HomeMy WebLinkAbout0895.06 DFR 305, 307, 309.pdfEarth Solutions NW, LLC
LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development Date: August 24, 2021
401 Central Street SE ESNW No.: ES- 895.06
Olympia, WA 98501 Project: Weatherly Inn
Attn: Mr. Jeff Bennett
Email: jeffb@accrete.build
No. of
Copies Date Description
1 4/8 – 4/19/21 Daily Field Report(s) # 305, 307, & 309
Comments:
CC:
1: Mark Richardson ATTN: mark@accrete.build
2: Jennifer Vogele ATTN: jennifer@accrete.build
3: Jonathan Chavez ATTN: jchavez@rentonwa.gov
4: Joe W ATTN: joew@accrete.build
5: Brittany Perry ATTN: brittany@accrete.build
6: ATTN:
7: ATTN:
8: ATTN:
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 305
Time On Site Time Off Site Date Day of Week
11:00 AM 11:30 AM 4/8/21 Thursday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test utility trench backfill at the Weatherly Inn
development.
Utility Trench Backfill:
EDSNW rep arrived onsite and observed contractor had backfilled approximately 100’ of 3.5’ deep secondary
utility trench running East to main building from utility vault with 1 1/4’’ minus recycled crushed concrete
compacted in 12’’ lifts to grade with a hoe pack. ESNW rep used a ½’’ steel T-probe and found the subgrade to
be suitably dense, firm, and unyielding. ESNW rep observed that the contractor had achieved minimum
compaction standards of 95% or greater in tested locations.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Utility trench with 4’’ schedule 40 PVC conduit bedded in pea gravel and backfilled with 1 ¼’’ recycled concrete
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 305
Time On Site Time Off Site Date Day of Week
11:00 AM 11:30 AM
4/8/21
Thursday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Utility trench
backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
295 See map SG 9 127.7 6.2 122.2 96
296 See map SG 9 127.7 7.1 123.3 97
Fig. 2 Approximate location of compaction tests 295-296 on utility trench backfill.
2/2
296
295
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 307
Time On Site Time Off Site Date Day of Week
12:15 PM 12:45 PM
4/14/21
Monday
Travel Time Weather
1.00Hr. RT 40s, OC
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test utility trench backfill at the Weatherly Inn
development.
Utility Trench Backfill:
EDSNW rep arrived onsite and observed contractor had backfilled approximately 50’ of 3’ deep secondary utility
trench running parallel to the main building with 1 1/4’’ minus recycled crushed concrete compacted in 12’’ lifts to
grade with a hoe pack. ESNW rep recommended adding water to material in order to reach optimum moisture.
ESNW rep used a ½’’ steel T-probe and found the subgrade to be suitably dense, firm, and unyielding. ESNW
rep observed that the contractor had achieved minimum compaction standards of 95% or greater in
tested locations.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Utility trench with 2’’ schedule 40 PVC conduit bedded in pea gravel and backfilled with 1 ¼’’ recycled concrete
Jackson Lundgren, G.I.T.
Senior Field Technician
206-468-0991
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 307
Time On Site Time Off Site Date Day of Week
12:15 PM 12:45 PM
4/14/21
Monday
Travel Time Weather
1.00Hr. RT 40s, OC
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Test Number Test Location
(Utility trench
backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
300 See map SG 9 127.7 5.4 122.7 96
301 See map SG 9 127.7 6.1 121.9 95
Fig. 2 Approximate location of compaction tests 300-301 on utility trench backfill.
2/2
301
300
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 309
Time On Site Time Off Site Date Day of Week
1:00 PM 1:45 PM
4/19/21 Monday
Travel Time Weather
1.00Hr. RT 60s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test stromwater trench backfill at the Weatherly Inn
development.
Utility Trench Backfill:
EDSNW rep arrived onsite and observed contractor had backfilled approximately 100’ of 3’ deep stormwater
trench between CB#4 and CB# 5 running parallel to the East margin of the main building with 1 1/4’’ minus
recycled crushed concrete compacted in 12’’ lifts to grade with a hoe pack. ESNW rep observed contractor
adding water to material in order to reach optimum moisture. ESNW rep used a ½’’ steel T-probe and found the
subgrade to be suitably dense, firm, and unyielding. ESNW rep observed that the contractor had achieved
minimum compaction standards of 95% or greater in tested locations.
ESNW rep will return as requested to continue observation and testing of further earthwork activities.
Fig.1: Trench with 12’’ corrugated ABS bedded in pea gravel and backfilled with 1 ¼’’ recycled concrete
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 309
Time On Site Time Off Site Date Day of Week
1:00 PM 1:45 PM 4/19/21 Monday
Travel Time Weather
1.00Hr. RT 60s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Johannsen Brad LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test Number Test Location
(Stormwater
trench backfill) Elevation Reference
Compaction
Curve
Maximum Dry
Density (pcf) Fill Moisture
(%) Test
Dry Density
(pcf)
% of Maximum
Dry Density
302 See map SG 9 127.7 11.2 123.7 97
303 See map SG 9 127.7 12.1 123.6 97
Fig. 2 Approximate location of compaction tests 302-303 on stormwater trench backfill.
2/2
302
303