Loading...
HomeMy WebLinkAbout09 - Construction Mitigation DescriptionDecember 22, 2016 Aberdeen Avenue Short Plat: Construction Mitigation Description Project Site Location: 1824 Aberdeen Ave NE, Renton WA 98056 Parcel Number: 334390-1606 Existing Lot Area: 16,161 SF / 0.37 Acres Proposed construction dates: Construction is expected to start late spring or early summer of 2017. Hours and days of operation: Construction will occur within hours allowed by the City of Renton (7:00 am to 8 pm Monday through Friday, and 9:00 am to 8:00 pm Saturday.) Proposed hauling/transportation routes: / Measures to be implemented to minimize dust, traffic and transportation impacts, erosion, mud, noise, and other noxious characteristics: A Temporary Erosion Control Plan is provided to mitigate erosion and sedimentation impacts with the civil design drawings. Best Management Practices include temporary and permanent seeding, plastic covering, and a silt fence. Construction will occur within hours allowed by the City to mitigate noise. Preliminary traffic control plan: The Manual on Uniform Traffic Control Devices will be used to develop a temporary traffic control plan. Trenching will occur within Aberdeen Ave NE for water, sewer, and storm. It is expected that work will occur on the shoulder for water service installation (MUTCD Typical Application 3). An alternating lane closure for a low-traffic volume road is proposed to install sewer and storm lines (MUTCD Typical Application 11). / /