Technical Information Report
PREPARED FOR:
Studio19 Architects
207 ½ 1st Avenue South, Suite 300
Seattle, WA 98104-3462
PROJECT:
Watershed Affordable Housing
Apartments
615 and 617 Williams Avenue South
Renton WA
2200335.10
PREPARED BY:
Jesse Newman, EIT
Project Engineer
REVIEWED BY:
Charlie Palmer, PE
Project Manager
DATE:
November 2020
Revised May 2021
Technical Information Report
PREPARED FOR:
Studio19 Architects
207 ½ 1st Avenue South, Suite 300
Seattle, WA 98104-3462
PROJECT:
Watershed Affordable Housing
Apartments
615 and 617 Williams Avenue South
Renton WA
2200335.10
PREPARED BY:
Jesse Newman, EIT
Project Engineer
REVIEWED BY:
Charlie Palmer, PE
Project Manager
DATE:
November 2020
Revised May 2021
I hereby state that this Technical
Information Report for the Watershed
Affordable Housing Apartments project
has been prepared by me or under my
supervision, and meets the standard of
care and expertise that is usual and
customary in this community for
professional engineers. I understand that
City of Renton does not and will not
assume liability for the sufficiency,
suitability, or performance of drainage
facilities prepared by me.
05/03/2021
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Table of Contents
1.0 Project Overview.........................................................................................................................1-1
1.1 Purpose and Scope .........................................................................................................1-1
1.2 Existing Conditions ..........................................................................................................1-1
1.3 Post-Development Conditions .........................................................................................1-1
Section 1.0 Figures
Figure 1-1 ...................................TIR Worksheet
Figure 1-2 ...................................Vicinity Map
Figure 1-3A.................................Predeveloped Site Area Map
Figure 1-3B.................................Proposed Area Map
Figure 1-4 ...................................Soils Map
2.0 Conditions and Requirements Summary.................................................................................2-1
2.1 Core Requirements..........................................................................................................2-1
2.1.1 CR 1 – Discharge at the Natural Location ..........................................................2-1
2.1.2 CR 2 – Offsite Analysis.......................................................................................2-1
2.1.3 CR 3 – Flow Control ...........................................................................................2-1
2.1.4 CR 4 – Conveyance System...............................................................................2-1
2.1.5 CR 5 – Erosion and Sediment Control................................................................2-1
2.1.6 CR 6 – Maintenance and Operations .................................................................2-2
2.1.7 CR 7 – Financial Guarantees and Liability .........................................................2-2
2.1.8 CR 8 – Water Quality..........................................................................................2-2
2.2 Special Requirements......................................................................................................2-2
2.2.1 SR 1 – Other Adopted Area-Specific Requirements...........................................2-2
2.2.2 SR 2 – Flood Hazard Area Delineation...............................................................2-2
2.2.3 SR 3 – Flood Protection Facilities.......................................................................2-2
2.2.4 SR 4 – Source Controls......................................................................................2-2
2.2.5 SR 5 – Oil Control...............................................................................................2-2
2.2.6 SR 6 – Aquifer Protection ...................................................................................2-2
Section 2.0 Figures
Figure 2-1 ...................................FEMA Floodplains Map
Figure 2-2 ...................................Groundwater Protection Map
3.0 Offsite Analysis...........................................................................................................................3-1
3.1 Purpose and Scope .........................................................................................................3-1
3.2 Existing Conditions ..........................................................................................................3-1
3.3 Offsite Analysis................................................................................................................3-1
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
3.3.1 Downstream Analysis .........................................................................................3-1
3.3.2 Upstream Analysis..............................................................................................3-7
3.4 Conclusion.......................................................................................................................3-7
Section 3.0 Figures
Figure 3-1 ..................................Vicinity Map
Figure 3-2 ...................................Existing Conditions Map
Figures 3-3A through 3-3F .........Offsite Analysis Maps
Figure 3-4 ...................................Offsite Analysis Drainage Table
Figure 3-5 ...................................Offsite Drainage Photos
Figure 3-6 ...................................FEMA Flood Insurance Rate Map
Figure 3-7 ...................................Critical Area Map
Figure 3-8 ...................................Soil Survey
Figure 3-9 ...................................WA DOE Clean Water Act Section 303(d) Map
Figure 3-10 .................................Wetland Inventory Map
4.0 Flow Control and Water Quality Facility Analysis and Design...............................................4-1
4.1 Flow Control.....................................................................................................................4-1
4.1.1 Existing Site Hydrology (Part A) .........................................................................4-1
4.1.2 Developed Site Hydrology (Part B).....................................................................4-1
4.1.3 Performance Standards (Part C) ........................................................................4-2
4.1.4 Flow Control System (Part D).............................................................................4-4
4.2 Water Quality System (Part E).........................................................................................4-5
Section 4.0 Figures
Figure 4-1 ...................................MGSFlood Report
Figure 4-2 ...................................Proposed Area Map
Figure 4-3 ...................................Water Quality Area Map
Figure 4-4 ...................................BioPod Sizing Chart
5.0 Conveyance System Analysis and Design...............................................................................5-1
Section 5.0 Figures
Figures will be provided later in design.
6.0 Special Reports and Studies.....................................................................................................6-1
Section 6.0 Figures
Figure 6-1 ...................................Geotechnical Report
7.0 Other Permits..............................................................................................................................7-1
8.0 CSWPPP Analysis and Design..................................................................................................8-1
8.1 ESC Plan Analysis and Design (Part A) ..........................................................................8-1
8.1.1 ESC Maintenance...............................................................................................8-1
8.1.2 ESC Supervisor ..................................................................................................8-1
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
8.1.3 Documentation....................................................................................................8-2
8.1.4 Review Timing ....................................................................................................8-2
8.2 Stormwater Pollution Prevention and Spill (SWPPS) Plan Design (Part B) ....................8-2
8.2.1 Pollution and Spill Prevention Source Controls and BMPs.................................8-2
8.2.2 Responsible Personnel and Contact Information ...............................................8-4
8.2.3 Pollution and Spill Prevention Worksheets.........................................................8-4
8.2.4 Disposal Methods ...............................................................................................8-4
Section 8.0 Figures
Erosion Control will be designed at a later submittal.
9.0 Bond Quantities, Facility Summaries, and Declaration of Covenant ....................................9-1
Section 9.0 Figures
Figures will be provided later in design.
10.0 Operations and Maintenance Plan..........................................................................................10-1
10.1 Facility Descriptions.......................................................................................................10-1
10.2 Maintenance Tasks........................................................................................................10-1
10.3 Maintenance Requirements...........................................................................................10-2
Section 10.0 Figures
Figures will be provided later in design.
11.0 Conclusion................................................................................................................................11-1
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 1
Project Overview
Technical Information Report
Watershed Affordable Housing Apartments 1-1
2200335.10
1.0 Project Overview
1.1 Purpose and Scope
This report accompanies the civil engineering plans and documents for the Watershed Affordable
Housing Apartments located at 617 Williams Avenue South, Renton, Washington. The site is
divided into four parcels, Title Parcel A – 172305-9069 (southeast), Title Parcel B – 172305-9136
(northeast), Title Parcel C – 172305-9136 (west), and Title Parcel D – 182305-9282 (southwest).
The project site is approximately 1.34 acres in size; with the right-of-way dedication, the project
site measures 1.286 acres. Refer to Figure 1-1 for the TIR Worksheet and Figure 1-2 for a
Vicinity Map.
The project proposes to construct two buildings (one with 50 residential units and one with
28 residential units) over at-grade parking. In addition, the project proposes to construct exterior
parking. The buildings will be served with new water, sewer, fire, and storm utilities to support the
buildings. Frontage improvements include new sidewalk along South Grady Way and Williams
Avenue South. Street trees will be planted in an amenity strip along South Grady Way and in tree
pits along Williams Avenue South. In addition, a walking path/emergency access drive will
connect South Grady Way to Burnett Linear Park, running west of the building.
The site is located within the city of Renton, which has adopted the 2017 King County Surface
Water Design Manual, herein referenced as the City of Renton Surface Water Design Manual
(CORSWDM). Per the CORSWDM, Flow Control Best Management Practices (BMPs), Peak
Rate Flow Control, and Enhanced Basic Water Quality Menus will apply to the proposed project.
1.2 Existing Conditions
The existing site is developed with one existing condominium, a gravel driveway, and an existing
billboard. The site is vegetated with lawn and sparse trees. Access to the site is from the gravel
driveway at the southwest portion of the project site along South Grady Way and from the parking
area at the northeast corner along Williams Avenue South.
The topography of the site is relatively flat and slightly undulating, with less than 1-foot fall from
one end to the other. Based on a geotechnical report dated June 10, 2020, in general, site soils
beneath the topsoil consist of very loose to medium dense alluvial, and floodplain deposits
consisting of non-plastic silt (ML), silty fine sand (SM), and sand (SP, SP-SM) were encountered
extending to the maximum exploration depth of 46.5 feet. Per the King County Soil Survey Map
(Figure 1-4), site soils consist primarily of Urban Land (Ur) soils. Per the Geotechnical Report,
the groundwater table was observed at an average depth of 6 to 9 feet below existing grades on
one visit, and between 9 and 10 feet on another visit. Refer to the attached Geotechnical Report
titled, “Updated Geotechnical Engineering Study,” by Earth Solutions NW, Figure 6-1.
The site drains to a catch basin found at the southwest corner of the site near South Grady Way.
The existing drainage patterns are analyzed and discussed in the Level One Downstream
Analysis in Section 3.0. Refer to the attached Predeveloped Site Area Map, Figure 1-3A.
1.3 Post-Development Conditions
The project proposes to construct an apartment building over at-grade parking, new exterior
parking, and an emergency access drive/pedestrian walk on the west portion of the property. In
addition, the project proposes to construct new curb and sidewalk along South Grady Way and
Williams Avenue South. Drainage along Williams Avenue South and South Grady Way will be
improved by sloping the gutters more steeply.
Technical Information Report
Watershed Affordable Housing Apartments 1-2
2200335.10
Stormwater from the new parking area and a portion of the emergency access road will be
conveyed to a BioPod system. After the BioPod treats the runoff for water quality, flows will be
conveyed to a detention pipe system. The detention pipe will also accept flows from the new
building roof and areas that could not be treated for water quality.
A portion of the parking lot is situated in such a way that runoff cannot be collected and conveyed
to the water quality system; however, runoff can be conveyed to the detention pipe.
Following detention, stormwater will discharge via pipe to the existing public downstream
conveyance system along South Grady Way.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 1.0 Figures
Figure 1-1.........TIR Worksheet
Figure 1-2.........Vicinity Map
Figure 1-3A.......Predeveloped Site Area Map
Figure 1-3B.......Proposed Area Map
Figure 1-4.........Soils Map
Jesse Newman
AHBL
206-267-2425
Watershed Affordable
Housing Apartments
617 Williams Ave S.
Renton, Washington.
23N
5E
Section 18 and 17
Black River
Fill Flat Minimal
Vertical Limitations,
only 4.9-feetfrom rim to invert of discharge location.
TDA 1
1
Peak Rate Flow Control
June 8, 2020
NA
BIOPOD
PIPE TANK
1200 6th AvenueSuite 1620Seattle, WA 98101206.267.2425 TEL206.267.2429 FAXWATERSHED AFFORDABLE HOUSING APARTMENTSVICINITY MAPEX1-2GRAPHIC SCALE050010001" = 500 FEET250NPROJECT SITE
1200 6th Avenue
Suite 1620
Seattle, WA 98101
206.267.2425 TEL
206.267.2429 FAX DRAWN BY:DATE:JOB NO.:
WATERSHED AFFORDABLE HOUSING APARTMENTS
PREDEVELOPED SITE AREA MAP
JN 11/2020 20201106
EX
1-3A
12"CON.
14DL8"CON.
14DL
18"CON.
25DL
14"CON.
18DL
48"DEC.
40DL
48"DEC.
40DL
60"DEC.
50DL
36"DEC.
45DL
32"DEC.
40DL
60"DEC.
50DL
72"DEC.
55DL
8"DEC.
20DL
GRAPHIC SCALE
0 40 80
1" = 40 FEET
20
N
LEGEND
Description Quantity Unit
EXISTING IMPERVIOUS AREA 0.299 ac
TOTAL PROJECT SITE AREA WITH DEDICATION 1.286 ac
TOTAL PROJECT SITE AREA 1.336 ac
PROJECT
SITE
DISCHARGE
LOCATION
EXISTING ROW
LINE
1200 6th Avenue
Suite 1620
Seattle, WA 98101
206.267.2425 TEL
206.267.2429 FAX DRAWN BY:DATE:JOB NO.:
12"CON.
14DL8"CON.
14DL
18"CON.
25DL
14"CON.
18DL
48"DEC.
40DL
48"DEC.
40DL
EG: 30.14
UP
UP
32
Watershed Affordable Housing Apartments
Proposed Area Map
JN 11/2020 2200335
FIG
1-3B
GRAPHIC SCALE
0 40 80
1" = 40 FEET
20
N
LEGEND
Description Quantity Unit
BYPASS GRASS (GRASS PAVE)0.001 ac
BYPASS IMPERVIOUS 0.025 ac
BYPASS TOTAL 0.041 ac
GRASS (GRASS PAVE)0.023 ac
NEW + REPLACED IMPERVIOUS 1.118 ac
TOTAL PROJECT SITE AREA WITH DEDICATION 1.286 ac
DISCHARGE
LOCATION
LIMITS OF
DEVELOPMENT
PROPOSED
BUILDING
3-FT DIAMETER
FLOW CONTROL
TANK
WQ
TREATMENT
WITH
BIOPOD
WQ
TREATMENT
WITH
BIOPOD
NEW IMP PGIS BYPASS AND PASTURE
TOTAL NEW PLUS REPLACED IMP=
1.118 sc
TOTAL SITE AREA=
1.286 ac
TOTAL PASTURE=
1.286 ac (total proj sitre area) - 1.118 ac (New + Repl IMP) -
0.041 ac (bypass total area) - 0.023 ac (grass pave) =0.104 ac
BYPASS
BYPASS IMP
=0.025 ac
BYPASS PASTURE
0.041 ac- 0.025-0.001 ac (BYPASS GRASS)
= 0.015 ac
Soil Map—King County Area, Washington
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
6/15/2020
Page 1 of 3525810052581105258120525813052581405258150525816052581705258180525819052582005258210525822052581005258110525812052581305258140525815052581605258170525818052581905258200525821052582205258230559690559700559710559720559730559740559750559760559770559780
559690 559700 559710 559720 559730 559740 559750 559760 559770 559780
47° 28' 29'' N 122° 12' 28'' W47° 28' 29'' N122° 12' 23'' W47° 28' 24'' N
122° 12' 28'' W47° 28' 24'' N
122° 12' 23'' WN
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 10N WGS84
0 30 60 120 180
Feet
0 5 10 20 30
Meters
Map Scale: 1:666 if printed on A portrait (8.5" x 11") sheet.
Soil Map may not be valid at this scale.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Map Unit Polygons
Soil Map Unit Lines
Soil Map Unit Points
Special Point Features
Blowout
Borrow Pit
Clay Spot
Closed Depression
Gravel Pit
Gravelly Spot
Landfill
Lava Flow
Marsh or swamp
Mine or Quarry
Miscellaneous Water
Perennial Water
Rock Outcrop
Saline Spot
Sandy Spot
Severely Eroded Spot
Sinkhole
Slide or Slip
Sodic Spot
Spoil Area
Stony Spot
Very Stony Spot
Wet Spot
Other
Special Line Features
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:24,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
of the version date(s) listed below.
Soil Survey Area: King County Area, Washington
Survey Area Data: Version 15, Sep 16, 2019
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Jul 1, 2019—Jul 25,
2019
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Soil Map—King County Area, Washington
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
6/15/2020
Page 2 of 3
Map Unit Legend
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
Ur Urban land 1.4 100.0%
Totals for Area of Interest 1.4 100.0%
Soil Map—King County Area, Washington
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
6/15/2020
Page 3 of 3
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 2
Conditions and Requirements Summary
Technical Information Report
Watershed Affordable Housing Apartments 2-1
2200335.10
2.0 Conditions and Requirements Summary
2.1 Core Requirements
2.1.1 CR 1 – Discharge at the Natural Location
The project site naturally drains to a catch basin at the southwest corner of the site via
conveyance and sheet flow. The proposed project will pipe developed flows to the same drainage
facility. This meets the requirement for discharging at the natural location.
2.1.2 CR 2 – Offsite Analysis
AHBL staff performed a Level One Downstream Analysis for the project. The analysis included:
Defining and mapping the study area.
Reviewing available information on the study area.
Field inspecting the study area.
Describing the existing drainage system, including its existing and predicted drainage and
water quality problems.
Refer to Section 3.0 for the full offsite analysis.
2.1.3 CR 3 – Flow Control
This project is in a Peak Rate Flow Control Standard area, which requires matching existing site
conditions for the 2-, 10-, and 100-year peak rate runoff. Because there were no observed
drainage problems within 1 mile downstream, there are no further flow control requirements. Flow
control and flow control BMPs are further discussed in Section 4.0, Flow Control and Water
Quality Facility Analysis and Design.
2.1.4 CR 4 – Conveyance System
The project has designed all new conveyance systems to convey the 25-year storm event and to
not overtop in the 100-year storm event. If overtopping occurs, the drainage will be routed to the
natural discharge location without creating a severe flooding or severe erosion problem. The
design and calculations for the new conveyance system are included in Section 5.0.
The project will not change the flow characteristics of the existing conveyance systems because
flow control will be provided prior to discharging to the existing public system. For flow control
analysis, refer to Section 4.0, Flow Control and Water Quality Facility Analysis and Design.
Spill control is required because the project constructs a new onsite conveyance system that
collects runoff from non-rooftop pollution generating impervious surface (PGIS). Spill control will
be provided by use of a tee section in a manhole.
2.1.5 CR 5 – Erosion and Sediment Control
An erosion and sediment control plan will be developed for this site in accordance with the
CORSWDM and to conform to the requirements of the Construction Stormwater National
Pollutant Discharge Elimination System (NPDES) permit issued by the Department of Ecology
(Ecology). The preliminary erosion and sediment control plan is described further in Section 8.0
and in the project plans.
Technical Information Report
Watershed Affordable Housing Apartments 2-2
2200335.10
2.1.6 CR 6 – Maintenance and Operations
The onsite drainage facilities will be privately maintained by the owner. An Operations and
Maintenance Manual will be provided in Section 10.0 at a later submittal.
2.1.7 CR 7 – Financial Guarantees and Liability
This project will provide a Drainage Facilities Restoration and Site Stabilization Financial
Guarantee. Bond Quantity Worksheets will be provided in Section 9.0 at a later submittal.
2.1.8 CR 8 – Water Quality
The project site is subject to the Enhanced Basic Water Quality Treatment Menu per the
CORSWDM. Design of these water quality facilities is discussed further in Section 4.0.
2.2 Special Requirements
2.2.1 SR 1 – Other Adopted Area-Specific Requirements
To our knowledge, no other adopted area-specific requirements apply to the project site.
2.2.2 SR 2 – Flood Hazard Area Delineation
Floodplain/Floodway (FEMA) Maps: The project site is located in Zone X per Flood Insurance
Rate Map No. 53033C0977G, Panel 977, which is determined to be outside the 500-year
(0.02 percent reoccurrence) floodplain. Refer to Figure 2-1 of this section for the FEMA
Floodplains Map.
2.2.3 SR 3 – Flood Protection Facilities
The project does not contain, will not construct, and is not adjacent to any existing flood
protection facilities.
2.2.4 SR 4 – Source Controls
The proposed project consists of a parking lot and apartments. The King County Stormwater
Pollution Prevention Manual (KCSPPM) will be referenced for source control measures, in
addition to erosion and sediment control measures, during construction. For construction source
controls, see Section 8.0 CSWPPP Analysis and Design. Post-construction source controls will
be supplied at a later submittal in Section 10.0, Operations and Maintenance Plan.
2.2.5 SR 5 – Oil Control
The project does not fit the definition of a high-use site; therefore, it is not subject to oil control
requirements.
2.2.6 SR 6 – Aquifer Protection
The project does not fall under Zone 1 or Zone 2 of the Aquifer Protection Area; thus, this
requirement is not applicable. Refer to Figure 2-2, Groundwater Protection Map.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 2.0 Figures
Figure 2-1.........FEMA Floodplains Map
Figure 2-2.........Groundwater Protection Map
1200 6th Avenue
Suite 1620
Seattle, WA 98101
206.267.2425 TEL
206.267.2429 FAX
COMMUNITY NUMBER PANEL SUFFIX
CONTAINS:
(SEE MAP INDEX FOR FIRM PANEL LAYOUT)
Federal Emergency Management Agency
FLOOD INSURANCE RATE MAPFIRM
Notice to User: The Map Number shown belowshould be used when placing map orders; theCommunity Number shown above should beused on insurance applications for the subject community.
MAP REVISED
MAP NUMBER53033C0977G
KING COUNTY,WASHINGTONAND INCORPORATED AREAS
KING COUNTY 530071 0977 GRENTON, CITY OF 530088 0977 G
NFIP
NATIONAL FLOOD INSURANCE PROGRAMPANEL 0977G
PANEL 977 OF 1700
PRELIMINARY
9/15/2017
D :,,SSB
E
A
C
O
N
WAYSWHITWORTHMOSESAVENUE¥k405
ST
SSMITHERSAVENUE S WYGRANTMORRIS4TH
LANE SSS T REET
AVENUE530088 CEDAR4T H
AVENUES
ZONE AH MILLS
HIGHRENTONS AVENUEAVENUEWHITWORTHSMORRISAVEAVENUEMILLS
PedestrianBridge
S GRADYSG R ADYAVENUE S9THAVENUEWAY S5TH
S
S 10TH STR
R
O
A
DRAILRO ADLOGAWILLIAMST
A
L
B
O
T
ZONEX
AVENUECITY OF R ENTON BURNETTSSTREET
AVENUE7T H
SSMITHERSAVENUESTREETSS3RDSTREETSS RA
ILROAD
AVENUEAVENUEWHITWORTHSS
41
ROAD3RD
STREET SS
19 AVENUEMAINW
A
Y
SY0624 X6TH SLANEBENSONWELLSSÑ
WATERSHED AFFORDABLE HOUSING APARTMENTS
FEMA FLOODMAPS
EXHIBIT
2-1
OTHER AREAS
ZONE X
ZONE D
mile; and areas protected by levees from 1% annual chance flood.
Areas determined to be outside the 0.2% annual chance floodplain.
Areas in which flood hazards are undetermined, but possible.
250 10000FEET
150 3000METERS
MAP SCALE 1" = 500'500
150
COMMUNITY NUMBER PANEL SUFFIX
CONTAINS:
(SEE MAP INDEX FOR FIRM PANEL LAYOUT)
Federal Emergency Management Agency
FLOOD INSURANCE RATE MAPFIRM
Notice to User: The Map Number shown belowshould be used when placing map orders; theCommunity Number shown above should beused on insurance applications for the subject community.
MAP REVISED
MAP NUMBER53033C0977G
KING COUNTY,WASHINGTONAND INCORPORATED AREAS
KING COUNTY 530071 0977 G
RENTON, CITY OF 530088 0977 G
NFIP
NATIONAL FLOOD INSURANCE PROGRAMPANEL 0977G
PANEL 977 OF 1700
PRELIMINARY
9/15/2017
PROJECT SITE
PROJECT SITE
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 3
Offsite Analysis
Technical Information Report
Watershed Affordable Housing Apartments 3-1
2200335.10
3.0 Offsite Analysis
3.1 Purpose and Scope
The project encompasses four tax parcels at and surrounding 617 Williams Avenue South in
Renton, Washington. site is divided into four parcels, Title Parcel A – 172305-9069 (southeast),
Title Parcel B – 172305-9136 (northeast), Title Parcel C – 172305-9136 (west), and Title Parcel D
– 182305-9282 (southwest). The project is bordered by Williams Avenue South to the east, South
Grady Way to the south, and parcel properties to the north and west. The combined parcel size is
1.34 acres and the project site is a zero-lot development.
The project proposes to construct two buildings, one with 50 residential units and one with
28 residential units, over at-grade parking. In addition, the project proposes to construct exterior
parking onsite. The buildings will be served with new water, sewer, fire, and storm utilities to
support the buildings.
This report has been prepared to review the upstream and downstream conditions, research any
downstream challenges, review any potential downstream impacts, provide a field inspection
report, and provide recommendations for mitigation.
3.2 Existing Conditions
The existing site is developed with one existing condominium, a gravel driveway, and lawn. In
addition, there are six trees located on the site. Access to the site is from the gravel driveway at
the southwest portion of the project site along South Grady Way and from the parking area at the
northeast corner along Williams Avenue South.
The site is relatively flat and slightly undulating, with less than 1-foot fall from one end to the
other. The site drains to a catch basin found at the southwest corner of the site near South Grady
Way. Refer to Figure 3-2 for the Existing Conditions Map for topographical and aerial depiction of
project site.
Soils for the downstream analysis area, including the project site, are typically of the Urban Land
or Woodinville Silt Loam variety, per the King County Soil Survey Map (Figure 3-8). Refer to the
attached Geotechnical Report (Figure 6-1) for further soil information.
3.3 Offsite Analysis
3.3.1 Downstream Analysis
Task 1 – Study Area Definition Maps
The project is in the Black River Subbasin and has one Threshold Discharge Area. Stormwater
drains to the existing City of Renton storm line that borders the east and south edge of the project
site. Stormwater in this existing system travels south on Williams Avenue South in a series of
pipe and catch basins, and then drains west along South Grady Way to a catch basin located at
the south edge of the project site.
The study area includes the downstream drainage path from the project site for 1 mile
downstream. Field inspection was extended 0.25 mile downstream from the project site. The
upstream was analyzed for identifying potential impacts to the site and drainage systems.
Refer to Figures 3-3A through 3-3F, 3-4, and 3-5 for maps, the offsite analysis table, and photos.
Technical Information Report
Watershed Affordable Housing Apartments 3-2
2200335.10
Task 2 – Resource Review
The following resources were reviewed to discover any existing or potential problems in the study
area:
Adopted Basin Plans: The project site is located within the Black River Subbasin, which is
part of the Green River North Basin, as identified by the CSI Project: Green River North
Sub Regional Planning Area, dated May 2003.
Floodplain/Floodway (FEMA) Maps: The project site is in Zone X per Flood Insurance Rate
Map No. 53033C0977G, Panel 977, which is determined to be outside the 500-year
(0.02 percent reoccurrence) floodplain. Refer to Figure 3-6.
Other Offsite Analysis Reports: No other known offsite analysis reports have been
identified for the areas immediately upstream or downstream of this project site.
Sensitive Areas Folio: Refer to Figure 3-7 for the Critical Area Map, per City of Renton GIS.
The project in within a seismic hazard area; otherwise, the City of Renton GIS does not
show any other sensitive areas near the project site or within 1-mile downstream of the
project. In addition, there are riparian wetlands surrounding the Black River (see Wetland
Inventory Map, Figure 3-10.
Drainage Complaints: There was a drainage complaint listed on the City of Renton GIS at
645 Shattuck Avenue near the associated drainage system. The complaint was that the
sidewalk was flooding, per discussion with a City of Renton Public Works Maintenance
employee. The drainage complaint has been closed since April 18, 2018. Based on the
aerial imagery, it appears that the sidewalk in this area has been replaced.
USDA Soils Survey: Soils for the downstream analysis area, including the project site, are
typically of the Urban Land (58.4%) or Woodinville Silt Loam variety (40.8%), per the King
County Soil Survey Map (Figure 3-8).
Wetlands Inventory: There is a non-delineated wetland surrounding the Black River. Refer
to the Wetlands Inventory Map, Exhibit 3-10.
Section 303d List of Polluted Waters: No polluted waters are located within 1 mile
downstream of the project site per Ecology’s Clean Water Act Section 303d list of polluted
waters and published maps. There was a 303d listed waterbody approximately 1.4 miles
downstream from the project site. Refer to Figure 3-9 for a copy of the area map.
Task 3 – Field Inspect the Study Area (Level 1)
A Level 1 (qualitative) downstream field inspection was completed on June 8, 2020. Weather was
sunny, with temperatures around 70° F. The site was dry.
The Level 1 inspection included the following tasks:
1.Investigate any problems reported or observed during the resource review – No problems
were found downstream of the project area.
2.Locate all existing/potential constrictions or lack of capacity in the existing drainage system –
At one location, based on City of Renton GIS, the drainage system went from 42-inch
diameter pipe to 36-inch diameter pipe. No drainage complaints have been reported in this
area.
Technical Information Report
Watershed Affordable Housing Apartments 3-3
2200335.10
3.Identify all existing/potential downstream drainage problems as defined in Section 1.2.2.1 –
All existing and potential drainage problems are listed in the drainage table, Figure 3-4.
4.Identify existing/potential overtopping, scouring, bank sloughing, or sedimentation – None of
these problems were identified during field inspection.
5.Identify significant destruction of aquatic habitat or organisms – No areas of destruction were
identified, including siltation, bank erosion, or incision in a stream.
6.Collect qualitative data on features such as land use, impervious surfaces, topography, and
soil types – Data reviewed during resource review were confirmed during the field inspection.
7.Collect information on pipe sizes, channel characteristics, drainage structures, and relevant
critical areas – This information is identified in Task 4; however, some of the catch basins
were located in a busy roadway and we were not able to collect information.
8.Verify tributary basins delineated in Task 1 – Tributary basins were confirmed from Task 1.
9.Contact neighboring property owners or residents in the area about past or existing drainage
problems, and describe these in the report – We spoke with a City employee, Gary Fink, who
stated that there were no known drainage issues in the area.
10.Note the date and weather conditions at the time of inspection – Noted above.
Task 4 – Describe the Drainage System, and Its Existing and Predicted Drainage and Water
Quality Problems
The field inspection including walking the downstream flow path from the south site discharge
location to just beyond the 1 mile downstream. The Offsite Analysis Maps, Offsite Analysis
Drainage Table, and Offsite Drainage Photos from the field inspection are provided in
Figures 3-3A through 3-3F (Offsite Analysis Maps), Figure 3-4 (Offsite Analysis Drainage Table),
and Figure 3-5 (Offsite Drainage Photos), respectively. A written description of the downstream
drainage system is given below.
The downstream inspection began at the catch basin located near the southwest corner of the
site adjacent to South Grady Way. Runoff from the project site is directed to this catch basin via
surface flow. The inlet appeared to be surrounded with a slightly bare area, with little or no
vegetation; this does have potential to introduce sediment into the drainage system. In addition,
sediment was observed in the catch basin. The sediment did not appear to hinder the flow
characteristics of the drainage system; there was a small amount of sediment at the invert of the
pipe. Refer to Element 1 in the Downstream Analysis Map (Figure 3-3B), Offsite Analysis
Drainage Table (Figure 3-4), and Offsite Drainage Photos (Figure 3-5).
Drainage Problem Review at Element 1:
1. Description of the problem – Little or no vegetation found directly surrounding inlet and
sediment in standing water.
2. Magnitude of damage caused by the drainage problem – No damage was observed. There
were some signs of sediment in the catch basin. There were no signs of erosion around
the catch basin, and no signs of flooding or significant destruction of aquatic habitat to
organisms.
3. General frequency and duration of drainage problem – There are no known issues with this
area.
Technical Information Report
Watershed Affordable Housing Apartments 3-4
2200335.10
4. Return frequency of storm or flow of the water when the problem occurs (option for Level 1)
– Frequency and duration of the drainage problems have not been reported.
5. Water surface elevation when problem occurs – No water has been observed to be backed
up.
6. Names and concerns of involved parties (optional) – No involved parties have identified a
concern.
7. Current mitigation of drainage problem – None identified.
8. Possible cause of the drainage problem – Lack of vegetation surrounding the catch basin.
9. Will project aggravate problem – No. The improved condition will use peak flow control
standards, assuming existing conditions. It is expected that the detained flows may
experience a net decrease in peak flows and durations. In addition, the landscaping in this
area will all be new.
Based on reviews of the nine areas above, the identified potential existing drainage problem may
not meet the definition of any of the four defined problem types in Section 1.2.2.1.1 of the
CORSWDM.
The inlet discharges to the southwest in a 24-inch concrete pipe to another catch basin located at
the southwest corner of the property line. This structure has a single vine of a blackberry bush
growing inside of it, and there appeared to be a small amount of soil at the bottom of the catch
basin. Refer to Element 2 in the Downstream Analysis Map (Figure 3-3B), Offsite Analysis
Drainage Table (Figure 3-4), and Offsite Drainage Photos (Figure 3-5).
Drainage Problem Review at Element 2
1. Description of the problem – The catch basin has a single blackberry vine growing within it.
If left unchecked, more blackberry vines could sprout up, creating a potential drainage
problem.
2. Magnitude of damage caused by the drainage problem – No damage was observed. There
were some signs of sediment in the catch basin. There were no signs of flooding or
significant destruction of aquatic habitat to organisms.
3. General frequency and duration of drainage problem – There are no known issues with this
area.
4. Return frequency of storm or flow of the water when the problem occurs (option for Level 1)
– Frequency and duration of the drainage problems have not been reported.
5. Water surface elevation when problem occurs – No water has been observed to be backed
up.
6. Names and concerns of involved parties (optional) – No involved parties have identified a
concern.
7. Current mitigation of drainage problem – None identified.
8. Possible cause of the drainage problem – Vegetation inside the catch basin.
Technical Information Report
Watershed Affordable Housing Apartments 3-5
2200335.10
9. Will project aggravate problem – No. The improved condition will use peak flow control
standards, assuming existing conditions. It is expected that the detained flows may
experience a net decrease in peak flows and durations. This catch basin will be cleared
during construction.
Based on reviews of the nine areas above, the identified potential existing drainage problem may
not meet the definition of any of the four defined problem types in Section 1.2.2.1.1 of the
CORSWDM.
Drainage flows west in a 24-inch concrete pipe to a catch basin located on South 7th Street, found
east of Burnett Avenue South. The structure appeared to be in good condition. An orange liquid
was observed entering the catch basin from the inlet pipe; this orange material is most likely iron
oxidized bacteria. As seen in the following Elements, this liquid was observed throughout the
drainage system. Refer to Element 3 in the Downstream Analysis Map (Figure 3-3B), Offsite
Analysis Drainage Table (Figure 3-4), and Offsite Drainage Photos (Figure 3-5).
Drainage continues west in a 24-inch concrete pipe, to the next catch basin, approximately
25 feet downstream. This catch basin appeared to be in good condition. Refer to Element 4 in the
Downstream Analysis Map (Figure 3-3B), Offsite Analysis Drainage Table (Figure 3-4), and
Offsite Drainage Photos (Figure 3-5).
Drainage then travels beneath South 7th Street through a 24-inch ductile iron pipe to a solid-
rimmed catch basin in Burnett Linear Park. This catch basin appeared to be in good condition.
Refer to Element 5 in the Downstream Analysis Map (Figure 3-3B), Offsite Analysis Drainage
Table (Figure 3-4), and Offsite Drainage Photos (Figure 3-5).
Afterward, drainage travels west along South 7th Street through a series of catch basins and
36-inch polyethylene pipes. Elements 6 through 8 were not observed due to safety concerns with
accessing the catch basins in the roadway. The City of Renton GIS was consulted to determine
the characteristics of the existing system. Refer to Elements 6 through 8 in the Downstream
Analysis Map (Figure 3-3B) and the Offsite Analysis Drainage Table (Figure 3-4).
Element 8 drains through a 36-inch pipe to a catch basin located at an alley found between
Smithers Avenue South and Morris Avenue South. This structure appeared to be in good
condition. Refer Element 9 in the Downstream Analysis Map (Figure 3-3B), Offsite Analysis
Drainage Table (Figure 3-4), and Offsite Drainage Photos (Figure 3-5).
Similar to Elements 6 through 8, Elements 10 through 14 were not observed due to safety
concerns with accessing the catch basins in the roadway. According to City of Renton GIS,
drainage continues west through a series of 36-inch polypropylene pipes until Element 11. At
Element 11, the outlet size changes to a 42-inch polypropylene pipe. At Element 12, the outlet
pipe size changes back to a 36-inch polypropylene pipe. This introduces a potential constriction
of flows at this location.
Drainage Problem Review at Element 12
1. Description of the problem – The pipe size changes from 42-inch to 36-inch.
2. Magnitude of damage caused by the drainage problem – No damage was observed around
the catch basins. No drainage complaints have been filed in the area.
3. General frequency and duration of drainage problem – There are no known issues with this
area.
Technical Information Report
Watershed Affordable Housing Apartments 3-6
2200335.10
4. Return frequency of storm or flow of the water when the problem occurs (option for Level 1)
– Frequency and duration of the drainage problems have not been reported.
5. Water surface elevation when problem occurs – No water has been observed to be backed
up.
6. Names and concerns of involved parties (optional) – No involved parties have identified a
concern.
7. Current mitigation of drainage problem – None identified.
8. Possible cause of the drainage problem – Pipe size changing from larger to smaller
diameter.
9. Will project aggravate problem – No. The improved condition will use peak flow control
standards, assuming existing conditions. It is expected that the detained flows may
experience a net decrease in peak flows and durations.
10. Based on reviews of the nine areas above, the identified potential existing drainage
problem may not meet the definition of any of the four defined problem types in Section
1.2.2.1.1 of the CORSWDM.
Following Element 12, drainage continues west along South 7th Street in a 36-inch polypropylene
pipe to a catch basin located east of Whitworth Lane South. The catch basin structure appeared
to be in good condition.
Drainage continues west on South 7th Street to the 0.25-mile point downstream from the project
site to a catch basin at Whitworth Lane South. This structure appeared to be in working order.
According to City of Renton GIS, drainage continues west along South 7th Street through a series
of catch basins and increasing pipe diameters ranging from 36-inch to 60-inch at the outfall to the
Black River drainage basin. Refer to Element 17 in the Downstream Analysis Map (Figure 3-3B),
Offsite Analysis Drainage Table (Figure 3-4), and Offsite Drainage Photos (Figure 3-5).
The field investigation ended at this point.
Task 5 – Mitigation of Existing or Potential Problems
The downstream path is entirely comprised of a manmade system composed of pipes and catch
basins. The piped conveyance system appears to have adequate capacity. Pipe sizes appear to
generally increase as flow continues downstream. Where present, flows appeared to be shallow
and slow. No signs of flooding or overtopping of structures were observed.
Based on the review of the areas discussed in Task 4, the identified potential existing drainage
problems may not meet the definition of any of the four defined problem types in Section 1.2.2.1.1
of the CORSWDM. As such, mitigation of potential or existing problems will be provided through
Flow Control and Water Quality Management.
Flow control BMPs will not be proposed. The project will use a detention tank to match peak flows
of the 2-, 10-, and 100-year events. In addition, the project will use a bipod system to treat water
quality. The project is not expected to aggravate any downstream drainage issues.
Technical Information Report
Watershed Affordable Housing Apartments 3-7
2200335.10
3.3.2 Upstream Analysis
The project site is in a large flat area with little to no drainage entering the project site from
adjacent properties. It was determined that upstream drainage will not adversely impact the site
drainage.
3.4 Conclusion
This analysis is based on data and records either supplied to or obtained by AHBL, Inc. These
documents are referenced within the text of the analysis. The analysis has been prepared using
procedures and practices within the standard accepted practices of the industry. We conclude
that this analysis represents the field conditions as observed and researched by AHBL.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 3.0 Figures
Figure 3-1 ..................................Vicinity Map
Figure 3-2...................................Existing Conditions Map
Figures 3-3A through 3-3F.........Offsite Analysis Maps
Figure 3-4...................................Offsite Analysis Drainage Table
Figure 3-5...................................Offsite Drainage Photos
Figure 3-6...................................FEMA Flood Insurance Rate Map
Figure 3-7...................................Critical Area Map
Figure 3-8...................................Soil Survey
Figure 3-9...................................WA DOE Clean Water Act Section 303(d) Map
Figure 3-10.................................Wetland Inventory Map
1200 6th AvenueSuite 1620Seattle, WA 98101206.267.2425 TEL206.267.2429 FAXWATERSHED AFFORDABLE HOUSING APARTMENTSVICINITY MAPEX3-1GRAPHIC SCALE050010001" = 500 FEET250NPROJECT SITE
1,128
94
Existing Conditions Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
None
6/9/2020
Legend
64032
THIS MAP IS NOT TO BE USED FOR NAVIGATION
Feet
Notes
64
WGS_1984_Web_Mercator_Auxiliary_Sphere
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
City and County Labels
City and County Boundary
Addresses
Parcels
Streets
Points of Interest
Parks
Waterbodies
2019.sid
Red: Band_1
Green: Band_2
Blue: Band_3
Map
PROJECT SITE
STORMWATER
DISCHARGE
LOCATION
EX 3-2
9,0281505
Downstream Analysis Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
1023 0 512 1023 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Pump Stations
Discharge Points
Stormwater Mains
Culverts
Open Drain
Facility Outlines
Private Pump Stations
Private Discharge Points
Private Pipes
Private Culverts
Private Open Drain
Private Facility Outlines
Stormwater Ponds
Streets
Parks
Waterbodies
2019.sid
Red: Band_1
Green: Band_2
Blue: Band_3
Map
FLOW PATH PROJECT SITE
TDA 1
DISCHARGE TO
BLACK RIVER,
APPRX. 1.4 MILES
DOWNSTREAM.
1- MILE
DOWNSTREAM
1/4 MILE
DOWNSTREAM
EX 3-3A
2,257376
Downstream Analysis Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
256 0 128 256 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Parcels
Network Structures
Access Riser
Inlet
Manhole
Utility Vault
Clean Out
Unknown
Control Structures
Pump Stations
Discharge Points
Water Quality
Detention Facilities
Pond
Tank
Vault
Bioswale
Wetland
Other
Stormwater Mains
Culverts
Open Drain
Virtual Drainlines
Facility Outlines
Private Network Structures
Access Riser
Inlet
Manhole
Clean Out
Utility Vault
Unknown
Private Control Structures
Private Pump Stations
Private Discharge Points
Private Water Quality
Private Detention Facilities
Tank
Wetland
Filter Strip
Infiltration Trench
Vault
Pond
Bioswale
Stormtech Chamber
Other
Private Pipes
Private Culverts
Private Open Drain
Private Facility Outlines
Flow Control BMPs
Fences
Stormwater Ponds
Streets
Points of Interest
Parks
Waterbodies
2019.sid
1/4 MILE
DOWNSTREAM
1
2
FLOW
PATH
3
4
5
6
7
8
9
10
11-13
1415
16
FLOW PATH
CONTINUED
3-3C
LEGEND
Description
1/4 MILE FLOW PATH
a
DRAINAGE ELEMENT
SEE PHOTOS
PROJECT
SITE
DISCHARGE
LOCATION
EX 3-3B
2,257376
Downstream Analysis Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
256 0 128 256 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Parcels
Network Structures
Access Riser
Inlet
Manhole
Utility Vault
Clean Out
Unknown
Control Structures
Pump Stations
Discharge Points
Water Quality
Detention Facilities
Pond
Tank
Vault
Bioswale
Wetland
Other
Stormwater Mains
Culverts
Open Drain
Virtual Drainlines
Facility Outlines
Private Network Structures
Access Riser
Inlet
Manhole
Clean Out
Utility Vault
Unknown
Private Control Structures
Private Pump Stations
Private Discharge Points
Private Water Quality
Private Detention Facilities
Tank
Wetland
Filter Strip
Infiltration Trench
Vault
Pond
Bioswale
Stormtech Chamber
Other
Private Pipes
Private Culverts
Private Open Drain
Private Facility Outlines
Flow Control BMPs
Fences
Stormwater Ponds
Streets
Points of Interest
Parks
Waterbodies
2019.sid
0.61 MILES
FLOW PATH
CONTINUED
3-3D
FLOW PATH
EX 3-3C
2,257376
Downstream Analysis Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
256 0 128 256 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Parcels
Network Structures
Access Riser
Inlet
Manhole
Utility Vault
Clean Out
Unknown
Control Structures
Pump Stations
Discharge Points
Water Quality
Detention Facilities
Pond
Tank
Vault
Bioswale
Wetland
Other
Stormwater Mains
Culverts
Open Drain
Virtual Drainlines
Facility Outlines
Private Network Structures
Access Riser
Inlet
Manhole
Clean Out
Utility Vault
Unknown
Private Control Structures
Private Pump Stations
Private Discharge Points
Private Water Quality
Private Detention Facilities
Tank
Wetland
Filter Strip
Infiltration Trench
Vault
Pond
Bioswale
Stormtech Chamber
Other
Private Pipes
Private Culverts
Private Open Drain
Private Facility Outlines
Flow Control BMPs
Fences
Stormwater Ponds
Streets
Points of Interest
Parks
Waterbodies
2019.sid
FLOW PATH
FLOW PATH
CONTINUED
3-3E
0.95 MILES
DOWNSTREAM
EX 3-3D
2,257376
Downstream Analysis Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
256 0 128 256 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Parcels
Network Structures
Access Riser
Inlet
Manhole
Utility Vault
Clean Out
Unknown
Control Structures
Pump Stations
Discharge Points
Water Quality
Detention Facilities
Pond
Tank
Vault
Bioswale
Wetland
Other
Stormwater Mains
Culverts
Open Drain
Virtual Drainlines
Facility Outlines
Private Network Structures
Access Riser
Inlet
Manhole
Clean Out
Utility Vault
Unknown
Private Control Structures
Private Pump Stations
Private Discharge Points
Private Water Quality
Private Detention Facilities
Tank
Wetland
Filter Strip
Infiltration Trench
Vault
Pond
Bioswale
Stormtech Chamber
Other
Private Pipes
Private Culverts
Private Open Drain
Private Facility Outlines
Flow Control BMPs
Fences
Stormwater Ponds
Streets
Points of Interest
Parks
Waterbodies
2019.sid
1 MILE
DOWNSTREAM
FLOW PATH
CONTINUED
3-3F
FLOW PATH
EX 3-3E
2,257376
Downstream Analysis Map
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
256 0 128 256 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Parcels
Network Structures
Access Riser
Inlet
Manhole
Utility Vault
Clean Out
Unknown
Control Structures
Pump Stations
Discharge Points
Water Quality
Detention Facilities
Pond
Tank
Vault
Bioswale
Wetland
Other
Stormwater Mains
Culverts
Open Drain
Virtual Drainlines
Facility Outlines
Private Network Structures
Access Riser
Inlet
Manhole
Clean Out
Utility Vault
Unknown
Private Control Structures
Private Pump Stations
Private Discharge Points
Private Water Quality
Private Detention Facilities
Tank
Wetland
Filter Strip
Infiltration Trench
Vault
Pond
Bioswale
Stormtech Chamber
Other
Private Pipes
Private Culverts
Private Open Drain
Private Facility Outlines
Flow Control BMPs
Fences
Stormwater Ponds
Streets
Points of Interest
Parks
Waterbodies
2019.sid
DISCHARGE TO
BLACK RIVER
17
LEGEND
Description
a
DRAINAGE ELEMENT
DRAINAGE ELEMENT OBSERVED, SEE PHOTOS
FLOW PATH
EX 3-3F
DATE:6/8/2020BY:Jesse Newman#DESCRIPTIONINOUTEXISTINGPOTENTIALPHOTOSOBSERVATIONS OF FIELD INSPECTOR1 Catch Basin Inlet 24" CONC. 24" CONC. 0-2% 0'Inlet appeared to be surrounded by a bare area, where little grass was growing, water appeared to have sediment in it.Element 1 PhotosStanding water in catch basin has some sediment visible, inlet surrounded by vegetation2 Catch Basin Inlet 24" CONC. 24" CONC. 0-2% 51'Catch basin has vegetation growing inside Element 2 Photos Black berry bush growing from inside the CB.3 Catch Basin Inlet 24" CONC. 24" CONC. 0-2% 344'Element 3 PhotosSome orage liquid observed. Potentially from iron oxidizing bacteria.4 Catch Basin Solid LID 24" CONC. 24" DIP 0-2% 389'Element 4 PhotosSome orage liquid observed. Potentially from iron oxidizing bacteria.5 Catch Basin Solid LID 24" DIP 36" PP 0-2% 435'Element 5 PhotosSome orage liquid observed. Potentially from iron oxidizing bacteria.6 Catch Basin Solid LID 36" PP 36" PP 0-2% 523'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.7 Catch Basin Inlet 36" PP 36" PP 0-2% 598'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.8 Catch Basin Solid LID 36" PP 36" PP 0-2% 654'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.9 Catch Basin Inlet 36" PP 36" PP 0-2% 797'Element 9 Photos10 Catch Basin Inlet 36" PP 36" PP 0-2% 923'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.11 Catch Basin Solid LID 36" PP 42" DIP 0-2% 940'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.12 Catch Basin Solid LID 42" DIP 36" PP 0-2% 951'Constriction of storm Pipe from 42" to 36"Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.13 Catch Basin Solid LID 36" PP 36" CONC. 0-2% 965'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.14 Catch Basin Solid LID 36" CONC. 36" PP 0-2% 1073'Not observed due to safety concerns accessing CB in roadway. (sizes from City of Renton GIS.15 Catch Basin Solid Inlet 36" PP 36" PP 0-2% 1254'Element 15 Photos16 Catch Basin Solid Inlet 36" PP 36" PP 0-2% 1363'Element 16 Photos Some orage liquid observed. Potentially from iron oxidizing bacteria.17 Outfall to Black River 60-72" Corrugated Metal, oval 2-4% 1.4 milesElement 17 PhotosDRAINAGE ELEMENT (SEE MAP)PROBLEMSDISTANCE FROM SITE DISCHARGEAPPROXIMATE SLOPE OUTEX 3-4Watershed Affordable Housing ApartmentsOffsite Drainage Table
EXHIBIT 3-5 OFFSITE DRAINAGE PHOTOSELEMENT 1 PHOTOS
ELEMENT 2 PHOTOS
ELEMENT 3 PHOTOS
ELEMENT 4 PHOTO
ELEMENT 5 PHOTOS
ELEMENT 9 PHOTOS
ELEMENT 16 PHOTOS
ELEMENT 17 PHOTOS
1200 6th Avenue
Suite 1620
Seattle, WA 98101
206.267.2425 TEL
206.267.2429 FAX
COMMUNITY NUMBER PANEL SUFFIX
CONTAINS:
(SEE MAP INDEX FOR FIRM PANEL LAYOUT)
Federal Emergency Management Agency
FLOOD INSURANCE RATE MAPFIRM
Notice to User: The Map Number shown belowshould be used when placing map orders; theCommunity Number shown above should beused on insurance applications for the subject community.
MAP REVISED
MAP NUMBER53033C0977G
KING COUNTY,WASHINGTONAND INCORPORATED AREAS
KING COUNTY 530071 0977 GRENTON, CITY OF 530088 0977 G
NFIP
NATIONAL FLOOD INSURANCE PROGRAMPANEL 0977G
PANEL 977 OF 1700
PRELIMINARY
9/15/2017
D :,,SSB
E
A
C
O
N
WAYSWHITWORTHMOSESAVENUE¥k405
ST
SSMITHERSAVENUE S WYGRANTMORRIS4TH
LANE SSS T REET
AVENUE530088 CEDAR4T H
AVENUES
ZONE AH MILLS
HIGHRENTONS AVENUEAVENUEWHITWORTHSMORRISAVEAVENUEMILLS
PedestrianBridge
S GRADYSG R ADYAVENUE S9THAVENUEWAY S5TH
S
S 10TH STR
R
O
A
DRAILRO ADLOGAWILLIAMST
A
L
B
O
T
ZONEX
AVENUECITY OF R ENTON BURNETTSSTREET
AVENUE7T H
SSMITHERSAVENUESTREETSS3RDSTREETSS RA
ILROAD
AVENUEAVENUEWHITWORTHSS
41
ROAD3RD
STREET SS
19 AVENUEMAINW
A
Y
SY0624 X6TH SLANEBENSONWELLSSÑ
WATERSHED AFFORDABLE HOUSING APARTMENTS
DRAWING_TITLE
EXHIBIT
3-6
OTHER AREAS
ZONE X
ZONE D
mile; and areas protected by levees from 1% annual chance flood.
Areas determined to be outside the 0.2% annual chance floodplain.
Areas in which flood hazards are undetermined, but possible.
250 10000FEET
150 3000METERS
MAP SCALE 1" = 500'500
150
COMMUNITY NUMBER PANEL SUFFIX
CONTAINS:
(SEE MAP INDEX FOR FIRM PANEL LAYOUT)
Federal Emergency Management Agency
FLOOD INSURANCE RATE MAPFIRM
Notice to User: The Map Number shown belowshould be used when placing map orders; theCommunity Number shown above should beused on insurance applications for the subject community.
MAP REVISED
MAP NUMBER53033C0977G
KING COUNTY,WASHINGTONAND INCORPORATED AREAS
KING COUNTY 530071 0977 G
RENTON, CITY OF 530088 0977 G
NFIP
NATIONAL FLOOD INSURANCE PROGRAMPANEL 0977G
PANEL 977 OF 1700
PRELIMINARY
9/15/2017
PROJECT SITE
FEMA FLOOD INSURANCE RATE MAP
9,0281505
CRITICAL AREA MAP
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
THIS MAP IS NOT TO BE USED FOR NAVIGATIONWGS_1984_Web_Mercator_Auxiliary_Sphere
Notes
None
06/05/2020
Legend
1023 0 512 1023 Feet
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
Parcels
Erosion Hazard - High
Floodway
Special Flood Hazard Areas (100 year flood)
Other Flood Areas (Zone X - 500 year flood)
Channel Migration Zones (CMZ) as mapped by
King County
Moderate Hazard Area
Potential Hazard Area
Severe Hazard Area
Landslide
Very High
High
Moderate
Unclassified
Slope City of Renton
>15% & <=25%
>25% & <=40% (Sensitive)
>40% & <=90% (Protected)
>90% (Protected)
Environment Designations
Natural
Shoreline High Intensity
Shoreline Isolated High Intensity
Shoreline Residential
Urban Conservancy
Jurisdictions
Streams (Classified)
<all other values>
Type S Shoreline
Type F Fish
Type Np Non-Fish
Type Ns Non-Fish Seasonal
Unclassified
Not Visited
Wetlands
Seismic Hazard Areas
Faults
Streets
Parks
Waterbodies
Map
PROJECT SITE
DISCHARGE TO
BLACK RIVER
APPROXIMATELY
1.4 MILES
DOWNSTREAM
EX 3-7
Soil Map—King County Area, Washington
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
6/5/2020
Page 1 of 35257500525770052579005258100525830052585005258700525890052575005257700525790052581005258300525850052587005258900557300557500557700557900558100558300558500558700558900559100559300559500559700559900
557300 557500 557700 557900 558100 558300 558500 558700 558900 559100 559300 559500 559700 559900
47° 28' 54'' N 122° 14' 27'' W47° 28' 54'' N122° 12' 15'' W47° 28' 5'' N
122° 14' 27'' W47° 28' 5'' N
122° 12' 15'' WN
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 10N WGS84
0 350 700 1400 2100
Feet
0 100 200 400 600
Meters
Map Scale: 1:7,400 if printed on B landscape (17" x 11") sheet.
Soil Map may not be valid at this scale.
EXHIBIT 3-8 SOIL SURVEY
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Map Unit Polygons
Soil Map Unit Lines
Soil Map Unit Points
Special Point Features
Blowout
Borrow Pit
Clay Spot
Closed Depression
Gravel Pit
Gravelly Spot
Landfill
Lava Flow
Marsh or swamp
Mine or Quarry
Miscellaneous Water
Perennial Water
Rock Outcrop
Saline Spot
Sandy Spot
Severely Eroded Spot
Sinkhole
Slide or Slip
Sodic Spot
Spoil Area
Stony Spot
Very Stony Spot
Wet Spot
Other
Special Line Features
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:24,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
of the version date(s) listed below.
Soil Survey Area: King County Area, Washington
Survey Area Data: Version 15, Sep 16, 2019
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Jun 29, 2019—Jul
25, 2019
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Soil Map—King County Area, Washington
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
6/5/2020
Page 2 of 3
Map Unit Legend
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
Py Puyallup fine sandy loam 0.4 0.8%
Ur Urban land 30.6 58.4%
Wo Woodinville silt loam 21.4 40.8%
Totals for Area of Interest 52.5 100.0%
Soil Map—King County Area, Washington
Natural Resources
Conservation Service
Web Soil Survey
National Cooperative Soil Survey
6/5/2020
Page 3 of 3
Water Quality Atlas Map
Sources: Esri, HERE, Garmin, Intermap, increment P Corp., GEBCO, USGS,FAO, NPS, NRCAN, GeoBase, IGN, Kadaster NL, Ordnance Survey, EsriJapan, METI, Esri China (Hong Kong), (c) OpenStreetMap contributors, and
Ju ne 5, 202 0
0 0.25 0.50.125Miles
K
AssessedWaters/Sediment
Water
Category 5 - 303d
Category 4C
Category 4B
Category 4A
Category 2
Category 1
Sedim ent
Category 5 - 303d
Category 4C
Category 4B
Category 4A
Category 2
Category 1
DRAINAGE PATH
PROJECT SITE
APPROXIMATELY
1.4 MILES DOWN
STREAM
EXHIBIT 3-9 WA DOE Clean Water Act Section 303(d) Map
4,800
400
City of Renton Wetland Inventory
This map is a user generated static output from an Internet mapping site and
is for reference only. Data layers that appear on this map may or may not be
accurate, current, or otherwise reliable.
None
6/9/2020
Legend
2720136
THIS MAP IS NOT TO BE USED FOR NAVIGATION
Feet
Notes
272
WGS_1984_Web_Mercator_Auxiliary_Sphere
Information Technology - GIS
RentonMapSupport@Rentonwa.gov
City and County Labels
City and County Boundary
Parcels
Environment Designations
Natural
Shoreline High Intensity
Shoreline Isolated High Intensity
Shoreline Residential
Urban Conservancy
Jurisdictions
Streams (Classified)
<all other values>
Type S Shoreline
Type F Fish
Type Np Non-Fish
Type Ns Non-Fish Seasonal
Unclassified
Not Visited
Wetlands
Streets
Points of Interest
Parks
Waterbodies
2019.sid
Red: Band_1
Green: Band_2
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 4
Flow Control and Water Quality Facility Analysis and
Design
Technical Information Report
Watershed Affordable Housing Apartments 4-1
2200335.10
4.0 Flow Control and Water Quality Facility Analysis and Design
4.1 Flow Control
4.1.1 Existing Site Hydrology (Part A)
Based on a geotechnical report dated June 10, 2020, in general, site soils beneath the topsoil,
consist of very loose to medium dense alluvial and floodplain deposits consisting of non-plastic
silt (ML). Silty fine sand (SM) and sand (SP, SP-SM) were encountered extending to the
maximum exploration depth of 46.5 feet. Per the King County Soil Survey Map (Figure 1-4) site
soils consist primarily of Urban Land (Ur) soils. Per the geotechnical report, seasonal high
groundwater was observed at 6 to 9 feet below grade. The existing site was modelled as till grass
and impervious area.
MGSFlood was used to design the storm drainage facilities. The predeveloped site was modeled
in the existing condition because the site is in the peak rate flow control area shown on the City of
Renton GIS map.
Refer to Figure 1-3A for the Predeveloped Site Area Map.
The annual peak flows were determined using the information above and the surface conditions
below.
Table 1 - Existing Site Hydrology
Description Target Area (Acres)Total Area (Acres)
Till Grass 0.987 0.987
Impervious 0.299 0.299
Total Area 1.286 1.286
4.1.2 Developed Site Hydrology (Part B)
The project proposes to construct storm detention facilities to the Peak Rate Flow Control
standard. The developed inflow to the detention facility includes all developed target areas
tributary to the facility. Additionally, bypass areas were developed for target areas that are not
physically capable of being conveyed to the detention facility. Site soils are modelled as till soils.
The project proposes to design a 36-inch pipe tank to address the Peak Rate Flow Control
requirements.
In addition, the site proposes grass pave in strips totaling 0.023 acre. The grass pave area was
modeled as 100 percent grass per the CORSWDM, Table 1.2.9.A.
This facility will release surface water runoff to the existing public stormwater conveyance system.
The annual peak flows for the proposed site were determined using the basin information above
and the surface conditions below. Refer to Figure 4-2 for the Proposed Area Map.
Technical Information Report
Watershed Affordable Housing Apartments 4-2
2200335.10
Table 2 - Developed Site Hydrology
Description
Target
Detained
Area
(Acres)
Target
Bypass Area
(Acres)
Total
Area
(Acres)
Till Forest ------
Till Grass (Grass Pave)0.023 0.001 0.024
Till Pasture 0.104 0.015 .119
Impervious 1.118 0.025 1.143
Total Area 1.245 0.041 1.286
4.1.3 Performance Standards (Part C)
Area-Specific Flow Control Facility Standard
This project is in a Peak Rate Flow Control Standard area, which requires matching developed
discharge rates to the existing peak discharge rates for the 2-, 10-, and 100-year return periods.
Refer to Section 4.1.4 for flow calculation results. Existing site conditions are assumed to be till
grass and impervious area.
Flow Control BMP Requirements
Flow Control BMPs are required per CR 3. The project site totals 1.286 acres, including all
parcels. The developed site includes 1.143 acres of impervious area, including new and replaced
impervious areas and bypass areas. This results in 88 percent impervious in the proposed
conditions. The project falls under the Large Lot BMP Requirements. Refer to Figure 4-2 for the
Proposed Area Map, which includes the total imperious surface for the site.
Below is a summary of the Flow Control BMPs (per CORSWDM Section 1.2.9.2.2) that the
project will assess:
1.Full dispersion: This is infeasible because there is not enough native vegetated surface.
2.Target Impervious Surface Flow Control BMPs: Per CORSWDM, Table C.1.3.A -
Onsite BMP Application Rates, because the project site is above 85 percent impervious
surface coverage, the onsite BMP application is not required.
o Full Infiltration: This BMP is infeasible because we cannot meet the minimum
design requirements. Per Section C2.2.2 1a. of the CORSWDM, these soil conditions
must be met: existing soil must be coarse sands or cobbles or medium sands. In
general, the soils layers that could be used for infiltration consist of silty sand and
inorganic silts.
o Limited Infiltration: This BMP is infeasible because we cannot meet the minimum
design requirements. Per Section C2.2.2 1a. of the CORSWDM, these soil conditions
must be met: existing soil must be coarse sands or cobbles or medium sands. In
general, the soils layers that could be used for infiltration consist of silty sand and
inorganic silts.
Technical Information Report
Watershed Affordable Housing Apartments 4-3
2200335.10
o Basic Dispersion: This BMP is infeasible. The minimum distance of vegetated flow
path (50 feet) cannot be met. In addition, this project is on very flat terrain and
surrounded by impervious area.
o Rain Garden: This BMP is infeasible. Per CORSWDM Section C.2 - Onsite BMPs
Infeasibility Criteria, for a bioretention planter that accepts greater than 5,000 square
feet of PGIS, a minimum of 3 feet of vertical separation is required below
bioretention. Per the Geotechnical Report, seasonal high groundwater depth ranges
from 6 to 9 feet below grade and may be higher during larger rain events. This does
not yield enough vertical separation between the rain garden and the seasonal high
ground water.
o Permeable Pavement: The paved portion of the site cannot be permeable pavement
because the surface is a parking lot and driving isle that will generate PGIS. In
addition, the site soils have not been analyzed to meet the soil suitability qualities for
providing treatment listed in the infeasibility criteria in Section C.2.7, Criterion 20.
Further, the owner does not have the budget for the maintenance required to clean
the pores from clogging.
o Rainwater Harvesting: This BMP is infeasible; no irrigation systems are proposed.
o Vegetated Roof: The project will have a green roof.
o Reduced Impervious Surface Credit: This BMP is not achievable because none of
the proposed techniques are feasible for the site’s intended use.
o Native Growth Retention Credit: This BMP is not achievable because there is no
presence of native growth in the existing conditions to retain.
o Perforated Pipe Connection for Roof Drains: Perforated pipe connections were
not provided for the roof drain connections due to the non-infiltrative soil type that
characterizes the site.
The project is not required to mitigate any area according to Table C1.3.A of the CORSWDM.
Conveyance System Capacity Standards
The onsite stormwater networks will be sized to adequately convey the fully developed, 25-year
storm event, as stipulated by the CORSWDM, and to not overtop during the 100-year storm
event.
Area-Specific Water Quality Treatment Menu
In accordance with the CORSWDM, onsite flows will be treated to the specifications provided by
the Enhanced Basic Water Quality standards. The goal of this treatment menu is to reduce total
suspended solids (TSS) by 80 percent and to reduce zinc concentration by 50 percent for a
typical rainfall year. This goal will be accomplished by providing a proprietary system approved by
Ecology, a BioPod system.
Source Controls
The proposed project consists of a new parking lot, portable classrooms, and a covered play
area. The CORSWDM will be referenced for source control measures, in addition to erosion and
sediment control measures, during construction. For construction source controls, refer to
Technical Information Report
Watershed Affordable Housing Apartments 4-4
2200335.10
Section 8.0 CSWPPP Analysis and Design. For post-construction source controls, refer to
Section 10.0, Operations and Maintenance Plan.
Oil Controls
Not applicable.
4.1.4 Flow Control System (Part D)
Flow Control BMPs
A vegetated green roof will be used.
Detention Sizing
Detention and control structure requirements were designed using the MGSFlood program and
hydrology summarized in Sections 4.1.1 and 4.1.2. For the results, refer to Figure 4-1, MGSFlood
Report. The system requirements are summarized as follows:
Table 3 – Detention Pipe Requirements
Required Provided
Detention Volume 3,141 cf 3,298 cf
Live Storage Depth 2 ft 2 ft
Outlet Control Structure
Orifice #1 Diameter 2-11/16 in 2-11/16 in
Orifice #2 Diameter 2-3/8 in 2-3/8 in
Orifice #3 Diameter 2 in 2 in
Orifice #1 Height 100.50 ft 100.50 ft
Orifice #2 Height 101.70 ft 101.70 ft
Orifice #3 Height 102.00 ft 102.00 ft
Point of Compliance Review
The developed peak flows for the 2-, 10-, and 100-year storms match that of the existing peak
flows. Refer to Figure 4-1, MGSFlood Report for results.
Discharge Requirements
The project meets the natural discharge location requirement and is not subject to discharge
requirements 1 through 3, per the following:
1. The project discharges to a manmade conveyance system.
2. The project is not located within a Landslide Hazard Drainage Area.
3. The project is not adjacent to or does not contain a landslide, steep slope, or erosion
hazard area.
Technical Information Report
Watershed Affordable Housing Apartments 4-5
2200335.10
4.2 Water Quality System (Part E)
The new PGIS for the proposed site includes 16,422 square feet (0.377 acre) of area that will be
treated for water quality prior to detention. Roughly 4,914 square feet (0.113 acre) of target
pollution generating surface cannot feasibly be conveyed to the water quality facility. In addition,
about three-quarters of the 5,000-square foot area are located beneath a building. The area that
cannot be treated is less than the 5,000 square feet of new plus replaced PGIS.
Onsite runoff from PGIS will be treated to the Enhanced Basic Water Quality standards of the
CORSWDM using three different BioPods, a proprietary system with Ecology approval to treat
enhanced basic water quality. MGSFlood was used to determine the online flows, and a chart
from the manufacturer was used to size the BioPod system. Refer to Figure 4-3 for the Water
Quality Area Map and Figure 4-4 for the BioPod Sizing Chart.
A summary of the results is tabulated below:
Area from WQ
Area Map
Required Online
Discharge Rate
Provided
Size from BioPod
Sizing Chart
Treatment Flow
Capacity from
Figure 4-5, BioPod
Sizing Chart
WQ #1 0.01 cfs 4’ x 6’0.074 cfs
WQ #2 0.02 cfs 4’ x 6’0.074 cfs
WQ #3 0.03 cfs 4’ x 6’0.074 cfs
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 4.0 Figures
Figure 4-1.........MGSFlood Report
Figure 4-2.........Proposed Area Map
Figure 4-3.........Water Quality Area Map
Figure 4-4.........BioPod Sizing Chart
—————————————————————————————————
MGS FLOOD
PROJECT REPORT
Program Version: MGSFlood 4.54
Program License Number: 201710010
Project Simulation Performed on: 05/03/2021 2:18 PM
Report Generation Date: 05/03/2021 2:18 PM
—————————————————————————————————
Input File Name: Grady Way 3' Tank.fld
Project Name: Grady Way Apartments
Analysis Title: Preliminary Model
Comments:
———————————————— PRECIPITATION INPUT ————————————————
Computational Time Step (Minutes): 15
Extended Precipitation Time Series Selected
Climatic Region Number: 3
Full Period of Record Available used for Routing
Precipitation Station : 95004005 Puget West 40 in_5min 10/01/1939-10/01/2097
Evaporation Station : 951040 Puget West 40 in MAP
Evaporation Scale Factor : 0.750
HSPF Parameter Region Number: 1
HSPF Parameter Region Name : USGS Default
********** Default HSPF Parameters Used (Not Modified by User) ***************
********************** WATERSHED DEFINITION ***********************
Predevelopment/Post Development Tributary Area Summary
Predeveloped Post Developed
Total Subbasin Area (acres) 1.286 1.286
Area of Links that Include Precip/Evap (acres) 0.000 0.000
Total (acres) 1.286 1.286
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
---------- Subbasin : Existing Predeveloped ----------
-------Area (Acres) --------
Till Grass 0.987
Impervious 0.299
----------------------------------------------
Subbasin Total 1.286
Watershed Affordable Housing Apartments
FIG 4-1
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 5
---------- Subbasin : NEW IMP PGIS BYPASS AND PASTURE AND GRASS PAVE ----------
-------Area (Acres) --------
Till Pasture 0.104
Till Grass 0.023
Impervious 0.741
----------------------------------------------
Subbasin Total 0.868
---------- Subbasin : Bypass ----------
-------Area (Acres) --------
Till Pasture 0.015
Till Grass 0.001
Impervious 0.025
----------------------------------------------
Subbasin Total 0.041
---------- Subbasin : WQ 1 ----------
-------Area (Acres) --------
Impervious 0.053
----------------------------------------------
Subbasin Total 0.053
---------- Subbasin : WQ 2 ----------
-------Area (Acres) --------
Impervious 0.132
----------------------------------------------
Subbasin Total 0.132
---------- Subbasin : WQ 3 ----------
-------Area (Acres) --------
Impervious 0.192
----------------------------------------------
Subbasin Total 0.192
************************* LINK DATA *******************************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
------------------------------------------
Link Name: POC 1
Link Type: Copy
Downstream Link: None
************************* LINK DATA *******************************
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 5
------------------------------------------
Link Name: TDA 1
Link Type: Copy
Downstream Link: None
------------------------------------------
Link Name: Pipe Tank
Link Type: Structure
Downstream Link Name: TDA 1
User Specified Elevation Volume Table Used
Elevation (ft) Pond Volume (cu-ft)
100.00 0.
100.10 31.
100.20 109.
100.30 185.
100.40 271.
100.50 399.
100.60 504.
100.70 616.
100.80 771.
100.90 894.
101.00 1019.
101.10 1191.
101.20 1322.
101.30 1455.
101.40 1635.
101.50 1770.
101.60 1905.
101.70 2084.
101.80 2217.
101.90 2349.
102.00 2521.
102.10 2646.
102.20 2768.
102.30 2924.
102.40 3035.
102.50 3141.
102.60 3269.
102.70 3355.
102.80 3430.
102.90 3508.
103.00 3540.
Hydraulic Conductivity (in/hr) : 0.00
Massmann Regression Used to Estimate Hydralic Gradient
Depth to Water Table (ft) : 100.00
Bio-Fouling Potential : Low
Maintenance : Average or Better
Riser Geometry
Riser Structure Type : Circular
Riser Diameter (in) : 18.00
Common Length (ft) : 0.000
Riser Crest Elevation : 102.50 ft
Hydraulic Structure Geometry
Number of Devices: 3
---Device Number 1 ---
Device Type : Circular Orifice
Control Elevation (ft) : 100.50
Diameter (in) : 2.69
Orientation : Horizontal
Elbow : Yes
---Device Number 2 ---
Device Type : Circular Orifice
Control Elevation (ft) : 101.70
Diameter (in) : 2.38
Orientation : Horizontal
Elbow : Yes
---Device Number 3 ---
Device Type : Circular Orifice
Control Elevation (ft) : 102.00
Diameter (in) : 2.00
Orientation : Horizontal
Elbow : Yes
------------------------------------------
Link Name: WQ 1
Link Type: Copy
Downstream Link Name: Pipe Tank
------------------------------------------
Link Name: WQ 2
Link Type: Copy
Downstream Link Name: Pipe Tank
------------------------------------------
Link Name: WQ 3
Link Type: Copy
Downstream Link Name: Pipe Tank
**********************FLOOD FREQUENCY AND DURATION STATISTICS*******************
----------------------SCENARIO: PREDEVELOPED
Number of Subbasins: 1
Number of Links: 1
----------------------SCENARIO: POSTDEVELOPED
Number of Subbasins: 5
Number of Links: 5
***********Groundwater Recharge Summary *************
Recharge is computed as input to Perlnd Groundwater Plus Infiltration in Structures
Total Predeveloped Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: Existing Predevelope 116.858
Link: POC 1 0.000
_____________________________________
Total: 116.858
Total Post Developed Recharge During Simulation
Model Element Recharge Amount (ac-ft)
-----------------------------------------------------------------------------------------------
Subbasin: NEW IMP PGIS BYPASS 20.588
Subbasin: Bypass 2.695
Subbasin: WQ 1 0.000
Subbasin: WQ 2 0.000
Subbasin: WQ 3 0.000
Link: TDA 1 0.000
Link: Pipe Tank Not Computed
Link: WQ 1 Not Applicable
Link: WQ 2 Not Applicable
Link: WQ 3 Not Applicable
_____________________________________
Total: 23.284
Total Predevelopment Recharge is Greater than Post Developed
Average Recharge Per Year, (Number of Years= 158)
Predeveloped: 0.740 ac-ft/year, Post Developed: 0.147 ac-ft/year
***********Water Quality Facility Data *************
----------------------SCENARIO: PREDEVELOPED
Number of Links: 1
********** Link: POC 1 **********
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 347.16
Inflow Volume Including PPT-Evap (ac-ft): 347.16
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 347.16
Secondary Outflow To Downstream System (ac-ft): 0.00
Volume Lost to ET (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered+ET)/Total Volume: 0.00%
----------------------SCENARIO: POSTDEVELOPED
Number of Links: 5
********** Link: TDA 1 **********
Infiltration/Filtration Statistics--------------------
Inflow Volume (ac-ft): 543.17
Inflow Volume Including PPT-Evap (ac-ft): 543.17
Total Runoff Infiltrated (ac-ft): 0.00, 0.00%
Total Runoff Filtered (ac-ft): 0.00, 0.00%
Primary Outflow To Downstream System (ac-ft): 543.17
Secondary Outflow To Downstream System (ac-ft): 0.00
Volume Lost to ET (ac-ft): 0.00
Percent Treated (Infiltrated+Filtered+ET)/Total Volume: 0.00%
********** Link: WQ 1 **********
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.01 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.00 cfs
********** Link: WQ 2 **********
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.02 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.01 cfs
********** Link: WQ 3 **********
15-Minute Timestep, Water Quality Treatment Design Discharge
On-line Design Discharge Rate (91% Exceedance): 0.03 cfs
Off-line Design Discharge Rate (91% Exceedance): 0.02 cfs
***********Compliance Point Results *************
Scenario Predeveloped Compliance Link: POC 1
Scenario Postdeveloped Compliance Link: TDA 1
*** Point of Compliance Flow Frequency Data ***
Recurrence Interval Computed Using Gringorten Plotting Position
Predevelopment Runoff Postdevelopment Runoff
Tr (Years) Discharge (cfs) Tr (Years) Discharge (cfs)
----------------------------------------------------------------------------------------------------------------------
2-Year 0.208 2-Year 0.198
5-Year 0.305 5-Year 0.294
10-Year 0.381 10-Year 0.358
25-Year 0.495 25-Year 0.411
MATCHING
PREDEVELOPED
RUNOFF
DISCHARGE
FOR 2, 10, AND
100 YR EVENTS
50-Year 0.602 50-Year 0.443
100-Year 0.627 100-Year 0.553
200-Year 0.695 200-Year 0.602
500-Year 0.785 500-Year 0.666
** Record too Short to Compute Peak Discharge for These Recurrence Intervals
MATCHING
PREDEVELOPED
RUNOFF
DISCHARGE 100
YR EVENTS
1200 6th Avenue
Suite 1620
Seattle, WA 98101
206.267.2425 TEL
206.267.2429 FAX DRAWN BY:DATE:JOB NO.:
12"CON.
14DL8"CON.
14DL
18"CON.
25DL
14"CON.
18DL
48"DEC.
40DL
48"DEC.
40DL
EG: 30.14
UP
UP
32
Watershed Affordable Housing Apartments
Proposed Area Map
JN 11/2020 2200335
FIG
4-2
GRAPHIC SCALE
0 40 80
1" = 40 FEET
20
N
LEGEND
Description Quantity Unit
BYPASS GRASS (GRASS PAVE)0.001 ac
BYPASS IMPERVIOUS 0.025 ac
BYPASS TOTAL 0.041 ac
GRASS (GRASS PAVE)0.023 ac
NEW + REPLACED IMPERVIOUS 1.118 ac
TOTAL PROJECT SITE AREA WITH DEDICATION 1.286 ac
DISCHARGE
LOCATION
LIMITS OF
DEVELOPMENT
PROPOSED
BUILDING
3-FT DIAMETER
FLOW CONTROL
TANK
WQ
TREATMENT
WITH
BIOPOD
WQ
TREATMENT
WITH
BIOPOD
NEW IMP PGIS BYPASS AND PASTURE
TOTAL NEW PLUS REPLACED IMP=
1.118 sc
TOTAL SITE AREA=
1.286 ac
TOTAL PASTURE=
1.286 ac (total proj sitre area) - 1.118 ac (New + Repl IMP) -
0.041 ac (bypass total area) - 0.023 ac (grass pave) =0.104 ac
BYPASS
BYPASS IMP
=0.025 ac
BYPASS PASTURE
0.041 ac- 0.025-0.001 ac (BYPASS GRASS)
= 0.015 ac
1200 6th Avenue
Suite 1620
Seattle, WA 98101
206.267.2425 TEL
206.267.2429 FAX DRAWN BY:DATE:JOB NO.:
12"CON.
14DL8"CON.
14DL
18"CON.
25DL
14"CON.
18DL
48"DEC.
40DL
48"DEC.
40DL
EG: 30.14
UP
UP
32
Watershed Affordable Housing Apartments
Water Quality Area Map
Name Date Job No.
FIG
4-3
GRAPHIC SCALE
0 40 80
1" = 40 FEET
20
N
LEGEND
Description Quantity Unit
PGIS- BYPASS 0.117 ac
PGIS WQ 1 0.053 ac
PGIS WQ 2 0.132 ac
PGIS WQ 3 0.192 ac
DISCHARGE
LOCATION
LIMITS OF
DEVELOPMENT
PROPOSED
BUILDING
3-FT DIAMETER
FLOW CONTROL
TANK
WQ 1
TREATMENT
WITH
BIOPOD
WQ 2
TREATMENT
WITH
BIOPOD
WQ 3
TREATMENT
WITH
BIOPOD
DRAWN BY:DATE:JOB NO.:
1200 6th Avenue, Suite 1620
Seattle, WA 98101
206.267.2425 TEL 206.267.2429 FAX
Watershed Affordable Housing Apartments
Biopod Sizing Chart
Jesse N 07/01/2020 2200335.10
FIG
4-4
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 5
Conveyance System Analysis and Design
Technical Information Report
Watershed Affordable Housing Apartments 5-1
2200335.10
5.0 Conveyance System Analysis and Design
Conveyance will be sized to convey the 25-year storm event and checked for adequate capacity
for the 100-year event during final design.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 5.0 Figures
Figures will be provided later in design.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 6
Special Reports and Studies
Technical Information Report
Watershed Affordable Housing Apartments 6-1
2200335.10
6.0 Special Reports and Studies
“Updated Geotechnical Engineering Study” dated June 10, 2020, by Earth Solutions NW.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 6.0 Figures
Figure 6-1.........Geotechnical Report
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 7
Other Permits
Technical Information Report
Watershed Affordable Housing Apartments 7-1
2200335.10
7.0 Other Permits
A Construction Stormwater NPDES Permit is necessary for the proposed construction.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 8
CSWPPP Analysis and Design
Technical Information Report
Watershed Affordable Housing Apartments 8-1
2200335.10
8.0 CSWPPP Analysis and Design
The proposed development will comply with guidelines set forth in the CORSWDM and in
conformance with the required Construction Stormwater NPDES Permit. The plan will include
erosion/sedimentation control features designed to prevent sediment-laden runoff from leaving
the site or from adversely affecting critical water resources during construction.
8.1 ESC Plan Analysis and Design (Part A)
The erosion potential of the site is influenced by four major factors: soil characteristics, vegetative
cover, topography, and climate. Erosion/sedimentation control is achieved by a combination of
structural measures, cover measures, and construction practices that are tailored to fit the
specific site.
The following measures will be used to control sedimentation/erosion processes:
Clearing Limits: Areas of clearing will be delineated on a TESC plan. Areas will be
delineated in the field with high visibility construction flags or temporary construction
fencing.
Cover Measures: Disturbed areas shall be permanently or temporarily covered, as
required in Section D.4.2 of the CORSWDM. Temporary measures include plastic sheeting
and mulch. Permanent measures include hydroseed.
Perimeter Protection: Silt fencing and straw wattles will be used for perimeter protection.
Traffic Area Stabilization: Existing paved surfaces will be used for the construction
entrance to the maximum extent feasible. A construction entrance will be supplied in areas
that are unpaved. Wheel washing and/or street sweeping will be provided as necessary to
prevent tracking of sediment onto adjacent surfaces. Dust control measures will be
implemented when exposed soils are dry to the point that wind transport is possible.
Sediment Retention: Inlet protection will be provided on all new and existing catch basins
downstream of construction activities.
Surface Water Control: This will be designed at a later submittal.
Wet Season Requirements: Construction activities will occur during the months of May
through August and will thus not trigger wet season requirements. The Contractor shall
ensure that the site is stabilized prior to a predicted storm event with plastic sheeting or
mulch.
Critical Areas Restrictions: No critical areas are located onsite.
8.1.1 ESC Maintenance
All ESC measures shall be maintained and reviewed on a regular basis, as prescribed in the
maintenance requirements of each BMP.
8.1.2 ESC Supervisor
The Contractor shall designate an ESC supervisor who shall be responsible for maintenance and
review of ESC and for compliance with all permit conditions relating to ESC. The ESC supervisor
must be available for rapid response to ESC problems. The ESC supervisor is required to be a
Technical Information Report
Watershed Affordable Housing Apartments 8-2
2200335.10
Certified Erosion and Sedimentation Control Lead (CESCL) with demonstrated expertise in ESC
to perform these reviews and to be responsible for ESC implementation.
8.1.3 Documentation
The ESC supervisor shall review the site at least once a month during the dry season, weekly
during the wet season, and within 24 hours of significant storms. Written records of these
reviews shall be kept onsite, with copies submitted to the King County Department of
Development and Environmental Services (DDES) within 48 hours.
If DDES requires that a written record be maintained, a standard ESC Maintenance Report will be
included closer to final design. A copy of all required maintenance reports shall be kept onsite
throughout the duration of construction.
8.1.4 Review Timing
During the wet season, weekly reviews shall be carried out every 6 to 8 calendar days. During
the dry season, monthly reviews shall be carried out within 3 days of the calendar day for the last
inspection (e.g., if an inspection occurred on June 6, then the next inspection must occur between
July 3 and July 9). Reviews shall also take place within 24 hours of significant storms. In
general, a significant storm is one with more than 0.5 inch of rain in 24 hours or less. Another
indication that a storm is “significant” is if gullies form as a result of the runoff.
8.2 Stormwater Pollution Prevention and Spill (SWPPS) Plan Design (Part B)
The below SWPPS Plan shall be completed by the Contractor for use during construction of the
project. Blanks are intentional because they are part of the Contractor’s means and methods.
The SWPPS Plan includes three elements: a site plan, a pollution prevention report, and a spill
prevention and cleanup report. This report includes identifying the expected sources of potential
pollution and spills that may occur during construction, and works to develop a plan to prevent
pollution and spills. It also develops a plan to mitigate spills that may occur. The SWPPS Plan
will be kept onsite at all times during construction. The general contractor will be responsible to
ensure that subcontractors are aware of the SWPPS Plan and a form or record will be provided
stating that all subcontractors have read and agree to the SWPPS Plan. An employee training
worksheet will be provided for the Contractors use.
A SWPPS Site Plan will be developed by the Contractor. The SWPPS Site Plan, Pollution
Prevention Report, and Spill Prevention and Cleanup Report have been preliminarily developed
and BMPs have been selected based on Section 2.3.1.4 of the CORSWDM and the KCSPPM.
8.2.1 Pollution and Spill Prevention Source Controls and BMPs
The sources of pollution and spills have been identified below, and the BMPs to be used for each
source for prevention of both pollution and spills have been listed below:
Liquids that will be handled or stored onsite are the following: _________. Containers will be
stored as shown on the SWPPS Site Plan and include the following types and sizes:
___________. Tight-fitting lids shall be placed on all containers containing liquids. Containers
shall be covered with plastic sheeting during rain events. Drip pans or absorbent materials shall
be placed beneath all mounted container taps and at all potential drip and spill locations during
filling and unloading of containers. Containers shall be stored such that if a container leaks or
spills, the contents will not be discharged, flow, or be washed into the storm drainage system,
surface water, or groundwater. Appropriate spill cleanup materials shall be stored and
maintained near the container storage area. Storage area shall be swept and cleaned as
Technical Information Report
Watershed Affordable Housing Apartments 8-3
2200335.10
needed. Area shall not be hosed down such that water drains to the storm drainage system or
neighboring areas. Containers shall be checked daily for leaks and spills and replaced, as
necessary. All spilled liquids will be collected and disposed of properly. Spill control devices
shall be routinely inspected on a weekly basis.
Dry pesticides and fertilizers shall be covered with plastic sheeting or stored in a sealed
container. Materials shall be stored on pallets or another raised method to prevent contact with
stormwater runoff. Alternatively, the materials shall be contained in a manner such that if the
container leaks or spills, the contents will not discharge, flow, or be washed into the storm
drainage system, surface waters, or groundwater. Maintenance requirements are the same as
liquid materials described above.
Chemicals that will be handled or stored onsite are the following: _________. Containers will be
stored as shown on the SWPPS Site Plan and include the following types and sizes:
___________. BMPs and maintenance requirements are the same as liquids with the addition of
the following ______.
Soil, sand, and other erodible materials shall be stored onsite in a contractor-designated
location. Materials shall be covered with plastic sheeting per standard detail. Perimeter controls
shall be constructed as shown on the TESC plan to prevent eroded materials from leaving the
project site.
Fueling shall not occur onsite. If fueling does occur onsite, the Contractor shall develop a
containment plan for spills and provide lighting and signage if fueling occurs at night in
conformance with the KCSPPM.
Maintenance and repair of vehicles shall not occur onsite. If maintenance or repair of vehicles
does occur onsite, the Contractor shall develop a spill prevention plan in conformance with the
KCSPPM.
Truck wheel washing shall occur in a controlled manner, such that runoff is collected and
disposed of in a legal manner.
Rinsing of hand tools shall occur in a designated location and water for washing shall be
collected and disposed of in a legal manner.
Contaminated soils shall be covered with plastic sheeting or contained to prevent stormwater
from carrying pollutants away to surface or ground waters. Appropriate spill cleanup materials,
such as brooms, dustpans, vacuum sweepers, etc., shall be stored and maintained near the
storage area. Storage area shall be swept and cleaned as needed. Area shall not be hosed
down such that water drains to the storm drainage system, groundwater, surface water, or
neighboring areas.
During concrete and asphalt construction, the Contractor shall provide the following BMPs or
equivalent measures, methods or practices as required:
1. Drip pans, ground cloths, heavy cardboard, or plywood wherever concrete, asphalt, and
asphalt emulsion chunks and drips are likely to fall unintentionally, such as beneath
extraction points from mixing equipment.
2. Storm drains shall be covered to prevent concrete and asphalt from entering the storm
system.
Technical Information Report
Watershed Affordable Housing Apartments 8-4
2200335.10
3. Concrete, concrete slurry and rinse water shall be contained and collected and shall not be
washed or allowed to discharge into storm drain, ditch, or neighboring parcels. All
collected runoff shall be properly disposed of.
4. Contractor shall designate an area where application and mixing equipment cleaning will
be conducted. Rinse water and slurry shall be collected, contained, and disposed of in a
legal manner.
5. Routine maintenance: the pouring area shall be swept at the end of each day or more
frequently if needed. Loose aggregate chunks and dust shall be collected. Areas shall not
be hosed down.
The Contractor may provide the following optional BMPs if the above do not provide adequate
source controls:
1. Cover portable mixing equipment with an awning or plastic sheeting to prevent contact with
rainfall.
2. Provide catch basin inserts configured for pollutant removal.
pH elevated water shall not be discharged from the site. Contractor shall monitor stormwater for
pH prior to discharging from the site. Contractor shall implement a pH treatment plan if pH is not
within the natural range.
8.2.2 Responsible Personnel and Contact Information
The Contractor shall designate a CESCL and post their contact name, company, and phone
number and/or email in a readily visible location onsite.
[name] with [company] shall be responsible for pollution and spill prevention and
cleanup and can be contacted at [phone] or [email] .
Contractor shall fill out a Pollution Prevention Team Worksheet that will be supplied later.
8.2.3 Pollution and Spill Prevention Worksheets
Pollution prevention, BMP implementation reports, material inventory worksheets, pollutant
source identification worksheet, and spill/leak report will be supplied closer to final design.
8.2.4 Disposal Methods
Contractor shall dispose of contaminated soils and water in a legal manner. Options include the
following: _______________.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 8.0 Figures
Erosion Control will be designed at a later submittal.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 9
Bond Quantities, Facility Summaries, and Declaration
of Covenant
Technical Information Report
Watershed Affordable Housing Apartments 9-1
2200335.10
9.0 Bond Quantities, Facility Summaries, and Declaration of Covenant
This section will be completed later in design.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 9.0 Figures
Figures will be provided later in design.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 10
Operations and Maintenance Plan
Technical Information Report
Watershed Affordable Housing Apartments 10-1
2200335.10
10.0 Operations and Maintenance Plan
The drainage facilities detailed in this report will be privately owned and maintained.
10.1 Facility Descriptions
Control Structure
The control structure is a manhole on the downstream end (south end) of the pond. The control
structure includes a flow restrictor attached to the outlet pipe that looks like a tee. The bottom of
the tee has an orifice plate, and one downturned elbow also has orifice plates attached to the
bottom. The top of the tee is open. The purpose of the flow restrictor is to control the release of
flows to the downstream system, which prevents flooding and excessive erosion. The manhole
also includes a jailhouse overflow, which is an opening with vertical bars set on the side and near
the top of the structure.
In order to function properly, the control structure should be kept free of excessive accumulated
sediment, trash, and debris. Damage to the structure or the flow restrictor should be repaired or
replaced. The orifice plates and flow restrictor tee should be free of obstructions. If the orifice
plates are damaged or missing, it should be repaired or replaced. The inlet and outlet pipes
should be free of sediment accumulation, trash, and debris. The jailhouse should be clear of
blockages and the grates should be intact.
Conveyance Systems
Pipes transport stormwater runoff from developed portions of the property to the detention pond,
and then to the downstream points of connection. To work properly, pipes must be kept free of
silt and other debris. If pipes become blocked, surface flooding will occur.
Debris Barrier
Debris barriers are a metal trash rack located over the entrance to a pipe or culvert. A debris
barrier may also be a conical structure constructed of metal bars and/or rods placed over a catch
basin. Trash and debris should be removed so that the barrier is clear to receive stormwater
flows. Damaged or missing bars should be repaired or replaced.
Catch Basins and Area Drains
Catch basins collect surface drainage and direct it into storm conveyance pipes. They help
prevent downstream drainage problems by trapping sediment and other debris that would
otherwise flow downstream with the runoff. It is important to keep catch basins clean so that
accumulated silt is not flushed out during a significant storm. In addition, if the outflow pipe
becomes blocked with debris, surface flooding will occur. All catch basins should be inspected at
least once each year and after major storms.
Area drains convey runoff directly into conveyance pipes. To prevent surface flooding, their
surface grates must be kept free of litter and debris. If dirt or other sediment gets into the pipes
and they become blocked, the pipes will need to be cleaned, either manually or using a Vactor
truck.
10.2 Maintenance Tasks
A stormwater Facility Maintenance Checklist will be supplied later.
Technical Information Report
Watershed Affordable Housing Apartments 10-2
2200335.10
10.3 Maintenance Requirements
Maintenance requirements will be supplied later.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 10.0 Figures
Figures will be provided later in design.
Technical Information Report
Watershed Affordable Housing Apartments
2200335.10
Section 11
Conclusion
Technical Information Report
Watershed Affordable Housing Apartments 11-1
2200335.10
11.0 Conclusion
This site has been designed to meet the 2017 CORSWDM. The site incorporates detention and
water quality facilities to treat stormwater draining from the site. Flow calculations/modeling used
City of Renton standards for sizing stormwater conveyance networks and treatment facilities.
It was determined using these criteria that:
Detention facilities have been designed to meet the required Peak Rate Flow Control
Standard.
Water quality facilities have been designed to meet the required Enhanced Basic Water
Quality Treatment Level for the site.
Pipe networks will be designed to be of adequate size to effectively convey the 25-year
storm event and to contain the 100-year storm event. Calculations will be supplied closer
to final design.
This analysis is based on data and records either supplied to or obtained by AHBL. These documents
are referenced within the text of the analysis. The analysis has been prepared using procedures and
practices within the standard accepted practices of the industry. We conclude that this project, as
schematically represented, will not create any new problems within the downstream drainage system.
This project will not noticeably aggravate any existing downstream problems due to either water quality or
quantity.
AHBL, Inc.
Jesse Newman, EIT
Project Engineer
JN/lsk
November 2020
Revised May 2021
Q:\2020\2200335\WORDPROC\Reports\20210503 Rpt (TIR) 2200335.10.docx