HomeMy WebLinkAboutRS_Geotechnical summary letter_20220522_v1
17425 NE Union Hill Road, Suite 250
Redmond, Washington 98052
425.861.6000
May 20, 2022
Topgolf
8750 North Central Expressway
Suite 1200
Dallas, Texas 75231
Attention: Bryan Musgrove (Topgolf)/Erik Silvis (Arco/Murray)
Subject: Summary Letter
Geotechnical Construction Phase Services
Topgolf Renton Landing Project
780 Logan Avenue North,
Renton, Washington
GeoEngineers File No. 23325-001-01
Permit No. R-412301
INTRODUCTION
This letter presents a summary of GeoEngineers’ construction observation services for the TopGolf Renton
Landing development project located in Renton, Washington. Our services for this project were completed
in general accordance with our Services Agreement executed on June 25, 2021.
The project involved the development of a low-rise structure, an outfield area consisting of turf and enclosed
with nets supported by poles up to 170 feet in height, and surface parking. The site is bounded by
North 8th Street to the north, Park Avenue North to the east, office and parking structures to the south, and
Logan Avenue North to the west in Renton, Washington.
OBSERVATIONS
GeoEngineers visited the site on an intermittent basis between June 17, 2021, and April 28, 2022, to
observe Geopier installation and testing, major utility installation, foundation subgrade and backfill, outfield
construction, parking, and sidewalk, drilled shaft for net pole and helical anchors installation, observe
temporary erosion control, and attend pre-construction meetings. Detailed reports of our construction
observation services were presented in our daily field reports for the project, GI-001 through GI-018, GT-
001 through GT-138, and DS_FR 001 through DS_FR012. Copies of these field reports were provided to
Topgolf, ARCO/Murray, Geopier Northwest, Judge Netting, and the City of Renton.
This summary letter focuses on the following geotechnical inspection items:
Topgolf| May 20, 2022 Page 2
File No. 23325-001-01
■ Observation of rammed aggregate pier installation for building footing subgrade improvement.
■ Building foundation soil bearing verification.
■ Verify fill and compaction.
■ Utility and subsurface drainage installation.
■ Outfield construction and settlement verification.
■ Parking lot subgrade preparation.
■ Drilled shaft and helical anchor installation.
■ Temporary erosion control and groundwater discharge monitoring.
Observation of rammed aggregate pier Installation for building footing subgrade improvement
We observed the installation of ground improvement consisting of rammed aggregate piers (i.e. Geopier®)
beneath the shallow foundations supporting a low-rise structure building. Approximately 808 geopiers were
completed for the project from June 29, 2021, and July 21, 2021. Installation of geopiers consisted of
using a hollow mandrel driven to the required depth and having the aggregate placed into the mandrel and
compacted by raising the redriving the mandrel in lifts until the geopier is constructed. The daily field
reports, GI-001 through GI-018, and as-built geopiers constructed at the site were submitted to Geopier
Northwest (ground improvement designer), Topgolf, ARCO/Murray, and the City of Renton, to ensure that
the design intent was met. Geopier Northwest submitted a letter of acceptance of the installed geopiers
dated August 9, 2021.
Building foundation soil bearing verification
We observed the building foundation subgrade during our site visits from June 17, 2021, and September
17, 2021. Based on our observations, the soils at the foundation subgrade elevation consisted of silty sand
with gravel (existing fill) and aggregate from stone columns installation.
Based on the letter of acceptance of the rammed aggregate pier ground improvement by Geopier
Northwest, the foundation subgrade soils that we evaluated are capable of providing an allowable static
bearing pressure of 4,500 pounds per square foot (psf) for spread footings.
Verify fill placement and compaction
We observed and verified the placement of fill and compaction of the material during our site visits. Based
on our observations, it is our opinion that fill placement and compaction was installed in general
accordance with the project plans and specifications.
Utility and subsurface drainage Installation
We observed utility installation during our site visits from June 18, 2021, and January 24, 2022. The utilities
installation completed at the site consisted of excavation, subgrade evaluation, installation of respective
utilities, and trench backfill.
Perforated subsurface footing drains were installed around the building and French drainpipe was installed
at the site property limits with the Boeing facility located at the south central side of the project.
Topgolf| May 20, 2022 Page 3
File No. 23325-001-01
Based on our observations, it is our opinion that the utilities and subsurface drainage were installed in
general accordance with the project plans and specifications.
Outfield construction and settlement verification
We observed the construction of the outfield during our site visits from August 3, 2021, and April 5, 2022.
The outfield construction consisted of outfield structures including 11 concrete targets, drainage systems,
electrical installation, and pavement/turf subgrade grading. Targets construction work consisted of
excavations, subgrade, and backfill evaluations. During outfield grading, two settlement markers were
installed and monitored to evaluate settlement. No significant settlement was observed at the outfield.
Proof roll tests were completed for the outfield subgrade and subbase preparation prior to the pavement
placement. Proof rolls were performed with a fully loaded dump truck driving at speed limit less than 5 miles
per hour.
Based on our observations, it is our opinion that the outfield construction was completed in general
accordance with those portions of the project plans and specifications that pertain to our services.
Parking lot subgrade preparation
We observed the construction of the parking lot constructed on site during our site visits. The construction
of the parking lot consisted of exposing the firm subgrade and placing compacted base coarse fill. Proof
roll and compaction tests were performed prior to the placement of the asphalt pavement.
Based on our observations, it is our opinion that the construction of the parking lots was completed in
general accordance with the project plans and specifications that pertain to our services.
Drilled shaft and helical anchor installation
A total of 25 drilled shafts were installed for the installation of net poles between March 10, and
April 8, 2022. The drilled shaft for net pole installation consisted of drilling with a temporary casing, a 4- or
5-foot-diameter vertical hole to the required depth, installing the pole base and then placing concrete from
the bottom of the hole with a tremie connected to a concrete truck pump. Centralizers were placed halfway
of the pole base to ensure the net pole was centered.
At the request of the General contractor, we observed installation of helical anchor at the corner poles 1,
11, 15, and 25. Helical anchors for net cables were installed at various depth reaching between 4,000 foot-
pounds to 4,500 foot-pounds (ft-lbs) per designer specifications, Engel and Company Engineers.
Based on our observations, it is our opinion that the drilled shaft for net pole installation and helical anchors
for net cables were completed in general accordance with the project plans and specifications and the
designer’s recommendations.
Temporary erosion control and groundwater discharge monitoring
Temporary erosion and sediment controls (TESC) was monitored during each site visit by GeoEngineers.
A Certified Erosion and Sediment Control Lead (CESCL) from GeoEngineers also completed a once per week
site inspection per the projects Washington State Department of Ecology Construction Stormwater General
Topgolf| May 20, 2022 Page 4
File No. 23325-001-01
Permit number WAR30928. The contractor implemented TESC measures, as necessary, to prevent turbid
water and soils from leaving the site. Based on our observations, it is our opinion that the TESC measures
were in accordance with the project plans, specifications, and guidance established under the project
General Permit.
A CESCL from GeoEngineers also monitored the water quality of groundwater removed from the subsurface
using well points and discharged to the City of Renton stormwater system and groundwater removed from
excavations and drilled shafts using sump pumps and discharged to the ground surface of the site
periodically during the project. Based on our observations and groundwater quality monitoring, it is our
opinion that the groundwater discharge was completed in accordance with the project plans, specifications,
and guidance established under the project General Permit.
CONCLUSIONS
Based on observations and evaluations completed for the project, we conclude that the work discussed
herein for the for the TopGolf Renton Landing development project has been completed in accordance with
the intent of our recommendations and the City of Renton approved project plans and specifications.
We trust this letter meets your current needs. Please call if you have any question regarding this letter.
Respectfully submitted,
GeoEngineers, Inc.
Lucy Hoch, PE King H. Chin, PE
Geotechnical Engineer Principal
RN:LH:KHC:tjh
One copy submitted electronically
Disclaimer: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record.