Construction Mitigation Description
The proposed construction start date will be approximately in the Spring/Summer of 2017 and
completion will be in about two months.
Hours of operation will be 7:00 AM to 4:00 PM Monday through Friday.
The proposed haul route is South on Jones Avenue NE then East on NE 16th St, then south on Aberdeen
Ave NE, west on NE Park Drive to Interstateā405
Water trucks, street sweepers and any other requirements deemed necessary would be implemented
for any impacts that may occur.
There will be no anticipated weekend, late night or any other specialty hours proposed for construction
or hauling at this time.
Flag persons will be employed and signs will be installed for traffic control when necessary.