UTILITY MEMO
60% Draft Report
King County Department of Transportation
Communications
King County Department of Transportation
Rob Mattern, Project Manager
Kale Chang Yuen, Project Engineer
Ian Kowalski, Capital Projects
HDR Inc.
Michael Starling, Civil/Utility P.E., Kent Utility Lead
Joe Griffin, Civil/Utility P.E.
Joel Corlew, Civil/Utility E.I.T
Jacobs Engineering, Inc.
Scott Bareither, PMP, LEED AP BD+C, Civil/Utility, Renton & Auburn Utility Lead
Mohammad Khan, Civil/Utility
Chris Pylant, Civil/Utility INCE
Luke Saladin, Civil/Utility
1 I Line 60% Draft Utility Memo
Contents
1.0 Introduction ................................................................ 3
1.1 Project Background ................................................................ 3
1.2 Utility Elements ...................................................................... 3
2.0 Utility Ownership & Base Map ...................................... 3
2.1 Record Drawings within the City of Renton ............................. 3
2.1.1 Renton Base Map Verification ............................................ 3
2.2 Record Drawings within the City of Kent ................................. 4
2.2.1 Kent Base Map Verification ............................................... 4
2.3 Record Drawings within the City of Auburn ............................. 4
2.3.1 Auburn Base Map Verification ............................................ 4
2.4 Field Survey ........................................................................... 4
2.4.1 Potholes ........................................................................ 4
3.0 Potential Utility Conflicts .............................................. 5
4.0 Recommended Pothole Locations ............................... 18
5.0 Utility Contacts .......................................................... 19
Tables
Table 3-1 Renton Potential Utility Conflicts .............................................................. 6
Table 3-2 Kent Potential Utility Conflicts ............................................................... 10
Table 3-3 Auburn Potential Utility Conflicts ............................................................ 16
Table 4-1 Renton Recommended Pothole Locations ................................................ 18
Table 4-2 Kent Recommended Pothole Locations .................................................... 18
Table 4-3 Auburn Recommended Pothole Locations ................................................ 19
Table 5-1 Utility Contact Information ................................................................... 19
2 I Line 60% Draft Utility Memo
Appendix
This Page Intentionally left Blank.
3 I Line 60% Draft Utility Memo
1.0 Introduction
1.1 Project Background
King County Metro Transit (Metro) is planning to upgrade its existing Routes 169 and 180 to the
RapidRide I Line (I Line) bus rapid transit service. The existing Routes 169 and 180 provide service
between the cities of Renton, Kent, and Auburn, as well as portions of unincorporated King County.
The I Line improvements would include additional service along the route, upgraded RapidRide
branded buses, stops upgraded to stations, additional passenger amenities, and capital investments
along the route to improve transit speed and reliability.
1.2 Utility Elements
This Utility Memo discusses the creation of the utility base map, identifies utility conflicts with proposed improvements, and makes recommendations for future utility locate activities (potholing)
that are needed for the next stage in design.
2.0 Utility Ownership & Base Map
Utility record drawings and system maps have been requested from all franchise and
public utility owners. The sections below describe information that has been received to
date.
2.1 Record Drawings within the City of Renton
The City of Renton provided record drawings and GIS data for water, sanitary sewer, and storm drain
networks. CenturyLink provided schematics for their franchise utility aerial and underground
telecommunications network. PSE provided gas and electric field schematics for their network that
covers the entire Renton segment.
2.1.1 Renton Base Map Verification
A field visit was conducted over 3 days on December 8th, 14th, and 15th, 2020 to verify the information on the existing utility base map. In January 2021, field notes, finalized base maps, and survey
information was compared prior to finalization of this memo.
4 I Line 60% Draft Utility Memo
2.2 Record Drawings within the City of Kent
Record drawings were provided by the City of Kent for their water, sanitary sewer, and storm drain network. Soos Creek Water and Sewer District provided network information for their services which
cover part of the alignment in northeast Kent. CenturyLink provided schematics for their franchise
utility aerial and underground telecommunications network. PSE provided gas and electric field
schematics for their network that covers the entire Kent segment.
2.2.1 Kent Base Map Verification
A field visit was conducted over two days on October 9th and 10th, 2020 to verify the information on the existing utility base map. Observations in the field that differed from the existing utility base map
were recorded such as missing or mislabeled assets and previously unidentified conflicts with
proposed facilities. Further review, comparing field notes to the finalized base map completed in
November 2020 was completed prior to finalization of this memo.
2.3 Record Drawings within the City of Auburn
The City of Auburn provided record drawings for domestic water, sanitary sewer, and storm drain networks. CenturyLink provided schematics for their franchise utility aerial and underground
telecommunications network. PSE provided gas and electric field schematics for their network that
covers the entire Auburn segment.
2.3.1 Auburn Base Map Verification
A field visit was conducted over 3 days on December 8, 14, 15, 2020 to verify the information on the existing utility base map. In January 2021, field notes, finalized base maps, and survey information was
compared prior to finalization of this memo.
2.4 Field Survey
1Alliance provided survey services to develop the base map. The 1-800 Locate Center was called to provide painted utility marks that 1Alliance then surveyed. Full site survey is ongoing, to be
completed in the next phase of the project.
2.4.1 Potholes
Initial potholing was conducted by Allied Professional Services INC (APS) prior to the 60 percent
submittal and the transmitted to the design team.. The 60 percent utility plan set displays the pothole
locations with the utility depths and sizes or widths Additional potholes will be needed after the 60
percent design; locations to be determined.
5 I Line 60% Draft Utility Memo
Potholing was conducted and information field surveyed where civil improvements such as platforms, storm drains, curb revisions, retaining walls, etc., are near existing utility lines. Recommended pothole
locations are found in Section 4.0 of this report. The initial potholing results from APS are provided in
Appendix A. Plans with additional recommended pothole locations are in Appendix B.
3.0 Potential Utility Conflicts
The proposed improvements design, including roadway, drainage, signals, retaining walls, and station foundations, were reviewed to identify potential conflicts with existing utilities. Potential conflicts
occur largely where the curb line is being adjusted to accommodate bus platforms, new crosswalks,
roadway repaving, and where new storm facilities are proposed. Utilities that are pot entially impacted
by project construction are noted in the report. See Table 3-1, 3-2, and 3-3 for the identified conflicts
for each jurisdiction (cities of Renton, Kent and Auburn).
3.1 Identified Utility Conflicts
Renton:
As of the 60 percent design, there is a gas line, telecom lines, and underground electrical
lines along S Grady Way that need to be relocated by PSE and the third-party telecom
service provider. The relocations are between Lake Ave S and Talbot Rd S along S Grady
Way and along Talbot Rd S. There is also a PSE power pole that needs relocating at
Talbot Rd S and S 37th St. In addition to the third-party utilities, there are 3 fire hydrant
assemblies that need replacing.
Kent:
As of the 60 percent design there are two water main relocations within the Kent
segment. Southwest of SE 216th street the existing 12-inch water main conflicts with
proposed storm drainage system improvements. Further south, at the 235th Station, the
8-inch water main underneath the existing planter area on the west side of the roadway
conflicts with the proposed station platform. In addition to the water main replacements
6 fire hydrant assemblies are to be replaced due to various conflicts.
West of the 256th and 101st Ave SE intersection, a PSE owned pole with a guy wire is
anticipated to be replaced with an engineered pole due to the conflict with the proposed
retaining wall. Other preliminary pole relocations are shown in the plans in Appendix B.
Auburn:
As of the 60 percent design, there are telecom lines and underground electrical lines
along Auburn Way N that need to be relocated by PSE and the third-party telecom
service provider. Additionally, a PSE power pole needs relocating at Auburn Way N and
6 I Line 60% Draft Utility Memo
49th St NE. There is also 1 fire hydrant assembly that needs to be relocated and
replaced.
Additional utility relocations are anticipated in future phases of design.
Table 3-1 Renton Potential Utility Conflicts
CL Station Offset Street Utility Conflict Description
30+85 41' LT 108th Ave
SE Down guy
Proposed underground(?)
power distribution passes
very close to existing down
guy anchor
31+38 15' RT 108th Ave
SE
Overhead
power/telecom lines
Check conflict with proposed
Crosswalk signal mast arm
54+13 30' LT 108th Ave
SE Water valves Revised curb line through
valve cluster
54+28 29' LT 108th Ave
SE Storm catch basin
Revised curb line through
existing storm catch basin,
no replacement CB shown
16+96 69' LT S 2nd St Water valve In revised sidewalk
20+06 62' LT S 2nd St Storm catch basin In revised sidewalk
11+58 40' LT S Grady
Way
Underground Power
Line Proposed TS line crosses
11+58 40' LT S Grady
Way
Underground
Telcom line Proposed TS line crosses
15+08 56' LT S Grady
Way Junction box In revised roadway
16+15 37' LT S Grady
Way Fire Hydrant In revised roadway
17+09 31' LT S Grady
Way Junction box In revised roadway
17+30 31' LT S Grady
Way Junction box In revised roadway
18+28 34' LT S Grady
Way
Traffic Control
Cabinet? In revised roadway
18+51 32' LT S Grady
Way Junction box In revised roadway
7 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
20+53 32' LT S Grady
Way Junction box In revised roadway
20+58 38' LT S Grady
Way Water valve Revised curb line through
valve
22+08 50' LT S Grady
Way Telecom Cabinet In Sidewalk, low height could
be dangerous
22+63 33' LT S Grady
Way Junction box In revised roadway
22+74 51' LT S Grady
Way Light pole (private) In revised sidewalk
22+85 37' LT S Grady
Way Water Valve In revised roadway
23+13 43' RT S Grady
Way Junction box In revised roadway
24+19 47' LT S Grady
Way Fire Hydrant In middle of sidewalk
24+25 49' RT S Grady
Way Junction box In revised roadway
24+31 44' RT S Grady
Way Junction box In revised roadway
24+41 55' RT S Grady
Way Telecom Manhole In revised roadway
24+52 52' RT S Grady
Way
Underground Power
Line Proposed TS line crosses
10+54 46' LT Talbot Rd
S Junction box Revised curb line through
box
10+56 19' RT Talbot Rd
S Gas Line Proposed TS line crosses
10+57 63' RT Talbot Rd
S
Underground Power
Line Proposed TS line crosses
10+57 40' RT Talbot Rd
S Water Line Proposed TS line crosses
10+57 30' RT Talbot Rd
S Gas Line Proposed TS line crosses
10+58 58' RT Talbot Rd
S
Underground Power
Line Proposed TS line crosses
10+63 68' RT Talbot Rd
S
Underground Power
Line
Proposed stormwater
connection crosses
10+71 66' RT Talbot Rd
S Junction box In revised roadway
8 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
10+71 49' LT Talbot Rd
S
Telecom and Power
vaults
In middle of sidewalk,
change in grade?
10+89 59' RT Talbot Rd
S Junction box In revised roadway
10+92 58' RT Talbot Rd
S
Underground Power
Line
Proposed stormwater
connection crosses
10+97 51' RT Talbot Rd
S
Underground Power
Line
Proposed stormwater
connection crosses
11+03 57' RT Talbot Rd
S Junction box In revised roadway
11+07 57' RT Talbot Rd
S Streetlight In revised roadway
11+13 54' RT Talbot Rd
S Water valve In revised roadway
11+68 43' LT Talbot Rd
S
Red Light Camera
pole
Revised curb line through
pole
12+16 39' LT Talbot Rd
S Junction box In revised roadway
13+32 40' LT Talbot Rd
S Junction box In revised roadway
14+55 36' LT Talbot Rd
S Junction box In revised roadway
15+18 34' LT Talbot Rd
S Telecom Line Proposed stormwater
connection crosses
15+18 36' LT Talbot Rd
S
Underground Power
Line
Proposed stormwater
connection crosses
15+40 33' LT Talbot Rd
S Telecom Line Proposed stormwater
connection crosses
15+40 35' LT Talbot Rd
S
Underground Power
Line
Proposed stormwater
connection crosses
15+90 46' RT Talbot Rd
S Water Manhole In revised roadway
16+22 32' RT Talbot Rd
S Junction box In revised roadway
16+86 48' RT Talbot Rd
S Water Junction Box In revised sidewalk
16+86 45' RT Talbot Rd
S Water valve In revised sidewalk
16+86 41' RT Talbot Rd
S Water valve In revised sidewalk
9 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
16+89 47' RT Talbot Rd
S ICV In revised sidewalk
17+60 31' RT Talbot Rd
S
Light pole and
Junction box In revised roadway
21+78 48' RT Talbot Rd
S Telecom Line Proposed TS line crosses
existing telecom lines
21+88 49' RT Talbot Rd
S Telecom Line Proposed TS line crosses
existing telecom lines
22+37 43' RT Talbot Rd
S Water Line Parallel to CL. In street
concrete repaving area
22+44 49' RT Talbot Rd
S Telecom Line In street concrete repaving
area
22+44 48' RT Talbot Rd
S Telecom Line In street concrete repaving
area
22+54 115'
RT
Talbot Rd
S Water Line
Revised gutter on top of
water line running parallel to
Renton Village CL
25+45-
25+85
9-10'
RT
Talbot Rd
S Gas Line Parallel to CL. In street
concrete repaving area
25+45-
25+85 17' RT Talbot Rd
S Telecom Line
Parallel to CL. In street
concrete repaving area/under
revised curb
25+67 25' RT Talbot Rd
S Revised Curb Large rock under existing
bush in revised curb area
25+84 17' RT Talbot Rd
S Sewer Manhole Revised curb face crosses
through manhole
28+17 18' RT Talbot Rd
S Telecom Line Crosses under gutter
repaving
56+82-
57+43 26' RT Talbot Rd
S Drainage ditch
Proposed bus stop area will
encroach into drainage ditch,
need to replace with culvert
71+64-
73+95
12-14'
LT
Talbot Rd
S Water Line
Parallel to CL. Near revised
curb line or possibly in street
repaving area on either side
of 37th, in the repaving area
at intersection of 37th/Talbot
72+59 17' LT Talbot Rd
S Water Valve In street concrete repaving
area
73+10 16' LT Talbot Rd
S Water Line Relocated catch basin above
water line
10 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
73+46-
74+52
15-17'
RT
Talbot Rd
S Gas Lines Parallel to CL. In street
concrete repaving area
73+60 19' LT Talbot Rd
S Storm catch basin
In the middle of revised
sidewalk, no replacement
shown
73+74 25' RT Talbot Rd
S
Utility Pole/Street
Light
In revised street, no
replacement shown on roll
plot
73+97 15' RT Talbot Rd
S Gas Valve In street concrete repaving
area
73+98 15' RT Talbot Rd
S Gas Valve In street concrete repaving
area
88+11-
88+86
30-33'
LT
Talbot Rd
S
Underground Power
Line
In widened bus stop area,
which likely needs to be
graded lower
88+14-
88+87 11' LT Talbot Rd
S Telecom Line Parallel to CL. In street
concrete repaving area
88+36-
89+13
12-17'
RT
Talbot Rd
S Gas Lines Parallel to CL. In street
concrete repaving area
88+36-
89+31 8' LT Talbot Rd
S Water Line Parallel to CL. In street
concrete repaving area
89+08 13' RT Talbot Rd
S Gas Valve In street concrete repaving
area
Table 3-2 Kent Potential Utility Conflicts
CL Station Offset Street Utility Conflict Description
82+58 28’ RT 108th Ave SE Water Main Proposed storm catch basin
above existing water line
83+06 28’ RT 108th Ave SE Water Main Proposed storm catch basin
above existing water line
83+19 48’ RT 108th Ave SE Underground
Telecom
Communication pedestal
and underground line under
existing back of curb
101+37 32’ RT 108th Ave SE Water valves (3) Revised curb line through
valve cluster
101+68 38’ RT 108th Ave SE PSE Power Proposed storm catch basin
above underground power
11 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
102+53 43’ RT 108th Ave SE Utility Pole Revised curb line places
utility pole in sidewalk
103+00 48’ RT 108th Ave SE Telecom pedestal Revised curb line places
telecom pedestal in
sidewalk
104+02 49’ RT 108th Ave SE Hydrant Revised curb places hydrant
in curb line
104+12 54’ RT 108th Ave SE PSE Power Proposed wall is above PSE
power conduit
105+62 49’ LT 108th Ave SE Hydrant Fire hydrant and water
meter in proposed driveway
106+10 47’ LT 108th Ave SE Utility Pole Revised curb line is over
utility pole
108+16 16’ RT 108th Ave SE Water Valve Revised curb is adjacent to
valve
109+64 59’ RT 108th Ave SE Utility Pole Revised sidewalk places
utility pole in sidewalk
110+02 52’ LT 108th Ave SE Utility Pole Revised sidewalk places
utility pole in sidewalk
111+57 48’ LT 108th Ave SE Utility Pole and
guy wire
Revised sidewalk places
utility pole in sidewalk
111+62 37’ LT 108th Ave SE Underground
Telecom
Telecom conduit crosses
storm drain detention
facility
136+94 29’ RT Benson RD SE Hydrant valve Hydrant valve in revised
curb line
137+01 29’ RT Benson RD SE Water main Water main conflicts with
proposed storm drain
manhole
157+75 44’ LT Benson RD SE Cell Tower Cell tower in landscape area
39+17 27’ LT 104th Ave SE Water valves (3)
and Main
Station platform over water
main
49+54 31’ LT 104th Ave SE Water service,
meters,
standpipe, and
hydrant
Revised back wall conflicts
with water structures
12 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
49+78 36’ LT 104th Ave SE Gas service Revised back wall adjacent
to gas valve
51+06 38’ RT 104th Ave SE Water meter Water meter conflicts with
proposed curb line
51+33 50’ LT 104th Ave SE Sanitary Sewer Sanitary sewer MH in
sidewalk and sewer main
crosses proposed storm
51+63 33’ RT 104th Ave SE Water main, and
underground
power and
telecom
Multiple underground
utilities cross proposed
storm
52+76 40’ RT 104th Ave SE Water meter Water meter conflicts with
proposed sidewalk
55+80 50’ RT 104th Ave SE PSE Power Power transformer and
vault with underground
power lines in revised
sidewalk
56+35 41’ RT 104th Ave SE Hydrant Fire hydrant in revised
driveway and sidewalk
57+24 39’ RT 104th Ave SE Telecom Pedestal Pedestal in revised sidewalk
57+52 40’ RT 104th Ave SE Telecom Pedestal Pedestal in revised sidewalk
57+76 37’ RT 104th Ave SE Telecom Pedestal Pedestal in revised sidewalk
79+78 38’ LT 104th Ave SE Telecom MH TCMH in revised curb ramp
79+86 37’ LT 104th Ave SE Underground
Telecom
Telecom conduit conflicts
with proposed storm drain
catch basin
99+56 00’ 104th Ave SE Underground
Power
Underground power below
the proposed crosswalk
center curb
101+22 22’ RT 104th Ave SE Underground
power and
Telecom
Power vault and telecom
pedestal behind proposed
wall
101+26 40’ RT 104th Ave SE Power Pole Proposed wall over PSE Pole
102+49 40’ RT 104th Ave SE Hydrant Fire hydrant in revised
roadway
103+92 47’ RT 104th Ave SE Water meter Water meter in adjusted
roadway
104+30 48’ RT 104th Ave SE Water Meter Water meter in adjusted
roadway
13 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
104+33 44’ RT 104th Ave SE Utility pole Utility pole with
transmission, distribution
and communications lines in
curb line.
105+84 52’ RT 104th Ave SE Hydrant Hydrant in revised curb
ramp
17+75 47’ RT SE 256th Sanitary Sewer
MH
SSMH in revised sidewalk.
17+22 37’ LT SE 256th Power Pole Power pole conflicts with
proposed wall
17+04 50’ RT SE 256th Utility Pole Pole and guy in new
sidewalk and driveway
15+69 48’ RT SE 256th Utility Pole Guy wire support crosses
the revised sidewalk
15+70 49’ RT SE 256th Utility Pole Guy wire support in revised
sidewalk
15+46 17’ LT SE 256th Water main Water main conflicts with
proposed storm detention
facility
15+55 35’ RT SE 256th Sanitary Sewer
MH
Proposed storm line near
SSMH lid.
13+83 54’ RT SE 256th Utility pole Guy wire support crosses
the revised sidewalk
28+76 39’ RT E Smith Utility pole Utility pole with power
risers in revised bike lane
21+20 19’ LT E Smith Telecomm
Maintenance
Hole
Revised grade at MH
20+96 41’ RT E Smith Water meter Water meter is in revised
sidewalk
20+74 5’ LT,
14’ RT
E Smith Sanitary Sewer
Maintenance
holes (2)
Revised grade at MH
20+59 14’ LT,
8’ LT
E Smith Telecomm
Maintenance
Holes (2)
Revised grade at MH
14 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
20+33 9’ RT E Smith Sanitary Sewer
Maintenance hole
Revised grade at MH
20+20 34’ RT E Smith Water meter Water meter is in revised
traffic lane
19+35 34’ RT E Smith Water Meter Revised curb line is
adjacent water meter
18+88 33’ RT E Smith Telecom Vault Telecom vault in revised
curb line
18+65 39’ RT E Smith Power Vault,
Transformers,
and telecom
pedestal
Revised curb line is
adjacent several power and
telecom utilities
17+91 21’ RT E Smith Underground
power and
telecom
Underground power and
telecom cross proposed
storm
17+03 53’ LT E Smith Hydrant Proposed curb ramps in
between existing hydrant
16+82 17’ LT E Smith Water Valve Revised grade at valve
16+80 44’ LT E Smith Telecom
Pedestals (2)
Revised sidewalk places
telecom pedestals in
walkway
16+70 48’ RT E Smith Utility pole Revised curb places utility
pole with telecom lines in
road
16+62 10’ LT E Smith Telecomm
Maintenance
Hole
Revised grade at MH
16+45 22’ RT E Smith Underground
power and
telecom
Underground power and
telecom cross proposed
storm
16+44 1’ RT E Smith Water Valve Revised grade at valve
16+29 13’ LT E Smith Water Valve Revised grade at valve
16+20 78’ LT E Smith Guy Wire Guy wire in revised curb
16+14 44’ LT, E Smith Hydrant Revised curb line places
hydrant in sidewalk
15+63 27’ RT E Smith Water Meter Revised meter at valve
15+31 28’ RT E Smith Water Meter Revised meter at valve
14+96 16’ LT E Smith Gas valve Revised grade at valve
15 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
14+96 17’ RT E Smith Sanitary Sewer
Maintenance
Hole
Revised grade at MH
14+94 29’ RT E Smith Power and
Telecomm vault
Revised curb line places
vaults in roadway
14+81 17’ RT E Smith Sanitary Sewer
Maintenance
Hole
Revised grade at MH
14+81 35’ RT E Smith Sanitary Sewer
Maintenance
Hole
Revised curb line is
adjacent to MH lid
14+95 17’ RT E Smith Sanitary Sewer
Maintenance
Hole
Revised grade at MH
14+80 4’ LT E Smith Gas valve Revised grade at valve
14+80 20’ LT E Smith Water valve Revised grade at valve
14+64 48’ LT E Smith Hydrant Proposed hydrant in revised
sidewalk
14+15 34’ RT E Smith Water Meter Revised curb line places
meter on sidewalk
13+70 43’ LT E Smith Hydrant Revised curb line places
hydrant in sidewalk
13+70 13’ LT E Smith Water Valve (2) Revised grade at valve
13+44 13’ LT E Smith Water valve Revised grade at valve
13+03 16’ LT E Smith Water valve Revised grade at valve
13+40 60’ LT E Smith Storm Drain MH Revised grade at MH
13+50 30’ LT E Smith Storm Drain MH Revised grade at MH
12+90 30’ RT E Smith Storm Drain MH Revised grade at MH
11+82 27’ RT E Smith Telecomm
Maintenance
Hole
Revised grade at MH
11+82 37’ RT E Smith Power and
Telecomm vault
Revised curb line places
power and telecom vaults in
sidewalk
11+62 15’ RT E Smith Sanitary Sewer
Maintenance
Hole
Revised grade at MH
16 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
11+62 37’ LT E Smith Sanitary Sewer
Maintenance
Hole
SSMH in revised driveway.
10+56 42’ RT E Smith Utility pole Revised curb places utility
pole in pedestrian ramp
10+47 15’ LT E Smith Water valve Revised grade at valve
10+47 45’ RT E Smith Hydrant Revised curb places hydrant
between pedestrian ramps
10+31 27’ RT E Smith Power
Maintenance hole
Revised grade at MH
9+70 30’ LT E Smith Gas valve Revised grade at valve
11+06 26’ RT Railroad Ave
N
Utility Pole Utility pole in proposed
station
11+81 26’ RT Railroad Ave
N
Utility Pole Utility pole in proposed
station
20+75 32’ LT Central Ave N Utility Pole Utility pole in proposed
station
37+59 41’ LT Central Ave S Guy Wire Guy wire in proposed
station
Table 3-3 Auburn Potential Utility Conflicts
CL Station Offset Street Utility Conflict Description
19+09 38' RT Auburn Way N Utility Pole Existing Utility pole located
in proposed sidewalk
50+81 39' RT Auburn Way N Light pole Light pole located in
proposed
pavement/driveway
63+16 27' LT Auburn Way N Storm Drain Existing storm drain
passes through proposed
curb/gutter/pavement.
63+75 29' LT Auburn Way N Utility/Illumination
Pole
Existing utility/Illumination
pole (with risers) conflicts
with the light on the
proposed illumination pole.
114+00 44' LT Auburn Way N Storm sewer line Storm sewer line seen in
CAD file (not on roll plot)
17 I Line 60% Draft Utility Memo
CL Station Offset Street Utility Conflict Description
runs through asphalt that
is being removed for
proposed landscaping.
115+56 35' RT Auburn Way N Underground
Telecom line
Proposed
illumination/electrical work
crosses existing
underground telecom line
135+40-
135+70
30-60'
RT
Auburn Way N Multiple Utilities Relocated signals will
probably include relocation
of many other associated
utilities. Check carefully in
this area
136+10 46' RT Auburn Way N Monitoring Well In revised bus shelter
footprint/sidewalk
136+27 34' RT Auburn Way N Telecom Manhole In revised roadway
136+32 38' RT Auburn Way N Telecom Cabinet In revised roadway
136+41 38' RT Auburn Way N Unknown Water
equipment
In revised roadway
150+72 44' RT Auburn Way N Telecom manhole Revised gutter in driveway
goes through manhole
151+18 48' RT Auburn Way N Fire hydrant In middle of revised
sidewalk
151+61 36' RT Auburn Way N Existing standpipe Revised catch basin
appears to overlap or near
existing standpipe
151+87 45' RT Auburn Way N Existing standpipe Revised catch basin
appears to overlap or near
existing standpipe
152+06 53' RT Auburn Way N Power Vault In revised sidewalk,
changed grade
152+34 32' LT Auburn Way N Fire Hydrant Proposed power vault
overlaps, or will be near
fire hydrant
152+75 42' RT Auburn Way N Traffic Junction
Box
In revised street, changed
grade
18 I Line 60% Draft Utility Memo
4.0 Recommended Pothole Locations
Following review of the base map and proposed improvements, recommended locations
for utility potholes were developed for each jurisdiction. Potholes are recommended at
locations that have potential utility conflicts, in order to identify solutions in the next
phase of the project. Plans showing the recommended pothole locations are included in
the appendix.
Table 4-1 Renton Recommended Pothole Locations
Pothole Utility Street Centerline
Station
Offset Pothole Description
1 New Potholes -
TBD
New pothole
Locations will be
needed for 90P
design.
Table 4-2 Kent Recommended Pothole Locations
Pothole Utility Street Centerline
Station
Offset Pothole Description
1
Underground
Telecom 108th Ave SE 82+50 40’ RT
Verify elevation of
telecom lines from
pedestal at existing
back of curb. APS
Pothole 34 was
evaluated ~4' west of
memo location. Re-
pothole in directed
location
2 Water main 108th Ave SE 136+95 27’ RT Verify size and
elevation
3 Water main 104th Ave SE 38+20 29’ RT Verify size and
elevation
4 Water main 104th Ave SE 39+17 12’ RT Verify size and
elevation
19 I Line 60% Draft Utility Memo
Pothole Utility Street Centerline
Station
Offset Pothole Description
5 Underground
Power and
telecom
E Smith 17+91 21’ RT Verify size and number
of underground power
6
Underground
Power E Smith 17+53 62’ RT
Verify elevation of
underground power
crossing proposed
storm
7
Power and
telecom E Smith 16+45 27’ RT
Verify size and location
of underground power
and telecom crossing
proposed storm
8
Underground
power E Smith 13+52 63’ RT
Verify number and
location of
underground power
lines
Table 4-3 Auburn Recommended Pothole Locations
Pothole Utility Street Centerline
Station
Offset Pothole Description
1 New Potholes
- TBD
New Pothole locations
needed for 90P design.
5.0 Utility Contacts
Contact information for public and franchise utilities is listed in Table 5-1.
Table 5-1 Utility Contact Information
20 I Line 60% Draft Utility Memo
Utility Contact
City of Renton Renton Map Support
RentonMapSupport@Rentonwa.gov
City of Kent Brennan Taylor
Btaylor@KentWA.gov
(253) 856-5591
City of Kent Jamie Warning Simo
Jsimo@KentWA.gov
(253) 856-5490
City of Auburn Shawn Campbell, City Clerk at
scampbell@auburnwa.gov
Hannah Scholl, Records Clerk at
hscholl@auburnwa.gov
Puget Sound Energy
(Gas)
Glenn Helton
Glenn.Helton@pse.com
(425) 559-4647
Puget Sound Energy
(Power)
Hong Nguyen
Hong.Nguyen@pse.com
(425) 449-6609
Soos Creek Water and
Sewer District
Ken VanDenBergh
KVan@sooscreek.com
14616 SE 192nd St
RENTON, WA 98058
(253) 893-7615
(425) 531-4114
Sirena Clark
Lead, Development Administration
253.630.9900 ext 107
CenturyLink Kelly Casteel
kcasteel@terratechllc.net
(206) 353-6847
CenturyLink Phil Stevens
pstevens@terratechllc.net
(360) 970-4902
21 I Line 60% Draft Utility Memo
Utility Contact
Comcast Danny Cooley
Danny_Cooley@cable.comcast.com
410 Valley Ave NW
Puyallup, WA 98371
(253) 686-7592
Zayo Jason Tesdal
Jason.Tesdal@zayo.com
(253) 221-7585
22 I Line 60% Draft Utility Memo
Appendix A: 30% Potholes
23 I Line 60% Draft Utility Memo
Appendix B: 60% Utility Plans
24 I Line 60% Draft Utility Memo
Appendix C: 60% Drainage Plans
25 I Line 60% Draft Utility Memo