HomeMy WebLinkAboutM_Hazardous Materials_Management_Statement_20210521_v1.pdfSECTION 49
HAZARDOUS MATERIALS MANAGEMENT STATEMENT
Hazardous Materials Management Statement
To: Studio 19 Architects Date: 11/6/2020
Job Name: GMD
Renton
Project Location: Renton, WA
Attn: Jeff Walls
Dear Jeff,
This is supplemental information for the GMD Renton project to address the hazardous materials
management statement requested.
49.
a. Only designated persons shall conduct fueling operations. In case of spillage, filler caps shall be
replaced and spillage disposed of before engines are started. Engines shall be stopped and
operators shall not be on the equipment during refueling operations, Smoking and open
flames shall be prohibited in areas used for fueling, fuel storage or enclosed storage of
equipment containing fuel. Liquid fuels not handled by pump shall be handled and transported
only in portable containers or equivalent means designed for that purpose. Portable
containers shall be metal, have tight closures with screw or spring covers and shall be
equipped with spouts or other means to allow pouring without spilling. Leaking containers
shall not be used. There is not currently an inventory of hazardous material planned for the
project. Generally, portable metal containers are held in a fuel containment cell if storage is
required.
b. Construction debris such as concrete, lumber, etc… will all be removed from site and not
buried. Waste disposal operations such as Roll-off, Waste Management, etc… will be utilized
on an as needed basis. Contractor and their subcontractors shall comply with RMC 4-4-030C8
as/if required.
By: Kory Knudson
Sr. Project Manager