HomeMy WebLinkAboutC21004289 - Civil Construction Permit_20220428DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Construction Permit: C21004289
IVR Number: 21004289
Permit Information
Permit Name: RSD Elementary #16
Address/Location:09/02/2021Application Date:1023059124Parcel Number: 1075 DUVALL AVE NE
Permit Type:04/28/2022Issue Date:Engineering
Permit Work Class:04/28/2023Expiration Date:Construction
Inspector: Tom Main 206-999-1833 Plan Reviewer: Michael Sippo 425-430-7298
Description: Civil Construction permit for the Renton School District Hearing Examiner Site Plan Review, Conditional Use Permit,
and two modifications for a new elementary school located at 1058 Chelan Ave NE. The project site includes 11
parcels approximately 11.08 acres with street frontage along both Chelan Ave NE and Duvall Ave NE. The zoning
designation for 10 of the 11 parcels is Residential 8 with one Residential 10 parcel located on the northwestern
portion of the project site. The proposed elementary school building would be approximately 77,000 square feet and
two stories. In addition to the building, there would be an outdoor classroom area, multipurpose playfield, hard/soft
play areas, and a covered play area. A surface lot would provide parking for 82 vehicles and a school bus load/unload
area would provide capacity for eight full size busses and two special education buses. Passenger vehicle access to
the subject property is proposed at the south end of the site with one full access driveway along the Duvall Ave NE
frontage and one exit only access on Chelan Ave NE. School bus access would be provided via two driveways along
Duvall Ave NE. The applicant would construct street frontage improvements along both the Duvall Ave NE and Chelan
Ave NE frontages. The project site contains two wetlands, one of the which the applicant proposes to permanently
impact with the proposed improvements, and the other to temporarily impact the buffer area during construction.
Proposed mitigation to the permanently impacted wetland would occur via credits purchased from the City’s
Springbrook Creek Wetland and Habitat Mitigation Bank. Temporary impacts to the retained wetland’s buffer would
be mitigated via restoration/enhancement and then permanent protection following construction. Stormwater
generated from the proposed improvements would be conveyed to two subsurface detention facilities with treatment
provided via modular vaults prior to discharge into the City’s system. Portions of the site would also disperse flows to
gravel trenches and eventually discharge into the remaining wetland. The site contains 499 trees of which 208 are
located on the site’s western wetland and buffer and would be retained. Approximately 20 trees would be removed for
street improvements. Of the remaining 271 trees in the developable portion of the site, the applicant proposes to
retain 18 trees. The applicant has requested two code modifications with the application related to onsite parking and
street frontage improvements. The Renton School District will act as Lead Agency for SEPA review. Studies submitted
with the application include critical areas report, drainage report, geotechnical report, arborist report, and traffic
impact analysis.
Contacts
Name Address PhoneTypeBilling
KATIE POND
Hutteball + Oremus Architecture
4010 Lake Wash Blvd NE, Suite 320
Kirkland, WA 98033
B: (425) 282-8948Applicant
RENTON SCHOOL DISTRICT NO 4 300 SW 7TH ST
RENTON, WA 98057
Contact
Gerard Boulanger
CORNERSTONE GENERAL
11805 North Creek Pkwy S, Suite
115
Bothell 98011
B: (425) 481-7460
C: (206) 484-4136
Contractor
Business License Number: 55015Construction Contractor: CORNEGC970J3
THERESA REECE
RENTON SCHOOL DISTRICT#403
300 SW 7TH ST
RENTON, WA 98057
Owner
Traci Brewer-Rogstad
Renton School District
300 SW 7th St
Renton, WA 98057-2307
B: (425) 204-4403
C: (206) 643-3261
OwnerX
GARY+DENISE LONG 1024 CHELAN Ave NE O: (000) 000-0000Owner
Gerard Boulanger
CORNERSTONE GENERAL
11805 North Creek Pkwy S, Suite
115
Bothell 98011
B: (425) 481-7460
C: (206) 484-4136
Specialized
Billing
Page 1 of 2THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Construction Permit: C21004289
General Conditions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
Ÿ
This permit and plans must be posted at the job site at all times.Ÿ
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton codes and ordinances.
Ÿ
Call 425.430.7203 or go to: https://permitting.rentonwa.gov one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Ÿ
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.Ÿ
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
Ÿ
(Date)(Signature)
Page 2 of 2THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES