CITY OF RENTON
AGENDA - Committee of the Whole Meeting
6:00 PM - Monday, June 21, 2021
Videoconference
1. WSDOT/SOUND TRANSIT - I-405 BRT CORRIDOR UPDATE
a) WSDOT Presentation
b) Sound Transit Presentation
Currently, due to the spread of COVID-19, all regularly-scheduled committee meetings will be held as
necessary via video-conference. City Hall is closed to the public.
If you would like to attend this week's meeting remotely, you can do so by going to
https://us02web.zoom.us/j/86753290028?pwd=M2pOc09HWWNrY05uVnlIWnpGS1E4UT09
Zoom Meeting ID: 867 5329 0028, Passcode: 881839
You can call through Zoom at (253) 215-8782 and use the Meeting ID.
City of Renton
June 21, 2021
I-405 Renton to Bellevue Widening and
Express Toll Lanes Project
Lisa Hodgson, P.E., DBIA
I-405/SR 167 Program Administrator AGENDA ITEM #1. a)
Agenda
•I-405 Renton to Bellevue Widening and Express Toll Lanes
Project: Project Update
•I-405/SR 167 Corridor Update: Legislative Direction
–Program delivery schedule
–Financial assumptions, risks and results
–Legislative Provisos
•Discussion
2AGENDA ITEM #1. a)
3
Project award and goals
Design-build contract awarded August
2019 to Flatiron/Lane Joint Venture.
1.M i n i m i z e i m p a c t s
2.C o l l a b o r a t i on
3.S m o o t h t o l l s ys t e m r o l l o u t
4.E f f e c t i v e s t a r t -u p a n d c l o s e -
o u t , a n d Q u a l i t y M a n a g e m e n t AGENDA ITEM #1. a)
Northeast 44th Street Interchange
4AGENDA ITEM #1. a)
5
Conceptual design
AGENDA ITEM #1. a)
6
Updated design
AGENDA ITEM #1. a)
Current Northeast 44th Street work
7AGENDA ITEM #1. a)
Cedar Avenue and Renton Avenue bridges
8AGENDA ITEM #1. a)
Renton Hill Bridges
9
•Cedar Avenue bridge
remains in place
•Renton Avenue bridge
will be modified
o Reduces single-
bridge-only access
by 300 days
o Preliminary
scheduled for 2022
•Bridges receive updated
aesthetic treatments
N
Renton Ave. S
Cedar Ave. S AGENDA ITEM #1. a)
Bridge Highway View
10
Existing With aesthetic enhancements
AGENDA ITEM #1. a)
Bridge Street View
11
Existing With aesthetic enhancements
AGENDA ITEM #1. a)
12
Schedule
AGENDA ITEM #1. a)
I-405/SR 167 Corridor Update
13AGENDA ITEM #1. a)
Projects funded through bonded toll revenues
2019 (ESSB 5825)
1)I-405, SR 522 to SR 527 Express Toll Lanes
Improvement Project (design and construction) -
$600M
2)I-405 Renton to Bellevue Widening and Express
Toll Lanes Project (completion) -$215M
3)SR 167 Master Plan Update -$3M
4)SR 167 Express Toll Lanes Extension to SR 410
and SR 512 (construction) -$100M
5)I-405/North 8th Street Direct Access Ramp Project
in Renton (design) -$20M
2021 (SSB 5165)
1)I-405, SR 522 to SR 527 Express Toll Lanes
Improvement Project (design/construction) -$600M
2)I-405 Renton to Bellevue Widening and Express Toll
Lanes Project (completion) -$215M
3)SR 167 Master Plan Update -$3M
4)SR 167 Express Toll Lanes Extension to SR 410 and
SR 512 (construction) -$100M
5)I-405/North 8th Street Direct Access Ramp Project
$20M (design) + $230 (design/construction)
6)NE 85th Street Inline Station -$10M (toll infrastructure)
14
Total: $938M-$1.16B Total: $1.178B
It is the intent of the legislature to provide construction
funding for this project at a later date AGENDA ITEM #1. a)
What has happened since 2019?
Addressing our challenges
•Project changes since 2019 (ESSB 5825)
•Traffic and revenue is down
•Project delivery schedules are affected
•System management needs
•Multiple variables that influence project financing
15AGENDA ITEM #1. a)
I-405/SR 167 actual revenue
compared to pre-COVID forecast
16AGENDA ITEM #1. a)
17
*Dashed lines represent changes related
to the Current Law Budget
AGENDA ITEM #1. a)
Sec. 306: SR 522 to SR 527
Explore phasing and funding alternatives
18
Substitute Senate Bill 5165, Section 306 (9)(b)
For the Department of Transportation –Improvements, Program I
The department may advance the I-405/SR 522 to I-5 Capacity
Improvements project (L2000234) and construct the project earlier
than is scheduled in the LEAP transportation document referenced in
subsection (2) of this section of additional funding is identified and
submitted through the existing unanticipated receipts process by
September 1, 2021. The department and state treasurer shall pursue
alternatives to toll revenue funding including but not limited to federal
loan and grant programs. The department shall explore phasing and
modifying the project to attempt to align project completion with the
anticipated deployment of bus rapid transit on the corridor in the 2023-
2025 biennium. The department shall report back to the transportation
committees of the legislature on this work by September 15, 2021.
▪May advance and construct
earlier than is scheduled if
funding is identified and
submitted by Sept. 1, 2021.
▪Shall pursue alternatives to
toll revenue funding.
▪Shall explore phasing and
modifying the project.
▪Report to the Legislature by
Sept. 15, 2021. AGENDA ITEM #1. a)
Alternative finance/funding sources
Funding gap is $360 -$400M
•Loans
–TIFIA and Garvee
–State loans
•New Revenue/Grants
–State
•2022 Supplemental Budget
•New Revenue Pkg.
–Federal
•Received ARPA
•Surface Transportation
Reauthorization
•Other considerations
–Sales tax deferral
–Alternative funds
–WSTC Toll Rate Policy
–Bonding climate
19AGENDA ITEM #1. a)
Sec. 209: I-405/SR 167 corridor
Submit a bond proceeds corridor plan
20
Substitute Senate Bill 5165, Section 209 (8)
For the Department of Transportation –Toll Operations and
Maintenance, Program B
The department shall submit a plan to the legislature for the Interstate
405 and state route number 167 express toll lanes account detailing
how bond proceeds can cover the proposed construction plan on the
Interstate 405 and state route number 167 express toll lane corridor
outlined on LEAP Transportation Document 2021-1 as developed
April 23, 2021, by January 1, 2022.
▪Submit a plan detailing
how bond proceeds can
cover the proposed
construction plan from
the 2021-23
transportation budget.
▪Report to the Legislature
by Jan. 1, 2022.AGENDA ITEM #1. a)
EAG engagement opportunities
21
EAG:
Discuss policy
framework &
identify needs
Today
IWG:
Review initial
funding &
phasing
options
July
EAG:
Review refined
funding &
phasing
options before
Sept. 15
submittal
August
EAG:
Review plan
before Jan. 1
submittal
Fall
AGENDA ITEM #1. a)
22
Questions?AGENDA ITEM #1. a)
Capital Program Realignment &
I-405 Bus Rapid Transit
Renton City Council
June 21, 2021 AGENDA ITEM #1. b)
2
What we’ll cover today
•Discuss recession’s impact on revenues and project costs
•Outline the 2021 realignment process to adjust project plans and
schedules.
•Sound Transit I-405 BRT Project Update & Refinements
AGENDA ITEM #1. b)
Program Realignment
AGENDA ITEM #1. b)
4
What is realignment?
A required response to estimated shortfalls
•The Board responds to estimated affordability gaps by
‘realigning’ the financial plan to balance costs and
revenue.
•Options include cutting costs, raising new revenues,
and/or delaying or phasing projects.AGENDA ITEM #1. b)
5
Financial changes
Current 25 -year capital program runs 2016 -2041
•The Sound Transit Board is required to maintain an
affordable financial plan, defined as not exceeding debt
capacity within a 25-year planning horizon.
•Lower revenue: The COVID recession will reduce
revenue by an estimated $1.5 billion.
•Higher costs: estimated $6.4 billion.
•Total estimated affordability gap of $7.9 billion.AGENDA ITEM #1. b)
Scenarios
AGENDA ITEM #1. b)
7
Scenario 1: Hybrid -Integrated Network -Subarea Equity
Tier 1
≤ 2 years delay
Tier 2
≤ 6 years delay
Tier 3
≤ 9 years
delay
Tier 4
10+ years delay
System
Bus Base North (2025)
OMF South (2030)
OMF North (2035)
2nd DSTT (2037)
Sounder Maint. Base (2036)
ST2 Bus Base (2036)
Bus-on-Shoulder (2034)
North Lynnwood-Mariner NP (2038) Mariner-Everett NP (2041)Everett Link Parking (2046)
Edmonds &Mukilteo (2034)
East 405 Stride South NP (2026)
405 Stride North NP (2026)
522 Stride NP (2029)
S. Kirk.–Issaquah NP (2046)
405/522 Stride Parking (2034)
S. Kirk–Issaquah Parking (2051)
N Sammamish (2034)
Central Delridge*–Smith Cove
(2035/37)
Alaska Jct.-Delridge (2035)
Smith Cove-Ballard (2040)
Graham St. (2036)
NE 130th St. (2041)
RapidRide C/D (2034)
South
T. Dome Link NP (2032)
Sumner (2026)
Lakewood, S Tacoma (2032)
Kent, Auburn (2029)
Boeing Access Rd. (2036)
TCC Tacoma Link (2044)
DuPont Sounder (2041)
Sounder
platforms
(2036)
T-Dome Link parking (2040)
Sounder trips & access (2046)
SR-162 (2034)
NP = no parking; DSTT = Downtown Seattle Transit Tunnel
*Delridge stations opens with Tier 2 extension to Alaska Jct, followed by Smith Cove in 2037 AGENDA ITEM #1. b)
8
Tier Projects Years
Delay Work plan
1
Lynnwood -Mariner NP, T-Dome Link NP,
405 Stride NP, Delridge* –Smith Cove, Sumner, S.
Tacoma, Lakewood, OMF North,OMF South, Bus
Base North, 2nd DSTT
≤ 2
Environmental
Full design
Full ROW
Construction
2
Mariner –Everett NP, 522 Stride NP, Delridge -
Alaska Jct., Smith Cove –Ballard, Kent, Auburn, S.
Hilltop, S. Kirkland–Issaquah, DuPont Sounder,
Graham St., Boeing Access Rd., TCC T-Link
≤ 6
Environmental
Full Design
Full ROW
3 Sounder platforms ≤ 9
Environmental
Preliminary Design
Strategic ROW
4
Sounder trips & access, Edmonds &Mukilteo, NE
130th St., RapidRide C/D, N Sammamish, SR-162,
ST3 parking
10 +Pause work
Scenario 1: Hybrid Integrated Network -Subarea Equity
NP = no parking; DSTT = Downtown Seattle Transit Tunnel
*Delridge stations opens with Tier 2 extension to Alaska Jct in 2035, followed by Smith Cove in 2037 AGENDA ITEM #1. b)
9
Tier 1
≤ 2 years delay
Tier 2
≤ 6 years delay
Tier 3
≤ 9 years delay
Tier 4
10+ years delay
System
Bus Base North (2025)
OMF South (2029)
OMF North (2035)
2nd DSTT (2035)
Sounder
Maintenance
Base (2034)
ST2 Bus Base (2036)
Bus-on-Shoulder (2045)
North Lynnwood-Mariner NP (2038)Mariner-Everett NP (2041)Edmonds &Mukilteo (2034)
Everett Link Parking (2046)
East 405 Stride South (2026)
522 Stride NP (2026)
405 Stride North (2029)
522 Stride parking (2029)
S. Kirk.–Issaquah (2045)
N Sammamish P&R (2045)
Central Delridge* –Denny (2035)Denny-Ballard (2041)Alaska Jct.-
Delridge (2038)
NE 130th St. (2041)
Graham St. (2041)
RapidRide C/D (2045)
South
Kent, Auburn, Sumner (2025)
T-Dome Link NP (2032)
Lakewood, S Tacoma (2032)
TCC Tacoma Link (2041)
DuPont Sounder (2041)
T-Dome Link Parking (2040)
Boeing Access Rd. (2045)
Sounder platforms (2045)
Sounder trips/access (2045)
SR-162 (2045)
NP = no parking; DSTT = Downtown Seattle Transit Tunnel
*constrained by timing of 2nd DSTT
Scenario 2: WSBLE, Stride, and Access Variations
AGENDA ITEM #1. b)
10
Tier Projects Years
Delay Work plan
1
405 Stride South, 522 Stride NP, 2nd DSTT,Delridge
–Denny*, Lynnwood-Mariner NP,Kent, Auburn,
Sumner, T-Dome Link NP,Lakewood, S Tacoma,
TCC Tacoma Link, Bus Base North, OMF S, OMF N
≤ 2
Environmental
Full design
Full ROW
Construction
2
Mariner-Everett NP, 405 Stride North,522 Stride
parking, Denny-Ballard, S. Kirk.–Issaquah, DuPont
Sounder
≤ 6
Environmental
Full Design
Full ROW
3 Alaska Jct.-Delridge, Sounder Maintenance Base ≤ 9
Environmental
Preliminary Design
Strategic ROW
4
NE 130th St.,Graham St., Boeing Access Rd.,
Edmonds &Mukilteo,T-Dome Link Parking, Everett
Link Parking, Sounder platforms, Sounder
trips/access, N Sammamish P&R,RapidRide C/D,
SR-162, ST2 Bus Base, Bus-on-Shoulder
10 +Pause work
Scenario 2: WSBLE, Stride, and Access Variations
NP = no parking; DSTT = Downtown Seattle Transit Tunnel
*constrained by timing of 2nd DSTT AGENDA ITEM #1. b)
11
Tier 1
≤ 2 years delay
Tier 2
≤ 6 years delay
Tier 3
≤ 9 years delay
Tier 4
10+ years delay
System
Bus Base North (2025)
OMF South (2029)
OMF North (2035)
2nd DSTT (2038)
Sounder
Maintenance Base
(2034)
ST2 Bus Base (2045)
Bus-on-Shoulder (2045)
North Lynnwood-Mariner NP (2038)Mariner-Everett NP (2041)Edmonds &Mukilteo (2034)
Everett Link Parking (2046)
East 405 Stride S. (2026)
522 Stride NP (2026)
405 Stride N. NP (2027)
S. Kirk.–Issaquah (2045)
522 Stride parking (2034)
405 Stride N. parking (2034)
N Sammamish P&R (2045)
Central Alaska Jct.-SODO (2032)
SODO-Smith Cove (2038)
Smith Cove-Ballard (2040)
NE 130th (2037)
Graham St. (2037)
RapidRide C/D (2045)
South
Kent, Auburn, Sumner (2025)
T-Dome Link NP (2032)
Lakewood, S Tacoma (2032)
TCC Tacoma Link (2041)
Boeing Access (2037)
Sounder platforms &
access (2036)
Sounder trips (2045)
DuPont Sndr (2045)
T-Dome Link Parking (2040)
SR-162 (2045)
NP = no parking; DSTT = Downtown Seattle Transit Tunnel
Scenario 3: WSBLE, Stride, and Infill Variations
AGENDA ITEM #1. b)
12
Tier Projects Years
Delay Work plan
1
Lynnwood-Mariner NP,405 Stride South, 522 Stride
NP, Alaska Jct.-SODO, Kent, Auburn, Sumner, T-
Dome Link NP, Lakewood, S Tacoma,TCC Tacoma
Link, Bus Base North, OMF South,OMF North
≤ 2
Environmental
Full design
Full ROW
Construction
2
2nd DSTT, SODO-Smith Cove, Smith Cove-Ballard,
Mariner-Everett NP, 405 Stride North NP,S.
Kirkland–Issaquah, NE 130th St., Graham St., Boeing
Access Rd.
≤ 6
Environmental
Full Design
Full ROW
3 Sounder platforms, access & trips,DuPont Sounder,
Sounder Maintenance Base ≤ 9
Environmental
Preliminary Design
Strategic ROW
4
T-Dome Link & Everett Link Parking, 405 Stride N &
522 Stride Parking, Edmonds &Mukilteo, N
Sammamish P&R, RapidRide C/D,SR-162, ST2 Bus
Base, Bus-on-Shoulder
10 +Pause work
Scenario 3: WSBLE, Stride, and Infill Variations
NP = no parking; DSTT = Downtown Seattle Transit Tunnel AGENDA ITEM #1. b)
13
Realignment timeline overview
December 2020
Board approves TIP with
placeholder 5 year delay
for all projects, pending
realignment
December 2021
Adopt 2022 final
Budget & TIP
March 2020
Pandemic begins
July 2021
Potential
adoption of
flexible
framework
April 2020
Board informed
that program is
unaffordable
April 2021
Public
engagement via
online survey
AGENDA ITEM #1. b)
14
Next steps
Anticipated realignment work through July
Ongoing public engagement
June Continued development of realignment action
July Consider potential action to adopt realignment framework
AGENDA ITEM #1. b)
I-405 Bus Rapid Transit
AGENDA ITEM #1. b)
1616
I -405 BRT Project
Project Overview: Lynnwood to Burien
37-mile corridor
11 BRT stations across 8 cities
Three new/expanded parking facilities
One transit center
Connections to Link light rail in Lynnwood,
Bellevue and Tukwila
Estimated 19,100 –26,000 riders daily by 2042
Two distinct lines:
•South, Burien to Bellevue (S1)
•North, Bellevue to Lynnwood (S2)AGENDA ITEM #1. b)
17
I -405 BRT: S1
Refinements include:
•Burien Transit Center: Reduced
roadway improvements & ROW
•Tukwila: Smaller station
footprint.
•Development of SRTC design
concept
•I-405/SR 518 at I-5: widening
eliminated.
•Flip concept at NE 44th AGENDA ITEM #1. b)
18
I -405 BRT: WSDOT Partnership at NE 44 th
Changes since 2019:
•Fixed-cost agreement with WSDOT to construct
infrastructure improvements
•Cost effective and efficient: Part of WSDOT’s
Renton to Bellevue Express Toll Lanes project
•Under construction AGENDA ITEM #1. b)
19
South Renton Transit Center
New Transit Center at Grady
Way & Rainier Ave
•New Transit Center to
accommodate BRT and local
transit routes
•700 parking stalls
•Future TOD in SW Corner
AGENDA ITEM #1. b)
2020
I -405 BRT travel times
AGENDA ITEM #1. b)
2121
BRT Project schedule
Project refinement Q1 2019
–Board advances refined
project
Conceptual Engineering &
Environmental Review
Preliminary engineering
PUBLIC INVOLVEMENT
•Final design of roadway
improvements
•Final station designs and
public art
•Obtain land use and
construction permits
PUBLIC INVOLVEMENT
•Groundbreaking
•Construction updates and
mitigation
•Construction of roadway
improvements, parking
and stations.
PUBLIC INVOLVEMENT
WE ARE HERE
**Pending Board Realignment Decisions AGENDA ITEM #1. b)
22
•Independent review will support further updates to cost
assumptions and methodologies .
•Sound Transit Board Realignment Process
•Project to be Built decision(s) by the Sound Transit Board
Agency Next steps AGENDA ITEM #1. b)
Thank you.
soundtransit.org/wsblink AGENDA ITEM #1. b)