HomeMy WebLinkAboutECF_SEPA_MDNS_Draft_RSD_220124_v1.pdfMITIGATED DETERMINATION OF NON-SIGNIFICANCE
RENTON SCHOOL DISTRICT NO. 403
Lindbergh High School Modernization and Additions
DESCRIPTION OF PROPOSAL: The proposed action is the construction of modernization improvements
and additions at Lindbergh High School. Work at the high school consists of the construction of two additions
and an interior remodel to various spaces of the existing school. The high school will be occupied for the
duration of the project. In order to reduce impact to students and staff, construction will be phased. The scope
of work includes:
• A 1,630 square foot addition at the main entrance of the building. The addition will be the new location for
the Administration and Health Suite. Existing Lobby and Commons will be renovated to accommodate the
new Administration location.
• A 3,000 square foot addition at the northeast area of the school (known as the Lincoln House) will house
four new science classrooms and support spaces. The addition will require demolition of the roof, the north
wall and a portion of the east wall of the existing Lincoln House.
• The existing science wing of the school will be renovated to modernize science classrooms and support
spaces. A 700 square foot mechanical addition will be built on the east side of the existing science classroom
wing.
• Both science wings will have a rooftop clerestory to bring in daylighting to classrooms. The clerestory will
contain mechanical ductwork and equipment to serve classrooms.
• The existing Locker Rooms at the Gymnasium will be modernized. New Girls and Boys Locker Rooms
will be equally sized and provide shower and changing facilities. A classroom, training room and storage
rooms will also be provided.
• Interior renovations to support the relocation of various program areas will also be required at the existing
Administration Office, which will be demolished and reconfigured for the Counseling Office and Career
Center. The existing restrooms at the science wing will also be modernized.
• The HVAC systems throughout the existing building and Gymnasium will be upgraded.
Other key elements of the project include required frontage improvements along 128th Avenue SE and the
dedication of additional right-of-way. This work will involve the majority of earthwork for the project. An
estimated earthwork quantity for the total project is: Cut = 2,100 cubic yards and Fill = 600 cubic yards (Total
On-site Cut = 2,000 CY and Fill = 500 CY; Total Off-site Cut = 100 CY and Fill = 100 CY).
The proposal will require approval of a Site Plan Review, Frontage Improvements Standard Modification and
building/other public works permits from City of Renton.
CITY OF RENTON FILE NUMBER: #PRE21-000376
PROPONENT: Renton School District No. 403
LOCATION OF PROPOSAL: Lindbergh High School (LHS) is located at 16426 - 128th Avenue SE in
Renton. The subject site is over 37 acres in size and contains three tax parcels (KCA#282305 -9004, 282305-
9042, and 282305-9093). The school site is located within the northeast quarter of Section 28, Township 23
North, Range 5 East, Wm.M.
ZONING: R-6
GENERAL POLICY PLAN: Residential Medium Density
Renton School District No. 403 Mitigated Determination of Non-Significance
Page 2 Lindbergh High School
LEAD AGENCY: The Renton School District No. 403 (District) is the lead agency for this Mitigated
Determination of Non-Significance (MDNS). The lead agency for this proposal has determined that it does not
have a probable significant adverse impact on the environment. An Environmental Impact Statement (EIS) is
not required under RCW 43.21C.030(2)(c). This determination assumes compliance with State law and City of
Renton (as the permitting jurisdiction) ordinances related to general environmental protection. Issuance of this
threshold determination does not constitute approval of the permit(s). This proposal will be reviewed for
compliance with all applicable City of Renton (City) codes, which regulate development activities.
This decision was made after review of a completed Environmental Checklist and other information on file with
the lead agency. This information is available to the public upon request.
It is the policy of the District that, when undertaking an action involving the exercise of substantive SEPA
authority, the District shall consider, as appropriate under the circumstances, the ramifications of such action as
to one or more of the factors listed in Renton School District Policy 6890, Section 3.3 Substantive Authority.
This MDNS is issued with the following condition:
Transportation
• The proposal will comply with street frontage improvement requirements along 128th Avenue SE as outlined
by the City. The District is currently evaluating these improvements and the need for a modification to City
standards. Any modification will require City approval.
This MDNS is issued under WAC 197-11-350. The lead agency will not act on this proposal for 14 days from
the published date below. Comments must be submitted by February __, 2022 to the Responsible Official as
named below.
Responsible Official: Matt Feldmeyer, Architect
Title: Executive Director – Capital Planning & Construction
Address: Renton School District No. 403, 7812 South 124th Street, Seattle, WA 98178-4830
Phone: 425.204.4475 (Office) / 206.482.5253 (Mobile)
Email: matthew.feldmeyer@rentonschools.us
Signature: ______________________________ Date: __________________
Date Published: February __, 2021
There is no administrative appeal process for this determination.