HomeMy WebLinkAboutPA PARK Addendum A - 5-20-2022PHILIP ARNOLD PARK BID PHASE
ADDENDUM A 20 May 2022
Addendum A - Page 1 of 1
ADDENDUM – A
TO THE CONTRACT DOCUMENTS FOR
City of Renton
PHILIP ARNOLD PARK
Project Issued: May 9, 2022
Addendum A Issued: May 20, 2022
Bid Opening Date: June 1, 2022
To: All Holders of Bid/Contract Documents:
This addendum forms part of the Contract Documents and modifies the original Plans and
Specifications, for which proposals are due on the date and time above.
Acknowledge receipt of this addendum on “Addenda Received” of the Bid Documents in the
Contract Documents. Failure to do so might subject the bidder to disqualification.
This addendum shall clarify the Contract Documents as follows:
Item No. 1 – Drawing No. G.02 | Sheet 02 – DRAWING INDEX
1. In the DRAWING INDEX, add (UNDER SEPARATE COVER) behind sheet titles for
Sheets 03, 04, and 05.
2. In the DRAWING INDEX, revise sheet title listed for Sheet CU.04 to "UTILITY NOTES /
DETAILS."
Item No. 2 – Specification 00 00 02 – TABLE OF CONTENTS
1. Under DIVISION 32 – EXTERIOR IMPROVEMENTS, revise Section 33 33 00 to 32 33
00.
Item No. 3 – Specification 00 80 00 – FORMS
1. Change Proposal Bid Bond – Form A, revise to separate Principal and Surety signature
lines.
– – – – DRAWING INDEX NOTES, & ABBREVIATIONSBID SETPHILIP ARNOLD PARKIN COMPLIANCE WITH CITY OF RENTON STANDARDS2101 4TH AVENUE, SUITE 1800 SEATTLE, WA 98121206.682.3051 phone206.682.3245 faxSTATEOFWASHING
TONLICENSEDLANDSCAPEARCH
ITECT MERIT OVIIRNO. 1396 EXP.03/2023
C: C21006142
TED-04-4211
DRAWING INDEXG.02 PHILIP ARNOLD PARK
PHILIP ARNOLD PARK PR:LUA:
R-421102
PHILIP ARNOLD PARK BID PHASE
REVISED - ADDENDUM A 20 May 2022
Contract No. CAG-22-015 00 00 00 - 1
Philip Arnold Park Site Improvements May 20, 2022
TABLE OF CONTENTS
Contract No. CAG-22-015
City of Renton
Philip Arnold Park Site Improvements
DIVISON 0 – PROCUREMENT & CONTRACTING REQUIREMENTS
00 00 00 Table of Contents
00 00 03 Bid Proposal Form
00 11 13 Advertisement for Bids
00 20 00 Bidder’s Qualification Statement
00 21 00 Instructions to Bidders
00 23 00 Supplementary Instructions
00 42 10 Bid Submittal Checklist
00 52 00 Agreement Between Owner and Contractor – City of Renton Agreement
00 72 00 General Conditions
00 73 00 Supplemental Conditions
00 80 00 Forms:
Form A – Proposal Bid Bond
Form B – List of Subcontractors, Part 1 (Plumbing, Electrical)
Form C – List of Subcontractors, Part 2 (Structural Steel)
Form D – Contractor Qualification, Evaluation
Form E – Qualifications of Key Personnel
Form F – Contract Bond Form
DIVISION 1 – GENRAL REQUIREMENTS
01 10 00 Summary of Work
01 11 30 Hazardous Materials
01 12 00 Delegated Design
01 14 00 Work Restrictions
01 20 00 Payment Procedures
01 21 00 Prevailing Wage Rates
01 30 00 Administrative Requirements
01 32 16 Construction Schedule
01 40 00 Quality Requirements
01 40 10 Product Substitution Request
01 42 00 Definitions
01 50 00 Temporary Facilities and Control
01 58 00 Temporary Project Signage
01 70 00 Execution and Closeout Requirements
01 74 00 Construction Waste Management and Disposal
01 78 00 Closeout Submittals
PHILIP ARNOLD PARK BID PHASE
REVISED - ADDENDUM A 20 May 2022
Contract No. CAG-22-015 00 00 00 - 2
Philip Arnold Park Site Improvements May 20, 2022
DIVISION 2 – EXISTING CONDITIONS
02 41 00 Site Demolition
DIVISION 3 – CONCRETE
03 10 00 Concrete Forming and Accessories
03 15 00 Concrete Joints and Accessories
03 21 00 Steel Reinforcement
03 30 00 Cast‐in‐Place Concrete
03 30 05 Concrete Mix Design
03 39 00 Concrete Curing
03 62 00 Grout
DIVISION 11 – EQUIPMENT
11 68 23 Exterior Court Structures & Surfacing
DIVISION 26 – ELECTRICAL
26 00 00 Basic Electrical Materials and Methods
26 05 19 Conductors and Cables
26 05 26 Grounding and Bonding
26 05 33 Raceways and Boxes
26 05 43 Underground Ducts and Handholes
26 05 53 Electrical Identification
26 27 26 Wiring Devices
DIVISION 31 – EARTHWORK
31 10 00 Site Preparation
31 23 13 Subgrade Preparation
31 23 16 Excavation
31 23 23.00 Fill and Backfill
31 23 23.15 Trench Backfill
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base Courses
32 12 16 Asphalt Paving
32 13 13 Concrete Paving
32 17 23 Pavement Markings
32 32 19 Unit Masonry Block Walls (& Scramble Alternate 1)
32 33 00 Site Furnishings
32 33 00.01 Boardwalk
32 84 00 Planting Irrigation
32 90 00 Planting
DIVISION 33 – UTILITIES
33 11 00 Water Utility
33 31 00 Sanitary Sewer Utility
33 40 00 Storm Drainage Utility
PHILIP ARNOLD PARK BID PHASE
REVISED - ADDENDUM A 20 May 2022
Contract No. CAG-22-015 00 00 00 - 3
Philip Arnold Park Site Improvements May 20, 2022
APPENDIX
Appendix A City of Renton Parks & Trails Sign Panel Memorandum
Appendix B Geotechnical Design Recommendations for Philip Arnold Park
Appendix C Building Asbestos and Lead Assessment Report
Appendix D Boardwalk Plans & Details
Appendix E Picnic Shelters Plans & Details
Appendix F Record Drawings for Picnic Shelter
Appendix G Record Drawings for Community Building
Appendix H Portland Loo Plans & Details
Appendix I Temporary Project Sign Example
Appendix J Permits
PHILIP ARNOLD PARK SITE IMPROVEMENTS
Proposal Bid Bond – FORM A
REVISED - ADDENDUM A
BID BOND PAGE 1 OF 1
FORM A
Proposal Bid Bond
KNOW ALL MEN BY THESE PRESENTS, That we, [Contractor] ________________________________
____________________of [address] ____________________________________________ as
Principal, and [Surety] __________________________________________________________________
a corporation duly organized under the laws of the State of ____________________________________ ,
and authorized to do business in the State of Washington, as Surety, are held and firmly bound unto the
City of Renton in the sum of five (5) percent of the total amount of the Bid of said Principal for the Work
hereinafter described, for the payment of which, well and truly to be made, we bind ourselves, our heirs,
executors, administrators and assigns, and successors and assigns, jointly and severally, firmly by these
presents.
The condition of this bond is such, that whereas the Principal herein is herewith submitting his/her or its
sealed Bid for the following construction, to wit:
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
said Bid and proposal, by reference thereto, being made a part hereof.
NOW, THEREFORE, if the said proposal Bid by said Principal be accepted, and the Contract be awarded
to said Principal, and if said Principal shall duly make and enter into and execute said Contract and shall
furnish performance bond as required by the City of Renton within a period of ten (10) days from and after
said award, exclusive of the day of such award, then this obligation shall be null and void, otherwise it
shall remain and be in full force and effect.
IN THE EVENT the Principal, following award, fails to execute an Agreement with the City of Renton in
accordance with the terms of the Bidding Documents and furnish a performance bond with Surety or
Sureties approved by the City of Renton within ten (10) days from and after said award, then Principal
shall forfeit the Bid Bond/Bid Proposal Deposit or Surety shall immediately pay and forfeit to the City of
Renton the amount of the Proposal Bid Bond, as set forth in RCW 35A.40.200 and RCW 35.23.352.
IN TESTIMONY WHEREOF, the Principal and Surety have caused these presents to be signed and
sealed this ___________________________ day of ___________________________, ________.
________________________________ ________________________________
[Principal] [Surety]
________________________________ ________________________________
[Signature of authorized official] [Signature of authorized official]
________________________________ By: _____________________________
[Title] [Attorney-in-Fact]
________________________________
[Address]
________________________________
[Phone Number]
Parks & Recreation
Department Memorandum
DATE: May 16, 2022
TO: Potential Bidders
FROM: Betsy Severtsen, RLA, Capital Projects Coordinator
SUBJECT: Philip Arnold Park Improvements, CAG-22-015, Pre-Bid
Conference Notes
1. Link to Audio and Video Recordings of Pre-Bid Conference
https://fileshare.rentonwa.gov:8443/?ShareToken=A3AA363F093A5D21EEA818
C4EDDAC6E934A82474
2. Attendees
a. City of Renton – Betsy Severtsen, Capital Projects Coordinator
b. City of Renton – Alan J. Wyatt, Capital Projects Manager
c. HBB Landscape Architecture – Dean Koonts
d. PND Engineers – Chris Wiest
e. Ohno Construction - Jill Agnelli
f. Ohno Construction - Raquel Tomas
g. JW Fowler – Shannon Williams
h. Pivetta Brothers – Jamie Osborn
i. LW Sundstrom – Robin Carlton
3. Introduction
a. Philip Arnold Park in the Renton Hills neighborhood, built in the 1960s
b. Intent for project: improve ADA accessibility, renovation/improvements
to meet current needs
4. Schedule
a. Release of Bid Documents: May 9, 2022
b. Pre-Bid Conference: May 16, 2022, 8:30 AM PST
c. Questions Due: March 24, 2022, 4:00 PM (Submit questions via email to
bsevertsen@rentonwa.gov)
d. Bids Due: June 1, 2022, prior to 2:00 PM. City of Renton, City Clerk.
Lobby, City Hall, 1055 S. Grady Way; Renton, WA 98057.
e. Bid Opening: June 1, 2022, at 3:00 PM. City of Renton, ZOOM
(Refer to ZOOM link in ADVERTISEMENT FOR BIDS).
f. Notice to Proceed (Anticipated): July 20, 2022.
Page 2 of 3
May 19, 2022
g. Mobilization on-site: September 6, 2022
h. Substantial Completion Date: May 26, 2023.
i. Final Acceptance: 30 days from Substantial Completion Date.
5. General Project Requirements
a. Bid Submittal Checklist – 00 42 10, provides details on
requirements/timing for form submittals
b. Bid Proposal Form – City of Renton Bid Form
i. Acknowledge Receipt of Addenda
ii. Complete Bid Form in entirety and all Supplemental Forms.
iii. Subcontractor Listing
iv. Alternates
c. Proposal Bid Bond
d. Bidder’s Qualification Statement
e. Performance Bond Required
f. City of Renton Business License
g. Statement of Intent to Pay Prevailing Wages
h. Certificate of Liability Insurance
i. Certificate of Compliance with Wage Payment Statues
j. Agreement – City of Renton Standard Agreement
k. General Conditions – City of Renton Standard General Conditions
l. Product Substitution Request 01 40 10 – Substitution requests allowed up
to 10 days prior to bid opening. Approved substitutions will be listed on
an addenda
6. Project Description and Scope of Work – HBB Landscape Architecture and PND
Engineers
a. General
b. Landscape
c. Irrigation
d. Civil
e. Electrical
7. Special Conditions/Construction Access
a. Work Hours
i. Monday – Friday 7:00 am to 8:00 pm
ii. Saturday 9:00 am to 8:00 pm, only with approval of Owner
iii. Sunday – no work.
iv. City recognized Holidays – no work.
b. Site Access – note locked SPU gate on Beacon Way S
c. Project Schedule
d. Contractor Staging Area
e. Special Material Testing/Inspections
Page 3 of 3
May 19, 2022
i. Special Material Testing & Inspection Firm provided by Owner.
ii. Contractor shall coordinate and schedule all special testing and
inspections.
8. Questions
a. No questions were submitted during the pre-bid conference
The above information is reflecting the Pre-Bid Conference meeting agenda items, notes, questions, and
attendees as provided in the information provided in the Pre-Bid Conference ZOOM meeting of May 16,
2022. Please notify Betsy Severtsen, City of Renton, of any discrepancies within 24 hours of receipt.