HomeMy WebLinkAboutC18006619 TCP B - ApprovedDEPARTMENT OF PUBLIC WORKS
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 1 of 2 | Published: 11/25/2019
Transportation Division | 1055 South Grady Way, 5th Floor | Renton, WA 98057 | 425-430-7380
Website: rentonwa.gov
TRAFFIC CONTROL PLAN (TCP) APPLICATION
Published: 11/25/2019
TRAFFIC CONTROL PLAN (TCP) MUST BE SUBMITTED TO PUBLIC WORKS TRANSPORTATION DIVISION
FOR REVIEW/APPROVAL NO LATER THAN FIVE (5) WORKING DAYS BEFORE THE DATE OF WORK.
The City of Renton requires any contractor, firm, corporation, or other public/private agency to prepare a TCP and
obtain City of Renton's approval of that plan when construction, repair, or maintenance work is to be conducted
within the city's right-of-way.
TO THE APPLICANT: Submit the TCP application form and required submittal documents to
TCP@rentonwa.gov with the subject line “TCP Application – [Project Name]” or the above address.
The following items, electronic copies preferred, are all required for submittal of the TCP Application:
1.☐ A copy of the Traffic Control Plan (TCP) Application form.
2.☐ A copy of the required TCP layout, preferred 11” X 17” paper size format, which shall:
☐Include map(s) showing the location of the project and work area.
☐Be legible lettering and clear, contrasting, symbols of viewing or printing.
☐Must indicate street names, and north arrow and scale.
☐All signs and detour routes shall conform to the MUTCD, WSDOT TCPs, and the Washington State
Traffic Control Flagger Certification handbook, by the Evergreen Safety Council.
☐Types of plans required:
☐Work hour plan – show all mobility impacts during construction hours.
☐Non-work plan - show all mobility impacts after work hours when limited or no work is
happening in the right-of-way (ROW), if applicable.
☐Changing construction phases – show construction sequence and each construction phase
change even if the traffic control is not modified, if applicable.
☐Pedestrian access/detour plan, if applicable.
Project Name: ______________________________________________ Permit #: _____________________
Project Address: ____________________________________________________________________________
Work Date: From _____________ To _____________ Work Time: Start ______________ End ______________
Description of Work, Work Schedule, Equipment Used: _____________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Construction Company: ________________________________________ Phone/Cell: (_____) _____-________
Applicant Name: _________________________________ Email: ______________________________________
Business Address: _________________________________ City/State: __________________ Zip: __________
Approved By: _______________________________________________ Date: ________________________
Transportation Operations Engineering
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 2 of 2 | Published: 11/25/2019
APPLICANT AGREES TO ALL THE FOLLOWING:
•TCP must be approved prior to commencing the work, and all permit conditions shall be met.
•Existing pedestrian access shall be maintained. The work on pedestrian facilities shall be limited to one corner
at a time, with the least possible inconvenience or delay to pedestrians.
•Signage shall be used to warn motorcyclists/bicyclists of the potential hazards on any uneven surfaced or
slippery road conditions during work and non-work hours.
•The start of Work Time begins when any street or travel lane is fully/partially closed or impacts the follow of
traffic. This includes set up within the traveled way or immediately adjacent to the roadway.
•Emergency services (253-852-2121) shall be notified twenty-four (24) hours before any street or lane closures.
•Contractor or entity must call Renton School District (425-204-4455) or any public/private agency, including
public transit, to be affected by a temporary lane or road closure.
•TCP for all street and/or lane closures shall be implemented and performed in compliance with the Manual on
Uniform Traffic Control Devices (MUTCD) and/or State of Washington Department of Transportation (WSDOT)
and all traffic regulations of the City of Renton and Revised Code of Washington (RCW).
•Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of RCW 47.36.200 Signs or
Flaggers at thoroughfare work sites and RCW 9A.36.050 Reckless Endangerment, and other applicable State
and City codes.
•Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments, including all
costs of defense and attorney’s fees incurred in defending against same, arising from and related to
implementation of the approved traffic control plans including claims arising from towing of private vehicles
and the acts of the Applicant’s agents and employees.
•The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or judgment, and
in such event shall indemnify and hold harmless the City for any such claims paid, including the City’s
reasonable attorney’s fees and litigation costs incurred resulting from such claim.
•In the event any claim or suit is brought against the City within the scope of this Agreement, Applicant will pay
for legal counsel chosen by the City to defend against same.
•Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address traffic or
pedestrian safety or travel.
•Total road closure lasting more than twenty-four (24) hours is subject to the approval by the City Council.
•Approved Temporary TCP must be at the work site during work hours.
•Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded to safely redirect pedestrians around a work zone.
•Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
•Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations
for vacate parking or curb lane usage.
•Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
seventy-two (72) hours in advance of effective date and time.
•The cover sheet of this TCP form must be attached to each Temporary No Parking Sign on the project site.
•Temporary traffic control devices must be removed immediately when work is done or no construction
activities are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance
shop (3555 NE 2nd Street; 425-430-7423).
_______________________________ _______________________________ _______________________
Applicant’s Signature Print Name Date
UNION AVE NE
UNION AVE NE
NE 24th StNE 25th PlNE 27th PlSE 95th Way200 ft
SLOW
SLOW
200 ft200 ft
200 ft 200 ft 100 ft
100 ft
100 ft
100 ft
100 ft
100 ft
100 ft
X X X
X
X
X
X
X
X X X
ROADWORKAHEAD
ROADWORKAHEAD
ROADWORKAHEAD
ROAD
WORKAHEAD ONE LANEROADAHEAD
ONE LANEROADAHEAD
ONE LANEROADAHEAD
ONE LANEROADAHEAD
SLOW
50' MIN
100' MAX
6 DEVICE MIN
100 ft
TCP: Union Ave NE NScale:
All Signs & Spacing to conform to the MUTCD SPEED
LIMIT
30
Legend
Work Area
Class B Sign
ConeSLOW
flagger
Manifest
30 x Cone
4 x W20-1 road work ahead
4 x W20-7a flagger
4 x W20-4 one lane road ahead
Date:2/24/2020 Author:Anthony Stordahl, TCS #010394 Exp 7/31/2020Phone:(206)372-1452Email:antstordahl@yahoo.com Anthony Stordahl Consulting, LLC:.
Comments:
Work hours/days: M-F, 7:00 AM –3:30 PM Sat 9:00am-3:30pmType of work to be done: Utilities and Paving
(1) All spacing may be adjusted to accommodate interchange ramps,at-grade intersections, and driveways.(2) The spacing may be reduced in urban areas to fit roadway conditions
RURAL HIGHWAYS
RURAL ROADS
ALL SIGNS ARE 48'' X 48'' BLACK ON ORANGE UNLESS OTHERWISE DESIGNATED.
RURAL ROADS & URBAN ARTERIALS
60/65 MPH
45/55 MPH
35/40 MPH
800'
SIGN SPACING=X (FEET) (1)
500'
350'
FREEWAYS & EXPRESSWAYS 55/70 MPH 1500 (OR ASPER MUTCD)
RURAL ROADS, URBAN ARTERIALSRESIDENTIAL & BUSINESS DISTRICTS 25/30 MPH 200'
URBAN STREETS 25 MPH OR LESS 100'
(2)
(2)CHANNELIZING DEVICE SPACING (FEET)
MPH TAPER TANGENT
50/70
35/45
25/30
40
40
30
20
80
60
Contact Info:
Hos Bros Construction
Mike Harding
425-864-4550
www.invarion.com
UNION AVE NE
UNION AVE NE
NE 24th StNE 25th PlNE 27th PlSE 95th Way200 ft
SLOW
SLOW
200 ft200 ft
200 ft 200 ft 100 ft
100 ft
100 ft
100 ft
100 ft
100 ft
100 ft
X X X
X
X
X
X
X
X X X
ROADWORKAHEAD
ROADWORKAHEAD
ROADWORKAHEAD
ROAD
WORKAHEAD ONE LANEROADAHEAD
ONE LANEROADAHEAD
ONE LANEROADAHEAD
ONE LANEROADAHEAD
SLOW
Steel sheets over trenches
trenches backfilled with crushed
rock to surface. To maintain
access to NE 27th Pl
50' MIN100' MAX
6 DEVICE MIN
100 ft
TCP: Union Ave NE NScale:
All Signs & Spacing to conform to the MUTCD SPEED
LIMIT
30
Legend
Work Area
Class B Sign
ConeSLOW
flagger
Manifest
26 x Cone
4 x W20-1 road work ahead
4 x W20-7a flagger
4 x W20-4 one lane road ahead
Date:2/24/2020 Author:Anthony Stordahl, TCS #010394 Exp 7/31/2020Phone:(206)372-1452Email:antstordahl@yahoo.com Anthony Stordahl Consulting, LLC:.
Comments:
Work hours/days: M-F, 7:00 AM –3:30 PM Sat 9:00am-3:30pmType of work to be done: Utilities and Paving
(1) All spacing may be adjusted to accommodate interchange ramps,at-grade intersections, and driveways.(2) The spacing may be reduced in urban areas to fit roadway conditions
RURAL HIGHWAYS
RURAL ROADS
ALL SIGNS ARE 48'' X 48'' BLACK ON ORANGE UNLESS OTHERWISE DESIGNATED.
RURAL ROADS & URBAN ARTERIALS
60/65 MPH
45/55 MPH
35/40 MPH
800'
SIGN SPACING=X (FEET) (1)
500'
350'
FREEWAYS & EXPRESSWAYS 55/70 MPH 1500 (OR ASPER MUTCD)
RURAL ROADS, URBAN ARTERIALSRESIDENTIAL & BUSINESS DISTRICTS 25/30 MPH 200'
URBAN STREETS 25 MPH OR LESS 100'
(2)
(2)CHANNELIZING DEVICE SPACING (FEET)
MPH TAPER TANGENT
50/70
35/45
25/30
40
40
30
20
80
60
Contact Info:
Hos Bros Construction
Mike Harding
425-864-4550
www.invarion.com
UNION AVE NEUNION AVE NENE 27TH PL
TRANSFER
TRANSFER
RE-PULL
1Ø 1/O
40.5'30'
25'
25'
27'
27'
NE 27TH
P
L
10.5' ROW
DEDICATION
10.5' ROW
DEDICATION FEEDPRE14ABCN336.4ACSR336.4ACSRC4/OACSRABCN
4/OACSRTRANSFER 4/OACSRABCN
ABCN
#2ACSR
ABCN
4/OACSRC#4ACSR
'A''B'
'C''D'
'E'
TRANSFER
25.0'
5.0'
5.0'
40.5'30'
2.0'
8.0'
0.5'New R.O.W.New R.O.W.R.O.W.R.O.W.C/LC/L5.0'
2-2" Sch.80 1-6" Sch.80
1-4" Sch.801-3" Sch.80
2-3" Sch.80
1-4" Sch.80
1-6" Sch.80
10.5' ROW
DEDICATION
UNION AVE NEEASEMENTEASEMENTUNION AVE NETHIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL (800) 424-5555
2 BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
DESIGNED BY
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
LEE BROWN 425.417.8620 4.01.21
A. DUNN 206.437.9150 7.21.21
...
J.COSSETTE 206.584.4408 6.13.21
REDT # ( RW-112327 )RENTON/ KING COUNTY
FOREST TERRACE SCH 73
SCHEDULE 73 OH-UG CONVERSION - 2 SPANS
2611 UNION AVE NE, RENTON, WA 98059
PUGET SOUND ENERGY
..
.101140385
AS SHOWN 3 OF 5
KING N/A N/A QCSOKE
NE 4-T23N-R05E N/A N/A
2305E013 2305E040 2305E013 PRE-14
COMCAST
JAMES COHN
253.569.0636
CENTURYLINK
KENNETH LUU
206.346.0144
RENTON SCHOOL DIST.
.
.
PSE RIGHT OF WAY
AMBER YANG
425.456.2774
...
...
...
CIRCUIT FEET REMOVED:486'
CIRCUIT FEET ADDED: 455'
1"=50'
SITE PLAN
SITE SPECIFIC NOTES
AT P01 (319075-167131) 1986 CL1 - 40'
-TRANSFER 3Ø 4/O ACSR OH FEEDER & NEUTRAL (N&S) TO P1A
-REMOVE OH SEC TPX (N&S)
-TRANSFER EX 50kVA OH TRF TO P1A
-REMOVE ALL PSE FACILITIES & TOP POLE 1' ABOVE COMM
-COMM TO TRANSFER TO P1A
-REMOVE POLE (2ND TRIP)
AT P1A (NEW)
-INSTALL NEW 45FT CLASS 1 POLE (PD451) 6010.1000 PER STAKED
LOCATION
-INSTALL EXISTING 3Ø TERM ON NEW 3Ø TANGENT FIBERGLASS 2
ACSR ARM (TANC312) 6033.2010
-INSTALL EXISTING 50kVA OH TRF FROM P01
-TRANSFER 3Ø 4/O ACSR OH FEEDER &-ADD AMR 54404
-INSTALL GRID #319068-167131
AT P02 (319092-167131) 1969 CL1 - 40'
-DISCONNECT OH SEC TPX TO 2616 & TRANSFER TO P05
-REMOVE OH SEC TPX TO 2611
-REMOVE POLE AND ALL PSE EQUIPMENT
AT P2A (NEW)
-INSTALL NEW 50FT CLASS H1 POLE (PD50H1) 6010.1000 PER STAKED
LOCATION
-INSTALL 200A/600A 3Ø DBL TERM (TSU6D31) ON NEW 3Ø TANGENT
FIBERGLASS 339 AAC ARM (TANC313) 6033.2012
-INSTALL (3) STIRRUPS (2254100)
-INSTALL (1) NEW 6" FEEDER RISER ON NEW STNADOFF BRACKETS
(RIS6CSS) 6042.1000
-INSTALL (1) NEW 4" PRI RISER ON NEW STANDOFF BRACKETS
(RIS4CSS) 60421000
-INSTALL NEW GRID#319081-167131
AT P03 (319112-167131) 1961 CL1 - 40'
-REMOVE UG SEC TPX - SPLICE TO RE-FEED FROM V01 (SPL10J)
6041.2000
-REMOVE OH 1Ø 2" PRIMARY UP TO IP1
-REMOVE 25kVA OH TRF
-REMOVE AMR UNIT 54404
-REMOVE 40T SOLID BLADE SWITCH
-REMOVE POLE AND ALL PSE EQUIPMENT
Installed at site:
Grid Number:
kVA Rating:
TRANSFORMER INSTALLATION (OH)
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
Material ID#:
Foreman to redline the following information
50kVA 120/240v
6211350
P1A
319068-167131
1"=10'
SITE DETAIL 'A'
SITE DETAIL 'A'
Developer Note:
The following Fault Current information MUST BE conveyed
to the builder of the units:
All units may require upgraded house electrical equipment as the
fault current at the meter base may exceed 10,000 amps.
FAULT CURRENT TABLE
3075$16)250(569
120V WINDINGS 240V WINDINGS
LOCATION SIZE R/X MIN.
%Z
FAULT
CURRENT
MIN.
%Z
FAULT
CURRENT
V01 75KVA 0.5 2.30 36,200 1.80 23,100
DEVELOPER TO COORDINATE WITH PSE
PROJECT MANGER & SERVICE PROVIDER
PRIOR TO EXCAVATING WITHIN 3' OF
LOCATE MARKS OF PSE ENERGIZED
FACILITIES
SPAN NOTES
P01 TO P1A
-REMOVE ± 25' 4/0 ACSR AS NEEDED
REMOVED ( ') 4/0 ACSR
-TRANSFER EX OH 4/0 ACSR TO NEW P1A
P01 TO P02
-REMOVE ± 145' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-TRANSFER EX 4/0 ACSR SVC TO NEW P2A
P02 TO 2616
-REMOVE ± 115' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-TRANSFER EX OH TPX SEC TO NEW P05
P02 TO P03
-REMOVE ± 115' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-TRANSFER EX OH TPX SEC TO NEW P05
P2A TO P4A
-INSTALL ± 460' 397.5 MCMAAC FEEDER
INSTALLED ( ') 397.5 NCNAAC FEEDER
P03 TO IP1
-ABANDON ± 135' 2" DB120 CONDUIT
ABANDONED ( ') 2" DB120 CONDUIT
P03 TO 2623
-REMOVE ± 35' OH TPX SEC AS NEEDED
REMOVED ( ') OH TPX SEC
-SPLICE TAIL SP1 TO V01
P03 TO P04
-REMOVE ± 255' 4/0 ACSR AS NEEDED
REMOVED ( ') 4/0 ACSR
P04 TO P4A
-INSTALL ± 35' #2 ACSR OH PRIMARY AS NEEDED
INSTALLED ( ') #2 ACSR OH PRIMARY
P05 TO 2616
-TRANSFER EX OH TPX SEC TO NEW P05
TRANSFERRED ( ') OH TPX SEC
CROSSING CONDUIT TABLE
X-ING
#
LOCATION POWER
XING
LENGTH
ASBUILT
LOCATION
TYPE OF CROSSING
(Feeder, Primary, Secondary,
etc.)FROM TO
SIZE
(IN)TYPE QTY
X01 'A''B'3 SCH80 1 80 ( )'SCL SECONDARY
X02 'C''D'2 SCH80 1 95 ( )'SCL PRIMARY
X03 'C''E'
2 SCH80 1 90 ( )'WCL FUT PRIMARY
4 SCH80 1 90 ( )'WCL PRIMARY
6 SCH80 1 90 ( )'WCL FEEDER
2" SCH80 GREY PVC = 185 FT 2" PVC PLUG /CAPS = 4
3" SCH80 GREY PVC = 80 FT 3" PVC PLUG /CAPS = 2
4" SCH80 GREY PVC = 90 FT 4" PVC PLUG /CAPS = 2
6" SCH80 GREY PVC = 90 FT 6" PVC PLUG /CAPS = 2
Removed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER REMOVAL
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
P03
319112-167131
25kVA
Removed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER REMOVAL
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
P01
319075-167131
50kVA
DEVELOPER TO PROVIDE TYPICAL 5' PSE
FRONTAGE EASEMENT FOR OPERATION
AND MAINTENANCE OF PSE EQUIPMENT.
EASEMENT TO BE CLEAR OF ALL BUILDING
OVERHANGS AND FOUNDATION FOOTINGS
1"=10'
SITE DETAIL 'B'
SITE DETAIL 'B'
SITE SPECIFIC NOTES CONT.
AT P04 (319151-167130) 2001 CL UNK - 45'
-AT EXISTING P04 INSTALL 10" SINGLE HELIX 1" ROD
PLATE ANCHOR (ANDH1) WITH ±30FT LEAD(S)
6012.1000
-INSTALL (2) 3/8 GUY STRANDS (GYD3SA) 6013.0100
-REMOVE EXISTING 3Ø 4/0 ACSR
-ROTATE TRANSFORMER BANK TO NORTH SIDE OF
POLE
-POLE TO REMAIN
AT P4A (NEW)
-INSTALL NEW 45' CLASS 1 POLE (PD451) 6010.1000
-INSTALL 200A/600A TERM (TSUD631) PER STD
6043.1022
-INSTALL FEEDER TERMINATION (3ɸ -
397.5MCMAAC) (TSU3DF1) 6043.1020
-INSTALL (3) WEDGE CONNECTORS (MID: 2368200)
-INSTALL (1) 6'' RISERS (RIS6CSS) 6042.1000
-INSTALL (1) 4'' PRIMARY RISER (RIS4CSS)
-INSTALL GRID #319127-167132
AT P05 (NEW)
-INSTALL NEW 35' CLASS 3 POLE (PS353) 6010.1000
-INSTALL NEW 3" SECONDARY RISER (RIS3CSS)
6042.1000
-INTERCEPT EXISTING OH SECONDARY TPX TO
2616
-INSTALL GRID #319091-167137
AT E01
-INSTALL NEW E MARKER (7668501)
AT E02
-INSTALL NEW E MARKER (7668501)
NEW:
%V DROP: 3.4 @ P05
% FLICKER: 3.7 @ P05
EXISTING:
% V. DROP: 1.6% @ P01
% FLICKER: 4.1% @ P01
NEW:
%V DROP: 3.5 @ SP1
% FLICKER: 3.7 @ SP1
EXISTING:
% V. DROP: 1.6% @ P03
% FLICKER: 4.1% @ P03