HomeMy WebLinkAboutCombined_Exhibits_1-26_Front_PagesDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Project Location Map
ERCReport_VIA405_170816_v2
ENVIRONMENTAL REVIEW COMMITTEE REPORT
ERC MEETING DATE: August 14, 2017
Project Name: VIA 405 Apartments
Owner: RVA Cinema LLC, 520 Pike St Suite 1500, Seattle, WA 98101
Applicant/Contact: Parkway Capital, Inc, Craig Koeppler, 520 Pike St, Suite 1500, Seattle, WA 98101
Project File Number: PR17000215
Land Use File Number: LUA17-000237,ECF,PUD
Project Manager: Matt Herrera, Senior Planner
Project Summary: The applicant is requesting a Preliminary Planned Urban Development (PUD) land use
decision and threshold determination under the State Environmental Policy Act (SEPA)
for the construction of a mixed use building containing 270 multi-family dwelling units,
ground floor commercial and residential amenity space, ground floor and second floor
structured parking, and associated improvements. The property is located within the
Commercial Office (CO) zoning classification and Commercial Mixed Use (CMU) land use
designation. The site's existing theater building will be removed. Access to the subject
property is provided via existing vehicle driveway easements within the Renton Village
Shopping Center and Evergreen Building properties that connect to S Grady Way and S
Renton Village Pl with new pedestrian connections proposed to these public streets with
the project. Critical Areas identified on City maps include Flood Hazard, Seismic Hazard,
Regulated Slopes, and a Non-Fish Perennial (Np) stream. A stream buffer determination
as it relates to non-regulated sites separated from critical areas by pre-existing
substantial improvements will also be a component of the PUD application.
Project Location: 25 S Grady Way (APN 723200-0010)
Exist. Bldg. Area SF: 42,479sf Proposed New Bldg. Area (footprint):
Proposed New Bldg. Area (gross):
49,866sf
242,889sf
Site Area: 2.6 acres (113,294sf)
STAFF
RECOMMENDATION:
Staff Recommends that the Environmental Review Committee issue a Determination
of Non-Significance – Mitigated (DNS-M).
N
N
APRIL 22, 2017 VIA 405 Apartments • RENTON PPUD Submittal RVA Cinema LLC
North elevation
West elevation
scale 1" = 30' - 0"
1st Floor EL. 0
2nd Floor EL. 10
3rd Floor el. 20
4th Floor el. 30
5th Floor el. 40
6th Floor el. 50
7th Floor el. 60
8th Floor el. 70
roof el. 82
Amenity ROOM roof el. 84
Residential exercise room
Residential Leasing
office
entrance/ lobby entrance
p2
Storefront
Private Terrace
P-2 Private
Balcony w/
metal
railing S 5 S 6 S 1
S 7
Aluminum
Storefront B1 Brick Veneer
P3
P3 metal louvers & green screen
1st Floor EL. 0
2nd Floor EL. 10
3rd Floor el. 20
4th Floor el. 30
5th Floor el. 40
6th Floor el. 50
7th Floor el. 60
8th Floor el. 70
roof el. 82
Corner
North & west exterior elevations
PROPOSED EXTERIOR MATERIALS A
Elevator and stair overrun el. 87
APRIL 22, 2017 VIA 405 Apartments • RENTON PPUD Submittal RVA Cinema LLC
Aerial view Southeast Along I 405
Aerial view from North Entrance Drive Aerial view from east
Aerial view Southwest Along I 405
Distant views
1093 SF (OFF
SITE)
1304 SF (OFF SITE)1958 SF (OFF
SITE)
161 SF (OFF
SITE)
658 SF (OFF
SITE)
99 SF (OFF SITE)
90 SF (OFF
SITE)57 SF (OFF
SITE)
819 SF
1494 SF INCL. LAWN
297 SF
75 SF
340 SF
1392 SF565 SF
52 SF
162 SF (ON SITE)
126 SF
160 SF
315 SF
19,956 SF STREAM
AND EXISTING
FUNCTIONAL BUFFER
LOADING AREA
FOR MOVE-IN
PROPOSED ART OR
VERTICAL FEATURE
PROPOSED WATER
FEATURE
MAIN ENTRY &
RESIDENTIAL
LOBBY
MAIL
ROOM
LEASING
OFFICE
MECH.
ROOM
GAS METER
(OUTSIDE)
GARAGE
ENTRY/EXIT
GARAGE
ENTRY/EXIT
TRASH
ROOM
ACTIVE /PEDESTRIAN
OPEN SPACE AREA
279 SF (121 SF IS
INTERIOR PARKING
LOT PLANTING)
325 SF
47 SF
284 SF
EXISTING
BUILDING
LINE
PROPOSED
BUILDING
LINE
ELECTRICAL
ROOM
ELECTRICAL
TRANSFORMER
ROOM
75'LIMITOFDISTURBANCELIMITOFDISTURBANCERESIDENTIAL
AMENITY
PROPOSED 5 FT. HT.
VINYL COATED CHAIN
LINK BUFFER
PROTECTION
FENCING.
(8) NEW
STALLS
PLANTER WITH
FLOWERING
VINES AND
SUPPORT
LAWN
LOW
SHRUBS
SEEDED LAWN
TO LIMITS OF
DISTURBANCE
NEW C.I.P.
CONCRETE
WALL -
SEE CIVIL
SITE PLAN
LOW
SHRUBS
EXISTING RED
CEDAR TREE
TO REMAIN OR
RELOCATE
PROPOSED VOLUNTARY CRITICAL
AREA BUFFER ENHANCEMENT
PLANTING. SEE SHEETS LE1
THROUGH LE4.
PROPOSED BENCHES
AND MOVEABLE SEATING
PROPOSED
TOT LOT
STREET TREES
IN 4' X 6' GRATES
EXISTING FUNCTIONAL
STREAM BUFFER EDGE
AND EDGE OF EXISTING
PAVEMENT.
R R R R R R
(7) NEW
STALLS
POTS WITH
SEASONAL
PLANTINGS
POTS WITH
SEASONAL
PLANTINGS
APPROX. 6770 SF
VOLUNTARY STREAM
BUFFER ENHANCEMENT.
SEE SHEETS LE1-LE4.
4 SF (ON SITE)
85 SF 350 SF (86 SF IS
INTERIOR PARKINGLOT PLANTING)
LIMIT OF DISTURBANCE AT EXISTING
CURB LINE & NEW UTILITY TRENCHES
ADDITIONAL MINOR DISTURBANCE TOINSTALL FENCE & ENHANCEMENT
PLANTINGS
BUFFER ENHANCEMENT
TREES, TYP. SEE SHEET LE1.
BACKLESS
BENCHES AT
NORTH SIDE
OF BUILDING,
TYP.
127 SF (ON SITE)
STREAM BUFFER LINE
EXISTING OAK TREE
TO REMAIN WITH
GROUNDCOVERS AT
BASE OF TREE
4 FT. HT. BLACK
METAL FENCE ON
CONCRETE CURB
TO CONTAIN PLAY
Magnollia grandiflora 'Victoria'/Victoria Evergreen Magnolia
Cornus kousa 'Chinensis'/Kousa Dogwood
Malus spp./Flowering crabapple
Quercus rober alba 'Crimschmidt'/Crimson Spire Oak
Crateagus phaenopyrum/Washington Hawthorne
Juniperus chinensis/Hollywood juniper
Abies lasiocarpa/Alpine fir
Cornus stol. 'Midwinter Fire'/Red Twig Dogwood
Abelia 'Kaleidoscope'/Kaleidoscope Abelia
Acer truncatum platanoides 'Warrensred'/Pacific Sunset Maple
Betula papyfera/ Paper birch (native)
Spiraea spp./Spiraea varieties
SHRUBS
PERENNIALS AND SEASONAL ACCENTS
Acer palmatum spp./ Japanese Maple
Hemerocallis sp./Daylily varieties
Geranium sp./Perennial Geranium varieties
Helictotrichon sempervirens/Blue Oat Grass
Calamagrostis acutiflora 'Karl Foerster'/ Feather Reed Grass
Hydrangea spp./Hydrangea varieties
Carex oshiminensis/Evergreen Sedge varieties
Miscanthus sinensis/Maiden Grass
Pennisetum spp./Fountain Grass varieties
Liriope spp./Lily Turf
Lavandula angustifolia/Lavander
Rudbeckia hirta/Blackeyed Susan
Echinacea sp./Coneflower varieties
Ilex crenata/Japanese Holly
GROUNDCOVERS & GRASSES
Arctostaphyllos uva ursi/Kinnickinnick
Fragraria chiloensis/Sand Strawberry
(REPRESENTATIVE TYPES OF PLANT MATERIAL PROPOSED)
Styrax japonica/ Japanese Snowbell
Juniperus virginiana 'Taylor'/Taylor Columnar Juniper
Existing decidous tree to remain
Existing coniferous tree to remain
Synthetic Turf or Sod/Natural Lawn (owner to determine)
Acer circinatum/ Vine Maple (native)
Pyrus c. 'Chanticleer'/ Chanticleer Fl. Pear
Prunus laurocerasus/Laurel
Berberis thunbergii/ Crimson Barberry
Viburnum davidii/David's Viburnum
Potentilla fruticosa/Shrubby Cinquefoil
Erica & Calluna/Heather & Heath
Nandina domestica/Heavenly Bamboo
Lonicera pileata/Boxleaf Honeysuckle
Cotoneaster dameri/ Bearberry
Shrubs, groundcover and lawn
Existing decidous tree to remain -in buffer or off-site
Existing coniferous tree to remain- in buffer or off-site
(Minimum 2" caliper or multi-s
(Minimum 6
REPLACEMENT TREES:
(6) 2" CALIPER TREES REQUIRED, SHOWN WITH "R"
PROPOSED NEW SHADE REPLACEMENT TREES = 14
MINIMUM
- 5 gal. at 4' o.c.; 2&3 gal. at 30 - 36" o.c. spacing
- 1 gal. at 24" o.c. spaci
See stream buffer enhancement plans on sheets
LE1 through LE4.
N
Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation
A world ofcapabilitiesdeliveredlocally
GEOTECHNICAL REPORT
VIA 405 APARTMENTS
Submitted To: Mr. Craig Koeppler, Vice President RVA Cinema LLC Parkway Capital, Inc.
520 Pike Street, Suite 1500 Seattle, WA 98101
Submitted By: Golder Associates Inc. 18300 NE Union Hill Road, Suite 200
Redmond, WA 98052
March 20, 2017 Project No.: 1771669.100 REPORT
VIA 405 APARTMENTS
SECTION 10
CONSTRUCTION MITIGATION DESCRIPTION
Memorandum
DATE: 03/20/17
(Revised 06/19/2017)
TO: Rick Tomkins, PE
FROM: Richard Pratt
Senior Biologist
Gray Rand
Senior Biologist
SUBJECT: Stream, Critical Areas, and Habitat Assessment
PROJECT: VIA 405 Apartments (Roxy Cinema Redevelopment), Renton, WA
PROJECT NO.: RVAC0000-0002
COPIES: File
INTRODUCTION
At the request of RVA Cinema LLC, David Evans and Associates, Inc. (DEA) conducted a stream
and habitat assessment at the proposed VIA 405 Apartments property (parcel # 7232000010) on
February 2, 2017, near the intersection of Rainier Avenue South and South Grady Way in Renton,
Washington. The assessment was performed in support of a preliminary planned urban
development (PPUD) application to redevelop the existing Roxy Cinema site into a 270-unit
apartment project. The site visit was conducted to identify streams, wetlands, and habitat on or
adjacent to the site. The project location is shown in Figure 1. One stream (Rolling Hills Creek)
was identified in the study area. No wetlands or ditches were identified in the study area. Stream
locations, as mapped by the City of Renton, are shown in Figure 2.
STREAM CHANNEL AND BUFFER SOUTHOF STREAM TO REMAIN UNDISTURBED75.00'PROPOSED 4 FT. HT. BLACK VINYLCOATED CHAIN LINK FENCE(LIMIT OF WORK)O.H.W.M.PROPERTY BOUNDARY
PROPERTY BOUNDARY(LIMIT OF WORK)O.H.W.M.O.H.W.M.O.H.W.M.RC(LIMIT OF WORK)FLOWFLOWFLOWFLOWFLOWPROPOSED PARKINGCURBEXISTING CURB TO REMAIN6,796 SFOLD PARKING CURBTO BE REMOVEDO.H.W.M.WOOD STRAND MULCHSHRUBSGROUND COVERBOTANICAL NAMESYMBOLCOMMON NAMESIZEREMARKSQNTYPLANT SCHEDULEMYRICA CALIFORNICAPACIFIC WAX-MYRTLE77SYMPHORICARPUS ALBUSSNOWBERRY28PHILADELPHUS LEWISIIMOCK ORANGE6ACER CIRCINATUMTALL OREGON GRAPEAMELANCHIER ALNIFOLIA SERVICEBERRY3MAHONIA AQUIFOLIUMVINE MAPLE22'-4' HT., 2 GAL.4' MIN. HT., 5 GAL.FULL, WELL BRANCHEDMULTI STEMMED MULTI-STEMMEDFULL, WELL BRANCHEDSPACING5' O.C.5' O.C.AS SHOWN6' O.C.5' O.C.FULL, WELL BRANCHEDFULL, WELL BRANCHEDRIBES SANGUINEUM ROSA NUTKANANOOTKA ROSERED FLOWERING CURRANT504' O.C.FULL, WELL BRANCHED275' O.C.FULL, WELL BRANCHED4' MIN. HT., 5 GAL.4' MIN. HT., 5 GAL.4' MIN. HT., 5 GAL.2'-4' HT., 2 GAL.2'-4' HT., 2 GAL.2'-4' HT., 2 GAL.INDIAN PLUMSWORD FERNOCEAN SPRAYHERBACEOUSHOLIDISCUS DISCOLOROEMLERIA CERASIFORMISPOLYSTICHUM MUNITUM56' O.C.FULL, WELL BRANCHED2'-4' HT., 2 GAL.165' O.C.FULL, WELL BRANCHED2'-4' HT., 2 GAL.734' O.C.FULL, WELL BRANCHED2'-4' HT., 2 GAL.AS SHOWNTREESTHUJA PLICATAPSEUDOTSUGA MENZIESIIDOUGLAS FIR2WESTERN RED CEDAR14' MIN. HT., B&BSINGLE LEADERSINGLE LEADERAS SHOWN4' MIN. HT., B&BAS SHOWNCORNUS NUTTALLIIPACIFIC DOGWOOD7AS SHOWNRC3AS SHOWNSALIX LUCIDAPACIFIC WILLOW1'-2' HT., 1 GAL.1.5" CAL., B&BFULL, WELL BRANCHEDFULL, WELL BRANCHEDNGENERAL NOTESROOT CROWN 2"-4" ABOVEAMENDED SOIL GRADE2X2 HARDWOOD STAKEDRIVEN TO REFUSAL (24"MIN.). SECURE TO TREEWITH PLASTIC LOCK STRIP.TOP OF STAKE TO POINT TOPREVAILING WIND. REMOVESTAKES AFTER ONE YEAR.FINISH GRADE3" UNIFORM WOOD STRANDMULCH, HOLD BACK 2"-3"FROM MAIN STEMREMOVE ALL BURLAP ANDWIRE BASKET FROM ROOTBALLEXISTING SUBGRADEFERTILIZER PER PLANTINGNOTESFINISH GRADEAMENDED SOILEXISTING SUBGRADEFERTILIZER PER PLANTINGNOTESROOT CROWN 1"-2" ABOVEAMENDED SOIL GRADE3" UNIFORM WOOD STRANDMULCH, HOLD BACK 2"-3"FROM MAIN STEMNOT TO SCALESTRAW WATTLE TIGHTLY ABUTTADJOINING WATTLESFLOWPLAN VIEWSECTION 8 INCHESMINIMUMSTAKE SPACING4 FT MAXIMUM3 TO 7 INCHESWOOD STAKE X X 24 INCHESSTRAW WATTLE8 TO 10 INCHESIN DIAMETERNOT TO SCALECONIFER TREE PLANTINGNOT TO SCALESHRUB PLANTINGPLANTING BED PREPARATIONNOT TO SCALE3" WOOD STRAND MULCH3" COMPOST TILLED INTO 7"EXISTING SOIL7" EXISTING SOIL3" SCARIFIED SUBGRADEFINISH GRADEEXISTING SUBGRADEBUFFER ENHANCEMENT PLAN DECIDUOUS TREE PLANTINGNOT TO SCALEROOT CROWN 2"-4" ABOVEAMENDED SOIL GRADE2' MIN. OR UNTIL
REFUSAL
+(,*+72)
TREE
(2) 2"x2"x8' HARDWOOD STAKES(NON-TREATED) LOCATEDEQUIDISTANTLY OUTSIDEPLANTING PITPREVAILINGWINDDIRECTIONSTAKINGPLANREMOVE ALL BURLAP ANDWIRE BASKET FROM ROOT BALLHOLD BACK SPECIFIED COVER2"-3" AWAY FROM MAIN STEM3" UNIFORM WOOD STRANDMULCH
N
Job No. 15-098
Via 405 Apartments
PRELIMINARY
TECHNICAL INFORMATION REPORT
Renton, Washington
Issued: June 22, 2017
Prepared For:
RVA Cinema, LLC
14410 Bel-Red Road
Bellevue, WA 98007
Prepared By:
Beau J. Willert, EIT
Travis J. Wageman, EIT
Reviewed By:
Richard A. Tomkins, PE
1
C5
2
C5
3
C5
N
N
Shoffner Consulting
21529 4TH AVE. W #C31 BOTHELL, WA 98021 MOBILE:(206)755-2871
February 16, 2017
Craig Koeppler
RVA Cinema, LLC
520 Pike St. Suite 1500
Seattle, WA
98101
RE: Tree Inventory and Retention Plan - RVA Cinema, Renton
Craig:
This report is provided to address the recent inventory I conducted on the RVA
Cinema property in the City of Renton. Please see the accompanying Tree
Inventory Map and Tree Evaluation Data spreadsheet for reference to this report.
1. Site Conditions and Proposed Development
The property is located in Renton off Grady Way in an office/industrial/retail area.
It’s currently developed with a cinema complex and an access road. A critical
area stream corridor runs across the site behind the building along the southern
boundary.
The proposed development of the site is to remove the existing building and to
re-develop the site with a 270 unit multi-family building including covered parking.
The critical area stream corridor will remain and not be impacted by the
development.
2. Tree Inventory Results
I visited the site recently to conduct an inventory and gather information on all of
the trees. All of the trees were labeled by the surveyors with numbered metal
tags which correspond to the numbers on the inventory map and in the tree
evaluation data spreadsheet.
I conducted visual condition assessments according to the methods and
procedures specified in the ISA Tree Risk Assessment Manual (2013) by viewing
them up close to observe the trunk and root collar and from afar to observe
conditions in the crown. The tree evaluation data spreadsheet provides
information on all of the trees. In total, I conducted on 63 trees; 31 in the
developable portion of the site around the building and 32 in the critical area
stream corridor. 1
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: July 31, 2017
TO: Matt Herrera, Senior Planner
FROM: Brianne Bannwarth, Development Engineering Manager
SUBJECT: Traffic Concurrency Test – VIA 405 Apartments;
LUA17-000237, ECF, PUD
The applicant is requesting a Preliminary Planned Urban Development (PUD) land use decision
and threshold determination under the State Environmental Policy Act (SEPA) for the
construction of a mixed use building with 270 multi-family dwelling units, ground floor
commercial and residential amenity space, ground floor and second floor structured parking, and
associated improvements. The property is located within the Commercial Office (CO) zoning
classification and Commercial Mixed Use (CMU) land use designation. The site's existing theater
building will be removed. Access to the property is provided via existing vehicle driveway
easements within the Renton Village Shopping Center connecting to S. Grady Way and S. Renton
Village Pl. with new pedestrian connections proposed to these streets with the proposal.
The proposed development would generate a reduction of approximately 340 net new average
weekday daily trips. During the weekday AM peak hour, the project would generate
approximately 64 net new trips (5 inbound and 59 outbound). During the weekday PM peak hour,
the project would generate a reduction of approximately 102 net new trips (43 inbound and 59
outbound). The proposed project passes the City of Renton Traffic Concurrency Test per RMC 4-
6-070.D as follows:
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 of 3 LUA**-000***
ADVISORY NOTES TO APPLICANT
The following notes are supplemental information provided in conjunction with the administrative land use
action. Because these notes are provided as information only, they are not subject to the appeal process for
the land use action.
Planning:
(Contact: Matt Herrera, 425-430-6593, mherrera@rentonwa.gov)
1. RMC section 4-4-030.C.2 limits haul hours between 8:30 am to 3:30 pm, Monday through Friday unless
otherwise approved by the Development Services Division.
2. Commercial, multi-family, new single family and other nonresidential construction activities shall be
restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through
Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight
o’clock (8:00) p.m. No work shall be permitted on Sundays.
3. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an
appropriate ground cover over any portion of the site that is graded or cleared of vegetation and where
no further construction work will occur within ninety (90) days. Alternative measures such as mulch,
sodding, or plastic covering as specified in the current King County Surface Water Management Design
Manual as adopted by the City of Renton may be proposed between the dates of November 1st and
March 31st of each year. The Development Services Division’s approval of this work is required prior to
final inspection and approval of the permit.
4. A National Permit Discharge Elimination System (NPDES) permit is required when more than one acre is
being cleared.
5. The applicant will be required to submit a Final Stream Mitigation Report and Maintenance and
Monitoring proposal. In addition, the applicant will be required to comply with all the code requirements
of RMC 4-3-050 Critical Areas. This includes, but is not limited to, placing the critical area within a Native
Growth Protection Easement, providing fencing and signage, and providing the City with a site
restoration surety device and, later, a maintenance and monitoring surety device.
6. The applicant may not fill, excavate, stack or store any equipment, dispose of any materials, supplies or
fluids, operate any equipment, install impervious surfaces, or compact the earth in any way within the
area defined by the drip line of any tree to be retained.
7. The applicant shall erect and maintain six foot (6') high chain link temporary construction fencing around
the drip lines of all retained trees, or along the perimeter of a stand of retained trees. Placards shall be
placed on fencing every fifty feet (50') indicating the words, “NO TRESPASSING – Protected Trees” or on
each side of the fencing if less than fifty feet (50'). Site access to individually protected trees or groups
of trees shall be fenced and signed. Individual trees shall be fenced on four (4) sides. In addition, the
applicant shall provide supervision whenever equipment or trucks are moving near trees.
8. This permit is shall comply with the Bald and Golden Eagle Protection Act. The permitted is responsible
for adhering to the U.S. Fish and Wildlife Service National Bald Eagle Management Guidelines (2007) and
/or your U.S. Fish and Wildlife Service permit.
Development Engineering:
(Contact: Ann Fowler, 425-430-7382, afowler@rentonwa.gov)
1. See Attached Development Engineering Memo dated July 28, 2017
ADVISORY NOTES TO APPLICANT
Page 2 of 3 LUA17-000237
Fire Authority:
(Contact: Corey Thomas, 425-430-7024, cthomas@rentonwa.gov)
1. Fire impact fees are applicable at the rate of $495.10 per multifamily unit. This fee is paid at time of
building permit issuance. The fee increases to $718.56 per unit on January 1st, 2017. Credit will be
granted for the removal of the existing building. No charges apply to parking garage areas.
2. The preliminary fire flow is 3,750 gpm. A minimum of four fire hydrants is required. One within 150-
feet and three within 300-feet of the building. Project shall meet maximum hydrant spacing of 300-
feet on center also. Hydrants are required within 50-feet of the fire department connection for the
standpipe and sprinkler system. A new looped fire main is required around the entire building. A
number of lengthy water main extensions and replacements are required in order to meet this fire
flow requirement as fire flow is inadequate as it exists.
3. Approved fire sprinkler and fire alarm systems are required throughout the building. Dry standpipes
are required in all stairways. Direct outside access is required to the fire sprinkler riser room. Fire
alarm system is required to be fully addressable and full detection is required. Separate plans and
permits required by the fire department.
4. Fire department apparatus access roadways are required within 150-feet of all points on the building.
Fire lane signage required for the on-site roadways. Required turning radius is 25-feet inside and 45-
feet outside. Roadways shall be a minimum of 20-feet wide. Roadways shall support a minimum of a
30-ton vehicle and 75-psi point loading. Any required fire access roadways required for this project
that are located on other parcels shall have a separate dedicated fire access easement specifically
recorded for each parcel.
5. The building is required to be equipped with an elevator that meets the size requirements for a
bariatric size stretcher to all areas of the building. Car size shall accommodate a minimum of a 40-inch
by 84-inch stretcher.
6. All areas of the building shall comply with the City of Renton Emergency Radio Coverage ordinance.
Testing shall verify both incoming and outgoing minimum emergency radio signal coverage. If
inadequate, the building shall be enhanced with amplification equipment in order to meet minimum
coverage. Separate plans and permits are required for any proposed amplification systems.
Community Services:
(Contact: Name, 425-430-6619, lbetlach@rentonwa.gov)
1. Parks Impact fee per Ordinance 5824 applies.
Police:
(Contact: Cyndie Parks, 425-430-7521, cparks@rentonwa.gov)
224 Police Calls for Service Estimated
CONSTRUCTION PHASE
1. To protect materials and equipment it is recommended that all materials and tools be locked up when
not in use. The site will need security lighting and any construction trailers should be completely
fenced in with portable chain link fencing. Fencing will provide both a physical and psychological
barrier to any prospective thief and will demonstrate that this area is private property. Construction
trailers should be kept locked when not in use, and should also have a heavy duty deadbolt installed
with no less then a 1 1/2” throw when bolted. Glass windows in the trailer should be shatter resistant.
Any construction material that contains copper should be removed from the construction site at the
end of each working day; housing this material at the site will only tempt thieves to try and steal it.
Toolboxes and storage containers should be secured with heavy duty padlocks and kept locked when
not in use or removed from site altogether.
ADVISORY NOTES TO APPLICANT
Page 3 of 3 LUA17-000237
2. I also recommend the business post the appropriate “No Trespassing” signs on the property while it’s
under construction. This will aid police in making arrests on the property after hours if suspects are
observed vandalizing or stealing building materials. The use of private security personnel to patrol the
site during the hours of darkness is recommended.
COMPLETED BUILDING
1. All exterior doors should be made of solid metal or metal over wood, with heavy duty deadbolt locks,
latch guards or pry resistant cylinders around the locks and peepholes. If glass doors are used, they
should be fitted with the hardware described above and additionally be fitted with a layer of security
film. Security film can increase the strength of the glass by up to 300%, greatly reducing the likelihood
of breaking glass to gain entry. Access to the back of any retail buildings should be limited, or at
minimum, only accessed via keypad or locking hardware that can’t be tampered with from the outside.
2. It is recommended that any outside common areas be monitored with surveillance cameras to include
the limited access parking garage levels. It’s not uncommon for multi housing properties to experience
theft and/or vandalism during the hours of darkness. An auxiliary security service could be used to
patrol the property (this includes the limited access garages), especially during the hours of darkness.
Any alternative entrances should have controlled access doors to prevent trespassing.
3. All areas of this project need to have adequate lighting. This will assist in the deterrent of theft from
motor vehicle (one of the most common crimes in Renton) as well as provide safe pedestrian travel for
both employees and residents. Signage advising residents and guests to keep valuables out of their
vehicles while parked should be heavily posted in all parking areas (to include the limited access
garages).
4. Landscaping should be installed with the objective of allowing visibility – not too dense and not too
high. Too much landscaping will make residents and their guests feel isolated and will provide criminals
with concealment to commit crimes such as burglary and theft. With the expanse of land surrounding
this site, there is also the possibility of attracting transients to the area.
5. The limited access garage will be a very tempting target for auto thieves. Theft from motor vehicle and
auto theft are prevalent and any garage housing vehicles utilized by visitors, employees, and /or
residents are likely to be items of value left inside (electronic equipment, GPS units, garage fobs, etc.). I
recommend the installation, and substantial advertisement of, surveillance cameras inside and outside
any limited access garage, an overabundance of lighting, and a noticeable presence of courtesy patrol.
I assume there will be a large influx of unwanted curiosity seekers brought into this particular area due
to its isolated location and ease of access. Police will not be monitoring, towing or citing vehicles
onsite or in garages so the utilizing of security patrol services is highly recommended for this property.
6. All dumpster areas should be housed within a structure of a height and strength that will deter loitering
subjects from gaining access to them when not in service. Due to the location of this development, I
would assume it will experience a population of transients and having easy access to trash receptacles
will motivate them to remain in the area.
7. I highly recommend that the developer have a Renton Police Crime Prevention Representative conduct
a security survey of the premises once construction is complete. This will allow for a more
comprehensive security evaluation that would be specific to each structure. Contact Cyndie Parks,
425.430.7521, when you would like to make an appointment.
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: July 28, 2017
TO: Mathew Herrera, Senior Planner
FROM: Ann Fowler, Civil Plan Reviewer
SUBJECT: Utility and Transportation Comments for VIA 405 Apartments
25 South Grady Way
LUA16-000866
I have reviewed the application for the VIA 405 Apartments at 25 South Grady Way (APN(‘s) 7232000010)
and have the following comments:
EXISTING CONDITIONS
The site is approximately 2.6 acres in size and is square in shape. The existing site contains a 38,000 square
foot cinema building, surface parking and landscaping. The site is bordered by neighboring commercial
sites to the north, east and west, and is bordered by Rolling Hills Creek and Interstate 405 to the south.
Water Water service is provided by the City of Renton. The site is in the Valley service area in the 196
hydraulic pressure zone. The static water pressure is approximately 74 psi at ground elevation
of 25 feet. The site is located outside of an Aquifer Protection Area. There are existing water
mains within easements near the site as follows:
8-inch water main along Renton Village private access road with maximum capacity of 2,100
gallons per minute (gpm) – refer to water project plan no. 1883.
12-inch water main in parking lot along the south side of building at 501 S Grady Way with
maximum capacity of 4,200 gpm – refer to water project plan no. w 2114.
There is an existing 3 inch domestic water meter, 6-inch fire sprinkler service and 2-inch
irrigation meter serving the existing building.
Sewer Wastewater service is provided by the City of Renton. There is an existing 18-inch Concrete
wastewater main located in South Renton Place (see City plan no. S-0079).
Storm There is an existing private storm drainage system located on the subject parcel which appears
to drain to the outfall to Rolling Hills Creek.
Streets The project is bordered by I-405 to the south. Future widening of I-405 may impact the buildable
portion of the proposed Lot.
VIA 405 Apartments – LUA16-000866
Page 2 of 6
CODE REQUIREMENTS
WATER
1. Based on the information submitted with the land use application, Renton Regional Fire Authority
has determined that the preliminary fire flow demand for the development is 3,750 gpm. This
exceeds the available capacity of the 8-inch water mains servicing the development.
2. The proposed water main improvements as shown on the composite utility civil plan submitted
with the Land Use Application provides the required extension of a new 12-inch water main
from the end of the existing 12-inch main near the southwest corner of the building at 501 S
Grady Way to the northeast corner of the subject property. The applicant is providing the
required looped 12-inch water main around the building since the fire flow demand is above
2,500 gpm. The installation of the proposed 12-inch water main continues from the southwest
corner of the new looped water main to an existing 8-inch main located in the south access
road.
a. A 15-ft water easement is required for the looped water main.
b. If the water mains are outside the subject property or outside of existing easements, the
applicant shall acquire additional easement from adjacent property owners. Portion of
existing easement within the proposed building footprint will need to be vacated by the
City. No buildings, structures or vaults shall be placed within the easement area and
within 5 feet of the water main.
3. Installation of fire hydrants shall be as required by Renton Fire Prevention will be required. The
number and location of the hydrants shall be determined based on the City’s review of the final
building and site plans.
4. Installation of a fire sprinkler stub with a detector double check valve assembly (DDCVA) for
backflow prevention to the building. The DDVCA shall be installed in an outside underground vault
per City standard plan no. 360.1 (or 360.2 depending on the size of the system). The DDVCA may
be installed inside the building if it meets the conditions as shown on the City’s standard plan
360.5 for the installation of a DDCVA inside a building.
5. Installation of a domestic water meter with a reduced-pressure principle assembly (RPPA) behind
the meter. The RPPA shall be installed in an above ground heated enclosure per Renton Standard
plan no. 350.2.
6. Meter sizing shall be based on Uniform Plumbing Code meter sizing criteria. Sizing calculations
shall be provided to the City. Meters 3” or larger, shall be installed in a concrete vault located
outside of the building per COR Standard Plan 320.4. By-pass piping, valves, and associated piping
shall be purchased and installed by the developer / contractor under City observation for meters
3” or larger.
7. A separate meter is required for landscape irrigation per COR Standard Plan 320.1. A double check
valve assembly (DCVA) is required behind the meter per COR Standard Plan 340.8.
8. Please refer to City of Renton General Design and Construction Standards for Water Main
Extensions as shown in Appendix J of the City’s 2012 Water System Plan.
9. Adequate horizontal and vertical separation between the new water main and other utilities
(storm sewer pipes and vaults, sanitary sewer, power, gas, electrical) shall be provided for the
operation and maintenance of the water main.
10. Retaining walls, rockeries or similar structures cannot be installed over the water main unless the
water main is inside a steel casing.
VIA 405 Apartments – LUA16-000866
Page 3 of 6
11. The development is subject to a water system development charge (SDC) fee. This is payable at
construction permit issuance.
a. The SDC fee for water is based on the size of the new domestic water to serve the project.
The current water fee for a single 1-inch meter is $3,486.00 per meter, 1-1/2 inch meter
is $17,430.00 and a 2-inch meter is $27,888.00.
b. A water system redevelopment credit will apply for the existing domestic water meters if
they are abandoned.
c. The SDC fee for fire service is based on the size of the fire service line to serve the project.
The current SDC fee for a 6-inch fire service line is $22,476.00.
d. SDC fees are assessed and payable at construction permit issuance.
12. Water service installation charges for each proposed domestic water service is applicable. Water
Service installation for a 1-inch water service line is $2,850.00* per service line, a 1-1/2 inch water
service is $4,580.00* per service line and for $4,710.00* for each 2-inch water service line. This is
payable at construction permit issuance.
13. Drop-in meter fee is $460.00* per meter for a 1-inch meter, $750.00* for a 1-1/2 inch meter,
and $950.00* for a 2-inch meter. This is payable at issuance of the building.
14. Final determination of applicable fees will be made after the water meter size has been
determined.
15. Additional water system development charges and water meter charges will apply if a landscape
irrigation meter is required and is based on the size of the meter.
SEWER
1. All existing sewers will be required to be cut and capped during demolition of the building. New
sewers shall be installed to serve the development.
2. Covered parking areas will need to direct parking drainage to the sanitary sewer system through
an oil/water interceptor. If any parking is not covered, it will need to be directed away from the
sanitary sewer and into the storm sewer system.
3. Retail restaurant space will need to be directed to a grease interceptor(s) prior to connecting into
the City’s Sanitary Sewer system. The grease interceptor shall be sized in accordance with
standards found in the latest edition of the Uniform Plumbing Code (UPC). The grease interceptor
shall drain by gravity to the sewer main and shall be located so that it is accessible for routine
owner maintenance.
4. The development is subject to applicable wastewater system development charges based on the
size of the new domestic water to serve the project.
a. SDC fee for sewer is based on the size of the new domestic water to serve the project.
The current sewer fee for a 1-inch meter is $2,540.00 per meter, 1-1/2 inch meter is
$12,700.00 and a 2-inch meter is $20,320.00.
b. A redevelopment credit of the wastewater system development charges in the amount
equal to the SDC fee for the size of the existing domestic water meter(s) will be applied
to each of the existing meters if they are abandoned and capped at the main line.
c. SDC fees are payable at construction permit issuance.
SURFACE WATER
1. A geotechnical report, dated March 20, 2017, completed by Golder Associates Inc. for the site
has been provided. The submitted report describes the site is a Low Erosion and Low Landslide
VIA 405 Apartments – LUA16-000866
Page 4 of 6
Hazard areas. Erosion control measures will need to be in place prior to starting grading activities
on the site. The supplemental addendum to the geotechnical report entitled Infiltration
Feasibility – Via 405 Apartments LUA17-000237, PPUD, dated June 12, 2017, discusses the soil
and groundwater characteristics of the site including infiltration potential and provides
recommendations for project design and construction of on-site BMPs. The report discounts the
use of infiltration due to the fill soils, which is underlain by native alluvial deposits consisting of
silt or sandy silt, which would be considered a low permeability restrictive layer that would
impede infiltration. Geotechnical recommendations presented need to be address within the
project plans.
2. A Preliminary Drainage Plan and Technical Information Report (TIR), dated June 22, 2017, was
submitted by Triad a division of David Evans and Associates, inc. with the Land Use Application.
Based on the City of Renton’s flow control map, the site falls within the
Peak Rate Flow Control Standard area matching Existing Site Conditions and is within the Black
River Drainage Basin. The development is subject to Full Drainage Review in accordance with the
2017 Renton Surface Water Design Manual (RSWDM). All nine core requirements and the six
special requirements have been discussed in the Technical Information Report.
3. As discussed in the TIR, the proposed developed is exempt from Core Requirement #3, Flow
Control, since the proposed development will result in less than a 0.15 cfs increase in surface
water run-off from the existing site conditions 100-year peak flow rate when modeled using the
latest version of the Western Washington Hydrology Model (WWHM 2012), as outlined in Core
Requirement #3.
4. A portion of the project site lies within the 100-year FEMA flood boundary. The proposed project
improvements will increase the floodplain storage volume from 31,108 cubic feet to 34,688 cubic
feet.
a. The building finished floor is required to be 1-foot above the FEMA map base flood
elevation of 27.6 (NAVD 88). An Elevation Certificate will be required showing the
building finished floor is 1-ft above the FEMA base flood elevation prior to granting of
certificate of occupancy.
5. The development is required to provide enhanced basic water quality treatment prior to
discharge. A modular wetland biofiltration vault is proposed to meet the water quality treatment
requirement to satisfy Core Requirement #8.
6. Any proposed water quality vault shall be designed in accordance with the RSWDM that is current
at the time of civil construction permit application.
7. All new conveyance systems constructed as part of the project (including relocation of existing
storm lines that convey off-site runoff) must be sized to RSWDM standards for the total tributary
area (onsite and offsite) that the storm systems serve.
8. Some of the existing on-site storm system that is being relocated may have been designed
originally to provide flow control as a detention tank facility as part of the Renton Village Cinema
development project. The applicant needs to determine if this is the case and maintain the same
level of flow control provided by the existing system for the existing site and/or off-site area.
9. The oil/water separator that is being relocated will need to be designed based upon the 2017
RSWDM.
10. Appropriate on-site BMPs will be required to help mitigate the new runoff created by this
development. A preliminary drainage plan, including the application of on-site BMPs, has been
included with the land use application. The final drainage plan and drainage report must be
submitted with the civil construction permit application.
a. Final evaluation of the application of on-site BMPs to the maximum extent feasible will
be completed during civil construction permit review. The applicant may be required to
VIA 405 Apartments – LUA16-000866
Page 5 of 6
apply additional on-site BMPs in order to meet the minimum requirements outlined in
Core Requirement #9.
11. A Construction Stormwater General Permit from Department of Ecology will be required since
grading and clearing of the site exceeds one acre. A Stormwater Pollution Prevention Plan
(SWPPP) is required for this site.
12. Surface water system development fee is $0.641 per square foot of new impervious surface, but
not less than $1,608. This is payable prior to issuance of the construction permit.
TRANSPORTATION
1. The proposed development does not front any existing City public roads or rights-of-way. Site
access is obtained via a network of internal private easements.
2. Additional easements may need to be obtained to provide emergency access to the development.
3. ADA access ramps shall be installed at all pedestrian crossings. Ramps shall be shown at each
intersection. Ramps shall be oriented to provide direct pedestrian crossings.
4. Parking lot construction shall be in accordance with City code 4-4-80G.
5. Lighting plans are required to be submitted with the land use application and will be reviewed
during the construction utility permit review.
6. A traffic analysis dated April 18, 2017, was provided by Transportation Engineering Northwest
(TENW). The site generated traffic volumes were calculated using data from the Institute of
Transportation Engineers (ITE) Trip Generation Manual, 9th Edition, (2009). Based on the
calculations provided and providing credit for the existing trips utilized for the current site use,
the proposed development would generate a decrease of approximately 340 net new average
weekday daily trips. During the weekday AM peak hour, the project would generate an increase
of approximately 64 net new trips (5 inbound and 59 outbound). During the weekday PM peak
hour, the project would generate a decrease of approximately 102 net new trips (a decrease of
43 inbound and a decrease of 59 outbound). As detailed in the report the proposed project is
not expected to lower the levels of service of the surrounding intersections included in the
traffic study. Increased traffic created by the development will be mitigated by payment of
transportation impact fees.
7. Paving and trench restoration shall comply with the City’s Trench Restoration and Overlay
Requirements.
8. Payment of the transportation impact fee is applicable on the construction of the development
at the time of application for the building permit. The 2017 rate of transportation impact fee for
an apartment is $3,358.55 per room. The 2017 rate of transportation impact fee for a shopping
center is $13.29 per square foot of building. The 2017 rate of transportation impact fee for a sit-
down restaurant is $30.48 per square foot of building. The transportation impact fee that is
current at the time of building permit application will be levied, payable at building permit issue.
GENERAL COMMENTS
1. All existing and proposed utility lines (i.e. electrical, phone, and cable services, etc.) along property
frontage or within the site must be underground. The construction of these franchise utilities
must be inspected and approved by a City of Renton inspector.
2. Maximum exposed retaining wall height is 6-ft and shall be setback a minimum of 3-ft from the
right-of-way as outlined in RMC 4-4-040 – Fences, Hedges and Retaining Walls.
VIA 405 Apartments – LUA16-000866
Page 6 of 6
3. Adequate separation between utilities as well as other features shall be provided in accordance
with code requirements.
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other utilities is
required with the exception of water lines which require 10-ft horizontal and 1.5-ft
vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.
4. All construction utility permits for utility and street improvements will require separate plan
submittals. All utility plans shall confirm to the Renton Drafting Standards. A licensed Civil
Engineer shall prepare the civil plans. Please visit the Development Engineering Forms page for
the most up-to-date plan submittal requirements:
http://rentonwa.gov/business/default.aspx?id=42473
5. A landscaping plan shall be included with the civil plan submittal. Each plan shall be on separate
sheets.
6. Fees quoted in this document reflect the fees applicable in the year 2017 only and will be assessed
based on the fee that is current at the time of the permit application or issuance, as applicable to
the permit type. Please visit www.rentonwa.gov for the current development fee schedule.
7. * An additional 3% technology fee will be added to each fee marked with an asterisk (*).
From: Karen Walter <KWalter@muckleshoot.nsn.us>
Sent: Sunday, August 06, 2017 4:48 PM
To: Matthew Herrera
Subject: RE: City of Renton Notice of Application LUA - VIA 405 Apartments-
LUA17-000237 ECF, PPUD, HEX
Matthew,
This email is a follow-up to our July 2017 phone conversation regarding the VIA 405 Apartments project
and the stream classification of Rolling Hills Creek. As I noted in the call, Rolling Hills Creek is considered
a Type F stream by WSDOT, WDFW, and the Tribe. The culvert 995470 conveying this stream is on the
State's Fish Passage Barrier list and to be on this list means that there is at least 200 meters of available
fish habitat upstream. Please see WSDOT's fish passage barrier map
http://www.wsdot.wa.gov/data/tools/geoportal/?config=fish-passage-
barriers&layers=%7B%22layer0%22%3A%5B%5D%2C%22Uncorrected+Barriers+Statewide%22%3A%5B0
%5D%2C%22Corrected+Barriers+Statewide%22%3A%5B0%5D%7D¢er=-
122.19989776607876%2C47.47051349086841&zoom=14
The data used to make the fish barrier determination and available habitat upstream is done by WDFW
in a cooperative effort with WSDOT. In fact, Mike Barber, the person noted on the link above used to
work for WDFW and was in charge of their fish barrier assessment program. Arguably any data available
via this source was completed by WDFW and should be considered as a WDFW stream study.
Please note that Salmonscape is but one source regarding fish passage barriers and fish distribution. It is
not the only source and should never be considered the sole source of fisheries data. As noted it does
not currently show Rolling Hills on it even though this stream has been mapped by Renton and WSDOT
for some time. WSDOT provided detailed information about the stream as part of its Ecosystems Report
for the I-405 Tukwila to Renton project; however, obviously this information was not provided to the
WDFW staff involved in Salmonscape.
Please note, too, that when the City did its stream study, it did not consult with us. We received the
Study several years after its completion and have questioned the water typing for some streams in the
area (i.e. Maplewood Creek tributaries) and noted that this study did not adequately consider fish
passage barriers and how they may affect salmon distribution and observations.
If you need further information regarding the classification of Rolling Hills Creek, I suggest you call Mike
Barber at WSDOT (formerly with WDFW) and discuss the data with him.
Also as we discussed on the phone, we recommend that the applicant maximize the native tree and
shrub plantings along Rolling Hills Creek including areas that are along the south side of the stream
outside of WSDOT's right of way on I-405 to improve stream conditions prior to WSDOT's replacements
of the I-405 culverts to become fish passable.
Thank you,
Karen Walter
Watersheds and Land Use Team Leader
Muckleshoot Indian Tribe Fisheries Division Habitat Program
CDEPARTMENTOFCOMMUNITY—“Renton0ANDECONOMICDEVELOPMENTENVIRONMENTAL(SEPA)DETERMINATIONOFNON-SIGNIFICANCE-MITIGATED(DNS-M)PROJECTNUMBER:LUA17-000237,ECF,PUDAPPLICANT:ParkwayCapital,Inc,CraigKoeppler,520PikeSt,Suite1500,Seattle,WA98101PROJECTNAME:VIA405ApartmentsPROJECTDESCRIPTION:TheapplicantisrequestingaPreliminaryPlannedUrbanDevelopment(PUD)landusedecisionandthresholddeterminationundertheStateEnvironmentalPolicyAct(SEPA)fortheconstructionofamixedusebuildingcontaining270multi-familydwellingunits,groundfloorcommercialandresidentialamenityspace,groundfloorandsecondfloorstructuredparking,andassociatedimprovements.ThepropertyislocatedwithintheCommercialOffice(CO)zoningclassificationandCommercialMixedUse(CMU)landusedesignation.Thesite’sexistingtheaterbuildingwillberemoved.AccesstothesubjectpropertyisprovidedviaexistingvehicledrivewayeasementswithintheRentonVillageShoppingCenterandEvergreenBuildingpropertiesthatconnecttoSGradyWayandSRentonVillageP1withnewpedestrianconnectionsproposedtothesepublicstreetswiththeproject.CriticalAreasidentifiedonCitymapsincludeFloodHazard,SeismicHazard,RegulatedSlopes,andaNon-FishPerennial(Np)stream.Astreambufferdeterminationasitrelatestonon-regulatedsitesseparatedfromcriticalareasbypreexistingsubstantialimprovementswillalsobeacomponentofthePUDapplication..PROJECTLOCATION:255GradyWay(APN723200-0010)LEADAGENCY:CityofRentonEnvironmentalReviewCommitteeDepartmentofCommunity&EconomicDevelopmentTheCityofRentonEnvironmentalReviewCommitteehasdeterminedthatitdoesnothaveaprobablesignificantadverseimpactontheenvironment.AnEnvironmentalImpactStatement(ElS)isnotrequiredunderRCW43.21C.030(2)(c).ConditionswereimposedasmitigationmeasuresbytheEnvironmentalReviewCommitteeundertheirauthorityofSection4-9-070DRentonMunicipalCode.Theseconditionsarenecessarytomitigateenvironmentalimpactsidentifiedduringtheenvironmentalreviewprocess.Becauseotheragenciesofjurisdictionmaybeinvolved,theleadagencywillnotactonthisproposalforfourteen(14)days.Appealsoftheenvironmentaldeterminationmustbefiledinwritingonorbefore5:00p.m.onSeptember1,2017.Appealsmustbefiledinwritingtogetherwiththerequiredfeewith:HearingExaminer,CityofRenton,1055SouthGradyWay,Renton,WA98057.AppealstotheExamineraregovernedbyRMC4-8-110andmoreinformationmaybeobtainedfromtheRentonCityClerk’sOffice,(425)430-6510.PUBLICATIONDATE:AUGUST18,2017DATEOFDECISION:AUGUST14,2017