City of Renton
RE: Construction Mitigation Description for Cedar River Apartments
Proposed Construction Dates:
• The Cedar River Apartments project will have an aggressive construction schedule and
be built in phases. Those phased dates are listed below, but are dependent on building
permit issuance.
o Phase 1 Start 09-03-2019 Completed 08-11-2021
o Phase 2 Start 08-21-2021 Completed 04-12-2023
o Phase 3 Start 04-12-2023 Complete 05-13-2024
Hours and Days of Operation:
• Hours and days of construction will follow the City of Renton standard.
o Monday – Friday 7am – 8pm
o Saturday (if needed) 9am – 10pm
Proposed Hauling and Transportation Route:
• Truck routes to and from the site for all major phases will be from Interstate 405 via Exit
#4 to the Site: Trucks will take exit 4 and drive East on the Maple Valley Highway,
Right on Cedar River Park Dr until they arrive at the site. From the site: Turn right on
Cedar River Park Dr, turn left on Maple Valley Highway, which will lead to Interstate
405.
Measures to Minimize Construction Impact Characteristics:
• COR and Ecology approved erosion control BMP’s such as stabilized construction
entrances, perimeter silt fence, catch basin inlet protection, site watering to control dust,
and street sweeper as necessary to clean up dust or mud.
• The contractor will submit a traffic control plan for City approval prior to the start of
construction.
• Construction vehicles will park on-site to eliminate the impact of worker parking on the
surrounding neighborhood. The site will also be fully fenced (to aid in controlling
construction traffic egress/ingress).
• All equipment will be kept in good working order and have limited idling to minimize
noise impacts.
Special Hours Proposed for Construction / Hauling:
• There are no planned special hours for construction or hauling at this time. But may be
required for work on adjacent arterial right-of-ways.
Preliminary Traffic Control Plans:
• The contractor will submit a traffic control plan for City approval prior to the start of
construction.
Use of Cranes:
• The mixed-use buildings will utilize cranes. Crane height and placement will be
permitted as part of the mixed-use building permits.