Loading...
HomeMy WebLinkAboutWater main at Shelton _ Forest Crest-082321 Request For Information Hos Job No.: 1981 Project Manager: Pat Carter Request Date 08/18/2021 Respond By 08/20/2021 Initiated By Cole Borseth RFI No. 1981-24 Spec Section Submittal Drawing No. C47 Addendum Schedule No. From: Hos Bros. Construction, Inc. Project: Forest Terrace To: Pulte Homes Attention: Lance Adams Subject: Water Main on Shelton Ave in Wall 12 Grid Status: New Requested Information: Heading North on Shelton Ave NE the new water main ends behind Wall 12 at STA 51+84.14 with a thrust block for future road extension. Prior to water main install roadway subgrade had to be established and compaction complete. Excavation of the water will impact the 20’ standard wall grid. -Please advise on how the grid should be replaced to not effect the design of the wall. -Is the thrust block per COR STD 300.6 acceptable this close directly behind back of wall? Notes: Response: Signature: Title: Date: Signature: Title: Date: IN COMPLIANCE WITH CITY OF RENTON STANDARDSTED-40-4048FOREST TERRACE PLAT PULTE GROUP, INC3535 FACTORIA BLVD S.E., #600 BELLEVUE, WA 98006FOREST TERRACE PLATLUA: 18-000124C: 18-006619FOREST TERRACE PLATPR: 18-0000817/15/2020 FOREST TERRACE PLAT WTR-27-4048W-404806S-404806WWP-27-4048SCALE: 1"=20' SCALE: 1"=5' SCALE: 1"=20' WATER UTILITY M.Mitchell 09/10/2020 DEVELOPMENT ENGINEERING MSippo 09/11/2020 WASTEWATER UTILITY Ann Fowler 09/10/2020