Applicant Information
Project Address 3101 Mountain View Ave N Renton, WA 98056
Parcel Number: 334210-3895
Applicant: Seaborn Pile Driving Company, 1080 W Ewing St Building B, Seattle, WA 98119 206-236-1700
Property Owner: Sin Lew - 3101 Mountain View Ave N Renton, WA 98056
Legal Description: HILLMANS LK WN GARDEN OF EDEN # 1 POR OF LOTS 56-57 & 58 & OF ADJ 2ND CL
SH LDS DAF BEG AT INTX OF S LN OF LOT 58 WITH GOV MDR LN TH S 80-13-02 W 42.78 FT TH N 72-03-
18 W 99.44 FT TH S 89-50-57 W 190.56 FT TO INNER HARBOR LN TH N 23-40-00 E ALG SD HARBOR LN
52.76 FT TH N 89-50-57 E 219.38 FT TH S 75-24-20 E 83.14 FT TH S 61-50-30 E 22.86 FT TH N 89-50-57 E
TO ELY LN OF BLK A TH SLY ALG SD ELY LN TO S LN OF LOT 58 TH S 89-50-57 W ALG SD S LN TO BEG TGW
POR OF LOTS 57 & 58 & OF ADJ 2ND CL SH LDS DAF BEG AT INTX OF S LN OF LOT 58 WITH MDR LN TH S
80-13-02 W 42.78 FT TO TPOB TH N 72-03-18 W 99.44 FT TH S 89-50-57 W 190.56 FT TO INNER HARBOR
LN TH S 23-40-00 W ALG SD HARBOR LN TAP S 80-13-02 W FR TPOB TH N 80-13-02 E TO TPOB
Description of Work: We propose to drive (18) new 8" steel piles and construct a 613 sq ft dock covered
by grated decking material.
Job specific comments
Purpose
The proposed dock is to provide for safe boat moorage and safe water recreational activities for a single
family residence.
Habitat Enhancement
The proposed planting plan has been designed to mitigate for the existing and proposed pier.
Water Quality
In order to prevent debris from entering the lake during the demolition stage of the project, a
containment boom will surround the crane barge and work area.
Permits
Renton Substantial Development Permit:
We are applying for the permit to be reviewed under the:
4-3-090.E.7 Use Regulations - Piers and Docks
2
Mitigation
Shoreline Plantings: The shoreline plantings have been designed to provide the spread of tree and shrub
nutrients into the adjacent waters of Lake Washington.
Fully grated deck: The proposed dock will have a fully grated deck to provide light penetration below
the dock where there is no light penetration with the existing structure.
Piles: The proposed pier has been designed to maximize the distance between pile bents and minimize
the number of piles. The proposed 6” – 8” piles meet local building codes and reduce the pile footprint.
Contractor: Seaborn Pile Driving Company License #: SEABOPD942CG
Address: 1080 W Ewing St. Bldg B. Seattle WA 98119
Office: 206.236.1700 Mobile: 253-459-3267
Contact: Madison Johnson Email: permits@seabornpiledriving.com
Construction Narrative
Mobilization
Mobilize crew, crane barge, supply and debris barges, and materials on site
Pile Driving
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and debris
that may be generated during construction.
2. Locate the new piles to be driven per the building permit drawings.
3. Using the crane and a vibro-hammer, drive the piles to required refusal.
4. Cut the piles to elevation.
5. Clean the work area and remove the silt fence/boom.
Dock construction (New Dock)
1. Construct a silt fence/boom waterward of the bulkhead to contain any silt and debris that
may be generated during construction.
2. Install new piles where applicable.
3. Install new steel I-beam pile caps and attach to the piles by welding.
4. Install metal brackets on edge of cap by welding them to I-beam to support glulam beams.
5. Install ledgers, stringers, and beams via screws to support the SunWalk decking
6. Install electrical conduit and water lines under the deck along the dock. Wiring and re-
connection to be completed by others.
7. Install the SunWalk grating with stainless steel screws making sure the screws are aligned
and flush with the surface.
8. Install any boat or PWC lifts.
9. Clean the work area and remove the silt fence/boom.
3
Structural Notes
General
● All materials, workmanship, design and construction shall conform to the submitted
drawings and the International Building Code.
● The contractor will be responsible for all safety precautions and methods and processes
to perform the designated work.
Design Criteria
● The existing design and construction meets the live load specification of a minimum of
40 PSF.
Materials
All materials used in the construction of the dock will be for use on the water and of the highest quality
available on the market. All materials will conform to the International Building Code.
For example:
● Wood piles and pile stubs. The proposed wood pile stub will be Class B (12” @ 3’ from Butt) –
40’ Douglas Fir pilings per ASTM D-25.
● Steel pile collars – ASTM A53 GrB with Devran 261QC low temperate cure epoxy (16 mils) finish
coated full length.
● Structural Lumber – All lumber will be graded and marked in conformance with WCLIB standard
grading rules.
● Fasteners – All fasteners, bolts, nuts and nails will be epoxy-coated.
● Decking – The decking will consist of SunWalk fiberglass grating which is pet and children
friendly and will provide years of safe and comfortable use.
Preservatives
● All wood preservatives to be state approved and will be applied and fully cured prior to
installation over the water.
● All hardware and fasteners to be epoxy-coated.
4
Best Management Practices
1. Above the Water Line Work
1. Seaborn Pile Driving Company will employ one each crane barge, one supply and
one debris barge to complete the scope of work. A tug will tow the barges on
and off the job site.
2. Seaborn Pile Driving Company personnel working in, near or over the water will
at all time wear either USCG approved life vests or work vest as well as hard hats
and safety glasses.
2. Material Handling
1. While at the job site, a floating containment boom will completely surround the
work area.
2. All removed piles and the existing dock structure will be placed on the debris
barge where they will be contained and kept out of the lake.
3. Hazardous Materials
● No hazardous materials will be mixed or stored in or near the water. No cleaning
of materials will be performed in or near the water.
4. Polluting Materials in Water
● Seaborn Pile Driving Company will take extra precautions to ensure materials
don’t fall into or pollute the water. Any material that enters the water will be
removed immediately. Any hazardous material such as oily rags will not be
handled near or over the water.
● A spill kit will be employed on the barges at the job site.
● If any pollutants enter the water, Seaborn Pile Driving Company will contact the
appropriate agencies and report the spill immediately.
5. Materials Disposal
● Seaborn Pile Driving Company will dispose of the rotten wood and pile sections
in an approved legal disposal site in accordance with all applicable laws and
permit requirements.