HomeMy WebLinkAboutPN-Project narrative_ Boeing New slot drain_210612_v1.pdfProject narrative
BOEING COMMERCIAL AIRPLANE GROUP
RENTON WASHINGTON
The project consists of saw cutting and removing approx. 750 square feet of
existing concrete and asphalt. Installing 96 Linear feet of 13 inch slot drain and
connecting to existing catch basin. The new slot drain will provide for better
drainage and eliminate storm water build up on the apron.
737 Logan Avenue. N, Renton WA 98055
Adjacent to the shoreline of the Cedar River and Renton municipal Airport
Master use permit, Substantial Shoreline development permit is the land use
permits for the proposed projects.
Zoning designation is Urban Center north 2
Boeing Commercial Airplane plant in Renton. Adjacent to the Renton Airport
The Cedar River & Lake Washington are the Special site features
The site soils consist of 3 to 8 feet of imported fill materials over sandy silt loam
soil. The work is within 200 ft. of the ordinary high water mark of the Cedar River
The North area of the Cedar River has abundant variety of fish and wildlife
No trees will be removed. No vegetation to be disturbed along the bank
.
No views will be obstructed by the proposed project
The project is 100% impervious surface
Cost of the project is 178,000