HomeMy WebLinkAboutSummary of Bidder Inquiries No. 2Page 1 of 1
Summary of Bidders Inquiries No. 2
2022 Curb Ramps for Overlay
CAG-22-009
Date: April 20, 2022
The responses to bidder inquiries, unless incorporated into a formal addendum to the contract,
are not part of the contract and are provided for the bidders’ convenience only. The responses
may be considered along with all other information furnished to prospective bidders for the
purpose of bidding on the project. The use of information provided in the responses to bidder
inquiries is not to be construed in any way as a waiver of the provisions nor excuse the contractor
from full compliance with the contract requirements. Bidders are cautioned that subsequent
responses or contract addenda may affect or vary a response previously given and any such
subsequent response or addenda should be taken into consideration when submitting a bid for
the project.
Bidder Inquiry No. 1
We are a new general contractor and are wanting to bid on the 2022 curb ramps for overlay
project. We currently do not have employment security number and they are saying we will have
it the 20th of May. Are we still able to bid without this number?
City of Renton Response to Bidder Inquiry No. 1
Per section 1-02.5 Proposal Forms, the Employment Security Department Number shall be
included in the Bid Proposal.
End of Summary of Bidder Inquiries No. 2