HomeMy WebLinkAboutLUA02-022 STAFF REPORTREPORT City of Renton Department of Planning / Building / Public Works & DECISION ENVIRONMENTAL REVIEW & ADMINISTRATIVE LAND USE ACTION DECISION DATE: March 20, 2002 Project Name: Boeing Binding Site Plan Applicant/Owner. The Boeing Company File Number. • LUA-02-022, ECF, BSP Project Manager., Lesley Nishihira Project Description: The proposal is to subdivide a 157.8-acre site into 5 utility tracts and 35 lots intended for future commercial or office development. The creation of access and utility easements, as well as the installation of required plat improvements, would occur as necessary with site specific development proposals. Site preparation activities may also occur in advance of individual site plan proposals for the installation of required plat improvements. Such earthwork activities are estimated at an average of 4,500 cubic yards per parcel. If necessary, additional SEPA and Site Plan review will be required at the time of site specific development proposals. Project Location: Between Oakesdale Avenue SW & BNRR R-O-W; South of SW 16th Street & North of SW 29th Street Exist. Bldg. Area SF.' 80,697 sf Proposed New Bldg. Area SF: N/A Site Area: 157.8-acres Total Building Area SF.- N/A Project Location Map bsprpt City of Renton P/B/PW Department - Adrr,. trative Binding Site Plan Approval & Environrn. ll Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 2 of 10 11 PART ONE: PROJECT DESCRIPTION/BACKGROUND The applicant is requesting Environmental (SEPA) Review and Binding Site Plan approval for the subdivision of a 158- acre site into 35 lots, ranging in size from 2.11-acres to 5.4-acres, as well as 5 tracts starting at 1.6-acres to 14.61- acres in size. The lots are intended for future commercial or office development and would require additional SEPA and Site Plan review at the time of individual, site specific development proposals. The property is currently undeveloped with the exception of the existing BCAG Headquarters and Family Care Center buildings, as well as portions of the existing storm water detention pond which serves the site. An 11-acre wetland and conservation area is contained in the southernmost area of the property. The creation of access and utility easements, as well as the installation of required improvements, would occur as necessary with site specific development proposals. Easement areas have been depicted on the submitted plans in order to demonstrate access to each lot is available. Site preparation activities may also occur in advance of individual site plan proposals for the installation of required plat improvements. Such earthwork activities are estimated at an average of 4,500 cubic yards per parcel. The property, which is known as the Longacres Office Park, is subject to a Development Agreement between the Boeing Company and the City of Renton dated December of 2000. The applicant has informed the City that an updated Development Agreement, which would rescind the existing document, will be submitted in the near future. An Environmental Impact Statement and Mitigation Document for the 2,700,000 square foot office park was also completed in 1995, for which Addendums were issued in December of 2000. 11 PART TWO: ENVIRONMENTAL REVIEW --I A. B. CI@ Environmental Impacts The analysis of the proposed binding site plan does not present any adverse environmental impacts requiring mitigation above and beyond existing code provisions. Subsequent site specific development proposals on the site however, would, require additional, more detailed SEPA review and may require additional mitigation measures as appropriate. Recommendation Based on analysis of probable impacts from the proposal, staff recommends that the Responsible Officials make the following Environmental Determination: DETERMINATION OF XX NON -SIGNIFICANCE XX Issue DNS with 14 day Appeal Period. Mitigation Measures No mitigation is recommended. DETERMINATION OF NON- SIGNIFICANCE- MITIGATED Issue DNS-M with 14 day Appeal Period. Issue DNS-M with 15 day Comment Period with a Concurrent 14 day Appeal Period. PART THREE: ADMINISTRATIVE LAND USE ACTION - REPORT & DECISION This decision on the administrative land use action is made concurrently with the environmental determination. A. Type of Land Use Action Site Plan Review Shoreline Substantial Development Permit Conditional Use XX Binding Site Plan Special Permit for Grade & Fill Administrative Code Determination . t City of Renton P/B/PW Department - Ada. rative Binding Site Plan Approval & Environrr, ;l Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 3 of 10 B. Exhibits The following exhibits were entered into the record: Exhibit No. 1: Yellow file containing application, proof of posting and publication, environmental review and other documentation pertinent to this request. Exhibit No. 2: Sheets 1 through 7, Binding Site Plan (Received February 18, 2002). Exhibit No. 3: Overall Site Map (Received February 18, 2002). Exhibit No. 4: Neighborhood Detail Map (Received February 18, 2002). Exhibit No. 5: Pages G2E & H2E, City of Renton Zoning Atlas. C. Staff Review Comments Representatives from various city departments have reviewed the application materials to identify and address issues raised by the proposed development. These comments are contained in the official file, and the essence of the comments has been incorporated into the appropriate sections of this report and the Departmental Recommendation at the end of the report. D. Consistency with Binding Site Plan Regulations Approval of a binding site plan is based upon several factors as established by RMC section 4-7-230 of the Subdivision Regulations contained within Title IV, Development Regulations. The following binding site plan criteria have been established to assist decision -makers in the review of the subdivision: 1. Conformance with the Comprehensive Plan, its Elements and Policies The subject site is designated Employment Area - Valley (EAV) on the City's Comprehensive Plan Land Use Map. The EAV designation is intended to provide for a mix of employment -based uses, including commercial, office and industrial development to support the economic development of the City. The proposed binding site plan would create lots that would eventually be developed in a manner consistent with the EAV policies established by the Comprehensive Plan. At the time site specific development proposals are made, such projects would be analyzed for consistency and compatibility with the EAV designation. 2. Conformance with Underlying Zoning Designation The subject site is designated Commercial Office (CO) on the City of Renton Zoning Map. The proposed binding site plan would create 35 lots with the potential to be held under different ownership and to be developed individually with commercial or office uses. Future development of the overall site would be limited to a maximum of 2.7-million gross square feet of building area as established by the Longacres Office Park (LOP) Master Plan. Such development must be consistent with the Environmental Impact Statement (EIS), Mitigation Document, and Addendums issued for the LOP project, as well as with Development Agreements entered into by the City of Renton and the Boeing Company. The proposed subdivision must comply with the applicable development standards of the CO zone as discussed below. In addition, further review of the pertinent development standards of the CO zone (i.e., setbacks, building height, landscaping, etc.), as well as compliance with the parking regulations, would be necessary when site specific development proposals are made. Lot Coverage - The CO zone limits lot coverage by buildings to a maximum of 65% of the lot area, or 75% if parking is provided within the building. The existing 59,715 square foot BCAG Headquarters building to remain on proposed lot 22 (182,685 square feet) would arrive at a building lot coverage of approximately 33%. In addition, the 20,982 square foot Family Care Center building on proposed lot 23 (233,834 square feet) would result in 9% lot coverage by buildings. Lot Size - The minimum lot size required in the CO zone is 25,000 square feet. The CO zone does not mandate specific lot dimensions. The proposed binding site plan would create 35 lots ranging in size from 2.11-acres (lot 1) to 5.4-acres (lot 23). Five tracts would also be established for on -site facilities and would range from 1.6-acre to City of Renton P/B/PW Department - Adrn. rative Binding Site Plan Approval & Environm. J Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 4 of 10 14.61-acres in area. The proposed lots/tracts exceed the minimum lot size required in the CO zone. As proposed, the lots appear to be suitable for future development of commercial or office uses. Setbacks - The CO zone requires a minimum front yard/street setback of 15 feet to 30 feet depending on building height. No rear or side yard setbacks are required unless abutting residentially zoned property. The existing buildings to remain on proposed lots 22 and 23 appear to comply with the required setbacks of the CO zone as measured from the proposed property lines to the nearest point of the existing structures. 3. Compliance with Binding Site Plan Design Standards Legal Lots: Lots, parcels, or tracts created through the binding site plan procedure shall be legal lots of record. The number of lots, tracts, parcels, sites, or divisions shall not exceed the number of lots allowed in the applicable zoning district. The proposed binding site plan would create 35 lots and 5 tracts within the 157.87acre site. The CO zone does not contain density restrictions, nor minimum lot width or depth dimension requirements. As proposed, the lots/tracts created by the binding site plan would comply with the minimum 25,000 square foot lot size required in the CO zone. In addition, the lots appear to contain adequate building areas for future construction when taking setbacks and lot coverage requirements into consideration. Access: AM lots shall provide access to a public street or to a public street by means of an access easement or other recorded instrument approved by the City. New public roads shall be provided for lot access where determined to be appropriate and necessary. The proposed binding site plan would create interior lots (lots 1 through 16 and 27 through 35), as well as lots abutting the Oakesdale Avenue right-of-way (lots 17 through 26). As required, the plans submitted depict a 32-foot wide access easement extending throughout the property that would provide access to all lots not directly abutting a public right-of-way. The proposed binding site plan has demonstrated the availability of access to each of the created lots. As the exact location of the necessary easements are likely to change as site specific development is designed, the applicant has proposed to record the easements at a future date to be determined by the proposed development of individual lots. Dedication Statement. Where lands are required or proposed for dedication, the applicant shall provide a dedication statement and acknowledgement on the binding site plan. In order to establish the Strander Boulevard connection to SW 271h Street through the southern third of the property (west of Oakesdale Avenue SW, aligning with SW 27th Street), future right-of-way dedication for portions of the property will be necessary. However, the final alignment of Strander Boulevard, as well as the installation and costs of required street improvements, are still under negotiation. Therefore, the proposed binding site plan has indicated an area of reservation for the required right-of-way that would provide a width of 90 feet and would transect the south and north ends of lots 9 and 27, 10 and 28, tract C and 29, and 17 and tract D/E, respectively. Staff has determined that the reservation area noted on the face of the binding site plan is appropriate considering final design issues remain unresolved. As depicted on the plans submitted, the right-of- way reservation area is shown similar to an easement and does not effect lot dimensions or area. When the portion of Strander Boulevard located within the site is dedicated to public right-of-way under separate procedures, the boundaries and areas of the affected lots referenced above would be slightly adjusted through the dedication process. Adequate Provision of Utilities: Each parcel created by the binding site plan shall have access to water supply, sanitary sewer, and utilities by means of direct access, access easement, or supporting document approved by the City. The proposal depicts 32-foot wide access and utility easements extending throughout the property that would provide utility access to each of the lots created by the binding site plan. As the exact location of the necessary easements are likely to change as site specific development is designed, the applicant has proposed to record the easements at a future date to be determined by the proposed development of individual lots. City of Renton P/B/PW Department -- Adm,. ative Binding Site Plan Approval & Environm, ' Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 5 of 10 Required Improvements: Required improvements shall be provided for, either by actual construction or a construction schedule approved by the City and bonded by the applicant. The Administrator may also authorize the phasing of installation of improvements provided any delay in satisfying requirements will not adversely impact public health, safety, or welfare. The required street and utility improvements, which are further described below, would occur as necessary with site specific development proposals. Site preparation activities may also occur in advance of individual site plan proposals for the installation of required plat improvements with the approval of appropriate construction permits. Streets — With the project application, the applicant provided a generalized traffic analysis indicating estimated trip capacities of 7,000 to 11,000 average daily trips for private streets internal to the site with average daily demands between 3,000 and 5,000 average daily trips. Private driveways providing circulation between parking areas and buildings within the site would have design capacities of approximately 7,000 average daily trips with average daily demands between 1,000 and 2,000 trips. The appropriate design of the internal circulation system must be tailored to adequately serve the development of individual lots so as to not unduly burden public roadways. At present the majority of the site's frontage along Oakesdale Avenue SW is improved with full street improvements, with the remainder of improvements to be completed in the near future. Once dedicated to public right-of-way, the portions of Strander Boulevard that transect the site would eventually be improved with a minimum of two 12-foot wide drive lanes with curb, gutter, sidewalk, and street lighting on one side. The final design, timing, cost and responsibility of improvements would be established as part of the Strander Boulevard negotiations between the City and the Boeing Company. With the exception of lots 17 through 26, which have direct frontage to a public right-of-way, the interior lots created by the binding site plan would be served by a private roadway system to include two travel lanes and pedestrian connections. The private roadways would be developed within a 32-foot wide easement and would include 22 feet of paving with curb and sidewalk on one side. The design of future site development may, however, dictate the need for flexibility within these standards in order to allow for alternative, but equivalent, designs (i.e., separate pedestrian connections, angled parking on one side, etc.). In such cases, the Administrator or designated appointee may approve a modification from these standards when appropriate justification is given and the applicant is able to demonstrate specific designs would accomplish an equivalent standard. In order to ensure the aforementioned standards are applicable to the development of the entire site, staff recommends the applicant be required to place the following language on the face of the binding site plan: Vehicular and Pedestrian Circulation Improvement Standards: The development of the lots created herein shall provide suitable vehicular and pedestrian connections to public rights -of -way with the development of the site as follows: • Pedestrian connections shall be provided from building entrances within each individual parcel to a public right-of-way. • Private roadways shall be constructed with a minimum pavement width of 22 feet plus curb and sidewalk on one side. • The Administrator, or appointed designee, may approve the modification of these standards if the applicant is able to demonstrate equivalent standards would be accomplished and appropriate justification is given. • The City reserves the right to require reasonable landscape enhancements along street frontages in order to establish a consistent streetscape throughout the site. Utilities — There are no utility improvements within the property, with the exception of those serving the BCAG Headquarters and Family Care Center buildings located in the northeast corner of the site and the storm system improvements developed on the property in 1999. The construction of utility improvements to serve each of the lots will be dependent upon the design of parcel specific development, as well as the location of the lots to be constructed upon. The establishment of all necessary easements would be required prior to the issuance of construction permits for specific development. Drainage improvements for future development of the lots created by the binding site plan would also be required to integrate with the existing drainage facilities. City of Renton P/B/PW Department -Adm. :native Binding Site Plan Approval & Environm, .l Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 6 of 10 In order to address consistency with the installation of necessary access and utility improvements and to ensure such improvements are adequate for future site development, staff recommends the applicant be required to place the following note on the face of the binding site plan: Installation of Improvements: All required street, utility, and grading improvements necessary for site specific development must be installed to the satisfaction of the Development Services Division prior to the issuance of a Certificate of Occupancy for any building within the lots created herein; unless otherwise installed in advance of building construction, in which case approval of a Site Preparation/Construction permit by the Development Services Division will be necessary. Required access and utility improvements necessary to serve any lot, or lots, associated with a proposed development shall comply with all applicable code requirements, including but not limited to, standards as established under Chapter 6, Street and Utility Standards, contained within Title IV, Development Regulations, of the Renton Municipal Code. Shared Conditions: The Administrator may authorize sharing of open space, parking, access and other improvements among contiguous properties subject to the binding site plan. Conditions of use, maintenance and restrictions on redevelopment of shared open space, parking, access and other improvements shall be identified on the binding site plan and enforced by covenants, easements or other similar mechanisms. The lots created by the binding site plan would be subject to private Covenants, Conditions and Restrictions to be established by the property owner. At the time of individual lot development, if shared parking, access or maintenance of common improvements is necessary between separate properties, staff will require the applicant to demonstrate that the appropriate legal mechanisms have been established. In order to ensure future property owners are properly notified of any shared access and maintenance responsibilities outside of the applicable CC&Rs for the property, staff recommends the applicant be required to record the following language on the face of the binding site plan: Maintenance Provision: The owners of the lots created herein have the right to enter any easement located within other parcels in order to inspect and/or repair existing common private utility and access improvements. 4. Reasonableness of Proposed Boundaries Topography. The topography of the site is relatively flat and does not contain any sensitive or critical geological areas. The property does contain a portion of a large storm water detention pond and water quality pond in the western half of the site. In addition, an 11-acre wetland and conservation area is located in the southern most portion of the site. The subject binding site plan proposal would not affect these on -site water features. Additional analysis of future development of the site will be necessary to reduce or minimize potential adverse impacts to the wetland areas. Relationship to Existing Uses: The subject site is currently developed with the BCAG Headquarters and the Family Care Center buildings, both of which are located in the upper northeast corner of the property. The surrounding area includes both developed and undeveloped property zoned CO, IL and IM. The proposed lots are compatible with other existing lots in this area, are consistent with the intent of both the Comprehensive Plan and Zoning Code, and would not be out of character with existing or recent development in the area. 5. Availability and Impact on Public Services Transportation: Future development of the site is anticipated to generate additional traffic on the City's street system. In order to mitigate transportation impacts, a Transportation Mitigation Fee based on $75.00 per new average daily trip attributed to site specific development will be required at the time such projects are proposed. Police and Fire: Police and Fire Prevention staff indicate that sufficient resources exist to furnish services to the proposed development, subject to the condition that the applicant provide Code City of Renton P/B/PW Department -- Adrr,. trative Binding Site Plan Approval & Environm. .11 Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 7 of 10 required improvements and fees at the time of site specific development. A Fire Mitigation Fee, based on $0.52 per square foot of new building area, would be required with the approval of future development proposals in order to mitigate potential impacts to emergency services. Recreation: If future development includes residential uses, the applicant's payment of a Parks Mitigation Fee would be required as it is anticipated that new residents would use existing and future City parks and recreational facilities. Schools: The site is located within the boundaries of the Renton School District. If future development proposals include residential uses, further analysis of the District's available capacity and ability to serve residents of the development would be necessary. Utilities: Presently, there are no existing utility improvements on the subject site, with the exception of those serving the existing buildings located in the northeast corner of the property and the surface water management program installed on the in 1999. As previously discussed, future property owner(s) will be responsible for installing the necessary utilities as individual lot development is proposed. E. Findings Having reviewed the written record in the matter, the City now enters the following: 1. Request: The applicant has requested Environmental Review and Administrative Binding Site Plan Approval for the Boeing Longacres Binding Site Plan, Project No. LUA-02-022, ECF, BSP. 2. Environmental Review: The applicant's file containing the application, State Environmental Policy Act (SEPA) documentation, comments from various City departments, public notices requesting citizen comment, and other pertinent documents was entered as Exhibit No. 1. 3. Binding Site Plan Review: The applicant's binding site plan application complies with the requirements for information for binding site plan review. The applicant's binding site plan and other project drawings are entered as Exhibits No. 2 through 5. 4. Comprehensive Plan: The subject proposal is consistent with the Comprehensive Plan designation of Employment Area — Valley (EAV). 5. Zoning: The binding site plan as presented, complies with the zoning requirements and development standards of the Commercial Office (CO) zoning designation. 6. Existing Land Use: Land uses surrounding the subject site include: North: Commercial/Office development, zoned CO; East: Commercial and industrial development, zoned CO and IM; South: Undeveloped property, zoned RC and IM; and West. Commercial development, City of Tukwila. F. Conclusions 1. The subject proposal complies with the policies and codes of the City of Renton provided all conditions of approval are satisfied. 2. The proposal complies with the Comprehensive Plan designation of Employment Area — Valley (EAV) and the Zoning designation of Commercial Office (CO). City of Renton P/B/PW Department -- Adm. trative Binding Site Plan Approval & Environm. W Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 8 of 10 G. Decision The Boeing Longacres Binding Site Plan proposal, File No. LUA-02-022, ECF, BSP, is approved subject to the following condition(s): The applicant shall place and record the following items on the face of the binding site plan: a. Vehicular and Pedestrian Circulation Improvement Standards: The development of the lots created herein shall provide suitable vehicular and pedestrian connections to public rights - of -way with the development of the site as follows: • Pedestrian connections shall be provided from building entrances within each individual parcel to a public right-of-way. • Private roadways shall be constructed with a minimum pavement width of 22 feet plus curb and sidewalk on one side. • The Administrator, or appointed designee, may approve the modification of these standards if the applicant is able to demonstrate equivalent standards would be accomplished and appropriate justification is given. • The City reserves the right to require reasonable landscape enhancements along street frontages in order to establish a consistent streetscape throughout the site. b. Installation of Improvements: All required street, utility, and grading improvements necessary for site specific development must be installed to the satisfaction of the Development Services Division prior to the issuance of a Certificate of Occupancy for any building within the lots created herein; unless otherwise installed in advance of building construction, in which case approval of a Site Preparation/Construction permit by the Development Services Division will be necessary. Required access and utility improvements necessary to serve any lot, or lots, associated with a proposed development shall comply with all applicable code requirements, including but not limited to, standards as established under Chapter 6, Street and Utility Standards, contained within Title IV, Development Regulations, of the Renton Municipal Code. C. Maintenance Provision: The owners of the lots created herein have the right to enter any easement located within other parcels in order to inspect and/or repair existing common private utility and access improvements. The satisfaction of these requirements shall be subject to the review and approval of the Development Services Division prior to the recording of the binding site plan. APPROVAL SIGNATURE: Gregg Zimmerman, P/B/PW Administrator Decision date City of Renton P/B/PW Department - Adm, native Binding Site Plan Approval & Environm, 41 Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 9 of 10 Advisory Notes to Applicant. The following notes are supplemental information provided in conjunction with the environmental determination. Because these notes are provided as information only, they are not subject to the appeal process for environmental determinations. Planning 1. The site is located within the Employment Area - Valley (EAV) Comprehensive Plan Land Use Map and Commercial Office (CO) Zoning designations. 2. Additional Site Plan and Environmental (SEPA) Review will be necessary for site specific proposals for the lots created by the Binding Site Plan. 3. Staff recommends future development proposals on individual lots undergo the pre -application review process in order to adequately address site specific issues. Fire Prevention 1. A fire mitigation fee based on $0.52 per square foot of new building area will be required at the time of individual lot development. 2. The preliminary fire flow will be calculated for each structure when plans are submitted. One hydrant is required within 150 feet of each structure and additional hydrants are required within 300 feet of the structure based on one hydrant for every 1,000 gallons of required fire flow. 3. Separate plans and permits are required for the installation of the fire alarm system. 4. Fire Department access roadways are required to be within 150 feet of all portions of the building exterior. Roadways must be a minimum width of 20 feet with an inside turning radius of 25 feet and 45 feet on the outside. 5. Dead-end roadways exceeding 150 feet in length must provide an emergency turnaround as required by code. Plan Review 1. There are no existing utilities or street improvements on the subject site. No utility or street improvements will be required at this time. 2. The applicant will be required to construct all water, sewer, storm, erosion control and street improvements to City standards prior to the issuance of building permits for individual lot development. 3. Storm drainage report and design is required to comply with the 1990 King County Surface Water Design Manual requirements for detention and water quality. 4. All fire flow requirements must be met with future development proposals. Property Services - Comments for Final Binding Site Plan Submittal 1. Note the City of Renton land use action number and land record number, LUA-02-022-BSP and LND-35-0010, respectively, on the drawing. The type size used for the land record number should be smaller than that used for the land use action number. 2. Show two ties to the City of Renton Survey Control Network. The geometry will be checked when the ties are provided. 3. Provide binding site plan and lot closure calculations. 4. The legal description would be clearer if those parcels not included in this binding site plan were excluded from said legal altogether. Additionally, the exception for King County Rec. No. 9803250371 (Oakesdale Ave SW) does not include that portion of street right-of-way shown as a westerly extension of SW 27th Street as it intersects with Oakesdale Ave SW (Sheet 7 of 7). 5. The indexing information includes a reference to the northeast quarter of Section 24 that should be removed. None of the subject parcels fall within that particular quarter section. Note the indexing information on all seven sheets of the binding site plat submittal. 6. Indicate what has been, or is to be, set at the corners of the proposed lots. 7. Note the date the existing monuments were visited, per WAC 332-130-150, and what was found. 8. Note discrepancies between bearings and distances of record and those measured or calculated, if any. 9. Note whether the adjoining properties are platted (give plat name and lot number) or unplatted. 10. The city will provide addresses for the proposed lots as soon as possible. The addresses will need to be noted on the drawing submittal. 11. The required City of Renton signature (for approval of the binding site plan) is that of the Administrator of Planning/Building/Public Works, not the City of Renton Engineer, as is currently noted on Sheet 1 of 7. 12. The acknowledgment blocks noted on Sheet 1 of 7 should reference The Boeing Corporation or Longacres Park. Inc., not the "Quadrant Corporation", as is currently shown. 13. The City of Renton Finance Division Certification block is not needed and should be removed from Sheet 1 of 7. 14. The "Recording Certificate" block (Sheet 1 of 7) currently references the "King County Council' instead of the City of Renton. 15. The easements listing, noted under "EASEMENTS AFFECTING PARCELS A, B, C, F AND G", on Sheet 2 of 7, appears to be incomplete. See Item Nos. 16, 35, and 43 under Schedule B of Title Commitment No. 870559 for City of Renton P/B/PW Department - Admi. rative Binding Site Plan Approval & Environm6 .l Review Committee Staff Report BOEING BINDING SITE PLAN LUA-02-022, ECF, BSP REPORT AND DECISION OF MARCH 20, 2002 Page 10 of 10 additional pertinent easements. Were these items noted elsewhere on the binding site plan? 16. All proposed easements should be noted as either "Public" or "Private". 17. A common maintenance agreement will be needed for private access and utility easements. 18. Note that if there are restrictive covenants, easements or agreements to others (the City of Renton, etc.) as part of this subdivision, they can be recorded concurrently with the binding site plan. The binding site plan drawings and the associated document(s) are to be given to the Project Manager as a package. The binding site plan shall have the first recording number. The recording number(s) for the associated document(s) are to be referenced on the binding site plan in the appropriate locations. 19. New easements are proposed for the benefit of future owners of the proposed lots. However, since the new lots created via this plat are under common ownership at the time of recording of the binding site plan, there can be no easement until such time as ownership of the lots is conveyed to others, together with and/or subject to specific easement rights. 20. Add the following Declaration of Covenant language on the face of the subject drawing, if the previous paragraph applies: DECLARATION OF COVENANT. - The owners of the land embraced within this binding site plan, in return for the benefit to accrue from this subdivision, by signing hereon covenants and agree to convey the beneficial interest in the new easements shown on this binding site plan to any and all future purchasers of the lots, or of any subdivisions thereof. This covenant shall run with the land as shown on this binding site plan. TRANSMITTED this 2e day of March, 2002 to the owner, applicant, and contact. Attn: Walter E. Warden The Boeing Company P.O. Box 3707, M/C 1 F-58 Seattle, WA 98124-2207 Laura Whitaker Perkins Coie 1201 Third Avenue, 40'h Floor Seattle, WA 98101-3099 Dave Blanchard Heartland 524 Second Avenue, Suite 200 Seattle, WA 98104 TRANSMITTED this 25;h day of March, 2002 to the following. Jennifer Henning, Development/Planning Larry Meckling, Building Official Larry Rude, Fire Prevention Kayren Kittrick, Public Works Division Lawrence J. Warren, City Attorney South County Journal Environmental Determination and Land Use Decision Appeal Process: Appeals of either the environmental determination [RCW 43.21.0075(3), WAC 197-11-680] and/or the land use decision must be filed in writing on or before 5:00 PM April 8, 2002. If no appeals are filed by this date, both actions will become final. Appeals must be filed in writing together with the required $75.00 application fee with: Hearing Examiner, City of Renton, 1055 South Grady Way, Renton, WA 98055. Appeals to the Examiner are governed by City of Renton Municipal Code Section 4-8-110.B. Additional information regarding the appeal process may be obtained from the Renton City Clerk's Office, (425) 430-6510. r- m n BOEING LONGACRES PROPERTY awme am ftm ST. 1/4 SEQ 2b T.27N., RIE. W.Y. SE 1, 4 SEG 24, T.ZFI. R.4E, W.Y. N.E 1 4 SEQ 24, Ti M, R.4E, W.Y. N.W. /4 SEG EST LT.A4. L4E, " ME 1,14 SM A T.M. R4E, W.M. Off OF M WMN, OVO COUNTY, WAaM GMN amrAnom IONOW ALL PEa°LE BY rww PRESEMS DUT %E THE LmaE aRD ow4ms OF,REREST w DC LAND HDM DEA:FWE0 00 NETEBY 11.0E A EWNDWO STE FLAN MR.SIANT TO CHAPM R 5117 R.GW. AND 0E0.ARE THE &NDWG STE RAN TO BE A GRAPWC FWWC.%NTARON OF SAYE AND THAT SAID BWOWG 9Tf PLAN K MADE wiN FREE IXWSENT Am W ACCORDANCE wru THE OESRE OF THE OWfim IN WITNESS WHEREOF WE SET OUR HANDS AND SEALS: TTE SMA CO PMIADDK A DMAWX DOP17/ IDON DATE STATE OF WASIWGTON ) ) SS a WTY OF TONG ) OH DNS DAY FERSOULLY APPEARED BFORE ME Mom TO BE A MOE PRE90ENT OF DIE DUADRAWT OCRPORAROM THE NRPMATION OER080 N THE FO9EWNC WSTRUYRIT. AND ACWOMEUSFD THE SARI W57RVYENT TO BE THE FREE AND VOLUNTARY ACT AND OEM OF SAID CORKRADOY FOR ME USES AND PURPOSES THEREIN MENTIONED. AND ON GAIN STATED THAT SHE WAS AUTNO9'2ED TO EXECUTE THE SAW WSTR(H67? ON BEHALF OF THE CCRPwu VON. GVEN UNDER MY HAND AND O CFAL SEAL WS _ DAY OF . 20_, SONATURE OF NOTARY PU8UC W AND FOR THE STATE OF WASIRIGTOK RESONG AT PWNIED NAME OF NOTARY PUBIC MY CONMK9ON EXPIRES LOWACR S PAFK WC. A WASF&4GTUN CQWMATW BY ) SS STATE OF WA9iWGTON ) COUNTY OF mic ) ON TINS DAY PERSONALLY APPEARED WOREME MOW TO BE A VICE PRESOENT OF THE OUACRANT CORPORATION, THE CORPORATION DESMSED W THE FaREGOWG WS)RUYENT, AMU ACWOMIFDGED THE SAW WSiRVYENT TO BE THE FREE Am MUWARY ACT AND DEED OF SAD CORPORATION FOR THE USES AND PURPDSE3 iNERON 1/ENWkym AND ON aA H STATED THAT SHE WAS AUTHO ZED TO EXECUTE THE SAW WSRR ENT ON BEHALF OF TW CORPORATW. GLEN UNDER MY HAND AND OMCFAL SEAL rWS _ DAY OF S CHATURE OF NOTARY PWUC W AND FOR THE STATE OF WA- MWOTOK RESONO AT PRINTED NAME OF NOTARY PUBIC MY CmaassOW EDARES I Am amEM CS CM7FICAM, T Np7EBY CERTIFY MAT TNK BNO 9TE RAN OF BONG LONGCRES K BASED O'OI AN ACTUAL SURVEY AN7 $UBaKSNOV OF SECTIONS 2{ AND 25, iDXHSRNP 20 NORM EAST TNLLAMETTE IETIDIAN AND THAT 7NE COURSES AND OSTANGES ARE sNow CORRECTLY Kwom. PROE59ONAL LAW SURVEYOR, CERfIFlGTIOf Na STI{B m DESIGNED BY-' CHECKED BY.- DRAWN BY." MUD APPROVED BY.• LAST EDIT. 01/3r/O2 PLOT DATE.- D//JI/OFT A / DATE BY REV REV19ON CK'11APPR eePRaVAL2% CITY OF RENTON ENGINEER ENAYWED AND APPROVED PER RCW 5817.,QO (1) THIS ONGWETR aTr OF RENTON DAY OF 20 WNG COUNTY DEPARTMENT OF ASSESSMENTS EXAMINED AND APPROVED THIS DAY OF 24_. #WC COLNTY ASSESSOR DEPUTY ATNG COUNTY ASSESSOR ACCOUNT NINBER CITY OF RENTON FINANCE OlWSION CERT]FlCATION I HEREBY CTR7R7 THAT ALL PROPERTY TAXES ARE PAID. THAT MERE ARE NO OEUNOUNT SPEC,AL ASSESSMENTS CERTRED TO TARS OFTCE FOR COLLECTION AND THAT ALL SPEaAL AS2MUENTS CER7) W TO TINS OFFICE FOR COLLECTION ON ANY OF THE PROPERTY NERaV CON7A NED OMCATED AS STREE-M ALLEYS OR FOR MY OTHER PUBIC USE ARE PART W FULL TARS DAY OF - 20. ORECTOR OF FINANCE OF RENTON KING COUNTY FINANCE DiVISON CERTIFICATION I HEREBY CERTIFY THAT ALL PROPERTY TAXES ARE PAW, iHAT )HERE ARE ND OELwaANT SPEaAL ASWsw&NTS CERTIFIED TO TNS OFFICE FOR COLLECTION AND THAT ALL S°ECUL ASSESSMENTS CERTBED TO TARS ONCE FOR COLEGBYR ON ANY OF THE PROPERTY WRON CONTAWED OMCATED AS STREET$ ALLEIS OR FOR ANY OTHER PUBIC USE ARE PAW W FU - TWSLDAY OF 24_.. O'RECrOR. 10N0 COUNTY Dewy D/RECTOL MR; COUNTY O CE OF FINANCE OFFICE OF FINANCE RECaROINC NO FRED FOR RECORD AT THE REOUEST OF TIE IONC COUNTY COUNCN_ TMS _ DAY OF _ 2 ✓ AT_ MLMIIES PAST_ 1L AND RELORM W 4 UYE _ O` PATS. PAGES RECORDS OF LONG COUNTY, WASMNGTON. DIVISION OF RECORDS AND ELECTIONS MALMLER S/FEMMENDEHi OF RECORDS BOEING REALTY COMPANY HEARTLAND B„u.,0, rmRyw PeaPl—erc BOEING LONGACRES PROPERTY RENTON. KING WASHINGTON .r..u..+ SCALE: PROJECT NO. JDRAMNG FILE NAME: 825913.2538000E 1 S913BS01.OWG EEC._ 2 J BOEING LONGACRES PROPERTY TRANSNA7KN TITLE NSURANCI COMPANY TITLE COMMITMENT NO 1170559 DATED MARCH D. 2OOf AT S00 ,LM. r7E TM BOOM 4iE PLAN INCLUDES PARCELS A. B. G F. S G OF M i OILY.) SCTRDIHE A, - PARCEL I PARCELS A A G F. G I. A K L AND M AS OELNEA TO ON SURVEY REOOMED UNDER TONG COUNTY REOOKTNG Na 9XII69002 (VAZUME 85 DF SIRWM PAGES 27 AND 27A); EXCEPT MAT PORTION D4ERECF CONYEMM TO THE CITY CF FENlON FOR THE GAKESOALE D rTENSON BY DEED RECORDED 1AOOERt MC COUNTY RECROAIC NO 9803250M. ANO EXLEPr MAT ATNMN THEREOF cmvnED 10 THE QTY OF RENTON FOR SIC Tow STREET BY am RECVRGED LINDEN IONC LVtaNTY RECmwc NO 9501060f3R SITUATE N THE CITY OF RENTO, COUNTY OF TONG STATE OF WASWNC70N. F�4y.7FNTC AFF'Er'7�rr_ P e B - F Ate± . wRDULE 3 III AF 1230= PORK AFFECTS PARCEL A. NOT PLOTTED 2C AF 440471CL PoNER. AFFECTS PARCEL A NOT PLOTTED 26 AF 5398621 POTHER, AFFECTS PARCEL C 27. AF 84f7049, PoXFTL AFFECTS PARCEL F 24. AF 5640T72 PoMER. AFFECTS Ii PARi PARCEL A 29. AF 79270e1/6251972 QINFPC GAS PPELINE AFFECTS PARCEL 1 36. AT 625526Z SANITARY SEMEN AFFECTS PARCEL F. S KN DOES NOT FALL N ES1T. 38. AF 760T280694, PoMEIL AFFECTS PARCEL A 41. AF a0I7290J71 WATFR/SWfTARY SENEFL AFFECTS PARCEL A 42 AF 0212090467, WA 11F/S4WTARY SEMEN, AFFECTS PARCEL A 45. AT, 84f2070644, WA77F/StWTARY SEMEN, AFFECTS PARCELS F ! G 46. AF a602I40681 PoMEFL AFfl:CiS PARCELS C t F 4A Al . 1)OJ01 POMER/R1EP;.M AFFECTS PARCEL C 49. AF 8803161006/115O1260432 WATERIUNITARY SEMEN, AFFECTS PARCELS A A, C SIX 40 AF 2O0f0I240003. TELEPHQNE AFFECTS PARCEL A 77. AF DJMi21692/SUltOZIJ6d. SANITARY SEBEIL AFFECTS PARCELS B 4, C 85 AF 9712f21f7o. ACC PARCEL 0 90 AF 961210007. WATER AFFECTS PARCEL A 91. AF 96121003TG STOW, AFFECTS PARCEL A 9Z AF 990SZIfi4O ACCESS AFFECTS PARCEL a NOT PLOr1ED 91 AF M*12121 POKRR AFFECTS PARCEL 6 94. AT 9903231481. WATER AFFECTS PARCEL B %. AT, 9e012311sz PA"OIG NGRESSACRE= AFFECTS PARCEL A 101. AF 980422f87$ POTHER AFFECTS PARCEL 6 101 AF 99=147Z WATER. AFFECTS PARCEL A Ncml� 1. BASIS OF SCARINGS FOR 1NS BARLEY IS N OI9276' E AL ME NEST IME OF THE STXTNEAST OOMrER OF NE NOTTHEAST GUAR ER OF SECTION 21 TOWSTSP 2J NORTH, RANGE 4 EAST, TOM- AS SHOMN ON THE RECORO OF SURVEY FOP LONGACRM RECORDED UNDER RECORDING NUMBER 96010290f1 Z REFERENCE THE FOLOYINC SR%-YS FOR SECTTON SUMW90N ANO BOUNDARY 94FOLMATIOC AF D2OfI690GZ PARCEL EXHIBIT FOR LONGACRE5 AF 9504060139. G® OF DEDICATION FOR SW 16M Sr. AT WOF029011 RECORD OF SURVEY FOR LONGACRES AF 980325017I. DEW OF DEDICATION FOR OAESOALE ME SW AF 200006.7090000E RECOW OF SURVEY FOR OAIE97ALE AVE SW RIGHT-OF-WAY 1 FIELD MEASUREMOTS FOR TARS MAP MERE PERFORMED METH MAo TOTAL STATIONS AND MEET OT EXCEED A LINEAR CLOSURE OF 1. 15.000 ALL PRIMARY MEASUREMENT ECOPUENT HAS BEEN COMPARED AND AO.USTED TO A NATIONAL GEODETIC CAf/BPA FED BASELINE MTI9N THE LAST YEAR_ 4. ME NEiLNO AEID BUFFER DELINEATIONS SHOW ARE AS FROMM BY SVERGRP CTAL, NC ME METL ND CONSERVATION AREA SHOW AT ME SOUTH END OF THE SITE IS PER ME DEVELOPMENT AOM1911T. DEVELOPER HEARTLAND 324 SECOND METRE SATE 200 SEATRE WA OM04 PHONE (205) 6W-2500 SRIE/LRIENG EER WAN PAOFTC 33W MOTE VQLA PARKWAY 90MELL, WA 90021 PNOOE (423) 9Sf-4800 ARCI6ECT HELLMUIK OBAM + KASSA8AUM, INC ARCC ECTURE ENCNEERNG PLAFNNG N7EAIOP9, tiP,1AFAC5; GONSLCiWC ZONING COMIARCAL CFFTCE ZONE (Lb) TOTAL 6.a74,40Zaa SF. 157.8 ACRES 9U[DNG USES OFFICE BUSINESS PARK LOT AREA TABLE PARCEL NAME SOL FT. ACRES LOi / 91.744 Zlf LOT 2 1 160,393 3.68 LOT 3 109.460 2-St LOT 4 Team laid LOTLorS f644.Te 157 e f31729 153 LOT 7 127495 Z93 LOT 5 23137E 140 LOT 9 141429 129 LOT 10 224,253 Ste LOT It 14Z249 127 LOT 12 200.33f 4.60 LOT 13 1a19J0 4.22 LOT 14 226.2D2 0/9 LOT IJ 12z087 Z87 LOT 16 100.974 Z32 LOT IT 266,435 612 LOT T8 Ifla10 lot LOT I9 156,s30 157 LOT 20 22a.65s 5.25 LOT 21 279.701 8.42 LOT 22 ISIZ685 4.19 LOT ZT 2-,X&4 5.37 LOT 24 IJZ491 104 LOT 25 f47,7M .LJ9 LOT 26 IM250 142 LOT 27 f39,950 121 LOT 28 2fa fag Sof LOT 29 TOM= Z40 LOT 30 f10.122 Z53 LOT 31 127.111 2.92 LOT 32 /Jf,.707 I lot LOT 33 r3G96317.47 car J4 /114x LOT 3s 15Z691 TRACT A J21207TRACT S 90.7MTRACT C I09,96JTRACT 0 69.660TRACT E 636.372 NCNTY YAP NOT m SC E armor LAWW 0 - BOEING REALTY COMPANY HEARTLAND N = BOEING LONGACRES PROPERTY m RENTQY, KING WASHINGTON V SCALE: PROJECT N0. DRAWING FILE NAME 825913.25380002 S9136S01.DWG DESIGNED BY. CHECKED BY.' DRAW By. MAD APPROVED BY LAST EDIT. 011.71/02 PLOT DATE OIIJI102 JRI r.. DATE I BY IREVI T • 2- J NM•.SY2YE NaM't i$ 11 T P6PL POIIER EASE AF 7EO.m60W{ T owmT iaswo E AF 2WI912400040 m 1 n BOEING LONQACRES PROPERTY mwmo arcs mm 1.744 -0- zrr _{2a5W - I lift N90O0'00'E ' J{f.10' 10' 7.00' W 2S q8 100.460 6q.R 201 olsa I N8; NDOI]0'00T {D{.{Y I 16&916 67.1E aaa o� I I 0016,9 {a0o' a a SEE SHEET 4 e TRACT A HEX" O ZY a,7CR W Ld I N A- I SCALE i00 0 50 100 200 FEET 1 INCH - 100 FT DESIGNED BY. CHECKED BY HOEING REALTY COMPANY DRAWN BY." MAD APPROVED BY. HEARTLAND mte.0 i.em6D6a�-eD72 W �+ LAST EDIT: 01/31/02 PLOT DATE: Q]/31/02 BOEING LONGACRES PROPERTY m DATE BY REV REVISION CK'O PR RENTON. KING WASHINGTON .6�..� SCALE: PROJECT NO. DRAWING FILE NAME: 825913.25380002 IS913BSOl.DWG L - _.___ FJA - SEE I NIXASf `USE MM- PALM % Ai SMXMI 18S(JO p R Y PYL roNm ufJOTf 1ST oar AF )sri7>msW t Y G16T 7QfP/AX fAs/Tf AF ?9C(o18100Df6T fZ7.10.3 p.R 2YJ — m BOEING LONQACRES PROPERTY i 4i7— 8 fv/ I 1 12 L1726 nIt 1ST rlw I 13MW b•36m71'' 1J pp� !ll LLJ 6 ( (U (10 Ld y R-IIQ03' b47 'Sf' 1 14 a SIY uzm .wrt S10 r.v V �t U7[l� ° III 10 SEE SHEET 6 SEE SHEET 7 i \11, 1 SEPARATE D2� VR }u N SCALE TRACT C 1b Too o so Too soo ( FEET ) T INCH -TOO FT 411 y y V DESIGNED BY CHECKED BY.. DRAW BY, MAD APPROVED BY. LAST EDIT: 0113f/02 PLOT OATS olariD BOEING REALTY COMPANY HEARTLAND BOEING LONGACRES PROPERTY RENTON. KING WASHINGTON 3�ao .ra.l. wu. lrN�T —.e— H. _ DATE BY REV REVISION CK'O R I SCALE: 1' = 100' PROJECT N0. 825913.25380002 DRAWING FILE NAME: S9138SO1.DWG F4,6 Zw J r — BOEING LONQACRES PROPERTY marva airs n.,w ' Aj\ � ' v 11 sn.Jr NBnrSrw I L-14L8J' , R-16000' ' o-szs6'1rj I TRACT A / 22 f8Z88J qfL 4.10 eor� 1 W w�pO� 24R C-6ae4' R.16aa5' �.d ii _ $ EE 3 I i o-J51.S'O4' 10' 142,210 p.R Sr 327 OLOIALMG FOOTPRxr avq f 261-"SMO i 274.01 L-16244' R-So4iaO• 11 1 1 1 1 f, d-f70{f' 1 O N90�DA'00 n 46564•—•—N909�b0'� :•/ _ y f0• aTr of RFNTav — PROPOSED 32, AF iaa7L7/s72 f- I EASSOffTo = (Be accORDEU iWOER 1 I IS v��ott a2 I SEPARATE ooaAem p 1 1 LLJ Lo 12 IS I—ILI 18{`u'ooawR 1b P Lu I$ t$ I I 1 I 1607442' 1aS 43' I I I I i I IR 1 14 I / SIo oaR —_ t UTUTY EASYENT _ TO 8E RECORDED MDER ARAM DOM40M TRACT B p.R k IM7D8 208 oav I8 I. PROPOSED JY AC= t I IL�f281' 1 e ,UljE t R�7Z255 . TRACT C I 13 SEE SHEET 7 fr w� vi = m y DESIGNED BY. CHECKED BY., ORAWN BY., IAAO APPROVED BY LAST EOIL Qj/S1/02 PLOT DATE; Ol/X/07 / DATE BY REVISION CK'O PR IREVA N N8725 v —'7ITY OF r f2M MGt =Rx maefT 1 W OW=4M I I I o ux u - OOTPW t di z�u4 q.R �e 7�. t-rsJ.26• vq R-4oSS00' Sy.... 6.21410C OF AE3NON — IF7R 46f iil4 Af iia�Jlsdl roornt zr/�e Hole _gyps �Iw ROE7YW 7 $ '- !Df.1IM ACROSS E75S1M0 Ro04= ,$ AM NO. Sf1MIF40 — Nooyo o0 E 2795" � i I I I R-iass.00' i I I 1 III II I4CI sy2 j O4 oce I S I I i No018'361w IL' Zn,701 p.R 1 1 �. n90�0'OOY S42 — 1 I 1 449.24' 1 S4(TARY d¢ji !!155 j11 I Y I { s 9 IO21m 8 6�(+RCw0.4D J2' ACCESS g p I I I (TO BE RECORM wow 1 B C4 O I SEPARATE 0a]aENO _ o I i 25 N90fl0'001' s41.eo' f47.750 -q.R I 7W � ; SJ➢ oaw 1 1 I I 1 li 10 I 1 8 1 8 2 2 1 1 y a; 26 I 2Q ; I I ; /04250� R 226.6M525 evR I 1 i 92'�.• i 1d �� L� S7T� la �0. OTY Of !!E'ATRF MMFF E9fZ i AF fwoI212I03 I I SCALE 100 O 50 IGO 200 r FEET f INCH - 100 FT BOEING REALTY COMPANY HEARTLAND B.0 mm► BOEING LONGACRES PROPERTY RENTON, KING WASHINGTON .p.r..� SCALE. PROJECT NO. ORAWI14G FILE NAME 1' = 100' 825913.25380002 S913BSO1.DWG ImAt .Pe w�aa-ev7a SEE SHEET 4 7 BOEING LONQAGRES PROPERTY I� 1444" a.R. I6 10 S29 oco 'I I 914,D5.5 �42 SI! ocra 1 I31 'E U� � PROPOSED 3Y ACCFSS ! DDI rTY FL4LFNi 29214--��.�� �..�� OMM F.R Ap pNEj/592700 `_ {� H1 N�7�'SZ'1Y 299.00� I NW29Q3YW 31501' 1 304.iY — — NOW I F 1 1 1 32' ACCESS 3FPARARECORDDOOED UMDER SEPARATE TED LNDER _err nl i 27 28 09,950 sQ.R — 81 gg8 �1 N9OWD0'W SZ1.31� _ _ —PROPOSED 32' ACCESS k utlun EASEIANr i (to OE RECORDED UNDER tv, SEPARATE OOCWINT) 3D 31 ff4f22 2SS aaa z N9O90b0E � � � S ( 'lot KR Of wrK 8 N90W'OO�W fJ0,9W p.2 I I SOf oaw �i N 0 W W Z W W 1 IN SCALE 100 0 50 too 200 (FEET) I INCH = 100 FT DESIGNED BY.' CHECKED BY BOEING REAL TY COMPANY r� DRAWN BY: MAD APPROVED BY: HEARTLAND o80�F=-Z. - LAST EDIT: 01/31/02 PLOTDATE: OI/31/02 BOEING LONGACRES PROPERTYBDATE Y REV RfNSIONRENTON• KING WASHINGTON SCALE. PROJECT NO. DRAW NG FILE NAME: 1" = 100' 825913.25380002 S913BS01.DWG " - 4_ e g T SHEET 4 as BOEING LONGACRES PROPERTY p BOW LAkE A d3w Raw AF.ftf3f W7 -_- 1RACT 8 •N o dirt PLAN f4 III 46az ----- twEn 10 2sz1 [f. It Ji Igl I Its I) rlr.9cr 15 L_=24' 109.963 t R 300.� _j_�eINKWOSED J2' ACCE35 Q UWTY fAS�IENT ro a rr�cro[rom ue+�rr srnARA>E ooaiu r_ _� � � � 103.43' Ni3'16•If'E NB679=J�SO�' 43,00 y0A -- AF /7d621tN0or bem 5FE igE%W db3•H• a•4 J✓•4�`b , R_isoc.00' 16 . (�yfla B -Oo �11j ; 6-14IY30- 100.074 p.R _EROPOSED .' ACCESS ((7�0 FIECOROED UNDER 2S IQ 3EPARAIE Doasfl7[n �� PRoposm BLW (T0 SE DEDICATED LWDER SEPARATE (aCtAhxiWT ) 26 valsa0v IL \ J� j g ]0437— Al\ \ z4s gl / \\� \ h� \� NIlTJ'.%'E 2fl49' 1023Y �� w__ 4 317. 2� NBOTNI'00'W 6W� \ PRAP0.5FDC'�TA \ 31 (TO SE J2• A:.._�7 R H7979.26_E 24.43 f2� f�'rt SEPARATE DOL WUMM'�^I� 6 N4T36'09'E 1RACT O � g � 64660qJL 1.60 LU W 35 Cr) fs2a91,o-rt rT it 32 R.tstss• a-7nm9s' f3'-�•.l�W �A S37 oae� ( mTM002 - 1-I "0-440 - fF2LZ p.rt L I3233' 26/ avw R-109now A•a4Y4r 10' PSWC ,,o E SOMW.• AF MM40M L-10190'- R•.f09", A•0=4 R-f09 oo. v� A"01 47' m 17 I W &12 fll2 ao�� I I NT I � WNa7i J 175Y? f -NT ' zsQf .204'W 2S D� 7:.L0:" ST 5 30' NETLAND BLOFER I I I I wI I jI f T I - _ - - 24.4 / _ NCTLA 1[ARSN 2 N90170'OOiI' 74Q34r 1'Id� a!D�• g MEiC.WD MN9ERVARQY AREA I �� �"'�+'$7 1RACT E I34 '/�.a�rtr- N Qx372R c-514e — o-osys4• NB97370'W �7D s tnti`" I S00 �[ I .l.0-(4 � .o cd" SCALE uErRo swTARY SEYVt _. JETLA Se73T42T am m DESIGNED By. CHECKED BY. DRAW BY.' UAO APPROVED BY LAST EDIT: OI/31/02 PLOT DATE: 01 31/02 DATE BY REVIIRENSION CK'D PR .�. t00 0 50 100 200 L-281.97- Tya1 INCH -100 FT NEFLAND�a2 BOEING REALTY COMPANY�y��_� HEARTLAND - BWb.O, r BOEING LONGACRES PROPERTY [ar/r-w RENTON, KING WASHINGTON SCALE: PROJECT N0. DRAWING FILE NAME: 1" = 100' 825913.25380002 S913BSO1.DWG Cam. 2 BOEING LONOACRES PROPERTY SULE w56�S Ex, S FZ - 13 T23N RO E 1 /2 z IM ? I 7th� St. < coco IM iM _ -- I ! co .. . . —405 w I z I M w sht. I M - -I � W �\ I M co co` 5rre " C H2 - 25 T23N RO E IIZ Q� 0 G 2 �Y o 1=4800 �O ZONING PIBIPWotwol °� `� 24 T23N ME E 1/2 t2l C N I2 - 36 T23N ME E 1/2 �Y 4 HZ ZONING 1:4600 + -~ P/B/PW TECf�1ICAL SHRVICBS ��Nz� OLWM 25 T23N ME E 1/2