HomeMy WebLinkAboutEX09_ConstructionMitigation1 Construction Mitigation Description Chick-fil-A Restaurant 375 Rainier Ave S Renton WA 98055 11/21/21 Planning Division City of Renton 1055 South Grady Way, Renton, WA 98057 Proposed Construction Start Date: • Fourth Quarter, 2022 Hours of Operation: • Per City Restrictions “Commercial, multi-family, new single family and other non-residential construction activities shall be restricted to the hours between 7:00 a.m. and 8:00 p.m., Monday through Friday. Work on Saturdays shall be restricted to the hours between 9:00 a.m. and 8:00 p.m. No work shall be permitted on Sundays”. • Majority of the work will be performed Monday through Friday from 7am to 5pm. Proposed Hauling/Transportation Routes: • Access from Rainier Ave and Renton. Measures to be implemented to minimize dust/traffic/erosion/mud/noise: • Temporary fencing will be provided around the perimeter of the subject site • Erosion control measures will be provided as required by the City. • Construction noise will be limited to the allowed hours of construction established in the City code. No special hours of operation are anticipated. Estefania Escamilla 4G Development & Consulting, Inc. Phone: 619-654-4431 Email: eescamilla@4gdev.com Address: PO BOX 270571, San Diego, CA 92198 Phasing: The goal is to always have the DT open in some form. Because we have the ability to demo curbs and pour new DT on the northern part of the site, we should be able to make all transitions on Saturday evening/Sunday for Monday green light. We will make sure we have clear signage, striping, and delineation to keep traffic flow moving. All vehicles will have the same access as they currently do. Once we are ready to transfer from current DT to new DT the access point on Rainier will change. The access point will be a little more north, and then we will close off the current access point to finish Phase 4. and delineators to keep the traffic flow moving. · How will circulation through the site work during construction? Once the driveway on Rainier is closed, will vehicles be forced to access the site to/from the signal at S 3rd Place?All vehicles will have the same access as they currently do. Once we are ready to transfer from current DT to new DT the ac- cess point on Rainier will change. The ac- cess point will be a little more north, and then we will close off the current access point to finish Phase 4. I can hope on a call with yourself or TENW to explain. To reiter- ate, it is our goal to always have the DT open and street access open. How will circulation through the site work during construction? Once the driveway on Rainier is closed, will vehicles be forced to access the site to/from the signal at S 3rd Place?All vehicles will have the same access as they currently do. Once we are ready to transfer from current DT to new DT the ac- cess point on Rainier will change. The ac- cess point will be a little more north, and then we will close off the current access point to finish Phase 4. I can hope on a call with yourself or TENW to explain. To reiter- ate, it is our goal to always have the DT open and street access open. EXHIBIT 9 RECEIVED 12/15/2021 AVanGordon PLANNING DIVISION DocuSign Envelope ID: F94832C8-5168-46AD-9392-B611DC851286