.31 -0.57 1.08 1.089 0.193 1.7 5.48 0.189 2.4 4.43 -0.71 1.04 1.0410 0.186 1.7 5.40 0.179 2.3 4.24 -0.56 1.00 1.0011 0.178 1.7 5.31 0.174 2.2 4.16 -0.53 1.00 1.0012 0.178 1.6 5.30 0.188 2.2 4.15 -0.53 0.97 0.9713 0.173 1.6 5.25 0.193 2.1 4.12 -0.52 0.97 0.9714 0.172 1.6 5.26 0.187 2.1 4.11 -0.52 1.00 1.0015 0.179 1.6 5.29 0.185 2.2 4.21 -0.57 1.06 1.0616 0.189 1.7 5.34 0.187 2.4 4.41 -0.75 1.09 1.0917 0.194 1.7 5.41 0.188 2.3 4.30 -0.61 1.13 1.1318 0.201 1.7 5.54 0.193 2.3 4.30 -0.55 1.17 1.1719 0.208 1.8 5.56 0.221 2.3 4.35 -0.59 1.12 1.1220 0.200 1.7 5.50 0.211 2.4 4.43 -0.69 1.02 1.0221 0.182 1.7 5.46 0.185 2.2 4.20 -0.49 0.92 0.9222 0.165 1.6 5.21 0.165 2.1 4.06 -0.48 0.81 0.8123 0.144 1.5 5.00 0.148 2.0 3.92 -0.43 0.76 0.7624 0.147 1.5 4.88 0.142 1.9 3.85 -0.39 0.73 0.7325 0.131 1.5 4.74 0.143 1.9 3.86 -0.44 0.75 0.7526 0.134 1.5 4.63 0.120 1.9 3.83 -0.42 0.74 0.7427 0.131 1.5 4.64 0.120 1.8 3.74 -0.36 0.79 0.7928 0.140 1.5 4.72 0.128 1.9 3.80 -0.39 0.83 0.8329 0.148 1.5 4.85 0.143 1.9 3.87 -0.43 0.99 0.9930 0.176 1.6 5.07 0.170 2.1 4.07 -0.52 1.18 1.1831 0.210 1.7 5.43 0.193 2.3 4.27 -0.56 1.29 1.2932 0.230 1.8 5.68 0.206 2.5 4.54 -0.68 1.29 1.2933 0.230 1.9 5.74 0.211 2.4 4.43 -0.55 1.26 1.2634 0.225 1.9 5.69 0.228 2.4 4.36 -0.51 1.20 1.2035 0.214 1.8 5.65 0.203 2.4 4.44 -0.57 1.18 1.1836 0.210 1.8 5.56 0.192 2.4 4.36 -0.57 1.16 1.1637 0.207 1.8 5.51 0.187 2.3 4.27 -0.51 1.13 1.1338 0.201 1.8 5.44 0.191 2.2 4.22 -0.47 1.13 1.1339 0.201 1.8 5.46 0.207 2.2 4.23 -0.47 1.15 1.1540 0.206 1.8 5.46 0.196 2.5 4.45 -0.69 1.14 1.1441 0.203 1.8 5.46 0.188 2.3 4.29 -0.54 1.20 1.2042 0.214 1.8 5.48 0.191 2.3 4.29 -0.51 1.18 1.1843 0.210 1.8 5.57 0.190 2.3 4.26 -0.46 1.15 1.1544 0.205 1.8 5.50 0.210 2.4 4.44 -0.62 1.06 1.0645 0.189 1.8 5.43 0.190 2.3 4.26 -0.53 0.94 0.9446 0.168 1.7 5.18 0.167 2.1 4.08 -0.46 0.82 0.8247 0.146 1.6 4.96 0.155 2.1 4.01 -0.49 0.82 0.82Weekday 0.175 1.6 5.22 0.160 2.0 3.99 0.98 #DIV/0! 0.98Weekend 0.186 1.7 5.28 0.178 2.2 4.18 1.05 #DIV/0! 1.05ADWF(1)0.178 1.6 5.24 0.165 2.1 4.04 1.00 #DIV/0! 1.00Weekday-8.4% 0.75Weekend-4.4% 0.69Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH2999 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250.300 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.01.02.03.04.05.06.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.0024681012141618202224262830323436384042444648Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.027 1.9 0.68 0.025 1.8 0.86 0.08 0.48 0.481 0.024 1.8 0.65 0.023 1.7 0.85 0.13 0.46 0.462 0.023 1.8 0.62 0.023 1.7 0.86 0.07 0.57 0.573 0.028 1.8 0.64 0.029 1.9 0.92 -0.10 0.75 0.754 0.037 2.0 0.73 0.039 2.3 0.99 -0.27 1.05 1.055 0.051 2.3 0.86 0.052 2.6 1.07 -0.36 1.25 1.256 0.061 2.5 0.96 0.061 2.9 1.11 -0.36 1.35 1.357 0.066 2.6 1.02 0.065 3.0 1.12 -0.38 1.41 1.418 0.069 2.7 1.04 0.066 3.0 1.12 -0.35 1.37 1.379 0.067 2.7 1.06 0.065 3.0 1.11 -0.28 1.34 1.3410 0.065 2.7 1.03 0.063 2.9 1.10 -0.30 1.28 1.2811 0.062 2.6 1.02 0.061 2.9 1.10 -0.30 1.34 1.3412 0.065 2.6 1.02 0.064 3.0 1.11 -0.36 1.36 1.3613 0.066 2.7 1.03 0.063 2.9 1.10 -0.28 1.23 1.2314 0.060 2.6 1.01 0.058 2.8 1.08 -0.21 1.18 1.1815 0.058 2.6 0.99 0.055 2.7 1.06 -0.18 1.08 1.0816 0.053 2.5 0.94 0.052 2.7 1.05 -0.23 1.16 1.1617 0.057 2.5 0.95 0.056 2.8 1.07 -0.29 1.21 1.2118 0.059 2.6 0.98 0.055 2.7 1.07 -0.19 1.05 1.0519 0.051 2.5 0.95 0.049 2.6 1.03 -0.09 0.96 0.9620 0.047 2.4 0.91 0.044 2.4 1.00 -0.03 0.82 0.8221 0.040 2.3 0.85 0.038 2.2 0.96 0.03 0.69 0.6922 0.034 2.1 0.78 0.032 2.0 0.91 0.08 0.58 0.5823 0.028 2.0 0.72 0.027 1.9 0.88 0.09 0.55 0.5524 0.028 2.0 0.69 0.026 1.8 0.87 0.11 0.49 0.4925 0.024 1.9 0.66 0.025 1.8 0.87 0.07 0.48 0.4826 0.024 1.8 0.63 0.025 1.8 0.88 0.02 0.52 0.5227 0.026 1.8 0.64 0.028 1.9 0.91 -0.07 0.63 0.6328 0.031 1.9 0.67 0.035 2.1 0.96 -0.22 0.85 0.8529 0.042 2.1 0.76 0.047 2.5 1.04 -0.38 1.12 1.1230 0.055 2.4 0.89 0.062 2.9 1.12 -0.48 1.44 1.4431 0.070 2.6 0.98 0.074 3.2 1.17 -0.57 1.45 1.4532 0.071 2.8 1.06 0.073 3.2 1.16 -0.40 1.36 1.3633 0.066 2.8 1.06 0.068 3.1 1.13 -0.30 1.26 1.2634 0.062 2.6 0.98 0.063 2.9 1.10 -0.34 1.15 1.1535 0.056 2.6 0.98 0.060 2.9 1.09 -0.28 1.23 1.2336 0.060 2.6 0.96 0.061 2.9 1.09 -0.37 1.13 1.1337 0.055 2.6 0.98 0.056 2.8 1.06 -0.17 1.01 1.0138 0.049 2.5 0.91 0.051 2.6 1.03 -0.17 0.94 0.9439 0.046 2.3 0.87 0.049 2.6 1.03 -0.26 1.00 1.0040 0.049 2.3 0.87 0.053 2.7 1.05 -0.37 1.13 1.1341 0.055 2.5 0.93 0.056 2.8 1.07 -0.32 1.05 1.0542 0.051 2.5 0.93 0.053 2.7 1.05 -0.22 1.00 1.0043 0.049 2.4 0.91 0.050 2.6 1.03 -0.17 0.89 0.8944 0.044 2.3 0.86 0.044 2.4 1.00 -0.11 0.78 0.7845 0.038 2.3 0.83 0.039 2.3 0.97 -0.02 0.67 0.6746 0.033 2.1 0.77 0.033 2.1 0.93 0.02 0.58 0.5847 0.028 2.0 0.71 0.030 2.0 0.90 0.00 0.57 0.57Weekday 0.050 2.4 0.89 0.048 2.5 1.02 1.02 #DIV/0! 1.02Weekend 0.046 2.3 0.86 0.048 2.5 1.02 0.95 #DIV/0! 0.95ADWF(1)0.049 2.3 0.88 0.048 2.5 1.02 1.00 #DIV/0! 1.00Weekday-2.4% 0.38Weekend5.0% 0.57Note:City of RentonLong-range Wastewater Management PlanFLOW MONITORING SITE MH3216 DRY WEATHER FLOW CALIBRATIONWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.020.040.060.080.100 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday-0.10.10.30.50.70.91.11.31.5024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.00.51.01.52.02.53.03.54.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.51.01.50 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.52.024 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.347 4.2 2.30 0.339 3.6 2.35 0.66 0.57 0.571 0.310 3.9 2.19 0.313 3.4 2.28 0.57 0.55 0.552 0.303 3.8 2.13 0.336 3.5 2.33 0.35 0.60 0.603 0.331 3.9 2.15 0.312 3.6 2.36 0.32 0.72 0.724 0.395 4.2 2.26 0.365 3.7 2.43 0.41 1.01 1.015 0.557 4.8 2.47 0.481 4.3 2.62 0.51 1.16 1.166 0.637 5.4 2.69 0.491 4.6 2.71 0.87 1.15 1.157 0.633 5.6 2.75 0.646 5.0 2.85 0.58 1.11 1.118 0.607 5.5 2.70 0.561 5.1 2.90 0.41 1.06 1.069 0.581 5.4 2.68 0.589 4.9 2.85 0.48 1.03 1.0310 0.565 5.2 2.64 0.540 5.3 2.94 -0.10 0.97 0.9711 0.533 5.2 2.63 0.538 4.8 2.78 0.39 0.97 0.9712 0.534 5.1 2.61 0.607 5.2 2.89 -0.08 0.97 0.9713 0.533 5.0 2.59 0.570 4.8 2.79 0.29 0.97 0.9714 0.532 5.0 2.59 0.613 5.2 2.90 -0.24 1.01 1.0115 0.552 5.1 2.63 0.565 4.8 2.83 0.29 1.09 1.0916 0.598 5.3 2.67 0.641 5.3 2.92 0.01 1.18 1.1817 0.648 5.5 2.72 0.634 4.9 2.80 0.65 1.26 1.2618 0.693 5.7 2.79 0.673 5.1 2.88 0.65 1.33 1.3319 0.729 5.9 2.82 0.656 5.3 2.96 0.58 1.25 1.2520 0.685 5.9 2.82 0.644 5.0 2.84 0.86 1.09 1.0921 0.598 5.6 2.76 0.666 5.3 2.89 0.38 0.88 0.8822 0.485 5.1 2.61 0.527 4.6 2.73 0.51 0.74 0.7423 0.406 4.6 2.47 0.537 5.0 2.83 -0.39 0.63 0.6324 0.402 4.5 2.45 0.354 3.5 2.35 0.97 0.64 0.6425 0.350 4.3 2.36 0.361 4.0 2.54 0.22 0.58 0.5826 0.320 4.0 2.25 0.435 4.2 2.54 -0.22 0.60 0.6027 0.332 3.9 2.22 0.301 3.7 2.37 0.28 0.63 0.6328 0.347 4.0 2.24 0.315 3.6 2.35 0.40 0.66 0.6629 0.364 4.1 2.29 0.340 4.4 2.67 -0.27 0.90 0.9030 0.496 4.4 2.43 0.444 4.4 2.70 0.00 1.16 1.1631 0.638 5.1 2.68 0.525 4.8 2.78 0.36 1.39 1.3932 0.764 6.0 2.83 0.667 5.3 2.96 0.72 1.44 1.4433 0.787 6.3 2.90 0.751 6.0 3.13 0.39 1.45 1.4534 0.794 6.4 2.88 0.675 5.2 2.92 1.20 1.36 1.3635 0.745 6.2 2.85 0.677 5.3 2.94 0.86 1.30 1.3036 0.711 6.0 2.83 0.634 5.0 2.83 1.06 1.25 1.2537 0.683 5.9 2.83 0.619 4.9 2.81 0.93 1.20 1.2038 0.659 5.8 2.77 0.603 5.7 3.06 0.05 1.19 1.1939 0.653 5.7 2.76 0.596 4.9 2.84 0.81 1.21 1.2140 0.662 5.7 2.77 0.670 5.1 2.90 0.54 1.26 1.2641 0.689 5.8 2.79 0.612 4.7 2.76 1.07 1.31 1.3142 0.716 5.8 2.79 0.621 4.9 2.83 0.89 1.29 1.2943 0.709 6.0 2.82 0.613 4.8 2.80 1.19 1.25 1.2544 0.683 5.9 2.78 0.628 4.7 2.77 1.17 1.11 1.1145 0.608 5.6 2.76 0.513 5.2 2.94 0.41 0.95 0.9546 0.521 5.2 2.66 0.450 4.3 2.65 0.96 0.84 0.8447 0.460 4.7 2.50 0.400 3.9 2.54 0.80 0.73 0.73Weekday 0.533 5.0 2.57 0.535 4.7 2.74 0.97 #DIV/0! 0.97Weekend 0.587 5.3 2.64 0.534 4.7 2.75 1.07 #DIV/0! 1.07ADWF(1)0.548 5.1 2.59 0.535 4.7 2.74 1.00 #DIV/0! 1.00Weekday0.4% 0.87Weekend-9.1% 1.20Note:FLOW MONITORING SITE MH3625 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.200.400.600.801.00024681012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.00.51.01.52.02.53.03.54.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.02.04.06.08.010.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.52.024 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.125 1.7 4.06 0.127 1.4 3.45 0.28 0.73 0.731 0.120 1.7 3.93 0.122 1.4 3.42 0.27 0.72 0.722 0.119 1.7 3.83 0.121 1.4 3.41 0.27 0.75 0.753 0.124 1.7 3.84 0.128 1.4 3.48 0.23 0.90 0.904 0.149 1.7 3.91 0.151 1.5 3.67 0.14 1.04 1.045 0.172 1.8 4.24 0.174 1.6 3.81 0.11 1.11 1.116 0.184 1.8 4.45 0.185 1.7 3.87 0.12 1.10 1.107 0.183 1.8 4.34 0.184 1.7 3.86 0.16 1.07 1.078 0.177 1.8 4.41 0.179 1.7 3.83 0.16 1.04 1.049 0.173 1.8 4.36 0.175 1.6 3.80 0.17 1.01 1.0110 0.167 1.8 4.38 0.169 1.6 3.77 0.17 0.99 0.9911 0.163 1.8 4.29 0.165 1.6 3.74 0.17 0.97 0.9712 0.161 1.8 4.26 0.163 1.6 3.73 0.17 0.95 0.9513 0.158 1.8 4.18 0.160 1.6 3.71 0.17 0.97 0.9714 0.160 1.7 4.24 0.163 1.6 3.73 0.15 1.03 1.0315 0.171 1.8 4.28 0.173 1.6 3.80 0.12 1.08 1.0816 0.178 1.8 4.58 0.181 1.7 3.85 0.12 1.13 1.1317 0.187 1.8 4.56 0.190 1.7 3.90 0.11 1.18 1.1818 0.195 1.9 4.51 0.197 1.7 3.94 0.12 1.18 1.1819 0.195 1.9 4.54 0.197 1.7 3.94 0.13 1.15 1.1520 0.190 1.9 4.47 0.191 1.7 3.90 0.16 1.04 1.0421 0.173 1.8 4.42 0.174 1.6 3.78 0.21 0.92 0.9222 0.152 1.8 4.27 0.154 1.5 3.65 0.23 0.83 0.8323 0.137 1.7 4.12 0.139 1.5 3.54 0.25 0.75 0.7524 0.128 1.7 4.09 0.127 1.4 3.45 0.31 0.74 0.7425 0.122 1.7 3.83 0.119 1.4 3.39 0.31 0.72 0.7226 0.120 1.7 3.81 0.116 1.3 3.36 0.32 0.72 0.7227 0.119 1.7 3.70 0.115 1.3 3.37 0.32 0.75 0.7528 0.125 1.7 3.56 0.121 1.4 3.42 0.30 0.81 0.8129 0.134 1.7 3.85 0.131 1.4 3.51 0.25 0.96 0.9630 0.159 1.7 3.95 0.155 1.6 3.69 0.16 1.16 1.1631 0.191 1.8 4.28 0.184 1.7 3.88 0.12 1.27 1.2732 0.210 1.9 4.49 0.201 1.8 3.97 0.14 1.28 1.2833 0.212 1.9 4.60 0.204 1.8 3.98 0.17 1.26 1.2634 0.209 1.9 4.54 0.200 1.8 3.96 0.18 1.21 1.2135 0.201 1.9 4.54 0.193 1.7 3.91 0.20 1.17 1.1736 0.193 1.9 4.47 0.186 1.7 3.87 0.20 1.16 1.1637 0.192 1.9 4.57 0.185 1.7 3.87 0.18 1.17 1.1738 0.193 1.9 4.42 0.186 1.7 3.87 0.19 1.15 1.1539 0.190 1.9 4.34 0.183 1.7 3.86 0.20 1.15 1.1540 0.190 1.9 4.36 0.183 1.7 3.85 0.19 1.14 1.1441 0.188 1.9 4.43 0.182 1.7 3.85 0.18 1.18 1.1842 0.195 1.9 4.46 0.187 1.7 3.88 0.17 1.18 1.1843 0.195 1.9 4.46 0.187 1.7 3.88 0.19 1.14 1.1444 0.188 1.9 4.42 0.179 1.7 3.82 0.21 1.02 1.0245 0.168 1.8 4.37 0.162 1.6 3.71 0.26 0.92 0.9246 0.152 1.8 4.24 0.146 1.5 3.60 0.26 0.84 0.8447 0.139 1.7 4.12 0.134 1.4 3.51 0.29 0.77 0.77Weekday 0.163 1.8 4.27 0.165 1.6 3.73 0.99 #DIV/0! 0.99Weekend 0.171 1.8 4.24 0.165 1.6 3.73 1.04 #DIV/0! 1.04ADWF(1)0.165 1.8 4.26 0.165 1.6 3.73 1.00 #DIV/0! 1.00Weekday1.4% 0.28Weekend-3.4% 0.32Note:FLOW MONITORING SITE MH4628 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250.30024681012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.01.02.03.04.05.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.00.51.01.52.02.53.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.177 1.2 8.38 0.177 4.1 7.60 -2.84 0.83 0.831 0.172 1.2 8.09 0.172 4.0 7.55 -2.73 0.84 0.842 0.172 1.2 7.99 0.173 3.9 7.57 -2.69 0.86 0.863 0.178 1.2 8.10 0.180 3.9 7.66 -2.69 0.93 0.934 0.192 1.2 8.43 0.194 4.0 7.85 -2.78 1.03 1.035 0.213 1.3 8.91 0.212 4.3 8.04 -3.00 1.06 1.066 0.217 1.3 9.30 0.216 4.4 8.08 -3.13 1.05 1.057 0.215 1.3 9.27 0.215 4.9 8.06 -3.57 1.04 1.048 0.213 1.3 9.25 0.213 4.8 8.04 -3.52 1.03 1.039 0.211 1.3 9.27 0.211 4.9 8.02 -3.62 1.02 1.0210 0.209 1.3 9.21 0.209 4.7 8.00 -3.46 1.02 1.0211 0.210 1.3 9.17 0.209 4.7 8.00 -3.44 1.01 1.0112 0.208 1.3 9.14 0.208 4.6 7.98 -3.32 1.01 1.0113 0.208 1.3 9.13 0.208 4.6 7.98 -3.36 1.00 1.0014 0.206 1.3 9.10 0.207 4.6 7.97 -3.27 1.02 1.0215 0.210 1.3 9.13 0.211 4.6 8.03 -3.35 1.06 1.0616 0.219 1.3 9.29 0.219 4.6 8.12 -3.34 1.10 1.1017 0.226 1.3 9.45 0.226 4.8 8.19 -3.44 1.11 1.1118 0.229 1.3 9.56 0.228 4.8 8.21 -3.52 1.11 1.1119 0.228 1.3 9.57 0.227 4.9 8.19 -3.59 1.09 1.0920 0.223 1.3 9.54 0.221 5.0 8.13 -3.72 1.03 1.0321 0.213 1.3 9.38 0.211 4.8 8.01 -3.49 0.97 0.9722 0.200 1.3 9.08 0.199 4.6 7.87 -3.33 0.91 0.9123 0.188 1.3 8.75 0.187 4.4 7.73 -3.09 0.86 0.8624 0.177 1.2 8.36 0.178 4.2 7.61 -2.97 0.85 0.8525 0.175 1.2 8.13 0.174 4.0 7.57 -2.79 0.82 0.8226 0.170 1.2 8.03 0.171 3.9 7.53 -2.66 0.84 0.8427 0.173 1.2 7.93 0.172 3.9 7.55 -2.65 0.83 0.8328 0.172 1.2 7.94 0.173 3.9 7.57 -2.66 0.88 0.8829 0.181 1.2 8.10 0.183 4.0 7.71 -2.81 0.97 0.9730 0.199 1.3 8.60 0.202 4.3 7.94 -3.01 1.08 1.0831 0.222 1.3 9.22 0.223 4.5 8.17 -3.17 1.15 1.1532 0.236 1.3 9.62 0.237 4.9 8.31 -3.53 1.19 1.1933 0.244 1.4 9.73 0.243 4.9 8.37 -3.49 1.18 1.1834 0.243 1.4 9.69 0.240 5.0 8.32 -3.59 1.11 1.1135 0.228 1.4 9.61 0.227 5.1 8.19 -3.73 1.08 1.0836 0.221 1.3 9.48 0.222 4.9 8.14 -3.62 1.08 1.0837 0.222 1.3 9.42 0.220 5.0 8.11 -3.70 1.03 1.0338 0.211 1.3 9.36 0.212 4.9 8.02 -3.63 1.03 1.0339 0.211 1.3 9.25 0.211 4.9 8.02 -3.61 1.02 1.0240 0.210 1.3 9.31 0.211 4.9 8.03 -3.58 1.05 1.0541 0.216 1.3 9.32 0.217 4.9 8.09 -3.60 1.08 1.0842 0.222 1.3 9.50 0.219 5.0 8.11 -3.73 1.03 1.0343 0.212 1.3 9.39 0.213 5.0 8.03 -3.66 1.03 1.0344 0.212 1.3 9.38 0.210 5.0 8.00 -3.74 0.98 0.9845 0.202 1.3 9.23 0.201 4.8 7.90 -3.53 0.94 0.9446 0.194 1.3 8.96 0.192 4.6 7.79 -3.35 0.89 0.8947 0.182 1.2 8.64 0.182 4.4 7.67 -3.13 0.86 0.86Weekday 0.205 1.3 9.02 0.205 4.5 7.95 1.00 #DIV/0! 1.00Weekend 0.205 1.3 9.01 0.205 4.6 7.95 1.00 #DIV/0! 1.00ADWF(1)0.205 1.3 9.02 0.205 4.6 7.95 1.00 #DIV/0! 1.00Weekday0.0% 3.72Weekend0.0% 3.74Note:FLOW MONITORING SITE MH4646 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250.30024681012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.02.04.06.08.010.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 1.424 7.8 3.12 1.388 6.0 3.77 1.82 0.72 0.721 1.213 7.3 2.91 1.089 5.8 2.97 1.50 0.65 0.652 1.097 6.9 2.73 0.886 5.8 2.75 1.09 0.64 0.643 1.082 6.7 2.67 0.747 5.4 2.73 1.36 0.72 0.724 1.220 6.9 2.71 0.770 5.5 2.62 1.39 0.89 0.895 1.503 7.4 2.94 0.891 5.7 2.88 1.76 1.04 1.046 1.751 8.0 3.18 1.129 6.3 3.41 1.73 1.11 1.117 1.874 8.5 3.34 1.424 6.8 3.97 1.72 1.10 1.108 1.851 8.6 3.36 1.832 6.7 4.10 1.90 1.09 1.099 1.845 8.5 3.35 1.908 7.0 4.13 1.55 1.07 1.0710 1.810 8.5 3.33 1.806 6.7 4.13 1.72 1.06 1.0611 1.799 8.4 3.33 1.897 6.8 4.06 1.66 1.06 1.0612 1.795 8.4 3.32 1.790 6.8 4.07 1.62 1.04 1.0413 1.765 8.3 3.31 1.681 6.5 4.00 1.81 1.04 1.0414 1.752 8.3 3.30 1.644 6.4 3.95 1.92 1.05 1.0515 1.769 8.3 3.30 1.687 6.4 3.99 1.87 1.07 1.0716 1.805 8.3 3.32 1.572 6.4 3.91 1.96 1.12 1.1217 1.887 8.5 3.37 1.580 6.3 4.00 2.16 1.16 1.1618 1.960 8.6 3.42 1.808 6.7 4.09 1.89 1.19 1.1919 2.009 8.8 3.47 1.813 6.7 4.14 2.05 1.17 1.1720 1.983 8.8 3.48 1.956 7.0 4.19 1.75 1.14 1.1421 1.923 8.7 3.45 1.954 7.0 4.21 1.69 1.06 1.0622 1.793 8.5 3.40 1.974 6.9 4.10 1.59 0.97 0.9723 1.636 8.2 3.28 1.791 6.6 3.95 1.57 0.84 0.8424 1.430 7.8 3.13 1.377 5.9 3.73 1.86 0.72 0.7225 1.209 7.3 2.90 1.121 6.0 2.99 1.35 0.63 0.6326 1.060 6.8 2.72 0.864 5.8 2.79 1.07 0.60 0.6027 1.007 6.5 2.63 0.716 5.4 2.59 1.14 0.59 0.5928 0.990 6.5 2.61 0.714 5.3 2.50 1.21 0.61 0.6129 1.035 6.5 2.61 0.710 5.2 2.52 1.28 0.75 0.7530 1.260 6.8 2.73 0.701 5.3 2.67 1.52 0.94 0.9431 1.596 7.6 3.03 0.909 5.7 2.97 1.85 1.14 1.1432 1.918 8.3 3.28 1.194 6.5 3.58 1.87 1.22 1.2233 2.053 8.9 3.43 1.733 6.4 4.19 2.43 1.22 1.2234 2.069 9.0 3.50 2.112 7.3 4.32 1.73 1.22 1.2235 2.054 8.9 3.51 2.244 7.6 4.33 1.38 1.19 1.1936 2.016 8.9 3.51 2.272 7.4 4.30 1.48 1.18 1.1837 1.986 8.8 3.48 2.108 7.3 4.25 1.49 1.15 1.1538 1.938 8.7 3.46 2.109 7.1 4.19 1.53 1.14 1.1439 1.931 8.6 3.44 1.882 6.9 4.13 1.72 1.14 1.1440 1.925 8.6 3.44 1.882 6.7 4.11 1.85 1.15 1.1541 1.936 8.6 3.45 1.752 6.7 4.14 1.94 1.16 1.1642 1.968 8.6 3.45 1.870 6.7 4.15 1.91 1.18 1.1843 1.986 8.8 3.49 1.768 6.7 4.15 2.07 1.16 1.1644 1.956 8.7 3.48 1.913 6.9 4.15 1.82 1.11 1.1145 1.884 8.6 3.44 1.817 6.8 4.10 1.84 1.03 1.0346 1.745 8.4 3.38 1.764 6.6 4.05 1.75 0.95 0.9547 1.607 8.0 3.27 1.583 6.3 3.88 1.73 0.85 0.85Weekday 1.689 8.1 3.22 1.542 6.4 3.76 1.00 #DIV/0! 1.00Weekend 1.690 8.1 3.22 1.546 6.4 3.70 1.00 #DIV/0! 1.00ADWF(1)1.689 8.1 3.22 1.544 6.4 3.74 1.00 #DIV/0! 1.00Weekday-8.7% 2.16Weekend-8.5% 2.43Note:FLOW MONITORING SITE MH5302 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.501.001.502.002.503.000 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.01.02.03.04.05.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.02.04.06.08.010.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.180 1.5 5.57 0.191 1.9 3.81 -0.37 0.80 0.801 0.169 1.5 5.42 0.172 1.8 3.75 -0.36 0.80 0.802 0.170 1.4 5.38 0.165 1.9 3.88 -0.48 0.83 0.833 0.175 1.4 5.43 0.171 1.9 3.85 -0.46 0.91 0.914 0.192 1.5 5.53 0.198 1.9 3.87 -0.44 1.01 1.015 0.214 1.6 5.76 0.210 2.1 4.09 -0.53 1.07 1.076 0.227 1.6 6.00 0.225 2.1 4.08 -0.49 1.10 1.107 0.232 1.6 6.09 0.232 2.2 4.21 -0.56 1.08 1.088 0.229 1.6 6.11 0.232 2.1 4.08 -0.45 1.05 1.059 0.223 1.6 6.01 0.223 2.2 4.15 -0.52 1.04 1.0410 0.220 1.6 5.95 0.223 2.1 4.03 -0.44 1.02 1.0211 0.216 1.6 5.90 0.218 2.1 4.10 -0.50 1.02 1.0212 0.216 1.6 5.90 0.216 2.0 4.01 -0.43 1.00 1.0013 0.213 1.6 5.87 0.216 2.1 4.08 -0.49 1.01 1.0114 0.213 1.6 5.81 0.210 2.0 3.99 -0.42 1.01 1.0115 0.214 1.6 5.84 0.220 2.1 4.09 -0.50 1.03 1.0316 0.219 1.6 5.88 0.213 2.0 4.02 -0.44 1.07 1.0717 0.226 1.6 5.98 0.231 2.2 4.14 -0.53 1.10 1.1018 0.234 1.6 6.09 0.228 2.2 4.14 -0.51 1.12 1.1219 0.238 1.7 6.18 0.241 2.2 4.15 -0.50 1.11 1.1120 0.234 1.7 6.15 0.235 2.2 4.22 -0.55 1.04 1.0421 0.220 1.6 6.04 0.223 2.1 4.03 -0.41 0.96 0.9622 0.204 1.6 5.83 0.206 2.1 4.07 -0.50 0.91 0.9123 0.194 1.5 5.70 0.201 1.9 3.89 -0.39 0.85 0.8524 0.176 1.5 5.56 0.179 1.9 3.86 -0.43 0.81 0.8125 0.172 1.5 5.50 0.167 1.9 3.87 -0.47 0.77 0.7726 0.163 1.4 5.44 0.169 1.8 3.73 -0.40 0.74 0.7427 0.158 1.4 5.34 0.167 1.8 3.66 -0.36 0.80 0.8028 0.169 1.4 5.40 0.171 1.8 3.70 -0.38 0.83 0.8329 0.175 1.4 5.48 0.173 1.9 3.83 -0.45 0.95 0.9530 0.201 1.5 5.65 0.189 2.0 4.01 -0.55 1.08 1.0831 0.229 1.6 5.95 0.230 2.1 4.05 -0.48 1.15 1.1532 0.244 1.6 6.27 0.234 2.2 4.22 -0.57 1.16 1.1633 0.246 1.7 6.28 0.250 2.2 4.24 -0.55 1.18 1.1834 0.249 1.7 6.33 0.247 2.2 4.17 -0.49 1.13 1.1335 0.240 1.7 6.25 0.237 2.2 4.21 -0.53 1.12 1.1236 0.236 1.7 6.18 0.243 2.2 4.17 -0.51 1.11 1.1137 0.235 1.7 6.12 0.228 2.1 4.12 -0.47 1.07 1.0738 0.227 1.6 6.05 0.234 2.2 4.18 -0.53 1.05 1.0539 0.222 1.6 6.02 0.216 2.1 4.04 -0.43 1.06 1.0640 0.224 1.6 5.95 0.229 2.2 4.16 -0.55 1.09 1.0941 0.231 1.6 6.08 0.223 2.1 4.08 -0.46 1.11 1.1142 0.234 1.7 6.13 0.239 2.2 4.18 -0.54 1.13 1.1343 0.239 1.7 6.17 0.232 2.2 4.18 -0.51 1.09 1.0944 0.230 1.7 6.11 0.232 2.1 4.10 -0.46 1.03 1.0345 0.218 1.6 5.99 0.217 2.1 4.13 -0.50 0.94 0.9446 0.199 1.6 5.79 0.206 2.0 3.93 -0.39 0.89 0.8947 0.189 1.5 5.66 0.183 1.9 3.89 -0.40 0.83 0.83Weekday 0.211 1.6 5.85 0.212 2.1 4.03 1.00 #DIV/0! 1.00Weekend 0.212 1.6 5.90 0.212 2.1 4.03 1.00 #DIV/0! 1.00ADWF(1)0.211 1.6 5.87 0.212 2.1 4.03 1.00 #DIV/0! 1.00Weekday0.6% 0.56Weekend-0.1% 0.57Note:FLOW MONITORING SITE MH5505 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.100.200.300.400.500.600.700.800 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday-1.01.03.05.07.09.011.013.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.205 1.8 4.91 0.208 2.3 4.52 -0.51 0.61 0.611 0.192 1.7 4.73 0.195 2.2 4.45 -0.50 0.60 0.602 0.188 1.7 4.64 0.193 2.2 4.44 -0.53 0.63 0.633 0.197 1.7 4.65 0.208 2.3 4.55 -0.63 0.76 0.764 0.238 1.8 4.96 0.252 2.6 4.82 -0.80 0.96 0.965 0.300 1.9 5.50 0.310 2.8 5.12 -0.91 1.09 1.096 0.341 2.1 5.98 0.348 2.9 5.26 -0.86 1.14 1.147 0.357 2.2 6.16 0.364 3.0 5.35 -0.86 1.17 1.178 0.365 2.2 6.19 0.373 3.1 5.38 -0.87 1.19 1.199 0.374 2.2 6.29 0.379 3.1 5.41 -0.87 1.19 1.1910 0.373 2.2 6.31 0.381 3.1 5.42 -0.87 1.21 1.2111 0.380 2.2 6.34 0.386 3.1 5.44 -0.87 1.21 1.2112 0.379 2.2 6.38 0.384 3.1 5.43 -0.85 1.19 1.1913 0.373 2.2 6.30 0.380 3.1 5.41 -0.85 1.20 1.2014 0.374 2.2 6.30 0.380 3.1 5.41 -0.86 1.19 1.1915 0.373 2.2 6.31 0.381 3.1 5.42 -0.86 1.22 1.2216 0.380 2.2 6.30 0.386 3.1 5.43 -0.89 1.21 1.2117 0.377 2.2 6.35 0.384 3.1 5.43 -0.86 1.20 1.2018 0.377 2.2 6.32 0.380 3.1 5.41 -0.84 1.16 1.1619 0.364 2.2 6.28 0.366 3.0 5.35 -0.80 1.10 1.1020 0.345 2.2 6.19 0.343 2.9 5.25 -0.73 0.98 0.9821 0.308 2.1 5.89 0.307 2.8 5.08 -0.65 0.87 0.8722 0.271 2.0 5.63 0.269 2.6 4.88 -0.56 0.74 0.7423 0.231 1.9 5.29 0.233 2.4 4.67 -0.49 0.65 0.6524 0.206 1.8 5.17 0.211 2.3 4.54 -0.50 0.61 0.6125 0.192 1.7 4.72 0.206 2.3 4.52 -0.58 0.57 0.5726 0.178 1.7 4.54 0.196 2.2 4.45 -0.54 0.56 0.5627 0.177 1.7 4.47 0.194 2.2 4.45 -0.58 0.58 0.5828 0.183 1.7 4.54 0.206 2.3 4.54 -0.66 0.69 0.6929 0.217 1.7 4.80 0.246 2.5 4.78 -0.82 0.87 0.8730 0.271 1.8 5.32 0.306 2.8 5.10 -0.99 1.05 1.0531 0.328 2.0 5.82 0.366 3.0 5.36 -1.05 1.19 1.1932 0.372 2.2 6.22 0.408 3.2 5.53 -1.03 1.23 1.2333 0.386 2.2 6.40 0.423 3.2 5.59 -1.01 1.26 1.2634 0.395 2.3 6.50 0.430 3.3 5.61 -1.01 1.25 1.2535 0.392 2.3 6.53 0.424 3.2 5.58 -0.98 1.20 1.2036 0.376 2.2 6.48 0.407 3.2 5.52 -0.94 1.15 1.1537 0.361 2.2 6.24 0.391 3.1 5.45 -0.93 1.11 1.1138 0.347 2.2 6.21 0.378 3.1 5.40 -0.91 1.09 1.0939 0.341 2.1 6.18 0.368 3.0 5.36 -0.89 1.03 1.0340 0.323 2.1 6.00 0.358 3.0 5.32 -0.91 1.08 1.0841 0.337 2.1 6.11 0.370 3.0 5.37 -0.93 1.11 1.1142 0.349 2.1 6.11 0.373 3.0 5.38 -0.91 1.02 1.0243 0.320 2.1 6.12 0.351 3.0 5.28 -0.84 1.02 1.0244 0.318 2.1 5.95 0.337 2.9 5.22 -0.83 0.89 0.8945 0.279 2.0 5.81 0.299 2.7 5.03 -0.71 0.78 0.7846 0.245 1.9 5.50 0.269 2.6 4.88 -0.70 0.77 0.7747 0.241 1.8 5.25 0.255 2.5 4.81 -0.68 0.66 0.66Weekday 0.319 2.1 5.84 0.325 2.8 5.14 1.02 #DIV/0! 1.02Weekend 0.297 2.0 5.71 0.324 2.8 5.13 0.95 #DIV/0! 0.95ADWF(1)0.313 2.1 5.80 0.324 2.8 5.13 1.00 #DIV/0! 1.00Weekday1.7% 0.91Weekend9.1% 1.05Note:FLOW MONITORING SITE MH5519 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.100.200.300.400.500.600.700.80024681012141618202224262830323436384042444648Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday-1.01.03.05.07.09.011.013.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.01.02.03.04.05.06.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.022 0.7 2.75 0.021 1.5 1.18 -0.79 0.39 0.391 0.018 0.6 2.34 0.017 1.3 1.13 -0.74 0.39 0.392 0.018 0.6 2.18 0.018 1.4 1.16 -0.80 0.50 0.503 0.023 0.6 2.31 0.024 1.6 1.27 -0.98 0.71 0.714 0.032 0.7 2.83 0.033 1.8 1.42 -1.16 0.95 0.955 0.043 0.8 3.47 0.042 2.1 1.53 -1.30 1.10 1.106 0.050 0.8 3.91 0.049 2.2 1.60 -1.37 1.17 1.177 0.053 0.8 3.99 0.052 2.2 1.63 -1.41 1.23 1.238 0.056 0.9 4.24 0.054 2.3 1.65 -1.43 1.26 1.269 0.057 0.9 4.34 0.055 2.3 1.66 -1.44 1.24 1.2410 0.057 0.9 4.38 0.056 2.3 1.67 -1.47 1.34 1.3411 0.061 0.9 4.40 0.058 2.4 1.69 -1.50 1.32 1.3212 0.060 0.9 4.42 0.056 2.3 1.67 -1.44 1.20 1.2013 0.055 0.9 4.34 0.052 2.2 1.62 -1.35 1.11 1.1114 0.051 0.8 3.97 0.049 2.2 1.59 -1.34 1.08 1.0815 0.049 0.8 3.85 0.049 2.2 1.60 -1.36 1.20 1.2016 0.055 0.9 3.94 0.055 2.3 1.67 -1.45 1.41 1.4117 0.064 0.9 4.23 0.061 2.4 1.72 -1.52 1.41 1.4118 0.064 0.9 4.38 0.062 2.4 1.73 -1.52 1.43 1.4319 0.065 1.0 4.39 0.061 2.4 1.72 -1.46 1.32 1.3220 0.060 0.9 4.28 0.056 2.3 1.66 -1.38 1.13 1.1321 0.052 0.9 4.03 0.046 2.1 1.55 -1.24 0.84 0.8422 0.038 0.8 3.76 0.035 1.9 1.42 -1.04 0.65 0.6523 0.030 0.7 3.21 0.027 1.6 1.29 -0.94 0.47 0.4724 0.020 0.6 2.86 0.022 1.5 1.22 -0.89 0.45 0.4525 0.021 0.6 2.58 0.022 1.5 1.21 -0.91 0.39 0.3926 0.018 0.6 2.35 0.020 1.4 1.18 -0.83 0.39 0.3927 0.018 0.6 2.14 0.019 1.4 1.17 -0.82 0.39 0.3928 0.018 0.6 2.35 0.022 1.5 1.23 -0.93 0.57 0.5729 0.026 0.6 2.68 0.031 1.8 1.38 -1.18 0.79 0.7930 0.036 0.7 3.22 0.042 2.1 1.54 -1.39 1.05 1.0531 0.048 0.7 3.82 0.054 2.3 1.66 -1.57 1.23 1.2332 0.056 0.8 4.28 0.061 2.4 1.72 -1.62 1.26 1.2633 0.057 0.8 4.51 0.062 2.4 1.73 -1.58 1.23 1.2334 0.056 0.8 4.46 0.061 2.4 1.71 -1.57 1.19 1.1935 0.054 0.8 4.31 0.059 2.4 1.69 -1.53 1.13 1.1336 0.052 0.8 4.33 0.056 2.3 1.67 -1.49 1.10 1.1037 0.050 0.8 4.31 0.057 2.3 1.68 -1.53 1.22 1.2238 0.056 0.8 4.18 0.058 2.4 1.69 -1.56 1.08 1.0839 0.049 0.8 4.27 0.054 2.3 1.65 -1.48 1.09 1.0940 0.050 0.8 4.16 0.056 2.3 1.67 -1.52 1.21 1.2141 0.055 0.8 4.14 0.057 2.3 1.67 -1.49 1.01 1.0142 0.046 0.8 4.15 0.053 2.3 1.64 -1.43 1.13 1.1343 0.052 0.8 3.95 0.056 2.3 1.66 -1.53 1.10 1.1044 0.050 0.8 4.20 0.054 2.3 1.64 -1.46 1.04 1.0445 0.047 0.8 4.12 0.048 2.1 1.57 -1.33 0.78 0.7846 0.036 0.8 3.71 0.037 1.9 1.44 -1.13 0.58 0.5847 0.027 0.7 3.20 0.028 1.7 1.31 -1.01 0.44 0.44Weekday 0.047 0.8 3.75 0.045 2.1 1.53 1.04 #DIV/0! 1.04Weekend 0.041 0.7 3.68 0.045 2.1 1.53 0.91 #DIV/0! 0.91ADWF(1)0.045 0.8 3.73 0.045 2.1 1.53 1.00 #DIV/0! 1.00Weekday-3.5% 1.52Weekend9.6% 1.62Note:FLOW MONITORING SITE MH6041 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.020.040.060.080.100 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.01.02.03.04.05.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.00.20.40.60.81.01.21.40 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.51.01.52.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.20.40.60.81.01.21.424 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
Flow Level Velocity Flow Level Velocity Level Diff Initial Modified CalibratedHour (mgd) (in) (ft/s) (mgd) (in) (ft/s) (in) Curve Curve Diurnal0 0.068 0.8 4.46 0.072 1.6 4.79 -0.73 0.54 0.541 0.065 0.8 4.37 0.068 1.5 4.73 -0.72 0.54 0.542 0.065 0.8 4.31 0.067 1.5 4.73 -0.74 0.57 0.573 0.067 0.8 4.32 0.071 1.6 4.82 -0.77 0.67 0.674 0.080 0.8 4.42 0.083 1.7 5.09 -0.89 0.87 0.875 0.103 0.9 4.93 0.105 1.9 5.46 -1.00 1.00 1.006 0.119 1.0 5.50 0.121 2.1 5.68 -1.07 1.02 1.027 0.121 1.0 5.72 0.126 2.1 5.72 -1.07 1.05 1.058 0.125 1.0 5.77 0.129 2.1 5.77 -1.10 1.07 1.079 0.127 1.0 5.96 0.132 2.1 5.80 -1.10 1.10 1.1010 0.130 1.0 5.94 0.135 2.2 5.84 -1.13 1.12 1.1211 0.133 1.0 6.13 0.137 2.2 5.87 -1.14 1.11 1.1112 0.132 1.0 6.16 0.136 2.2 5.86 -1.14 1.11 1.1113 0.132 1.0 6.05 0.136 2.2 5.85 -1.13 1.08 1.0814 0.128 1.0 6.01 0.134 2.2 5.83 -1.11 1.13 1.1315 0.135 1.0 6.00 0.141 2.2 5.93 -1.17 1.24 1.2416 0.148 1.1 6.15 0.152 2.3 6.07 -1.22 1.30 1.3017 0.154 1.1 6.41 0.158 2.3 6.13 -1.24 1.27 1.2718 0.151 1.1 6.46 0.156 2.3 6.09 -1.21 1.25 1.2519 0.148 1.1 6.42 0.152 2.3 6.05 -1.20 1.19 1.1920 0.141 1.1 6.33 0.141 2.2 5.90 -1.10 0.92 0.9221 0.110 1.0 5.90 0.115 2.0 5.50 -0.94 0.75 0.7522 0.089 0.9 5.27 0.094 1.8 5.18 -0.85 0.65 0.6523 0.077 0.9 4.83 0.081 1.7 4.96 -0.78 0.57 0.5724 0.081 0.9 4.63 0.072 1.6 4.80 -0.66 0.62 0.6225 0.074 0.9 4.48 0.068 1.5 4.73 -0.65 0.59 0.5926 0.070 0.9 4.36 0.064 1.5 4.65 -0.64 0.57 0.5727 0.067 0.8 4.31 0.062 1.5 4.62 -0.64 0.59 0.5928 0.070 0.8 4.29 0.065 1.5 4.71 -0.70 0.72 0.7229 0.085 0.9 4.53 0.078 1.7 5.01 -0.82 0.94 0.9430 0.112 1.0 4.96 0.102 1.9 5.41 -0.94 1.17 1.1731 0.139 1.0 5.72 0.126 2.1 5.76 -1.07 1.32 1.3232 0.157 1.1 6.22 0.145 2.3 5.99 -1.14 1.52 1.5233 0.181 1.2 6.46 0.163 2.4 6.21 -1.21 1.57 1.5734 0.187 1.2 6.86 0.168 2.4 6.24 -1.20 1.48 1.4835 0.176 1.2 6.89 0.163 2.4 6.17 -1.16 1.51 1.5136 0.179 1.2 6.79 0.162 2.4 6.17 -1.18 1.43 1.4337 0.170 1.2 6.78 0.154 2.3 6.07 -1.14 1.32 1.3238 0.157 1.1 6.61 0.145 2.2 5.95 -1.08 1.31 1.3139 0.155 1.1 6.45 0.142 2.2 5.93 -1.09 1.29 1.2940 0.154 1.1 6.38 0.140 2.2 5.91 -1.08 1.28 1.2841 0.152 1.1 6.45 0.138 2.2 5.88 -1.07 1.25 1.2542 0.148 1.1 6.29 0.136 2.2 5.85 -1.07 1.26 1.2643 0.149 1.1 6.35 0.135 2.2 5.83 -1.04 1.18 1.1844 0.140 1.1 6.11 0.126 2.1 5.70 -0.98 1.01 1.0145 0.120 1.0 6.02 0.110 1.9 5.44 -0.89 0.86 0.8646 0.102 1.0 5.56 0.093 1.8 5.19 -0.79 0.72 0.7247 0.085 0.9 4.95 0.080 1.7 4.95 -0.73 0.68 0.68Weekday 0.114 1.0 5.58 0.118 2.0 5.57 0.96 #DIV/0! 0.96Weekend 0.129 1.0 5.77 0.118 2.0 5.55 1.09 #DIV/0! 1.09ADWF(1)0.119 1.0 5.63 0.118 2.0 5.56 1.00 #DIV/0! 1.00Weekday3.6% 1.24Weekend-8.6% 1.21Note:FLOW MONITORING SITE MH6704 DRY WEATHER FLOW CALIBRATIONCity of RentonLong-range Wastewater Management PlanWeekdayWeekendAverage% ErrorMeasured DataModeled DataDiurnal0.000.050.100.150.200.250 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Flow (mgd)HourFlow CalibrationMeasured FlowModeled FlowWeekday Weekday0.01.02.03.04.05.06.07.0024681012141618202224262830323436384042444648Velocity (ft/s)HourVelocity CalibrationMeasured VelocityModeled VelocitySeries3WeekdayWeekday0.00.51.01.52.02.53.00 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48Level (in)HourLevel CalibrationMeasured LevelModeled LevelSeries3Weekday Weekday0.00.20.40.60.81.01.21.40 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23Hourly MultiplierHourWeekday Diurnal Pattern0.00.51.01.52.024 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47Hourly MultiplierHourWeekend Diurnal Pattern
LRWWMP | TM 2 | CITY OF RENTON
DRAFT | SEPTEMBER ͮͬͭ͵
Attachment G
WET WEATHER CALIBRATION RESULTS
Table 1 Wet Weather CalibrationLong-range Wastewater Management PlanCity of RentonMaxMaxMaxPipe Total Avg. Peak Avg. Avg. Total Avg. Peak Avg. Avg. Volume Peak Level Total Avg. Peak Avg. Total Avg. Peak Avg. Volume Peak Level Total Avg. Peak Avg. Volume Avg. Peak Avg. Avg. Volume Peak LevelMeter Diameter Flow Flow Flow Velocity Level Flow Flow Flow Velocity Level Flow Flow Diff Flow Flow Flow Level Flow Flow Flow Level Flow Flow Diff Flow Flow Flow Level Flow Flow Flow Velocity Level Flow Flow DiffNumber (in) (MG) (mgd) (mgd) (ft/s) (in) (MG) (mgd) (mgd) (ft/s) (in) (%) (%) (inches) (MG) (mgd) (mgd) (in) (MG) (mgd) (mgd) (in) (%) (%) (inches) (MG) (mgd) (mgd) (in) (MG) (mgd) (mgd) (ft/s) (in) (%) (%) (inches)MH016612 16.1 0.074 1.109 0.87 1.6 23.3 0.108 1.092 1.23 2.231.1%-1.5%5.151.6 0.134 1.238 2.4 50.1 0.131 1.385 2.6-3.0% 11.9%21.044.9 0.110 1.206 2.2 53.0 0.130 1.195 0.78 1.715.4% -0.9%7.4MH0286 10 15.1 0.070 0.133 0.68 3.3 16.3 0.075 0.131 1.00 2.37.2% -1.8% 1.529.2 0.076 0.139 3.4 29.2 0.076 0.122 2.30.1% -11.9% 1.730.8 0.080 0.151 3.6 28.5 0.074 0.112 0.99 2.3-7.8%-25.8%1.8MH0537 8 74.2 0.344 0.527 8.96 1.8 82.5 0.382 0.537 7.74 2.310.1% 2.0% 0.2144.5 0.377 0.551 1.9 152.5 0.398 0.515 2.45.2% -6.6% 0.9123.4 0.321 0.479 1.7 149.0 0.387 0.542 7.78 0.017.2% 13.3% 1.1MH1360 10.75 77.7 0.360 0.903 4.00 2.8 94.8 0.439 0.990 2.32 5.218.1% 9.7%5.7215.2 0.561 0.998 3.7 190.7 0.497 1.070 5.6-12.8%7.2%5.8153.8 0.400 0.901 3.0 181.1 0.471 0.923 2.36 5.415.1% 2.5%6.0MH1763 15 51.9 0.240 0.585 0.43 10.3 59.6 0.276 0.665 0.35 7.513.0% 13.7%6.2159.1 0.415 0.677 11.4 114.6 0.299 0.575 8.0-38.9% -15.0% 6.4109.1 0.284 0.571 90.0 108.7 0.283 0.543 0.36 7.8-0.3% -5.0%5.3MH2116 14.5 0.0 0.000 0.000 0.00 0.0 205.9 0.953 2.308 2.36 8.3 451.9 1.179 2.213 8.4 412.6 1.076 1.934 8.8-9.5% -12.6%6.0397.6 1.034 2.040 7.0 413.0 1.074 2.190 2.45 8.83.7% 7.3%4.0MH2171 11.25 54.4 0.252 0.781 1.35 4.7 58.3 0.270 0.867 1.41 5.76.8% 10.9% 3.5118.6 0.309 0.694 5.1 111.2 0.290 0.748 6.0-6.7% 7.7% 2.492.3 0.240 0.525 4.5 111.7 0.290 0.627 1.44 6.017.3% 19.5% 3.8MH2252 18 205.6 0.951 2.800 5.37 3.7 200.7 0.929 2.638 3.09 3.8-2.5% -5.8% 1.6417.6 1.089 2.664 3.9 381.8 0.996 2.988 4.0-9.4% 12.2% 1.6356.0 0.926 1.958 3.7 387.6 1.007 3.099 3.17 4.08.1%58.3%2.0MH2999 8 52.9 0.245 0.556 5.79 1.9 59.4 0.275 0.495 4.73 2.811.0% -10.9% 1.3102.4 0.267 0.457 2.0 115.4 0.301 0.465 2.911.3% 1.8% 1.395.0 0.247 0.453 1.9 114.3 0.297 0.485 4.84 2.916.8% 7.0% 1.4MH3216 7.38 11.1 0.051 0.218 0.65 2.9 13.6 0.063 0.208 1.09 2.918.8% -4.4% 2.928.1 0.073 0.115 2.7 25.3 0.066 0.144 3.0-11.3% 25.2%1.722.6 0.059 0.101 2.6 26.1 0.068 0.149 1.11 3.013.5%47.8%1.9MH3625 12 158.9 0.736 1.379 2.79 6.1 166.7 0.772 1.448 3.14 5.64.7% 5.0% 3.1357.8 0.933 1.507 7.0 311.9 0.814 1.414 5.8-14.7%-6.1% 3.8313.8 0.816 1.487 6.4 308.4 0.802 1.360 3.18 5.7-1.7% -8.5% 3.7MH4628 10.38 61.2 0.284 0.757 4.95 2.1 68.3 0.316 0.783 4.48 0.910.4% 3.5% 2.2165.3 0.431 0.770 2.8 136.3 0.356 0.885 1.0-21.2%15.0% 2.6115.9 0.301 0.752 2.2 130.1 0.338 0.740 4.57 0.910.9% -1.6% 2.3MH4646 8 48.6 0.225 0.298 9.28 1.3 47.7 0.221 0.278 8.12 5.2-1.9% -6.6%5.4102.3 0.267 0.341 1.5 86.5 0.226 0.274 5.4-18.3% -19.7% 5.489.3 0.232 0.286 1.3 87.4 0.227 0.291 8.19 5.4-2.2% 1.9%5.6MH5302 14 525.7 2.434 5.106 3.74 9.5 503.9 2.333 4.663 4.34 7.6-4.3% -8.7% 3.81043.8 2.722 4.054 10.2 967.4 2.525 4.327 7.9-7.9% 6.7%4.5966.8 2.514 4.403 9.8 951.3 2.472 4.439 4.41 7.8-1.6% 0.8%4.3MH5505 10 68.8 0.319 0.585 6.69 1.9 73.7 0.341 0.573 4.62 2.66.6% -1.9% 1.5151.8 0.396 0.576 2.1 138.6 0.362 0.612 2.7-9.5% 6.3% 1.2137.6 0.337 0.642 2.0 134.6 0.329 0.548 2.49 1.4-2.2% -14.7% 2.8MH5519 10.25 67.5 0.313 0.480 5.84 2.0 77.0 0.356 0.639 5.27 2.912.2%33.1%1.5123.8 0.323 0.447 2.1 139.1 0.363 0.555 3.010.9% 24.0% 1.4126.1 0.328 0.534 13.4 139.7 0.363 0.541 5.31 3.09.8% 1.3%21.3MH6041 8 19.6 0.090 0.300 2.66 1.6 17.1 0.079 0.273 1.82 2.6-14.5%-8.9% 2.628.0 0.073 0.132 0.9 33.5 0.087 0.158 2.816.5% 19.7% 2.621.7 0.057 0.100 0.9 35.8 0.093 0.241 1.95 2.839.3% 140.3%3.5MH6704 12 35.5 0.164 0.384 7.43 1.0 32.7 0.152 0.310 5.89 2.3-8.4%-19.1%1.950.6 0.132 0.229 1.0 60.7 0.158 0.279 2.316.7% 21.8% 2.052.6 0.137 0.262 1.0 62.0 0.161 0.269 5.97 2.315.2% 3.0% 1.9Notes:1. Source: City of Renton 2018 Temporary Flow Monitoring Program, ADS2. Average flows are computed from hydraulic modeling results. Maximum flow values are hourly peaks. 3. Percent Difference = (Modeled - Measured)/Measured*100.Measured Data(1)Percent Error(3)Measured Data(1)Storm 2 (1/23/2018-2/7/2018)Storm 3 (4/6/2018-4/22/2018)Measured Data(1)Modeled Data(2)Modeled Data(2)Modeled Data(2)Storm 1 (12/26/2017-1/3/2018)Percent Error(3)Percent Error(3)
FLOW MONITORING MH0166 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Springbrook TrailPipeline diameter: 12''City Manhole ID: MH0166Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.21.41.612/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.00.51.01.52.02.53.03.54.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000005101520253012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH0286 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Oakside Ave and SW Grady WayPipeline diameter: 15''City Manhole ID: MH0286Model Mahhole ID: Silt Level at Site: ''0.000.100.200.300.400.500.600.00.20.40.60.81.01.21.412/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/19Rain (inches/15-minutes)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000.100.200.300.400.500.6001234567891012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/19Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data0.000.050.100.150.200.250.300.00.00.00.10.10.10.10.10.212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/19Rain (inches/15-minutes)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data
FLOW MONITORING MH0537 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 2803 Burnett AvePipeline diameter: 8''City Manhole ID: MH0537Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.20.30.40.50.60.712/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.02.04.06.08.010.012.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000112233412/2212/2612/301/31/71/111/151/191/231/271/312/42/82/122/162/202/242/283/43/83/123/163/203/243/284/14/54/94/134/174/21Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH1360 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Ferndale and 7th StPipeline diameter: 10.75''City Manhole ID: MH1360Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000002468101212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataMeasured Data
FLOW MONITORING MH1763 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 3000 SE th StPipeline diameter: 15''City Manhole ID: MH1763Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.20.30.40.50.60.70.812/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.00.10.20.30.40.50.60.70.80.91.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000246810121416182012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH2116 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Shattuck Ave and Tobin StPipeline diameter: 14.5''City Manhole ID: MH2116Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.51.01.52.02.512/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.00.51.01.52.02.53.03.54.04.55.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000246810121416182012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataSeries4
FLOW MONITORING MH2171 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 540 Burnett Ave SPipeline diameter: 11.25''City Manhole ID: MH2171Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.20.30.40.50.60.70.80.91.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.00.51.01.52.02.512/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000002468101212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH2252 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Rainier and Grady WayPipeline diameter: 18''City Manhole ID: MH2252Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.51.01.52.02.53.03.54.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000123456712/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH2999 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 3431 Shattuck Ave SPipeline diameter: 8''City Manhole ID: MH2999Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.20.30.40.50.612/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.60000011223344512/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH3216 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: West of 4022 Talbot Rd SPipeline diameter: 7.38''City Manhole ID: MH3216Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.60000-0.10.00.10.10.20.20.312/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.21.41.61.82.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.60000012345612/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH3625 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 4201 NE Sunset BlvdPipeline diameter: 12''City Manhole ID: MH3625Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.21.41.61.812/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.00.51.01.52.02.53.03.54.04.55.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000002468101212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataSeries4
FLOW MONITORING MH4628 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 766 Monroe Ave NEPipeline diameter: 10.38''City Manhole ID: MH4628Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000001234567891012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH4646 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 582 Bronson Way NEPipeline diameter: 8''City Manhole ID: MH4646Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.10.20.20.30.30.40.412/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.02.04.06.08.010.012.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000001234567891012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH5302 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Royal Hills and SE Harrington PlPipeline diameter: 14''City Manhole ID: MH5302Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.81.31.82.32.83.33.84.34.85.35.812/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.60000024681012141612/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataSeries4
FLOW MONITORING MH5505 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 4444 NE Sunset BlvdPipeline diameter: 10''City Manhole ID: MH5505Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.09.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000001234567891012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
FLOW MONITORING MH5519 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Access via Talbot Rd SPipeline diameter: 10.25''City Manhole ID: MH5519Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.20.40.60.81.01.212/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.6000001234567891012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataSeries4
FLOW MONITORING MH6041 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: Edmonds Ave and NE Sunset BlvdPipeline diameter: 8''City Manhole ID: MH6041Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.10.20.20.30.30.412/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000112233445512/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataSeries4
FLOW MONITORING MH6704 WET WEATHER FLOW CALIBRATIONLong-range Wastewater Management PlanCity of RentonLocation: 2623 NE Sunset BlvdPipeline diameter: 12''City Manhole ID: MH6704Model Mahhole ID: Silt Level at Site: ''0.000000.100000.200000.300000.400000.500000.600000.00.10.10.20.20.30.30.40.40.512/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Flow (mgd)Flow CalibrationRainADWFMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000.01.02.03.04.05.06.07.08.09.010.012/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/hour)Velocity (ft/s)Velocity CalibrationRainMeasured DataModeled Data0.000000.100000.200000.300000.400000.500000.600000112233412/2512/291/21/61/101/141/181/221/261/302/32/72/112/152/192/232/273/33/73/113/153/193/233/273/314/44/84/124/164/20Rain (inches/15-minutes)Level (inches)Level CalibrationRainMeasured DataModeled Data
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix I
TM 4 - RISK FINDINGS
1218 THIRD AVENUE, SUITE 1600 • SEATTLE, WASHINGTON 98101 • P. 206.684.6532 • F. 206.903.0419
pw://Carollo/Documents/Client/WA/Renton/9971A00/Deliverables/TM01.docx
CITY OF RENTON
LONG-RANGE WASTEWATER MANAGEMENT PLAN
TECHNICAL MEMORANDUM NO. 4
RISK FINDINGS
DRAFT June 2017
This document is released for the purpose of information exchange review and planning only under the authority of Lara R. Kammereck, June 16, 2017, 34428, WA.
June 2017 - DRAFT i
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
CITY OF RENTON
LONG-RANGE WASTEWATER MANAGEMENT PLAN
TECHNICAL MEMORANDUM
NO. 4
RISK FINDINGS
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION/METHODOLOGY...................................................................... 4-1
1.1 Methodology .............................................................................................. 4-1
2.0 CRITERIA ............................................................................................................. 4-2
3.0 DATA SOURCES .................................................................................................. 4-6
4.0 SCORING ............................................................................................................. 4-6
4.1 Vulnerability Score Range ......................................................................... 4-6
4.2 Criticality Score Range .............................................................................. 4-7
4.3 Risk Scoring .............................................................................................. 4-7
5.0 VULNERABILITY RESULTS ................................................................................. 4-8
6.0 CRITICALITY RESULTS ..................................................................................... 4-23
7.0 RISK ................................................................................................................... 4-41
LIST OF TABLES
Table 2.1 Vulnerability Criteria ..................................................................................... 4-3
Table 2.2 Criticality Criteria ......................................................................................... 4-4
Table 4.1 Vulnerability Score Range ........................................................................... 4-6
Table 4.2 Criticality Score Range ................................................................................ 4-7
Table 4.3 Normalized Risk Ratings.............................................................................. 4-8
Table 5.1 Vulnerability Score by Length ...................................................................... 4-8
Table 6.1 Criticality Score Range .............................................................................. 4-23
Table 7.1 Normalized Risk Ratings............................................................................ 4-41
Table 7.2 Pipe Length Totals Based on Risk Rating .................................................. 4-41
LIST OF FIGURES
Figure 5.1 Summary of Vulnerability Scoring ................................................................ 4-9
Figure 5.2 Structural Condition, CCTV Inspection Results .......................................... 4-11
Figure 5.3 O&M Condition, CCTV Inspection Results ................................................. 4-13
Figure 5.4 Remaining Useful Life Results ................................................................... 4-15
Figure 5.5 Frequency of Preventative Maintenance .................................................... 4-17
Figure 5.6 Slope of Pipe Segment Results ................................................................. 4-19
Figure 5.7 Vulnerability Criteria Results ...................................................................... 4-21
June 2017 - DRAFT ii
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
Figure 6.1 Summary of Criticality Rating and Scores .................................................. 4-24
Figure 6.2 Cost to Repair Failure Results ................................................................... 4-25
Figure 6.3 Loss of Critical Infrastructure and Transportation Links Results ................. 4-27
Figure 6.4 Damage to Property Results ...................................................................... 4-29
Figure 6.5 Environmental Impacts Results.................................................................. 4-31
Figure 6.6 Loss of Service to Customers Results ....................................................... 4-33
Figure 6.7 Reputational Damage Results ................................................................... 4-35
Figure 6.8 Damage to Local Business and Economy Results ..................................... 4-37
Figure 6.9 Criticality Criteria Results ........................................................................... 4-39
Figure 7.1 Map of Criticality x Vulnerability ................................................................. 4-43
June 2017 - DRAFT 4-1
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
Technical Memorandum No. 4
RISK FINDINGS
1.0 INTRODUCTION/METHODOLOGY
The City of Renton (City) requested Carollo Engineers, Inc. (Carollo) to develop a risk-based prioritization for their repair and replacement (R&R) projects in conjunction with implementation of Phase 2 of the City’s closed-circuit television (CCTV) Implementation program. The City’s risk based R&R program will be an important component meeting the City's goal to:
• Provide adequate, reliable sanitary sewer service at a minimum cost to the customer.
Risk of an asset (pipe, manhole, pump, etc.) is a measure of the impact of asset failure on the overall system. Risk is calculated as the product of criticality and vulnerability, or
Risk = Criticality x Vulnerability
Criticality represents the consequence of failure, and the vulnerability represents the likelihood of failure. This assessment is at a conceptual planning level and does not include survey, site inspections, or other detailed investigations.
1.1 Methodology
A risk ranking was developed for all gravity collection pipelines in the system during the study. The vulnerability and criticality criteria, data sources, and levels were identified. Criteria were developed from the Halcrow Risk and Remaining Life Planning Tools (Weber Davis Aqueduct, March 2011), which was consistent with the City’s prior risk based R&R prioritization of force mains (Existing Force Main Condition Assessment and Lift Station Evaluation, Carollo 2016). The Halcrow criteria were refined for meet the City’s objectives and available data sources. Data sources and levels were chosen that represented the selected criteria, were readily available, and that could be applied consistently across the entire system.
Once the criteria and data sources were set, each pipe segment was assigned a score based criteria ratings in GIS. The levels varied from negligible criticality or vulnerability (Level 1) to severe (Level 4). The levels are represented numerically as 1 to 4. W eighted factors were applied to reflect the City’s priorities. The pipe segments' weight for each criteria were then summed to find a final vulnerability and criticality score for that segment. Those two scores were then combined into 16 different "criticality, vulnerability" combinations (for example, 1,2; 2,3; or 4,4), and each combination was categorized with a risk ranking of low, moderately-low, moderately-high, and high.
June 2017 - DRAFT 4-2
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
2.0 CRITERIA
Tables 2.1 and 2.2 show the criteria, weighting, and description of each level for vulnerability and criticality, respectively. These criteria and data sources reflect an iterative refinement process that reflected the City’s typical key decision factors and the perceived accuracy of the data. Where the decision factors or available data did not support four levels of scoring two levels of scoring were typically used. For example, the criticality criterion for environmental impacts receives a level of 3 when within 50 feet from a critical area and a level of 1 at greater distances. Given the high level of the critical area data, the City was not comfortable in differentiating the criteria further without a site-specific investigation (wetland delineation, geotechnical analysis, etc.). These site-specific analyses are generally conducted as part of the design of the R&R project and could not be reasonably completed City wide.
A total score was calculated for each criteria for all gravity collection pipes in the system. For example, if a pipe segment's remaining useful life (RUL) was between five and ten years, the segment would fall into the Vulnerability Level 3, or moderate, rating. Multiplying the level of three (3) by an RUL weight of one (1), the final weighed level for that criteria would be 3 x 1 = 3. The same calculation would be made for the remaining criteria and summed for an overall score. To aid in review, a consistent color scheme is applied to the levels and scores in all mapping. Additionally, a code was given for each criteria for simplicity when identifying the criteria on the figures later in this Technical Memo (TM).
June 2017 - DRAFT 4-3 pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx Table 2.1 Vulnerability Criteria
Long-Range Wastewater Management Plan
City of Renton
Criteria Code Weighting Level 1 Level 2 Level 3 Level 4
Structural Condition, CCTV Inspection Results
CCTV STRUCTURAL 1 Negligible Pipe not yet inspected: material is PVC or DIP Structural NASSCO Score ≤ 2
Low Pipe not yet inspected: all other materials Structural NASSCO Score > 2 and ≤ 3
Moderate Structural NASSCO Score
> 3 and ≤ 4
Severe Structural NASSCO Score > 4
O&M Condition, CCTV Inspection Results
CCTV OM 1 Negligible Pipe not yet inspected: material is PVC or DIP O&M NASSCO
Score ≤ 2
Low Pipe not yet inspected: all other materials O&M NASSCO
Score > 2 and ≤ 3
Moderate O&M NASSCO Score > 3 and ≤ 4
Severe O&M NASSCO Score > 4
Remaining Useful Life Estimate RUL 1 Negligible RUL > 20 years Low RUL between 10 and 20 years
Moderate RUL between 5 and 10 years
Severe Less than 5 years RUL
Frequency of Preventative Maintenance
MAINT 1 Negligible No Cleaning Low Annual OR Biannual Cleaning
Moderate Monthly or Quarterly Cleaning
Severe Biweekly or Weekly Cleaning
Slope of Pipe Segment SLOPE 1 Negligible Slope > 0.5% Low
Slope ≤ 0.5% Moderate Severe
June 2017 - DRAFT 4-4 pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx Table 2.2 Criticality Criteria
Long-Range Wastewater Management Plan
City of Renton
Criteria Code Weighting Level 1 Level 2 Level 3 Level 4
Cost to Repair Failure REPAIR 1 Small Repair Effort by City Crew
Pipe Diameter: ≤ 12" AND
Pipe Depth: <12'
Large Repair Effort by City Crew
Pipe Diameter: > 12" AND
Pipe Depth: <12'
Small Repair Effort by Contractor
Pipe Diameter: ≤ 12" AND
Pipe Depth: ≥12'
Large Repair Effort by Contractor
Pipe Diameter: > 12" AND
Pipe Depth: ≥12'
Loss of Critical Infrastructure and Transportation Links
TRANS 2 Negligible
No Site of Interest OR
Non-arterials
Low
No Site of Interest OR
Collector Street
Moderate
Site of Interest OR
Arterial Street
Severe
Critical Infrastructure OR
Freeways
Damage to Property PROP 1 Negligible
Distance to Building Footprint - > 10 ft
Moderate
Distance to Building
Footprint ≤ 10 ft
Environmental Impacts to waterway, wetland, or other Sensitive Area
ENV 1 Negligible
Distance from Critical Area > 50 ft
Moderate
Distance to Critical Area < 50 ft
Loss of Service to Customers LOS 1 Negligible
Collection Line
Moderate
Trunk Line
Reputational Damage REP 1 Negligible
Outside Wellfield Capture Zone OR
Low Moderate Severe
Within 200 ft. of Wellfield OR
June 2017 - DRAFT 4-5 pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx Table 2.2 Criticality Criteria
Long-Range Wastewater Management Plan
City of Renton
Criteria Code Weighting Level 1 Level 2 Level 3 Level 4
Distance to Critical Water Body >200 ft Within 5 year Wellfield Capture Zone OR
2. Distance to Critical Water Body
> 100 ft and ≤ 200 ft
Within 1 year Wellfield Capture Zone OR
2. Distance to Critical Water Body > 50 ft and ≤ 100 ft
Distance to Critical Water Body <50 ft
Damage to Local Business and Economy
BIZ 1 Negligible
Pipeline outside of Overlay District
Moderate
Pipeline within Overlay District
June 2017 - DRAFT 4-6
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
3.0 DATA SOURCES
Data sources were largely available for the majority of the gravity collection system. Where data was missing (typically less than 2 percent of records), a Level 1 designation was assigned, except for CCTV criteria. The majority of the system has not undergone National Association of Sewer Services Companies (NASSCO) based CCTV inspections; therefore data is limited. Based on the NASSCO based CCTV inspections completed to date, pipes without data were rated based on material.
A detailed list of the data sources used for this technical memo can be found in the Pipe Risk Calculation technical memo.
4.0 SCORING
The following section shows the three types of scoring used to find the risk ranking. A detailed description of the scoring and how it was implemented can be found in the Pipe Risk Calculation technical memo.
4.1 Vulnerability Score Range
Weighted vulnerability levels for each pipe segment were summed up to find a total score for that pipe. For the force main risk assessment, vulnerability scores were separated into four levels, roughly equal to each other. For this study, scores were instead selected based on point ratings for specific conditions. Pipes with a criterion at a Level 3 or 4 received a vulnerability score of 3. Pipes with multiple of Level 3 and 4 criteria received a vulnerability score of 4. The adjusted scores are shown in the Table 4.1.
Table 4.1 Vulnerability Score Range
Long-Range Wastewater Management Plan
City of Renton
Vulnerability Level Minimum Score Maximum Score
1 (negligible) 5 5
2 (low) 6 6
3 (moderate) 7 9
4 (severe) 10 16
June 2017 - DRAFT 4-7
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
4.2 Criticality Score Range
Similar to the vulnerability score range, the criticality ranges were selected point ratings based on specific conditions and shown in Table 4.2.
The minimum criticality score any pipe can receive is an 8, which would be the minimum scores for each criteria and assigned a criticality level of 1. Pipes with two Level 3 criteria result in a score in the Level 3 Criticality range. Multiple Level 3 and 4 criteria ratings result in a score in the Level 4 Criticality range. The rest of the levels are also shown in Table 4.2.
Table 4.2 Criticality Score Range
Long-Range Wastewater Management Plan
City of Renton
Criticality Level Minimum Score Maximum Score
1 (negligible) 8 8
2 (low) 9 10
3 (moderate) 11 15
4 (severe) 16 23
4.3 Risk Scoring
The criticality, vulnerability, and risk ranking for each collection main were quantified in a relative risk scale, with one representing the lowest risk and four representing the highest risk. Table 4.3 below shows how the risk rating is scored based on the criticality and vulnerability scores.
It is recommended that the City implement the following actions based on the risk ranking the pipes receive:
• High Risk pipes should be prioritized for R&R. More frequent monitoring and/or preventative maintenance is recommended for these pipes until they are repaired or replaced.
• Moderately high risk pipes should be frequently monitored.
• Moderately low risk pipes should be monitored on a bi-monthly basis.
• Low risk pipe are typically monitored on a yearly basis.
June 2017 - DRAFT 4-8
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
Table 4.3 Normalized Risk Ratings
Long-Range Wastewater Management Plan
City of Renton Normalized Risk Ranking Vulnerability Level 4 (severe) Moderately Low Moderately High High High
3 (moderate) Moderately Low Moderately High Moderately High High
2 (low) Low Moderately Low Moderately High Moderately High
1 (negligible) Low Low Moderately Low Moderately Low
1 (negligible) 2 (low) 3 (moderate) 4 (severe)
Criticality Level
5.0 VULNERABILITY RESULTS
Table 5.1 shows the amount of pipe found in each vulnerability level. Approximately 45 percent of the City's system is considered a negligible vulnerability. Pipes having a low and moderate vulnerability make up approximately 14 and 31 percent of the system, respectfully. The City has approximately 10 percent of their system in the severe vulnerability.
Table 5.1 Vulnerability Score by Length
Long-Range Wastewater Management Plan
City of Renton
Vulnerability Level Length (feet) Percent
1 (negligible) 589,783 45%
2 (low) 180,580 14%
3 (moderate) 397,772 31%
4 (severe) 133,099 10%
Total: 1,301,234 100%
Figure 5.1 shows the summary of the four vulnerability criteria given the rating. In general, each criteria increases as the level increases. The remaining useful life (RUL) criteria shows the most change as the level increases.
June 2017 - DRAFT 4-9
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
Figure 5.1 Summary of Vulnerability Scoring
The results of the vulnerability scores for each criteria are shown in Figures 5.2 through 5.7. The levels for each criteria are typically identified by the following colors:
• Red = Level 4 (severe)
• Orange = Level 3 (moderate)
• Dark Green = Level 2 (low)
• Light Green = Level 1 (negligible)
Showing the individual criteria on a map of the City's system gives the City a clear snapshot of where the current problem areas are located and what potential problem areas could occur if not monitored. For example, Figure 5.4 shows a large area of red pipe that have a vulnerability level of 4, or severe. This would indicate that most of this area has pipe with an RUL of less than five years, and should be reviewed for possible R&R in the near future.
Figure 5.7 shows the overall vulnerability scores. A large portion of moderate to severe pipe is located in the northern part of the City, east of the interstate. This is mainly due to the RUL of the pipe, and some pipe requiring periodic cleaning.
CCTV Structural CCTV Structural
CCTV Structural CCTV Structural
CCTV OM CCTV OM
CCTV OM CCTV OMRULRUL
RUL
RUL
MAINT MAINT
MAINT
MAINT
SLOPE
SLOPE
SLOPE
SLOPE
0
1
2
3
4
5
6
7
8
9
10
1 2 3 4Total Vulnerability ScoreVulnerabiliity Rating
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 5.2 Structural Condition, CCTV Inspection Results
Legend
City of Renton
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 5.3 O&M Condition, CCTV Inspection Results
Legend
City of Renton
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 5.4 Remaining Useful Life Results
Legend
City of Renton
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 5.5 Frequency of Preventative Mainenance
Legend
City of Renton
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 5.6 Slope of Pipe Segment Results
Legend
City of Renton
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 5.7 Vulnerability Criteria Ranking
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
Legend
City of Renton
Street Centerlines
June 2017 - DRAFT 4-23
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
6.0 CRITICALITY RESULTS
Table 6.1 shows the amount of pipe found in each criticality level. Criticality level 1 pipes
make up approximately 25.7 percent of the total pipe count. Criticality Level 2 pipes make
up approximately 27.1 percent of the total pipe count. Pipes that fall into criticality level 3
represent approximately 34.7 percent of the total count. Pipes found in criticality level 4
have scores between 16 and 23, and make up approximately 13 percent of the total count.
Table 6.1 Criticality Score Range
Long-Range Wastewater Management Plan
City of Renton
Criticality Level Length (feet)
1 (negligible) 333,777
2 (low) 352,977
3 (moderate) 447,195
4 (severe) 167,286
Total: 1,301,234
Figure 6.1 shows the total criticality scores broken down for each criticality rating of the
seven criteria for criticality. Each rating falls within the score range as shown in Table 4.2.
The Loss of Critical Infrastructure and Transportation Links criteria increases significantly
as the rating increases. This is due to both the larger weight it is given and the City's pipe
segments being near critical infrastructure or a freeway.
June 2017 - DRAFT 4-24
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
Figure 6.1 Summary of Criticality Rating and Scores
The results of the criticality scores for each criteria are shown in Figures 6.2 to 6.9. Similar
to the vulnerability maps, the levels of criteria are color-coded to identify the different levels
when compared with the location of the pipe. Figure 6.9 shows the overall criticality criteria
ranking, with the majority of pipe in the severe and moderate levels located near the
downtown area and major roadways. Figure 6.3 shows the moderate and severe level pipe
found near the City's arterial streets and freeways. Figure 6.8 identifies the City's downtown
area as moderately critical, as the area is an Overlay District.
The results are reasonable, since pipe in these areas would have a larger impact to the
system should they be damaged.
REPAIR REPAIR REPAIR REPAIRTRANSTRANSTRANS
TRANS
PROP
PROP
PROP
PROP
LOS
LOS
LOS
LOS
ENV
ENV
ENV
ENV
REP
REP
REP
REP
BIZ
BIZ
BIZ
BIZ
0
2
4
6
8
10
12
14
16
18
20
1 2 3 4Total Criticality ScoreCriticality Rating
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.2 Cost to Repair Failure Results
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
Legend
City of Renton
Street Centerlines
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
!A
!A
!A
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!ï
!A
!A
H!A
Ã
!A
m
m
m
m
m
m
mm
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
mo
m
m
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.3 Loss of Critical Infrastructure and Transportation Links Results
Legend
Non-Arterials
Collector
Arterial
Freeway
Ramp
H Hospital / Medical Center
à Light Rail Station
!ï Fire Station / EMS Station!A Urgent Care Facility
m School
oAirport Runway / Airfield
Level 1 (Negligible)
Level 2 (Low)Level 3 (Moderate)Level 4(Severe)
Non-Critical Infrastructure
City of Renton
Critical Infrastructure
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.4 Damage to Property Results
Legend
City of Renton
Building Footprints
Street Centerlines
Level 1 (Negligible)
Level 3 (Moderate)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.5 Environmental Impact Results
Legend
City of Renton
Streams
Type S
Type F
Type Np
Type Ns
Wetlands
Percentage of Slope
>40% and <=90%
>90%
Street Centerlines
Level 1 (Negligible)Level 3 (Moderate)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.6 Loss of Service to Customers Results
Legend
City of Renton
Level 1 (Negligible)
Collection
Level 3 (Moderate)
Trunk
Street Centerlines
&<
&<&<
&<&<
&<
&<MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NELake Washington
Cedar
R
ive
r
M
a
y
C
r
e
e
k
Disclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.7 Reputational Damage Results
Legend
City of Renton
&<Well
Streams
Wellfield Capture Zone
One Year Capture Zone
Five Year Capture Zone
Ten Year Capture Zone
Lake Washington
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.8 Damage to Local Business and Economy Results
Legend
City of Renton
Overlay Districts
Auto Mall A
Auto Mall B
City Center Sign Regulation Area
Urban Design District A
Urban Design District B
Urban Design District C
Urban Design District D
Downtown Business District
Level 1 (Negligible)
Level 3 (Moderate)
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 14, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 6.9 Summary of Criticality Ranking and Scores
Legend
City of Renton
Criticality Criteria Rank
Street Centerlines
Level 1 (Negligible)
Level 2 (Low)
Level 3 (Moderate)
Level 4(Severe)
June 2017 - DRAFT 4-41
pw:\\Carollo/Documents\Client/WA/Renton/9971A00/Deliverables\TM01.docx
7.0 RISK
Figure 7.1 shows the final result of the normalized risk ranking for the City's piping system.
There are 16 combinations that have been designated one of four colors, which represents
the overall level of risk. For example, a risk rating that has a vulnerability rating of 4 but a
criticality rating of 1 (shown on Figure 7.1 as 1,4) receives a light green designation, or a
moderately low risk rating as shown in Table 6.2. The amount of pipe that falls in each risk
ranking is shown in Table 7.1 and the amount of pipe length based on the four colored risk
ranking are shown in Table 7.2. Approximately 782,000 feet, or 60 percent, of the City's
piping system falls in the low or moderately low categories. The city has approximately
379,000 feet, or 29 percent, of the piping system in the moderately-high (yellow) category.
And approximately 140,000 feet, or 11 percent of the piping system, falls in the red, or high
risk, category.
Table 7.1 Normalized Risk Ratings
Long-Range Wastewater Management Plan
City of Renton
Normalized Risk Ranking Vulnerability Level 4 (severe) 18,503
(%1.4)
38,202
(%2.9)
63,030
(%4.8)
13,364
(%1.0)
3 (moderate) 97,627
(%7.5)
95,897
(%7.4)
140,271
(%10.8)
63,978
(%4.9)
2 (low) 27,886
(%2.1)
48,447
(%3.7)
70,219
(%5.4)
34,028
(%2.6)
1 (negligible) 189,761
(%14.6)
170,430
(%13.1)
173,675
(%13.3)
55,916
(%4.3)
1 (negligible) 2 (low) 3 (moderate) 4 (severe)
Criticality Level
Table 7.2 Pipe Length Totals Based on Risk Rating
Long-Range Wastewater Management Plan
City of Renton
Color Total Length (ft) % of Total Length
Low 388,077 30%
Moderately-Low 394,169 30%
Moderately-High 378,617 29%
High 140,372 11%
MaplewoodSE Petrovitsky Rd
Be
a
c
o
n
W
a
y
S
SE 168th StOakesdale Ave SWSW 7th St
SW 16th St
SR 167SE 192nd StInterurban TrailCeda
r
R
i
v
e
r
T
r
a
i
l
SW SunsetBlvd Monroe Ave NENile Ave NESE 116th St
N 6th St
Garden Ave NN 4th St
RentonA v e S Rainer Ave N132nd Ave SE§¨¦405
§¨¦405
N 40th St
N 29th St
Edmonds Ave NEDisclaimer: Features shown in this figure are for planning purposes and represent approximate locations. Engineering and/or survey accuracy is not implied.
Data Sources: City of Renton, WA
O
0 0.5 10.25 Miles
Last Revised: June 13, 2017 \\io-fs-1\Data\GISBackup\Renton\CricalityAnalysis\AllCriteriaFigures.mxd
LONG-RANGE WASTEWATER MANAGEMENT PLAN – RISK ASSESSMENT | TM 2 | CITY OF RENTON
Figure 7.1 Map of Criticality x Vulnerability
Legend
City of Renton
Critcality x Vulnerability Risk
1,1
1,2
1,3
1,4
2,1
2,2
2,3
2,4
3,1
3,2
3,3
3,4
4,1
4,2
4,3
4,4
Street Centerlines
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix J
STANDARD PLANS AND SPECIFICATIONS
1
SPECIAL PROVISIONS ................................................................................................. 12
1-01 DEFINITIONS AND TERMS .................................................................................. 12
1-01.1 General ............................................................................................................... 12
1-01.3 Definitions ........................................................................................................ 12
1-02 BID PROCEDURES AND CONDITIONS ............................................................. 15
1-02.1 Prequalification of bidders .............................................................................. 15
1-02.2 Plans and Specifications ................................................................................. 15
1-02.5 Proposal Forms ................................................................................................ 16
1-02.6 Preparation of Proposal .................................................................................. 16
1-02.6(1) Proprietary Information ............................................................................... 17
1-02.7 Bid Deposit ....................................................................................................... 17
1-02.9 Delivery of Proposal ........................................................................................ 18
1-02.12 Public Opening of Proposals ........................................................................ 18
1-02.13 Irregular Proposals ........................................................................................ 18
1-02.14 Disqualification of Bidders ........................................................................... 18
1-02.15 Pre Award Information ................................................................................... 19
1-03 AWARD AND EXECUTION OF CONTRACT ....................................................... 19
1-03.1 Consideration of bids ...................................................................................... 19
1-03.2 Award of Contract ............................................................................................ 20
1-03.3 Execution of Contract ...................................................................................... 20
1-03.4 Contract Bond .................................................................................................. 20
1-03.7 Judicial Review ................................................................................................ 21
1-04 SCOPE OF WORK ............................................................................................... 21
1-04.2 Coordination of Contract Documents… ........................................................ 21
1-04.8 Progress Estimates and Payments ................................................................ 22
1-04.11 Final Cleanup .................................................................................................. 22
1-04.3 Contractor-Discovered Discrepancies ........................................................... 22
1-05 CONTROL OF WORK .......................................................................................... 22
1-05.4 Conformity With and Deviation from Plans and Stakes ............................... 22
1-05.4(3) Contractor Supplied Surveying .................................................................. 24
1-05.4(4) Contractor Provided As-Built Information ................................................ 24
1-05.7 Removal of Defective and Unauthorized Work ............................................. 25
1-05.10 Guarantees ..................................................................................................... 26
1-05.11 Final Inspection .............................................................................................. 26
2
1-05.11(1) Substantial Completion Date .................................................................... 26
1-05.11(2) Final Inspection and Physical Completion Date ..................................... 27
1-05.11(3) Operational Testing ................................................................................... 28
1-05.12 Final Acceptance ........................................................................................... 28
1-05.13 Superintendents, Labor and Equipment of Contractor .............................. 28
1-05.14 Cooperation with Other Contractors ............................................................ 29
1-05.16 Water and Power ............................................................................................ 29
1-05.17 Oral Agreements ............................................................................................ 29
1-05.18 Contractor's Daily Diary ................................................................................ 29
1-06 CONTROL OF MATERIAL ................................................................................... 31
1-06.1 Approval of Materials Prior to Use ................................................................. 31
1-06.2(1) Samples and Tests for Acceptance ........................................................... 31
1-06.2(2) Statistical Evaluation of Materials for Acceptance ................................... 31
1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC ..................... 31
1-07.1 Laws to be Observed ....................................................................................... 31
1-07.6 Permits and Licenses ...................................................................................... 32
1-07.9 Wages ............................................................................................................... 33
1-07.9(5) Required Documents .................................................................................. 33
1-07.11 Requirements for Non-Discrimination ......................................................... 33
1-07.11(11) City of Renton Affidavit of Compliance ................................................. 33
1-07.12 Federal Agency Inspection ........................................................................... 33
1-07.13 Contractor’s Responsibility for Work .......................................................... 34
1-07.13(1) General ....................................................................................................... 34
1-07.15 Temporary Water Pollution/Erosion Control ............................................... 34
1-07.16 Protection and Restoration of Property ....................................................... 36
1-07.16(1) Private/Public Property ............................................................................. 36
1-07.17 Utilities and Similar Facilities ....................................................................... 38
1-07.17(1) Site Specific Potholing .............................................................................. 39
1-07.17(3) Interruption of Services ............................................................................ 40
1-07.17(4) Resolution of Utility Conflicts .................................................................... 40
1-07.18 Public Liability and Property Damage Insurance ....................................... 40
1-07.18(1) General ....................................................................................................... 40
1-07.18(2) Coverages .................................................................................................. 41
1-07.18(3) Limits .......................................................................................................... 42
1-07.18(4) Evidence of Insurance: ............................................................................. 43
3
1-07.22 Use of Explosives .......................................................................................... 44
1-07.23 Public Convenience and Safety .................................................................... 44
1-07.23(1) Construction Under Traffic ....................................................................... 44
1-07.23(2) Construction and Maintenance of Detours ............................................. 46
1-07.24 Rights of Way ................................................................................................. 46
1-07.28 Confined Space Entry .................................................................................... 47
1-08 PROSECUTION AND PROGRESS ...................................................................... 47
1-08.0 Preliminary Matters .......................................................................................... 47
1-08.0(1) Preconstruction Conference ...................................................................... 47
1-08.0(2) Hours of Work .............................................................................................. 49
1-08.0(3) Reimbursement for Overtime Work of Contracting Agency Employees 49
1-08.1 Subcontracting ................................................................................................. 50
1-08.2 Assignment ...................................................................................................... 50
1-08.3 Progress Schedule .......................................................................................... 50
1-08.4 Notice to Proceed and Prosecution of the Work .......................................... 52
1-08.5 Time For Completion ....................................................................................... 52
1-08.6 Suspension of Work ........................................................................................ 54
1-08.7 Maintenance During Suspension ................................................................... 54
1-08.9 Liquidated Damages ........................................................................................ 54
1-08.11 Contractor's Plant and Equipment ............................................................... 55
1-08.12 Attention to Work ........................................................................................... 55
1-09 MEASUREMENT AND PAYMENT ....................................................................... 55
1-09.1 Measurement of Quantities ............................................................................. 55
1-09.3 Scope of Payment ............................................................................................ 56
1-09.6 Force Account .................................................................................................. 57
1-09.7 Mobilization ...................................................................................................... 57
1-09.9 Payments .......................................................................................................... 58
1-09.9(1) Retainage ..................................................................................................... 59
1-09.9(2) Contracting Agency’s Right to Withhold and Disburse Certain Amounts
........................................................................................................................................ 59
1-09.9(3) Final Payment .............................................................................................. 60
1-09.11 Disputes and Claims ....................................................................................... 61
1-09.11(2) Claims ......................................................................................................... 61
1-09.11(3) Time Limitations and Jurisdiction ........................................................... 61
1-09.13 Claims and Resolutions ................................................................................. 62
4
1-09.13(3) Claims $250,000 or Less ........................................................................... 62
1-09.13(3)A Administration of Arbitration ................................................................. 62
1-09.13(3)B Procedures to Pursue Arbitration ......................................................... 62
1-09.14 Payment Schedule ......................................................................................... 63
1-09.14(1) Scope .......................................................................................................... 63
1-09.14(2) Bid Items .................................................................................................... 63
1-10 TEMPORARY TRAFFIC CONTROL .................................................................... 95
1-10.1 General .............................................................................................................. 95
1-10.2(1)B Traffic Control Supervisor ........................................................................ 97
1-10.2(2) Traffic Control Plans ................................................................................... 97
1-10.3 Flagging, Signs, and All Other Traffic Control Devices ................................ 97
1-10.3(3) Construction Signs ..................................................................................... 97
1-10.3(3) Construction Signs ..................................................................................... 97
1-10.4 Measurement .................................................................................................... 97
1-10.5 Payment ............................................................................................................ 98
1-11 RENTON SURVEYING STANDARDS .................................................................. 98
1-11.1(1) Responsibility for surveys .......................................................................... 98
1-11.1(2) Survey Datum and Precision ...................................................................... 98
1-11.1(3) Subdivision Information .............................................................................. 99
1-11.1(4) Field Notes ................................................................................................... 99
1-11.1(5) Corners and Monuments ............................................................................ 99
1-11.1(6) Control or Base Line Survey ...................................................................... 99
1-11.1(7) Precision Levels ........................................................................................ 100
1-11.1(8) Radial and Station -- Offset Topography ................................................. 100
1-11.1(9) Radial Topography .................................................................................... 100
1-11.1(10) Station--Offset Topography .................................................................... 101
1-11.1(11) As-Built Survey ........................................................................................ 101
1-11.1(12) Monument Setting and Referencing ...................................................... 101
1-11.12 Materials ...................................................................................................... 102
1-11.12(1) Property/Lot Corners ............................................................................... 102
1-11.12(2) Monuments ............................................................................................... 102
1-11.12(3) Monument Case and Cover .................................................................... 102
2-01 CLEARING, GRUBBING, AND ROADSIDE CLEANUP .................................... 102
2-01.1 Description ..................................................................................................... 102
2-01.2 Disposal of Usable Material and Debris ....................................................... 103
5
2-01.5 Payment .......................................................................................................... 103
2-02 REMOVAL OF STRUCTURE AND OBSTRUCTIONS ....................................... 103
2-02.3(3) Removal of Pavement, Sidewalks, and Curbs ........................................ 103
2-02.4 Measurement .................................................................................................. 103
2-02.5 Payment .......................................................................................................... 103
2-03 ROADWAY EXCAVATION AND EMBANKMENT .............................................. 104
2-03.3 Construction Requirements .......................................................................... 104
2-03.4 Measurement .................................................................................................. 105
2-03.5 Payment .......................................................................................................... 105
2-04 HAUL .................................................................................................................. 106
2-04.5 Payment .......................................................................................................... 106
2-06 SUBGRADE PREPARATION ............................................................................. 106
2-06.5 Measurement and Payment ......................................................................... 106
2-09 STRUCTURE EXCAVATION .............................................................................. 106
2-09.1 Description ..................................................................................................... 106
2-09.3(1)D Disposal of Excavated Material ............................................................. 106
2-09.4 Measurement .................................................................................................. 106
2-09.5 Payment .......................................................................................................... 107
5-04 ASPHALT CONCRETE PAVEMENT .................................................................. 108
5-06 TEMPORARY RESTORATION IN PAVEMENT AREAS .................................... 137
5-06.1 Description ..................................................................................................... 137
5-06.2 Materials ......................................................................................................... 137
5-06.3 Construction Requirements .......................................................................... 137
7-01 DRAINS .............................................................................................................. 138
7-01.2 Materials ......................................................................................................... 138
7-01.3 Construction Requirements .......................................................................... 138
7-01.4 Measurement .................................................................................................. 138
7-02 CULVERTS ......................................................................................................... 138
7-02.2 Materials ......................................................................................................... 138
7-04 STORM SEWERS .............................................................................................. 139
7-04.2 Materials ......................................................................................................... 139
7-04.2 Materials ......................................................................................................... 139
7-04.3(1) Cleaning and Testing ................................................................................ 139
7-04.3(1)G Abandon Existing Storm Sewer Pipes .................................................. 140
7-04.3(2) CCTV Inspection ........................................................................................ 141
6
7-04.3(3) Direct Pipe Connections ............................................................................ 141
7-05 MANHOLES, INLETS, AND CATCH BASINS ................................................... 141
7-05.3 Construction Requirements .......................................................................... 141
7-05.3(1) Adjusting Manholes and Catch Basins to Grade .................................... 142
7-05.3(3) Connections to Existing Manholes .......................................................... 143
7-05.3(5) Manhole Coatings ...................................................................................... 143
7-06 TRENCH DRAINS (NEW SECTION) ................................................................... 144
7-06.1 Description ....................................................................................................... 144
7-06.2 Materials ........................................................................................................... 144
7-06.3 Construction Requirements ............................................................................ 144
7-08 GENERAL PIPE INSTALLATION REQUIREMENTS ........................................ 145
7-08.3 Construction Requirements .......................................................................... 145
7-08.3(1)A Trenches ................................................................................................... 145
7-08.3(1)C Bedding the Pipe ..................................................................................... 145
7-08.3(1)D Pipe Foundation ..................................................................................... 146
7-08.3(2)A Survey Line and Grade ........................................................................... 146
7-08.3(2)B Pipe Laying – General ............................................................................ 146
7-08.3(2)E Rubber Gasketed Joints ......................................................................... 147
7-08.3(2)H Sewer Line Connections ........................................................................ 147
7-08.3(2)J Placing PVC Pipe ..................................................................................... 147
7-08.3(3)A Backfilling Pipe Trenches....................................................................... 147
7-04.2(2) Temporary Stormwater Diversion ............................................................ 148
7-17.4 Measurement .................................................................................................. 149
7-09 PIPE AND FITTINGS FOR WATER MAINS ....................................................... 149
7-09.3(15)A Ductile Iron Pipe .................................................................................... 149
7-09.3(15)B Polyvinyl Chloride (PVC) Pipe (4 inches and Over) ........................... 150
7-09.3(17) Laying Ductile Iron Pipe and Fittings with Polyethylene Encasement
...................................................................................................................................... 150
7-09.3(19)A Connections to Existing Mains ............................................................ 150
7-09.3(21) Concrete Thrust Blocking and Dead-Man Block .................................. 152
7-09.3(23) Hydrostatic Pressure Test ...................................................................... 153
7-09.3(24)A Flushing and Poly-pigging ................................................................... 155
7-09.3(24)D Dry Calcium Hypochlorite .................................................................... 155
7-09.3(24)K Retention Period ................................................................................... 156
7-09.3(24)N Final Flushing and Testing ................................................................... 156
7
7-09.3(25) Joint Restraint Systems .......................................................................... 156
7-09.4 Measurement .................................................................................................. 158
7-09.5 Payment .......................................................................................................... 158
7-12 VALVES FOR WATER MAINS ........................................................................... 159
7-12.3(1) Installation of Valve Marker Post ............................................................. 159
7-12.3(2) Adjust Existing Valve Box to Grade ......................................................... 159
7-12.4 Measurement .................................................................................................. 159
7-12.5 Payment .......................................................................................................... 160
7-14 HYDRANTS ........................................................................................................ 160
7-14.3(1) Setting Hydrants ........................................................................................ 160
7-14.3(3) Resetting Existing Hydrants ..................................................................... 161
7-14.3(4) Moving Existing Hydrants ........................................................................ 161
7-14.3(7) Remove and Salvage Hydrant .................................................................... 161
7-14.5 Payment .......................................................................................................... 162
7-15 SERVICE CONECTIONS ................................................................................... 162
7-15.3 Construction Details ...................................................................................... 162
7-15.5 Payment .......................................................................................................... 163
7-17 SANITARY SEWERS ......................................................................................... 163
7-17.2 Materials ......................................................................................................... 163
7-17.3 Construction Requirements .......................................................................... 164
7-17.3(1) Protection of Existing Sewerage Facilities ............................................. 164
7-17.3(2)H Television Inspection .............................................................................. 164
7-17.3(2)I Abandon Existing Sanitary Sewer Pipes ............................................................ 165
7-17.5 Payment .......................................................................................................... 165
7-17.4 Measurement .................................................................................................. 165
7-17.4 Measurement .................................................................................................. 165
7-17.4 Measurement .................................................................................................. 166
7-17.4 Measurement .................................................................................................. 166
7-17.4 Measurement .................................................................................................. 166
7-21 GENERAL SPECIFICATIONS FOR CURED IN PLACE PIPE (CIPP) .............. 166
7-21.1 Description ......................................................................................................... 166
7-21.1(2) Licensing ......................................................................................................... 166
7-21.1(3) Contractor and Manufacturer Qualifications ..................................................... 167
7-21.1(4) Contractor Submittals ...................................................................................... 167
8
7-21.1(6) Warranty ........................................................................................................ 168
7-21.2 Materials ............................................................................................................ 169
7-21.2 Cured in Place Resin Impregnated Material in General ........................................... 169
7-21.2 Cured in Place Resin Impregnated Material in General ........................................... 169
7-21.2 Cured in Place Resin Impregnated Material in General ........................................... 170
7-21.2(2) Resin .............................................................................................................. 171
7-21.2(3) Physical Properties ................................................................................... 173
7-21.3 Construction Requirements .......................................................................... 174
7-21.3(1)A Flow Management ................................................................................... 174
7-21.3(1)B Cleaning ....................................................................................................... 175
7-21.3(1)C Point Repairs ................................................................................................. 176
7-21.3(1)D Manholes ..................................................................................................... 177
7-21.3(1)D Manholes ..................................................................................................... 177
7-21.3(2) Liner Installation ............................................................................................. 177
7-21.3(2) Liner Installation ............................................................................................. 178
7-21.3(4) Testing ............................................................................................................ 180
7-21.3(4)C Post Installation CCTV Inspection ................................................................... 180
7-21.3(4)A Material Testing ............................................................................................ 180
7-21.3(4)B Field Testing .................................................................................................. 181
7-21.4 Measurement ..................................................................................................... 181
7-21.4 Measurement ..................................................................................................... 181
7-21.5 Payment ............................................................................................................. 181
7-21 GENERAL SPECIFICATIONS FOR CURED IN PLACE PIPE (CIPP) .............. 181
8-02 ROADSIDE RESTORATION .............................................................................. 181
8-02.3(4)A Topsoil Type A ......................................................................................... 181
8-02.3(16)A Lawn Installation ................................................................................... 181
8-02.3(16)A2 Submittals ............................................................................................ 181
8-02.3(16)A2a Certification of Material ..................................................................... 181
8-02.3(16)A2b Manufacturer’s Certificates of Conformance ................................. 182
8-02.3(16)A2c Schedule for Installation .................................................................. 182
8-02.3(16)A3 Product Handling ................................................................................ 182
8-02.3(16)A4 Site Information ................................................................................... 182
8-02.3(16)A5 Sod ....................................................................................................... 182
8-02.3(16)A5a Other Materials .................................................................................. 182
9
8-02.3(16)A6 Execution ............................................................................................. 182
8-02.3(16)A6a Installation Preparation .................................................................... 183
8-02.3(16)A6b Sod Installation ................................................................................. 183
8-02.3(16)B Lawn Establishment ............................................................................. 183
8-02.3(16)B Lawn Establishment and Final Acceptance ....................................... 183
8-02.3(16)B1 Establishment Period ......................................................................... 183
8-02.3(16)B2 Guarantee ............................................................................................ 184
8-02.3(16)B3 Final Acceptance ................................................................................ 184
8-09 RAISED PAVEMENT MARKERS ....................................................................... 184
8-09.5 Payment .......................................................................................................... 184
8-13 MONUMENT CASES ......................................................................................... 185
8-13.1 Description ..................................................................................................... 185
8-13.3 Construction Requirements .......................................................................... 185
8-13.4 Measurement .................................................................................................. 185
8-13.5 Payment .......................................................................................................... 185
8-14 CEMENT CONCRETE SIDEWALKS ................................................................. 185
8-14.3(4) Curing ......................................................................................................... 185
8-14.4 Measurement .................................................................................................. 186
8-14.5 Payment .......................................................................................................... 186
8-17 IMPACT ATTENUATOR SYSTEMS ................................................................... 186
8-17.5 Payment .......................................................................................................... 186
8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, AND ELECTRICAL ............... 187
8-20.2(1) Equipment List and Drawings .................................................................. 187
8-22 PAVEMENT MARKING ...................................................................................... 187
8-22.1 Description ..................................................................................................... 187
8-22.3(5) Installation Instructions ............................................................................ 188
8-22.5 Payment .......................................................................................................... 188
8-23 TEMPORARY PAVEMENT MARKINGS ............................................................ 189
8-23.5 Payment .......................................................................................................... 189
9-03.8(7) HMA Tolerances and Adjustments ............................................................ 189
9-05 DRAINAGE STRUCTURES, CULVERTS, AND CONDUITS ............................. 190
9-05.4 Steel Culvert Pipe and Pipe Arch (RC) ......................................................... 190
9-05.7(2) Reinforced Concrete Storm Sewer Pipe (RC) ......................................... 190
9-05.7(2)A Basis for Acceptance (RC) ..................................................................... 190
9-05.7(3) Concrete Storm Sewer Pipe Joints (RC) ................................................. 190
10
9-05.7(4) Testing Concrete Storm Sewer Pipe Joints (RC) .................................... 190
9-05.9 Steel Spiral Rib Storm Sewer Pipe (RC) ...................................................... 191
9-05.12 Polyvinyl Chloride (PVC) Pipe .................................................................... 191
9-05.14 ABS Composite Sewer Pipe ........................................................................ 192
9-05.17 Aluminum Spiral Rib Storm Sewer Pipe .................................................... 192
9-05.24 Polypropylene Culvert Pipe, Polypropylene Storm Sewer Pipe, and
Polypropylene Sanitary Sewer Pipe .......................................................................... 193
9-05.24(1) Polypropylene Culvert Pipe and Storm Sewer Pipe .............................. 193
9-08 PAINTS ............................................................................................................... 194
9-08.8 Manhole Coating System Products .............................................................. 194
9-08.8(1) Coating Systems Specification ................................................................ 194
9-14 EROSION CONTROL AND ROADSIDE PLANTING ......................................... 194
9-14.1(1) Topsoil Type A ........................................................................................... 194
9-14.6(8) Sod .............................................................................................................. 195
9-23 CONCRETE CURING MATERIALS AND ADMIXTURES .................................. 195
9-23.9 Fly Ash (RC) ................................................................................................... 195
9-30 WATER DISTRIBUTION MATERIALS ............................................................... 195
9-30.1 Pipe ............................................................................................................... 195
9-30.1(1) Ductile Iron Pipe .......................................................................................... 195
9-30.1(2) Polyethylene Encasement ........................................................................ 196
9-30.2 Fittings ............................................................................................................ 196
9-30.2(1) Ductile Iron Pipe ........................................................................................ 196
9-30.2(2) Galvanized Iron Pipe ................................................................................. 197
9-30.2(3) Steel Casing Pipe ...................................................................................... 197
9-30.2(4) Spacers and Seals for Steel Casing Pipe ................................................ 197
9-30.2(6) Restrained Joint ........................................................................................ 198
9-30.2(6) Restrained Joint Pipe and Fittings .......................................................... 198
9-30.2(7) Bolted, Sleeve-Type Couplings for Plain End Pipe ................................ 198
9-30.3 Valves ............................................................................................................ 198
9-30.3(1) Gate Valves (3 inches to 16 inches) ......................................................... 199
9-30.3(3) Butterfly Valves .......................................................................................... 199
9-30.3(4) Valve Boxes ................................................................................................ 200
9-30.3(5) Valve Marker Posts .................................................................................... 200
9-30.3(6) Valve Stem Extensions ............................................................................. 200
9-30.3(7) Combination Air Release/Air Vacuum Valves ......................................... 200
11
9-30.3(8) Tapping Sleeve and Valve Assembly ....................................................... 200
9-30.3(9) Blow-Off Assembly .................................................................................... 200
9-30.5 Hydrants ......................................................................................................... 201
9-30.5(1) End Connections ....................................................................................... 201
9-30.5(2) Hydrant Dimensions .................................................................................. 201
9-30.6 Water Service Connections (2 Inches and Smaller) ................................. 202
9-30.6(3) Service Pipes ............................................................................................. 202
9-30.6(3)B Polyethylene Pipe ................................................................................... 202
9-30.6(4) Service Fittings .......................................................................................... 202
9-30.6(5) Meter Setters .............................................................................................. 202
9-30.6(7) Meter Boxes ............................................................................................... 202
10 Removal of Utility Locate Markings From Sidewalks Required ...................... 202
11/4/2020
12
SPECIAL PROVISIONS The work on this project shall be accomplished in accordance with the Standard Specifications for Road, Bridge and Municipal Construction, 2020 edition, as issued by the Washington State Department of Transportation (WSDOT) and the American Public Works Association (APWA), Washington State Chapter (hereafter “Standard Specifications”) The Standard Specifications, as modified or supplemented by the Amendments to the Standard Specifications and these Special Provisions, all of which are made a part of the Contract Documents, shall govern all of the Work. These Special Provisions are made up of both General Special Provisions (GSPs) from various sources, which may have project-specific fill-ins; and project-specific Special Provisions. Each Provision either supplements, modifies, or replaces the comparable Standard Specification, or is a new Provision. The deletion, amendment, alteration, or addition to any subsection or portion of the Standard Specifications is meant to pertain only to that particular portion of the section, and in no way should it be interpreted that the balance of the section does not apply. Also incorporated into the Contract Documents by reference are:
• Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted edition, with Washington State modifications, if any
• Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current edition
• City of Renton Standard Plans, City of Renton Public Works Department, Current Edition
• Public Rights-Of-Way A ccessibility Guidelines (PROWAG), current edition Contractor shall obtain copies of these publications, at Contractor’s own expense.
1-01 DEFINITIONS AND TERMS
1-01.1 General Section 1-01.1 is supplemented with the following: (******) Whenever reference is made to the State, State of Washington, Commission, Department of Transportation, Secretary of Transportation, Owner, Contracting Agency or Engineer, such reference shall be deemed to mean the City of Renton acting through its City Council, employees, and duly authorized representatives for all contracts administered by the City of Renton. All references to “State Materials Laboratory” shall be revised to read “Contracting Agency designated location”.
1-01.3 Definitions Section 1-01.3 is revised and supplemented with the following: (******)
Act of God "Act of God" means an earthquake, flood, cyclone, or other cataclysmic phenomenon of nature. A rain, windstorm, high water or other natural phenomenon of unusual intensity for the specific locality of the Work , which might reasonably have been anticipated from historical records of the general locality of the Work , shall not be construed as an act of God.
11/4/2020
13
Consulting Engineer The Contracting Agency's design consultant, who may or may not administer the construction program for the Contracting Agency.
Contract Documents See definition for “Contract”.
Contract Price Either the unit price, the unit prices, or lump sum price or prices named in the proposal, or in properly executed change orders.
Contract Time The period of time established by the terms and conditions of the Contract within which the Work must be physically completed.
Dates Bid Opening Date: The date on which the Contracting Agency publicly opens and reads the bids. Award Date: The date of the formal decision of the Contracting Agency to accept the lowest responsible and responsive Bidder for the Work . Contract Execution Date: The date the Contracting Agency officially binds the agency to the Contract. Notice to Proceed Date: The date stated in the Notice to Proceed on which the Contract Time begins. Substantial Completion Date: The day the Engineer determines the Contracting Agency has full and unrestricted use and benefit of the facilities, both from the operational and safety standpoint, and only minor incidental Work , replacement of temporary substitute facilities, or correction or repair remains for the physical completion of the total contract. Contract Completion Date: The date by which the Work is contractually required to be physically completed. The Contract Completion Date will be stated in the Notice to Proceed. Revisions of this date will be authorized in writing by the Engineer whenever there is an extension to the Contract time. Completion Date: The day all the Work specified in the Contract is completed and all the obligations of the Contractor under the Contract are fulfilled by the Contractor. Final Acceptance Date: The date the Contracting Agency accepts the Work as complete per the Contract requirements.
Day Unless otherwise designated, day(s) as used in the Contract Documents, shall be understood to mean working days.
Engineer The City Engineer or duly authorized representative, or an authorized member of a licensed consulting firm retained by the Contracting Agency for the construction engineering of a specific public works project.
11/4/2020
14
Inspector The Contracting Agency ’s authorized representative assigned to make necessary observations of the Work performed or being performed, or of materials furnished or being furnished by the Contractor.
Notice of Award: The written notice from the Contracting Agency to the successful bidder signifying the Contracting Agency’s acceptance of the bid.
Notice to Proceed: The written notice from the Contracting Agency or the Engineer to the Contractor authorizing and directing the Contractor to proceed with Work and establishing the date on which the Contract time begins.
Or Equal Where the term "or equal" is used herein, the Contracting Agency, or the Contracting Agency on recommendation of the Engineer, shall be the sole judge of the quality and suitability of the proposed substitution. The responsibility and cost of furnishing necessary evidence, demonstrations, or other information required to obtain the approval of alternative materials or processes by the Contracting Agency shall be entirely borne by the Contractor.
Owner The City of Renton or its authorized representative also referred to as Contracting Agency.
Performance and Payment Bond Same as “Contract Bond” defined in the Standard Specifications.
Plans The Contract Plans and/or Standard Plans which show location, character, and dimensions of prescribed Work including layouts, profiles, cross-sections, and other details. Drawings may either be bound in the same book as the balance of the Contract Documents or bound in separate sets, and are a part of the Contract Documents, regardless of the method of binding. The terms "Standard Drawings" or "Standard Plans" generally used in Specifications refers to drawings bound either with the specification documents or included with the Plans or the City of Renton Standard Plans.
Points Wherever reference is made to the Engineer ’s points, this shall mean all marks, bench marks, reference points, stakes, hubs, tack, etc., established by the Engineer for maintaining horizontal and vertical control of the Work .
Provide Means “furnish and install” as specified and shown in the Plans.
Secretary, Secretary of Transportation The chief executive officer of the Department and other authorized representatives. The chief executive officer to the Department shall also refer to the Department of Public Works Administrator.
Shop Drawings Same as “Working Drawings” defined in the Standard Specifications.
11/4/2020
15
Special Provisions Modifications to the Standard Specifications and their amendments that apply to an individual project. The special provisions may describe Work the Specifications do not cover. Such Work shall comply first with the Special Provisions and then with any Specifications that apply. The Contractor shall include all costs of doing this Work within the bid prices.
State The state of Washington acting through its representatives. The State shall also refer to The City of Renton and its authorized representatives where applicable.
Supplemental Drawings and Instructions Additional instructions by the Engineer at request of the Contractor by means of drawings or documents necessary, in the opinion of the Engineer, for the proper execution of the Work . Such drawings and instructions are consistent with the Contract Documents.
Traffic Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and equestrian traffic.
Utility Public or private fixed improvement for the transportation of fluids, gases, power, signals, or communications and shall be understood to include tracks, overhead and underground wires, cables, pipelines, conduits, ducts, sewers, or storm drains.
1-02 BID PROCEDURES AND CONDITIONS
1-02.1 Prequalification of Bidders Delete this Section and replace it with the following: (******) Bidders shall be qualified by experience, financing, equipment, and organization to do the Work called for in the Contract Documents. The Contracting Agency reserves the right to take whatever action it deems necessary to ascertain the ability of the bidder to perform the Work satisfactorily.
1-02.2 Plans and Specifications Delete this Section and replace it with the following: (******) Information as to where Bid Documents can be obtained or reviewed will be found in the Call for Bids (Advertisement for Bids) for the Work . After award of the Contract, Plans and Specifications will be issued to the Contractor at no cost as detailed below:
To Prime Contractor No. of Sets Basis of Distribution Reduced Plans (11” x 17”) and contract provisions 4 Furnished automatically upon award Large Plans (22” x 34”) 4 Furnished only upon request
11/4/2020
16
Additional Plans and Contract Provisions may be purchased by the Contractor by payment of the cost stated in the Call for Bids.
1-02.4(2) Subsurface Information Section 1-02.4(2) is supplemented with the following: (******) If a geotechnical study was prepared for the project, then the findings and recommendations are summarized in a report that upon request, may be obtained from the City of Renton.
1-02.5 Proposal Forms Delete this Section and replace it with the following: (******) At the request of the bidder, the Contracting Agency will provide a proposal form for any project on which the bidder is eligible to bid. The proposal form will identify the project and its location and describe the Work . It will also list estimated quantities, units of measurement, the items of Work , and the materials to be furnished at the unit bid prices. The bidder shall complete spaces on the proposal form that call for, but are not limited to, unit bid prices; extensions; summations; the total bid amount; signatures; date; and, where applicable, retail sales taxes and acknowledgement of addenda; the bidder’s name, address, telephone number, and signature; and a State of Washington Contractor’s Registration Number. Bids shall be completed by typing or shall be printed in ink by hand, preferably in black ink. The required certifications are included as part of the proposal form. The Contracting Agency reserves the right to arrange the proposal forms with alternates and additives, if such be to the advantage of the Contracting Agency. The bidder shall bid on all alternates and additives set forth in the proposal forms unless otherwise specified. Any correction to a bid made by interlineations, alteration, or erasure, shall be initialed by the signer of the bid. The bidder shall make no stipulation on the Bid Form, nor qualify the bid in any manner. A bid by a corporation shall be executed in the corporate name, by the president or a vice president (Or other corporate officer accompanied by evidence of authority to sign). A bid by a partnership shall be executed in the partnership name and signed by a partner. A copy of the partnership agreement shall be submitted with the Bid Form if any D/M/WBE requirements are to be satisfied through such an agreement. A bid by a joint venture shall be executed in the joint venture name and signed by a member of the joint venture. A copy of the joint venture agreement shall be submitted with the Bid Form if any D/W/MBE requirements are to be satisfied through such an agreement.
1-02.6 Preparation of Proposal Section 1-02.6 is supplemented with the following:
11/4/2020
17
Supplement the second paragraph with the following: (******) 4. If a minimum bid amount has been established for any item, the unit or lump sum price must equal or exceed the minimum amount stated. 5. Any correction to a bid made by interlineation, alteration, or erasure, shall be initialed by the signer of the bid. Delete the last paragraph, and replace it with the following: The Bidder shall make no stipulation on the Bid Form, nor qualify the bid in any manner.
A bid by a corporation shall be executed in the corporate name, by the president or a vice president (or other corporate officer accompanied by evidence of authority to sign).
A bid by a partnership shall be executed in the partnership name and signed by a partner. A copy of the partnership agreement shall be submitted with the Bid Form if any D/M/WBE requirements are to be satisfied through such an agreement.
A bid by a joint venture shall be executed in the joint venture name and signed by a member of the joint venture. A copy of the joint venture agreement shall be submitted with the Bid Form if any D/W/MBE requirements are to be satisfied through such an agreement.
1-02.6(1) Proprietary Information 1-02.6(1) is a new Section. (******) Vendors should, in the bid proposal, identify clearly any material(s), which constitute "(valuable) formula, designs drawings, and research data" so as to be exempt from public disclosure, RCW 42.56.210, or any materials otherwise claimed to be exempt, along with a Statement of the basis for such claim of exemption. The Department (or State) will give notice to the vendor of any request for disclosure of such information received within 5 (five) years from the date of submission. Failure to so label such materials or failure to timely respond after notice of request for public disclosure has been given shall be deemed a waiver by the submitting vendor of any claim that such materials are, in fact, so exempt.
1-02.7 Bid Deposit Section 1-02.7 is supplemented with the following: (******) Bid Bonds shall contain the following: 1. Number assigned to the project by the Contracting Agency; 2. Name of the project; 3. The Contracting Agency named as obligee; 4. The amount of the bid bond stated either as a dollar figure or as a percentage which represents five percent of the maximum bid amount that could be awarded; 5. Signature of the bidder’s officer empowered to sign official statements. The signature of the person authorized to submit the bid should agree with the signature on the bond, and the title of the person must accompany said signature; 6. The signature of the surety’s officer empowered to sign the bond form included in the Contract Provision.
11/4/2020
18
1-02.9 Delivery of Proposal Replace first paragraph with: (******) Each proposal shall be submitted in a sealed envelope, with Project Name and Project Number clearly marked on the outside of the envelope as stated in the Call for Bids, or as otherwise stated in the Bid Documents.
1-02.12 Public Opening of Proposals Section 1-02.12 is supplemented with the following: (******) The Contracting Agency reserves the right to postpone the date and time for bid opening. Notification to bidder will be by addenda.
1-02.13 Irregular Proposals Revise item 1 to read: (******) 1. A proposal will be considered irregular and will be rejected if: a. The bidder is not prequalified when so required; b. The authorized proposal form furnished by the Contracting Agency is not used or is altered; c. The complete proposal form contains any unauthorized additions, deletions, alternate bids, or conditions; d. The bidder adds provisions reserving the right to reject or accept the award, or enter into the Contract; e. A price per unit cannot be determined from the bid proposal; f. The proposal form is not properly executed; g. The bidder fails to submit or properly complete a subcontractor list, if applicable, as required in Section 1-02.6 h. The bidder fails to submit or properly complete a Disadvantaged, Minority or Women’s Business Enterprise Certification, if applicable, as required in Section 1-02.6; or i. The bid proposal does not constitute a definite and unqualified offer to meet the material terms of the bid invitation. j. More than one proposal is submitted for the same project from a Bidder under the same or different names.
1-02.14 Disqualification of Bidders Delete this section in its entirety and replace with the following: (******) 1. A bidder will be deemed not responsible and the proposal rejected if the bidder does not meet the responsibility criteria in RCW 39.04. 2. A bidder may be deemed not responsible and the proposal rejected if: a. More than one proposal is submitted for the same project from a bidder under the same or different names; b. Evidence of collusion exists with any other bidder or potential bidder. Participants in collusion will be restricted from submitting further bids; c. The bidder, in the opinion of the Contracting Agency, is not qualified for the Work or to the full extent of the bid, or to the extent that the bid exceeds the authorized
11/4/2020
19
prequalification amount as may have been determined by a prequalification of the bidder; d. An unsatisfactory performance record exists based on past or current Contracting Agency Work or for Work done for others, as judged from the standpoint of conduct of the Work ; workmanship; progress; affirmative action; equal employment opportunity practices; or Disadvantaged Enterprise, Minority Enterprise, or Women’s Business Enterprise utilization. e. There is uncompleted Work (Contracting Agency or otherwise) which might hinder or prevent the prompt completion of the Work bid upon; f. The bidder failed to settle bills for labor or materials on past or current contracts; g. The bidder has failed to complete a written public contract or has been convicted of a crime arising from a previous public contract; h. The bidder is unable, financially or otherwise, to perform the Work ; i. A bidder is not authorized to do business in the State of Washington (not registered in accordance with RCW 18.27) j. There are any other reasons deemed proper by the Contracting Agency.
1-02.15 Pre Award Information Revise this section to read: (******) Before awarding any contract, the Contracting Agency may require one or more of these items or actions of: 1. A complete statement of the origin, composition, and manufacture of any or all materials to be used; 2. Samples of these materials for quality and fitness tests; 3. A progress schedule (in a form the Contracting Agency requires) showing the order of time required for the various phases of Work ; 4. A breakdown of costs assigned to any bid item; 5. Attendance at a conference with the Engineer or representatives of the Engineer; 6. Obtain, and furnish a copy of, a business license to do business in the city and/or county where the Work is located; 7. A copy of State of Washington Contractor’s Registration; or 8. Any other information or action taken that is deemed necessary to ensure that the bidder is the lowest responsible bidder.
1-03 AWARD AND EXECUTION OF CONTRACT
1-03.1 Consideration of bids Section 1-03.1 is supplemented with the following: (******) All bids will be based on total sum of all schedules of prices. No partial bids will be accepted unless so stated in the call for bids or special provisions. The City reserves the right to award all or any schedule of a bid to the lowest bidder at its discretion.
11/4/2020
20
1-03.2 Award of Contract Section 1-03.2 is supplemented with the following: (******) The Contract, bond form, and all other forms requiring execution, together with a list of all other forms or documents required to be submitted by the successful bidder, will be forwarded to the successful bidder within 10 days of the award. The number of copies to be executed by the Contractor shall be determined by the Contracting Agency.
1-03.3 Execution of Contract Section 1-03.3 is revised and supplemented with the following: (******) Within 10 calendar days after receipt from the City of the forms and documents required to be completed by the Contractor, the successful bidder shall return the signed Contracting Agency-prepared contract, an insurance certification as required by Section 1-07.18, and a satisfactory bond as required by law and Section 1-03.4. Before execution of the Contract by the Contracting Agency, the successful bidder shall provide any pre-award information the Contracting Agency may require under Section 1-02.15. Until the Contracting Agency executes a contract, no proposal shall bind the Contracting Agency nor shall any Work begin within the project limits or within Contracting Agency-furnished sites. The Contractor shall bear all risks for any Work begun outside such areas and for any materials ordered before the Contract is executed by the Contracting Agency. If the bidder experiences circumstances beyond their control that prevents return of the Contract documents within 10 calendar days after the award date, the Contracting Agency may grant up to a maximum of 10 additional calendar days for return of the documents, provided the Contracting Agency deems the circumstances warrant it. The Contracting Agency is prohibited by RCW 39.06.010 from executing a contract with a Contractor who is not registered or licensed as required by the laws of the state. In addition, the Contracting Agency requires persons doing business with the Contracting Agency to possess a valid City of Renton business license prior to award. When the Bid Form provides spaces for a business license number, a Washington State Contractors registration number, or both, the Bidder shall insert such information in the spaces provided. The Contracting Agency requires legible copies of the Contractor's Registration and business license be submitted to the Engineer as part of the Contracting Agency's post-award information and evaluation activities.
1-03.4 Contract Bond Revise the first paragraph to read: (******) The successful bidder shall provide an executed contract bond for the full contract amount. This contract bond shall: 1. Be on the Contracting Agency-furnished form; 2. Be signed by an approved surety (or sureties) that: a. Is registered with the Washington State Insurance Commissioner, and
11/4/2020
21
b. Appears on the current Authorized Insurance List in the State of Washington published by the Office of the Insurance Commissioner; 3. Be conditioned upon the faithful performance of the Contract by the Contractor within the prescribed time; 4. Guarantee that the surety shall indemnify, defend, and protect the Contracting Agency against any claim of direct or indirect loss resulting from the failure: a. Of the Contractor (or any of the employees, subcontractors, or lower tier subcontractors of the Contractor) to faithfully perform the Contract, or b. Of the Contractor (subcontractors, or lower tier subcontractors of the Contractor) to pay all laborers, mechanics, subcontractors, lower tier subcontractors, material person, or any other person who provides supplies or provisions for carrying out Work ; 5. Be accompanied by a power of attorney for the Surety’s officer empowered to sign the bond; and 6. Be signed by an officer of the Contractor empowered to sign official statements (sole proprietor or partner). If the Contractor is a corporation, the bond must be signed by the president or vice-president, unless accompanied by a written proof of the authority of the individual signing the bond to bind the corporation (i.e., corporate resolution, power of attorney or a letter to such effect by the president or vice-president).
1-03.7 Judicial Review Revise the last sentence to read: (******) The venue of all causes of action arising from the advertisement, award, execution, and performance of the Contract shall be in the Superior Court of the County where the Contracting Agency’s headquarters are located.
1-04 SCOPE OF WORK
1-04.2 Coordination of Contract Documents, Plans, Special Provisions Specifications, and
Addenda Revise the second paragraph to read: (******) Any inconsistency in the parts of the Contract shall be resolved by following this order of precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth): 1. Addenda 2. Proposal Form 3. Special Provisions 4. Contract Plans 5. Contracting Agency’s Standard Plans (if any) 6. Amendments to the Standard Specifications 7. WSDOT/APWA Standard Specifications for Road, Bridge and Municipal Construction 8. WSDOT/APWA Standard Plans for Road, Bridge and Municipal Construction
11/4/2020
22
1-04.8 Progress Estimates and Payments Section 1-04.8 is supplemented with the following: (******) Prior to progress payments, the Contractor is encouraged to provide to the Engineer an estimate of “Lump Sum” Work accomplished to date. The Engineer's calculations and decisions shall be final in regard to the actual percentage of any lump sum pay item accomplished and eligible for payment unless another specific method of calculating lump sum payments is provided elsewhere in the Specifications.
1-04.11 Final Cleanup Section 1-04.11 is supplemented with the following: (******) All salvage material as noted on the Plans and taken from any of the discarded facilities shall, at the Engineer's discretion, be carefully salvaged and delivered to the City shops. Any cost incurred in salvaging and delivering such items shall be considered incidental to the project and no compensation will be made. The Contract price for "Finish and Cleanup, Lump Sum," shall be full compensation for all Work, equipment and materials required to perform final cleanup. If this pay item does not appear in the Contract Documents then final cleanup shall be considered incidental to the Contract and to other pay item and no further compensation shall be made.
1-04.12 Contractor-Discovered Discrepancies Section 1-04.12 is a new section: (******) Upon receipt of award of contract, the Contractor shall carefully study and compare all the components of the Contract Documents and other instructions, and check and verify all field measurements. The Contractor shall, prior to ordering material or performing Work, report in writing to the Engineer any error, inconsistency, or omission with respect to design or mode of construction, which is discovered. If the Contractor, in the course of this study or in the accomplishment of the Work, finds any discrepancy between the Plans and the physical condition of the locality as represented in the Plans, or any such errors or omissions with respect to design or mode of construction in the Plans or in the layout as given by points and instructions, it shall be the Contractor’s duty to inform the Engineer immediately in writing, and the Engineer will promptly check the same. Any Work done after such discovery, until correction of Plans or authorization of extra Work is given, if the Engineer finds that extra Work is involved, will be done at the Contractor's risk. If extra Work is involved, the procedure shall be as provided in Section 1-04.4 of the Standard Specifications.
1-05 CONTROL OF WORK
1-05.4 Conformity With and Deviation from Plans and Stakes Section 1-05.4 is supplemented with the following: (******) If the project calls for the Contractor supplied surveying, the Contractor shall provide all required survey Work, including such Work as mentioned in Sections 1-05, 1-11 and elsewhere in these
11/4/2020
23
Specifications as being provided by the Engineer. All costs for this survey Work shall be included in "Contractor Supplied Surveying," per lump sum. The Engineer or the Contractor supplied surveyor will provide construction stakes and marks establishing lines, slopes, and grades as stipulated in this section and will perform such Work per Section 1-11. The Contractor shall assume full responsibility for detailed dimensions, elevations, and excavation slopes measured from the Engineer or the Contractor supplied surveyor furnished stakes and marks. The Contractor shall provide a work site, which has been prepared to permit construction staking to proceed in a safe and orderly manner. The Contractor shall keep the Engineer or the Contractor supplied surveyor informed of staking requirements and provide at least 48 hour notice to allow the Engineer or the Contractor supplied surveyor adequate time for setting stakes. The Contractor shall carefully preserve stakes, marks, and other reference points, including existing monumentation, set by Contracting Agency forces. The Contractor will be charged for the costs of replacing stakes, markers and monumentation that were not to be disturbed but were destroyed or damaged by the Contractor's operations. This charge will be deducted from monies due or to become due to the Contractor. Any claim by the Contractor for extra compensation by reason of alterations or reconstruction Work allegedly due to error in the Engineer's line and grade, will not be allowed unless the original control points set by the Engineer still exist, or unless other satisfactory substantiating evidence to prove the error was furnished by the Engineer. Three consecutive points set on line or grade shall be the minimum points used to determine any variation from a straight line or grade. Any such variation shall, upon discovery, be reported to the Engineer. In the absence of such report the Contractor shall be liable for any error in alignment or grade. The Contractor shall provide all surveys required other than those to be performed by the Engineer. All survey Work shall be done in accordance with Section 1-11 SURVEYING STANDARDS of these Specifications. The Contractor shall keep updated survey field notes in a standard field book and in a format set by the Engineer, per Section 1-11.1(4). These field notes shall include all survey Work performed by the Contractor's surveyor in establishing line, grade and slopes for the construction Work. Copies of these field notes shall be provided to the Engineer upon request and upon completion of the Contract Work the field book or books shall be submitted to the Engineer and become the property of the Contracting Agency. If the survey Work provided by the Contractor does not meet the standards of the Engineer, then the Contractor shall, upon the Engineer's written request, remove the individual or individuals doing the survey Work and the survey Work will be completed by the Engineer at the Contractor's expense. Costs for completing the survey Work required by the Engineer will be deducted from monies due or to become due the Contractor. All costs for survey Work required to be performed by the Contractor shall be included in the prices bid for the various items which comprise the improvement or be included in the bid item for "Contractor Supplied Surveying" per lump sum if that item is included in the contracts.
11/4/2020
24
1-05.4(1) Contractor Supplied Surveying Section 1-05.4(1) is a new section: (******) When the Contract provides for Contractor Supplied Surveying, the Contractor shall supply the survey Work required for the project. The Contractor shall retain as a part of the Contractor Organization an experienced team of surveyors under the direct supervision of a professional land surveyor licensed by the State of Washington. All survey Work shall be done in accordance with Sections 1-05.4 and 1-11. The Contractor and/or the Surveyor shall inform the Engineer in writing of any errors, discrepancies, and omissions to the Plans that prevent the Contractor and/or the Surveyor from constructing the project in a manner satisfactory to the Engineer. All errors, discrepancies, and omissions must be corrected to the satisfaction of the Engineer before the survey Work may be continued. The Contractor shall coordinate his Work with the Surveyor and perform his operations in a manner to protect all survey stakes from harm. The Contractor shall inform the Surveyor of the Contractor's intent to remove any survey stakes and/or points before physically removing them. The Surveyor shall be responsible for providing As-Built Information for the project. The Contractor shall coordinate his operations and assist the Surveyor in maintaining accurate As-Built Information for the project. If the Contractor and the Surveyor fail to provide, as directed by the Engineer and/or these Plans and Specifications, accurate As-Built Information and other Work the Engineer deems necessary, the Engineer may elect to provide at Contractor expense, a surveyor to provide all As-Built Information and other Work as directed by the Engineer. The Engineer shall deduct expenses incurred by the Engineer-supplied surveying from monies owed to the Contractor. Payment per Section 1-04.1 for all Work and materials required for the full and complete survey Work required to complete the project and provide As-Built Information shall be included in the lump sum price for "Construction Surveying, Staking, and As-Built Information."
1-05.4(2) Contractor Provided As-Built Information Section 1-05.4(2) is a new section: (******) Prior to the backfilling of the trenches It shall be the Contractors responsibility to record the location, by centerline station, offset, and depth below pavement, of all existing utilities uncovered or crossed during his Work as covered under this project. It shall be the Contractor’s responsibility to have his Surveyor locate each major item of Work done under this contract per the survey standard of Section 1-11. Major items of Work shall include but not be limited to: Manholes, Catch basins and Inlets, Valves, vertical and Horizontal Bends, Junction boxes, Cleanouts, Side Sewers, Street Lights & Standards, Hydrants, Major Changes in Design Grade, Vaults, Culverts, Signal Poles, and Electrical Cabinets. After the completion of the Work covered by this contract, the Contractor’s Surveyor shall provide to the City electronic files , both AutoCad and pdf files of the project drawings, containing the surveyor’s
11/4/2020
25
as-built information and one set of white prints of the project drawings upon which he has plotted the notes of the Contractor locating existing utilities. This drawing shall bear the Surveyor’s seal and signature certifying its accuracy. All costs for as-built Work shall be included in the Contract item "Construction Surveying, Staking, and As-Built Information", lump sum.
1-05.7 Removal of Defective and/or Unauthorized Work Section 1-05.7 is supplemented with the following: (******) Upon written notice from the Engineer, the Contractor shall promptly replace and re-execute Work by Contractor forces, in accordance with the intent of the Contract and without expense to the Contracting Agency, and shall bear the expense of making good all Work of other contractors destroyed or damaged by such removal or replacement. If the Contractor does not remove such condemned Work and materials and commence re-execution of the Work within 7 calendar days of written notice from the Engineer, or fails to perform any part of the Work required by the Contract Documents, the Contracting Agency may correct and remedy such Work as may be identified in the written notice, with Contracting Agency forces or by such other means as the Contracting Agency may deem necessary. In that case, the Contracting Agency may store removed material. Direct or indirect costs incurred by the Contracting Agency attributable to correcting and remedying defective or unauthorized Work , or Work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from monies due, or to become due, the Contractor. Such direct and indirect costs shall include in particular, but without limitation, compensation for additional professional services required, and costs for repair and replacement of Work of others destroyed or damaged by correction, removal, or replacement of the Contractor’s unauthorized Work . If sufficient funds do not remain in the Contract and the Contractor does not pay the cost of such removal and storage within 10 calendar days from the date of the notice to the Contractor of the fact of such removal, the Contracting Agency may, upon an additional 10 calendar days written notice, sell such materials at public or private sale, and deduct all costs and expenses incurred from monies due to the Contractor, including costs of sale, and accounting to Contractor for the net proceeds remaining. The Contracting Agency may bid at any such sale. The Contractor shall be liable to the Contracting Agency for the amount of any deficiency from any funds otherwise due the Contractor. If the Contractor fails to comply with a written order to remedy what the Engineer determines to be an emergency situation, the Engineer may have the defective and unauthorized Work corrected immediately, have the rejected Work removed and replaced, or have Work the Contractor refuses to perform completed by using Contracting Agency or other forces. An emergency situation is any situation when, in the opinion of the Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk of loss or damage to the public, the Property Owner and the Property Owner’s property.
11/4/2020
26
No adjustment in contract time or compensation will be allowed because of the delay in the performance of the Work attributable to the exercise of the Contracting Agency’s rights provided by this section. The rights exercised under the provisions of this section shall not diminish the Contracting Agency’s right to pursue any other avenue for additional remedy or damages with respect to the Contractor’s failure to perform the Work as required.
1-05.10 Guarantees Section 1-05.10 is supplemented with the following: (******) If within one year after the Acceptance Date of the Work by the Contracting Agency, defective and/or unauthorized Work is discovered, the Contractor shall promptly, upon written order by the Contracting Agency, return and in accordance with the Engineer’s instructions, either correct such Work , or if such Work has been rejected by the Engineer, remove it from the project site and replace it with non-defective and authorized Work , all without cost to the Contracting Agency. If the Contractor does not promptly comply with the written order to correct defective and/or unauthorized Work , or if an emergency exists, the Contracting Agency reserves the right to have defective and/or unauthorized Work corrected or removed and replaced pursuant to Section 1-05.7 “Removal of Defective and/or Unauthorized Work.” The Contractor agrees the above one year limitation shall not exclude or diminish the Contracting Agency’s rights under any law to obtain damages and recover costs resulting from defective and/or unauthorized Work discovered after one year but prior to the expiration of the legal time period set forth in RCW 4.16.040. The Contractor shall warrant good title to all materials, supplies, and equipment purchased for, or incorporated in the Work . Nothing contained in this paragraph, however, shall defeat or impair the right of persons furnishing materials or labor, to recover under any bond given by the Contractor for their protection, or any rights under any law permitting such persons to look to funds due the Contractor in the hands of the Contracting Agency. The provisions of this paragraph shall be inserted in all subcontracts and material contracts, and notice of its provisions shall be given to all persons furnishing materials for the Work when no formal contract is entered into for such materials.
1-05.11 Final Inspection
1-05.11(1) Substantial Completion Date Section 1-05.11(1) is a new section: (******) When the Contractor considers the Work to be substantially complete, the Contractor shall so notify the Engineer and request the Engineer establish the Substantial Completion Date. The Engineer will schedule an inspection of the Work with the Contractor to determine the status of completion.
11/4/2020
27
To be considered substantially complete the following conditions must be met: 1. The Contracting Agency must have full and unrestricted use and benefit of the facilities both from the operational and safety standpoint. 2. Only minor incidental Work, replacement of temporary substitute facilities, or correction of repair Work remains to reach physical completion of the Work . The Contractor’s request shall list the specific items of Work in subparagraph two above that remains to be completed in order to reach physical completion. The Engineer may also establish the Substantial Completion Date unilaterally. If after this inspection, the Engineer concurs with the Contractor that the Work is substantially complete and ready for its intended use, the Engineer, by written notice to the Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer does not consider the Work substantially complete and ready for its intended use, the Engineer will, by written notice, so notify the Contractor giving the reasons therefore. Upon receipt of written notice concurring with or denying substantial completion, whichever is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized interruption, the Work necessary to reach Substantial and Physical Completion. The Contractor shall provide the Engineer with a revised schedule indicating when the Contractor expects to reach substantial and physical completion of the Work. The above process shall be repeated until the Engineer establishes the Substantial Completion Date and the Contractor considers the Work physically complete and ready for Final Inspection.
1-05.11(2) Final Inspection and Physical Completion Date Section 1-05.11(2) is a new Section: (******) When the Contractor considers the Work physically complete and ready for Final Inspection, the Contractor, by Written Notice, shall request the Engineer to schedule a final inspection. The Engineer will set a date for Final Inspection. The Engineer and the Contractor will then make a final inspection and the Engineer will notify the Contractor in writing of all particulars in which the Final Inspection reveals the Work incomplete or unacceptable. The Contractor shall immediately take such corrective measures as are necessary to remedy the listed deficiencies. Corrective Work shall be pursued vigorously, diligently, and without interruption until physical completion of the listed deficiencies. This process will continue until the Engineer is satisfied the listed deficiencies have been corrected. If action to correct the listed deficiencies is not initiated within 7 days after receipt of the Written Notice listing the deficiencies, the Engineer may, upon Written Notice to the Contractor, take whatever steps are necessary to correct those deficiencies pursuant to Section 1-08.5. The Contractor will not be allowed an extension of contract time because of a delay in the performance of the Work attributable to the exercise of the Engineer’s right hereunder. Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting Agency, in writing, of the date upon which the Work was considered physically complete, that date shall constitute the Physical Completion Date of the Contract, but shall not imply all the obligations of the Contractor under the Contract have been fulfilled.
11/4/2020
28
1-05.11(3) Operational Testing Section 1-05.11(3) is a new section: (******) Unless otherwise noted in the Contract Documents, the Contractor shall give the Engineer a minimum of 3 working days’ notice of the time for each test and inspection. If the inspection is by another authority than the Engineer, the Contractor shall give the Engineer a minimum of 3 working days’ notice of the date fixed for such inspection. Required certificates of inspection by other authority than the Engineer shall be secured by the Contractor. It is the intent of the Contracting Agency to have at the Physical Completion Date a complete and operable system. Therefore, when the Work involves the installation of machinery or other mechanical equipment; street lighting, electrical distribution or signal systems; irrigation systems; buildings; or other similar Work , it may be desirable for the Engineer to have the Contractor operate and test the Work for a period of time, after final inspection but prior to the physical completion date. Whenever items of Work are listed in the Contract Provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Physical Completion Date. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment which prove faulty, or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer. The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing, shall be included in the unit contract prices related to the system being tested, unless specifically set forth otherwise in the proposal. Operational and test periods, when required by the Engineer, shall not affect a manufacturer’s guaranties or warranties furnished under the terms of the Contract.
1-05.12 Final Acceptance The third and fourth sentences in paragraph 1 are deleted and replaced with: (******) The Final Acceptance date shall be that date in which the Renton City Council formally approves acceptance of the Work .
1-05.13 Superintendents, Labor and Equipment of Contractor Revise the last paragraph to read: (******) Whenever the Contracting Agency evaluates the Contractor’s qualifications pursuant to Section 1-02.1, the Contracting Agency will take these performance reports into account.
11/4/2020
29
1-05.14 Cooperation with Other Contractors Section 1-05.14 is supplemented with the following: (******) The Contractor shall afford the Contracting Agency and other contractors working in the area reasonable opportunity for the introduction and storage of their materials and the execution of their respective Work , and shall properly connect and coordinate the Contractor’s Work with theirs. Other utilities, districts, agencies, and contractors who may be working within the project area may include, but are not limited to: 1. Puget Sound Energy (gas and electric) 2. AT&T Broadband 3. CenturyLink 4. City of Renton (water, wastewater, surface water, transportation) 5. Comcast 6. Seattle Public Utilities 7. Soos Creek Sewer and Water District 8. Cedar River Sewer and Water District 9. Skyway Sewer and Water District 10. Coal Creek Sewer and Water District 11. Water District 90 12. Olympic Pipeline 13. Private contractors employed by adjacent property owners
1-05.16 Water and Power Section 1-05.16 is a new Section: (******) The Contractor shall make necessary arrangements and shall bear the costs for power and water necessary for the performance of the Work , unless the Contract includes power and water as a pay item.
1-05.17 Oral Agreements Section 1-05.17 is a new section: (******) No oral agreement or conversation with any officer, agent, or employee of the Contracting Agency, either before or after execution of the Contract, shall affect or modify any of the terms or obligations contained in any of the documents comprising the Contract. Such oral agreement or conversation shall be considered as unofficial information and in no way binding upon the Contracting Agency, unless subsequently put in writing and signed by the Contracting Agency.
1-05.18 Contractor's Daily Diary Section 1-05.18 is a new section: (******) The Contractor and subcontractors shall maintain and provide to the Engineer a Daily Diary Record of this Work. This diary will be created by pen entries in a hardbound diary book of the type that is commonly available through commercial outlets, or in a commonly-accepted electronic format. The diary must contain the Project and Number; if the diary is in loose-leaf form, this information must appear on every page. The diary must be kept and maintained by the Contractor's designated project
11/4/2020
30
superintendent(s). Entries must be made on a daily basis and must accurately represent all of the project activities on each day. At a minimum, the diary shall show on a daily basis: 1. The day and date. 2. The weather conditions, including changes throughout the day. 3. A complete description of Work accomplished during the day with adequate references to the Plans and Contract Provisions, so that the reader can easily and accurately identify said Work in the Plans. Identify location/description of photographs or videos taken that day. 4. An entry for each and every changed condition, dispute or potential dispute, incident, accident, or occurrence of any nature whatsoever which might affect the Contractor, the Contracting Agency, or any third party in any manner. 5. Listing of any materials received and stored on or off-site by the Contractor for future installation, to include the manner of storage and protection of the same. 6. Listing of materials installed during each day. 7. List of all subcontractors working on-site during each day. 8. Listing of the number of the Contractor's employees working during each day by category of employment. 9. Listing of the Contractor's equipment working on the site during each day. Idle equipment on the site shall be listed and designated as idle. 10. Notations to explain inspections, testing, stake-out, and all other services furnished by the Contracting Agency or other party during each day. 11. Entries to verify the daily (including non-Work days) inspection and maintenance of traffic control devices and condition of the traveled roadway surfaces. The Contractor shall not allow any conditions to develop that would be hazardous to the public. 12. Any other information that serves to give an accurate and complete record of the nature, quantity, and quality of Contractor's progress on each day. 13. Plan markups showing locations and dimensions of constructed features to be used by the Engineer to produce record drawings. 14. All pages of the diary must be numbered consecutively with no omissions in page numbers. 15. Each page must be signed and dated by the Contractor's official representative on the project. The Contractor may use additional sheets separate from the diary book, if necessary, to provide a complete diary record, but they must be signed, dated, and labeled with project name and number.
It is expressly agreed between the Contractor and the Contracting Agency that the Daily Diary
maintained by the Contractor shall be the “Contractor's Book of Original Entry” for the
documentation of any potential claims or disputes that might arise during this contract. Failure of
the Contractor to maintain this diary in the manner described above will constitute a waiver of any
such claims or disputes by the Contractor. The Engineer or other Contracting Agency’s representative on the job site will also complete a Daily Construction Report.
11/4/2020
31
1-06 CONTROL OF MATERIAL
1-06.1 Approval of Materials Prior to Use Section 1-06.1 is supplemented with the following: (******) The materials and equipment lists submitted to the Engineer at the Preconstruction Conference shall include the quantity, manufacturer, and model number, if applicable, of materials and equipment to be installed under the Contract. This list will be checked by the Engineer as to conformity with the Contract Documents. The Engineer will review the lists within 10 working days, noting required corrections. The Contractor shall make required corrections and file 2 corrected copies with the Engineer within one week after receipt of required corrections. The Engineer's review and acceptance of the lists shall not relieve the Contractor from responsibility for suitability for the intended purpose, nor for deviations from the Contract Documents.
1-06.2(1) Samples and Tests for Acceptance Section 1-06.2(1) is supplemented with the following: (******) The finished Work shall be in accordance with approved samples. Approval of samples by the Engineer does not relieve the Contractor of responsibility for performance of the Work in accordance with the Contract Documents.
1-06.2(2) Statistical Evaluation of Materials for Acceptance Section 1-06.2(2) is supplemented by with the following: (******) Unless stated otherwise in the special provisions, statistical evaluation will not be used by the City of Renton.
1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC
1-07.1 Laws to be Observed Section 1-07.1 is supplemented with the following: (******) The Contractor shall erect and properly maintain, at all times, as required by the conditions and progress of the Work , all necessary safeguards for protection of workers and the public; shall post danger signs warning against known or unusual hazards; and shall designate as Safety Supervisor, a responsible employee on the construction site whose duty shall be the enforcement of safety. The name and position of such person so designated shall be reported in writing to the Engineer by the Contractor. The Contractor shall, at all times, enforce strict discipline and good order among all employees and shall not employ any person unfit or not skilled in the Work assigned to him/her. Necessary sanitation conveniences for the use of the workers on the job, properly secluded from public observation, shall be provided and maintained by the Contractor. In cases of conflict between different safety regulations, the more stringent regulation shall apply.
11/4/2020
32
The Washington State Department of Labor and Industries shall be the sole and paramount administrative agency responsible for the administration of the provisions of the Washington Industrial Safety and Health Act of 1973 (WISHA). The Contractor shall maintain at the project site office, or other well-known place at the project site, all articles necessary for providing first aid to the injured. The Contractor shall establish, publish, and make known to all employees, procedures for ensuring immediate removal to a hospital or doctor’s care, and persons, including employees, who may have been injured on the project site. Employees should not be permitted to Work on the project site before the Contractor has established and made known procedures for removal of injured persons to a hospital or a doctor’s care. The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of the Contractor’s plant, appliances, and methods, and for any damage or injury resulting from their failure, or improper maintenance, use, or operation. The Contractor shall be solely and completely responsible for the conditions of the project site, including safety for all persons and property in the performance of the Work . This requirement shall apply continuously, and not be limited to normal working hours. The required or implied duty of the Engineer to conduct construction review of the Contractor’s performance does not, and shall not, be intended to include review and adequacy of the Contractor’s safety measures, in, on, or near the project site.
1-07.6 Permits and Licenses Section 1-07.6 is supplemented with the following: (******) The Contractor shall ensure that all necessary permits are obtained, and is responsible for reviewing all permits to become familiar with the requirements. The Contractor and all subcontractors of any tier must obtain a City of Renton Business License (Contractor). The permits, easements, and right of entry documents that have been acquired are available for inspection and review. The Contractor shall be required to comply with all conditions of the permits, easements, and rights of entry, at no additional cost to the Contracting Agency. The Contractor is required to indemnify the Contracting Agency from claims on all easements and rights of entry. All other permits, licenses, etc., shall be the responsibility of the Contractor. The Contractor shall comply with the special provisions and requirements of each. Permits, permission under franchises, licenses and bonds of a temporary nature necessary for and during the prosecution of the Work , and inspection fees in connection therewith shall be secured and paid for by the Contractor. If the Contracting Agency is required to secure such permits, permission under franchises, licenses and bonds, and pay the fees, the costs incurred by the Contracting Agency thereby shall be charged against the Contractor and deducted from any funds otherwise due the Contractor.
11/4/2020
33
The Contractor is cautioned to review all permits and other Contract Documents and schedule the work activities appropriately to complete the work within the number of days stated in the Contract Document. No additional compensation or extensions to time will be granted to the Contractor due to the time constraints imposed by such documents. The Contractor shall assume all responsibility for meeting all requirements of all permits. Any fines or penalties incurred by Contracting Agency for not meeting state water quality standards and/or lack of stormwater pollution prevention on this Project shall be deducted from monies otherwise due to Contractor. Any fines assessed directly to Contractor shall be paid directly to the fining authority, at the Contractor’s own cost.
1-07.9 Wages
1-07.9(5) Required Documents Delete the first sentence of the third paragraph, and replace it with the following: (******) The Contractor must submit weekly-certified payrolls for the Contractor and all subcontractors and lower tier subcontractors, regardless of project’s funding source.
1-07.11 Requirements for Non-Discrimination
1-07.11(11) City of Renton Affidavit of Compliance Section 1-07.11(11) is a new section: (******) Each Contractor, Subcontractor, Consultant, and or Supplier shall complete and submit a copy of the “City of Renton Fair Practices Policy Affidavit of Compliance”. A copy of this document will be bound in the bid documents.
1-07.12 Federal Agency Inspection Section 1-07.12 is supplemented with the following: (******)
Required Federal Aid Provisions The Required Contract Provisions Federal Aid Construction Contracts (FHWA 1273) and the amendments thereto supersede any conflicting provisions of the Standard Specifications and are made a part of this contract; provided, however, that if any of the provisions of FHWA 1273, as amended, are less restrictive than Washington State Law, then the Washington State Law shall prevail. The provisions of FHWA 1273, as amended, included in this contract require that the Contractor insert the FHWA 1273 and amendments thereto in each subcontract, together with the wage rates which are part of the FHWA 1273, as amended. Also, a clause shall be included in each subcontract requiring the subcontractors to insert the FHWA 1273 and amendments thereto in any lower tier subcontracts, together with the wage rates. The Contractor shall also ensure that this Section, REQUIRED FEDERAL AID PROVISIONS, is inserted in each subcontract for subcontractors and lower tier subcontractors. For this purpose, upon request to the Project Engineer, the Contractor will be provided with extra copies of the FHWA 1273, the amendments thereto, the applicable wage rates, and this Special Provision.
11/4/2020
34
1-07.13 Contractor’s Responsibility for Work
1-07.13(1) General Section 1-07.13(1) is supplemented with the following: (******) During unfavorable weather and other conditions, the Contractor shall pursue only such portions of the Work as shall not be damaged thereby. No portion of the Work whose satisfactory quality or efficiency will be affected by unfavorable conditions shall be constructed while these conditions exist, unless the Contractor shall be able to overcome said unfavorable conditions by special means or precautions acceptable to the Engineer.
1-07.15 Temporary Water Pollution Prevention Delete this section in its entirety and replace with the following: (******) The Contractor shall perform all Work in strict accordance with all Federal, State, and local laws and regulations governing waters of the State, as well as permits acquired for the project. The Contractor shall prepare a final Temporary Water Pollution/Erosion Control Plan (TWPECP) and a final SWPPP. The TWPECP and SWPPP shall be developed in accordance with the erosion control standards contained in the Current City of Renton Surface Water Design Manual. The plan shall include any assumptions, detailed calculations, sketches and sequencing. The plan shall be signed and stamped by a Washington State Professional Engineer. A TESC supervisor shall be designated by the Contractor, whose name and phone number shall be given to the Engineer at the Preconstruction Conference. The TESC supervisor must be CESCL certified in accordance with NPDES permit requirements. The plan shall be submitted for approval to the City within 10 days of the Notice of Award. The TWPECP shall include the various configurations that may be necessary to adequately control erosion and sediment at the site during the various stages of construction. Design of dewatering, water control, bypass systems, and temporary erosion and sediment control during construction shall be the responsibility of the Contractor. At a minimum, the plan shall contain: 1. Manufacturer’s data and detailed plans for the erosion control products specified in the plan. 2. Plan for temporary pipe system diversions. This shall include a description of when the piping will be used, pipe material, locations, elevations, plan and profile views, inlet and outlet protection, hydraulic capacity, and details of important design features. 3. Plan for collecting, pumping and pipe surface stormwater runoff, dewatering discharge, and seepage from the source to the Baker Tank or acceptable discharge. The plan shall be shown in phases to coincide with the phases of construction. The plan shall include: a. Layout and details of system. b. Diversion systems manufacturer’s data and material submittals. c. Pump and pipe types, sizes, manufacturer’s data, and design criteria for pump sizing.
11/4/2020
35
d. Flow calculations for stormwater, seepage, and dewatering pump discharge. Schedule and sketch of location for dewatering systems. Pumps shall be sized to pump stormwater runoff for the tributary area plus an allowance for groundwater and surface seepage. Each pump area location shall be equipped with two pumps meeting the capacity requirement, in case one is non-operational. e. Source of power for pumps, description of schedule and fueling requirements, storage location, and methods. 4. Manufacturer’s literature and test results (certificates) on the temporary silt fence, erosion control matting, riprap gradations, and any other necessary erosion control materials. 5. Planned installation and maintenance schedule for temporary erosion and sedimentation control facilities. Indicate locations and outlets of dewatering systems. 6. The boundaries of the clearing limits, sensitive areas and their buffers, and areas of vegetation preservation and tree retention. The Contractor shall also prepare a final SWPPP. The SWPPP must meet the requirements of the Department of Ecology’s NPDES and State Waste Discharge General Permit for Stormwater Discharges Associated with Construction Activity (General Permit). The SWPPP shall include and modify as necessary the Site Preparation and Erosion Control Plan drawings provided as part of the Contract Plans. The Contractor shall prepare, review, and modify the SWPPP as necessary to be consistent with the actual work schedule, sequencing, and construction methods that will be used on the project. The Contractor’s SWPPP shall meet the requirements of the general permit. The Contractor shall:
• Furnish, install, operate, and maintain necessary machinery, appurtenances, and equipment to keep excavations free of water during construction;
• Dewater and dispose of water in a manner that will not cause injury to public and private property, as well as keep sediment-laden water from entering the City surface water system or violate applicable water standards;
• Keep sufficient pumping equipment and machinery on hand at all times for emergencies, including electric power failures;
• Keep experienced personnel available at all times to operate pumping equipment, machinery and appliances;
• Not shut down dewatering systems between shifts, on holidays and weekends, nor during work stoppages without prior authorization by the Engineer;
• Control groundwater to prevent softening of bottoms of excavations, or formation of “quick” conditions or “boils”;
• Design and operate dewatering system that will not remove natural soils;
• Keep excavations free of water during excavation, construction of structures, installation of pipelines, placing of structures, backfill, and placing and curing of concrete; and
• Control surface water runoff to prevent entry and collection in excavations. As construction progresses and unexpected or seasonal conditions dictate, the Contractor shall anticipate that more water pollution/erosion control measures will be necessary. It shall be the obligation and responsibility of the Contractor to revise or supplement the pollution/erosion control measures as may be needed to protect the work, adjacent properties, storm drains, streams, and other water bodies.
11/4/2020
36
At all times, there must be material on the job site to handle any spills caused by the Contractor, such as tack, oils, diesel, etc. Materials would include, but not be limited to, oil absorbent pads and “kitty litter.” The Contractor must supply said materials at his expense and, in the event of a spill, be responsible for cleanup and disposal of contaminated materials. In addition, the SWPPP shall outline the procedures to be used to prevent high pH stormwater or dewatering water from entering surface waters. The plan shall include how the pH of the water will be maintained between pH 6.5 and pH 8.5 prior to being discharged from the project or entering surface waters. Prior to beginning any concrete or grinding work, the Contractor shall submit the plan, for the Engineer’s review and approval. An Ecology template is available to the Contractor for producing the SWPPP, using project- specific information added by the Contractor. The template and instructions are available at: http://www.ecy.wa.gov/programs/wq/stormwater/construction. The Engineer’s review and any resulting approval of the Contractor’s SWPPP and TESCP will be only regarding conformance with the specification requirement that the Contractor have the plans prepared by a CPESC or professional Civil Engineer who has expertise in the type of facilities and that the SWPPP and TESCP include the items specified for such plans. The Contractor shall be solely responsible for the adequacy of the SWPPP and TESCP and if erosion sediment, and other pollutant control measures in deviation or addition to those described in the SWPPP become necessary to minimize erosion and prevent storm water contamination from sediment and other pollutants, the Contractor shall prepare and submit a revised SWPPPP to the Engineer for review as specified for the original plan. The Contracting Agency will not be liable to the Contractor for failure to accept all or any portion of an originally submitted or revised SWPPP, nor for any delays to the Work due to the Contractor’s failure to submit and implement an acceptable SWPPP.
1-07.16 Protection and Restoration of Property
1-07.16(1) Private/Public Property Section 1-07.16(1) is supplemented with the following: (******) The Contracting Agency will obtain all easements and franchises required for the project. The Contractor shall limit his operation to the areas obtained and shall not trespass on private property. The Contracting Agency may provide certain lands, as indicated in connection with the Work under the Contract together with the right of access to such lands. The Contractor shall not unreasonably encumber the premises with his equipment or materials. The Contractor shall provide, with no liability to the Contracting Agency, any additional land and access thereto not shown or described that may be required for temporary construction facilities or storage of materials. He shall construct all access roads, detour roads, or other temporary Work as required by his operations. The Contractor shall confine his equipment, storage of material, and operation of his workers to those areas shown and described and such additional areas as he may provide.
11/4/2020
37
A. General. All construction Work under this contract on easements, right-of-way, over private property or franchise, shall be confined to the limits of such easements, right-of-way or franchise. All Work shall be accomplished so as to cause the least amount of disturbance and a minimum amount of damage. The Contractor shall schedule his Work so that trenches across easements shall not be left open during weekends or holidays and trenches shall not be open for more than 48 hours. B. Structures. The Contractor shall remove such existing structures as may be necessary for the performance of the Work and, if required, shall rebuild the structures thus removed in as good a condition as found. He shall also repair all existing structures that may be damaged as a result of the Work under this contract. C. Easements, cultivated areas, and other surface improvements. All cultivated areas, either agricultural or lawns, and other surface improvements which are damaged by actions of the Contractor shall be restored as nearly as possible to their original condition. Prior to excavation on an easement or private right-of-way, the Contractor shall strip topsoil from the trench or construction area and stockpile it in such a manner that it may be replaced by him, upon completion of construction. Ornamental trees and shrubbery shall be carefully removed with the earth surrounding their roots wrapped in burlap and replanted in their original positions within 48 hours. All shrubbery or trees destroyed or damaged, shall be replaced by the Contractor with material of equal quality at no additional cost to the Contracting Agency. In the event that it is necessary to trench through any lawn area, the sod shall be carefully cut and rolled and replaced after the trenches have been backfilled. The lawn area shall be cleaned by sweeping or other means, of all earth and debris. The Contractor shall use rubber wheel equipment similar to the small tractor-type backhoes used by side sewer contractors for all Work, including excavation and backfill, on easements or rights-of-way, which have lawn areas. All fences, markers, mailboxes, or other temporary obstacles shall be removed by the Contractor and immediately replace, after the trench is backfilled, in their original position. The Contractor shall notify the Contracting Agency and Property Owner at least 24 hours in advance of any Work done on easements or rights-of-way. Damage to existing structures outside of easement areas that may result from dewatering and/or other construction activity under this contract shall be restored to their original condition or better. The original condition shall be established by photographs taken and/or inspection made prior to construction. All such Work shall be done to the satisfaction of the Property Owners and the Contracting Agency at the expense of the Contractor. D. Streets. The Contractor will assume all responsibility of restoration of the surface of all streets (traveled ways) used by him if damaged. In the event the Contractor does not have labor or material immediately available to make necessary repairs, the Contractor shall so inform the Contracting Agency. The Contracting Agency will make the necessary repairs and the cost of such repairs shall be paid by the Contractor.
11/4/2020
38
The Contractor is responsible for identifying and documenting any damage that is pre-existing or caused by others. Restoration of excavation in City streets shall be done in accordance with the City of Renton Trench Restoration Requirements, which is available at the Public Works Department Customer Services counter on the 6th floor, Renton City Hall, 1055 South Grady Way or can be found on the City’s website at https://edocs.rentonwa.gov/Documents/ElectronicFile.aspx?docid=1074326&dbid=0&repo=CityofRenton.
1-07.17 Utilities and Similar Facilities Section 1-07.17 is supplemented with the following: (******) Existing utilities indicated in the Plans have been plotted from the best information available to the Engineer. Information and data shown or indicated in the Contract Documents with respect to existing underground utilities or services at or contiguous to the project site are based on information and data furnished to the Contracting Agency and the Engineer by owners of such underground facilities or others, and the Contracting Agency and the Engineer do not assume responsibility for the accuracy or completeness thereof. It is to be understood that other aboveground or underground
facilities not shown in the Plans may be encountered during the course of the Work. All utility valves, manholes, vaults, or pull boxes which are buried shall be conspicuously marked in a fashion acceptable to the Contracting Agency and the Engineer by the Contractor to allow their location to be determined by the Engineer or utility personnel under adverse conditions, (inclement weather or darkness). Where underground main distribution conduits, such as water, gas, sewer, electric power, or telephone, are shown on the Plans, the Contractor, for the purpose of preparing his bid, shall assume that every property parcel will be served by a service connection for each type of utility. The Contractor shall check with the utility companies concerning any possible conflict prior to commencing excavation in any area. The Contractor shall resolve all crossing and clearance problems with the utility company concerned. No excavation shall begin until all known facilities, in the vicinity of the excavation area, have been located and marked. In addition to the Contractor having all utilities field marked before starting Work , the Contractor shall have all utilities field marked after they are relocated in conjunction with this project.
Call Before You Dig
The 48-Hour Locators
1-800-424-5555 At least 2 and not more than 10 working days prior to commencing any excavations for utility potholing or for any other purpose under this Contract, the Contractor shall notify the Underground Utilities Location Center by telephone of the planned excavation and progress schedule. The Contractor is also warned that there may be utilities on the project that are not part of the One Call system. They must be contacted directly by the Contractor for locations. The Contractor shall make arrangements 48 hours in advance with respective utility owners to have a representative present when their utility is exposed or modified, if the utility chooses to do so.
11/4/2020
39
Existing utilities for telephone, power, gas, water, and television cable facilities shall be adjusted or relocated by the appropriate utility company unless otherwise noted in the Plans. These adjustments may be completed before the Contractor begins Work or may be performed in conjunction with the Contract Work . The Contractor shall be entirely responsible for coordination with the utility companies and arranging for the movement or adjustment, either temporary or permanent, of their facilities within the project limits. See also Section 1-05.14 of these Special Provisions. If or when utility conflicts occur, the Contractor shall continue the construction process on other aspects of the project whenever possible. No additional compensation will be made to the Contractor for reason of delay caused by the actions of any utility company, and the Contractor shall consider such costs to be incidental to the other items of the Contract.
Utility Potholing Potholing may be included as a bid item for use in determining the location of existing utilities in advance of the Contractor's operations. If potholing is not included as a bid item then it shall be considered incidental to other Work . The Contractor shall submit all potholing requests to the Engineer for approval, at least 2 working days before potholing is scheduled. Additionally, the Contractor shall provide potholing at the Engineer's request. In no way shall the Work described under Utility Potholing relieve the Contractor of any of the responsibilities described in Section 1-07.17 of the Standard Specifications and Special Provisions, and elsewhere in the Contract Documents.
1-07.17(3) Site Specific Potholing Section 1-07.17(3) is a new section: (******) Site Specific Potholing is intended to be additional potholing as directed by the Engineer, which is in addition to potholing included as incidental for utility installation. Where underground utilities are found to be in the way of construction, such condition shall not be deemed to be a changed or differing site condition, and if necessary, pipe alignment or grade shall be modified. No payment will be made unless potholing has been performed prior to trench excavation, and witnessed by the Engineer. Different utilities may be found to occupy a common trench. Any two or more utilities separated by 3 feet or less shall constitute one locate. Where multiple utilities exist in close proximity, the Contractor shall be paid for one locate for every 5 feet of exploration trench. The quantity for this item is included to provide a common proposal for bid purposes. The actual quantity used in construction may vary from that amount. The unit price will not be adjusted if the actual quantity used varies by more than 25 percent. The contractor shall perform this potholing a minimum of five working days prior to crossing to allow for potential revisions. The contractor shall not have cause for claim of down-time or any other additional costs associated with ‘waiting’ if the owner provides design revisions (related to the information supplied per this section) within three working days after the contractor provides the surveyed elevations. In no way shall the Work described under Site Specific Potholing relieve the Contractor of any of the responsibilities described in Section 1-07.17 of the Standard Specifications and Special Provisions, and elsewhere in the Contract Documents.
11/4/2020
40
1-07.17(4) Interruption of Services Section 1-07.17(4) is a new section: (******) Whenever, in the course of the construction operation, it becomes necessary to cause an outage of utilities, it shall be the Contractor's responsibility to notify the affected users and the Engineer not less than 48 hours in advance of such outage. The Contractor shall make reasonable effort to minimize the duration of outages, and shall estimate the length of time service will be interrupted and so notify the users. In the case of any utility outage that has exceeded or will exceed four hours, user contact shall again be made. Temporary service, if needed, will be arranged by the Contractor at no cost to the Contracting Agency. Overhead lighting outages shall not exceed 24 hours. All cost to the Contractor for providing temporary overhead lighting to meet above requirements shall be incidental to the various unit and Lump sum items of the Contract; no separate payment will be made.
1-07.17(5) Resolution of Utility Conflicts (******) Section 1-07.17(5) is a new section: In no way shall the work described under Resolution of Utility Conflicts relieve Contractor of any of the responsibilities described in Section 1-07.17 of the Standard Specifications and Special Provisions, and elsewhere in the Contract Documents. If or when utility conflicts occur, Contractor shall continue the construction process on other aspects of the project whenever possible. If “Resolution of utility conflicts” is included as a bid item in Section 1-09.14, it shall be used to resolve any new identified utility conflicts not otherwise shown on the Contract Drawing or Specifications that are identified during the course of construction.
1-07.18 Public Liability and Property Damage Insurance Section 1-07.18 Delete this section in its entirety and replace with the following: (******)
1-07.18(1) General The Contractor shall obtain and maintain in full force and effect, from the Contract Execution Date to the Completion Date, public liability and property damage insurance with an insurance company(ies) or through sources approved by the State Insurance Commissioner pursuant to RCW 48.05. The Contractor shall not begin work under the Contract until the required insurance has been obtained and approved by the Contracting Agency. Insurance shall provide coverage to the Contractor, all subcontractors, Contracting Agency and the Contracting Agency's consultant. The coverage shall protect against claims for bodily injuries, personal injuries, including accidental death, as well as claims for property damages which may arise from any act or omission of the Contractor or the subcontractor, or by anyone directly or indirectly employed by either of them. If warranted work is required, the Contractor shall provide the City proof that insurance coverage and limits established under the term of the Contract for work are in full force and effect during the period of warranty work.
11/4/2020
41
The Contracting Agency may request a copy of the actual declaration pages(s) for each insurance policy effecting coverage(s) required on the Contract prior to the date work commences. Failure of the Contractor to fully comply during the term of the Contract with the requirements described herein will be considered a material breach of contract and shall be caused for immediate termination of the Contract at the option of the Contracting Agency. All costs for insurance shall be incidental to and included in the unit or Lump Sum prices of the contract and no additional payment will be made.
1-07.18(2) Coverages All coverage provided by the Contractor shall be in a form and underwritten by a company acceptable to the Contracting Agency. The City requires that all insurers: 1. Be licensed to do business within the State of Washington. 2. Coverage to be on an "occurrence" basis (Professional Liability and Pollution coverage are acceptable when written on a claims-made basis). The City may also require proof of professional liability coverage be provided for up to two (2) years after the completion of the project. 3. The City may request a copy of the actual declaration page(s) for each insurance policy affecting coverage(s) required by the Contract prior to the date work commences. 4. Possess a minimum A.M. best rating of AVII (A rating of A XII or better is preferred.). If any insurance carrier possesses a rating of less than AVII, the City may make an exception. The City reserves the right to approve the security of the insurance coverage provided by the insurance company(ies), terms, conditions, and the Certificate of Insurance. Failure of the Contractor to fully comply during the term of the Contract with these requirements will be considered a material breach of contract and shall be cause for immediate termination of the contract at the option of the City. The Contractor shall obtain and maintain the minimum insurance coverage set forth below. By requiring such minimum insurance, the City of Renton shall not be deemed or construed to have assessed the risks that may be applicable to the Contractor. The Contractor shall assess its own risks and if it deems appropriate and/or prudent, maintain higher limits and/or broader coverage. Coverage shall include: A. Commercial General Liability - ISO 1993 Form or equivalent. Coverage will be written on an occurrence basis and include:
• Premises and Operations (including CG2503; General Aggregate to apply per project, if applicable)
• Explosion, Collapse, and Underground Hazards.
• Products/Completed Operations
• Contractual Liability (including Amendatory Endorsement CG 0043 or equivalent which includes defense coverage assumed under contract)
• Broad Form Property Damage
• Independent Contractors
11/4/2020
42
• Personal/Advertising Injury
• Stop Gap Liability B. Automobile Liability including all:
• Owned Vehicles
• Non-Owned Vehicles
• Hired Vehicles C. Workers' Compensation:
• Statutory Benefits (Coverage A) - Show Washington Labor & Industries Number D. Umbrella Liability (when necessary):
• Excess of Commercial General Liability and Automobile Liability. Coverage should be as broad as primary. E. Professional Liability - (whenever the work under this Contract includes Professional Liability, including Advertising activities) the (CONTRACTOR) shall maintain professional liability covering wrongful acts, errors and/or omissions of the (CONTRACTOR) for damage sustained by reason of or in the course of operations under this Contract. F. Pollution Liability - the City may require this coverage whenever work under this Contract involves pollution risk to the environment. This coverage is to include sudden and gradual coverage for third party liability including defense costs and completed operations. Contractor shall name City of Renton, and its officers, officials, agents, employees and volunteers as Additional Insured (ISO Form CG 2010 or equivalent). The Contractor shall provide City of Renton Certificates of Insurance prior to commencement of work. The City reserves the right to request copies of insurance policies, if at their sole discretion it is deemed appropriate. Further, all policies of insurance described above shall: A. Be on a primary basis not contributory with any other insurance coverage and/or self-insurance carried by City of Renton. B. Include a Waiver of Subrogation Clause. C. Severability of Interest Clause (Cross Liability). D. The Contractor shall provide the Contracting Agency and all Additional Insured’s with written notice of any policy cancellation, within two business days of their receipt of such notice. E. Failure on the part of the Contractor to maintain the insurance as required shall constitute a material breach of contract, upon which the Contracting Agency may, after giving five business days’ notice to the Contractor to correct the breach, immediately terminate the contract or, at its discretion, procure or renew such insurance and pay any and all premiums in connection therewith, with any sums so expended to be repaid to the Contracting Agency on demand, or at the sole discretion of the Contracting Agency, offset against funds due the Contractor from the Contracting Agency.
1-07.18(3) Limits LIMITS REQUIRED Providing coverage in these stated amounts shall not be construed to relieve the Contractor from liability in excess of such limits. The Contractor shall carry the following limits of liability as required below:
11/4/2020
43
Commercial General Liability General Aggregate* $2,000,000 ** Products/Completed Operations Aggregate $2,000,000 ** Each Occurrence Limit $1,000,000 Personal/Advertising Injury $1,000,000 Fire Damage (Any One Fire) $50,000 Medical Payments (Any One Person) $5,000 Stop Gap Liability $1,000,000 * General Aggregate to apply per project (ISO Form CG2503 or equivalent) **Amount may vary based on project risk Automobile Liability Bodily Injury/Property Damage $1,000,000 (Each Accident) Workers' Compensation Statutory Benefits - Coverage A Variable (Show Washington Labor and Industries Number) Umbrella Liability Each Occurrence Limit $1,000,000 General Aggregate Limit $1,000,000 Products/Completed Operations Aggregate $1,000,000
Professional Liability (If required) Each Occurrence/ Incident/Claim $1,000,000 Aggregate $2,000,000 Pollution Liability (If required) to apply on a per project basis Per Loss $1,000,000 Aggregate $1,000,000
The City may require the Contractor to keep professional liability coverage in effect for up to two (2) years after completion of the project. The Contractor shall promptly advise the CITY OF RENTON in the event any general aggregates are reduced for any reason, and shall reinstate the aggregate at the Contractor’s expense to comply with the minimum limits and requirements as stated above and shall furnish to the CITY OF RENTON a new certificate of insurance showing such coverage is in force.
1-07.18(4) Evidence of Insurance:
Within 20 days of award of the Contract, the Contractor shall provide evidence of insurance by submitting to the Contracting Agency the Certificate of Insurance (ACORD Form 25s or equivalent) conforming to items as specified in Sections 1-07.18(1), 1-07.18(2), and 1-07.18(3) as revised above. Other requirements are as follows: A. Strike the following or similar wording: "This Certificate is issued as a matter of information only and confers no rights upon the Certificate Holder".
11/4/2020
44
B. Strike the wording regarding cancellation notification to the City: "Failure to mail such notice shall impose no obligation or liability of any kind upon the company, its agents or representatives". C. Amend the cancellation clause to state: "Should any of the above described policies be cancelled before the expiration date thereof, notice will be delivered in accordance with the policy provisions."
For Professional Liability coverage only, instead of the cancellation language specified above, the
City will accept a written agreement that the consultant's broker will provide the required
notification.
1-07.22 Use of Explosives Section 1-07.22 is supplemented with the following: (******) Explosives shall not be used without specific authority of the Engineer, and then only under such restrictions as may be required by the proper authorities. Explosives shall be handled and used in strict compliance with WAC 296-52 and such local laws, rules and regulations that may apply. The individual in charge of the blasting shall have a current Washington State Blaster Users License. The Contractor shall obtain, comply with, and pay for such permits and costs as are necessary in conjunction with blasting operations.
1-07.23 Public Convenience and Safety
1-07.23(1) Construction Under Traffic Revise the second paragraph to read: (******) To disrupt public traffic as little as possible, the Contractor shall permit traffic to pass through the Work with the least possible inconvenience or delay. The Contractor shall maintain existing roads, streets, sidewalks, driveways, and paths within the project limits, keeping them open, and in good, clean, safe condition at all times. Accessibility to existing or temporary pedestrian push buttons shall not be impaired. Deficiencies caused by the Contractor’s operations shall be repaired at the Contractor ’s expense. Deficiencies not caused by the Contractor’s operations shall be repaired by the Contractor when directed by the Engineer, at the Contracting Agency’s expense. The Contractor shall also maintain roads, streets, sidewalks, driveways, and paths adjacent to the project limits when affected by the Contractor’s operations. Snow and ice control will be performed by the Contracting Agency on all projects. Cleanup of snow and ice control debris will be at the Contracting Agency’s expense. The Contractor shall perform the following: 1. Remove or repair any condition resulting from the Work that might impede traffic or create a hazard. 2. Keep existing traffic signal and highway lighting systems in operation as the Work proceeds. (The Contracting Agency will continue the route maintenance on such system.) 3. Maintain the striping on the roadway at the Contracting Agency’s expense. The Contractor shall be responsible for scheduling when to renew striping, subject to the approval of the Engineer. When the scope of the project does not require Work on the roadway, the Contracting Agency will be responsible for maintaining the striping. 4. Maintain existing permanent signing. Repair of signs will be at the Contracting Agency’s expense, except those damaged due to the Contractor’s operations.
11/4/2020
45
5. Keep drainage structures clean to allow for free flow of water. Cleaning of existing drainage structures will be at the Contracting Agency’s expense when approved by the Engineer, except when flow is impaired due to the Contractor’s operations. 6. At the request of the Contracting Agency, the contractor shall remove steel plates and temporarily backfill and patch utility trenches to allow the Contracting Agency to utilize equipment for snow and ice removal through the project area. This request shall be considered a change of conditions and eligible for reimbursement of costs.
1-07.23(1) is supplemented with the following:
(******) The Contractor shall be responsible for controlling dust and mud within the project limits and on any street, which is utilized by his equipment for the duration of the project. The Contractor shall be prepared to use watering trucks, power sweepers, and other pieces of equipment as deemed necessary by the Engineer, to avoid creating a nuisance. Dust and mud control shall be considered as incidental to the project and no compensation will be made for this section. Complaints of dust, mud, or unsafe practices and/or property damage to private ownership will be transmitted to the Contractor and prompt action in correcting them will be required by the Contractor. The Contractor shall maintain the roads during construction in a suitable condition to minimize affects to vehicular and pedestrian traffic. All cost to maintain the roads shall be borne by the Contractor. At least one-way traffic shall be maintained on all cross-streets within the project limits during working hours. One lane shall be provided in each direction for all streets during non-working hours. The Contractor shall provide one drivable roadway lane and maintain convenient access for local and commuter traffic to driveways, businesses, and buildings along the line of Work throughout the course of the project. Such access shall be maintained as near as possible to that which existed prior to the commencement of construction. This restriction shall not apply to the paving portion of the construction process. The Contractor shall notify and coordinate with all property owners and tenants of street closures, or other restrictions which may interfere with their access at least 24 hours in advance for single-family residential property, and at least 48 hours in advance for apartments, offices, and commercial property. The Contractor shall give a copy of all notices to the Engineer. When the abutting owners’ access across the right-of-way line is to be eliminated and replaced under the Contract by other access, the existing access shall not be closed until the replacement access facility is available. All unattended excavations shall be properly barricaded and covered at all times. The Contractor shall not open any trenches that cannot be completed and refilled that same day. Trenches shall be patched or covered by a temporary steel plate, at the Contractor’s expense, except in areas where the roadway remains closed to public traffic. Steel plates must be anchored.
11/4/2020
46
1-07.23(2) Construction and Maintenance of Detours (******) Revise the first paragraph to read: Unless otherwise approved, the Contractor shall maintain two-way traffic during construction. The Contractor shall build, maintain in a safe condition, keep open to traffic, and remove when no longer needed: 1. Detours and detour bridges that will accommodate traffic diverted from the roadway, bridge, sidewalk, driveway, or path during construction, 2. Detour crossings of intersecting highways, and 3. Temporary approaches.
1-07.24 Rights-of-Way Delete this section in its entirety, and replace it with the following: (******) Street right-of-way lines, limits of easements, and limits of construction permits are indicated on the Drawings. The Contractor’s construction activities shall be confined within these limits unless arrangements for use of private property are made. Generally, the Contracting Agency will have obtained, prior to bid opening, all rights-of-way and easements, both permanent and temporary, necessary for carrying out the completion of the Work . Exceptions to this are noted in the Contract Documents or brought to the Contractor’s attention by a duly issued addendum. Whenever any of the Work is accomplished on or through property other than public right-of-way, the Contractor shall meet and fulfill all covenants and stipulations of any easement agreement obtained by the Contracting Agency from the owner of the private property. Copies of the easement agreements are included in the Contract Provisions or made available to the Contractor as soon as practical after they have been obtained by the Engineer. Whenever easements or rights-of-entry have not been acquired prior to advertising, these areas are so noted on the Drawings. The Contractor shall not proceed with any portion of the Work in areas where right-of-way, easements, or rights-of-entry have not been acquired until the Engineer certifies to the Contractor that the right-of-way or easement is available or that the right-of-entry had been received. If the Contractor is delayed due to acts of omission on the part of the Contracting Agency in obtaining easements, rights of entry of right-of-way, the Contractor will be entitled to an extension of time. The Contractor agrees that such delay shall not be a breach of contract. Each property owner shall be given 48 hours’ notice prior to entry by the Contactor. This includes entry onto easements and private property where private improvements must be adjusted. The Contractor shall be responsible for providing, without expense or liability of the Contracting Agency, any additional land and access thereto that the Contractor may desire for temporary construction facilities, storage of materials, or other Contractor needs. However, before using any private property, whether adjoining the Work or not, the Contractor shall file with the Engineer a written permission of the private property owner, and, upon vacating the premises, a written release from the property owner of each property disturbed or otherwise interfered with by reasons of construction pursued under this Contract. The statement shall be signed by the private property
11/4/2020
47
owner, or proper authority acting for the owner of the private property affected, stating that permission has been granted to use the property and all necessary permits have been obtained or, in the case of a release, that the restoration of the property has been satisfactorily accomplished. The statement shall include the parcel number, address and date of signature. Written releases must be filed with the Engineer before the Completion Date will be established.
1-07.28 Confined Space Entry Section 1-07.28 is a new section: The Contractor shall: 1. Review and be familiar with the City’s Public Works Confined Space Entry Program. 2. Review documented information about the City confined spaces in which entry is intended as listed and described in the City’s Attribute and Map Book. This information includes identified hazards for each permit-required confined space. 3. Each contractor shall have their own confined space entry program. Upon request of the City they will provide a statement confirming they are in compliance with their confined space entry program including requirements for confined space training for employees associated with the project. 4. Be responsible for following all confined space requirements established by the provisions in WAC 296-809 and its chapters. 5. Coordinate entry operations with the City when employees from the contractor will be working in or near City confined spaces. 6. Discuss entry operations with the City, including the program followed during confined space entry. 7. Debrief the City on any hazards confronted or created at the completion of entry operations. 8. Place signs stating, “Danger, Follow Confined Space Entry Procedure before Entering” at each confined space to be entered. Never leave the confined space open and unattended. The contractor’s or consultant’s point of contact with the City in regard to confined space entry will be the City’s assigned construction inspector.
1-08 PROSECUTION AND PROGRESS
1-08.0 Preliminary Matters Section 1-08.0 is a new section with subsection: (******)
1-08.0(1) Preconstruction Conference Section 1-08.0(1) is a new subsection: (******) The Engineer will furnish the Contractor with copies of the Contract Documents per Section 1-02.2 “Plans and Specifications”. Additional documents may be furnished upon request at the cost of reproduction. Prior to undertaking each part of the Work the Contractor shall carefully study and compare the Contract Documents, and check and verify pertinent figures shown therein and all applicable field measurements. The Contractor shall promptly report in writing to the Engineer any conflict, error or discrepancy, which the Contractor may discover.
11/4/2020
48
After the Contract has been executed, but prior to the Contractor beginning the Work , a preconstruction conference will be held between the Contractor, the Engineer and such other interested parties as may be invited. The Contractor shall prepare and submit at the preconstruction meeting: 1. Contractor's plan of operation and progress schedule (3+ copies) 2. Approval of qualified subcontractors (bring list of subcontractors if different from list submitted with bid) 3. List of materials fabricated or manufactured off the project 4. Material sources on the project 5. Names of principal suppliers 6. Detailed equipment list, including “Rental Rate Blue Book” hourly costs (both working and standby rates) 7. Weighted wage rates for all employee classifications anticipated to be used on Project 8. Cost percentage breakdown for lump sum bid item(s) 9. Shop Drawings (bring preliminary list) 10. Traffic Control Plans (3+ copies) 11. Temporary Water Pollution/Erosion Control Plan 12. Shoring Plans (per section 1-09.14(2)B), if applicable In addition, the Contractor shall be prepared to address: Bonds and insurance Project meetings – schedule and responsibilities Provision for inspection for materials from outside sources Responsibility for locating utilities Responsibility for damage Time schedule for relocations, if by other than the Contractor Compliance with Contract Documents Acceptance and approval of Work Labor compliance, payrolls, and certifications Safety regulations for the Contractors’ and the Contracting Agency's employees and representatives Suspension of Work , time extensions Change order procedures Progress estimates, procedures for payment Special requirements of funding agencies Construction engineering, advance notice of special Work Any interpretation of the Contract Documents requested by the Contractor Any conflicts or omissions in Contract Documents Any other problems or questions concerning the Work Processing and administration of public complaints Easements and rights-of-entry Other contracts The franchise utilities may be present at the preconstruction conference, and the Contractor should be prepared for their review and discussion of progress schedule and coordination.
11/4/2020
49
1-08.0(2) Hours of Work Section 1-08.0(2) is a new subsection: (******) Except in the case of emergency or unless otherwise approved by the Contracting Agency, the normal straight time working hours for the Contract shall be any consecutive 8-hour period between 7:00 a.m. and 5:00 p.m. of a working day with a maximum 1-hour lunch break and a 5-day Work week. The normal straight time 8-hour working period for the Contract shall be established at the preconstruction conference or prior to the Contractor commencing the Work. If a Contractor desires to perform Work before 7:00 a.m. or after 5:00 p.m. on any day, the Contractor shall apply in writing to the Engineer for permission to Work such times. Permission to Work longer than an 8-hour period between 7:00 a.m. and 5:00 p.m. is required. Such requests shall be submitted to the Engineer no later than noon on the working day prior to the day for which the Contractor is requesting permission to Work . Permission to Work between the hours of 10:00 p.m. and 7:00 a.m. during weekdays and between the hours of 10:00 p.m. and 7:00 a.m. on weekends or holidays may also be subject to noise control requirements. Approval to continue Work during these hours may be revoked at any time the Contractor exceeds the Contracting Agency’s noise control regulations or complaints are received from the public or adjoining property owners regarding the noise from the Contractor’s operations. The Contractor shall have no claim for damages or delays should such permission be revoked for these reasons. Permission to Work Saturdays, Sundays, holidays or other than the agreed upon normal straight time working hours Monday through Friday may be given subject to certain other conditions set forth by the Contracting Agency or the Engineer. These conditions may include but are not limited to: requiring the Engineer or such assistants as the Engineer may deem necessary to be present during the Work; requiring the Contractor to reimburse the Contracting Agency for the cost of engineering salaries paid Contracting Agency employees who worked during such times; considering the Work performed on Saturdays, Sundays, and holidays as working days with regards to the Contract Time; and considering multiple Work shifts as multiple working days with respect to Contract Time even though the multiple shifts occur in a single 24-hour period. Assistants may include, but are not limited to, survey crews; personnel from the material testing labs; inspectors; and other Contracting Agency employees when in the opinion of the Engineer such Work necessitates their presence.
1-08.0(3) Reimbursement for Overtime Work of Contracting Agency Employees Section 1-08.0(3) is a new subsection: (******) Where the Contractor elects to Work on a Saturday, Sunday, holiday, or longer than an 8-hour Work shift on a regular working day, as defined in the Standard Specifications, such Work shall be considered as overtime Work . On all such overtime Work an inspector will be present, and a survey crew may be required at the discretion of the Engineer. The Contractor shall reimburse the Contracting Agency for the full amount of the straight time plus overtime costs for employees and representative(s) of the Contracting Agency required to work overtime hours. The Contractor, by these Specifications, does hereby authorize the Engineer to deduct such costs from the amount due or to become due the Contractor.
11/4/2020
50
1-08.1 Subcontracting (******) Revise the second paragraph to read: The Contractor shall not subcontract Work unless the Engineer approves in writing. Each request to subcontract shall be on the form the Engineer provides. If the Engineer requests, the Contractor shall provide proof that subcontractor has the experience, ability, and equipment the Work requires. The Contractor shall require each subcontractor to comply with Section 1-07.9 and to furnish all certificates and statements required by the Contract. The Contractor shall require each subcontractor of every tier to meet the responsibility criteria stated in RCW 39.06, and shall include these requirements in every subcontract of every tier. Section 1-08.1 is supplemented with the following: (******) Written requests for change in subcontractors shall be submitted by the Contractor to the Engineer at least 7 calendar days prior to start of a subcontractor's Work . The Contractor agrees that he/she is fully responsible to the Contracting Agency for the acts and omissions of all subcontractors and lower-tier subcontractors, and persons either directly or indirectly employed by the subcontractors, as well as for the acts and omissions of persons directly employed by the Contractor. The Contractor shall be required to give personal attention to the Work that is sublet. Nothing contained in the Contract Documents shall create any contractual relation between any subcontractor and the Contracting Agency. The Contractor shall be responsible for making sure all subcontractors submit all required documentation, forms, etc.
1-08.2 Assignment The second paragraph of Section 1-08.2 is deleted and replaced with the following: (******) The Contractor shall not assign any moneys due or to become due to the Contractor hereunder without the prior written consent of the Contracting Agency. The assignment, if approved, shall be subject to all setoffs, withholdings, and deductions required by law and the Contract.
1-08.3 Progress Schedule Delete this section in its entirety and replace with the following: (******) The progress schedule for the entire project shall be submitted 7 calendar days prior to the
Preconstruction Conference. The schedule shall be prepared using the critical path method (CPM), preferably using Microsoft Project or equivalent software. The schedule shall contain the following information, at a minimum: 1. Construction activities, in sufficient detail that all activities necessary to construct a complete and functional project are considered. Any activity that has a scheduled duration exceeding 30 calendar days shall be subdivided until no sub-element has a duration exceeding 30 calendar days. 2. The schedule shall clearly indicate the activities that comprise the critical path. For each activity not on the critical path, the schedule shall show the float, or slack, time.
11/4/2020
51
3. Procurement of material and equipment. 4. Submittals requiring review by the Engineer. Submittal by the Contractor and review by the Engineer shall be shown as separate activities. 5. Work to be performed by a subcontractor, agent, or any third party. 6. Allowances for delays that could result from normal inclement weather (time extensions due to inclement weather will not be allowed). 7. Allowances for the time required by utilities (Contracting Agency’s and others) to locate, monitor, and adjust their facilities as required. The Engineer may request the Contractor to alter the progress schedule when deemed necessary in the opinion of the Engineer, in the interest of public safety and welfare of the Contracting Agency, or for coordination with any other activity of other contractors, the availability of all or portions of the job site, or special provisions of this Contract, or to reasonably meet the completion date of the project. The Contractor shall provide such revised schedule within 10 days of request. If, at any time, in the opinion of the Engineer, the progress of construction falls significantly behind schedule, the Contractor may be required to submit a plan for regaining progress and a revised schedule indicating how the remaining Work items will be completed within the authorized contract time. The Contractor shall promptly report to the Engineer any conditions that the Contractor feels will require revision of the schedule and shall promptly submit proposed revisions in the progress schedule for acceptance by the Engineer. When such changes are accepted by the Engineer, the revised schedule shall be followed by the Contractor.
Weekly Schedule. The Contractor shall submit a weekly progress schedule to the Engineer which sets forth specific Work to be performed the following week, and a tentative schedule for the second week.
Failure to Maintain Progress Schedule. The Engineer will check actual progress of the Work against the progress schedule a minimum of two times per month. Failure, without just cause, to maintain progress in accordance with the approved schedule shall constitute a breach of Contract. If, through no fault of the Contractor, the proposed construction schedule cannot be met, the Engineer will require the Contractor to submit a revised schedule to the Engineer for acceptance. The approved revisions will thereafter, in all respects, apply in lieu of the original schedule. Failure of the Contractor to follow the progress schedule submitted and accepted, including revisions thereof, shall relieve the Contracting Agency of any and all responsibility for furnishing and making available all or any portion of the job site, and will relieve the Contracting Agency of any responsibility for delays to the Contractor in the performance of the Work . The cost of preparing the progress schedule, any supplementary progress schedules, and weekly schedules shall be considered incidental to the Contract and no other compensation shall be made.
11/4/2020
52
1-08.4 Prosecution of the Work Section 1-08.4 Delete this section in its entirety and replace with the following: (******) Notice to Proceed will be given after the Contract has been executed and the Contract bond and evidence of insurances have been approved and filed by the Contracting Agency. The Contractor shall not commence the Work until the Notice to Proceed has been given by the Engineer. The Contractor shall commence construction activities on the project site within ten days of the Notice to Proceed date. The Work thereafter shall be prosecuted diligently, vigorously, and without unauthorized interruption until physical completion of the Work . There shall be no voluntary shutdowns or slowing of operations by the Contractor without prior approval of the Engineer. Such approval shall not relieve the Contractor from the contractual obligation to complete the Work within the prescribed Contract Time.
1-08.5 Time For Completion Delete this section in its entirety and replace with the following: (******) The Work shall be physically completed in its entirety within the time specified in the Contract Documents or as extended by the Engineer. The Contract Time will be stated in “working days”, shall begin on the Notice To Proceed date, or the date identified in the Notice to Proceed as “the first working day”, and shall end on the Contract Completion date. A non-working day is defined as a Saturday, a Sunday, a day on which the Contract specifically suspends Work , or one of these holidays: New Year’s Day Martin Luther King Day Memorial Day Independence Day Labor Day Veteran’s Day Thanksgiving Day the day after Thanksgiving Christmas Day. Note for holidays that land on a Saturday or Sunday: The day before Christmas shall be a holiday when Christmas Day occurs on a Tuesday, Wednesday, or Friday. The day after Christmas shall be a holiday when Christmas Day occurs on a Monday or Thursday. When Christmas Day occurs on a Saturday, the two preceding working days shall be observed as holidays. When Christmas day occurs on a Sunday, the two working days following shall be observed as holidays. When holidays other than Christmas fall on a Saturday, the preceding Friday will be counted as a non-working day and when they fall on a Sunday the following Monday will be counted as a non-working day. The Contract Time has been established to allow for periods of normal inclement weather that, from historical records, is to be expected during the Contract Time, and during which periods, Work is anticipated to be performed. Each successive working day, beginning with the Notice to Proceed date and ending with the Physical Completion date, shall be charged to the Contract Time as it occurs except a day, or part of a day, which is designated a non-working day or an Engineer determined unworkable day.
11/4/2020
53
The Engineer will furnish the Contractor a weekly report showing (1) the number of working days charged against the Contract Time for the preceding week; (2) the Contract Time in working days; (3) the number of working days remaining in the Contract Time; (4) the number of non-working days; and (5) any partial or whole days the Engineer declared unworkable the previous week. This weekly report will be correlated with the Contractor’s current approved progress schedule. If the Contractor elects to work 10 hours a day and 4 days a week (a 4-10 schedule), and the fifth day of the week in which a 4-10 shift is worked would ordinarily be charged as a working day, then the fifth day of that week will be charged as a working day whether or not the Contractor works on that day. The Contractor will be allowed 10 calendar days from the date of each report in which to file a written protest of an alleged discrepancy in the Contract Time as reported. Otherwise, the report will be deemed to have been accepted by the Contractor as correct. The requirements for scheduling the Final Inspection and establishing the Substantial Completion, Physical Completion, and Completion Dates are specified in Sections 1-05.11 and 1-05.12. The Engineer will give the Contractor written notice of the completion date of the Contract after all the Contractor’s obligations under the Contract have been performed by the Contractor. The following events must occur before the Completion Date can be established: 1. The physical Work on the project must be complete; and 2. The Contractor must furnish all documentation required by the Contract and required by law, to allow the Contracting Agency to process final acceptance of the Contract. The following documents must be received by the Engineer prior to establishing a completion date: a. Certified Payrolls per Section 1-07.9(5) b. Material Acceptance Certification Documents c. Annual Report of Amounts Paid as MBE/WBE Participants or Quarterly Report of Amounts Credited as DBE Participation, as required by the Contract Provisions. d. FHWA 47 (Federal-aid Projects) e. Final Contract Voucher Certification f. Property owner releases per Section 1-07.24 g. A copy of the Notice of Termination sent to the Washington State Department of Ecology (Ecology); the elapse of 30 calendar days from the date of receipt of the Notice of Termination by Ecology; and no rejection of the Notice of Termination by Ecology. This requirement will not apply if the Construction Stormwater General Permit is transferred back to the Contracting Agency in accordance with Section 8-01.3(16), as required by the Contract Provisions. Within 10 calendar days after execution of the Contract by the Contracting Agency, the Contractor shall provide the Contracting Agency with copies of purchase orders for all equipment items deemed critical by the Contracting Agency, including but not limited to signal controller materials, lighting standards, and signal standards required for the physical completion of the Contract. Such purchase orders shall disclose the estimated delivery dates for the equipment. All items of Work that can be performed without delivery of the critical items shall start and be completed as soon as possible. At that time, the Engineer may suspend the Work upon request of the Contractor until the critical items are delivered to the Contractor, if the Contracting Agency
11/4/2020
54
received a purchase order within 10 calendar days after execution of the Contract by the Contracting Agency. The Contractor will be entitled to only one such suspension of time during the performance of the Work and during such suspension shall not perform any additional Work on the project. Upon delivery of the critical items, contract time will resume and continue to be charged in accordance with Section 1-08.
1-08.6 Suspension of Work Section 1-08.6 is supplemented with the following: (******) Contracting Agency may at any time suspend the Work , or any part thereof, by giving notice to the Contractor in writing. The Work shall be resumed by the Contractor within 14 calendar days after the date fixed in the written notice from the Contracting Agency to the Contractor to do so. The Contractor shall not suspend Work under the Contract without the written order of the Contracting Agency. If it has been determined that the Contractor is entitled to an extension of time, the amount of such extension shall be only to compensate for direct delays, and shall be based upon the Contractor's diligently pursuing the Work at a rate not less than that which would have been necessary to complete the original Contract Work on time.
1-08.7 Maintenance During Suspension Revise the second paragraph to read: (******) At no expense to the Contracting Agency, the Contractor shall provide through the construction area a safe, smooth, and unobstructed roadway, sidewalk, driveway, and path for public use during suspension (as required in Section 1-07.23 or the Special Provisions). This may include a temporary road or detour.
1-08.9 Liquidated Damages Section 1-08.9 is supplemented with the following: (******) In addition, the Contractor shall compensate the Contracting Agency for actual engineering inspection and supervision costs and any other expenses and legal fees incurred by the Contracting Agency as a result of such delay. Such labor costs will be billed to the Contractor at actual costs, including administrative overhead costs. In the event that the Contracting Agency is required to commence any lawsuit in order to enforce any provision of this Contract or to seek redress for any breach thereof, the Contracting Agency shall be entitled to recover its costs, including reasonable attorney’s fees, from the Contractor.
11/4/2020
55
1-08.11 Contractor's Plant and Equipment Section 1-08.11 is a new Section: (******) The Contractor alone shall at all times be responsible for the adequacy, efficiency, and sufficiency of his and his subcontractor's plant and equipment. The Contracting Agency shall have the right to make use of the Contractor's plant and equipment in the performance of any Work on the site of the Work . The use by the Contracting Agency of such plant and equipment shall be considered as extra Work and paid for accordingly. Neither the Contracting Agency nor the Engineer assumes any responsibility, at any time, for the security of the site from the time the Contractor's operations have commenced until final acceptance of the Work by the Engineer and the Contracting Agency. The Contractor shall employ such measures as additional fencing, barricades, and watchmen service, as he deems necessary for the public safety and for the protection of the site and his plant and equipment. The Contracting Agency will be provided keys for all fenced, secured areas.
1-08.12 Attention to Work Section 1-08.12 is a new section: (******) The Contractor shall give his personal attention to and shall supervise the Work to the end that it shall be prosecuted faithfully, and when he is not personally present on the Work site, he shall at all times be represented by a competent superintendent who shall have full authority to execute the same, and to supply materials, tools, and labor without delay, and who shall be the legal representative of the Contractor. The Contractor shall be liable for the faithful observance of any instructions delivered to him or to his authorized representative.
1-09 MEASUREMENT AND PAYMENT
1-09.1 Measurement of Quantities Section 1-09.1 is supplemented with the following: (******)
Lump Sum. The percentage of lump sum Work completed, and payment will be based on the cost percentage breakdown of the lump sum bid price(s) submitted at the preconstruction conference. The Contractor shall submit a breakdown of costs for each lump sum bid item. The breakdown shall list the items included in the lump sum together with a unit price of labor, materials, and equipment for each item. The summation of the detailed unit prices for each item shall add up to the lump sum bid. The unit price values may be used as a guideline for determining progress payments or deductions or additions in payment for ordered Work changes.
Cubic Yard Quantities. The Contractor shall provide truck trip tickets for progress payments only in the following manner. Where items are specified to be paid by the cubic yard, the following tally system shall be used.
11/4/2020
56
All trucks to be employed on this Work will be measured to determine the volume of each truck. Each truck shall be clearly numbered, to the satisfaction of the Engineer, and there shall be no duplication of numbers. Duplicate tally tickets shall be prepared to accompany each truckload of material delivered on the project. All tickets received that do not contain the following information will not be processed for payment: 1. Truck number 2. Quantity and type of material delivered in cubic yards 3. Driver ’s name, date and time of delivery 4. Location of delivery, by street and stationing on each street 5. Place for the Engineer to acknowledge receipt 6. Pay item number 7. Contract number and/or name It will be the Contractor's responsibility to see that a ticket is given to the Engineer on the project for each truckload of material delivered. Pay quantities will be prepared on the basis of said tally tickets. Loads will be checked by the Engineer to verify quantity shown on ticket.
Quantities by Ton. It will be the Contractor's responsibility to see that a certified weight ticket is given to the Inspector on the project at the time of delivery of materials for each truckload delivered. Pay quantities will be prepared on the basis of said tally tickets, delivered to the Inspector at time of delivery of materials. Tickets not receipted by Inspector will not be honored for payment. Each truck shall be clearly numbered to the satisfaction of the Engineer and there shall be no duplication of numbers. Duplicate tickets shall be prepared to accompany each truckload of material delivered to the project. All tickets received that do not contain the following information will not be processed for payment: 1. Truck number 2. Truck tare weight (stamped at source) 3. Gross truckload weight in tons (stamped at source) 4. Net load weight (stamped at source) 5. Driver's name, date, and time of delivery 6. Location for delivery by street and stationing on each street 7. Place for the Engineer to acknowledge receipt 8. Pay item number 9. Contract number and/or name
1-09.3 Scope of Payment Section 1-09.3 is supplemented with the following: (******) The bid items listed in Section 1-09.14 will be the only items for which compensation will be made for the Work described in each section of the Standard Specifications when the Contractor performs the specified Work . Should a bid item be listed in a “Payment” clause but not in the Proposal Form, and Work for that item is performed by the Contractor and the Work is not stated as included in or incidental to a pay item in the Contract and is not Work that would be required to complete the intent
11/4/2020
57
of the Contract per Section 1-04.1, then payment for that Work will be made as for Extra Work pursuant to a Change Order. The words “Bid Item,” “Contract Item,” and “Pay Item,” and similar terms used throughout the Contract Documents are synonymous. If the “payment” clause in the Specifications relating to any unit bid item price in the Proposal Form requires that said unit bid item price cover and be considered compensation for certain Work or material essential to the item, then the Work or material will not be measured or paid for under any other unit bid item which may appear elsewhere in the Proposal Form or Specifications. Pluralized unit bid items appearing in these Specifications are changed to singular form. Payment for bid items listed or referenced in the “Payment” clause of any particular section of the Specifications shall be considered as including all of the Work required, specified, or described in that particular section. Payment items will generally be listed generically in the Specifications, and specifically in the bid form. When items are to be “furnished” under one payment item and “installed” under another payment item, such items shall be furnished FOB project site, or, if specified in the Special Provisions, delivered to a designated site. Materials to be “furnished,” or “furnished and installed” under these conditions, shall be the responsibility of the Contractor with regard to storage until such items are incorporated into the Work or, if such items are not to be incorporated into the Work , delivered to the applicable Contracting Agency storage site when provided for in the Specifications. Payment for material “furnished,” but not yet incorporated into the Work , may be made on monthly estimates to the extent allowed.
1-09.6 Force Account Section 1-09.6 is supplemented with the following: (******) Contracting Agency has estimated and included in the proposal, dollar amounts for all items to be paid per force account, only to provide a common proposal for Bidders. All such dollar amounts are to become a part of the Contractor’s total bid. However, the Contracting Agency does not warrant expressly or by implication that the actual amount of Work will correspond with those estimates. Payment will be made on the basis of the amount of Work actually authorized by the Engineer.
1-09.7 Mobilization Section 1-09.7 is supplemented with the following: (******) Mobilization shall also include, but not be limited to, the following items: the movement of Contractor's personnel, equipment, supplies, and incidentals to the project site; the establishment of an office, buildings, and other facilities necessary for Work on the project; providing sanitary facilities for the Contractor's personnel; and obtaining permits or licenses required to complete the project not furnished by the Contracting Agency. This item shall also include providing the Engineer and the Inspectors with access to telephone, facsimile machine, and copy machine during all hours the Contractor is working on the jobsite; and a table and chair for their use when needed.
11/4/2020
58
Payment will be made for the following bid item(s): “Mobilization & Demobilization,” Lump Sum.
1-09.9 Payments Delete the fourth paragraph and replace it with the following: (******) Progress payments for completed Work and material on hand will be based upon progress estimates prepared by the Engineer. A progress estimate cutoff date will be established at the preconstruction meeting. The initial progress estimate will be made not later than 30 days after the Contractor commences the Work , and successive progress estimates will be made every month thereafter until the Completion Date. Progress estimates made during progress of the Work are tentative, and made only for the purpose of determining progress payment. The progress estimates are subject to change at any time prior to the calculation of the final payment. The value of the progress estimate will be the sum of the following: 1. Unit Price Items in the Bid Form – the approximate quantity of acceptable units of Work completed multiplied by the unit price. 2. Lump Sum Items in the Bid Form – the estimated percentage complete multiplied by the Bid Forms amount for each lump sum item, or per the schedule of values for that item. 3. Materials on Hand – 100 percent of invoiced cost of material delivered to job site or other storage area approved by the Engineer. 4. Change Orders – entitlement for approved extra cost or completed extra Work as determined by the Engineer. Progress payments will be made in accordance with the progress estimate less: 1. Retainage per Section 1-09.9(1); 2. The amount of Progress Payments previously made; and 3. Funds withheld by the Contracting Agency for disbursement in accordance with the Contract Documents. Progress payments for Work performed shall not be evidence of acceptable performance or an admission by the Contracting Agency that any Work has been satisfactorily completed.
Payments will be made by check or electronic transfer, issued by the Contracting Agency’s fiscal officer, against the appropriate fund source for the project. Payments received on account of Work performed by a subcontractor are subject to the provisions of RCW 39.04.250.
Section 1-09.9 is supplemented with the following: (******) Applications for payment shall be itemized and supported to the extent required by the Engineer by receipts or other vouchers showing payment for materials and labor, payments to subcontractors, and other such evidence of the Contractor's right to payment as the Engineer may direct, including “red line” as-built drawings showing work installed by the contractor during the progress payment period.
11/4/2020
59
The Contractor shall submit a progress report with each monthly request for a progress payment. The progress report shall indicate the estimated percent complete for each activity listed on the progress schedule (see Section 1-08.3) and a revised and updated schedule to reflect the most current project completion date.
1-09.9(1) Retainage Section 1-09.9(1) is supplemented with the following: (******) The retained amount shall be released as stated in the Standard Specifications if no claims have been filed against such funds as provided by law, and if the Contracting Agency has no unsatisfied claims against the Contractor. In the event claims are filed, the Contracting Agency shall withhold, until such claims are satisfied, a sum sufficient to satisfy all claims and to pay attorney's fees. In addition, the Contracting Agency shall withhold such amount as is required to satisfy any claims by the Contracting Agency against the Contractor, until such claims have been finally settled. Neither the final payment nor any part of the retained percentage shall become due until the Contractor, if requested, delivers to the Contracting Agency a complete release of all liens arising out of this Contract, or receipts in full in lieu thereof, and, if required in either case, an affidavit that so far as the Contractor has knowledge or information, the release and receipts include all labor and materials for which a lien could be filed: but the Contractor may, if any subcontractor refuses to furnish a release or receipt in full, furnish a bond satisfactorily to the Engineer to indemnify the Contracting Agency against the lien. If any lien remains unsatisfied after all payments are made, the Contractor shall reimburse to the Contracting Agency all monies that the latter may be compelled to pay in discharging such lien, including all costs and reasonable engineer's and attorney's fees.
1-09.9(2) Contracting Agency’s Right to Withhold and Disburse Certain Amounts Section 1-09.9(2) is a new section: (******) In addition to monies retained pursuant to RCW 60.28 and subject to RCW 39.04.250, RCW 39.12 and RCW 39.76, the Contractor authorizes the Engineer to withhold progress payments due or deduct an amount from any payment or payments due the Contractor which, in the Engineer’s opinion, may be necessary to cover the Contracting Agency’s costs for or to remedy the following situations: 1. Damage to another contractor when there is evidence thereof and a claim has been filed. 2. Where the Contractor has not paid fees or charges to public authorities of municipalities, which the Contractor is obligated to pay. 3. Utilizing material tested and inspected by the Engineer, for purposes not connected with the Work (Section 1-05.6). 4. Landscape damage assessments per Section 1-07.16. 5. For overtime Work performed by City personnel per Section1-08.0(3). 6. Anticipated or actual failure of the Contractor to complete the Work on time: a. Per Section 1-08.9 Liquidated Damages; or b. Lack of construction progress based upon the Engineer’s review of the Contractor’s approved progress schedule, which indicates the Work will not be complete within the contract time. When calculating an anticipated time overrun, the Engineer will make allowances for weather delays, approved unavoidable delays, and suspensions of the Work. The amount withheld under this subparagraph will be based upon the liquidated damages amount per day set forth in Contract Documents multiplied by
11/4/2020
60
the number of days the Contractor’s approved progress schedule, in the opinion of the Engineer, indicates the Contract may exceed the Contract Time. 7. Failure of the Contractor to perform any of the Contractor’s other obligations under the Contract, including but not limited to: a. Fa ilure of the Contractor to provide the Engineer with a field office when required by the Contract Provisions. b. Failure of the Contractor to protect survey stakes, markers, etc., or to provide adequate survey Work as required by Section 1-05.4. c. Failure of the Contractor to correct defective or unauthorized Work (Section 1-05.7). d. Failure of the Contractor to furnish a Manufacturer’s Certificate of Compliance in lieu of material testing and inspection as required by Section 1-06.3. e. Failure to submit weekly payrolls, Intent to Pay Prevailing Wage forms, or correct underpayment to employees of the Contractor or subcontractor of any tier as required by Section 1-07.9. f. Failure of the Contractor to pay worker’s benefits (Title 50 and Title 51 RCW) as required by Section 1-07.10. g. Failure of the Contractor to submit and obtain approval of a progress schedule per Section 1-08.3. The Contractor authorizes the Engineer to act as agent for the Contractor disbursing such funds as have been withheld pursuant to this Section to a party or parties who are entitled to payment. Disbursement of such funds, if the Engineer elects to do so will be made only after giving the Contractor 15 calendar days prior written notice of the Contracting Agency’s intent to do so, and if prior to the expiration of the 15-calendar day period, 1. No legal action has commenced to resolve the validity of the claims, and 2. The Contractor has not protested such disbursement. A proper accounting of all funds disbursed on behalf of the Contractor in accordance with this Section will be made. A payment made pursuant to this section shall be considered as payment made under the terms and conditions of the Contract. The Contracting Agency shall not be liable to the Contractor for such payment made in good faith.
1-09.9(3) Final Payment Section 1-09.9(3) is a new section: (******) Upon Acceptance of the Work by the Contracting Agency, the final amount to be paid the Contactor will be calculated based upon a Final Progress Estimate made by the Engineer. Acceptance by the Contractor of the final payment shall be and shall operate as a release: 1. To the Contracting Agency of all claims and all liabilities of the Contractor, other than claims in stated amounts as may be specifically excepted in writing by the Contractor; 2. For all things done or furnished in connection with the Work ; 3. For every act and neglect by the Contracting Agency; and 4. For all other claims and liability relating to or arising out of the Work. A payment (monthly, final, retainage, or otherwise) shall not release the Contractor or the Contractor’s Surety from any obligation required under the terms of the Contract Documents or the Contract Bond; nor shall such payment constitute a waiver of the Contracting Agency’s ability to investigate and act upon findings of non-compliance with the WMBE requirements of the Contract;
11/4/2020
61
nor shall such payment preclude the Contracting Agency from recovering damages, setting penalties, or obtaining such other remedies as may be permitted by law. Before the Work will be accepted by the Contracting Agency, the Contractor shall submit an affidavit, on the form provided by the Engineer, of amounts paid to certified disadvantaged (DB), minority (MBE) or women business enterprises (WBE) participating in the Work . Such affidavit shall certify the amounts paid to the DB, MBE or WBE subcontractors regardless of tier. On federally funded projects the Contractor may also be required to execute and furnish the Contracting Agency an affidavit certifying that the Contractor has not extended any loans, gratuity or gift and money pursuant to Section 1-07.19 of these Specifications. If the Contractor fails, refuses, or is unable to sign and return the Final Progress Estimate or any other documents required for the final acceptance of the Contract, the Contracting Agency reserves the right to establish a completion date and unilaterally accept the Contract. Unilateral acceptance will occur only after the Contractor has been provided the opportunity, by written request from the Engineer, to voluntarily submit such documents. If voluntary compliance is not achieved, formal notification of the impending unilateral acceptance will be provided by certified letter from the Engineer to the Contractor that will provide 30 calendar days for the Contractor to submit the necessary documents. The 30-calendar day deadline shall begin on the date of the postmark of the
certified letter from the Engineer requesting the necessary documents. This reservation by the Contracting Agency to unilaterally accept the Contract will apply to contracts that are completed in accordance with Section 1-08.5 and for contracts that are terminated in accordance with Section 1-08.10. Unilateral acceptance of the Contract by the Contracting Agency does not relieve the Contractor of the provisions under contract or of the responsibility to comply with all laws, ordinances, and federal, state, and local regulations that affect the Contract. The date the Contracting Agency unilaterally signs the Final Progress Estimate constitutes the final acceptance date (Section 1-05.12).
1-09.11 Disputes and Claims
1-09.11(2) Claims Paragraph 5 is revised with the following: (******) Failure to submit with the Final Application for Payment such information and details as described in this section for any claim shall operate as a waiver of the claims by the Contractor as provided in Section 1-09.9.
1-09.11(3) Time Limitations and Jurisdiction Paragraph 1, Sentence 1 is revised with the following: (******) …such claims or causes of action shall be brought in the Superior Court of the county where the Work is performed.
11/4/2020
62
1-09.13 Claims and Resolutions
1-09.13(3) Claims $250,000 or Less Delete this Section and replace it with the following: (******) The Contractor and the Contracting Agency mutually agree that those claims that total $250,000 or less, submitted in accordance with Section 1-09.11 and not resolved by nonbonding ADR processes, shall be resolved through litigation, unless the parties mutually agree in writing to resolve the claim through binding arbitration.
1-09.13(3)A Administration of Arbitration Revise the third paragraph to read: (******) The Contracting Agency and the Contractor mutually agree to be bound by the decision of the arbitrator, and judgment upon the award rendered by the arbitrator may be entered in the Superior Court of the county in which the Contracting Agency’s headquarters are located. The decision of the arbitrator and the specific basis for the decision shall be in writing. The arbitrator shall use the Contract as a basis for decisions.
1-09.13(3)B Procedures to Pursue Arbitration Section 1-09.13(3)B is supplemented with the following: (******) The findings and decision of the board of arbitrators shall be final and binding on the parties, unless the aggrieved party, within 10 days, challenges the findings and decision by serving and filing a petition for review by the superior court of King County, Washington. The grounds for the petition for review are limited to showing that the findings and decision: 1. Are not responsive to the questions submitted; 2. Is contrary to the terms of the contract or any component thereof; 3. Is arbitrary and/or is not based upon the applicable facts and the law controlling the issues submitted to arbitration. The board of arbitrators shall support its decision by setting forth in writing their findings and conclusions based on the evidence adduced at any such hearing. The arbitration shall be conducted in accordance with the statutes of the State of Washington and court decisions governing such procedure. The costs of such arbitration shall be borne equally by the Contracting Agency and the Contractor unless it is the board's majority opinion that the Contractor's filing of the protest or action is capricious or without reasonable foundation. In the latter case, all costs shall be borne by the Contractor.
11/4/2020
63
1-09.14 Payment Schedule
Measurement and Payment Schedule for Bid Items in This Project Proposal Section 1-09.14 is a new section: (******)
GENERAL
1-09.14(1) Scope Section 1-09.14(1) is a new section: (******) A. Payment for the various items of the bid sheets, as further specified herein, shall include all compensation to be received by the Contractor for furnishing all tools, equipment, supplies, and manufactured articles, and for all labor, operations, and incidentals appurtenant to the items of Work being described, as necessary to complete the various items of the Work all in accordance with the requirements of the Contract Documents, including all appurtenances thereto, and including all costs of compliance with the regulations of public agencies having jurisdiction, including Safety and Health Administration of the U.S. Department of Labor (OSHA). No separate payment will be made for any item that is not specifically set forth in the Bid Schedules, and all costs therefore shall be included in the prices named in the Bid Schedules for the various appurtenant items of Work described in these Special Provisions and shown on the Plans. B. The Contracting Agency shall not pay for material quantities, which exceed the actual measured amount used and approved by the Engineer. C. It is the intention of these Specifications that the performance of all Work under the bid for each item shall result in the complete construction, in an accepted operating condition, of each item. Work and material not specifically listed in the proposal but required in the Plans, Specifications, and general construction practice, shall be included in the bid price. No separate payment will be made for these incidental items.
1-09.14(2) Bid Items Section 1-09.14(2) is a new section: (******) This section describes the bid items. Measurement and Payment, where described in a bid item,
shall supersede Measurement and Payment listed in other sections of the Special Provisions and
Standard Specifications. Several bid items listed below are included in Schedules A, B, and C. In no case shall any bid item that is installed be considered as part of more than one schedule:
• Schedule A: Work Associated with the Storm pipes, manholes, lateral connections, cleanouts, outfall, sidewalk and curb and gutter restoration, required asphalt restoration. This Schedule falls under State Sales Tax Rule 171 (see section 1-07.2(2)) and state retail sales taxes shall be included in bid items prices.
• Schedule B: Work Associated with the Sewer pipes, manholes, side sewers, and required asphalt restoration. This Schedule falls under State Sales Tax Rule 170 (see section 1-07.2(3)) and state retail sales taxes shall not be included in bid items prices. Rather, the Contractor shall collect retail sales tax on the full contract amount.
• Schedule C: Work Associated with the new Water lines, including pipeline, fittings, concrete blocking, utility relocations, sidewalk and curb and gutter restoration for the water main
11/4/2020
64
work, and required asphalt restoration. This Schedule falls under State Sales Tax Rule 170 (see section 1-07.2(3)) and state retail sales taxes shall not be included in bid items prices. Rather, the Contractor shall collect retail sales tax on the full contract amount.
The following subsection provides the measurement and payment information of the Bid Items
common to two or more schedules.
1-09.14(2)A Mobilization & Demobilization (Bid Item A-1, B-1 and C-1) – Lump Sum Measurement for “Mobilization & Demobilization” will be lump sum. The lump sum price shown will cover the complete cost of furnishing and installing, complete and in-place all Work and materials necessary to move and organize equipment and personnel onto the job site, provide and maintain all necessary support facilities and utilities, obtain all necessary permits and licenses, prepare the site for construction operations, and maintain the site and surrounding areas during construction, provide protection of existing utilities, provide component and system testing, and move all personnel and equipment off the site after contract completion.
The Contractor shall prepare a Work Plan that shall include the following: A. Mobilization Plan showing the proposed location for storage of all equipment and materials. Storage shall not interfere with use of the City ROW and commercial and residential access. For any proposed storage on private property outside the easement or work area, the Contractor shall obtain a Temporary Use Permit for storage areas on private property. The Contractor shall be responsible for all fees, applications, and work needed to obtain the permit. The Contractor shall allow 3 to 4 weeks to obtain the Temporary Use Permit from the City. B. Temporary Erosion and Sediment Control Plan for all stages of the project C. Traffic Control Plan, including provisions for cleaning and sweeping of any impacted roadways. D. Trench Excavation Safety Systems plan/provisions. E. Identify Disposal Sites for various waste materials and provide copies of the site’s permits, licenses, and approvals. F. Pedestrian Handling Plan. The Work Plan shall be submitted to the City for review and approval within 10 days of the contract award. Payment for “Mobilization & Demobilization” will be made at the lump sum amount bid (NOT to exceed 80% of bid price prior to completion of construction) based on the percent of completed Work as defined in the 2020 Standard Specifications for Road, Bridge, and Municipal Construction (WSDOT) for mobilization. Payment for the remaining 20% will be made upon completion and final clean-up of the construction site. Such payment will be complete compensation for all mobilization of employees, equipment and materials, Mobilization Plan, Work Plan, preparation of all necessary submittals, bonds, insurance, site improvements, permits, clean-up, Contaminated Soil and Groundwater Handling and Management Plan, safety plan, and other plans/submittals not specifically covered in bid items, etc. all in conformance with the Contract Documents. This bid item may not be more than
ten percent (10%) of the total amount of Bid for the schedule.
11/4/2020
65
1-09.14(2)B Trench Safety Systems (Bid Item A-2, B-2 and C-2) – Lump Sum Section 1-09.14(2)B is a new section: (******) Measurement for “Trench Safety Systems” will be per the lump sum bid price based on a percentage defined as the amount of storm/sewer/water pipelines installed divided by the total length of sewer/storm/water pipe shown to be installed in conformance with the Contract Documents. Payment for “Trench Safety Systems” will be made at the measured percentage amount for the pay period times the lump sum amount bid, said payment will be complete compensation for all equipment, labor, materials, hauling, planning, design, engineering, submittals, furnishing and constructing and removal and disposal of such temporary sheeting, shoring, and bracing complete as required under the provisions of any permits and in the requirements of OSHA and RCW Chapter 49.17, etc., required to complete this item of Work in conformance with the Contract Documents. The work includes, but not limited to, preparing and submitting a shoring plan stamped by a professional engineer registered in the State of Washington by the preconstruction conference.
1-09.14(2)C Construction Surveying, Staking, and As-Built Drawings (Bid Item A-3, B-3, and
C-3) – Lump Sum Section 1-09.14(2)C is a new section: (******) Measurement for “Construction Surveying, Staking and As-Built Drawings” information will be per the lump sum bid price and based on the percentage of total Work complete at the time of measurement. Payment may be prorated over the construction period based on the amount of work completed for construction surveying, staking and as-built information. Survey will be per Section 1-05.4 and Section 1-11. The as-built survey will be per Section 1-11. The contractor shall provide the City with a set of redline drawings with the as-built locations and elevations of all new utilities and construction work. Payment will be complete compensation for all labor, materials, equipment, tools, all incidental work needed to provide construction surveying and of the improvements (including providing a Washington State licensed surveyor for said work), staking in advance of pipe laying, fittings and structure installation, surveying the horizontal and vertical locations of all potholed existing utilities within the work area, verification and recording of the elevations of existing roadway centerline, crown, and edge of pavement to ensure that all roadways can be reconstructed to existing grade, and preparation of cut-sheets. Said payment will be complete compensation for all labor, materials, equipment, tools, all incidental work needed to provide as-built surveying, preparing “red line” as-built drawings for pay estimate submittal with fittings and dimensions of existing and proposed facilities installed or encountered during the pay period, furnishing an electronic file with construction drawings stamped and signed by a licensed land surveyor that contains the as-built information and copies of field notes, and furnishing and resetting property corners when disturbed by the contractor’s activities. No more than 50% of the bid amount for this item shall be paid prior to the review and acceptance of the as-constructed information by the Engineer.
11/4/2020
66
1-09.14(2)D Temporary Traffic Control (Bid Item A-4, B-4 and C-4) – Lump Sum Section 1-09.14(2)D is a new section: (******) Measurement for “Temporary Traffic Control” k will be will per the lump sum bid price and shall be based on the percentage of total Work complete, at the time of measurement in conformance with the Contract Documents. Payment for “Temporary Traffic Control” will be made at the measured percentage amount for the pay period times the lump sum bid amount. Payment will be complete compensation for preparing and submitting a traffic control plan and pedestrian handling plan as well as all labor, tools, materials, equipment used in accordance with the approved Traffic Control Plan and pedestrian handling plan that is not included in other bid items. The Lump Sum contract price shall be full pay for all costs for performing the work described in Section 1-10.3), and in the Traffic Control Information. Payment shall include but not be limited to providing for public convenience and safety, flaggers, traffic control supervisor, construction signs, detours, barricades, sequential arrow boards, a minimum of two Portable Changeable Message Signs, traffic control devices, truck-mounted attenuator, temporary striping, cleanup, etc. required to complete this item of Work in conformance with the Contract Documents and the Manual on Uniform Traffic Control Devices (MUTCD) and as directed by the Engineer and by the City’s Transportation Department. Also, included in the contract price is the cost to furnish traffic control services and equipment for construction surveying, staking, and as-built plans. All adjustments to the Traffic Control Plan are considered incidental, and no additional payment will be made for adjustments.
1-09.14(2)E Stormwater Pollution Prevention and TESC Plan and Implementation (Bid Item A-5,
B-5 and C-5) – Lump Sum Section 1-09.14(2)E is a new section: (******) Measurement for “Stormwater Pollution Prevention and TESC Plan and Implementation” will be based on the lump sum bid price in conformance with the Contract Documents. Temporary Erosion Control measures include inlet protection (catch basin inserts), cleaning catch basins, filter fabric fencing, construction entrance, straw mulch, plastic sheeting, etc. at a minimum. Other erosion control measures may be necessary depending on weather and site conditions, including but not limited to, hay bales, placement of plastic sheets over exposed soil and stockpiles, mulching, netting, etc., and any other activities needed to control erosion from the project. The Contractor shall update the DRAFT Storm Water Pollution Prevention Plan, develop a "red lined" Temporary Erosion and Sediment Control plan and submit it to the City for review and approval. The plan shall be based on the City of Renton Surface Water Design Manual, and proper construction practices. After the erosion control system is installed the Contractor shall make any field adjustments necessary to reduce or eliminate any erosion and discharge of sediment-laden water. All adjustments are considered incidental and no additional payment will be made for adjustments. The lump sum price for “Stormwater Pollution Prevention and TESC Plan and Implementation” shall be full pay for all labor, material, tools, equipment, and other incidental costs required to prepare the Stormwater Pollution Prevention Plan and Temporary Erosion and Sediment Control Plan as
11/4/2020
67
described in Section 1-07.15 and implement the temporary erosion and sediment control BMP’s including but not limited to installation, monitoring, and maintenance of sediment ponds, straw wattles, filter fabric fencing, pumping of construction water, coffer dams, temporary storm drain diversions including temporary piping, check dams, cover measures including plastic covering, street sweeping, collection and disposal of wastewater from asphalt and concrete cutting operations and other work necessary to meet the contract and permit requirements, not otherwise shown as a separate payment item. Payment shall also include the Contractor’s use of Baker Tanks, as needed during construction and associated labor, tools, equipment and incidental costs including Baker Tank mobilization, set up, maintenance, and relocation as work progresses, and incidentals required to use Baker Tanks, when needed to meet regulatory discharge requirements. Work shall include coordination, permitting, fees, and treatment required by King County as required in 1-07.15 if discharging to the sanitary sewer.
1-09.14(2)F Landscape Restoration (Bid Item A-6, B-6 and C-6) –– Lump Sum Section 1-09.14(2)F is a new section: (******) Measurement for “Landscape Restoration” work will be based on the percentage of total Work complete, at the time of measurement in conformance with the Contract Documents. Payment for “Landscape Restoration” will be made at the unit price bid per lump sum, which payment will be complete compensation for all labor, equipment, materials, hauling, excavation, sod, grass seed, topsoil, landscape bark, gravel, concrete, planting, preparation, compaction, watering, restoration, etc. required to restore landscaped, grass, and planted areas to an equal or better condition in conformance with the Contract Documents. It shall include but not be limited to the following: • Hauling and disposing unsuitable, surplus and/or waste materials • Replacing and restoring any landscaping, rockeries, walls, tree removal and replacement, trees, bark, and other improvements disturbed by construction activities, as directed by the Engineer • Preparation, placement, and maintenance of 8” depth topsoil and lawn sod in conformance with the contract documents. All lawn areas shall be replaced with topsoil and sod. Bare areas shall be replaced at a minimum with mulch and seed. • Site cleanup of all areas disturbed by contractor’s activities to match the conditions as closely as existed prior to contractor’s beginning work or as directed by the Engineer.
1-09.14(2)G Select Imported Trench Backfill (Bid Item A-7, B-7 and C-7) – Ton Section 1-09.14(2)G is a new section: (******) Measurement for “Select Imported Trench Backfill” will be measured in tons based on the weight of material installed into the Work in conformance with the Contract Documents. Certified weight tickets will accompany each load, a copy of tickets will be given to the Engineer daily. Wasted materials will not be included in the measurement or payment. Only materials placed within the pay limits shown will be considered for payment. Material placed outside of the pay limits shown on the Plans or as approved by the Engineer will be deducted from the certified tickets. Payment for “Select Imported Backfill” will be made at the amount bid per ton, which payment will be complete compensation for all labor, materials, tools, equipment, incidentals necessary to furnish
11/4/2020
68
and install select import backfill, hauling, placement, compaction, removal, haul and disposal of unsuitable excavated materials, waste and surplus materials, etc., required to complete this item of Work in conformance with the Contract Documents.
1-09.14(2)H Hot Mix Asphalt Patch Including CSTC (Bid Item A-8, B-8 and C-8) – Square Yard Section 1-09.14(2)H is a new section: (******) Measurement for “Hot Mix Asphalt Patch Including CSTC ” shall be measured in Square Yards. Pavement repair measurement width shall be as defined by the limit of trench patch payment shown in the Contract Documents, unless otherwise approved by the Engineer. Wasted materials will not be included in the measurement or payment. Only materials placed within the pay limits shown will be considered for payment. Material placed outside of the pay limits shown on the plans or as approved by the Engineer will be deducted from the certified tickets. Payment for “Hot Mix Asphalt Patch including CSTC ” will be made at the amount bid per Square Yard, which payment will be complete compensation for all labor, materials, tools, equipment required to complete the work specified in the contract documents and plans, and shall include but not be limited to the following:
• Sawcutting, removal and disposal of existing pavement
• Placing and compacting crushed surfacing top course for utility trenches
• Furnishing, placing, and compacting hot mix asphalt materials for pavement repair
• Sealing all cold joints
• Tack coat
• Joint seal
• Asphalt Sidewalk Transitions
• Hauling
• Aggregate
• Sweeping
• Adjustment of utilities to grade
• Furnishing and preparing subgrade
• Cleanup
• All other incidentals necessary for a complete paving and restoring the roadway grade to existing elevations.
1-09.14(2)I Remove and Replace Concrete Sidewalk and Driveway (Bid Item A-9, B-9 and C-9) –
Square Yard Section 1-09.14(2)I is a new section: (******) Measurement for “Remove and Replace Concrete Sidewalk and Driveway” will be based on square yard of concrete sidewalk and driveway, to match existing, restored to a saw-line line cut in conformance with the contract documents. Payment for “Remove and Replace Concrete Sidewalk and Driveway” will be made at the unit price bid per square yard, which payment will be complete compensation for all labor, equipment, materials, tools and incidentals to remove and replace cement concrete driveway and sidewalk in conformance with the Contract Documents, and shall include but not be limited to the following:
• Sawcutting existing driveway, curb, sidewalk, and existing pavement
11/4/2020
69
• Removal and disposal of surplus, unsuitable and/or waste materials
• Placing and compacting crushed surfacing top course for subgrade
• Furnishing and installing formwork
• Furnishing, placing, compacting, and finishing concrete for new driveway and/or sidewalk surface. Gravel driveway and gravel parking areas, if existing, shall be restored under landscape restoration.
1-09.14(2)J Remove and Replace Concrete Curb and Gutter (Bid Item A-10, B-10 and C-10) – Linear
Foot Section 1-09.14(2)J is a new section: (******) Measurement for “Remove and Replace Concrete Curb and Gutter” shall be per linear foot of curb repair required for installation of utilities in conformance with the Contract Documents. Payment for “Remove and Replace Concrete Curb and Gutter” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Sawcutting, removal and disposal of existing curb and gutter
• Removal and disposal of surplus, unsuitable and /or waste materials
• Placing and compacting crushed surfacing top course for subgrade
• Furnishing and installing temporary formwork
• Furnishing and placing concrete and joint filler for new curb and gutter
1-09.14(2)K Replace Pavement Markings (Bid Item A-11, B-11 and C-11) – Lump Sum Section 1-09.14(2)K is a new section: (******) Measurement for “Replace Pavement Markings” will be per lump sum in conformance with the Contract Documents. Payment for “Replace Pavement Markings” will be made at contract lump sum and constitute full compensation for all material, equipment, tools, labor and all else necessary for and incidental to re-establish existing pavement markings in accordance with the plans and specifications.
1-09.14(2)L Removal and Replacement of Unsuitable Foundation Material (Bid Item A-12, B-12
and C-12) – TON Section 1-09.14(2)L is a new section:
(******) Measurement for “Removal and Replacement of Unsuitable Foundation Material” will be measured in Tons based on the placed weight of material installed in conformance with the Contract Documents. Placement of foundation material will be measured only for the area(s) authorized by the Engineer. Certified tickets will accompany each load, a copy of tickets will be given to the Engineer daily. Wasted materials will not be included in the measurement or payment. Payment for “Removal and Replacement Of Unsuitable Foundation Material” will be made at the unit bid price, which will be complete compensation for all labor, materials, tools, equipment, excavation,
11/4/2020
70
foundation materials, haul, placement, water, compaction, removal haul and disposal of waste material, etc., required to complete this item of Work in conformance with the Contract Documents. Payment for this item will be only for the removal and replacement of unsuitable material requested by the City.
1-09.14(2)M CCTV Inspection (Bid Item A-13 and B-13) – Linear Foot Section 1-09.14(2)M is a new section:
(******) Measurement for “CCTV inspection” will be per linear foot of storm and sanitary sewer pipe inspected in conformance with section 7-17.3(2)H and the Contract Documents. Payment for “CCTV Inspection” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Bypass sewer pumping (if needed),
• CCTV inspection of all new open-cut installed storm and sanitary sewers,
• Delivery of the CCTV inspections entirely in a PACP compatible format data base on an External HDD or USB flash drive to the Engineer. Costs for additional Television Inspection required to verify corrections or replacement of pipe, or done solely for the Contractor's convenience, shall be at the Contractor's sole expense.
1-09.14(2)N Site Specific Utility Potholing (Bid Item A-14 and C-13) – Each Section 1-09.14(2)N is a new section:
(******) Measurement for “Site Specific Potholing ” will be per each for each location shown on the engineering drawings, or as directed by the Engineer. Work shall be performed in conformance with the Contract Documents (see Section 1-07.17(3) for Site Specific Potholing). Payment for “Site Specific Potholing ” will be made at the unit price bid per each, which payment will be complete compensation for all labor, tools, equipment, and materials required to complete the work in conformance with the Contract Documents including but not limited to pavement and concrete cutting, excavation, dewatering, potholing for utility location, removal, hauling and disposal of all pavement, waste and excess materials, shoring, relocating or coordinating relocation of the unknown utility, placement of backfill (native) material, compaction, water, grading, temporary patch, and cleaning. Payment also includes all temporary traffic control operations, utility one-call and, coordination with utility owner, and temporary restoration work associated with potholing. If the native material is unsuitable to use to refill the pothole, imported backfill may be used. Imported backfill will be paid under a separate bid item. Permanent pavement patch will be paid under a separate bid item. Prior to beginning construction of the new underground utility, the Contractor shall pothole the existing underground utilities at the locations required by the Plans, or as identified by the Engineer. The Contractor shall perform potholing a minimum of ten (10) working days prior to construction at the pothole location to allow for potential revisions. The City shall have ten (10) working days after
11/4/2020
71
receiving the written results to make any design revisions to the plans, if needed. The Engineer may revise the design as needed if there is a conflict with existing utilities. The Contractor shall not have cause for claim of downtime or any other additional costs associated with “waiting” if the City provides design revisions (related to the information supplied per this section) within ten (10) working days after the Contractor provides the written potholing results.
1-09.14(2)O Replace Survey Monument (Bid Item A-15 and C-14) – Each Section 1-09.14(2)O is a new section:
(******) “Replace Survey Monument” shall be per Section 1-05.4 and Section 1-11. The surveyor shall comply with WAC 332-120 Survey Monuments – Removal or Destruction. Contractor shall contact the City of Renton’s Property & Technical Services Manager prior to performing work. The work includes, but is not limited to: A. Locating and surveying all existing monuments, and providing the City with a copy of the survey results. B. Providing the City with a copy of the Application to Remove a Monument submitted to the State DNR for each monument. C. Resetting the monuments in the original positions, or setting witness monuments if needed. All new monuments, discs, materials, and the work needed to set them are included. D. Providing the City with a copy of the Completion Report submitted to the State DNR for each monument. E. Submitting a City Monument Card to the City showing the new monument and monument ties. Existing monument ties will be used whenever possible. New ties shall be set where needed. New monuments and monument cards are subject to City review and approval. Any corrections or resurveying needed shall be incidental. F. All work shall be located per the City of Renton Survey Control Network. Coordinates shall be given for the new and existing monument. Measurement for “Replace Survey Monument ” shall be per each survey monument replaced, including each witness monument placed (if needed). This bid item shall also be used for new survey monument where required on the plans. Payment for “Replace Survey Monument” will be complete compensation for all labor, materials, equipment, travel, surveying, documentation, permits, and replacement of each survey monument as shown on the plans required to complete this item of work in conformance with the Contract Documents. Up to 50 percent of the unit bid price for each monument will be paid after each existing monument is surveyed, and the City receives a copy of the Application to Remove a Monument submitted to the State DNR. The remaining 50 percent of the unit bid price for each monument will be paid after each new monument is placed, a copy of the Completion Report and a new Monument Card is submitted to the City, and the City review and acceptance of the new monument and Monument Card.
11/4/2020
72
The following subsection provides the measurement and payment information of the Bid Items
specific to Schedule A – Storm Water.
1-09.14(2)AA Stormwater Minor Changes (Bid Item A-16) – Estimated Section 1-09.14(2)AA is a new section:
(******) For the purpose of providing a common proposal for all bidders, the Contracting Agency has entered an amount for “Stormwater Minor Change” in the Proposal to become a part of the total bid by the Contractor. At the discretion of the Contracting Agency, all or part of this estimated amount may be used in lieu of the more formal procedure as outlined in Section 1-04. The unit contract price for Minor Changes is given in the Schedule of Prices and shall not be changed by the bidder. All work and payment under this item will be authorized in writing by the City Project Manager or Manager. Payment will be determined in accordance with Section 1-09.4. Payment for this item will be only for the changes and amounts approved by the City. If no changes are authorized under this bid item final payment for this item will be $0 (zero).
1-09.14(2)AB Resolution of Utility Conflicts with Stormwater (Bid Item A-17) – Force Account Section 1-09.14(2)AB is a new section:
(******) Payment will be made at the discretion of the Engineer, for the following bid item(s) in accordance with Section 1-09.6 when included in the Proposal: "Resolution of Utility Conflicts with Stormwater," per Force Account. In no way shall the work described under “Resolution of Utility Conflicts” relieve Contractor of any of the responsibilities described in Section 1-07.17, and elsewhere in the Contract Documents. Resolution of utility conflicts is included as a bid item for use in resolving any new identified utility conflicts not otherwise shown on the Contract Drawing or Specifications that are identified during the course of construction. Resolution of conflicts with gas services, water services, and sewer services shall be incidental to other pay items. To provide a common basis for all bidders, the Contracting Agency has entered an amount for the item “Resolution of Utility Conflicts with Stormwater" in the Proposal to become a part of the total bid by the Contractor. Payment for this item will be only for the changes and amounts approved by the City. If no changes are authorized under this bid item, final payment for this item will be $0 (zero).
1-09.14(2)AC Construction Geotextile For Separation Bid Item A-18) – Square Yard Section 1-09.14(2)AC is a new section: (******) Measurement for “Construction Geotextile For Separation” will be per square yard installed as measured by the length installed by the standard width of the trench/sections as shown on the Plans. All use of geotextile shall be pre-approved by the Engineer. Payment will be made at contract unit price and will constitute full compensation for all material, equipment, tools, labor, and all necessary for and incidental to the installation of geotextile in
11/4/2020
73
accordance with the Contract Documents and as directed by the Engineer. The geotextile bid item is exempt from Section 1-04.6 and no price adjustment will be made for variation in actual quantity used. The “Construction Geotextile for Separation” bid item is exempt from Section 1-04.6 and no price adjustment will be made for variation in actual quantity used.
1-09.14(2)AD Storm Drain, 6-inch Diameter [CPEP] (Bid Item A-19) – Linear Foot Section 1-09.14(2)AD is a new section: (******) Measurement for “Storm Drain Pipe, 6-in Diameter [CPEP]” will be based on linear foot measured horizontally over the centerline of the installed pipe from the center of structures in conformance with the Contract Documents. Payment for furnishing and installing “Storm Drain Pipe, 6-in Diameter [CPEP]” will be made at the amount bid per linear foot, which payment will be complete compensation for:
• All labor, materials, equipment and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal and excavation
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material in the excavation necessary to construct the improvements including but not limited to: existing pipes; catch basins; manholes; structures; and abandoned utilities
• Pipe of the size and material type required, gaskets, fittings and adaptors
• Installation, laying and jointing pipe and fittings
• Furnishing and placing pipe zone bedding material
• Furnishing, placement and compaction of imported trench backfill
• Appurtenances, ethafoam pads, water, grading, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents
• Removal of pipe and catch basins beyond the excavation where shown on the Drawings or where directed by the Engineer as well as plugging existing pipes to be abandoned and plugging existing pipes where sections have been removed for the storm installation, and providing end caps were shown on the plans. These items shall not be limited to those mentioned on the Plans or specified herein.
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching. Contractor is advised that year-round groundwater seeps entering the drainage system must be controlled and bypassed and shall be paid for as a part of this bid item. Select Imported Trench Backfill above the pipe zone bedding is included in other bid items.
11/4/2020
74
1-09.14(2)AE Storm Drain, 8-inch Diameter [CPEP] (Bid Item A-20) – Linear Foot Section 1-09.14(2)AE is a new section: (******) Measurement for “Storm Drain Pipe, 8-in Diameter [CPEP]” will be based on linear foot measured horizontally over the centerline of the installed pipe from the center of structures in conformance with the Contract Documents. Payment for furnishing and installing “Storm Drain Pipe, 8-in Diameter [CPEP]” will be made at the amount bid per linear foot, which payment will be complete compensation for:
• All labor, materials, equipment and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal and excavation
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material in the excavation necessary to construct the improvements including but not limited to: existing pipes; catch basins; manholes; structures; and abandoned utilities
• Pipe of the size and material type required, gaskets, fittings and adaptors
• Installation, laying and jointing pipe and fittings
• Furnishing and placing pipe zone bedding material
• Furnishing, placement and compaction of imported trench backfill
• Appurtenances, ethafoam pads, water, grading, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents.
• Removal of pipe and catch basins beyond the excavation where shown on the Drawings or where directed by the Engineer as well as plugging existing pipes to be abandoned and plugging existing pipes where sections have been removed for the storm installation, and providing end caps were shown on the plans. These items shall not be limited to those mentioned on the Plans or specified herein.
• Replacing, protecting, and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching. Contractor is advised that year-round groundwater seeps entering the drainage system must be controlled and bypassed and shall be paid for as a part of this bid item. Select Imported Trench Backfill above the pipe zone bedding is included in other bid items.
1-09.14(2)AF Storm Drain, 8-inch Diameter [DI] (Bid Item A-21) – Linear Foot Section 1-09.14(2)AF is a new section: (******) Measurement for Storm “Drain Pipe, 8-in Diameter [DI]” will be based on linear foot measured horizontally over the centerline of the installed pipe from the center of structures in conformance with the Contract Documents. Payment for furnishing and installing “Storm Drain Pipe, 8-in Diameter [DI]” will be made at the amount bid per linear foot, which payment will be complete compensation for:
• All labor, materials, equipment and hauling
11/4/2020
75
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal and excavation
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material in the excavation necessary to construct the improvements including but not limited to: existing pipes; catch basins; manholes; structures; and abandoned utilities
• Pipe of the size and material type required, gaskets, fittings and adaptors
• Installation, laying and jointing pipe and fittings
• Furnishing and placing pipe zone bedding material
• Furnishing, placement and compaction of imported trench backfill
• Appurtenances, ethafoam pads, water, grading, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents.
• Removal of pipe and catch basins beyond the excavation where shown on the Drawings or where directed by the Engineer as well as plugging existing pipes to be abandoned and plugging existing pipes where sections have been removed for the storm installation, and providing end caps were shown on the plans. These items shall not be limited to those mentioned on the Plans or specified herein.
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching. Contractor is advised that year-round groundwater seeps entering the drainage system must be controlled and bypassed and shall be paid for as a part of this bid item. Select Imported Trench Backfill above the pipe zone bedding is included in other bid items.
1-09.14(2)AG Storm Drain, 12-inch Diameter [PPP] (Bid Item A-22) – Linear Foot Section 1-09.14(2)AG is a new section: (******) Measurement for “Storm Drain Pipe, 12-in Diameter [PPP]” will be based on linear foot measured horizontally over the centerline of the installed pipe from the center of structures in conformance with the Contract Documents. Payment for furnishing and installing Storm Drain Pipe, 12-in Diameter [PPP] will be made at the amount bid per linear foot, which payment will be complete compensation for:
• All labor, materials, equipment and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal and excavation
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material in the excavation necessary to construct the improvements including but not limited to: existing pipes; catch basins; manholes; structures; and abandoned utilities
• Pipe of the size and material type required, gaskets, fittings and adaptors
• Installation, laying and jointing pipe and fittings
• Furnishing and placing pipe zone bedding material
• Furnishing, placement and compaction of imported trench backfill
11/4/2020
76
• Appurtenances, ethafoam pads, water, grading, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents.
• Removal of pipe and catch basins beyond the excavation where shown on the Drawings or where directed by the Engineer as well as plugging existing pipes to be abandoned and plugging existing pipes where sections have been removed for the storm installation, and providing end caps were shown on the plans. These items shall not be limited to those mentioned on the Plans or specified herein.
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching. Contractor is advised that year-round groundwater seeps enter the drainage system must be controlled and bypassed and shall be paid for as a part of this bid item. Select Imported Trench Backfill above the pipe zone bedding is included in other bid items.
1-09.14(2AH Storm Drain, 12-inch Diameter [DI] (Bid Item A-23) – Linear Foot Section 1-09.14(2)AH is a new section: (******) Measurement for “Storm Drain Pipe, 12-in Diameter [DI”] will be based on linear foot measured horizontally over the centerline of the installed pipe from the center of structures in conformance with the Contract Documents. Payment for furnishing and installing “Storm Drain Pipe, 12-in Diameter [DI]” will be made at the amount bid per linear foot, which payment will be complete compensation for:
• All labor, materials, equipment and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal and excavation
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material in the excavation necessary to construct the improvements including but not limited to: existing pipes; catch basins; manholes; structures; and abandoned utilities
• Pipe of the size and material type required, gaskets, fittings and adaptors
• Installation, laying and jointing pipe and fittings
• Furnishing and placing pipe zone bedding material
• Furnishing, placement and compaction of imported trench backfill
• Appurtenances, ethafoam pads, water, grading, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents
• Removal of pipe and catch basins beyond the excavation where shown on the Drawings or where directed by the Engineer as well as plugging existing pipes to be abandoned and plugging existing pipes where sections have been removed for the storm installation, and providing end caps were shown on the plans. These items shall not be limited to those mentioned on the Plans or specified herein.
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching.
11/4/2020
77
Contractor is advised that year-round groundwater seeps enter the drainage system must be controlled and bypassed and shall be paid for as a part of this bid item. Select Imported Trench Backfill above the pipe zone bedding is included in other bid items.
1-09.14(2)AI Trench Drain (Bid Item A-24) – Linear Foot Section 1-09.14(2)AI is a new section: (******) Measurement for “Trench Drain” will be based on linear foot measured horizontally over the centerline of the trench drain installed as measured from the end of the grates in conformance with the Contract Documents. Payment for furnishing and installing “Trench Drain” will be made at the amount bid per linear foot, which payment will be complete compensation for:
• All labor, materials, equipment and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement/concrete cutting (sawcutting), pavement removal and disposal, concrete curb and gutter removal and disposal and excavation
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material in the excavation necessary to construct the improvements including but not limited to; existing pipes; structures; and abandoned utilities
• Placing and compacting crushed surfacing top course bedding, trench drain and grate, replacement concrete curb, connecting pipe at termination of trench drain, gaskets, fittings and adaptors, installation, laying and jointing trench drain and fittings
• Appurtenances, ethafoam pads
• Placement of backfill material, compaction, water and grading, submittals, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents.
• Furnishing and placing temporary pavement patching Select Imported Trench Backfill used as backfill for the Trench Drain is included in other bid items.
1-09.14(2)AJ Connect Existing Lateral to New Storm Pipe (Bid Item A-25) – Each Section 1-09.14(2)AJ is a new section: (******) Measurement for “Connect Existing Lateral to New Storm Pipe” will be per each in conformance with Contract Documents. Payment for connect existing lateral to new storm pipe will be made at the unit price per each, which will be complete compensation for all labor, equipment, materials, excavation around and protection of existing pipe, cleaning the existing pipe, pipe sleeve or other fittings required to connect to existing pipe, and removal and disposal of waste material. Pipe material shall be under separate item.
11/4/2020
78
1-09.14(2)AK Connect New Storm Pipe to Existing Catch Basin (Bid Item A-26) – Each Section 1-09.14(2)AK is a new section: (******) Measurement for “Connect New Storm Pipe to Existing Catch Basin” will be per each in conformance with Contract Documents. Payment for “Connect New Storm Pipe to Existing Catch Basin” will be made at the unit price per each, which will be complete compensation for all labor, equipment, materials, excavation around and protection of existing structure, core drilling, cleaning the existing catch basin and other materials required to connect to existing catch basin.
1-09.14(2)AL Storm Lateral Cleanout - 6” or 8" Diameter (Bid Item A-27) – Each Section 1-09.14(2)AL is a new section: (******) Measurement for “Storm Lateral Cleanout – 6” or 8" Diameter” will be per each in conformance with Contract Documents. City may require an 8” diameter cleanout for an existing 6” lateral. Payment for “Storm Lateral Cleanout – 6” or 8" Diameter” will be made at the unit price per each, which will be complete compensation for all labor, equipment, materials, excavation around and protection of existing pipe, bedding, pipe associated with the cleanout riser including wye connection to lateral, pipe reducer fitting if transitioning from 6” to 8”, or other fittings/couplings required to connect to existing main pipe, removal and disposal of waste material, cast iron ring and cover, watertight plug, concrete pad, and furnishing and placing temporary pavement patching.
1-09.14(2)AM Catch Basin Type 1 (Bid Item A-28) – Each Section 1-09.14(2)AM is a new section: (******) Measurement for furnishing and installing “Catch Basin Type 1 ” will be per each for each catch basin installed in conformance with the Contract Documents. Payment for furnishing and installing “Catch Basin Type 1” will be made at the unit bid price per each, which will be complete compensation for:
• All labor, equipment, materials, and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal, excavation and shoring
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material including existing pipes and structures in the excavation and any abandoned utilities
• Furnishing and placing foundation material
• Precast concrete catch basin, gaskets, catch basin frame and lid, installation, adjustment of frames to grade, appurtenances, Kor-N-Seal boots (or approved equal), connections to new pipes, reconnections to existing pipes including pipe and couplings, placement of subsequent backfill materials, compaction, water, cleaning, and testing, etc. required in conformance with the Contract Documents.
• Furnishing and placing temporary pavement patching
11/4/2020
79
Select imported backfill material is included in other bid items. Maximum pay limit for select imported backfill material around structures shall be limited to 3-feet.
1-09.14(2)AN Catch Basin Type 1L with Special Frame and Grate (Bid Item A-29) – Each Section 1-09.14(2)AN is a new section: (******) Measurement for furnishing and installing “Catch Basin Type 1L” with special grate will be per each for each catch basin installed in conformance with the Contract Documents. Payment for furnishing and installing “Catch Basin Type 1L” with special grate will be made at the unit bid price per each, which will be complete compensation for:
• All labor, equipment, materials, and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal, excavation and shoring
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material including existing pipes and structures in the excavation and any abandoned utilities
• Furnishing and placing foundation material
• Precast concrete catch basin, gaskets, catch basin frame and lid, installation, adjustment of frames to grade, appurtenances, Kor-N-Seal boots (or approved equal), connections to new pipes, reconnections to existing pipes including pipe and couplings, placement of subsequent backfill materials, compaction, water, cleaning, and testing, etc. required in conformance with the Contract Documents.
• Furnishing and placing temporary pavement patching Select imported backfill material is included in other bid items. Maximum pay limit for select imported backfill material around structures shall be limited to 3-feet.
1-09.14(2)AO Catch Basin Type 2, 48-inch Diameter (Bid Item A-30) – Each Section 1-09.14(2)AO is a new section: (******) Measurement for “Catch Basin Type 2, 48-inch Diameter ” will be measured per each installed in conformance with the Contract Documents. Payment for “Catch Basin Type 2, 48-inch Diameter” will be made at the contract unit price and will constitute full compensation for:
• All labor, equipment, materials, and hauling
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, protecting and providing temporary support of existing utilities
• Pavement cutting (sawcutting), pavement removal, excavation and shoring
• Dewatering, temporary bypass pumping and control of water
• Removal and disposal of waste material including existing pipes and structures in the excavation and any abandoned utilities
• Furnishing and placing foundation material
• Precast concrete catch basin, gaskets, catch basin frame and lid, installation, adjustment of frames to grade, appurtenances, Kor-N-Seal boots (or approved equal), connections to new
11/4/2020
80
pipes, reconnections to existing pipes including pipe and couplings, placement of subsequent backfill materials, compaction, water, cleaning, and testing, etc. required in conformance with the Contract Documents.
• Furnishing and placing temporary pavement patching Select imported backfill material is included in other bid items. Maximum pay limit for select imported backfill material around structures shall be limited to 3-feet.
1-09.14(2)AP Controlled Density Fill (Bid Item A-31) – Cubic Yard Section 1-09.14(2)AP is a new section: (******) Measurement for “Control Density Fill” will be per cubic yard in conformance with the Contract Documents. All use of CDF shall be pre-approved by the Engineer. CDF used beyond the agreed amount or CDF used without prior Engineer approval will not be paid. Payment for “Control Density Fill” will be made at contract unit price and will constitute full compensation for all material, equipment, tools, labor, and all necessary for and incidental to the installation of Control Density Fill in accordance with the Contract Documents and as directed by the Engineer. Payment for this item will be only for the control density fill pre-approved by the City. If no control density fill is authorized under this bid item, final payment for this item will be $0 (zero). The control density fill bid item is exempt from Section 1-04.6 and no price adjustment will be made for variation in actual quantity used. The Control Density Fill bid item is exempt from Section 1-04.6 and no price adjustment will be made for variation in actual quantity used.
1-09.14(2)AQ Sewer Service Relocation for Stormwater Conflict (Bid Item A-32) – Each Section 1-09.14(2)AQ is a new section: (******) Measurement for “Sewer Service Relocation for Stormwater Conflict” will be per each in conformance with Contract Documents. Only those sewer service relocations authorized by the City in advance will be paid. Payment for “Sewer Service Relocation for Stormwater Conflict” will be made at the unit price per each, which will be complete compensation for all labor, equipment, material, to relocate an existing side sewer service to avoid a conflict with the new storm, including but not limited to hauling, sawcutting, excavation, dewatering, temporary control of sewer or sewer bypass pumping, removal and disposal of waste material including existing sewer service piping, pipe of the size and material type required, gaskets, fittings and adaptors, installation, laying and jointing pipe and fittings, furnishing and placing pipe zone bedding material and pipe zone fill material, appurtenances, placement of subsequent backfill materials, compaction, water, grading, cleaning, and testing, etc. required to complete the work in accordance with the Contract Documents. Select Imported Trench Backfill above the pipe zone bedding, if used, is included in other bid items. There shall be no separate payment for adjusting the new storm pipe profile to avoid a conflict with the sewer. This shall be considered incidental to other bid items.
11/4/2020
81
To provide a common basis for all bidders, the Contracting Agency has entered a quantity for this bid item, however, the actual quantity is unknown and may be zero. If no sewer service relocation for stormwater conflicts are authorized under this bid item, final payment for this item will be $0 (zero).
1-09.14(2)AR Abandon Existing Manhole (Bid Item A-33) –– Each Section 1-09.14(2)AR is a new section: (******) Measurement for “Abandon Existing Manhole” will be per each performed in conformance with the Contract Documents. The unit price per each for “Abandon Existing Manhole” shall be full pay for all labor, equipment, material, and equipment to plug pipe connections, remove and dispose of top 4 feet of structure and filling remaining structure with sand in accordance with the standard specifications. The ring and cover shall be salvaged if requested by the City.
The following subsection provides the measurement and payment information of the Bid Items
specific to Schedule B – Wastewater.
1-09.14(2)BA Furnish and Install 8-inch PVC Sewer Pipe (Bid Item B-14) –– Linear Foot Section 1-09.14(2)BA is a new section: (******) Measurement for “Furnish and Install 8-Inch PVC Sewer Pipe” will be based on linear footage measured horizontally over the centerline of the installed pipe. Payment for “Furnish And Install 8-Inch PVC Sewer Pipe” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation
• Furnishing, installing, laying and joining sewer pipes and fittings of the size and type shown, and all incidentals,
• Ethafoam pads (when needed),
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Air-Testing (if required)
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
11/4/2020
82
1-09.14(2)BB Furnish and Install 8-inch HDPE Sewer Pipe (Bid Item B-15) –– Linear Foot Section 1-09.14(2)BB is a new section: (******) Measurement for “Furnish and Install 8-Inch HDPE Sewer Pipe” will be based on linear footage measured horizontally over the centerline of the installed pipe. Payment for “Furnish And Install 8-Inch HDPE Sewer Pipe” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, installing, laying and joining sewer pipes, fittings and couplings of the size and type shown, and all incidentals,
• Ethafoam pads (when needed),
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Air-Testing (if required)
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BC Furnish and Install 10-inch PVC Sewer Pipe (Bid Item B-16) –– Linear Foot Section 1-09.14(2)BC is a new section: (******) Measurement for “Furnish and Install 10-Inch PVC Sewer Pipe” will be based on linear footage measured horizontally over the centerline of the installed pipe. Payment for “Furnish And Install 10-Inch PVC Sewer Pipe” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
11/4/2020
83
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, installing, laying and joining sewer pipes, fittings and couplings of the size and type shown, and all incidentals,
• Ethafoam pads (when needed),
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Air-Testing (if required)
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BD Furnish and Install 6-inch PVC Side Sewer Pipe (Bid Item B-17) –– Linear Foot Section 1-09.14(2)BD is a new section: (******) Measurement for “Furnish and Install 6-Inch PVC Side Sewer Pipe” will be based on linear footage measured horizontally over the centerline of the installed pipe. Payment for “Furnish And Install 6-Inch PVC Side Sewer Pipe” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, installing, laying and joining sewer pipes, fittings and couplings of the size and type shown, and all incidentals,
• Furnishing and installing cleanout frame and cover,
• Furnishing and installing concrete around cleanout frame (as required by the project plans),
• Ethafoam pads (when needed),
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Air-Testing (if required)
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BE Furnish and Install 4-inch or 6-inch CIPP Side Sewer Pipe (Bid Item B-18) –– Each Section 1-09.14(2)BE is a new section: (******) Measurement for Furnish and Install 4- inch or 6-Inch CIPP Side Sewer Pipe will be based on linear footage measured horizontally over the centerline of the installed pipe.
11/4/2020
84
Payment for “Furnish And Install 4-inch or 6-Inch CIPP Side Sewer Pipe” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Equipment and tools need to confirm size and suitability for lining of each side sewer stub as shown on the project plans,
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing and installing the CIPP sewer pipes of the size necessary,
• Post installation CCTV Inspection.
1-09.14(2)BF Furnish and Install Internal Sewer Drop in Existing Manhole (Bid Item B-19) –– Each Section 1-09.14(2)BF is a new section: (******) Measurement for Furnish and Install Internal Sewer Drop in Existing Manhole” will be per each for each internal sewer drop installed in conformance with the Contract Documents. Payment for “Furnish And Install Internal Sewer Drop in Existing Manhole” will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, installing, joining and attaching sewer pipes, fittings, couplings and mounting brackets of the size and type shown for the internal drop, and all incidentals,
• Core-drilling of the existing manhole and installation of a Kor-N-Seal boot (or approved equal),
• Furnishing and installing concrete and aggregate for plugging existing outside drop,
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
11/4/2020
85
1-09.14(2)BG Furnish and Install Sanitary Sewer Manhole Extra Shallow (Bid Item B-20) –– Each Section 1-09.14(2)BG is a new section: (******) Measurement for “Furnish and Install Shallow Sanitary Sewer Manhole Extra Shallow” will be per each for each type manhole installed in conformance with the Contract Documents. Payment for “Furnish And Install Shallow Sanitary Sewer Manhole Extra Shallow” will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, install precast or poured-in-place concrete base, concrete manhole sections, gaskets, Kor-N-Seal boots (or approved equal), ladder and rungs, appurtenances, connections, channeling, reconnection to existing sewer pipes including pipe and couplings, coating system (sealer), manhole frame and lid,
• Furnishing and installing material to adjustment of frames to grade including HMA,
• Furnishing foundation and bedding materials, placing and compacting foundation and bedding,
• Placing and compacting backfill,
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BH Furnish and Install 54-inch Shallow Sanitary Sewer Manhole (Bid Item B-21) –– Each Section 1-09.14(2)BH is a new section: (******) Measurement for “Furnish and Install 54-inch Diameter Shallow Sanitary Sewer Manhole” will be per each for each type manhole installed in conformance with the Contract Documents. Payment for “Furnish And Install 54-Inch Diameter Shallow Sanitary Sewer Manhole” will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
11/4/2020
86
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, install precast or poured-in-place concrete base, concrete manhole sections, gaskets, Kor-N-Seal boots (or approved equal), ladder and rungs, appurtenances, connections, channeling, reconnection to existing sewer pipes including pipe and couplings, coating system (sealer), manhole frame and lid,
• Furnishing and installing material to adjustment of frames to grade including HMA,
• Furnishing foundation and bedding materials, placing and compacting foundation and bedding,
• Placing and compacting backfill,
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BI Furnish and Install 54-inch Sanitary Sewer Manhole (Bid Item B-22) –– Each Section 1-09.14(2)BI is a new section: (******) Measurement for “Furnish and Install 54-inch Diameter Sanitary Sewer Manhole” will be per each for each type manhole installed in conformance with the Contract Documents. Payment for “Furnish And Install 54-Inch Diameter Sanitary Sewer Manhole” will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, install precast or poured-in-place concrete base, concrete manhole sections, gaskets, Kor-N-Seal boots (or approved equal), ladder and rungs, appurtenances, connections, channeling, reconnection to existing sewer pipes including pipe and couplings, coating system (sealer), manhole frame and lid,
• Furnishing and installing material to adjustment of frames to grade including HMA,
• Furnishing foundation and bedding materials, placing and compacting foundation and bedding,
• Placing and compacting backfill,
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
11/4/2020
87
1-09.14(2)BJ Furnish and Install 60-inch Sanitary Sewer Manhole with Inside Drop (Bid Item
B 23) – Each Section 1-09.14(2)BJ is a new section: (******) Measurement for “Furnish and Install 60-inch Diameter Sanitary Sewer Manhole with Inside Drop” will be per each for each type manhole installed in conformance with the Contract Documents. Payment for “Furnish and Install 60-inch Diameter Sanitary Sewer Manhole with Inside Drop” will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, install precast or poured-in-place concrete base, concrete manhole sections, gaskets, Kor-N-Seal boots (or approved equal), ladder and rungs, appurtenances, connections, channeling, reconnection to existing sewer pipes including pipe, couplings and bends, coating system (sealer), manhole frame and lid,
• Furnishing and installing clamping brackets, inside-drop pipe, laying and joining new sewer pipe to the inside-drop, bends,
• Furnishing and installing material to adjustment of frames to grade including HMA,
• Furnishing foundation and bedding materials, placing and compacting foundation and bedding,
• Placing and compacting backfill,
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BK Furnish and Install 8-inch Sewer Cleanout (Bid Item B-24) –– Each Section 1-09.14(2)BK is a new section: (******) Measurement for “Furnish and Install 8-Inch Sewer Cleanout” will be per each for the installation of C.O. installed in conformance with the Contract Documents. Payment for “Furnish and Install 8-Inch Sewer Cleanout” will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
11/4/2020
88
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, installing, laying and joining sewer pipes, fittings and couplings of the size and type shown, and all incidentals,
• Furnishing and installing cleanout frame and cover,
• Furnishing and installing concrete around cleanout frame (as required by the project plans),
• Furnishing and installing material to adjustment of frames to grade,
• Furnishing foundation and bedding materials, placing and compacting foundation and bedding,
• Placing and compacting backfill,
• Replacing, protecting and/or maintaining existing utilities,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BL Furnish and Install 6-inch Sewer and Cleanout in Easement (Bid Item B-25) –– Lump
Sum Section 1-09.14(2)BL is a new section: (******) Measurement for “Furnish and Install 6-Inch Sewer and Cleanout in Easement” will be per each for the installation of 6-Inch sewer and cleanout installed in conformance with the Contract Documents. Payment for furnish and install 6-inch sewer and cleanout in easement will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Furnishing, installing, laying and joining sewer pipes, fittings and couplings of the size and type shown (approximately 15 linear feet of 6” PVC and three 6”x6” tees), and all incidentals,
• Furnishing and installing cleanout frame and cover,
• Furnishing and installing concrete around cleanout frame (as required by the project plans),
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Landscape restoration.
11/4/2020
89
1-09.14(2)BM Connect New Sewer to Existing Sewer Manhole (Bid Item B-26) –– Each Section 1-09.14(2)BM is a new section: (******) Measurement for “Connect New Sewer to Existing Sewer Manhole” will be per each in conformance with the Contract Documents. Payment for Connect New Sewer to Existing Sewer Manhole will be made at the amount bid per each, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Trench excavation, and dewatering (if needed),
• Bypass sewer pumping (if needed),
• Removal, hauling and disposal of waste materials including but not limited to pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, existing pipes and structures in the excavation,
• Core-drilling of existing manhole,
• Furnish and install new Kor-N-Seal boot, sand collar (or approved equal) and grouting,
• Connection of new sewer to existing manhole,
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Furnishing and Placing Temporary Pavement Patching.
1-09.14(2)BN Pre-installation Cleaning and Inspection for CIPP in Easement (Bid Item
B-27) – Linear Foot Section 1-09.14(2)BN is a new section: (******) Measurement for “Pre-Installation Cleaning and Inspection for CIPP in Easement” will be based on the linear feet of pipe inspected and each in conformance with the Contract Documents. Payment for Pre-Installation Cleaning and Inspection for CIPP in Easement will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• bypass sewer routing if necessary.
• cleaning,
• root cutting and removal of obstructions,
• removal and disposal of waste material,
• water,
• CCTV inspection in a PACP compatible format and provision of the CCTV record on an external HDD to the Engineer,
11/4/2020
90
1-09.14(2)BO Furnish and Install 6-inch Cured-in-place Pipe in Easement (Bid Item B-28) –– Linear
Foot Section 1-09.14(2)BO is a new section: (******) Measurement for “Furnish and Install 6-Inch Cured-In-Place Pipe in Easement ” will be based on the linear feet of 6-Inch cured-in-place pipe installed. The length will be the number of linear feet of completed installation measured along the invert and will include the length through elbows, tees and fittings. The number of linear feet will be measured from the center of manhole to center of manhole, center of cleanout or the actual end of the cured-in-place pipe if it does not end in a structure. Payment for “Furnish and Install 6-Inch Cured-In-Place Pipe in Easement” will be made at the amount bid per linear foot, which payment will be complete compensation for all labor, materials, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• bypass sewer routing if necessary,
• dewatering,
• cleaning,
• root cutting and removal of obstructions,
• furnishing and installing 6” diameter CIPP,
• removal and disposal of waste material,
• water
The following subsection provides the measurement and payment information of the Bid Items
specific to Schedule C – Water.
1-09.14(2)CA Furnish and Install 8”, 6”, and 4” Cl 52 DI Water Pipe & Fittings w/ Polywrap (Bid Item
C-15, C-16, & C-17) –– Linear Foot Section 1-09.14(2)CA is a new section: (******) Measurement for furnishing and installing water pipes and fittings of the size, type and class specified will be based on the actual lineal footage measured horizontally over the centerline of the installed pipe. Payment for furnishing and installing ductile iron water pipes and fittings of the size, type and class specified shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location, including potholing in advance for existing side sewers and television inspection of existing sanitary sewer to determine location of side sewer branches if necessary.
• Saw cutting up to 12” in depth, trench excavation, and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
11/4/2020
91
• Furnishing, installing, laying and jointing water pipes and fittings of the size, type and class shown, polyethylene encasement, special fittings, horizontal and vertical bends, mechanical joint pipe restraint, vertical crosses for poly-pigging, shackle rods, temporary blow-off assemblies, and all incidentals,
• Furnishing bedding materials, placing and compacting pipe bedding, as shown on the plans,
• Placing and compacting trench backfill,
• Testing, poly-pigging, disinfecting and flushing of new valves,
• Replacing, protecting and/or maintaining existing utilities.
• Furnishing and placing temporary pavement patching
1-09.14(2)CB Cut In 6” Gate Valve Assembly (Bid Item C-18) – Each Section 1-09.14(2)CB is a new section: (******) Measurement for furnishing and installing 6” gate valve cut in will be per each, installed in conformance with the Contract Documents. Payment for furnishing and installing 6” gate valve cut in shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Furnishing all required fittings, adapters, couplings and incidentals as required for City’s water department’s personnel to perform the installation.
• Placing and compacting trench backfill,
• Replacing, protecting and/or maintaining existing utilities.
• Furnishing and placing temporary pavement patching
1-09.14(2)CC Furnish and Install 8”, 6”, & 4” Gate Valve Assembly (Bid Item C-19, C-20, &
C-21) – Each Section 1-09.14(2)CC is a new section: (******) Measurement for furnishing and installing 8”, 6”, and 4” gate valve assemblies will be per each for each type valve installed in conformance with the Contract Documents. Payment for furnishing and installing 8”, 6”, and 4” gate valve assemblies shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
11/4/2020
92
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Furnishing and installing valves, valve boxes and covers to grade, stem extensions, valve marker posts, pipe nipples, couplings, polyethylene encasement, concrete blocking, and all incidentals,
• Placing and compacting trench backfill,
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching
1-09.14(2)CD Concrete for Thrust Blocking, Dead-Man Anchor Blocks (Bid Item C-22) – Cubic Yard Section 1-09.14(2)CD is a new section: (******) Measurement for concrete for thrust blocking, horizontal and vertical, dead-man anchor blocks will be per cubic yard for all concrete installed for thrust blocking and dead-man anchor blocks in conformance with the Contract Documents. Payment for concrete thrust blocking and dead man anchor blocks shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, shoring and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Furnishing and placing concrete for vertical and horizontal blocks, dead-man anchor blocks, reinforcing steel, shackle rods, clamp assembly, anchor bolts, turnbuckles, concrete form work,
• Placing and compacting trench backfill,
• Replacing, protecting and/or maintaining existing utilities.
• Furnishing and placing temporary pavement patching
1-09.14(2)CE Furnish and Install Fire Hydrant Assembly (Bid Item C-23) –– Each Section 1-09.14(2)CE is a new section: (******) Measurement for furnishing and installing fire hydrant assembly will be per each for each fire hydrant assembly installed in conformance with the Contract Documents. Payment for furnishing and installing fire hydrant assembly shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Removal of existing fire hydrant, if existing hydrant is being replaced,
11/4/2020
93
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Furnishing and installing new fire hydrant assembly, standpipe, shoe, and 6-inch DI piping, Storz adapter,
• Furnishing and installing shut-off valve, valve box, valve extension,
• Furnishing and installing shackles, tie-rods, concrete blocking, and joint restraints, drain rocks, polyfilm,
• Adjust hydrant to finish grade and install concrete shear block,
• Placing and compacting trench backfill,
• Testing, disinfecting and flushing of new hydrants,
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching
• Painting the hydrants
1-09.14(2)CF Furnish and Install 1” Water Service Connection (Bid Item C-24) –– Each Section 1-09.14(2)CF is a new section: (******) Measurement for furnishing and installing 1” water connection will be per each for each 1” water connection installed in conformance with the Contract Documents. Payment for furnishing and installing 1” water connection shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation as needed, shoring and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Boring, hole-hogging, tunneling, mechanical or hand trenching to install new water service lines,
• Furnishing and installing new 1- inch ball valve corporation stops, tapping the main, laying and jointing the new copper water service lines and fittings, new meter setter, new meter boxes and lids,
• Testing, disinfecting and flushing the new service line,
• Connecting the customer-side private service line to the new copper tailpiece behind the new meter setter and property lines,
• Placing and compacting trench backfill,
• Replacing, protecting and/or maintaining existing utilities.
• Restoration of public and private properties
• Furnishing and placing temporary pavement patching
11/4/2020
94
1-09.14(2)CG Furnish and Install Air Release and Vacuum Valve Assembly (Bid Item C-25) –– Each Section 1-09.14(2)CG is a new section: (******) Measurement for air release and vacuum valve assembly will be per each unit installed for completion in conformance with the Contract Documents. Payment for air release and vacuum valve assembly shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, shoring and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Concrete blocking, extension of the vent lines, installation of concrete and rock pads,
• Testing, flushing and cleanup, connection to mainline,
• Placing and compacting trench backfill,
• Testing, poly-pigging, disinfecting and flushing of new valves,
• Replacing, protecting and/or maintaining existing utilities.
• Furnishing and placing temporary pavement patching
1-09.14(2)CH Connection to Existing Water Main (Bid Item C-26) –– Each Section 1-09.14(2)CH is a new section: (******) Measurement for connection to existing water main will be per each connection for completion in conformance with the Contract Documents. Payment for connection to existing water main shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the Contract Documents, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, shoring and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material including existing pipes and structures in the excavation and the like,
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Furnishing all required pipes, fittings, adapters, couplings and incidentals as required for City’s water department’s personnel to perform the initial cut-in installation of valves, and fittings on the existing water main(s),
• Furnishing all required pipes, fittings, adapters, couplings and incidentals as required for City’s water department’s personnel to perform the second and final connection of the new water line to the existing water system and to the valves installed during the initial cut-in as described above,
• Placing and compacting trench backfill,
11/4/2020
95
• Replacing, protecting and/or maintaining existing utilities
• Furnishing and placing temporary pavement patching
1-09.14(2)CI Cut, Cap, and Block Existing Water Main (Bid Item C-27) –– Each Section 1-09.14(2)CI is a new section: (******) Measurement for cut, cap, and block existing water main will be per each in conformance with the Contract Documents. Payment for cut, cap, and block water main shall cover the complete cost of providing all labor, materials, tools, equipment required to complete the work specified in the contract documents and plans, and shall include but not be limited to the following:
• Locating all existing utilities and potholing in advance to determine their horizontal and vertical location,
• Saw cutting, trench excavation, shoring and dewatering (if needed),
• Removal, hauling and disposal of pavement, curbs, gutters, sidewalks, surplus and unsuitable excavated material, excluding any asbestos cement pipe or fittings
• Stockpiling suitable excavated material for use as pipe bedding and trench backfill as directed by the Engineer,
• Furnishing all required pipes, fittings, adapters, couplings and incidentals as required for City’s water department’s personnel to perform the cut and cap,
• Excavating for and installing thrust block,
• Placing and compacting trench backfill,
• Replacing, protecting and/or maintaining existing utilities.
• Furnishing and placing temporary pavement patching
1-10 TEMPORARY TRAFFIC CONTROL
1-10.1 General
1-10.1(2) Description Delete the first paragraph and replace with: (******) The Contractor shall provide flaggers, signs, and other traffic control devices not otherwise specified as being furnished by the Contracting Agency. The Contractor shall erect and maintain all construction signs, warning signs, detour signs, and other traffic control devices necessary to warn and protect the public at all times from injury or damage as a result of the Contractor’s operations which may occur on highways, roads, streets, sidewalks, or paths. No Work shall be done on or adjacent to any traveled way until all necessary signs and traffic control devices are in place. Section 1-10.1(2) is supplemented with the following: (******) When the bid proposal includes an item for “Traffic Control,” the Work required for this item shall be all items described in Section 1-10, including, but not limited to: 1. Furnishing and maintaining barricades, flashers, construction signage, and other channelization devices, unless a pay item is in the bid proposal for any specific device and
11/4/2020
96
the Special Provisions specify furnishing, maintaining, and payment in a different manner for that device; 2. Furnishing traffic control labor, equipment, and supervisory personnel for all traffic control labor; 3. Furnishing any necessary vehicle(s) to set up and remove traffic control devices; 4. Furnishing labor and vehicles for patrolling and maintaining all of the construction signs and the traffic control devices, unless a pay item is in the bid proposal to specifically pay for this Work ; 5. Furnishing labor, material, and equipment necessary for cleaning up, removing, and replacing of the construction signs and the traffic control devices destroyed or damaged during the life of the project. 6. Removing existing signs as specified or as directed by the Engineer and delivering to the City Shops, or storing and reinstalling as directed by the Engineer. 7. Preparing a traffic control plan for the project and designating the person responsible for traffic control at the Work site. The traffic control plan shall include descriptions of the traffic control methods and devices to be used by the prime Contractor, and subcontractors, shall be submitted at or before the preconstruction conference, and shall be subject to review and approval of the Engineer. 8. Contacting police, fire, 911, and ambulance services to notify them in advance of any Work that will affect and traveled portion of a roadway. 9. Assuring that all traveled portions of roadways are open to traffic during peak traffic periods, 6:30 a.m. to 8:30 a.m., and 3:00 p.m. to 6:00 p.m., or as specified in the special provisions, or as directed by the Engineer. 10. Promptly removing or covering all non-applicable signs during periods when they are not needed. If the Engineer requires the Contractor to furnish additional channelizing devices, pieces of equipment, or services, which could not be usually anticipated by a prudent Contractor for the maintenance and protection of traffic, then a new item or items may be established to pay for such items. Further limitations for consideration of payment for these items are that they are not covered by other pay items in the bid proposal, they are not specified in the Special Provisions as incidental, and the accumulative cost for the use of each individual channelizing device, piece of equipment, or service must exceed $200 in total cost for the duration of their need. In the event of disputes, the Engineer will determine what is usually anticipated by a prudent Contractor. The cost for these items will be by agreed price, price established by the Engineer, or by force account. Additional items required as a result of the Contractor’s modification to the traffic control plan(s) appearing in the Contract shall not be covered by the provisions in this paragraph. If the total cost of all the Work under the Contract increases or decreases by more than 25 percent, an equitable adjustment will be considered for the item “Traffic Control” to address the increase or decrease. Traffic control and maintenance for the safety of the traveling public on this project shall be the sole responsibility of the Contractor and all methods and equipment used will be subject to the approval of the Contracting Agency. Traffic control devices and their use shall conform to City of Renton standards and the Manual on
Uniform Traffic Control Devices( MUTCD).
11/4/2020
97
Any days lost due to improper traffic control will be charged against the Contractor’s allowable contract time, and shall not be the cause for a claim for extra days to complete the Work. If no bid item “Traffic Control” appears in the proposal, then all Work required by these sections will be considered incidental and their cost shall be included in the other items of Work.
1-10.2(1)B Traffic Control Supervisor Paragraphs 1 and 2 are deleted in their entirety and replaced with the following: (******) A Traffic Control Supervisor (TCS) shall be on the project whenever traffic control labor is required or as authorized by the Engineer. The TCS shall assure that all the duties of the TCS are performed during the duration of the Contract. During non-Work periods, the TCS shall be able to be on the job site within a 45-minute time period after notification by the Engineer.
1-10.2(2) Traffic Control Plans Section 1-10.2(2) is supplemented with the following: (******)
1-10.3 Traffic Control Labor, Procedure, and Devices Section 1-10.3 is supplemented with the following: (******) At the end of each working day, provisions shall be made for the safe passage of traffic and pedestrians during non-working hours.
1-10.3(3) Traffic Control Devices
1-10.3(3)A Construction Signs Section 1-10.3(3)A paragraph 3 is supplemented with the following: (******) No separate pay item will be provided in the bid proposal for Class A or Class B construction signs. All costs for the Work to provide Class A or Class B construction signs shall be included in the unit contract price for the various other items of the Wor k in the bid proposal.
1-10.4 Measurement Section 1-10.4 is deleted in its entirety and replaced with: (******) No specific unit of measurement will apply to the lump sum item of “Traffic Control”. No adjustment in the lump sum bid amount will be made for overtime Work or for use of relief flaggers.
11/4/2020
98
1-10.5 Payment Section 1-10.5 is deleted in its entirety and replaced with: (******) Payment for all labor, materials, and equipment described in Section 1-10 will be made in accordance with Section 1-04.1, for the following bid items when included in the proposal: “Traffic Control,” Lump Sum.
1-11 RENTON SURVEYING STANDARDS
The following is a new section with new subsections: (******)
1-11.1(1) Responsibility for Surveys All surveys and survey reports shall be prepared under the direct supervision of a person registered to practice land surveying under the provisions of Chapter 18.43 RCW. All surveys and survey reports shall be prepared in accordance with the requirements established by the Board of Registration for Professional Engineers and Land Surveyors under the provisions of Chapter 18.43 RCW.
1-11.1(2) Survey Datum and Precision The horizontal component of all surveys shall have as its coordinate base: The North American Datum of 1983/91. All horizontal control for projects must be referenced to or in conjunction with a minimum of two of the City of Renton's Survey Control Network monuments. The source of the coordinate values used will be shown on the survey drawing per RCW 58.09.070. The horizontal component of all surveys shall meet or exceed the closure requirements of WAC 332-130-110. The control base lines for all surveys shall meet or exceed the requirements for a Class A survey revealed in Table 2 of the Minimum Standard Detail Requirements for ALTA/ACSM Land Title Surveys jointly established and adopted by ALTA and ACSM in 1992 or comparable classification in future editions of said document. The angular and linear closure and precision ratio of traverses used for survey control shall be revealed on the face of the survey drawing, as shall the method of adjustment. The horizontal component of the control system for surveys using global positioning system methodology shall exhibit at least 1 part in 50,000 precision in line length dependent error analysis at a 95 percent confidence level and performed pursuant to Federal Geodetic Control Subcommittee Standards for GPS control surveys as defined in Geometric Geodetic Accuracy Standards & Specifications for Using GPS Relative Positioning Techniques dated August 1, 1989, or comparable classification in future editions of said document. The vertical component of all surveys shall be based on NAVD 1988, the North American Vertical Datum of 1988, and tied to at least one of the City of Renton Survey Control Network benchmarks. If there are two such benchmarks within 3000 feet of the project site a tie to both shall be made. The benchmark(s) used will be shown on the drawing. If a City of Renton benchmark does not exist within
11/4/2020
99
3000 feet of a project, one must be set on or near the project in a permanent manner that will remain intact throughout the duration of the project. Source of elevations (benchmark) will be shown on the drawing, as well as a description of any benchmarks established.
1-11.1(3) Subdivision Information Those surveys dependent on section subdivision shall reveal the controlling monuments used and the subdivision of the applicable quarter section. Those surveys dependent on retracement of a plat or short plat shall reveal the controlling monuments, measurements, and methodology used in that retracement.
1-11.1(4) Field Notes Field notes shall be kept in conventional format in a standard bound field book with waterproof pages, and/or in an electronic field book/data collector format in an unedited, original field-produced state capable of being printed. In all cases, original field notes must be dated with the day the field
work was performed and include a sketch and with a record of control and base line traverses describing station occupations and what measurements were made at each point. Every point located or set shall be identified by a number and a description. Point numbers shall be unique within a complete job. The preferred method of point numbering is field notebook, page and point set on that page. Example: The first point set or found on page 16 of field book 348 would be identified as Point No. 348.16.01, the second point would be 348.16.02, etc. Upon completion of a City of Renton project, either the field notebook(s) provided by the City or the original field notebook(s) used by the Surveyor will be given to the City. For all other Work , Surveyors will provide a copy of the notes to the City upon request. In those cases where an electronic data collector is used, a hard copy print out in ASCII text format will accompany the field notes.
1-11.1(5) Corners and Monuments Corner: A point on a land boundary, at the juncture of two or more boundary lines. A monument is usually set at such points to physically reference a corner's location on the ground. Monument: Any physical object or structure of record, which marks or accurately references:
• A corner or other survey point established by or under the supervision of an individual per Section 1-11.1(1) and any corner or monument established by the General Land Office and its successor the Bureau of Land Management including section subdivision corners down to and including one-sixteenth corners; and
• Any permanently monumented boundary, right-of-way alignment, or horizontal and vertical control points established by any governmental agency or private surveyor including street intersections but excluding dependent interior lot corners.
1-11.1(6) Control or Base Line Survey Control or Base Line Surveys shall be established for all construction projects that will create permanent structures such as roads, sidewalks, bridges, utility lines or appurtenances, signal or light poles, or any non-single family building. Control or Base Line Surveys shall consist of such number of permanent monuments as are required such that every structure may be observed for staking or "as-builting" while occupying one such monument and sighting another such monument. A minimum of two of these permanent monuments shall be existing monuments, recognized and on record with
11/4/2020
100
the City of Renton. The Control or Base Line Survey shall occupy each monument in turn, and shall satisfy all applicable requirements of Section 1-11.1 herein. The drawing depicting the survey shall be neat, legible, and drawn to an appropriate scale. North orientation should be clearly presented and the scale shown graphically as well as noted. The drawing must be of such quality that a reduction thereof to one-half original scale remains legible. If recording of the survey with the King County Recorder is required, it will be prepared on 18 inch by 24 inch mylar and will comply with all provisions of Chapter 58.09 RCW. A photographic mylar of the drawing will be submitted to the City of Renton and, upon their review and acceptance per the specific requirements of the project, the original will be recorded with the King County Recorder. If recording is not required, the survey drawing shall be prepared on 22 inch by 34 inch mylar, and the original or a photographic mylar thereof will be submitted to the City of Renton. The survey drawings shall meet or exceed the requirements of WAC 332-130-050 and shall conform to the City of Renton's Drafting Standards. American Public Works Association symbols shall be used whenever possible, and a legend shall identify all symbols used if each point marked by a symbol is not described at each use. An electronic listing of all principal points shown on the drawing shall be submitted with each drawing. The listing should include the point number designation (corresponding with that in the field notes), a brief description of the point, and northing, easting, and elevation (if applicable) values, all in ASCII format, on IBM PC compatible media.
1-11.1(7) Precision Levels Vertical Surveys for the establishment of benchmarks shall satisfy all applicable requirements of Sections 1-05 and 1-11.1. Vertical surveys for the establishment of benchmarks shall meet or exceed the standards, Specifications and procedures of third order elevation accuracy established by the Federal Geodetic Control Committee. Benchmarks must possess both permanence and vertical stability. Descriptions of benchmarks must be complete to insure both recoverability and positive identification on recovery.
1-11.1(8) Radial and Station -- Offset Topography Topographic surveys shall satisfy all applicable requirements of Section 1-11.1 herein. All points occupied or back sighted in developing radial topography or establishing baselines for station-offset topography shall meet the requirements of Section 1-11.1 herein. The drawing and electronic listing requirements set forth in Section 1-11.1 herein shall be observed for all topographic surveys.
1-11.1(9) Radial Topography Elevations for the points occupied or back sighted in a radial topographic survey shall be determined either by, 1) spirit leveling with misclosure not to exceed 0.1 feet or Federal Geodetic Control
11/4/2020
101
Committee third order elevation accuracy Specifications, OR 2) trigonometric leveling with elevation differences determined in at least two directions for each point and with misclosure of the circuit not to exceed 0.1 feet.
1-11.1(10) Station--Offset Topography Elevations of the baseline and topographic points shall be determined by spirit leveling and shall satisfy Federal Geodetic Control Committee Specifications as to the turn points and shall not exceed 0.1 foot's error as to side shots.
1-11.1(11) As-Built Survey All improvements required to be "as-built" (post construction survey) per City of Renton Codes, TITLE 4 Building Regulations and TITLE 9 Public Ways and Property, must be located both horizontally and vertically by a Radial survey or by a Station offset survey. The "as-built" survey must be based on the same base line or control survey used for the construction staking survey for the improvements being "as-built". The "as-built" survey for all subsurface improvements should occur prior to backfilling. Close cooperation between the installing Contractor and the "as-builting" surveyor is therefore required. All "as-built" surveys shall satisfy the requirements of Section 1-11.1(1) herein, and shall be based upon control or base line surveys made in conformance with these Specifications. The field notes for "as-built" shall meet the requirements of Section 1-11.1(4) herein, and submitted with stamped and signed "as-built" drawings which includes a statement certifying the accuracy of the "as-built". The drawing and electronic listing requirements set forth in Section 1-11.1(6) herein shall be observed for all "as-built" surveys.
1-11.1(12) Monument Setting and Referencing All property or lot corners, as defined in 1-11.1(5), established or reestablished on a plat or other recorded survey shall be referenced by a permanent marker at the corner point per 1-11.2(1). In situations where such markers are impractical or in danger of being destroyed, e.g., the front corners of lots, a witness marker shall be set. In most cases, this will be the extension of the lot line to a tack in lead in the curb. The relationship between the witness monuments and their respective corners shall be shown or described on the face of the plat or survey of record, e.g., “Tacks in lead on the extension of the lot side lines have been set in the curbs on the extension of said line with the curb." In all other cases the corner shall meet the requirements of Section 1-11.2(1) herein. All non-corner monuments, as defined in 1-11.1(5), shall meet the requirements of Section 1-11.2(2) herein. If the monument falls within a paved portion of a right-of-way or other area, the monument shall be set below the ground surface and contained within a lidded case kept separate from the monument and flush with the pavement surface, per Section 1-11.2(3). In the case of right-of-way centerline monuments all points of curvature (PC), points of tangency (PT), street intersections, center points of cul-de-sacs shall be set. If the point of intersection (PI) for the tangents of a curve fall within the paved portion of the right-of-way, a mon ument can be set at the PI instead of the PC and PT of the curve.
11/4/2020
102
For all non-corner monuments set while under contract to the City of Renton or as part of a City of Renton approved subdivision of property, a City of Renton Monument Card (furnished by the city) identifying the monument; point of intersection (PI), point of tangency (PT), point of curvature (PC), one-sixteenth corner, Plat monument, street intersection, etc., complete with a description of the monument, a minimum of two reference points and NAD 83/91 coordinates, and NAVD 88 elevation shall be filled out and filed with the city.
1-11.2 Materials
1-11.2(1) Property/Lot Corners Corners per 1-11.1(5) shall be marked in a permanent manner such as 1/2 inch diameter rebar 24 inches in length, durable metal plugs or caps, tack in lead, etc., and permanently marked or tagged with the surveyor's identification number. The specific nature of the marker used can be determined by the surveyor at the time of installation.
1-11.2(2) Monuments Monuments per 1-11.1(5) shall meet the requirements as set forth in City of Renton Standard Plans page H031 and permanently marked or tagged with the surveyor's identification number.
1-11.2(3) Monument Case and Cover Materials shall meet the requirements of Section 9-22 and City of Renton Standard Plan H031.
2-01 CLEARING, GRUBBING, AND ROADSIDE CLEANUP
2-01.1 Description Section 2-01.1 is supplemented with the following: (******) The limits of clearing and grubbing (construction limits) shall be defined as being the construction limit lines as shown in the Plans. Where, in the opinion of the Engineer, any trees abutting or adjacent to the limits of clearing and grubbing are damaged and require removal, the Contractor shall remove such trees. Any trees flagged by the Engineer to remain within the clearing and grubbing limits shall be left undamaged by the Contractor’s operations. Any flagged trees, which are damaged, shall be replaced in kind at the Contractor’s expense. Existing landscaping outside the construction limits, including but not limited to, sod, rockeries, beauty bark, decorative gravel or rock, bushes, and shrubbery shall be protected from damage. The property owners shall be responsible for removing and/or relocating irrigation equipment, trees, shrubs, curbing, ornamental plants, and any other decorative landscaping materials within the construction limits that they wish to save. The Contractor shall give property owners 10 days’
written notice prior to removing landscaping materials. All landscaping materials that remain in the construction limits after that time period shall be removed and disposed of, by the Contractor, in accordance with Section 2-01 and the Plans. The Contractor shall receive approval from the Engineer prior to removal.
11/4/2020
103
2-01.2 Disposal of Usable Material and Debris Section 2-01.2 is supplemented with the following: (******) The Contractor shall dispose of all debris by Disposal Method No. 2 – Waste Site.
2-01.5 Payment Section 2-01.5 is supplemented with the following: (******) The lump sum price for “Clearing and Grubbing” shall be full compensation for all Work described herein and shown in the Plans, including removing trees and shrubbery where shown in the Plans and directed by the Engineer.
2-02 REMOVAL OF STRUCTURE AND OBSTRUCTIONS
2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters Section 2-02.3(3) is revised and supplemented with the following: (******) Item “1” is deleted and replaced with the following: Haul broken-up pieces to some off-project site. The section is supplemented with the following: In locations where pavement, sidewalk or driveway has been removed and that must remain open to traffic prior to final restoration, a temporary asphalt patch shall be installed. Temporary asphalt patches shall be in accordance with Section 5-06.
2-02.4 Measurement Section 2-02.4 replaces the existing vacant section: (******) Sawcutting existing cement and asphalt concrete pavements shall be measured by the linear foot along the sawcut, full depth. Wheel cutting of pavement will not be measured for separate payment, but shall be included in other items of Work.
2-02.5 Payment Section 2-02.5 is supplemented with the following: (******) "Saw Cutting", per lineal foot. "Remove Sidewalk", per square yard. "Remove Curb and Gutter", per lineal foot. "Cold Mix", per ton "Remove Asphalt Concrete Pavement," per square yard. "Remove Cement Concrete pavement," per square yard. "Remove existing ___________," per ___________. All costs related to the removal and disposal of structures and obstructions including saw cutting, excavation, backfilling, and temporary asphalt shall be considered incidental to and included in other items unless designated as specific bid items in the proposal. If pavements, sidewalks, or curbs lie
11/4/2020
104
within an excavation area and are not mentioned as separate pay items, their removal will be paid for as part of the quantity removed in excavation. If they are mentioned as a separate item in the proposal, they will be measured and paid for as provided under Section 2-02.5 and will not be included in the quantity calculated for excavation.
2-03 ROADWAY EXCAVATION AND EMBANKMENT
2-03.3 Construction Requirements Section 2-03.3 is supplemented with the following: (******) Roadway excavation shall include the removal of all materials excavated from within the limits shown on the Plans. Suitable excavated material shall be used for embankments, while surplus excavated material or unsuitable material shall be disposed of by the Contractor. Earthwork quantities and changes will be computed, either manually or by means of electronic data processing equipment, by use of the average end area method. Any changes to the proposed Work as directed by the Engineer that would alter these quantities shall be calculated by the Engineer and submitted to the Contractor for his review and verification. Any excavation or embankment beyond the limits indicated in the Plans, unless ordered by the Engineer, shall not be paid for. All Work and material required to return these areas to their original conditions, as directed by the Engineer, shall be provided by the Contractor at his sole expense. All areas shall be excavated, filled, and/or backfilled as necessary to comply with the grades shown on the Plans. In filled and backfilled areas, fine grading shall begin during the placement and the compaction of the final layer. In cut sections, fine grading shall begin within the final six (6) inches of cut. Final grading shall produce a surface, which is smooth and even, without abrupt changes in grade. Excavation for curbs and gutters shall be accomplished by cutting accurately to the cross sections, grades and elevations shown. Care shall be taken not to excavate below the specified grades. The Contractor shall maintain all excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the Work . Following removal of topsoil or excavation to grade, and before placement of fills or base course, the subgrade under the roadway shall be proof-rolled to identify any soft or loose areas which may warrant additional compaction or excavation and replacement. The Contractor shall provide temporary drainage or protection to keep the subgrade free from standing water. Acceptable excavated native soils shall be used for fill in the area requiring fills. Care shall be taken to place excavated material at the optimum moisture content to achieve the specified compaction. Any native material used for fill shall be free of organics and debris, and have a maximum particle size of 6 inches.
11/4/2020
105
It shall be the responsibility of the Contractor to prevent the native materials from becoming saturated with water. The measures may include sloping to drain, compacting the native materials, and diverting runoff away from the materials. If the Contractor fails to take such preventative measures, any costs or delay related to drying the materials shall be at his own expense. If the native materials become saturated, it shall be the responsibility of the Contractor to dry the materials, to the optimum moisture content. If sufficient acceptable native soils are not available to complete construction of the roadway embankment, Gravel Borrow shall be used. If subgrade trimmer is not required on the project, all portions of Section 2-03 shall apply as though a subgrade trimmer were specified. If sufficient acceptable native soils, as determined by the Engineer, are not available to complete construction of the roadway embankment, Gravel Borrow meeting the requirements of Section 9-03.14 of the Standard Specifications, shall be used.
2-03.4 Measurement Section 2-03.4 is supplemented with the following: (******) At the discretion of the Engineer, roadway excavation, borrow excavation, and unsuitable foundation excavation - by the cubic yard (adjusted for swell) may be measured by truck in the hauling vehicle at the point of loading. The Contractor shall provide truck tickets for each load removed. Each ticket shall have the truck number, time and date, and be approved by the Engineer.
2-03.5 Payment Section 2-03.5 is revised with the following: (******) Payment for embankment compaction will not be made as a separate item. All costs for embankment compaction shall be included in other bid items involved. Payment will be made for the following bid items when they are included in the proposal: “Roadway Excavation Including Haul,” per cubic yard “Removal and Replacement of Unsuitable Foundation Material,” per ton “Gravel Borrow Including Haul,” per ton “Roadway Excavation Including Haul” shall be considered incidental and part of the bid item(s) provided for the installation of the utility mains and appurtenances. When the Engineer orders excavation below subgrade, then payment will be in accordance with the item “Removal and Replacement of Unsuitable Foundation Material”. In this case, all items of Work other than roadway excavation shall be paid at unit contract prices. The unit contract price per cubic yard for “Roadway Excavation Including Haul” shall be full pay for excavating, loading, placing, or otherwise disposing of the material. The unit contract price per ton for “Removal and Replacement of Unsuitable Foundation Material” shall be full pay for excavating, loading, and disposing of the material. Payment for embankment compaction will not be made as a separate item. All costs for embankment compaction shall be included in other bid items involved.
11/4/2020
106
2-04 HAUL
2-04.5 Payment Delete Section 2-04.5 and replace with the following: (******) All costs for the hauling of material to, from, or on the job site shall be considered incidental to and included in the unit price of other units of Work .
2-06 SUBGRADE PREPARATION
2-06.5 Measurement and Payment Section 2-06.5 is supplemented with the following: (******) Subgrade preparation and maintenance including watering shall be considered as incidental to the construction and all costs thereof shall be included in the appropriate unit or lump sum contract bid prices.
2-09 STRUCTURE EXCAVATION
2-09.1 Description Section 2-09.1 is supplemented with the following: (******) This Work also includes the excavation, haul, and disposal of all unsuitable materials such as peat, muck, swampy or unsuitable materials, including buried logs and stumps.
2-09.3(1)D Disposal of Excavated Material Section 2-09.3(1)D is revised with the following: (******) The second paragraph is deleted and replaced with: All costs for disposing of excavated material within or external to the project limits shall be included in the unit contract price for structure excavation, Class A or B. The third paragraph is deleted and replaced with: If the Contract includes structure excavation, Class A or B, including haul, the unit contract price shall include all costs for loading and hauling the material the full required distance, otherwise all such disposal costs shall be considered incidental to the Work .
2-09.4 Measurement The ninth paragraph of Section 2-09.4 is deleted and replaced with the following: (******)
Gravel backfill. Gravel backfill, except when used as bedding for culvert, storm sewer, sanitary sewer, manholes, and catch basins, will be measured by the cubic yard in place determined by the neat lines required by the Plans or by the ton as measured in conformance with Section 1-09.2.
11/4/2020
107
2-09.5 Payment Section 2-09.5 is revised and supplemented with the following: (******) Payment will be made for the following bid items when they are included in the proposal: “Structure Excavation Class A”, per cubic yard. “Structure Excavation Class B”, per cubic yard. “Structure Excavation Class A Incl. Haul”, per cubic yard. “Structure Excavation Class B Incl. Haul”, per cubic yard. Payment for reconstruction of surfacing and paving, within the limits of structure excavation, will be at the applicable unit prices for the items involved. If the Engineer orders the Contractor to excavate below the elevations shown in the Plans, the unit contract price per cubic yard for “Structure Excavation Class A or B” will apply. But if the Contractor excavates deeper than the Plans or the Engineer requires, the Contracting Agency will not pay for material removed from below the required elevations. In this case, the Contractor, at no expense to the Contracting Agency, shall replace such material with concrete or other material the Engineer approves. The unit contract price per cubic yard for the bid items listed as 1 through 4 above shall be full pay for all labor, materials, tools, equipment, and pumping, or shall be included in the unit bid price of other items of Work if "Structure Excavation" or "Structure Excavation Incl Haul" are not listed as pay items in the Contract. “Shoring or Extra Excavation Class B”, per square foot. The unit contract price per square foot shall be full pay for all excavation, backfill, compaction, and other Work required when extra excavation is used in lieu of constructing shoring. If select backfill material is required for backfilling within the limits of the structure excavation, it shall also be required as backfill material for the extra excavation at the Contractor’s expense. Any excavation or backfill material being paid by unit price shall be calculated by the Engineer only for the neat line measurement of the excavation and shall not include the extra excavation beyond the neat line. If there is no bid item for shoring or extra excavation Class B on a square foot basis and the nature of the excavation is such that shoring or extra excavation is required as determined by the Engineer, then shoring or extra excavation shall be considered incidental to the Work involved and no further compensation shall be made. “Gravel Backfill (Kind) for (Type of Excavation)”, per cubic yard or per ton. When gravel backfill is paid by the ton, the Contractor shall take care to assure to the satisfaction of the Engineer that such per ton backfill is only being used for the specified purpose and not for purposes where backfill is incidental or being paid by cubic yard. Evidence that per ton gravel backfill is not being used for its designated purpose shall be grounds for the Engineer to deny payment for such load tickets. “Controlled Density Fill”, per cubic yard.
11/4/2020
108
5-04 HOT MIX ASPHALT
(March 5, 2018 APWA GSP) Delete this Section in its entirety and replace it with the following:
(******)
5-04.1 Description This Work shall consist of providing and placing one or more layers of plant-mixed hot mix asphalt (HMA) on a prepared foundation or base in accordance with these Specifications. The Contractor shall maintain the existing street surface contours (e.g. street profile and cross section, etc.), unless otherwise directed by the Engineer. The manufacture of HMA may include warm mix asphalt (WMA) processes in accordance with these Specifications. WMA processes include organic additives, chemical additives, and foaming.
HMA shall be composed of asphalt binder and mineral materials as may be required, mixed in the
proportions specified to provide a homogeneous, stable, and workable mixture. See Appendix A for the Summary of Quantities that lists the streets to receive an overlay, the paving limits and the thickness of HMA. All HMA to be placed in this contract shall be HMA CL. ½” PG 64-22.
5-04.2 Materials Materials shall meet the requirements of the following sections: Asphalt Binder 9-02.1(4) Cationic Emulsified Asphalt 9-02.1(6) Anti-Stripping Additive 9-02.4 HMA Additive 9-02.5 Aggregates 9-03.8 Recycled Asphalt Pavement 9-03.8(3)B Mineral Filler 9-03.8(5) Recycled Material 9-03.21 Portland Cement 9-01 Sand 9-03.1(2) (As noted in 5-04.3(5)C for crack sealing) Joint Sealant 9-04.2 Foam Backer Rod 9-04.2(3)A The Contract documents may establish that the various mineral materials required for the manufacture of HMA will be furnished in whole or in part by the Contracting Agency. If the documents do not establish the furnishing of any of these mineral materials by the Contracting Agency, the Contractor shall be required to furnish such materials in the amounts required for the designated mix. Mineral materials include coarse and fine aggregates, and mineral filler. The Contractor may choose to utilize recycled asphalt pavement (RAP) in the production of HMA. The RAP may be from pavements removed under the Contract, if any, or pavement material from an existing stockpile.
11/4/2020
109
The Contractor may use up to 20 percent RAP by total weight of HMA with no additional sampling or testing of the RAP. The RAP shall be sampled and tested at a frequency of one sample for every 1,000 tons produced and not less than ten samples per project. The asphalt content and gradation test data shall be reported to the Contracting Agency when submitting the mix design for approval on the QPL. The Contractor shall include the RAP as part of the mix design as defined in these Specifications. The grade of asphalt binder shall be as required by the Contract. Blending of asphalt binder from different sources is not permitted. The Contractor may only use warm mix asphalt (WMA) processes in the production of HMA with 20 percent or less RAP by total weight of HMA. The Contractor shall submit to the Engineer for approval the process that is proposed and how it will be used in the manufacture of HMA. Production of aggregates shall comply with the requirements of Section 3-01. Preparation of stockpile site, the stockpiling of aggregates, and the removal of aggregates from stockpiles shall comply with the requirements of Section 3-02.
5-04.2(1) How to Get an HMA Mix Design on the QPL If the contractor wishes to submit a mix design for inclusion in the Qualified Products List (QPL), please follow the WSDOT process outlined as follows: Comply with each of the following:
• Develop the mix design in accordance with WSDOT SOP 732.
• Develop a mix design that complies with Sections 9-03.8(2) and 9-03.8(6).
• Develop a mix design no more than 6 months prior to submitting it for QPL evaluation.
• Submit mix designs to the WSDOT State Materials Laboratory in Tumwater, including WSDOT Form 350-042.
• Include representative samples of the materials that are to be used in the HMA production as part of the mix design submittal.
• Identify the brand, type, and percentage of anti-stripping additive in the mix design submittal.
• Include with the mix design submittal a certification from the asphalt binder supplier that the anti-stripping additive is compatible with the crude source and the formulation of asphalt binder proposed for use in the mix design.
• Do not include warm mix asphalt (WMA) additives when developing a mix design or submitting a mix design for QPL evaluation. The use of warm mix asphalt (WMA) additives is not part of the process for obtaining approval for listing a mix design on the QPL. Refer to Section 5-04.2(2)B.
5-04.2(1)A Vacant
5-04.2(2) Mix Design – Obtaining Project Approval No paving shall begin prior to the approval of the mix design by the Engineer.
11/4/2020
110
Nonstatistical evaluation will be used for all HMA not designated as Commercial HMA in the contract documents.
Commercial evaluation will be used for Commercial HMA and for other classes of HMA in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, pre-level, and pavement repair. Other nonstructural applications of HMA accepted by commercial evaluation shall be as approved by the Project Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the option of the Project Engineer. The Proposal quantity of HMA that is accepted by commercial evaluation will be excluded from the quantities used in the determination of non-statistical evaluation.
Nonstatistical Mix Design. Fifteen days prior to the first day of paving the contractor shall provide one of the following mix design verification certifications for Contracting Agency review;
• The WSDOT Mix Design Evaluation Report from the current WSDOT QPL, or one of the mix design verification certifications listed below.
• The proposed HMA mix design on WSDOT Form 350-042 with the seal and certification (stamp & signature) of a valid licensed Washington State Professional Engineer.
• The Mix Design Report for the proposed HMA mix design developed by a qualified City or County laboratory that is within one year of the approval date.** ** The mix design report shall be performed by a lab accredited by a national authority such as Laboratory Accreditation Bureau, L-A-B for Construction Materials Testing, The Construction Materials Engineering Council (CMEC’s) ISO 17025 or AASHTO Accreditation Program (AAP) and shall supply evidence of participation in the AASHTO: resource proficiency sample program. Mix designs for HMA accepted by Non-statistical evaluation shall;
• Have the aggregate structure and asphalt binder content determined in accordance with WSDOT Standard Operating Procedure 732 and meet the requirements of Sections 9-03.8(2), except that Hamburg testing for ruts and stripping are at the discretion of the Engineer, and 9-03.8(6).
• Have anti-strip requirements, if any, for the proposed mix design determined in accordance with AASHTO T 283 or T 324, or based on historic anti-strip and aggregate source compatibility from previous WSDOT lab testing. At the discretion of the Engineer, agencies may accept verified mix designs older than 12 months from the original verification date with a certification from the Contractor that the materials and sources are the same as those shown on the original mix design.
Commercial Evaluation. Approval of a mix design for “Commercial Evaluation” will be based on a review of the Contractor’s submittal of WSDOT Form 350-042 (For commercial mixes, AASHTO T 324 evaluation is not required) or a Mix Design from the current WSDOT QPL or from one of the processes allowed by this section. Testing of the HMA by the Contracting Agency for mix design approval is not required. For the Bid Item Commercial HMA, the Contractor shall select a class of HMA and design level of Equivalent Single Axle Loads (ESAL’s) appropriate for the required use.
11/4/2020
111
5-04.2(2)B Using Warm Mix Asphalt Processes The Contractor may elect to use additives that reduce the optimum mixing temperature or serve as a compaction aid for producing HMA. Additives include organic additives, chemical additives and foaming processes. The use of Additives is subject to the following:
• Do not use additives that reduce the mixing temperature more than allowed in Section 5-04.3(6) in the production of mixtures.
• Before using additives, obtain the Engineer’s approval using WSDOT Form 350-076 to describe the proposed additive and process.
5-04.3 Construction Requirements
5-04.3(1) Weather Limitations Do not place HMA for wearing course on any Traveled Way beginning October 1st through March 31st of the following year without written concurrence from the Engineer. Do not place HMA on any wet surface, or when the average surface temperatures are less than those specified below, or when weather conditions otherwise prevent the proper handling or finishing of the HMA.
Minimum Surface Temperature for Paving
Compacted Thickness
(Feet)
Wearing Course Other Courses
Less than 0.10 55◦F 45◦F
0.10 to .20 45◦F 35◦F
More than 0.20 35◦F 35◦F
5-04.3(2) Paving Under Traffic When the Roadway being paved is open to traffic, the requirements of this Section shall apply. The Contractor shall keep intersections open to traffic at all times except when paving the intersection or paving across the intersection. During such time, and provided that there has been an advance warning to the public, the intersection may be closed for the minimum time required to place and compact the mixture. In hot weather, the Engineer may require the application of water to the pavement to accelerate the finish rolling of the pavement and to shorten the time required before reopening to traffic. Before closing an intersection, advance warning signs shall be placed and signs shall also be placed marking the detour or alternate route. During paving operations, temporary pavement markings shall be maintained throughout the project. Temporary pavement markings shall be installed on the Roadway prior to opening to traffic. Temporary pavement markings shall be in accordance with Section 8-23. All costs in connection with performing the Work in accordance with these requirements, except the cost of temporary pavement markings, shall be included in the unit Contract prices for the various Bid items involved in the Contract.
11/4/2020
112
5-04.3(3) Equipment
5-04.3(3)A Mixing Plant Plants used for the preparation of HMA shall conform to the following requirements: 1. Equipment for Preparation of Asphalt Binder – Tanks for the storage of asphalt binder shall be equipped to heat and hold the material at the required temperatures. The heating shall be accomplished by steam coils, electricity, or other approved means so that no flame shall be in contact with the storage tank. The circulating system for the asphalt binder shall be designed to ensure proper and continuous circulation during the operating period. A valve for the purpose of sampling the asphalt binder shall be placed in either the storage tank or in the supply line to the mixer. 2. Thermometric Equipment – An armored thermometer, capable of detecting temperature ranges expected in the HMA mix, shall be fixed in the asphalt binder feed line at a location near the charging valve at the mixer unit. The thermometer location shall be convenient and safe for access by Inspectors. The plant shall also be equipped with an approved dial-scale thermometer, a mercury actuated thermometer, an electric pyrometer, or another approved thermometric instrument placed at the discharge chute of the drier to automatically register or indicate the temperature of the heated aggregates. This device shall be in full view of the plant operator. 3. Heating of Asphalt Binder – The temperature of the asphalt binder shall not exceed the maximum recommended by the asphalt binder manufacturer nor shall it be below the minimum temperature required to maintain the asphalt binder in a homogeneous state. The asphalt binder shall be heated in a manner that will avoid local variations in heating. The heating method shall provide a continuous supply of asphalt binder to the mixer at a uniform average temperature with no individual variations exceeding 25°F. Also, when a WMA additive is included in the asphalt binder, the temperature of the asphalt binder shall not exceed the maximum recommended by the manufacturer of the WMA additive. 4. Sampling and Testing of Mineral Materials – The HMA plant shall be equipped with a mechanical sampler for the sampling of the mineral materials. The mechanical sampler shall meet the requirements of Section 1-05.6 for the crushing and screening operation. The Contractor shall provide for the setup and operation of the field testing facilities of the Contracting Agency as provided for in Section 3-01.2(2). 5. Sampling HMA – The HMA plant shall provide for sampling HMA by one of the following methods: a. A mechanical sampling device attached to the HMA plant. b. Platforms or devices to enable sampling from the hauling vehicle without entering the hauling vehicle.
5-04.3(3)B Hauling Equipment Trucks used for hauling HMA shall have tight, clean, smooth metal beds and shall have a cover of canvas or other suitable material of sufficient size to protect the mixture from adverse weather. Whenever the weather conditions during the work shift include, or are forecast to include, precipitation or an air temperature less than 45°F or when time from loading to unloading exceeds 30 minutes, the cover shall be securely attached to protect the HMA. The contractor shall provide an environmentally benign means to prevent the HMA mixture from adhering to the hauling equipment. Excess release agent shall be drained prior to filling hauling equipment with HMA. Petroleum derivatives or other coating material that contaminate or alter the
11/4/2020
113
characteristics of the HMA shall not be used. For live bed trucks, the conveyer shall be in operation during the process of applying the release agent.
5-04.3(3)C Pavers HMA pavers shall be self-contained, power-propelled units, provided with an internally heated vibratory screed and shall be capable of spreading and finishing courses of HMA plant mix material in lane widths required by the paving section shown in the Plans. listed in the Summary of Quantities located in Appendix A. The HMA paver shall be in good condition and shall have the most current equipment available from the manufacturer for the prevention of segregation of the HMA mixture installed, in good condition, and in working order. The equipment certification shall list the make, model, and year of the paver and any equipment that has been retrofitted. The screed shall be operated in accordance with the manufacturer’s recommendations and shall effectively produce a finished surface of the required evenness and texture without tearing, shoving,
segregating, or gouging the mixture. A copy of the manufacturer’s recommendations shall be provided upon request by the Contracting Agency. Extensions will be allowed provided they produce the same results, including ride, density, and surface texture as obtained by the primary screed. Extensions without augers and an internally heated vibratory screed shall not be used in the
Traveled Way. When specified in the Contract or directed by the Engineer, reference lines for vertical control will be required. Lines shall be placed on both outer edges of the Traveled Way of each Roadway. Horizontal control utilizing the reference line will be permitted. The grade and slope for intermediate lanes shall be controlled automatically from reference lines or by means of a mat referencing device and a slope control device. When the finish of the grade prepared for paving is superior to the established tolerances and when, in the opinion of the Engineer, further improvement to the line, grade, cross-section, and smoothness can best be achieved without the use of the reference line, a mat referencing device may be substituted for the reference line. Substitution of the device will be subject to the continued approval of the Engineer. A joint matcher may be used subject to the approval of the Engineer. The reference line may be removed after the completion of the first course of HMA when approved by the Engineer. Whenever the Engineer determines that any of these methods are failing to provide the necessary vertical control, the reference lines will be reinstalled by the Contractor. The Contractor shall furnish and install all pins, brackets, tensioning devices, wire, and accessories necessary for satisfactory operation of the automatic control equipment. If the paving machine in use is not providing the required finish, the Engineer may suspend Work as allowed by Section 1-08.6. Any cleaning or solvent type liquids spilled on the pavement shall be thoroughly removed before paving proceeds.
5-04.3(3)D Material Transfer Device or Material Transfer Vehicle A Material Transfer Device/Vehicle (MTD/V) shall only be used with the Engineer’s approval, unless otherwise required by the contract. A MTD/V is not required for this contract.
11/4/2020
114
Where an MTD/V is required by the contract, the Engineer may approve paving without an MTD/V, at the request of the Contractor. The Engineer will determine if an equitable adjustment in cost or time is due. When used, the MTD/V shall mix the HMA after delivery by the hauling equipment and prior to laydown by the paving machine. Mixing of the HMA shall be sufficient to obtain a uniform temperature throughout the mixture. If a windrow elevator is used, the length of the windrow may be limited in urban areas or through intersections, at the discretion of the Engineer.
To be approved for use, an MTV: 1. Shall be self-propelled vehicle, separate from the hauling vehicle or paver. 2. Shall not be connected to the hauling vehicle or paver. 3. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 4. Shall mix the HMA after delivery by the hauling equipment and prior to placement into the paving machine. 5. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the mixture. To be approved for use, an MTD: 1. Shall be positively connected to the paver. 2. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 3. Shall mix the HMA after delivery by the hauling equipment and prior to placement into the paving machine. 4. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the mixture.
5-04.3(3)E Rollers Rollers shall be of the steel wheel, vibratory, oscillatory, or pneumatic tire type, in good condition and capable of reversing without backlash. Operation of the roller shall be in accordance with the manufacturer’s recommendations. When ordered by the Engineer for any roller planned for use on the project, the Contractor shall provide a copy of the manufacturer’s recommendation for the use of that roller for compaction of HMA. The number and weight of rollers shall be sufficient to compact the mixture in compliance with the requirements of Section 5-04.3(1). The use of equipment that results in crushing of the aggregate will not be permitted. Rollers producing pickup, washboard, uneven compaction of the surface, displacement of the mixture or other undesirable results shall not be used.
5-04.3(4) Preparation of Existing Paved Surfaces When the surface of the existing pavement or old base is irregular, the Contractor shall bring it to a uniform grade and cross-section as shown on the Plans or approved by the Engineer. Preleveling of uneven or broken surfaces over which HMA is to be placed may be accomplished by using an asphalt paver, a motor patrol grader, or by hand raking, as approved by the Engineer. Compaction of preleveling HMA shall be to the satisfaction of the Engineer and may require the use of small steel wheel rollers, plate compactors, or pneumatic rollers to avoid bridging across preleveled areas by the compaction equipment. Equipment used for the compaction of preleveling HMA shall be approved by the Engineer.
11/4/2020
115
Before construction of HMA on an existing paved surface, the entire surface of the pavement shall be clean. All fatty asphalt patches, grease drippings, and other objectionable matter shall be entirely removed from the existing pavement. All pavements or bituminous surfaces shall be thoroughly cleaned of dust, soil, pavement grindings, and other foreign matter. All holes and small depressions shall be filled with an appropriate class of HMA. The surface of the patched area shall be leveled and compacted thoroughly. Prior to the application of tack coat, or paving, the condition of the surface shall be approved by the Engineer. A tack coat of asphalt shall be applied to all paved surfaces on which any course of HMA is to be placed or abutted; except that tack coat may be omitted from clean, newly paved surfaces at the discretion of the Engineer. Tack coat shall be uniformly applied to cover the existing pavement with a thin film of residual asphalt free of streaks and bare spots at a rate between 0.02 and 0.10 gallons per square yard of retained asphalt. The rate of application shall be approved by the Engineer. A heavy application of tack coat shall be applied to all joints. For Roadways open to traffic, the application of tack coat shall be limited to surfaces that will be paved during the same working shift. The spreading equipment shall be equipped with a thermometer to indicate the temperature of the tack coat material. Equipment shall not operate on tacked surfaces until the tack has broken and cured. If the Contractor’s operation damages the tack coat it shall be repaired prior to placement of the HMA. The tack coat shall be CSS-1, or CSS-1h emulsified asphalt. The CSS-1 and CSS-1h emulsified asphalt may be diluted once with water at a rate not to exceed one part water to one part emulsified asphalt. The tack coat shall have sufficient temperature such that it may be applied uniformly at the specified rate of application and shall not exceed the maximum temperature recommended by the emulsified
asphalt manufacturer. All utility appurtenances (e.g. manhole covers, valve covers, etc.) located within the paving limits shall be coated with a biodegradable soap to prevent the tack coat and HMA from sticking to them. Diesel shall not be used for this purpose. After application of the biodegradable soap, all catch basins shall be covered to prevent tack and HMA from entering into them.
5-04.3(4)A Crack Sealing
5-04.3(4)A1 General When the Proposal includes a pay item for crack sealing, seal all cracks ¼ inch in width and greater.
Cleaning: Ensure that cracks are thoroughly clean, dry and free of all loose and foreign material when filling with crack sealant material. Use a hot compressed air lance to dry and warm the pavement surfaces within the crack immediately prior to filling a crack with the sealant material. Do not overheat pavement. Do not use direct flame dryers. Routing cracks is not required.
Sand Slurry: For cracks that are to be filled with sand slurry, thoroughly mix the components and pour the mixture into the cracks until full. Add additional CSS-1 cationic emulsified asphalt to the sand slurry as needed for workability to ensure the mixture will completely fill the cracks. Strike off the sand slurry flush with the existing pavement surface and allow the mixture to cure. Top off cracks that were not completely filled with additional sand slurry. Do not place the HMA overlay until the slurry has fully cured.
11/4/2020
116
The sand slurry shall consist of approximately 20 percent CSS-1 emulsified asphalt, approximately 2 percent portland cement, water (if required), and the remainder clean Class 1 or 2 fine aggregate per section 9-03.1(2). The components shall be thoroughly mixed and then poured into the cracks and joints until full. The following day, any cracks or joints that are not completely filled shall be topped off with additional sand slurry. After the sand slurry is placed, the filler shall be struck off flush with the existing pavement surface and allowed to cure. The HMA overlay shall not be placed until the slurry has fully cured. The requirements of Section 1-06 will not apply to the portland cement and sand used in the sand slurry. In areas where HMA will be placed, use sand slurry to fill the cracks. In areas where HMA will not be placed, fill the cracks as follows: 1. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. 2. Cracks greater than 1 inch in width – fill with sand slurry.
Hot Poured Sealant: For cracks that are to be filled with hot poured sealant, apply the material in accordance with these requirements and the manufacturer’s recommendations. Furnish a Type 1 Working Drawing of the manufacturer’s product information and recommendations to the Engineer prior to the start of work, including the manufacturer’s recommended heating time and temperatures, allowable storage time and temperatures after initial heating, allowable reheating criteria, and application temperature range. Confine hot poured sealant material within the crack. Clean any overflow of sealant from the pavement surface. If, in the opinion of the Engineer, the Contractor’s method of sealing the cracks with hot poured sealant results in an excessive amount of material on the pavement surface, stop and correct the operation to eliminate the excess material.
5-04.3(4)A2 Crack Sealing Areas Prior to Paving In areas where HMA will be placed, use sand slurry to fill the cracks.
5-04.3(4)A3 Crack Sealing Areas Not to be Paved In areas where HMA will not be placed, fill the cracks as follows: a. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. b. Cracks greater than 1 inch in width – fill with sand slurry.
5-04.3(4)B Vacant
5-04.3(4)C Pavement Repair The Contractor shall excavate pavement repair areas and shall backfill these with HMA in accordance with the details shown in the Plans and as marked in the field. The Contractor shall conduct the excavation operations in a manner that will protect the pavement that is to remain. Pavement not designated to be removed that is damaged as a result of the Contractor’s operations shall be repaired by the Contractor to the satisfaction of the Engineer at no cost to the Contracting Agency. The Contractor shall excavate only within one lane at a time unless approved otherwise by the Engineer. The Contractor shall not excavate more area than can be completely finished during the same shift, unless approved by the Engineer. Unless otherwise shown in the Plans or determined by the Engineer, excavate to a depth of 1.0 feet. The Engineer will make the final determination of the excavation depth required. The minimum width
11/4/2020
117
of any pavement repair area shall be 40 inches unless shown otherwise in the Plans. Before any excavation, the existing pavement shall be sawcut or shall be removed by a pavement grinder. Excavated materials will become the property of the Contractor and shall be disposed of in a Contractor-provided site off the Right of Way or used in accordance with Sections 2-02.3(3) or 9-03.21. Asphalt for tack coat shall be required as specified in Section 5-04.3(4). A heavy application of tack coat shall be applied to all surfaces of existing pavement in the pavement repair area. Placement of the HMA backfill shall be accomplished in lifts not to exceed 0.35-foot compacted depth. Lifts that exceed 0.35-foot of compacted depth may be accomplished with the approval of the Engineer. Each lift shall be thoroughly compacted by a mechanical tamper or a roller.
5-04.3(5) Producing/Stockpiling Aggregates and RAP Aggregates and RAP shall be stockpiled according to the requirements of Section 3-02. Sufficient storage space shall be provided for each size of aggregate and RAP. Materials shall be removed from stockpile(s) in a manner to ensure minimal segregation when being moved to the HMA plant for processing into the final mixture. Different aggregate sizes shall be kept separated until they have been delivered to the HMA plant.
5-04.3(5)A Vacant
5-04.3(6) Mixing After the required amount of mineral materials, asphalt binder, recycling agent and anti-stripping additives have been introduced into the mixer the HMA shall be mixed until complete and uniform coating of the particles and thorough distribution of the asphalt binder throughout the mineral materials is ensured. When discharged, the temperature of the HMA shall not exceed the optimum mixing temperature by more than 25°F as shown on the reference mix design report or as approved by the Engineer. Also, when a WMA additive is included in the manufacture of HMA, the discharge temperature of the HMA shall not exceed the maximum recommended by the manufacturer of the WMA additive. A maximum water content of 2 percent in the mix, at discharge, will be allowed providing the water causes no problems with handling, stripping, or flushing. If the water in the HMA causes any of these problems, the moisture content shall be reduced as directed by the Engineer. Storing or holding of the HMA in approved storage facilities will be permitted with approval of the Engineer, but in no event shall the HMA be held for more than 24 hours. HMA held for more than 24 hours after mixing shall be rejected. Rejected HMA shall be disposed of by the Contractor at no expense to the Contracting Agency. The storage facility shall have an accessible device located at the top of the cone or about the third point. The device shall indicate the amount of material in storage. No HMA shall be accepted from the storage facility when the HMA in storage is below the top of the cone of the storage facility, except as the storage facility is being emptied at the end of the
working shift. Recycled asphalt pavement (RAP) utilized in the production of HMA shall be sized prior to entering the mixer so that a uniform and thoroughly mixed HMA is produced. If there is evidence of the
11/4/2020
118
recycled asphalt pavement not breaking down during the heating and mixing of the HMA, the Contractor shall immediately suspend the use of the RAP until changes have been approved by the Engineer. After the required amount of mineral materials, RAP, new asphalt binder and asphalt rejuvenator have been introduced into the mixer the HMA shall be mixed until complete and uniform coating of the particles and thorough distribution of the asphalt binder throughout the mineral materials, and RAP is ensured.
5-04.3(7) Spreading and Finishing The mixture shall be laid upon an approved surface, spread, and struck off to the grade and elevation established. HMA pavers complying with Section 5-04.3(3) shall be used to distribute the mixture. Unless otherwise directed by the Engineer, the nominal compacted depth of any layer of any course shall not exceed the following: HMA Class 1” 0.35 feet HMA Class ¾” and HMA Class ½” wearing course 0.30 feet other courses 0.35 feet
HMA Class ⅜” 0.15 feet On areas where irregularities or unavoidable obstacles make the use of mechanical spreading and finishing equipment impractical, the paving may be done with other equipment or by hand. When more than one JMF is being utilized to produce HMA, the material produced for each JMF shall be placed by separate spreading and compacting equipment. The intermingling of HMA produced from more than one JMF is prohibited. Each strip of HMA placed during a work shift shall conform to a single JMF established for the class of HMA specified unless there is a need to make an adjustment in the JMF. All cast off rock from raking shall be removed prior to compaction of final HMA lift.
5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA For HMA accepted by nonstatistical evaluation the aggregate properties of sand equivalent, uncompacted void content and fracture will be evaluated in accordance with Section 3-04. Sampling and testing of aggregates for HMA accepted by commercial evaluation will be at the option of the Engineer.
5-04.3(9) HMA Mixture Acceptance Acceptance of HMA shall be as provided under nonstatistical, or commercial evaluation. Nonstatistical evaluation will be used for the acceptance of HMA unless Commercial Evaluation is specified. Commercial evaluation will be used for Commercial HMA and for other classes of HMA in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, prelevel, temporary pavement, and pavement repair. Other nonstructural applications of HMA accepted by commercial evaluation shall be as approved by the Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the option of the Engineer.
11/4/2020
119
The mix design will be the initial JMF for the class of HMA. The Contractor may request a change in the JMF. Any adjustments to the JMF will require the approval of the Engineer and may be made in accordance with this section.
HMA Tolerances and Adjustments 1. Job Mix Formula Tolerances – The constituents of the mixture at the time of acceptance shall conform to the following tolerances:
Aggregate Percent Passing Non-Statistical Evaluation Commercial Evaluation 1”, ¾”, ½”, and 3/8” sieves +/- 6% +/- 8% No. 4 sieve +/-6% +/- 8% No. 8 Sieve +/- 6% +/-8% No. 200 sieve +/- 2.0% +/- 3.0% Asphalt Binder +/- 0.5% +/- 0.7% Air Voids, Va 2.5% min. and 5.5% max N/A These tolerance limits constitute the allowable limits as described in Section 1-06.2. The tolerance limit for aggregate shall not exceed the limits of the control points, except the tolerance limits for sieves designated as 100 percent passing will be 99-100. 2. Job Mix Formula Adjustments – An adjustment to the aggregate gradation or asphalt binder content of the JMF requires approval of the Engineer. Adjustments to the JMF will only be considered if the change produces material of equal or better quality and may require the development of a new mix design if the adjustment exceeds the amounts listed below. a. Aggregates – 2 percent for the aggregate passing the 1½ʺ, 1ʺ, ¾ʺ, ½ʺ, ⅜ʺ, and the No. 4 sieves, 1 percent for aggregate passing the No. 8 sieve, and 0.5 percent for the aggregate passing the No. 200 sieve. The adjusted JMF shall be within the range of the control points in Section 9-03.8(6). b. Asphalt Binder Content – The Engineer may order or approve changes to asphalt binder content. The maximum adjustment from the approved mix design for the asphalt binder content shall be 0.3 percent
5-04.3(9)A Vacant
5-04.3(9)B Vacant
5-04.3(9)C Mixture Acceptance – Nonstatistical Evaluation HMA mixture which is accepted by Nonstatistical Evaluation will be evaluated by the Contracting Agency by dividing the HMA tonnage into lots.
5-04.3(9)C1 Mixture Nonstatistical Evaluation – Lots and Sublots A lot is represented by randomly selected samples of the same mix design that will be tested for acceptance. A lot is defined as the total quantity of material or work produced for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to one day’s production or 800 tons, whichever is less except that the final sublot will be a minimum of 400 tons and may be increased to 1200 tons.
11/4/2020
120
All of the test results obtained from the acceptance samples from a given lot shall be evaluated collectively. If the Contractor requests a change to the JMF that is approved, the material produced after the change will be evaluated on the basis of the new JMF for the remaining sublots in the current lot and for acceptance of subsequent lots. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the Engineer is satisfied that material conforming to the Specifications can be produced. Sampling and testing for evaluation shall be performed on the frequency of one sample per sublot.
5-04.3(9)C2 Mixture Nonstatistical Evaluation Sampling Samples for acceptance testing shall be obtained by the Contractor when ordered by the Engineer. The Contractor shall sample the HMA mixture in the presence of the Engineer and in accordance with AASHTO T 168. A minimum of three samples should be taken for each class of HMA placed on a project. If used in a structural application, at least one of the three samples shall be tested. Sampling and testing HMA in a structural application where quantities are less than 400 tons is at the discretion of the Engineer. For HMA used in a structural application with a total project quantity less than 800 tons but more than 400 tons, a minimum of one acceptance test shall be performed. In all cases, a minimum of 3 samples will be obtained at the point of acceptance, a minimum of one of the three samples will be tested for conformance to the JMF:
• If the test results are found to be within specification requirements, additional testing will be at the Engineer’s discretion.
• If test results are found not to be within specification requirements, additional testing of the remaining samples to determine a Composite Pay Factor (CPF) shall be performed.
5-04.3(9)C3 Mixture Nonstatistical Evaluation – Acceptance Testing Testing of HMA for compliance of Va will at the option of the Contracting Agency. If tested, compliance of Va will use WSDOT SOP 731. Testing of HMA for compliance of Va will not be performed by the Contracting Agency for this contract. Testing for compliance of asphalt binder content will be by WSDOT FOP for AASHTO T 308. Testing for compliance of gradation will be by FOP for WAQTC T 27/T 11.
5-04.3(9)C4 Mixture Nonstatistical Evaluation – Pay Factors For each lot of material falling outside the tolerance limits in 5-04.3(9), the Contracting Agency will determine a Composite Pay Factor (CPF) using the following price adjustment factors:
Table of Price Adjustment Factors
Constituent Factor “f”
All aggregate passing: 1½ʺ, 1ʺ, ¾ʺ, ½ʺ, ⅜ʺ and No.4 sieves 2
All aggregate passing No. 8 sieve 15
11/4/2020
121
Table of Price Adjustment Factors
Constituent Factor “f”
All aggregate passing No. 200 sieve 20
Asphalt binder 40
Air Voids (Va) (where applicable) 20 Each lot of HMA produced under Nonstatistical Evaluation and having all constituents falling within the tolerance limits of the job mix formula shall be accepted at the unit Contract price with no further evaluation. When one or more constituents fall outside the nonstatistical tolerance limits in the Job Mix Formula shown in Table of Price Adjustment Factors, the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The nonstatistical tolerance limits will be used in the calculation of the CPF and the maximum CPF shall be 1.00. When less than three sublots exist, backup samples of the existing sublots or samples from the Roadway shall be tested to provide a minimum of three sets of results for evaluation.
5-04.3(9)C5 Vacant
5-04.3(9)C6 Mixture Nonstatistical Evaluation – Price Adjustments For each lot of HMA mix produced under Nonstatistical Evaluation when the calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The total job mix compliance price adjustment will be calculated as the product of the NCMF, the quantity of HMA in the lot in tons, and the unit Contract price per ton of mix.
If a constituent is not measured in accordance with these Specifications, its individual pay factor will
be considered 1.00 in calculating the Composite Pay Factor (CPF).
5-04.3(9)C7 Mixture Nonstatistical Evaluation - Retests The Contractor may request a sublot be retested. To request a retest, the Contractor shall submit a written request within 7 calendar days after the specific test results have been received. A split of the original acceptance sample will be retested. The split of the sample will not be tested with the same tester that ran the original acceptance test. The sample will be tested for a complete gradation analysis, asphalt binder content, and, at the option of the agency, Va. The results of the retest will be used for the acceptance of the HMA in place of the original sublot sample test results. The cost of testing will be deducted from any monies due or that may come due the Contractor under the Contract at the rate of $500 per sample.
5-04.3 (9)D Mixture Acceptance – Commercial Evaluation If sampled and tested, HMA produced under Commercial Evaluation and having all constituents falling within the tolerance limits of the job mix formula shall be accepted at the unit Contract price with no further evaluation. When one or more constituents fall outside the commercial tolerance limits in the Job Mix Formula shown in 5-04.3(9), the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The commercial tolerance limits will be used in the calculation of the CPF and the maximum CPF shall be 1.00. When less than three sublots exist, backup
11/4/2020
122
samples of the existing sublots or samples from the street shall be tested to provide a minimum of three sets of results for evaluation. For each lot of HMA mix produced and tested under Commercial Evaluation when the calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The Job Mix Compliance Price Adjustment will be calculated as the product of the NCMF, the quantity of HMA in the lot in tons, and the unit Contract price per ton of mix. If a constituent is not measured in accordance with these Specifications, its individual pay factor will
be considered 1.00 in calculating the Composite Pay Factor (CPF).
5-04.3(10) HMA Compaction Acceptance HMA mixture accepted by nonstatistical evaluation that is used in traffic lanes, including lanes for intersections, ramps, truck climbing, weaving, and speed change, and having a specified compacted course thickness greater than 0.10-foot, shall be compacted to a specified level of relative density. The specified level of relative density shall be a Composite Pay Factor (CPF) of not less than 0.75 when evaluated in accordance with Section 1-06.2, using a minimum of 92 percent of the maximum density. The maximum density shall be determined by WSDOT FOP for AASHTO T 729. The specified level of density attained will be determined by the evaluation of the density of the pavement. The density of the pavement shall be determined in accordance with WSDOT FOP for WAQTC TM 8, except that gauge correlation will be at the discretion of the Engineer, when using the nuclear density gauge and WSDOT SOP 736 when using cores to determine density. Tests for the determination of the pavement density will be taken in accordance with the required procedures for measurement by a nuclear density gauge or roadway cores after completion of the finish rolling. If the Contracting Agency uses a nuclear density gauge to determine density the test procedures FOP for WAQTC TM 8 and WSDOT SOP T 729 will be used on the day the mix is placed and prior to opening to traffic. Roadway cores for density may be obtained by either the Contracting Agency or the Contractor in accordance with WSDOT SOP 734. The core diameter shall be 4-inches minimum, unless otherwise approved by the Engineer. Roadway cores will be tested by the Contracting Agency in accordance with WSDOT FOP for AASHTO T 166. If the Contract includes the Bid item “Roadway Core” the cores shall be obtained by the Contractor in the presence of the Engineer on the same day the mix is placed and at locations designated by the Engineer. If the Contract does not include the Bid item “Roadway Core” the Contracting Agency will obtain the cores. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the Engineer is satisfied that material conforming to the Specifications can be produced. A lot is represented by randomly selected samples of the same mix design that will be tested for acceptance. A lot is defined as the total quantity of material or work produced for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to one day’s production
11/4/2020
123
or 400 tons, whichever is less except that the final sublot will be a minimum of 200 tons and may be increased to 800 tons. Testing for compaction will be at the rate of 5 tests per sublot per WSDOT T 738. HMA mixture accepted by commercial evaluation and HMA constructed under conditions other than those listed above shall be compacted on the basis of a test point evaluation of the compaction train. The test point evaluation shall be performed in accordance with instructions from the Engineer. The number of passes with an approved compaction train, required to attain the maximum test point density, shall be used on all subsequent paving. HMA for preleveling shall be thoroughly compacted. HMA that is used for preleveling wheel rutting shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer.
Test Results For a sublot that has been tested with a nuclear density gauge that did not meet the minimum of 92 percent of the reference maximum density in a compaction lot with a CPF below 1.00 and thus subject to a price reduction or rejection, the Contractor may request that a core be used for determination of the relative density of the sublot. The relative density of the core will replace the relative density determined by the nuclear density gauge for the sublot and will be used for calculation of the CPF and acceptance of HMA compaction lot. When cores are taken by the Contracting Agency at the request of the Contractor, they shall be requested by noon of the next workday after the test results for the sublot have been provided or made available to the Contractor. Core locations shall be outside of wheel paths and as determined by the Engineer. Traffic control shall be provided by the Contractor as requested by the Engineer. Failure by the Contractor to provide the requested traffic control will result in forfeiture of the request for cores. When the CPF for the lot based on the results of the HMA cores is less than 1.00, the cost for the coring will be deducted from any monies due or that may become due the Contractor under the Contract at the rate of $200 per core and the Contractor shall pay for the cost of the traffic control.
5-04.3(10)A HMA Compaction – General Compaction Requirements Compaction shall take place when the mixture is in the proper condition so that no undue displacement, cracking, or shoving occurs. Areas inaccessible to large compaction equipment shall be compacted by other mechanical means. Any HMA that becomes loose, broken, contaminated, shows an excess or deficiency of asphalt, or is in any way defective, shall be removed and replaced with new hot mix that shall be immediately compacted to conform to the surrounding area. The type of rollers to be used and their relative position in the compaction sequence shall generally be the Contractor’s option, provided the specified densities are attained. Unless the Engineer has approved otherwise, rollers shall only be operated in the static mode when the internal temperature of the mix is less than 175°F. Regardless of mix temperature, a roller shall not be operated in a mode that results in checking or cracking of the mat. Rollers shall only be operated in static mode on bridge decks.
5-04.3(10)B HMA Compaction – Cyclic Density Low cyclic density areas are defined as spots or streaks in the pavement that are less than 90 percent of the theoretical maximum density. At the Engineer’s discretion, the Engineer may evaluate the HMA pavement for low cyclic density, and when doing so will follow WSDOT SOP 733. A $500 Cyclic Density
11/4/2020
124
Price Adjustment will be assessed for any 500-foot section with two or more density readings below 90 percent of the theoretical maximum density.
5-04.3(10)C Vacant
5-04.3(10)D HMA Nonstatistical Compaction
5-04.3(10)D1 HMA Nonstatistical Compaction – Lots and Sublots HMA compaction which is accepted by nonstatistical evaluation will be based on acceptance testing performed by the Contracting Agency dividing the project into compaction lots. A lot is represented by randomly selected samples of the same mix design that will be tested for acceptance, with a maximum of 15 sublots per lot; the final lot for a mix design may be increased to 25 sublots. Sublots will be uniform in size with a maximum sublot size based on original Plan quantity tons of HMA as specified in the table below. The sublot locations within each density lot will be determined by the Engineer. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request after the Engineer is satisfied that material conforming to the Specifications can be produced.
HMA Original Plan
Quantity (tons) Sublot Size (tons)
<20,000 100
20,000 to 30,000 150
>30,000 200 HMA mixture accepted by commercial evaluation and HMA constructed under conditions other than those listed above shall be compacted on the basis of a test point evaluation of the compaction train. The test point evaluation shall be performed in accordance with instructions from the Engineer. The number of passes with an approved compaction train, required to attain the maximum test point density, shall be used on all subsequent paving. HMA for preleveling shall be thoroughly compacted. HMA that is used to prelevel wheel ruts shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer.
5-04.3(10)D2 HMA Compaction Nonstatistical Evaluation – Acceptance Testing The location of the HMA compaction acceptance tests will be randomly selected by the Engineer from within each sublot, with one test per sublot.
5-04.3(10)D3 HMA Nonstatistical Compaction – Price Adjustments For each compaction lot with one or two sublots, having all sublots attain a relative density that is 92 percent of the reference maximum density the HMA shall be accepted at the unit Contract price with no further evaluation. When a sublot does not attain a relative density that is 92 percent of the reference maximum density, the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The maximum CPF shall be 1.00, however, lots with a calculated CPF in excess of 1.00 will be used to offset lots with CPF values below 1.00 but greater than 0.90. Lots with CPF lower than 0.90 will be evaluated for compliance per 5-04.3(11). Additional testing by either
11/4/2020
125
a nuclear moisture-density gauge or cores will be completed as required to provide a minimum of three tests for evaluation. For compaction below the required 92% a Non-Conforming Compaction Factor (NCCF) will be determined. The NCCF equals the algebraic difference of CPF minus 1.00 multiplied by 40 percent. The Compaction Price Adjustment will be calculated as the product of CPF, the quantity of HMA in
the compaction control lot in tons, and the unit Contract price per ton of mix.
5-04.3(11) Reject Work
5-04.3(11)A Reject Work General Work that is defective or does not conform to Contract requirements shall be rejected. The Contractor may propose, in writing, alternatives to removal and replacement of rejected material. Acceptability of such alternative proposals will be determined at the sole discretion of the Engineer. HMA that has been rejected is subject to the requirements in Section 1-06.2(2) and this specification, and the Contractor shall submit a corrective action proposal to the Engineer for approval.
5-04.3(11)B Rejection by Contractor The Contractor may, prior to sampling, elect to remove any defective material and replace it with new material. Any such new material will be sampled, tested, and evaluated for acceptance.
5-04.3(11)C Rejection Without Testing (Mixture or Compaction) The Engineer may, without sampling, reject any batch, load, or section of Roadway that appears defective. Material rejected before placement shall not be incorporated into the pavement. Any rejected section of Roadway shall be removed. No payment will be made for the rejected materials or the removal of the materials unless the Contractor requests that the rejected material be tested. If the Contractor elects to have the rejected material tested, a minimum of three representative samples will be obtained and tested. Acceptance of rejected material will be based on conformance with the nonstatistical acceptance Specification. If the CPF for the rejected material is less than 0.75, no payment will be made for the rejected material; in addition, the cost of sampling and testing shall be borne by the Contractor. If the CPF is greater than or equal to 0.75, the cost of sampling and testing will be borne by the Contracting Agency. If the material is rejected before placement and the CPF is greater than or equal to 0.75, compensation for the rejected material will be at a CPF of 0.75. If rejection occurs after placement and the CPF is greater than or equal to 0.75, compensation for the rejected material will be at the calculated CPF with an addition of 25 percent of the unit Contract price added for the cost of removal and disposal.
5-04.3(11)D Rejection - A Partial Sublot In addition to the random acceptance sampling and testing, the Engineer may also isolate from a normal sublot any material that is suspected of being defective in relative density, gradation or asphalt binder content. Such isolated material will not include an original sample location. A minimum of three random samples of the suspect material will be obtained and tested. The material will then be statistically evaluated as an independent lot in accordance with Section 1-06.2(2).
5-04.3(11)E Rejection - An Entire Sublot
11/4/2020
126
An entire sublot that is suspected of being defective may be rejected. When a sublot is rejected a minimum of two additional random samples from this sublot will be obtained. These additional samples and the original sublot will be evaluated as an independent lot in accordance with Section 1-06.2(2).
5-04.3(11)F Rejection - A Lot in Progress The Contractor shall shut down operations and shall not resume HMA placement until such time as the Engineer is satisfied that material conforming to the Specifications can be produced: 1. When the Composite Pay Factor (CPF) of a lot in progress drops below 1.00 and the Contractor is taking no corrective action, or 2. When the Pay Factor (PF) for any constituent of a lot in progress drops below 0.95 and the Contractor is taking no corrective action, or 3. When either the PFi for any constituent or the CPF of a lot in progress is less than 0.75.
5-04.3(11)G Rejection - An Entire Lot (Mixture or Compaction) An entire lot with a CPF of less than 0.75 will be rejected.
5-04.3(12) Joints
5-04.3(12)A HMA Joints
5-04.3(12)A1 Transverse Joints The Contractor shall conduct operations such that the placing of the top or wearing course is a continuous operation or as close to continuous as possible. Unscheduled transverse joints will be allowed and the roller may pass over the unprotected end of the freshly laid mixture only when the placement of the course must be discontinued for such a length of time that the mixture will cool below compaction temperature. When the Work is resumed, the previously compacted mixture shall be cut back to produce a slightly beveled edge for the full thickness of the course. A temporary wedge of HMA constructed on a 20H:1V shall be constructed where a transverse joint as a result of paving or planing is open to traffic. The HMA in the temporary wedge shall be separated from the permanent HMA by strips of heavy wrapping paper or other methods approved by the Engineer. The wrapping paper shall be removed and the joint trimmed to a slightly beveled edge for the full thickness of the course prior to resumption of paving. The material that is cut away shall be wasted and new mix shall be laid against the cut. Rollers or tamping irons shall be used to seal the joint. All transverse (butt) joints between new and existing asphalt shall be milled to the full overlay depth as listed on the Summary of Quantities located in Appendix A. All transverse (butt) joints shall be sealed after paving. See Section 5-04.3(17) for requirements.
5-04.3(12)A2 Longitudinal Joints The longitudinal joint in any one course shall be offset from the course immediately below by not more than 6 inches nor less than 2 inches. All longitudinal joints constructed in the wearing course shall be located at a lane line or an edge line of the Traveled Way. A notched wedge joint shall be constructed along all longitudinal joints in the wearing surface of new HMA unless otherwise
11/4/2020
127
approved by the Engineer. The notched wedge joint shall have a vertical edge of not less than the maximum aggregate size or more than ½ of the compacted lift thickness and then taper down on a slope not steeper than 4H:1V. The sloped portion of the HMA notched wedge joint shall be uniformly compacted.
5-04.3(12)B Bridge Paving Joint Seals
5-04.3(12)B1 HMA Sawcut and Seal Prior to placing HMA on the bridge deck, establish sawcut alignment points at both ends of the bridge paving joint seals to be placed at the bridge ends, and at interior joints within the bridge deck when and where shown in the Plans. Establish the sawcut alignment points in a manner that they remain functional for use in aligning the sawcut after placing the overlay. Submit a Type 1 Working Drawing consisting of the sealant manufacturer’s application procedure. Construct the bridge paving joint seal as specified ion the Plans and in accordance with the detail shown in the Standard Plans. Construct the sawcut in accordance with the detail shown in the Standard Plan. Construct the sawcut in accordance with Section 5-05.3(8)B and the manufacturer’s application procedure.
5-04.3(12)B2 Paved Panel Joint Seal Construct the paved panel joint seal in accordance with the requirements specified in Section 5-04.3(12)B1 and the following requirement: 1. Clean and seal the existing joint between concrete panels in accordance with Section 5-01.3(8) and the details shown in the Standard Plans.
5-04.3(13) Surface Smoothness The completed surface of all courses shall be of uniform texture, smooth, uniform as to crown and grade, and free from defects of all kinds. The completed surface of the wearing course shall not vary more than ⅛ inch ¼ inch from the lower edge of a 10-foot straightedge placed on the surface parallel to the centerline. The transverse slope of the completed surface of the wearing course shall vary not more than ¼ inch in 10 feet from the rate of transverse slope shown in the Plans. of the existing street surface.
When deviations in excess of the above tolerances are found that result from a high place in the HMA,
the pavement surface shall be corrected by one of the following methods: 1. Removal of material from high places by grinding with an approved grinding machine, or 2. Removal and replacement of the wearing course of HMA, or 3. By other method approved by the Engineer. Correction of defects shall be carried out until there are no deviations anywhere greater than the allowable tolerances. Deviations in excess of the above tolerances that result from a low place in the HMA and deviations resulting from a high place where corrective action, in the opinion of the Engineer, will not produce satisfactory results will be accepted with a price adjustment. The Engineer shall deduct from monies
due or that may become due to the Contractor the sum of $500.00 for each and every section of
single traffic lane 100 feet in length in which any excessive deviations described above are found.
11/4/2020
128
When utility appurtenances such as manhole covers and valve boxes are located in the traveled way, the utility appurtenances shall be adjusted to the finished grade prior to paving. This requirement may be waived when requested by the Contractor, at the discretion of the Engineer or when the adjustment details provided in the project plan or specifications call for utility appurtenance adjustments after the completion of paving. For this contract, utility appurtenances shall be adjusted to final grade after paving, unless otherwise directed by the Engineer. See Section 5-04.3(20) for requirements. Utility appurtenance adjustment discussions will be included in the Pre-Paving planning planing (5-04.3(14)B3). Submit a written request to waive this requirement to the Engineer prior to the start of paving.
5-04.3(14) Planing (Milling) Bituminous Pavement
The planning planing plan must be approved by the Engineer and a pre planning planing meeting must be held prior to the start of any planing. See Section 5-04.3(14)B2 for information on planning planing submittals. Prior to planing operations, existing induction loop vehicle detectors shall be disconnected. Induction loop vehicle detectors shall be removed during planing operations. The planing operation on any street and/or street segment shall not precede the HMA paving operation by more than three (3) calendar days, unless otherwise allowed by the Engineer. Locations of existing surfacing to be planed are as shown in the Drawings. Refer to the Summary of Quantities in Appendix A for the list of streets and/or street segments to be planed in this contract. The depth of planing shall match the thickness of HMA to be placed, as listed on the Summary of Quantities. Where planing an existing pavement is specified in the Contract, the Contractor must remove existing surfacing material and to reshape the surface to remove irregularities. The finished product must be a prepared surface acceptable for receiving an HMA overlay. Use the cold milling method for planing unless otherwise specified in the Contract. Do not use the planer on the final wearing course of new HMA. Conduct planing operations in a manner that does not tear, break, burn, or otherwise damage the surface which is to remain. The finished planed surface must be slightly grooved or roughened and must be free from gouges, deep grooves, ridges, or other imperfections. The Contractor must repair any damage to the surface by the Contractor’s planing equipment, using an Engineer approved method. Repair or replace any metal castings and other surface improvements damaged by planing, as determined by the Engineer.
11/4/2020
129
A tapered wedge cut must be planed longitudinally along curb lines sufficient to provide a minimum of 4 inches of curb reveal after placement and compaction of the final wearing course. The dimensions of the wedge must be as shown on the Drawings or as specified by the Engineer. A tapered wedge cut must also be made at transitions to adjoining pavement surfaces (meet lines) where butt joints are shown on the Drawings. Cut butt joints in a straight line with vertical faces 2 inches or more in height, producing a smooth transition to the existing adjoining pavement. After planing is complete, planed surfaces must be swept, cleaned, and if required by the Contract or as directed by the Engineer, patched and preleveled. before opening planed areas to traffic. The Contractor shall provide for safe vehicular travel over existing utility appurtenances during and after planing operations. For utility appurtenances not lowered prior to planing operations, the Contractor shall place temporary fillets of HMA, with a minimum slope of 4H:1V, around all exposed utility appurtenances if any vehicular traffic will be permitted to travel through the work area prior to paving. The HMA used for this purpose shall be considered an incidental use of HMA as described in Section 5-04.3(18). The Contractor shall provide for safe vehicular travel over driveway entrances during and after planing operations. If the depth of exposed curb or drop off exceeds two (2) inches at a driveway and paving is not occur in the same work shift, the Contractor shall place temporary fillets of HMA along the driveway to provide a transition with a minimum slope of 4H:1V. The HMA used for this purpose shall be considered incidental use of HMA as described in Section 5-04.3(18). The Engineer may direct additional depth planing. Before performing this additional depth planing, the Contractor must conduct a hidden metal in pavement detection survey as specified in Section 5-04.3(14)A.
5-04.3(14)A Pre-Planing Metal Detection Check Before starting planing of pavements, and before any additional depth planing required by the Engineer, the Contractor must conduct a physical survey of existing pavement to be planed with equipment that can identify hidden metal objects. Should such metal be identified, promptly notify the Engineer. See Section 1-07.16(1) regarding the protection of survey monumentation that may be hidden in pavement. The Contractor is solely responsible for any damage to equipment resulting from the Contractor’s failure to conduct a pre-planing metal detection survey, or from the Contractor’s failure to notify the Engineer of any hidden metal that is detected.
5-04.3(14)B Paving and Planing Under Traffic
11/4/2020
130
5-04.3(14)B1 General In addition the requirements of Section 1-07.23 and the traffic controls required in Section 1-10, and unless the Contract specifies otherwise or the Engineer approves, the Contractor must comply with the following: 1. Intersections:
a. Keep intersections open to traffic at all times, except when paving or planing operations through an intersection requires closure. Such closure must be kept to the minimum time required to place and compact the HMA mixture, or plane as appropriate. For paving, schedule such closure to individual lanes or portions thereof that allows the traffic volumes and schedule of traffic volumes required in the approved traffic control plan. Schedule work so that adjacent intersections are not impacted at the same time and comply with the traffic control restrictions required by the Traffic Engineer. Each individual intersection closure or partial closure, must be addressed in the traffic control plan, which must be submitted to and accepted by the Engineer, see Section 1-10.2(2).
b. When planing or paving and related construction must occur in an intersection, consider scheduling and sequencing such work into quarters of the intersection, or half or more of an intersection with side street detours. Be prepared to sequence the work to individual lanes or portions thereof.
c. Should closure of the intersection in its entirety be necessary, and no trolley service is impacted, keep such closure to the minimum time required to place and compact the HMA mixture, plane, remove asphalt, tack coat, and as needed.
d. Any work in an intersection requires advance warning in both signage and a number of Working Days advance notice as determined by the Engineer, to alert traffic and emergency services of the intersection closure or partial closure.
e. Allow new compacted HMA asphalt to cool to ambient temperature before any traffic is allowed on it. Traffic is not allowed on newly placed asphalt until approval has been obtained from the Engineer. 2. Temporary centerline marking, post-paving temporary marking, temporary stop bars, and maintaining temporary pavement marking must comply with Section 8-23. 3. Permanent pavement marking must comply with Section 8-22.
5-04.3(14)B2 Submittals – Planing Plan and HMA Paving Plan The Contractor must submit a separate planing plan and a separate paving plan to the Engineer at least 5 Working Days in advance of each operation’s activity start date. These plans must show how the moving operation and traffic control are coordinated, as they will be discussed at the pre-planing briefing and pre-paving briefing. When requested by the Engineer, the Contractor must provide each operation’s traffic control plan on 24 x 36 inch 11 x 17 inch or larger size Shop Drawings with a scale showing both the area of operation and sufficient detail of traffic beyond the area of operation where detour traffic may be required. The scale on the Shop Drawings is 1 inch = 20 feet 100 feet, which may be changed if the Engineer agrees sufficient detail is shown. The planing operation and the paving operation include, but are not limited to, metal detection, removal of asphalt and temporary asphalt of any kind, tack coat and drying, staging of supply trucks, paving trains, rolling, scheduling, and as may be discussed at the briefing.
11/4/2020
131
When intersections will be partially or totally blocked, provide adequately sized and noticeable signage alerting traffic of closures to come, a minimum 2 Working Days in advance. The traffic control plan must show where peace officers will be stationed when signalization is or may be, countermanded, and show areas where flaggers are proposed. At a minimum, the planing and the paving plan must include:
1. A copy of the accepted traffic control plan, see Section 1-10.2(2), detailing each day’s traffic control as it relates to the specific requirements of that day’s planing and paving. Briefly describe the sequencing of traffic control consistent with the proposed planing and paving sequence, and scheduling of placement of temporary pavement markings and channelizing devices after each day’s planing, and paving.
2. A copy of each intersection’s traffic control plan.
3. Haul routes from Supplier facilities, and locations of temporary parking and staging areas, including return routes. Describe the complete round trip as it relates to the sequencing of paving operations.
4. Names and locations of HMA Supplier facilities to be used.
5. List of all equipment to be used for paving.
6. List of personnel and associated job classification assigned to each piece of paving equipment.
7. Description (geometric or narrative) of the scheduled sequence of planing and of paving, and intended area of planing and of paving for each day’s work, must include the directions of proposed planing and of proposed paving, sequence of adjacent lane paving, sequence of skipped lane paving, intersection planing and paving scheduling and sequencing, and proposed notifications and coordinations to be timely made. The plan must show HMA joints relative to the final pavement marking lane lines.
8. Names, job titles, and contact information for field, office, and plant supervisory personnel.
9. A copy of the approved Mix Designs.
10. Tonnage of HMA to be placed each day.
11. Approximate times and days for starting and ending daily operations.
5-04.3(14)B3 Pre-Paving and Pre-Planing Briefing At least 2 Working Days before the first paving operation and the first planing operation, or as scheduled by the Engineer for future paving and planing operations to ensure the Contractor has adequately prepared for notifying and coordinating as required in the Contract, the Contractor must be prepared to discuss that day’s operations as they relate to other entities and to public safety and convenience, including driveway and business access, garbage truck operations, Metro transit operations and working around energized overhead wires, school and nursing home and hospital and other accesses, other contractors who may be operating in the area, pedestrian and bicycle traffic, and emergency services. The Contractor, and Subcontractors that may be part of that day’s operations, must meet with the Engineer and discuss the proposed operation as it relates to the submitted planing plan and paving plan, approved traffic control plan, and public convenience and safety. Such discussion includes, but is not limited to: 1. General for both Paving Plan and for Planing Plan: a. The actual times of starting and ending daily operations. b. In intersections, how to break up the intersection, and address traffic control and signalization for that operation, including use of peace officers.
11/4/2020
132
c. The sequencing and scheduling of paving operations and of planing operations, as applicable, as it relates to traffic control, to public convenience and safety, and to other contractors who may operate in the Project Site. d. Notifications required of Contractor activities, and coordinating with other entities and the public as necessary. e. Description of the sequencing of installation and types of temporary pavement markings as it relates to planning planing and to paving. f. Description of the sequencing of installation of, and the removal of, temporary pavement patch material around exposed castings and as may be needed g. Description of procedures and equipment to identify hidden metal in the pavement, such as survey monumentation, monitoring wells, street car rail, and castings, before planning planing, see Section 5-04.3(14)B2. h. Description of how flaggers will be coordinated with the planing, paving, and related operations. i. Description of sequencing of traffic controls for the process of rigid pavement base repairs. j. Other items the Engineer deems necessary to address. 2. Paving – additional topics: a. When to start applying tack and coordinating with paving. b. Types of equipment and numbers of each type equipment to be used. If more pieces of equipment than personnel are proposed, describe the sequencing of the personnel operating the types of equipment. Discuss the continuance of operator personnel for each type equipment as it relates to meeting Specification requirements. c. Number of JMFs to be placed, and if more than one JMF how the Contractor will ensure different JMFs are distinguished, how pavers and MTVs are distinguished if more than one JMF is being placed at the time, and how pavers and MTVs are cleaned so that one JMF does not adversely influence the other JMF. d. Description of contingency plans for that day’s operations such as equipment breakdown, rain out, and Supplier shutdown of operations. e. Number of sublots to be placed, sequencing of density testing, and other sampling and testing.
5-04.3(15) Sealing Pavement Surfaces Apply a fog seal where shown in the plans. Construct the fog seal in accordance with Section 5-02.3. Unless otherwise approved by the Engineer, apply the fog seal prior to opening to traffic.
5-04.3(16) HMA Road Approaches HMA approaches shall be constructed at the locations shown in the Plans or where staked by the
Engineer. The Work shall be performed in accordance with Section 5-04.
5-04.3(17) Construction Joint Sealing Transverse Joints - Joints between new and existing asphalt shall be sealed within five (5) calendar days after final rolling of the final lift of HMA. The seal shall be CSS-1 emulsified asphalt. The emulsified asphalt shall be placed in a way to be smooth and flush with roadway surface with minimal overbanding. This work is considered incidental to the bid item “HMA CL. ½” PG 64-22”.
5-04.3(18) Incidental Uses for HMA Incidental uses for HMA shall consist of restoration and adjustment to paved areas and other such uses as directed by the Engineer. For example, a thickened edge may be required for some streets
11/4/2020
133
and/or street segment(s). Incidental uses for HMA shall be measured and paid under the “HMA CL. ½” PG 64-22” bid item for the overlay related HMA and “HMA for Pavement Repair CL ½” PG 64-22” bid item for full depth spot repair related HMA.
5-04.3(19) Edge of Pavement Alignment Where curb and gutter do not exist, the Contractor shall maintain a ± 2 inches per 100 linear feet tolerance for the edge of pavement. The Contractor may establish a reference line as a guide at their discretion or as directed by the Engineer. This work is considered incidental to the bid item “HMA CL. ½” PG 64-22”.
5-04.3(20) Adjusting Utility Covers and Monument Cases to Final Grade The following section only applies to existing utility covers and monument cases covered by HMA. The work shall be completed after the final rolling of the final lift of HMA. The work consists of locating and marking these features and then adjusting them final grade. The Contractor shall locate all utility covers and monument cases covered by HMA immediately after paving operations are complete for a street and/or street segment. Each location shall be marked with paint and identify the type of buried feature. The Contractor shall completely expose all water valve boxes and gas valves for access within five (5) calendar days after final rolling of the final lift of HMA. The Contractor shall adjust the following features to final grade per the requirements listed below. Manholes – Refer to Renton Standard Plan 106 included in Appendix C. Water Valve Boxes – Refer to Renton Standard Plan 330.1 in Appendix C. Gas Valves – Same as Water Valve Boxes. Monument Cases – Refer to Renton Standard Plan 113 in Appendix C. J-boxes, Electrical Vaults, Communications Vaults – These features shall not to be covered with HMA.
5-04.3(21) Temporary Pavement Marking The furnishing and installing of temporary pavement marking shall be as described in Section 8-23. For this contract, all temporary pavement marking is considered short duration.
5-04.4 Measurement
HMA Cl. ___ PG ___, HMA for ___ Cl. ___ PG ___, and Commercial HMA will be measured by the ton in accordance with Section 1-09.2, with no deduction being made for the weight of asphalt binder,
mineral filler, or any other component of the mixture. If the Contractor elects to remove and replace mix as allowed by Section 5-04.3(11), the material removed will not be measured. Roadway cores will be measured per each for the number of cores taken. Preparation of untreated roadway will be measured by the mile once along the centerline of the main line Roadway. No additional measurement will be made for ramps, Auxiliary Lanes, service roads, Frontage Roads, or Shoulders. Measurement will be to the nearest 0.01 mile.
11/4/2020
134
Soil residual herbicide will be measured by the mile for the stated width to the nearest 0.01 mile or by the square yard, whichever is designated in the Proposal. Pavement repair excavation will be measured by the square yard of surface marked prior to excavation. Asphalt for prime coat will be measured by the ton in accordance with Section 1-09.2. Prime coat aggregate will be measured by the cubic yard, truck measure, or by the ton, whichever is designated in the Proposal. Asphalt for fog seal will be measured by the ton, as provided in Section 5-02.4. Longitudinal joint seals between the HMA and cement concrete pavement will be measured by the linear foot along the line and slope of the completed joint seal. Planing bituminous pavement will be measured by the square yard. Planing bituminous pavement to a 2 inch depth will be measured by the square yard. Planing bituminous pavement to a 4 inch depth will be measured by the square yard. Temporary pavement marking will be measured by the linear foot as provided in Section 8-23.4. Water will be measured by the M gallon as provided in Section 2-07.4. Adjust Manhole Cover will be measured per each. Adjust Water Valve Box will be measured per each. Adjust Gas Valve will be measured per each. Adjust Monument Case will be measured per each.
5-04.5 Payment Payment will be made for each of the following Bid items that are included in the Proposal: “HMA Cl. ___ PG ___”, per ton. “HMA for Approach Cl. ___ PG ___”, per ton. “HMA for Preleveling Cl. ___ PG ___”, per ton. “HMA for Pavement Repair Cl. ___ PG ___”, per ton. “Commercial HMA”, per ton.
11/4/2020
135
The unit Contract price per ton for “HMA Cl. ___ PG ___”, “HMA for Approach Cl. ___ PG ___”, “HMA for Preleveling Cl. ___ PG ___”, “HMA for Pavement Repair Cl. ___ PG ___”, and “Commercial HMA” shall be full compensation for all costs, including anti-stripping additive, incurred to carry out the requirements of Section 5-04 except for those costs included in other items which are included in this Subsection and which are included in the Proposal. “Preparation of Untreated Roadway”, per mile. The unit Contract price per mile for “Preparation of Untreated Roadway” shall be full pay for all Work described under 5-04.3(4), with the exception, however, that all costs involved in patching the Roadway prior to placement of HMA shall be included in the unit Contract price per ton for “HMA Cl. ___ PG ___” which was used for patching. If the Proposal does not include a Bid item for “Preparation of Untreated Roadway”, the Roadway shall be prepared as specified, but the Work shall be included in the Contract prices of the other items of Work. “Preparation of Existing Paved Surfaces”, per mile. The unit Contract Price for “Preparation of Existing Paved Surfaces” shall be full pay for all Work described under Section 5-04.3(4) with the exception, however, that all costs involved in patching the Roadway prior to placement of HMA shall be included in the unit Contract price per ton for “HMA Cl. ___ PG ___” which was used for patching. If the Proposal does not include a Bid item for “Preparation of Existing Paved Surfaces”, the Roadway shall be prepared as specified, but the Work shall be included in the Contract prices of the other items of Work. “Crack Sealing”, by force account. “Crack Sealing” will be paid for by force account as specified in Section 1-09.6. For the purpose of providing a common Proposal for all Bidders, the Contracting Agency has entered an amount in the Proposal to become a part of the total Bid by the Contractor. “Pavement Repair Excavation Incl. Haul”, per square yard. The unit Contract price per square yard for “Pavement Repair Excavation Incl. Haul” shall be full payment for all costs incurred to perform the Work described in Section 5-04.3(4) with the exception, however, that all costs involved in the placement of HMA shall be included in the unit Contract price per ton for “HMA for Pavement Repair Cl. ___ PG ___”, per ton. “Asphalt for Prime Coat”, per ton. The unit Contract price per ton for “Asphalt for Prime Coat” shall be full payment for all costs incurred to obtain, provide and install the material in accordance with Section 5-04.3(4). “Prime Coat Agg.”, per cubic yard, or per ton. The unit Contract price per cubic yard or per ton for “Prime Coat Agg.” shall be full pay for furnishing, loading, and hauling aggregate to the place of deposit and spreading the aggregate in the quantities required by the Engineer.
11/4/2020
136
“Asphalt for Fog Seal”, per ton. Payment for “Asphalt for Fog Seal” is described in Section 5-02.5. “Longitudinal Joint Seal”, per linear foot. The unit Contract price per linear foot for “Longitudinal Joint Seal” shall be full payment for all costs incurred to perform the Work described in Section 5-04.3(12). “Planing Bituminous Pavement”, per square yard. “Planing Bituminous Pavement – 2 inch depth”, per square yard. “Planing Bituminous Pavement – 4 inch depth”, per square yard. The unit Contract price per square yard for “Planing Bituminous Pavement”, “Planing Bituminous Pavement – 2 inch depth”, “Planing Bituminous Pavement – 4 inch depth” shall be full payment for all costs incurred to perform the Work described in Section 5-04.3(14). “Temporary Pavement Marking”, per linear foot. Payment for “Temporary Pavement Marking” is described in Section 8-23.5. “Water”, per M gallon. Payment fo r “Water” is described in Section 2-07.5. “Job Mix Compliance Price Adjustment”, by calculation. “Job Mix Compliance Price Adjustment” will be calculated and paid for as described in Section 5-04.3(9)C6. “Compaction Price Adjustment”, by calculation. “Compaction Price Adjustment” will be calculated and paid for as described in Section 5-04.3(10)D3. “Roadway Core”, per each. The Contractor’s costs for all other Work associated with the coring (e.g., traffic control) shall be incidental and included within the unit Bid price per each and no additional payments will be made. “Cyclic Density Price Adjustment”, by calculation. “Cyclic Density Price Adjustment” will be calculated and paid for as described in Section 5-04.3(10)B. “Adjust Manhole Cover”, per each. “Adjust Water Valve Box”, per each.
11/4/2020
137
“Adjust Gas Valve”, per each. “Adjust Monument Case”, per each. The unit Contract price per each for “Adjust Manhole Cover”, “Adjust Water Valve Box”, “Adjust Gas Valve”, “Adjust Monument Case” shall be full payment for all costs incurred to perform the Work described in Section 5-04.3(20).
5-06 TEMPORARY RESTORATION IN PAVEMENT AREA
Section 5-06 is new Section with subsections: (******)
5-06.1 Description Pavement areas that have been removed by construction activities must be restored by the Contractor prior to the end of each working period. Within paved streets, driveways or sidewalks, the Contractor may use temporary pavement to allow vehicular/pedestrian traffic to travel over the construction areas. Temporary pavement shall be placed around trench plates or others devices used to cover construction activities in a manner that provides a smooth and safe transition between surfaces.
5-06.2 Materials The asphalt pavement for temporary patches shall be 2” of a hot mix or cold mix asphalt composition determined by the Contractor to provide a product suitable for the intended application. The Contractor shall not use materials that are a safety or health hazard. Temporary pavement material that does not form a consolidated surface after compaction shall be considered unsuitable and shall be removed from the site. Unsuitable temporary pavement shall be disposed of offsite.
5-06.3 Construction Requirements The Contractor shall maintain temporary asphalt patches to the satisfaction of the governing road agency and the Engineer until said patch is replaced with permanent hot patch. The completed temporary pavement shall be free from ridges, ruts, bumps, depressions, objectionable marks, or other irregularities. The permanent hot mix asphalt patch shall be placed and sealed within 30 calendar days. The Contractor shall immediately repair, patch, or remove any temporary pavement that does not provide a flat transition between existing pavement areas. All temporary asphalt pavement shall be removed from the site by the end of the project and shall not be used as permanent asphalt pavement or subgrade material.
11/4/2020
138
7-01 DRAINS
7-01.2 Materials The second paragraph of Section 7-01.2 is revised with the following: (******) Drain pipes may be concrete, zinc coated (galvanized) corrugated iron with Asphalt Treatment I, aluminum coated (aluminized) corrugated iron with Asphalt Treatment I, zinc coated (galvanized) steel with Asphalt Treatment I, corrugated aluminum alloy, polyvinyl chloride (PVC), corrugated polyethylene (PE), or corrugated polypropylene (PP) at the option of the Contractor unless the Plans specify the type to be used.
7-01.3 Construction Requirements
7-01.3(1) Drain Pipe Section 7-01.3(1) is revised with the following: (******) PVC drainpipe shall be jointed with a bell and spigot joint using a flexible elastomeric seal as described in Section 9-04.8. The bell shall be laid upstream. PE or ABS drainpipe shall be jointed with snap-on, screw-on, or wraparound coupling bands as recommended by the manufacturer of the tubing.
7-01.3(2) Underdrain Pipe The second paragraph is revised with the following: PVC under drain pipe shall be jointed using either the flexible elastomeric seal as described in Section 9-04.8 or solvent cement as described in Section 9-04.9, at the option of the Contractor unless otherwise specified in the Plans. The bell shall be laid upstream. PE or ABS drainage tubing under drain pipe shall be jointed with snap-on, screw-on, or wraparound coupling bands, as recommended by the manufacturer of the tubing.
7-01.4 Measurement Section 7-01.4 is supplemented with the following: (******) When the Contract does not include "Structure Excavation Class B" or "Structure Excavation Class B Including Haul" as a pay item all costs associated with these items shall be included in other contract pay items.
7-02 CULVERTS
7-02.2 Materials The second paragraph of Section 7-02.2 is revised and supplemented with the following: (******) Where steel or aluminum are referred to in this section in regard to a kind of culvert pipe, pipe arch, or end sections, it shall be understood that steel is zinc coated (galvanized) with Asphalt Treatment I or aluminum coated (aluminized) corrugated iron or steel, and aluminum is corrugated aluminum alloy as specified in Sections 9-05.4 and 9-05.5. Where plain or reinforced concrete, steel, or aluminum are referred to in Section 7-02 it shall be understood that reference is also made to PVC.
11/4/2020
139
7-04 STORM SEWERS
7-04.2 Materials The first paragraph of Section 7-04.2 is deleted in its entirety and replaced with the following: (******) Unless a pipe material is specifically called out on the Plans, materials shall meet the following requirements.
Size Pipe Material Allowed Specification
6-12” Polypropylene Storm Sewer Pipe
Ductile Iron Pipe
Corrugated Polyethylene Storm Sewer Pipe (CPEP)
9-05.24(2)
9-05-13
9-05.20
Where bends are specifically called out on the plans, they shall be of the same material and manufacturer as the main pipe and meet the manufacturer’s recommendations. The second paragraph of Section 7-04.2 is supplemented with the following: (******) The Contractor shall require pipe suppliers to furnish certificates signed by their authorized representative, stating the specifications to which the materials or products were manufactured. The Contractor shall provide 2 copies of these certifications to the Engineer for approval. Certificates showing nonconformance with the Contract shall be sufficient evidence for rejection. Approval of certificates shall be considered only as tentative acceptance of the materials and products, and such action by Engineer will not relieve Contractor of his/her responsibility to perform field tests and to replace or repair faulty materials, equipment, and/or workmanship and Contractor’s own expense. Section 7-04.2 is supplemented with the following: (******) Dense foam shall meet 9-05.52 of these Special Provisions.
7-04.3 Construction Requirements
7-04.3(1) Cleaning and Testing Section 7-04.3(1) is supplemented with the following: (******) Before testing begins and in adequate time to obtain approval through submittal process, prepare and submit test plan for approval by Engineer. Include testing procedures, methods, equipment, and tentative schedule. Obtain advance written approval for any deviations from Drawings and Specifications. Repair, correct, and retest sections of pipe which fail to meet specified requirements when tested. Perform testing as work progresses. Schedule testing so that no more than 1000 linear feet of installed pipeline remains untested at one time. Perform testing under observation of Engineer or Inspector.
11/4/2020
140
Schedule testing during no rain. Plug the lower end of the pipe if needed to test pipe. At the request of the Engineer, all pipe larger than 30-inch diameter shall have joints individually tested for Joint Tightness. Prior to final backfill, all joints shall be individually tested using low-pressure air per ASTM C1103. For the installation of any flexible pipe larger than 30-inches in diameter, the Contractor shall retain the services of a pipe manufacturer representative, knowledgeable in the installation methods and practices for the specific pipe product used on this project, as well as on the installation practices for flexible pipelines in general. The manufacturer’s representative shall be present full time on site during the construction of the first 300 feet of pipe installation, and part-time, as required, thereafter until the entire pipeline installation is complete. The manufacturer’s representative shall observe pipe foundation, pipe installation, placement and compaction of pipe zone bedding and backfill, and testing procedures. The manufacturer’s representative shall notify Engineer and Contractor of any non-conforming installation, identifying the manufacturer recommended corrective action(s), within 24 hours of such occurrence. At the request of the Engineer, all flexible pipe shall be tested for maximum pipe deflection by pulling a rigid mandrel through the entire (i.e., 100%) flexible pipe length installed. Maximum deflection shall not exceed 5%. Mandrel testing shall conform to ASTM D3034, and be performed no sooner than 30 days after backfilling and prior to final acceptance testing of the segment. Submit test results to the Engineer. 1. Rigid mandrel shall have outside diameter (O.D.) equal to 95 percent of inside diameter (I.D.) of pipe. Inside diameter of pipe, for purpose of determining outside diameter of mandrel, shall be average outside diameter minus two minimum wall thicknesses for O.D. controlled pipe and average inside diameter for I.D. controlled pipe, dimensions shall be per appropriate standard. Statistical or other "tolerance packages" shall not be considered in mandrel sizing. 2. Rigid mandrel shall be constructed of metal or rigid plastic material that can withstand 200 psi without being deformed. Mandrel shall have nine or more "runners" or "legs" as long as total number of legs is odd number. Barrel section of mandrel shall have length of at least 75 percent of inside diameter of pipe. Rigid mandrel shall not have adjustable or collapsible legs which would allow reduction in mandrel diameter during testing. Provide and use proving ring for modifying each size mandrel. 3. Furnish "proving ring" with each mandrel. Fabricate ring of 1/2-inch-thick, 3-inch-wide bar steel to diameter 0.02 inches larger than approved mandrel diameter. 4. If a rigid mandrel is not available, the Contractor may substitute a round steel bar meeting #3 above. “Testing Storm Sewer Pipe” shall be incidental to and included in storm sewer pipe bid items.
7-04.3(1)G Abandon Existing Storm Sewer Pipes Section 7-04.3(1)G is a new section: (******) Where it is shown on the plans that existing storm sewer pipe is to be abandoned by filling with grout, all abandonment of storm drain lines shall conform to Section 7-17.3(2)I.
11/4/2020
141
7-04.3(2) CCTV Inspection Section 7-04.3(2)is a new added section: (******) All storm drain main lines constructed as part of this project shall be inspected by the use of closed-circuit television (CCTV) before substantial completion. The costs incurred in making the inspection shall be paid for under “CCTV Inspection”. All CCTV inspections for storm drain lines shall conform to Section 7-17.3(2)H.
7-04.3(3) Direct Pipe Connections Section 7-04.3(3) is a new added section as follows: (******) Direct Pipe Tee Connections: Direct pipe tee connections for use in gravity-flow sewer and storm drainage direct connections to pipe shall be Inserta Tee service connections, as manufactured by Inserta Tee and shall meet ASTM F2946 and consist of a PVC hub, rubber sleeve, and stainless steel band. Connection shall be a compression fit into the cored wall of a mainline pipe. Hub shall be made from heavy-duty PVC material. Stainless steel clamping assembly shall be of SS #301 for the band and housing and SS #305 for screws. Rubber sleeve and gasket, when applicable, shall meet the requirements of ASTM F477. Gaskets shall be installed by the manufacturer. A water-based solution provided by the manufacturer shall be used during assembly. Inserta Tee product shall provide a water connection according to the requirements of ASTM D3212. Field Pipe and Joint Performance: To assure water tightness, field performance verification may be accomplished by testing in accordance with ASTM F2487, ASTM F1417 or ASTM C1103. Appropriate safety precautions must be used when field-testing any pipe material. Contact the manufacturer for recommended leakage rates. Installation: Installation shall be accordance with the manufacturer’s recommended installation guidelines. Backfill around the Inserta Tee service connection shall be, at a minimum, of the same material type and compaction level as specified for the mainline pipe installation.
7-05 MANHOLES, INLETS, AND CATCH BASINS
7-05.3 Construction Requirements Section 7-05.3 is supplemented with the following: (******) All manholes shall be in accordance with City of Renton Standard Plans. Connection to manholes or catch basins for storm sewer pipe less than 24-inch shall be “Kor-n-Seal” boot or approved equal. Sanitary sewer pipe to sanitary sewer manhole connections shall be “Kor-n-Seal” boot or approved equal.
11/4/2020
142
7-05.3(1) Adjusting Manholes and Catch Basins to Grade Section 7-05.3(1) is replaced with the following: (******) Where shown in the Plans or where directed by the Engineer, the existing manholes, catch basins, or inlets shall be adjusted to the grade as staked or otherwise designated by the Engineer. The existing cast iron ring and cover on manholes and the catch basin frame and grate shall first be removed and thoroughly cleaned for reinstalling at the new elevation. From that point, the existing structure shall be raised or lowered to the required elevation. The Contractor shall construct manholes so as to provide adjustment space for setting cover and casting to a finished grade as shown on the Construction Plans. Manhole ring and covers shall be adjusted to the finished elevations per Standard Plan 106 prior to final acceptance of the Work. Manholes in unimproved areas shall be adjusted to 6” above grade. In unpaved streets: manholes, catch basins, and similar structures in areas to be surfaced with crushed rock or gravel shall be constructed to a point approximately eight inches below the subgrade and covered with a temporary wood cover. Existing manholes shall be cut off and covered in a similar manner. The Contractor shall carefully reference each manhole so that they may be easily found upon completion of the street Work. After placing the gravel or crushed stone surfacing, the manholes and manhole castings shall be constructed to the finished grade of the roadway surface. Excavation necessary for bringing manholes to grade shall center about the manhole and be held to the minimum area necessary. At the completion of the manhole adjustment, the void around the manhole shall be backfilled with materials which result in the section required on the typical roadway section, and be thoroughly compacted. In cement concrete pavement: manholes, catch basins, and similar structures shall be constructed and adjusted in the same manner as outlined above except that the final adjustment shall be made and cast iron frame be set after forms have been placed and checked. In placing the concrete pavement, extreme care shall be taken not to alter the position of the casting in any way. In asphalt concrete pavement: manholes shall not be adjusted until the pavement is completed, at which time the center of each manhole shall be carefully relocated from references previously established by the Contractor. The manhole shall then be brought to proper grade utilizing the same methods of construction as for the manhole itself. The cast iron frame shall be placed on the concrete grade rings and mortar. The complete patch shall match the existing paved surface for texture, density, and uniformity of grade. The joint between the patch and the existing pavement shall then be carefully painted with hot asphalt cement or asphalt emulsion and shall be immediately covered with dry paving sand before the asphalt cement solidifies. Adjustment of inlets: The final alignment and grade of cast iron frames for new and old inlets to be adjusted to grade will be established from the forms or adjacent pavement surfaces. The final adjustment of the top of the inlet will be performed in similar manner to the above for manholes. On asphalt concrete paving projects using curb and gutter section, that portion of the cast iron frame not embedded in the gutter section shall be solidly embedded in asphalt also. The existing concrete pavement and edge of the casting shall be painted with hot asphalt cement. Adjustments in the inlet structure shall be constructed in the same manner and of the same material as that required for new inlets.
11/4/2020
143
Monument cast iron frame and cover: monument castings shall be adjusted to grade in the same manner as for manholes. Valve box castings: adjustments of valve box castings shall be made in the same manner as for manholes.
7-05.3(3) Connections to Existing Manholes Section 7-05.3(3) is supplemented by adding the following: (******) Where shown on the Plans, new drain pipes shall be connected to existing line, catch basin, curb inlets and/or manholes. The Contractor shall be required to core drill into the structure, shape the new pipe to fit and re-grout the opening in a workmanlike manner. Where directed by the Engineer or where shown on the Plans, additional structure channeling will be required. Connections to existing sanitary sewer manholes shall be core drilled. Couplings shall be equal to “Kor-n-Seal” boots. Existing sanitary sewer manholes shall be cleaned, repaired, and re-channeled as necessary to match the new pipe configuration and as shown on the Construction Plans. A "connection to existing" item will be allowed at any connection of a new line to an existing structure. No "connection to existing" will be accepted at the location of new installation, relocation and adjustment of line manholes, catch basins, or curb inlets. The unit bid price per each shall be full compensation for all labor, materials and equipment required.
7-05.3(5) Manhole Coatings Section 7-05.3(5) is an added new section: (******) All interior surfaces of new precast concrete sanitary sewer manholes shall be shop coated in accordance with 9-08.8. Coating shall be applied in accordance with manufacturer’s recommendations in a controlled environment before arriving on site. Field application of interior coating will not be accepted. Coating Material: High Solids Urethane Surfaces: Concrete Surface Preparation: In accordance with SSPC SP-7 (Sweep of brush off blast) Application: Shop The drying time between coats shall not exceed 24 hours in any case System Thickness: 3.0-4.0 mils dry film Coatings: Primer: One coat of Wasser MC-Shieldcoat 100 (1.5.0-2.0 mils DFT) Finish: Two or more coats of Wasser MC-Shieldcoat 100 (min. 1.5-2.0 mils DFT) Color: White
11/4/2020
144
7-06 TRENCH DRAINS (NEW SECTION)
Section 7-06 is a new section. (******)
7-06.1 Description This Work consists of the construction of new trench drain in accordance with the plans and specifications.
7-06.2 Materials Trench drain shall be Polydrain PDX 15” wide, or acceptable equal. Trench drain and supporting concrete shall be designed for HS20 loading. Grate shall be either Model #603 or #606 as determined by the City. Submittals: A. Shop Drawings: Show a schematic plan of the total drainage system including fabrication details. Shop drawing shall indicate the number and type of each pre-sloped channels and non pre-sloped channels. B. Product Data: Manufacturer's catalog sheets, specifications, and installation instructions for each item specified. C. Samples: Section of trench drain and grate (minimum 6-inch length) D. Product Data: 1. Concrete Design Mix: Submit proposed concrete design mix together with name and location of batching plant at least 28 days prior to the start of concrete work. 2. Portland Cement: Brand and Manufacturer’s name. 3. Air-entraining Admixture: Brand and manufacturer’s name. 4. Water-reducing or High Range Water-reducing Admixture: Brand and manufacturer’s name. 5. Curing and Anti-Spalling Compound: Manufacturer’s specifications and application instructions.
7-06.3 Construction Requirements Cement concrete shall be constructed with air entrained concrete Class 4000 confirming to the requirements of Section 6-02. Applicable requirements for concrete curbs and gutters in Section 8-4.2 shall apply. Trench drain shall be installed per manufacturer’s recommendations and product installation procedures.
11/4/2020
145
7-08 GENERAL PIPE INSTALLATION REQUIREMENTS
7-08.3 Construction Requirements
7-08.3(1)A Trenches Section 7-08.3(1)A is supplemented with the following: (******) Trench Excavation Incl. Haul includes the trench excavation for the storm sewer, sanitary sewer, and water main construction in accordance with the trench limits outlined on the plan drawings. All trench excavated materials shall be disposed of off-site at an approved Contractor-provided disposal site. Excavation outside the excavation limits shown on the plan drawings shall be at no additional expense to the City. Contaminated Trench Excavation includes the trench excavation of materials characterized as contaminated based on sampling results for the storm sewer, sanitary sewer, and water main construction and in accordance with the trench limits outlined on the plan drawings. This excavated soil shall be managed in accordance with applicable state and federal regulations outlined in the Contract Documents. Handling and disposal of materials shall adhere to all transportation requirements, receive pre-approval from a disposal facility, manifesting, and record keeping, etc., as outlined in the Contractor’s Contaminated Soil and Groundwater Handling and Management Plan . Excavations will require a shoring system to limit the volume of excavation. Excavation outside the trench limits shown on the plan drawings shall be at no additional expense to the City.
7-08.3(1)C Bedding the Pipe Section 7-08.3(1)C is supplemented with the following: (******) Bedding material shall meet the requirements of Gravel backfill for Pipe Zone Bedding in accordance with Standard Specification Section 9-03.12(3).. Pipe bedding shall be considered incidental to the pipe and no further compensation shall be made. Pipe bedding material shall be placed to a depth of 6" over and 6" under the exterior walls of the pipe. Hand compaction of the pipe bedding materials under the pipe haunches shall be required. Pipe bedding should provide a firm uniform cradle for support of the pipes. Prior to installation of the pipe, the pipe bedding should be shaped to fit the lower part of the pipe exterior with reasonable closeness to provide uniform support along the pipe. Hand compaction shall be accomplished by using a suitable tamping tool to firmly tamp bedding material under the haunches of the pipe. Care shall be taken to avoid displacement of the pipe during the compaction effort. In areas where the subgrade soils in the trench excavation consist of fine-grained soils, such as silt/clay, or organic rich soils, the Engineer may direct the Contractor to use a geotextile separator fabric be placed over the native soils prior to placement of the pipe bedding. The geotextile shall meet the requirements of Section 9-33.2(1) Table 3 for Separation. Geotextile shall be paid for by other items.
11/4/2020
146
7-08.3(1)D Pipe Foundation Section 7-08.3(1)D is a new section: (******) Pipe foundation in poor soil: When soft or unstable material is encountered at the subgrade which, in the opinion of the Engineer, will not uniformly support the pipe, such material shall be excavated to an additional depth as required by the Engineer and backfilled with foundation gravel material placed in maximum 12-inch lifts. Foundation gravel shall conform to the requirements of Section 9-03.17 of the Standard Specifications. Corrections faulty grade: Excess excavation below grade shall be backfilled with foundation gravel as specified above and thoroughly compacted to the required grade line.
7-08.3(2)A Survey Line and Grade Section 7-08.3(2)A is replaced with: (******) Survey line and grade control shall be provided in accordance with Sections 1-05.4, 1-05.5 and 1-11 in a manner consistent with accepted practices. The Contractor shall transfer line and grade into the trench where they shall be carried by means of a laser beam. Any other procedure shall have the written approval of the Engineer.
7-08.3(2)B Pipe Laying – General Section 7-08.3(2)B is supplemented with the following: (******) Checking of the invert elevation of the pipe may be made by calculations from measurements on the top of the pipe, or by looking for ponding of 1/2" or less, which indicates a satisfactory condition. At manholes, when the downstream pipe(s) is of a larger size, pipe(s) shall be laid by matching the (eight-tenths) flow elevation, unless otherwise approved by the Engineer. All pipe, fittings, etc. shall be carefully handled and protected against damage, impact shocks, and free fall. All pipe handling equipment shall be acceptable to the Engineer. Pipe shall not be placed directly on rough ground but shall be supported in a manner, which will protect the pipe against injury whenever stored at the trench site or elsewhere. No pipe shall be installed where the lining or coating show defects that may be harmful as determined by the Engineer. Such damaged lining or coating shall be repaired, or a new undamaged pipe shall be furnished and installed. The Contractor shall inspect each pipe and fitting prior to installation to insure that there are not damaged portions of the pipe. Any defective, damaged, or unsound pipe shall be repaired or replaced. All foreign matter or dirt shall be removed from the interior of the pipe before lowering into position in the trench. Pipe shall be kept clean during and after laying. All openings in the pipeline shall be closed with watertight expandable type sewer plugs at the end of each day's operation, or whenever the pipe openings are left unattended. The use of burlap, wood, or other similar temporary plugs will not be permitted. Where necessary to raise or lower the pipe due to unforeseen obstructions or other causes, the Engineer may change the alignment and/or the grades. Except for short runs, which may be permitted by the Engineer, pipes shall be laid uphill on grades that exceed 10 percent. Pipe, which is laid on a
11/4/2020
147
downhill grade, shall be blocked and held in place until sufficient support is furnished by the following pipe to prevent movement. Unless otherwise required, all pipe shall be laid straight between the changes in alignment, and at uniform grade between changes in grade. For concrete pipes with elliptical reinforcement, the pipe shall be placed with the minor axis of the reinforcement in a vertical position. Immediately after the pipe joints have been made, proper gasket placement shall be checked with a feeler gage as approved by the pipe manufacturer to verify proper gasket placement.
7-08.3(2)E Rubber Gasketed Joints Section 7-08.3(2)E is supplemented with the following: (******) Care shall be taken by the Contractor to avoid over-inserting the pipe and damaging the pipe or joint system. Any damaged pipe shall be replaced by the Contractor at his expense.
7-08.3(2)H Sewer Line Connections Section 7-08.3(2)H is supplemented with the following: (******) All connections not occurring at a manhole or catch basin shall be done utilizing pre-manufactured tee connectors or pipe sections approved by the Engineer. Any other method or materials proposed for use in making connections shall be subject to approval by the Engineer. Unless otherwise approved by the Engineer, all connections of lateral sewers to existing mains shall be as follows: A. Vitrified Clay Main Cut in new PVC “Tee” using “Strong-Back” Flexible Couplings (Fernco or approved equal). B. Concrete Main Cut in new PVC “Tee” using “Strong-Back” Flexible Couplings (Fernco or approved equal). C. PVC & C900 PVC Main Core-drilled with Romac Saddle (or approved equal) or cut in new “Tee” using “Strong-Back” Flexible Couplings (Fernco or approved equal). D. Ductile Iron Main Core-drilled with Romac Saddle (or approved equal). E. Lined Sewer Main Connection to sewer mains that have been lined (CIPP, Etc.); cut in new “Tee” using “Strong-Back” Flexible Couplings (Fernco or approved equal). F. HDPE Core-Drilled with Romac Saddle. “Inserta-Tee” may be used on sewer mains 12” diameter or larger. Connections (unless booted connections have been provided for) to existing concrete manholes shall be per Section 7-05.3(3).
7-08.3(3)A Backfilling Pipe Trenches Section 7-08.3(3)A is a new section supplementing 7-08.3(3) (******) To the maximum extent available, suitable material obtained from trench or pond excavation shall be used for trench backfill. All material placed as trench backfill shall be free from rocks or stones larger
11/4/2020
148
than 6 inches in their greatest dimension, brush, stumps, logs, roots, debris, and organic or other deleterious materials. No stones or rock shall be placed in the upper three feet of trench backfill. Rock or stones within the allowable size limit incorporated in the remainder of fills shall be distributed so that they do not congregate or interfere with proper compaction. The existing soils shall not be reused as trench backfill unless otherwise required by the Engineer. Structural fill shall consist of Gravel Borrow, meeting the requirements of Section 9-03.14(1) of the Standard Specifications. It should be free of organics and other debris. The structural trench backfill should be moisture conditioned to within approximately 3 percent of optimum moisture content, placed in loose horizontal lifts less than 6 inches in thickness, and compacted to at least 95 percent of the maximum dry density (MDD) as determined by the Modified Proctor compaction test method ASTM D 1557. Trench backfill shall be densely compacted in a systematic manner using methods that consistently produce adequate compaction levels. During placement of the initial lifts, the trench backfill material shall not be bulldozed into the trench or dropped directly on the pipe. Heavy vibratory equipment shall not be permitted to operate directly over the pipe until a minimum of 2 feet of backfill has been placed over the pipe bedding. Contactor shall take special care to obtain good compaction up to the edges of the excavation as the shoring is removed. The Engineer may be on-site to collect soil samples and to test compaction. The Contractor shall provide site access at all times for compaction testing and sample collection. Areas of the trench which fail to meet the compaction requirements shall be removed and replaced and re-compacted at the Contractor’s expense. The Contractor shall be responsible for any settlement of backfill, sub-base, and pavement that may occur during the period stipulated in the Contract conditions. All repairs necessary due to settlement shall be made by the Contractor at his expense. Backfill in unimproved areas shall be compacted to at least 90 percent of maximum dry density as determined by the modified proctor compaction test, ASTM D1557. The Contractor shall be responsible for the disposal of any excess excavated material.
Section 7-08.3(5) Temporary Stormwater Diversion Section 7-08.3(5) is an added new section (******) It shall be the Contractor’s responsibility to maintain operation of the existing storm sewer system throughout the duration of the project without any disruption of service until the new storm drain has been accepted by the City to receive stormwater flows, and connections are made between the existing and new storm based on scheduling approved by the Engineer. A temporary stormwater diversion shall be capable of bypassing at least the 2-year peak flow during construction.
11/4/2020
149
The Contractor shall submit proposed methods for providing the diversions to the Engineer for approval prior to construction. The diversions shall have the least impact on property owners and traffic flow through the site. The diversions shall be installed, operated, and maintained only when needed where the existing storm drain system must be demolished to allow construction of the new system. Where shown on the Plans, Contractor shall time work of bypasses during period of anticipated no or little rain. If bypass pumping is provided, it shall be scheduled for continuous operation with backup equipment available at all times for periods of maintenance and refueling or failure of the primary bypass pump(s) or diversion system. The Contractor shall submit a Temporary Stormwater Diversion Plan in accordance with Section 1-05. The Contractor’s plan shall be reviewed by the City before the plan is implemented. The review of the flow diversion plan shall, as well as the Contractor’s proposed size of the bypass, in no way relieve the Contractor of his responsibility to provide a bypass system that conveys encountered flows without property damage or damage to the project or construction area. As risk associated with sizing the bypass and impacts to construction is born by the Contractor.
7-08.4 Measurement Section 7-17.4 is supplemented with the following: (******) Measurement of “Bank Run Gravel for Trench Backfill Sewer” will be determined by the cubic yard in place, measured by the neat line dimensions shown in the Plans, or by the ton on truck tickets.
7-09 PIPE AND FITTINGS FOR WATER MAINS
7-09.3(15)A Ductile Iron Pipe Section 7-09.3(15) is deleted in its entirety and replaced with the following: (******) Long radius curves with radius of 400 feet or more, either horizontal or vertical, pipe may be laid with standard pipe lengths by deflecting the joints. If the pipe is shown curved on the Plans and no special fittings are shown, the Contractor can assume that the curves can be made by deflecting the joints with standard lengths of pipe. If shorter lengths are required, the Plans will indicate maximum lengths that can be used. The amount of deflection at each pipe joint when pipe is laid on a horizontal or vertical curve shall not exceed 50% of the manufacturer’s printed recommended deflections. The Contractor shall submit to the Engineer the pipe manufacturer's joint deflection recommendations prior to pipe installation indicating deflections are within allowable AWWA specification tolerances. Where field conditions require deflection or curves not anticipated by the Plans, the Engineer will determine the methods to be used. No additional payment will be made for laying pipe on curves as shown on the Plans, or for field changes involving standard lengths of pipe deflected at the joints. When special fittings not shown on the Plans are required to meet field conditions, additional payment will be made for special fittings as provided in Section 1-09.6. When rubber gasketed pipe is laid on a curve, the pipe shall be jointed in a straight alignment and then deflected to the curved alignment. Trenches shall be made wider on curves for this purpose.
11/4/2020
150
Where pipe installation on curves requires the use of special fittings, concrete blocking shall be used per Section 7-09.3(21). Where restrained joint pipe is installed on a curve, the Contractor shall submit the pipe manufacturer’s recommendations to the Engineer for approval.
7-09.3(15)B Polyvinyl Chloride (PVC) Pipe (4 inches and Over) Section 7-09.3(15)B is deleted in its entirety and replaced with the following: (******) Polyvinyl Chloride (PVC) Pipe shall not be used for water mains and appurtenances.
7-09.3(17) Laying Ductile Iron Pipe and Fittings with Polyethylene Encasement The title and text of section 7-09.3(17) has been revised with the following: (******) The Contractor shall lay ductile iron pipe with a polyethylene encasement. Pipe and polyethylene encasement shall be installed in accordance with AWWA C105. The polyethylene encasement shall also be installed on all appurtenances, such as pipe laterals, couplings, fittings, and valves, with 8-mil polyethylene plastic in accordance with Section 4-5 of ANSI 21.5 or AWWA C105. The polyethylene wrap shall be tube type and black color. Any damage that occurs to the wrap shall be repaired in accordance with ANSI/AWWA C105/A21.5-93. Installation of the polyethylene encasement shall be considered incidental to the installation of the pipe and no additional payment shall be allowed.
7-09.3(19)A Connections to Existing Mains Section 7-09.3(19) is revised to read as follows: (******) The Contractor shall not operate any valve on existing Water Main. The City of Renton Water Operations and Maintenance staff will make all connections to charged water mains and will operate all valves to accomplish shutdowns and subsequent reactivation. The draining of existing water mains will be done by City water maintenance staff. The Contractor shall provide pumping and disposal of the water from the draining of the existing water mains including de-chlorination of the water prior to disposal. Connections to the existing water main shall not be made without first making the necessary scheduling arrangements with the Engineer in advance. The Contractor shall request water main shut-offs for connections of new water mains to existing water mains at least ten (10) working days in advance for each connection. Approval of connections to existing water main is contingent on the Water Main and appurtenances being completely installed, tested, cleaned with polypig, disinfected and flushed per Contract requirements. City’s water operations and maintenance staff will notify in writing all water customers affected by the shut-offs of the water mains at least 48 hours in advance (not including weekends and holidays) of any water shut-offs. The Contractor may be required to perform the connection during times other than normal working hours. Water main shut-offs shall occur during non-holiday weekdays unless
11/4/2020
151
otherwise specified in the contract documents. Water main shut-offs shall not occur in the five (5) weekdays preceding or the day after the major holidays listed below: New Year’s Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Christmas Day. Due to the needs of various water customers in the project vicinity, water shut-off periods are limited to the times set forth below: Days Hours Monday to Thursday 9:00 AM TO 3:00 PM Friday to Sunday DO NOT SCHEDULE The City of Renton’s Water Maintenance Manager, at his/her sole discretion, may adjust the above shut-off periods in order to address specific project circumstances and customer needs. No water main shutoffs affecting public schools will be allowed during scheduled school hours. The City reserves the right to re-schedule the connection if the work area is not ready at the scheduled time for the connection. Points of connection to existing water mains shall be exposed by hydro excavation or potholing prior to trenching of the new water mains. Before the installation of the new water mains, the Contractor shall field verify, in the presence of the Engineer, the actual location and depth of the existing water mains where new connections will be made to assure proper fit. Care shall be taken not to disturb existing thrust blocks and soil bearing areas. After excavation, the Contractor shall verify the dimensions, type, condition, and roundness of the exposed water main. The Contractor shall immediately notify the Engineer if the connection cannot be made as specified by the Contract Plans in order that the connection detail may be revised. When necessary, the profile shall be adjusted as directed by the Engineer to prevent abrupt changes in grade and alignment of the water main and connection. The Contractor shall provide all saw-cutting, removal and disposal of existing surface improvements, excavation, haul and disposal of unsuitable materials, shoring, de-watering, foundation material, at the connection areas before the scheduled time for the connection by the City. The Contractor shall provide all materials necessary for the City Water Maintenance personnel to install all connections to existing water mains as indicated on the contract plans, including fittings, couplings, pipe spools, shackle materials to complete the connections. The City Water Operations and Maintenance staff will: a) Deactivate and dewater the existing and new water main to perform the connections. The Contractor shall provide pumping and disposal of the water from the draining of the water mains including de-chlorination. b) Cut, remove and dispose pipe sections as necessary to install the new Materials with Contractor’s assistance c) Swab all connecting pipe and fittings with 5-6%chlorine solution d) Perform the connection work e) Reactivate and flush the Water Main
11/4/2020
152
The Contractor shall install the polywrap on all pipe and fittings at the connection points and installed concrete thrust blocks per Contract standard plans and specifications. In addition to those connections shown on the Plans, segments of a new Water Main may be placed in service prior to completion of the new Water Main. All connection between the charged and uncharged segments of the new Water Main, including connection to a new Tapping Tee and Valve will be done by the City of Renton Water Operations and Maintenance staff. Connections to existing water mains which include the cutting of the existing water main for the installation of new in-line tee and valves shall be done in two steps: Step 1: Cut-in of existing water main for installation of in-line tee, valves and appurtenances. The Contractor shall provide all materials necessary for the City Water Maintenance personnel to cut the existing water main as indicated on the contract plans for the installation of the in-line tee and valves, including but not limited to the required fittings, couplings, pipe spools, shackle materials to complete the cut-in. After the cut-in of the in-line tee and valves by City personnel, the Contractor shall provide and install concrete blocking and polyethylene encasement behind the tee and other fittings. A minimum 3-day curing period is for all concrete blockings before a connection can be made to the new water mains or new tapping valve.
Step 2: Connection of new water main to the above cut-in tee and valves, or to a new tapping valve on existing water mains
7-09.3(21) Concrete Thrust Blocking and Dead-Man Block Section 7-09.3(21) is deleted in its entirety and replaced with the following: (******) Concrete thrust blocking shall be placed at bends, tees, dead ends, crosses and on other fittings in conformance to the City of Renton Standards Plans, latest revisions and Contract Plans. Concrete thrust collar and blocking and dead-man thrust blocking shall be installed at locations shown on the plans and shall be in conformance with the Standard Plans and contract Plans. Reinforcement steel shall be Grade 40 or better. Blocking shall be poured in place Ready-Mix Concrete Class 3000 with a minimum compressive strength at 28 days of 3,000 psi. Job site mixing, hand-mixed concrete and mobile concrete mixers are not allowed. All fittings to be blocked shall be wrapped with 8-mil polyethylene plastic. Concrete blocking shall bear against solid undisturbed earth at the sides and bottom of the trench excavation and shall be shaped and properly formed with plywood or other acceptable forming materials so as not to obstruct access to the joints of the pipe, bolts or fittings. The forms shall be removed prior to backfilling. Unacceptable concrete blocking shall be replaced at the Contractor’s expense. The Contractor shall provide the Engineer at least 1 Working Day advance notice before pouring concrete thrust blocking and 1 Working Day advance notice for inspection and approval of all concrete blocking prior to backfilling.
11/4/2020
153
7-09.3(23) Hydrostatic Pressure Test Section 7-09.3(23) is revised to read as follows: (******) Water main and appurtenances including service connections to the meter setter shall be tested in sections of convenient length under a hydrostatic pressure equal to 150 psi in excess of that under which they will operate or in no case shall the test pressure be less than 225 psi at the highest point on the water main. Pumps, gauges, plugs, saddles, corporation stops, miscellaneous hose and piping, and measuring equipment necessary for performing the test shall be furnished and operated by the Contractor. The Contractor shall obtain a hydrant meter permit from the City by completing a permit application and making the required security deposits. The Contractor shall use the City’s issued hydrant meter with an attached backflow prevention assembly to draw water from the City’ water system to fill the water mains for poly-pigging, testing, cleaning, disinfection and for subsequent flushing purposes. There will be a charge for the water used for filling, testing, cleaning and disinfection of the water mains. Sections to be tested shall normally be limited to 1,500 feet or less. The Engineer may require that the first section of pipe, not less than 1,000 feet in length, installed by each of the Contractor’s crews, be tested in order to qualify the crew and the materials. Pipe laying shall not be continued more than an additional 1,000 feet until the first section has been tested successfully. The pipeline shall be backfilled sufficiently to prevent movement of the pipe under pressure. Thrust blocks shall be in place and time allowed for the concrete to cure before testing. Where permanent blocking is not required, the Contractor shall furnish and install temporary blocking and remove it after testing. Before applying the specified test pressure, the water main shall be slowly filled and air shall be expelled completely from the pipe, valves and hydrants. If permanent air vents are not located at all high points, the contractor shall install corporation cocks at such points so that the air can be expelled as the line is filled with water. After all the air has been expelled, the corporation cocks shall be closed and the test pressure applied. At the conclusion of the pressure test, the corporation cocks shall be removed and plugged. The Contractor shall perform a leakage test concurrently with the pressure test. The pressure test shall be conducted for a 2-hour period. The test shall be accomplished by pumping the main up to the required pressure, stopping the pump for 2 hours, and then pumping the main up to the test pressure again. During the test, the section being tested shall be observed to detect any visible leakage. A clean container shall be used for holding water for pumping up pressure on the main being tested. This makeup water shall be sterilized by the addition of chlorine to a concentration of 50 mg/l. The acceptability of the pressure test and leakage test will be determined by two factors as follows: 1. The loss in pressure shall not exceed 5 psi during the 2-hour test period. 2. The quantity of water lost from the main and appurtenances shall not exceed the number of gallons during the 2-hour test period as listed in the following table.
11/4/2020
154
Allowable leakage in gallons per 1000 ft. of pipeline* for a 2-hour test period Nominal Pipe Diameter in inches Test Pressure in psi 4” 6" 8" 10" 12" 16" 20" 24"
400 0.60 0.90 1.20 1.50 1.80 2.40 3.00 3.60 375 0.58 0.87 1.16 1.45 1.74 2.33 2.91 3.49 350 0.56 0.84 1.12 1.40 1.69 2.25 2.81 3.37 275 0.50 0.75 1.00 1.24 1.49 1.99 2.49 2.99 250 0.47 0.71 0.95 1.19 1.42 1.90 2.37 2.85 225 0.45 0.68 0.90 1.13 1.35 1.80 2.25 2.70 200 0.42 0.64 0.85 1.06 1.28 1.70 2.12 2.55 *If the pipeline under test contains sections of various diameters, the allowable leakage will be the sum of the computed leakage for each size. For those diameters or pressures not listed, the formula below shall be used: The quantity of water lost from the main shall not exceed the number of gallons per hour as determined by the formula: L= SD√P__ 266,400 where: L = Allowable leakage in gallons/hour S = Gross length of pipe tested, feet D = Nominal diameter of the pipe in inches P = Test pressure during the leakage test in psi The quantity of water required to restore the pressure shall be accurately determined by either 1) pumping from an open container of suitable size such that accurate volume measurements can be made by the Engineer or, 2) by pumping through a positive displacement water meter with a sweep unit hand registering one (1) gallon per revolution. The meter shall be approved by the Engineer. Pressure gauges used in the test shall be accompanied with certifications of accuracy from a testing Laboratory approved by the Engineer. Any visible leakage detected shall be corrected by the Contractor regardless of the allowable leakage specified above. Should the tested section fail to meet the pressure test successfully as specified, the Contractor shall, at no additional expense to the Contracting Agency, locate and repair the defects and then retest the pipeline. All tests shall be made with the hydrant auxiliary gate valves open and pressure against the hydrant inlet valve. After the test is completed, each valve shall be tested by closing each in turn and relieving the pressure beyond. This test of the valve will be acceptable if there is no immediate loss of pressure on the gauge when the pressure comes against the valve being checked. The Contractor shall verify that the pressure differential across the valve does not exceed the rated working pressure of the valve.
11/4/2020
155
Prior to calling out the Engineer to witness the pressure test, the Contractor shall have all equipment set up completely ready for operation and shall have successfully performed the test to ensure that the pipe is in satisfactory condition. Defective materials or workmanship, discovered as a result of hydrostatic field test, shall be replaced by the Contractor at no additional expense to the Contracting Agency. Whenever it is necessary to replace defective material or correct the workmanship, the hydrostatic test shall be re-run at the Contractor’s expense until a satisfactory test is obtained.
7-09.3(24)A Flushing and "Poly-pigging" Section 7-09.3(24)A shall be revised and supplemented with the following: (******) Prior to disinfection and prior to final flushing of the Water Mains for bacteriological sampling and testing, all Water Mains shall first be poly-pigged to remove any solids or contaminated materials that may have entered or become lodged in the pipes during installation. The "Poly-pig" shall be light density foam (1-2 lbs/cubic-foot) with 90A durometer urethane rubber coating on the rear of the "Poly-pig" only. The "Poly-pig" shall be cylinder shaped with bullet nose or squared end. The “Poly-pigs” shall be inserted in the pipes and retrieved form the pipes through launching stations with vertical crosses and blow-off assemblies as shown and on the Contract Plans and Standard Plans. If the main cannot be poly-pigged, then a tap shall be provided large enough to develop a flow velocity of at least 2.5 fps in the water main. Taps required by the Contractor for temporary or permanent release of air, chlorination or flushing purposes shall be provided by the Contractor as part of the construction of water mains. The Contractor shall be responsible for disposal of treated water flushed from mains and shall neutralize the wastewater for protection of aquatic life in the receiving water before disposal into any natural drainage channel, i.e., receiving water, waters of the State, including wetlands. The Contractor shall be responsible for disposing of disinfecting solution to the satisfaction of the Contracting Agency and local authorities. At a minimum, chlorinated water shall be dechlorinated to a concentration of 0.1 parts per million (ppm) or less, and pH adjustment to within 6.5 – 8.5 standard units before discharging to surface waters of the State or to a storm sewer system that drains to surface waters of the State. If approved by the Engineer and by the local authority responsible for the sanitary sewer system, disposal of treated water from mains may be made to an available sanitary sewer, provided the rate of disposal will not overload the sewer.
7-09.3(24)D Dry Calcium Hypochlorite Section 7-09.3(24)D is deleted in its entirety and replaced with the following: (******) Dry calcium hypochlorite shall not be placed in the pipe as laid.
11/4/2020
156
7-09.3(24)K Retention Period Section 7-09.3(24)K is deleted in its entirety and replaced with the following: (******) Treated water shall be retained in the pipe at least 16 hours but no longer than 48 hours. After the retention period, the chlorine residual shall be tested at all pipe extremities and at other representative points and shall measure at least 10 mg/L. If a measurement of less than 10 mg/L is obtained repeat disinfection is required.
7-09.3(24)N Final Flushing and Testing Section 7-09.3(24)N is deleted in its entirety and replaced with the following: (******) Following chlorination, treated water shall be flushed from the newly-laid pipe until the replacement water throughout its length shows, upon test, the absence of chlorine. In the event chlorine is normally used in the source of supply, then the tests shall show a residual not in excess of that carried in the water supply system. A sample tap shall be located ahead of the flushing hose for convenience and for sanitary sampling. Before placing the lines into service, two satisfactory reports taken at least 15 minutes apart from each sampling point shall be received from the local or State Health Department or from a State accredited testing laboratory on samples collected from representative points in the new system. Samples will be collected and bacteriological tests obtained by the Engineer. At a minimum, chlorinated water shall be dechlorinated to a concentration of 0.1 parts per million (ppm) or less, and pH adjustment to within 6.5 to 8.5 standard units, if necessary, before discharging to surface waters of the State or to a storm sewer system that drains to surface waters of the State.
7-09.3(25) Joint Restraint Systems Section 7-09.3(25) is a new section: (******) General: Where shown in the Plans, in the Specifications or required by the Engineer, joint restraint system (shackle rods) shall be used. All joint restraint materials used shall be those manufactured by Star National Products, 1323 Holly Avenue, PO Box 258, Columbus Ohio 43216, unless an equal alternate is approved in writing by the Engineer. Materials: Steel types used shall be: High strength low-alloy steel (cor-ten), ASTM A242, heat-treated, superstar "SST" series. High strength low-alloy steel (cor-ten), ASTM A242, superstar "SS" series. Items to be galvanized are to meet the following requirements: ASTM A153 for galvanizing iron and steel hardware. ASTM A123 for galvanizing rolled, pressed and forged steel shapes.
11/4/2020
157
Joint restrainer system components: Tiebolt: ASTM A242, type 2, zinc plated or hot-dip galvanized. SST 7:5/8" for 2" and 3" mechanical joints, 3/4" for 4" to 12" mechanical joints, ASTM A325, type 3D, except tensile strength of full-body threaded section shall be increased to 40,000 lbs. minimum for 5/8" and 60,000 lbs. minimum for 3/4" by heat treating (quenching and tempering) to manufacturer’s reheat and hardness Specifications. SST 753: 3/4" for 14" to 24" mechanical joints. Same ASTM Specification as SST 7. SST 77: 3/4" same as SST 7, except 1" eye for 7/8" rod. Same ASTM Specification as SST 7. Tienut: Heavy hex nut for each tiebolt: SS8: 5/8" and 3/4", ASTM A563, grade C3, or zinc plated. S8: 5/8" and 3/4", ASTM A563, grade A, zinc plated or hot-dip galvanized. Tiecoupling: Used to extend continuous threaded rods and are provided with a center stop to aid installation, zinc plated or hot-dip galvanized. SS10: for 5/8" and 3/4" tierods, ASTM A563, grade C3. S10: for 5/8" and 3/4" tierods, ASTM A563, grade A. Tierod: Continuous threaded rod for cutting to desired lengths, zinc plated or hot-dip galvanized. SS12: 5/8" and 3/4" diameter, ASTM A242, type 2; ANSI B1.1. S12: 5/8" and 3/4" diameter, ASTM A36, A307. Tiewasher: Round flat washers, zinc plated or hot-dip galvanized. SS17: ASTM A242, F436. S17: ANSI B18.22.1. Installation: Install the joint restraint system in accordance with the manufacturer’s instructions so all joints are mechanically locked together to prevent joint separation. Tie-bolts shall be installed to pull against the mechanical joint body and not the MJ follower. Torque nuts at 75-90 foot pounds for 3/4" nuts. Install tie-couplings with both rods threaded equal distance into tie-couplings. Arrange tie-rods symmetrically around the pipe. Pipe Diameter Number of 3/4" Tie Rods Required 4” 2 6” 2 8” 2 10” 4 12” 4 14” 6 16” 6 18” 8 20 10 24” 12 Where a manufacturer’s mechanical joint valve or fitting is supplied with slots for "T" bolts instead of holes, a flanged valve with a flange by mechanical joint adapter shall be used instead, so as to provide adequate space for locating the tie-bolts.
11/4/2020
158
Where a continuous run of pipe is required to be restrained, no run of restrained pipe shall be greater than 60 feet in length between fittings. Insert long body solid sleeves as required on longer runs to keep tie-rod lengths to the 60 foot maximum. Pipe used in continuously restrained runs shall be mechanical joint pipe and tie-bolts shall be installed as rod guides at each joint. Where poly wrapping is required all tie-bolts, tie-nuts, tie-couplings, tie-rods, and tie-washers, shall be galvanized. All disturbed sections will be painted, to the Inspector ’s satisfaction, with Koppers Bitomastic No. 300-m, or approved equal. Where poly wrapping is not required all tie-bolts, tie-nuts, tie-couplings, tie-rods and tie-washers may be galvanized as specified in the preceding paragraph or plain and painted in the entirety with Koppers Bitumastic No. 800-m, or approved equal. Tie-bolts, tie-nuts, tie-couplings, tie-rods, and tie-washers shall be considered incidental to installation of the pipe and no additional payment shall be made.
7-09.4 Measurement Section 7-09.4 is revised with the following: (******) Measurement of bank run gravel for trench backfill will be by the cubic yard measured by the calculation of neat lines based on maximum trench width per Section 2-09.4 or by the ton, in accordance with Section 1-09. Measurement for payment of concrete thrust blocking and dead-man blocks will be per cubic-yard when these items are included as separate pay items. If not included as separate pay items in the contract, then thrust blocking and dead-man blocks shall be considered incidental to the installation of the water main and no further compensation shall be made. Measurement for payment for connections to existing water mains will be per each for each connection to existing water main(s) as shown on the Plans.
7-09.5 Payment Section 7-09.5 is revised and supplemented with the following: (******) "Furnish and Install ____Ductile Iron Water Main & Fittings”, per lineal foot. The unit contract price per linear foot for each size and kind of “Furnish and Install ____Ductile Iron Water Main & Fittings" shall be full pay for the bid item as described in Section 1-09.14. "Concrete Thrust Blocking and Dead-Man Anchor Blocks", per cubic yard. The unit contract price per cubic yard for "Concrete Concrete Thrust Blocking and Dead-Man Anchor Blocks " shall be full pay for the bid item as described in Section 1-09.14. "Connection to Existing Water Mains", per each. The unit contract price per each for “Connection to Existing Water Mains” shall be full pay for the bid item as described in Section 1-09.14.
11/4/2020
159
“Select Imported Trench Backfill”, per cubic yard or ton. The unit contract price per cubic yard or ton for “Select Imported Trench Backfill” shall be full pay for the bid item as described in Section 1-09.14. "Removal and Replacement of Unsuitable Foundation Material", per ton or cubic yard. The unit contract price per cubic yard or ton for "Removal and Replacement of Unsuitable Foundation Material" shall be full pay for the bid item as described in Section 1-09.14.
7-12 VALVES FOR WATER MAINS
7-12.3(1) Installation of Valve Marker Post Section 7-12.3(1) is deleted in its entirety and replaced with the following: (******) Where required, a valve marker post shall be furnished and installed with each valve. Valve marker posts shall be placed at the edge of the right-of-way opposite the valve and be set with 18 inches of the post exposed above grade.
7-12.3(2) Adjust Existing Valve Box to Grade Section 7-12.3(2) is a new section: (******) Valve boxes shall be adjusted to grade in the same manner as for manholes, as detailed in Section 7-05.3(1) and the City of Renton Standard Details. Valve box adjustments shall include, but not be limited to, the locations shown on the Plans. Existing roadway valve boxes shall be adjusted to conform to final finished grades. The final installation shall be made in accordance with the applicable portions of Section 7-12. In the event that the existing valve box is plugged or blocked with debris, the Contractor shall use whatever means necessary to remove such debris, leaving the valve installation in a fully operable condition. The valve box shall be set to an elevation tolerance of one-fourth inch (1/4") to one-half inch (1/2") below finished grade.
7-12.4 Measurement Section 7-12.4 is supplemented with the following: (******) Adjustment of existing valve boxes to grade shall be measured per each, if included as a separate pay item in the Contract; if not a separate pay item but required to complete the Work, then value box adjustment shall be considered incidental. Hydrant auxiliary gate valve will be included in the measurement for hydrant assembly and will not be included in this measurement item.
11/4/2020
160
7-12.5 Payment Section 7-12.5 is deleted in its entirety and replaced with the following: (******) "Furnish and Install ____-Inch Gate Valve Assembly”, per each. The unit contract price per each for "Furnish and Install ____-Inch Gate Valve Assembly" shall be full pay for the bid item as described in Section 1-09.14. "Air-Release/Air-Vacuum Valve Assembly," per each. The unit contract price per for air-release/air-vacuum valve assembly shall be for all, labor, equipment and material to complete the installation of the assembly including but not limited to, excavating, tapping the main, laying and jointing the pipe and fittings and appurtenances, backfilling, testing, flushing, and disinfection, meter box and cover, at location shown on the plans, and per the City of Renton Standard Details, latest revision. "Adjust Existing Valve Box to Grade (RC)," per each. The contract bid price for "Adjust Existing Valve Box to Grade" above shall be full compensation for all labor, material, tools and equipment necessary to satisfactorily complete the Work as defined in the Contract Documents, including all incidental Work. If not included as a separate pay item in the Contract, but required to complete other Work in the Contract, then adjustment of valve boxes shall be considered incidental to other items of Work and no further compensation shall be made.
7-14 HYDRANTS
7-14.3(1) Setting Hydrants Section 7-14.3(1) is deleted in its entirety and replaced with the following: (******) Where shown on the Plans, hydrants shall be installed in accordance with the Standard Plans and Contract specifications. A minimum 3-foot radius unobstructed working area shall be provided around all hydrants. The bottom surface of the breakaway flange shall be set 2-inches minimum and 7-inches maximum above the concrete shear block finished grade. For each hydrant requiring vertical adjustment, see Section 7-14.3(6). Fire hydrants shall be of such length as to be suitable for installation with connections to 6", 8" and 10" piping in trenches 3 - 1/2 feet deep unless otherwise specified. The hydrant shall be designed for a 4-1/2 foot burial where 12" and larger pipe is shown unless otherwise noted in the Plans. After installation hydrants shall be subjected to a hydrostatic test as specified in Section 7-09.3(23). The hydrant excavation shall be backfilled and compacted when installation and testing are complete and accepted by the Engineer. A concrete shear block as shown by the hydrant details on the Standard Plans shall be constructed for all hydrants. Construction, Materials, and finishing of the concrete shear block shall conform to
11/4/2020
161
Section 8-14, Cement Concrete Sidewalk. The shear block shall be set flush with the immediately surrounding finish grade. The Contractor shall flush, test and disinfect furnished hydrants and hydrant barrel extensions according to Section 7-14.3(6). Upon completion of the project, all fire hydrants shall be painted with two field coats of Kelly-Moore/Preservative paint No. 5780-563 DTM Acrylic Gloss Safety Yellow or approved equal. Any hydrants not in service shall be identified by covering with a burlap or plastic bag properly secured. Fire hydrant assembly shall include: main line cast-iron or ductile iron tee (MJ x FL), 6" gate valve (FL x MJ), 6" DI spool (PE x PE) up to 18 feet in length, 5-1/4" MVO fire hydrant (MJ connection), 4" x 5" Storz adapter with stainless steel cable, cast iron valve box, cover, valve operating nut extension, 2-3/4" Cor-Ten shackle rods and accessories, concrete blocks, shear block and blue pavement marker.
7-14.3(3) Resetting Existing Hydrants Section 7-14.3(3) is supplemented with the following: (******) All existing hydrants to be reset shall be rebuilt to the approval of the Engineer. All rubber gaskets shall be replaced with new gaskets of the type required for a new installation of the same type. Unless a specific bid item has been included in the Proposal/Contract Document, resetting existing hydrants shall be incidental to and included in the various bid items.
7-14.3(4) Moving Existing Hydrants Section 7-14.3(4) is supplemented with the following: (******) All existing hydrants to be moved shall be rebuilt to the approval of the Engineer. All rubber gaskets shall be replaced with new gaskets of the type required for a new installation of the same type. Unless a specific bid item has been included in the Proposal/Contract Document, resetting existing hydrants shall be incidental to and included in the various bid items. Unless a specific bid item has been included in the Proposal/Contract Document, resetting existing hydrants shall be incidental to and included in the various bid items.
7-14.3(7) Remove and Salvage Hydrant Section 7-14.3(7) is a new section: (******) Existing hydrants shall be removed where shown in the Plans. Removed hydrants shall be delivered to the City of Renton shops by the Contractor. The existing hydrant lateral tee shall be removed from the main. Unless a specific bid item has been included in the Proposal/Contract Document, resetting existing hydrants shall be incidental to and included in the various bid items.
11/4/2020
162
7-14.5 Payment Section 7-14.5 is revised with the following: (******) Payment will be made in accordance with Section 1-04.1, for each of the following bid items that are included in the proposal: “Furnish and Install Hydrant Assembly”, per each. The unit contract price per each for " Furnish and Install Hydrant Assembly”, shall be full pay for the bid item as described in Section 1-09.14. “Resetting Existing Hydrants”, per each. The unit contract price per each for “Resetting Existing Hydrant” shall be full pay for all Work to reset the existing hydrant, including rebuilding (or replacement with a new hydrant), shackling, blocking, painting, and guard posts and reconnecting to the main. The new pipe connecting the hydrant to the main shall be considered incidental and no additional payment shall be made. Guard posts, shown on the Plans shall be incidental to the contract. “Moving Existing Hydrants”, per each. The unit contract price per each for “Moving Existing Hydrant” shall be full pay for all Work to move the existing hydrant, including new tee, rebuilding (or replacement with a new hydrant), shackling, blocking, painting, and guard posts and reconnecting to the main. The new pipe connecting the hydrant to the main shall be considered incidental and no additional payment shall be made. Guard posts, shown on the Plans shall be incidental to the contract.
7-15 SERVICE CONNECTIONS
7-15.3 Construction Details Section 7-15.3 is supplemented with the following: (******) All pipe materials for new water service lines and for extension or replacement of existing water service lines shall be copper and lead free in accordance with the Federal Reduction of Lead in Drinking Water Act. Pipe materials for water service line installation for size 2-inch or less and connection to ductile iron water main shall be copper type “K” annealed tubing and seamless (ANSI H33.1). Ductile iron pipe Class 52 or stronger shall be direct-tapped with 1-inch corporation stops for 1-inch service lines. All meter setters for residential domestic use shall be 1-inch by 1-inch setters unless otherwise specified on the Contract Plans. For existing 3/4-inch meters, the Contractor shall furnish and install reducing couplings to adapt the 1-inch setter to the standard 3/4-inch domestic meter.
11/4/2020
163
Where installation of service lines is within existing paved streets, the service lines shall be installed by a trenchless percussion and impact method (hoe-hogging). If the trenchless percussion and impact method fails, regular open trench methods may be used. Where shown in the Plans, the Contractor shall:
• Furnish and install new water service lines from the new water main to the new meter setters and new meter boxes near the existing meters
• Furnish and install adaptors for the relocation of the existing water meters to the new meter setters and re-install the existing meters in the new meter setters
• Connect the new meter setters to the customers’ private service lines
• Restore disturbed areas to their approximate original condition as directed by the Engineer.
7-15.5 Payment Section 7-15.5 deleted in its entirety and replaced with the following: (******) Payment will be made in accordance with Section 1-04.1, for the following bid item when it is included in the proposal: “Furnish and Install ____ In. Water Service Connection”, per each. The unit contract price per each for " Furnish and Install ____ In. Water Service Connection”, shall be full pay for the bid item as described in Section 1-09.14.
7-17 SANITARY SEWERS
7-17.2 Materials Section 7-17.2 is deleted in its entirety and replaced with the following: (******)
Pipe Gravity sewer pipe shall be as specified herein and as shown on the Plans. The Contractor shall provide electronic copies of the pipe manufacturer’s technical literature and tables of dimensional tolerances to the Engineer. Any pipe found to have dimensional tolerances in excess of those prescribed or having defects, which prevent adequate joint seal or any other damage, shall be rejected. If requested by the Engineer, not less than three nor more than five lengths of pipe for each size, selected from stock by the Engineer, shall be tested as specified for maximum dimensional tolerance of the respective pipe. Materials shall meet the requirements of the following sections: Material for sewer pipe shall meet the requirements of Section 9-05.12 as modified in these special provisions or as specified on the project plans. (Specification to list acceptable materials and applicable specification for project). All pipe shall be clearly marked with type, class, and thickness. Lettering shall be legible and permanent under normal conditions of handling and storage.
11/4/2020
164
7-17.3 Construction Requirements
7-17.3(1) Protection of Existing Sewerage Facilities Section 7-17.3(1) is supplemented with the following: (******) When extending an existing sewer, the downstream system shall be protected from construction debris by placing a screen or trap in the first existing manhole downstream of the connection. It shall be the Contractor's responsibility to maintain this screen or trap during construction of the new sewer and then remove it once the new system is placed into service. The Contractor shall remove any construction debris that enters the existing downstream system as a result of his work at his expense. When the first manhole is set, its outlet shall be plugged until acceptance of the new construction by the Engineer.
7-17.3(2)H Television Inspection Section 7-17.3(2)H is supplemented with the following: (******)
CCTV Inspection 1. All newly-installed and newly-rehabilitated (public and private) Sanitary Sewer and Storm Drain main lines shall be inspected by means of remote CCTV. CCTV inspections and reports shall be submitted to the City of Renton inspector assigned to the project prior to receiving approval to install project curbs, gutters and/or pavement. 2. The Contractor shall perform all CCTV inspections in accordance with the National Association of Sewer Service Companies (NASSCO) Pipeline Assessment Certification Program (PACP). 3. All CCTV operators shall have current NASSCO PACP certification. 4. CCTV inspections shall be recorded in a GraniteNet compatible format database using the latest software version and submitted with electronic links between the data and the video on an External HDD, DVD or Flash Drive. 5. All CCTV inspection reports shall be within +/- two (2) feet of the measured linear footage between manholes along the existing pipeline centerline from the start of pipe to end of pipe. 6. All Owner and PACP required header information must be fully and accurately entered on all CCTV reports. Work not following these specifications will be rejected and the Contractor shall be required to re-CCTV the work. 7. The documentation of the work shall consist of PACP CCTV Reports, PACP database, logs, electronic reports, etc. noting important features encountered during the inspection. The speed of travel shall be slow enough to inspect each pipe joint, tee connection, structural deterioration, infiltration and inflow sources, and deposits, but should not, at any time, be faster than 30 feet per minute, except as noted otherwise in this document. 8. The camera must be centered in the pipe to provide accurate distance measurements to provide locations of features in the sewer and these footage measurements shall be displayed and documented on the video. All PACP Observations shall be identified by audio and on a PACP log. All video must be continuously metered from manhole to manhole. All video recording shall be continuous from structure to structure with no “pausing” of the video recording during each pipeline inspection. The pipe shall be cleaned prior to the CCTV inspection to ensure all defects, features and observations are seen and logged. 9. Just prior to beginning the CCTV inspection, while the CCTV camera is in place and recording, water (containing dye) shall be introduced into the upstream manhole of each
11/4/2020
165
pipe segment until it is observed and recorded flowing past the camera’s field of vision in its entirety. 10. The CCTV camera shall have a water-level measuring device (ball, cylinder, etc.) attached that has ¼” markings to show the depth of water in the pipe during the CCTV inspection. 11. All manholes shall be channeled and coated prior to CCTV inspection. 12. Per City of Renton specification 7-08.3(2)B, sewer and storm drain pipeline shall have no more than ½” of ponding to be considered acceptable.
7-17.3(2)I Abandon Existing Sanitary Sewer Pipes Section 7-17.3(2)I is a new section: (******) Where it is shown on the plans that existing sanitary sewer pipe(s) is to be abandoned by filling with grout, both ends of the abandoned pipe and all lateral connections to the pipe shall be plugged with 3,000 psi cement concrete and the pipe shall be filled with cement-based grout. The grout mix design and method of installation shall be approved by the Engineer prior to beginning the operation (See Section 9-03.22 for Grout Mix requirements).
7-17.5 Payment Section 7-17.5 is revised and supplemented with the following: (******) Payment will be made in accordance with Section 1-04.19, for each of the bid items that are included in the proposal. The unit contract price per linear foot for “Testing Sewer Pipe” shall be full pay for all labor, material and equipment required to conduct the leakage tests required in Section 7-17.3(2). If no unit price for “Testing Sewer Pipe” is included it shall be considered incidental to the pipe items.
7-18 SIDE SEWERS
7-18.3(2) Fittings Section 7-18.3 is deleted in its entirety and replaced with the following: (******) Fittings and connections to new and existing sewers shall be per the City of Renton’s Standard Plans.
7-18.3(3) Testing Section 7-18.3(3) is deleted in its entirety and replaced with the following: (******) All side sewers constructed in conjunction with a new sewer main shall, for purposes of testing as specified in Section 7-17, have the side sewer cleanout at the right-of-way (as shown in the respective City of Renton Standard Plans) installed prior to testing. Caps shall be installed and sufficiently restrained on the end of each side sewer and its respective surface cleanout to withstand the internal pressure created for testing in conjunction with the sewer main. Where a sewer main and its respective side sewer are constructed to replace and existing, in-operation sewer system, pressure testing will not be required.
11/4/2020
166
7-18.3(5) End Pipe Marker Section 7-18.3(5) is deleted in its entirety and replaced with the following: (******) The location of side sewers at the property line shall be indicated by the presents of a surface cleanout installed per the associated City of Renton Standard Plan.
7-19 SEWER CLEANOUTS
7-19.3 Construction Requirements Section 7-19.3 is deleted in its entirety and replaced with the following: (******) Sewer cleanouts shall be installed per the associated City of Renton Standard Plan(s).
7-19.4 Measurement Section 7-19.4 is deleted in its entirety and replaced with the following: (******) Sewer cleanouts that are installed on sewer main lines will be measured per each. Sewer cleanouts that are installed on side sewers shall be considered incidental to the side sewer pipe.
7-20 CURED IN PLACE PIPE (CIPP)
Section 7-20 is a New Section.
Description This Section specifies rehabilitation of existing wastewater or stormwater (host pipes) by the installation of felt or fiberglass resin-impregnated liner cured-in-place piping (CIPP). Service connections and manholes may be rehabilitated with products specified in other Sections. Contractor shall coordinate rehabilitation of manholes, mainlines, and lateral interfaces with product installers. Contractor shall ensure that resin systems are compatible with all rehabilitation products that they will contact. Work to remove and replace manhole cones, risers, frame and cover, and concrete collars necessary for the installation of the CIPP shall be considered incidental as part of the CIPP Work.
Licensing The Contractor or sub-contractors shall have a current City of Renton business license. The Contractor or sub-contractor installing the CIPP shall have a current license agreement with the product Manufacturer. All individuals installing the CIPP shall be certified by the product Manufacturer. Certification showing that the Installer is currently licensed by the appropriate licensor to perform CIPP installation shall be submitted in accordance with Section 1-07.6.
11/4/2020
167
Contractor and Manufacturer Qualifications Manufacturer Qualifications:
• The Manufacturer’s CIPP liner shall have successfully installed a minimum of 200,000 linear feet in accordance with these specifications.
• Manufacturers using standards other than those listed in these specifications shall demonstrate, to the satisfaction of the Owner, that their standards produce a product that is, at a minimum, equal to the quality of a product produced using these specifications. Contractor Qualifications:
• A minimum of five (5) successful projects totaling a minimum of 50,000 linear feet of installed CIPP meeting the requirements of these specifications
• The Contractor’s superintendent shall have a minimum of three (3) successfully completed projects totaling a minimum of 25,000 linear feet of installed CIPP meeting the requirements of these specifications. The superintendent shall be onsite during installation of the CIPP work for the duration of the project.
• At least one (1) person on the Contractor’s installation crew shall have a minimum of one (1) year of CIPP installation experience. This person shall be onsite at all times during the CIPP installation work.
• The Contractor’s identified Lateral Cutting Technician shall have a minimum of one (1) year of experience reinstating laterals.
Contractor Submittals All procedures or material descriptions requiring the Engineer's approval shall be submitted not less than 15 calendar days prior to mobilizing or commencing any CIPP activities at the site of the work. Submit as specified in Section 6-07.3(2). The following submittals are required: 1. CIPP Lining Plan to include the following: a. Work sequence organized by pipe section with installation schedule. b. Confirmation of liner length and diameter. c. Locations of all service connections with disposition for each. d. Anticipated cleaning and preparation requirements. e. Proposed lining material and curing method. f. Sewer Service Interruption Notification Plan. 2. Spill Prevention Plan. 3. Manufacturer’s certificate(s) indicating that the supplied lining materials meet the requirements of the specifications, ASTM standards, and a certificate of compliance from an independent third-party lab. 4. Certification stating CIPP tube has been manufactured in accordance with ASTM F1216 or F2019 and resin is suitable for its intended use. 5. Certification showing the Contractor is currently licensed by the appropriate licensor to perform CIPP installation. 6. Name of resin supplier and liner fabric supplier. 7. Test reports on testing of CIPP products illustrating they meet the relevant requirements of this specification. Manufacturer shall provide ISO 9001 certificate by a third party confirming that all the ASTM test reports are valid and up to date at the time of the bid and during construction period. 8. Manufacturer’s recommendations for factory and field (whichever applies) wet out procedures including: volume of resin per unit of liner, mixing ratios and procedures for
11/4/2020
168
resin and catalyst/hardener, shelf life of resin, pot life of resin, required wet out procedure to ensure full saturation, and other criteria deemed necessary to ensure proper wet out of the liner. 9. Manufacturer’s data sheets for factory wet out and/or Contractor’s data sheets for field wet out showing quantity of resin and catalyst used for each length of liner, at or prior to time of installation. 10. Manufacturer’s certification that all Manufacturer’s wet out recommendations have been followed on all lengths of CIPP which have factory wet out, at or prior to time of installation. 11. Manufacturer’s recommendations for storage procedures and temperature control, handling and inserting the liner, curing details, service connection methods, trimming and finishing, QA/QC procedures, and minimum equipment requirements to allow for an adequate installation. 12. Manufacturer’s recommendations and procedures for minimum and maximum pressures, temperatures, and time durations to be used. 13. Data on Contractor’s equipment to be used on site including: type and tolerance of temperature gages and thermocouples used to monitor cure temperature; type and tolerance of equipment used to generate liner inversion pressure; make, model, and technical data of all equipment used to generate heat for the curing process; make, model and technical data of backup equipment used to maintain curing temperature; rough size of vehicle(s) which carries the CIPP pipe and overall installation equipment footprint required. 14. Contractor shall calculate and submit to the Engineer for review after field verification of pipe sizes and prior to ordering any material from the manufacturer the required minimum thickness for the CIPP to be installed in each pipe reach based on the internal inspection data. 15. Manufacturer onsite Representative’s Certification that the Contractor’s installation meets all requirements of the Manufacturer and will not void the Owner’s warranty. 16. CIPP field samples from field installations. Field sampling procedure shall be in accordance with the latest version of ASTM F1216 or F2019 or ASTM F1743 and in accordance with ASTM D5813. 17. Material Safety Data Sheets for resins, hardeners, catalysts, solvents, and all other compounds or chemicals to be used on the job site. 18. Data logger output in a graphic format showing pipe section, time, pressure, and temperature during activation, heating, curing, and cool down, as applicable for CIPP technology used. 19. Informational hand out that describes the materials, processes, and odors associated with the lining process. This handout shall be provided at the request of residents. 20. Pre- and Post-Installation CCTV inspection videos. 21. Contractor shall obtain a Discharge Authorization Permit from King County’s Wastewater Treatment Division for any proposed discharges to the existing Sanitary Sewer System, including process water resulting from the curing process (if applicable). Contractor is responsible for adhering to all discharge limitations associated with the received permit. Contractor shall submit a copy of the permit to the City once obtained.
Warranty Contractor shall provide a 1-year written bonded warranty for the full value of the contract with a 3.5 percent inflation allowed per year after acceptance of the liner to cover the repairs resulting
11/4/2020
169
from liner failure within the warranty period, including new pipe, labor and incidentals as well as any fines by the local, state, and federal environmental agencies. The written bonded warranty shall be issued by a BB+ rated surety with more than 20 years of business history and with headquarters in the United States.
Product Storage and Handling Requirements Contractor shall be responsible for the delivery, storage, and handling of all materials for CIPP and end sealing material in accordance with the written requirements of the manufacturer. Contractor shall exercise adequate care during transportation, handling, and installation to ensure the CIPP material is not torn, cut, or otherwise damaged. If any part or parts of the CIPP material becomes torn, cut, or otherwise damaged before or during insertion, it shall be repaired or replaced in accordance with the manufacturer’s recommendations and approval of the Engineer before proceeding.
Materials CIPP products and materials shall be in accordance with the latest version of ASTM F1216 for Resin-Impregnated Flexible Tube (Felt Liner) or ASTM F2019 for Glass Reinforced Plastic (GRP) Thermosetting Resin Pipe (Fiberglass Liner), with Suppliers recommendations as described below.
CIPP The CIPP design shall be in accordance with the latest version of ASTM F2019, with physical properties and chemical resistance demonstrated per ASTM D5813, F2019 for Type III, Grade 2 CIPP classification, with final approval from the Engineer. The liner thickness shall be designed based on the engineering formulas listed in ASTM F1216 and F2019 for “fully deteriorated” pipes and the conditions indicated below: 1. Design Safety Factor = 2.0. 2. Ovality factor = 2 percent. 3. Constrained Soil Modulus = Per ASTM D3839, Soil Class III at 90 percent compaction. 4. Modulus of soil reaction, E’ = 700 psi. 5. Groundwater Depth = At ground surface. 6. Soil Depth = As indicated on the drawings. 7. Live load using an AASHTO HS20 vehicle loading. 8. Soil Unit Weight = 140 lbs/cf. 9. Minimum Service Life = 50 years.
Felt Cured-in-Place Resin Impregnated Material The liner shall be designed in accordance with the procedures of ASTM F1216. All material properties used in design calculations shall be long-term (time-corrected) values. The design for the CIPP shall recognize any non-uniform cross section and the liner bifurcation present at the spring line of the host pipe. Accounting for this condition by the use of an ovality reduction factor alone is unacceptable. The CIPP will be continuous in length and the wall thickness shall be uniform. No overlapping sections shall be allowed throughout the circumference or the length of the liner.
11/4/2020
170
The CIPP will be capable of conforming to offset joints, bells, and disfigured pipe sections. It shall be able to stretch to fit irregular pipe sections and negotiate bends as shown on the drawings. The CIPP service life shall be a minimum of 50 years. The Contractor shall be responsible for control of all material and process variables to provide a finish CIPP possessing the minimum properties specified in ASTM F1216. The CIPP shall be marked at a distance of regular intervals along its entire length, not to exceed five (5) feet. Markings shall include Manufacturer’s name or identifying symbol. The CIPP liner shall be manufactured with materials from a consistent supplier. All materials of similar type shall be from a single source for the entire project. The CIPP shall be fabricated to a size that, when installed, will tightly fit the internal circumference and length of the original pipe. Allowance shall be made for circumferential and longitudinal stretching during the installation process. Diametric shrinking during the curing process shall meet the requirements of ASTM D5813, Section 6.3.1 or better. For liners inserted by the inversion method, the CIPP shall be coated on one side with a translucent waterproof coating of polyvinyl chloride (PVC) or polyurethane. For liners inserted by the pull/winch method, the CIPP shall be coated on one side with a translucent waterproof coating of PVC, polyurethane, polyethylene, or polypropylene.
Fiberglass Cured-in-Place Resin Impregnated Material Glass Reinforced Plastic Flexible Tube (fiberglass liner), consists of at least two separate tubes of corrosion resistant glass fiber in accordance with ASTM D5780 and F2019. Liner shall include an inner foil (or calibration hose) to contain resin which shall be removed after completion of installation (unless intended to be a permanent part of the CIPP system and fabricated as an integral part of the tube by bonding or fusing). In addition, an external permanent foil shall be provided that is resistant and impermeable to moisture and all wave lengths of light as part of the UV curing process. The liner shall be continuous in length and the wall thickness shall be uniform. No overlapping sections shall be allowed throughout the circumference or length of the liner. The liner shall be capable of conforming to offset joints, bells, and disfigured pipe sections. It shall be able to stretch to fit irregular pipe sections and negotiate bends as shown on the drawings. The liner shall be marked at regular intervals along its entire length, not to exceed five (5) feet. Markings shall include Supplier's name or identifying symbol. The liner shall be manufactured with materials from a consistent supplier. All materials of a similar type shall be from a single source for the entire project. The liner shall be fabricated to a size that, when installed, will tightly fit to the internal, circumference and length of the host pipe. Allowance shall be made for circumferential stretching during the installation process.
11/4/2020
171
The liner shall not be of a dark or non-reflective material which would inhibit proper closed-circuit television inspection. The liner shall meet the chemical resistance criteria specified in ASTM D5813, D578 and ASTM F2019 (Appendix X2) for Type III, Grade 2. The liner shall be handled with care during delivery to protect from UV exposure prior to installation.
Resin & Cured CIPP Properties The resin used shall be compatible with the CIPP system used, and designed for use depending on the application. The resin shall be a general purpose, unsaturated polyester, catalyst system compatible with the CIPP system that provides the cured physical strengths and properties specified herein. Resins shall be tinted for adequate visibility suitable for internal inspection and provide positive indication of adequate liner wet-out. The resin system for the cure-in-place pipe process, using steam or water curing, shall be manufactured in accordance with ASTM F1216. Resin shall have the following characteristics: 1. The resin shall be thermosetting polyester. 2. When cured, the resin shall have a flexural strength of not less than 4,500 psi (ASTM D790). 3. When cured, the resin shall have a flexural modulus (short term) of not less than 250,000 psi (ASTM D790). 4. When cured, the resin shall have a tensile strength of not less than 3,000 psi (ASTM 0368). 5. 50-year flexural creep modulus: 150,000 psi per ASTM D 2990. 6. Tensile strength: 9,000 psi per ASTM D638 for sectional liner. For materials that do not allow sufficiently accurate hoop/weft testing in accordance with ASTM D638, initial tensile strength may also be substantiated by short-term flat plate specimen testing. 7. The resin shall be able to cure in the presence of water. 8. The resin initiation temperature for curing should be as recommended by manufacturer. 9. The resin color shall be in contrast to the color of the liner fabric to assist in visual inspection. 10. The CIPP resin shall be compatible with the liner fabric, liner coating, other rehabilitation systems and the host pipe materials that it may contact. 11. The resin shall form no excessive bubbling or wrinkling during lining. 12. The resin shall be manufactured with materials from a consistent supplier. All materials of similar type shall be from a single source for the entire project. 13. The resin shall have no fillers added for the sole purpose of increasing the resin volume. Resin shall include no more than five (5) percent filler by volume for the purpose of modifying resin viscosity, heat transfer characteristics, or flexural modulus of a cured liner. The resin system for the cure-in-place pipe process using ultraviolet curing shall be manufactured in accordance with ASTM F2019. Resin shall have the following characteristics: 1. The resin shall be chemically resistant polyester thermoset and catalyst system compatible with UV curing installation process. A photo-inhibitor system shall be added to the resin prior to impregnation. The initiator system of the resin shall be optimized to the output of the ultraviolet curing lights. 2. When cured, the resin shall have a flexural strength of not less than 6,500 psi (ASTM D790). 3. When cured, the resin shall have a flexural modulus (short term) of not less than 725,000 psi (ASTM D790).
11/4/2020
172
4. When cured, the resin shall have a tensile strength of not less than 9,000 psi (ASTM D3039, D368). 5. 50-year flexural creep modulus: 150,000 psi per ASTM D 2990. 6. Tensile strength: 9,000 psi per ASTM D 638 for sectional liner. For materials that do not allow sufficiently accurate hoop/weft testing in accordance with ASTM D638, initial tensile strength may also be substantiated by short-term flat plate specimen testing. 7. The resin color shall be in contrast to the color of the liner fabric to assist in visual inspection. 8. The CIPP resin shall be compatible with the liner fabric, foils and host pipe materials. 9. The resin shall form no excessive bubbling or wrinkling during lining. 10. The resin shall be manufactured with materials from a consistent supplier. All materials of similar type shall be from a single source for the entire project. 11. The resin shall have no fillers added for the sole purpose of increasing the resin volume Resin shall include no more than five (5) percent filler by volume for the purpose of modifying viscosity, heat transfer characteristics, or flexural modulus of a cured liner.
Dimensions of CIPP Contractor shall measure the actual inside diameter of the host pipe, at different locations along its length, to verify the appropriate size of CIPP liner to use. The existing host pipe may be larger than their nominal size due to corrosion of the concrete pipe. It is the Contractor’s responsibility to measure the actual inside diameter at different locations of the host pipe to verify the appropriate size of the CIPP liner to use.
The Contractor shall make allowances in determining the felt tube length and circumference for stretch during installation and shrinkage during curing and aging. The minimum length shall be that which continuously spans the distance from the center of the inlet manhole to the center of the outlet manhole, based on the specifics of the repair and pipe diameter. The Contractor shall verify the lengths in the field before the liner tube is cut and impregnated. Individual installation runs may include one or more manhole-to-manhole sections as authorized by the Engineer.
Wall Thickness The wall thickness of the tube shall be ordered to the next standard incremental thickness above the minimum calculated design thickness. Unless otherwise specified to provide for excess resin migration, the gap thickness of the wetting out equipment shall be sized to allow an excess of 5 to 10 percent resin to pass during impregnation.
The nominal CIPP thickness shall be at least the calculated design thickness, per ASTM F1216 (felt liner) or F2019, (fiberglass liner) except where fabric layers overlap, in which case it may be in excess of this value.
CIPP Liner Labeling Manufacturer label on each liner tube shall be in 1-inch letters, minimum, and include the following information: 1. Date of manufacture of the liner. 2. Name or trademark of the manufacturer. 3. Liner diameter. 4. Liner thickness. 5. Liner length.
11/4/2020
173
Chemical Resistance The cured pipe shall be resistant to a variety of chemical effluents as described in ASTM D543. Testing for chemical resistance may be performed on the sample of the finished product prior to this contract, provided a certified affidavit, signed by an officer of the company, is submitted stating the resin the tests apply to and the resin submitted for this project are the same. Testing data up to 2-years prior to bid date will be accepted. Finished and cured CIPP liner properties shall perform as specified.
Chemical resistance test results shall be provided in accordance with Test Method D543 on samples of the cured liner material that are the same as that proposed for installation. Exposure should be for a minimum of one month at 73.4 degrees F. During this period, the CIPP test specimens should lose no more than 20 percent of their initial flexural strength and flexural modulus when tested in accordance with Section 8 of ASTM F1216, when subjected to the following solutions:
Chemical Solution Concentration, percent Tap Water (pH 6-9) 100 Nitric Acid 5 Phosphoric Acid 10 Sulfuric Acid 10 Gasoline 100 Vegetable Oil 100 Detergent 0.1 Soap 0.1 The Contractor shall be responsible for all costs associated with the chemical resistance tests. Proof of meeting the requirements for the design specified shall be provided to the Engineer for approval at least seven (7) days prior to ordering any material.
CIPP End and Connection Seal Contractor shall seal the end points of the liner so that no leakage of fluids may infiltrate between the liner and the existing pipe. Contractor shall apply epoxy sealant (after CIPP acceptance) to completely seal area around opening of the liner and the connection. Hydraulic cements and quick-set cement products are not acceptable. The installation of the connection seal shall not, in any way, damage or adversely affect the CIPP. If damage to the CIPP liner does occur, the Contractor shall repair or replace the area at no additional cost to the Owner. Contractor shall trim loose or hanging/intruding pipe connection seals so that they are flush with the internal pipe wall. The Contractor shall not fold the hanging/intruding material.
Allowable CIPP and End Connection Seal Manufacturers The following manufacturers of CIPP are approved: 1. Inliner Technologies. 2. Insituform Technologies, Inc. 3. National Liner. 4. Premier-Pipe. 5. Spiniello Companies. 6. SAK, LLC.
11/4/2020
174
7. Saertex. 8. Reline America Inc. 9. Or approved equal. The following manufacturers of CIPP end and connection sealing are approved: 1. Neopoxy. 2. Or approved equal.
Construction Requirements
Pre-Installation CCTV Inspection Contractor shall conduct CCTV video inspection of the host pipe prior to commencing construction. All CCTV inspections shall be performed in accordance with Section 7-17.3(2)H. Contractor will review the CCTV inspection and indicate where the following deficiencies are located: 1. Any obstructions within the host pipe that may affect the sliplining operation. 2. Joint separation. 3. Offset joint. 4. Cracked or damaged host pipe. 5. Out of round host pipe. 6. Infiltration point. The findings of the pre installation inspection shall be summarized in an inspection report and submitted along with the video files and corresponding database to the Engineer for review.
Flow Management It shall be the Contractor's responsibility to maintain operation of the existing sewer and/or storm systems throughout the duration of the project. The Contractor shall divert all flows around each segment of the pipe designated for rehabilitation. This diversion shall consist of redirecting flow from an upstream manhole and discharging it to a manhole downstream of the rehabilitation operation. This can be accomplished via a combination of pumping and/or gravity flow. After the work is completed, flow shall be returned to the rehabilitated sewer and/or storm system. The area affected by the bypass operation shall be fully restored to pre-bypassing conditions. Bypass pumping system of stormwater shall be capable of bypassing at least the 2-year peak flow during construction. Bypass pumping shall be scheduled for continuous operation. Back-up equipment shall be on-site and available for periods of maintenance, refueling or failure of the primary bypass pump(s) or diversion system. Bypass pumping shall be done in such a manner as not to damage private or public property, or create a nuisance or public menace. The bypass-pumping pipe shall not block any driveways or intersections unless approved by the Engineer. The sewage shall be pumped through a watertight hose or pipe that is adequately protected from traffic. The discharge of raw sewage to private property, city streets, sidewalks, storm sewer, or any location other than an approved sanitary sewer is prohibited. The Contractor shall be liable for all cleanup, damages, and resultant fines should the Contractor's operation cause any backups or overflows.
11/4/2020
175
The Contractor's bypass operation shall be sized to handle, at a minimum, the full pipe capacity in each subject line removed from service. If flow conditions are greater than full pipe, the Contractor may elect to wait for flow conditions to subside prior to removing the subject line from service. Working days will not be charged for the period of time during which the flow is greater than full pipe. No additional payment will be made for periods of high flows during which the Contractor elects to wait for lower flows. Once the Contractor removes a section of line from service he/she is responsible to bypass any and all flow in the system during construction, even in the event the system surcharges and exceeds the full pipe capacity, until the line is returned to service. All bypassing systems shall be approved by the Engineer. The Contractor shall submit a plan for bypassing the existing system to the Engineer for review. The Contractor's plan for bypass pumping shall be satisfactory to the Engineer before the Contractor will be allowed to commence bypass pumping. The sewage and/or storm bypass pumping plan shall include an emergency response plan detailing procedures to be taken in the event of a failure of the bypass pumping. The review of the bypassing system and equipment by the Engineer shall in no way relieve the Contractor of their responsibility and public liability. The Contractor shall coordinate activities with impacted property owners. Property Owners shall be notified at least 24 hours in advance of any disruption to their sewer service. All construction-related service disruptions shall be approved by the Engineer prior to the disruption taking place. When situations exist where impacted properties cannot be disconnected, plugged, or subjected to any other service interruption, i.e., hospitals, care facilities, restaurants, etc., bypass pumping of the side sewer to the downstream sanitary sewer system shall be required prior to insertion of the liner system. The Contractor shall verify, with the approval of the Engineer, whether a property is able to be interrupted prior to lining operations. If the subject property’s side sewer requires bypass pumping, the costs for the bypass pumping shall be covered by Force Account.
Host Pipe Access Contractor shall install access structures necessary for installation of CIPP liner. Access structures to the host pipe for installation of the CIPP liner shall be excavated as required by the Contractor. Access structures shall be located in areas that minimize excavation requirements. Provide excavation and backfill, pipe work, reconnection, and access structures including manhole cones, risers, frame and cover, and concrete collars as necessary. The Contractor shall plug the downstream manhole to prevent excavation material from entering the sewer and/or storm system during the installation of all access structures. Prior to entering any permit-required confined space, the Contractor shall evaluate the atmosphere to determine the presence of toxic, flammable vapors or lack of oxygen in accordance with local, state, and federal safety regulations.
Host Pipe Cleaning, Preparation, and Inspection Prior to CIPP tube installation, the Contractor shall clean the host pipe. The Contractor shall clear the existing host pipe of obstructions such as solids, collapsed pipe, roots, rocks or other intrusions that will prevent or hinder CIPP liner installation. Minimize infiltration into the existing pipe so as not to interfere with the proper installation and cure of the CIPP liner.
11/4/2020
176
The Contractor shall perform pre-lining inspection after cleaning and preparation to confirm that the host pipe is ready for lining. The pre-lining inspection video shall be submitted to the Engineer for review at least 24 hours prior to the scheduled installation of the liner. Installation of the liner shall not proceed prior to receiving approval by the Engineer. The Engineer will confirm the following: 1. Necessary cleaning and pipe preparation work, including any internal and external repairs/modifications have been completed. 2. That the condition of the host pipe is consistent with the design conditions and specifications. Prior to commencing lining, the Contractor shall notify the Engineer of any condition that is contrary to the design conditions or assumptions made that may affect either long term or short term performance or the liner. 3. The location, condition, and operational status of all lateral tap connections. At each location within the Project, prior to diversion of flows the Contractor shall initiate odor control measures. The Contractor shall perform post-lining CCTV inspection following installation of the liner. The Contractor shall confirm the adequacy of all lateral tap connection reinstatements and the fit and the finish of the CIPP liner prior to submitting the post-installation inspection video files to the Engineer. The Contractor shall submit CCTV post-installation inspection reports and video files along with the corresponding data base to Engineer within one (1) week of the inspection.
Point Repairs The Contractor shall advise the Engineer of any point repairs that can only be performed by excavating the defect. The Contractor shall repair all defects in the host pipe including but not limited to open joints, fractures, cracks, protruding taps and holes in the pipe that may adversely affect the successful installation of the liner. Those repairs shall include, but not limited to, the following: 1. Grouting all defects as recommended by liner manufacturer or installer. 2. Grouting all locations with excessive infiltration as outlined below: a. The determination of an excessive leak shall be made by the Owner’s representative and shall be based on PACP leak designations: i. Leaks that would be categorized as a Runner(IR) – Severity 4 or Gusher (IG) – Severity 5 shall be considered as excessive. Measurement and Payment for Excessive Leak Repairs shall be as designated in Section 7-20.6 and 7-20.7. ii. Leaks categorized as Weeper(IW) – Severity 2 or Dripper(ID) – Severity 3 shall be considered incidental to the unit price for CIPP rehabilitation. Measurement and Payment for Excessive Leak Repairs shall be as designated in Section 7-20.6 and 7-20.7. 3. Make point repairs of any host pipe defect that be accomplished using conventional sewer cleaning equipment or by remotely performed repair methods acceptable to the Engineer such as grout packers, link seal, or spot liner. Remove protruding laterals, rolled gaskets, roots, mineral deposits, and other objects protruding into the host pipe utilizing a remote-controlled cutter.
11/4/2020
177
Trimming Intruding Laterals Contractor shall trim intruding laterals so that the service connection is flush with the internal pipe wall. All lateral trimming shall be documented by pre and post trimming photos. The Contractor shall ensure that the existing pipe is not damaged during cutting operations.
Protection of Existing Manholes The Contractor shall protect all manholes from any damage that may result from the lining operation.
Spill Prevention and Control Contractor shall keep a stockpile of spill cleanup materials, such as rags or absorbents, readily accessible on-site. Contractor shall immediately contain and prevent leaks and spills from entering storm drainage systems, and properly clean up and dispose of all waste and cleanup materials. If the waste is hazardous, the Contractor shall dispose of hazardous waste only at authorized and permitted disposal facilities. Only licensed hazardous waste haulers shall transport the hazardous waste to an off-site location, unless the quantities to be transported are below those applicable threshold limits for transportation by the Contractor as specified under State and Federal regulations. Contractor shall immediately report any hazardous materials spill to the Owner and Engineer.
Installation
Felt Liner CIPP Tube Installation Lining installation shall be in accordance with the requirements of the product Manufacturer and as directed by their Technical Representative. This includes the correction of defective work. Contractor shall designate the location where the CIPP tube will be impregnated with resin (“wet-out”). These locations shall be subject to approval by the Engineer. The Contractor shall allow the Engineer to inspect the materials and “wet-out” procedure. If the “wet-out” location is not at the project site, the impregnated CIPP tube shall be transported to site under controlled environmental conditions as specified by the Manufacturer of the product. Transport vehicles shall include a tamper resistant, sealed temperature recording device which records the temperature of the liner at all times after leaving the wet-out site. Contractor shall decide when to transport the resin impregnated CIPP tube and when to commence installation depending on prevailing weather conditions, so as to not jeopardize the installation or be detrimental to the long-term performance of the CIPP. The liner shall be installed by the inversion tube method where possible. The resin-impregnated tube shall be lowered into the insertion pit through an inversion tube and reducer if needed. The liner shall be installed at a rate less than 10 feet per minute at all times. The CIPP liner shall be installed through existing manholes. Liner shall not be installed through intermediate manholes unless approved in advance by the Engineer. All requests to line through intermediate manholes shall be submitted in writing to the Engineer. There shall be no separate payment for additional or enhanced access to facilitate the Contractor’s CIPP liner installation process.
11/4/2020
178
For CIPP liner thicknesses greater than 0.75 inch, or where the existing pipe, soil, and groundwater is likely to provide a significant heat sink affecting the temperature gradient across the CIPP liner material, the temperature of the exotherm shall be monitored by remote temperature sensors placed at the interface of the existing pipe and the CIPP. A minimum of two temperature sensors shall be installed, one at either end of the length being lined. The curing process shall not be terminated until the temperature sensor readings indicated that a satisfactory cure has been completed. Any extended cure times shall not adversely affect the properties of the CIPP lining material. The curing process shall follow a step cure using steam, where possible, as recommended by the manufacturer and approved by the Engineer. The curing process shall be held at the top step for an adequate length of time to ensure that the design physical properties of the liner are attained. For the water curing method, circulation water shall cool down to at least 100 degrees F for 1 hour before releasing the hydrostatic head. The rate of temperature rise and fall during heating and cooling shall not exceed 2 degrees F per minute. The circulation water shall be filtered through a carbon filter treatment system, approved by the Engineer, prior to release into the sanitary sewer system. Evacuate water from the pipe at a controlled rate to prevent negative pressure in the pipe. The Contractor shall provide a sampling plan to the Engineer that demonstrates pollutants are not being discharged into the sanitary sewer system. After liner has cooled down, perform a preliminary television inspection of the newly installed liner. Verify the liner is continuous over the entire length. Verify the liner is free from visual defects such as foreign inclusions, dry spots, lifts, pinholes, seam separation, delamination, and wrinkling beyond the specification allowances. Liner shall be impervious and free of any leakage. Wrinkles in the finished CIPP, that create a void between the wrinkle and the pipe which reduce the structural integrity of the CIPP, and which adversely decreases the hydraulic capacity of the pipe, or cause a backwater of one (1) inch, are unacceptable and shall be removed and repaired at no additional cost to the Owner. After the curing is complete and verified, all existing active service connections, as determined by the Engineer, shall be reinstated. Reinstate all service laterals using only remote internal methods. Where the CIPP liner does not create dimples at the service connections or in other ways indicate the locations, the exact location shall be determined from the internal inspection data. It shall be the Contractor’s responsibility to accurately locate and reinstate all service connections after the CIPP installation and curing has been completed. All service connections shall be reinstated to a minimum of 95 percent of the original opening, matching the invert of the lateral.
Fiberglass Liner CIPP Tube Installation Liner installation shall be in accordance with the requirements of the product Manufacturer and as directed by their Technical Representative. This includes the correction of defective work. Resin Impregnation: The wet out procedure for flexible fiberglass tube liner impregnation shall conform to the following requirements: 1. Furnish glass reinforced plastic tube liner (fiberglass liner) per this specification. 2. Impregnate the flexible fiberglass tube liner with resin under controlled conditions at the manufacturer's plant. 3. Use a volume of resin sufficient to fill all voids in the liner material at nominal thickness and diameter. Volume shall be adjusted by adding 5 to 10 percent excess resin for the
11/4/2020
179
change in resin volume due to polymerization and to allow for any migration of resin into the cracks and joints of the host pipe. Keep logs of resin volume actually used in the wet out process and submit to Engineer prior to installation. 4. The impregnated liner shall be stored, transported, and installed in accordance with the manufacturer’s recommendations and in such a manner that it will not be damaged, exposed to direct sunlight, exposed to any curing environment, or result in a public safety hazard. All materials may be subject to inspection and review by the Engineer prior to installation. Liner installation shaft conform to the following requirements: 1. Sliding Foil and Winch Cable — upon verification of removal of debris and protrusions, pull in sliding foil as recommended by the manufacturer. 2. Pulling Head or Pulling Manifold and Inverted Roller — Connect liner to the winch cable forming a pulling head or using a pulling manifold. Care shall be taken in mounting a pulling manifold to provide an airtight fit. The rate of the pulling head or manifold shall not exceed the maximum rate recommended by the Manufacturer and in accordance with ASTM F2019. 3. Pull resin impregnated fiberglass liner into position using a power winch. The pulling speed shall not exceed the maximum rate recommended by the Manufacturer. If product is sensitive to elongation, measure overall elongation of the fiberglass liner after the pull-in completion. The acceptable longitudinal elongation shall be less than two (2) percent of the overall length specified by the manufacturer. 4. The fiberglass liner shall be inflated with air until it is fitting tight against the wall of the existing host pipe. The air pressure shall be adjusted to hold the impregnated fiberglass liner in place during the curing process. Ultraviolet Light Curing: 1. Curing process shall conform with ASTM F2019. 2. Assemble multi-lamp ultraviolet light curing assembly (UV curing assembly) according to Manufacturer’s recommendations for the pipe and liner diameter. Ultraviolet (UV) curing lights shall be tuned or optimized to the photo initiator system of the resin. Provide quantity and strength of UV lamps per manufacturer's recommendation. UV lamps shall not exceed 80 percent of logged hours of usage of the manufacturer’s stated usage rate. UV curing assembly shall have minimum of one CCTV camera and sensors to record temperature and pressure during curing process. 3. While maintaining sufficient air pressure to inflate the impregnated fiberglass liner, insert multi-lamp ultraviolet light curing assembly (UV curing assembly) in order with UV curing bulbs OFF to draw the curing mechanism through the impregnated liner and perform a pre-curing inspection. Upon confirmation that the liner is ready for curing, turn on UV curing bulbs and conduct curing process. Unless approved by Engineer, do not pull UV light train in a downstream direction during the curing process. 4. UV curing assembly shall travel through the impregnated fiberglass liner at a pre-determined speed to allow polymerization of the resin as recommended by the manufacturer. 5. The Contractor shall follow the Supplier’s cool-down instructions prior to relieving the air pressure of the liner.
11/4/2020
180
6. The Contractor shall document a UV curing report and submit a file copy to the Engineer for each pipe. This sheet shall contain, but not be limited to, the following: a. Date of Installation. b. Site number(s) and address. c. The curing method used (i.e. UV). d. Time and rate of travel for UV curing process. e. Pressure and temperature readings. f. Amount of lamps in operation on UV curing assembly. g. Time of installation from start to finish.
Testing
Post Installation CCTV Inspections Contractor will review the CCTV inspection video tapes and indicate where the following deficiencies are located: 1. Cracked or damaged liner pipe. 2. Out of round liner pipe. 3. Debris in liner pipe. The findings of the post installation inspections shall be summarized in inspection reports and submitted to the Engineer for review. Final acceptance of the installation will not take place until any deficiencies identified in the inspections are addressed.
Material Testing Contractor shall prepare a sample of the installed CIPP liner for subsequent testing of its physical properties. Sampling shall be performed for each separate installation of CIPP or one (1) test per batch-order of sectional liner. The Owner reserves the right to take five (5) random core samples of the installed CIPP liner at no additional cost in accordance with the procedures in ASTM D5813, as is applicable. The method of repair will be as recommended by the Contractor. The minimum wall thickness shall be determined at a minimum of three locations on a cut section of the CIPP lining using a method of measurement accurate to the nearest 0.005 inch or one (1) test per batch order of sectional liner not taken from actual live installation. The sample shall be prepared using the flat plate sampling method in accordance with the procedures in ASTM F1216. The flat plate sample shall be large enough to provide five sample specimens each for short-term flexural (bending) properties, as per ASTM D790. The sample will be clamped in a mold and placed in the downtube during the curing of the CIPP tube. The sample shall be removed after all the water is removed from the cured pipe tube. The samples shall be identified by Date, Project Name, Size, Thickness, Location, Resin, and Catalyst. The cured sample shall be tested by an independent testing laboratory as recommended by the CIPP liner manufacturer and approved by the Engineer for the short-term flexural (bending) properties and tensile properties, per ASTM D790 and ASTM D638, respectively. The sample shall be double bagged and sealed. The Contractor shall provide liner test results for long-term properties in accordance with ASTM D 2990. The Contractor shall be responsible for any deviation from the specified physical properties and those evaluated through testing. Failure to meet the specified physical properties
11/4/2020
181
shall result in the CIPP liner being considered defective Work and shall be rejected. The Contractor shall be responsible for all costs associated with the testing of the liner physical properties. For UV-Cured Systems — Contractor shall provide an additional restrained field sample to allow circumferential (hoop) directions of the fiberglass reinforcement, at least 2-inches wide (axial direction of the liner, along the length) to test a representative amount of fibers if glass roving mats are used. The samples are to be tested in a curved beam configuration where the minimum beam width is 2-inches, in accordance with ASTM F2019.
Cleanup Following inspection, the Contractor shall clean up the entire Project area. All excess material and debris, not incorporated into the permanent installation, shall be disposed off site by the Contractor at a site approved by the Engineer.
Measurement Measurement for “X-Inch CIPP Pipe” will be linear feet installed. Linear feet installed shall be measured along the invert. The number of linear feet will be measured from the center of manhole to center of manhole. Measurement for “Lateral Reinstatement” will be per each. Measurement for “Excessive Leak Repair” will be per each.
Payment Payment Schedule for “X-Inch CIPP Pipe”, “Lateral Reinstatement”, and “Excessive Leak Repair” is shown in Section 1-09.14.
7-21
8-02 ROADSIDE RESTORATION
8-02.3(4)A Topsoil Type A Section 8-02.3(4)A is supplemented with the following: (******) The contractor shall provide a material submittal for topsoil prior to use.
8-02.3(16)A Lawn Installation Section 8-02.3(16)A has been supplemented with the following: (******)
8-02.3(16)A1 Submittals
8-02.3(16)A1a Certification of Material 1. Include seed mix percentages, purity, germination rates, weed experience, and date tested for the preceding. Include complete data on source, size and quality. 2. Supply on-site 12” x 12” sample of each sod specified for inspection and approval in advance by the City.
11/4/2020
182
3. Supply Grower’s written recommendations for fertilizer type, rate of application, and frequency. 4. All certificates required by law shall accompany shipments. 5. Upon completion of the installation and prior to final inspection, deliver all certificates to the Engineer.
8-02.3(16)A1b Manufacturer’s Certificates of Conformance 1. Supply for Certificates of Conformance for fertilizer being used for the project.
8-02.3(16)A1c Schedule for Installation 1. The Contractor shall coordinate all work with the City and submit a watering plan for the Establishment Period.
8-02.3(16)A2 Product Handling Deliver all items to the site in their original containers, with all labels intact and legible, at the time of the City’s inspection. Coordinate delivery and installation of sod to ensure sod is installed immediately upon delivery. Use all means necessary to protect new lawn areas before, during, and after installation and to protect the installed work and materials of all other trades. In the event of damage or rejection, immediately make all repairs and replacements necessary for the approval of the Inspector and at no additional cost to the City.
8-02.3(16)A3 Site Information If sod is stored onsite, preserve and protect all sod on site prior to and during installation. Protect from wind, drought, unusual weather and vandalism. Store all sod on site within limits of work. Protect adjacent property, public walks, curbs and pavement from damage. Do not block public access routes with plant material.
8-02.3(16)A4 Sod The Contractor shall provide sod to all new lawn areas and to those lawn areas requiring restoration from the Contractor’s operations. Sod shall conform to section 9-14.6(8) as shown in the Special Provisions.
8-02.3(16)A4a Other Materials All other materials not specifically described but required for a complete and proper planting installation, shall be selected by the Contractor subject to the approval of the Engineer.
8-02.3(16)A5 Execution Prior to all work of this section, carefully inspect the installed work of all other trades and verify that all such work is complete to the point where this installation may properly commence. Verify that lawn installation may be completed in accordance with the original design and the referenced standards. In the event of discrepancy, immediately notify the Engineer for specific instructions.
11/4/2020
183
8-02.3(16)A5a Installation Preparation 1. Prepare subgrade in all lawn areas by scarifying to a 8” minimum depth and removing rocks and debris over 1” in diameter. Subgrade soils should be free-draining and without any impervious soils or other materials harmful to plant growth. Notify the Inspector of any subgrade conditions deleterious to plant growth. 2. Spread topsoil to a minimum depth of 6” after settlement in all lawn areas. 3. Thoroughly rototill topsoil to a minimum depth of 6 inches. 4. Fine grade per Contract Specifications in turf areas as indicated on drawings. Rake entire surface to conform to site grading. Grade edges to 1” below adjacent paved surfaces to provide a smooth transition. Roll as necessary to firm grade to satisfaction of the Inspector. 5. Apply fertilizer to the prepared lawn areas at rates recommended by sod grower and lightly rake to incorporate into the soil.
8-02.3(16)A5b Sod Installation 1. Moisten sod bed and roll lightly for compaction. 2. Lay sod strips per supplier’s instructions. Tightly butt joints, trim edges to conform to smooth curves and straight lines of pavement. Sod is to be flush with paved surfaces after settlement. Avoid gaps and overlaps and stagger sod joints in a brick-like fashion. 3. Remove any bumps, undulations, or low-high spots with a light rolling. 4. Water daily for a minimum of two weeks to prevent dehydration. 5. Protect all turf areas by erecting temporary fences, barriers, signs, etc. as necessary to prevent trampling. 6. Do not work in, over, or adjacent to planting areas without proper protection and safeguards.
8-02.3(16)B Lawn Establishment Section 8-02.3(16)B has been deleted and replaced with the following: (******)
8-02.3(16)B Lawn Establishment and Final Acceptance The Contractor shall maintain all new lawn areas in this project; shall be responsible for the survival of turf in acceptable condition and shall maintain all new lawn areas in a neat and orderly fashion until Final Acceptance of the project by the City. The period for Final Acceptance shall be no sooner than the second mowing. The Contractor will be held responsible for all damage or loss caused by his inattention or carelessness. The Contractor shall repair damage caused by traffic, vandalism, weather or other outside causes.
8-02.3(16)B1 Establishment Period The Establishment Period will commence on the date of Preliminary Acceptance and will extend to Substantial Completion or Final Acceptance by the City of landscape work, whichever is later. Maintenance during this period will include: 1. Watering: Water areas of new turf so they receive adequate water for survival of the plant in a healthy position. 2. Lawns shall be fertilized every six weeks from March through September per Grower’s written recommendations. Lawns shall be maintained weed-free. 3. Lawns are to be mowed weekly or as needed to maintain a neat appearance. All grass clippings shall be removed from the site. Maximum height of lawn shall not exceed three inches.
11/4/2020
184
4. Protect all lawn areas against damage, including erosion and trespassing, by providing and maintaining proper safeguards. 5. Debris Control: Debris control shall be accomplished in all landscaped lawn areas on a regular basis, at least weekly or more often where necessary. This will include leaf fall control in Fall period. Policing for paper and litter in all areas shall be conducted at least weekly. During the Fall period leaves, windblown into gutters and catch basins, are considered as litter and shall be removed as debris.
8-02.3(16)B2 Guarantee All new turf areas shall be guaranteed by the Contractor to be in a healthy condition for a period of one year from the date of Final Acceptance.
8-02.3(16)B3 Final Acceptance Acceptance of lawn planting as specified shall be based on a uniform stand of grass and a uniform grade at the time of final inspection. Final inspection of the work of the Section will be made at the time of the Final Inspection of the entire project or earlier, if approved by the Engineer. A final punch list will be issued. Final Acceptance of the new turf areas which are the responsibility of the Contractor will be contingent upon Final Acceptance of the entire project or at the determination of the City if earlier than Final Acceptance of the entire project.
8-09 RAISED PAVEMENT MARKERS
8-09.5 Payment Section 8-09.5 has been revised with the following: (******) Payment will be made for each of the following bid items that are included in the proposal: “Raised Pavement Marker Type 1”, per each. “Raised Pavement Marker Type 2”, per each. “Raised Pavement Marker Type 3-______ In.”, per each. “Recessed Pavement Marker”, per each. The unit contract price per each for “Raised Pavement Marker Type 1”, “Raised Pavement Marker Type 2”, and “Raised Pavement Marker Type 3-______ In.” and “Recessed Pavement Marker” shall be full pay for all labor, materials, and equipment necessary for furnishing and installing the markers in accordance with these Specifications, including all cost involved with traffic control unless traffic control is listed in the Contract as a separate pay item.
11/4/2020
185
8-13 MONUMENT CASES
8-13.1 Description Section 8-13.1 is revised and supplemented with the following: (******) This Work shall consist of furnishing and placing monument cases and covers, in accordance with the Standard Plans and these Specifications, in conformity with the lines and locations shown in the Plans or as staked by the Engineer or by the Contractor supplied Surveyor.
8-13.3 Construction Requirements Paragraphs 2 and 3 of Section 8-13.3 is revised and supplemented with the following: (******) The monument will be furnished and set by the Contractor supplied Surveyor. When existing monuments will be impacted by a project, the Contractor shall be responsible for assuring that a registered surveyor references the existing monuments prior to construction. After construction is complete, the monuments shall be re-established by the Surveyor in accordance with RCW58.09.130.
8-13.4 Measurement Section 8-13.4 is supplemented with the following: (******) All costs for surveying and resetting existing monuments impacted by construction shall be considered incidental to the Contract unless specifically called out to be paid as a bid item.
8-13.5 Payment Section 8-13.5 is supplemented with the following: (******) "Reset Existing Monument" per each. Resetting an existing monument impacted by construction shall be incidental unless included as a pay item in the Schedule of Prices.
8-14 CEMENT CONCRETE SIDEWALKS
8-14.3(4) Curing Section 8-14.3(4) is replaced with: (******) The curing materials and procedures outlined in Section 5-05.3(13) of the Standard Specifications shall prevail, except that white pigmented curing compound shall not be used on sidewalks. The curing agent shall be applied immediately after brushing and be maintained for a period of 5 days. The Contractor shall have readily available sufficient protective covering, such as waterproof paper or plastic membrane, to cover the pour of an entire day in the event of rain or other unsuitable weather. During the curing period, all traffic, both pedestrian and vehicular, shall be excluded. Vehicular traffic shall be excluded for such additional time as the Engineer may specify.
11/4/2020
186
The Contractor shall be responsible for barricading, patrolling, or otherwise protecting the newly placed concrete to prevent damage. Damaged, vandalized, discolored, stained, or unsightly concrete shall be removed and replaced at the expense of the Contractor.
8-14.4 Measurement Section 8-14.4 is supplemented by adding the following: (******) When the Contract contains a pay item for "Curb Ramp, Cement Concrete," the per each measurement shall include all costs for the complete installation per the Plans and standard details including expansion joint material, curb and gutter and ramped sidewalk section. Sawcutting, removal and disposal of excavated materials including existing pavement and sidewalk, crushed surfacing base materials and all other Work , materials and equipment required per Section 8-14, shall be included in the per each price for "Curb Ramp, Cement Concrete" unless any of these other items are listed and specified to be paid as separate pay items. If the Contract does not provide a pay item for "Curb Ramp, Cement Concrete," but the Plans call for such installation, then quantities shall be measured with and paid for under the bid items for Curb and Gutter and for Cement Concrete Sidewalk. When curb ramps are to be constructed of asphalt concrete, the payment shall be included in the pay item for "Miscellaneous and/or Driveway Asphalt Concrete."
8-14.5 Payment Section 8-14.5 is supplemented with the following: (******) "Curb Ramp, Cement Concrete," per each. Payment for excavation of material not related to the construction of the sidewalk but necessary before the sidewalk can be placed, when and if shown in the Plans, will be made in accordance with the provisions of Section 2-03. Otherwise, the Contractor shall make all excavations including haul and disposal, regardless of the depth required for constructing the sidewalk to the lines and grades shown, and shall include all costs thereof in the unit contract price per square yard for “Cement Concrete Sidewalk” and the per each contract price for “Curb Ramp, Cement Concrete.”
8-17 IMPACT ATTENUATOR SYSTEMS
8-17.5 Payment Section 8-17.5 is supplemented with the following: (******) If no pay item is included for temporary impact attenuators then all costs to provide and install shall be considered a part of the pay item for "Traffic Control."
11/4/2020
187
8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, AND ELECTRICAL
8-20.2(1) Equipment List and Drawings (******) Paragraph four of Section 8-20.2(1) is revised and supplemented with the following: The Contractor shall submit for approval six sets of shop drawings for each of the following types of standards called for on this project: 1. Light standards with or without pre-approved Plans. 2. Signal standards with or without pre-approved Plans. 3. Combination Signal and lighting standards. 4. Metal Strain Poles. Paragraph five of Section 8-20.2(1) is deleted. Paragraph six of Section 8-20.2(1) is deleted. Section 8-20.2(1) is supplemented with the following: The Contractor also shall submit either on the signal standard shop drawings or attached to the signal standard shop drawings all dimensions to clearly show the specific mast arm mounting height and signal tenon locations for each signal pole to be installed.
8-22 PAVEMENT MARKING
8-22.1 Description The following item in Section 8-22.1 is revised with the following: (******) Crosswalk Stripe A SOLID WHITE line, 8 inches wide and 10-feet long, installed parallel to another crosswalk stripe and parallel to the direction of traffic flow and centered in pairs on lane lines and the center of lanes. See detail sheet. Skip Center Line (Replacement) A BROKEN YELLOW line 4 inches wide. The broken or “skip” pattern shall be based on a 24-foot unit consisting of a 9-foot line and a 15-foot gap. Skip center strip is used as centerline delineation on two-lane or three-lane, two-way highways. Double Yellow Center Line (Replacement) Two SOLID YELLOW lines, each 4 inches wide, separated by a 4-inch space. Double yellow center stripe is used as centerline delineation on multilane, two-way highways and for channelization. Approach Line (New) A SOLID WHITE line, 8 inches wide, used to separate left and right turning movements from through movements, to separate high occupancy vehicle lanes from general-purpose lanes, for islands, hash marks, and other applications. Hash mark stripes shall be placed on 45-degree angle and 10 feet apart.
11/4/2020
188
Lane Line (Replacement) A BROKEN WHITE line, 4 inches wide, used to delineate adjacent lanes traveling in the same direction. The broken or “skip” pattern shall be based on a 24-foot unit consisting of a 9-foot line and a 15-foot gap. Two Way Left Turn Line (Replacement) A SOLID YELLOW line, 4 inches wide, with a BROKEN YELLOW line, 4 inches wide, separated by a 4-inch space. The broken or “skip” pattern shall be based on a 24-foot unit consisting of a 9-foot line and a 15-foot space. The solid line shall be installed to the right of the broken line in the direction of travel. Crosswalk Line (Replacement) A SOLID WHITE line, 8 inches wide and 10 feet long, installed parallel to another crosswalk stripe and parallel to the direction of traffic flow and centered in pairs on lane lines and the center of lanes. See detail sheet. Stop Line (Replacement) A SOLID WHITE line 12, 18, or 24 inches wide as noted on the Contract Plans.
8-22.3(5) Installation Instructions Section 8-22.3(5) is revised with the following: (******) A manufacturer’s technical representative need not be present at the initial material installation to approve the installation procedure.
8-22.5 Payment Section 8-22.5 is supplemented with the following: (******) “Approach Stripe,” per linear foot. "Remove Paint Line ....." wide," per linear foot.* "Remove Plastic Line ......" Wide," per linear foot.* "Remove existing traffic markings, "per Lump Sum.* *The linear foot contract price for "Remove Paint Line" and "Remove Plastic Line" and the lump sum contract price for "Remove existing traffic markings" shall be full compensation for furnishing all labor, tools, material, and equipment necessary for removal of existing traffic markings as per the Plans, Specifications and detail sheets. If these pay items do not appear in the contract schedule of prices, then the removal of old or conflicting traffic markings required to complete the channelization of the project as shown on the Plans or detail sheets shall be considered incidental to other items in the Contract and no further compensation shall be made.
11/4/2020
189
8-23 TEMPORARY PAVEMENT MARKINGS
8-23.5 Payment Section 8-23.5 is supplemented with the following: (******) If no pay item is included in the Contract for installation, or for removal of temporary pavement markings, then all costs associated with these items are considered incidental to other items in the Contract or included under "Traffic Control," if that item is included as a bid item.
9-03.8(7) HMA Tolerances and Adjustments Item 1 is deleted and replaced with: (******) 1. Job Mix Formula Tolerances. After the JMF is determined as required in 5-04.3(7)A, the constituents of the mixture at the time of acceptance shall conform to the following tolerances: Nonstatistical Commercial
Evaluation Evaluation Aggregate, percent passing 1”, ¾”, ½”, and 3/8” sieves ±6% ±8% U.S. No. 4 sieve ±6% ±8% U.S. No. 8 sieve ±6% ±8% U.S. No. 16 sieve ±4% ±6% U.S. No. 30 sieve ±4% ±6% U.S. No. 50 sieve ±4% ±6% U.S. No. 100 sieve ±3% ±5% U.S. No. 200 sieve ±2.0% ±3.0% Asphalt Binder ±0.5% ±0.7% VMA 1.5% below minimum value in 9-03.8(2) VFA minimum and maximum as listed in 9-03.8(2) Va 2.5% minimum and 5.5% maximum These tolerance limits constitute the allowable limits as described in Section 1-06.2. The tolerance limit for aggregate shall not exceed the limits of the control point’s section, except the tolerance limits for sieves designated as 100% passing will be 99-100.
9-03.22 Cement-based Grout for Abandoning Existing Utilities (Additional Section) Section 9-03.22 is a new section: (******) The Contractor shall submit a mix proposal that has flow characteristics appropriate for filling a utility pipeline. The mix proposal for “Cement-base Grout for Abandoning Existing Utilities” shall be approved by the Engineer prior to commencing work on this item. Cement-based Grout for Abandoning Existing Utilities shall be equal to a 1-sack mix and the materials shall conform to the following: Cement: This material shall be Portland cement as specified in section 9-01.
11/4/2020
190
Aggregate: This material shall meet the requirements for fine aggregate as specified in Section 9-03.1. Water: Water shall conform to the provisions of Section 9-25.1. Minimum Strength: 100 psi
9-05 DRAINAGE STRUCTURES, CULVERTS, AND CONDUITS
9-05.4 Steel Culvert Pipe and Pipe Arch (RC) Section 9-05.4 is revised with the following: (******) Steel culvert pipe and pipe arch shall meet the requirements of AASHTO M 36, Type I and Type II. Welded seam aluminum coated (aluminized) corrugated steel pipe and pipe arch with metallized coating applied inside and out following welding is acceptable and shall be asphalt treatment coated.
9-05.7(2) Reinforced Concrete Storm Sewer Pipe (RC) Section 9-05.7(2) is replaced by the following: (******) Reinforced Concrete Storm Sewer pipe shall conform to the requirements of ASTM C-76 and shall be Class IV. Cement used in the manufacture of reinforced concrete pipe shall be Type II in conformance with ASTM C150. No admixture shall be used unless otherwise specified.
9-05.7(2)A Basis for Acceptance (RC) Section 9-05.7(2)A is supplemented with the following: (******) All pipe shall be subject to (1) a three-edge-bearing strength (D-load) test in accordance with ASTM C76; and (2) a hydrostatic test of rubber gasket joints in accordance with ASTM C361 or AWWA C302 except test pressure shall be 5 psi.
9-05.7(3) Concrete Storm Sewer Pipe Joints (RC) Section 9-05.7(3) is replaced by the following: (******) Joint assembly design shall be reinforced concrete bell and spigot type incorporating a fully retained single rubber gasket in accordance with ASTM C361 or AWWA C302. Rubber gasket material shall be neoprene.
9-05.7(4) Testing Concrete Storm Sewer Pipe Joints (RC) Section 9-05.7(4) is supplemented with the following: (******) Hydrostatic testing of rubber gasket joints shall be performed in accordance with ASTM C361 or AWWA C302 except test pressure shall be 5 psi.
11/4/2020
191
9-05.9 Steel Spiral Rib Storm Sewer Pipe (RC) Section 9-05.9 is replaced with: (******) The manufacturer of spiral rib storm sewer pipe shall furnish the Engineer a Manufacturer's Certificate of Compliance stating that the materials furnished comply in all respects with these Specifications. The Engineer may require additional information or tests to be performed by the Contractor at no expense to the City. Unless otherwise specified, spiral rib storm sewer pipe shall be furnished with pipe ends cut perpendicular to the longitudinal axis of the pipe. Pipe ends shall be cut evenly. Spiral rib pipe shall be fabricated either by using a continuous helical lock seam or a continuous helical welded seam paralleling the rib. Steel spiral rib storm sewer pipe shall be manufactured of metallic coated (aluminized or galvanized) corrugated steel and inspected in conformance with Section 9-05.4. The size, coating, and metal shall be as shown in the Plans or in the Specifications. For spiral rib storm sewer pipe, helical ribs shall project outwardly from the smooth pipe wall and shall be fabricated from a single thickness of material. The ribs shall be essentially rectangular and shall be 3/4 inch plus two times the wall thickness (2t) plus or minus 1/8 inch (measured outside to outside) and a minimum of 0.95 inch high (measured as the minimum vertical distance from the outside of pipe wall immediately adjacent to the lockseam or stiffener to the top surface of rib). The maximum spacing of the ribs shall be 11.75 inches center to center (measured normal to the direction of the ribs). The radius of bend of the metal at the corners of the ribs shall be a minimum of 0.10 inch and a maximum of 0.17 inch. If the sheet between adjacent ribs does not contain a lockseam, a stiffener shall be included midway between ribs, having a nominal radius of 0.25 inch and a minimum height of 0.20 inch toward the outside of the pipe. Pipe shall be fabricated with ends that can be effectively jointed with coupling bands. When required, spiral rib or narrow pitch spiral rib pipe shall be bituminous treated or paved. The bituminous treatment for spiral rib pipe shall conform to the requirements of Sections 9-05.4(3) and 9-05.4(4). For narrow pitch spiral rib sewer pipe, the helical ribs shall project outwardly from the smooth pipe wall and shall be fabricated from a single thickness of material. The ribs shall be .375 inch + 1/8 inch wide (measured outside to outside) and a minimum of .4375 inch high (measured as the minimum vertical distance of ribs shall be 4.80 inches center to center (measured normal to the direction of the ribs). The radius of bend of the metal at the corners of the ribs shall be 0.0625 inch with an allowable tolerance of + 10 percent.
9-05.12 Polyvinyl Chloride (PVC) Pipe Section 9-05.12(3) is a new additional section: (******) Gravity sewer pipe shall be as specified herein and as shown on the Plans. The Contractor shall provide one electronic copy of the pipe manufacturer’s technical literature including tables of dimensional tolerances to the Engineer. Any pipe found to have dimensional tolerances in excess of those prescribed or having defects, which prevent adequate joint seal or any other damage, shall be rejected. If requested by the Engineer, not less than three nor more than five lengths of pipe for each
11/4/2020
192
size, selected from stock by the Engineer, shall be tested as specified for maximum dimensional tolerance or the respective pipe. Materials shall meet the requirements of the following sections: PVC sewer pipe – Section 9-05.12(1) PVC (C900/C905) sewer pipe – Section 9-30.1(5)A All pipe shall be clearly marked with type, class, and thickness. Lettering shall be legible and permanent under normal conditions of handling and storage.
9-05.14 ABS Composite Sewer Pipe Section 9-05.14 is deleted in its entirety (******)
9-05.17 Aluminum Spiral Rib Storm Sewer Pipe Section 9-05.17 is replaced with: (******) Unless otherwise specified, spiral rib storm sewer pipe shall be furnished with pipe ends cut perpendicular to the longitudinal axis of the pipe. Pipe ends shall be cut evenly. Spiral rib pipe shall be fabricated by using a continuous helical lock seam with a seam gasket. For spiral rib storm sewer pipe, helical ribs shall project outwardly from the smooth pipe wall and shall be fabricated from a single thickness of material. The ribs shall be 3/4 inch wide by 3/4 inch deep with a nominal spacing of 7-1/2 inches center to center. Pipe shall be fabricated with ends that can be effectively jointed with coupling bands. For narrow pitch spiral rib storm sewer pipe, helical ribs shall project outwardly from the smooth pipe wall and shall be fabricated from a single thickness of material. The ribs shall be 0.375 inch + 1/8 inch wide (measured outside to outside) and a minimum spacing of ribs shall be 4.80 inches center to center (measured normal to the direction of the ribs). The radius of bend of the metal at the corners of the ribs shall be 0.0625 inch with an allowable tolerance of + 10 percent. For wide pitch spiral rib storm sewer pipe, helical ribs shall project outwardly from the smooth pipe wall and shall be fabricated from a single thickness of material. The ribs shall be 3/4 inch + 1/8 inch wide (measured outside to outside) and a minimum of 0.95 inch high (measured as the minimum vertical distance from the outside of pipe wall to top surface of the rib). The maximum spacing of ribs shall be 11.75 inches center to center (measured normal to the direction of the ribs). The radius of bend of the metal at the corners of the ribs shall be 0.0625 inch with an allowable tolerance of + 10 percent.
9-05.20 Corrugated Polyethylene Storm Sewer Pipe (CPEP) Section 9-05.19 is replaced with the following: (******)
9-05.20(1) Description Corrugated Polyethylene Pipe (CPEP) shall be corrugated high-density polyethylene pipe with smooth internal wall manufactured by Advanced Drainage Systems (ADS), or approved equivalent.
11/4/2020
193
9-05.20(2) Pipe Material and Fabrication CPEP shall be in conformance with the latest version of ASTM F 667 or AASHTO M 294, Type S.
9-05.20(3) Fittings and Gaskets Fittings shall be gasketed PVC fittings. Gaskets shall conform to ASTM F 477. Fittings shall conform to ASTM F 1536 or ASTM D 3212. Fittings shall be manufactured by Nyloplast USA, Inc., or approved equivalent.
9-05.20(4) Installation Pipe and fittings shall be installed per the manufacturer's recommendations. Lubricate gasket and fitting socket with manufacturer-approved lubricant prior to pushing pipe into fitting.
9-05.24 Polypropylene Culvert Pipe, Polypropylene Storm Sewer Pipe, and
Polypropylene Sanitary Sewer Pipe This sections content is deleted and replaced with the following: (******) All joints for polypropylene pipe shall be made with a bell/bell or bell and spigot coupling and shall conform to ASTM D 3212 using elastomeric gaskets conforming to ASTM F 477. All gaskets shall be factory installed on the pipe in accordance with the producer’s recommendations. Qualification for each producer of polypropylene storm sewer pipe requires joint system conformance to ASTM D 3212 using elastomeric gaskets conforming to ASTM F 477 and a formal quality control plan for each plant proposed for consideration. A Manufacturer’s Certificate of Compliance shall be required and shall accompany the materials delivered to the project. The certificate shall clearly identify production lots for all materials represented. The Contracting Agency may conduct verification tests of pipe stiffness or other properties it deems appropriate. This section is supplemented with the following new sub-sections:
9-05.24(1) Polypropylene Culvert Pipe and Storm Sewer Pipe Polypropylene culvert and storm sewer pipe shall conform to the following requirements: 1. For dual wall pipe sizes up to 30 inches: ASTM F2736. 2. For triple wall pipe sizes from 30 to 60 inches: ASTM F2764. 3. For dual wall profile pipe sizes 36 to 60 inches: AASHTO MP 21, Type S or Type D. 4. Fittings shall be factory welded, injection molded or PVC.
9-05.52 Dense Foam Section 9-05.52 is a New Section as follows: (******) Dense foam shall be Ethafoam HS 600 high density, polyethylene foam, as manufactured by Dow Chemical Company, or approved equivalent.
11/4/2020
194
9-08 PAINTS AND RELATED MATERIALS
9-08.9 Manhole Coating System Products Section 9-08.8 is a new section and subsections:
(******)
9-08.8(1) Coating Systems Specification A. High Solids Urethane Coating System: C1 Coating Material: High Solids Urethane Surfaces: Concrete Surface Preparation: In accordance with SSPC SP-7 (Sweep or brush off blast) Application: Shop: The drying time between coats shall not exceed 24 hours in any case System Thickness: 3.0-4.0 mils dry film Coatings: Primer: One coat of Wasser MC-Shieldcoat 100 high solids urethane (1.5-2.0 DFT) Finish: One coat of Wasser MC-Shieldcoat 100 (min. 1.5-2.0 DFT) Color: White
9-14 EROSION CONTROL AND ROADSIDE PLANTING
9-14.1(1) Topsoil Type A Section 9-14.1(1) is supplemented with the following: (******) Planting soil / topsoil shall consist of loose, moderately well-drained, friable soil of sandy loam texture, free of ice, snow and rubbish with no admixture of refuse or material toxic to plant growth. Soil shall be reasonably free of stones, lumps, roots, and weeds or similar objects. Topsoil should be fertile and free-flowing (pulverized). Topsoil shall be Mycorrhizae inoculated. Topsoil shall meet the following parameters: Parameter Range pH 6.7-7.5 Moisture Content 25%-55% Soluble Salts 2.5 mmhos/(dS) Coarse Sand 50%max (by weight) Clay 25%max (by weight) Silt 15%max (by weight) Organic matter 10%max (by weight)
11/4/2020
195
9-14.6(8) Sod Section 9-14.6(8) is supplemented with the following: (******) Sod shall be nursery-grown (farm-grown) under climatic conditions similar to or hardier than those at the site. Sod shall have normal habit of growth and be healthy, vigorous and free of disease, insects, insect eggs and larvae. Sod material shall meet or exceed the specification of Federal, State and local laws requiring inspection for plant disease and insect control. Sod: Non-net “Premium Shadow Master” Sod Mixture from Emerald Turfgrass Farms, Inc., Sumner, WA, Ph: 253 838 9911 or 425 641 0608, or approved equal. Approved equal must be from a local grower and be established in growing sod in sandy loam soils. Sod grown in heavy clay soils is not acceptable. All required certifications apply for “approved equal”. Sod shall contain 65% perennial turf-type ryegrass by weight and 35% hard fescue by weight.
9-23 CONCRETE CURING MATERIALS AND ADMIXTURES
9-23.9 Fly Ash (RC) Section 9-23.9 is revised with the following: (******) Fly ash shall not be used around water lines.
9-30 WATER DISTRIBUTION MATERIALS
9-30.1 Pipe Section 9-30.1 is supplemented and revised with the following: (******) All materials for water distribution and transmission shall be new and undamaged. Prior to ordering any pipe and fittings to be used in a potable water supply, the Contractor shall submit the material source as required by Section 1-06.1 of the Standard Specifications. All direct and indirect drinking water system components which come in contact with potable water shall have National Sanitation Foundation (NSF) certification. All pipe and fittings shall be clearly marked with the manufacturer’s name, type, class, and thickness as applicable and shall be marked on the component at the place of manufacture. Marking shall be legible and permanent under normal conditions of handling and storage.
9-30.1(1) Ductile Iron Pipe Section 9-30.1(1) is revised with the following: (******) 1. Ductile iron pipe shall be centrifugally cast in 18 or 20 foot nominal lengths and meet the requirements of AWWA C151. Ductile iron pipe shall have a double thick cement mortar lining and a 1-mil thick seal coat meeting the requirements of AWWA C104. Ductile iron pipe shall be minimum Standard Thickness Class 52 or the thickness class as shown in the Plans. Flanged ductile iron pipe shall be Class 53 per AWWA C115. 2. Non-restrained joint shall be rubber gasket, push-on type joint (Tyton) or mechanical joint (M.J.) conforming to AWWA C111, unless otherwise specified. 3. Restrained joints shall be as specified in Section 9-30.2(6).
11/4/2020
196
4. Flanged joints shall conform to ANSI B16.1, class 125 drilling pattern, rated for 250 psi working pressure. Flanged ductile iron pipe shall be Class 53 per AWWA C 115. Thicker Classes are acceptable.
The Contractor shall furnish certification from the manufacturer of the pipe and gasket being supplied that the inspection and all of the specified tests have been made and the results thereof comply with the requirements of the above referenced standards.
9-30.1(2) Polyethylene Encasement Section 9-30.1(2) is supplemented and revised with the following: (******) Polyethylene encasement (plastic film wrap) shall be eight mil polyethylene, tube type conforming to AWWA C105. All ductile iron pipes and fittings shall be installed with a polyethylene encasement, tube-type and in black color.
9-30.2 Fittings
9-30.2(1) Ductile Iron Pipe Section 9-30.2(1) is supplemented and revised with the following: (******) Fittings for ductile iron pipe shall be ductile iron conforming to AWWA C110, and AWWA C111 or AWWA C153 and shall be cement-lined conforming to AWWA C104. All water main fittings shall be ductile iron, short body, cement lined and for pressure rating of 350 psi for mechanical joint fittings and 250 psi for flange joint fittings, unless otherwise specified. Metal thickness and manufacturing process shall conform to applicable portions of ANSI/AWWA C110/A21.10. Mechanical joint, ductile iron, compact fittings 24 inches and less shall conform to ANSI A21.53 (AWWA C153). Flanged fittings, cast or ductile iron, shall conform to ANSI B16.1, class 125 drilling pattern.
Ductile iron fittings include: tees, crosses, wyes, bends, adapters, sleeves, plugs, caps, offsets, reducers, and ells.
Rubber gaskets for push-on joints (Tyton) or mechanical joint (M.J.) shall conform to ANSI A21.11 / AWWA C111. Gasket materials for flange joints shall be neoprene, Buna N, chlorinated butyl, or cloth-inserted rubber suitable for pressurized water service purposes. Type of connections shall be specified as push-on joint (Tyton), mechanical joint (M.J.), plain end (P.E.), flanged (FL), restrained joint (RJ) and threaded.
Sleeves less than 12 inches in diameter shall be 12 inches minimum length and shall be mechanical joint. Sleeves greater than 12 inches in diameter shall be of the long body type and shall be 15 inches minimum length and shall be mechanical joint.
Where ductile iron pipe is to be joined to existing cast iron pipe of the same nominal size and the outside diameter of the existing cast iron pipe is 0.05 inches or less from the outside diameter of the ductile iron pipe being joined, the pipe shall be joined with a mechanical joint sleeve.
Where ductile iron pipe is to be joined to existing cast iron pipe of the same nominal size and the outside diameter of the existing cast iron pipe conforms to AWWA 1908 classifications A, B, C, D, or F,
11/4/2020
197
the pipe shall be joined with a transition mechanical joint sleeve having a single-piece casting. Threaded pipe and flanges combinations shall not be used.
Bolts in piping and fittings shall be malleable iron, Cor-ten or stainless steel. Bolts and nuts for flanged pipe and fittings shall conform in size and length with ANSI/AWWA C111/A21.11. Stainless steel bolts shall meet the requirements of ASTM A-307, Grade A. Shackle rods shall be Cor-ten or stainless steel all thread 316SS. Stainless steel nuts and bolts shall be type 316SS.
Contractor shall provide Manufacturer’s Certificate of Compliance in accordance with Section 1-06.3 Manufacturer’s Certificate of Compliance of the Standards Specifications for all fittings and bolts to be used.
9-30.2(2) Galvanized Iron Pipe Section 9-30.2(2) is a new section and shall read as follows: (******) Where galvanized iron pipe is specified, the pipe shall be standard weight, Schedule 40, steel pipe per Standard Specifications for black and hot-dipped, zinc coated (galvanized) welded and seamless steel pipe for ordinary uses (ASTM A-120). Fittings shall be screwed malleable iron galvanized per ANSI B16.3.
9-30.2(3) Steel Casing Pipe Section 9-30.2(3) is a new section and shall read as follows: (******) Steel casing shall be black steel pipe conforming to ASTM A 53. Before installation, coat casing exterior with shop-applied anticorrosive coating conforming to AWWA C210. Minimum coating thickness shall be 16 mils dry film thickness (DFT); however, thickness shall not exceed manufacturer’s recommended thickness. Coating type shall be a polyamide epoxy-coal tar equal to Tnemec Hi-Build Theme-Tar, Series 46H-413.
Casing wall thickness shall be 0.250 inch for casings 24 inches or less in diameter and 0.375 inch for casings over 24 inches in diameter.
Carrier pipe for water main shall be Restrained Joint Ductile Iron, Class 52.
(******)
9-30.2(4) Spacers and Seals for Steel Casing Pipe Casing spacers shall be “centered positioning” type bands at least 12 inch in width, and shall be either stainless steel or heavy duty fusion bonded epoxy coated steel. Runners shall be 2-inch wide glass reinforced plastic securely bonded to the spacer, and shall be aligned on the spacer along the axis of insertion of the water main into the casing pipe. Runner length shall approximate the width of the spacer. Securing the spacer to the water main shall be in accordance with the manufacturer’s instruction. The height of the risers and runners combined shall be sufficient to keep the carrier pipe bell, couplings or fittings at least 0.75 inch from the casing pipe wall at all times and provide at least 1-inch clearance between the runners and the top of the casing wall, to prevent jamming during installation.
11/4/2020
198
Acceptable spacers and end seals manufacturers are Pipeline Seal and Insulator model S12G-2 for stainless steel and model C12G-2, C8G-2 for fusion-bonded and coated steel, Cascade Waterworks Mfg. Co., Advance Products & Systems, Inc. or approved equal.
9-30.2(6) Restrained Joint Section 9-30.2(6) including title isdeleted and replaced with with the following: (******)
9-30.2(6) Restrained Joint Pipe and Fittings Restrained joints (RJ) ductile iron pipe and fittings, where required on the plans, shall be flexible after assembly and be able to be disassembled. Restrained joints shall meet the following criteria: 1. The restrained joint shall have a positive metal to metal contact locking system without the use of gripping teeth. Gaskets for push-on joint pipe with integrally molded steel or metal teeth or locking segments shall not be allowed as substitutes for restrained-joint pipes. 2. The joint restraint system for the pipe shall be the same as the joint restraint system for the pipe fittings, except as provided in item 4 below. 3. The joint restraint system for the pipe shall be boltless. 4. Where restrained joint fittings required on the plans cannot be furnished or where restrained jointed fittings are required in areas that are known to be subject to location adjustments, the Contractor may submit a lay plan showing mechanically jointed fittings with wedge restraint glands for approval. Mechanically jointed pipe with wedge restraint glands shall not be substituted for restrained joint pipe.
Wedge Restraint Glands Wedge restraint glands shall conform to AWWA C111, ASTM A 536-80 Grade 65-42-12. All bolts and wedges shall be ductile iron. Wedge shall be heat-treated to a minimum 370 BHN. Wedge restraint glands shall be rated for 350 psi for pipe 12 inch in diameter and smaller.
9-30.2(7) Bolted, Sleeve-Type Couplings for Plain End Pipe Section 9-30.2(7) is revised with the following: (******) Transition couplings, reducing couplings, transition reducing couplings, sleeves, flexible couplings for water main shall be compression type by pipe manufacturer: Romac or Ford or approved equal. Bolts and nuts shall be high strength, low alloy steel, corrosion resistant per AWWA C111. Stainless steel bolts require anti-seize compound. Heavy hex nuts shall be used.
The long body pattern with a minimum center ring or center sleeve length of 12-inches for pipe less than 12 inches in diameter and equal to or greater than the pipe diameter for pipe greater than 12 inches in diameter. Solid sleeves (greater than 12 inch diameter) shall be a 15 inch minimum length.
9-30.3 Valves Section 9-30.3 is supplemented and revised with the following: (******) The valves shall be a standard pattern of a manufacturer whose products are approved by the Engineer and shall have the name or mark of the manufacturer, year valve casting was made, size and working pressure plainly cast in raided and legible letters on the valve body. All valves shall be NSF
11/4/2020
199
approved and valve bodies shall be ductile iron. All valves shall be stamped with “NSF APPROVED” and “DI”. Where a valve is required to operate in a higher pressure environment than the Class of valve specified in Section 9-30.3, the class of valve shall be as specified in the Contract.
9-30.3(1) Gate Valves (3 inches to 16 inches) Section 9-30.3(1) is supplemented and revised with the following: (******) All valve material shall be new and undamaged. Unless otherwise approved by the Engineer, the same manufacturer of each item shall be used throughout the work. All gate valves shall be ductile iron body, bronze mounted, resilient seat, non-rising stem and shall be equipped with a standard two (2) inch square operating nut and O-ring stem seals. Valves shall open counterclockwise when viewed from above. Valves shall be designed for a minimum water operating pressure of 200 PSI. Resilient seated gate valves shall be manufactured to meet or exceed the requirements of AWWA Standard C-509 and C-515 latest revisions. Valve ends shall be mechanical joints, flanged joints or mechanical by flanged joints as shown on the project plans. Where restrained joints are called out, valve ends shall be flanged with appropriate flange by restrained joint adapters. All gate valves shall include an 8" x 24" cast iron gate valve box and extensions, as required. A valve stem extension is required where the valve operating nut is more than 3 feet below finished grade. Valve stem extensions are to be a minimum of 1 foot with only one extension per valve in shall be installed in accordance to the City of Renton standard plans. Acceptable gate valves are Clow, M & H/Kennedy, American Flow Control (ACIPCo), Pratt/Mueller, US Metroseal or approved equal in sizes 16 inches and less. Approval of valves other than models specified shall be obtained prior to bid opening.
9-30.3(3) Butterfly Valves Section 9-30.3(3) is supplemented and revised with the following: (******) In addition to the requirements of section 9-30.3, water main butterfly valves shall conform to AWWA C504 and shall be Class 150B. The valve shall be short-body type and shall have flanged ends. Flanged ends shall be sized and drilled in conformance with ANSI B16.1 Class 125. Valve shall be suitable for direct bury and shall have a stem extension with AWWA 2-inch square operating nut and suitable valve box. All butterfly valves bodies and discs shall be ductile iron. The butterfly valves shall be manufactured by Henry Pratt Company, Mueller, DeZurick, Mosser Valve Division of Olsen Technologies, Dresser 450, Pratt Groundhog or approved equal.
11/4/2020
200
9-30.3(4) Valve Boxes Section 9-30.3(4) is supplemented and revised with the following: (******) Valve boxes shall be installed on all buried valves. The box and lid shall be cast iron, 2-piece slip type with cast iron extension as necessary, conforming to the City of Renton latest standard plans. The cover shall have the word “WATER” cast in it and shall have cast-iron “ears” installed in the direction of the main. Valve box extension pieces shall be provided for valves with groundcover in excess of the depth of the standard valve box. Acceptable manufacturers of valves boxes and covers are Olympic Foundry, Inc., EJCO, Rich (Varnish Casting Corp.)
9-30.3(5) Valve Marker Posts Section 9-30.3(5) is supplemented and revised with the following: (******) Valve markers shall be Carsonite composite utility marker .375"x 6'-0" or approved equal with blue label "water”. The valve markers shall be installed in conformance with the City of Renton Standard Plans.
9-30.3(6) Valve Stem Extensions Section 9-30.3(6) is supplemented and revised with the following: (******) Valve stem extensions shall have a 2-inch square operating nut and self-centering rockplate. A valve stem extension is required where the valve operating nut is more than 3 feet below finished grade. Valve stem extensions are to be a minimum of 1 foot with only one extension per valve in shall be installed in accordance to the City of Renton standard plans.
9-30.3(7) Combination Air Release/Air Vacuum Valves Section 9-30.3(7) is supplemented and revised with the following: (******) Combination air release/air vacuum valves shall comply with the requirements of ANSI/AWWA C512. Air and vacuum release valves shall be APCO No. 143C- Valve and Primer Corp, "Heavy-Duty," combination air release valve, Val-Matic No. 201C, Crispin UL10 or approved equal. Installation shall be per the City of Renton Standard Details, latest revision. Piping and fitting shall be copper or brass. Location of the air release valve as show on the plans is approximate. The installation shall be set at the actual high point of the line.
9-30.3(8) Tapping Sleeve and Valve Assembly Section 9-30.3(8) is supplemented and revised with the following: (******) Tapping sleeves shall be cast iron, ductile iron, or epoxy coated steel. Bolt and nuts shall be Cor-Ten or stainless steel.
9-30.3(9) Blow-Off Assembly Section 9-30.3(9) is a new section: (******) Installation of blow-off assembly shall be per City of Renton Standard Details, latest revision. Pipe and fittings shall be galvanized. Blow-off assembly shall be installed at location(s) shown on the plans.
11/4/2020
201
Temporary blow-off assembly on new dead-end water main shall be installed at location shown on the plans. Temporary blow-off assemblies for testing and flushing of the new water mains will not be included under this item and shall be considered incidental to the contract and no additional payment shall be made.
9-30.5 Hydrants Section 9-30.5 is supplemented and revised with the following: (******) Fire hydrants shall conform to AWWA C502 and shall be of standard manufacture and of a pattern approved by the City of Renton. The name or mark of the manufacturer, size of the valve opening and year made shall be plainly cast in raised letters on the hydrant barrel to be visible after the hydrant is installed. Hydrants of the following manufacture and pattern have been approved by the City of Renton. Clow Medallion, M&H 929, Mueller Centurion Model A-423, Waterous Pacer, American Darling Model B-62B, Kennedy K81D Guardian, East Jordan WaterMaster 5CD250.
9-30.5(1) End Connections Section 9-30.5(1) is revised with the following: (******) Hydrant end connections shall be mechanical joint connection unless otherwise specified in the description of the bid of proposal.
9-30.5(2) Hydrant Dimensions Section 9-30.5(2) is replaced with the following: (******) Fire hydrants shall have a valve opening with minimum diameter of 5-1/4 inches, “O” ring stem seal, two 2-1/2 inches National Standard Thread (N.S.T.) hose nozzle connections, one 4-inches pumper port connection with City of Seattle standard threats and with a 4.875” Seattle thread x 5” Storz adapter attached with a 1/8” stainless steel cable. The shoe connection and hydrant connection inside pipe size and auxiliary gate valve shall be 6 inches, mechanical joint with lugs. The operating nut and port cap nuts are 1-1/4-inch pentagonal. Hydrant restraint system shall be two 3/4-inch diameter Cor-Ten steel shackle rods with a poured in place concrete thrust block behind the hydrant shoe. If a wedge restraint system is used in lieu of shackle rods, mechanical joint pipe shall be used. Hydrants shall be provided with a breakaway flange assembly and be equipped with breaking devices at the sidewalk. The hydrant curb stand section of the hydrant that is above ground including all exposed surfaces of the breakaway flange shall be painted with 2 field coats of paint Kelly-Moore Luxlite or approved equal in Safety Yellow color. Fire hydrants shall be installed per City of Renton Standard Details for fire hydrants, latest revisions.
11/4/2020
202
9-30.6 Water Service Connections (2 Inches and Smaller)
9-30.6(3) Service Pipes
9-30.6(3)B Polyethylene Pipe Section 9-30.6(3)B is revised to read as follows: (******) Polyethylene pipe shall not be used.
9-30.6(4) Service Fittings Section 9-30.6(4) has been revised with the following: (******) Fittings used for copper tubing shall be compression type with gripper ring.
9-30.6(5) Meter Setters Section 9-30.6(5) has been supplemented with the following: (******) Meter setters shall be installed per the City of Renton Standard Details for water meters, latest revision.
9-30.6(7) Meter Boxes Section 9-30.6(7) has been supplemented with the following: (******) Meter boxes shall be installed per the City of Renton Standard Details for water meters, latest revision.
SECTION 10
10-01 MARKING PAINT REMOVAL
The permittee will be required to remove utility locate marks on sidewalks only within the Downtown Core Area. The permittee shall remove the utility locate marks within 14 days of job completion.
APPENDICES | LONG-RANGE WASTEWATER MANAGEMENT PLAN | CITY OF RENTON
MARCH 2021
Appendix K
CIP DETAIL SHEETS
Unprotect password: CIP
Capital Improvement Program Summary (Current Dollars)Capital Improvement Projects
Project ID Project Name
Project Type Short-term Long-term Pump Station
(2020-2025) (2030-2039) LS-01 Lift Station Rehabilitation
Cross Category 9,130,000$ 630,000$ 9,760,000$ LS-02 Forcemain Rehabilitation/Replacement
Maintenance 14,740,000$ 49,470,000$ 64,210,000$ LS-03 Telemetry Upgrade
Planning 2,880,000$ 2,000,000$ 4,880,000$ LS-04 Devil's Elbow Stream Bank Study
Total Cost 26,750,000$ 52,100,000$ 96,590,000$ LS-05 Kennydale Lakeline Sewer Upgrade
Annual Cost 4,458,000$ 5,210,000$ 4,830,000$ LS-06 Kennydale Lakeline Renewal
LS-07 Low and Moderately-Low Risk Lift Station and FM Rehabilitation
LS-08 Moderately-High and High Risk Lift Station and FM Rehabilitation
Pipeline
P-01 2020 Sanitary Sewer Main Replacement/Rehabilitation
P-02 2021 Sanitary Sewer Main Replacement/Rehabilitation
P-03 2022 Sanitary Sewer Main Replacement/Rehabilitation
P-04 2023 Sanitary Sewer Main Replacement/Rehabilitation
P-05 2024 Sanitary Sewer Main Replacement/Rehabilitation
P-06 2025 Sanitary Sewer Main Replacement/Rehabilitation
P-07 2026-2029 Sanitary Sewer Main Replacement/Rehabilitation
P-08 2030-2039 Sanitary Sewer Main Replacement/Rehabilitation
P-09 Sewer Capacity Improvements
P-10 Flow Monitoring Program
P-11 I/I Evaluation Program
General
G-01 Wastewater Operations Master Plan
$20,160,000 21%G-02 Long-Range Wastewater Management Plan
$71,230,000 74%G-03 Sanitary Sewer Hydraulic Model
$5,200,000 5%G-04 Miscellaneous/Emergency Projects
$96,590,000 100%
$3,480,000 13%
$20,870,000 78%
$2,400,000 9%
$26,750,000 100%
$14,110,000 37%
$35,990,000 9%
$2,000,000 8%
$52,100,000 100%
Total CIP Cost
Estimate
City of Renton
Long-Range Wastewater Management Plan
Capital Improvement Program
CIP Phasing
Total
Lift Station
Total
Short-Term
Long-Term
Total
Lift Station
Pipeline
General
Lift Station
Pipeline
General
Pipeline
General
Lift Station ,
$20,160,000 , 21%
Pipeline, $71,230,000 ,
74%
General ,
$5,200,000 , 5%
Cost by Project Category
Lift Station ,
$3,480,000 , 13%
Pipeline
78%
General
9%
Cost by Project Category (Short-Term)
Lift Station ,
$14,110,000 , 27%
Pipeline,
$35,990,000 , 69%
General ,
$2,000,000 , 4%
Cost by Project Category (Long-Term)
0CIP Phasing (Current Dollars)Project2028 Short-termMedium-termLong-termEnter Cost Type Here:Current Dollars(2020-2025)(2026-2029)(2030-2039)$20,160,000 $3,000,000 $180,000 $0 $300,000 $0 $0 $650,000$640,000 $640,000 $640,000 $3,480,000 $2,570,000 $14,110,000LS-01$900,000 $900,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $900,000 $0 $0LS-02$400,000 $400,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $400,000 $0 $0LS-03$300,000 $0 $0 $0 $300,000 $0 $0 $0 $0 $0 $0 $300,000 $0 $0LS-04$180,000 $0 $180,000 $0 $0 $0 $0 $0 $0 $0 $0 $180,000 $0 $0LS-05$1,700,000 $1,700,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,700,000 $0 $0LS-06$8,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,000,000LS-07$6,110,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,110,000LS-08$2,570,000 $0 $0 $0 $0 $0 $0 $650,000 $640,000 $640,000 $640,000 $0 $2,570,000 $0Pipelines$71,230,000 $1,500,000 $3,450,000 $4,780,000 $3,730,000$3,660,000 $3,750,000 $3,750,000 $3,540,000 $3,540,000 $3,540,000 $20,870,000 $14,370,000 $35,990,000P-01$1,500,000 $1,500,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,500,000 $0 $0P-02$2,000,000 $0 $2,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $2,000,000 $0 $0P-03$2,000,000 $0 $0 $2,000,000 $0 $0 $0 $0 $0 $0 $0 $2,000,000 $0 $0P-04$2,000,000 $0 $0 $0 $2,000,000 $0 $0 $0 $0 $0 $0 $2,000,000 $0 $0P-05$2,000,000 $0 $0 $0 $0 $2,000,000 $0 $0 $0 $0 $0 $2,000,000 $0 $0P-06$3,540,000 $0 $0 $0 $0 $0 $3,540,000 $0 $0 $0 $0 $3,540,000 $0 $0P-07$14,160,000 $0 $0 $0 $0 $0 $0 $3,540,000 $3,540,000 $3,540,000 $3,540,000 $0 $14,160,000 $0P-08$35,360,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $35,360,000P-09$5,800,000 $0 $1,450,000 $1,450,000 $1,450,000 $1,450,000 $0 $0 $0 $0 $0 $5,800,000 $0 $0P-10$1,190,000 $0 $0 $280,000 $280,000 $210,000 $210,000 $210,000 $0 $0 $0 $980,000 $210,000 $0P-11$1,680,000 $0 $0 $1,050,000 $0 $0 $0 $0 $0 $0 $0 $1,050,000 $0 $630,000General$5,200,000 $500,000 $500,000 $500,000 $200,000 $500,000 $200,000 $200,000 $200,000 $200,000 $200,000 $2,400,000 $800,000 $2,000,000G-01$300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300,000 $0 $0G-02$300,000 $0 $0 $0 $0 $300,000 $0 $0 $0 $0 $0 $300,000 $0 $0G-03$600,000 $0 $300,000 $300,000 $0 $0 $0 $0 $0 $0 $0 $600,000 $0 $0G-04$4,000,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $1,200,000 $800,000 $2,000,000CIP Total (Current Dollars)$96,590,000 $5,000,000 $4,130,000 $5,280,000 $4,230,000$4,160,000 $3,950,000 $4,600,000 $4,380,000 $4,380,000 $4,380,000 $26,750,000 $17,740,000 $52,100,000Annual Cost (Current Dollars)$4,830,000 $5,000,000 $4,130,000 $5,280,000 $4,230,000 $4,160,000 $3,950,000 $4,600,000 $4,380,000 $4,380,000 $4,380,000 $4,458,000 $4,435,000 $5,210,000City of RentonLong-Range Wastewater Management PlanCapital Improvement Program (Current Dollars)Capital Improvement Program Summary (Current Dollars)Wastewater Operations Master PlanDevil's Elbow Stream Bank Study2020 2021 2024 2029 2027 2026 2022 2023 2025 Long-Range Wastewater Management PlanSanitary Sewer Hydraulic ModelMiscellaneous/Emergency ProjectsTelemetry Upgrade2020 Sanitary Sewer Main Replacement/Rehabilitation2021 Sanitary Sewer Main Replacement/Rehabilitation2022 Sanitary Sewer Main Replacement/Rehabilitation2023 Sanitary Sewer Main Replacement/RehabilitationI/I Evaluation ProgramFlow Monitoring ProgramForcemain Rehabilitation/Replacement Total CIP Cost Estimate Lift Station RehabilitationPump Stations2024 Sanitary Sewer Main Replacement/Rehabilitation2025 Sanitary Sewer Main Replacement/RehabilitationKennydale Lakeline Sewer UpgradeKennydale Lakeline RenewalLow and Moderately-Low Risk Lift Station and FM RehabilitationModerately-High and High Risk Lift Station and FM Rehabilitation2026-2029 Sanitary Sewer Main Replacement/Rehabilitation2030-2039 Sanitary Sewer Main Replacement/RehabilitationSewer Capacity ImprovementsRenton CIP and Financial.xlsxCIP Summary TableDraftPage 1 of 1Printed on 1/7/2021
City of Renton
Long-Range Wastewater Management Plan
Capital Improvement Program
Notes:
1 All costs are in 2019 dollars. Cost estimate made in:2020
2 Engineering News Report (ENR) U.S. 20-City Construction Cost Index for July 2019 is 11293
3 Cost estimates do not include costs for easements or ROW acquisition.
4 Cost estimates per foot of pipe before contingencies are as follows:
5 Allowances are used based upon planning level budgeting. Estimates will be refined based on subsequent studies
6 To update costs for inflation to future value, insert inflation rate here:3%
7 When considering cost inflation for long-term projects, timing is assumed to be 15 years from current date.
Gravity Sewer Unit Costs
Pipe Diameter Value Unit Notes
6"$330 LF 15' depth
8"$341 LF 15' depth
10"$352 LF 15' depth
12"$363 LF 15' depth
14"$374 LF 15' depth
16"$385 LF 15' depth
18"$396 LF 15' depth
24"$407 LF 15' depth
CIPP Costs
Pipe Diameter Value Unit Notes
6"$52.80 LF
8"$70.40 LF
10"$88.00 LF
12"$105.60 LF
14"$123.20 LF
16"$140.80 LF
18"$158.40 LF
21"$184.80 LF
24"$211.20 LF
Force Main Cleaning
Parameter Cost Unit Notes
Force Main Rehab/Replacement 119,895$ FM
Lift Station Unit Costs
Parameter Cost Unit Notes
Low to Moderately-Low R&R 138,400$ LS
High to Moderately-High R&R 138,400$ LS City price may differ
Cost Estimate Assumptions
Renton CIP and Financial.xlsx Assumptions
City of Renton
Long-Range Wastewater Management Plan
Capital Improvement Program
Cost Estimate Assumptions
Monitoring Costs
Cost Unit Notes
I&I Micro-Monitoring 5,000$ meter/month
Depth Monitoring 2,000$ meter/month
Condition Assessment 10$ LF
Adjustment Factors Notes
City Admin 10%
Design 20%
Construction 10%
Scope Contingency 30%
Level Five Cost Estimate Disclaimer:
The cost estimates within this CIP tool are based on our perception of current conditions at the project location. This
estimate reflects our professional opinion of accurate costs at this time and is subject to change as the project design
matures. Carollo Engineers, Inc. has no control over variances in the cost of labor, materials, equipment; nor services
provided by others, contractor's means and methods of executing the work or of determining prices, competitive
bidding or market conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or
Renton CIP and Financial.xlsx Assumptions
Project ID:LS-01Project Cost (Current $):900,000$ Project Name:Project Cost (Future $):900,000$ Facility Type:Lift StationProject Timing:2020 to 2020Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LS900,000$ 900,000$ 900,000$ 900,000$ Notes on Cost Estimation:January 2021LS-01 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryLift Station RehabilitationThe Wastewater Utility operates 20 lift stations throughout the City. At this point, the City is going into the maintenance/rehabilitation phase for each of the stations. In 2016, the City completed the process of evaluating the needs for each station. The second phase of full rehabilitation of lift stations began in 2017 and will be completed in 2020. The cost for this has been reported by the City at $0.9 M in 2020.Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Lift Station RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:LS-01Project Cost (Current $):900,000$ Project Name:Project Cost (Future $):900,000$ Facility Type:Lift StationProject Timing:2020 to 2020Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Capacity:100%900,000$ 2020900,000$ 900,000$ R&R:0%-$ -$ -$ General Programmatic0%-$ -$ -$ Total Project Cost100%900,000$ 900,000$ 900,000$ Project Location:Notes:January 2021LS-01 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryLift Station RehabilitationProject ElementLift Station RehabilitationTotal Project CostSee full map on "Maps" tab.
Project ID:LS-02Project Cost (Current $):400,000$ Project Name:Project Cost (Future $):400,000$ Facility Type:Lift StationProject Timing:2020 to 2020Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1400,000$ 400,000$ 400,000$ 400,000$ Notes on Cost Estimation:January 2021LS-02 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryForcemain Rehabilitation/ReplacementThe Wastewater Utility operates lift stations that each have their own FM that delivers the flow to the gravity system. While many of the lift stations have been either rehabilitated or replaced, their FMs often times were not. In 2016, a FM evaluation was completed that prioritized FMs. The replacement and rehabilitation of FMs identified began in 2016 and will be complete in 2020. The estimated cost is $400,000 in 2020. Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Forcemain Rehabilitation/ReplacementTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:LS-02Project Cost (Current $):400,000$ Project Name:Project Cost (Future $):400,000$ Facility Type:Lift StationProject Timing:2020 to 2020Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Capacity:100%400,000$ 2020400,000$ 400,000$ R&R:0%-$ -$ -$ General Programmatic0%-$ -$ -$ Total Project Cost100%400,000$ 400,000$ 400,000$ Project Location:Notes:January 2021LS-02 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryForcemain Rehabilitation/ReplacementProject ElementForcemain Rehabilitation/ReplacementTotal Project CostSee full map on "Maps" tab.
Project ID:LS-03Project Cost (Current $):300,000$ Project Name:Project Cost (Future $):327,818$ Facility Type:Lift StationProject Timing:2023 to 2023Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1300,000$ 300,000$ 300,000$ 300,000$ Notes on Cost Estimation:January 2021LS-03 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryTelemetry UpgradeThe telemetry and control system records and stores flow rates and alarms for each lift station, which is then monitored in a Supervisory Control and Data Acquisition (SCADA) system. SCADA can then be accessed by the operations and maintenance (O&M) team, as well as engineers, to help the City monitor infrastructure. This system occasionally experiences communication and other issues that result in data errors which can be critical at times. Automatically generated reports are a benefit of the updated SCADA. It is currently anticipated that the system will be updated every five years. The cost for this has been reported by the City to be $300,000 and is planned for 2023.Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Telemetry UpgradeTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:LS-03Project Cost (Current $):300,000$ Project Name:Project Cost (Future $):327,818$ Facility Type:Lift StationProject Timing:2023 to 2023Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2023300,000$ 327,818$ Maintenance0%-$ -$ -$ Planning100%300,000$ -$ -$ Total Project Cost100%300,000$ 300,000$ 327,818$ Project Location:Notes:January 2021LS-03 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryTelemetry UpgradeProject ElementTelemetry UpgradeTotal Project CostSee full map on "Maps" tab.
Project ID:LS-04Project Cost (Current $):182,000$ Project Name:Project Cost (Future $):187,460$ Facility Type:Lift StationProject Timing:2021 to 2021Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1100,000$ 100,000$ 10,000$ 20,000$ 10,000$ 42,000$ 182,000$ 182,000$ Notes on Cost Estimation:January 2021LS-04 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryDevil's Elbow Stream Bank StudyIt is recommended that the City monitor the condition of stream banks adjacent to the Devil’s Elbow lift station and evaluate alternatives to armor the bank to protect the lift station and FM. The timing for this project is recommended to be completed in the short-term. The FM length is 506 LF with 6 inch diameter. The Level 5 AACE estimated cost for this project is $180,000 in the short-term.Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Devil's Elbow Stream Bank StudyTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:LS-04Project Cost (Current $):182,000$ Project Name:Project Cost (Future $):187,460$ Facility Type:Lift StationProject Timing:2021 to 2021Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2021182,000$ 187,460$ Maintenance0%-$ -$ -$ Planning100%182,000$ -$ -$ Total Project Cost100%182,000$ 182,000$ 187,460$ Project Location:Notes:January 2021LS-04 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryDevil's Elbow Stream Bank StudyProject ElementDevil's Elbow Stream Bank StudyTotal Project CostSee full map on "Maps" tab.
Project ID:LS-05Project Cost (Current $):1,700,000$ Project Name:Project Cost (Future $):1,700,000$ Facility Type:Lift StationProject Timing:2020 to 2020Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1P1,700,000$ 1,700,000$ ----1,700,000$ 1,700,000$ Notes on Cost Estimation:January 2021LS-05 (1 of 2)Kennydale Lakeline Sewer UpgradeTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP SummaryKennydale Lakeline Sewer UpgradeThe Kennydale Lake Line Sewer System Improvement Project will allow long-term operation of the system. This program includes design and construction of a preferred alternative: 1. Lake Line System rehabilitation and repair or 2. Replacement with Individual Lift Stations. The City has budgeted a total of $1.7 M for 2019 and $1.7 M for 2020 for a total of $3.4 M for this effort.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:LS-05Project Cost (Current $):1,700,000$ Project Name:Project Cost (Future $):1,700,000$ Facility Type:Lift StationProject Timing:2020 to 2020Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20201,700,000$ 1,700,000$ Maintenance100%1,700,000$ -$ -$ Planning0%-$ -$ -$ Total Project Cost100%1,700,000$ 1,700,000$ 1,700,000$ Project Location:Notes:January 2021LS-05 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP SummaryKennydale Lakeline Sewer UpgradeProject ElementKennydale Lakeline Sewer UpgradeCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:LS-06Project Cost (Current $):8,000,000$ Project Name:Project Cost (Future $):12,463,739$ Facility Type:Lift StationProject Timing:Long-termDeveloper Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%18,000,000$ 8,000,000$ 8,000,000$ 8,000,000$ Notes on Cost Estimation:January 2021LS-06 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryKennydale Lakeline RenewalThe Kennydale Lake Line Sewer System Evaluation identified multiple options for the replacing the system at the end of its usable life. For budgetary purposes, the least expensive option, Individual Lift Stations, for$8 M will be budgeted in the long-term. For additional details, see the 2019 Kennydale Lake Line Sewer System Evaluation Phase 2B and 3 Summary Report.Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Kennydale Lakeline RenewalTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:LS-06Project Cost (Current $):8,000,000$ Project Name:Project Cost (Future $):12,463,739$ Facility Type:Lift StationProject Timing:Long-termDeveloper Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ Long-term2,666,667$ 4,154,580$ Maintenance100%8,000,000$ Long-term2,666,667$ 4,154,580$ Planning0%-$ Long-term2,666,667$ 4,154,580$ Total Project Cost100%8,000,000$ 8,000,000$ 12,463,739$ Project Location:Notes:January 2021LS-06 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryKennydale Lakeline RenewalProject ElementKennydale Lakeline RenewalKennydale Lakeline RenewalKennydale Lakeline RenewalTotal Project CostSee full map on "Maps" tab.
Project ID:LS-07Project Cost (Current $):6,111,253$ Project Name:Project Cost (Future $):9,521,134$ Facility Type:Lift StationProject Timing:Long-termDeveloper Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%13LS138,400$ 1,799,200$ 179,920$ 359,840$ 179,920$ 755,664$ 3,274,544$ 13FM119,895$ 1,558,632$ 155,863$ 311,726$ 155,863$ 654,625$ 2,836,709$ 6,111,253$ Notes on Cost Estimation:January 2021LS-07 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryLow and Moderately-Low Risk Lift Station and FM RehabilitationThis project addresses long-term renewal needs for existing facilities. Lift stations and FMs in the moderately-low to low risk categories are recommended to be evaluated for rehabilitation in the long-term, which are listed in Table 8.4. The recommended rehabilitation is consistent with the City’s historical Lift Station rehabilitation schedule. Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Lift Station RehabilitationFM Rehabilitaton/ReplacementTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:LS-07Project Cost (Current $):6,111,253$ Project Name:Project Cost (Future $):9,521,134$ Facility Type:Lift StationProject Timing:Long-termDeveloper Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ Long-term3,274,544$ 5,101,633$ Maintenance100%6,111,253$ Long-term2,836,709$ 4,419,501$ Planning0%-$ Total Project Cost100%6,111,253$ 6,111,253$ 9,521,134$ Project Location:Notes:January 2021LS-07 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryLow and Moderately-Low Risk Lift Station and FM RehabilitationProject ElementLow and Moderately-Low Risk Lift Station and FM RehabilitationFM Rehabilitaton/ReplacementTotal Project CostSee full map on "Maps" tab.
Project ID:LS-08Project Cost (Current $):2,568,691$ Project Name:Project Cost (Future $):8,110$ Facility Type:Lift StationProject Timing:2026 to 2029Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%5LS138,400$ 692,000$ 69,200$ 138,400$ 69,200$ 290,640$ 1,259,440$ 6LF119,895$ 719,368$ 71,937$ 143,874$ 71,937$ 302,135$ 1,309,251$ 2,568,691$ Notes on Cost Estimation:January 2021LS-08 (1 of 2)Lift Station RehabilitationFM Rehabilitation/ReplacementTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryModerately-High and High Risk Lift Station and FM RehabilitationLift stations and FMs that are moderately-high to high risk are recommended for rehabilitation in the long-term, which are listed in Table 8.5. The recommended rehabilitation is consist with the City’s historical Lift Station rehabilitation schedule. These stations are the Talbot Crest, Long, Wedgewood, Devil's Elbow, and Kensington Crest. Estimated cost of lift station rehabilitation is $1.26 M in the short term and medium term and $1.31 M in the long term for a total of $2.57 M. This does not include the rehabilitation of Lake WA No. 1 and Lake WA Flush Stations.
Project ID:LS-08Project Cost (Current $):2,568,691$ Project Name:Project Cost (Future $):8,110$ Facility Type:Lift StationProject Timing:2026 to 2029Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2026642,173$ 2,026$ Maintenance100%2,568,691$ 2027642,173$ 2,027$ Planning0%-$ 2028642,173$ 2,028$ 2029642,173$ 2,029$ Total Project Cost100% 2,568,691$ 2,568,691$ 8,110$ Project Location:Notes:January 2021LS-08 (2 of 2)Lift Station RehabilitationSee full map on "Maps" tab.Total Project CostCity of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryModerately-High and High Risk Lift Station and FM RehabilitationProject ElementLift Station RehabilitationLift Station RehabilitationLift Station Rehabilitation
Project ID:Project Cost (Current $):-$ Project Name:Project Cost (Future $):-$ Facility Type:PipeProject Timing:Long-termDeveloper Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):1.82City Admin Design Construction Scope Contingency10%20% 10%30%1,432LF330$ 472,560$ 47,256$ 94,512$ 47,256$ 198,475.20$ 860,059$ 31,289LF341$ 10,669,549$ 1,066,955$ 2,133,910$ 1,066,955$ 4,481,210.58$ 19,418,579$ 1,759LF352$ 619,168$ 61,917$ 123,834$ 61,917$ 260,050.56$ 1,126,886$ 5,890LF363$ 2,138,070$ 213,807$ 427,614$ 213,807$ 897,989.40$ 3,891,287$ 2,490LF374$ 931,260$ 93,126$ 186,252$ 93,126$ 391,129.20$ 1,694,893$ 5,316LF385$ 2,046,660$ 204,666$ 409,332$ 204,666$ 859,597.20$ 3,724,921$ 2,151LF396$ 851,796$ 85,180$ 170,359$ 85,180$ 357,754.32$ 1,550,269$ 3,909LF407$ 1,590,963$ 159,096$ 318,193$ 159,096$ 668,204.46$ 2,895,553$ 7,590LF53$ 400,752$ 40,075$ 80,150$ 40,075$ 168,315.84$ 729,369$ 123,932LF70$ 8,724,778$ 872,478$ 1,744,956$ 872,478$ 3,664,406.59$ 15,879,095$ 11,354LF88$ 999,108$ 99,911$ 199,822$ 99,911$ 419,625.36$ 1,818,377$ 14,238LF106$ 1,503,480$ 150,348$ 300,696$ 150,348$ 631,461.60$ 2,736,334$ 297LF123$ 36,590$ 3,659$ 7,318$ 3,659$ 15,367.97$ 66,595$ 7,475LF141$ 1,052,480$ 105,248$ 210,496$ 105,248$ 442,041.60$ 1,915,514$ 4,169LF158$ 660,290$ 66,029$ 132,058$ 66,029$ 277,321.97$ 1,201,729$ 2,921LF185$ 539,708$ 53,971$ 107,942$ 53,971$ 226,677.53$ 982,269$ 5,179LF211$ 1,093,699$ 109,370$ 218,740$ 109,370$ 459,353.66$ 1,990,533$ 2,935LF10$ 29,350$ 2,935$ 5,870$ 2,935$ 12,327.00$ 53,417$ 34,360,262$ 62,535,677$ 29,964,658$ 2025 - 20393,535,711.79$ 53,035,677$ Notes on Cost Estimation:1,997,643.84$ 3,535,711.79$ 24" High Risk Gravity Sewer Rehabilitation12" High Risk Gravity Sewer Rehabilitation14" High Risk Gravity Sewer Rehabilitation16: High Risk Gravity Sewer Rehabilitation18" High Risk Gravity Sewer RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryRehabilitation ProgramThis project is used to identify the annual cost of the Sanitary Sewer Main Replacement and Rehabilitation Program on spreadsheets P-06 to P-08.Total Cost (Current $)8" High Risk Gravity Sewer Rehabilitation10" High Risk Gravity Sewer Rehabilitation6" High Risk Gravity Sewer RehabilitationProject Element Quantity UnitUnit Cost ($/Unit)Subtotal6" Moderately-High Risk Gravity Sewer Rehabilitation14" Moderately-High Risk Gravity Sewer RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab. 50% of moderately-high risk pipes and 100% of high risk pipes are estimated to be replaced.Go to Assumptions Tab8" Moderately-High Risk Gravity Sewer Rehabilitation10" Moderately-High Risk Gravity Sewer Rehabilitation12" Moderately-High Risk Gravity Sewer Rehabilitation16" Moderately-High Risk Gravity Sewer Rehabilitation18" Moderately-High Risk Gravity Sewer Rehabilitation24" Moderately-High Risk Gravity Sewer Rehabilitation21" Moderately-High Risk Gravity Sewer RehabilitationGravity Sewer Condition Assessment
Project ID:Project Cost (Current $):-$ Project Name:Project Cost (Future $):-$ Facility Type:PipeProject Timing:Long-termDeveloper Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ Maintenance100%62,535,677$ Planning0%-$ Total Project Cost100%62,535,677$ -$ -$ Project Location:Notes:January 2021Total Project CostCity of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryRehabilitation ProgramProject ElementSee full map on "Maps" tab.
Project ID:P-01Project Cost (Current $):1,500,000$ Project Name:Project Cost (Future $):1,500,000$ Facility Type:PipeProject Timing:2020 to 2020Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LF1,500,000$ 1,500,000$ 1,500,000$ 1,500,000$ Notes on Cost Estimation:January 2021P-01 (1 of 2)2020 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)This is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects. Similar to FMs and lift stations, a vulnerability and criticality analysis was conducted. RUL was determined for different pipe materials. For the CIP, pipes with RUL greater than 20 years were not considered. In order to confirm the condition of individual pipe’s RUL, the City should conduct ongoing monitoring through CCTV inspections and tracking of point repairs and other maintenance issues. If the pipe has higher criticality or vulnerability, then a more advanced condition assessment may be required. This may include CCTV inspection, soil resistivity testing, pipe couponing, and other types of pipeline studies.City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP Summary2020 Sanitary Sewer Main Replacement/Rehabilitation
Project ID:P-01Project Cost (Current $):1,500,000$ Project Name:Project Cost (Future $):1,500,000$ Facility Type:PipeProject Timing:2020 to 2020Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20201,500,000$ 1,500,000$ Maintenance100%1,500,000$ -$ -$ General0%-$ -$ -$ Total Project Cost100%1,500,000$ 1,500,000$ 1,500,000$ Project Location:Notes:January 2021P-01 (2 of 2)See full map on "Maps" tab.Total Project Cost2020 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP Summary2020 Sanitary Sewer Main Replacement/RehabilitationProject Element
Project ID:P-02Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,060,000$ Facility Type:PipeProject Timing:2021 to 2021Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LF2,000,000$ 2,000,000$ 2,000,000$ 2,000,000$ Notes on Cost Estimation:January 2021P-02 (1 of 2)2021 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2021 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects. City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-02Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,060,000$ Facility Type:PipeProject Timing:2021 to 2021Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20212,000,000$ 2,060,000$ Maintenance100%2,000,000$ -$ -$ General0%-$ -$ -$ Total Project Cost100%2,000,000$ 2,000,000$ 2,060,000$ Project Location:Notes:January 2021P-02 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP Summary2021 Sanitary Sewer Main Replacement/RehabilitationProject Element2021 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-03Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,121,800$ Facility Type:PipeProject Timing:2022 to 2022Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LF2,000,000$ 2,000,000$ 2,000,000$ 2,000,000$ Notes on Cost Estimation:January 2021P-03 (1 of 2)2022 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2022 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-03Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,121,800$ Facility Type:PipeProject Timing:2022 to 2022Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20222,000,000$ 2,121,800$ Maintenance100%2,000,000$ -$ -$ General0%-$ -$ -$ Total Project Cost100%2,000,000$ 2,000,000$ 2,121,800$ Project Location:Notes:January 2021P-03 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP Summary2022 Sanitary Sewer Main Replacement/RehabilitationProject Element2022 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-04Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,185,454$ Facility Type:PipeProject Timing:2023 to 2023Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LF2,000,000$ 2,000,000$ 2,000,000$ 2,000,000$ Notes on Cost Estimation:January 2021P-04 (1 of 2)2023 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2023 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-04Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,185,454$ Facility Type:PipeProject Timing:2023 to 2023Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20232,000,000$ 2,185,454$ Maintenance100%2,000,000$ -$ -$ General0%-$ -$ -$ Total Project Cost100%2,000,000$ 2,000,000$ 2,185,454$ Project Location:Notes:January 2021P-04 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP Summary2023 Sanitary Sewer Main Replacement/RehabilitationProject Element2023 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-05Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,251,018$ Facility Type:PipeProject Timing:2024 to 2024Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LF2,000,000$ 2,000,000$ 2,000,000$ 2,000,000$ Notes on Cost Estimation:January 2021P-05 (1 of 2)2024 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2024 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-05Project Cost (Current $):2,000,000$ Project Name:Project Cost (Future $):2,251,018$ Facility Type:PipeProject Timing:2024 to 2024Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20242,000,000$ 2,251,018$ Maintenance100%2,000,000$ -$ -$ General0%-$ -$ -$ Total Project Cost100%2,000,000$ 2,000,000$ 2,251,018$ Project Location:Notes:January 2021P-05 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP Summary2024 Sanitary Sewer Main Replacement/RehabilitationProject Element2024 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-06Project Cost (Current $):3,535,712$ Project Name:Project Cost (Future $):4,098,859$ Facility Type:PipeProject Timing:2025 to 2025Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1LF2,000,000$ 2,000,000$ 3,535,712$ 3,535,712$ Notes on Cost Estimation:January 2021P-06 (1 of 2)2025 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)These unit costs were calculated annually in the 'Rehabilitation Program' spreadsheet.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2025 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-06Project Cost (Current $):3,535,712$ Project Name:Project Cost (Future $):4,098,859$ Facility Type:PipeProject Timing:2025 to 2025Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20253,535,712$ 4,098,859$ Maintenance100%3,535,712$ -$ -$ General0%-$ -$ -$ Total Project Cost100%3,535,712$ 3,535,712$ 4,098,859$ Project Location:Notes:January 2021P-06 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP Summary2025 Sanitary Sewer Main Replacement/RehabilitationProject Element2025 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-07Project Cost (Current $):14,142,847$ Project Name:Project Cost (Future $):17,662,540$ Facility Type:PipeProject Timing:2026 to 2029Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%43,535,712$ 14,142,847.16$ 14,142,847$ 14,142,847$ Notes on Cost Estimation:January 2021P-07 (1 of 2)2026-2029 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)These unit costs were calculated annually in the 'Rehabilitation Program' spreadsheet.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2026-2029 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-07Project Cost (Current $):14,142,847$ Project Name:Project Cost (Future $):17,662,540$ Facility Type:PipeProject Timing:2026 to 2029Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 20263,535,712$ 4,221,825$ Maintenance100%14,142,847$ 20273,535,712$ 4,348,480$ General0%-$ 20283,535,712$ 4,478,934$ 20293,535,712$ 4,613,302$ Total Project Cost100%14,142,847$ 14,142,847$ 17,662,540$ Project Location:Notes:January 2021P-07 (2 of 2)2026-2029 Sanitary Sewer Main Replacement/RehabilitationSee full map on "Maps" tab.Total Project CostGo to CIP Summary2026-2029 Sanitary Sewer Main Replacement/RehabilitationProject Element2026-2029 Sanitary Sewer Main Replacement/Rehabilitation2026-2029 Sanitary Sewer Main Replacement/Rehabilitation2026-2029 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-08Project Cost (Current $):35,357,118$ Project Name:Project Cost (Future $):55,085,238$ Facility Type:PipeProject Timing:Long-termDeveloper Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%103,535,712$ 35,357,117.89$ 35,357,118$ 35,357,118$ Notes on Cost Estimation:January 2021P-08 (1 of 2)2030-2039 Sanitary Sewer Main Replacement/RehabilitationTotal Project Cost (Current $)These unit costs were calculated annually in the 'Rehabilitation Program' spreadsheet.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary2030-2039 Sanitary Sewer Main Replacement/RehabilitationThis is an annual program that is performed to identify and either repair, rehabilitate, or replace portions of sewer pipe that do not meet current standards. The program will be city-wide and may consist of individual projects.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-08Project Cost (Current $):35,357,118$ Project Name:Project Cost (Future $):55,085,238$ Facility Type:PipeProject Timing:Long-termDeveloper Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ Long-term35,357,118$ 55,085,238$ Maintenance100%35,357,118$ General0%-$ Total Project Cost100%35,357,118$ 35,357,118$ 55,085,238$ Project Location:Notes:January 2021P-08 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP Summary2030-2039 Sanitary Sewer Main Replacement/RehabilitationProject Element2030-2039 Sanitary Sewer Main Replacement/RehabilitationCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-09Project Cost (Current $):5,808,763$ Project Name:Project Cost (Future $):6,257,687$ Facility Type:PipeProject Timing:2021 to 2024Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%386LF363$ 140,118$ 14,012$ 28,024$ 14,012$ 58,849.56$ 255,015$ 42LF385$ 16,170$ 1,617$ 3,234$ 1,617$ 6,791.40$ 29,429$ 1,718LF363$ 623,634$ 62,363$ 124,727$ 62,363$ 261,926.28$ 1,135,014$ 3,278LF363$ 1,189,914$ 118,991$ 237,983$ 118,991$ 499,763.88$ 2,165,643$ 73LF385$ 28,105$ 2,811$ 5,621$ 2,811$ 11,804.10$ 51,151$ 843LF341$ 287,463$ 28,746$ 57,493$ 28,746$ 120,734.46$ 523,183$ 50LF385$ 19,250$ 1,925$ 3,850$ 1,925$ 8,085.00$ 35,035$ 240LF341$ 81,840$ 8,184$ 16,368$ 8,184$ 34,372.80$ 148,949$ 100LF363$ 36,300$ 3,630$ 7,260$ 3,630$ 15,246.00$ 66,066$ 1,477LF352$ 519,904$ 51,990$ 103,981$ 51,990$ 218,359.68$ 946,225$ 447LF341$ 152,427$ 15,243$ 30,485$ 15,243$ 64,019.34$ 277,417$ 283LF341$ 96,503$ 9,650$ 19,301$ 9,650$ 40,531.26$ 175,635$ 5,808,763$ Notes on Cost Estimation:January 2021P-09 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramSewer Capacity ImprovementsPipe upsizing is determined after the pipe was monitored, the most cost effective solution for these pipes are to increase their size. Since a larger pipe would need to be installed, the construction is estimated with open-cut installation. Additionally, the pipe reconfiguration includes locations where the pipe has a reverse slope causing a deficiency in the system. After confirmation that the slope information is accurate, pipe replacement is the recommended action. For pipe replacement, it would involve open cut construction. Locations include the following sections: Edmonds Ave and NE 9th St, Monroe Ave and NE 7th St, Grant Ave and SE 9th St, SE 99th Ct, and Jericho Pl and NE 16th St.Unit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP Summary46A - 8" to 12" Diameter Pipe46A - 12" to 16" Diameter PipeTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab24A: 8" Monroe Ave and NE 7th St Reconfiguration24A: 12" Monroe Ave and NE 7th St Reconfiguration11A: 10" Grant Ave and Se 9th St Reconfiguration20A: 8" SE 99th Ct Reconfiguration20B: 8" Jericho Pl and NE 16th St ReconfigurationProject Element Quantity Unit37A: 8" Edmonds Ave and NE 9th St Reconfiguration37A: 16" Edmonds Ave and NE 9th St Reconfiguration23A - 8" to 12" Diameter Pipe23A - 12" to 16" Diameter PipeBA - 8" to 12" Diameter Pipe
Project ID:P-09Project Cost (Current $):5,808,763$ Project Name:Project Cost (Future $):6,257,687$ Facility Type:PipeProject Timing:2021 to 2024Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category100%5,808,763$ 20211,452,191$ 1,495,756$ Maintenance0%-$ 20221,452,191$ 1,540,629$ Planning0%-$ 20231,452,191$ 1,586,848$ 20241,452,191$ 1,634,453$ Total Project Cost100%5,808,763$ 5,808,763$ 6,257,687$ Project Location:Notes:January 2021P-09 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramSewer Capacity ImprovementsProject ElementSewer Capacity ImprovementsSewer Capacity ImprovementsSewer Capacity ImprovementsGo to CIP SummarySewer Capacity ImprovementsTotal Project CostSee full map on "Maps" tab.
Project ID:P-10Project Cost 1,201,200$ Project Name:Project Cost (Future $):1,329,855$ Facility Type:PipeProject Timing:2022 to 2026Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):Project ElementNo. Dur.10% 20% 10% 30%05A - Talbot Rd S and 36th St to 27th Place160Meter/Mo20,000$ 95,000$ 9,500$ 19,000$ 9,500$ 39,900$ 172,900$ 22A - Whitman Ct NE and NE 12th St224Meter/Mo20,000$ 70,000$ 7,000$ 14,000$ 7,000$ 29,400$ 127,400$ 21A - Anacortes Ave NE and NE 17th to NE 26th St260Meter/Mo20,000$ 115,000$ 11,500$ 23,000$ 11,500$ 48,300$ 209,300$ 41A: Lake Washington Blvd and 32nd to 36th St160Meter/Mo20,000$ 95,000$ 9,500$ 19,000$ 9,500$ 39,900$ 172,900$ 15A - Renton High School1 60 Meter/Mo 20,000$ 95,000$ 9,500$ 19,000$ 9,500$ 39,900$ 172,900$ 14A160Meter/Mo20,000$ 95,000$ 9,500$ 19,000$ 9,500$ 39,900$ 172,900$ 48A1 60 Meter/Mo 20,000$ 95,000$ 9,500$ 19,000$ 9,500$ 39,900$ 172,900$ 1,201,200$ Notes on Cost Estimation:January 2021P-10 (1 of 2)Go to CIP SummaryFlow Monitoring ProgramThe additional long-term depth monitoring project is to verify the existence of a deficiency in the specified pipe. These locations have typically not been observed deficient, so additional monitoring over a specified period of time to observe deficiency is recommended. The Talbot Rd S and 36th St to 27th Place location is recommended for monitoring for at most 5 years to determine potential deficiency.The Whitman Ct NE and NE 12th location is recommended for monitoring for a maximum of 2 years to determine potential deficiency. The Anacortes Ave NE and NE 17th St to NE 26th St location is recommended for monitoring for a maximum of 1 year to determine potential deficiency. The Renton High School location is recommended for monitoring for a maximum of 1 year to determine potential deficiency. Altogether, the flow and monitoring program timing will be short, medium, and long-term.City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab. 20k for initial meter installation. 15k/yr/meter for service/analysisGo to Assumptions TabUnitsSubtotalTotal Cost (Current $)Design ConstructionScope ContingencyQuantityMeterUnit CostCity Admin
Project ID:P-10Project Cost (Current $):1,201,200$ Project Name:Project Cost (Future $):1,329,855$ Facility Type:PipeProject Timing:2022 to 2026Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category100%1,201,200$ Flow Monitoring Program2022278,460$ 278,460$ Maintenance0%-$ 2023278,460$ 304,281$ Planning0%-$ 2024214,760$ 241,714$ 2025214,760$ 248,966$ 2026214,760$ 256,435$ Total Project Cost100%1,201,200$ 1,201,200$ 1,329,855$ Project Location:Notes:See full map January 2021P-10 (2 of 2)Flow Monitoring ProgramGo to CIP SummaryFlow Monitoring ProgramProject ElementFlow Monitoring ProgramFlow Monitoring ProgramCity of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramFlow Monitoring ProgramTotal Project Cost
Project ID:P-11Project Cost (Current $):1,674,400$ Project Name:Project Cost (Future $):2,088,480$ Facility Type:Project Timing:2022 to Long-termDeveloper Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope ContingencyNo. Dur.10% 20% 10% 30%Basin Monitoring (8 Basins245Meters/Mo120,000$ 600,000$ 60,000$ 120,000$ 60,000$ 252,000$ 1,092,000$ Basin Study8Meters/Mo40,000$ 320,000$ 32,000$ 64,000$ 32,000$ 134,400$ 582,400$ 1,674,400$ Notes on Cost Estimation:January 2021P-11 (1 of 2)Total Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab. 5k/meter/month for evaluation and 40k per basin for the studyGo to Assumptions TabUnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)QuantityMeterProject ElementGo to CIP SummaryI/I Evaluation ProgramMicro-monitoring project is recommended for areas in wastewater basins where there were signs of significant I/I in the collection system. Micro-monitoring involved installing multiple flow monitors where there is high I/I, and break larger basins into smaller basis to better refine the location of high I/I. By micro-monitoring, an isolated location within the basin would be identified and only this section would need to be replaced. Locations include S Renton Village Pl from Valley Fwy to Talbot Rd S, Lake Ave S to 15th St, Benson Rd S to S Eagle Dr., and Jones Dr SE to SE 18th Pl as one project element of I/I Micro-Monitoring. Additionally Lake Washington Blvd and 32nd to 36th St are recommended for monitoring.PipeCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:P-11Project Cost (Current $):1,674,400$ Project Name:Project Cost (Future $):2,088,480$ Facility Type:PipeProject Timing:2022 to Long-termDeveloper Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category100%1,674,400$ 2022682,500$ 724,064$ Maintenance0%-$ Long-term409,500$ 637,988$ Planning0%-$ 2022364,000$ 386,168$ Long-term218,400$ 340,260$ Total Project Cost100%1,674,400$ 1,674,400$ 2,088,480$ Project Location:Notes:January 2021P-11 (2 of 2)Total Project CostSee full map on "Maps" tab.Long Term StudyShort Term StudyGo to CIP SummaryI/I Evaluation ProgramProject ElementShort Term I/I EvalLong Term I/I EvalCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:G-01Project Cost (Current $):300,000$ Project Name:Project Cost (Future $):300,000$ Facility Type:GeneralProject Timing:2020 to 2020Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1600,000$ 600,000$ 600,000$ 600,000$ Notes on Cost Estimation:January 2021G-01 (1 of 2)Wastewater Operations Master PlanTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab. Half of Master Plan total cost is distributed to 2019 which is prior to the CIP planning period.Go to Assumptions TabProject Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Go to CIP SummaryWastewater Operations Master PlanThe Wastewater Operations Master Plan (OMP) is a plan created by the City. The first purpose of this plan is to document current procedures and programs into an O&M manual, review existing programs for effectiveness and compliance of potential future regulatory requirements. The second purpose is to analyze and recommend program improvements in accordance with the City’s long-term goals and objectives, and assist with the development of an improvement implementation strategy. Based on the City’s existing resources and implementation budget, it is recommended to implement this plan over 5 years, with the highest priority improvements being completed first.City of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:G-01Project Cost (Current $):300,000$ Project Name:Project Cost (Future $):300,000$ Facility Type:GeneralProject Timing:2020 to 2020Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2020300,000$ 300,000$ Maintenance0%-$ -$ -$ Planning100%600,000$ -$ -$ Total Project Cost100%600,000$ 300,000$ 300,000$ Project Location:Notes:January 2021G-01 (2 of 2)See full map on "Maps" tab.Total Project CostGo to CIP SummaryWastewater Operations Master PlanProject ElementWastewater Operations Master PlanCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:G-02Project Cost (Current $):300,000$ Project Name:Project Cost (Future $):337,653$ Facility Type:GeneralProject Timing:2024 to 2024Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1300,000$ 300,000$ 300,000$ 300,000$ Notes on Cost Estimation:January 2021G-02 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryLong-Range Wastewater Management PlanThe Long Range Wastewater Management Plan considers a 20-year planning period for the analysis of existing and projected conditions. The sewage collection system’s operational and capital requirements are detailed to achieve the City’s operational goals and fulfill regulatory requirements. Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Long Range Wastewater Management PlanTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:G-02Project Cost (Current $):300,000$ Project Name:Project Cost (Future $):337,653$ Facility Type:GeneralProject Timing:2024 to 2024Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2024300,000$ 337,653$ Maintenance0%-$ -$ -$ Planning100%300,000$ -$ -$ Total Project Cost100%300,000$ 300,000$ 337,653$ Project Location:Notes:January 2021G-02 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummaryLong-Range Wastewater Management PlanProject ElementLong Range Wastewater Management PlanTotal Project CostSee full map on "Maps" tab.
Project ID:G-03Project Cost (Current $):600,000$ Project Name:Project Cost (Future $):627,270$ Facility Type:GeneralProject Timing:2021 to 2022Developer Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%1600,000$ 600,000$ 600,000$ 600,000$ Notes on Cost Estimation:January 2021G-03 (1 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummarySanitary Sewer Hydraulic ModelAs discussed in Chapter 7 in the System Infrastructure Capacity, the City has a hydraulic model that allows them to evaluate existing the sanitary sewer system and determine areas of capacity constraint, and provide a tool for planning future improvements. The model needs to be updated as the system expands, and flow monitoring and physical system data is collected by survey or field inspection.Project Element Quantity UnitUnit Cost ($/Unit)SubtotalTotal Cost (Current $)Sanitary Sewer Hydraulic ModelTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions Tab
Project ID:G-03Project Cost (Current $):600,000$ Project Name:Project Cost (Future $):627,270$ Facility Type:GeneralProject Timing:2021 to 2022Developer Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2021300,000$ 309,000$ Maintenance0%-$ 2022300,000$ 318,270$ Planning100%600,000$ -$ -$ Total Project Cost100%600,000$ 600,000$ 627,270$ Project Location:Notes:January 2021G-03 (2 of 2)City of RentonLong-Range Wastewater Master PlanCapital Improvement ProgramGo to CIP SummarySanitary Sewer Hydraulic ModelProject ElementSanitary Sewer Hydraulic ModelSanitary Sewer Hydraulic ModelTotal Project CostSee full map on "Maps" tab.
Project ID:G-04Project Cost (Current $):600,000$ Project Name:Project Cost (Future $):5,408,711$ Facility Type:GeneralProject Timing:2020 to Long-termDeveloper Share:Inflation Rate:3%Project Description:Project Cost Estimate (Current $):City Admin Design ConstructionScope Contingency10% 20% 10% 30%20200,000$ 4,000,000$ 4,000,000$ 4,000,000$ Notes on Cost Estimation:January 2021G-04 (1 of 2)Miscellaneous/Emergency ProjectsTotal Project Cost (Current $)Based on the pipe cost per linear foot assumptions found on the "Assumptions" tab.Go to Assumptions TabTotal Cost (Current $)Go to CIP SummaryMiscellaneous/Emergency ProjectsThis project is to perform small repairs, replacements, or installations of sewers that are not scheduled in the CIP, but become a priority due to unexpected problems, failures, or coordination with other projects.Project ElementQuantity UnitUnit Cost ($/Unit)SubtotalCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program
Project ID:G-04Project Cost (Current $):600,000$ Project Name:Project Cost (Future $):5,408,711$ Facility Type:GeneralProject Timing:2020 to Long-termDeveloper Share:0Inflation Rate:3%Cost Allocation:Project Timing:Project TypePercent CostTimingProject Cost (Current $)Project Cost (Future $)Cross Category0%-$ 2020200,000$ 200,000$ Maintenance0%-$ 2021200,000$ 206,000$ Planning100%4,000,000$ 2022200,000$ 212,180$ 2023200,000$ 218,545$ 2024200,000$ 225,102$ 2025200,000$ 231,855$ 2026200,000$ 238,810$ 2027200,000$ 245,975$ 2028200,000$ 253,354$ 2029200,000$ 260,955$ Long-term2,000,000$ 3,115,935$ Total Project Cost100%4,000,000$ 600,000$ 5,408,711$ Project Location:Notes:January 2021G-04 (2 of 2)Miscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsSee full map on "Maps" tab.Miscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsTotal Project CostGo to CIP SummaryMiscellaneous/Emergency ProjectsProject ElementMiscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsMiscellaneous/Emergency ProjectsCity of RentonLong-Range Wastewater Master PlanCapital Improvement Program