HomeMy WebLinkAboutEx_13_ Reconsideration Request.pdfFrom: Maduli-williams, Stephen <maduliwi@amazon.com>
Sent: Friday, April 15, 2022 12:37 PM
To: Alex Morganroth
Cc: Montesinos, Miriam; Eady, Nathaniel; Davis, Parker
Subject: RE: DNS-M Issuance: SWA2 Amazon LUA21-000233 - Reconsideration
Request
Hello Alex,
Amazon would like to officially request a reconsideration of the SEPA decision issued on April 5th, 2022
for the Amazon Sub Same Day Delivery site located at 1905 Raymond SW, Renton, WA. We intend to
submit a complete reconsideration packet for committee review by May 13th of 2022. Also, we like to
formally request that the SEPA review of our application be placed on hold until after the
reconsideration process is completed.
Best regards,
Stephen
Stephen Maduli-Williams | Amazon.com
Manager, Economic Development
188 Spear Street 5th Floor | San Francisco, CA 94105
cell: 415-230-9788
email: maduliwi@amazon.com
From: Alex Morganroth <AMorganroth@Rentonwa.gov>
Sent: Wednesday, April 13, 2022 6:14 PM
To: Maduli-williams, Stephen <maduliwi@amazon.com>
Subject: [EXTERNAL] Amazon SWA2 reconsideration
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless
you can confirm the sender and know the content is safe.
Hi Stephen,
I have confirmed that you may request a reconsideration of the SEPA decision issued for the Amazon
SWA2 project. See below for the reconsideration language found in RMC 4-8-100.I.
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open
attachments unless you know the content is safe.
The reconsideration request can be submitted to me via email and must be submitted by 5pm on
Tuesday, April 19th (i.e. two weeks after the SEPA determination was issued). There is no fee required for
a reconsideration request. Since I’m assuming that you will not have the documentation and data
regarding the phasing approach before you make you submit the reconsideration, please include a
rough timeline indicating when you anticipate obtaining the analysis/recommendation from your traffic
consultant. In addition, please include a request to place review of the project on-hold as the
reconsideration process plays out. Once the committee reviews the reconsideration request, they will
either uphold the original determination and mitigation measures, or issue a new determination with
altered/new mitigation measures. Upon issuance of the new determination (or upholding the current
determination), Amazon will have a new two-week period to appeal.
If you have any questions on the process, please let me know. I’d also be happy to give you a call
tomorrow if it’d be easier to discuss that way.
Thank you,
ALEX MORGANROTH, AICP, Senior Planner
City of Renton | CED | Planning Division
1055 S Grady Way | 6th Floor | Renton, WA 98057
Virtual Permit Center | Online Applications and Inspections
(425) 430-7219 | amorganroth@rentonwa.gov