HomeMy WebLinkAboutPRE22-000069_Meeting SummaryPREAPPLICATION MEETING FOR
SE 162nd Cottage Housing Development
PRE 22-000069
CITY OF RENTON
Department of Community & Economic Development
Planning Division
March 24, 2022
Contact Information:
Planner: Jill Ding, 425.430.6598, jding@rentonwa.gov
Public Works Plan Reviewer: Jonathan Chavez, 425-430-7288, jchavez@rentonwa.gov
Fire Prevention Reviewer: Corey Thomas, 425.276.9582, cthomas@RentonRFA.org
Building Department Reviewer: Rob Shuey, 425.430.7235
Please retain this packet throughout the course of your project as a reference. Consider
giving copies of it to any engineers, architects, and contractors who work on the
project. You will need to submit a copy of this packet when you apply for land use
and/or environmental permits.
Pre-screening: When you have the project application ready for submittal, call and
schedule an appointment with the project manager to have it pre-screened before
formal submittal.
The pre-application meeting is informal and non-binding. The comments provided on
the proposal are based on the codes and policies in effect at the time of review. The
applicant is cautioned that the development regulations are regularly amended and the
proposal will be formally reviewed under the regulations in effect at the time of project
submittal. The information contained in this summary is subject to modification and/or
concurrence by official decision-makers (e.g., Hearing Examiner, Planning Director,
Development Services Director, Department of Community & Economic Development
Administrator, Public Works Administrator and City Council).
M E M O R A N D U M
DATE: March 8, 2022
TO: Jill Ding, Senior Planner
FROM: Corey Thomas, Lead Plans Review Inspector
SUBJECT: Cottages Short Plat
1. The fire flow requirement for a single-family home is 1,000 gpm minimum for dwellings
up to 3,600 square feet (including garage and basements). If the dwelling exceeds 3,600 square
feet, a minimum of 1,500 gpm fire flow would be required. A minimum of one fire hydrant is
required within 300-feet of the proposed buildings and two hydrants if the fire flow goes up to
1,500 gpm. Water is provided by Soos Creek Water District. A water availability certificate is
required to be obtained from them. A minimum of one new fire hydrant will be required to be
installed.
2. The fire impact fees are currently applicable at the rate of $829.77 per single family unit.
Credit will be granted for the removal of the two existing homes.
3. Fire department apparatus access roadways are required to be a minimum of 20-feet
wide fully paved, with 25-feet inside and 45-feet outside turning radius. Fire access roadways
shall be constructed to support a 30-ton vehicle with 75-psi point loading. Access is required
within 150-feet of all points on all the buildings. Proposed lot layout does not meet this
requirement. Dead end streets shall be equipped with an approved turnaround. Dead end
streets over 300-feet require a full 90-foot diameter cul-de-sac. Since Southeast 162nd Street
already has an approved cul-de-sac, this development can just provide a hammerhead type
turnaround instead. See included diagram for dimensions. City ordinance does require all
homes beyond 500-feet dead end to have an approved fire sprinkler system. Dead end
measurement is from 114th Avenues Southeast. This fire sprinkler requirement will apply to all
lots except Lots 3, 4 and 5.
DEPARTMENT OF COMMUNITY
& ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: March 18, 2022
TO: Jill Ding, Senior Planner
FROM: Jonathan Chavez, Civil Engineer III
SUBJECT: SE 162nd Cottage Housing Development
PRE22-000069
I have reviewed the pre-application submittal for the above referenced project at 11233 SE
162nd Street (KC Parcel ID: 0088000151). The applicant is proposing a cottage housing
development, of 16 units.
WATER
1. Water service is provided by Soos Creek Water and Sewer District.
2. Applicant shall obtain a water availability certificate from the District and provide it with
the civil construction permit submittal.
3. Review of the water plans will be conducted by Soos Creek Water and Sewer District
and the Renton Regional Fire Authority.
4. Plans approved by Soos Creek Water and Sewer District shall be routed to the City for
final review prior to permit issuance.
SEWER
1. Sewer service is provided by Soos Creek Water and Sewer District.
2. Applicant shall obtain a sewer availability certificate from the District and provide it with
the civil construction permit submittal.
3. Review of the sewer plans will be conducted by Soos Creek Water and Sewer District.
4. Plans approved by Soos Creek Water and Sewer District shall be routed to the City for
final review prior to permit issuance.
SURFACE WATER
1. A drainage report complying with the current version of the City adopted Surfac e Water
Design Manual (SWDM) will be required. Based on the City’s flow control map, the site
falls within the Flow Control Duration Standard area matching Forested Site Conditions
and is within the Black River Drainage Basin. Refer to Figure 1.1.2.A – Flow chart to
determine the type of drainage review required in the RSWM. All stormwater
improvements as per the drainage review along with stormwater improvements in the
frontage are required to be provided by the developer.
2. The site topography slopes moderately from the east to the west. The site contains
regulated slopes. There is an existing stormwater ditch located along the property
frontage on SE 162nd Street.
3. Storm drainage improvements along all public street frontages are required to conform
to the City’s street and stormwater conveyance standards. Any new storm drain
SE 162nd Cottage Housing Development – PRE22-000069
Page 2 of 4
March 18, 2022
installed on or off-site shall be designed and sized in accordance with standards found in
Chapter 4 of the 2017 RSWDM and shall account for the total upstream tributary area,
assuming developed conditions for onsite tributary areas and existing conditions for any
offsite tributary areas.
4. Maintenance access is required for any proposed stormwater tracts and shall be
designed and installed in accordance with the City adopted SWDM.
5. If the new plus replaced pollution generating impervious surface exceeds 5,000 SF, the
applicant will be required to provide basic water quality treatment. Any proposed
detention and/or water quality vault shall be designed in accordance with the RSWDM
that is current at the time of civil construction permit application. Separate structural
plans will be required to be submitted for review and approval under a separate
building permit for the detention and/or water quality vault.
6. Appropriate on-site BMPs satisfying Core Requirement #9 will be required to help
mitigate the new runoff created by this development to the maximum extent feasible.
On-site BMPs shall be evaluated as described in Section C.1.3 of the 2017 RSWDM. A
preliminary drainage plan, including the application of on-site BMPs, shall be included
with the land use application, as applicable to the project. The final drainage plan and
drainage report must be submitted with the utility construction permit application.
7. A geotechnical soils report for the site is required per the 2017 Renton Surface Water
Design Manual Section C.1.3. Information on the water table and soil permeability
(measured infiltration rates), with recommendations of appropriate on-site BMPs per
Core Requirement #9 and Appendix C shall be included in the report. The report should
also include information concerning the soils, geology, drainage patterns and vegetation
present shall be presented in order to evaluate the drainage, erosion control and slope
stability for site development of the proposed plat. The applicant must demonstrate the
development will not result in soil erosion and sedimentation, landslide, slippage, or
excess surface water runoff.
8. Construction Storm water General Permit from the Department of Ecology is required if
clearing and grading of the site exceeds one acre.
9. Erosion control measures to meet the City requirements shall be provided.
10. The current City of Renton Surface Water Standard Plans that shall be used in all
drainage submittals are available online at the City of Renton website.
11. The 2022 Surface water system development fee is $0.84 per square foot of new
impervious surface, but no less than $2,100.00. This is payable prior to issuance of the
construction permit. This fee is subject to change based on the calendar year the
construction permit is issued.
TRANSPORTATION
1. The proposed development fronts SE 162nd Street along the north property line(s). SE
162nd Street is classified as a residential access street. Per RMC 4-6-060, the minimum
right of way width for a residential access street is 53 feet. Per City code 4-6-060, half
street improvements shall include a pavement width of 26 feet (13 feet from
centerline), a 0.5-foot curb, an 8-foot planting strip, an 5-foot sidewalk, street trees and
storm drainage improvements.
a. Refer to the following record drawings to design the frontage improvements to
match existing improvements along SE 162nd Street:
SE 162nd Cottage Housing Development – PRE22-000069
Page 3 of 4
March 18, 2022
i. https://edocs.rentonwa.gov/Documents/DocView.aspx?id=1336813&
2. New residential half street required along west property line. The right-of-way width
shall be 46-feet and include the following improvements: (2) .5-foot curbs, 26-feet of
pavement width, 8-foot planter, 5-foot sidewalk, street trees and storm drainage.
Dedication will be required.
3. For dead-ends between 500-feet and 700-feet in length, a Cul-de-Sac and fire sprinkler
systems for the homes will be required.
a. Coordinate with the Renton Fire Authority.
4. Street lighting and street trees are required to be installed by the developer AND must
meet current city standards. Lighting and Photometric plans are required to be
submitted with the land use application and will be reviewed during the construction
utility permit review.
5. The new street intersection radius must be a minimum of 25’.
6. Street grades shall not exceed 15 percent.
7. ADA access ramps shall be installed at all street crossings. Ramps shall be shown at each
intersection. Ramps shall be oriented to provide direct pedestrian crossings.
a. Ramps across new/existing curb ramps must be ADA compliant (upgraded) as
well.
8. Refer to City code 4-4-080 regarding driveway regulations:
a. Maximum driveway slope is 15%. Driveways which exceed 8% shall provide
slotted drains at the lower end with positive drainage discharge to restrict
runoff from entering the garage.
b. The maximum width of a single loaded garage driveway is 9-feet and the
maximum width of a double loaded garage driveway is 16 -feet. If a garage is not
present, the maximum driveway width is 16-feet.
c. Driveways shall not be closer than 5-feet to any property line.
9. Paving and trench restoration shall comply with the City’s Trench Restoration and
Overlay Requirements.
10. The transportation impact fee is based on the type of land use. For single-family
residential, the 2022 transportation impact fee is $10,861.69 per unit. Transportation
impact fees are subject to change based on the year the building permit is applied for.
GENERAL COMMENTS
1. All existing and proposed utility lines (i.e. electrical, phone, and cable services, etc.)
along property frontage or within the site must be underground. The construction of
these franchise utilities must be inspected and approved by a City of Renton inspector.
2. Adequate separation between utilities as well as other features shall be provided in
accordance with code requirements:
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other
utilities is required with the exception of water lines which require 10-ft
horizontal and 1.5-ft vertical.
b. The stormwater line should be minimum 5 feet away from any other structure
or wall or building.
c. Trench of any utility should not be in the zone of influence of the retaining wall
or of the building.
SE 162nd Cottage Housing Development – PRE22-000069
Page 4 of 4
March 18, 2022
3. All civil construction permits for utility and street improvements will require separate
plan submittals. All utility plans shall confirm to the Renton Drafting Standards. A
licensed Civil Engineer shall prepare the civil plans. Please visit the Development
Engineering Forms page for the most up-to-date plan submittal requirements:
http://rentonwa.gov/business/default.aspx?id=42473
4. A landscaping plan and tree retention shall be included with the civil plan submittal.
Each plan shall be on separate sheets.
5. Additional Building Permit Applications will be required for the following:
a. Any retaining walls that exceed 4 feet in height, as defined by RMC 4-4-040.
b. Detention vaults for storm water flow control.
c. Demo of any existing structures on the project site(s).
6. Fees quoted in this document reflect the fees applicable in the year 2022 only and will
be assessed based on the fee that is current at the time of the permit application or
issuance, as applicable to the permit type. Please visit www.rentonwa.gov for the
current development fee schedule.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE:
March 24, 2022
TO: Pre-Application File No. 22-000069
FROM: Jill Ding, Senior Planner
SUBJECT: SE 162nd St Cottage Housing Development
11221 & 11233 SE 162nd St
(Parcel Nos. 0088000132 & 0088000151)
General: We have completed a preliminary review of the pre-application for the above-referenced development
proposal. The following comments on development and permitting issues are based on the pre-application
submittals made to the City of Renton by the applicant and the codes in effect on the date of review . The
applicant is cautioned that information contained in this summary may be subject to modification and/or
concurrence by official decision-makers (e.g., Hearing Examiner, Community & Economic Development
Administrator, Public Works Administrator, Planning Director, and City Council). Review comments may also need
to be revised based on site planning and other design changes required by City staff or made by the applicant. The
applicant is encouraged to review all applicable sections of the Renton Municipal Code. The Development
Regulations are available online at https://www.codepublishing.com/WA/Renton/.
Project Proposal: The applicant is proposing a unit lot subdivision of 16 cottage units each with a minimum of
250 sf of private yard space. The units would include half of the units totaling between 1,000 sq. ft. and 1,500 sq.
ft. and the other half of the units totaling less than 1,000 sq. ft. The subject property is located at 11221 and
11233 SE 162nd St (parcel nos. 0088000132 and 0088000151) along the south side of SE 162 nd St. The project site
totals 67,977 square feet (1.56 acres) in area and is currently developed with two single-family homes and
associated detached accessory structures, proposed for removal. The site has a Comprehensive Plan Land Use of
Designation of Residential Medium Density and a zoning designation of Residential -8 (R-8). Onsite parking is
provided assuming all units would include 3 bedrooms. Each unit would have an assigned single car parking
space within the shared detached parking garage. Access to the site is proposed via a half street extension off of
SE 162nd St. No critical areas are mapped on the project site.
Current Use: The project site is currently developed with two single-family homes and associated detached
accessory structures, which are proposed for removal.
Development Standards: The project would be subject to RMC 4-2-110, “Development Standards for Single
Family Zoning Designations” effective at the time of complete application (noted as “R-8 standards” herein).
Zoning/Density Requirements: The subject property is located within the R-8 zoning classification. The density
range allowed in the R-8 zone is a minimum of 4.0 to a maximum of 8.0 dwelling units per one net acre. The
Residential Medium Density Land Use designation is intended to create opportunities for new single family
residential neighborhoods and to facilitate high-quality infill development that promotes reinvestment in existing
single family neighborhoods. Detached single family residential dwelling units are permitted uses within the R-8
zoning designation.
Cottage housing developments may be granted additional density, at a rate of two and one-half (2.5) times the
maximum density that could be achieved in a standard subdivision within the R-8 zone. The applicant shall
submit a pro forma subdivision plan for the proposed property showing the number of conventional lots that
would be permitted by the R-8 zone. This pro forma subdivision plan will be used to determine the maximum
number unit lots allowed, by multiplying the number of lots in the pro forma subdivision plan by two and one -
half (2.5).
The area of public and private streets (including driveway tracts and private access easements) an d critical areas
would be deducted from the gross site area to determine the “net” site area prior to calculating density.
The applicant would be required to provide a pro forma subdivision plan to determine the maximum number of cottage
housing units that could be developed on the project site.
Cottage Housing Development Standards:
Maximum Unit Size 1,500 sq. ft.
At least 50% of all cottages in a development shall be less than 1,000
sq. ft.
Minimum Number of Cottages
per Cluster
3
Maximum Number of Cottages
per Cluster
12
Minimum Distance Between
Structures
All units must be detached, with a minimum separation of 8 ft.
Maximum Wall Plate Height 18 ft.
Roofs with a pitch equal to or greater than 4:12 may project an
additional 6' vertically from the maximum wall plate height.
Maximum Number of Stories 2
Separation Between Clusters Individual clusters shall be separated by landscaping, common open
space, critical areas, or a community building.
Minimum Lot Size, Width and Depth –The minimum lot size in the R-8 zone is 5,000 sq. ft. The minimum lot
width is 50 feet for interior lots and 60 ft. for corner lots and the minimum lot depth is 80 feet. Additionally, the
subdivision regulations require new residential lots to contain a minimum width at their foremost points (where
the front property line meets ROW or private access) of no less than 80-percent of the required lot width and no
new lots shall have a depth-to-width ratio greater than four to one. Individual unit lots created for cottage
house developments are exempt from the minimum lot size, minimum lot width, and minimum lot de pth
requirements of the R-8 zone.
Building Standards – The R-8 standards allow a maximum building coverage of 50% of the lot area. The
maximum impervious coverage in the R-8 zone is 65%. Individual unit lots created for cottage house
developments are exempt from the maximum building coverage, and maximum impervious surface area
requirements of the R-8 zone.
Setbacks – Setbacks are the minimum required distance between the building footprint and the property line.
The required setbacks for the R-8 zone are: Front yard: 20 feet for the primary structure, except when all vehicle
access is taken from an alley, then 15 ft ; Rear yard: 20 feet; Side yards: 5 feet; and Secondary Front yard: 15
feet. Corner lots required to have a front yard and a secondary front y ard are relieved of the requirement to
have a rear yard; in place of a rear yard setback, the side yard setback of the zone shall apply. Individual unit
lots created for cottage house developments are exempt from setback requirements of the R-8 zone.
Fences/Walls: If the applicant intends to install any fences or retaining walls as part of this project, the location
must be designated on the landscape plan or grading plan. A fence and/or wall detail should also be included on
the plan. A retaining wall that is 4 feet or taller, as measured by the vertical distance from the bottom of the
footing to the finish grade at the top of the wall requires a building permit. A fence shall not be constructed on
top of a retaining wall unless the total combined height of the retaining wall and the fence does not exceed the
allowed height of a standalone fence. For more information about fences and retaining walls refer to RMC 4 -4-
040.
Landscaping: With the exception of critical areas, all pervious area shall have landscape treatment. Landscaping
may include hardscape such as decorative paving, rock outcroppings, fountains, plant containers, etc. Ten feet
(10') of on-site landscaping is required along all public street frontages. Where there is insufficient right -of-way
space or no public frontage, street trees are required in the front yard subject to approval of the Administrator.
A conceptual landscape plan shall be provided with the formal land use application as prepared by a
registered Landscape Architect or other certified professional.
Significant Tree Retention: If significant trees are proposed to be removed, a tree inventory and a tree retention
plan along with a tree retention worksheet shall be provided with the formal land use application. The tree
retention plan must show preservation of at least 30 percent (30%) of significant trees, and indicate how
proposed building footprints would be sited to accommodate preservation of significant trees that would be
retained. The Administrator may authorize the planting of replacement trees on the site if it can be
demonstrated to the Administrator's satisfaction that an insufficient number of trees can be retained.
In addition to retaining 30% of existing significant trees, the lot would be required to provide a mini mum tree
density of 2 trees per 5,000 square feet of lot area onsite.
Significant trees shall be retained in the following priority order:
Priority One: Landmark trees; significant trees that form a continuous canopy; significant trees on slopes greater
than twenty percent (20%); Significant trees adjacent to critical areas and their associated buffers; and
Significant trees over sixty feet (60') in height or greater than eighteen inches (18") caliper.
Priority Two: Healthy tree groupings whose associated undergrowth can be preserved; Other significant native
evergreen or deciduous trees; and Other significant non- native trees.
Priority Three: Alders and cottonwoods shall be retained when all other trees have been evaluated for retention
and are not able to be retained, unless the alders and/ or cottonwoods are used as part of an approved
enhancement project within a critical area or its buffer.
The Administrator may require independent review of any land use application that involves tree removal and
land clearing at the City's discretion.
If staff determines that the trees cannot be retained, replacement trees, with at least a 2-inch caliper or an
evergreen at least 6 feet tall, shall be planted at a rate of 12 caliper inches of new trees to re place each
protected tree removed. PLEASE NOTE: The City is currently in the process of updating its tree retention
regulations, which may impact the required tree retention for the project proposal. A formal tree retention
plan prepared by an arborist or landscape architect would be reviewed at the time of the formal land use
application if any trees are proposed for removal.
Access/Driveways/Parking: Access to the site is proposed via a 35-foot wide half street extension off of SE 162nd
St along the western boundary of the project site. The half street width shall be increased to accommodate on
street parking.
Parking requirements for cottage housing developments would be required to comply with the following: a
minimum and maximum of 1.6 parking spaces per cottage house of 3 bedrooms or greater; 1.4 spaces per 2-
bedroom cottage house; and 1.0 spaces per 1-bedroom cottage house or studio. In addition to the minimum
parking stalls required, a minimum 20% of the total number of required parking spaces in the cottage house
development shall be provided for guest parking and located in a common area accessible by guests. The
number of parking spaces required for cottage house development may be averaged and dispersed within the
parent site; provided, that at least one parking space is provided for each unit lot. Based on the proposal for 16
3-bedroom cottage units, the proposal would be required to provide 26 total parking spaces for the individual
cottages and five guest parking spaces for a total of 31 parking spaces on the project site. Parking would be
provided via four onsite, four-car garage units. In addition, nine surface parking spaces are proposed for a
total of 25 parking spaces, which would be less than the 31 spaces required. The proposal shall be revised to
include six additional parking spaces.
Residential Design and Open Space Standards: All single family residences would be subject to the Residential
Design Standards for the Cottage Housing Developments, outlined in RMC 4-2-115F. For cottage house
developments in the R-8 zone, the project is required to demonstrate compliance with the applicable Residential
Design and Open Space Standards at the time of subdivision application.
Critical Areas: No critical areas are mapped on the project site.
Environmental Review: Proposals that include residential developments of more than nine dwelling units are
subject to Environmental (SEPA) Review, in accordance with WAC 197-11.
Permit Requirements: The proposal would require Preliminary Plat approval, Environmental (SEPA) Review, and
Site Plan Review. All applications would be reviewed concurrently within an estimated timeframe of 12 weeks.
The 2022 fees would total is $17,041.50 ($10,830 Preliminary Plat + $1,600 SEPA + $3,800 Site Plan Review +
$811.50 Technology Fee = $17,041.50). Any modifications requested would be an additional $273 ($260 plus a
5% Technology Surcharge Fee). All fees are subject to change. The applications would be reviewed concurrently
within an estimated time frame of six to eight weeks. Detailed information regarding the land use application
submittal can be found on the City’s permitting page at permitting.rentonwa.gov and clicking on “Land Use”,
then “All Forms (A to Z).” The City now requires electronic plan submittal for all applications.
Once Preliminary Plat approval is obtained, the applicant must complete the required improvements and
dedications, as well as satisfy any conditions of the preliminary approval before submitting for Final Plat review.
Once final approval is received, the plat may be recorded. The newly created lots may only be sold after the plat
has been recorded. In addition to the required land use permits, separate construction and building permits
would be required.
Public Notice: A minimum of one Public Information Sign is required. The applicant is responsible for the
procurement, installation and maintenance of the sign. Detailed information regarding the land use application
submittal requirements is provided on the City of Renton website (www.rentonwa.gov).
Public Meeting: Please note a neighborhood meeting, according to RMC 4-8-090, is required for:
a. Preliminary plat applications;
b. Planned urban development applications; and
c. Projects estimated by the City to have a monetary value equal to or greater than ten million dollars
($10,000,000), unless waived by the Administrator.
The intent of this meeting is to facilitate an informal discussion between the project developer and the neighbors
regarding the project. The neighborhood meeting shall occur after a pre-application meeting and before submittal
of applicable permit applications. The public meeting shall be held within Renton city limits, at a location no
further than two (2) miles from the project site.
Public Outreach Sign: Preliminary Plats and projects estimated by the City to have a monetary value equal to or
greater than $10,000,000 require the applicant to install a public outreach sign. Public outreach signs are
intended to supplement information provided by public information signs by allowing an applicant to develop a
personalized promotional message for the proposed development. The sign is also intended to provide the
public with a better sense of proposed development by displaying a colored rendering of the project and other
required or discretionary information that lends greater understanding of the project. See the attached Public
Outreach sign handout for more information and specifications.
Fees: In addition to the applicable building and construction fees, impact fees would be required. Such fees
would apply to all projects and would be calculated at the time of building permit issuance and payable prior to
building permit issuance. The 2022 impact fees are as follows:
• A Transportation Impact Fee based on $10,861.69 per each new detached dwelling unit.
• A Parks Impact Fee based on $2,914.99 per each new detached dwelling unit.
• A Fire Impact fee of $829.77 per each new detached dwelling unit.
• A Renton School District Impact Fee of $7,681.00 (plus a 5% processing charge) per each new detached
dwelling unit.
A handout listing Renton’s development-related fees is available on the City of Renton website for your review.
Note: When the formal application materials are complete, the applicant is strongly encouraged to send a
copy of the application materials via email prior to submitting the complete application package. Please
contact Jill Ding, Senior Planner at jding@rentonwa.gov or 425-430-6598 before sending any documents
associated with the project.
Expiration: Upon approval, the Preliminary Plat is valid for five years with a possible one year extension (RMC 4 -
7-070M). It is the responsibility of the owner to monitor the expiration date.